Program on Technology Innovation: Grid Operation with 100% Inverter-Based Resources Final Report 2019 TECHNICAL REPORT 0 0 Program on Technology Innovation: Grid Operation with 100% Inverter-Based Resources Final Report EPRI Project Manager E. Farantatos 3420 Hillview Avenue Palo Alto, CA 94304-1338 USA PO Box 10412 Palo Alto, CA 94303-0813 USA 800.313.3774 650.855.2121 3002014775 Final Report, January 2019 askepri@epri.com www.epri.com 0 DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES THIS DOCUMENT WAS PREPARED BY THE ORGANIZATION(S) NAMED BELOW AS AN ACCOUNT OF WORK SPONSORED OR COSPONSORED BY THE ELECTRIC POWER RESEARCH INSTITUTE, INC. (EPRI). NEITHER EPRI, ANY MEMBER OF EPRI, ANY COSPONSOR, THE ORGANIZATION(S) BELOW, NOR ANY PERSON ACTING ON BEHALF OF ANY OF THEM: (A) MAKES ANY WARRANTY OR REPRESENTATION WHATSOEVER, EXPRESS OR IMPLIED, (I) WITH RESPECT TO THE USE OF ANY INFORMATION, APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM DISCLOSED IN THIS DOCUMENT, INCLUDING MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE, OR (II) THAT SUCH USE DOES NOT INFRINGE ON OR INTERFERE WITH PRIVATELY OWNED RIGHTS, INCLUDING ANY PARTY'S INTELLECTUAL PROPERTY, OR (III) THAT THIS DOCUMENT IS SUITABLE TO ANY PARTICULAR USER'S CIRCUMSTANCE; OR (B) ASSUMES RESPONSIBILITY FOR ANY DAMAGES OR OTHER LIABILITY WHATSOEVER (INCLUDING ANY CONSEQUENTIAL DAMAGES, EVEN IF EPRI OR ANY EPRI REPRESENTATIVE HAS BEEN ADVISED OF THE POSSIBILITY OF SUCH DAMAGES) RESULTING FROM YOUR SELECTION OR USE OF THIS DOCUMENT OR ANY INFORMATION, APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM DISCLOSED IN THIS DOCUMENT. REFERENCE HEREIN TO ANY SPECIFIC COMMERCIAL PRODUCT, PROCESS, OR SERVICE BY ITS TRADE NAME, TRADEMARK, MANUFACTURER, OR OTHERWISE, DOES NOT NECESSARILY CONSTITUTE OR IMPLY ITS ENDORSEMENT, RECOMMENDATION, OR FAVORING BY EPRI. THE FOLLOWING ORGANIZATIONS PREPARED THIS REPORT: Electric Power Research Institute (EPRI) Washington State University NOTE For further information about EPRI, call the EPRI Customer Assistance Center at 800.313.3774 or e-mail askepri@epri.com. Electric Power Research Institute, EPRI, and TOGETHER…SHAPING THE FUTURE OF ELECTRICITY are registered service marks of the Electric Power Research Institute, Inc. Copyright © 2019 Electric Power Research Institute, Inc. All rights reserved. 0 Acknowledgments The Electric Power Research Institute (EPRI) prepared this report. Principal Investigators D. Ramasubramanian Q. Wang E. Farantatos A. Tuohy E. Ela The following organization, under contract to the Electric Power Research Institute (EPRI), contributed to this report: Washington State University Pullman, WA, 99163 Principal Investigators A. Mehrizi-Sani This report describes research sponsored by EPRI. This publication is a corporate document that should be cited in the literature in the following manner: Program on Technology Innovation: Grid Operation with 100% InverterBased Resources: Final Report. EPRI, Palo Alto, CA: 2018. 3002014775. iii 0 0 Abstract The electric power system, once dominated by traditional synchronous generation, is experiencing a shift toward an increased share of power electronics interfaced generation. This shift is mainly due to increased integration of variable renewable energy resources, such as wind and solar photovoltaic, which use power electronic based inverters. Several R&D efforts in the industry are presently investigating the challenges of grid operation with high levels of inverter based resources (IBR), however whether or not a bulk power system can operate and how it could operate with 100% generation from IBR, i.e. without any synchronous generation, remains an open question. In such a scenario, maintaining the reliability of the bulk power system would require complex planning and operation paradigms. This project investigates the operation and associated reliability implications of an all inverter-interfaced generation system, given the new operational features and challenges of such a system (e.g. no inertia, no synchronizing torque, limited short circuit capacity, no physical link between load/generation and frequency, etc.). The work first investigates the dynamic and stability performance of an all inverter bulk power system. The definition of frequency in a 100% inverter based system is discussed, and a constant frequency operational paradigm is introduced. New inverter controls have been designed to support such a grid, and corresponding models in both positive sequence, as well as three-phase EMT simulation platforms, have been developed to investigate power sharing among generating units and voltage and frequency response of the grid under system disturbances. The performance of the proposed inverter controls and their interactions with synchronous machine controls are also evaluated under IBR dominated systems and operational conditions in which only a small portion of generation is provided by conventional rotating generators. The work also investigates steady state and balancing operation of a 100% variable energy resource system. Production cost simulations for operating scenarios with 100% energy provided by IBR for temporal intervals during a day have been performed, and the impact of curtailment and reserve determination strategies is analyzed. The applicability of traditional unit commitment and economic dispatch v 0 frameworks is also discussed. Some aspects of market operations with focus on the behavior of electricity price are also presented. The work conducted under this project is considered foundational towards a multi-year R&D plan that is expected to be executed under various Electric Power Research Institute (EPRI) projects in the near future. This project does not intend to answer all of the questions for such a wide and futuristic R&D topic, rather it raises open questions, presents ideas and conceptual designs for potential operating schemes, and demonstrates their performance and applicability through simulations on large scale synthetic bulk power systems. Keywords Inverter Grid forming Renewable resources Constant frequency Resource uncertainty vi 0 EXECUTIVE SUMMARY Deliverable Number: 3002014775 Product Type: Technical Report Product Title: Program on Technology Innovation: Grid Operation with 100% InverterBased Resources: Final Report PRIMARY AUDIENCE: Transmission Operations and Planning Engineers and Executives KEY RESEARCH QUESTION The power grid is experiencing a continuously increasing penetration of generating units that are interfaced to the system through power electronics, the majority of which are renewable energy resources. Several R&D efforts in the industry are presently investigating the challenges of grid operation with high levels of renewable resources, however whether or not the system can operate and how it could operate with 100% generation from inverter based resources (IBR), i.e. without any synchronous generation, remains an open question. In such a scenario, maintaining the reliability and stability of the bulk power system would require complex planning and operation paradigms. This project investigates the operation and associated reliability implications of an all inverter-interfaced generation system given the new operational features and challenges of such a system (no inertia, no synchronizing torque, limited short circuit capacity, no physical link between load/generation and frequency, etc.). RESEARCH OVERVIEW The work first investigates the dynamic and stability performance of an all inverter bulk power system. The definition of frequency in such a system is discussed, and an operating paradigm referred to as constant frequency operation is introduced. The viability and system reliability of constant frequency operation with respect to stability performance are evaluated based on detailed inverter models and associated inverter controls that have been developed and used in various simulation scenarios. A phase angle based droop scheme is proposed to ensure adequate power sharing among all available resources upon a generation/load imbalance event. Realizing that an all IBR system might be too far in the future, more realistic scenarios of inverter dominated systems with small percentages of energy provided by rotating generators are also studied. The work also investigates steady state and balancing operation of a 100% variable energy resource system. Production cost simulations for operating scenarios with 100% energy provided by IBR for temporal intervals during a day have been performed, and the impact of curtailment and reserve determination strategies is analyzed. The applicability of traditional unit commitment and economic dispatch frameworks is also discussed. Some aspects of market operations with focus on the behavior of electricity price are also presented. KEY FINDINGS • Frequency definition: In a 100% IBR system, the physical link between generation/load and frequency is lost due to the power electronics interface between the grid and the energy generating source • Constant frequency operation that restores frequency to nominal within a few seconds • Design of grid forming inverter controls that perform power sharing among inverter based resources • Investigation of steady-state balancing and dispatch operations for time periods with very high penetrations of variable energy resources (VERs), using state-of-the-art production cost modeling/tools vii 0 EXECUTIVE SUMMARY WHY THIS MATTERS Several regions/states internationally are setting targets of 100% energy production from renewable/clean sources within the next few decades. It is expected that in the future, system operators will have to manage and securely operate the system for periods of the day with 100% energy provided by VERs, with possible operating conditions in which all the energy may be produced by IBR. This report addresses the challenges and associated reliability implications of operating such a transmission grid. HOW TO APPLY RESULTS The insights and learnings from this report can be used to guide future research on the topic of grid operation with 100% variable and inverter based resources. LEARNING AND ENGAGEMENT OPPORTUNITIES The work conducted under this project is considered foundational towards a multi-year R&D plan that is expected to be executed under various Electric Power Research Institute (EPRI)projects in the near future. This project does not intend to answer all of the questions for such a wide and futuristic R&D topic, rather it raises open questions, presents ideas and conceptual designs for potential operating schemes, and demonstrates their performance and applicability through simulations on largescale synthetic bulk power systems. EPRI CONTACTS: Evangelos Farantatos, Senior Technical Leader, efarantatos@epri.com PROGRAM: Technology Innovation Together...Shaping the Future of Electricity® Electric Power Research Institute 3420 Hillview Avenue, Palo Alto, California 94304-1338 • PO Box 10412, Palo Alto, California 94303-0813 USA 800.313.3774 • 650.855.2121 • askepri@epri.com • www.epri.com © 2019 Electric Power Research Institute (EPRI), Inc. All rights reserved. Electric Power Research Institute, EPRI, and TOGETHER...SHAPING THE FUTURE OF ELECTRICITY are registered service marks of the Electric Power Research Institute, Inc. 0 Table of Contents Abstract ................................................................. V Executive Summary .............................................. VII Section 1: Introduction ........................................ 1-1 Section 2: Inverter Modeling and Constant Frequency Operation of an All Inverter System .................................. 2-1 Background ............................................................... 2-1 Constant Frequency Operational Paradigm ................... 2-2 Grid Forming Inverter Positive Sequence Modeling ........ 2-3 Voltage & Current Controlled Grid Forming Inverter ................................................................ 2-4 Constant Frequency Operation - Demonstrating Results - 433-Machine 2000-Bus System ....................... 2-5 Case 1: Grid Forming Inverter Operation ................ 2-5 Case 2: Under Frequency Trip ............................... 2-7 Case 3: Variation in Size, Location and Number of Grid Forming Inverters ..................................... 2-10 Case 4: Topology Change................................... 2-11 Inverter Based Resources Dominated Grid ................... 2-12 Modularized Constant Frequency Inverter Positive Sequence Models .................................... 2-13 IBR Dominated System - Demonstrating Results - 433Machine 2000-Bus System ........................................ 2-15 Scenario 1: System Operation for a Generation Loss Event .......................................................... 2-16 Scenario 2: Change in Power Command from the System Operator ........................................... 2-30 Scenario 3: Line fault followed by outage of the line ................................................................... 2-33 Section 3: Three-Phase Inverter Models for Constant Frequency Operation ............ 3-1 Inverter Controls ......................................................... 3-1 Inverter Control Objectives..................................... 3-1 Voltage Magnitude Controller ................................ 3-2 ix 0 Real Power Sharing Algorithm ................................ 3-3 Angle Droop Algorithm ......................................... 3-5 Parameter Design ................................................. 3-7 Simulation Case Studies .............................................. 3-8 Step Change in Pgs, i* and |vgs, i*| ..................... 3-10 Load Increase ..................................................... 3-10 Dynamic Loads ................................................... 3-11 Power Redispatch ............................................... 3-12 Fault .................................................................. 3-13 Performance Evaluation in the Presence of Synchronous Generation ........................................... 3-14 Synchronous Generator Connection ...................... 3-15 Load Change ..................................................... 3-16 Fault .................................................................. 3-18 Power Dispatch .................................................. 3-18 Effect of Controller Gains on the Oscillation Frequency of the SG ................................................. 3-19 Natural Frequencies of the Shaft System ................ 3-20 Changing Control Gains and Their Impacts on the Oscillation Frequency of the System ................. 3-22 Performance Comparison Between Three-Phase and Positive-Sequence Inverter Models .............................. 3-25 Section 4: Balancing and Market Operations of an All Inverter System .................... 