Cleco Transmission Planning Summit 2011 Coughlin Transmission Operations Center April 15, 2011 10:00 – 11:00am Introduction Welcome Terry Whitmore, Mgr- Trans Planning & Operation Support James Simms, Lead Engineer- Transmission Planning Chris Thibodeaux, Sr. Engineer- Transmission Planning Robby Michiels, Sr. Engineer- Transmission Planning Agenda • • • • • • • • • Introduction Economic Planning Studies Acadiana Load Pocket Project Update 2011 Transmission Construction Plan Facility Ratings Changes Model Review Stakeholder Business Final Questions Adjourn Agenda • • • • • • • • • Introduction Economic Planning Studies Acadiana Load Pocket Project Update 2011 Transmission Construction Plan Facility Ratings Changes Model Review Stakeholder Business Final Questions Adjourn Economic Planning Studies None were requested for 2011 Agenda • • • • • • • • • Introduction Economic Planning Studies Acadiana Load Pocket Project Update 2011 Transmission Construction Plan Facility Ratings Changes Model Review Stakeholder Business Final Questions Adjourn Acadiana Load Pocket Project Update Acadiana Load Pocket Acadiana Load Pocket Project Year 2010 Progress Report • Flanders – Hopkins 138KV Transmission line tapped for new Segura substation. • New Segura 230/138KV Cleco substation Phase I completed – 138KV facilities are presently energized – 230KV facility commission is scheduled for the end of second quarter 2011 • New Segura – Moril 138KV Transmission line completed & connected to Segura 138KV bus ALP Project Update – Summer 2010 •Cleco- 230KV Segura Substation •Cleco- Segura to Moril 138KV Trans. Line (0.2 mi) Note: Hopkins – Flanders 138KV line is tapped for new Segura substation. Just 138KV bus is energized at this point. ALP Project Update – Summer 2011 ALP Project Update – Summer 2012 ALP Project Update Questions ? Agenda • • • • • • • • • Introduction Economic Planning Studies Acadiana Load Pocket Project Update 2011 Transmission Construction Plan Facility Ratings Changes Model Review Stakeholder Business Final Questions Adjourn Cleco 2011 Transmission Construction Plan Cleco 2011 Transmission Construction Plan Budgeted Projects • Near term projects deal with Cleco’s obligations to the Acadiana Load Pocket Project and the Reliable operation of the Bulk Electric System. Cleco 2011 Transmission Construction Plan 2011 Budgeted Projects • Construction of a new Rork 230KV Substation adjacent to the one at Richard • Build a new 230KV Transmission line from Rork to the Sellers Road Substation • Construction of a new 230KV Sellers Road Substation • Build a new 230KV Transmission line from Sellers Road to the Segura Substation • Construction of a new Mansfield Compressor 230KV Substation tapping Dolet Hills – Fisher 230KV line • Construction of a new Clarence – Maurice 69KV transmission line • Transmission element replacements on Plaisance – Coughlin 138KV transmission line 2012 • Build a new 230KV Transmission line from Wells to the LUS Labbe Substation • Reconductor existing Segura – Hopkins 138KV transmission line (This will complete Cleco’s participation in the ALP project.) • Second 230/138KV Autotransformer at Cocodrie Substation Cleco 2011 Transmission Construction Plan ALP Project Timeline (All participants) 2011 • Cleco- 230KV Sellers Road Substation • Cleco- 230KV Rork Substation • Cleco- 230KV Rork - Sellers Road Trans. Line (30.1 mi) • Cleco- 230KV Sellers RoadSegura Trans. Line (17 mi) • Entergy- 230KV Sellers Road- Meaux Trans. Line (8.3 mi) 2012 • Cleco- 230KV Wells - Labbe Trans. Line (17 mi) • Entergy- 230KV Sellers Road Labbe Trans. Line (14 mi) • LUS- 230KV Labbe - Bonin Trans. Line (3 mi) • Cleco- Reconductor 138KV Segura- Hopkins Trans. Line (3 mi) [Serves to enhance the ALP project objectives] Cleco 2011 Transmission Construction Plan Long Range Planning- 5 years or greater • System models used in the analysis go out 5 years and beyond •Inputs are extrapolated from short term planning estimates •Accuracy is therefore limited •Results are given leeway in terms of interpretation •Long Term Planning does allow the identification of potential areas of concern •Attention is given to those problems