CMS Doc ID SOP-1061 SOP Title Standard Operating Procedure for RV sizing until vendor data sheet approval Date Issued 25/07/2022 Directorate UED Sub Team UEFP Security Restricted Page No 9 Version 02 Document Authorisation Document Owner (CFDH) / Dept. Head Document Custodian Document Author Niyaz, Salman UEF Hadhrami, Siham UEFP Busaidi, Mustafa UEFP25 Date : 23-06-2021 7:23 AM Date : 22-06-2021 4:34 PM Date : 21-06-2021 12:27 PM Printed copies are UNCONTROLLED Number of People involved___5____ Target Cycle Time_9 weeks_ Special Requirements Key Point Images Procedure Overview Instructions and Explanations Understanding the 1. Identify all credible 1.1 Identify credible reliving Project scope from scenarios and arrive scenarios based on system Process Design Basis at governing boundary/process units, see (PDB). scenario. the attached guide which shows credible scenario Understand Process By: Process identification (attachmentSystem /boundary 1). Engineer, TA-2 limits using Process Process Engineer 1.2 Provide required Design Flow Scheme (PFS) / data. Refer to Checklist for Process Engineering Via: Standard Process Calculation – PSV Flow Scheme sizing (attachment-2). Calculation Sheet For (PEFS). 1.3 Enter the required input for Relief Valve Sizing all RV sizing scenarios. Use UniSim Inputs cells are highlighted Time: 2-3 days Simulation model to in yellow. take the required fluid 1.4 Evaluate relieving load properties. resulted from each scenario reflected in the summary Obtain inlet/outlet sheet piping lengths 1.5 Identify required relief area estimate from piping for credible scenarios. engineer. 1.6 Select the scenario which gives highest orifice area as governing scenario for PEFS and PSFS. 1.7 Perform isenthalpic (JT) flash from credible high inlet pressure and lowest inlet temperature to flare / vent system superimposed back pressure, which is normally atmospheric pressure. Note, the inlet pressure and temperature condition do not need to be a relief condition, instead it may be low ambient temperature Input to RV data sheet template (Provided by Mechanical Piping Engineer). 2. Process inputs to Mechanical RV data sheet. By: Process Engineer, TA-2 Process Engineer Via: Mechanical RV data sheet Time: 1-2 days and trip pressure in the RV leakage scenario. Value from this step is used as minimum outlet temperature. 1.8 Perform isentropic flash from credible high inlet pressure and lowest inlet temperature combination to the choked pressure at the RV nozzle. Relief valve body design temperature is lowest of temperature calculated from 1.7 and 1.8 1.9 RV inlet line sizing to be performed along with RV sizing. The pressure loss between equipment with an RV and the inlet of an RV during a relief case must be less than 3% of the RV set pressure (in gauge units) value based on the rated flow to prevent “chattering”. Refer to SOP-1062 1.10 Calculation to be checked and approved by competent persons as per checking and approval schedules PR1768. 1.11 After checker and approver comments are incorporated, Calculation sheet to be signed off. 2.1 Obtain latest template for RV datasheet from Mechanical. 2.2 Process Engineer to fill all highlighted cells in yellow (Process inputs) based on All cases (including fire case) from the calculation sheet. 2.3 For gas / liquid and three phase relief scenarios, provide the liquid viscosity and mass flux, but no other properties are required. 2.4 The template from Mechanical Piping may have a tab for composition data. It is not required to fill this tab for any scenarios. 2.5 The superimposed backpressure to be determined for the different relief valve sizing scenarios and the different facility relieving scenarios. Refer to Annex for examples of scenarios when superimposed backpressure may be >0. 2.6 Enter the incremental backpressure caused by flow from this relief valve in the built-up back-pressure box. 2.7 Total back pressure is a calculated value in datasheet. Total back pressure is calculated by adding built-up and superimposed back pressure. Piping Class 3. Completed inputs 3.1 Selection report to to Mechanical Data / reflected selected Preparation of the material based on MR report / 3.2 the Material Selection Procurement Process Report / Review vendor offers / documents. By: Mechanical piping Engineer, TA-2 Mechanical piping Engineer, Procurement Engineer 3.3 Via: Mechanical RV data sheet 3.4 3.5 Time: 6-8 weeks 3.6 3.7 3.8 Inputs to be provided on the RV data sheet by Mechanical Engineer. Mechanical Engineer prepares Material Requisition for the RV, RV data sheet is included as attachment. MR to be sent for IDC / IFR Process to confirm sizing scenarios and provide mark-up of datasheet containing new scenarios if required by HAZOP, IPF or process design development. Procurement team to share AFT MR to approved vendors Vendor offers will be received. Disciplines to review submitted offer by vendors and start TQ cycle. Process Engineer to ensure that all the process inputs given in data sheets are correctly selected by the vendor and also check the calculation done by vendor is acceptable and agrees with company calculation. Differences need to be raised in TQ. Checklist to be developed in future for guidance. CDTP is provided by vendor in their datasheet, Process Engineer is to ensure that CTDP = set pressure - superimposed back pressure (Refer Annexure for CDTP description). 