Hud son River Hudson River Dredging: Overview and Update January, 2010 U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River The Hudson: History • 1948-1977: PCBs used by GE capacitor manufacturing plants GE Hudson Falls Capacitor Plant • 1973: Removal of Ft Edward Dam - PCBs spread downstream • 1976: New York and GE settle enforcement action for PCB discharges • 1984: 1st EPA ROD calls for shoreline capping (60 acres), but no dredging Dam Location • 1989-1990: GE implements 1984 Remedy • 1990 – EPA reassessment begins • 2/1/2002 : new EPA ROD calls for dredging U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River 3 WARREN WASHINGTON Glens Falls Hadley Hudson Falls Bakers Falls Fort Edward Section 1 Thompson Is. Dam Fort Miller Dam Section 2 Northumberland Dam SARATOGA Upper Hudson River Schuylerville Stillwater Section 3 Mechanicville RENSSELAER Waterford U nitedS ta tesE nvironm enta l P rotectionA gency Cohoes Green Island 0 Federal Dam 0 Troy 5 mi 10 k Hud son River Project Overview – 2002: ROD selects dredging remedy – 2004: EPA completes development of Quality of Life and Engineering Performance Standards, Siting of Processing Facility and Community Relations – 2002-2005: Three EPA/GE agreements to perform work — Sediment sampling (complete) — Engineering design of 2-phase project (Phase 1 complete) — Performance of project (Phase 1 complete). Agreement includes Phase 2 “opt-in/opt-out” provision for GE. Decision to be made in second half of 2010. If GE opts out, EPA retains all enforcement authorities to compel performance of Phase 2. – 2007-2009: Construction of Sediment Processing Facility – 2009: Phase 1 dredging commences May 15, continues to November U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Construction of Processing Facility – – – – – – – – – 2 miles of road; utilities; 90,000+ cy of fill Rail yard with 7 miles of new track 1,500 foot long wharf to unload barges; widen canal by 65 feet 2 MGD water treatment plant Screens and a bank of “hydrocyclones” to remove sand 12 filter presses 300,000 sq yds of liners, 55,000 sq yds paved area 7 acres of storm water basins to handle 100-year flood 5 staging areas for dewatered sediment (2 enclosed -- 19,000 cu yds each) U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River 9 Sediment Processing Facility •April 2007 Champlain Canal •November 2008 U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Sediment Processing Facility Operations • Once at the processing facility, the sediment is off-loaded and debris is removed • The sediment is then processed and the water is extracted. The water is treated on-site before being returned to the Champlain Canal • The remaining sediment, called “filter cake,” is loaded onto railcars for transport to a secure, PCB-approved landfill in Andrews, Texas – some sediment was directly off loaded, dried and then placed in railcars U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Phase 1 and 2 Dredge Area Delineation • > 50,000 sediment samples taken 2002-2006; sampling data collected to enable EPA and GE to: – determine the distribution of PCBs in the sediment – refine estimates of the amount and location of PCBs in the sediment – establish river sediment characteristics (e.g., silt, sand, gravel) • 490 acres planned to be dredged – 90 acres during Phase 1, 400 acres during Phase 2 U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Phase 1 Dredging – May-November 2009; operating 24/6 – Up to 12 mechanical clamshell dredges working at same time – 27 Hopper Barges/13 Tugs – Constant monitoring – Backfill (or cap) after dredging – Habitat replacement (in 2010) U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Dredging Operations • Dredging & Debris Removal • Resuspension controls – Rock dike – Silt curtain – 7,000 yds2 steel sheeting • Backfill, if area meets residual standard – 165,000cy – 12” of cover over much of area – 38,000cy near-shore backfill to match original bathymetry – Add’l. backfill in specified planting areas • Capping, if area cannot meet residual standard – Depends on residual concentrations – Consider capping if residuals not removed after 4 passes – Requires EPA approval • Dredging and/or backfilling operations continued 24/6 while Champlain Canal was open (May – November, 2009) U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Engineering Performance Standards • Engineering Performance Standards were developed to: - minimize resuspension of PCBs during dredging - set limits on PCBs left in sediment, and - set production rates • Resuspension standard designed to: - Protect drinking water intakes downriver of the dredging operations, and - Limit the downriver transport of PCBs • Performance standards now being evaluated through peer review process • Standards and design likely to be modified for Phase 2 U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Quality of Life Standards • Air • Noise • Light • Odor • Navigation U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Dredging Began May 15, 2009 U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River The First Scoop of Mud U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Shoreline Preparation Pre-Dredging Tree trimming U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Removal of Logs, Stumps & Debris from Western Channel of Rogers Island U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Debris