SmartMeterTM Steering Committee Update – April/May 2012 ©2011 Pacific Gas and Electric Company. All rights reserved. Agenda ► ► Monthly Updates ► Release Status Update ► Deployment Status Update ► Schedule Update ► Deployment Update ► Budget Status – Expenditures by Workstream ► Budget Status – Benefits ► Issues / Risks Summary ► Program Metrics Appendix ► Project Deployment Plan Progress ► Contingency Reconciliation ► SmartMeterTM Acronyms Steering Committee May 2012 Report 2 Release Status Update EAC Funded Budget ITD Scope Schedule Resources Issues Risks IT Releases: April 30, 2012 Release 1 Release 2 Release 3 Challenges Actions/Status Overall Overall ▪ IT has executed against the SmartMeter plan. HAN enablement and Peak Time Rebate roadmaps are in progress. ▪ Development for all in-scope functionality completed as of 3/30/12 ▪ Project stabilization work complete for all components except MV90 and NEMs. Steering Committee May 2012 Report 3 Deployment Status Update EAC 2012 Forecast Scope Schedule Resources Issues Risks (2012 EOY / CPI) Deployment: April 30, 2012 Endpoints (2012 YTD) Gas Network (2012 YTD) Electric Network (2012 YTD) Challenges Actions/Status Endpoints Endpoints ▪ Mass deployment nearly complete. Remaining meter installs in less concentrated geographic areas. ▪ Field Deployment team addressing less common meter types, customized solutions and final installations in areas containing meters left to exchange. ▪ Resources focused on opt-out requests during the months of February through April ▪ Increased number of ‘Unable-To-Complete’ meters due to non-standard meter installations in heavy urban areas (SF) and access refusals related to Customer Choice. ▪ Continuing to complete requests for opt-outs in a timely manner while addressing remaining SmartMeter™ installations and UTCs. ▪ Term Sheet developed with installation contractor to finalize 2012-2013 schedule for deployment of remaining meters while recognizing complexity of less common meter types. ▪ Development of NEMS-configured meter pilot underway ▪ Development of pilot for Transformer-Rated meter forms is scheduled for mid-June. Electric Network Electric Network ▪ Initial design scope of electric network now complete. ▪ Whether additional electric network is necessary is subject to ongoing review, particularly in light of customers opting-out of SmartMeter™ Program. ▪ Tracking opt-outs to assess impacts on network. ▪ Working with technology supplier and internal stakeholders to address network coverage in ‘hard-to-reach’ areas. Steering Committee May 2012 Report 4 Schedule Update As of 4/30/12 2012 Jan Feb Apr Mar IT Release Deployment May Jun Jul Aug Sep Oct Nov Dec 2013 Jan Feb Mar All in-scope functionality completed SM Operations Center Field Delivery 9.0M Meters/Modules in service Begin SmartMeter Opt-Out Program Begin NEMS pilot Begin NEMS deployment Begin Transformer Rated Pilot Release additional work per 2012 – 2013 Deployment Plan Benefits Meter Reading Reductions (ITD) Legend Baseline Milestone Forecasted Milestone (early) 594 Positions Captured Milestone Met Milestone TBD Forecasted Milestone (delay) Approved Milestone (delay) Steering Committee May 2012 Report 5 As of June 1, 2012 Deployment Update Steering Committee May 2012 Report 6 2012 Budget Status – Expenditures by Workstream Current Month - April # Work Stream Budget Actual Year to Date - April Variance Budget Actual