Strategic placement of compressors for future
mine developments
HG Brand
August 2012
Introduction
Rustenburg Platinum Mine (RPM) consists of eight
shafts supplied with air from six compressor
houses
Mandate of the simulation:
1. Determine the best position of the compressors
replacing the West 10 compressors
2. Reduce the system’s reliance on the VK-125
compressor
3. Determine whether Khusuleka 1 (Townlands) and
Khusuleka 2 (Boschfontein) can be isolated
Surface layout
Simulation 1: Description
Aim: Verify accuracy at high flow rates
The average flow profile for the air network is
determined
The simulation is run to replicate the pressures
at the shafts
These pressures are compared to the actual
pressures at the shafts
Simulation 1: Results
Simulation 2: Description
Aim: To alleviate the system’s reliance on the
VK-125
West 10 compressor house is decommissioned
The high risk pipe section from Siphumelele 3
(Bleskop), via West 10 to Khomanani 1 (Frank
1) is removed
Two BB Sulzer compressors are simulated at
Khomanani 1 (Frank 1)
A GHH compressor is moved from West 10 to
Siphumelele 1 (Turffontein) to replace the
VK-125
Simulation 2: Results
Simulation 2: Summary
Average required flow at Siphumelele 1
(Turffontein) is 107 Х 10³ m³/h
Peak flow can be 30 Х 10³ m³/h above average
profile and the required flow can be as high as
137 Х 10³ m³/h
Available flow from two GHHs is 66 Х 10³ m³/h
The available flow is too low and the VK-125
cannot be stopped
Simulation 3: Description
Both GHHs and the VK-125 are started at
Siphumelele 1 (Turffontein)
Aim: Determine maximum pressure at
Siphumelele 1 (Turffontein)
Simulation 3: Results
Simulation 3: Summary
The pressure at Siphumelele 1 (Turffontein)
increases to 622 kPa at the compressor house
while the pressure at the shaft is 605 kPa
The pressure rating of the pipes are 800 kPa
Simulation 4-6: Description
With the VK-125 running - Determined how
many additional BB Sulzers are required and
where to position them
A BB Sulzer was placed at Thembalani 1
(Paardekraal), Khomanani 1 (Frank 1) and
Khomanani 2 (Frank 2)
One GHH and the VK-125 was running at
Siphumelele 1 (Turffontein)
Simulation 4-6: Results
Simulation 4-6: Summary
Best position to place the BB Sulzer is at
Khomanani 2 (Frank 2), followed by
Khomanani 1 (Frank 1) and then Thembelani 1
(Paardekraal)
Flow spikes occur at Khusuleka 1 (Townlands)
and Khomanani 2 (Frank 2)
To accommodate flow spikes it is suggested
that the second BB Sulzer compressor be
positioned at Khomanani 1 (Frank 1)
Simulation 7-8: Description
Aim - Determine whether to place the two BB
Sulzers in one or two compressor houses
Three simulations are run
In all the simulations one GHH and the VK-125
is running at Siphumelele 1 (Turffontein)
Simulation 7-8: Description
Solution 1 - One compressor is placed at
Khomanani 1 (Frank 1) and one at Khomanani 2
(Frank 2)
Solution 2 - Both compressors are placed at
Khomanani 1 (Frank)
Solution 3 – Both GHH compressors at
Siphumelele are running together with the VK125
Compare to the existing system pressures
Simulation 7-8: Results
Simulation 7-8: Summary
Solution 3 is not viable
Solution 1 offers the best option, followed by
solution 2.
Solution 2 will be the preferred option
In both solution 1 and 2 the flow to Khusuleka 1
(Townlands) is in excess of 10 000 m³/h
This confirms that these shafts cannot be isolated
Conclusion
The simulations indicated that the system
relies too heavily on the VK-125 compressor
The best compressor placement was at
Khomanani 1 (Frank 1)
Khusuleka 1 (Townlands) and Khusuleka 2
(Boschfontein) cannot be isolated from the
rest of the air network.