1.1 INTRODUCTION Process control is concerned with the control of unit operation and unit processes. Chemical plant processes can be regulated to obtain the objectives and effectiveness by applying the feed backward or feed forward principles using various computing devices like sensors, transmitters, controllers etc. It requires sensors for measuring variables and valves for implementing decisions. The piping and instrumentation (P&I) diagram is a pictorial representation of a process plant having all the equipment along with the piping, valves, insulation and instrumentation. 1.2 INSTRUMENTS The different instruments used in the P&I diagram generally are • Flow meters • Level Meters • Pressure gauge • Thermometers and thermocouples • Quality analysis devices • Radiation measuring devices The instruments are used for indicating, recording and controlling purposes. The instruments are all identified by a code number. The first letter of the code refers to the property measured. ✓ F - Flow rate ✓ T - Temperature ✓ P - Pressure ✓ L - Level The second letter is either I, R or C which indicates to indicating, recording and controlling respectively. 1 1.3 MODES OF CONTROLLER PID-Controller The PID controller is used as temperature controller and the basic modes of controller are • On-off control • Integral control • Proportional control • Rate or derivative control P-Controller The most common application of the p-controller is level controller. There is an offset in the p-controller. The maintaining of the level does not require any accurate measurements. So, P-controller is used as level controller. PI-Controller The PI controller is used as flow rate controller. PI-controller does not have any offset. The measurement of the flow rate must be accurate and does not have any offset. So, PIcontroller is most commonly used as a flow controllerpressure controller. In PID controller, the response will be faster and accurate. the temperature and pressure must measure accurate and faster for taking the control action. So, PID controller is most commonly used. 1.4 CONTROL OBJECTIVES The main objective of process control and instrumentation on the chemical plants are as follows: • To suppress the external and internal disturbances on the process system. • To ensure the stability of the process. • To optimize the performance of the process there by making the process more economical. 1.4.1 NECESSITY OF PROCESS CONTROL 2 • Safety - To look for hazardous situation and to mitigate those situations by providing emergency alarms, control valves and automatic shutdown systems. • Product Specification - To maintain the production composition according to its quality standards. • Environmental Regulation - To avoid environmental pollution by treating the waste and vent gases and only an appreciable amount accepted by Pollution Control Board is made to release into the atmosphere. • Plant Economy - To operate the plant at very low production and operating cost in order to increase the plant economy. 1.5 MEASURING ELEMENTS: • Temperature Measurement - It is essential for the effective production of the product. Thermocouples, Resistance thermometers, Pyrometers are used for the measurement of temperature. • Pressure Measurement - Mechanical and Electrical pressure sensors are used for measuring pressure in the process plant. • Level Measurement - Liquid head pressure devices, dielectric constant measuring instruments, sonic resonance devices are used primarily for the measurement of level. • Flow Measurement - Obstruction type, inferential, electromagnetic, ultrasonic, Mass flow meters. These are the type of flow meters widely used. CONTROL LOOPS: For instrumentation and control of different sections and equipment’s of plants, following control loops are most often used. 1. Feedback control loop 2. Feedforward control loop 3. Cascade control loop 3 1.FEEDBACK CONTROL LOOP A method of control in which a measured value of a process variable is compared with the desired value of the process variable and any necessary action is taken. Feedback control is considered as the basic control loops system. Its disadvantage lies in its operational procedure. For example if a certain quantity is entering in a process, then a monitor will be there at the process to note its value. Any changes from the set point will be sent to the final control element through the controller so that to adjust the incoming quantity according to desired value (set point). But in fact changes have already occurred and only corrective action can be taken while using feedback control system. 2.FEEDFORWARD CONTROL LOOP A method of control in which the value of disturbance is measured than action is taken to prevent the disturbance by changing the value of a process variable. This is a control method designed to prevent errors from occurring in a process variable. This control system is better than feedback control because it anticipates the change in the process variable before it enters the process and takes the preventive action. While in feedback control system action is taken after the change has occurred. 3.CASCADE CONTROL LOOP This is a control in which two or more control loops are arranged so that the output of one controlling element adjusts the set point of another controlling element. This control loop is used where proper and quick control is difficult by simple feed forward or feed backward control. Normally first loop is a feedback control loop. 4 1.6 CASCADE CONTROL LOOP ON REACTOR (R-1): The reaction is exothermic and the heat generated is removed by coolant, which flows in the jacket around the tank. The control objectives is to keep the temperature of the reacting ammonia and nitric acid constant at 131℃. Possible disturbances to the reactor include feed temperature Tf and the coolant temperature Tc. The only manipulated variable is coolant flowrate Fc. If we use feedback control, we will measure reactor outlet temperature and manipulate coolant flowrate Fc. Therefore, the feedback control will be very effective for compensating changes in temperature of outlet but less effective for changes in coolant temperature. We can improve the response of feedback control to changes in the coolant temperature by measuring Tc and taking control action before its effect has been felt by the reacting mixture. Thus, if Tc goes up, increase the flowrate of the coolant to remove the same amount of heat. Decrease the coolant flowrate when Tc decreases. 5 Therefore, we have two control loops using two different measurements, T and Tc, but sharing a common manipulated variable, Fc. 1. The loop that measures T (controlled variable) is the dominant, or primary, or master control loop and uses a set point supplied by the operator. 2. The loop that measures Tc, uses the output of the primary controller as its set point and is called the secondary or slave loop. 1.7 PREHEATER: CONTROL OBJECTIVE To maintain the required temperature of feed CONTROLLER USED PID control is the satisfactory control for temperature control. MANIPULATED VARIABLE Flow rate of steam CONTROL VARIABLE Temperature of product stream in preheater. 6 1.8 COOLER CONTROL OBJECTIVE To maintain the product steam at desired temperature level CONTROLLER USED PID control is the satisfactory control for temperature control MANIPULATED VARIABLE Flow rate of water. CONTROL VARIABLE Temperature of product stream. 7 1.9 STORAGE TANK CONTROL OBJECTIVE To maintain the desired level of feed in tank and to ensure it does not overflow. CONTROLLER USED PI control is the satisfactory control for flow. MANIPULATED VARIABLE Flowrate of input stream CONTROL VARIABLE Level of liquid in vessel. 8 1.10 EVAPORATOR CONTROL OBJECTIVE 1.To maintain process stream at desired temperature range. 2. To maintain the optimum ratio of Nitric acid and ammonium nitrate. 3.To maintain desired inlet flow rate CONTROLLER USED PI control is the satisfactory control for flow. MANIPULATED VARIABLE Flowrate of input stream CONTROL VARIABLE Level of liquid in vessel. 9 1.11 PRILLING TOWER 2.FAULT TREE ANALYSIS FTA is a top-down process by which an undesirable event (failure in a project objective or a critical failure that can affect the project), referred to as the top event, is logically decomposed into possible causes in increasing detail to determine the causes or combinations of causes of the top event. FTA can yield both qualitative and quantitative information about the system understudy. 1. Qualitative information may include failure paths, root causes, and weak areas of the system/project. 2. Quantitative analysis of a fault tree gives a probabilistic estimation of the top event 10 2.1 LIST OF SYMBOLS IN FAULT TREE ANALYSIS : SYMBOL NAME DESCRIPTION Top event; Secondary or Contributing events; A Rectangle System state requiring more investigation on lower levels Circle Basic fault event; no further development required House Not a fault event; an event that is expected to occur under normal operation Diamond Undeveloped event; one that, by either choice or necessity, will not be developed further Oval An event that places qualified conditions on the fault sequence AND GATE Describes an operation where all input events must occur for the operation to occur OR GATE Describes an operation where one or more of the input events can occur in order for the output to occur Used to show logic flow between two parts of the fault tree; F Transfer GATE Transfers everything under the event it is attached to; Reference is made by an alphanumeric code 11 2.2 FAULT TREE ANALYSIS FOR STIRRED TANK REACTOR FIG 2.2 FAULT TREE ANALYSIS FOR STIRRED TANK REACTOR 12 2.3 FAULT TREE ANALYSIS FOR SHELL AND TUBE HEAT EXCHANGER FIG 2.3 FAULT TREE ANALYSIS FOR SHELL AND TUBE HEAT EXCHANGER 2.4 FAULT TREE ANALYSIS FOR CENTRIFUGAL PUMP FIG 2.4 FAULT TREE ANALYSIS FOR CENTRIFUGAL PUMP 13 2.5 FAULT TREE ANALYSIS FOR STORAGE TANK FIG 2.5 FAULT TREE ANALYSIS FOR STORAGE TANK 14 3.1 PARAMETERS FOR COST ESTIMATION The various parameters to be considered in the cost estimation are: • Process Equipment Cost • Fixed Capital Investment • Working Capital Investment • Fixed & Direct Charges • Total Manufacturing Cost 3.2 ESTIMATION OF PURCHASED EQUIPMENT COST The equipment costs are calculated using the following formulas: 1. Ce = a + b*Sn Where, Ce – Cost of equipment in lakhs S – Size a, b, n – constants depending on the equipment 2. CE = CB (Q/QB) M FP FM FY Where, CE – Equipment cost for carbon steel equipment at moderate temperature with capacity Q CB – Bare cost of equipment with capacity QB M – Constant depending on material used FP – Correction factor of design pressure FM – Correction factor depending on material of construction FY – Correction factor of design temperature 15 3.3 PURCHASED EQUIPMENT COST EQUIPMENT EQUIPMENT QUANTITY TOTAL COST(In Lakhs INR) CSTR 1 1 36.6 CSTR 2 1 43.6 PREHEATER 1 1 6.25 PREHEATER 2 1 7.13 EVAPORATOR 1 95.79 STORAGE TANK 4 45.22 PRILLING TOWER 1 97.16 CONDENSOR 1 11.84 PUMP 4 16.16 TOTAL PROCESS EQUIPMENT COST [PEC] = 359.86Lakhs INR 3.4 DIRECT COST (DC): S.NO COST TYPE INR(In Lakhs) 1 Purchased equipment installation [45% PEC] 161.94 2 Instrumentation (15% PEC) 53.98 3 Electrical (13% PEC) 46.78 4 Piping (13%PEC) 46.78 5 Building including services (30% PEC) 107.96 6 Yard Improvement (12% PEC) 43.18 7 Land 251.90 TOTAL DIRECT COST [DC] = 712.53 Lakhs INR 16 3.5 INDIRECT COST (IDC): S.NO COST TYPE INR(In Lakhs) 1 Engineering & Supervision (34% PEC) 122.35 2 Construction Expenses (32% PEC) 115.15 3 Contractor fees (20% PEC) 71.97 4 Contingency (30% PEC) 107.96 TOTAL INDIRECT COST [IDC] = 417.44 Lakhs INR FIXED CAPITAL INVESTMENT [FCI] = DC + IDC FIXED CAPITAL INVESTMENT [FCI] = 712.53 + 417.44 = 1129.98 Lakhs INR WORKING CAPITAL INVESTMENT [WCI] = 18% FCI = 203.39 Lakhs INR TOTAL CAPITAL INVESTMENT [TCI] = FCI + WCI = 1129.98 + 203.39 = 1333.38 Lakhs INR FIXED CHARGES [FC]: Depreciation, D = (𝑉−𝑉𝑠)/𝑛 (By straight-line method ) Where, V = FCI = 1129.98 Lakhs INR VS = 5% FCI = 56.49 Lakhs INR n = 20 years ∴ Depreciation = 53.67 Lakhs INR 17 TOTAL PRODUCT COST [TPC] = TCI – D = 1333.38 - 53.67 = 1279.70 Lakhs INR TOTAL FIXED CHARGES = 12% Total Product Cost = 0.12*1279.70 = 153.56 Lakhs INR 3.6 DIRECT CHARGES [DC]: Raw material Costs: S.NO RAW MATERIAL COST/kg TOTAL COST/ DAY (Lakhs INR) TOTAL COST (Lakhs INR) 1 Ammonia 68 1.191 393.14 2 Nitric Acid 48 3.169 1045.82 3 Water 12 0.253 83.66 TOTAL RAW MATERIAL COST=1522.63 Lakhs INR 18 OPERATING LABOUR COST: S.NO POSTS NO.OF POSTS ANNUAL SALARY IN Lakhs INR TOTAL SALARY IN Lakhs INR 1 General manager 1 12 12 2 Production manager 2 10 20 3 Engineer 5 7.5 37.5 4 Skilled Workers 15 4 60 5 Clerks 8 2 16 6 Medical Staff 6 1.5 9 7 Unskilled labour 20 1.1 22 8 Administrative 10 2 20 9 Security 4 1.1 4.4 10 Fire Officier 2 1.5 3 TOTAL OPERATING LABOUR COST = 203.90 Lakhs INR 19 S.NO COST TYPE COST (Lakhs INR) 1 Operating labour 203.90 2 Direct Supervisory & Electric 204.75 Labour (16%TPC) 3 Utilities (12% TPC) 153.56 4 Maintenance (4% TPC) 51.18 5 Operating Supplies (15% TPC) 191.95 6 Laboratory Charges (16% TPC) 204.75 7 Patent (4% TPC) 51.18 Operating Cost = OL + OS + M = 447.04 Lakhs INR Plant Overhead Cost = 60% OC PLANT OVERHEAD COST = 268.22 Lakhs INR TOTAL DIRECT CHARGES [TDC] = 2583.94 Lakhs INR GENERAL EXPENSES: S. NO COST TYPE COST (Lakhs INR) 1 Administration cost (25% OL) 50.975 2 Distribution & Selling Price (15% TPC) 191.95 3 Research & Development (5% TPC) 63.98 4 Finance (5% TPC) 63.98 20 TOTAL GENERAL EXPENSES = 370.90 Lakhs INR Total Manufacturing Cost = FC + DC + Overhead Cost + General Expense TOTAL MANUFACTURING COST [TMC] = 3376.63 Lakhs INR PROFITABILITY INDEX S.NO PRODUCT COST/kg kg/DAY (Lakhs INR) TOTAL COST (Lakhs INR) 1 Ammoium Nitrate 150 12.24 4088.16 2 Water 12 0.0049 1.641 TOTAL INCOME = 4089.802 Lakhs INR GROSS INCOME = Total Income – TMC = 713.16 Lakhs INR TAX = 28% of GROSS INCOME = 199.68 Lakhs INR NET PROFIT = GROSS INCOME – TAX = 513.47 Lakhs INR RATE OF RETURN = (Net Profit / Total Capital Investment) *100 = (513.47 / 1333.38) * 100 = 38.50 % PAY BACK PERIOD = FCI / (Net Profit + Depreciation) = 1.99 years = 2 years 21 4.1 HAZOP ANALYSIS A Hazard is something which may cause harm and is an undesired event. The word HAZOP refers to the detail study regarding operability and hazards. It’s a formal procedure to identify hazards in a chemical process facility. This systematic study is used to find out operability problems and equipment hazards or all plant hazards. The method for doing HAZOPS study involves detail examination of each equipment (instruments, piece of equipment, pipeline) and the finding out all possible deviation from normal operating conditions. Before the HAZOP study is started, detailed information on the process must be available. This includes up-to-date process flow diagrams (PFDs), process and instrumentation diagrams (P&IDs), detailed equipment specifications, materials of construction, and mass and energy balances. A HAZOP study is conducted in the following steps : Specify the purpose, objective, and scope of the study. The purpose may be the analysis of a yet to be built plant or a review of the risk of unexisting unit. The scope of the study is the boundaries of the physical unit, and also the range of events and variables considered. The initial establishment of purpose, objectives, and scope is very important and should be precisely set down so that it will be clear, now and in the future, what was and was not included in the study. These decisions need to be made by an appropriate level of responsible management. • HAZOP team is selected. • For the collection of data following materials are needed: • Process description • Process flow sheets • Data on the chemical, physical and toxicological properties of all raw materials, intermediates, and products. • Piping and instrument diagrams (P&IDs) • Equipment, piping, and instrument specifications 22 • Process control logic diagrams • Layout drawings • Operating procedures • Maintenance procedures • Emergency response procedures • Safety and training manuals 4.1.1 Objectives of HAZOP study: • To find out those areas in design which can have significant hazard potential. • To study and find out those aspect of design that effects the occurrences of hazardous incidence. • To make study team familiar with design information. • To make sure that systematic study of areas involving hazard potential is made. • To provide a mechanism for feedback to the client of the study team's detailed comments 4.2 Key Elements: Key elements of a HAZOP are: ✓ HAZOP team. ✓ Full description of process. ✓ Relevant guide words. ✓ Conditions conducive to brainstorming. ✓ Recording of meeting. ✓ Follow up plan 23 4.3 HAZOP Team: HAZOP studies are carried out using a `brainstorming' approach by a team, chaired and coordinated by a qualified person experienced in Team leadership Following are the members of HAZOP team: • Team Secretary • Process Engineer • Mechanical Engineer • Commissioning/Operations • Engineer/Manager • Instrument Engineer 4.3.1 Strength of HAZOP: • HAZOP is a systematic, reasonably comprehensive and flexible. • It gives good identification of cause and excellent identification of critical deviations. • The use of keywords is effective and the whole group is able to participate. • HAZOP is an excellent well-proven method for studying large plant in a specific manner. 4.3.2 Weakness of HAZOP: • HAZOP is very time consuming and can be laborious with a tendency for boredom for analysts. • It tends to be hardware-oriented and process-oriented, although the technique should be amenable to human error application. • HAZOP does not identify all causes of deviations and therefore omits many scenarios. 24 4.3.3 Responsibility of HAZOP Team Members: • Plan sessions and timetable • Control discussion • Limit discussion • Encourage team to draw conclusion • Ensure secretary has time for taking note • Keep team in focus • Encourage imagination of team members • Motivate members • Discourage recriminations • Judge importance issues 25 4.4 GUIDE WORDS: Guide Words Meaning Comments No, Not, None The complete negation of No part of the design intention is the intention achieved, but nothing else happens. More, Higher, Greater Quantitative increase Less, Lower Quantitative decrease As well as Qualitative increase Part of Qualitative decrease Reverse The logical opposite of the intention Other Than Complete substitution 26 Applies to quantities such as flow rate and temperature and to activities such as heating and reaction Applies to quantities such as flow rate and temperature and to activities such as heating and reaction. All the design and operating intentions are achieved along with some additional activity, such as contamination of process streams. Only some of the design intentions are achieved, some are not. Most applicable to activities such as flow or chemical reaction. Also applicable to substances, for example, poison instead of antidote. No part of the original intention is achieved. The original intention is replaced by something else. 4.5 HAZOP ANALYSIS OF REACTOR: Title: HAZOP Analysis Study Node: Reactor (CSTR) Operating conditions: 131oC GUIDE WORD DEVIATION CAUSES CONSEQUENCES Flow rate i.No Feed in storage i.Decrease in tank production or ii.Feed pump rupture no production iii.Supply pipe rupture iv.Valve is closed v.Pump is off i.Cleaning of line ii.Level control system iii.Maintenance of pipes iv.Automatic valve v.Automatic pump Level i.Blockage in line ii.Valve is closed i.Decrease in production or no production i.Maintenance of pipes ii.Automatic valve Temperature i.Fault in Preheater ii.Steam pipe rupture i.Decrease in production or no production i.Maintenance of pipes Pressure i.Fault in Preheater i.Decrease in production or no production i.Maintenance of Preheater Flow rate i.More valve opening i.Explosion i.Automatic valve ii.Less conversion ii.Check reactor conditions Level i.More valve opening i.Overflow No More 27 ACTION REQUIRED i.Check valve Temperature i.Fault in Preheater i.Explosion i.Maintenance Pressure i.Fault in Preheater i.Less production i.Check valve Flow rate i.Less of opening of i.Decrease in valves production or no production i.Automatic valve ii.Temperature control at reactor feed preparation Level i.Less of opening of i.Decrease in valves production i.Check valve Temperature i.Fault in Preheater i.Less conversion i.Temperature control Pressure i.Fault in Preheater i.Less Production i.Maintenance Impurities in feed stream i.Problem in raw material ii.Fouling in pipes i.Low Conversion i.Quality control of rate raw material and ii.Decrease in product product quality ii. Maintenance Higher or Lower percentage of Nitric Acid i.High quality of feed ii.Less quality of feed i.More or less pure production than intended Less All well as Part of 28 i.Quality control of raw material and product Other than Replacement of Raw Material i.Wrong connection i.Explosion during plant modification Corrosion of Equipment i.No proper cleaning and i.Scale i.Regular checks maintenance formation ii.Proper cleaning and ii.Leads to cracks maintenance and crevices iii.Reactor Explosion Corrosion of Cooling water coils i.No proper cleaning and maintenance Corrosion Conta mination i.Better management of changing procedure i.Scale i.Regular checks formation ii. Proper cleaning and ii.Leads to cracks maintenance and revises iii.process disruption Contamination i.leakage i.Disruption in the i.Regular checks of process ii.Catalyst getting mixed process ii.Proper cleaning and fluid line with process fluid ii.Damage in the maintenance internal and external parts of the equipment’s due to long term exposure if the chemical has harmful properties . 29 4.6 HAZOP ANALYSIS OF PREHEATER: Title: HAZOP Analysis Study Node: Preheater Operating conditions: 25oC PARAMETER GUIDE WORD DEVIATION Less CAUSES CONSEQUENCES ACTIONS REQUIRED Less i.Fouled temperature heat tubes ii.Flow leakage i.Impact on efficiency ii.Excessive pressure drop Incorporate Nickel to the MOC to improve corrosion resistance and prevent fouling More More High temperature feed flow rate i.Increase in pressure ii.Reboiler duty will fail Use plug valves to control feed flow rate No No flow Control valve fails/ closed No further operability Regular maintanance More More flow Plug control valve failure Coking Shutdown in case of either pump failure Control system is employed to control the amount of steam that passes through the turbine Temperature Flow 30 4.7 HAZOP ANALYSIS OF CONDENSOR: Title: HAZOP Analysis Study Node: Condensor Operating conditions: 66oC PARAMETER GUIDE WORD DEVIATION CAUSES Condenser Cooling Water System Temperature High High Tube’s heat Temperature up, then cool Excursion and with possible breakage from thermal induced stress Tube’s heat up, then cool and with possible breakage from thermal induced stress Condenser Suction System Flow regimes Phases Flow Condensate dropping out in the steam supply line Slugging leading to piping system damage Provide condensate upstream of isolation valve and a warm up line Condenser Ejector Supply Flow High Loss of condensate flow to the ejector condenser Full steam the exhaust line to the vent. Potential for increased friction losses in the vent piping. Check the pressure drop in exhaust line to vent at full steam flow conditions to determine if overpressure of the ejector 31 CONSEQUENCES ACTIONS REQUIRED Condenser Vessel System Flow Low Running the condensate system while shutdown Lose the steam condensate supply Add a line and valve from downstream to the condenser fill nozzle 4.8 HAZOP ANALYSIS OF PUMP: Title: HAZOP Analysis Study Node: Centrifugal pump Operating conditions: 25oC PARAMETER GUIDE WORD CAUSES CONSEQUENCES ACTIONS REQUIRED More i.Failure/leak/improper cooling system connections ii.Very low flow iii.High pressure iv.Pump not submerged Vaporization of liquid increase in Pressure causing destruction of pump internal explosion and fire i.Check cooling system ii.Check pressure/vent/ valve iii.Increasing cooling Temperature Low i.More open of cooling i.Lubricant system Character ii.Low flow rates changes and viscosity ii.Damage of bearings 32 i.Check cooling system ii.Check no of engine rounds More i.Blockage in outlet valve ii.Faulty pressure sensor Vaporizing liquid i.Deterioration of bearings ii.Stop production explosion Check drain pipes replace the gasket and damage check i.Close suction valve ii.Faulty sensor iii.Air leaks in suction Line Cavitation Vibration damaging internal pump i.Loss in fittings ii.Ensure NPSHa>NPSHr Pressure Low 4.9 HAZOP ANALYSIS OF STORAGE TANK: Title: HAZOP Analysis Study Node: Storage Tank Operating conditions: 25oC PARAMETER GUIDE WORD DEVIATION CAUSES CONSEQUENCES No No flow Delay in Install and dispatch maintain interlock Material system evaporation from storage tan More More flow Master valve failed to open Manifold valve failed to open Blockage in manifold valve There is no logical sequence Flow 33 There is no consequences ACTIONS REQUIRED No actions required 4.10 HAZOP ANALYSIS OF EVAPORATOR: Title: HAZOP Analysis Study Node: Evaporator Operating conditions: 131oC PARAMETER GUIDE WORD CAUSES CONSEQUENCES Less Valve fails open Difficult to control heating process More Pump failure, pipe partially blocked No Pipe blockage or valve fails open Waste energy and Install flow detector increase production and alarm Regular cost pipe cleaning and checking leakage No heating Less Steam Valve partially blocked Feed Flow ACTIONS REQUIRED Outlet temperature of feed varies Installing Temperature controller and alarm Feed More Temperature Steam Valve fails Close Possibility of explosion. Waste of energy and increase cost Less Valve failure or partially blocked Increases time to heat Frequent maintenance and cleaning More Valve fails Close Increases pressure Feed Overheated Installing Flow monitor Steam flow 34 5.1 PLANT LOCATION AND SITE SELECTION The location of the plant can have a crucial effect on the profitability of a project and the scope for future expansion. Many factors must be considered when selecting a suitable site, and only a brief review of the principal factors will be given in this section. Site selection for chemical process plants is discussed in more detail by Merims (1966) and Mecklenburgh (1985); see also AIChE (2003). The principal factors to consider are 1. Location, with respect to the marketing area; 2. Raw material supply; 3. Transport facilities; 4. Availability of labor; 5. Availability of utilities: water, fuel, power; 6. Availability of suitable land; 7. Environmental impact, including effluent disposal; 8. Local community considerations; 9. Climate; 10.Political and strategic considerations. 5.2 SITE LAYOUT The process units and ancillary buildings should be laid out to give the most economical flow of materials and personnel around the site. Hazardous processes must be located at a safe distance from other buildings. Consideration must also be given to the future expansion of the site. The ancillary buildings and services required on a site, in addition to the main processing units (buildings), include 1. Storage for raw materials and products: tank farms and warehouses; 2. Maintenance workshops; 3. Stores, for maintenance and operating supplies; 35 4. Laboratories for process quality control; 5. Fire stations and other emergency services; 6. Utilities: steam boilers, compressed air, power generation, refrigeration, transformer stations; 7. Effluent disposal plant: waste water treatment, solid and or liquid waste collection; 8. Offices for general administration; 9. Canteens and other amenity buildings, such as medical centers; 10. Parking lots. ➢ When the preliminary site layout is roughed out, the process units are normally sited first and arranged to give a smooth flow of materials through the various processing steps, from raw material to final product storage. Process units are normally spaced at least 30m apart; greater spacing may be needed for hazardous processes. ➢ The location of the principal ancillary buildings should then be decided. They should be arranged so as to minimize the time spent by personnel in traveling between buildings. ➢ Administration offices and laboratories, in which a relatively large number of people will be working, should be located well away from potentially hazardous processes. ➢ Control rooms are normally located adjacent to the processing units, but those with potentially hazardous processes may have to be sited at a safer distance. ➢ The siting of the main process units determines the layout of the plant roads, pipe alleys, and drains. Access roads to each building are needed for construction and for operation and maintenance. ➢ Utility buildings should be sited to give the most economical run of pipes to and from the process units. 36 ➢ The main storage areas should be placed between the loading and unloading facilities and the process units they serve. Storage tanks containing hazardous materials should be sited at least 70m (200 ft) from the site boundary. 5.3 PLANT LAYOUT The economic construction and efficient operation of a process unit will depend on how well the plant and equipment specified on the process flowsheet is laid out. A detailed account of plant layout techniques cannot be given in this short section. A fuller discussion can be found in the book edited by Mecklenburgh (1985) and in articles by Kern (1977, 1978), Meissner and Shelton (1992), Brandt et al. (1992), and Russo and Tortorella (1992). The principal factors to be considered are 1. Economic considerations: construction and operating costs; 2. The process requirements; 3. Convenience of operation; 4. Convenience of maintenance; 5. Safety; 6. Future expansion; 7. Modular construction. 5.3.1 COSTS The cost of construction can be minimized by adopting a layout that gives the shortest run of connecting pipe between equipment and the least amount of structural steel work; however, this will not necessarily be the best arrangement for operation and maintenance. 5.3.2 OPERATION Equipment that needs to have frequent operator attention should be located convenient to the control room. Valves, sample points, and instruments should be located at convenient positions and heights. Sufficient working space and headroom must be provided to allow easy access to equipment. If it is anticipated that equipment will need replacement, then sufficient space must be allowed to permit access for lifting equipment. 37 5.3.3 MAINTENANCE Heat exchangers need to be sited so that the tube bundles can be easily withdrawn for cleaning and tube replacement. Vessels that require frequent replacement of catalyst or packing should be located on the outside of buildings. Equipment that requires dismantling for maintenance, such as compressors and large pumps, should be placed under cover. 5.3.4 SAFETY Blast walls may be needed to isolate potentially hazardous equipment and confine the effects of an explosion. At least two escape routes for operators must be provided from each level in process buildings. 5.3.5 PLANT EXPANSION ✓ Equipment should be located so that it can be conveniently tied in with any future expansion of the process. ✓ Space should be left on pipe racks for future needs, and service pipes should be oversized to allow for future requirements. 5.3.6 MODULAR CONSTRUCTION In recent years there has been a move to assemble sections of a plant at the plantplant manufacturer’s site. These modules include the equipment, structural steel, piping, and instrumentation. The modules are then transported to the plant site, by road or sea. The advantages of modular construction are 1. Improved quality control; 2. Reduced construction cost; 3. Less need for skilled labor on site; 4. Less need for skilled personnel on overseas sites. Some of the disadvantages are 1. Higher design costs; 2. More structural steel work; 3. More flanged connections; 38 4. Possible problems with assembly, on site; A fuller discussion of techniques and applications of modular construction is given by Shelley (1990), Hesler (1990), and Whittaker (1984). 5.4 UTILITIES The word utilities is used for the ancillary services needed in the operation of any production process. These services are normally supplied from a central site facility and include 1. Electricity; 2. Steam, for process heating; 3. Water for general use; 5.4.1 ELECTRICITY The power required for electrochemical processes, motor drives, lighting, and general use may be generated on site, but will more usually be purchased from the local supply company.The voltage at which the supply is taken or generated will depend on the demand. In the United States, power is usually transmitted over long distances at 135, 220, 550, or 750 kV. Local substations step the power down to 35 to 69 kV for medium voltage transmission and then to 4 to 15 kV local distribution lines. Transformers at the plant are used to step down the power to the supply voltages used on site. Most motors and other process equipment run on 208V 3-phase power, while 120/240V single phase power is used for offices, labs, and control rooms. 5.4.2 STEAM The steam for process heating is usually generated in water tube boilers, using the most economical fuel available. 5.4.3 WATER FOR GENERAL USE The water required for general purposes on a site will usually be taken from the local mains supply, unless a cheaper source of suitable quality water is available from a river, lake, or well. 39 40 COOLER REACTOR AMMONIA STORAGE FIRE STATION GARDEN AREA PARKING AREA PRILLING TOWER REACTOR PREHEATER AMMONIUM NITRATE STORAGE PACKAGING UNIT PLANT EXPANSION CONTROL ROOM PREHEATER NITRIC ACID STORAGE PLANT EXPANSION RESEARCH AND DEVELOPMENT ADMINISTRATION BLOCK HEALTH CENTRE CANTEEN ELECTRIC SUBSTATION SECURITY DISPATCHING UNIT QUALITY CONTROL EVAPORATOR PLANT UTILITIES AMMONIUM NITRATE PRILLS STORAGE
0
You can add this document to your study collection(s)
Sign in Available only to authorized usersYou can add this document to your saved list
Sign in Available only to authorized users(For complaints, use another form )