Variance 2012 Annual Budget * Inception to Date Actual # A. Capital (000s) 1 BUSINESS OPERATIONS (PMO) 2 SM OPERATIONS $56 $10 $46 $953 $745 $208 $1,060 $50,048 1 $0 $0 $0 $0 $0 $0 $0 $11,310 3 2 SM FIELD DELIVERY $4,258 $1,075 $3,183 $19,702 $17,248 $2,454 $57,202 $418,598 3 4 SM SOLUTIONS $2,873 ($902) $3,775 $4,075 $1,526 $2,548 $21,970 $974,604 4 5 IT $162 $168 ($6) $6,206 $4,739 $1,467 $10,656 $374,365 5 $7,349 $350 $6,999 $30,936 $24,259 $6,677 $90,888 $1,828,926 6 $120 $11 $109 $825 $19 $806 $1,955 $26,359 7 $0 $0 $0 $0 $0 $0 $0 $56,594 8 $50 $114 ($64) $150 $124 $26 $150 $15,008 9 $1,897 $568 $1,329 $2,658 $1,566 $1,093 $13,960 $98,566 10 $23 $2 $21 $140 $3 $137 $302 $17,996 11 $0 $7 ($7) $0 $28 ($28) $0 $68,017 12 $215 $115 $100 $1,310 $769 $541 $5,363 $133,893 13 $2,305 $817 $1,488 $5,083 $2,509 $2,574 $21,730 $416,433 14 $176 $21 $155 $1,778 $764 $1,014 $3,016 $76,407 15 $0 $0 $0 $0 $0 $0 $0 $67,904 16 $50 $114 $150 $124 $26 $150 $15,008 17 6 Capital Total: B. Expense (000s) 7 BUSINESS OPERATIONS (PMO) 8 SM OPERATIONS 9 SM CHANGE MANAGEMENT 10 CUSTOMER 11 SM FIELD DELIVERY 12 SM SOLUTIONS 13 IT 14 Expense Total: C. Total: Capital + Expense (000s) 15 BUSINESS OPERATIONS (PMO) 16 SM OPERATIONS 17 SM CHANGE MANAGEMENT 18 CUSTOMER $1,897 $568 $1,329 $2,658 $1,566 $1,093 $13,960 $98,566 18 19 SM FIELD DELIVERY $4,281 $1,077 $3,204 $19,843 $17,252 $2,591 $57,503 $436,594 19 20 SM SOLUTIONS $2,873 $3,768 $4,075 $1,554 $2,520 $21,970 $1,042,622 20 21 IT 22 Capital + Expense Total: ($896) ($64) $377 $283 $94 $7,516 $5,508 $2,007 $16,019 $508,258 21 $9,654 $1,167 $8,487 $36,019 $26,768 $9,251 $112,618 $2,245,359 22 Year-to-Date Variance Explanations: Favorable YTD capital variance ($6.7M) primarily due to a misunderstanding during a staffing change resulting in goods receipts not being entered (#3), fewer electric meter purchases (#4), and a delayed timing of the initial HAN roll-out (#5). Favorable YTD expense variance ($2.6M) primarily due to lower spending than planned in Business Operations/PMO (#7) and Customer (#10). * 2012 capital and expense budgets currently in the process of revision to align with the revised 2012 – 2013 deployment schedule Steering Committee May 2012 Report 7 2012 Budget Status – Benefits SmartMeter Balancing Account (SBA) Credits * Actual ($ in thousands) 2007 2008 2009 2010 2011 Remaining Budget Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec ITD Actual # $ 117,744 1 $ 21,250 2 $ 138,994 3 # 1 111 $ 4,705 $ 26,055 $ 56,313 $ 20,269 $ 2,479 $ 2,587 $ 2,599 $ 2,626 $ 2,473 $ 2 Mainframe License Benefits: $ 1,250 $ 5,000 $ 5,000 $ 5,000 $ 5,000 $ 3 Total: $ 1,361 $ 9,705 $ 31,055 $ 61,313 $ 25,269 $ 2,479 $ 2,587 $ 2,599 $ 2,626 $ 2,473 $ 2,515 $ 2,557 $ 2,600 $ $ 2,479 $ 5,066 $ 7,665 $ 10,291 $ 12,764 $ 15,279 $ 17,836 $ 20,437 $ 23,081 $ 4 Activated Meter Benefits: $ 2012 Cumulative Actual + Forecast: - $ - $ - $ - $ - $ 2,515 $ - 2,557 $ $ - $ 2,600 $ - 2,644 $ $ - 2,689 $ $ 2,644 $ - 2,734 $ $ 2,689 $ - 2,780 $ - 2,734 $ 2,780 25,770 $ 28,504 $ 31,284 Oct Dec 4 2012 Benefits, Budget vs. Actual and Forecast ** ($ in thousands) Jan Feb Mar Apr May Jun Jul Aug Sep Nov Budgeted Benefits: 5 Monthly 6 Cumulative $ 2,373 $ 2,412 $ 2,392 $ 2,432 $ 2,473 $ 2,515 $ 2,557 $ 2,600 $ 2,644 $ $ 2,373 $ 4,785 $ 7,177 $ 9,609 $ 12,082 $ 14,597 $ 17,154 $ 19,755 $ 22,399 $ 2,734 $ 2,780 5 25,088 $ 27,822 $ 2,689 $ 30,602 6 2,734 $ 2,780 7 31,584 $ 34,318 $ 37,098 8 6,497 9 Actual / Current Forecast: 7 Monthly 8 Cumulative 9 YTD Variance $ 3,724 $ 4,244 $ 4,019 $ 4,118 $ 2,473 $ 2,515 $ 2,557 $ 2,600 $ 2,644 $ $ 3,724 $ 7,968 $ 11,987 $ 16,106 $ 18,579 $ 21,094 $ 23,651 $ 26,251 $ 28,895 $ $ 1,351 $ 3,183 $ 4,811 $ 6,497 $ 6,497 $ 6,497 $ 6,497 $ 6,497 $ 6,497 $ 2,689 $ 6,497 $ 6,497 $ * 2011 and 2012 SmartMeter Balancing Account (SBA) actuals and forecasts consistent with the GRC Settlement of $0.92 electric / $0.02 gas activated meter-month savings and the discontinuation of mainframe license savings already captured in the 2008 base year results ** 2012 benefits, budget versus actual and forecast, do not include meter reading costs and benefits which are being recorded in the Meter Reading Memorandum Account beginning on January 1, 2011. Steering Committee May 2012 Report 8 Issues Summary Target Resolution Date Ongoing Issue Increasing number of installations affected by access refusals and desire for customer choice program. Impact Increased costs, increase in unable to complete (UTC) back-log, customer change management. Status Summary Communicating with customers about the new SmartMeter Opt-Out Program to facilitate customer elections. Steering Committee May 2012 Report 9 Risks Summary # Created On I P Score Prev. Score 1 9/30/2011 5 4 20 20 Risk Impact Increased forecast deployment costs and external resources requirement Increased installation costs and contract resources required to complete remaining installations effectively and timely Pursuing identified opportunities to increase installation efficiency within ongoing operations and adherence to scope. Deployment delays, resource planning and increased costs. Pursuing resolution of network coverage in ‘hard-to-reach’ areas with technology supplier, including potential alternate network solutions. Key drivers: Delays in deployment, resource availability and installation complexity 2 9/1/2011 5 3 15 15 Network deployment and performance in ‘hard-to-reach’ areas can not be completed successfully. Status Summary Assoc. Issue Key drivers: Network performance in ‘hard-to-reach’ areas and availability of alternate solutions. Steering Committee May 2012 Report 10 Program Metrics Month Results Target Var March '12 Actual Metric Key Performance Indicator Month Results Target Var April '12 Actual Actual YTD Target Var 23.3 23.3 -0.1% 2012 Year End Forecast Actual Target Var P1 SM Earnings Contribution ($M estimated) P2 OSHA Recordable Rate (YTD) - 0.51 - 0.51 - 0.51 P3 MVI Recordable Rate (YTD) - 0.98 - 0.98 - 0.98 C1 Customers enrolled in SmartRate (net) 21,845 (track only) 21,731 (track only) C2 # of CPUC escalated Customer Complaints 8 (track only) 7 (track only) C10 Customer Complaint Rate (escalated to CPUC) 0.033% (track only) D1 Meters/Modules Installed Electric & Gas 24,529 24,000 2.2% 19,808 19,000 4.3% 127,065 127,000 0.1% 400,000 400,000 0.0% D5 UTC Rate 26.6% 15.0% 77% 15.0% 15.0% 0.1% 19.2% 15.0% 28% 15.0% 15.0% 0.0% D7 UTCs open beyond 90 days 223,661 (track only) 226,842 (track only) D8 CPI - Endpoints $150.11 D14 Total Weeks of Inventory on Hand - Electric Meters 10 6 57.5% 11 6 73.9% D15 Total Weeks of Inventory on Hand - Gas Modules 9 6 42.7% 8 6 27.1% O4 Transition Aging - Average Days 188 (track only) 319 (track only) O5 SM Billing accuracy % (SA) 99.95% 99.88% 0.1% 99.95% 99.88% 0.1% 99.95% 99.88% 0.1% 99.88% 99.88% 0.0% O6 SM Billing