Continuous Assessment 4
a) Draw the assembly diagram and product structure tree for desk assembly as shown below.
b) Determine the quantities of A, B, C, D, and E needed to assemble one desk.
c) Determine the quantities of these components that will be required to assemble 10 desks, taking
into account the quantities on hand (i.e., in inventory) of various components
Component
A
B
C
D
E
Lead Time
2
2
4
3
1
On Hand
3
20
5
7
11
d) Develop a master schedule in weeks.
e) An order for the Desk is scheduled to be shipped at the start of week 11. What is the latest week
that the order can be started and still be ready to ship on time?
f) Develop a Material Requirements Plan for component B using fixed order quantity ordering for
items.
Item
Description
Safety Stock
Fixed Order Quantity (FOQ)
Period (In Weeks)
Gross Requirements
Scheduled Receipts
On Hand / 60
Net Requirements
Planned Order Receipts
Planned Order Releases
B
Table Legs
20 units
80
1
2
50
3
4
70
5
130
6
20
7
8
60