Introduction to Operations
The Process Analysis Framework
Christian Terwiesch, Andrew M. Heller Professor of Operations,
Information and Decisions
Image source: Peavey Guitars
Introduction to Operations
2
Image source: Peavey Guitars
Introduction to Operations
3
Flow Unit
Image source: Peavey Guitars
Introduction to Operations
4
Resource:
Image source: Peavey Guitars
Introduction to Operations
5
Inventories:
Image source: Peavey Guitars
Introduction to Operations
6
Resources:
Inventories (Buffers):
Image source: Peavey Guitars
Introduction to Operations
7
Processing times: how long does the worker spend on the task?
Capacity = 1/ processing time: how many units can the worker make per unit of time
If there are m workers at the resource:
Capacity of a resource =
m
Processing Time
Bottleneck: process step with the lowest capacity
Process capacity: capacity of the bottleneck
Introduction to Operations
8
Flow rate = Number of flow units that go through the process
(Demand rate, Process Capacity)
Utilization = Flow Rate / Capacity
Utilization applies to the level of the resource and the level of the process
Capacity Constrained vs Demand Constrained
Inventory: The number of flow units in the system
Flow time: The amount of time it takes a flow unit to go through the process
These are the three most important measures for any operation…
… yet, they are typically not reported in financial statements
Introduction to Operations
9
Introduction to Operations
Drawing a Process Flow Diagram
Christian Terwiesch, Andrew M. Heller Professor of Operations,
Information and Decisions
Introduction to Operations
11
CFB
Preheater
1st Stage
CFB
Reactor
2nd Stage
FB
Reactor
~ 110 m
Inclined
Bucket Elevator
Briquetting
Plant
Process
Gas
Heat
Exchanger
Iron
Ore
Fines
Electrical
Substation &
Control
Room
Process Gas
Compressor
Fired Gas
Heaters
HBI
Product
~ 160 m
Introduction to Operations
12
Resources
Add value and are required for completion of flow unit
May or may not carry inventory
Have a capacity (maximum number of flow units that
can flow through the activity within a unit of time)
Arrows
Indicate the flow of the flow unit
Inventory / Buffers
Do NOT add value to the flow unit
Flow unit does not have to spend time there
Introduction to Operations
13
Where is the Bottleneck?
Discharge
Pre-Heater
Lock
Hoppers
1st Reactor
2nd Reactor
Briquetting
Flash
Heater
Pile of
Iron ore
fines
Finished
Briquets
Introduction to Operations
14
Where is the Bottleneck?
Discharge
118 tons/h
Pre-Heater
120 tons/h
Lock
Hoppers
110 tons/h
1st Reactor
120 tons/h
2nd Reactor
100 tons/h
Briquetting
165 tons/h
Flash
Heater
135 tons/h
Pile of
Iron ore
fines
Finished
Briquets
Introduction to Operations
15
Introduction to Operations
Thinking about Work as a Process
Christian Terwiesch, Andrew M. Heller Professor of Operations,
Information and Decisions
Resource Perspective
Capacity
Utilization
Bottleneck
Introduction to Operations
17
https://www.leansixsigmadefinition.com/glossary/ohno-circle/
Introduction to Operations
18
Example: Tesla Assembly Line
https://www.digitaltrends.com/cars/tesla-model-3-assembly-time-lapse-video/
Introduction to Operations
19
Flow Unit:
Vehicle
Completed
Vehicles
Aluminum
Coils
Stamping
Welding & Gluing
Stamped Pieces
Paint Line
Unpainted Vehicles
Assembly
Painted Vehicles
Resources:
300+ workers on
the line robots
Flow Rate:
7,000 cars per
week
Inventory: About
5,000 vehicles
Bottleneck/
Constraint: Very
well balanced
Introduction to Operations
20
Demand moves quickly while supply typically does not
Mismatch can take one of the following two forms (corresponding to different flow
units)
Supply waits for demand
(inventory=goods or resources)
Demand waits for supply
(inventory=waiting customers)
Difference between manufacturing operations and service operations
Introduction to Operations
21
Supply waits for demand
(inventory=goods or resources)
Demand waits for supply
(inventory=waiting customers)
Introduction to Operations
22
Key Definitions
Learning Objectives:
Flow Unit: The unit of analysis we consider in a process
analysis
Processing Time: Time taken by each resource to work on a
flow unit
Capacity: Number of flow units per unit time that can be
processed by a resource
Bottleneck: Resource with the lowest capacity (we will
update this definition)
Process Capacity: Maximum number of flow units that a
process can provide per unit of time
Demand Rate: The number of flow units that customers want
per unit time
Utilization: The degree to which a resource (or a process)
operates at its capacity
Flow Rate: The number of flow units flowing through the
process per unit time
Flow Time: Amount of time it takes a flow unit to go through
the process
Inventory: Number of flow units in the system
Map an operation as a process flow
Compute a capacity of an individual resource
and find the bottleneck in a process
Compute flow rate (and understand the
definitions of inventory, flow time and flow rate)
Compute the utilization of a resource
Key Formulas:
Capacityi =
Flow Rate =
Utilizationi=
Number of Resourcesi
Processing Timei
Min{Demand, Capacity}
Flow Rate
Capacityi
Introduction to Operations
23
Practice Problem:
Glenn Dental
Resource
Process
Number of resources
Processing time
(mins. per patient)
A. Self-service Kiosk
Paperwork
1
2
B. Receptionists
Data Entry
2
5
C. Dental Assistant
X-ray
3
15
D. Dentist
Check-up
10
30
1.
Draw a process flow diagram of this process
2.
What is the capacity (patients/hr) at the resource ”Dentist”?
3.
What is the bottleneck in the process?
4.
Assuming unlimited demand, what would be the flow rate?
5.
Assuming unlimited demand, what would be the utilization at resource “Receptionists”?
Introduction to Operations
24