IMPACT TO FREQUENCY CONTROL DURING STARTUP AND SHUT DOWN OF UNITS Sandip Sharma ERCOT Operations Analysis 1 Introduction This presentation is intended to explain ERCOT’s expectation of the Resource Entities and QSEs during start-up and shut-down of the units based on the ERCOT Protocol, Operating Guides and Business Practice manual. Due to improper start-up and shut-down at the individual Resource level, there have been performance issues and Base Point Deviation Charges. At the system level, ERCOT has experienced frequency deviations and exhaustion of regulating reserves. 2 Objectives At the completion of this course of instruction you will: 1. 2. 3. 4. 5. Identify the QSE’s responsibilities during Startup and Shutdown. Identify the correct sequence of generation resource Startup. Identify the correct sequence of generation resource Shutdown. Identify the impact on ERCOT Grid Operations of improper start-up or shut-down of units. Identify the impact on ERCOT Market Operations of improper startup or shut-down of units. 3 Agenda Definitions Resource Status QSEs responsibility during Start-up Start-up Sequence Start-up issues QSEs responsibility during Shut-Down Shutdown issues Other observed issues Questions 4 Definitions STARTUP – The Resource is On-Line and in a start-up sequence and has no Ancillary Service Obligations. This Resource Status is only to be used for Real-Time telemetry purposes; SHUTDOWN – The Resource is On-Line and in a shut-down sequence, and has no Ancillary Service Obligations. This Resource Status is only to be used for Real-Time telemetry purposes; GREDP – Generation Resource Energy Deployment Performance SCED – Security Constrained Economic Dispatch RLC – Resource Limit Calculator LSL – Low Sustained Limit HSL – High Sustained Limit NURR – Normal Up-Ramp Rate NDRR – Normal Down-Ramp Rate BP – Base Point 5 Resource Status Startup and Shutdown Status STARTUP – 16 SHUTDOWN - 15 Online Status ONRUC – 1 (hour is RUC-committed interval) ONREG – 2 (with energy offer curve and providing regulation) ON – 3 (online with energy offer curve) ONDSR – 4 (dynamically scheduled resources) ONOS – 5 (with output schedule) ONOSREG – 6 (with output schedule providing regulation) ONDSRREG – 7 (dynamically scheduled resource providing regulation) ONOPTOUT – 18 (online and the hour is a RUC buy back hour) Offline Status OUT – 11 (offline and unavailable) OFFNS – 12 (reserved for offline non-spinning) OFF – 13 (offline but available) 6 QSE’s Responsibility During Start-up Once the generator breaker is closed, QSE must change telemetered Resource Status to STARTUP from OFF. This should be done about a minute prior to SCED run. The QSE should telemeter a Normal Up Ramp Rate value to ERCOT that reflects the MW per minute rate at which the QSE anticipates bringing the Resource On-Line. Low Sustained Limit (LSL) and High Sustained Limit (HSL) should reflect the true capabilities of the Resource (In other words, don’t mess with them) ERCOT does not expect the telemetered Ramp Rate value will be exactly correct, but the QSE should update the ramp rate as often as needed during the start-up process to provide a reasonable estimation 7 Start-up Sequence The QSE should align bringing the Resource OnLine after a SCED execution, which takes into consideration the STARTUP status. RLC will calculate Low Dispatch Limit (LDL) as the telemetered real power output plus the fiveminute ramping capability of the Resources. RLC will set the High Dispatch Limit (HDL) equal to the Low Dispatch Limit (LDL) 8 Start-up Sequence When SCED observes Resource Status of STARTUP, SCED will issue a Base Point equal to LDL which is equal the current telemetered net real power plus five times normal ramp rate of the Resource During periods in which the Resource has a telemetered Resource Status of STARTUP, the QSE is exempt from GREDP scoring and Base Point deviation charges. Once the Resource has reached a stable operating condition and is ready to be dispatched normally by SCED, the QSE should change the Resource Status to an appropriate online status and begin responding directly to ERCOT dispatch instructions. 