4-1 System Operation with 100% VER During Some Periods of a Week ..................................................... 4-2 Test System and Data Used .................................... 4-2 Results for Case with No Reserves .......................... 4-5 Selection of Curtailment Resources .......................... 4-9 Electricity Price Behavior ...................................... 4-11 Effects of Enabling Technologies ........................... 4-16 Determination and Impact of Reserve Requirements ...................................................... 4-19 Conceptual Discussion of Electric Power Systems with 100% VER and Without Dispatchable Thermal Resources ................................................................ 4-25 Change of SCUC and SCED Models .................... 4-25 Change of Reserve Determination Method ............. 4-26 Electricity Market Design Evolution ........................ 4-27 Section 5: Summary and Future Work ................ 5-1 Section 6: References .......................................... 6-1 x 0 Appendix A: Test Case and Scenarios for Chapter 4 ........................................... A-1 Test System Description ............................................... A-1 Test Scenarios Description ........................................... A-1 xi 0 0 List of Figures Figure 1-1 Operating paradigm evolution of power system with inverter based resources ............................ 1-1 Figure 2-1 Definition and physical links of electrical frequency in a conventional system .............................. 2-1 Figure 2-2 Definition and physical links of electrical frequency in an all inverter system................................ 2-2 Figure 2-3 System frequency response for a conventional system and for an all inverter system with different types of inverter controls ............................................. 2-3 Figure 2-4 Controlled grid forming inverter positive sequence model schematic .......................................... 2-5 Figure 2-5 Frequency and angle droop schematic in grid supporting inverter ..................................................... 2-6 Figure 2-6 Comparison of change in mean system frequency with and without a grid forming inverter ........ 2-6 Figure 2-7 Voltage magnitude in the system with and without a grid forming inverter..................................... 2-7 Figure 2-8 Mean system frequency for the stressed system ...................................................................... 2-8 Figure 2-9 Bus voltage magnitude for the stressed system ..... 2-8 Figure 2-10 Mean system frequency for the stressed system with generator curtailment and load shedding ... 2-10 Figure 2-11 Mean system frequency with varying location, number & size of grid forming inverter .......... 2-11 Figure 2-12 Change in power output in Areas 2, 5 & 8 for a 500kV line trip in Area 5 .................................. 2-12 Figure 2-13 Modularized control structure with voltage source interface ....................................................... 2-13 xiii 0 Figure 2-14 Modularized control structure with current source interface ....................................................... 2-13 Figure 2-15 User defined active power controller structure .................................................................. 2-14 Figure 2-16 Average electrical frequency across the entire system for two generation trip events ................. 2-16 Figure 2-17 Average frequency in each area in Case 1 for two generation trip event ..................................... 2-17 Figure 2-18 Average frequency in each area in Case 2 for two generation trip event ..................................... 2-18 Figure 2-19 System electrical frequency in the immediate aftermath of two generation trip event ........................ 2-18 Figure 2-20 Geographic view of the test system ................ 2-20 Figure 2-21 Total active power from all inverter resources in Area 5, for a two generation trip ............. 2-22 Figure 2-22 Total active power from all inverters resources in Area 5, when controlled as a current source and voltage source, for two generation trip ....... 2-23 Figure 2-23 System average electrical frequency for simultaneous trip of both generators ........................... 2-25 Figure 2-24 Total active power in area 5 and 8 for simultaneous trip of both generators ........................... 2-25 Figure 2-25 Minimum voltage across the system for simultaneous trip of both generation ........................... 2-27 Figure 2-26 Total active power in areas 5 and 2 for the simultaneous trip of both generation ........................... 2-27 Figure 2-27 Minimum voltage across the system for a change in headroom ................................................ 2-28 Figure 2-28 Total active power in areas 5 and 2 with the inclusion of tie line deviation control signal ............ 2-29 Figure 2-29 Change in power output in areas 5 and 2 to a change in system operator command ................... 2-31 Figure 2-30 Total power output from areas 5 and 2 for a change in active and reactive power load, along with change in power reference................................. 2-32 xiv 0 Figure 2-31 Total power output from areas 5 and 2 for a change in only active power load, along with change in power reference ....................................... 2-33 Figure 2-32 Minimum voltage in the system for a line fault on an internal area line followed by outage of the line ................................................................... 2-34 Figure 2-33 Reactive power output of a inverter located close to the fault ....................................................... 2-35 Figure 2-34 Minimum voltage in the system for a line fault on a tie line followed by outage of the line .......... 2-36 Figure 2-35 Minimum voltage in the system for a line fault on a tie line followed by outage of the line, with few voltage source inverters ...................................... 2-36 Figure 3-1 Generic unit i interfaced to the power system. ..... 3-2 Figure 3-2 Overall structure of the proposed controller. ........ 3-2 Figure 3-3 Proposed voltage magnitude controller and current limiter............................................................. 3-2 Figure 3-4 Proposed real power controller. ......................... 3-3 Figure 3-5 A sample two-bus system. ................................. 3-4 Figure 3-6 Vector diagrams of the two-bus system in operating conditions (a) grid-forming unit is large (see text for definition); (b) grid-forming unit is limited; and (c) grid-forming unit is limited and brings δgft to zero...................................................... 3-5 Figure 3-7 (a) proposed angle droop; (b) conventional frequency droop. ....................................................... 3-6 Figure 3-8 Proposed real power sharing algorithm; (a) grid-forming unit; and (b) grid-supporting units. ............. 3-7 Figure 3-9 Vector diagrams of the generation units in the steady state when the grid-forming unit is (a) large (see text for definition); and (b) limited.......................... 3-8 Figure 3-10 Study system. ................................................ 3-9 Figure 3-11 Measurements as (a) Pgs, 3* changes from 85 to 120 MW at t=0.3 s; (b) vgs, 1* changes from 1.026 to 1.040 pu at t=1.3 s. .................................. 3-10 xv 0 Figure 3-12 Generation units measurements for the system with a (a) large (compared with load demand) grid-forming unit; (b) small grid-forming unit. In both systems, the load at bus 6 increases by 15 MW at t=1 s and the load at bus 5 increases by 80 MW at t=3 s. ..................................................... 3-11 Figure 3-13 Measurements of buses 1-3 and machine loads as IM1 changes from no-load to full-load at t=1 s and IM2 changes from no-load to full-load at t=3 s....................................................................... 3-12 Figure 3-14 Measurements at buses 1—3 when Pgf, max decreases from 192 MW to 120 MW at t=2 s. ........... 3-13 Figure 3-15 Measurements at buses 1—3 when a fault occurs at t=1.0 s and clears after 100 ms; (a) with the current limiter; (b) without. ................................... 3-14 Figure 3-16 Modified IEEE/WSCC 9-bus system. .............. 3-15 Figure 3-17 Performance of the controller when the SG is connected to the system. ........................................ 3-16 Figure 3-18 Performance of the controllers when the load at bus 6 increases by 20 MW at t=2 s and the load at bus 5 increases by 70 MW at t=4 s. ............... 3-17 Figure 3-19 Performance of the controllers when a threephase bolted fault occurs at t=1 s at the middle of the transmission line between bus 8 and bus 9. ........... 3-18 Figure 3-20 Performance of the controllers in a case of changing P*gs,1 and P*gs,3 ........................................... 3-19 Figure 3-21 Structure of a typical lumped –mass system model [3-1] ............................................................. 3-20 Figure 3-22 Real power of the system components and zoom-ins. (a) the real power of three inverters and the SG (b) the oscillation frequency of the real power of GS unit (c) the oscillation frequency of the real power of the GF unit (d) the oscillation frequency of the real power SG.................................................... 3-24 Figure 3-23 From top to bottom: Real powers of generation units, bus voltages of generation units, and system frequency measured at the buses of generation units in (a) PSPS method and (b) the proposed method. .................................................... 3-25 xvi 0 Figure 4-1 Comparison of VG and load in case 1 and case 2 as the input data in DA .................................... 4-4 Figure 4-2 Comparison of VG and load in case 1 and case 2 as the input data in RT...................................... 4-5 Figure 4-3 Real-time VER penetration percentages for different scenarios ...................................................... 4-6 Figure 4-4 Real-time thermal energy percentages for different scenarios ...................................................... 4-7 Figure 4-5 Comparing the load and VER production in real-time for one day ................................................ 4-10 Figure 4-6 Curtailment for wind resources in one day ........ 4-11 Figure 4-7 Curtailment for PV resources in one day ........... 4-11 Figure 4-8 DA LMP in one-week period in the system ......... 4-14 Figure 4-9 RT LMP in one-week period for case 4 .............. 4-15 Figure 4-10 Comparing LMPs with and without energy storage resources ..................................................... 4-18 Figure 4-11 A comparison of hourly aggregated operation costs in RT for one week ............................. 4-18 Figure 4-12 A comparison of the renewable energy percentage with and without operating reserves for case 4 .................................................................... 4-21 Figure 4-13 Comparison of the original case with the new case that allows renewables to provide reserves ... 4-23 Figure A-1 NREL Reliability Test System ............................. A-1 xvii 0 0 List of Tables Table 2-1 Number, location and size of grid forming inverter per simulation .............................................. 2-10 Table 2-2 Rate of change of frequency for each case ........ 2-19 Table 2-3 Generators with rate of change of frequency greater than 0.15 Hz/s in Case 1 ............................. 2-19 Table 2-4 Rate of change of frequency of the 16 synchronous machines in Case 2 and Case 4............... 2-21 Table 2-5 Rate of change of frequency of the 16 synchronous machines for simultaneous two generation trip ......................................................... 2-24 Table 2-6 Total energy supplied in each case for simultaneous trip of both generators ........................... 2-26 Table 3-1 Parameters of the Controllers .............................. 3-9 Table 3-2 Inertia constants and torsional stiffness coefficients of rotor system ........................................ 3-21 Table 3-3 Oscillation frequencies of an inverterdominated power system .......................................... 3-22 Table 4-1 Generation Capacity (MW) in Each Case (Peak load: 8192 MW) .............................................. 4-3 Table 4-2 Load violation and renewable energy curtailment analysis .................................................... 4-7 Table 4-3 Existence of intervals with zero system price (marginal cost) but non-zero costs .............................. 4-13 Table 4-4 Cost and Revenue for case 4 (two-settlement pricing mechanism was applied while calculating the revenue) ............................................................ 4-16 Table 4-5 Comparison of solutions for the system with and without storage.................................................. 4-17 xix 0 Table 4-6 Summary of simulation results with four types of reserves............................................................... 4-22 Table 4-7 Summary of simulation results for case 4 with and without VER providing reserves ........................... 4-24 Table A-1 Generation Capacity (MW) in Each Case (Peak load: 8192 MW) .............................................. A-2 Table A-2 Average percentages of Generation in One Week ....................................................................... A-2 xx 0 Section 1: Introduction The presence of inverter based resources (IBR) in the bulk power system has been steadily increasing over the past few years. While IBR may include emerging technologies such as battery technology, the majority of the expected IBR include variable energy resources (VER), such as wind plants and solar photovoltaic plants. This trend has in part been supported by government subsidies and renewable energy mandates directed towards a goal of covering a certain percentage of energy use from renewable energy sources. This influx of IBR/VER resources is expected to continue to increase in the United States [1-1] and around the world, and coupled with the scheduled retirement of conventional generating plants, is transforming the behavior of the bulk power system. Note that not all new renewable resources need to be IBR (e.g. hydro, geothermal, and biomass are typically synchronously connected and dispatchable), but the majority of the new resources are expected to be wind and solar PV. Projecting this scenario few years into the future, it is very likely that system operators would have to deal with an all inverter based generation and transmission network, completely isolated from other transmission networks [12], at least for certain periods of a year. The energy source behind the inverter, being primarily a renewable energy source, is bound to be variable and uncertain. In such a scenario, maintaining the reliability and economic efficiency of the bulk power system would require novel, complex planning and operation paradigms. Figure 1-1 Operating paradigm evolution of power system with inverter based resources This work investigates characteristics of a transmission system with all inverter based generation. Both the dynamic behavior and stability performance, as well as steady-state operation and balancing issues related to integrating these resources onto the bulk power grid are addressed. 