A National Perspective on Coordination of RBIG and Reticulation in

advertisement
Bulk Water Supply in Limpopo
Integrating Infrastructure Delivery towards 2030
Summit
Peter Mokaba Stadium
5 and 6 October 2010
A.M. Matukane
1
Contents
1. Growth Points
2. Water Resources - Dams, Transfers, Ground
water
3. ORWRDP, MCWAP, GLEWAP, LRGWS
- Description, Purpose, Map, Schedule,
Risks and Mitigation
4. Regional Bulk Infrastructure Grant (RBIG)
5. Funding
6. Challenges
2
Bulk Water Supply in Limpopo
Growth Points
1. Polokwane
2. Elias Motswaledi
3. Makhado
4. Lephalale
5. Greater Tubatse
6. Greater Tzaneen
Growth Points
7. Phalaborwa
8. Thabazimbi
9. Mogalakwena
10. Marble Hall
11. Musina
12. Lepelle Nkumpi
3
Bulk Water Supply in Limpopo
• The growth points in red are, apart from existing
supplies, currently not addressed by either
Implementation Ready Studies (IRS) or by
constructing of a water resource/services
project.
• The other growth points are covered with an IRS
or a phase of a regional bulk water project is
under construction to alleviate the water problem
• The water resources and transfer schemes are
to support the development of the different
growth points in the province.
4
Bulk Water Supply in Limpopo
All Growth Points must have water supply
schemes:
• A water resource – surface and/or groundwater
• A water treatment plant
• Pump stations
• Regional Bulk – from source to and including
bulk reservoir
• Internal Bulk– from bulk reservoir outlet to
reticulation connection
• Reticulation– from internal bulk end to
household meter
5
Bulk Water Supply in Limpopo
DWA has constructed many major dams in
Limpopo in the past which supply water to
people and other users, namely:
• Nzhelele, Vondo, Damani, Lupepe-Nwanedi in
Vhembe
• Middle Letaba, Ebenezer, Tzaneen, Thabina,
Tours, Blydepoort in Mopani
• Mokolo, Doorndraai, Glen Alpine in Waterberg
• Houtrivier, Chuene, Molepo in Capricorn
• Vergelegen, Nkadimeng, Piet Gouws, Flag
Boshielo in Sekhukhune
6
Bulk Water Supply in Limpopo
DWA is developing the major dams in Limpopo:
• Inyaka (now in Mpumalanga)
• Nandoni in Vhembe District
• Flag Boshielo Raising, and
• De Hoop in Sekhukhune District- construction
50% completed
• Nwamitwa in Mopani District in planning
• Possible dam in Olifants river under investigation
7
Bulk Water Supply in Limpopo
DWA is planning and developing major water
transfer schemes in Limpopo from:
• Inyaka (now in Mpumalanga) to Acornhoek
• Nandoni in Vhembe District to Makhado,
Matoks, Giyani, etc
• Flag Boshielo to Pruissen at Mokopane
• De Hoop in Sekhukhune District to Burgersfort,
Tubatse, Lebowakgomo and Polokwane
(ORWRDP)
• Crocodile river to Lephalale (MCWAP)
• Groblersdal to Moutse West
8
Bulk Water Supply in Limpopo
Major Schemes
1. Olifants River Water Resources
Development Project (ORWRDP)
2. Mokolo & Crocodile Water Augmentation
Project (MCWAP)
3. Groot Letaba Water Augmentation Project
(GLeWAP)
4. Luvuvhu River Government Water Scheme
(LRGWS) – Nandoni Distribution Scheme
5. Water Services
9
1. ORWRDP PHASE 2: DESCRIPTION & PURPOSE
•
•
•
•
•
88m high De Hoop Dam (R3 075 million) on
Steelpoort River – Implementation by DWA
Extensive bulk distribution systems (pump
stations, balancing dams and pipelines) from De
Hoop and Flag Boshielo Dams (R12 981 million)
Implementation by TCTA
Primary water supply in Middle Olifants River
catchment area – Regional Bulk and Reticulation
(R6 812 million)
Industrial water for mining on eastern limb of
Bushveld Igneous complex
10
1. ORWRDP (DE HOOP)
REGIONAL BULK AND PRIMARY RETICULATION TO HOUSEHOLD
FEASIBILITY STUDIES
Bulk and
Internal Bulk
(Rand million)
MOOIHOEK TO TUBATSE AND
BURGERSFORT
Reticulation
Total (Rand
(Rand million) million)
590
202
792
DE HOOP TO JANE FURSE
AND NEBO PLATEAU
1110
422
1531
PRUISSEN TO MOKOPANE
AND MOGALAKWENA LM
1141
184
1325
OLIFANTSPOORT TO
CAPRICORN (LEPELLENKUMPI).
