Cover Oregon Weekly status report covering week 2 For week ending May 23, 2014 Transition Project Director: Tina Edlund Senior Project Manager: Sarah Miller Submitted by: Deloitte Consulting Submission Date: May 27, 2014 Version 1 Executive Summary Overall Status Y Needs Attention Rationale: Lack of direct access to OHA development/test environments through the end of Week 2, has slowed down progress on the verification of OHA MAGI solution. Key Accomplishments • Submitted Deliverable 2 – Status Report for Week 1 • Submitted Deliverable Expectations Documents for: MAGI Medicaid Roadmap, Requirements Catalog, QHP to FFM Strategy for state review • FFM data collection tool for Oregon-specific Medicaid Program rules completed and submitted to CMS on May 23 • Began assessment of the Cover Oregon site to identify content needed to support the transition to FFM • Application Intake & Case Management and Interfaces Account transfer team sessions contributing to data crosswalks • Reviewed programs/benefit hierarchies for MAGI Medicaid Children’s Health Insurance Program (MAGI MA/CHIP) eligibility and reviewed Non-Financial rules to identify gaps in the current Cover Oregon rule set • Initiated the review of available Oregon Health Authority (OHA) security policies, procedures, security design, security system plan and other security related artifacts • Initiated ‘significant challenges (in transition to FFM by Nov)’ discussion to identify and prioritize scope decisions Key Next Steps • • • • • Discuss and document ‘significant challenges (in transition to FFM by Nov)’ and associated decisions needed to overcome them Review use cases, process flows and requirements with Modified Gross Adjusted Income (MAGI) Medicaid project stakeholders Review key financial rules for MAGI Medicaid/CHIP programs and document gaps in the current Cover Oregon rule set Complete services mapping matrix which compares State MAGI validation plan to FFM services Develop refined Application Intake options in conjunction with Security, Application Intake, and Eligibility teams Key Issues/Risks • Lack of direct access to OHA development/test environments through the end of Week 2 of the assessment, is negatively impacting available time for Deloitte to make feasible assessment of OHA system current state Status Report for week ending May 23, 2014 1 Copyright © 2014 Deloitte Development LLC. All rights reserved. Cover Oregon – Status Report Dashboard # Week ending May 23, 2014 % Complete Key Deliverables Completion Date Sign-Off Date Status Workstream #1: Project Management 1.1 Project approach and staffing plan 100% May 14, 2014 May19, 2014 G 1.2 Weekly status report covering week 1 100% May 19, 2014 May 22, 2014 G 1.3 Weekly status report covering week 2 80% May 26, 2014 May 29, 2014 G 1.4 Weekly status report covering week 3 0% June 2, 2014 June 5, 2014 N 1.5 Weekly status report covering week 4 0% June 9, 2014 June 12, 2014 N 1.6 Weekly status report covering week 5 0% June 16, 2014 June 19,2014 N 1.7 Final status report covering weeks 1-6 0% June 20, 2014 June 25, 2014 N In Progress June 20, 2014 June 25, 2014 G Workstream #2: Transition QHP to FFM 2.1 QHP to FFM Roadmap Workstream #3: Support MAGI Medicaid 3.1 Web Presence Strategy In Progress June 18, 2014 June 23, 2014 G 3.2 Security Strategy In Progress June 18, 2014 June 23, 2014 G 3.3 Organization Change Mgmt (OCM) Strategy Started June 18, 2014 June 23, 2014 G 3.4 Requirements Catalog In Progress June 18, 2014 June 23, 2014 G 3.5 MAGI Medicaid Roadmap In Progress June 20, 2014 June 25, 2014 Y % Complete Legend Status Legend N 0% - Not Started 50% - Half-way Complete 90% - Submitted for Approval 10% - Started 70% - Well Underway 100% - Complete / Approved 20% - In Progress 80% - Submitted for Review Not Started G On Track Status Report for week ending May 23, 2014 Y Needs attention 2 R At risk of meeting timelines Copyright © 2014 Deloitte Development LLC. All rights reserved. Cover Oregon – Status Report Dashboard # Week ending May 23, 2014 Key Activities % Complete Status 100% G Workstream #1: Project Management 1 Definition of Project methodology, Project management approach, and anticipated staffing for activities within this SOW 2 Planning, coordination, and weekly status reporting of activities within this SOW On-going G 3 Daily oral briefings with Cover