9 Observed Issues #1. Too high NURR during start-up GENERATION BASEPOINT DEVIATION RESOURCE STATUS NURR 150 30 120 27 90 24 60 21 30 18 MW NURR & 0 09:55 10:00 10:05 10:10 10:15 10:20 10:25 10:30 10:35 10:40 10:45 15 Status 10:50 -30 12 -60 9 -90 6 -120 3 -150 0 10 Observed Issues #2. Too Low NURR during start-up GENERATION BASEPOINT DEVIATION RESOURCE STATUS NURR 510 30 480 450 27 420 390 24 360 330 300 21 270 240 18 210 MW NURR & Status 180 150 15 120 90 12 60 30 0 -3009:40 -60 9 09:45 09:50 09:55 10:00 10:05 10:10 10:15 10:20 10:25 10:30 10:35 6 -90 -120 -150 3 -180 -210 0 11 CORRECT STARTUP SEQUENCE GENERATION BASEPOINT DEVIATION RESOURCE STATUS NURR 600 60 565 57 530 54 495 51 460 48 425 45 390 42 355 39 320 36 285 33NURR & 250 30 Status 215 27 180 24 145 21 110 18 75 15 40 12 MW 5 -3005:25 9 05:30 05:35 05:40 05:45 05:50 05:55 06:00 06:05 06:10 06:15 06:206 -65 3 -100 0 12 QSEs Responsibility During Shut-Down The QSE will initiate the shut-down sequence by changing the Resource status to SHUTDOWN The QSE should telemeter a Normal Down Ramp Rate value to ERCOT that reflects the MW per minute rate at which the QSE anticipates bringing the Resource Off-Line The QSE should not begin taking the Resource Off-Line until a SCED execution has completed taking into consideration the SHUTDOWN status. 13 Shut-Down Sequence RLC will calculate HDL as the telemetered real power output minus the five-minute ramping capability RLC will set the Low Dispatch Limit (LDL) equal to the High Dispatch Limit (HDL) SCED will issue Base Points equal to the HDL and ramp the resource smoothly down to a Base Point of zero 14 Shut-Down Sequence During the shut-down process when the Base Points issued by SCED is above the Resource’s telemetered LSL, the QSE must follow the Base Point instructions issued by SCED For periods in which the SCED Base Point is below the telemetered LSL, the QSE is exempt from Generation GREDP scoring and Base Point deviation charges Once the Resource has reached a real power output level of zero and the generator breaker has been opened, the QSE will change the telemetered Resource Status to an appropriate offline status 15 Observed Issues #1. NDRR not updated accurately during shut-down UDBP BASEPOINT DEVIATION SCED BP RESOURCE STATUS GENERATION NDRR 1000 33 880 30 760 27 640 24 520 21 MW 400 280 18 NDRR & Status 15 160 12 40 16:40 -80 -200 9 16:45 16:50 16:55 17:00 17:05 17:10 17:15 17:20 17:25 17:30 17:35 6 3 16 Observed Issues #2 Improper sequence of shut-down UDBP BASEPOINT DEVIATION SCED BP RESOURCE STATUS GENERATION NDRR 500 20 430 18 360 16 290 14 220 12 NDRR & Status MW 150 10 80 8 10 6 22:10 22:15 22:20 22:25 22:30 22:35 22:40 22:45 22:50 22:55 23:00 23:05 -60 4 -130 2 -200 0 17 CORRECT SHUTDOWN SEQUENCE UDBP SCED BP GENERATION DEVIATION BASEPOINT DEVIATION BASEPOINTRESOURCE STATUS GENERATION RESOURCE STATUS NDRR NDRR 400 400 MW MW 22 375 350 350 21 325 300 300 19 275 250 250 17 225 200 200 15 175 150 150 13 125 100 100 11 20 18 16 14 12 10 75 50 50 25 0 0 23:00 23:00 -25 -50 -50 -75 -100 -100 25 22.5 20 17.5 15 12.5 NDRR & NDRR & Status Status 10 9 8 7.5 7 23:05 23:05 