Michel Claessens Head of Communication ITER Organization Where is the energetic future of Central and Eastern Europe? 16-17 December 2011, Hotel Tartuf, Beladice, Slovakia 1 Energy: the next challenge 2000-2100: renewable energies x 20 ! 30 Energy consumption (Gtoe) DT > 2°C? Impact of fusion? 20 Decision on DEMO Start of ITER Clean energies? 9 billion humans 10 6 billion humans 0 Time 2 Fusion reactions on Earth E = mc² (Albert Einstein) + 3.5 MeV + 14.1 MeV 3 ITER, the new “way” Fusion powers the Sun and other stars On Earth, fusion could be a very attractive new energy source: • Unlimited scale • Safe, environmentally responsible • Almost limitless fuel (water), widely distributed • No CO2 or other greenhouse gases • No fissile materials such as uranium or plutonium • No long-lasting radioactive waste “Creating a Sun in Cadarache” 4 A plasma in Cadarache Tore Supra (Euratom-CEA): record duration of 6’30” (2003) 5 ITER: a key step towards fusion energy Aim: produce 10 times the energy input DEMO ~ 1000 - 3500 m3 ~ 2000 - 4000 MWth Q ~ 30 80 to 90 % ITER 800 m3 ~ 500 MWth Q ~ 10 70 % JET 80 m3 ~ 16 MWth Q~1 10 % Tore Supra 25 m3 ~0 Q~0 0% ------------------------- Self heating ------------------ 6 ITER – The way to fusion power Aim: produce 10 times the energy input • ITER Programme will – Demonstrate the scientific and technological feasibility of fusion power • Technical – Achieve extended burn of D-T plasmas, with steady state as the ultimate goal – Integrate and test all essential fusion power reactor technologies and components. – Demonstrate safety and environmental acceptability of fusion 7 The ITER History “For the benefit of mankind ” 1985: Secretary Gorbachev and President Reagan proposed an international effort to develop fusion energy… …“as an inexhaustible source of energy for the benefit of mankind”. Then… • 2001: final design report completed • 2005, June 28: Cadarache (France) selected as the ITER site • 2006, November 21: ITER Agreement signed at the Elysée (Paris) • 2007, October 24: ITER Organization established • 2010, August: construction started 8 ITER Tokamak Cryostat Feeders (31) Thermal Shield Toroidal Field Coils (18) Vacuum Vessel Poloidal Field Coils (6) In-vessel Coils Blanket Correction Coils (18) Central Solenoid (6) Divertor 9 ITER site after construction 39 Buildings, 180 hectares 10 years of construction 20 years of operation Coil Winding Building Present HQ Building Power Supply Tokamak Complex Office Buildings To Aix Parkings 10 IO Human Resources • Total of 470 staff members (October 2011): 300 professional and 170 technical support staff • New manpower resourcing policy (November 2010) to achieve the best performance at the lowest cost for the construction phase Professional staff Support staff Total CN 16 4 20 EU 183 125 309 IN 12 16 28 JA 25 7 32 KO 22 5 27 RU 19 3 22 US 24 10 34 Total 302 170 472 Professional staff distribution 11 ITER is addressing the key technical challenges of the tokamak • Tokamak – – – – – Large scale up of many systems High quality high tech components Tight tolerances Manufacturing around the world Highly integrated design • Superconducting magnets – Unprecedented magnet size – High field performance ~12T – Conductor and magnet manufacturing • Vessel Systems – Large size – Safety boundary • Plasma facing components – High heat flux – Plasma-Material Interactions – RH requirements 12 A unique project Each partner builds part of the machine ITER is being built largely through in-kind contribution by the seven Members of the ITER Organization 13 A unique project Each partner builds part of the machine China: magnet conductor, correction coils, feeders and supports, blankets, remote handling transfer casks, gas injection system, electrical switchgear, some diagnostics. India: vessel ferromagnetic inserts, cryostat, cryolines and cryodistribution, heat rejection system, ion cyclotron and startup electron cyclotron heating power supplies, diagnostic neutral beam, some diagnostics. Japan: half the TF coils, most of the TF coil structure, part of the TF and all the CS conductors, part of the first wall, divertor outer target, blanket remote handling equipment, atmosphere detritiation, equatorial electron cyclotron launchers and