Risk Assessment
Work Site:
Document Number:
Company:
Date:
Area: Abu Dhabi
RA –
Responsible Engineer: Site Engineer/Foreman
Revision: 0
Delivery, Storage and
Handling of Paint and
Thinner
- Cuts to Hands
- Slips, Trips and
Falls
- Back Injuries due
to Manual
Handling
6
6
36
Paint Application
Fire & Explosion
due to Flammable
Substances
Paint spillage due to
accidental leakage,
storing damaged
containers, wrong
handling of materials
2
Control /
Mitigation Measures
6
6
36
Action By
Residual Risk
Hazard / Effect
Risk Ranking
1
Activity /
Task Step
Severity
S/N
Likelihood
Task: Painting of Floors, Walls and Ceilings
Paint Cans & Thinners to be stored in steel containers.
Containers will be positioned away from any vehicle traffic to
avoid damage from collision.
Pallets of paints to be unloaded by forklift only and stacked
on even ground.
Proper access and walkways free of obstructions shall be
provided for persons carrying paints to work area.
Hand gloves shall be worn when handling paint cans to avoid
cuts to the hands.
Ensure that Material Safety Data Sheet available at site /
store.
Provide adequate warning signs for paint storage areas.
Task to be carried out with proper supervision.
CM
Site Engineer
Foreman
Store Keeper
Safety Officer
Low
No Hot work shall be permitted in the vicinity of paint or
thinner storage areas.
All Combustible/flammable materials should be removed
from the work area.
Suitable fire extinguishers and fire protection systems shall
be provided in the work area.
Keep minimum quantity of flammable materials at the work
place.
Adequate training to be given to the workforce regarding fire
risks.
Site Engineer
Foreman
Safety Officer
Low
Paint Application
Fumes from Paint /
Thinner
4
6
24
Control /
Mitigation Measures
Respiratory
problems, Asthma,
Ill-health
Slips, Trips and
Falls
4
6
24
Spillages and
Walkways not clear
or poor housekeeping
Manual Handling
6
6
36
Back Injuries can
occur from lifting and
hauling
Defective Hand
Tools
Injuries can occur
due to defective hand
tools,
6
4
24
Action By
Residual
Risk
2
Hazard / Effect
Risk Ranking
Activity /
Task Step
Severity
S/N
Likelihood
Risk Assessment
Adequate ventilation shall be provided on the work place to
extract fumes and blow fresh air.
Ensure MSDS available at work place and shall be
communicated to workers.
Adequate training / TBT shall be given to workers regarding
painting works.
Ensure usage of suitable PPEs such as respiratory mask,
hand gloves, safety glasses.
Site Engineer
Foreman
Safety Officer
Low
Drip trays or polythene sheet shall be provided to avoid paint
thinner spillage on the ground.
Obstruction shall be removed prior of lifting a load
All spillages and waste materials shall be disposed of and /
or cleaned up as per EAD requirements.
Access routes shall be kept clear at all times.
Mechanical handling devices shall be used whenever
possible.
Disposal of hazardous waste as per local authority regulation
EAD.
Site Engineer
Foreman
Safety Officer
Low
Provide wheelbarrows, Material basket or hydraulic jacks to
haul Paint cans within the work area.
Ensure workers are physical fit for the Job.
Ensure workers conduct periodic breaks to rest their backs
Ensure workers drink sufficient fluids to re-hydrate their body
which is lost due to sweating and heavy work.
Site
Engineer
Foreman
Safety Officer
Low
Inspect all hand tools before for any damage and repair or
remove from site.
Ensure workers are aware in the safe and correct use of
these tools
Site
Engineer
Foreman
Low
6
6
36
Serious Injuries or
Death to personnel
falling from height if
not protected by
handrails, guards or
fall protection
Falling Objects from
Height /
Scaffoldings
6
6
36
Personnel working
under or nearby can
sustain serious
injuries from falling
objects
Risk Ranking
Hazard / Effect
Severity
Activity /
Task Step
Likelihood
S/N
Action By
Residual Risk
Falling from Height
Control /
Mitigation Measures
Ensure all scaffoldings are inspected and scaff-tag
provided for safe use Green Safe / Red Unsafe.
All personnel working 2 meters or above to wear Safety
Harness and tied off to a suitable strong point.
All ladders used to be in the appropriate angle and
secured properly.
Only approved scaffoldings or working platforms to be
used.
If mobile platforms used, ensure wheels are locked when
persons working on top.
If mobile platforms are moved to different locations,
ensure personnel are removed before moving scaffolding
to different location.
Site Engineer
Foreman
Safety Officer
Scaffolding
Foreman
Low
Ensure area is barricaded were work is conducted at
height.
Install appropriate warning signs “Falling objects”
No materials to be stored on top of scaffolds
Highest standard of housekeeping to be observed on top
of scaffolds.
Ensure all scaffolds have toe boards installed to prevent
tools and materials from falling.
Any tools to be used on top of scaffoldings shall be
secured to prevent falling.
Site Engineer
Foreman
Safety Officer
Low
Control /
Mitigation Measures
Action By
Residual Risk
Working at Height and
on Scaffoldings
Hazard / Effect
Risk Ranking
3
Activity /
Task Step
Severity
S/N
Likelihood
Risk Assessment
Risk Assessment
4
Use of Air Compressor
Dust, Noise, Whip
Lash Injuries &
Flying Objects
6
6
36
5
Working during
Darkness (Night Shift)
Poor Visibility
6
4
24
Personnel can
sustain injuries due to
poor visibility by
falling / tripping over
an obstruction
All hoses must be inspected prior to use.
Ensure whip lash arrestor wires are installed on all
connections.
Always TURN OFF the compressor when not in use. .
Use appropriate PPE(hand gloves, respirators, safety
goggles, face shield, etc.,)
Dot not use diesel air compressor in enclosed spaces
due to exhaust fumes.
Site Engineer
Foreman
Safety Officer
Low
Ensure Work areas, walkways, access ways are
supplied with sufficient lighting.
All tripping hazards and obstructions to be removed for
personnel to move freely.
Ensure area is barricaded off and warning signs in place.
Ensure all pits and manholes are covered to prevent
personnel from falling.
Ensure workers are supervised at all times during the
Night shift.
Ensure workers are aware of Emergency Assembly
points during night time.
Ensure all emergency exits and assembly points are
provided with sufficient lighting.
Local task lights shall be installed where illumination is
insufficient provided by the normal lighting.
Site Engineer
Foreman
Safety Officer
Low
Severity / Likelihood Matrix:
Severity
Slight
Injury.
Minor or
Serious
Injury
Major
Injury.
Lost
Single
Fatality.
Multiple
Fatalities
Risk Assessment
First-Aid
Time
> 3 days
Permanent
Disability
0-8
Trivial Risk
No further improvements necessary provided control
measures are maintained.
12 - 24
Likelihood
2
4
6
8
10
Certain
10
20
40
60
80
100
Very
Likely
8
16
32
48
64
80
Likely
6
12
24
36
48
60
May
Happen
4
8
16
24
32
40
Unlikely
2
4
8
12
16
20
Adequately Controlled Risk
Risk is tolerable when control measures identified are
implemented.
32 - 48
Moderately Controlled Risk
Further Risk Reduction Measures should be considered.
60 - 100
Intolerable Risk
Seek specialist advice/support.
Reviewed By:
Name: ________________________ Signature: __________________ Designation: ________________ Date: ___________
Approved By:
Name: ________________________ Signature: __________________ Designation: ________________ Date: ___________