Oregon’s Contract Administrator On-going G 20% G Workstream #2: Transition QHP to FFM 1 Development of a strategy roadmap for transitioning individual enrollment for Qualified Health Plans to Federally Facilitated Marketplace Workstream #3: Support MAGI Medicaid 1 Scoping and recommendation of a strategy for interfaces 20% G 2 Comparison of data models 20% G 3 Requirements clarification and catalog update 20% G 4 Development of a strategy for the web presence for the Medicaid Eligibility System Front End 10% G 5 Hub On-Boarding Work & Bi-Directional Account Transfer Initiation Work 10% G 6 Complete a Security Assessment/Establish Security Strategy 10% G 7 Establish scope for organizational change management and training 0% N 8 Establish scope for all types of testing 10% G 9 Contingency planning for subsequent work 0% N % Complete Legend Status Legend N 0% - Not Started 50% - Half-way Complete 90% - Submitted for Approval 10% - Started 70% - Well Underway 100% - Complete / Approved 20% - In Progress 80% - Submitted for Review Not Started G On Track Status Report for week ending May 23, 2014 Y Needs attention 3 R At risk of meeting timelines Copyright © 2014 Deloitte Development LLC. All rights reserved. Appendix Status by Team Leads: David F./Annamarie B. Status by Team Workstream #1: Project Management Team Accomplishments (prior week) • • • • • Executed daily oral briefings with Cover Oregon’s Contract Administrator Coordinated access to State SharePoint site for all Deloitte resources On-boarded four additional Deloitte resources (per plan) and State team leads Coordinated two weeks of weekly meeting schedules with Deloitte and State team leads Coordinated ‘significant challenges (in transition to FFM by Nov)’ discussion with State leads; updates emailed to the team leads • Submitted Deliverable Expectations Documents for MAGI Medicaid Roadmap, QHP to FFM Roadmap, Requirement Catalog • Prepared Deliverable 2 – Status Report for Week 2 for submission Upcoming Work (current week) • Collaborate with OHA and Cover Oregon to obtain access to OHA and Cover Oregon’s development and test environments • Coordinate consolidation of work plans with the State PMO lead • Execute daily oral briefings with Cover Oregon’s Contract Administrator • Prepare Deliverable 3 – Status Report for Week 3 for submission Issues/Risks • None Status Report for week ending May 23, 2014 5 Copyright © 2014 Deloitte Development LLC. All rights reserved. Leads: [client - TBD]/Kevin K. Status by Team Workstream #2: QHP Transition to FFM Team Accomplishments (prior week) • Plan Management • • • • Completed first instance of Carrier Binder Training Drafted a work plan with inclusion of Centers for Medicare & Medicaid Services (CMS) materials Submitted list of 20 questions to CMS to better understand end-to-end process Developed and submitted QHP to FFM Roadmap Deliverable Expectations Document (DED) • Web based strategy – formulating • Conducted initial brain storming session for web strategy focusing on ‘significant challenges (in transition to FFM by Nov)’ for security (how public is public) and the baseline needs for a web portal • Participated in ‘significant challenges (in transition to FFM by Nov)’ meeting and identified base data collection requirements for Modified Adjusted Gross Income Medicaid (MAGI Medicaid) application • Began assessment of the Cover Oregon site to identify content needed to support the transition to Federally Facilitated Marketplace (FFM) • Started reviewing other FFM state sites to identify the ideas for Oregon’s home page • Developed DED and deliverable outline for web strategy deliverable Upcoming Work (current week) • Plan Management • Review answers to questions submitted to CMS to help us understand end-to-end process and begin defining gaps (TBD) • Review and update draft work plan to define activities required between current date and November 2014 • Discuss communication tools/process with the carriers • Web based strategy – formulating • Begin defining the user work flows for the Cover Oregon information pages, MAGI (Modified Adjusted Gross Income) Medicaid, and the FFM links • Continue reviewing other FFM state sites to identify the ideas for Oregon’s home page and other capabilities (i.e. pre-screen) • Continue assessment of the Cover Oregon site to identify content needed to