METHOD OF STATEMENT FOR SOIL RESISTIVITY TEST
General
The resistivity of earth varies over a wide range depending on its moisture
content, temperature, salt content and compactness.
Therefore, earth resistivity tests shall be conducted during the dry season in
order to get conservative results.
1.1
Instruments Required
a)
Four terminal Earth testers preferably a Digital version.
b)
Four no’s of 1.5m long, 16mm Dia Copper bond rod, the rod bottom shall be
made as cone to easily pierce through ground.
c)
Four Nos of 2.5 Sq.mm flexible stranded copper wires – length of each shall be
80m without any joints.
d)
Heavy duty hammer
e)
Earth tester used should have been calibrated and valid calibration certificate
should be available during testing.
f)
1.2
Thermometer
Instructions to be followed:
a) First the plot area to be identified
b) Location of soil resistivity Test shall be marked as per Soil resistivity layout.
c) Straight lines in two different directions (as per Soil resistivity layout) are to
be marked using chalk powder from the origin.
d) The test should be conducted, when the soil is in dry condition.
e) The recorded values shall be tabulated as per the Annexure-I.
2.0 PRINCIPLE OF WENNER’S FOUR ELECTRODE METHOD
In this method, four small electrodes are driven in the earth along a straight line
at equal intervals. A test current I is passed between the two outer electrodes and
the voltage difference V, between the two inner electrodes is measured. The test
current I thus flowing into earth produces an electric field proportional to its density
and to the resistivity of the soil. The voltage V measured between the inner
electrodes is, therefore, proportional to the field. Consequently, the resistivity will be
proportional to the ratio of the Voltage to Current. Thus, resistivity may be calculated
from the below mentioned equation (mentioned in Clause 2.2)
2.1.SITE PREPARATION
The Person in charge shall properly verify and inspect that the site work area is safe
to carry out the measurements before any work commencement.
The Person in charge shall finish the coordination survey (for every point to be
tested) before soil resistivity test measurements are carried out.
The Person in charge shall gather the weather information before the soil resistivity
measurement date and record the weather conditions prior and after to the test.
Before carrying out any testing, checks should be made on the location of any buried
cables, earth conductors or metal pipe work.
Saline water or any ground enhancement materials are strictly not allowed for
reducing earth resistance.
2.2
TEST PROCEDURE
METHOD
FOR
WENNER’S
FOUR
ELECTRODE
a) To start with, four nos. of electrodes are to be driven in Straight lines in
as t h e d i rec t i on s i n d i c at e d i n Soil resistivity layout. Place electrode ‘C1’
at center ‘O’.
b) The initial spacing between adjacent electrodes shall be 0.5 m
c) The electrodes shall be driven at a depth of n ot exceeding 1/20th of the
electrode spacing.
d) Earth Tester is to be placed in a steady and levelled base. Earth Tester shall
be checked for healthiness and zero error.
e) In case of Digital earth tester, the battery healthiness shall be checked before
performing the test.
f) An appropriate range on the Tester to be selected, provided the Tester has
that facility, to improve the accuracy of measurements.
g) Obtain the steady (i.e. constant) reading from the meter and tabulate the
values as indicated.
h) During testing, the soil resistivity value from the earth tester is measured
the resistance of potential & current circuit shall be measured and ensure
these values are equal. Same shall be recorded in the test format
i)
All correction factors like potential resistance high are being taken care by
microprocessor based digital earth tester.
j)
Now the values so obtained are for the spacing of 0.5m in the d ire cti on s
i ndi c ated i n Soil resistivity layout. Calculated earth resistivity value shall
be directly obtained from Digital Megger.
k) In case, the obtained reading is of very high value, if the earth tester is of
DIGITAL version, error code such as spike resistance “high” indicators appear.
The same shall be cleared by driving all 4 spikes to some more depth
(i.e. a> 1/20th spacing). The test is to be repeated. In case, if the error
message again occurs, the spike shall be driven to such a depth that the error
code is cleared. Under these circumstances, the actual depth of electrodes
shall be recorded. It is to be noted at all the four electrodes shall be driven to
same depth.
l)
Repeat the same test at different spacing (i.e. 0 . 5 m, 2 m, 4m, 8m, 10m,
1 6 m, 20m) in the same direction.
m) The sampled/recorder values are to be tabulated as indicated.
n) These are the readings obtained for the north direction only.
o) The same procedure is to be repeated for all other seven directions.
p) The soil resistivity is calculated using the following formula
a =
1+
4aR
2a
-
√a2+4b2
for b/a >20
(IEEE –81-2012 Eqn 2)
a
√a2+b2
a = 2aR
for b/a < 20 (IEEE –81-2012 Eqn 2)
where a – Apparent resistivity of soil (ohm-m)
R - Measured Resistance (ohm)
a - Distance between Electrodes (m)
b - Depth of Electrodes (m)
NOTE:
1) Before operating the earth Megger, its “Operating Instructions” shall be
studied
TEST SET UP
C1
P1
P2
C2
b
C1
P1
a
P2
a
C2
a
ANNEXURE‐I SOIL RESISTIVITY TEST REPORT
Client
Substation
Contract No.
NGCP
Marilao 500/230‐13.8kV SUBSTATION
Sp19.MESP.Lt‐0425
Main Contractor
STA. CLARA INTERNATION CORPORATION AND LARSEN & TOUBRO LIMITED
Test Date
Time
Project Name
Marilao EHV Substation Project
Weather on Measurement Day
Sunny
/ Cloudy / Rainy
Ambient Temperature on Measurement Day: ‐
Soil Condition on measurement day
Dry
/
Damp /Wet
Soil Type (From Investigation results) at
meter (Proposed Electrode Length
Units X
meters
Sand ‐ Loose /
Dense
Clay ‐ Soft / Firm / Stiff / Very Stiff / Hard
Stone ‐Very Poor
/ Poor
/ Fair / Good
Test Method
Four Point wenner Method
Test Instrument
Digital earth Tester
Model No.: ‐
Serial No.:
Instrument Calibration
Weather (Before and on Measurement day)
Day‐3
Day‐1
Day‐2
Day‐0
Day 1
Day‐3
Day 2
Test Location: SR1
Measurement
Point axis
X-1
X-2
Y-1
Y-2
Name
Designation
Date
Electrode
Depth ‘b’ (a/20)
(m)
0.025
0.10
0.2
0.4
0.5
0.8
1
0.025
0.10
0.2
0.4
0.5
0.8
1
0.10
0.2
0.4
0.5
0.8
1
0.10
0.2
0.4
0.5
0.8
1
C1-P1
0.5
2
4
8
10
16
20
0.5
2
4
8
10
16
20
2
4
8
10
16
20
2
4
8
10
16
20
Tested by:
Electrode
Spacing ’a' (m)
P1-P2
0.5
2
4
8
10
16
20
0.5
2
4
8
10
16
20
2
4
8
10
16
20
2
4
8
10
16
20
P2-C2
0.5
2
4
8
10
16
20
0.5
2
4
8
10
16
20
2
4
8
10
16
20
2
4
8
10
16
20
Meter
Reading 'R'
(ohm)
Witnessed by:
Soil Resistivity
ρ = 2πaR
(ohm-m)
Remarks
Witnessed by: