Troll HVDC

advertisement
Trygve Iversen, ABB AS – OGP, 2010-03-16, Bellona Seminar
Status, benefits and challenges of
Electrification by Power from Shore
© ABB Group
April 7, 2015 | Slide 1
Electrification
© ABB Group
April 7, 2015 | Slide 2

Advocate and develop economical and HSE
sensitive solutions for offshore installations

How

Studies /feasibility

Electrification (power from shore)

Automation

Remote Diagnostics/Condition based
maintenance

Maximize technology utilization to minimize
OPEX by moving the personnel on-shore
Power from (to) Shore solutions
HVDC
HVDC
HVDC
AC
AC
© ABB Group
April 7, 2015 | Slide 3
“Classic” (Radial Feed) Power from (to) Shore

E-On
Wind farm

Troll, Valhall, Luva, + +
Oil Platform
HVDC
HVDC
Station
offshore
HVDC

Gjøa, Goliat, Halul, + +
Oil Platform
HVAC
HVDC

>50MW

>150km

>200MW

>100km
HVAC

<150MW

<150km
Onshore
Converter
Onshore
Sub Station
© ABB Group
April 7, 2015 | Slide 4
onshore
Onshore
Converter
Offshore Grid
Multi-terminal HVDC Light solutions (Ring Net)
Wind farm
Wave farm
Wind farm
Platform
DC
Platform
DC
Platform
AC
Platform
AC
Hosted on platform
or buoy
Platform
DC
onshore
Onshore
Converter
© ABB Group
April 7, 2015 | Slide 5
Onshore
Converter
Technology Selection: GT vs. AC vs. DC
Power
(MW)
AC Transmission
An Example of
Economical Window of
Opportunity for Power From / To Shore
DC Transmission
Gas Turbines
Distance
(miles)
© ABB Group
April 7, 2015 | Slide 6
Business Process – Early Involvement / Studies
Market Shift to system approach
The most critical decisions are
made early
Secure best information for
optimal decisions
System approach
early start
Feasibility
Concept
All Electric
decision
© ABB Group
April 7, 2015 | Slide 7
Pre Feed
Product suppliers responds
to RFQ here
Feed
MEV
decision
Basic/
Detailed Design
/FAT
Products and
services
Installation/
Commissioning
Start-up
Operation
Power From Shore
Delivered
Statoil Troll, HVDC-Light Compressor drives, 2x40MW, ca. 80km
Statoil Gjøa, AC Power, 40MW, 100km, 90kV
Under Delivery
BP-Vallhall redevelopment, HVDC, 78MW, 292km (Revamp)
E.On Windpower hub, HVDC, 350MW, ca 200km incl onshore (power to shore!)
In pursuit
ENI-Goliat, 60-120MW, 90km, HVAC
Studies ABB has participated in recently:
Shell Draugen redevelopment, HVDC or AC, 60MW, 60km
Statoil & Others -Halten Banken electrification, HVDC and HVAC
In concept / feed
Conoco-Phillips Ekofisk –HVDC (Revamp)
Qatar Petroleum, PS4-platform, 25-30MW, 80km, 60-66kV (AC)
Qatar Petroleum, Halul Oil Terminal, 100-130MW, AC!
Saudi Aramco, Safaniyah
Statoil, Mariner & Bressney
Statoil, Gudrun (Platform to Platform, i.e. Sleipner to Gudrun)
Statoil, Sleipner (50/60Hz converter –Platform to platform)
(Statoil-Shell-Total, Norskehavet (to start end 2009) –Multi terminal HVDC and HVAC)
Statoil-Luva HVDC
© ABB Group
April 7, 2015 | Slide 8
Abu Dabi, Das Island
Troll HVDC
© ABB Group
April 7, 2015 | Slide 9
Off shore power supply .. Troll

Troll, HVDC-Light

Pre-Compressors


© ABB Group
April 7, 2015 | Slide 10
2x40MW, ca. 80km
In operation 2005
Valhall HVDC
© ABB Group
April 7, 2015 | Slide 11
Valhall
Description

