lic project selection, design & construction principles

advertisement

LIMPOPO DEPARTMENT OF PUBLIC WORKS

PRESENTATION TO

INFRASTRUCTURE SUMMIT ON:

Labour Intensive Construction (LIC ) principles and Requirement in

Infrastructure Delivery

Peter Mokaba Stadium

5 October 2010

1

Presentation Outline

Background to EPWP

Labour Intensive Construction(LIC) Definition

International Experiences

Areas of LIC Focus in Infrastructure Works

LIC Design Principles

Re-alignment of Tender Documents to

LIC/EPWP requirements

Challenges

Way Forward and Conclusion

2

Background to EPWP

EPWP is a nation-wide programme which will draw significant numbers of the unemployed into productive work, so that workers gain skills while they work, and increase their capacity to earn an income

To utilise public sector budgets to alleviate unemployment

The first phase of the Expanded Public Works Programme achieved its 1 million work opportunities targets a year ahead of schedule

The second phase of the EPWP to scale up further to contribute significantly to halving unemployment by 2014

DPW has set targets for provinces and municipalities and for them to report to DPW

EPWP 2 implementation has been launched Nationally, and

Provincially in April 2009

The Premier has signed a pledge committing the Province to its set target.

3

National Goal of EPWP Phase 2

To create 4.5 million Work Opportunities (WO) in 5 years

[2 million Full Time Equivalent (FTE) work opportunities] for poor and unemployed people in South Africa so as to contribute to halving unemployment by 2014, through the delivery of public and community services.

Employment Targets: 55% Women; 40% Youth, 2%

People with Disability.

• Limpopo’s contribution in 5 years is 441,993 WO or 10% of the national target.

EPWP to enable government to act as an employer of last resort as part of the Anti-Poverty Strategy

EPWP is being implemented in four sectors namely;

Infrastructure, Environmental, Social and Non-state sectors.

4

Labour Intensive Construction (LIC)

The Infrastructure Sector involves the use of

Labour Intensive Construction (LIC) methods to deliver medium to large scale public infrastructural projects. Covers the bulk

(48%) of employment opportunities.

LIC Definition:

The LIC method involves the use of an appropriate mix of labour and machines for infrastructure delivery, with a preference for labour where technically and economically feasible, without compromising the quality of the finished product .

5

International Experiences

China:

Labour-based rural Roads

Programme in China aimed at employment creation and stimulating the local economy

Used cobblestone pavement to provide all weather access to remote rural areas

In Yunnan Province alone over

5,000 km or roads have been paved using this technique

Yuanjiang – Wadie Rural Access Road

International Experiences Cont’d

India:

Rural Road Connectivity Programme:

•The Government of India launched the Programme in Dec.

2000 to improve road connectivity in rural areas with the aim of improving the livelihood of the rural community and jumpstart the local economy.

•The target of Programme is to provide connectivity to every habitation that has population more that 500 persons (250 in hilly and desert area).

•The programme is fully funded by the central government and implemented by the various state Governments using

LIC methods

•Under the programme some 160,000 unconnected settlements will be provided with all weather (black top) roads at an estimated cost of $13 billion.

International Experiences Cont’d

United States of America:

• Current $787 billion Economic Stimulus Package to create most needed employment, and jumpstart the economy which is currently in recession.

$ 250 billion allocated for Fixing the US Infrastructure

"Over the next two years, this plan will save or create

3.5 million jobs. More than 90% of these jobs will be in the private sector – jobs rebuilding our roads and bridges; constructing wind turbines and solar panels; laying broadband and expanding mass transit."

(President Barak Obama – Feb. 24, 2009)

AREAS OF LIC FOCUS IN INFRASTRUCTURE

WORKS

Roads & Storm-water

Water Works

Waste Management

Sewers

Haul of material

Electricity

Building Works

9

LIC PROJECT SELECTION, DESIGN &

CONSTRUCTION PRINCIPLES

In general, projects to be selected, designed and constructed as EPWP/LIC with the aim of maximizing employment creation , should satisfy the following basic principles/criteria:

– Socio-economic Conditions:

Projects should be in areas with high unemployment and poverty levels with low wage rates. LIC is competitive up to a break-even point daily wage rate of about R105.

Note: To prevent unnecessary labour unrest and ensure smooth operation, it is of paramount importance that applicable wage rates are standardized and regulated on all EPWP projects in a province or region.