power supplies, neutral beam components, some diagnostics. Korea: some conductor strand, part of the vessel and vessel ports, blankets, assembly tooling, thermal shield, tritium storage, part of the power supplies, some diagnostics. Russian Federation: PF coils 1 and 6 and some PF and TF coil conductor, some vacuum vessel ports, blankets and connectors, divertor dome and testing, electrical switchgear, some klystron tubes, some plasma diagnostics. USA: wind CS coils, some TF conductor, some blankets, port limiters, part of the cooling system, part of the vacuum pumping and fuelling system, tokamak exhaust processing, part of the steady power supplies, RF transmission lines, some plasma diagnostics. Europe: the remainder, including sharing in most of the above procurements, plus the buildings. 14 Fabrication has begun Hoisting superconducting Correction Coils, Institute of Plasma Physics, Hefei, China. ITER Organization and Domestic Agencies have signed 60 Procurement Arrangements (PAs) over a total of 128. This amounts to € 3.3 billion, or 72% of the total procurement value for the construction of ITER. 15 Cryostat Status Top Lid Upper Cylinder Lower Cylinder • Provides the vacuum insulation for operating the superconducting magnets and thermal shield system • 304L stainless steel 40 – 180 mm thick • Weight ~3500 tonnes Base Section IN-DA signed PA September 2011 16 TF superconducting strand Procurement is largest in History • Over 40% of required 450t of Nb3Sn strand has been produced around the world • Stepping up to 100 tons/year TF Strand Production Summary 17 TF & PF Conductor activity Underway in Hefei, China TF & PF Winding Building Winding & Compaction Machines Jacketing Line 18 Machine Assembly 19 Cost of ITER Most contributions are in kind • Total estimated construction cost of ~ 13 Billion €, if built in Europe • Total estimated value capped at 7.1 Billion euros, including 0.17 Billion euros as additional resources • Any additional resources to be made available by cost savings 20 Project schedule Approved by ITER Council in November 2011 Assembly: First Plasma: DT Operations: 2014-2018 Nov 2020 2027 21 Overview of Schedule for 2020 First Plasma 22 Latest construction progress on ITER Site 23 Latest construction progress on ITER Site Tokamak Complex Construction PF Coil Winding Building 400kV Substation ITER Headquarters Building 24 Latest construction progress on ITER Site Tokamak Complex Construction 25 Latest construction progress on ITER Site Tokamak Complex Construction 26 Excavation support & isolation basemat Support plinths for the antisismic pads (493 units) Lower basemat: 1.5m tick Confinment walls 27 Transports • • • • Biggest components: > 750 tons 104 km from Berre l’Etang to St Paul-lez-Durance (16 communes) 2 test convoys in 2012, first ITER component to arrive early 2013 212 convoys 2013-2018 (= one every 10th day): 32 very slow convoys (5 km/h) = 5 nights; 75 slow convoys (10 km/h) = 2 nights 28 Can anything like the Fukushima Daiichi incident happen in ITER? Fission Reactor Vessel Tons of solid Uranium isotopes Fusion Vacuum Vessel grams of gas hydrogen isotopes 29 How safe is ITER? A Fukushima-type accident is impossible in ITER Fusion reaction intrinsically safe Fuel inventory very small: less than one gram Any disturbance will stop the plasma Runaway and core-meltdown impossible Cooling is not a safety function: if power is lost, heat evacuation happens naturally Important safety margins for external risks (earthquake, flooding…) ITER is safe for workers, people and the environment 30 31 « Enquête Publique » 15 June – 20 July 2011 • • 13 cities Local residents invited to formulate questions and express opinions about the ITER project • Public Inquiry is a crucial step toward the obtention of ITER’s nuclear license 32 ITER in the press 2006-2011 Nr of articles / week quoting ‘ITER’ ITER Agreement New DG EP decision Fukushima Plan EC IO established Average 2006 2007 Source: Meltwater news reports 2008 2009 2010 2011 Summary • ITER project is moving into the real construction phase • Implementation of the approved ITER Baseline • New Management Structure • Improved governance • Cost Containment approach First Plasma in 2020 34 Thank you for your attention 35