Akpo COMPANY ref: CONTRACTOR ref: Akpo NIGERIA – OML 130 AKPO Field Development Project Project NG50-7-070-FAS-SP-AB-00-0001 J12126-RT-001 Revision: -- 01 Status: IFA -- Project Class: 1 date: page: -- -- 45 -- OLGA SUBSEA MODELLING Design Premise Reserved to COMPANY The document is: Approved code 1 Approved with minor comments code 2 Rejected code 3 Reviewed with comment code 4 date: ASB final acceptance code 5 date: Remarks: 01 REV Issued for Approval DATE DESIGNATION Genesis Company Obinna Isu Obinna Isu Initiator Reviewed by Approved by NG50-7-070-FAS-SP-AB-00-0001.doc This document is the property of TOTAL and shall not be disclosed to third parties or reproduced without permission of the COMPANY. Akpo Project CLIENT: TOTAL UPSTREAM NIGERIA LIMITED PROJECT/JOB TITLE: AKPO Field Development Project DOCUMENT TYPE: Report OLGA Subsea Modelling DOCUMENT TITLE: DESIGN PREMISE GENESIS JOB NUMBER: J-12126 GENESIS DOCUMENT NUMBER: J12126-RT-001 1 Issued For Approval SLE SJA SJA 0 Issued For Approval SJA SEA SJA A Issued For Review SJA SEA SJA Issued By Checked By Genesis Approval Rev Date Genesis France Description TOTAL Approval February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Akpo Project J12126-RT-001 Rev 0 Page 2 / 45 Table of Contents 1 INTRODUCTION................................................................................................. 4 1.1 1.2 1.3 2 ENVIRONMENTAL DATA .................................................................................. 7 2.1 2.2 2.3 2.4 3 AIR TEMEPRATURE.................................................................................................... 7 SEAWATER TEMEPRATURE ........................................................................................ 7 SOIL TEMEPRATURE .................................................................................................. 8 CURRENT ................................................................................................................. 9 FIELD DEVELOPMENT ARCHITECTURE ...................................................... 11 3.1 3.2 3.3 3.4 3.5 3.5.1 3.5.2 3.5.3 3.6 3.6.1 3.6.2 3.7 3.7.1 3.7.2 3.7.3 4 GENERAL PRESENTATION OF AKPO .......................................................................... 4 AIM OF THE DOCUMENT ............................................................................................. 5 REFERENCES ............................................................................................................ 6 FIELD LAYOUT ......................................................................................................... 11 WELL DISTRIBUTION ................................................................................................ 12 PRODUCTION LINES BATHYMETRY ........................................................................... 13 SCR DESCRIPTION ................................................................................................. 15 SINGULAR GEOMETRIES .......................................................................................... 16 Wellhead / Jumper Input in OLGA simulation.............................................................................. 16 Manifold / Spool / Sled Input in OLGA simulation ....................................................................... 17 Valves............................................................................................................................................ 17 TOPSIDE PROCESS ................................................................................................. 18 Separator Train ............................................................................................................................ 18 Temperature required at first stage separator.............................................................................. 18 PRODUCTION LINES CHARACTERISTICS ................................................................... 19 Insulation Thermal Properties...................................................................................................... 19 Pipe Wall Thickness...................................................................................................................... 19 Pipe Roughness............................................................................................................................. 20 RESERVOIR AND WELL DATA ...................................................................... 20 4.1 4.2 4.3 4.4 4.5 4.6 4.6.1 4.6.2 4.6.3 4.6.4 4.6.5 WELL ARCHITECTURE ............................................................................................. 20 MATERIAL CHARACTERISTICS .................................................................................. 22 RESERVOIR PRESSURES ......................................................................................... 23 RESERVOIR TEMPERATURES ................................................................................... 23 WELL PRODUCTIVITY INDEXES ................................................................................. 24 RESULTS OF RESERVOIR SIMULATIONS.................................................................... 25 All Production Loops .................................................................................................................... 26 Production Loop P10.................................................................................................................... 26 Production Loop P20.................................................................................................................... 27 Production Loop P30.................................................................................................................... 27 Production Loop P40.................................................................................................................... 27 5 FLUID COMPOSITION ..................................................................................... 28 6 SCOPE OF WORK ........................................................................................... 34 6.1 6.2 SOFTWARE ............................................................................................................. 34 OLGA MODEL ........................................................................................................ 34 Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project 6.3.1 6.3.2 6.3.3 6.3.4 6.3.5 6.3.6 6.4 6.5 Project J12126-RT-001 Rev 0 Page 3 / 45 6.3 Akpo OLGA 2000 SIMULATIONS ...................................................................................... 35 Steady State Runs.......................................................................................................................... 35 Branch Packing ............................................................................................................................ 36 Cooldown...................................................................................................................................... 36 Depressurisation........................................................................................................................... 36 Start-up sequence.......................................................................................................................... 37 Slugging analysis .......................................................................................................................... 37 DELIVERABLES ........................................................................................................ 37 SCHEDULE .............................................................................................................. 38 Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Akpo Project J12126-RT-001 Rev 0 Page 4 / 45 1 INTRODUCTION 1.1 General Presentation of AKPO The AKPO field lies Offshore Nigeria within OML 130, some 200km South of Port Harcourt, in water depths ranging from 1 250 m to 1 480 m. TOTAL, as Operator with a 24% share, and its partners SOUTH ATLANTIC PETROLEUM (60%) and PETROBRAS (16%) are developing the AKPO Field, estimated to contain reserves of 1 billion barrels of oil and 4 trillion cubic feet of natural gas. In summary, the overall AKPO Field Development Project consists of the following main elements: A Floating, Production, Storage and Offloading unit (referred to as the FPSO), including hull, mooring, risers structure, accommodation, process (oil, gas, water as needed), gas and water re-injection, flaring, oil storage and export facilities (pumping and metering), gas export and associated control systems. Such unit shall be designed with the following general characteristics: • • • • • • • • • • Spread moored (3 x 4 lines) FPSO in 1325 m water depth Stabilised oil (max): 185,000 Standard bopd maximum oil production rate Total liquids: 235,000 bpd Produced gas: 530 Mscfd Injected gas: 215 Mscfd (@ ~ 400 barg) Export gas: 320 Mscfd (@ ~ 200 barg) Fuel gas: 25 Mscfd Injected water: 420,000 bwpd (@ ~ 220 barg) Produced water: 150,000 bwpd Crude storage: circa 2,000,000 stb An Offshore Loading Terminal (OLT), consisting of an Offloading buoy (deep water CALM) moored down wind of FPSO in 1295 m water depth (connected to buoy via 2 x 16” I.D. steel lines). The Subsea Anchoring Systems, as needed for the FPSO and the OLT. The Subsea Production System (referred to as the SPS) including around 44 subsea wells (Wellheads, Xmas trees and associated control systems) subdivided as follows: • • • Genesis France 22 Oil producer subsea wells 2 Gas injector subsea wells 20 Water injection subsea wells February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Akpo Project J12126-RT-001 Rev 0 Page 5 / 45 The Umbilicals, Flowlines, Risers and Pipelines (referred to as UFR) consisting of: • • • • • • • 4 x 10” I.D. production flow loops (P10, P20, P30 and P40) & steel catenary risers, 1 x 8” I.D. gas injection line (GI 40) & steel catenary risers, 3 x 10” I.D. water injection lines (W10, W20 and W30) steel catenary risers, 4 x Production umbilicals, 4 x Injection umbilicals, Steel Catenary Risers hung off exterior of FPSO, 1 x Export Gas 16” pipeline to Amenam AMP2 Platform – approximate total length 150 km. The AKPO facilities will be designed with the following reservations and preinvestments for the potential future evolution of the development concept: • Spare riser porches and receptacles will be available on the FPSO for the potential tie-in of additional risers / umbilicals in the future, • Spare slots will be available on the subsea manifolds to facilitate the tie-in of additional production wells and spare in-line tee for the tie-in of future injection wells. 1.2 Aim of the Document The purpose of this document is to define the scope of work and the basis for design concerning the dynamic subsea model to be build up for the AKPO field development project. This model will later be used for various studies: Operations studies (start-up, preservation optimisation), topside studies (Dynamic simulations, OCWR design) and by OTS. Consequently, the quality of this model should be ensured by the use of the most upto-date data, by an extensive testing program and with clear interfaces. The update of some basis of design should be easily possible, which means well documented input files. This model is not built for design purposes, but for design validation, procedure preparation and training. Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 6 / 45 1.3 Akpo Project J12126-RT-001 Rev 0 References [1] Metocean specification NG50-1-CO-MET-PS-AB-000-001 [2] Surface and subsea Field Layout rev10C NG50-PJ-PJM-GEN-KE-0003 rev 3 [3] Surface and subsea Field Layout NG50-3-BE-PLR-DW-AB-000-604 rev10C [4] Impact on revised reservoir data and revised field layout on production and gas systems DED.2316_Rev0 FA impact of 10C layout [5] Flow assurance strategy NG50-7-BE-FAS-CN-AB-00-0001 [6] Subsea operating philosophy NG50-2-300-SPS-PH-AB-30-0281 [7] Manifold assembly drawing NG50-2-300-MAN-DW-SM-300232-manifold_detailed.pdf [8] Flow Assurance Reservoir Model 1 NG50-7-BE-FAS-TR-AB-00-0006 (Basis of Design) [9] Production FLET TYPE F-P11 NG50-3-200-ENG-DW-AB-30-2400 rev 1 (Preliminary Arrangement) [10] AKPO fluid temperature Dec04 EP/GSR/VDG/AKPO [11] WHSP & WHFT update NG50 - 090 # 000 - M.0001 [12] Production FLET TYPE FP1 NG50-3-200-ENG-DW-AB-30-2432 Rev 0 (Arrangement & Isometric) [13] Well Program – Dec05 [14] Process Systems Description NG50-5-500-PRO-PH-AB-00-0005 Rev 0 [15] Flow Assurance – Olga Model Build-up – Scope of Work and Basis of Design NG50-7-070-FAS-GN-AB-00-0002 [16] Heat and material balance NG50-5-500-PRO-CN-AB-00-002 Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 7 / 45 Akpo Project J12126-RT-001 Rev 0 2 ENVIRONMENTAL DATA All the data given in the present chapter are coming from the Site and environmental Survey [1]. They are required for heat transfer calculation in the flowlines and risers. 2.1 Air Temeprature The air ambient temperature is between 18.1°C and 32.6°C. Minimum temperature will be used in the simulations. 