KINH NGU TRANG – KINH NGU TRANG NAM
FIELD DEVELOPMENT, BLOCK 09-2/09
CPP KNT
SPECIFICATION FOR SHUTDOWN, BLOWDOWN
VALVE AND HAND VALVE WITH LIMIT SWITCH
KNT-002-TS-IA2-SP-004
Rev.
1
Page
2 of 7
TRACK CHANGES
No
Rev.
Content of Change
1
A
Issued for Review
2
0
Issued for Approval
3
1
Issued for Approval
Note
Update section 7.3.2, remove Fugitive Emission Test
____________________________________________________________________________________
KINH NGU TRANG – KINH NGU TRANG NAM
FIELD DEVELOPMENT, BLOCK 09-2/09
CPP KNT
SPECIFICATION FOR SHUTDOWN, BLOWDOWN
VALVE AND HAND VALVE WITH LIMIT SWITCH
KNT-002-TS-IA2-SP-004
Rev.
1
Page
3 of 7
TABLE OF CONTENTS
1
INTRODUCTION ................................................................................................................... 4
2
ADDENDUM ......................................................................................................................... 5
____________________________________________________________________________________
KINH NGU TRANG – KINH NGU TRANG NAM
FIELD DEVELOPMENT, BLOCK 09-2/09
CPP KNT
SPECIFICATION FOR SHUTDOWN, BLOWDOWN
VALVE AND HAND VALVE WITH LIMIT SWITCH
1
KNT-002-TS-IA2-SP-004
Rev.
1
Page
4 of 7
INTRODUCTION
Kinh Ngu Trang and Kinh Ngu Trang Nam fields belong to Block 09-2/09 in Cuu Long Basin
offshore southern Vietnam. Kinh Ngu Trang field locates in distance approximately 150km
from Vung Tau city, 40 km from the East of White Tiger field, 14 km from Rang Dong field and
25 km from Ca Ngu Vang field. Kinh Ngu Trang Nam field locates in distance 3.5km from Kinh
Ngu Trang field. Sea water depth at the Kinh Ngu Trang and Kinh Ngu Trang Nam locations is
approximately 65m.
Fig.1: Location of KNT/KTN fields at Block 09-2/09
The development of Block 09-2/09 was started since 2019 when Petroleum Sharing Contract
(PSC) was signed between JV Vietsovpetro (VSP) 40%, PVEP- 30% and AO Zerubezhneft30%. VSP took the operatorship of Block 09-2/09.
The field development of Kinh Ngu Trang and Kinh Ngu Trang Nam consists of installation of
two (02) offshore platforms namely CPP KNT and WHP KTN, in-field pipelines, inter-field
pipelines, submarine cable and modification on the existing platforms at White Tiger Field. The
CPP KNT will be located at Kinh Ngu Trang field and designed as a Central Processing
Platform, equipped with full process and utility facilities to ensure the safe and effective oil &
gas production of Block 09-2/09. WHP KTN will be located at Kinh Ngu Trang Nam field and
will be designed as an unmanned wellhead platform, which is monitored and controlled
remotely from CPP KNT. The production fluid of Kinh Ngu Trang and Kinh Ngu Trang Nam
fields will be gathered and processed on CPP KNT to meet the export conditions and selfsufficiently supply of the gaslift, fuel gas and electrical power for internal field’s demands. After
the processing on CPP KNT, including separation, heating, compression and pumping, the
mixture of gas and liquid will be transported to MSP-10 platform at White Tiger field via 38.8
km of subsea pipeline. At MSP10, the oil gas mixture from CPP KNT will be routed to new
process facilities to separate the liquid and gas, conduct the allocation measurement before
____________________________________________________________________________________
KINH NGU TRANG – KINH NGU TRANG NAM
FIELD DEVELOPMENT, BLOCK 09-2/09
CPP KNT
SPECIFICATION FOR SHUTDOWN, BLOWDOWN
VALVE AND HAND VALVE WITH LIMIT SWITCH
KNT-002-TS-IA2-SP-004
Rev.
1
Page
5 of 7
export the gas to MKS platform for compression, liquid to CPP2/CPP3 for further processing to
meet the commercial requirement before offloading. The water injection for Kinh Ngu Trang
and Kinh Ngu Trang Nam fields will be supplied from BK-15 platform on White Tiger field via
35.8 km of subsea pipeline.
In addition, to ensure the power supply capacity for serving the connection of Kinh Ngu Trang
& Kinh Trang Nam fields, a modification for installation of new transformer sub-station 2500
KVA on MSP9 platform will be conducted. The power supply to MSP10 platform via the
existing submarine cable 6.3 kV MSP9-MSP10.
Scheme of Kinh Ngu Trang and Kinh Ngu Trang Nam field development is shown in figure 2.
Fig. 2: Development scheme of Block 09-2/09
The field development of Kinh Ngu Trang and Kinh Ngu Trang Nam is intended to allow for the
installation of offshore facilities in 2023-2024 years, and have First Oil in 4th Quarter of 2024.