– Availability of Local Labour in Geographical locality:

The project location should be in close proximity (say within

5km radius) of large settlements where abundant labour supply can be obtained. Absence of abundant labour within the project vicinity can result in increased project costs (e.g. in transportation/accommodation) and administration.

10

LIC PROJECT SELECTION, DESIGN &

CONSTRUCTION PRINCIPLES CONT’D

– Site/terrain Conditions and complexity of project:

The nature and scope of the project should not be too sophisticated and difficult i.e. LIC is not quite conducive for very hard/rocky ground conditions; as well as entailing massive earthworks which may require heavy machines. Care must also be taken in the selection of construction materials to ensure quality and durability of infrastructure works.

– For roadworks, LIC is more appropriate and conducive to low-volume roads – traffic < 250 vehicles per day

11

LIC PROJECT SELECTION, DESIGN &

CONSTRUCTION PRINCIPLES Cont’d

– Availability and use of Local Materials:

The selection of construction materials during design should emphasize more on materials that will maximize employment creation during construction; and the use of locally-available resources. e.g. stone masonry and grouted stone pitching should be included wherever suitable material is available to the exclusion of pre-cast or cast in-situ concrete stormwater structures. Where there is an indication of local skills, e.g. bricklaying, structures should be designed to make use of such skills.

12

Bridge built using labour-intensive methods

Before – Collapsed structure Use of stones for Construction

Completed Structure

13

Drainage Structures built using LIC methods

Ditch Lining Construction using Stone Masonry

Culvert Headwall constructed using Stone

Masonry

14

LIC PROJECT SELECTION, DESIGN &

CONSTRUCTION PRINCIPLES Cont’d

– Prompt Payments:

By Client to Contractor

The Client’s procurement and payment processes must be streamlined to ensure prompt payment to Contractors for certified work done.

Success or failure of any LIC/EPWP project, no matter how well planned and implemented, is dependent on prompt payments. This is because unlike machine-based projects, human beings are the main producing units on LIC projects who need to be paid promptly The absence of prompt payment often leads to frequent strikes/industrial action and social chaos.

15

LIC PROJECT SELECTION, DESIGN &

CONSTRUCTION PRINCIPLES Cont’d

– Prompt Payments:

• By Contractor to Workers

Experience has shown that some contractors on EPWP projects often fail to pay their workers which result in serious social unrest, with workers ultimately demanding payment from

Client Bodies.

The clause below is inserted under the Special Conditions of

Contract:

Contractor’s default in Payment to Labourers and Employees

Any dispute between the Contractor and labourers, regarding delayed payment or default in payment of fair wages, if not resolved immediately may compel the Employer to intervene.

The Employer may, upon the Contractor defaulting payment, pay the moneys due to the workers not honoured in time, out of any moneys due or which may become due to the Contractor under the Contract”.

16

LIC PROJECT SELECTION, DESIGN &

CONSTRUCTION PRINCIPLES Cont’d

– Use of Good Quality Hand tools

The use of good quality hand tools is very crucial if the workers are not to be unduly strained and productivity is to be optimised on and LIC/EPWP project. For tendered projects, the onus is on the Contractor to provide hand tools and it is equally the responsibility of the Client Body to ensure that the Contractor provides his/her Workers with good quality hand tools, since the cost of the tools are included in the project cost and paid for by the Client

Body. To enforce this all-important issue, the following clause is added under the Special Conditions of Contract:

“Provision of Hand tools

The Contractor shall throughout the project duration, provide his labour force with hand tools of adequate quality, sufficient in numbers and make the necessary provisions to maintain the tools in good and safe working conditions”

17

LIC PROJECT SELECTION, DESIGN &

CONSTRUCTION PRINCIPLES Cont’d.

• Earthworks

(i) must be designed taking consideration of the method of construction, namely labour intensive. e.g. in LIC road works, it is more cost-effective to ensure transverse balancing instead of longitudinal balancing of earthworks as in Machine-Base Construction (MBC).

(ii) Vertical and horizontal alignment of the works (roads, trenches, pipelines and stormwater channels) should be such as to optimize cut and fill, minimize deep or hard excavation or areas requiring specialist engineering input for example dewatering or specialist ground stabilization.

