Below is a ready-to-paste set of review comments you can give to the planner /
scheduler.
Each line tells them exactly what to change in the master programme so that Level-5
IST and Punch-List Administration now satisfy every item in the AWS pre-energisation
checklist you showed earlier.
A. General Review Comment (put this in the transmittal e-mail)
“Level-5 IST tasks are generally captured, but sequencing and gating do not yet align
with the AWS Pre-Energisation Checklist Rev-1.
Please action the detailed remarks in the attached mark-up so that all checklist
prerequisites are logically tied to the ‘Ready for Energisation’ milestone and no
safety-critical task remains after the system is live.”
B. Detailed Mark-Ups (line-by-line)
# Current Task in Schedule Comment to Planner
Action Required
Split into two tasks: 1a
“CxA Checklist Review
Label says “check”, but
(Gate A)” – 1 day, F/S
AWS.L5.COMM – LEVEL 5
the bar spans 12 days and predecessor to FOD
1 ENERGIZATION CHECK
overlaps other tasks –
Sweep. 1b “Final CxA
(14-29 May 26, 12 d)
unclear purpose.
Sign-Off (Gate C)” –
0 days, F/S predecessor to
Ready for Energisation.
Good, but must finish
Add F/S predecessor to
FOD INSPECTION
2
before any soak test or oil HYPACT GIS & Tx Soak
COMPLETION (14-15 May)
filling.
Test and to Oil BDV.
Rename to “Stakeholder
WALK-THROUGH
Same dates OK; set F/S
Pre-C2E Meeting
3 BEFORE ENERGIZATION
link to Cold-Walk Safety
(Switching Sequence)”
Inspection (new Task 4).
(18-19 May)
to match AWS #9.
4 -- new
Cold-Walk Safety
Insert 19 May; predecessor
Inspection (LOTO
= Task 3; successor =
devices, barricades, PPE)
Ready for Energisation.
– 0.5 d
# Current Task in Schedule Comment to Planner
5
ICT – TESTING &
PRE-COMMISSIONING
Action Required
Runs 20-21 May, but TNB
End-to-End (Task 6)
Add F/S predecessor from
starts one day later; that’s
ICT to TNB End-to-End.
OK as long as logic links
exist.
TNB – END-TO-END
6 TESTING &
PRE-COMMISSIONING
Keep 21-22 May, but the
utility will not issue the
energisation permit until
this line closes.
READY FOR
7 ENERGIZATION
(23-24 May)
Move this bar to 28 May,
make it 0 days milestone,
Should be the last
and create F/S
Level-5 task before any
predecessors from: • Oil
live switching. Right now
BDV (Task 9)• HYPACT &
it sits before soak test
Tx Soak (Task 8)•
and oil BDV – that violates
Cold-Walk Safety (Task 4)•
AWS items 5, 6, 8, 10, 12.
TNB End-to-End (Task 6)•
ICT (Task 5)
Add successor: Ready for
Energisation.
HYPACT GIS &
One day is unrealistic:
TRANSFORMER
GIS pressurisation + Tx
8
CHARGING & SOAK TEST 24-h soak = 2 days
(25 May)
minimum.
Extend duration to
25-26 May; add
predecessor Oil BDV
(Task 9) and successor
Ready for Energisation.
OIL SAMPLING & BDV
Must precede the soak
MEASUREMENT (24 May) test, not follow.
Move to 23 May, set
successor HYPACT Soak.
9
TEMPORARY POWER
CANCELLATION &
10 COMMISSIONING OF
33 kV MV SWITCHGEAR
(27 May)
Add F/S predecessor to
OK, but must finish before
Switching of 33 kV Incomer
any incomer switching.
(Task 11).
SWITCHING OF 33 kV
11
INCOMER (28 May)
Combine with “Switching Delete Task 13; keep
Task 11; successor =
from Temporary to
Permanent Power Supply” Overall Commissioning.
# Current Task in Schedule Comment to Planner
Action Required
(Task 13) – they are the
same field operation.
• Start 24 May, finish
Should finish before
AUX TRANSFORMER
25 May.• Add predecessor
12
“Ready for Energisation”,
COMMISSIONING (28 May)
Oil BDV.• Add successor
not after.