1-1 0 The report is structured as follows. Chapter 2 first discusses the definition of frequency in an 100% IBR system, and introduces the constant frequency operational paradigm. Inverter models developed in positive sequence simulation platforms are used to evaluate the dynamic performance and stability of such a grid. Realizing that a 100% IBR operation may occur only temporarily (for a few hours/days), the proposed inverter controls are also evaluated under operational conditions with a small portion of generation provided by conventional rotating generators. Chapter 3 focuses on detailed EMT modeling of the proposed inverter controls. Chapter 4 addresses steady-state and balancing operation of a system with periods of 100% IBR/VER, applying a state-of-the-art unit commitment and economic dispatch framework. In addition, it discusses new features of market pricing under 100% IBR operation. Chapter 5 summarizes the report and discusses future work. 1-2 0 Section 2: Inverter Modeling and Constant Frequency Operation of an All Inverter System Background In a system with conventional synchronous machines, due to Newton’s laws of physics, electrical frequency has a physical link with the speed of the rotating machines and hence the mismatch between generation and load, as shown in Figure 2-1. However, with IBR, the source of energy is either stationary (e.g. solar PV and battery) or electrically isolated from the network by the inverter (e.g. Type 4 wind turbine generator). A change in the electrical frequency of the power network (due to any system event), would thus be decoupled from the source, as shown in Figure 2-2. In a 100% IBR system, the notion of frequency is only the electrical frequency (rate of change of bus voltage angle). Thus, a change in the injection of current from the inverter sources could change the angles across the system and thus change the electrical frequency. Figure 2-1 Definition and physical links of electrical frequency in a conventional system 2-1 0 Figure 2-2 Definition and physical links of electrical frequency in an all inverter system Presently, the majority of the IBR sources are primarily controlled in a grid parallel mode. In this mode, the power output of the inverter does not change with respect to changes in system conditions, and the sources (solar or wind) operate according to their maximum power point tracking algorithm. A second mode of control is known as a grid supporting mode. In this scenario, the power output of the inverters (possibly both active and reactive) can change upon a change in grid conditions. Both of these modes are typically collectively referred to as grid following modes as the inverters require the presence of a grid to operate. A phase locked loop (PLL) is used to track the voltage & frequency of the grid at the point of connection. A third operating mode known as grid forming mode has recently been discussed in microgrid research literature [2-1, 2-2, 2-3]. In this mode, the inverter is controlled as a voltage source (as opposed to the current source representation in the other two operating modes) and is responsible for the establishment and maintenance of the grid voltage and frequency. A system with no synchronous machines would thus require the presence of grid forming inverters to act as voltage sources to set the system frequency and voltage which can be tracked by other inverters in the system. Constant Frequency Operational Paradigm Presently, multiple criteria exist to ensure that each Balancing Area (BA) [2-4, 25, 2-6] in the system would contribute to the maintenance of system frequency. However, these criteria have been developed on the basis of the power system operating upon the principles of conventional synchronous machines. With the conventional methods of maintaining system frequency well understood, it is important to understand the impact that grid forming inverters might have in maintenance of system frequency. In a conventional system, inertial response occurs in the first few seconds after the disturbance. Following this, primary frequency response is designed to stabilize the recovery of frequency to an off nominal value in a duration of around one minute. Slower acting secondary frequency response then restores the frequency back to nominal in a duration of around five to ten minutes. With the presence of fast acting grid supporting inverters, the frequency decline can be arrested faster resulting in a higher nadir and thus subsequently, faster recovery of frequency to nominal value. However, in an all inverter system, network electrical frequency across large interconnections could possibly be restored back to nominal value within seconds. This operational paradigm is referred to as constant frequency operation. In this work, by bringing 2-2 0 about the operation of the system at constant frequency, it is hoped that new light will be shed on the importance (or unimportance) of frequency. Note that, when stating the operation as constant frequency, it is understood that there will be transients in the electrical frequency, however, the value of the electrical frequency would come back to the nominal value within a few seconds after the initiation of the transient. An illustrative diagram of this operational behavior is shown in Figure 2-3. Figure 2-3 System frequency response for a conventional system and for an all inverter system with different types of inverter controls In an all inverter system, power sharing upon a disturbance and frequency control will depend entirely on the control schemes of the inverters. Presently, inverter based sources in most balancing areas operate in a fixed non-dispatchable mode. This can lead to a depletion in the available frequency response. Under constant frequency operation, legacy frequency droop is not applicable to achieve power sharing among IBRs. In addition, the traditional mechanisms and concepts of system stability that rely on rotating machines’ physical inertia, do not apply to systems with 100% of inverter interfaced generation. Wind generation allows for non-synchronous operation while solar PV is completely free of rotating parts, and since these devices are connected to the rest of the grid through power electronics, there is no physical inertia. Upon a disturbance, the stability of the system will be characterized by the capability of the inverter control schemes to ride-through the fault and restore generation/load balance. Thus, system stability will mainly depend on the controls and physical limitations of the interface inverters. Grid Forming Inverter Positive Sequence Modeling Inverter interfaced renewable energy models presently available in positive sequence simulation software are representative examples of either grid supporting voltage source/current source models [2-7, 2-8] or grid paralleling 2-3 0 current source models [2-8]. In this work, a positive sequence model for a grid forming inverter is presented. In terms of modeling and implementation, a grid forming inverter in positive sequence is simply a controlled voltage source whose terminal voltage is maintained at a constant value. As the existing literature and development of a grid forming inverter model for the BPS is still in its infancy, it must be emphasized that the inverter modeling is simplified under the constraints of a positive sequence modeling platform. However, due to the modeling simplifications inherent to the positive sequence modeling platform, a three-phase point on wave model is also developed and compared with the positive sequence model in Chapter 3. The positive sequence model is thus considered sufficiently accurate to accomplish the purpose of this work, which is to understand the viability and operational implications/limitations of operating the BPS at constant frequency. The inverter models that have been developed are used to study the operation of systems in which all the generation resources are interfaced to the grid though a inverter. Voltage & Current Controlled Grid Forming Inverter In this inverter model, the current output of the inverter is controlled to ensure that there is power sharing between the various sources in the system. Additionally, a current limit can also be introduced to ensure that the current output is within expected operational levels. As the frequency of the system is constant, conventional frequency droop schemes would not allow for post disturbance steady state sharing of power amongst the various sources in the system. Thus, an angle droop scheme has been adopted instead. The inverter model has a PLL to track itself and change its phase angle δ in order to change its power output. The block diagram of the control scheme is shown in Figure 24. The individual equations describing the blocks in the schematics have been intentionally omitted in order to reinforce the focus of this section on the applicability and reliability impact of a constant frequency bulk power system. 2-4 0 Figure 2-4 Controlled grid forming inverter positive sequence model schematic Constant Frequency Operation - Demonstrating Results - 433Machine 2000-Bus System In this section, the constant frequency operation is studied. To test the implementation of the inverter model and to understand the dynamics of a large system, the 2000 bus synthetic Texas system [2-9, 2-10] was used. This system has 433 in-service energy sources with a total generation of 69 GW, a total load of 67 GW and 19 Gvar. The load in the entire system is represented as constant impedance for the transient time domain simulations. Case 1: Grid Forming Inverter Operation In this case, one source out of the 433 is represented by the controlled grid forming inverter model, while the remaining 432 sources are represented by the grid supporting inverter model in [2-11]. The performance is compared against the scenario wherein all generation sources are represented by the grid supporting inverter model. With the presence of the grid forming inverter, a combination of frequency and angle droop as shown in Figure 2-5 was used in the grid supporting inverter model, while only frequency droop control was used in the scenario wherein all sources were grid supporting inverters. 2-5 0 Figure 2-5 Frequency and angle droop schematic in grid supporting inverter In the grid forming inverter model, only angle droop is used. The values of the controller gains used in the grid forming model were 𝐾𝐾𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 =20, 𝐾𝐾𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖 =100, 𝐾𝐾𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓 =10, 𝐾𝐾𝛿𝛿 𝑒𝑒𝑒𝑒𝑒𝑒 =0.1, 𝐾𝐾𝑝𝑝𝑝𝑝 =1.0, 𝐾𝐾𝑖𝑖𝑖𝑖 =60.0. The angle droop in the grid supporting model has the same control gain values with the additional frequency droop (𝑅𝑅𝑝𝑝 ) of 5% on the inverter MVA base. At t = 5s, a generation outage of 2569 MW is simulated. Figure 2-6 shows the change in system mean frequency for both scenarios. The mean frequency was calculated by calculating the average of the frequency from each of the 8 areas. The frequency in each area is obtained as the rate of change of bus angle at a random 230 kV bus. Figure 2-6 Comparison of change in mean system frequency with and without a grid forming inverter 2-6 0 It can be seen that even in a large system, with just one grid forming inverter, the system frequency can be maintained at the nominal value. The grid forming inverter is however representative of a 1625 MVA generation source. The nadir of the frequency in both scenarios is around the same value of around 59.75 Hz. The voltage magnitude at a 230 kV bus in these 8 areas is shown in Figure 2-7. Figure 2-7 Voltage magnitude in the system with and without a grid forming inverter In the legend, ‘grdfrm’ corresponds to the scenario with the presence of the grid forming inverter while ‘nogrdfrm’ corresponds to the scenario with the absence of the grid forming inverter. It can be seen that transiently, there is minimal difference in the system voltage between the two scenarios. From the above, it can be concluded that for normal operation of the system, there appears to be no reliability risk at operating an all inverter system at constant frequency. This reliable operating condition is however contingent upon at least three pre-existing conditions: a) adequate availability of active power reserves, b) optimally tuned control parameters, and c) sufficient current margin in the inverter. Additionally, the sharing of power between the areas is in accordance with the electrical distance between the areas. Thus, the inverters in the disturbance area tend to respond by a larger amount as compared to the inverters in the other areas. Such a response can be considered similar to the combinatorial response of conventional primary and secondary frequency response in which the frequency is brought back to the nominal value by the generators in the disturbance area. However, with the grid forming inverter, it is not pure secondary response as the inverters in other areas still contribute to some extent. Case 2: Under Frequency Trip In a conventional system, the lack of availability of adequate reserves can cause under frequency load shed (UFLS) relays to activate. This action however takes place in the time frame of conventional primary frequency response. To 2-7 0 investigate the effect of constrained active power reserves in the all inverter system with the presence of a grid forming inverter model, the system is stressed by preventing grid supporting inverters in an entire area from responding to the generation outage. Figure 2-8 compares the system mean frequency for the following conditions: Inverters in all areas respond (Case A), Inverters only in areas 7 and 8 respond (Case B), and Inverters only in area 8 respond (Case C), while Figure 2-9 compares the terminal voltage magnitude at these 8 buses. Figure 2-8 Mean system frequency for the stressed system Figure 2-9 Bus voltage magnitude for the stressed system 2-8 0 As expected, it can be seen that as the deployable active power reserve decreases, the frequency response of the system deteriorates with Case C diverging. An additional effect of this is that the inverters hit their current limits in an effort to provide more reactive power to prevent the deterioration of the terminal voltage. The limited injection of current however causes the bus voltage angle to change rapidly as the solution of the network equation tries to obtain a voltage level suitable for the power level at that point in time. Thus, this large change in frequency is an artifact of the changing rate of change of bus voltage angle, which is in turn caused by limited injection of current into the network by the sources. It must however not be confused with the ‘out-of-sync’ phenomena observed in a conventional system wherein synchronous machine rotors fall out of synchronism. In order to prevent a system collapse, one can note that just like in a conventional system, opportunities to apply UFLS are also available in a constant frequency operation all inverter system. Additionally, in an all inverter system, it is highly probable that the majority of the resources would be renewable energy resources. In such a scenario, with many renewable resources operating at their maximum power point with zero deployable active power reserve, curtailment of these resources under transient over frequency conditions could also be a feature that could be exploited. To allow generation curtailment, the grid supporting inverters were only allowed to respond to the generation outage if 𝑃𝑃𝑐𝑐𝑐𝑐𝑐𝑐 < 𝑃𝑃𝑟𝑟𝑟𝑟𝑟𝑟 (Figure 2-5). To illustrate this, using the conditions of Case C, Figure 2-10 compares the system mean frequency for the following conditions: 1. Inverters in Areas 1-7 can transiently curtail their output for over frequency (Case Ca), 2. In addition to curtailment, active power load throughout the system is reduced by 5%, 1s after the disturbance (Case Cb), and 3. In addition to curtailment, active power load throughout the system is reduced by 5%, 0.5s after the disturbance (Case Cc). 