2.2 Seawater Temeprature The following graph gives the plots of the sea temperature versus the water depth, This was obtained during a one-year survey. From the graphic here above, the minimum, mean and maximum values of the temperature profiles have been considered and are given in the next table. Genesis France February 2006 Akpo Total Upstream Nigeria Limited AKPO Field Development Project Project J12126-RT-001 Rev 0 Page 8 / 45 Table 1: Temperature min & max vs water depth The minimum values will be used in order to obtain the maximum heat exchange with the surroundings and therefore the minimum fluid temperatures through the flow line. 2.3 Soil Temeprature The figure below illustrates the temperature gradient across the reservoir and the geothermal gradient to the seabed. The soil temperature profile to be used in OLGA model is issued from the results of the environmental data. But this temperature profile does not take into account the reservoir temperature associated to each well. As a consequence the soil temperature profile will be modelled in 2 steps: - From the mud line to the end of last casing, the temperature profile is deduced from the data presented in the figure below. - Upstream reservoir bottom hole, a linear regression is used: - The reservoir temperature is used as the reference point - The upstream temperature is extrapolated using the linear temperature slope at of the bottom of the temperature curve presented below. Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 9 / 45 2.4 Akpo Project J12126-RT-001 Rev 0 Current On behalf of Total Upstream Nigeria, Fugro GEOS have undertaken a year long measurement programme in the Akpo field. Current speed and direction profiles were measured at 20 minute intervals between 12 May-2001 and 19 May 2002. The water depth at the measurement location was 1376m. Extreme current speeds derived by the independent extrapolation of time series at each depth level are presented in the following Table. Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 10 / 45 Akpo Project J12126-RT-001 Rev 0 Most of the time (90%) the current velocity is around 0.02 m/s from 100 m to 1500 m below sea level. Between 100 m and 10 m below sea level, it increases up to 0.08 m/s. In order to maximise heat exchanges between production flowlines and the environment, profile of maximum measured current speed will be used in the subsea model. Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 11 / 45 Akpo Project J12126-RT-001 Rev 0 3 FIELD DEVELOPMENT ARCHITECTURE 3.1 Field Layout In summary, the overall AKPO field layout selected for the flow assurance studies is based on the one issued on August 2005 [2 & 3]. Note that in previous models, some margins have been added on each production and injection line in order to take into account any further layout modification, but the current should not take any margin, it should be as per frozen layout. The following values are given with no margin and including the steel catenary riser: • Spread moored (4 x 4 lines) FPSO in 1314 m from Mean Sea Level (MSL), • Offloading buoy moored down wind of FPSO in 1285 m water depth below MSL (connected to FPSO via 16” ID flexible lines), • 147 km 16” N.D. gas export pipeline to Amenam (AMP2), • 4 x 10” ID production flow loops & steel catenary risers – total length 50.72 km, • 1 x 8” ID gas injection line & steel catenary riser – total length 9.93 km, • 4 x 10” ID water injection line & steel catenary risers – total length 38.44 km, • 4 x production umbilicals – total length 26.4 km, • 3 x water injection umbilicals - total length 33.79 km. • 1 x gas injection umbilical - total length 5.67 km. • 22 oil producers on 4 production loops (P10, P20, P30 and P40) • 20 water injectors on 4 water injection loops (WI10, WI20, WI30 and WI50) • 2 gas injectors on 1 gas injection loop • 14 spare production slots It is important to note that the risers are steel catenary. Only production system will be included in the OLGA subsea modelling. Detailed field layout is given in Ref. [2 & 3]. Several comments can be made on this layout: - All production loops are up sloping toward the FPSO. This slope is due to the steel catenary configuration because the bathymetry shows that the mud line is down sloping from the touch down point to the FPSO location. - All the production loops have two manifolds, except P40 which has three manifolds, - Each production well can be tied-in to either branch of the loop, - The longest flow line is P20, with 7.11 km per branch (including the riser) - The length of the overall production lines is 48.36 km Genesis France February 2006 Akpo Total Upstream Nigeria Limited AKPO Field Development Project Project J12126-RT-001 Rev 0 Page 12 / 45 3.2 Well Distribution The following tables give for each loop the well sharing per branch for the full field. Loop P10 P20 P30 P40 Header FULL FIELD Manifold START UP First End A123_P1 & A123_P2 Right Header A568_P1 Left Header A4_P1 & A123_P4 Right Header A568_P2 A9_P2 & A456_P2 Left Header D_P2 & A68_P1 A123_P3 Right Header A689_P1 B_P2 Left Header A9_P1 G_P2 Right Header D_P1 Full of dead oil Left Header D_P3 G_P1 A456_P1 Manifold Loop Header P10 Right Header A568_P1 Left Header A568_P2 A9_P2 & A456_P2 A4_P1 & A123_P4 A123_P3 Right Header D_P2 & A68_P1 A689_P1 & EF_P2 Left Header A9_P1 B_P2 & G_P2 Right Header D_P1 EF_P1 Left Header D_P3 G_P1 P20 Right Header Left Header P30 P40 First End A simplified drawing of the above table wells arrangement per loop is given below : Genesis France February 2006 A123_P1 & A123_P2 A456_P1 B_P1 Total Upstream Nigeria Limited AKPO Field Development Project Project J12126-RT-001 Rev 0 Page 13 / 45 3.3 Akpo Production Lines Bathymetry The production line profile including SCR profile and the total length is as follows. P10 Production Loop Water Depth below MSL 0 -200 0 1000 2000 3000 4000 5000 6000 7000 7000 8000 -400 -600 -800 -1000 -1200 -1400 -1600 Production Line Length (m) P20 Production Loop Water Depth below MSL 0 -200 0 1000 2000 3000 4000 5000 6000 -400 -600 -800 -1000 -1200 -1400 -1600 Production Line Length (m) P30 Production Loop Water Depth below MSL 0 -200 0 1000 2000 3000 4000 5000 6000 -400 -600 -800 -1000 -1200 -1400 -1600 Production Line Length (m) P40 Production Loop Water Depth below MSL 0 -200 0 1000 2000 3000 4000 5000 6000 7000 -400 -600 -800 -1000 -1200 -1400 -1600 Production Line Length (m) Genesis France February 2006 Akpo Total Upstream Nigeria Limited AKPO Field Development Project Project J12126-RT-001 Rev 0 Page 14 / 45 Pipe lengths with elevation are shown in the table below. P10 Length (m) P20 Water Depth Well (m) Connections Length (m) P30 Water Depth Well (m) Connections Length (m) P40 Water Depth Well (m) Connections Length (m) Water Depth Well (m) Connections 0 20 0 20 0 20 0 20 25 -5 30 -10 33 -13 30 -10 113 -89 