Dye Penetrant
Examination
Positive Material
Identification
All
On all high
alloy
-
100% of machined core faces
-
100% root welds (Note 2)
-
100% final capping welds
-
100% lifting attachments
-
100% for welds not accessible for
radiography (Note 1)
-
Pressure retaining parts
-
Lifting lugs
-
Welding consumable
Checking of Hardness
values
All
General specification for pressure Vessels
Checking of Ferrite
content
All
General specification for pressure Vessels
Helium leak test
All
Note (1). When longitudinal welds are not accessible for radiography due to the header geometry, the
joint efficiency for the concerned header is 0.7.
Note (2). Except header to core internals as these are not accessible due to the header geometry
Helium Leak test shall be performed prior to Pressure/Strength Test:
•
For equipment with 2 circuits or more:
Towards
The outside
Interstreams
Hot Side(s)
He at deltaP = 1bar
Maxi. Allow.flowrate 1.10-4
mbar.l/s
Cold
Side(s)
He at deltaP = 1bar
Maxi. Allow.flowrate 1.10-4
mbar.l/s
He at deltaP = 1bar
Maxi. Allow.flowrate 1.10-5
mbar.l/s
The tracer gas shall be 100% He.
Drying prior to the test with relative humidity at -15°C with 1250 mg/m3 of water max.