Chapter 9 Project Management Lecture Outline • • • • • • • Project Planning Project Scheduling Project Control CPM/PERT Probabilistic Activity Times Microsoft Project Project Crashing and Time-Cost Trade-off Copyright 2011 John Wiley & Sons, Inc. 9-2 Project Management Process • Project • unique, one-time operational activity or effort Copyright 2011 John Wiley & Sons, Inc. 9-3 Project Management Process Copyright 2011 John Wiley & Sons, Inc. 9-4 Project Management Process Copyright 2011 John Wiley & Sons, Inc. 9-5 Project Elements • • • • • • • • Objective Scope Contract requirements Schedules Resources Personnel Control Risk and problem analysis Copyright 2011 John Wiley & Sons, Inc. 9-6 Project Team and Project Manager • Project team • made up of individuals from various areas and departments within a company • Matrix organization • a team structure with members from functional areas, depending on skills required • Project manager • most important member of project team Copyright 2011 John Wiley & Sons, Inc. 9-7 Scope Statement • Scope statement • a document that provides an understanding, justification, and expected result of a project • Statement of work • written description of objectives of a project Copyright 2011 John Wiley & Sons, Inc. 9-8 Work Breakdown Structure • Work breakdown structure (WBS) • Breaks a project into components, subcomponents, activities, and tasks Copyright 2011 John Wiley & Sons, Inc. 9-9 Work Breakdown Structure for Computer Order Processing System Project Copyright 2011 John Wiley & Sons, Inc. 9-10 Responsibility Assignment Matrix • Organizational Breakdown Structure (OBS) • a chart that shows which organizational units are responsible for work items • Responsibility Assignment Matrix (RAM) • shows who is responsible for work in a project Copyright 2011 John Wiley & Sons, Inc. 9-11 Responsibility Assignment Matrix Copyright 2011 John Wiley & Sons, Inc. 9-12 Global and Diversity Issues in Project Management • Global project teams are formed from different genders, cultures, ethnicities, etc. • Diversity among team members can add an extra dimension to project planning • Cultural research and communication are important elements in the planning process Copyright 2011 John Wiley & Sons, Inc. 9-13 Project Scheduling • Steps • • • • Define activities Sequence activities Estimate time Develop schedule Copyright 2011 John Wiley & Sons, Inc. • Techniques • Gantt chart • CPM/PERT • Software • Microsoft Project 9-14 Gantt Chart • • • • Graph or bar chart Bars represent the time for each task Bars also indicate status of tasks Provides visual display of project schedule • Slack • amount of time an activity can be delayed without delaying the project Copyright 2011 John Wiley & Sons, Inc. 9-15 Example of Gantt Chart 0 | 2 | Month 4 | 6 | 8 | 10 Activity Design house and obtain financing Lay foundation Order and receive materials Build house Select paint Select carpet Finish work 1 3 5 7 9 Month Copyright 2011 John Wiley & Sons, Inc. 9-16 Project Control • Time management • Cost management • Performance management • Earned Value Analysis – standard procedure to • numerically measure a project’s progress • forecast its completion date and cost • measure schedule and budget variation Copyright 2011 John Wiley & Sons, Inc. 9-17 Project Control • Quality management • Communication • Enterprise project management Copyright 2011 John Wiley & Sons, Inc. 9-18 CPM/PERT • Critical Path Method (CPM) • DuPont & Remington-Rand • Deterministic task times • Activity-on-node network construction • Project Evaluation and Review Technique (PERT) • US Navy and Booz, Allen & Hamilton • Probabilistic task time estimates • Activity-on-arrow network construction Copyright 2011 John Wiley & Sons, Inc. 9-19 Project Network • Activity-on-node (AON) • nodes represent activities • arrows show precedence relationships Branch 1 Node 2 3 • Activity-on-arrow (AOA) • arrows represent activities • nodes are events for points in time • Event • completion or beginning of an activity in a project Copyright 2011 John Wiley & Sons, Inc. 9-20 AOA Project Network for a House 3 Lay foundation 2 1 3 Design house and obtain financing Build house 0 1 2 Dummy Order and receive materials 4 Select paint Finish work 6 3 1 1 1 7 Select carpet 5 Copyright 2011 John Wiley & Sons, Inc. 9-21 Concurrent Activities • Dummy • two or more activities cannot share same start and end nodes 3 Lay foundation 2 Lay foundation 3 Order material (a) Incorrect precedence relationship Copyright 2011 John Wiley & Sons, Inc. 2 Dummy 2 0 1 4 Order material (b) Correct precedence relationship 9-22 AON Network for House Building Project Start Lay foundation Build house 2 2 4 3 Activity Number Activity Time 1 3 7 1 Design house and obtain financing 3 1 5 1 6 1 Order &receive materials Select paint Select carpet Copyright 2011 John Wiley & Sons, Inc. Finish work 9-23 Critical Path 2 2 Start 1 3 7 1 3 1 A: B: C: D: 4 3 1-2-4-7 3 + 2 + 3 + 1 = 9 months 1-2-5-6-7 3 + 2 + 1 + 1 + 1 = 8 months 1-3-4-7 3 + 1 + 3 + 1 = 8 months 1-3-5-6-7 3 + 1 + 1 + 1 + 1 = 7 months Copyright 2011 John Wiley & Sons, Inc. 5 1 6 1 Critical path Longest path through a network Minimum project completion time 9-24 Activity Start Times Start at 5 months 2 2 Start 4 3 Finish at 9 months 1 3 7 1 3 1 Start at 3 months Copyright 2011 John Wiley & Sons, Inc. 5 1 Finish 6 1 Start at 6 months 9-25 Node Configuration Activity number Activity duration Copyright 2011 John Wiley & Sons, Inc. Earliest start Earliest finish 1 0 3 3 0 3 Latest start Latest finish 9-26 Activity Scheduling • Earliest start time (ES) • earliest time an activity can start • ES = maximum EF of immediate predecessors • Forward pass • starts at beginning of CPM/PERT network to determine earliest activity times • Earliest finish time (EF) • earliest time an activity can finish • earliest start time plus activity time • EF= ES + t Copyright 2011 John Wiley & Sons, Inc. 9-27 Earliest Activity Start and Finish Times Lay foundation Build house 2 3 5 4 2 5 8 3 1 Start 0 Finish work 3 7 1 Design house and obtain financing 8 9 1 6 3 3 4 1 Order and receive materials 6 7 1 5 5 6 1 Select carpet Select paint Copyright 2011 John Wiley & Sons, Inc. 9-28 Activity Scheduling • Latest start time (LS) • Latest time an activity can start without delaying critical path time • LS= LF - t • Latest finish time (LF) • latest time an activity can be completed without delaying critical path time • LF = minimum LS of immediate predecessors • Backward pass • Determines latest activity times by starting at the end of CPM/PERT network and working forward Copyright 2011 John Wiley & Sons, Inc. 9-29 Latest Activity Start and Finish Times Lay foundation Build house 2 3 2 Start 3 5 5 4 5 8 3 5 8 Finish work 1 0 3 7 8 9 1 0 3 1 8 9 Design house and obtain financing 3 3 4 1 4 5 Order and receive materials 5 1 5 6 6 6 7 1 6 7 6 7 Select carpet Select paint Copyright 2011 John Wiley & Sons, Inc. 9-30 Activity Slack Activity LS ES LF EF