timeliness % (SA) 99.97% 99.81% 0.2% 99.97% 99.81% 0.2% 99.97% 99.80% 0.2% 99.79% 99.79% 0.0% O7 SM % Bills not estimated (BSEGs) 99.95% 99.90% 0.1% 99.95% 99.90% 0.1% 99.95% 99.90% 0.1% 99.90% 99.90% 0.0% B2 Meters Activated - Electric & Gas (end of month) 61,525 (track only) 54,683 (track only) $ 5.8 $ 5.8 -0.5% $ 5.8 $ 5.8 0.0% 24 0.035% (track only) $ 71.2 $ 70.8 Variance Analysis 0.6% (track only) 0.019% (track only) $111.24 CPI target under review in conjunction with revised deployment plan $128.45 168 524,416 See Deployment Status Update on page 4 (track only) (track only) 152 850,412 (track only) (track only) Steering Committee May 2012 Report 11 Project Deployment Plan Progress Combined Gas and Electric Plan, Target, and Actuals (Cumulative) 11,000 10,000 9,000 8,000 7,000 6,000 5,000 4,000 3,000 2,000 1,000 0 EOY Q108 Q208 Q308 EOY Q109 Q209 Q309 EOY Q110 Q210 Q310 EOY 2007 2008 2009 2010 # in Thousands Q111 Q211 Q311 EOY Q112 Q212 Q312 EOY 2011 2012 Q113 Q213 Target Bus Case Plan Actual Steering Committee May 2012 Report 12 Contingency Reconciliation Steering Committee May 2012 Report 13 SmartMeterTM Acronyms SmartMeter Acronyms Acronym ABS AFCI AMI AP Apps ASM BDG CC&B CEDSA CoE CPI CPUC DART DC DCU DR DRA DSCI EA EAC ED EMR EMT EOM EON EOY FA FD GE GFI HAN HC IHD ISTS IT ITD IVR KC KVAR LOB Definition Advanced Billing System Arc Fault Circuit Interrupter Advanced Metering Infrastructure Access Point Applications Automated Storage Management Business Development Group Customer Care and Billing Centralized Electric Distribution System Assets Center of Excellence Cost Per Install California Public Utilities Commission Distribution Asset Reconciliation Tool Data Center Data Collector Unit Disaster Recovery Division of Ratepayer Advocates Distribution Control Systems, Inc. Ecologic Analytics Estimate at Completion Energy Division Electric Meter Reader Electric Meter Technician End-of-Month Emergency Outage Notification End Of Year Functional Area Field Delivery General Electric Co. Ground Fault Interrupter Home Area Network Head Count In-Home Devices Information Systems and Technology Services Information Technology Inception To Date Interactive Voice Response Knowledge Center Kilo-Volts-Amps Reactive Line of Business Acronym MARA MDMS MLPP MPSC MV-90 MVI NEMS NIC OIR OIS OMT Ops OSHA PCR PCT PDP PDR PE PMO PTR QBR RCDC2 Rev. RF RFA RV SBA SM SM Apps SMU SR TBD TechArch TIC TLM TOU UIQ UTC YTD Definition My Account Re-Architecture Meter Data Management System Meter Location Problem Project Meter Power Status Check Multi Vendor - 90 Motor Vehicle Incidents Net Energy Metering Services Network Interface Card Order Instituting Rulemaking Outage Information System Outage Management Tools Operations Occupational Safety and Health Administration Project Change Request Programmable Communicating Thermostat Peak Day Pricing Project Decision Request Perfomance Engineering Company Project Management Office Peak Time Rebate Quarterly Business Review Remote Disconnect Phase 2 Revision Radio Frequency Request For Authorization Restoration Validation SmartMeter Balancing Accounts SmartMeter SmartMeter Applications SmartMeter Upgrade Service Request To Be Determined Technical Architechture Technology Innovation Center Transformer Load Management Time Of Use Utility IQ - SSN software Unable To Complete (meter installation) Year-To-Date Steering Committee May 2012 Report 14