118 -94 121 -97 118 -94 444 -405 449 -410 452 -413 449 -410 713 -655 718 -660 721 -663 718 -660 934 -852 939 -857 942 -860 939 -857 1116 -1004 1121 -1009 1124 -1012 1121 -1009 1269 -1120 1274 -1125 1277 -1128 1274 -1125 1400 -1205 1405 -1210 1408 -1213 1405 -1210 1515 -1262 1520 -1267 1523 -1270 1520 -1267 1621 -1296 1626 -1301 1629 -1304 1626 -1301 1721 -1307 1726 -1312 1729 -1315 1795 -1307 1800 -1312 1803 -1315 1895 -1307 1900 -1312 1903 -1315 1995 -1308 2000 -1315 2003 -1315 2381 -1310 2197 -1315 2330 -1320 TDP = 930m Flowline/Riser Transition TDP = 930m Flowline/Riser Transition TDP = 930m Flowline/Riser Transition A689-P1, A9P1, EF-P2 1726 -1312 1800 -1312 1900 -1312 2000 -1313 2093 -1315 3015 -1310 2739 -1320 2996 -1325 2548 -1320 4191 -1315 3477 -1325 3566 -1330 2792 -1322 4855 -1320 4018 -1330 4042 -1335 3071 -1325 5263 -1325 4215 -1335 4516 -1340 3525 -1330 5826 -1330 4658 -1335 4992 -1345 3981 -1335 6081 -1335 5150 -1340 5230 -1350 4435 -1340 6235 -1337 Genesis France 658-P1 & A658-P A123-P1, A123P2, A123-P4, A4-P1 A68-P1, A456P2, A9-P2, DP2 B-P1, B-P2, GP2 5415 -1345 4696 -1345 5574 -1350 4858 -1350 5786 -1355 5312 -1353 5997 -1360 6221 -1355 6209 -1365 6645 -1358 6474 -1370 6686 -1375 6845 -1380 7004 -1385 7110 -1390 5370 -1355 456-P1 & 123-P3 February 2006 TDP = 930m Flowline/Riser Transition D-P1, D-P3 EF-P1, G-P1 Total Upstream Nigeria Limited AKPO Field Development Project Page 15 / 45 3.4 Akpo Project J12126-RT-001 Rev 0 SCR Description The Steel Catenary Riser (SCR) is the base case on AKPO project. Therefore, all thermo-hydraulic calculations consider this technology, with a mainly up sloping shape from the far end manifold to the FPSO. The next graph shows the typical profile for the steel catenary riser to be used for OLGA simulations. The values are detailed in the following table. The developed length of the riser is 2000 m up to the riser / flowline transition. Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 16 / 45 3.5 Singular Geometries 3.5.1 Wellhead / Jumper Input in OLGA simulation Akpo Project J12126-RT-001 Rev 0 The jumpers will be designed with a nominal distance of 30 m from the trees to the manifold and a positioning tolerance of ± 10 m for the wells and ± 5 m on manifold position. This could result in a jumper distance of 45 m maximum or 15 m as a minimum. In order to obtain the maximum pressure and temperature drop through the jumpers, the longest distance will be considered for flow assurance simulations (45 m). Additional length is added in order to take into account the length of tree piping from production choke to tree connector interface and the dilatation lire (+ 5 m). The following layout will be input in OLGA. It does respect the distance and the top and low points. However, the exact elevation is not reproduced to limit the minimum pipe length which is time consuming for simulations (see sketch below): The modelled total length of a jumper is 70.7 m. It has to be noted that the subsea choke is considered +5 m above the mud level (i.e. the water depth). Moreover, it has to be noted that the connection tie-in (from the wellhead to the jumper) is located 4m above the mudline. The jumper layout changes during the detail phase, but the modifications are not yet been agreed on its shape, but should not have any significant impact on the thermohydraulic calculations. Indeed, its length contributes to less than 2% of the flowline and riser length. Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 17 / 45 3.5.2 Akpo Project J12126-RT-001 Rev 0 Manifold / Spool / Sled Input in OLGA simulation Manifold assembly drawing is given in refs [7, 9 & 12]. The valves of the manifold should not induce any pressure drop, but manifold header valves and dual block valve might be required to be operated from the OTS. The manifold and the flowline spool modelled in OLGA are schematised as follows. One 10-inch production branch of the manifold is represented only. For the manifolds furthest from the FPSO; manifold+spool model in OLGA will extend from the well jumper tie-in to the flowline tie-in. No pigging loop will be modelled. 3.5.3 Valves The following table gives the characteristics of the subsea and topside choke valves that will be used in the simulation. At end of life, a topside 6-inch choke valve will generate acceptable pressure drops. For start-up a 2” choke is also available topside, but currently no Cv curve is available. Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 18 / 45 Akpo Project J12126-RT-001 Rev 0 It has to be noted that the subsea choke is considered +5 m above the mud level (i.e. the water depth). 3.6 Topside Process 3.6.1 Separator Train In order to obtain optimum oil production, the oil and gas processing is based on a four stage separation scheme. The oil, associated gas and produced water from the wells are separated in a production train consisting of two 1st Stage Separators, a 2nd Stage Separator, a 3rd Stage Separator and a 4th stage Separator, operating respectively at 80 bara, 23.5 bara, 9 bara and 2 bara. Each 1st stage separator is dedicated to one production manifold and is designed for 60% of the inlet production. The oil stream from the 2nd Stage Separator is heated to about 90 °C in order to achieve the Reid Vapour Pressure (RVP) specification of crude oil-to-storage (10 psia). The liquid hydrocarbon stream is then routed to the Electrostatic Dehydrator for final water removal to meet the BS&W specification. The oil is then routed to the 4th Stage Separator for final stabilisation and is then cooled in the Crude Oil Coolers before being sent to the cargo tanks that are located in the hull for storage. The crude oil cooler are designed to provide a margin of 5 °C below the crude oil bubble point at atmospheric pressure in order to avoid any degassing in the storage tank. 3.6.2 Temperature required at first stage separator The minimum temperature at the inlet of the first stage separator is 50°C for the mix of the four production loops. The maximum is 92°C. A minimum of 48°C is required at riser choke to ensure that the 14 hours preservation sequence can be achieved as per plan. Genesis France February 2006 Akpo Total Upstream Nigeria Limited AKPO Field Development Project Project J12126-RT-001 Rev 0 Page 19 / 45 3.7 Production Lines Characteristics 3.7.1 Insulation Thermal Properties The following table summarises the characteristics of the insulation materials to be considered for the OLGA simulations (average values for the operating conditions of AKPO field). They are in line with the values given from SAIBOS. But as final design is not yet frozen, the thickness of the insulation (~550mm for the flowlines and risers, ~80mm for the jumpers) should be worked out to obtain a U value of 3.2 W/m²/K.ref. ID. The final description of the insulation will be made when the contractor will have frozen its choice. 