Meeting Agenda 9-04-13

advertisement
Meeting Agenda 11-05-13
(1) Overview (概观)
(2) Ongoing interview and Data Collection (SEAS) (进行
的访谈和数据收集)
(3) Input sheet update and NN training(GT) (输入更新)
(4) Ongoing tasks (进行中任务)
(5) Approaching Dates (日期)
(6) Timeline (时间安排)
(1) Overview (概观)
• Previous Week and Current Week:
– NN training with simulated data and KPI provided by SEAS. (GT)
(用仿真的数据以及SEAS提出的输出指标來使用人工神经)
– Input sheet update. (更新输入)
• Next Week:
– Continue NN training using more mathematical models (使用更多
的数学模式来训练神经网络)
– Verification of NN (验证人工神经)
(2) Ongoing Interview and Data
Collection
• SEAS will lead the discussion.
– Any updates to be reported.
– New update on KPI
(3) NN training
• NN will be trained by creating data and the KPI’s provided by SEAS
will be used as the output value. (用仿真的数据以及SEAS提出的
输出指标來训练人工神经)
– Check for compatibility (Completed) (检查兼容性)
– Simulate data (Completed) (模拟数据)
– Use a mathematical model (polynomial, exponential etc) to generate
output (In progress) (使用的数学模型(多项式,指数等),以生成输
出)
– Train the NN using the simulated data and outputs generated by the
mathematical model (In progress) (用模拟数据以及数学模型模拟输
出来训练人工神经)
– Generate new input and outputs using the mathematical model (In
progress) (采用数学模型,生成新的输入和输出)
– Validate the NN using the new inputs and outputs (In progress) (使用
新的输入和输出验证人工神经)
(4) Ongoing Tasks
• NN simulation data generation and
simulation. GT (人工神經仿真数据生成和
仿真)
• Input excel update. GT and SEAS (输入Excel
更新)
• Historic data collection and scheduler
interviews. SEAS (历史数据收集和采访)
(5) Approaching Dates
• Interview and historic production data: SEAS
(tentative)
• SEAS visit to GT (Confirmation between 11/511/7).
Month
Tasks
August
As of 11-05-2013
Completed
Work Plan
Completed
Intelligent Matrix
Completed
Literature Survey
Ongoing
Interview and Data Collection
Completed
Selection of ILE modeling methods and case
study
Completed
Predictive Modeling Module
Delayed
SEAS visit
Completed
Prognotic Module
Completed
Modification of ILE for case study
In progress
Modification of ILE for SEAS test bed
GT visit
Improving ILE
September
October
November
December