3.9 Obtain the inlet / outlet piping equivalent lengths from piping isometrics and repeat inlet/outlet pressure drop calculations (See Section 1.9). Inlet piping sizing to be performed based on vendor rated flow. 3.10 Vendor to list all deviations from datasheet and technical standards in the deviation list and the list to be reviewed by disciplines. 3.11 Once TQ stage completed, TBE will be prepared by mechanical discipline and issued. 3.12 Confirm all vendor data that may affect relief valve sizing; control valve sizes, pump and compressor curves, vessel sizes, Class-1 check valve sizes. Revise RV calculations. 3.13 For relief valves where Class-1 check valves limit the relieving, flow confirm check valve size from piping. 3.14 Approved TBE to be signed by discipline Lead Engineers. 3.15 Online bidding to be performed for the acceptable vendors. 3.16 PO will be placed for the selected vendor. 3.17 Piping will prepare AFP MR and send to selected vendor. 3.18 Vendor to provide GA, datasheet and sizing calculation. 3.19 GA / datasheet will be reviewed by Piping and sizing calculation / datasheet will be reviewed by Process. 3.20 Process engineer to review vendor data sheet / GA drawings against the vendor sizing calculations Approved Vendor documents - Code A and make sure all information is included and is consistent. 3.21 Comments to be provided in SPO and shared to vendor until vendor documents have no further comments and declared code A. 4. Update Process / 4.1 Piping engineer to provide piping documents mark-up of the PEFS based on the agreed showing the final RV size / vendor data. flange rating / insulating gaskets and material. By: Process 4.2 Final RV size to be updated in Engineer, TA-2 the PEFS, SM and Flare and Process Engineer Vent Report. HOLDs on these documents to be Piping engineer, TA-2 removed. On certain Piping Engineer projects PSFS may also show RV sizes. 4.3 RV inlet line size to be reTime: 3-5 days checked based final vendor rated flowrate in case any change in the process data between TQ stage (AFT MR for RV) and approved vendor documents after PO issue). 4.4 Piping to reflect vendor details in the 3D model Pre-Checks Key Point Images Things to Do Before Starting the Process ☐ Approved Process Design Basis ☐ Approved final Simulation model ☐ Process Flow Scheme (PFS) ☐ Process Engineering Flow Scheme (PEFS) ☐ Inlet piping length from piping engineer Tools and Materials Step ☐ Validated approved RV calculation sheet ☐ UNISIM Software 1.1-1.6 1.3 Things You Need Before Starting the Process Key Point Images People Who Is Required to Be Notified ☐ Process Engineer ☐ Process Engineer (TA-2) ☐ Piping Engineer ☐ Piping Engineer (TA-2) ☐ Procurement Engineer Key Learnings; Performance Points Key Point Images What Have We Learned That We Should Share Abbreviation: AFP Approved for Purchase AFT Approve for Tendering IDC Inter-Discipline Checking IFR Issued for Review MR Material Requisition MW Molecular Weight PSV Pressure Safety Valve Key Point Images RV SM SOP TA TBE TQ Relief Valve Safeguarding Memorandum Standard Operating Procedure Technical Authority Technical Bid Evaluation Technical Queries References and links: Relief Valves – Selection, Sizing and Specification DEP 80.36.00.30-Gen Sizing, selection and installation of pressure-relieving devices in refineries Part I – Sizing and Selection API Standard 520 API Standard 521 Pressure-relieving and Depressuring Systems. API Standard 526 Flanged Steel Pressure – Relief Valves DEP 80.45.10.10 Design of Pressure Relief , Flare and Vent Systems DEP 80.45.10.11 Overpressure and Underpressure – Prevention and Protection FEED-QM-FOM-144, Rev.01 Checklist for Process Calculation – RV sizing. WHAT IS CDTP? Relief valves are tested every 2 years to ensure that they open at the correct pressure. This test is performed in the workshop with no back-pressure on the outlet side of the relief valve and at ambient temperature. The test conditions differ from the installed conditions of the relief valve due to different back-pressure imposed by the flare / vent and different temperature of the process fluid. Cold Differential Test Pressure (CDTP) is the differential pressure that a relief valve must be shown to open at under test conditions to ensure that it opens correctly at relieving conditions when installed. CDTP value may be different to set-pressure. There are two reasons why CDTP is different to set-pressure, these