3.7.2 Pipe Wall Thickness The following table gives the steel thickness based on preliminary UFR calculations; the following steel thickness will be used for OLGA simulations: Production Jumper Diameter Riser (mm) Clad (mm) Flowline (mm) 10-inch ID 6-inch OD 27 No 3 No 24.7 14.3 Currently, the clad section is proposed at two locations for production lines: • at the touch down point, over ± 100 m upstream and downstream the nominal touch down point (TDP) • at the riser top, over 50 m below the flexible joint. Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 20 / 45 3.7.3 Akpo Project J12126-RT-001 Rev 0 Pipe Roughness The following hydraulic roughness will be considered for the flow assurance calculations: • Roughness of the production tubing: 1.52e-5 m (15 µm) • Roughness of the jumper: 4.6e-5 m (46 µm) • Roughness of the production flow line and the riser: 4.6e-5 m (46 µm) 4 RESERVOIR AND WELL DATA 4.1 Well Architecture Ten wells architectures have been selected for AKPO field development. The architecture is summarised in the excel file: WellProgramm-december05.xls, ref [13] It has been agreed that all the 22 well profiles will not be modelled and that generic well profiles will be used for pre-defined groups of wells. These generic well profiles and corresponding groups of wells are defined as follows : Two generic well profiles for the horizontal wells : - D_P1 (to be used for wells D_P1, D_P2, D_P3, EF_P1 and EF_P2) - A9_P1 And Four generic well profiles for the vertical wells : - G_P1 (to be used for G_P1, A4_P1 and A123_P2) - G_P2 (to be used for G_P2, A568_P1, A689_P1, B_P2,) - A456_P1 (to be used for A456_P1, A456_P2, A9_P2, A123_P3) - B_P1 (to be used for B_P1, A568_P2, A123_P1, A123_P4 and A68_P1) The curves below show the well profiles for vertical and horizontal wells and highlight the above groups with corresponding generic well : Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 21 / 45 Genesis France Akpo Project J12126-RT-001 Rev 0 February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Akpo Project J12126-RT-001 Rev 0 Page 22 / 45 The table hereafter summarizes the generic well profiles that will be used in the OLGA model, reference being see surface level : D_P1 x y 0 -1359 0 -1429 37.02702 -2114 475.8345 -2721 1451.012 -3396 2380.648 -3422 G_P2 x y 0 -1354 0 -1424 0 -2034 184.1195 -2584 628.1071 -3730 A9_P1 x y 0 -1330 0 -1400 0 -1993 184.8107 -2494 674.1828 -2956 1467.208 -3012 A456_P1 x y 0 -1392 0 -1462 0 -2130 441.1632 -2846 702.0464 -3220 G_P1 x y 0 -1360 0 -1430 0 -2050 46.51881 -2590 128.1828 -3700 B_P1 x y 0 -1354 0 -1424 34.94281 -2034 463.8484 -2591 833.4495 -3189 Description of well layers as a function of well True Measured depths are summarized in APPENDIX A. The well drain and the associated sand control will not be described in OLGA. It is simply modelled by production index and a reservoir pressure. 4.2 Material Characteristics The following table summarises the thermal characteristics of the materials to be used in the well description (from the bottom hole to the wellhead). Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Akpo Project J12126-RT-001 Rev 0 Page 23 / 45 The casing architecture of each well will be modelled in OLGA. To maximise the heat loss through the casing, the surrounding soil will be modelled by a heat transfer coefficient of 10000 W/m2/°C. 4.3 Reservoir Pressures The following table gives the initial reservoir pressures that will be used in the OLGA model : Reservoirs Reservoir True Vertical Pressure Depth TVD (m) (in bara) A /B 303 3108 D / EF 357 3436 G 422 3770 4.4 Reservoir Temperatures The initial reservoir temperature depends essentially on the burial depth of the well. A model with a liner regression was used to perform this evaluation (see memo “AKPO_Fluid_temperature_Dec04.doc”): Table 1 Initial reservoir temperatures for reservoir A Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Akpo Project J12126-RT-001 Rev 0 Page 24 / 45 Table 2 Initial reservoir temperatures for reservoir B, D, EF & G 4.5 Well Productivity Indexes The values of productivity index of each well are given in the tables below. This well PI is a result of ECLIPSE software. For the vertical well (all A wells) the PI are between 250 blpd/bar to 13 000 blpd/bar but in horizontal wells (B D & EF wells) the PI could achieved 30 000 blpd/bar. Tables of Well Productivity Index Genesis France February 2006 Akpo Total Upstream Nigeria Limited AKPO Field Development Project Project J12126-RT-001 Rev 0 Page 25 / 45 4.6 Results Of reservoir Simulations Summary of the reservoir results per well is given in the tables below. Location Res A123 Res A456 Res A458 Res A678 9 A123_P 1 A123_P 2 A123_P 3 A123_P 4 M 12 A4_P1 A456_P 1 A456_P 2 A568_P 1 A568_P 2 M 12 M 12 M 22 M 12 Res B Res D Loop P10 P20 P30 P40 WC > 80% after Maximum WC at the end of well life (%) Associated liquid flowrate (blpd) Associated GOR (Sm3/m3) 16500 8200 350 year 6 - 80 13000 420 15000 7000 400 year 5 - 50 5300 300 year 8 year 11 year 8 21000 10000 320 year 3 year 5 95 1400 310 End of field life 18500 9000 390 year 5 year 11 87 6300 380 480 year 7 - 70 7000 450 6000 year 18 End of field life Year 4 22500 12500 330 year 1 year 6 95 8000 320 M 21 M 11 15000 9000 520 year 7 - 50 6200 370 9000 - 585 - - - - - M 11 Year 1 Year 3 M 21 Year 1 17500 21000 8800 8200 330 330 year 2 year 5 year 3 year 14 95 82 16000 4200 310 340 M 31 Year 2 End of field life Year 3 13500 5000 480 year 8 - 25 8000 400 M 31 Year 7 16000 8800 540 year 5 year 8 92 3200 410 M 21 Field startup Year 1 Year 8 14000 9500 340 year 4 -year 5 94 9000 360 M 32 Year 2 End of field life Year 18 18700 9000 1090 year 14 - 50 2000 320 19700 - - start up year 12 94 6600 350 29200 - - start up - 33 2000 9000 25300 - - start up - 50 3000 11000 B_P1 B_P2 D_P1 M 32 Year 4 M 21 D_P2 M 42 D_P3 M 42 Field startup Field startup Field startup Year 5 End of field life End of field life End of field life End of field life End of field life End of field life End of field life EF_P1 M 43 Year 5 EF_P2 Res G Water break through 11500 M 31 Res EF Field startup Field startup Field startup Field startup GOR peak before water break through (Sm3/m3) year 8 A9_P1 A9_P2 End of Production Minimum flowrate for water cut - 0 Year 1 Field startup Field startup Year 2 M 22 A68_P1 A689_P 1 Start of Production Maximum peak flowrate (blpd) G_P1 M 43 G_P2 M 32 Field startup Field startup 14200 1000 - start up - 0 1000 5500 29000 10000 1080 year 8 year 11 95 22000 750 28300 5000 910 start 8 year 11 95 22000 900 35100 20000 660 year 4 year 10 90 28000 580 37300 17000 600 start 3 start 5 95 15000 560 Well EF Well G Loops Nominal flow Right Header Left Header 0 0 50200 15000 35200 NA NA 6 3 3 0 61000 21000 40000 START UP Well A Flow rate (blpd) 50200 0 0 Nb of wells 6 NA NA Flow rate (blpd) 46000 0 15000 0 Well B Well D Nb of wells 5 NA 1 NA NA 6 3 3 Flow rate (blpd) 16000 7000 0 0 18400 41400 8000 33400 Nb of wells 2 1 NA NA 1 4 1 3 Flow rate (blpd) 0 0 17500 0 18400 35900 10000 25900 Nb of wells NA NA 2 NA 1 3 1 2 Genesis France February 2006 Akpo Total Upstream Nigeria Limited AKPO Field Development Project Project J12126-RT-001 Rev 0 Page 26 / 45 Loop P10 P20 P30 P40 FULL FIELD Well A Flow rate (blpd) 44500 0 0 Nb of wells 6 NA NA Flow rate (blpd) 28900 0 7500 Nb of wells 5 NA 1 Flow rate (blpd) 7000 12000 0 Nb of wells 2 2 NA Well B Well EF Well D Well G Loops Nominal flow Right Header Left Header 0 0 44500 26500 18000 NA NA 6 3 3 0 0 36400 12700 23700 NA NA 6 3 3 14000 10000 43000 24000 19000 1 1 6 3 3 Flow rate (blpd) 0 0 7500 22500 25000 55000 27000 28000 Nb of wells NA NA 2 1 1 4 2 2 The following profile for each loop is revised based on new field layout and on reservoir management with a design plateau of 185 kbopd for the produced oil and 235 kblpd for the produced liquid. The production rate from each reservoir is given in these tables with the number of producing wells on each loop considered frozen. Further details of the field production profiles of the oil, the water and the gas are given for each well and each loop is given on Appendix 1 to 4 of ref [4]. 4.6.1 All Production Loops Production rate, WC, and GOR per branch is given on the table below. See ref [4], appendix1 for details. Loop 4.6.2 P10 P20 P30 P40 Year Early Mid Late Early Mid Late Early Mid Late Early Mid Late Average Flow Rate (blpd) 50200 44500 35500 61000 36400 28400 41400 43000 42500 35900 55000 35750 Water Cut WC (%) 15 60 75 30 65 75 7 25 80 5 70 60 GOR (Sm3/m3) 480 340 340 500 1200 2500 580 650 650 450 2000 4000 Production Loop P10 Loop P10 Right Header Well Year Average Flow Rate (blpd) Water Cut WC (%) GOR (Sm3/m3) Total flow rate per branch A568-P1 Left Header A123-P1 A123-P2 A568-P2 A4-P1 A123-P4 Early Mid Late Early Mid Late Early Mid Late Early Mid Late Early Mid Late Early Mid Late 6000 6500 6500 1000 5000 4000 8000 15000 10000 10000 9000 7200 15200 8000 6800 10000 1000 1000 45 85 95 0 55 90 0 10 60 5 60 90 0 60 85 0 85 85 530 370 370 330 310 320 430 320 310 400 400 400 380 350 350 380 340 340 Genesis France 15000 26500 20500 35200 18000 February 2006 15000 Akpo Total Upstream Nigeria Limited AKPO Field Development Project Project J12126-RT-001 Rev 0 Page 27 / 45 4.6.3 Production Loop P20 Loop P20 Right Header Well A9-P2 Year Average Flow Rate (blpd) Water Cut WC (%) GOR (Sm3/m3) Total flow rate per branch 4.6.4 A456-P1 D-P2 A68-P1 A123-P3 Early Mid Late Early Mid Late Early Mid Late Early Mid Late Early Mid Late Early Mid Late 5000 3200 2000 6000 2000 1000 10000 7500 6500 15000 7500 3500 15000 8500 8000 10000 7700 7400 20 90 90 0 45 70 35 70 90 0 7 7 5 70 85 40 88 90 350 360 360 450 370 370 380 370 370 600 2500 3700 350 350 350 350 350 350 21000 12700 9500 40000 23700 18900 Production Loop P30 Loop P30 Right Header Well EF-P2 Year Average Flow Rate (blpd) Water Cut WC (%) GOR (Sm3/m3) Total flow rate per branch 4.6.5 Left Header A456-P2 Left Header A689-P1 B-P1 A9-P1 B-P2 G-P2 Early Mid Late Early Mid Late Early Mid Late Early Mid Late Early Mid Late Early Mid Late 0 14000 27000 8000 2000 2000 0 8000 5000 8000 5000 2000 7000 4000 2000 18400 10000 4500 0 0 85 0 50 90 0 40 70 0 53 70 0 15 30 15 90 90 0 900 800 480 350 350 0 330 320 1000 380 380 600 550 350 580 580 580 8000 24000 34000 33400 19000 8500 Production Loop P40 Loop P40 Right Header Well Left Header D-P1 Year Average Flow Rate (blpd) Water Cut WC (%) GOR (Sm3/m3) Total flow rate per branch 10000 Note: Genesis France EF-P1 D-P3 G-P1 Early Mid Late Early Mid Late Early Mid Late Early Mid Late 10000 4500 2500 0 22500 12250 7500 3000 1000 18400 25000 20000 0 0 0 0 70 95 0 0 0 0 65 80 500 4500 5500 0 800 800 480 5000 20000 580 580 580 27000 Early 14750 Mid 25900 28000 21000 Late February 2006 Akpo Total Upstream Nigeria Limited AKPO Field Development Project Page 28 / 45 Project J12126-RT-001 Rev 0 5 FLUID COMPOSITION A first model will consider an average composition consistent to the HYSYS model for topside simulations. Same composition will be attributed to all wells and is given below (from ref 16): Average well fluid composition used in HYSYS simulations Genesis France February 2006 Akpo Total Upstream Nigeria Limited AKPO Field Development Project Project J12126-RT-001 Rev 0 Page 29 / 45 Below is given the hypothetical component data: Name C6* C7* C8* C9* C10* C11*+ C12* C13* C14* C15* C16* C17* C18*+ C19* CN2* CN3* NBP (°C) 69.11 99.25 126.3 151.9 174.3 188.7 204.6 217.6 233 253.1 269.7 287.9 300.9 313.5 370.6 498.3 Genesis France Mol Wt 85.11* 98.40* 111.7* 125.2* 137.8* 149.0* 163.0* 176.0* 191.0* 207.0* 221.0* 237.0* 249.0* 261.0* 320.0* 475.0* Liq Density (kg/m3) 685.0* 722.0* 745.0* 764.0* 778.0* 789.0* 800.0* 811.0* 822.0* 832.0* 839.0* 847.0* 852.0* 857.0* 877.0* 914.0* Tc (°C) 240.0* 280.0* 310.0* 345.0* 385.0* 390.0* 402.0* 417.0* 435.0* 452.0* 467.0* 480.0* 470.0* 480.0* 644.0* 800.0* Pc (bar) Vc Acentricity (m3/kgmole) 32.73* 30.97* 28.42* 27.24* 26.50* 24.82* 23.42* 22.24* 21.09* 19.93* 19.05* 18.20* 17.30* 16.80* 16.70* 14.25* 0.3800* 0.4300* 0.5000* 0.5300* 0.5600* 0.6269* 0.6858* 0.7405* 0.8036* 0.8710* 0.9299* 0.9972* 1.048* 1.098* 1.141* 1.565* 0.2590* 0.2790* 0.3250* 0.3440* 0.3780* 0.3960* 0.4140* 0.4320* 0.4590* 0.4770* 0.5040* 0.5220* 0.5400* 0.5490* 0.7700* 0.9200* February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 30 / 45 Akpo Project J12126-RT-001 Rev 0 In addition to that typical case, a more accurate model will be built based on true composition per well. Throughout the lifetime of the AKPO field, the compositions of the different reservoirs evolve significantly see ref [8]. This is particularly true for the reservoir panels supported by gas injection, where the GOR varies from around 300 Sm³/Sm³ to around 8000 Sm³/Sm³ over the field life. In order to perform representative characterisation of flowing conditions throughout the lifetime of the AKPO field, three compositions were selected for each well type (A; B; D; EF; G) to represent early, mid and late field life. The reservoir fluid is complex, varying from gas/condensate at the top of the reservoir to light oil