Slack S *1 0 0 3 3 0 *2 3 3 5 5 0 3 4 3 5 4 1 *4 5 5 8 8 0 5 6 5 7 6 1 6 7 6 8 7 1 *7 8 8 9 9 0 * Critical Path Copyright 2011 John Wiley & Sons, Inc. 9-31 Probabilistic Time Estimates • Beta distribution • probability distribution traditionally used in CPM/PERT Mean (expected time): Variance: a + 4m + b t= 6 b-a = 6 2 2 where a = optimistic estimate m = most likely time estimate b = pessimistic time estimate Copyright 2011 John Wiley & Sons, Inc. 9-32 P(time) P(time) Examples of Beta Distributions a m t b a t Time m b P(time) Time a m=t b Time Copyright 2011 John Wiley & Sons, Inc. 9-33 Project with Probabilistic Time Estimates Equipment installation Equipment testing and modification 1 4 6,8,10 2,4,12 System development Start 2 8 Manual testing 3,6,9 Position recruiting System training 3,7,11 5 2,3,4 Job Training 3 6 1,3,5 3,4,5 Final debugging 10 1,4,7 Finish 11 9 2,4,6 System testing 1,10,13 System changeover Orientation 7 2,2,2 Copyright 2011 John Wiley & Sons, Inc. 9-34 Activity Time Estimates TIME ESTIMATES (WKS) ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 MEAN TIME VARIANCE a m b t б2 6 3 1 2 2 3 2 3 2 1 1 8 6 3 4 3 4 2 7 4 4 10 10 9 5 12 4 5 2 11 6 7 13 8 6 3 5 3 4 2 7 4 4 9 0.44 1.00 0.44 2.78 0.11 0.11 0.00 1.78 0.44 1.00 4.00 Copyright 2011 John Wiley & Sons, Inc. 9-35 Activity Early, Late Times & Slack ACTIVITY 1 2 3 4 5 6 7 8 9 10 11 t б ES EF LS LF S 8 6 3 5 3 4 2 7 4 4 9 0.44 1.00 0.44 2.78 0.11 0.11 0.00 1.78 0.44 1.00 4.00 0 0 0 8 6 3 3 9 9 13 16 8 6 3 13 9 7 5 16 13 17 25 1 0 2 16 6 5 14 9 12 21 16 9 6 5 21 9 9 16 16 16 25 25 1 0 2 8 0 2 11 0 3 8 0 Copyright 2011 John Wiley & Sons, Inc. 9-36 Earliest, Latest, and Slack 1 0 8 1 Start 2 0 6 0 3 0 3 2 8 9 3 5 10 13 17 8 9 7 9 6 6 Critical Path 2-5-8-11 4 8 13 5 16 21 5 6 3 6 6 3 4 5 16 7 3 Finish 16 9 9 1 0 9 9 13 4 12 16 11 16 25 9 16 25 9 7 3 5 2 14 16 Copyright 2011 John Wiley & Sons, Inc. 9-37 Total Project Variance 2 = б22 + б52 + б82 + б112 = 1.00 + 0.11 + 1.78 + 4.00 = 6.89 weeks Copyright 2011 John Wiley & Sons, Inc. 9-38 CPM/PERT With OM Tools Copyright 2011 John Wiley & Sons, Inc. 9-39 Probabilistic Network Analysis Determine probability that project is completed within specified time Z= where = = x= Z= x- tp = project mean time project standard deviation proposed project time number of standard deviations that x is from the mean Copyright 2011 John Wiley & Sons, Inc. 9-40 Normal Distribution of Project Time Probability Z = tp Copyright 2011 John Wiley & Sons, Inc. x Time 9-41 Southern Textile What is probability that project is completed within 30 weeks? P(x 30 weeks) = 6.89 weeks 2 = 6.89 = 2.62 weeks Z= = x- 30 - 25 2.62 = 1.91 = 25 x = 30 Time (weeks) From Table A.1, (appendix A) a Z score of 1.91 corresponds to a probability of 0.4719. Thus P(30) = 0.4719 + 0.5000 = 0.9719 Copyright 2011 John Wiley & Sons, Inc. 9-42 Southern Textile What is probability that project is completed within 22 weeks? P(x 22 weeks) = 0.1271 0.3729 = 6.89 weeks 2 = 6.89 = 2.62 weeks Z= = x- 22 - 25 2.62 = -1.14 x = 22 = 25 Time (weeks) From Table A.1, (appendix A) a Z score of 1.14 corresponds to a probability of 0.3729. Thus P(22) = 0.5000 - 0.3729 = 0.1271 Copyright 2011 John Wiley & Sons, Inc. 9-43 Microsoft Project • Popular software package for project management and CPM/PERT analysis • Relatively easy to use Copyright 2011 John Wiley & Sons, Inc. 9-44 Microsoft Project Click on “Tasks” First step; Start Date Copyright 2011 John Wiley & Sons, Inc. 9-45 Microsoft Project