are pressure correction and temperature correction. Pressure Correction The pressure correction is normally straightforward. The back-pressure in the disposal system caused by other events when the relief valve is about to open is determined. This back-pressure is caused by other relief valves, EDP or PCV to flare that may be flowing at the same time or simply due to the purge flowrate. The CDTP is lowered to account for this. Pressure correction only applies to conventional spring relief valves. Temperature Correction This is less straightforward and can only be determined by the vendor. Temperature correction may apply to all types of relief valve. Note, temperature correction is not required for fire case relief valves. CDTP = (Set-pressure - superimposed back-pressure) * temp correction CDTP = Set-pressure x temperature correction Conventional Spring Types Pilot and Balanced Bellows Examples 1. Steam relief valve with fluid temperature at the relief valve inlet of 300 deg C relieving to atmosphere through short tailpipe. In this case, there is no superimposed back-pressure (0 kPag). Therefore, back-pressure at opening condition and test conditions are the same. However, the relieving temperature is much higher than ambient temperature. This reduces the strength of the spring and therefore, the temperature correction requires the CDTP to be higher than set-pressure. Vendor will determine the CDTP, CDTP cannot be checked. 2. High pressure vessel operating at 70 deg C relieving to low pressure vessel operating at 200 kPag. The superimposed back-pressure on the installed relief valve is higher than atmospheric pressure during the test. Therefore, the CDTP must be lower than set-pressure to ensure that the relief valve opens at the correct pressure when the process pressure is superimposed on the relief valve as back-pressure. However, the relieving temperature is close to ambient temperature, so no temperature correction is required. Vendor will determine the CDTP, but it can be checked by FO Process Engineers. Considerations If CDTP is lower than set-pressure, it may be necessary to lower pressure trip settings to ensure that the trip always happens at a lower pressure than the relief valve opens, or increase the design pressure / set-pressure to ensure sufficient margin above trip pressure. As this may affect project schedule, increase pressure rating of the piping and increase project cost, it may be simpler and more cost effective to specify a balanced bellows relief valve. WHAT IS SUPERIMPOSED BACK-PRESSURE? Superimposed back-pressure is the back-pressure imposed on a relief valve by other events in the relief valve discharge system. Examples: Simultaneous relief and depressurization. An example could be partial relief from a station inlet occurring at the same time plant depressurization. Flare gas recovery where the flare system is kept at slightly elevated pressure by a control valve to provide driving force to route flare gas to a compressor. Where the relief valve discharge is routed back to a process system operating at lower pressure. For example, routing a pump discharge relief valve back to the suction vessel. The suction vessel operating pressure acts as superimposed back-pressure on the relief valve. Why is Superimposed Back-Pressure Important? Any back-pressure on a relief valve will reduce the relief valve capacity and needs to be accounted for when sizing the relief valve. For conventional spring type relief valve, superimposed back-pressure acts on the reverse side of the disc. This superimposed back-pressure tries to prevent the relief valve opening. This is shown in Figure 8 from API-520 Part 1 (2020). Bursting discs are affected in the same way. Balanced bellows relief valves are not affected by superimposed back-pressure. pilot operated relief valves may be affected, it depends on the exact design of the pilot. Considerations Superimposed back-pressure values will be used by the supplier to calculate the CDTP for the relief valve. If the superimposed back-pressure is not present in operational setting, the relief valve will open early because the CDTP is less than the set-pressure. Therefore if the superimposed back-pressure is variable, the potential for opening early when the superimposed back-pressure is less than maximum must be evaluated. WHAT IS BUILT-UP BACK-PRESSURE? Built-up back-pressure is the increase in back-pressure caused by flow from the specific relief valve being considered. Built-up back-pressure is only present when the relief valve is open. Why is Built-up Back-Pressure Important? Built-up back-pressure on a relief valve will reduce the relief valve capacity and needs to
0
You can add this document to your study collection(s)
Sign in Available only to authorized usersYou can add this document to your saved list
Sign in Available only to authorized users(For complaints, use another form )