393
228
621
OLIFANTSPOORT TO
POLOKWANE (OLIFANTS
SAND)
1380
107
1487
OLIFANTSPOORT SOUTH
(FETAKGOMO).
341
32
373
LEBALELO
552
130
681
5507
1305
6812
TOTAL
11
12
1. ORWRDP PHASE 2: SCHEDULE
(Subject to availability of funding)
•
•
•
•
•
•
•
•
2A: June 2007 – Mar 2013
2B: Jul 2011 – Dec 2013
2C: Jul 2011 – June 2013 (Steel Bridge: July
2012)
2D: Jul 2011 – June 2013
2E: April 2012 – March 2014
2F: April 2012 – March 2014
2G: April 2012 – March 2014
2H: Incorporated by March 2013
13
1. ORWRDP PHASE 2:
PROJECT RISKS & MITIGATION
• Level of commitment by mines
and municipalities due to effects
of ongoing global recession
• High social demands
• Affordability
• High cost of scheme
• Reliance on electricity for
pumping
• Alignment of completion of
water resources & services
infrastructure
• Implement GWW with
government funding
• Implement WC & DM
• Government funding
• Step wise implementation
within funding constraints
• Align with Eskom’s
developments
• Aligned planning and water
supply agreements
14
2. MCWAP: DESCRIPTION & PURPOSE
•
•
•
•
•
•
•
•
Augmented water supply in the Lephalale area to meet the water
requirements of the Medupi Power Station, and the future water
requirements related to the expected growth in the Lephalale
Municipality
Industrial water for possible CTL plant by Sasol
Phase 1 (R2 059 million) includes a new pump station at Mokolo
Dam and pipeline to Medupi and Matimba Power Station, Exxaro
mine and Lephalale town
Sub-phase 2A (R13 455 million): Abstraction works at Vlieëpoort
and BDS to Steenbokpan and Lephalale areas
Sub-phase 2B (R1 590 million): Duplication of BDS
Social/Commercial portion on/off-budget
TCTA implementing agent
Regional Bulk and Reticulation (R 330 million)
15
16
2. MCWAP: SCHEDULE
(Subject to environmental
authorisation and Integrated Resource
Plan (IRP) for electricity)
•
•
•
MCWAP-1: July 2011 – July 2013
MCWAP-2A: Jan 2013 – Dec 2016
MCWAP-2B and further phases: Depends on
IRP and investment decisions by the private
sector and other stakeholders
17
2. MCWAP-1 AND 2A:
PROJECT RISKS & MITIGATION
• Likelihood of appeals against
environmental authorisation
high
• Very tight construction
programme
• Affordability of water by social
users
• Delayed IRP for electricity
• High dependence on single
resource, i.e. Mokolo Dam
• Concerted efforts to deal
swiftly with possible appeals
• Efficient implementation
strategies and contract
management
• Government funding
• Co-operative governance
• Investigate and implement
additional and alternatives
sources
18
3. GLeWAP: DESCRIPTION & PURPOSE
•
•
•
•
•
•
•
36m high Nwamitwa Dam (R1 262 million) on Groot Letaba River
– Implementation by DWA
3m raising of Tzaneen Dam (R84 million)
Regional Bulk Water supply (R410 million)
Provide primary water requirements in Mopani District
To implement the preliminary Reserve in compliance with the
National Water Act
To stabilise the assurance of supply to the existing irrigation
farming
To improve water availability for the establishment of resourcepoor irrigation farmers
19
20
3. GLeWAP: SCHEDULE
(Subject to environmental
authorisation and funding)
•
•
•
Tzaneen Dam Raising: 2013/14
Nwamitwa Dam: 2016/17
Regional Bulk: 2015/2016
21
3. GLeWAP: PROJECT RISKS &
MITIGATION
RISKS
MITIGATION
Likelihood of appeals against
environmental authorisation
Concerted efforts to deal swiftly
with possible appeals
Very tight construction
programme
Efficient implementation
strategies and contract
management
Affordability of water by social
users
Government funding
Funding constraints
Phased implementation &
rescheduling
Skills shortage
Training programmes
22
4. LRGWS – Nandoni Distribution Scheme:
Description & Purpose