23:10 23:10 23:15 23:15 23:20 23:20 23:25 23:25 23:30 23:30 23:35 23:35 23:40 23:40 23:45 23:45 23:50 23:50 5 6 23:55 23:55 5 2.5 4 3 2 0 18 Other Observed Issues NURR/NDRR telemetry is correct but it is outside the RARF reasonability limit For temporary limitations like configuration change, activation of power augmentation, start second boiler feed-pump, etc. Resource HSLs are not updated to reflect temporary limitations SCED continuously dispatches these Resources economically While SCED dispatches these Resources with temporary limits higher, SCED is also dispatching other more expensive generator lower. This has market impact as well as affects grid frequency and leads to exhaustion of regulation-up service. The impact of these large deviations are similar to what were discussed with Startup and Shutdown 1 For additional details on expected actions from a QSE, please see “ERCOT and QSE Operations Practices During the Operating Hour” Section 3.2 Generation Resource Power Operation. (http://www.ercot.com/content/mktrules/bpm/BP%20ERCOT%20And%20QSE%20Operations%20Practices_v5%205.doc ) 19 Temporary Limitations without AS UDBP MW SCED BP GENERATION HSL HASL BASEPOINT DEVIATION NURR 700 50 660 40 620 30 580 20 540 10 500 0 460 -10 420 -20 380 -30 340 -40 300 -50 260 220 Into duct firing mode -60 -70 180 -80 140 -90 100 -100 60 -110 20 -120 -2012:15 12:20 12:25 NURR/BP Deviation (MW) 12:30 12:35 12:40 12:45 12:50 12:55 13:00 13:05 13:10-130 -60 -140 -100 -150 20 Temporary Limitations with AS MW HSL GENERATION SCED BP UDBP HASL BASEPOINT DEVIATION NURR 700 50 660 40 620 30 580 20 540 10 500 0 460 -10 420 -20 380 -30 340 -40 300 -50 260 220 -60 Into duct firing mode -70 180 -80 140 -90 100 -100 60 -110 20 -120 -2012:15 12:20 12:25 NURR/BP Deviation (MW) 12:30 12:35 12:40 12:45 12:50 12:55 13:00 13:05 13:10-130 -60 -140 -100 -150 21 Summary Improper start-up and shut-down impacts Grid Frequency, leads to exhaustion of regulation service and has market impacts What RLC and SCED expects during Start-Up and Shut-Down of units were explained Proper sequence of start-up and shutdown were explained 22 Questions 23 1. The QSE’s responsibilities during Startup include: a) about a minute before a SCED run, change Resource Status from OFF to STARTUP b) calculate Low Dispatch Limit (LDL) c) set the High Dispatch Limit (HDL) equal to the Low Dispatch Limit (LDL) d) issue a Base Point equal to LDL which is equal the current telemetered net real power 24 2. When SCED observes a Resource Status of STARTUP on a unit: a) It will issue a Base Point equal to LDL which is equal to current output plus 5 times NURR. b) It will issue a Base Point equal to Normal Down Ramp Rate value. c) It will change the Resource Status to ONLINE. d) It will begin economically dispatching the unit. 25 3. The QSE correct sequence of generation resource Shut-Down is: a) The QSE will initiate the shut-down sequence by changing the Resource status to SHUTDOWN b) The QSE will telemeter a Normal Down Ramp Rate value to ERCOT c) The QSE should not begin taking the resource off-line until a SCED execution d) All of the above 26 4. One impact on ERCOT Grid Operations of improper shut-down of units is: a) b) c) d) Improper shut-down impacts grid frequency Off line non-spin is impacted Start of HRUC delayed during those hours Load resources are incorrectly calculated 27 5. One impact on ERCOT Market Operations of improper start-up of units is: a) Prolonged regulation deployment and impacts system lambda calculation b) DRUC is delayed for those hours c) HRUC is delayed for those hours d) Mid-term load forecast is incorrectly calculated 28