One HVDC light station
off-shore and one on-shore

292 km HVDC Cable
Lista
Main data

P
= 78 MW

UDC
= 150 kV
Status

Onshore station in operation

Offshore module being installed

Commercial operation 2010
© ABB Group
April 7, 2015 | Slide 12
Valhall
Valhall – PFS – Technical solution
Phase Reactors
Transformer
© ABB Group
April 7, 2015 | Slide 13
Valves
Eon Netz
Wind Power to Shore
© ABB Group
April 7, 2015 | Slide 14
EON 2 off shore cluster
400 MW off shore
convertor
128 km sea cable
75 km land cable
400 MW convertor
© ABB Group
April 7, 2015 | Slide 15
Gjøa HVAC
© ABB Group
April 7, 2015 | Slide 16
Gjøa

High Voltage AC

40MW, 100km

In operation 2010

Similar projects
underways
Goliat
Halul-Qatar
Al
Mojan-Qatar
Safaniyah-Saudi
(Abu
© ABB Group
April 7, 2015 | Slide 17
Dabi)
Middle East Electrification
© ABB Group
April 7, 2015 | Slide 18
Cable Projects in Qatar
Al-Morjan(Qxy)
Existing Cable
25-30 MW
PS 4(QP)
50/60 HZ
Handled
66kV
by ABB NO OGP
80-90 km
Ras Lafan
as a system delivery
100 km
Halul Island
Al-Khalij
Total
100 MW
Future
HVAC
132 kV
© ABB Group
April 7, 2015 | Slide 19
Cables
PS 2
PS 3
QP
QP
Saudi Arabia -Safaniyah
Customer

EPC’s : McDermott, NPCC
End-user:
Consultant:
Overall Project Scope
CLOUGH ZUHAIR FAYEZ PARTNERSHIP

Meet the Crude Program production and
Maximum Sustainable Capacity (MSC) targets for
the Safaniyah Field of 1,300 MCBD by 2013.
Increase transportation capacities. Install new
ESP’s
Project Location

© ABB Group
April 7, 2015 | Slide 20
Safaniyah is located in the Northern Area of
Arabian Gulf
Safaniyah KSA
PROJECT
SCOPE
TP-17
GOSP 4
69
kV
910
Upgrade &
electrification
KSA
Safaniyah is the
largest offshore oil
field in the world.
Customer:
EPC’s
End-User: Saudi
Aramco
© ABB Group
April 7, 2015 | Slide 21
656
930
470
348
15 kV
Existing
TP-18
GOSP 3
230 kV
646
940
Electrificatio
n
243
275
115kV
Project name:
Safaniyah Crude
Gathering upgrade
69 kV
TP-20
New Facilities
Country ;
TP-19
A
u
x
Offshore
TL-11
T
Y
V
S
SA
115
kV
115 kV O/H
230 kV O/H
SEC
230
kV
Onshore
SFNY GOSP-1
380 kV O/H
SEC
Maaden
Concept Krieger’s Flak
© ABB Group
April 7, 2015 | Slide 22
Kriegers Flak, individual cables

© ABB Group
April 7, 2015 | Slide 23
Classic issue
involving multiple
countries
Kriegers Flak, “Supergrid” concept
Barsebäck
BWL
100 km
1100 MW VSC
KF 2, 640 MW
KF 1, 330 MW
±300 kV DC
VSC
1100 MW VSC
11+60 km
11(55) +121
km
1100 MW
Bentwisch/Guestrow
© ABB Group
April 7, 2015 | Slide 24
KF 3, X MW
(Option)
Baltic 1
50 MW
Concept Super Grid
© ABB Group
April 7, 2015 | Slide 25
Supergrid concept (Vision)


Main concept, combine:

Integration of renewable energy

Interconnections for trading

Security of supply
Benefits

Reduced investment

Increased trading capacity

Back-up power, e.g. hydro power
can support wind power

Large geographic area gives more
stable production
© ABB Group
April 7, 2015 | Slide 26
WG Offshore grid


© ABB Group
April 7, 2015 | Slide 27
Vision 2020 – an offshore grid
enabling

Offshore wind parks

Power supply to oil fields

Energy exchange between
markets

Ancillary services (freq control
++)
Task

Describe technology status

Describe ambitions towards an
off shore grid

Describe R&D challenges
Opportunities and Challenges
Opportunities:

Technology is available, no significant technology gaps

More compact HVDC solutions possible (reduced installed costs, 2 years to
develop)
Challenges:

Time (not long until 2020)

Projects take time, typically 5-8 years from concept to operation


Production limits

Cables


Get started!!!
Build additional production lines (3-5 years)
Engineering resources

Limited supply of qualified engineers

© ABB Group
April 7, 2015 | Slide 28
Shift resources from other areas (2-4 years)
Download