support the transition to FFM • Begin reviewing available Portal solutions to support the MAGI Medicaid applications (Cover Oregon, Oregon Benefits Online, paper application..) Issues/Risks • Need state contact for Broker/Agent/Navigator track Status Report for week ending May 23, 2014 6 Copyright © 2014 Deloitte Development LLC. All rights reserved. Leads: Carol B./Yer V./Stephanie R. Status by Team Workstream #3: Application Intake & Case Management Team Accomplishments (prior week) • Initiated data crosswalk validations consisting of multiple system data fields and their respective alignments to understand flow and consistency of data across Cover Oregon (PDF application), CMS Account Transfer Interface and OHA application • Conducted requirements validation sessions to initiate requirements catalog and fit gap assessment for Application Intake & Case Management process areas, based on Cover Oregon and Oregon Health Authority (OHA) requirements documents • Conducted follow up reviews of the Cover Oregon web portal Upcoming Work (current week) • • • • • Continue review of Cover Oregon and OHA Siebel application and available documentation Review existing OHA application functionality by walking through selected end-to-end use cases Continue validation of Requirements Catalog for Application Intake and Case Management Continue fit gap assessment of initial requirements Review use cases, process flows and requirements with Modified Gross Adjusted Income (MAGI) Medicaid project stakeholders Issues/Risks • Lack of direct access to OHA development/test environments through the end of Week 2 of the assessment, is negatively impacting available time for Deloitte to make feasible assessment of OHA system current state. Status Report for week ending May 23, 2014 7 Copyright © 2014 Deloitte Development LLC. All rights reserved. Leads: Joyce C./Vivian L./Praneet R. Status by Team Workstream #3: Eligibility & Enrollment Team Accomplishments (prior week) • Validated programs and benefit hierarchies for MAGI Medicaid Children’s Health Insurance Program (MAGI Medicaid/CHIP) eligibility • Reviewed non-financial rules for MAGI Medicaid/CHIP programs and identified gaps in the current Cover Oregon rule set • Reviewed key household composition rules for MAGI cases • Discussed and documented existing enrollment process flow and existing notice generation process flow • Continuing to conduct gap analysis to determine gaps in Oracle Policy Automation (OPA) rules vs. MAGI Medicaid/CHIP eligibility required rules • Continuing to identify gaps in OHA data model vs. required data elements for eligibility determination Upcoming Work (current week) • Review key financial rules for MAGI Medicaid/CHIP programs and document gaps in the current Cover Oregon rule set • Identify gaps in Oregon Health Authority (OHA) data model vs. required data elements for eligibility determination • Identify gaps in OHA data model vs. required data elements for storing eligibility determination results • Conduct gap analysis to determine gaps in Cover Oregon Notices requirements to support minimum Affordability Care Act (ACA) compliance Issues/Risks • None Status Report for week ending May 23, 2014 8 Copyright © 2014 Deloitte Development LLC. All rights reserved. Leads: Britt S./Sandeep C. Status by Team Workstream #3: Interfaces Team Accomplishments (prior week) • Conducted four validation meetings with Oregon Health Authority (OHA) & Oracle team members to discuss Verification Interfaces, Account Transfer and Medicaid file transfer process from Cover Oregon to OHA Medicaid Application • Updated services mapping matrix which compares State Modified Adjusted Gross Income (MAGI) validation plan to Federally Facilitated Marketplace (FFM) services • Continued progress on updating data crosswalk document which maps data elements across Account Transfer payload, Cover Oregon and OHA Siebel applications • Created process flows / use cases for FFM to State & State to FFM account transfer functionality • Performed analysis of OHA Siebel repository to document the amount of customization, complexity and usage of best practices Upcoming Work (current week) • • • • • • • • Conduct follow up meeting with OHA, Cover Oregon & Oracle to address open questions and action items Complete services mapping matrix which compares State MAGI validation