• The Nandoni Dam and Distribution scheme forms part of the larger
Luvhuvhu River Government Water Scheme (LGWS) which also
includes the Xikundu scheme
• The project was initiated to provide potable water to the area
between Thohoyandou and Makhado after the completion of the
Nandoni Dam
• The Nandoni Distribution projects were started in 2005 in
conjunction with the Nandoni WTW after completion of the Nandoni
Dam and includes:
– 3 bulk pipelines takes water from Nandoni WTW to various
reservoirs
– NR6 and NN20B pipelines takes water in a northerly direction
– 3 bulk pipelines takes water from Nandoni WTW to various
reservoirs
– NR5 pipeline takes water in a southern and western direction
• Estimated cost for the completion Nandoni Distribution Scheme is
R701 million
23
24
4. LRGWS: SCHEDULE
•
•
•
•
DWA approved the accelerated plan to complete the Nandoni
Distribution Scheme’s bulk water pipelines up to the Valdezia Reservoir
Tender for PSPs to redesign the bulk water pipelines did close
Water delivery dates are as follows:
–
Thohoyandou CBD (via NR6 Reservoir and Rising Main) by October
2011
–
Mavambe to Gumbani and Mudabula (via Mavambe to Gumbani
Rising Main, Gumbani Reservoir and Pump Station). Water was
already being delivered as from 17 June 2010 Greater Vuwani
Area(Vuwani (NR7) Reservoir and Rising Main) by August 2012
–
Valdezia Area (Valdezia Reservoir and Rising Main) by November
2012
–
Mushiri, Mahagala and Lambani (Lambani Gravity Main) by October
2011
–
Peri-urban areas east of Thohoyandou (NN20B Reservoir and Rising
Main) by October 2011
The water from the bulk distribution systems will feed into the existing
local reticulation systems
25
4. LRGWS: PROJECT RISKS & MITIGATION
RISKS
MITIGATION
Quality control of construction
Adequate site supervision
including dedicated Resident
Engineer
Productivity of local labour
Implementing management
controls to increase
productivity
Condition of existing municipal
water infrastructure
Municipal infrastructure
refurbished or replaced by
Municipalities where critical e.g.
control valves at reservoirs
Extended lifespan of bulk water
infrastructure (quality of
materials and installation)
Independent 3rd party
inspectors and warrantees
26
Bulk Water Supply in Limpopo - RBIG
Table 1: List of RBIG projects and funding for 2010/11, 2011/12 and 2012/13
Scheme
District
Municipality
(Water
Services
Authority)
Total Project
Costs
RBIG
Expenditure
to date
(2007/8/9/10)
RBIG Budget
2010/11
RBIG Budget
2011/12
RBIG Budget
2012/13
Olifantspoort WTW
Capricorn
303,527,528
173,000,000
23,000,000
20,000,000
0
Specon BWS
Capricorn
74,316,000
39,500,000
19,000,000
0
0
Mametya Sekororo
Mopani
214,000,000
10,000,000
7,000,000
48,000,000
51,789,000
Giyani BW Supply
Drought Relief
Mopani
252,000,000
0
54,000,000
0
0
Greater
Sekhukhune
36,208,000
30,508,523
0
0
0
Groblersdal Lukau BWS
Nebo BWS
Greater
Sekhukhune
1,379,480,000
53,934,769
28,000,000
60,000,000
77,000,000
Mooihoek/Tubatse BWS
Greater
Sekhukhune
1,000,000,000
50,956,728
13,000,000
48,000,000
70,000,000
454,979,475
34,314,595
16,000,000
51,000,000
44,500,000
1,530,000,000
66,571,832
27,000,000
60,000,000
82,700,000
5,244,511,003
458,786,447
187,000,000
287,000,000
325,989,000
Sinthumule Kutama
BWA
Vhembe
Mogalakwena BWS
Mogalakwena
27
Bulk Water Supply in Limpopo - RBIG
Estimated total
cost of 9 projects
R 5 244 511 003
Minus RBIG
expenditure
2007/8/9/10
R 458 786 447
Minus RBIG
Budget
2010/11/12/13
Shortfall for 9
current projects to
be completed
R 799 989 000
R 1 258 775 447
R 3 985 735 556
28
Bulk Water Supply in Limpopo RBIG
• In addition to the projects being
implemented, Table 2 illustrates projects at
feasibility, or implementation ready study
stage that were funded through the RBIG.