Click on “Format” then ”Timescale” to scale Gantt chart. Create precedence relationships; click on predecessor activity, then holding “Ctrl” Key, click on successor activity. Copyright 2011 John Wiley & Sons, Inc. Precedence relationships Gantt chart; click on “View” to activate 9-46 Microsoft Project Click on “View” then Network Diagram Critical path in red Copyright 2011 John Wiley & Sons, Inc. 9-47 Microsoft Project – Zoom View Copyright 2011 John Wiley & Sons, Inc. 9-48 Microsoft Project – Task Information Enter % completion Copyright 2011 John Wiley & Sons, Inc. 9-49 Microsoft Project – Degree of Completion Activities 1, 2 and 3 100% complete Copyright 2011 John Wiley & Sons, Inc. Black bars show degree of completion 9-50 PERT Analysis with Microsoft Project Click on PERT Entry Sheet to enter 3 time estimates Click on PERT calculator to compute activity duration Copyright 2011 John Wiley & Sons, Inc. 9-51 PERT Analysis with Microsoft Project Copyright 2011 John Wiley & Sons, Inc. 9-52 PERT Analysis with Microsoft Project Copyright 2011 John Wiley & Sons, Inc. 9-53 Project Crashing • Crashing • reducing project time by expending additional resources • Crash time • an amount of time an activity is reduced • Crash cost • cost of reducing activity time • Goal • reduce project duration at minimum cost Copyright 2011 John Wiley & Sons, Inc. 9-54 Project Network – Building a House 4 2 8 12 7 4 1 12 3 4 Copyright 2011 John Wiley & Sons, Inc. 5 4 6 4 9-55 Normal Time and Cost vs. Crash Time and Cost $7,000 – $6,000 – Crash cost $5,000 – Crashed activity Slope = crash cost per week $4,000 – $3,000 – $2,000 – Normal activity Normal cost $1,000 – Normal time Crash time – 0 | 2 Copyright 2011 John Wiley & Sons, Inc. | 4 | 6 | 8 | 10 | 12 | 14 Weeks 9-56 Project Crashing ACTIVITY 1 2 3 4 5 6 7 NORMAL TIME (WEEKS) CRASH TIME (WEEKS) NORMAL COST 12 8 4 12 4 4 4 7 5 3 9 1 1 3 $3,000 2,000 4,000 50,000 500 500 15,000 $5,000 3,500 7,000 71,000 1,100 1,100 22,000 $75,000 $110,700 Copyright 2011 John Wiley & Sons, Inc. CRASH COST TOTAL ALLOWABLE CRASH TIME (WEEKS) 5 3 1 3 3 3 1 CRASH COST PER WEEK $400 500 3,000 7,000 200 200 7,000 9-57 $500 $7000 4 2 8 FROM … $7000 12 7 4 1 Project Duration: 36 weeks 12 $400 3 4 $3000 6 4 5 4 $200 $200 $7000 $500 TO… Project Duration: 31 weeks Additional Cost: $2000 $7000 12 7 4 1 7 $400 3 4 $3000 Copyright 2011 John Wiley & Sons, Inc. 4 2 8 5 4 6 4 $200 $200 9-58 Time-Cost Relationship • Crashing costs increase as project duration decreases • Indirect costs increase as project duration increases • Reduce project length as long as crashing costs are less than indirect costs Copyright 2011 John Wiley & Sons, Inc. 9-59 Time-Cost Tradeoff Minimum cost = optimal project time Total project cost Cost ($) Indirect cost Direct cost Crashing Time Project duration Copyright 2011 John Wiley & Sons, Inc. 9-60 Copyright 2011 John Wiley & Sons, Inc. All rights reserved. Reproduction or translation of this work beyond that permitted in section 117 of the 1976 United States Copyright Act without express permission of the copyright owner is unlawful. Request for further information should be addressed to the Permission Department, John Wiley & Sons, Inc. The purchaser may make back-up copies for his/her own use only and not for distribution or resale. The Publisher assumes no responsibility for errors, omissions, or damages caused by the use of these programs or from the use of the information herein. Copyright 2011 John Wiley & Sons, Inc. 6-61