Goals of DVA-1 Meeting • Overall goal: build an SKA antenna with SKA feeds/receivers, verify performance and fabrication/costs for the next stages of the SKA • Project description and definition – purpose and scope – cost – schedule • Partnership – resources (in-kind, cash) • Management – as in MoU draft? • Technical decisions • Program/project decisions 15-16 April 2010 DVA1 Meeting at NSF 1 Technical Decisions • • • • • • Required technical specifications Aperture size (12m – 15m) Optics (offset gregorian): shaping? Backup structure: spars, shell Pedestal type Feed and receiver plan – SPFs – PAFs – Indexer 15-16 April 2010 DVA1 Meeting at NSF 2 Program/Project Decisions • Management plan and MoU/LoI • Schedule – milestones (TDP, PrepSKA, SKA program) – deliverables (hardware test results, reports) • Site – which facility and where on site? • Testing program – single dish tests: • those necessary for the costed system by end-2012 • those needed for antennas program leading to the Phase-I dish array – interferometric tests not within timeline/scope of end-2012 project 15-16 April 2010 DVA1 Meeting at NSF 3 Scope of the DVA-1 Project • The first in a series of converging prototypes that will optimize performance at minimum cost (e.g. A/T per dollar + imaging performance) • A primary deliverable of the US SKA TDP – optimized antenna + feeds for SKA-mid – WBSPFs and PAFs accommodated • A global project but centered in North America • Delivered to the project by end of 2012 (including testing) • Current plan (to be agreed on): – fabrication, integration and testing at EVLA site by end of 2012 to provide input to the costed system design – single-dish tests with suite of feeds – extended testing program as needed for lead-up to Phase-I construction (with post-TDP, post-PrepSKA funding) 15-16 April 2010 DVA1 Meeting at NSF 4 Overall Context in TDP • System cost • Costs that scale with N (antennas, feeds) • Processing costs that scale as N2 x number of beams • Maximize A/T per antenna in a low-cost design • minimizes number of antennas needed for total A/T • also maximizes survey speed via the (A/T)2 factor • Target high imaging dynamic range and minimum susceptibility to RFI (clear aperture) • Demonstrate imaging capability through simulation by Calibration and Processing Group et al. using as input measurements on DVA-1 15-16 April 2010 DVA1 Meeting at NSF 5 Basic specifications • • • • • Offset Gregorian optics Frequency range: 0.3 to 10 GHz (1 to 10 GHz) Aperture efficiency: >60% above 1 GHz Antenna noise temperature <10K Pointing stability: <1% gain variation @half-power point at 1.4 GHz • Minimum 30 year lifetime • Minimum 1 year maintenance interval (target 5 year) • Design to be as close as possible to the final SKA dish design – Assessment of real performance – Good cost estimate 15-16 April 2010 DVA1 Meeting at NSF 6 Optical design of reflectors Working plan: • Dual shaped, offset reflectors with a Gregorian subreflector. • Subreflector opening angle chosen to accommodate wide band feed(s). • Shaped optics having very low spillover and high aperture efficiency to maximize A/T in a design intended to minimize costs • Usage of available real estate for multiple feeds and a PAF; DVA-1 will include a feed indexer 15-16 April 2010 DVA1 Meeting at NSF 7 Reflector design options Dual shell reflector and support, composites Single composite shell and sparse support framing 15-16 April 2010 DVA1 Meeting at NSF 8 Feed Options to Cover 0.3 to 10 GHz (nominal) 15-16 April 2010 DVA1 Meeting at NSF 9 Canadian CART program + TDP Work by Matt Fleming: 15-16 April 2010 DVA1 Meeting at NSF 10 Issues and Decisions • Diameter: 15m nominal (12m still possible as a choice) • Optical design: offset Gregorian optics – rationale for shaped optics in TDP Memo (in prep) – final choice depends on assessment of imaging performance and long-term flexibility as well as optimized A/T @ minimum cost • Fabrication material – dual-shell composite vs composite + metal spar structure – (segmented metal is a possible parallel approach) • Full suite of TDP-developed feed antennas that cover 0.3 to 10 GHz – various combinations of WBSPFs and octave feeds – antenna will accommodate a PAF when appropriate • Feed indexer included in design with deployment at appropriate phase of testing 15-16 April 2010 DVA1 Meeting at NSF 11 • Developing DVA-1 Partnership Cornell/TDP – – Optical design: Baker, Cortes, Imbriale (JPL) WBSPFs: • • • – – • N. Roddis and P. Dewdney NRAO – • • • • G. Lacy (mechanical, composites) G. Hovey S. Dougherty SPDO – • Mechanical design: Fleming (Minex) Calibration and Processing: Kemball (UIUC) et al DRAO (CART program for composite reflector) – – – • Cortes (Cornell) Weinreb (Caltech) Welch (UCB) Project management and integration with EVLA Australia/CASS China/JLRAT South Africa/MeerKAT Testing: – – single dish tests by TDP team + other partners array tests: in 2012+ post-preparatory/engineering design phase 15-16 April 2010 DVA1 Meeting at NSF 12 Management of DVA-1 To be agreed upon: • Project Manager • Project Engineer • Collaboration Board (Cornell, DRAO, NRAO, SPDO, …) – determined by groups that sign on to the project • DVA-1 design reviews – coordinated with (but separate from) SPDO design reviews 15-16 April 2010 DVA1 Meeting at NSF 13 DVA Context & DVP Goals P. Dewdney Apr 15, 2010 System Hierarchy (Part 1) SPDO SKA User System Telescope Dish Cryo WBSPF Feed Receptors PAF Receivers LNA Feed elements Beamformer LNA To Figure B People Sparse AA Array (Low) DVP Dish Array L7 User System Sparse AA Array (High) Beam management Receptors Feed elements LNA Beamformer L6 System L5 Elements Dense AA Array Beam management Receptors Feed elements Beam former L4 Sub systems Beam management L3 Assemblies LNA L2 Sub-assemblies L1 Components L0 Parts 16 System Hierarchy (Part 2) SPDO L7 User System From Figure A Facilities Signal Proc Channeliser and Correlator Non visibility processor Grid STaN Core site Backup Computing and Software Central site Alternative Power Outlying stations Antenna foundations Core site Infrastructure Central site Trenches Core site Outlying stations Roads Water Support Fences Signal Processing Facility L6 System Central site Visitor centre Stores Off site Support Support Workshops Offices L5 Elements Regional Centres HQ Operations and Maintenance Centre(s) L4 Sub systems Regional Engineering Centres L3 Assemblies L2 Sub-assemblies L1 Components L0 Parts 17 Dish Verification Program (DVP) SPDO • Process to verify performance of dishes for the Dish Array in the System Hierarchy. – Element level. • Dishes equipped with well defined interfaces to other system elements: – – – – • Power Signal transport Monitor and Control Other infrastructure Verified to be capable of handling all feeds and receivers needed to carry out the dish-based science. – May not be so-equipped at initial roll-out. 18 DVP Goals • Risk reduction SPDO – When built up into the SKA system, show that dishes will meet all the science requirements; – Also meet all other requirements needed to integrate into a system and operate in the field. • Design, produce and test one or more SKA antennas; – with the greatest system sensitivity (Ae/Tsys and/or Survey Speed) per unit system cost (total cost of ownership); – As well as possible, ensure that the contribution of antenna-related systematic errors is within acceptable limits; – Designs/testing programs converging to a detailed design that is manufacturable in production quantities. • • Understand the costs. Converge to a production-ready, documented antenna 19 design (production data-pack). Integrated Approach SPDO SKA Science Case DRM SYSTEM Tradeoffs Concept Phase System Definition Phase DRM Analysis Requirements Development Analysis Validation High level requirements Memo 100 Concepts System Prelim Design Phase C O D R Design Functional analysis, verification and synthesis Design verification S R R P D R Technologies Risk Management Plan Selections for reference design Risks ELEMENTS Concept Phase Concepts DVAs Tradeoffs Definition Phase C O D R Requirements (Development, Analysis , Validation) Prelim Design Phase S R R P D R Design (Functional analysis, verification and synthesis, Design verification) Risk mitigation strategies and projects Verification programmes (DVP, AAVP, other domains), Design studies, Precursors, Pathfinders Risks RISK MANAGEMENT 20 Time Scale SPDO 2009 2010 2011 2012 2013 2014 2015 2016 Detailed Design, Prod. Eng & Tooling SKA Preparatory Phase 2017 2018 Phase 1 Construction, Verification, Commissioning, Acceptance, Integration & First Science Phase 2 ….. REV Science REV REV REV Science / Engineering tradeoffs DRM Development Phase 2 Science Development Revision of Science Case Early Science Proposals Refinement of Early Science REV CoDR PDR SRR System Engineering Definition and Design CoDR Dishes Concept Definition AAs AAVS2 development and testing PDR CDR Preliminary Design SRR Factory Assembly, Integration and Testing Purchase or Fabrication PDR Sub-System Definition CDR Preliminary Design Data Storage Phase 2 Continuation PR Factory Assembly, Integration and Testing Site Assembly, Integration and Testing Detailed Design Phase 2 Correlator Design Temporary Software Correlator SRR Software Requirements Definition Preliminary high level architecture Phase 2 Continuation Phase 2 Continuation Site Assembly, Integration and Testing Pulsar and Transient Processor Monitoring & Control Phase 2 Continuation AAVS2 demo Hardware Correlator Early Fabrication Beamformer and Correlator Imaging Concept Factory Assembly, Integration and Testing PR Detailed Design Front End and Channeliser CoDR Software & Computing Review dates are preliminary. PR Tooling and Early Fabrication CDR Prototype AAVS1 Testing Sub-System Definition CoDR Signal Processing PDR SRR Concept definition CDR DVA2 