29
Bulk Water Supply in Limpopo - RBIG
Scheme
District
Municipality
(Water
Services
Authority)
Total Project
Costs
RBIG
Expenditure
to date
(2007/8/9/10)
RBIG
Budget
2010/11
RBIG
Budget
2011/12
Ohrigstad
Greater
Sekhukhune
450 000 000
949 554
0
0
Lebalelo Central & North
RWS
Greater
Sekhukhune
600 000 000
2 397 573
0
0
Nwamitwa RWS
Scheme(Great Letaba)
Mopani
644 000 000
3 122 166
0
0
Nzhelele Valley BWS
Vhembe
600 000 000
1 983 685
0
0
Makhado West and
Extension to Nandomi
Dam
Vhembe
400 000 000
4 005 464
0
0
Matoks RWS
Capricorn
1 000 000 000
2 335 362
0
0
Glen Alphine RWS
Capricorn
345 000 000
2 897 726
0
0
Lephalale - Bulk Water
Augmentation(Eskom)
Waterberg
330 000 000
5 049 991
1 000 000
0
Magalies Water to
Waterberg
Waterberg
800 000 000
2 800 986
0
0
5 169 000 000
25 542 507
1 000 000
300
Sub Total
Bulk Water Supply in Limpopo - RBIG
Minus RBIG expenditure
2007/8/9/10
Minus RBIG Budget
2010/11/12/13
R 25 542 507
R 1 000 000
R 26 542 507
Estimated total cost of 9
IRS projects to implement
R 5 169 000 000
Shortfall for 9 current
projects to be completed
R 3 985 735 556
Shortfall for 9 current IRS
projects to be constructed
R 5 169 000 000
Total Shortfall
R 9 154 735 556
31
Bulk Water Supply in Limpopo
FUNDING
• The dams are funded by National Treasury
• Funds not so easily available for RBIG and Reticulation
through MIG
Example:
• De Hoop is funded at R3 billion by National Treasury.
• Bulk Distribution and reticulation to Households require R20
billion.
• R1.2 billion is available from 2007 to 2013 through RBIG and
MIG.
• Shortfall of R18.8 billion is needed to serve 2 million people
and mining.
• Mines and Municipalities not in a position to sign off take
agreements with DWA.
32
Bulk Water Supply in Limpopo
Example:
• RBIG is funding a pipe line from Steelbridge to
Jane Furse – 70% completed
• Sekhukhune DM with MIG is on tender for WTW
at Steelbridge and 10 Megaliter reservoir at
Jane Furse for completion July 2012.
• DWA has to do Phase 2C pipe from De Hoop
Dam to Steelbridge for completion July 2012
depending on funding from National Treasury.
33
Life cycle planning
Cost of the Business
Planning
Design
Procure
Construct
Operate
Maintain
Refurb.
Typical % of Total Cost over the Life of Water Supply Infrastructure
0,2%
2%
17%
44%
37% Financing Cost
Based on actual local government case study (Paul le Roux)
34
Limpopo Picture
Rand (bil)
Identified Projects including:
59.3
•ORWRDP (De Hoop)
•MCWAP (Lephalale)
•GLeWAP (Nwamitwa)
•Waste Water Treatment Works
Capital = 20%
60.0
O&M 20 years = 40%
120.0
Financing 20 years = 40%
120.0
Total
35
300.0
Needs Classification/Definition – Water Services
Management
Regional Bulk
Illegal settlement
36
Needs Classification/Definition - Sanitation
Management
Illegal settlement
37
Backlog on Water: Households
Priority (Infrastructure Status)
Priority
Adequate
No Water Services
Inadequate Infrastructure: Need Extensions
Inadequate Infrastructure: Need Upgrade
Inadequate Resources
Inadequate Management: O & M
Inadequate Management: Refurbishment
Inadequate Housing: Interim
Inadequate Housing: Permanent
0
1
2
3
4
5
6
7
8
38
LIMPOPO WATER
CHALLENGES
EQUITABLE SHARES
• Currently R5 / kiloliter (1000 liters)
• ORWRDP at Nebo estimated R25 / kiloliter
(1000 liters)
• 85% indigents to get 6 kiloliter free
• 200 000 households (4 people / hh) x 6kl x
12months x R20 = R288 mil per year
39
STRATEGIC TARGETS / BACKLOG
ERADICATION PROGRESS AND
CHALLENGES
• Total Water Business – Industry, Agriculture, Tourism and
People
• Single Purpose Dams
• Water Services Provider – Cross Border Issues
• WSDP requirements – Water Resource Planning & Internal
Strategic Perspective
• Priorities of backlogs
• Eradicate per priority
• Water Resource shortfall (De Hoop)
• Funding shortfall – RBIG, MIG, ACIP
• Water Services Reference Framework - MIG Projects
outstanding
• Redesign EQUITTABLE SHARE formula
40
STRATEGIC TARGETS / BACKLOG
ERADICATION PROGRESS AND
CHALLENGES Cont…..
•
•
•
•
•
Materials availability
Manpower
Inexperienced PSPs and Contractors
Supply Chain
Not enough resources to support Population
Growth
• Population development require higher water
needs
41
THANK YOU
•
•
•
•
•