SAP C_S4PM_2504
Certification Exam Syllabus
and Exam Questions
SAP C_S4PM_2504 Exam Guide
www.ERPPrep.com
Prepare confidently for the SAP Certified Associate - Managing SAP S/4HANA
Cloud Public Edition Projects (C_S4PM_2504) exam with this comprehensive
preparation guide. The PDF covers the exam summary, detailed syllabus topics
including SAP Activate methodology and Project Management, and essential
sample questions with answers designed to simulate the actual certification
environment. Perfect for professionals targeting SAP S/4HANA Cloud
certification with a goal to pass with a high score.
Managing SAP S/4HANA Cloud Public Edition Projects - C_S4PM_2504
PDF
Introduction to SAP Certified Associate Managing SAP S/4HANA Cloud Public Edition
Projects Exam
Managing SAP S/4HANA Cloud Public Edition Projects (C_S4PM_2504) preparation
guide helps you to get focused on exam. This guide also helps you to be on the
C_S4PM_2504 exam track to get certified with a good score in the final exam.
C_S4PM_2504 Managing SAP S/4HANA Cloud Public Edition
Projects Exam Summary
● Exam Name: SAP Certified Associate - Managing SAP S/4HANA Cloud Public
Edition Projects
● Exam Code: C_S4PM_2504 » SAP Managing S/4HANA Cloud Public Edition
Projects Certification Online Practice Test
● Level: Associate
● Duration: 180 mins
● Number of Questions: 80
● Passing Score: 69%
● Reference Books / Trainings: Managing SAP S/4HANA Cloud Public Edition
Projects
● Schedule Exam: SAP Learning
Managing S/4HANA Cloud Public Edition Projects
1
Managing SAP S/4HANA Cloud Public Edition Projects - C_S4PM_2504
PDF
● Sample Questions: SAP Managing S/4HANA Cloud Public Edition Projects
Certification Sample Question
● Recommended Practice: SAP Managing S/4HANA Cloud Public Edition
Projects Certification Practice Exam
Exam Syllabus: C_S4PM_2504 SAP Certified Associate Managing SAP S/4HANA Cloud Public Edition Projects
Topic Areas
SAP S/4HANA Cloud Public Edition Implementation
Project Management / Organizational Change Management (OCM)
SAP Activate methodology
Weighting
31-40%
31-40%
31-40%
SAP C_S4PM_2504 Certification Sample Questions and
Answers
To make you familiar with Managing SAP S/4HANA Cloud Public Edition Projects
(C_S4PM_2504) certification exam structure, we have prepared this sample question
set. We suggest you to try our Sample Questions for Managing S/4HANA Cloud Public
Edition Projects C_S4PM_2504 Certification to test your understanding of SAP
C_S4PM_2504process with real SAP certification exam environment.
C_S4PM_2504 Managing SAP S/4HANA Cloud Public Edition Projects Sample
Questions:01. What does SAP Activate recommend to keep team members informed and
aligned?
Please choose the correct answer.
a) Daily e-mail status updates to project manager
b) Daily progress review meeting with sponsor
c) Daily status meeting with project manager
d) Daily team stand-up meeting
02. When planning a multi country deployment (20 or more countries), what is the
SAP best practice on activating countries in Central Business Configuration
(CBC) in a single Scope and Organizational Structure phase?
Please choose the correct answer.
a) Activate all countries
b) Activate most countries but not all
c) Activate some countries (<=5)
Managing S/4HANA Cloud Public Edition Projects
2
Managing SAP S/4HANA Cloud Public Edition Projects - C_S4PM_2504
PDF
d) Activate about half of the countries
03. In the Central Business Configuration task" Specify Primary Finance
Settings", which settings are not reversible?
There are 2 correct answers to this question.
a) Default Currency
b) Group Currency
c) Fiscal Year Variant
d) Leading Ledger
04. What are the benefits of using SAP Activate?
There are 3 correct answers to this question.
a) Leveraging standard content
b) Guided methodology
c) Focused Build
d) Tools for assisted implementation
e) Focused Run
05. Who determines the priority of user stories in the backlog of an Agile project?
Please choose the correct answer.
a) Product Owner
b) Scrum Master
c) Project Manager
d) Project Team
06. Where can you find Project Library Accelerators?
Please choose the correct answer.
a) SAP Cloud Appliance Library
b) Fully Activated Appliance
c) SAP Roadmap Viewer
d) SAP Signavio Process Navigator
07. When a project manager is setting up the implementation project in SAP
Cloud ALM, what must be assigned to the Deployment Plan?
There are 2 correct answers to this question.
a) System Group
b) SAP Activate Roadmap
c) Releases
d) Scope
Managing S/4HANA Cloud Public Edition Projects
3
Managing SAP S/4HANA Cloud Public Edition Projects - C_S4PM_2504
PDF
08. What do you recommend customers do whose Cloud Mindset Assessment
shows a medium risk rating?
There are 2 correct answers to this question.
a) Consume the Awareness Content
b) Execute an SAP Digital Culture Advisory Workshop
c) Consume the Enhanced Support Content
d) Implement a Transformation Package
09. What is the correct order of the SAP Activate Methodology phases?
Please choose the correct answer.
a) Prepare > Discover > Explore > Realize > Deploy > Run
b) Discover > Prepare > Explore > Realize > Deploy > Run
c) Plan > Build > Run > Sustain
d) Plan Design > Build > Operate
10. After a customer has requested a production system in SAP for Me, what are
some consequences?
There are 2 correct answers to this question.
a) The subscription period for the production system will start.
b) The customer can transport their configuration from the Test system to the new
production system.
c) The customer can transport their configuration from the development system to the
new production system.
d) The Starter System will be decommissioned after 30 days.
Solutions:
QUESTION: 01- Answer: d
QUESTION: 02- Answer: c
QUESTION: 03- Answer: b, c
QUESTION: 04- Answer: a, b, d
QUESTION: 05- Answer: a
QUESTION: 06- Answer: c
QUESTION: 07- Answer: a, c
QUESTION: 08- Answer: a, c
QUESTION: 09- Answer: b
QUESTION: 10- Answer: c, d
Managing S/4HANA Cloud Public Edition Projects
4