2-9 0 Figure 2-10 Mean system frequency for the stressed system with generator curtailment and load shedding Although the applied methodology of reduction of load is not in strict accordance with the methodology by which UFLS is applied in a conventional power system, the analysis serves to illustrate the possibility and use of applying UFLS in the all inverter system to maintain reliable operation at constant frequency. Additionally, it is entirely possible that with optimal control gains, the response of Case Ca can be damped to obtain a reliable system operation with no load reduction. Case 3: Variation in Size, Location and Number of Grid Forming Inverters In the previous two cases, a single large grid forming inverter was placed in Area 7 of the system. To observe the impact of location, size & number of grid forming inverters, simulations were run as per the setup in Table 2-1. In the first 8 simulations, the source with the lowest MVA in the area was chosen as the grid forming inverter. Table 2-1 Number, location and size of grid forming inverter per simulation Location MVA Area 1 12 MVA Area 2 12 MVA Area 3 18 MVA Area 4 11.5 MVA Area 5 2.0 MVA Area 6 1.8 MVA 2-10 0 Table 2-1 (continued) Number, location and size of grid forming inverter per simulation Location MVA Area 7 8.2 MVA Area 8 52.8 MVA Area 7 – Large Inverter 1625 MVA 2 Small Inverters Area 5 (2.0 MVA), Area 6 (1.8 MVA) 2 Large Inverters Area 7 (1625 MVA), Area 8 (1077 MVA) 3 Large Inverters Area 5 (1209 MVA), Area 7 (1625 MVA), Area 8 (1077 MVA) For the same generation outage event, Figure 2-11 shows the system mean frequency. It can be noticed that impact of the size of the grid forming inverter is more significant than the impact of the location. The nadir of the mean frequency is at a higher value with two large grid forming inverters present. Figure 2-11 Mean system frequency with varying location, number & size of grid forming inverter Case 4: Topology Change While the suggested angle droop method of sharing of power among sources might be effective for a load/generation event, it could also result in a new operating point due a change in the topology of the system. Although this change in operating point might not be large, it could still have implications on market settlement and economics of operation of the system. As an example, at t=5s, a 500 kV line in Area 5 carrying ≈ 890 MW/73 MVAr is tripped. Figure 212 shows the change in total power output of Areas 2, 5 & 8. With the presence of the grid forming inverter, angle droop control was used and without the grid forming inverter, conventional frequency droop control is used. 2-11 0 Figure 2-12 Change in power output in Areas 2, 5 & 8 for a 500kV line trip in Area 5 It can be seen that there is a change in power output in the individual areas to support the change in losses/load due to change in voltage magnitude and angle. Inverter Based Resources Dominated Grid The possibility of the bulk power system being all inverter could be questioned. It is true that the current power system is far from an all inverter operation, but there are possibilities where certain isolated power systems may temporarily operate in an all-inverter mode. Examples are the power grid of the Electric Reliability Council of Texas (ERCOT) in North America, or island systems such as the power grid of Ireland. Both these systems presently have a lot of existing wind generation with more slated to be in the interconnection queue. Ireland is presently curtailing wind generation to maximum of 65% due to frequency stability concerns. In a system with a small percentage of synchronous machines still online, the juxtaposition of fast inverter controls along with slower synchronous machine control can introduce reliability concerns. In this section, the constant frequency inverter control scheme described before is used to address the following questions in an IBR dominated grid: 1. For a large generation loss event, can power be shared in the short term among all participating inverter resources? 2. Over the long term, can the flows on the tie line interfaces between areas be restored to the pre-disturbance value? 3. If there are few synchronous machines remaining on the system, will the fast constant frequency control of the inverters have an adverse impact on the machines? 4. If the inverter resources receive a schedule change command from the system operator, can the control system track the change in schedule, and if it can, how will it behave if a disturbance occurs during the schedule change? 5. If there are severe N-1 line outages, then can the control scheme ride through? 2-12 0 Modularized Constant Frequency Inverter Positive Sequence Models In this section, a modularized modeling approach of the constant frequency control scheme is discussed. The modularized setup facilitates experiments with different control structures, while also making use of existing inverter models. A broad overview of the modularized setup is shown in Figure 2-13 and Figure 214 wherein a comparison can be made with existing current source inverter interface model (REGC_A) and new voltage source inverter interface models, while still using the same outer loop controls. Figure 2-13 Modularized control structure with voltage source interface Figure 2-14 Modularized control structure with current source interface 2-13 0 The user defined active power controller model is as shown in Figure 2-15. All quantities in this controller are in per unit on a MW value base which can be lower than the MVA rating of the inverter. Figure 2-15 User defined active power controller structure In order to assess the ability of the control scheme to control the power transfer between balancing areas, the ‘Tie-line deviation’ control loop was incorporated ′ on a system level, and each inverter resource receives a signal (𝑃𝑃𝑎𝑎𝑎𝑎𝑎𝑎 ) to mimic the operation of a simple automatic generation control loop. One ‘Tie-line deviation’ block is placed in each area of the system, and its internal algorithm can be generally described as: 1. Once every 2 seconds evaluate the total tie line power mismatch of the area 2. Compare the mismatch with a tolerance level, - If the mismatch is below the tolerance level – do nothing, - Else, integrate the difference through a PI controller to obtain a value of power that has to be raised/lowered in the area. 3. Once every 3 seconds, and through a further first order time constant of 1.0s, ′ to the active power the value of power evaluated in step 2b is sent as 𝑃𝑃𝑎𝑎𝑎𝑎𝑎𝑎 controller of every inverter resource in the area. The user-defined voltage source inverter model used in this study is the detailed inverter model that was developed in 2018 under the EPRI P173.03 project. This detailed inverter model is capable of representing the faster phase locked loop and inner current control dynamics that are of crucial importance while analyzing the behavior of inverter interfaced generation in low short circuit areas. Details regarding this model can be obtained in [2-12]. The electrical controller model REEC_A has been used in local voltage control mode, with Q priority, and no momentary cessation. It must be mentioned here that in both modular inverter interface representations, the dynamics of the dc bus and the source behind the dc bus 2-14 0 have been ignored. Additionally, it has been assumed that the dc bus is stiff and/or the dynamics of the controller controlling the dc bus voltage is fast enough to cater to the demands of the grid side inverter controllers. The next section discusses results from implementation of both modular inverter structures on a 2000 bus Synthetic Texas system. IBR Dominated System - Demonstrating Results - 433-Machine 2000-Bus System The same 2000 bus synthetic Texas system is used in this section. The positive sequence simulations were carried out in GE- PSLF™. Five cases were setup up as defined below: 1. Case 1: All 433 energy sources were modeled as conventional synchronous machines with a round rotor generator model (GENROU), a simple governor model (TGOV1) and a simple static excitation system model (SEXS) 2. Case 2: 417 energy sources were modeled as inverter interfaced generation with the voltage source inverter interface model, and the constant frequency control mode enabled. The remaining 16 energy sources, have an MVA greater than 500 MVA, and are represented as conventional synchronous machines, with the same type of models as in Case 1. 3. Case 3: 417 energy sources were modeled as inverter interfaced generation with the existing current source inverter interface model, but with the constant frequency control mode enabled. The remaining 16 energy sources, had an MVA greater than 500 MVA, and were represented as conventional synchronous machines, with the same type of models as in Case 1. 4. Case 4: 417 energy sources were modeled as inverter interfaced generation with the voltage source inverter interface model, but with the constant frequency control model disabled. Only frequency droop control was enabled. The remaining 16 energy sources, had an MVA greater than 500 MVA, and were represented as conventional synchronous machines, with the same type of models as in Case 1. 5. Case 5: 417 energy sources were modeled as inverter interfaced generation with the existing current source inverter interface model, but with the constant frequency control model disabled. Only frequency droop control was enabled. The remaining 16 energy sources, had an MVA greater than 500 MVA, and were represented as conventional synchronous machines, with the same type of models as in Case 1. The synchronous machines in Cases 2 – 5 represent approximately 15% of the capacity (and approximately 11% of MW) of all in service sources. Additionally, the loads in the system are represented according to the value of active power as: 1. 0.0 MW < 𝑃𝑃𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 ≤ 20.0 MW – Constant Impedance 2. 20.0 MW < 𝑃𝑃𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 < 60.0 MW – Three phase induction motor (H = 0.5s, quadratic P vs 𝜔𝜔) 2-15 0 3. 𝑃𝑃𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 ≥ 60.0 MW – Composite load model with NERC default data Below, the various scenarios studied are discussed. Scenario 1: System Operation for a Generation Loss Event The two largest generators in this system have approximately 1.2 GW of generation each. To evaluate the behavior of the system, both these generators were tripped in a sequential manner at t = 10s and 25s. Since in all five cases synchronous machines are still present in the system, the electrical frequency of the system still holds value. The average electrical frequency across the entire system (average of electrical frequency evaluated at every bus in the system) is shown in Figure 2-16. Figure 2-16 Average electrical frequency across the entire system for two generation trip events It can be seen that with all synchronous machines, the frequency response graph follows the well-known behavior. In the actual Texas power system, the set point for under frequency load shedding is 59.3 Hz and has remained at that value since 2012 [2-13]. Additionally, the nadir of frequency (around 59.7 Hz) is also approximately equivalent to the nadir observed in studies shown in [2-13] for a generation trip of this magnitude. For Case 4 and Case 5, where the inverters were only enabled with frequency droop response (with the same value of droop gain and headroom as the corresponding synchronous machine model used in Case 1), the final settling value of the frequency is the same as in the all synchronous case. These two cases are provided as reference intermediate cases to highlight the additional capabilities that can be extracted from inverters. It should be noted that inverters can have a smaller droop percentage (say 2% droop instead of 6%), which would result in a higher settling off-nominal frequency, but sensitivity to droop gain is 2-16 0 not the objective of this work. This kind of sensitivity analysis is discussed in detail in [2-14]. In Case 2 and Case 3, where the inverters were also enabled with the constant frequency control scheme, it can be seen that the electrical frequency is satisfactorily brought back to the nominal value of 60.0 Hz, within few seconds of the disturbance. Additionally, even with the presence of the large synchronous machines, the system frequency does not show any major oscillations that could be a cause of concern. This is however majorly influenced by the value of the control gains used in both the inverter and synchronous machine controls. However, in Case 1 as expected, there is a presence of inter area oscillatory modes. While these modes are not visible in the system frequency plot, they can be seen in the plot of each area’s frequency, as shown in Figure 2-17. The individual area frequencies for Case 2 are shown in Figure 2-18 for the duration around the first disturbance (i.e. 10s). Due to the fast action of the inverters, there are minimal inter area oscillations in frequency range that is common in an all synchronous machine system. This is despite the presence of the fast phase locked loop and inner current control loop controls in the inverter model. An interesting observation from Figure 2-18 is that the area where most of the 16 synchronous machines are present is readily observable as the frequency in that area has a slower rate of change of frequency. Figure 2-17 Average frequency in each area in Case 1 for two generation trip event 2-17 0 Figure 2-18 Average frequency in each area in Case 2 for two generation trip event While the plots with the large presence of inverters show a stable response, in all four of them, the rate of change of frequency is much steeper than the all synchronous machine case, while the nadir is higher. The higher nadir is attributed to the smaller time constants that are present in the frequency control path of the inverter model, than the time constant in the governor and machine models. This allows fast injection of energy from the inverters into the power system. But, with the chosen values of control gains, this injection of energy from the inverters is not fast enough to prevent a steep rate of change of frequency. This steep rate of change of frequency could be a cause of concern for the remaining 16 synchronous machines. In order to observe the rate of change of frequency better, the plot of the system electrical frequency in the immediate aftermath of the first disturbance (the few seconds around 10s) is shown in Figure 2-19. Figure 2-19 System electrical frequency in the immediate aftermath of two generation trip event 2-18 0 The rate of change of frequency is usually evaluated as a moving average over the period of 500ms. In this scenario, for each case, the rate of change is evaluated 500ms after the disturbance, as tabulated in Table 2-2. Table 2-2 Rate of change of frequency for each case Case Frequency (Hz) at 10s Frequency (Hz) at 10.5s 1 60.0 59.962 2 60.0 59.94 3 60.0 59.94 4 60.0 59.898 5 60.0 59.898 Rate of change (Hz/s) 59.962 − 60.0 = −0.076 0.5 59.94 − 60.0 = −0.12 0.5 59.94 − 60.0 = −0.12 0.5 59.898 − 60.0 = −0. 