Exercise 5: Given the following network for a stock repurchase project with outside
consulting resource demands, construct a modified Gantt AOA chart with resources and
a resource load diagram. Suggest how to level the outside consulting load if you can
split operations.
code: activity, time/ resource units
Figure 9.5a is a modified Gantt chart indicating resource consumption at the end of each
task bar. The major timescale is in weeks and the minor timescale is in days.
In Figure 9.5a, the peak resource load is 26 units beginning on September 4th and ending on
September 10th.
The Original Offered Load from Figure 9.5a.
Task 21 22 23 26 27 28 29 30 2 3 4 5 6 9 10 11 12 13 16 17 18 19 20 23 24
A
6 6 6 6 6 6 6 6 6 6
B
4 4 4 4 4 4 4 4 4 4
C
4 4 4 4 4
D
2 2 2 2 2 2 2 2 2 2
E
10 10 10 10 10
F
8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
G
6 6 6 6 6 6 6 6 6 6
H
2 2 2 2 2
I
2 2 2 2 2
Sum 14 14 14 14 14 16 16 16 16 16 26 26 26 26 26 12 12 12 12 12 10 10 10 10 10
Day
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Original Offered Load
30
25
Resource Units
20
15
10
5
0
1
2
3
4
5
6
7
8
9
10
A
B
C
D
E
F
G
H
I
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Days
Figure 9.5b presents the offered load in Figure 9.5a as a spreadsheet.
Figure 9.5c shows the resource histogram for Figure 9.5b.
The graphical layout of the resource histogram is useful in understanding the shape and
dispersion of the offered load to project resources. In leveling load, trade-offs may be required
between flattening a spiked distribution and increasing the number of critical and near critical
tasks in the project.
The Leveled Load from Figure 9.5a.
Task 21 22 23 26 27 28 29 30 2 3 4 5 6 9 10 11 12 13 16 17 18 19 20 23 24
A
6 6 6 6 6 6 6 6 6 6
B
4 4 4 4 4 4 4 4 4 4
C
4 4 4 4 4
D
2 2 2 2 2 2 2 2 2 2
E
10 10 10 10 10
F
8 8 8 8 8 8 8 8 8 8 8 8 8 8 8
G
6 6 6 6 6 6 6 6 6 6
H
2 2 2 2 2
I
2 2 2 2 2
Sum 14 14 14 14 14 16 16 16 16 16 16 16 16 16 16 20 20 20 20 20 12 12 12 12 12
Day
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Legend
New critical path.
Original position of task.
Original critical path.
Original noncritical path.
Original Offered Load After Leveling
25
Resource Units
20
15
10
5
0
1
2
3
4
5
6
7
8
9
10
A
B
C
D
E
F
G
H
I
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
Days
Figure 9.5d presents the changes made to level load as a spreadsheet
Figure 9.5e shows the leveled resource histogram for Figure 9.5bd.
Compare Figure 9.5e to Figure 9.5c. The peak demand for resources has been lowered by six
units. However, tasks E and I are now critical tasks due to the changes made in leveling the
originally offered resource loads.
Assuming the operations can be split, an outside consulting firm could help add additional
human resources to assist in leveling load.