WORK
SYSTEMS
ANALYSIS
AND
DESİGN
(IE250/1)
PRESENTATION OF CHAPTER 7
PROJECTS AND PROJECT MANAGEMENT
PROJECTS
1.Temporary: Clear start and end
2.Unique: Not repetitive task
3.Requires Resources: Budget, human labor,
equipment
4. Consists of Multiple Tasks: small works
5. Takes Time: Reguires significant amount of
effort,spesific schedule.
HIERARCICAL STRUCTURE OF A PROGRAM
PROJECT LIFECYCLE
PROJECT MANAGEMENT AND TEAMS
Project management is about people. We use
cross-functional teams, which means experts
from different departments work together. A key
concept here is the Matrix Structure. In this
system, team members report to two supervisors:
their department manager and the project
manager. It requires strong coordination, but it is
the best way to manage complex goals within a
limited time.
Matrix Structure: Reporting to both Department
and Projects Managers.
Cross-functional Collaboration: Experts from
different departments work together.
Strong Coordination: Essential for managing
complex goals.
PROJECT PLANNING
Project Planning
Defines objectives, scope, cost, and time
Creates a clear roadmap
Improves communication
Work Breakdown Structure (WBS)
Breaks project into smaller tasks
Improves time and cost estimation
Project Scheduling
Determines task order
Sets deadlines and milestones
Tools: Gantt Chart, CPM
PROJECT CONTROL
Project Control
Starts during execution
Monitors project progress
Compares actual vs planned
Focus Areas
Time
Cost
Performance
Scope
Control Methods
Performance reviews
Variance analysis
Earned value analysis
Comparison of planned and actual project progress
1.GANTT CHARTS
Definition: A graphical tool that
visualizes project activities
on a time axis.
function: Used to monitor progress and
provide a visual comparison
between planned and actual
accomplishments
Limitation:
May not always clearly indicate
complex precedence
relarionships among activities
2. Critical Path Method (CPM)
Key
Distinction:
Use a single time
estimate for each
activitiy ( deterministic
approach)
Notation: Commonly uses the ‘ Activity-on-Node’
(AON) convention , where nodes
represent activities and arrows
represent precedence.
Goal:
To determine the critical path-the longest
sequence of activities that dictates the total project
duration
3.Program Evalution and
Review Technique (PERT)
PLANNİNG
& TİMELİNE
Key Distinction:
Uses a distribution of times
(a probabilistic approach)
Historical Context:
Notation:
Developed in the late 1950s
( concurrently with CPM)
Orginally used ‘ Activity-on-Arrow’(AON) where
arrows represented activities and nodes
represented milestones.
3.2
Critical Path Method (CPM) – Summary
Purpose: Determine the sequence of project activities and calculate the total project duration.
Critical Path: The longest sequence of activities in the network
Determines the total completion time of the project
Activities on this path have zero slack (no delay allowed)
Time Analysis Steps
Forward PassFor each activity:
Earliest Start (ES): Earliest possible start time
Earliest Finish (EF): ES + activity duration
Goal: Find the earliest project completion time
Backward PassFor each activity:
Latest Finish (LF): Latest time the activity must finish
Latest Start (LS): LF – activity duration
Goal: Ensure the project is completed without delay
Slack (Float Time)
Formula:
Slack = LS – ES = LF – EF
Meaning:
The amount of time
an activity can be
delayed
without
affecting the project
Key Insight
Non-critical activities provide
flexibility in resource allocation
CPM helps in:
Time management
Risk control
Efficient resource planning
3.3
PROGRAM EVALUATION AND REVIEW TECHNIQUE (PERT)
PERT is a project scheduling technique that accounts for uncertainty in activity times.
Unlike CPM, it uses three time estimates for each activity:
Optimistic (Tmin): Minimum possible time
Most likely (Tml): Normal expected time
Pessimistic (Tmax): Maximum possible time
Using these estimates:
Expected time (Te) is calculated
Variance (σ²) is determined to measure uncertainty
PERT allows:
Probabilistic analysis of project completion time
Calculation of average project duration via the critical path
Estimation of completion probability using the z-score (normal distribution)
PROJECT CRASHING
WHY WE USE PROJECT CRASHING
-To meet a project deadline
earlier.
-To avoid penalties for
delays.
TIME-COST TRADE-OFF
Cost-Slope Formula
CRᵢ: Cost per unit time
reduction
ECᵢ: Expedited cost
Cᵢ: Normal cost
Tᵢ: Normal time
ETᵢ: Crashed time
(Activities with the lowest CR
are selected first.)
Normal point (Tᵢ, Cᵢ): Lower cost, longer
duration.
Expedited point (ETᵢ, ECᵢ): Higher cost,
shorter duration.
-To gain business advantages
by completing the project early
Reducing time always increases cost and
faster completion requires more resources and
higher expense
-To reduce indirect costs
1. Identify the critical path
2. Calculate cost slopes
3. Crash the least-cost
critical activity
INTRODUCTION TO MS PROJECT
Microsoft Project is a leading project
management tool used to plan,
schedule, and control projects.
In Microsoft Project:
Define tasks with durations &
dependencies
Automatically create schedules
& Gantt charts
Highlight the critical path
Other key features:
Activity-on-Node (AON) network
diagrams
Calendar system (Mon–Fri)
Customizable working days
SOFTWARE FOR
PROJECTS
Automatically create schedules & Gantt charts
Highlight the critical path
THANK
YOU
Work Systems Analysis and Design (IE250/1)
Esra ÜNAL - 230205014 (Group Leader)
Ayşe Nur İÇEN - 230205040
Efsa Gönül ÖZTÜRK- 230205024
Nisanur ÖZDEMİR - 230205007
Yağmur AKAY - 230205046