December 12, 2007
by
Stephen Diebold
Manager – Real Time Systems
Kansas City Power & Light
• Overview of KCP&L
• CIM / PI AF Project
A Convergence of Opportunities
Main Goal
Situation Without Project
Closing the Loop
Asset-Related Applications
Applications
• Interoperability Test
• Project Status
• Questions
• Over 810,000 customers
• Peak in excess of 5,660 MW
• Service territory across 47 counties in MO and KS covering 17,934 sq. miles
• Over 3,170 employees
• 30 office/service center locations
• 9 generation plant sites and 10 peaking facilities
• 3,309 miles transmission lines
• 24,466 miles of overhead distribution lines
• 3,400 miles of underground distribution lines
• 322 substations
A Convergence of Opportunities
• EMS comes with PI Historian
– Stores history of EMS real-time point data
– PI features for model-based access to tags
– Utilizes standards-based CIM model for
EMS database configuration
Main Goal
Transmission Engineering Interest in moving from
Event-based maintenance to
Condition-Based Maintenance
AF
CIM DE
Environment
Situation Without Project
EMS gathering 50,000+ points of real-time data
CIM database where equipment and associated real-time data points defined for EMS
PI Server
..
Point data history stored in PI tags, but accessible only by point name
PI product (AF) able to model equipment’s relationships to tags, but product not currently used field devices
EMS
AF
CIM DE
Environment
PI Server
Closing the Loop
Export CIM model data to PI AF product
Create PI equipment / asset model for retrieving historic tag data
GDA
(Utility Integration Bus)
.
.
• Create infrastructure for generalized retrieval of historic real-time information
– on equipment basis (by reference to equipment location in system)
– on asset basis no matter where asset has been moved in system
• Generalized retrieval is essential to the creation of applications field devices
Network Manager
EMS
Asset
Management
System
Asset-Related Applications
Condition-Based Maintenance
Applications for transformers and breakers
Condition-Based
Maintenance
Applications
AF
PI Server
GDA
(Utility Integration Bus)
PI Server
.
.
• Desktop access
• Paging/Email notification
• Web access
• First step toward
“dashboard” access to real-time Operations data field devices
CIM DE
Environment
Network Manager
EMS
• Demonstrate interoperability between ABB, SISCO and
OSISoft’s products based on the CIM and/or GDA.
• Verify compliance with the CIM for those CIM classes/attributes involved in the information exchanges.
• Demonstrate the exchange of power system models using the CIM and an RDF schema and XML representation of the model data.
• Demonstrate exchange between ABB and SISCO products using the services defined in the GDA Client and Server interface standard.
Vendor
ABB
OSISoft, LLC
SISCO, Inc .
Product Name
• Network Manager, CIM
DE Toolkit
• PI AF
• PI System Explorer
• Part number: UIB -
PIWRAP-412-
095 Version 2.0.0 Beta
• PI Adapter
Tests
• Full Import using CIM XML and
GDA services
• Incremental Import using CIM XML and GDA services
• Storage of the ABB model data
• Review and browsing of the ABB model data
• Full Import using CIM XML and
GDA services
• Incremental Import using CIM XML and GDA services
• Provide UIB message bus for transport and communication
• FAT completed June 4, 2010
• Interoperability tests completed
June 9, 2010
• SAT is being scheduled
Condition-Based
Maintenance
Applications
Asset
Management
System
AF
PI Server
GDA
(Utility Integration Bus)
PI Server
.
.
CIM DE
Environment
Network Manager
EMS field devices
Contact information:
Stephen.Diebold@KCPL.com
December 15, 2007