204 0.5 59.898 − 60.0 = −0. 204 0.5 While it is expected that with large presence of inverters the rate of change of frequency will be steeper, the rate of change of system electrical frequency only shows one side of the picture. Even in an all synchronous system, as seen in Figure 2-17, the rate of change of frequency is different in different areas of the system, and the electrical distance of a generator to the disturbance location also plays a role. In Case 1, for the same generation loss event, the rate of change of frequency at individual generator terminals was evaluated 500ms after the disturbance, and the generators with absolute value of rate of change greater than 0.15 Hz/s are tabulated in Table 2-3. It is interesting to note that although the generation loss event was in Area 5, the largest rate of change is observable in the adjoining areas of 2 and 8. Table 2-3 Generators with rate of change of frequency greater than 0.15 Hz/s in Case 1 Bus number Area number Rate of change (Hz/s) 2115 2 -0.1525 2117 2 -0.1536 2118 2 -0.1546 2119 2 -0.1502 2120 2 -0.1541 8129 8 -0.1524 8130 8 -0.1560 8131 8 -0.1529 2-19 0 Geographically, the 8 areas in the system are approximately spread out as shown in Figure 2-20, with the white lines denoting weaker portions of the network. The demarcation of areas is by no means accurate, and it is a very high level approximation. However, it shows that generators in Area 2 and 8, especially if they are at the edge of the areas, can easily be electrically close to the event bus in Area 5. Figure 2-20 Geographic view of the test system With the presence of inverters, the rate of change of frequency at the remaining 16 synchronous machines terminals is tabulated in Table 2-4 for Case 2 and Case4. 2-20 0 Table 2-4 Rate of change of frequency of the 16 synchronous machines in Case 2 and Case 4 Bus number Area number Rate of change (Hz/s) for Case 2 Rate of change (Hz/s) for Case 4 7098 7 -0.1624 -0.1994 7099 7 -0.1624 -0.2112 7208 7 -0.1655 -0.2111 7209 7 -0.1648 -0.2109 7335 7 -0.1648 -0.2109 7353 7 -0.1679 -0.2124 7354 7 -0.1665 -0.2118 7355 7 -0.1665 -0.2118 7356 7 -0.1663 -0.2117 7389 7 -0.1593 -0.2102 7400 7 -0.1626 -0.2104 8071 8 -0.1402 -0.2312 8088 8 -0.1358 -0.2211 8129 8 -0.1357 -0.2303 8130 8 -0.1430 -0.2377 8131 8 -0.1356 -0.2301 Only these two cases were considered because, from Figure 2-19 it can be seen that the difference between the current source and the voltage source implementation of the inverter interface occurs only in the first 300ms following the disturbance. At the time of calculation of the rate of the change of frequency, there is negligible difference between the current source and voltage source interface. In Case 2, with the constant frequency operation of the inverters, the rate of change of frequency at the terminals of the generators in area 7 have increased in comparison to their rate of change of frequency in an all synchronous machine setup. However, the rate of change at the terminals of the generators in area 8 have decreased when compared to the corresponding values (Table 2-3) in an all synchronous machine system. In Case 4, with the inverters operating only on conventional frequency droop control, the rate of change of frequency at the generator terminals has increased in comparison to the all synchronous machine case. The difference in the rate of change of frequency between Cases 2 and 4 can be attributed to the contribution from the inverters in the other areas. As an example, the total active power output from the inverters in Area 5 for Cases 2 and 4 (excluding the two generation sources that were tripped), is shown in Figure 2-21. 2-21 0 Figure 2-21 Total active power from all inverter resources in Area 5, for a two generation trip In Case 2, due to the constant frequency control, the inverters in Area 5 inject more energy into the system during the first 500ms. A similar behavior would occur in Areas 7 and 8 thereby, arresting the frequency decline at the terminals of the machine. It goes without saying that the injection of this additional energy is subject to conditions of a stiff dc bus and availability of energy from the source behind the inverter. Representation of the dynamics of these loops is a topic that will be pursued in the future. However, a question then arises is whether this behavior is strictly due to the voltage source interface of the inverter. An inverter which is controlled as a pure voltage source (known as grid forming inverters in some literature), is said to inject energy into the network without delay upon the occurrence of a disturbance. It has been postulated in literature that this rapid injection of energy from a voltage source inverter (subject to the availability of energy from the dc bus/source behind the inverter) can take the place of conventional inertial energy to help arrest the frequency decline as this rapid injection of energy is not possible from traditional current source controlled inverters. In order to test this hypothesis, Figure 2-22 shows the total active power in Area 5 for Cases 2 and 3 (again excluding the two generation sources that were tripped). 2-22 0 Figure 2-22 Total active power from all inverters resources in Area 5, when controlled as a current source and voltage source, for two generation trip Both Cases 2 and 3 have the constant frequency control mode enabled, but case 2 uses a voltage source interface inverter while case 3 uses the present state of the art current source interface inverter. The advantage of the voltage source interface inverter is observable in the near instant after the disturbance. The voltage source inverters provide more short circuit current than the current source interface. However, due to the nature of the energy balance, following the rapid injection of energy at the instant of disturbance, the injection from the voltage source interface inverter drops, and the action of the control loops become dominant. The current source interface inverter on the other hand, is unable to contribute short circuit at the instant of disturbance, and thus, only the action of the control loops is present. In both schemes, after the first 100ms, the delivery of energy into the network is roughly the same, and thus, from the perspective of arresting the frequency decline, it may be possible to continue to use current source interface inverters. But, it must be stated that this conclusion is only from the perspective of arresting the frequency decline, given that the rate of change of frequency is measured as a moving average over 500ms. In the real Texas power system, to plan for frequency response reserves, a loss of 2750 MW of generation, with a credit of 1209 MW of fast acting load response, is the benchmark event for analysis [2-13]. These numbers align with the net generation loss event that has been analyzed in this scenario. It is worthwhile to check if the same trend of rate of change holds if both the generators were tripped at the same time in this scenario. Table 2-5 tabulates the rate of change of frequency at the terminals of the 16 generator buses for all five cases. 2-23 0 Table 2-5 Rate of change of frequency of the 16 synchronous machines for simultaneous two generation trip Bus number Case 1 Case 2 Case 3 Case 4 Case 5 7098 -0.0232 -0.2846 -0.3129 -0.3578 -0.3766 7099 -0.0366 -0.2915 -0.3168 -0.3890 -0.4062 7208 -0.0279 -0.2951 -0.3205 -0.3863 -0.4040 7209 -0.0284 -0.2942 -0.3192 -0.3864 -0.4038 7335 -0.0309 -0.2933 -0.3177 -0.3867 -0.4037 7353 -0.0282 -0.2989 -0.3249 -0.3882 -0.4062 7354 -0.0291 -0.2968 -0.3222 -0.3877 -0.4053 7355 -0.0291 -0.2968 -0.3222 -0.3877 -0.4053 7356 -0.0292 -0.2966 -0.3218 -0.3876 -0.4052 7389 -0.0444 -0.2873 -0.3082 -0.3879 -0.4022 7400 -0.0310 -0.2913 -0.3149 -0.3865 -0.4029 8071 -0.2497 -0.2786 -0.2685 -0.4621 -0.4521 8088 -0.1997 -0.2659 -0.2601 -0.4368 -0.4319 8129 -0.3078 -0.2748 -0.2649 -0.4663 -0.4558 8130 -0.3147 -0.2882 -0.2810 -0.4804 -0.4716 8131 -0.3091 -0.2748 -0.2656 -0.4665 -0.4566 The two areas where the 16 synchronous machines are present (Area 7 and Area 8) have very different electrical distances with the point of disturbance in Area 5. Area 8 is electrically closer, while Area 7 is electrically farther away. This is immediately evident from the results of Case 1 where all the machines in Area 7 have a slow response, while the machines in Area 8 move quickly. In comparison, when the inverters operate in constant frequency control mode (both voltage source and current source, Cases 2 and 3), the rate of change of frequency for the machines in Area 8 reduces, while the rate of change increases quite significantly for the machines in Area 7. However, the increase in Area 7 is only large in comparison to the corresponding value in the all synchronous machine case while it is comparable to the values of rate of change of frequencies for the machines in Area 8. With the inverters in only frequency droop control mode (Cases 4 and 5), the rate of change of frequency is expectedly larger than the constant frequency control mode as the injection of energy by the inverters is lower in the frequency droop control mode. The system electrical frequency for this event is shown in Figure 2-23. The system electrical frequencies for Cases 1, 2 and 3 intersect at around 500ms after the event. 2-24 0 Figure 2-23 System average electrical frequency for simultaneous trip of both generators For all five cases, the total active power in Area 5 (excluding the two generation sources that tripped) and Area 8 is shown in Figure 2-24. Figure 2-24 Total active power in area 5 and 8 for simultaneous trip of both generators In Area 5, immediately upon the occurrence of the disturbance, the large amount of energy supplied by the synchronous machines in Case 1 is clearly observable. However, as time advances, the inverters catch up in energy injection. In Area 8, in Cases 2 – 5 with the large presence of inverters, the 5 remaining machines (buses 8071, 8088, 8129, 8130 and 8131) constitute approximately 64% (both by capacity and MW) of entire area’s in service generation. Hence, when the inverters in Area 5 are slow to begin injection of energy, the machines in Area 8 inject more energy than they did in Case 1. 2-25 0 But, the question then is, how much additional/reduced energy is injected in each case? In order to approximately compute the energy injected, the total active power curve in Area 5 was integrated over the duration of the simulation using a composite trapezoidal numerical integration rule, and the results are tabulated in Table 2-6. In addition to evaluating the energy injected over the entire duration of the simulation, the energy injected immediately after the disturbance (from 9.99s to 10.50s and from 9.99s to 11.014s) was also approximately calculated. The energy values in the table are in units of MWs approximated to the nearest integer. Table 2-6 Total energy supplied in each case for simultaneous trip of both generators Time duration Case 1 Case 2 Case 3 Case 4 Case 5 0s to 30s 316113 322585 322212 317174 317095 9.99s to 10.50s 5540 5439 5413 5355 5338 9.99s to 11.014s 10665 10913 10892 10653 10638 It can be seen that in Area 5, although the synchronous machines in Case 1 inject a large amount of power immediately upon the occurrence of the disturbance to arrest the frequency decline, the energy injection in comparison to the energy injection of the all inverter situations of Cases 2 and 3, is almost similar in the first 500ms after the disturbance. This is also confirmed from Figure 2-23 wherein the system frequency in Cases 1, 2 and 3 intersect at around 500ms after the disturbance. The energy evaluation also provides an idea of the additional MWs of energy required from inverter resources to be operated in the constant frequency control mode, as opposed to operation in a frequency droop control mode. At every time step, the minimum voltage magnitude across the entire system for this event is shown in Figure 2-25. It can be seen that for all the inverter cases, the voltage control is stricter. This is due to two primary reasons: 1. In the synchronous machines case, although the machines inject energy in the first 500ms after the disturbance, the energy injection reduces in the subsequent couple of seconds as is seen from Figure 2-24. This reduction in energy injection few seconds after the disturbance would cause the angles to spread across the system which causes the voltages to reduce. In the cases with the inverters, although the inverters have a slightly slower rate of injection of energy, there is no reduction in energy once the energy injection has begun. This is of course under the assumption that the controllers of the inverter plants are well tuned. In the first 500ms when there is a slower rate of energy injection from the inverters, the angles across the systems do spread faster, and this is observable from the greater rate of change of voltage in that small time frame. 2. The static excitation system used for the synchronous machines have not been tuned to optimal values which could otherwise possibly allow faster voltage control. 