The MYRRHA Project Lucia Popescu SCK•CEN lpopescu@sckcen.be Copyright © 2012 SCK•CEN Outlook MYRRHA Motivation Applications catalogue Technical design Project details GUINEVERE (FREYA) ISOL@MYRRHA Copyright © 2012 SCK•CEN MYRRHA - Accelerator Driven System • ADS experimental demonstrator scalable to an industrial demonstrator • corner stone of the ERAER • European Technology Pilot Plant for LFR technology Reactor Accelerator • Subcritical or Critical modes • 65 to 100 MWth (600 MeV - 4 mA proton) Spallation Source Multipurpose Flexible Irradiation Facility Fast Neutron Source Lead-Bismuth coolant Copyright © 2012 SCK•CEN Applications Catalogue Fuel research Φtot = 0.5 to 1.1015 n/cm².s F = 1 to 5.1014 n/cm².s (ppm He/dpa ~ 10) in medium-large volumes Material research FFast = 1 to 5.1014 n/cm².s (En>1 MeV) in large volumes Fission GEN IV 50 to 100 MWth FFast = ~1015 n/cm².s (En>0.75 MeV) (transmutation) Waste Fth = 0.5 to 2.1015 n/cm².s (En<0.4 eV) Multipurpose hYbrid Research Reactor for High-tech Applications Radioisotopes Fusion High-power LINAC 600 MeV – 1 GeV Long irradiation time Fundamental research Silicon doping (ISOL@MYRRHA) Fth = 0.1 to 1.1014 n/cm².s (En<0.4 eV) Copyright © 2012 SCK•CEN Relative radiotoxicity Motivation for Transmutation transmutation of spent fuel spent fuel reprocessing no reprocessing Uranium naturel Time (years) Duration Reduction 1.000x Volume Reduction 100x Copyright © 2012 SCK•CEN MYRRHA – Conceptual Design Reactor Accelerator • Subcritical or Critical modes • 65 to 100 MWth (600 MeV - 4 mA proton) Spallation Source Multipurpose Flexible Irradiation Facility Fast Neutron Source Lead-Bismuth coolant Copyright © 2012 SCK•CEN (1) MYRRHA - Reactor Reactor Vessel Reactor Cover Core Support Structure Core Barrel Core Support Plate Jacket Core Plug Multifunctional Channels Core Restraint System IVFS IVFHM Core Reflector Assemblies Dummy Assemblies Fuel Assemblies Spallation Target Assembly and Beam Line Above Core Structure Control Rods, Safety Rods, Mo-99 production units Primary Heat Exchangers Primary Pumps Si-doping Facility Diaphragm IVFHS Copyright © 2012 SCK•CEN (1) Reactor Layout - Core • 151 positions • Diameter: 1450 mm • keff≈0.95 (ADS mode) • 30-35 % MOX fuel • 37 multifunctional plugs Total flux (hottest pin) 4.7E+15 n/cm2/s Inlet temperature 270 °C Fast flux above 0.75 MeV (hottest pin) 1.01E+15 n/cm2/s Coolant delta T 130 °C Dpa(/350 EFPD's) (hottest pin) 45 Velocity (fuel rod) 1.9 m/sec Ppm He/dpa (hottest pin/target zone) 3.8/6.4 Temperature at cladding surface 500 °C Irradiation volume (8 In-Pile Sections) 3700*8 Maximum linear power 370 W/cm cm3 Spallation target IPS Fuel Assemblies 8 Copyright © 2012 SCK•CEN (2) MYRRHA - Spallation Target Design requirements enough neutrons to feed the sub-critical core at keff ≈ 0.95 heat evacuation (~ 65 % of the beam power, i.e. ≈ 2.1 MW) spatial constrains must reach an appropriate lifetime LBE Window-target design => high neutron gain and =>forced convective heat removal Windowless-target design Copyright © 2012 SCK•CEN (3) MYRRHA - Proton Driver Accelerator characteristics: Fundamental parameters (ADS) Particle p Beam energy 600 MeV Beam current 4 mA Mode CW MTBF > 250 h implementation Superconducting linac 10 frequency 176/352/704 MHz Reliability = redundancy Double injector “fault tolerant” scheme Copyright © 2012 SCK•CEN (3) MYRRHA - Proton Driver • implementation of reliability : 3 principles • 1. overrating 2. reliability (availability) 3. repairability redundancy parallel scheme (double-injector) serial scheme (modular high en. sections) principles to be applied to the basic linac layout, but also to much of the ancillary equipment Copyright © 2012 SCK•CEN (3) MYRRHA - Proton Driver • implementation of reliability : 3 principles • 1. overrating 2. reliability (availability) 3. reparability redundancy parallel scheme (double-injector) serial scheme (modular high en. sections) principles to be applied to the linac layout, but alsolinac to much of Principle of fault tolerance in basic the superconducting spoke the ancillary equipment within < 3 sec • Detection of an RF fault • Change RF phase in neighboring cavities • Increase RF field in neighboring cavities Increase of 25% field level -> 50% power margin required Copyright © 2012 SCK•CEN (3) MYRRHA - Proton Driver PA within MAX (FP7): Frankfurt University IPN Orsay INFN Milano Copyright © 2012 SCK•CEN MYRRHA on the European