18

LIC PROJECT SELECTION, DESIGN &

CONSTRUCTION PRINCIPLES ( cont.… )

Drainage Considerations

• Trapezoidal (open) side drains are more conducive to excavation by hand and hydraulically more efficient than ‘V’ drains, which are more easily excavated by machines

Setting out and Quality control

• Use of simplified tools and equipment for setting out and quality control e.g.

• Ranging rods & profile boards

• Shutters for layer works

• Concrete mixers

• Pedestrian rollers for compaction

• Etc.

19

Earthworks using labour-intensive methods

Trenching

Sloping

20

LIC PRINCIPLES (cont..…)

Use of Steel Shutters for LIC Layer works

21

LIC PROJECT SELECTION, DESIGN &

CONSTRUCTION PRINCIPLES (cont..…)

• Priming by hand Sprayer • Cold Asphalt Sealing by hand

22

LIC PROJECT SELECTION, DESIGN &

CONSTRUCTION PRINCIPLES ( cont..… )

• Chip Spreading on Hot seals

Spreading by Hand

Spreading by “Chippy” Spreader

23

LIC/EPWP Qualification Requirements

Consultant:

– Engineer – NQF Level 7 Qualification

– Consultant’s RE – NQF Level 5

Contractors

– Should have Employees Qualified in Labour

Intensive Construction (NQF Level 4); OR

– Employees are Registered for Training in LIC works.

24

RE-ALIGNMENT OF TENDER DOCUMENTS

TO EPWP REQUIREMENTS

The same conventional Tender documents are used on

EPWP Projects but certain project-specific clauses related to the use of LIC methods, are incorporated into the tender/contract documents under special conditions of contract, specifications, schedule of quantities, and drawings, as outlined in the “ Guidelines for the implementation of

Labour Intensive Infrastructure Projects under the EPWP”

(Second Edition, July 2005).

•These special clauses are meant to contractually bind the Contractor to those project activities to be executed labour-intensively thereby maximizing employment creation.

25

REALIGNED EPWP TENDER DOC. Cont’d

A summary of clauses inserted in the project document are:

• Project Cover Document –

EPWP logo inserted, as a means of branding the project is an EPWP Project.

• Under Instructions to Tenderers – I n the Tender Notice “

Eligibility is restricted to tenderers with CIDB registration in the specified classification and who have staff with the requisite qualifications in LIC” .

Under Special Conditions of contract

– A pplicable labour laws extracted from the Ministerial Determination for Special Public Works

Programmes containing the “Code of Good Practice”

(e.g., demographic consideration, prompt payment, labour standards and safety, task work system, protective clothing, community participation, etc.); observance of human rights, democratic, social and cultural values, gender equality, labour welfare and safety and equal opportunities for disabled; the provision of complaint mechanism for workers’ grievances such as, Community Liaison Officer, community-based Steering Committees, monthly workers welfare assessment forms, etc.

26

REALIGNED EPWP TENDER DOC. Cont’d

• Under Project Specifications –

The Client body would specify in the contract, the applicable daily wage rate for the project. In accordance with the Code of Good Practice for

Employment and Conditions of Work for Special Public Works

Programmes, clause 10.4 requires that the following should be considered when setting rates of pay for workers:

(i) The rate set should take into account wages paid for comparable unskilled work in the local area per sector, if necessary.

(ii) The rate should be an appropriate wage to offer an incentive for work, to reward effort provided and to ensure a reasonable quality of work. It should not be more than the average local rate to ensure people are not recruited away from other employment and jobs with longer-term prospects.

(iii) Men, women, disabled persons and the aged must receive the same pay for work of equal value .

27

REALIGNED EPWP TENDER DOC. Cont’d

• i.

Task (Productivity) Rates

LIC must be based on task rate system ii.

Appropriate task rates must be agreed upon & assigned.

A “task rate” is an approved quantity of work to be assigned to a worker(s) to complete within 5- 6 hours working day, whilst the “wage rate” is the set wage to be paid to a worker who completes an assigned daily task. i.e. task rate relates to assigned daily work whilst wage rate relates to the daily wage earned for completing a daily task.

28

REALIGNED EPWP TENDER DOC. Cont’d

• Hand Excavation Clauses:

The relevant LIC specification clauses pertaining to

Hand Excavation of different types, and consistencies of soil, hand compaction; haulage by wheelbarrows; and pre-cast concrete works, are inserted.