2-26 0 Figure 2-25 Minimum voltage across the system for simultaneous trip of both generation With the operation of the constant frequency control established, and the implications on frequency response discussed, henceforth, Cases 4 and 5 will not be considered in the discussion. With constant frequency operation, upon the occurrence of a disturbance (generation or load change), a valid concern is whether all areas will share the burden of the disturbance (as it presently occurs nowadays due to frequency droop control). In the constant frequency control scheme, based upon the proportion of the deviation of the terminal voltage bus angle from a set reference, the power command of the inverters is changed. With such a control, it is possible to share the burden of a disturbance among the various sources in the system. For the two generation trip event, the total active power in Areas 5 and 2 is shown in Figure 2-26. The sharing of power across the areas can be inferred from this figure. Figure 2-26 Total active power in areas 5 and 2 for the simultaneous trip of both generation 2-27 0 As the sharing of power is now linked to the deviation of bus voltage angle, the topology of the electrical network would now play a large role in determining the areas which are able to share more proportion of the burden. With a large portion of the fleet being inverter interfaced sources, the implications of uncertainty in input energy have to also be analyzed. In 2017, a stochastic based framework was explored to look into the various combinations of input energy uncertainty that can occur with a large fleet of inverter based generation, but a small system was used in the study with the inverters on conventional frequency droop control. In this report, the aim is to study the impact of the uncertainty on the constant frequency control scheme, when spread across the large system. In comparison to a scenario where there is sufficient available headroom, if the available energy headroom on inverters is suddenly limited, then angles across the system would change faster and by a larger magnitude, causing inverters which have available headroom to pick up more of the burden. This happens even in a conventional frequency droop control scheme. However, due to the fast nature of the controls on the inverter, it is possible that this fast change in angle can cause a fast voltage reduction in the system. For the same two generation trip event, a simulation was carried out for Cases 2 and 3, but with the headroom of the inverters in Areas 2 and 5 reduced by 20%, one second after the occurrence of the disturbance. Area 2 was chosen in addition to Area 5 as pre-disturbance, Area 5 imports active power from it. While it could be rare that there is a sudden decrease in available energy across a vast geographical area (as is the geographical spread of these two areas), such a scenario serves as a benchmark test case. Figure 2-27 shows the minimum voltage magnitude across the system for both cases in comparison to the minimum voltage magnitude when the headroom is sufficient. Figure 2-27 Minimum voltage across the system for a change in headroom 2-28 0 As the headroom decreases in these areas, the voltage across the system becomes increasingly oscillatory, and as expected, the magnitude of the sag deepens. In these scenarios, the inverters were operated in a Q priority mode, wherein, during the disturbance, priority is given to the injection of reactive current over the injection of active current. In the present power system, the deviation in frequency is used as an integral component in the calculation of area control error (ACE) which drives the implementation of secondary frequency control. But in the constant frequency control model implemented here, the frequency deviation is essentially zero within a few seconds after the disturbance. In such a situation, the research question that arises is would the tie line deviation error be a sufficient signal for the implementation of the secondary frequency control? By enabling the ‘Tie line deviation’ control block, Figure 2-28 shows the total active power output in Areas 5 and 2 for the two generation trip event. It can be seen by just using the tie line deviation as a signal, the individual areas are able to respond to the changes in command to either increase or decrease their power output resulting in the sources in Area 5 having to increase their power output by almost the total generation loss, while the sources in Area 2, after having initially shouldered part of the burden to bring the frequency back to nominal, go back to their pre-disturbance values. Figure 2-28 Total active power in areas 5 and 2 with the inclusion of tie line deviation control signal 2-29 0 To conclude this scenario, few take away points are: 1. The constant frequency control mode is able to bring the entire system electrical frequency back to the nominal value within a few seconds after the disturbance, even with the presence of synchronous machines. 2. With constant frequency control mode, apart from the first 200-300ms after a disturbance, there is little difference between the workings of a current source interface inverter and a voltage source interface inverter. 3. With rate of change of frequency evaluated 500ms after the disturbance, operation of a majority inverter dominant system, results in no significant change in the rate of change of frequency at the synchronous machine terminals that are located electrically close to the point of disturbance. However, for machines that located electrically farther away, an increase in the rate of change is observed. 4. Evaluation of the energy injected by the inverters in the few milli-seconds after the disturbance provides an insight into the capacity planning requirements for the satisfactory operation of a inverter dominated power system. 5. The angle droop control mode allows for inverters in all areas to share the burden of generation – load imbalance. 6. Only tie – line active power deviation could be used successfully as a control signal for secondary frequency control. Scenario 2: Change in Power Command from the System Operator A crucial portion of the constant frequency control mode is the change in power command of the inverter in proportion to the deviation of the terminal bus voltage angle, in reference to a constant value of angle. Few questions that then arise are, 1. What is the constant value of angle? 2. How is it set? 3. Can it be changed based upon a dispatch setting from the system operator? In the control scheme developed, the angle reference (𝛿𝛿𝑟𝑟𝑟𝑟𝑟𝑟 in Figure 2-15), is the angle of the terminal bus voltage of the inverter itself at a previous point in time, when the system was in steady state. However, in a practical system, it is impossible to define a pure steady state, as there are always minute load variations occurring across the system. Thus, to define the value of 𝛿𝛿𝑟𝑟𝑟𝑟𝑟𝑟 with respect to a practical system, the angle reference variable tracks the angle of the inverter as long as the frequency deviation is within a tolerance value. Once the frequency deviation exceeds the tolerance, the value of 𝛿𝛿𝑟𝑟𝑟𝑟𝑟𝑟 is frozen at the value just before the larger deviation in frequency, and is held frozen at this value, until the frequency deviation is lower than the tolerance. This operation can be expressed by following pseudo-code, with the variables in reference to Figure 2-15, 2-30 0 𝑖𝑖𝑖𝑖 (|𝑓𝑓 − 1.0| < 𝑑𝑑𝑑𝑑𝑑𝑑) 𝑡𝑡ℎ𝑒𝑒𝑒𝑒 (𝛿𝛿𝑟𝑟𝑟𝑟𝑟𝑟 = 𝑠𝑠2 ) Eq. 2-1 With this expression, the reference angle does not have to be compared with any other system reference, and thus no wide area communication system is required. Admittedly, the variable 𝑠𝑠2 is not a true representation of the terminal bus voltage angle of the inverter, but it is the controller’s interpretation of the terminal bus voltage angle. As the angle is not a true representation of the terminal bus voltage angle, there is a cause of concern whether the control scheme can accept change in power reference commands from the system operator. In a conventional frequency droop scheme, the change in power reference commands are implemented by shifting the 𝑓𝑓 − 𝑃𝑃 droop curve up or down, in parallel to the present set point droop curve. By shifting the curve, the value of 𝜔𝜔𝑟𝑟𝑟𝑟𝑟𝑟 changes, while keeping the slope of the curve the same, thereby resulting in a new active power level at nominal frequency. Additionally, with knowledge of the new active power set point, and the slope of the droop curve, the new value of 𝜔𝜔𝑟𝑟𝑟𝑟𝑟𝑟 can be easily calculated. This kind of maneuvering could be quite tedious in the constant frequency control scheme, as 𝛿𝛿𝑟𝑟𝑟𝑟𝑟𝑟 and 𝑠𝑠2 are in a way internal variables of the control scheme. However, the same result of change in output power to system operator command can be achieved by adjusting the value of 𝑃𝑃𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖 in the control scheme, and then due to the self-angle tracking algorithm, the controller would reset itself to be ready for the next event that occurs at the new operating point. The working of this mechanism is illustrated in Figure 2-29 for Cases 2 and 3 wherein the total active power of Areas 5 and 2 are shown for a change in system operator command. The total active power in Area 5 was commanded to decreased by 5 MW at each inverter, over a period of 10s, while during the same time interval, the inverters in Area 2 were commanded to increase their active power by 5 MW each. Figure 2-29 Change in power output in areas 5 and 2 to a change in system operator command 2-31 0 For this scenario, the ‘Tie line deviation’ control block was disabled, as the change in system operator command was issued without consideration of maintaining tie line flows. Additionally, due to this, the inverters in other areas also respond by changing their power outputs. If a disturbance occurs during the ramp change, and also after the change, is the controller able to handle these situations? For the same change in system operator command, Figure 2-30 shows the total active power in Areas 5 and 2 for Cases 2 and 3. However, this time, midway through the ramp change, the entire static load in the system (both active and reactive power) was increased by 1%, and after the end of the ramp change, the static load was further increased by 2%. It can be seen that the constant frequency control is fairly robust and stable to track system operator commands, and address any sudden disturbance that might occur during a change, and after a change. The reason for the difference between Cases 2 and 3 is due to the difference in performance of the voltage source interface as compared to the current source interface. As the load change is applied, the voltages across the system change differently whether the sources are voltage sources or current sources as the network impedance is different in both cases, with the voltage source interface introducing its source impedance in the system. This variation in voltage, is more prominent when only the active power load is increased, as shown in Figure 2-31. While the performance of the voltage source interface inverter remains roughly the same as before, the current source interface inverter shows a much varied change in output. Another contributing factor to this difference is that in the voltage source interface, the input frequency to the power controller is the phased locked loop calculated frequency, while in the current source interface, the network bus frequency is the input to the controller. Figure 2-30 Total power output from areas 5 and 2 for a change in active and reactive power load, along with change in power reference 2-32 0 Figure 2-31 Total power output from areas 5 and 2 for a change in only active power load, along with change in power reference Further investigation into this difference between the voltage source and current source inverter performance is yet to be carried out, however, it can be concluded that both inverter interfaces, when operating in the constant frequency control mode, are able to follow dispatch commands from the system operator, and reset their control references to be ready for the next event. Scenario 3: Line fault followed by outage of the line In scenario 1, the response of the constant frequency control scheme to generation trip events was discussed. In this scenario, the behavior to a line fault, followed by outage of the line will be discussed. In general, the 2000 bus Synthetic Texas system is robust to a N – 1 line outage. To determine the weakest lines, a brute force continuation power flow solution was carried out for every line in the system according to the following algorithm: 1. Load the base case power flow file, and make the status of a branch 0 2. Solve the power flow 3. Increase all active and reactive power load by 1% 4. Increase all generation active power by 1%, as long as the maximum limit is not violated 5. Solve power flow 6. If a successful solution is obtained, go back to step 3. 7. If a solution is not obtained, record the total amount of load increase, and go back to Step 1 to proceed to the next branch. Using this method, it was found that for the outage of almost all branches, the system could handle an approximate 10% increase in total active and reactive power load. However, there were two branches in the system, upon whose 2-33 0 outage, the resultant system couldn’t handle a large increase in load. For one of these branches, a tie line between Area 1 and Area 3, the system could only handle a load increase of 2%, while for the other branch, a branch internal to Area 3, the system could only handle a load increase of 4%. The minimum voltage in the system for Cases 1, 2 and 3 for a 6 cycle fault at the center of the branch between buses 3041 – 3046 (branch internal to Area 3), followed by outage of the branch, is shown in Figure 2-32. Figure 2-32 Minimum voltage in the system for a line fault on an internal area line followed by outage of the line It can be seen that the voltage source interface inverter is the most controlled response. The current source interface response was numerically unstable for the immediate duration around the fault, but since recovered. The synchronous machines response, while being oscillatory, is also stable. The oscillatory behavior can be attributed to the settings of the excitation system of the machine. Due to the fault occurring at one of the weaker locations in the system, fast voltage support is required to prevent the spread of the angles across the system. The voltage source interface inverter, is able to provide this fast response, while the current source interface is unable to do so quickly. The reactive power output of an inverter located close to the faulted bus is shown in Figure 2-33 for Cases 2 (blue curve) and 3 (red curve). 