Ed Briggs (CenterPoint Energy)

advertisement

IMPACTS OF LARGE

DISTRIBUTED GENERATORS

ON CENTERPOINT ENERGY’S

DISTRIBUTION SYSTEM

Presented by Ed Briggs, P.E.

Manager of Electric Distribution Planning

SWEDE Presentation May 9, 2014

CenterPoint Energy Proprietary and Confidential Information

1

SAFETY MOMENT

PUBLIC AND EMPLOYEE

SAFETY IS THE MOST

IMPORTANT CONSIDERATION

OF DG DESIGN, CONSTRUCTION

AND UTILITY

INTERCONNECTION !

2

WHAT IS DISTRIBUTED

GENERATION (DG) ?

Texas PUC Substantive Rule 25.211

An electric generating facility located at a customer’s point of delivery (point of common couple) of ten megawatts (MW) or less and connected at a voltage less than 60 kilovolts (kV) which may be connected in parallel operation to the utility system.

3

DISTRIBUTED GENERATION

BY FUEL TYPE

4

Total Pending and

Connected DGs

Through 4/16/14

5

Large DG (7500+ KW) Statistics

6

WHATS DRIVING THE LARGE

DISTRIBUTED GENERATION

INTERCONNECTIONS?

• Emergency Response Service (ERS) or

Demand Response

• Close transition-parallel with the utility grid for less than 1 second (closed transition switching)

• Parallel operation with power export option

• Parallel operation with no power export

7

IMPACTS OF LARGE

DISTRIBUTED GENERATION

• LOAD

• VOLTAGE

• POWER FACTOR

• FAULT CURRENT

• CIRCUIT PROTECTION

• LATERAL FUSE COORDINATION

• EFFECTIVE GROUNDING

• RELIABILITY

• SAFETY

8

DG SIZE RATING

A GENERATOR NAME PLATE RATING SHOWS

2500 kVA @ 80% POWER FACTOR

• WHAT IS THE DG kW CAPACITY ?

 2000 kW or 2500 kW ?

SAME QUESTION AS ABOVE EXCEPT THE PRIME

MOVER OF THE GENERATOR IS A DIESEL ENGINE

RATED AT 1800kW

• WHAT IS THE DG kW CAPACITY ?

 1800 kW or 2000 kW or 2500 kW ?

9

12.47 kV DISTRIBUTION

FEEDER DG STUDY

• 7 GENERATORS RATED AT 2500 kW EACH

(7 X 2500 = 17,500 kW)

• PRIME MOVER DIESEL ENGINE RATED AT

1800kW

• ACTIVE GENERATION = 7 X 1800 = 12,600 kW

• 12.47 kV FEEDER RATED AT 12,960 kW

• DG VOLTAGE CONTROL @ 100%PF

10

12.47kV FEEDER PEAK LOAD

10,260 kW 540 kVAR 99.9 PF

SUB

DG

11

DISTRIBUTIVE GENERATION

SETUP (PCC IS POINT OF

COMMON COUPLING)

PCC 2

TO SUBSTATION

PCC 1

12.47 kV BUS

2500 kVA TRANSFORMER

2500 kW GENERATOR

480Y277V

12

DG VOLTAGE TRIP SETTING

DG TRIPS IF:

VOLTAGE = 126V FOR 30 SECONDS

VOLTAGE = 132V FOR 10 CYCLES

CUSTOMER WANTS TO OPERATE DG

AT 100% PF

13

DG ANALYSIS

CNP SUBSTATION VOLTAGE REGULATION IS SET

AT 122V TO 125V

FOUR CIRCUIT MODELING SENARIOS ARE:

 SUMMER PEAK LOADING

• SUB AT 125V

• SUB AT 122V

 OFF-PEAK LOADING

• SUB AT 125V

• SUB AT 122V

14

LOCATION AT PCC WITH SUB AT

125 V WITH SUMMER PEAK LOAD

15

LOCATION AT PCC WITH SUB AT

122 V WITH SUMMER PEAK LOAD

16

LOCATION AT PCC WITH SUB AT

125 V WITH OFF-PEAK LOAD

17

LOCATION AT PCC WITH SUB AT

122 V WITH OFF-PEAK LOAD

18

LOCATION AT PCC WITH SUB AT 125 V

WITH SUMMER PEAK LOAD & EFFECTS

OF CAPACITOR BANKS

19

DG CAN REDUCE THE VOLTAGE AT PCC

BUT RESULTS IN INCREASED kVAR

WHICH RESULTS IN A 394 kVA DEMAND

THUS A $$$$$ MONTHLY BILL

20

DURING OFF PEAK SEASON 4 DGs

BACKFEEDS SUBSTATION

TRANSFORMER WITH 2279 kW

Substation

Transformer

Circuits #1 #2

2279 kW

#3

21

12.47kV FEEDER PEAK LOAD

10,260 kW 540 kVAR 99.9 PF

DG

DG

SUB

DG

22

At PCC with Sub at 125 V with

Summer peak load & DG located near Sub

23

At PCC with Sub at 125 V with

Summer peak load & DG located at end of circuit

24

DG INCREASES CIRCUIT FAULT CURRENT

AND CAUSES 100T FUSE NOT TO COORDINATE

WITH 65T, MUST CHANGE LATERAL TO A

FEEDER AT CUSTOMER EXPENSE

65T fuse

Without DGs, I

LG max =

With 7 DGs, I

LG max =

2578 A

3976 A

100 T fuse

25

DG ELEVATES FAULT CURRENT

ON SUBSTATION BUS AND

ADJACENT CIRCUITS

 A FAULT ON ADJACENT CIRCUIT WILL BE FED BY DG CIRCUIT

AND MAY RESULT IN TWO CIRCUITS OPERATING THUS

IMPACTING RELIABILITY

 LATERAL FUSE COORDINATION WILL NEED TO BE ASSESSED ON

ADJACENT CIRCUITS DUE TO HIGHER FAULT CURRENT

26

Line to Ground Fault Currents

27

EFFECTIVELY GROUNDED SYSTEM PER

IEEE STANDARD 142

28

EFFECTIVELY GROUNDED SYSTEM CHECK ?

CUSTOMER’S HIGHSIDE RESISTIVE

GROUNDING 24 OHM ON 12.47kV SIDE OF THE

TRANSFORMER

29

CNP REQUIRES TRANSFER TRIP FOR DGs

OVER 2000 kW. HOWEVER CIRCUIT

SWITCHING CAN SCUTTLE THIS

N.C.

N.O. (TIE)

Sub 1

Utility crew opens the N.C. switch

N.C.

Lateral

DG

Sub 2

Utility crew closes the tie switch

DG will be transferred from a feeder from sub 1 to another feeder from sub 2

30

SWEDE 2015

NEXT YEAR’S PRESENTATION DG

ACTUAL DATA VERSUS MODELED

THANK YOU !

31

NEXT YEAR

DG ACTUAL VERSUS MODELED

THANK YOU !

Any Questions ?

32

Download