FPP location
assumption: 50m
from Building
Line
FPP: 13.5kV
Primary
incomming
with LA,LBS & PF
4.02 m
Concrete pedestal
4x 110 mm dia
PVC
VERTICAL 1 = FPP Height
HORIZONTAL 1 = 55m (PEDESTAL to Building
Line)
Concrete
Encasement
450 x 450mm
VERTICAL 2 = MVSG Height x 2
HORIZONTAL 2 = EE Room (Building line to
MVSG)
50.02 m
MANHOLE
VERTICAL 3 = TRANSFORMER Height
HORIZONTAL 3 = MVSG to TRANSFORMER
MANHOLE
4.91 m
10.82 m
5m
GROUND FLOOR
XXXXX SYSTEM LAYOUT
INCHARGE
DRAWN BY:
CHECKED BY:
FILE PATH: Z:\ELECTRICAL EST\2022\01. DESIGN DRAWING\CE-W-73001-A_PROPOSED STANLEY PROJECT\DESIGN 02\E-00 (BASEPLAN); PLOT: 2/8/2022 2:01:48 pm LAST SAVED: eleazar_c
INITIAL
DATE
ELEAZAR_C
Feb 08, 2022
- 2:01pm
MEZZANINE FLOOR
XXXXX SYSTEM LAYOUT
INCHARGE
DRAWN BY:
CHECKED BY:
FILE PATH: Z:\ELECTRICAL EST\2022\01. DESIGN DRAWING\CE-W-73001-A_PROPOSED STANLEY PROJECT\DESIGN 02\E-00 (BASEPLAN); PLOT: 2/8/2022 2:01:49 pm LAST SAVED: eleazar_c
INITIAL
DATE
ELEAZAR_C
Feb 08, 2022
- 2:01pm