OP300installation

advertisement
OP300
Technical training presentation
Installation
OP 300 delivery content
OP 300 is delivered in 2 boxes
BOX 1 contains
- Column and carriage
- Accessories
- Wall bracket
- Manuals
BOX 2 contains
- Main Support
- Rotating unit
Pre-installation requirements
Installation room
Check minimum room size from pre-sales
check-list.
Physical environment specs in the pre-sales
check-list.
Unit mounts to the floor and wall with mounting
hardware (not supplied).
PC minimum requirements
Windows XP Professional with SP2 (32-bit)
2.4 GHz Core 2 Duo dual core processor or equivalent
2 GB RAM
500 GB HDD or larger
Gigabit Ethernet (CAT6)
One available PCI-Express x16 bus slot for a GPU card
2 available USB ports (hardware key locks)
19" LCD display, 1280 x 1024
Time and persons
Radiation shielding
For complete installation 1 day and 2 persons are
needed
Local requirements must be met
Product dimensions
Range:
54.5”
to
56.1”
(78.9”)
Installation overview
Stand up the column
Attach unit to the wall
and / or to the floor
Lift the carriage and
hang it on the column.
Check leveling of the unit
Connect all cables and
attach exposure button
and touch panel
Install and configure
Cliniview
Carry out calibration procedure
for the unit
For detailed instructions
please refer to Installation
manual
Unpacking the unit; column box
Unpacking the unit; overhead box
Stand up the column
Three mounting variations:
With one wall mounting bracket
and bolting unit to the floor
With two wall mounting brackets -no floor drilling is needed
With one wall mounting bracket
and base plate
Note: Base plate and second wall mounting bracket has to be ordered separately
For the Wall Mounting Bracket:
Prior to mounting column to the
mounting bracket, ensure that the
bracket has room to adjust forward
and back, otherwise there will be
no room to level the unit front-toback. Leveling is done after the
overhead is mounted onto the
column, using levels built into the
overhead.
Remove the side covers
Cut the foam, leave the foam banded onto the
overhead
Prepare for the overhead
Slide the overhead onto the column
Pins align the overhead prior to fixing with the bolts
Making the connections from overhead to column
Connections, continued
Connections, continued
Mains power, handswitch and Ethernet connections
Remote handswitch terminals
Remove the packing foam
Remove the plywood
Remove the brackets
Configure the rotation stop
• Remove rotation stop bracket
• Rotate the tubearm 90 degrees
CCW, as seen from above
• Reinstall rotation stop bracket
Level the unit
• Levels located in overhead
• Use column bracket to set level
Configuring the mains power jumpers
• Default 220V configuration
• 100V, 115V jumpers stored on
side panel
Install and Wire the GUI
Set the column height microswitch
Install the side covers
Ceph arm mounting hardware
Ceph arm mounting brackets
Ceph head packaging
Mounting the ceph head
Level the ceph head
Ceph head connections
Ceph head connections, continued
Host computer video card
• Reconstruction video card
packed in column box
•Open host computer,
remove old video card from
PCI slot (A)
•Locate “Y” power adapter
(B)
•Install “Y” power adapter (C)
•Plug in reconstruction video
card
•Ensure that two power plugs
are connected to video card
(D)
•Locate reconstruction
dongle, plug into available
USB port on the host
computer
A
B
C
D
Powering on the unit
“Push any button” to initialize the unit
Configure the host computer’s NIC
Launch Cliniview Software
Configure Driver
• Left-ctrl/right click on driver icon
to open the driver setup script
•Enter the IP address of the unit to
be controlled
Launch S2 Terminal
Calibration of the unit
How to start:
Patient record must be active
- select
in the control panel
- select “Service” in the control panel
-check to see if any items have red
exclamation points on them – those items
must be recalibrated
Alignment and QA Tools
Pan alignment
cone assembly
Leveling base
QA Phantom
CT Geometry
tool
Acceptance limits
Passed
Calibration program is successfully done.
Move on to next calibration.
Not passed
Adjustment is still needed. Follow the instructions the image (if any) and take
another exposure. Some calibration programs are iterative and demands a few
repetitions.
Failed
System could not decide what adjustment should be done in order for the
calibration to succeed. This calibration status is always the result of some error
condition. Taking another exposure will not help. The image may give a hint on
what the problem is (e.g. no radiation, collimator severely tilted, image data
corrupted…).
Pan geometry calibration
Purpose:
Panoramic geometry position
calibration
Acceptance limits:
Passed / Not passed / Failed
GUI informs if calibration has
passed
CT Geometry calibration
Purpose:
Calibrates ct geometry, needed
only with 3D units
Acceptance limits:
Passed / Not passed / Failed
GUI informs if calibration has
passed
Pan pixel calibration
Purpose:
Panoramic sensor pixel
calibration
Acceptance limits:
Passed / Not passed / Failed
GUI informs if calibration has
passed
CT pixel calibration
Purpose:
Performing pixel gain and dead pixel correction
Acceptance limits:
Passed / Not passed / Failed
GUI informs when calibration is passed
Other calibration items
• Perform full calibration if red exclamation points are
found on calibration screen
•Full calibration if ceph arm is added
•Use S2 service mode command “indicator service
clear” to reset calibration period
Confidential, for distributors only
51
Install the rear cover