is a Major Problem Debris removal U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Dredging in Ft. Edward, NY U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Residents Watch Dredging in the Ft. Edward Yacht Basin U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Loading a Mini-Scow U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Large Hopper Scow U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Noise Monitors Along Shore of Rogers Island, Ft. Edward, NY U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Locks Open May - November Barge transport through Lock 7 U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River 100+ Acre Processing Facility Unloading at processing facility U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Installation of Plastic Liners in Rail Cars for Transport of Contaminated Sediment U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Workers Load Rail Cars with Dried Sediment U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Rail Transport to West Texas U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Assessment & Peer Review • Assessment of Phase 1 underway. Purpose is to evaluate engineering & performance standards and make appropriate changes • EPA & GE prepared draft reports evaluating Phase 1; reports exchanged and released to public in midJanuary; final reports released March 8 – Reports draw some significantly different conclusions from same facts • Peer Review started mid-February, continues to June U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River EPA Report Findings: Overview – Phase 1 Plan: • Minimum removal was to be 200,000 CY • Target was 265,000 CY removed from 90 acres – Phase 1 Achieved: • 283,000 CY removed from 48 acres • >1.5 times more PCB mass removed than estimated in ROD – About the same mass as estimated in design, but from fewer acres • 31 acres backfilled; 17 acres capped – Significantly less capping expected in Phase 2 – East Rogers Island area is atypical of rest of River – about 11.5 acres capped -- About half of the remaining capped areas were buried under several feet of clean backfill thus addressing habitat concerns U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River 283,000 Cubic Yards 265,000 Cubic Yards U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Phase 1 Target = 18 CUs dredged; Achieved = 10 CUs dredged U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River EPA Draft Report Findings • Phase 1 indicated much greater mass of PCB in the areas dredged than estimated. In fact, PCB-bearing oils were frequently encountered. • The depth of contamination (DOC) was greater than estimated in the design (in one area DOC was 13 feet deeper than designed). On average the depth of cut was 1.5 X deeper than designed. – Inaccurate estimates primarily attributable to woody debris interference with sediment sampling during design phase. • If the actual DOC is better defined prior to actual dredging, the contaminated material can be removed with fewer and fuller bucket bites, and fewer passes over a given area. Fewer bucket bites equates to less resuspension and greater productivity. U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River EPA Draft Report Findings: Resuspension Standards Findings • Near-field TSS - 100 m Evaluation Level - 700 mg/L • Av. TSS well below Evaluation Level • Near-field TSS - 300 m Evaluation Level - 100 mg/L • Av. TSS well below Evaluation Level; 4 exceedances observed (but not supported by continuous turbidity measurements). • Max. allowable Total PCBs in water column -- 500 ng/L • 3 exceedances; dredging activities halted less than 4 four days. • Far-field net suspended solids concentration Evaluation Level -- 12 mg/L • Not exceeded U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Monitoring PCBs During Dredging: Schuylerville, NY Data U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River EPA Draft Report Findings: Resuspension Standards Findings • Far-field Total and Tri+ • Exceeded at Thompson Island for PCB load Control levels: majority of the dredging period. 1,080 grams/day and At Waterford, loads were significantly 361 grams/day lower -- exceeded control level ~ 20% of time. Note: load criteria were not revised during Phase 1 to address the largerthan-planned PCB mass removed. Overall target of no more than 1% export to lower Hudson was achieved. U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River EPA Draft Report Findings: Residuals Standards Findings • Affirmation of removal of all PCB-contaminated sediment inventory in target dredging areas (“Certification Units” or CUs) • Substantial removal of inventory confirmed in all CUs. Where inventory left in place, engineered caps constructed to isolate the remaining inventory. • Arithmetic average Tri+ PCBs concentration in the residual sediments ≤ 1 mg/kg • Expect that ≤ 1 mg/kg can be achieved in residual sediments during Phase 2 U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River EPA Draft Report Findings: Productivity Standards Findings • Target Phase 1 dredging volume = 265,000 CY • Total volume removed = 283,000 cy • Targeted Maximum Phase 1 monthly volume = 88,350 CY • Max. monthly Phase 1 volume removed = ~77,000 CY. (Very likely that the target of 88,350 CY would have been achieved but for shortages of empty scows.) • Shoreline stabilization, backfilling, and