ASSIGNMENT # 3
CARRY OUT the quantity-take-off for excavation work and wall using the layout shown in Figure . USE
Separate wall method.
Figure 1 The layout of 9" masonry wall, to COMPUTE excavation quantity.
•
•
•
•
Notes:
The thickness of the wall is 9 inches.
The bottom of the excavation is 3 ft below the road level.
The total width of the foundation is 2 ft 3 inches, and no extra space will be left around it for
work.