development and testing Site Assembly, Integration and Testing AA Prototype Fabrication CoDR Signal transport & Networks Phase 1 Verification and Commisioning Continuous Performance Evaluation DVA1 Prototype Dish Testing SRR AA Sub-Sys. Definition Phase 1 Systems integration Phase 1 System Testing Continued System Engineering for Phase 2 PDR SRR CoDR Aperture Arrays CDR System refinement, change management DVP DVA1 Dish Prototype Fabrication Dish Sub-Sys. Definition Concept Definition Dishes, AAs Shared Risk Science Operations REV PDR Refine high level architecture Preliminary Design CDR Detailed Design, Coding, Integration with platforms and testing Phase 1 Refinement and Roll-out On-site Testing S/W Development & Roll-out for Phase 2 PDR RFI Monitoring RQZ Site characteristics Atmospheric studies Configuration studies Continued RFI and Tropo Monitoring Remote Station Land Acquisition & Environmental Studies report Site Engineering CDR CDR Central Data Processing Facility Site Acceptance tests including RFI qualification Science Computing Facility Infrastructure Detailed Design (fibre & power) Infrastructure Detailed Design (buildings) Phase 2 Continuation Ops and Maintenance Facility Antenna Foundations and Trenching Roll out CoDR Project management PrepSKA Plan SKA Scope definition WBS, resource allocation PDR CDR PM Plan & Schedule Final SKA Deployment Plan Project execution, monitor and control Project staffing & development Milestones Baseline design for Phase 1 Rev 7a 2010-04-13 2009 2010 2011 Phase 1 construction approval Costed system design Site decision 2012 2013 Start of Phase 1 Construction 2014 2015 Baseline design for Phase 2 2016 2017 Start of Phase 2 Construction 2018 21 Time Scale SPDO 2009 2010 2011 2012 2013 SKA Preparatory Phase CoDR Dishes Concept Definition PDR SRR Dish Sub-Sys. Definition DVA1 Prototype Fabrication 2014 2015 2016 Detailed Design, Prod. Eng & Tooling DVA1 Prototype Testing Phase 1 Construction CDR DVA2 development and testing PR Tooling and Early Fabrication Milestones Baseline design for Phase 1 Rev 7a 2010-04-13 2009 2010 2011 Phase 1 construction approval Costed system design Site decision 2012 2013 Start of Phase 1 Construction 2014 2015 2016 Review dates are preliminary. 22 End 23 Extra 15-16 April 2010 DVA1 Meeting at NSF 24 Verifying dish performance • Antenna and feed design parameters: – Mount type – Reflector: • Overall system performance verification: – Cost per unit achieved sensitivity as a function of: • Angular distance from center of main lobe: ρ • Polarization: {I,Q,U,V} • Frequency: ω • Size, shape, and manufacturing method – – – – – Optics Feed and illumination Polarization purity Net bandwidth Etc. • Measurements on DVA-1 15-16 April 2010 – Feasibility: • Limiting sensitivity in {I,Q,U,V} (ρ ,ω) due to uncorrected systematic errors. • Assessment of antenna performance vis a vis science requirements (end to end simulations) DVA1 Meeting at NSF 15-16 April 2010 DVA1 Meeting at NSF 26 • Optical design of reflectors. Dual shaped, offset reflectors with a Gregorian subreflector. Subreflector opening angle chosen to accommodate wide band feed(s). Shaped optics having very low spillover and high aperture efficiency. Incorporation of “real estate” for multiple feeds and a PAF. • Light weight, optimized mechanical design Utilization of single shell reflectors as integral structural members. Inclusion of a feed indexer to mount multiple feeds. Design for low cost in mass production. • Mount and test multiple feeds and receivers. Optics designed to accommodate feeds of intermediate gain which achieves a practical primary reflector size. • Basic specifications: Frequency range: .3 to 10 GHz. Aperture efficiency: >60% Antenna noise temperature <10K Pointing stability: <1% gain variation @ ½ power point (1.4 GHz.) Minimum 30 year lifetime Minimum 1 year maintenance interval (target 5 year) • 15-16 April 2010 DVA1 Meeting at NSF 27 15-16 April 2010 DVA1 Meeting at NSF 28 Meeting Motivations and Outcomes • • • • NSF review of TDP and DVA plan forthcoming Overall timelines for SKA, TDP and PrepSKA Readiness for convergence in D&D Parallel development plan for SKA antennas – DVA-1, DVA-2 … – Large volume manufacturing options and costs • conventional, composites, hydroforming • SKA project decision tree over next 5yr – tradeoffs between science, costs and schedule 15-16 April 2010 DVA1 Meeting at NSF 29 DVA-1 Project Book • Purpose of DVA-1 – • • Relationship to DVA-2 How it fits into overall DVP activity Technical description • • • • • • • • Test site (and reflector fab) Testing plan and elements • • • • • Reflectors Backup structure Pedestal Indexer Feeds and receivers Interface to EVLA network and correlator single-dish tests array tests Decommissioning of DVA-1 Detailed schedule Management • • • Organizations, Personnel and Org chart Funding and funding profile MoA or MoU? 15-16 April 2010 DVA1 Meeting at NSF 30