PASUKAN PELAKSANAAN PERAKAUNAN AKRUAN STRATEGI DRY RUN 2015 1GFMAS 19 DISEMBER 2014 KSL RESORT, JOHOR BAHRU 1 PASUKAN PELAKSANAAN PERAKAUNAN AKRUAN STRATEGI DAN HALATUJU PELAKSANAAN DRY RUN 1GFMAS Definisi Mini-pelaksanaan dalam persekitaran yang terkawal merangkumi Kump PTJ & PTJ terpilih dalam tempoh masa yang terhad, authorisation terhad dan data/transaksi yang ditentukan. Objektif Execute business process in 1GFMAS as close to Production in sequence and timing Manage risks and prepare for smooth Go Live Prepare contingencies for potential live issues Aktiviti Data migration activities Execute daily activities Execute month end activities Execute closing and reporting activities Execute year end activities Disaster Recovery simulation 2 PASUKAN PELAKSANAAN PERAKAUNAN AKRUAN SKOP Tempoh Pihak terlibat Transaksi (semua business process dalam blueprint 1GFMAS) Dry Run period – Mid June until end October 2015 Accounting year – January to Period 14 Dec 2015 & January 2016 HO (BPOPA), BPAS, BPTM, PPPA, BPOPP, SKP, Treasury 49 Pejabat Perakaunan (24 JANM Negeri & Cawangan, 25 Bahagian Akaun Kementerian) Kementerian • Bahagian Kewangan Kementerian • Bahagian-bahagian di Ibu Pejabat Kementerian • PTJ di negeri dan cawangan (3% dari jumlah PTJ ; 3-4 pengguna setiap PTJ) End User terlibat: Penyedia, Peraku 1, Peraku 2, PTJ Aku Terima, Pelulus dll peranan yang terlibat 11 Agensi Luar Waran am Sub waran Baki awal Tarnsaksi semasa Penutupan bulanan Penutupan akhir tahun sehingga dibawa ke hadapan tahun berikutnya Agensi pukal (MAS) Agensi potongan gaji 3 PASUKAN PELAKSANAAN PERAKAUNAN AKRUAN STRATEGI PELAKSANAAN Jun 2015 Jul 2015 Meet Exit Criteria Dry Run Pre-requisites Go Live Assessment completed Infra readiness User readiness Data readiness Dry Run 1 (Jan 2015) Day 0** (pre activities) Migration activities Day 1* (Black out period) • Upload Budget Book End day activities Day 2 & 3 • Sub allocation of budget End day activities Day 4 - 14 • Daily activities End day activities * Opening balance perlu ada untuk Panjar & Baki Vot S. ** 5 days before day 1 – Migration activities End of Month 1 • Month End Activities • First Month End Closing Aug 2015 Meet Exit Criteria Dry Run 2 (Feb 2015) Day 0** (pre activities) Migration activities • Sign off before upload • Opening balance b/f • Sign off after upload End day activities Day 1 – 5 • Daily activities • Payroll process (regular cycle) • Payroll optimization/Stress Test End day activities End of Month 2 • Month End Activities • 2nd month end closing Sep 2015 Meet Exit Criteria Dry Run 3 (Mar - Dec 2015) Day 1 – 15 • Daily activities • Payroll process • Regular cycle • Separate cycle • Bonus • Daily rated End day activities End of Month 3 - 12 • Month End Activities • 3rd - 12 month end closing Meet Exit Criteria Dry Run 4 (Dec (13) 2015 / Jan 2016) Day 1 – 7 • Opening balance for new year 2 • Period 13 adjustments End day activities Day 8 onwards • Disaster Recovery switch over activities • Daily transaction of year 2. • Period 14 adjustments. End of Year 1 • Year end activities • Year end closing • Carry forward activities 4 PASUKAN PELAKSANAAN PERAKAUNAN AKRUAN SENARAI SEMAK PRE DRY RUN DAN KESEDIAAN PTJ SEBELUM SEMASA PELAKSANAAN AWAL Komputer Perisian Pemasangan perisianperisian SAPGUI, DRIVERS, BROWSER, OS, EPIPLEX di AO Pemilihan PTJ-PTJ untuk dry run Telah ada 1GovNet Bandwidth menepati keperluan minimum 1Mbps Printers Token Authorisation Manual Prosedur Kerja Manual Pengguna Manual Latihan Firewall & DNS Manual Kod Perakaunan Latihan kepada teknikal di SAD dan AO KETERSEDIAAN INFRASTRUKTU R DI PTJ Latihan KETERSEDIAAN RANGKAIAN PTJ KETERSEDIAAN PENGGUNA 5 PASUKAN PELAKSANAAN PERAKAUNAN AKRUAN CRITICAL SUCCESS FACTOR PENGGUNA DATA INFRA AGENSI LUAR PENYELARASAN & PEMANTAUAN Latihan Authorisation Manual Pengguna Manual Kod Perakaunan • • • • • Token • Manual Prosedur Kerja (MPK) • Manual Latihan • Data dari Mock Run 3 • Sign off • • • • Komputer Perisian & Pemasangan Perisian Pencetak Firewall & DNS • • • 4 Bank (CIMB, ALLIANCE, BANK ISLAM, MAYBANK) Agensi Pukal/Potongan /Terimaan ePerolehan • • DAPAT JPN/SSM • Mesyuarat Kumpulan Kerja Kementerian • Floor Manager Dry Run (PPPA & IA) • Team Structure & TOR 6 PASUKAN PELAKSANAAN PERAKAUNAN AKRUAN SESI SOAL JAWAB 7 PASUKAN PELAKSANAAN PERAKAUNAN AKRUAN SEKIAN, TERIMA KASIH 8