• Under Preamble to the Schedule/Bill of

Quantities:

Clauses are inserted indicating that all works or part thereof on the bill specified to be done labourintensively as “LI” must be constructed by labour intensive methods; and payments for such ‘LI’ designated items will not be made unless they are constructed using labour intensive methods.

29

REALIGNED EPWP TENDER DOC. Cont’d

Under the preliminaries & General Items of the Bill of

Quantities

Training Allowance

– A bill item for cost allowance provision for training of workers on the project is inserted.

• On the Bill of Quantity sheets

– To indicate or mark every bill item specified to be done labourintensively as “ LI ”

• Client bodies would ensure that:

• During implementation of the project, all itemized works to be done labour-intensively, are so carried out by the Contractor.

• Workers’ skills audits and the requisite training are carried out for the workers.

• Contractors’ produce regular monthly reports on employment creation reporting – to tie reporting with payment for works done.

30

Challenges/Risks and Mitigation

Challenges/ Risks

Lack of awareness and understanding of EPWP

Performance below minimum set targets by some implementing bodies,

Administrative bottlenecks of

Government bodies (e.g. unnecessary delays in planning, implementation and procurement, delays in the payment for services delivered, and in payment to workers on

EPWP projects etc.)

Mitigation Measures

- Conduct continued awareness and sensitisation exercises through workshops, seminars, promotional materials

- Targeted short courses for managers of programmes and projects

- Enforcement of legislations and government directives

(National, Provincial, Treasury, lead sector, and

Accounting officers to take necessary action for compliance)

- Conduct continued awareness and sensitisation exercises through workshops, seminars, promotional materials

- Targeted short courses for new managers of programmes and projects

- Streamline management structures and procedures for efficient service delivery

- Provision of adequate staffing

- Continuous training and reorientation of management staff

- Enforcement of procedures

31

Challenges/Risks and Mitigation Cont’d

Challenges/ Risks

High trained staff turnover

Inferior quality in service delivery

Lack of acceptance and under-standing of potential benefits of EPWP/LIC concept (e.g. EPWP is DPW’s programme; and slow, etc.)

Mitigation Measures

- Provide incentives, such as training and Career-pathing, to retain staff

- Harmonization of working conditions

- Training and reorientation of service providers and staff of implementing bodies

- Establish adequate supervision and monitoring systems

- Streamline procurement processes

- Establish quality assurance/control systems

- Apply appropriate penalties for continuous non performance (e.g., black listing) on projects, and noncompliance to EPWP requirements.

- Conduct continued awareness and sensitisation exercises through workshops, seminars, promotional materials

- Targeted short courses for managers of programmes and projects

- Show-case successful projects and good practices

- Proper design of projects

- Review of Supply Chain Management systems in procurement of service providers

- Black-listing of non-compliant Service Providers

32

Challenges/Risks and Mitigation Cont’d

Challenges/ Risks

Inadequate experience in

LIC by management and supervisory staff of both

Government and consulting firms

General lack of reporting by most implementing bodies; and inconsistencies and substandard quality of submitted reports

The Use of two systems for reporting on EPWP

Phase 2 namely, the web-based system, and the Management

Information System (MIS)

Mitigation Measures

- Continuous training and reorientation of management and supervisory staff

- Show-case successful projects and good practices (through workshops, study tours, etc.)

- Use of CIDB requirement of mandatory reporting – to tie reporting with payment for works done

- National DPW to merge the two systems into one

33

Way forward and Conclusion

It is mandatory for all Public Bodies to implement EPWP using LIC methods to increase labour intensity on projects.

Set targets are the barest minimum and all Public Bodies must endeavour to exceed the set targets.

Projects should be deliberately designed to maximize employment

Implementing Bodies whose annual projects and budgets are inadequate to achieve the minimum set targets must either get more projects or increase the labour intensity on their projects

Accounting Officers of Government Bodies to sign an MoU to achieve their set targets

Accurate reporting is essential to capture the employment created.

• Use of CIDB requirement of mandatory reporting – to tie reporting with payment for works done.

The Executive to ensure all institutions to make EPWP a success

34

Thank You

Augustus Asare

ILO Technical Adviser

Limpopo EPWP

Tel: 015 284 7111

Fax: 086 593 1502

Email: asarea@dpw.limpopo.gov.za

35

Download