plan to FFM services Explore leveraging requirement matrix from other states that have built the FFM interfaces Continue validating the Requirement Catalog for interfaces Refine process flows / use cases for FFM to State & State to FFM account transfer functionality Create Interface Architecture diagram to show interactions between OHA applications Continue security review meeting with OHA Oracle, Identity Management (IDM) resource Submit paper work on the dual hub connection Issues/Risks • Lack of direct access to OHA development/test environments through the end of Week 2 of the assessment, is negatively impacting available time for Deloitte to make feasible assessment of OHA system current state. Status Report for week ending May 23, 2014 9 Copyright © 2014 Deloitte Development LLC. All rights reserved. Leads: Stefan R./Debi M. Status by Team Workstream #3: Security Team Accomplishments (prior week) • Initiated the review of available Oregon Health Authority (OHA) security policies, procedures, security design, security system plan and other security related artifacts • Coordinated with the application teams to define the security boundary for the solution and created the draft architectural diagram for further discussions • Identified the key security deliverables and tentative completion timeline for connecting with federal hub • Participated in the discussions to identify key security items (i.e. security tools requirements, user identity management and disaster recovery) and the approach for Nov-2014 deployment timeline • Initiated discussion to identify the scope for user registration for Nov-2014 and the strategy to achieve a fully functional user portal for registration and self-service activities Upcoming Work (current week) • Continue to work with the Chief Information Security Officer (CISO) office and security team to identify the gaps as per Center for Medicare and Medicaid Services (CMS) security requirements and define a roadmap to achieve the compliance • Review the detail OHA security infrastructure including IAM infrastructure and associated configurations, data base encryptions and web service security • Validate the draft security requirements and the prioritization for Nov-2014 • Begin defining the security strategy for Nov-2014 and beyond to meet CMS security requirements • Meet with CMS to review FFM security process and requirements Issues/Risks • Lack of direct access to OHA development/test environments through the end of Week 2 of the assessment, is negatively impacting available time for Deloitte to make feasible assessment of OHA system current state. Status Report for week ending May 23, 2014 10 Copyright © 2014 Deloitte Development LLC. All rights reserved. Leads: Rob T./Jeremy B. Status by Team Workstream #3: Solution Architecture & Infrastructure Team Accomplishments (prior week) • Review Oregon Health Authority (OHA) Environment Strategy to understand mapping of testing activity (Unit, System/Integration, User Acceptance, Performance) to environments • Development of to-be High Level Solution Architecture draft is in-progress • Began developing Integration Security Strategy draft in conjunction with Security team • Reviewed OHA Production Infrastructure to understand current physical architecture, scalability, and High Availability/Disaster Recovery capability • Participated in Web presence strategy session to align across multiple teams • Participated in Data Conversion sessions to develop initial strategy options Upcoming Work (current week) • Validate to-be High Level Solution Architecture draft with State Architect • Validate to-be Integration Security Strategy draft with Security Team and State Security Architects • Provide recommendation on leveraging Cover Oregon Fed Integrations for reuse in OHA in conjunction with Security and Integration teams • Develop refined Application Intake options in conjunction with Security, Application Intake, and Eligibility teams • Review and publish OHA Siebel repository analysis report on customization and best practices • Develop refined Data Conversion strategy options Issues/Risks • Need access to Household Grouping design from OHA team to validate implications on assessment and inform the MAGI Medicaid Roadmap deliverable • Oracle Web Services Manager (OWSM) not currently in a de-militarized zone which exposes