NGN/SP/NDT/2 Specification for Non-Destructive Testing of Welded Joints on Construction and Fabrication Projects September 2019 NGN/SP/NDT/2 1 Uncontrolled when printed / after download NGN/SP/NDT/2 Contents Page Foreword 4 Disclaimer 4 Brief History 4 Mandatory and non-mandatory requirements 5 Approval 6 Key changes 6 1. Scope 7 2. References 7 3. Definitions 7 4. Destructive Testing 7 5. Non-Destructive Testing Method 8 6. Personnel Qualification 8 7. Non-Destructive Testing of Procedure Welds 8 8. Non-Destructive Testing of Production Welds 9 9. Radiographic Examination 11 10. Manual Ultrasonic Examination of Welded Joints 12 11. Automatic Ultrasonic Examination for Pipeline 16 12. Phased Array Ultrasonic Examination for Pipework 16 13. Magnetic Particle Flaw Detection 17 14. Dye Penetrant Flaw Detection 18 15. Non-Destructive Testing of Repaired Production Welds 18 2 Uncontrolled when printed / after download NGN/SP/NDT/2 16. Records 18 Appendix A – References 19 Appendix B – Management of Site Radiography 21 Appendix C – Site Radiation Safety Monitoring Checklist & Report Sheet 29 Appendix D – Requirements for Automatic Ultrasonic Inspection (AUT) for Pipeline Fabrication/Construction & Phased Array Ultrasonic (PAUT) for Pipework Construction 33 Appendix E – Non-Destructive Testing 50 Endnote 56 3 Uncontrolled when printed / after download NGN/SP/NDT/2 Foreword This document was approved by the appropriate Technical Authority Level (TAL) and Standards Steering Group (SSG) for use throughout Northern Gas Networks Limited (NGN). NGN documents are revised, when necessary, by the issue of new editions. Users should ensure that they are in possession of the latest edition by referring to the NGN Register of Documents available on NGN intranet. Compliance with this document does not confer immunity from prosecution for breach of statutory or other legal obligations. Contractors and other users external to NGN should direct their requests for further copies of NGN documents to the department or group responsible for the initial issue of their contract documentation. Disclaimer This safety and engineering document is provided for use by NGN and such of its contractors as are obliged by the terms and conditions of their contracts to comply with this document. Where this document is used by any other party it is the responsibility of that party to ensure that this document is correctly applied. Brief History First published as NGN/SP/NDT/2 June 2004 EPSG/T03/867 Amended into NGN format July 2007 Updated to include the use of phase array ultrasonic (PAUT) on inspection of pipework and pipeline. Updating of the reference list and Competence of the inspectors. July 2017 Version 2.0 Review to address regular deviations around the design of calibration blocks. Blocks can now be designed to BS EN ISO 13588 as opposed to ASME BPVC Section V which are not readily available. August 2019 NGN/SP/NDT/2 Version 3.0 4 Uncontrolled when printed / after download NGN/SP/NDT/2 Non-material change to re-instate missing bullet points in Appendix D. June 2020 Version 3.1 5 Uncontrolled when printed / after download NGN/SP/NDT/2 Mandatory and non-mandatory requirements In this document: Must: Indicates a mandatory requirement Should: Indicates best practice and is the preferred option. If an alternative method is used then a suitable and sufficient risk assessment must be completed to show that the alternative method delivers the same, or better, level of protection. 6 Uncontrolled when printed / after download NGN/SP/NDT/2 Approval Technical Authority Level: Andrew Middleton 05th September 2019 19th September 2019 Standards Steering Group: Key Changes Section Amendments D 4.3.1 & D 4.11.2 PAUT qualification requirements amended to the satisfaction of NGN, rather than ASME standards. D 4.3.5, D 4.3.9, D 4.5.4 & D 4.5.5. BS EN ISO 13588 specified for calibration blocks in place of ASME standards. 7 Uncontrolled when printed / after download NGN/SP/NDT/2 Specification for Non-Destructive Testing of Welded Joints on Construction and Fabrication Projects 1. Scope This Specification defines the minimum or additional NGN requirements necessary for non-destructive examination of welded joints. Where National or International standards referenced in this document require specific items to be agreed between the contracting parties, the requirements of this specification must apply. This specification is not intended for the revalidation of welded joints in pressure containing components. In such cases reference to NGN/PR/NDT/1 should be made. This Specification details the requirements for non-destructive examination of welded joints in carbon, carbon manganese and stainless steel materials specified for use on the NGN Gas Network only. Where non-destructive testing alone cannot confirm that a welded joint fully meets the acceptance criteria of a qualified welding procedure, additional destructive testing may be needed to prove that the requirements of the appropriate welding standard or specification have been met. 2. References Unless otherwise specified, the latest edition, including addenda and revisions, of the documents listed in Appendix A must apply. 3. Definitions For the purpose of this specification the terms and definitions used in BS EN 1330 must apply. Employer: NGN acting directly or through an authorised representative. Class I Welding: For the purpose of this specification, Class I welding must be categorised as those welds which are designed to operate at pressures greater than 7 bar. Class II Welding: For the purpose of this specification, Class II welding must be categorised as those welds that are designed to operate at pressures not greater than 7 bar. 4. Destructive Testing The Employer reserves the right to require the complete removal of production welds to prove that the mechanical properties of the weld conform to specification criteria. Destructive testing must consist of the removal of complete welds for mechanical testing in accordance with the appropriate welding standard or specification. 8 Uncontrolled when printed / after download NGN/SP/NDT/2 5. Non Destructive Testing Method 5.1 General The method of non-destructive testing (NDT) used must be capable of producing indications of imperfections which can be accurately interpreted and evaluated in order to assess whether the defect acceptance criteria specified in the relevant welding standard have or have not been met. The results of the non-destructive testing must be recorded and must include the location, size and nature of all flaws detected. 5.1.1 Operators of all types of non-destructive testing equipment should be required to demonstrate to the approval of the Employer the capability of the equipment and examination procedure to detect flaw indications. The operator may be asked to demonstrate their ability to make correct interpretation of defect indications given by the equipment. 5.1.2 Welds must be examined in the as welded, or post weld heat-treated condition (PWHT), as applicable. If the weld has been subject to PWHT the non-destructive testing must follow this treatment. Local dressing of the weld reinforcement may be required to confirm transverse indications. 5.1.3 Where local dressing is used to aid the interpretation of non-destructive testing or to confirm defect indications, care must be taken to maintain the material minimum design thickness. 6. Personnel Qualification Personnel performing non-destructive examination in accordance with this specification must have qualifications from a scheme meeting the requirements of BS EN ISO 9712 (e.g. PCN, CSWIP or ACCP). Acceptance of certification by the inspection company in accordance with a written practice meeting the recommendations in SNT-TC-1A or ANSI/ASNT CP-189 shall be subject to review and agreement by Employer. The Employer may consider personnel approved to an alternative qualification scheme as a variation to the specification. 7. Non Destructive Testing of Procedure Test Welds 7.1 General Non-destructive testing on weld procedure qualification test welds must conform to the welding procedure qualification standard and this specification. All non-destructive testing must be carried out on the test pieces prior to cutting of the test specimens for mechanical test. Any post-weld heat treatment that is specified shall be completed prior to nondestructive testing. The quality of the test welds must be determined by non-destructive testing after weld specimens have been allowed to cool to ambient temperatures in production conditions for a minimum of 24 hours. 9 Uncontrolled when printed / after download NGN/SP/NDT/2 Non-destructive testing procedure specifications must be submitted to the Employer and be approved prior to weld testing. All test butt welds must be examined visually and by X-radiography. Automatic Ultrasonic Testing (AUT) may be substituted for X-radiography when agreed between the contracting parties. If AUT is used, then it must be carried out in accordance with Appendix D of this specification. Non-destructive testing procedure specifications must be submitted to the Employer for approval prior to production welding commencing. The weld root region must be examined by magnetic particle inspection (MPI) or dye penetrant inspection (DPI), as appropriate, where access permits. All fillet test welds must be examined visually and by MPI or DPI as appropriate. MPI must be the preferred method to be used for the examination of carbon steel welds. The DPI method must be used for the examination of austenitic stainless steel welds. Complementary non-destructive testing methods, such as Ultrasonic Testing, may be required to identify flaw characteristics. 7.1.1 The results from visual examination and non-destructive testing must be assessed according to the appropriate acceptance criteria of the welding standard specified. 8. Non Destructive Testing of Production Welds 8.1 General 8.1.1 Non-destructive testing must be performed in accordance with the Inspection and Test Plan and Quality Control Procedure developed for the project. As a minimum, the extent of non-destructive testing (percentage or number of production welds to be examined) must meet the requirements of the construction code and this specification. 8.1.2 All completed welds must be examined visually in accordance with BS EN ISO 17637. To verify compliance with the approved welding procedure, where practicable, individual weld passes, in particular the root bead, must be examined during welding. When a completed weld cap is still above the minimum inter-pass temperature stated in the approved welding procedure, repairable welding defects revealed by visual examination may be removed and re-welded. 8.1.3 In addition to the requirements of the construction code, 100% volumetric examination by Xradiography or a fully automated ultrasonic system must be applied for the butt welds in the following circumstances: • • • Pipelines designed to transport category D and E fluids. The fluid categorisation is defined in table 1 of BS PD 8010-1. Pipelines designed to transport category B and C fluids at hoop stresses above 77% of SMYS. Pipework and sections of pipelines designed to transport category B and C fluids in stations and terminal. 10 Uncontrolled when printed / after download NGN/SP/NDT/2 • • • • • Pipelines designed to category B and C fluids within populated areas, such as residential areas, shopping centres and designated commercial and industrial area. Pipelines with river, lake and stream crossings, including overhead crossings or crossings on bridge. Pipelines on railway or public rights-of-way, including tunnels, bridges and overhead crossing. Pipelines in offshore and coastal water. Pipelines or pipework where “golden welds” are permitted in-lieu of pressure (strength) testing. 8.1.4 In addition to the requirements of the construction code, 100% surface crack detection by either MPI or DPI as appropriate must be applied for the branch connection weld designed to transport category B, C, D and E fluids. 8.1.5 When required by the Employer, the primary method of weld examination must be supplemented by a complementary method of non-destructive testing. Supplementary inspection may include the following scenarios: • • • • Supplementary examination is required for a specific number of welded joints to enable early identification of potential welding problems. Surface crack detection method to support volumetric inspection and vice versa. Additional volumetric weld examination method to support the primary volumetric weld examination method (Ultrasonic Testing to support Radiography Testing or vice versa) or additional surface crack detection method (Dye Penetrant Test to support Magnetic Particle Inspection). Complementary methods may include Positive Material Identification, Hardness Test, Field Metallography Replica and Lamination Examination. Employer must specify the supplementary non-destructive testing method to be used, the number of welds to be examined and the extend of the examination. 8.1.6 Non-destructive testing procedure specifications must be submitted to the Employer for approval prior to production welding commencing. 8.1.7 All non-destructive testing must be completed prior to pressure (strength) testing or coating/insulation activities, where it is applicable. 8.1.8 All final non-destructive testing must be completed after the completion of Post Weld Heat Treatment, where is its applicable. 8.1.9 The time delay before the final non-destructive testing must be in accordance with the Inspection and Test Plan. If the time delay is not specified in the Inspection and Test Plan, a time delay of at least 24 hours is required for carbon manganese steel with yield strength not greater than 450MPa and weld heat input not greater that 3kJ/mm. For a higher strength steel or higher heat input, the time delay must be agreed with Employer prior to production weld commence. 11 Uncontrolled when printed / after download NGN/SP/NDT/2 9. Radiographic Examination 9.1 General 9.1.1 The main requirement of the ionising radiation regulations is that NDT contractors should adopt working practices capable of keeping radiation exposures of employees as low as reasonably practicable. If work involves routine radiography of readily moveable articles, an assessment must be made to establish whether site radiography is appropriate or if the articles should be taken to a cell for examination. Appendix E provides a flowchart and guidance to facilitate the assessment. 9.1.2 It is not NGN policy to use sealed sources, i.e. Gamma isotopes, for weld examination. However, conditions may exist that prevent the practical use of X-ray or ultrasonic methods, and in such circumstances the Employer should consider the use of alternative NDT methods. Any alternative procedures or methods of weld examination proposed must be approved by the Employer and be qualified, prior to weld testing commencing. 9.1.3 Radiography must be carried out in accordance with BS EN ISO 17636-1 and to the requirements of this specification. The minimum standard of radiography produced must be in accordance with Class B (improved techniques). Class A must not be permitted without the written agreement of the Employer and only where Class B cannot be achieved for sound technical reasons. 9.1.4 The use of fluoro-metallic screens or pre-packed films may be used provided that radiographic quality level, contrast and density requirements as per section 9.1.2 and 9.6 are achieved. Damaged screens must not be used. The Employer has the final decision whether screens or the use of pre-packed films are acceptable for further use. 9.1.5 Only fine grain high contrast direct type film or ultra-fine grain high contrast direct type film meeting the requirements of BS EN ISO 11699-1 Class C4 must be used. The film type must be stated on the radiographic procedure sheet and must be approved for use by the Employer. 9.1.6 All radiographs must be interpreted when dry. 9.1.7 Permanent marking of the pipe as in BS EN ISO 17636-1, Clause 6.5 must be by waterproof marker only. No hard stamping must be permitted. 9.1.8 Suitable padding must be used on external X-ray sets to prevent damage to the pipe coating. 9.2 Radiographic Personnel Radiography must be carried out in accordance with national and company safety standards. All personnel engaged in radiography must be familiar with the current legislation with respect to carrying out work with ionising radiation. Each radiographic crew must consist of at least two people. Each member of the crew must hold, as a minimum, Radiographic Testing (Weld) level 2 qualification from a scheme meeting the requirements of BS EN ISO 9712. Prior to submitting radiographs to the Employer, the films must be viewed by personnel 12 Uncontrolled when printed / after download NGN/SP/NDT/2 holding a valid Radiographic Interpreter (Weld) level 2 qualification from a scheme meeting the requirements of BS EN ISO 9712. They must confirm that the quality of the radiographs meets the requirements of this specification before submission to the Employer. 9.3 Radiation Protection The exposure of the human body to X-rays or Gamma-rays can be injurious, therefore it is essential that when radiographic equipment is used, adequate precautions are taken to protect all persons in the vicinity of the operation. Radiography must not be undertaken unless the radiographers fully comply with the requirements of The Ionising Radiation Regulations (IRR99) and the recommendations given in the Approved Code of Practice and Guidance (Working with ionising radiation). Attention is drawn to the need for audible and visual warning arrangements. Regular monitoring of radiation levels by the radiographers is required. 9.4 Radiation Safety Monitoring NGN has an obligation to its employees, contractors and members of the public to monitor the standard of radiological safety maintained by radiographic contractors on NGN sites. The items listed in Appendix B must be regularly monitored by NGN or their representative and the results recorded. 9.5 Radiographic Procedures 9.5.1 Radiographic examination of fusion welded circumferential butt welds in steel pipes must be carried out as described in BS EN ISO 17636-1, using techniques 7.1.4, 7.1.3, 7.1.8 or 7.1.6 (i.e. the preferred order), as appropriate. 9.5.2 Where fittings are welded to other fittings or to short lengths of pipe, technique number 7.1.3 of BS EN ISO 17636-1 may be used. When using technique 7.1.3 then the number of exposures required must be calculated using BS EN ISO 17636-a figure A.1. 9.5.3 Where BS EN ISO 17636-1 technique No 7.1.6 is used for pipe to pipe weld exposures, a minimum of three exposures 120° or 60° apart in that order (i.e. the preferred order), must be made. Pipe to fitting and fitting-to fitting butt welds will require a greater number of exposures to achieve satisfactory coverage. Superimposed images are not permitted. 9.5.4 When using technique 7.1.8 then the number of exposures required must be calculated using BS EN ISO 17636-1 figure A.2. Where technique 7.1.8 is used to examine pipeline butt welds, the 6 o’clock weld location must be positioned in the centre of the diagnostic film length. 9.5.5 When a complete circumferential weld is radiographed in a single exposure with the source inside the pipe (technique 6.1.4), at least one of the image quality indicators (IQI) must be placed outside the pipe at the 6 o’clock location. When a circumferential weld is radiographed using multiple exposures, an IQI must be located at each end of the diagnostic film length with the thinnest wire outermost. 9.5.7 For examining branches of the forged set-in type, panoramic type techniques, where the complete weld is examined in one exposure, are not permitted. The weld must be examined in separate exposures with the X-ray focal point positioned at normal incidence to the area being examined to within 13 Uncontrolled when printed / after download NGN/SP/NDT/2 5 as shown in Figure 1. Either the single-wall, single-image or the double-wall, single-image technique should be used. When the single-wall, single-image technique is used (technique 6.1.3), the film must be placed against the inner pipe or fitting surface with the X-ray focal spot on the outside. The focal-spot-tofilm distance must be not less than 690 mm. When access and/or other fittings prevent correct alignment of the beam, the double- wall, single-image technique (technique 6.1.8) must be used. Branches not greater than 150 mm nominal bore require a minimum of four exposures equidistant round the weld circumference. Branches of 200 mm nominal bore require a minimum of six exposures equidistant round the circumference. Exposures of larger branches, or branches with proportions significantly different from those shown in Figure 1, must be subject to agreement with the Employer. Figure 1 – X-Ray Focal Spot Positioning A= Film Centres (4 Film Exposures) B= Focal Spot 9.6 Radiography Density 9.6.1 For pipe and fittings of the same nominal wall thickness, the radiographic density measured immediately adjacent to the weld reinforcement must be within the range 2.5 to 3.5. 9.6.2 For pipe to pipe joints between pipes of different nominal wall thicknesses, where the thicker pipe has been transitioned to match the bore of the thinner pipe, the radiographic density measured immediately adjacent to the weld reinforcement must be within the range to 2.5 to 3.8. 9.6.3 Where the difference in wall thickness between the components being joined is substantial, i.e. certain types of fitting to pipe and fitting to fitting, the radiographic density measured in sound weld 14 Uncontrolled when printed / after download NGN/SP/NDT/2 metal (typical of the average weld and reinforcement through thickness) must be within the range 2.3 to 3.3. If a film density within this range cannot be achieved in one exposure, either a sandwich technique using fine grain, high contrast film and ultra-fine grain, high contrast film (technique 6.1.9), or two separate exposures of the weld must be made. 9.7 Approved Radiographic Procedures All radiographic procedures, details of the radiographic techniques and test radiographs* for each procedure must be submitted to the Employer for approval prior to production radiography commencing. The procedure details must include the following: a) b) c) d) e) f) g) h) i) j) k) Technique Type of equipment and kV rating. Type of film. Intensifying screens. Shielding. Geometric relationship defined by sketch. Limit of film coverage. Tube voltage and exposure. Material thickness range. Type of image quality indicator and positions. Processing. Note: An example radiographic procedure specification is given in Appendix E. * To qualify a radiographic procedure three individual radiographs must be made of each weld configuration covered by that procedure (preferably using the procedure test weld), this is used to establish consistency of the radiographic procedure. The x- ray equipment must be re-positioned for each exposure. 9.8 Approved Radiographic Procedures 9.8.1 All unexposed film must be stored in a clean, dry place where the surrounding conditions must not detrimentally affect the emulsion. At the discretion of the Employer, the radiographic contractor must demonstrate to the Employer’s satisfaction that the film can be processed, using the site facilities, to have a fog level not greater than 0.3. 9.8.2 The film must be processed such as to allow storage without deterioration for a minimum of three years. Adequate washing of the processed film is required to reduce residual fixer content. Where the quantity of work allows, a Thiosulphate test is required on 1 film in 45 and the results recorded in a register held at site. The procedure for this test must be submitted to the Employer for approval prior any work commencing. 9.8.3 If radiographic images are to be stored digitally on compact disc, the proposed method of storage, retrieval and the definition and sensitivity of the recorded image must be approved by the Employer prior to storage commencing. 15 Uncontrolled when printed / after download NGN/SP/NDT/2 Any software required to view the results must be included on the data disc. Any software licenses must be agreed prior to production welds being examined. The software version/number must be clearly visible on all display presentations. The software must be capable of displaying the retrieved radiographic image in the original format viewed by the interpreter at the time of sentencing. 10. Manual Ultrasonic Examination of Welded Joints 10.1 General When required by the Employer, manual ultrasonic examination must be applied to welds as described in BS EN ISO 17640 and this specification. 10.1.1 Before ultrasonic examination is carried out, scanning surfaces must be thoroughly cleaned and weld spatter removed to permit examination, as required in BS EN ISO 17640, Clause 8. In order to prevent pipe wall thinning the pipe surface must not be prepared by dressing. 10.1.2 Ultrasonic examination of welded joints must be undertaken as required by the Employer. This must include: a) Welds between pipes with wall thickness 8mm and greater. b) Welds not subject to hydrostatic pressure test (golden welds). c) In support of radiographic interpretation or to confirm other indications. 10.2 Ultrasonic Equipment The flaw detector and probes will be in accordance with BS EN ISO 17640, i.e. A-scan presentation capable of working at a test frequency of 1 MHz TO 6 MHz. 10.3 Ultrasonic Equipment Performance The combined performance of the ultrasonic equipment must be checked in accordance with BS EN 12668 and must be comply with the permitted tolerances for each function. 10.4 Ultrasonic Flaw Detector Calibration Calibration of the flaw detector, cable and probe combination must be carried out prior to each ultrasonic examination using the standard test block as described in BS EN ISO 2400 or BS EN ISO 7963. 10.4.1 Calibration of the probe beam angles must be carried out at least daily using the test block. The flaw detector time base and amplification must be calibrated before examining each weld. 10.5 Ultrasonic Weld Examination A probe of 60 to 70 refraction angle, 4 MHz to 5 MHz frequency with a crystal area of approximately 80mm2 must be used. When examining for lack of side fusion or lack of inter-run fusion, the weld must be scanned in a zig-zag manner, the probe being moved between the weld reinforcement and one skip distance. The beam must be directed at the weld length normally. The weld must be scanned from both sides, 16 Uncontrolled when printed / after download NGN/SP/NDT/2 10.5.1 The reference level must be set using Technique 1 described in BS EN ISO 17640 section 10.2. All indications greater than 20% DAC must be investigated and reported. Indications greater than 50% DAC or 6dB must be reported and evaluated. The position, length (depth within the weld if required) and amount by which the DAC is exceeded must be recorded. It is recommended that reference blocks be representative of the material under test, i.e. same grade, curvature, surface finish and wall thickness. Notes: 1) Where an indication is investigated, it is sufficient to confirm that a flaw reflector is present and does not exceed 50% DAC. 2) Where a flaw reflector exceeds 50% DAC the dynamic characteristics of the flaw must be fully evaluated. Pipe Thickness Examination Level Notes 8mm<t<15mm A T-scan required 15mm<t<40mm B T-scan required 10.6 Qualification of Personnel Operators must be qualified, as a minimum, to Ultrasonic Testing (Weld) level 2 qualification from a scheme meeting the requirements of BS EN ISO 9712. 10.7 Ultrasonic Examination Procedure Written ultrasonic examination procedures must be submitted to the Employer for approval prior to testing commencing. Each procedure must satisfy the requirements of BS EN ISO 17640 clause 5.3 and specify the relevant information required in Clause 5.2. 10.8 Examination of Pipe Material All pipe which is to be cut back must be examined visually prior to and after cutting. The pipe material around planned cut-outs for nozzles, branches and cut pipe ends for pipe wall thicknesses greater than 6.1 mm, must be ultrasonically examined for 100 mm each side of the proposed cut line to ensure freedom from unacceptable laminations. This must be done as described in BS EN 10160 using method 5.1a to calibrate the test equipment. In such cases the probe must be moved in a zig-zag manner in a zone 100 mm wide. 11. Automatic Ultrasonic Examination for Pipeline Automatic Ultrasonic Testing (AUT) of pipeline must be carried out in accordance with the requirements of Appendix D. 12. Phased Array Ultrasonic Examination for Pipework Phased array ultrasonic testing (PAUT) may be performed in lieu of radiography for pipework construction. The PAUT must be carried out in accordance with the requirements of Appendix D. 17 Uncontrolled when printed / after download NGN/SP/NDT/2 13. Magnetic Particle Flaw Detection 13.1 General When required by the Employer, Magnetic Particle Inspection (MPI) as described in BS EN ISO 17638 must be used. Inspection personnel must be qualified to Magnetic Particle Testing (Weld) level 2 qualification from a scheme meeting the requirements of BS EN ISO 9712. The preferred method of magnetising components must be by AC electromagnetic yoke or the coil technique, the prods method must not be used. Permanent magnets must not be used unless specifically agreed and approved by the Employer. Permanent magnets should only be considered for use where access precludes the use of an AC electromagnetic yoke. Only wet detection media methods must be used. 13.2 Equipment Performance The overall performance of the Magnetic Particle Examination technique must be confirmed prior to use. Either representative test pieces containing real or artificial flaws, or portable shim type flux indicators must be used. AC electromagnetic yokes must demonstrate a lifting power of 4.5 kg and a pull off force equivalent to 2.25 kg at a maximum pole spacing of 200 mm. Portable flux indicators must not be used with permanent magnets. A guide to the adequacy of permanent magnets with a pole spacing greater than 75 mm, is that the magnet should demonstrate a lifting power of 18 kg and a pull off force equivalent to 9 kg. The maximum pole spacing permitted is 50 mm and the pull off force must be demonstrated on a sample of the actual component thickness and material under test. The methods to be used to confirm overall performance of the technique and frequency of test must be stated on the approved Magnetic Particle Examination procedure. 13.3 Magnetic Particle Inspection Procedure A specific examination procedure must be submitted for the Employer’s approval prior to commencement of any MPI. 13.3.1 When examining welds, the technique used must ensure full coverage of both weld and heat affected zones. Magnetising techniques as described in BS EN ISO 17638 section 5.6.2 must be used. 13.3.2 Welds must be examined in the as-welded condition, apart from set-in fittings (i.e. sweepolet type). The internal (where possible) and external weld reinforcement of sweepolet type fittings must be dressed to avoid false or misleading indications. When required by the Employer, local dressing of other weld types must be made, to permit accurate interpretation of indications. 13.3.3 Demagnetisation of the weld or material surfaces following MPI is not generally required. However, consideration should be given to component demagnetisation should excessive magnetism affect subsequent Operations (the NGN/SP/P/2 specification gives guidance on demagnetisation techniques for pipeline applications). 18 Uncontrolled when printed / after download NGN/SP/NDT/2 13.3.4 The results of all MPI examinations must be recorded and be assessed in accordance with the relevant welding standard or specification. 14. Dye Penetrant Flaw Detection 14.1 General When required by the Employer, Dye Penetrate Inspection (DPI) as described in BS EN ISO 3452-1 must be used. Inspection personnel must be qualified to Dye Penetrate Inspection level 2 qualification from a scheme meeting the requirements of BS EN ISO 9712. 14.2 Dye Penetrant Inspection Procedure A specific examination procedure must be submitted for the Employer’s approval prior to commencement of any DPI 14.2.1 Mechanical pre-cleaning must not be carried out. 14.2.2 The results of all DPI must be recorded and assessed to the relevant specification. 15. Non-Destructive Testing of Repaired Production Welds 15.1 General Defective welds that have been repaired must be re-examined visually and by non-destructive testing. 15.1.1 Repair areas must be examined using radiography or a manual ultrasonic technique in accordance with this specification. If the inspection is carried out using manual ultrasonic methods then a separate procedure must be approved by NGN prior to the work commencing. 15.1.2 If the repair is conducted by fully removing the defective weld and re-welding by an automated or fully mechanized welding system, the new weld may be examined using AUT to these procedures. 16. Records The results of all non-destructive testing examinations must be recorded on an appropriate record form. The examination report must include, as a minimum, the information required by the appropriate national standard and this specification. Examples of record forms are included in Appendix E. 19 Uncontrolled when printed / after download NGN/SP/NDT/2 Appendix A References IGEM/TD series Recommendations on Transmission and Distribution Practice S.I. No. 3232 The Ionising Radiations Regulations including the IRR 1999 S.I. No. 1713 The Confined Spaces Regulations BS EN ISO 9001 Quality Management Systems BS EN ISO 138588 Non-Destructive Testing of Welds. Ultrasonic Testing. Use of Automated Phased Array Technology BS ENO ISO/IEC/170202 Conformity assessment – Requirements for the Operation of Various Types of Performing Bodies Performing Inspection. BS EN ISO 9712 Non-Destructive Testing – Qualifications and Certification of NDT Personnel BS EN ISO 17636-1 Radiographic Examination of Welded Joints BE EN ISO 19232-1 Non-Destructive Testing. Image Quality of Radiographs. Determination of the Image Quality using Image Quality Indicators. BS EN ISO 19232-2 Determination of the Image Quality Value using Step/Hole-Type Image Quality Indicators BS EN ISO 17638 Magnetic Particle Testing BS EN ISO 3452-1 Penetrant Testing – General Principles BS EN ISO 3452-2 Penetrant Testing – Testing of Penetrant Materials BS EN ISO 3452-3 Penetrant Testing – Reference Test Blocks BS EN ISO 11699-1 Industrial Radiographic Film Classification of Film Systems for Industrial Radiography BS EN ISO 17637 Visual Testing of Fusion-Welded Joints BS EN ISO 17640 Ultrasonic Testing. Techniques, Testing Levels and Assessment BS EN ISO 16828 Non – Destructive Testing. Ultrasonic Testing. Time-of-Flight Diffraction technique as a Method for Detection and Sizing of Discontinuities. 20 Uncontrolled when printed / after download NGN/SP/NDT/2 BS 7910 Guide on Methods for Assessing the Acceptability of Flaws in Metallic Structures BS EN 12668 Part 2 Characterisation and Verification of Ultrasonic Equipment. Probes. BS EN 10160 Ultrasonic Testing of Steel Flat Product of Thickness Equal or Greater than 6mm (Reflection Method) BS EN ISO 2400 Specification for Calibration Block No.1 for Ultrasonic Examination of Welds BS EN ISO 7963 Specification for Calibration Block No. 2 for Ultrasonic Examination of Welds BS EN 1330 Non-Destructive Testing – Terminology – Part 1 List of General Terms BS PD 8010-1 Pipeline Systems – Part 1: Steel Pipelines on Land – Code of Practice NGN/PR/NDT/1 Procedure for Carrying Out Non-Destructive Testing of Plant and Equipment NGN/SP/P/2 Specification for Welding of Landing Pipelines and Installations Designed to Operate at Pressures Greater than 7 Bar. (Supplementary to BS 4515-1) NGN/PM/SHE/18 Confined Spaces IRR99 Ionising Radiations Regulations 1999. 21 Uncontrolled when printed / after download NGN/SP/NDT/2 Appendix B Management of Site Radiography B1. Scope This procedure identifies the controls necessary for the management of site radiography. Adherence to these requirements must be audited as per the requirements of construction checklist Appendix C. This procedure must also be used to determine the most appropriate method of conducting radiography. The procedure provides a decision tree, which must be used to determine whether items requiring radiography testing should be transported off-site to a purpose-built enclosure for radiography. Implementation of these requirements does not imply that sufficient data has been included to demonstrate compliance with Ionising Radiation Regulations, it is the responsibility of the Radiographic Subcontractor and the main works contractor to ensure these regulations are complied with in full. B2. Introduction The main requirement of the Ionising Radiations Regulations is that NDT contractors should adopt working practices capable of keeping radiation exposures of employees as low as reasonably practicable. The HSE guidance on complying with Ionising Radiations Regulations clearly states that if work involves routine radiography of readily moveable articles it is nearly always reasonably practicable to carry it out in an adequately shielded enclosure or cabinet. Where practicable, using a suitable shielded enclosure must always be the first choice for radiography work. This enclosure can either be constructed on site or articles can be transported to a purpose-built enclosure off site. The flowchart in figure E1.0 of this Appendix provides a process which demonstrates that the selected method for conducting radiography keeps radiation exposures of employees as low as reasonably practicable. Where site radiography is the only practicable option the objective of this document is to provide best practice guidelines to enable radiographic subcontractors to undertake site radiography in a safe, consistent and auditable manner across all projects. B3. Roles and Responsibilities The main responsibility for the implementation of this procedure lies with the specialist Radiographic Sub- contractor and the main works Contractor. Adequate information on radiation safety must be included within the contractor’s site induction talk and relevant toolbox talks must be provided to personnel likely to be in the vicinity of radiographic works. All personnel are responsible for ensuring that site radiography is undertaken in a safe manner, any deviation to the planned safe system of work must be reported immediately to the project supervisor for 22 Uncontrolled when printed / after download NGN/SP/NDT/2 rectification. A formal audit should be undertaken to ensure these requirements are implemented as per the checklist in Appendix B. B4. Radiography Options Where radiography is required during the construction or modification of a Pipeline, AGI, Compressor Station or Terminal the following options are available to the NDT contractor: a) Radiography is carried out in-situ with suitable local shielding and boundary monitoring. b) Radiography is carried out on sire in a controlled area with suitable local shielding and boundary monitoring c) Radiography is carried out on sire in a temporary enclosure. d) Articles are transported off site where radiography is carried out in a purpose-built enclosure. B5. Radiography Decision Tree The flowchart in Figure B.1 should be used to determine which is the most appropriate method of carrying radiography. The size and transportability of pipework fabrications will vary throughout a project, therefore, to take account of this the flowchart will need to be run more than once. The factors which must influence the selection of the most appropriate radiography method for each stage of a project are: a) The ability to pre-fabricate and radiograph pipework off site. b) The transportability of pipework fabricated on site, which can be broken down further as: I. Fabrications which are only transportable off site; and II. Fabrications which are only transportable around the site. c) The proximity of a purpose-built radiography enclosure to the construction site. d) The availability of a controlled safe area for radiography on the construction site. B6. Requirements B6.1 Submission of Documentation for Client Review B6.1.1 Project Specific Local Site Rules As per IRR99 this must include the production of prior risk assessments and the methodology for dealing with the risks, that must as a minimum identify the following; • • 6.1.2 Generic Risks – generally found on all projects: ▪ Road crossings ▪ Public footpaths Unique Risks – specific features that are unique to the project: ▪ Street works ▪ Working in the vicinity of high-density housing or schools etc. ▪ Specific risks associated with working in AGI’s or compressor stations Technique Sheers Technique sheers are required for each technique to be used. 23 Uncontrolled when printed / after download NGN/SP/NDT/2 B6.1.3 Method Statement NGN/Procedures The Method Statement should identify the practical aspects of undertaking site radiography including: • • • • • • • Equipment used; Equipment ratings; Type of film; Storage of film; Film processing; Handling of chemicals; and Manual handling of radiography equipment B6.1.4 HSE Notification A copy of the greater than 7 day notification sent to HSE prior to site radiography being undertaken, advising them of location and timescales involved. B6.2 General Issues B6.2.1 Storage of Processed Films Processed film for record keeping purposes must be stored in a separate location from the dark room. B6.2.2 Storage of Sealed Sources When not in use, sealed sources must be stored in a suitable approved transport container, secured within a secondary non-flammable container identified with appropriate radiation signs. B6.2.3 Radiation Signs Appropriate radiation signs must be clearly displayed on the outside of the storage area containing the sealed source. B6.2.4 Contact Details The Radiation Protection Supervisor’s name and contact number must be posted on the cabin where the sealed source is stored and on the project notice board(s). B6.2.5 Transportation of Sealed Sources When sealed sources are in transport on the spread, relevant radiation signs must be posted on both sides and to the rear of the vehicle. When the source is in the vehicle and is left unattended for any reason, the vehicle must be left in a secure state to prevent unauthorised access. B6.2.6 Fire Extinguishers Appropriate fire extinguishers must be available within the darkroom, sealed source storage area and site vehicles. B6.2.7 Disposal of Processing Chemicals Unless agreed in writing with the EA/SEPA, no disposal of processing chemicals or wash water must be dispersed to ground. 24 Uncontrolled when printed / after download NGN/SP/NDT/2 B6.2.8 Lifting Equipment All lifting equipment (slings, belts, chains etc) must be suitably controlled, identified and have current test certification. B6.2.9 Inspection and Test Equipment All inspection and test equipment used to provide primary measurement must be uniquely identified, subject to formal control and calibrated to a known national standard. B6.2.10 QMS The Radiographic Subcontractor must implement and maintain a quality management system in accordance with ISO 9001 and must be accredited to ISO/IEC 17020. B6.2.11 Daily Checks All equipment must be maintained in a serviceable condition and daily equipment checks must be carried out on cables, crawlers and X-ray equipment. B6.4 Control of Site Activities B6.4.1 PPE All personnel must wear basic construction PPE whilst on the spread (hard hat, hi-vis vest, protective footwear, overalls), and additional PPE may be required as identified within applicable risk assessments. B6.4.2 TLDs/Film Badges Named Thermoluminescent Dosimeter (TLDs) / film badges must be worn at all times by classified workers and must be clearly visible at all times whilst on the spread, under no circumstance are they to be left in overall pockets, in crew cabs etc. Consideration should also be given to the use of electronic dose meters / alarms. Unnamed (i.e. spare numbered) TLD must only be accepted during the first month of a new worker’s contract period. B6.4.3 Precautions Barriers must prevent access from both ends of the spread to the controlled area. The following precautions must also be included, radiation signs, warning lights, RPS contact details at each end. The spoil heap and right of way fencing must provide natural boundaries on the other sides, however where there is a likelihood of public access, e.g. footpaths, playing fields etc, all relevant point of access must have barriers and relevant signage. It is the responsibility of the radiographic subcontractor to ensure the requirements of IRR99 are complied with. B6.4.4 Monitoring of the Controlled Area No amount of precautions should replace the importance of vigilance and proactive monitoring of the controlled area, to ensure that corrective action can be taken in the event of persons not involved in the work approaching the controlled area. The radiographic subcontractor must ensure that monitoring and patrolling of the controlled area is undertaken on a routine basis and this requirement should be included for in the Local Rules. 25 Uncontrolled when printed / after download NGN/SP/NDT/2 B6.4.5 Recording Boundary Dose Rates Boundary dose rates must be recorded in a formal manner identifying the section number and weld numbers of the location worked for reference. Formal measurement must be undertaken for the first production exposure on each day, details of person undertaking the test and equipment used must be recorded. Formal monitoring must be carried out for each subsequent controlled area and verification that it meets IRR99 requirements must be made. Any change to the size and type of the controlled area will require formal measurement to be undertaken e.g. work in the AGI etc. B6.4.6 Record Keeping The responsible person must undertake daily mobile sealed source accounting and formal records must be kept to verify this. As a minimum the record must identify source number, location, date and time of inspection, details of person undertaking inspection. B6.4.7 Movement Logs Sealed source movement logs must be kept to identify location of sealed source, this must be completed when the source is issued for use, as a minimum the record should contain, source number, date and time issued, recipient of source, date and time returned. B6.4.8 Spare Accessories Spare bulbs and batteries must be available with the crew(s) for all safety critical equipment. B6.4.9 Suitable Shielding Where risk assessment requires, suitable shielding must be available with the crew(s). B6.4.10 Spare Calibrated Radiation Detector A spare calibrated radiation detector must be available with the crew(s) (it is not acceptable to rely on personnel monitors as the spare). B6.4.11 Mobile Phones All radiographic crew(s) must have access to a mobile phone or two-way radio for contact purposes. B6.4.12 PAT Testing All relevant portable electrical equipment must be PAT tested. B6.4.13 Audits As a minimum the RPS must undertake a formal documented audit on all crews within 5 days of commencement of site radiography to ensure safety controls are in operation and remain effective. B6.5 Audit Records/Documentation The following records/documentation must be available for reference during on site audits. If any of the following are not present on site, work must not be allowed to commence / continue: • • • Certificate of registration for radioactive source’s (Environment Agency) HSE notification of site radiography document Local rules and risk assessment (with crews) 26 Uncontrolled when printed / after download NGN/SP/NDT/2 • • • • • • • • • • • • • Technique sheets (with crews) Procedures/method statement (with crews) Controlled copy of IRR99 Controlled copy of NGN/SP/P/2 Passbooks for outside workers (if applicable) Calibration records for inspection and test equipment Sealed source wipe test results (2 yearly) Lifting equipment register and certification Daily source accounting records Source movement log Records of boundary dose rates Records of RPS crew audits Relevant personnel training records (RPS training, Driver training, QMS inductions, ISO 9712 approvals, Safety passport etc) 27 Uncontrolled when printed / after download NGN/SP/NDT/2 Radiography Decision Tree Start 7 1 Yes Pre-fabricate pipework offsite Is the pipework to be pre-fabricated offsite? No 9 2 Can the pipework be moved around site? Yes Is the pipework in situ or not transportable from site? No Yes 3 10 No No Is the risk/cost of transporting items offsite greater than constructing a temporary enclosure onsite? Will the pipework fit within a temporary enclosure? Yes Yes 4 No 11 Carry out radiography in-situ with suitable local shielding Is the project of sufficient value/duration that it is reasonably practicable to construct a temporary enclosure onsite? Yes No 5 Carry out radiography in a safe area with local shielding 6 8 Carry out radiography in a temporary enclosure onsite Transport items for radiography to a purpose built enclosure offsite Produce appropriate method statements and risk assessments 28 Uncontrolled when printed / after download NGN/SP/NDT/2 B7. Flowchart Explanation Notes 1) Where this is feasible pipework should be pre-fabricated off site and radiographed in a purpose built enclosure. 2) Some pipework can only be constructed in situ and therefore will not be transportable from site. Other pipework fabricated on site will either be too large or heavy to be reasonably practicable to transport off site. 3) Where pipework fabricated on site is transportable the cost of transporting to a purpose-built enclosure for radiography should be compared against the cost of constructing a temporary enclosure on site. Pipework fabricated on site should always be transported off site to a purpose-built enclosure when this is demonstrated as the least cost option unless it can be demonstrated that transportation off site actually presents a greater risk to personnel from for example the lifting Operations required. 4) As assessment should be carried out to determine whether it is reasonably practical to construct a temporary enclosure on site. Consideration will need to be given to the duration/value of the project and the amount of radiography which must actually be taking place on site. To avoid the construction of a temporary enclosure it will need to be demonstrated that the cost is grossly disproportionate to the reduction in risk which will be gained. 5) Where the assessment in 4. Above concludes that radiography is to be carried out on site in a controlled area the appropriate HSE guidance should be followed to ensure that the radiation exposures of employees is kept as low as reasonably practicable. 6) Where the assessment in 4. Above concludes that a temporary enclosure must be constructed on site to carry out radiography, the temporary enclosure should be constructed to the appropriate HSE guidance giving consideration to the installation of appropriate interlocks which prevent or terminate an exposure if the door of the enclosure door is opened. 7) Purpose built enclosures should be constructed to the appropriate HSE guidance giving consideration to the installation of appropriate interlocks which prevent or terminate an exposure if the door of the enclosure is opened. 8) Although it may not be practicable to transport some items off site because of the size of the fabrication, these items should still be radiographed in a controlled area on sire if they can be moved around site. 9) Where pipework will fit within a temporary enclosure it should be transported to such an enclosure for radiography if it is available on site, otherwise it should be moved to a controlled area for radiography. 10) Where items fabricated on site cannot be moved because they are constructed in situ the only reasonably practicable option should be to conduct the radiography in situ providing the appropriate local shielding. Consideration will have to be given to conducting the radiography out of hours to ensure that the radiation exposures of employees is kept as low as reasonably practicable. 29 Uncontrolled when printed / after download NGN/SP/NDT/2 Appendix C Site Radiation Safety Monitoring Checklist and Report Sheet Site Radiation Monitoring Checklist and Report Sheet Project: Date: Location: Radiographic contractor: a General notes: Radiography is a hazardous activity. NGN has a responsibility to members of the public, its own employees and other contractors to ensure that site radiography is carried out in a safe manner. No one should enter ‘controlled or supervised radiography zones’ without the permission of the Radiographer and only when it is safe to do so. ‘Classified personnel ‘are permitted to enter these zones during an exposure. b Only suitably trained personnel must monitor and report on radiation levels and site radiation safety issues. Prior to starting radiography on site, a review of the appropriate preparations required must be made using this checklist. Where work is ongoing, regular monitoring of site radiography is required. Should any of the checks reveal that the work cannot be carried out in a safe manner and in accordance with the Regulations (or any related documentation or procedures), work must not commence or cease immediately until rectified. The use of this checklist by NGN does not relieve the Radiation sub-contractor of their duties and responsibilities under the Ionising Radiation Regulations. This record sheet should be circulated to the Project Manager, the Site Occupier and the Site Safety Officer as appropriate. c d These records should be retained for the duration of the contract unless there are other requirements to keep them longer. Abbreviations used: e HSE RPS Health & Safety Executive Radiation Protection Supervisor Item 1 2 3 RCD TLD Residual Current Device Thermo-luminescence Dose meter Question Finding Authorisation for site radiography ✓/X Comments Has prior authorisation been granted by the HSE for industrial radiography using specified practices? Is there a copy of the authorization document available? (A generic authorisation from the HSE Internet website may suffice). Have the HSE been notified that site radiography is to take place? (28 days notice may be required). 30 Uncontrolled when printed / after download NGN/SP/NDT/2 4 Have the HSE acknowledged receipt of notification? (The HSE may not always provide documentary evidence of receipt of notification). Radiographer 5 6 7 8 9 Are the radiographers qualified to the ISO 9712 approval scheme or to an approved equivalent? Has the RPS been identified in the local rules? Is (are) the RPS(s) in attendance? Is all equipment in good visual condition? Are all cables and connectors in good condition? Finding ✓ Item checked - Satisfactory Item checked - Unsatisfactory NDT2 Sheet 1 of 3 Site Radiation Monitoring Checklist and Report Sheet (continued) Item Question 10 Is the power generator earthed? 11 Is an RCD fitted and operable? 12 Is local shielding required? 13 Are local shielding materials available? Finding ✓/X Comments Barriers, Warning Notices and Signals 15 Have barriers been erected at the correct distance? Are the correct warning notices being displayed? 16 Are spare warning boards available? 17 Is the boundary patrolled? 14 18 19 20 21 22 Are records of boundary dose rate monitoring available? Is the x-ray control panel key adequately controlled? Are audible/visual warning signals available and working satisfactorily? Are spare light bulbs etc. available? Have all site staff been briefed on the dangers associated withradiographic 31 Uncontrolled when printed / after download NGN/SP/NDT/2 Operations (Safety induction). Dosemeters 23 24 25 26 27 Are film badges or TLD being worn by the radiographers? Are the TLD’s named, or if numbered are they traceable to the wearer? Are badge holders in good condition? Are surplus badges available on site? (If specified on contingency plan) Are TLD readers in use? (If specified on contingency plan) Risk assessment, Local rules, Contingency plans 30 Has a prior risk assessment been made? Is a copy of the risk assessment available? Are local rules and contingency plans available on site? 31 Are the local rules site specific? 32 Are the radiation employees familiar with the above documentation? (see28-31) 28 29 Radiation Monitor 33 34 35 36 Is there a monitor available and suitable for each source in use? IS there a spare monitor available? Are the monitors in current calibration with valid certificates? Are the monitors in good condition without obvious damage? Finding ✓ Item checked - Satisfactory Item checked - Unsatisfactory NDT2 Sheet 2 of 3 Site Radiation Monitoring Checklist and Report Sheet (continued) Item Question Finding ✓ /X Comments Sealed sources Note: It is not general NGN policy to use sealed sources. However, where they are used on site, in addition to the above list, the Radiographic sub-contractor must confirm the following items. 37 Are the monitor battery levels satisfactory? 38 Are spare batteries available? 32 Uncontrolled when printed / after download NGN/SP/NDT/2 39 40 41 42 43 44 45 What type(s) of radioactive isotope (s) will be used? Are the source container’s design, construction and maintenance appropriate? Have test to detect leakage been regularly carried out and recorded? Is a record sheet (updated daily), which shows the type, strength and location of each radiographic isotope in site available? Are all sealed sources stored and transported on site in accordance with the Ionising Radiations Regulations? Are contingency plans included in the local rules in the event of loss or damage to a radiographic isotope? Are all emergency tools and equipment listed in the contingency plan available for use? Finding ✓ Item checked - Satisfactory Item checked - Unsatisfactory Notes: Print Name Signature NGN Auditor or representative: 33 Uncontrolled when printed / after download NGN/SP/NDT/2 Appendix D Requirements for Automatic Ultrasonic Inspection (AUT) for Pipeline Fabrication/Construction and Phased Array Ultrasonic (PAUT) for Pipework Construction D1. Scope D1.1 The specification details the minimum NGN requirements for an Automatic Ultrasonic Testing (AUT) system, AUT procedure approval and AUT system operator/interpreter competency for inspection during pipeline construction. D1.2 Any AUT system and examination procedure proposed for use must, as a minimum, meet the requirements of this specification and be approved by NGN prior to any production weld examination being carried out. D1.3 This specification also includes the minimum NGN requirement for inspection of pipework welds during fabrication/construction using Phased Array Ultrasonics (PAUT). D1.4 Section D4 of this specification may also be used for PAUT on existing pipework. To perform PAUT on existing welds, the scanning surfaces of the existing pipework must be even and free from foreign matter likely to interfere with probe coupling (e.g. rust, loose scale, weld spatter, notches and grooves). Unevenness of the test surface must not result in a gap between probe and test surface greater than 0.5 mm. D2. References BS EN 12668-1 Non-destructive testing – Characterisation and verification of ultrasonic examination equipment – Part 1: Instruments BS EN 12668-2 Non-destructive testing – Characterisation and verification of ultrasonic examination equipment – Part 2: Probes BS EN 12668-3 Non-destructive testing – Characterisation and verification of ultrasonic examination equipment – Part 3: Combined equipment BS EN ISO 16828Non-destructive testing. Ultrasonic testing. Time-of-flight diffraction technique as a method for detection and sizing of discontinuities DNV-OS-F101 Automated Ultrasonic Girth Weld Testing Appendix E DNV-RP-F118 Pipe Girth Weld AUT System Qualification and Project Specific Procedure Validation BS 7910 Guide to methods for assessing the acceptability of flaws in metallic structures EN ISO 13588 Non-destructive testing of welds - Ultrasonic testing - Use of Automated Phased Array Technology 34 Uncontrolled when printed / after download NGN/SP/NDT/2 DNV-OS-F101 Appendix E Automated Ultrasonic Girth Weld Testing DNV-RP-F118 Pipe Girth Weld AUT System Qualification and Project Specific Procedure Validation BS 7910 Guide to methods for assessing the acceptability of flaws in metallic structures NGN/SP/P/2 Welding of Land Pipelines and Installations Designed to Operate at Pressures Greater than 7 Bar (Incorporating BS 4515) D3. Automatic Ultrasonic Inspection (AUT) for Pipelines D3.1 Qualification D3.1.1 Before an AUT system is used for the inspection of production welds on a pipeline then it must be qualified in accordance with DNV-RP-F118 for the application it is intended to be used for. The qualification must be based on the required performance as identified by the requirements for Probability of Detection (PoD) and sizing ability; or, alternatively, a requirement for defect rejection. The qualification programme and results must be approved by NGN. D3.1.2 The qualification is AUT system specific and will only be valid when all essential variables remain nominally the same as covered by the documented qualification. This specification does not require a new qualification to be performed provided that the documented performance, i.e. PoD and sizing ability; meets or exceeds the requirements for the specific application. D3.1.3 The following items must be agreed by NGN prior to performing the procedure qualification: • • • • The qualification block design The system sizing accuracy for defect heights The method used to determine the length of defects The proposed examination procedure. D3.1.4 Where there are any changes to the essential variable for a system, the equipment may require re-qualification to DNV-RP-F118. Essential variables must include, but are not limited to the following: • • • • • Welding method and groove geometry, including repair welds (if relevant) Root and cap probe set-up. This involves the use of hybrid systems where a combination of Phased Array technology and Pulse Echo single or dual or tandem configurations are used. Wall thickness, requiring any change in focal law set up, adding or removing legs. Pipe diameter requiring transducer curvature which may impact on length accuracy. Systems qualified on samples larger than 12” may not be readily qualified on smaller pipe diameters. Beam profile and effect of transducer curvature must be determined. Base material and welding consumables. The distinction is made for materials with substantial differences in ultrasonic response, for instance between CMn 13% Cr, 13&Cr, duplex or austenitic steels. 35 Uncontrolled when printed / after download NGN/SP/NDT/2 • • • • • Reference reflectors, e.g. change from Flat Bottom Hole (FBH) or Notches to other type of geometries. Diameter of FBH and notch depth may be reduced provided that necessary area focus and resolution is maintained. Working temperature range. System, data acquisition and data treatment. Software version (except changes affecting viewings, display or bug fixing only) System operator interpreter training and qualification. D3.1.5 Before the ultrasonic system is used for examination of production welds, the system set up must be validated. If any of the echo amplitudes from the reflectors of the calibration block deviate more than 2dB from the initial calibration, the system must not be used until acceptable corrections have been made. For an acceptable test 3 satisfactory scans and recalibrations are required. D3.2 AUT Systems D3.2.1 The ultrasonic system may use pulse echo, tandem, time-of-flight diffraction (TOFD) and/or through transmission techniques employing either fixed of phased arrays. It must have a fully automatic recording system to indicate the location of defects and the integrity of the acoustic coupling. D3.2.2 The ultrasonic probes must normally operate within a frequency range of 2.5 to 6 MHz however; it is recognised that certain systems may employ higher frequency probes. If the system uses higher frequencies then NGN must be advised. D3.2.3 The system must include probe set specifically designed to detect transverse defect indications on both the internal and external weld near surface zones. The transverse defect scanning unit does not require a complimentary TOFD scan. D3.2.4 The weld scanning direction (clockwise or anti-clockwise relative to a fixed datum) must be agreed with NGN and must be consistent for all production girth weld examination. D3.2.5 The system must have sufficient examination channels, configured so that the complete weld through thickness can be examined in a single circumferential scan. D3.2.6 The volume of weld examined by each channel must be divided into primary examination zones of a height not exceeding mm. Each examination channel must provide: • • • • • A linear A-scan presentation Adjustable gain control with maximum of 2dB steps over a range of at least 60dB One or more gates, each adjustable for start position and length Recording threshold between 5% and 100% of full screen height Signal outputs that record signal amplitude and time/beam travel distance 36 Uncontrolled when printed / after download NGN/SP/NDT/2 D3.2.7 50mm. The system must provide an overlap at the start and/or end of the scans of at least D3.2.8 The recording or marking system must clearly indicate the location of imperfections relative to the 12 o’clock position of the weld, with a +/- 10mm accuracy. The system resolution must be such that each segment of recorded data from an individual inspection channel does not represent more than 1mm of circumferential weld distance. D3.2.9 The ultrasonic examination equipment performance characteristics must meet the requirements of BS EN 12668, as appropriate. Instrument amplitude linearity must be within 5% of the ideal amplitude and must be assessed prior to qualification and production AUT commencing. Calibration certificates must be available upon request. D3.2.10 General requirements for Time-of-flight-diffraction systems: The instrument must provide a record of the TOFD D scan image; this must complement the AUT system in confirming the presence and sizing of weld defects. TOFD must not be used in place of Pulse Echo. D3.2.11 General requirements for Phased Array: Periodic verification must be performed on the function of required active elements to maintain the focal law. In addition to this, a system must be in place to prevent any unqualified alterations to agreed focal laws for the phased array AUT system. D3.2.12 If conventional transducers are used in addition to the phased array ones, for example for transverse inspection and ToFD, the information for all transducers must be available in the same set up and recording system. D3.2.13 The instrument must meet the requirements for ultrasonic instruments detailed in BS EN 12688-1. D3.3 Examination Procedure D3.3.1 Prior to the examination of any production pipeline welds the proposed examination procedure must be submitted to NGN for review and acceptance. The procedure must contain but not limited to the following: • • • • • • • • • Brief functional description of the system. Any limitations of the system with regard to material or weld features including sound velocity variations, geometry, size, surface finish, material composition etc. Transducer configuration(s), characteristics, types, coverage. Number of and height of examination zones, where relevant. Gate settings. Ultrasonic instrument, number of channels and data acquisition system. Phased Array steering system, and the transducer characteristics including the frequency, beam angle, wedge characteristics, number of elements, and pitch. Phased Array focal laws (if applicable) Recording and processing of data. 37 Uncontrolled when printed / after download NGN/SP/NDT/2 • • • • • • • • • • • • • • Couplant monitoring method. Temperature range for testing and limitations. Maximum scanning speed and direction. Reporting of indications and documentation of calibration and sensitivity settings. Description of calibration block(s) including type, size and location of all calibration reflectors. Calibration intervals. Calibration records. Identification of inspection starting point, scanning direction. Method for scanner alignment and maintenance of alignment. Transducer and overall functional checks. Height and length sizing methodology. Instructions for reporting including example of recorder chart and forms to be used. Diagram showing the weld scan zones for the weld prep to be tested. Table of indication size against signal amplitude which must be used for indication sizing. D3.4 Operators D3.4.1 Details of the contractors proposed AUT operators/interpreters must be submitted to NGN for review and approval prior to the start of any pipeline weld examination. D3.4.2 All AUT/TOFD operators and interpreters must as a minimum be qualified to Ultrasonic Testing (Weld) level 2 qualification from a scheme meeting the requirements of BS EN ISO 9712. Operators and interpreters possessing an equivalent qualification in an alternative scheme may be proposed by the contractor for consideration by NGN. D3.4.3 All operators/interpreters must be trained and competent in the use of the particular AUT/TOFD equipment that they should be expected to operate. Documentary evidence of adequate training and ongoing practical ability must be provided to NGN for each proposed operator/interpreter. NGN reserve the right to request the operators to perform blind testing using the procedure qualification test block to demonstrate their capability in using the technique. Any “missed” flaws or miscalls of either acceptable or rejectable flaws/regions may be cause for rejection of the operator. D3.4.4 Operators/interpreters of all types of AUT/TOFD equipment should be required to demonstrate under field conditions and to the approval of NGN, their application of the approved contract AUT/TOFD procedures. This must include their capability to calibrate the equipment properly, to interpret correctly the indications given by the equipment, and to clearly record and report the results of the examination, including the location, size and nature of all flaws detected. D3.4.5 Operators must not be changed without the prior approval of NGN. D3.5 Preparation D3.5.1 The scanning band must be positioned adjacent to the completed weld at the same distance used for calibration of the unit. Prior to welding, a reference line must be scribed on the pipe surface at a distance specified by the AUT contractor from the centre line of the weld. This will provide a datum to ensure band positioning within a tolerance of ± 1 mm. 38 Uncontrolled when printed / after download NGN/SP/NDT/2 D3.5.2 The scanning area must be free of spatter and other irregularities, which may interfere with the movement of the transducers, or the transmission of acoustic energy into the material. The longitudinal seam welds must be ground flush and smooth for a specified distance, normally in the range of 150 mm from the factory bevel face to ensure that no transducers are lifted from the pipe surface. The pipe coating must be cut back from the original factory bevel face for a distance of 150 mm. The internal pipe seam must be ground back 70 mm from the weld bevel to prevent interference with the ultrasonic beam during scanning. D3.5.3 The “0” starting point and the scanning direction must be clearly marked on the surface of the pipe by permanent marker or paint. D3.5.4 The location of the pipe seam welds must be identified and recorded on the final inspection report for each weld. D3.5.5 The weld and adjacent pipe must be allowed to cool to a maximum temperature of 60 °C before scanning should commence unless otherwise agreed with NGN. D3.6 Scanning D3.6.1 Acoustic coupling must be achieved using a non-toxic liquid medium. When choosing the medium, consideration must be given to the Health, Safety and Environmental impact of any materials used. D3.6.2 No residue from the liquid medium must remain on the pipe surface after the liquid has evaporated. D3.6.3 Positive confirmation of acoustic coupling during the weld examination scan is required for each weld examination. The loss of signal amplitude associated with inadequate coupling must be specified by the contractor and agreed with NGN (see section D.3.16 a). Any loss of acoustic coupling during a weld examination may require a complete re-examination of the weld (see Section D.3.16). D3.6.4 The operator must keep a logbook detailing the performance/characteristics data and identification for instruments and transducers. The logbook must be updated as changes are made, or, as additional information is gathered. The logbook must be kept at the place of inspection and be made available for review upon request. D3.6.5 Each weld must be numbered in the sequence used in the pipe tracking system as specified by the NGN inspection team. D3.6.6 Transition welds joining pipes of different wall thickness must only be examined by AUT when the thicker material is counter-bored back at least 70 mm from the weld face. D3.7 Circumferential Scanning Velocity D3.7.1 The maximum allowable circumferential scanning velocity (Vc), must be determined according to: Vc ≤ Wc * PRF/3 39 Uncontrolled when printed / after download NGN/SP/NDT/2 Where Wc is the narrowest –6 dB beam width at the appropriate operating distance of all transducers within the array, and PRF is the effective pulse repetition frequency per transducer. Or 100 mm per second whichever is the lower. D3.8 Reference Standard D3.8.1 A reference block(s) must be used to establish sensitivity, qualify the examination system and monitor the system performance on an ongoing basis. The block(s) must be manufactured from a section of (unflawed, project specific) line pipe material provided by NGN or their main contractor. D3.8.2 The AUT contractor must supply the necessary reference blocks. The design of the block(s) must be specific to the mechanised welding system weld bevel geometry and pipe thickness to be used on the project. NGN reserve the right to retain any or all reference blocks on completion of any pipeline inspection. D3.8.3 The AUT contractor must submit their design for a reference block(s), detailing the number, orientation and location of FBH and transverse EDM slot reflectors or other reflectors, to NGN for approval before manufacture. D3.8.4 Details of the specific weld geometries must be provided in order to determine the particulars and numbers of calibration blocks required, including the calibration reflectors required and their relative positions. D3.8.5 The preferred principal calibration reflectors are normally 2mm flat bottom holes (FBH) and 1mm deep surface slots. Other reflector dimensions and types may, however, be used, if it is demonstrated during the system qualification that the defect detection and sizing capabilities of the system is acceptable. D3.8.6 The calibration blocks must be designed with sufficient surface area so that the complete transducer array will traverse the target areas in a single pass. D3.8.7 The calibration block must be identified with a hard stamped unique serial number providing traceability to the examination work and the material source of supply for which the standard was manufactured. Records of the serial number, wall thickness, bevel design, diameter and ultrasound velocity must be kept and be available. D3.8.8 The machine tolerances for calibration reflectors are: a) Hole diameters b) Flatness of FBH c) All pertinent angles d) Notch depth e) Notch length f) Central position or reference reflectors g) Hole centre depth ± 0.2mm ± 0.1mm ± 0.1° ± 0.1mm ± 0.5mm ± 0.2mm ± 0.2mm D3.8.9 The lateral position of all calibration reflectors must be such that there will be no interference from adjacent reflectors, or from the edges of the blocks. D3.8.10 Dimensional verification of all calibration reflectors and their position must be performed 40 Uncontrolled when printed / after download NGN/SP/NDT/2 and recorded by an independent party. The record of this verification must be presented to NGN before pipeline production weld are examined. D3.8.11 A calibration block register must be established. The register must include all calibration blocks to be used identified with the unique serial number and include the dimensional verification records, ultrasound velocity, name of the plate/pipe manufacturer and the heat number. The register must be available for review. D3.8.12 The surface condition of the reference blocks must be made to be typical of that of the pipe ends to be AUT scanned, including any roughness due to grit-blasting, surface corrosion, painting or power brushing. D3.9 AUT/TOFD System Equipment Calibration D3.9.1 Static calibration - The system must be set-up and calibrated using the reference standard block in accordance with the AUT contractors approved procedure. D3.9.2 For each pulse echo ultrasonic transducer in each examination channel the peak signal response from the target reflector must be maximised and then adjusted to 80% full screen height (FSH). This must be the Primary Reference Level (PRE). D3.9.3 The ultrasonic transducer stand-off distance, the gain level required to attain the PRE, and the signal to noise ratio (S/N) must be recorded. D3.9.4 With each transducer positioned for the peak signal response from the calibration reflector the detection gates are to be set. The gate must start before the theoretical weld preparation and a suitable allowance must be included to allow for the width of the heat affected zone, so that complete coverage of the heat affected zone is achieved. The gate ends must be after the theoretical weld centreline, including a suitable allowance for offset of the weld centreline after welding. D3.9.5 Gate settings must be set in accordance with the AUT contractors approved procedure. The settings for gate start and gate length for each examination channel must be recorded. D3.9.6 Ideally for TOFD the time gate start should be at least 1 s prior to the time of arrival of the lateral wave and should at least extend up to the first back wall echo. D3.9.7 For phased array, the focal laws must be designed to provide a peak signal from each of the calibration reflectors as appropriate. This signal must be adjusted to the specified percentage of full screen height (FSH). D3.9.8 Dynamic Calibration – With the system optimised the reference/calibration standard must be scanned at the same travel speed at which the examination will be performed. The positional accuracy of the recorded target reflectors relative to each other must be within ± 2mm and with respect to the zero datum be within ± 10mm over the circumference. Gate settings must not deviate by more than 0.25 mm from the reference positions. D3.9.9 The output display chart / record produced during the dynamic calibration scan must confirm that all ultrasonic transducers produce an 80% FSH signal response from each calibration reflector in its correctly assigned position 41 Uncontrolled when printed / after download NGN/SP/NDT/2 D3.9.10 Subsequent system calibration charts produced during field inspection, must be comparable with the dynamic output display chart / record and must meet the set-up reference standards. D3.9.11 All calibration signals must be within the range 70 to 90% FSH, if during the dynamic field calibration, the signal falls outside this range then one of the following must apply. D3.9.12 When a signal is over 90%FSH then the results for all welds scanned since the last successful calibration must be reviewed and where an indication has been identified in the effected channel then these must be re-scanned to confirm the original diagnosis. D3.9.13 If when checking the calibration any signal falls below 70% FSH then all welds inspected since the last successful calibration scan must be re-tested unless otherwise agreed by NGN. D3.10 Calibration Frequency D3.10.1 The system must be calibrated by scanning the reference/calibration block(s) at the start of each work period and before and after the examination of each weld: • • • • • For the first 20 welds. At any change of reference/calibration block. At any change in nominal wall thickness. At any change of components. At the completion of each work period. D3.10.2 Subject to satisfactory performance and at the discretion of NGN, the frequency of calibration may be reduced to a minimum of 1 calibration scan for each 10 consecutive welds or every 1 hours whichever comes first. D3.10.3 Hard copy recordings of all calibration scans, indicating any gain changes required to maintain sensitivity, must be included as part of the final report. The last weld number examined before calibration and the time at which the calibration was performed must appear on each calibration chart. D3.10.4 The peak signal responses from each calibration must be recorded. Any gain changes required to maintain proper sensitivity must also be recorded. D3.11 Transverse Cracking Scanning must be conducted to detect the incidence of cracking which may be transverse to the weld line, the transverse defect detection channels’ sensitivity should be demonstrated using calibration slots. These should be in both the inner and outer surface of the calibration sample and of length equal to the width of the girth weld cap or root plus a further 6 mm. Their through-wall heights should be such as to guarantee detection of defect heights equivalent to 10% of the wall thickness (e.g. an N10 slot). This must be done by: 42 Uncontrolled when printed / after download NGN/SP/NDT/2 • • • Using three slots for the internal surface calibration and three slots for the external surface calibration. One of the three slots to be at 10% of the wall thickness, one to be at 10% PLUS a height margin and one to be at 10% MINUS a height margin. The height margin to be calculated so as to be equivalent to a difference in the ultrasonic beam path, between the send and receive transducers, of a quarter wavelength, at the transducer nominal frequency. The system sensitivity must be set at 9db above that required to give a signal of 80% of full screen height from the largest signal of the three slots. D3.12 Repairs Defective welds that have been repaired must be re-examined visually and by non-destructive testing. Repair areas must be examined using radiography or a manual ultrasonic technique in accordance with this specification. If the inspection is carried out using manual ultrasonic methods then a separate procedure must be approved by NGN prior to the work commencing. If the repair is conducted by fully removing the defective weld and re-welding the new weld may be examined using AUT to the agreed procedure. D3.13 Acceptance/Rejection Criteria D3.13.1 Before any inspection using this procedure is performed, the criteria for weld defect acceptance must be agreed with NGN. For normal pipeline projects this should be obtained by using an Engineering Critical Assessment (ECA), but where this is not available then the requirements of NGN welding specification NGN/SP/P/2 should be used. D3.13.2 The defect length should normally be defined as being from the point at which the full interacting defect first attains a signal of 30% of Full Screen Height (FSH) to that point where it lasts falls below 30% of FSH. D3.13.3 Where two or more defects occur in close proximity to each other, they must be assessed for interaction to the requirements of BS 7910 clause 7.1.2.3, figure 11 and figure 12. D3.13.4 The ECA requirements are unique to each project / pipe wall thickness and pipe diameter. An ECA to allow specific defect acceptance criteria must be produced for each pipeline project prior to the commencement of inspection. D3.13.5 To allow for combined AUT system and interpreter error, all recorded defect heights must be increased by an amount to be agreed by the Employer prior to commencement of production weld examination. This value may vary according to the AUT system used and operator competence. The AUT contractor must provide evidence and fully demonstrate to the satisfaction of Employer that the sizing error value to be adopted is accurate. D3.13.6 All transverse indications that exceed the threshold must be evaluated as cracks. D3.13.7 When any three out of ten welds consecutively tested fail to meet the ECA acceptance criteria, then the accept / reject requirements must revert to the workmanship standard of the 43 Uncontrolled when printed / after download NGN/SP/NDT/2 applicable welding standard in use (e.g. NGN/SP/P/2, clause 13). The application of the ECA acceptance criteria cannot be reintroduced until the reason for the defective welding has been identified and rectified. D3.14 Software D3.14.1 Any software required to view the results must be included on the data disc which must be provided as part of the final results. Any software licenses must be agreed before any of the production welds are examined. D3.14.2 For phased array system, the software must be able to display the scan results, phased array steering parameters and focal law set up. D3.14.3 The version number of any software must be clearly visible on all display and printout presentations. D3.15 Evaluation and Reporting D3.15.1 Indications recorded from sources other than weld imperfections must be evaluated. Their nature must be clearly identified on the examination report. D3.15.2 The recording threshold for planar detection channels must be at least 6 dB more sensitive than the reference reflector and must be such that the smallest non-allowable imperfections are detected. D3.15.3 The recording threshold for porosity detection channels must be at least 14 dB more sensitive than the reference reflector. D3.15.4 It is recommended that the recording threshold for TOFD remains at the calibration threshold. D3.15.5 Channel output signals must be arranged on the recording media in an agreed order. The function of each channel must be clearly identified. The hard copy recording must be corrected to account for any variation introduced due to different circumferential positions of the transducers. D3.15.6 The welding foreman responsible for weld production must be immediately notified of any defect recorded during the AUT scan. The exact position of the defect must be marked on the pipe surface using permanent markers D3.15.7 The AUT record must be annotated with the size evaluation of each weld imperfection selected for assessment. Comments must be added, as necessary to allow a later re-evaluation by another operator. D3.16 Re-Examination Welds must be re-examined whenever any of the following occur: a. Scanning exhibiting a loss of coupling i.e. a drop in echo amplitude of more than 10dB from the level though a clean weld, where the length is more than the allowable defect length for the effected channel. b. Any calibration scan that shows that the system is “out of calibration”, must be subject to the requirements of 11.10. 44 Uncontrolled when printed / after download NGN/SP/NDT/2 D3.17 Inspection Records D3.17.1 The following Inspection records must be provided: • • • • A hard copy record of each weld examined An assessment of the weld quality according to the acceptance criteria A hard copy record of all calibration scans Examination data in electronic form D3.17.2 The electronic data must display the results in the same manner that the operator viewed at the time of inspection. A print option must be provided as part of the software. D3.17.3 A Scan and TOFD data must be saved as part of the original weld scan data and included in the weld record. D4. Phased Array Ultrasonic Testing (PAUT) for Pipework D4.1 Limitations D4.1.1 The welds for new pipework fabrication/construction may be inspected using a Semi Automated Phased Array Ultrasonic Testing (PAUT) in lieu of Radiography Testing (RT) provided the following requirements are met: • • • • • The material of construction is carbon steel or low alloy steel Only pipe to pipe girth weld joints are examined The wall thickness of the pipe is greater than 6mm The test temperature is between 0°C and 50°C Scanning is performed from both sides of the weld. D4.2 Information to be Provided by NGN D4.2.1 The following information should be provided by NGN to the PAUT service provider: • • • • • • • Material specification and product form (cast, forged, rolled, etc.) Information on the welding procedure, including welding method and joint design. Time of inspection relative to post weld heat treatment. Acceptance criteria for weld imperfections (if applicable). Construction standard used. Results of any parent material testing prior to and after welding. Whether transverse defects are to be inspected. D4.3 Procedure Qualification D4.3.1 Before any system is used for the inspection of production welds on pipework, the Phased Array Ultrasonic Testing (PAUT) procedure must be qualified to the satisfaction of NGN / The qualification programme must be administered by the PAUT supplier. D4.3.2 The qualification of the PAUT system is only valid when all essential variables remain nominally the same as covered by the documented qualification. This specification does not require a new qualification to be performed provided that the documented performance meets or exceeds the requirements for the specific application being considered. 