2-34 0 Figure 2-33 Reactive power output of a inverter located close to the fault The sluggishness of the current source interface and the rapid injection of current from the voltage source interface is observable from the figure. This rapid injection of reactive current from the voltage source interface inverter is crucial in order to help support the voltage at nearby buses in the system. The inverters are able to inject reactive current, as they were operating in a Q-priority mode. However, even with operation in a P-priority mode, the frequency control loop reduces the active power command during the fault, as upon inception of the fault, the frequency rises in the system. As the active power command reduces, and the voltage reduces, the active current command will reduce, providing more room for reactive power command to be injected. Thus, even in the P – priority mode, the inverters are able to provide voltage support. For the outage of the tie line between Areas 1 and 3, the minimum voltage in the system for Cases 2 and 3 for a 6 cycle fault at the center of the branch between buses 1081 – 3058 followed by outage of the branch, is shown in Figure 2-34. The outage of this tie line, causes an extreme low voltage condition in the vicinity of the boundary buses between the two areas. Area 1 exports power to Area 3, and thus, with the outage of this tie line, the power (around 410 MW) is routed through other tie line paths, which causes the transmission bus voltages to drop. This reduction in the transmission bus voltages impacts the motor loads in this region. Case 1 for this event had rotor angle instability issues, and is thus, not shown in the figure. The rotor angle instability in Case 1 for all synchronous machines could be prevented by increasing the speed of response of the static excitation system on the machines in Area 1, but the oscillations were still undamped. From the figure, it can be seen that Case 2, with the voltage source interface inverter, is the most robust source, for this event. 2-35 0 Figure 2-34 Minimum voltage in the system for a line fault on a tie line followed by outage of the line It is possible that the current source interface inverter’s gains can be tuned to be stable for this event. As an alternative, the sources in Area 1 whose MVA was greater than 150.0 MVA were replaced by the voltage source interface inverter. Thus, in this temporary setup (labeled as Case 2a), there were now 16 synchronous machines, 13 voltage source inverter interfaces, and the remaining 404 sources were represented by the current source interface inverter. For the same tie line outage, Figure 2-35 shows the minimum voltage across the system. Figure 2-35 Minimum voltage in the system for a line fault on a tie line followed by outage of the line, with few voltage source inverters The voltage source interface inverters, by rapidly injecting current into the system upon the occurrence of the fault, are able to reduce the drop in voltage, and this contributes towards a more stable response. Thus, it is possible that the entire system may need only few voltage source interfaced inverters to prevent a system collapse, while the other inverters can be current source interfaced, with all the inverters operating on a constant frequency control scheme. 2-36 0 Section 3: Three-Phase Inverter Models for Constant Frequency Operation In this chapter, detailed three-phase EMT-type inverter models with controls that enable constant frequency operation, as described in the previous chapter, are presented. Inverter Controls Inverter Control Objectives Figure 3-1 shows a generic generation unit interfaced to the power system via an inverter [as a voltage-sourced inverter (VSC)] and an RLC filter. The control objective of the inverter is to regulate real power Pi(t) and voltage magnitude �𝑣𝑣𝑠𝑠,𝑖𝑖 (𝑡𝑡)�|vt (t)| to their reference set points Pi* and �𝑣𝑣𝑠𝑠,𝑖𝑖 (𝑡𝑡)�*. The instantaneous three-phase output voltages of the inverter are 𝑣𝑣𝑡𝑡𝑡𝑡,𝑖𝑖 (𝑡𝑡) = �𝑣𝑣𝑡𝑡,𝑖𝑖 (𝑡𝑡)� 𝑐𝑐𝑐𝑐𝑐𝑐 �𝜃𝜃𝑡𝑡,𝑖𝑖 (𝑡𝑡)� 𝑣𝑣𝑡𝑡𝑡𝑡,𝑖𝑖 (𝑡𝑡) = �𝑣𝑣𝑡𝑡,𝑖𝑖 (𝑡𝑡)� 𝑐𝑐𝑐𝑐𝑐𝑐 �𝜃𝜃𝑡𝑡,𝑖𝑖 (𝑡𝑡) − 𝑣𝑣𝑡𝑡𝑡𝑡,𝑖𝑖 (𝑡𝑡) = �𝑣𝑣𝑡𝑡,𝑖𝑖 (𝑡𝑡)� 𝑐𝑐𝑐𝑐𝑐𝑐 �𝜃𝜃𝑡𝑡,𝑖𝑖 (𝑡𝑡) + 2𝜋𝜋 3 2𝜋𝜋 3 � Eq. 3-1 �. These voltages can be constructed at the inverter terminals via a modulation method by specifying |𝑣𝑣𝑡𝑡 (𝑡𝑡)| and 𝜃𝜃𝑡𝑡 (𝑡𝑡), whose reference points are determined by the proposed power sharing algorithm. Figure 3-2 shows the overall structure of the associated controller. In a system at constant frequency 𝑓𝑓0 , 𝜃𝜃𝑡𝑡,𝑖𝑖 (𝑡𝑡) is 𝜃𝜃𝑡𝑡,𝑖𝑖 (𝑡𝑡) = 𝛿𝛿𝑡𝑡,𝑖𝑖 (𝑡𝑡) + (2𝜋𝜋)𝑓𝑓0 𝑡𝑡. Eq. 3-2 In the proposed control architecture, units need access to accurate time. While it is possible to receive time t from GPS at every time step of 50us (GPS data is typically accurate to within 40 ns), another approach would be to run a local timer which is synchronized with GPS periodically. This method helps with occasional loss of data due to for example equipment malfunctioning. Modern power systems extensively use GPS data for measurement and control purposes. 3-1 0 Figure 3-1 Generic unit i interfaced to the power system. Figure 3-2 Overall structure of the proposed controller. Voltage Magnitude Controller Figure 3-3 shows the proposed voltage magnitude controller. When the selector is in +1 state, the controller uses an integral controller with gain G1 to determine the inverter terminal voltage �𝑣𝑣𝑡𝑡,𝑖𝑖 (𝑡𝑡)�. However, if current magnitude �𝑖𝑖𝑡𝑡,𝑖𝑖 (𝑡𝑡)� exceeds its limit �𝑖𝑖𝑡𝑡,𝑖𝑖 (𝑡𝑡)�max , the selector switches to -1 state, when the controller decreases the inverter terminal voltage with the gain G1G2 until it limits �𝑖𝑖𝑡𝑡,𝑖𝑖 (𝑡𝑡)�. Figure 3-3 Proposed voltage magnitude controller and current limiter. 3-2 0 Real Power Sharing Algorithm The underlying idea behind the proposed real power sharing algorithm is that the injected real power of a generating unit at the transmission level can be controlled by adjusting its voltage angle. We assume each grid-supporting unit has a ∗ preferred real power set point 𝑃𝑃𝑔𝑔𝑔𝑔 that depends on factors such as maximizing profit, required power reserve, available power, and possibly operator commands. The proposed algorithm needs to ensure that the allocation of power to gridforming and grid-supporting units can meet the total load demand. It calculates the modified power set point for each grid-supporting unit as ∗ ∗ 𝑃𝑃𝑔𝑔𝑔𝑔 ,∗𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 (𝑡𝑡) = 𝑃𝑃𝑔𝑔𝑔𝑔 + ∆𝑃𝑃𝑔𝑔𝑔𝑔 (𝑡𝑡) Eq. 3-3 ∗ ∗ ∑ ∆𝑃𝑃𝑔𝑔𝑔𝑔,𝑖𝑖 = 𝑃𝑃𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 – 𝑃𝑃𝑔𝑔𝑔𝑔 − ∑ 𝑃𝑃𝑔𝑔𝑔𝑔,𝑖𝑖 Eq. 3-4 ∗ where 𝑃𝑃𝑔𝑔𝑔𝑔 ,∗𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 (𝑡𝑡) is the is the modified set point due to droop, and ∆𝑃𝑃𝑔𝑔𝑔𝑔 (𝑡𝑡) is its adjustment. The sum of these adjustments should equal the difference between the total demand and sum of the power supplied by the grid-forming unit and the preferred powers of the grid-supporting units: where 𝑃𝑃𝑔𝑔𝑔𝑔 ≤ 𝑃𝑃𝑔𝑔𝑔𝑔,max . In the proposed power sharing algorithm, we follow the following design principles: Principle 1: The power limits of all grid-forming and grid supporting units should be met. Principle 2: The reference set points of grid-supporting units should not deviate from the preferred set points unless needed to meet power demand. - Principle 2*: The algorithm should also be able to enable participation of grid-forming and grid-supporting units, irrespective of their preferred set points, in power sharing. Principle 3: The share of grid-supporting units in power sharing should be based on their droop characteristic. If the grid-forming unit is large enough, the grid-supporting units continue to ∗ . In this case, the grid-forming unit's inject their preferred real power values 𝑃𝑃𝑔𝑔𝑔𝑔,𝑖𝑖 voltage angle 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡) is maintained at zero, and the angles 𝛿𝛿𝑔𝑔𝑔𝑔,𝑖𝑖 (𝑡𝑡) of grid∗ as supporting units are changed in a ramp at rate at C1 until 𝑃𝑃𝑔𝑔𝑔𝑔,𝑖𝑖 (𝑡𝑡) reaches 𝑃𝑃𝑔𝑔𝑔𝑔,𝑖𝑖 shown in Figure 3-4. Figure 3-4 Proposed real power controller. 3-3 0 However, if the grid-forming unit is not large enough or if its 𝑃𝑃𝑔𝑔𝑔𝑔,max is lowered to redispatch power, the grid-supporting units do need to participate in power sharing. We first discuss the proposed power sharing algorithm for the two-bus system shown in Figure 3-5, in which the power generated by one inverter is consumed by the other (e.g., an island consisting of a PV unit and a battery unit) and then extend it to a generic power system. For simplicity, we assume we start from a steady-state in which 𝛿𝛿𝑔𝑔𝑔𝑔 = 0; then the grid-supporting unit increases its ∗ ∗ power output to 𝑃𝑃𝑔𝑔𝑔𝑔,𝑖𝑖 . To meet 𝑃𝑃𝑔𝑔𝑔𝑔,𝑖𝑖 , the controller of the grid-supporting unit (similar to the controller shown in Figure 3-4) ramps its angle 𝛿𝛿𝑔𝑔𝑔𝑔,𝑖𝑖 (𝑡𝑡) at a rate of C1. Simultaneously, the grid-forming unit monitors its output power and ∗ compares it with the limit |𝑃𝑃𝑔𝑔𝑔𝑔,max |. If |𝑃𝑃𝑔𝑔𝑔𝑔 | < |𝑃𝑃𝑔𝑔𝑔𝑔,max |, we have the same controls as the large grid-forming case discussed above. Figure 3-6(a) shows the vector diagram for this operating condition in the dq frame synchronized to ∗ | > |𝑃𝑃𝑔𝑔𝑔𝑔,max |, i.e., the power by the grid-supporting unit (2πf0)t. However, if |𝑃𝑃𝑔𝑔𝑔𝑔 exceeds the capability of the grid-forming unit, as soon as |𝑃𝑃𝑔𝑔𝑔𝑔 | > |𝑃𝑃𝑔𝑔𝑔𝑔,max |, the controller of the grid-forming unit changes its angle 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡) to avoid further increase of its power and violating the limit. Figure 3-6(b) shows the vector diagram for this operating condition. If 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡) is ramped at a rate C2>C1, 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡) − 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡) changes at the rate C2–C1 until |𝑃𝑃𝑔𝑔𝑔𝑔 (t)|= |𝑃𝑃𝑔𝑔𝑔𝑔 (t)|=| 𝑃𝑃𝑔𝑔𝑔𝑔,max |. Then the controller of the grid-supporting unit continues to ramp up ∗ 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡)δgs (t), but it cannot regulate 𝑃𝑃𝑔𝑔𝑔𝑔 (t) to 𝑃𝑃𝑔𝑔𝑔𝑔 because 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡) − 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡) is influenced by the grid-forming unit and C2 > C1. As a result, both 𝑣𝑣𝑔𝑔𝑔𝑔 (𝑡𝑡) and 𝑣𝑣𝑔𝑔𝑔𝑔 (𝑡𝑡) vectors rotate in the dq frame at a speed of C1 rad/s. Therefore, the system frequency 𝑓𝑓𝑠𝑠𝑠𝑠𝑠𝑠 changes such that |𝑓𝑓𝑠𝑠𝑠𝑠𝑠𝑠 - f0|=C1/2π. ∗ | <= |𝑃𝑃𝑔𝑔𝑔𝑔,max |, at which point it is preferred to bring Eventually, we have |𝑃𝑃𝑔𝑔𝑔𝑔 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡) back to zero to maximize power sharing capability reserves. However, changing 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡) should not affect the ability of the grid-supporting unit to control its power 𝑃𝑃𝑔𝑔𝑔𝑔 (t). Therefore, C0 should be smaller than C1 so that while the grid-forming unit adjusts 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡), the grid-supporting unit can adjust its angle relative to 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡). Figure 3-6(c) shows the vector diagrams for this operating condition. Figure 3-5 A sample two-bus system. 3-4 0 Figure 3-6 Vector diagrams of the two-bus system in operating conditions (a) grid-forming unit is large (see text for definition); (b) grid-forming unit is limited; and (c) grid-forming unit is limited and brings 𝜹𝜹𝒈𝒈𝒈𝒈 (𝒕𝒕) to zero. Angle Droop Algorithm To avoid steady-state deviation of 𝑓𝑓𝑠𝑠𝑠𝑠𝑠𝑠 from f0, we define upper and lower trigger ∗ when 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡) points for 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡). In the angle droop implementation, we reduce 𝑃𝑃𝑔𝑔𝑔𝑔 ∗ is outside these trigger points. The adjustment ∆𝑃𝑃𝑔𝑔𝑔𝑔 in (3) is calculated as ⎧ 0, ⎪ ∗ ∆𝑃𝑃𝑔𝑔𝑔𝑔 = 𝐷𝐷 �𝛿𝛿𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 − 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡)�, ⎨ ⎪𝐷𝐷 �𝛿𝛿𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 − 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡)�, ⎩ 𝛿𝛿𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 < 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡) < 𝛿𝛿𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 𝛿𝛿𝑔𝑔𝑠𝑠,𝑚𝑚𝑚𝑚𝑚𝑚 < 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡) Eq. 3-5 𝛿𝛿𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 > 𝛿𝛿𝑔𝑔𝑔𝑔 (𝑡𝑡) where D is the angle droop gain. With multiple grid-supporting units, D of each unit determines its power share. Figure 3-7 compares the droop characteristic of the proposed angle droop algorithm with conventional frequency droop. The angle droop characteristic, Figure 3-7(a), has a soft limiter shape (in governor terminology, this type of limiter is called a non-step deadband) while the frequency droop characteristic, Figure 3-7(b), is primarily a straight sloped line. However, practically, the frequency droop characteristic also has a small dead band of around 0.017 – 0.036 Hz to prevent unnecessary movement of the governor of machines. The use of the dead band in the angle droop path of the grid supporting inverters is to allow the grid forming inverter control to react first, while allowing for a stabilizing effect on the entire system control. This is because in frequency droop all units naturally stabilize to settle at the same frequency as frequency is a system wide variable. However, voltage angles are a local property in the power system, and in order to ensure transfer of power, a difference must exist in value of the angles, and thus in order to stabilize the system after a disturbance, the dead band in the controller plays a role. For symmetry, in the remainder of this report, we assume 𝛿𝛿𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 = - 𝛿𝛿𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 but the proposed angle droop algorithm can operate without this assumption. The choice of 𝛿𝛿𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 is a trade-off between 3-5 0 power sharing accuracy based on D coefficients and the time it takes to reach the steady state. This is discussed later in detail under parameter selection. Figure 3-8 shows the overall real power sharing algorithm generalized to multiple grid-supporting units. The hysteresis band prevents interference of the power limiting and angle control features of the grid-forming unit. A bandwidth too large has allows |𝑃𝑃𝑔𝑔𝑔𝑔 (t)| to exceed 𝑃𝑃𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 ; a bandwidth too small may result in system instability due to frequent changes in the control mode. Therefore, the bandwidth should be chosen as a modest fraction of 𝑃𝑃𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 , e.g., 1%. In the proposed method, communication error in the GPS signal, e.g., delay or corrupted signal) does not affect real power tracking: Due to closed loop control of P as shown in Figure 3-8, P tracks its reference. Therefore, a delay or miscommunication in t does not affect δ in the steady state. However, it can change δi, which has no effect on our real power control. However, it changes the share of inverter i in power sharing. Nevertheless, the inverter units can continue their operation with their internal clock until a trusted signal is received. Figure 3-7 (a) proposed angle droop; (b) conventional frequency droop. 