that remain consistent over model runs especially those that get closer to the present •Typically, there is enough time to develop mitigation plans and fund projects •Long Range Planning Analysis has identified some areas of concern •These occur at the end of the planning horizon •At this time, these areas don’t warrant the outlay of capital but will be noted Cleco 2011 Transmission Construction Plan Regions in purple indicate potential planning criteria violations Bus Under Voltage Cleco 2011 Construction Plan 2022 Study Cases Bus under voltage Violations Most limiting Contingency: Coughlin – Pine Prairie 138KV Line Pine Prairie 138KV Bus Voltage 0.8907 P.U. Most limiting Contingency: Coughlin – Plaisance 138KV Line Plaisance 138KV Bus Voltage 0.885 P.U. Oakdale 138KV Bus Voltage 0.8979 P.U. Mitigation: Investigate installation of capacitor banks at Pine Prairie. Mitigation: Investigate installation of capacitor banks at Plaisance. Cleco 2011 Transmission Construction Plan Questions ? Agenda • • • • • • • • • Introduction Economic Planning Studies Acadiana Load Pocket Project Update 2011 Transmission Construction Plan Facility Ratings Changes Model Review Stakeholder Business Final Questions Adjourn • New NERC standards mandated Cleco to re-evaluate all 100KV and above Transmission Line Ratings including the following elements: – – – – – – – – Breakers Switches Conductor Jumpers Bus CT Ratios Wave Traps Relay Setting Limits Results of Analysis • Upgrade of multiple lines whose limiting element created base case overloads • Since 2010 – Changed Normal Rating temperature basis from 85° to 93°C • Increased Normal Ratings – Changed Normal and Emergency Rating procedures for jumpers • Increased Normal and Emergency Ratings • Comparison of 2010 to 2011 SPP series of models: – Cleco Transmission lines 100KV or greater • 51% had their A rating increase – 8% had their A rating decrease • 13% had their B rating increase – 1% had their B rating decease – Cleco Tie Lines • 11% had their A rating increase – 49% had their A rating decrease • 19% had their B rating increase – 28% had their B rating decrease • Refer to the SPP models for specific line ratings Facility Rating Changes Questions ? Agenda • • • • • • • • • Introduction Economic Planning Studies Acadiana Load Pocket Project Update 2011 Transmission Construction Plan Facility Ratings Changes Model Review Stakeholder Business Final Questions Adjourn Model Review • • • New Substations in Regional models New 69KV Transmission Line N-1 ACCC Results Model Review New Transmission Line and Substations in 2011 Regional models Mansfield Compressor Clarence – Maurice 69KV Line Barker’s Corner Youngsville Model Review New Substations in Regional models LAGN : (2011) Barkers Corner 230KV Substation (moving load from other subs) Model Review CLECO : (2011) Mansfield Compressor 230KV Substation (Serving projected area load growth ) New Substations in Regional models Model Review New Substations in Regional models ENTERGY : (2011) Youngsville 138KV Substation (Moves load off of 69KV System) Model Review Cleco : (2011) Clarence – Maurice 69KV Line New 69KV Transmission Line in Regional models SPP 2011 Series Model ACCC Results Unmitigated Thermal Overloads Champagne – Plaisance 138KV: 120% Contingency: Cocodrie – Ville Platte 230KV Models: Summer/Winter 2013, 2017 & 2022 Limiting element resides outside of the Cleco Control Area Will be monitored in subsequent years SPP 2011 Series Model ACCC Results Unmitigated Long Range Low Bus Voltages Oakdale & Pine Prairie 138KV : 0.89PU Contingency: Coughlin – Pine Prairie 138KV Model: Summer 2022 Long Range Mitigation Plan considers adding capacitor banks at Pine Prairie Plaisance 138KV : 0.885PU Contingency: Coughlin – Plaisance 138KV Model: Summer 2022 Will monitor this voltage in future years Model Review Questions ? Agenda • • • • • • • • • Introduction Economic Planning Studies Acadiana Load Pocket Project Update 2011 Transmission Construction Plan Facility Ratings Changes Model Review Stakeholder Business Final Questions Adjourn Stakeholder Business • Chance for Stakeholders to bring issues up for discussion Final Questions?