at the base. During field life, the fluids produced from the reservoir panels supported by water injection will become heavier with time (hydrocarbon produced from the top, with water injected at the base). On the contrary fluids produced from reservoir panels supported by gas injection will become lighter with time, with a high potential for gas breakthrough to occur. • For reservoirs supported by water injection, compositions were taken from the Top, Middle and Bottom of the reservoir to represent Early, Mid and Late Life. • For reservoirs supported by gas injection (D type wells), compositions were taken from the Bottom of the reservoir for Early Life. For Mid Life, the composition was taken from a reservoir depth yielding a GOR of around 3000 Sm³/Sm³. For Late Life, the composition was provided with a corresponding GOR of around 8000 Sm³/Sm³, as this period covers operation following gas breakthrough and the composition cannot be directly derived from the PVT analysis. The molar compositions (on a dry basis) for each well type are provided in the following table, completed with the corresponding GORs. Note: The water cut of the produced fluid is determined from the production profiles of each well (see chapter above). Regarding the GOR, it is important to note that the average GOR value for A wells (<500 Sm3/m3) resulting from this composition is largely below the one issued from the reservoir simulation that reaches up to 970 Sm3/m3 for some A wells. Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 31 / 45 Akpo Project J12126-RT-001 Rev 0 For reservoir A and G, latest reservoir shall be used and the fluid composition for these two wells are summarized hereafter : Genesis France February 2006 Akpo Total Upstream Nigeria Limited AKPO Field Development Project Project J12126-RT-001 Rev 0 Page 32 / 45 Well type A Depth Early Mid Later mSL -3040 -3160 -3300 N2 0.105 0.100 0.095 CO2 C1 C2 C3 IC4 NC4 IC5 NC5 C6 C7 C8 C9 C10 C11 C12 C13 C14 C15 C16 C17 C18 C19 0.135 62.544 7.704 4.360 1.609 2.066 1.393 0.982 2.867 3.367 2.653 2.008 1.769 1.088 0.885 0.858 0.726 0.535 0.440 0.344 0.277 0.258 0.120 59.633 6.880 4.463 1.647 2.115 1.521 1.073 3.130 3.676 2.896 2.372 2.090 1.285 1.045 1.013 0.902 0.665 0.546 0.427 0.344 0.320 0.106 56.928 6.036 4.522 1.669 2.142 1.625 1.146 3.344 3.927 3.094 2.701 2.379 1.463 1.190 1.154 1.068 0.787 0.646 0.506 0.407 0.379 CN2 0.593 0.928 1.337 CN3 0.432 0.809 1.349 Total 100 100 100 Table 3 Fluid composition for reservoir A Genesis France February 2006 Akpo Total Upstream Nigeria Limited AKPO Field Development Project Project J12126-RT-001 Rev 0 Page 33 / 45 Wel type G Depth Early Mid Later mSL -3644 -3674 -3694 N2 0.078 0.077 0.075 CO2 C1 C2 C3 IC4 NC4 IC5 NC5 C6 C7 C8 C9 C10 C11 C12 C13 C14 C15 C16 C17 C18 C19 0.918 64.063 8.500 5.134 1.692 1.955 1.420 0.983 2.737 3.153 1.819 1.805 1.403 0.787 0.609 0.600 0.427 0.344 0.275 0.224 0.217 0.167 0.915 62.507 8.479 5.200 1.713 1.980 1.494 1.034 2.880 3.318 1.914 1.980 1.540 0.863 0.668 0.658 0.482 0.389 0.310 0.252 0.245 0.188 0.913 61.449 8.458 5.237 1.726 1.994 1.542 1.068 2.973 3.425 1.976 2.100 1.633 0.915 0.708 0.698 0.520 0.420 0.335 0.273 0.264 0.203 CN2 0.434 0.555 0.650 CN3 0.260 0.361 0.447 Total 100 100 100 Table 4 Fluid composition for reservoir G Note: The above compositions have been extracted from the PVT Synthesis report of Jan 2006, for different reservoir depths, in order to obtain compositions corresponding to Early, Mid and Late Life operation. Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 34 / 45 Akpo Project J12126-RT-001 Rev 0 6 SCOPE OF WORK The main objectives of this first study are to build a dynamic model using the design basis described previously, and to perform several OLGA runs in steady state and transient conditions to ensure that the model is working correctly and give results similar to what was found during Basic Engineering. 6.1 Software The following software will be used: PVTsim version 4.15.0 in order to characterise the fluids and create the PVT tables OLGA 2000 standard version 3.02 was used during basic engineering. But the new release 4.16 was bench mark during FA impact due to the new layout [4]. This revision as well as 4.17.3 can be used for the multiphase flow dynamic simulations. Compositional and slug tracking options will have to be available when required. 6.2 OLGA Model Four OLGA models will be built, one for each production loop P10, P20, P30 and P40. Hence the all production network will be modelled. Each OLGA model will include wells, jumpers, manifolds, spools, flowlines, risers, subsea chocke valves at each wellhead and topsides choke valves at each riser top. All the production wells will be modelled with the WELL keyword in OLGA by using the following parameters : reservoir Static Bottom Hole Pressures, reservoir temperatures and reservoir productivity indexes. In the simulations, the required flowrate per well will be obtained by adding a controller at wellhead that will act on the subsea choke opening. Topside pressure will be fixed at 80 bara at the FPSO (pressure at the first stage separator at early field life). The model will be built to allow easy update/modification of most critical parameters which are likely to change during the project phase :production modification, well allocation to branches, branches allocation to manifolds (production or test), etc… For that purpose it is proposed to provide a detailed description of the OLGA input files in order to quickly identify where the required modifications need to be performed. The PVT tables needed to perform the simulations described in § 6.3 will be built based on the reservoir composition given in the design premise. Equation of state Peng Robinson with Peneloux volume correction will be used, and Corresponding States (CSP) for viscosity correlation. The fluid GOR and water cut will be tuned to meet the values given in the production profile per well. Genesis France February 2006 Akpo Total Upstream Nigeria Limited AKPO Field Development Project Project J12126-RT-001 Rev 0 Page 35 / 45 It is also highlighted that all the required modifications to be performed on the OLGA subsea modelling prior to its link to the topside HYSYS model will be performed by the topside dynamic simulation contractor (modification/addition of OLGA output variables, modification of topside arrangement…). It is not considered part of this scope to prepare the model to take these changes into considerations. 