2
ADDENDUM
This document uses the Typical Engineering Documentation for this Project. However, some
design intends or requirements may require to be revised to fit with Project’s purpose. This
section lists changes in the applied typical documents, originating in Typical Engineering
Documentation for any reason including those indicated in Table 1. These changes are
identified in this Addendum to the applied typical document, identifying the document and
section affected and the required change.
VENDOR shall review the required changes in conjunction with the referenced document and
project’s engineering documents.
The type of modification shall be defined and indicated in subsequent text as follows:
____________________________________________________________________________________
KINH NGU TRANG – KINH NGU TRANG NAM
FIELD DEVELOPMENT, BLOCK 09-2/09
CPP KNT
SPECIFICATION FOR SHUTDOWN, BLOWDOWN
VALVE AND HAND VALVE WITH LIMIT SWITCH
KNT-002-TS-IA2-SP-004
Rev.
1
Page
6 of 7
✓ “ADD” - Indicates the following statement(s) is/are added to the Company referenced
text.
✓ “DELETE” - Indicates the following statement(s) is/are deleted from the Company
referenced text.
✓ “REPLACE WITH” - Indicates the following statement(s) is/are revision(s) to the
Company referenced text.
Table – 1: List of Changes
Section
REFERENCE
DOCUMENTS
Whole
document
Current Statement or Requirement
Revised to
REPLACE WITH:
- VSP-NIPI-TYP-TS-PI1-SP-01
- KNT-002-TS-PI1-SP-001
- VSP-NIPI-TYP-TS-PI1-SP-02
- KNT-002-TS-PI1-SP-002
- VSP-NIPI-TYP-TS-IA2-SP-05
- KNT-002-TS-IA2-SP-005
miniBK/Unmanned WHP/WHP
REPLACE WITH:
KTN
Host Platform
REPLACE WITH:
KNT
3.2
Design Life:
REPLACE WITH:
Design Life
All new equipment shall be designed All new equipment shall be designed for a
for a service life of 15 years
service life of 25 years
5.1
REPLACE WITH:
Piping
Specification
Bolting
Material
5.6
KNT-002-TSPI1-SP-001
Piping Material Class
Specification
REPLACE WITH:
Protective
Coatings
VSP-NIPI-TYPGEN-AZ7-SP-01
Painting
Specification
for Platform
KNT-002-GEAC7-SP-002
Painting Specification
For Platform
VSP-NIPI-TYP
- Basic Painting
GEN-AZ7-SCH-01 Schedules
6.3
Accessories
6.7.10
Tubing
Fittings
and
REPLACE WITH:
316L Stainless Steel
VSP-NIPI-TYPTS-IA2-SP-03
316/316L Stainless Steel
General
Instrument
Specification
REPLACE WITH:
KNT-002-TSIA2-SP-003
General Instrument
Specification
7.3.2
Test • Fugitive Emissions Test (it shall DELETED
Requirements be demonstrated that the level of
fugitive emissions measured on the
valves under test are representative
____________________________________________________________________________________
KINH NGU TRANG – KINH NGU TRANG NAM
FIELD DEVELOPMENT, BLOCK 09-2/09
CPP KNT
SPECIFICATION FOR SHUTDOWN, BLOWDOWN
VALVE AND HAND VALVE WITH LIMIT SWITCH
KNT-002-TS-IA2-SP-004
Rev.
1
Page
7 of 7
for all valves supplied. Vendor to
advise no of valves to test based on
variations in packing / valve style.)
____________________________________________________________________________________
RESEARCH AND ENGINEERING INSTITUTE FOR
OFFSHORE OIL AND GAS
AGREED BY
Deputy General Director of
Vietsovpetro
APPROVED BY
~~~~I~I"r of Vietsovpetro
Tran Xu an Hoang
t. .> 1 O~
12022
TYPICAL ENGINEERING DOCUMENTATION
DOCUMENT TITLE
SPECIFICATION FOR SHUTDOWN,
BLOWDOWN VALVE AND HAND VALVE WITH
LIMIT SWITCH
DOCUMENT NO.
VSP-NI PI-TYP-TS-IA2-SP-04
Name
AGREED:
Date
Signed by : Nglly~n 1-16ng Gi ang
Date: 22/0812022 01 :26: 13
Ccr1ified by: Vietsovpetro CA
Capital Construction Department
Material and Equipment Department
Signed by; Chau Ng9C 1-10
Dale: 19/0812022 11 :20:28
Mechanical Electrical Division
Signed by: Trinh Hoang Linh
Date: I9!Osn022 08:07:21
Ccnified by: VielSovpetro CA
Cen ifk d by: Vietsovpetro CA
IFA
28/07/2022
T.A. NGUYEN
ID.Q.HUY
N.H.CHUNG
G.E.N
T.D.HAI
B.T.HAN
0
IFA
25/10/2019
N.H.CHUNG
N. H.C HUNG
G.E.N
T.D.HAI
B.T.HAN
REV.
DES.
DATE
PREPARED
CHECKED
DEPART.
MANAGER
ENG.
MANAGER
PRO.
MANAGER