Ready for Energisation.
SWITCHING FROM
TEMPORARY TO
13
PERMANENT POWER
SUPPLY (28 May)
Redundant – delete and
roll into Task 11.
Remove bar; adjust
predecessors as per
Comment 11.
Make it a Level-of-Effort
Leave as is, but this is the
OVERALL
(LOE) summary spanning
14
first post-energisation
COMMISSIONING (29 May)
29 May–29 Jul to cover
activity.
30-day burn-in.
PUNCH LIST ADMIN –
AS-LEFT SETTING
15
INSPECTION (30 May–
11 Jun)
Split: 15a As-Left Freeze
(Protection Settings) –
27 May, 0 d milestone;
AWS item 12 says the
successor = Ready for
“As-Left” freeze is before
Energisation. 15b As-Left
energisation.
Audit Report – leave
30 May–11 Jun if you want
a documented review.
PUNCH LIST ADMIN –
16 O&M TRAINING (12 Jun–
30 Jun)
OK – matches AWS
item 22
(post-energisation).
PUNCH LIST ADMIN –
POST-ENERGIZATION
17
PUNCH POINT CLOSING
(01-29 Jul)
Good, but should finish
Add F/S predecessor to
before “As-Built Drawing
Task 18.
Submission”.
CLOSE-OUT – AS-BUILT
18 DRAWING SUBMISSION
(30 Jul–28 Aug)
No change, but add
Post-Energisation
Punch-List Closing as
predecessor.
Ensure predecessor
Overall Commissioning
Start.
—
C. New Tasks to Insert (not in the current file)
Task Name
Target
Duration
Date
Predecessors
AWS
Checklist
Ref.
Documentation Upload
to Procore (Drawings & 2 d
L1-L4 Packs)
20-21 May none
#2, #4-#7
Spare Parts / Switching
0.5 d
PPE Staged in HV Yard
25 May
Cold-Walk Safety
#17
27 May
Documentation upload +
#1, #3
As-Left Freeze +
Cold-Walk + FOD + Soak
Certificate of Readiness
0d
Issued (CxA)
(Add them exactly where shown, or the energisation permit will be issued with open
items.)
D. Logic Links to Add
1. Oil BDV → HYPACT Soak (F/S)
2. HYPACT Soak → Ready for Energisation (F/S)
3. Ready for Energisation → Switching of 33 kV Incomer (F/S)
4. Switching 33 kV Incomer → Overall Commissioning (F/S)
5. Overall Commissioning (start) → O&M Training (F/S)
6. Post-Energisation Punch Close → As-Built Submission (F/S)
E. Duration / Resource Reality Checks
GIS + Tx Soak: minimum 24 h continuous monitoring – give it 2 calendar days so
the schedule reflects a night shift.
TNB End-to-End: utility witness often slips; insert 1 day free float ahead of
Ready for Energisation.
Training: 15 days appears long; confirm with the client – may be 5 days
classroom + 5 days on-site is enough.
F. Resulting High-Level Milestones
Milestone
New Date Status Gate
Gate A – Documentation & FOD Complete
23 May 26 ✅ Checklist items 1-7
Gate B – Plant Conditioned (Oil, GIS, Earthing,
✅ Checklist
26 May 26
Aux TF)
items 8, 10, 12
Gate C – Ready for Energisation (Permit in
hand)
28 May 26
Energisation – 33 kV Incomer Live
28 May 26 —
Gate E – Punch-List Closed / As-Built Issued
28 Aug 26 Project Close-Out
✅ All prerequisites
green
How to Deliver These Comments
1. Export the Primavera bar chart to PDF, turn on Activity ID + Activity Name +
Start/Finish columns.
2. Redline exactly the changes above (use call-out bubbles; reference the
comment numbers).
3. Attach this table as “Comment Register – Rev 0”.
4. Ask the planner for a re-run of the schedule logic and an updated critical-path
report within 48 h.
That gives the scheduler clear, unambiguous instructions and ties every amendment
back to the AWS checklist, so nothing gets lost in version churn.