6.3 OLGA 2000 Simulations Aim of the simulations presented below is to ensure that the OLGA models are working correctly in typical steady state and transient scenarios. Sequences and timing of the simulations have been fixed arbitrary and do not correspond necessarly to the AKPO preservation and operating procedures. Review and optimisation of these procedures could be further addressed in a separated scope. The following simulations will be performed with the models : 6.3.1 Steady State Runs The following steady state cases will be performed, selected to be representative of early field life: Loop P10 Right Header Left Header Well A568-P1 A123-P1 A123-P2 A568-P2 A4-P1 A123-P4 Year Average Flow Rate (blpd) Early Early Early Early Early Early 6000 1000 8000 10000 15200 10000 Water Cut WC (%) 45 0 0 5 0 0 GOR (Sm3/m3) 530 330 430 400 380 380 Loop P20 Right Header Left Header Well A9-P2 A456-P2 A456-P1 D-P2 A68-P1 A123-P3 Year Average Flow Rate (blpd) Early Early Early Early Early Early 5000 6000 10000 15000 15000 10000 Water Cut WC (%) 20 0 35 0 5 40 GOR (Sm3/m3) 350 450 380 600 350 350 Loop P30 Right Header Left Header Well EF-P2 A689-P1 B-P1 A9-P1 B-P2 G-P2 Year Average Flow Rate (blpd) Early Early Early Early Early Early 0 8000 0 8000 7000 18400 Water Cut WC (%) 0 0 0 0 0 15 GOR (Sm3/m3) 0 480 0 1000 600 580 Loop P40 Right Header Left Header Well D-P1 EF-P1 D-P3 G-P1 Year Average Flow Rate (blpd) Early Early Early Early 10000 0 7500 18400 Water Cut WC (%) 0 0 0 0 GOR (Sm3/m3) 500 0 480 580 Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 36 / 45 Akpo Project J12126-RT-001 Rev 0 After presenting the results for the early field life, TOTAL may require results for Mid and Later field life. In a first approach these cases are considered optional and will be the subject for a variation. Results of these simulations will be compared against results of the Basic Engineering. Acceptance criteria for this benchmark exercise will be further discussed with TOTAL once results are available. 6.3.2 Branch Packing The branch packing simulations will be performed from a restart of the above steady state cases. The simulation sequence for the branch packing will be to close the topsides choke valves over 30 seconds allowing the wells to continue flowing by keeping the production wing and production choke valve open. This caused the wells to pack the branch. For these simulations, controlers will be removed from the model and wellhead valve opening will be set at the one defined by the controllers in the steady state runs. 6.3.3 Cooldown The cooldown simulations will be performed from a restart of the above branch packing cases. The simulations will allow the pipeline to settle out and cooldown for a duration fixed at 14 hours. 6.3.4 Depressurisation The depressurisation simulations will be performed from a restart of the above cooldown cases. Target pressure of this depressurisation will be fixed at 20 bara at topside and depressurisation rate will be adjusted in order to depressurise each loop in one hour. However depressurisation of each loop is initiated in sequence. The depressurisation sequence of all loops will last less than 3 hours. The simulations will utilise the LEAK function of OLGA with a fixed size orifice. Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 37 / 45 6.3.5 Akpo Project J12126-RT-001 Rev 0 Start-up sequence Start-up simulations will be performed from a restart of the above depressurisation cases. Wells will be started-up in sequence with a ramp-up time of 3 hours to reach the well nominal flowrates defined in § 6.3.1 (steady state nominal flowrates at early field life). As for steady state cases, topsides pressure will be fixed at 80 bara. Usually this kind of simulations, where several wells with different fluid compositions are brought into production, require the use of OLGA compositional tracking module (fluid composition not constant in the production loop). However as this start-up sequence is just simulated to ensure that the model is working correctly, it is proposed that PVT files of steady state simulations (§6.3.1) are used to simulate the start-up sequence. Use of compositional tracking module could be considered in a separate scope if review and optimisation of operating procedures is requested afterwards. 6.3.6 Slugging analysis Simulations will be performed to determine the extent of slugging in the production flowlines and risers. In addition to assessing slugging at production profile rates at early field life (§ 6.3.1), the minimum turndown rate that avoid slugging issues will be established for the four production loops. In the OLGA model, wells and jumpers will be removed and flowrates will be applied at manifolds. OLGA slugtracking option will be used for these simulations. It is highlighted that only early field life will be studied within the scope of this study. Mid and late field life will have to be studied separately. This model may be used by others (OCWR contractor) to investigate the slug control aspect. 6.4 Deliverables The deliverables of this study will be : Four models of the subsea production network : P10, P20, P30, and P40 A list of the available runs with a description and potential case associated File descriptions Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Project J12126-RT-001 Rev 0 Page 38 / 45 6.5 Akpo Schedule This study could be started as soon as both parties agree on this design premise. The OLGA model should be made available to Topside simulation sub-contractor to be interfaced with topside simulations, and also to support the OTS (Operator Training Simulator) scope. Planned duration for this scope of work : Genesis France 9 weeks February 2006 Akpo Total Upstream Nigeria Limited AKPO Field Development Project Page 39 / 45 Project J12126-RT-001 Rev 0 APPENDIX A Generic Well Layer Descriptions Genesis France February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 40 / 45 Genesis France Akpo Project J12126-RT-001 Rev 0 February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 41 / 45 Genesis France Akpo Project J12126-RT-001 Rev 0 February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 42 / 45 Genesis France Akpo Project J12126-RT-001 Rev 0 February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 43 / 45 Genesis France Akpo Project J12126-RT-001 Rev 0 February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 44 / 45 Genesis France Akpo Project J12126-RT-001 Rev 0 February 2006 Total Upstream Nigeria Limited AKPO Field Development Project Page 45 / 45 Genesis France Akpo Project J12126-RT-001 Rev 0 February 2006
0
You can add this document to your study collection(s)
Sign in Available only to authorized usersYou can add this document to your saved list
Sign in Available only to authorized users(For complaints, use another form )