the web services to external threats Status Report for week ending May 23, 2014 11 Copyright © 2014 Deloitte Development LLC. All rights reserved. Leads: David V./Dmitry K. Status by Team Workstream #3: Testing Team Accomplishments (prior week) • Facilitated planning sessions to define scope for all relevant types of testing to be performed • Discussed Testing Strategy Overview with the Modified Adjusted Gross Income (MAGI) Medicaid project teams • Participated in the Eligibility and Enrollment meetings to clarify scope of testing for future MAGI implementation phases • Initiated development of an approach for Testing Strategy to be used in the future roadmap Upcoming Work (current week) • Facilitate planning sessions to clarify roles and responsibilities across the project testing team • Facilitate discussion to define requirements for testing environments and for creating test data • Schedule meeting with Track leads to estimate the number and type of test scenarios needed Issues/Risks • None Status Report for week ending May 23, 2014 12 Copyright © 2014 Deloitte Development LLC. All rights reserved. Leads: Chris B./Nancy R./Lali C. Status by Team Workstream #9: Reporting Team Accomplishments (prior week) • Decision: OHA database will be the only source for Reporting • Identified some of the suggested Modified Gross Adjusted Income (MAGI) Medicaid Affordable Care Act (ACA) compliant reports • Identified some of the suggested Consumer Information and Insurance Oversight (CCIIO) reports Upcoming Work (current week) • Review current OHA and Cover Oregon reports and conduct deep dive analysis for Reporting scope for minimum ACA compliance for Nov 2014 • Obtain and analyze Centers for Medicare & Medicaid Services (CMS)/CCIIO minimum reporting needs • Review MAGI Medicaid reporting requirements from a sample Determination state Issues/Risks • None Status Report for week ending May 23, 2014 13 Copyright © 2014 Deloitte Development LLC. All rights reserved. Leads: Chris B./Nancy R./Lali C. Status by Team Workstream #5: Data Conversion Team Accomplishments (prior week) • Initiated discussion on Data Conversion needs for Nov 2014 • Participated in the data cross walk approach discussions Upcoming Work (current week) • Conduct a deep-dive Analysis for data mapping between Cover Oregon and Oregon Health Authority (OHA) systems to examine the following: • Understand the current OHA Process Flow • Discuss data issues like duplicate client data and its implications on Data Conversion • Semantic differences in data definition of fields between Cover Oregon and OHA • Policy and Process implications due to this conversion Issues/Risks • Data model / Data Dictionary for Cover Oregon and OHA needs to be updated leaves a significant body of work to be completed for the assessment • Need access to Household Grouping design from OHA team to validate implications on assessment and inform the MAGI Medicaid Roadmap deliverable Status Report for week ending May 23, 2014 14 Copyright © 2014 Deloitte Development LLC. All rights reserved. Leads: [client - TBD]/Jennifer M. Status by Team Workstream #3: Org Change Management Team Accomplishments (prior week) • Drafted the Deliverable Expectations Document for Organization Change Management (OCM) Strategy • Prepared for Cover Oregon and Oregon Health Authority (OHA) staff interviews • Reviewed Cover Oregon OCM documentation Upcoming Work (current week) • Identify Modified Gross Adjusted Income (MAGI) Medicaid project staff to interview, schedule meetings, and conduct interviews • Conduct Cover Oregon and OHA staff interviews • Consolidate notes from interviews • Conduct follow-up conversations as needed Issues/Risks • None Status Report for week ending May 23, 2014 15 Copyright © 2014 Deloitte Development LLC. All rights reserved. About Deloitte Deloitte refers to one or more of Deloitte Touche Tohmatsu, a Swiss Verein, and its network of member firms, each of which is a legally separate and independent entity. Please see www.deloitte.com/about for a detailed description of the legal structure of Deloitte Touche Tohmatsu and its member firms. Please see www.deloitte.com/us/about for a detailed description of the legal structure of Deloitte LLP and its subsidiaries. Copyright © 2014 Deloitte Development LLC. All rights reserved. Member of Deloitte Touche Tohmatsu