Context ESFRI European Strategic Forum for Research Infrastructure Knowledge Economy Energy Independence SET Plan European Strategic Energy Plan 27.11.2010 15.11.2010 Confirmed on ESFRI priority list projects in ESNII (SNETP goals) December 2010 on NuPECC lrp Copyright © 2012 SCK•CEN Belgian Commitment: Secured International Consortium: under Construction 2nd phase (11 y) others 576 M€ Consortium Belgium 60 M€ (12 M€/y x 5 y) Belgium 324 M€ (36 M€/y x 9 y) Copyright © 2012 SCK•CEN The Project Schedule 2010-2014 2015 Front End Tendering & Engineering Procurement Design 2016-2018 Construction of components & civil engineering 2019 On site assembly 2020-2022 2023 2024Commissioning Progressive Full start-up exploitation Minimise technological risks PDP Secure the licensing Secure a sound management and investment structure preliminary dismantling plan Central Project Team PSAR preliminary safety assesment Owner Consortium Group EIAR environmental impact assesment Owner Engineering Team FEED (Front End Engineering Design) 2010-2014 Copyright © 2012 SCK•CEN MYRRHA: an International Project Copyright © 2012 SCK•CEN INVESTMENT PHASE International Members Consortium – Phase 1 As of early 2012 Primary «investors» Belgian Federal Ministry of Energy (50%) Belgian Federal Ministry of Science Policy (50%) Participation vehicle (Consortium members) Contribution to investment capital (960 M€’09) «ERIC» (*) IPR management rules tbd SCK•CEN (on behalf of Belgian Federal Government) 40 % BE Major European partners EU country Public foundation 25-30 % EU countries A major Asian partner Asian country 15 ~ 20% Asian country EU FP7 (RTD) / SET-Plan (Energy) EU participation 2 -10 % EU ROW participation 0 -10 % ROW ROW (*) European Research Infrastructure Consortium Copyright © 2012 SCK•CEN OPERATION PHASE International Members Consortium - Phase 2 «ERIC» (*) CLOSED/ SHARED INFORMATION for MoC OPEN INFORMATION SHARED INFORMATION for participants CLOSED INFORMATION for participants Members of Consortium ~25% - Individual research of a member of Consortium - Collaborative research amongst members of Consortium - 3 years program commitment Open User Facility BENEFITS for Members of Consortium • Board position to control overal operation • Priority of access • Potential benefit of low price (compensation profit from commercial revenues) • Capacity transfer flexibility (rules tbd) ~25% - Governments funding - Criteria of research excellence - Independant program access committee (PAC) ~25% Collaborative research - Distribution of information to participants Contract research….. Commercial services - RI - NTD Silicon ~25% SCK•CEN as qualified and licenced operator of the MYRRHA infrastructure under contractual arrangement with ERIC (*) European Research Infrastructure Consortium Copyright © 2012 SCK•CEN Joining the MYRRHA Project Belgium is welcoming international participation in the MYRRHA consortium Membership eligibility for the international MYRRHA consortium is based on a balanced in-cash/in-kind contribution Until end 2014: Partners are invited to express their interest in a participation in the MYRRHA programme by sending an Expression of Interest to SCK•CEN by end of August 2012. After having received this Expression of Interest, the candidate Partner will confirm the contribution level of its commitment by sending a Commitment Letter by end of December 2012. After having received the Commitment Letter, the candidate Partner and SCK•CEN will enter immediately into negotiation on their co-operation aiming at the signature of a Bilateral Agreement covering the Investment Phase and/or the Operation Phase. This Bilateral Agreement should be signed and enter into force before the mid 2013. Copyright © 2012 SCK•CEN Outlook MYRRHA Motivation Applications catalogue Technical design Project details GUINEVERE (FREYA) ISOL@MYRRHA Copyright © 2012 SCK•CEN GUINEVERE – a Step Towards MYRRHA (Generator of UnInterrupted NEutrons at the VEnus REactor) Zero-power fast-n-spectrum facility @ SCK•CEN (sub-critical & critical mode) Collaborative work within EUROTRANS 90° bending magnet D+ source 250 keV acc. D+, D2+, D3+ D+ Ti-T target GENEPI-3C • • • pulsed continuous continuous with beam interruptions VENUS-F fast subcritical reactor with solid Pb coolant simulation Copyright © 2012 SCK•CEN GUINEVERE: A Modular Fuel Element Design 8 cm Top lead reflector (40 cm) fuel (60 cm active height) • rodlets: d = 1.27 cm, h = 20.32 cm • metallic uranium (30 w% U-235) Copyright © 2012 SCK•CEN GUINEVERE - Objectives of an ADS zero-power experiment Perform qualification of sub-criticality monitoring Validate the core power - beam current relationship • For different subcriticality levels • For different types of cores provide input for MYRRHA Investigate start-up and shut-down procedures Validate instrumentation and perform dedicated experiments Interpret and validate experimental data Perform code validation activities and benchmarks Study safety and licensing issues of different component parts as well as that of the integrated system as a whole Identify licensing aspects for a full-scale ADS Copyright © 2012 SCK•CEN Outlook MYRRHA Motivation Applications catalogue Technical design Project details GUINEVERE (FREYA) ISOL@MYRRHA Copyright © 2012 SCK•CEN ISOL@MYRRHA Conceptual Design Copyright © 2012 SCK•CEN Beam-Splitting System (Concept) ISOL target station 600 MeV ~ 100 - 200 mA pulsed beam (up to 250 Hz) ~ 60 m long 600 - (later 800 MeV upgrade to 1 GeV p) 2 - 4 mA CW Copyright © 2012 SCK•CEN ISOL@MYRRHA Facility Characteristics based on proven technology (largely based on experience at ISOLDE and TRIUMF) keep open the possibilities for higher intensity beams can deliver: pure RIB: selective ionization, chemistry, M/DM > 10.000 intense RIB (x100 compared to the present ISOLDE ‘standard’ RIB) RIB of good ion optical quality optimal experimental conditions/lay-out/support (green-field facility!) extended beam times with stable operation experiments need very high statistics; need many time-consuming systematic measurements; hunt for very rare events; have an inherent limited detection efficiency. complementary to ISOL and In-Flight facilities Copyright © 2012 SCK•CEN Applications (ISOL@MYRRHA Applications) Masses Nuclear Physics Condensed Matter Bohr-Weisskopf: A- and g-factors Decay (log ft, Pxn/yp) Ultra-high selectivity: LIST configuration Rare decays: GTGR, b xn/yp, cluster decay, SHE Extreme precision: e.g., crystal spectrometry Reactions (s, B(E2), C2S) Astrophysics Fundamental Interactions QED tests in HCI d<r2>, m, Q Atomic Physics Prototyping Ft values, Correlations (b-n,…), EDM Mössbauer, b-NMR, PAC, EC-SLI Correlations (b -n, ...), EDM: Statistics + control systematic effects of setup Systematic sample measurements Chemistry Biology Medical Applications Typical Beam Time/Experiment SHE chemistry Mn, Fe, Ni, Cu, Zn b-NMR in proteins Systematic sample measurements Radiopharmacy Systematic production of Radiopharmaceuticals (prototyping) Radiotherapy (prototyping) Dedicated radiotherapy center Day Week Month Year Copyright © 2012 SCK•CEN ISOL@MYRRHA Project at SCK•CEN ISOL@MYRRHA - an integral part of the MYRRHA project Delivery of the proton beam by MYRRHA but To be developed within a separate consortium Physics experiments (from the focal plane of the separator) To be set up and run by users Support by ISOL@MYRRHA physics group at SCK•CEN Conceptual design phase (2012-2014) followed by a basic design in the FEED-phase (2015-2017) Funded BriX project within IAP programme of BELSPO also during phase 7 (2012-2017) R&D on target-ion-source systems and parallel operation with MYRRHA Copyright © 2012 SCK•CEN ISOL@MYRRHA Project Schedule 2012-2014 Conceptual Design 2015-2017 Front End Engineering Design 2018 Awarding construction contracts 2019-2021 Manufacturing of components & construction 2022 Assembly & Installation 2023-2024 Commissioning 2025 - Exploitation Copyright © 2012 SCK•CEN Outlook MYRRHA Motivation Applications catalogue Technical design Project details GUINEVERE (FREYA) ISOL@MYRRHA Copyright © 2012 SCK•CEN MYRRHA: EXPERIMENTAL ACCELERATOR DRIVEN SYSTEM A pan-European, innovative and unique facility at Mol (BE) Copyright © 2012 SCK•CEN Copyright © 2012 - SCKCEN PLEASE NOTE! This presentation contains data, information and formats for dedicated use ONLY and may not be copied, distributed or cited without the explicit permission of the SCK•CEN. If this has been obtained, please reference it as a “personal communication. By courtesy of SCK•CEN”. SCK•CEN Studiecentrum voor Kernenergie Centre d'Etude de l'Energie Nucléaire Belgian Nuclear Research Centre Stichting van Openbaar Nut Fondation d'Utilité Publique Foundation of Public Utility Registered Office: Avenue Herrmann-Debrouxlaan 40 – BE-1160 BRUSSELS Operational Office: Boeretang 200 – BE-2400 MOL Copyright © 2012 SCK•CEN