processing and shipment of removed sediment accomplished prior to the end of calendar year. U nitedS ta tesE nvironm enta l P rotectionA gency • Due to difficulties at disposal site, not all sediment shipped off-site by end of 2009. Provisions should be made for back-up disposal site for Phase 2. Hud son River What Went Well • Met or exceeded sediment volume & PCB mass goals • Few shut-downs with limited impact on production • ~70% of dredged area closed in compliance with the Residuals Standard • No measurable impacts to Lower River •We learned enough in Phase 1 to improve the project and do it well in Phase 2 U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Phase 1 Challenges • Higher than normal flows • Extent of wood debris • DoC consistently underestimated • NAPL releases • Limitations on scow unloading • Extent of erosion since 2001 – 35K CY lost in the 18 planned CU’s before start of dredging; system is dynamic, redistribution occurs all the time • % of bedrock/clay bottom U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River 48 Resuspension Standard: Summary of Observations • No significant release of solids during dredging • Water column PCB concentrations were significantly above baseline during dredging. • PCB-bearing oil sheens were extensive and are likely a significant vector for PCB release. • Water column concentrations of PCB decreased substantially downstream of Thompson Island to Waterford. – Tri+ PCB Loads at Lock 5 and Waterford were significantly lower than loads at Thompson Island, yet solids transport increased slightly (though still within the baseline variations) • There were no observable impacts of dredging to PCB water column concentrations downstream of Albany. U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Resuspension Standard Observations (con’t.) • Net load at Thompson Island was still small relative to the overall mass removed : 440 kg vs. the 20,000 kg removed (roughly 2 percent). • The net load to the Lower Hudson was roughly 150 kg total PCB. • The resuspension goal of maintaining the Total PCB export rate to 1 percent or less relative to the mass of PCBs removed was achieved at Waterford and nearly met at Schuylerville. U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River 50 Productivity Standard: Major Factors Affecting Productivity During Phase 1 • Scow unavailability due to limited scow unloading capacity at Dewatering Facility • Presence of wood debris in sediment • Limited capacity of mini-scows • Underestimated DoC • Fine grading to meet cut line tolerances U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Debris in Sediment U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Impacts of Underestimated DoC and Fine Grading • Underestimated DoC: – Additional dredge passes – Time lost in mapping, sampling, and designing new cut lines – CUs open longer • Fine Grading: – Reduced production rate • Both factors also increased resuspension losses U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Phase 2 Productivity Standard Can be Met by: • Addressing uncertainty in DoC to minimize passes • Improving scow unloading capacity • Minimizing fine grading and small cuts • Conducting access dredging where needed U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Residual Standard – Summary of Findings • Resuspension, Productivity and Residual standards are related • Basic problems arise from the uncertainty in the design DoC – Core samples used for design were often incomplete, yielding inaccurate design • Modifications needed in the approaches for dredging and post-dredging sampling • EPA is recommending simplifications to the Residuals Standard but not changes to the basic approach U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Closure Summary Percent of Phase 1 Area Closure Cap on Cap due to Archaeologically Schedule Sensitive Areas Constraints 0.26% 25% Cap per Residual Cap on Bedrock/clay Standard Backfill 63% 10% 2% U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River Simultaneously Meeting Standards • Efficient dredging of inventory with fewer cuts (productivity) leads to fewer bottom disturbances and smaller dredging releases (resuspension) and quicker certification of post-dredging concentrations (residuals) reducing duration of exposed bottom surface (resuspension). • Per Residual Standard, appropriate selection of cut lines is important in minimizing re-dredging...and therefore in meeting the standards simultaneously. U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River OVERALL BENEFITS OF PROJECT • Far more PCBs in the River than estimated • The River is NOT “cleaning itself” at the rate predicted by the model used in the 1990s. – Sediments are not being buried.. – Surface concentrations are 3x higher, and water column concentrations are 2-3 X higher, than 1990s model predicted. Both show little or no decline over a decade. • Even with an increase in the resuspension standard, completion of the dredging project will confer significant and lasting benefits. U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River More Information For information on Hudson River Dredging Project: http://www.epa.gov/hudson/ For EPA’s Report on Phase 1: http://www.hudsondredgingdata.com/Report For GE’s Report on Phase 1: http://www.hudsondredging.com/ U nitedS ta tesE nvironm enta l P rotectionA gency Hud son River