45 Uncontrolled when printed / after download NGN/SP/NDT/2 • • • • Acceptance criteria Specification of qualification block Procedure qualification programme Reporting requirement D4.3.3 The qualification programme and results must be approved by NGN. NGN has the option to witness the qualification programme. It is the responsibility of NGN to determine the acceptability of the procedures based on its review of the qualification test results. D4.3.4 The qualification must demonstrate acceptable performance on the qualification blocks. The PAUT contractor must supply the necessary qualification blocks for testing. The reference blocks used for calibration shall meet the requirements of BS EN ISO 13588 A.2 curved reference blocks shall be used having diameters from 0.9 to 1.5 times the pipe to be tested OD, for Pipe OF greater than 300mm a flat reference block may be used. The PAUT contractor must submit their design for qualification block(s) to NGN for approval before manufacture, detailing the number, orientation and location of slot reflectors or other reflectors. The slot reflectors should be made using Electric Discharge Machining (EDM). D4.3.5 The qualification blocks must be prepared by welding or hot isostatic process (HIP) and must contain as a minimum three flaws, as follows: • • • D4.3.6 • • • • One surface flaw on the side of the block representing the pipe OF surface, One surface flaw on the side of the block representing the pipe ID surface, and One subsurface flaw. Acceptable performance is defined as: Detection of all flaws in the qualification block Response from the maximum allowable flaw and other flaws of interest demonstrated to exceed the reference level for examination as per the procedure The flaws are sized as being equal to or greater than the actual size (both length and height) The flaws are properly categorised (surface or subsurface) D4.3.7 The PAUT supplier must maintain a record of each procedure qualification test and make the test records available to NGN upon request. The following parameters must be recorded: • • • • • • • • • • • Search unit details, including the element pitch, size, number and gap dimensions Focal set up including the plane, depth and sound path (if applicable) Virtual aperture sizes including the number of elements, element width and effective height Wedge natural refracted angle Sweep angular range, and minimum and maximum beam angles Details of qualification block (thickness, diameter, joint geometry, flaw position and flaw size) Scanning sensitivity and details of reference block Probe travel speed Flaw sizing data Test date Details of examiner and details of any test witness 46 Uncontrolled when printed / after download NGN/SP/NDT/2 D4.3.8 Where there are any changes to the essential variables for a system, the procedure may require re- qualification. Essential variables must include the following: • • • • • • • • All the essential variables listed in BS EN ISO 13588 Changes in welding method and weld join design, including repair welds Change in wall thickness Change in pipe diameter (applicable for pipe smaller than DN 300mm) Base material and welding consumables (The distinction is made for materials with substantially differences in ultrasonic response, for instance between CMn 13% Cr, duplex or austenitic steels) System, data acquisition and data treatment Software version (except changes affecting viewings, display or bug fixing only) System operator interpreter training and qualification. D4.4 Examination Procedures D4.4.1 Before any testing of production welds can begin, two types of PAUT procedures must be provided by the PAUT supplier to NGN for review and approval. The two procedures are a generic procedure and a project specific procedure. D4.4.2 A generic procedure must be provided and approved by NGN prior to procedure qualification and include the following: • • • • • • • • The proposed equipment to be used Proposed procedure qualification programme Details of the qualification and reference block Reference standard Personnel qualifications Data acquisition and storage Flaw evaluation and acceptance criteria Reporting requirement D4.4.3 The project specific procedure must be provided and approved by NGN prior to testing of production welds. The project specific procedure must include the following: • • • • Thickness and diameter of the pipe to be inspected Material of construction and welding method Weld joint design and dimensions Details of the scan plans, including the search unit placement, beam angles and beam steering set up. D4.5 Calibration and Sensitivity Settings D4.5.1 The acquisition unit must have a current calibration certification to the manufacturer’s specification. Calibration periods must not exceed 12 months. D4.5.2 All relevant channels, probes and cables for the PAUT must be checked for their functionality. The check must be performed daily before and after testing. If any item fails, all the tests carried out since the last valid check must be repeated. 47 Uncontrolled when printed / after download NGN/SP/NDT/2 D4.5.3 The setting of range must be carried out prior to each test. The probe velocity must be calibrated using the V1 block, V2 block or the reference block side drilled holes. The wedge delay calibration should be performed using the reference block. Range settings must be checked at least every 4 hours and after the completion of testing. If the deviations are 0.5 mm or 2% of the depthrange, whichever is greater, all the tests carried out since the last valid check must be repeated. D4.5.4 Sensitivity settings must be carried out prior to each test for every beam generated. The reference blocks used for calibration shall meet the requirements of BS EN ISO 13588 A.2 curved reference blocks shall be used having diameters from 0.9 to 1.5 times the pipe to be tested OD, for Pipe OD greater than 300mm a flat reference block may be used. The PAUT contractor must supply the necessary reference blocks and must submit their design for a reference block(s) to NGN for approval before manufacture, detailing the number, orientation and location of Flat Bottom Hole (FBH) and transverse EDM slot reflectors or other reflectors. D4.5.5 During the sensitivity setting, the gain control must be set at 80% ± 5% of full screen height. Sensitivity settings must be checked at least every 4 hours and after the completion of testing. If the deviations are greater than 4 dB, all the tests carried out since last valid check must be repeated. D4.6 Scanner and Encoder D4.6.1 The probe assembly must run on a mechanical guided scanner capable of maintaining a fixed and consistent search unit position relative to the weld centreline. If there is an obstruction to fixing the scanner, the weld must be inspected using Radiographic Testing. D4.6.2 A position encoder must be incorporated into the scanner mechanism with an accuracy of better than ± 1 % of the actual distance moved. The encoder must be calibrated on a weekly basis, with records to be provided to NGN. D4.7 Operators & Interpreter Qualification D4.7.1 Details of the contractor’s proposed PAUT operators and interpreters must be submitted to NGN for review and approval prior to the start of weld examination. NGN has the option to assign a secondary interpreter who acts on behalf of NGN D4.7.2 All operators/interpreters must be trained and competent in the use of the particular PAUT equipment that they should be expected to operate. Documented evidence of adequate training and ongoing practical ability must be provided to NGN for each proposed operator/interpreter. D4.7.3 PAUT operators and interpreters must as a minimum be qualified in Ultrasonic Testing Level 2 to a scheme meeting the requirement of ISO 9712. Operators /interpreters possessing an equivalent qualification under an alternative scheme may be proposed by the PAUT supplier for consideration by NGN. D4.7.4 Operators of PAUT equipment must be required to demonstrate under field conditions and to the approval of NGN, their application of the approved contract PAUT procedures. This must include their capability to calibrate the equipment properly, to interpret correctly the indications given by the equipment, to clearly record and report the results of the examination, including the location, size and nature of all flaws detected. D4.7.5 Operators of PAUT equipment must have completed PAUT specific training and examination 48 Uncontrolled when printed / after download NGN/SP/NDT/2 on representative pieces. These training and examination results should be documented. If this is not the case, examination should be performed on representative samples containing natural or artificial defects similar to those expected. D4.7.8 Operators must not be changed without the prior approval of NGN. D4.8 Weld Testing D4.8.1 The scanning area must be clean, even and free from foreign matter likely to interfere with probe coupling over an area wide enough to permit the testing volume to be covered. D4.8.2 The datum must be clearly identified and marked on the equipment. The weld scanning direction (clockwise or anti-clockwise relative to a fixed datum) must be agreed with NGN and must be consistent for all production girth weld examination. D4.8.3 The system must provide an overlap at the start and/or end of the scans of at least 25 mm. D4.8.4 Each linear scan must be parallel to the weld axis at a constant stand-off distance with the beam oriented perpendicular to the weld axis. D4.8.5 The examination area must include the volume of the weld plus the lesser of 25mm or the thickness of the adjacent parent pipe. D4.8.6 The maximum allowable circumferential scanning velocity must not exceed 150mm/s and must be selected such that satisfactory images are generated. The maximum allowable missing lines are 2 lines per 25 mm of the linear scan and there should be no adjacent line skip. D4.8.7 If imperfections are found during data acquisition, the exact position of the defect must be marked on the pipe surface using permanent markers and the welding foreman responsible for weld production must be immediately notified. D4.9 Data Acquisition and Storage D4.9.1 The PAUT must be performed using a device employing computer-based data acquisition. Ascan data must be recorded for the area of interest in an unprocessed form with no thresholding and must be stored in an electronic storage media. The correspondent equipment set up parameters must also be stored. D4.9.2 The data must be clearly identified and referenced to the weld joint numbering system. D4.9.3 The data must be securely stored and able to be retrieved for a minimum of 5 years from the project completion date. D4.10 Evaluation of Phased Array Data D4.10.1 Upon completion of the data acquisition, the data must be evaluated by a PAUT interpreter supplied by the PAUT contractor. NGN has the option to provide an NGN representative to evaluate the phased array data. The data evaluation should ensure the following: • Satisfactory scan images were acquired during the data acquisition, including satisfactory 49 Uncontrolled when printed / after download NGN/SP/NDT/2 • • • coupling, range and sensitivity settings and signal to noise ratio. Identification and classification of the indications. Determination of the location and size of the indications. Evaluation of the indications against the acceptance criteria. D4.10.2 For any response greater than 20% above the reference level, the location, amplitude and extent of all reflectors must be investigated. D4.11 Acceptance Criteria Before any system is used for the inspection of production welds on the pipeline it shall be qualified to the satisfaction of NGN. The procedure for qualification may be to scan a weld which may be agreed by NGN and report any flaws that are outside the acceptance criteria in accordance with the relevant standard. The results from the qualification scan may be analysed by NGN to confirm acceptance of the system and operators. D4.12 Reporting D4.12.1 As a minimum, the PAUT inspection report must include all the information as listed in section 15 of ISO 13588. 50 Uncontrolled when printed / after download NGN/SP/NDT/2 Appendix E Non Destructive Testing The following specimen NDT forms are typical of the format required by NGN for inspection details. The information given on the sheets is considered to be the minimum needed for the following procedures: a) b) c) d) e) Radiographic Procedure Specifications Radiographic Inspection Report Ultrasonic Inspection Report Magnetic Particle Inspection Report Weld Report Sheet 51 Uncontrolled when printed / after download NGN/SP/NDT/2 52 Uncontrolled when printed / after download NGN/SP/NDT/2 53 Uncontrolled when printed / after download NGN/SP/NDT/2 54 Uncontrolled when printed / after download NGN/SP/NDT/2 55 Uncontrolled when printed / after download NGN/SP/NDT/2 56 Uncontrolled when printed / after download NGN/SP/NDT/2 Endnote Comments Comments and queries regarding the technical content of this safety and engineering document should be directed to standards@northerngas.co.uk. © Northern Gas Networks Limited This NGN document is copyright and must not be reproduced in whole or in part by any means without the approval in writing of NGN. Northern Gas Networks Limited 1100 Century Way Thorpe Park Business Park Colton Leeds LS15 8TU 57 Uncontrolled when printed / after download
0
You can add this document to your study collection(s)
Sign in Available only to authorized usersYou can add this document to your saved list
Sign in Available only to authorized users(For complaints, use another form )