EXERCISE 4
Question. HB Construction Company is building a house. They have the following list of activities, precedence and durations for the
project as following. Calculate Expected time (te), Standard Deviation (σ), Variance (σ²).
Task
Obtain building
permits
Excavate the
building site
Pour the
foundation
Frame the house
Install wall
Install roofing
Complete exterior
siding
Code
Predecessor
Optimistic
Time (to)
Most
Likely
Time (tm)
Pessimistic
Time (tp)
A
-
2
5
8
B
A
2
3
4
C
A
6
8
10
D
E
F
A
B
C
2
2
6
4
6
7
6
10
8
G
D, E, F
6
8
10
Expected
time (te)
Standard
Deviation
(σ)
Variance
(σ²)
Show your network diagram:
The Critial Path is:
Duration of the Critical Path or the expected project duration TE (of all activities on the critical path):
Standard Deviation of Project Duration (sum of the variances for all critical path activities): σE = √Σσ² =
Calculate the Z-scores for completing the project within 30 weeks with Z = (X - TE) / σE. X is the desired time frame. Z =
Normal Probability Distribution Table of Z is:
Probability of the project = 0.5 + Normal Probability Distribution of Z =