3-6 0 Figure 3-8 Proposed real power sharing algorithm; (a) grid-forming unit; and (b) gridsupporting units. Parameter Design As mentioned above, the proposed angle droop algorithm ensures voltage angles are within their limits. However, the ramp rates Ci to change angles are finite to accommodate the physical capabilities of the prime mover and possibly stability considerations. The limits for Ci in this work are based on values found heuristically, but if needed, studies can be performed to find the theoretical limits. Because the angles change with a certain rate, it takes some finite time for the voltage vectors to rotate and reach the steady state. Without extra measures, during this time, the real powers of grid-supporting units are uncontrolled and may exceed their limits even though their reference values are limited. To prevent this, a variable gain is adopted: If the real power of a grid-supporting unit reaches its limit, the ramp rate is changed from C1 to a larger value C3. If C3 > C2, real power limiting scheme of the grid-forming unit is no longer able to change the real power of the grid-supporting unit because the voltage vector of the gridsupporting unit will rotate at the speed of C3 - C2. Therefore, the grid-supporting unit can limit its output real power during this time. Therefore, these parameters should be chosen such that C0<C1<C2<C3. (Note that the same should be true for each individual inverter when there are multiple inverters.) 3-7 0 To determine the share of each grid-supporting unit in supplying the needed real power 𝑃𝑃𝑔𝑔𝑔𝑔−𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡−𝑐𝑐ℎ𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 can be defined as ∗ * 𝑃𝑃𝑔𝑔𝑔𝑔−𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡−𝑐𝑐ℎ𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 = ∑ 𝛥𝛥𝑃𝑃𝑔𝑔𝑔𝑔,𝑖𝑖 = ∑ 𝐷𝐷𝑖𝑖 (𝛿𝛿𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 − 𝛿𝛿𝑔𝑔𝑔𝑔,𝑖𝑖 ) Pgs-total-change = ∑ ∆Pgs,i = ∑ Di (δgs,min -δave ) Eq. 3-6 If 𝑃𝑃𝑔𝑔𝑔𝑔−𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡−𝑐𝑐ℎ𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 = 0, i.e., the grid-forming unit is large enough to supply the power demand beyond the preferred set points of the grid-supporting units, 𝛿𝛿𝑔𝑔𝑔𝑔 = 0 and all 𝑣𝑣𝑔𝑔𝑔𝑔,𝑖𝑖 vectors cluster around it as shown in Figure 3-9(a). Otherwise, as shown in Figure 3-9(b), voltage vectors cluster around a hypothetical vector at 𝛿𝛿𝑎𝑎𝑎𝑎𝑎𝑎 = 𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚 (𝛿𝛿𝑔𝑔𝑔𝑔,𝑖𝑖 ). If Di values are small, |𝛿𝛿𝑎𝑎𝑎𝑎𝑎𝑎 | is large and for all gridsupporting units 𝛿𝛿𝑔𝑔𝑔𝑔,𝑖𝑖 ≈ 𝛿𝛿𝑎𝑎𝑎𝑎𝑎𝑎 . Therefore, ∗ 𝑃𝑃𝑔𝑔𝑔𝑔−𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡−𝑐𝑐ℎ𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 = ∑ 𝛥𝛥𝑃𝑃𝑔𝑔𝑔𝑔,𝑖𝑖 = ∑ 𝐷𝐷𝑖𝑖 (𝛿𝛿𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 − 𝛿𝛿𝑎𝑎𝑎𝑎𝑎𝑎 ) Eq. 3-7 Subsequently, 𝐷𝐷 ∗ 𝛥𝛥𝑃𝑃𝑔𝑔𝑔𝑔,𝑖𝑖 = ∑ 𝑖𝑖 𝑃𝑃𝑔𝑔𝑔𝑔−𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡−𝑐𝑐ℎ𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 𝐷𝐷𝑖𝑖 Eq. 3-8 That is, the real power change of each grid-supporting unit is (approximately) proportional to its droop gain Di. Figure 3-9 Vector diagrams of the generation units in the steady state when the grid-forming unit is (a) large (see text for definition); and (b) limited. Simulation Case Studies Several case studies are conducted to evaluate the performance of the proposed algorithms in different operating conditions. The software tool PSCAD/EMTDC is employed to model the fast, electromagnetic transients of power electronics-based inverters. Figure 3-10 shows the study system chosen as the three-machine, IEEE/WSCC nine-bus system. The base values of the 3-8 0 voltage and power used for per-unit calculations are 230 kV and 100 MVA. The rated powers of the generation units at buses 1-3 are 250 MVA, 192 MVA, and 128 MVA. Per-unit currents are calculated on the base of their associated generator. The loads are modeled as a constant impedance calculated at the nominal voltage, except for the section where induction motor loads are used. All three generation units are interfaced to the grid via an inverter. The generation unit at bus 2 is chosen as the grid-forming unit (gf), and the generation units at buses 1 and 3 are chosen as grid-supporting units (gs1 and gs3). Initially, buses 1-3 regulate their output real power and bus voltage magnitudes to the rated values of the nine-bus system. Table 3-1 shows the controller parameters. Figure 3-10 Study system. Table 3-1 Parameters of the Controllers G1= 10, G2= 2 𝑖𝑖𝑡𝑡𝑡𝑡,𝑡𝑡ℎ𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒ℎ𝑜𝑜𝑜𝑜𝑜𝑜 = 1.5 pu (i=1, 2, 3) Voltage controller Real power controller 𝑃𝑃𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 = 192 MW D1=5*103 Angle droop 3-9 0 C0= 0.75, C1= 1, C2= 1.25, C3= 5 𝑃𝑃𝑔𝑔𝑔𝑔,1,𝑚𝑚𝑚𝑚𝑚𝑚 = 250 MW, 𝑃𝑃𝑔𝑔𝑠𝑠,3,𝑚𝑚𝑚𝑚𝑚𝑚 = 128 MW 𝑀𝑀𝑀𝑀 𝑟𝑟𝑟𝑟𝑟𝑟 , D3=2.5*103 𝑀𝑀𝑀𝑀 𝑟𝑟𝑟𝑟𝑟𝑟 𝛿𝛿𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 = − 𝛿𝛿𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 = 0.75 rad Step Change in 𝑷𝑷∗𝒈𝒈𝒈𝒈,𝒊𝒊 and |𝒗𝒗∗𝒈𝒈𝒈𝒈,𝒊𝒊 | In this case study, initially the grid-supporting units output their preferred real ∗ ∗ increases in a step by 35 MW, and at t=1.3 s, |𝑣𝑣𝑔𝑔𝑔𝑔,1 | powers. At t=0.3 s, 𝑃𝑃𝑔𝑔𝑔𝑔,3 increases in a step by 0.014 pu. The loads do not change. Figure 3-11 shows voltage, current, real power, and frequency at buses 1—3. 𝑃𝑃𝑔𝑔𝑔𝑔,3 (𝑡𝑡) tracks its set ∗ with a rise time of 150 ms (inversely proportional to C1) and point 𝑃𝑃𝑔𝑔𝑔𝑔,3 ∗ | with a rise time of 50 ms. During transients, the current |𝑣𝑣𝑔𝑔𝑔𝑔,1 (𝑡𝑡)| tracks |𝑣𝑣𝑔𝑔𝑔𝑔,1 magnitudes change smoothly. Because the load is unchanged, after the increase in 𝑃𝑃𝑔𝑔𝑔𝑔,3 (𝑡𝑡), 𝑃𝑃𝑔𝑔𝑔𝑔 (𝑡𝑡) decreases to maintain power balance. The system frequency returns to its rated value (60 Hz) in the steady state. Figure 3-11 Measurements as (a) 𝑷𝑷∗𝒈𝒈𝒈𝒈,𝟑𝟑 changes from 85 to 120 MW at t=0.3 s; (b) 𝒗𝒗∗𝒈𝒈𝒈𝒈,𝟏𝟏 changes from 1.026 to 1.040 pu at t=1.3 s. Load Increase In this case study at t=1s the real power of the load at bus 6 increases by 15 MW, and at t=3s, the real power of the load at bus 5 increases by 80 MW. This scenario is simulated once assuming the grid-forming unit can accommodate the whole load change (𝑃𝑃𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 is large) and once when it cannot. Figure 3-12 shows the results. In both cases, the first load increase is supported by an increase in 𝑃𝑃𝑔𝑔𝑔𝑔 (𝑡𝑡) because �𝑃𝑃𝑔𝑔𝑔𝑔 (𝑡𝑡)� < 𝑃𝑃𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 . However, the two systems respond differently to the second load increase. In the system with the large grid-forming unit, the load increase is supported by an increase in 𝑃𝑃𝑔𝑔𝑔𝑔 (𝑡𝑡) and in the steady state, 𝑃𝑃𝑔𝑔𝑔𝑔 =264 MW. In the system with the small grid-forming unit, the load increase is initially responded to by an increase in 𝑃𝑃𝑔𝑔𝑔𝑔 (𝑡𝑡) until 𝑃𝑃𝑔𝑔𝑔𝑔 (𝑡𝑡)= 𝑃𝑃𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 . Then, 𝑃𝑃𝑔𝑔𝑔𝑔,1 (𝑡𝑡) and 𝑃𝑃𝑔𝑔𝑔𝑔,3 (𝑡𝑡) ramp up. It takes approximately 1.5 s for the grid-supporting units to reach their new reference power set points. During this time, 𝑃𝑃𝑔𝑔𝑔𝑔,1 (𝑡𝑡) and 𝑃𝑃𝑔𝑔𝑔𝑔,3 (𝑡𝑡) are not under control ∗ ∗ =48 MW and ∆𝑃𝑃𝑔𝑔𝑔𝑔,3 =23 but are within their limits. In the steady state, ∆𝑃𝑃𝑔𝑔𝑔𝑔,1 ∗ ∗ MW. The ratio ∆𝑃𝑃𝑔𝑔𝑔𝑔,1 / ∆𝑃𝑃𝑔𝑔𝑔𝑔,3 is 2.09, which is very close to the ratio 𝐷𝐷1 /𝐷𝐷3 = 3-10 0 2.00 (4.5% error). Choosing smaller a 𝐷𝐷𝑖𝑖 results in more precise power sharing but a longer response time. The frequency returns to 60 Hz in both cases. Figure 3-12 Generation units measurements for the system with a (a) large (compared with load demand) grid-forming unit; (b) small grid-forming unit. In both systems, the load at bus 6 increases by 15 MW at t=1 s and the load at bus 5 increases by 80 MW at t=3 s. Dynamic Loads This case study investigates the performance of the proposed algorithm in the presence of dynamic loads with inertia. Two induction motors (IM) are connected to bus 6 (15 MW, IM1) and bus 5 (80 MW, IM2). Initially, both IMs run at no-load conditions. IM1 is loaded at t=1 s, and IM2 is loaded at t=3 s. Both loads are linear with a mechanical torque proportional to speed. Figure 313 shows the results. The grid-forming unit provides the power needed by IM1 without exceeding its real power limit. However, loading of IM2 needs power to be provided by the grid-supporting unit and hence, results in increase of 𝑃𝑃𝑔𝑔𝑔𝑔,1 (𝑡𝑡) and 𝑃𝑃𝑔𝑔𝑔𝑔,3 (𝑡𝑡). During start-up, the rotor speeds of the IMs are smooth, but their electromagnetic torques oscillate. Subsequently, their real powers (product of electromagnetic torque and rotor speed) oscillate too, resulting in small oscillations in the voltage and real power. These oscillations are related to the mechanical modes of the IMs and their analysis is beyond the scope of this work. The proposed algorithm performs effectively with dynamic loads represented by induction machines. 3-11 0 Power Redispatch In this case study, initially the grid-supporting units output their preferred real powers and the grid supporting unit provides 170 MW. At t=2 s, 𝑃𝑃𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 decreases from 192 MW to 120 MW. Subsequently, a portion of the load initially supplied by the grid-forming unit has to be provided by the gridsupporting units. Figure 3-14 shows that after the reduction in 𝑃𝑃𝑔𝑔𝑓𝑓,𝑚𝑚𝑚𝑚𝑚𝑚 , 𝑃𝑃𝑔𝑔𝑔𝑔,1 (𝑡𝑡) and 𝑃𝑃𝑔𝑔𝑔𝑔,3 (𝑡𝑡) increase by 33 MW and 17 MW. This change is proportional to the droop gains of the grid-supporting units as expected. Figure 3-13 Measurements of buses 1-3 and machine loads as IM1 changes from no-load to full-load at t=1 s and IM2 changes from no-load to full-load at t=3 s. 3-12 0 Figure 3-14 Measurements at buses 1—3 when 𝑷𝑷𝒈𝒈𝒈𝒈,𝒎𝒎𝒎𝒎𝒎𝒎 decreases from 192 MW to 120 MW at t=2 s. Fault This case study evaluates the system response to a fault. Initially, the system operates at nominal conditions when a three-phase bolted fault occurs at t=1.0 s in the middle of one of the double transmission lines between buses 4 and 5 (this second line is added for this case study). After 100 ms, the fault is cleared by the circuit breakers at the two ends of the line. Figure 3-15(a) shows the system response. The current limiting function of the controller activates when the current reaches the threshold value. This threshold in general depends on the rating of the switches (with respect to the inverter rating), cooling mechanism, and system considerations. In this paper, this limit is chosen heuristically. The limiter is clearly not a replacement for protection or the current limitation provided by limiting the reference current values. The maximum instantaneous current magnitude is 1.8 pu. Moreover, minimum and maximum voltage voltages of the generation buses are 0.2 pu and 1.1 pu, respectively. When the fault is cleared, the system returns to its normal operation. Figure 3-15(b) shows the result of the same case study if the proposed 3-13 0 voltage controller is not augmented with a current limiter. The maximum current is 4.8 pu, and the minimum and maximum voltages are 0.5 pu and 2.0 pu. Figure 3-15 Measurements at buses 1—3 when a fault occurs at t=1.0 s and clears after 100 ms; (a) with the current limiter; (b) without. Performance Evaluation in the Presence of Synchronous Generation The previous sections focused on an angle droop-based power sharing method for a 100% inverter-based power system, which is an extreme operating scenario and presently may occur only a few hours during a day. In this section, the interactions between the proposed controllers of inverters and SG controls is investigated, using the EMT-type models described before. This study is important because the proposed angle droop-based method enables constant frequency operation of the power system, but the speed—droop controller of the synchronous generator (SG) changes its real power when its frequency changes. Thus, studying the potential interaction between the angle droop-based method in inverter-based units and the SG controller in systems with a small percentage of synchronous generation is required. To evaluate the performance of the proposed controllers for an inverterdominated power system, different case studies are simulated in PSCAD/EMTDC software for the modified IEEE/WSCC nine-bus system. Figure 3-16 shows the study system with four generation units. Three generation units at bus 1-3 are integrated to the system via a VSC unit. Based on IEEE 9bus system, the generation unit at bus 2 with the rated power of 192 MVA is considered as the grid-forming unit, and generation units at buses 1 and 3 with the rated power of 250 MVA and 128 MVA are considered as grid-supporting units. A synchronous generator (SG) with a rated power of 33 MVA is connected to bus 6. The base values of power and voltage for per-unit calculations are 100 MVA and 230 kV. Per-unit currents are calculated based on their own generation units. 3-14 0 Figure 3-16 Modified IEEE/WSCC 9-bus system. Synchronous Generator Connection This case study evaluates the performance of the proposed controller for the inverter-based power system when an additional SG is connected to bus 6. In this case, the SG is synchronized to the network at t=1 s and its input torque is ramped up at t = 2 s and reaches the rated value at t=3.5 s. Figure 3-17 shows the real power, frequency, current magnitude, and voltage magnitude of buses 1—3 and 6. The SG provides 33 MW of power. Thus, to maintain power balance, the real power controller of the grid-forming unit reduces 𝑃𝑃𝑔𝑔𝑔𝑔 (t) with a constant rate of C2, and the real power controllers of grid-supporting units track their defined set point values, which confirms the performance of the controller to maintain power balance. In addition, the voltage controller of all generation units regulate ∗ | at rated values, which confirms the performance of the amplitude voltages |𝑣𝑣𝑠𝑠,𝑖𝑖 the voltage controller. Note that because synchronization does not occur exactly at the moment of zero power transfer (when the angles on the sides of the switch are the same), there is some exchange of power immediately after switch closure. Compared to the results presented later in this subsection, e.g., load change and power redispatch, more deviation in delta is experienced in the case presented here. 3-15 0 Figure 3-17 Performance of the controller when the SG is connected to the system. Load Change This case study evaluates the performance of the proposed controllers when loads change. Initially the system operates at nominal conditions. The load at bus 6 increases by 20 MW at t=2 s and the load at bus 5 increases by 70 MW at t=4 s respectively. Figure 3-18 shows the response of the controllers. When the load at bus 6 increases, the grid-forming unit responds by increasing 𝑃𝑃𝑔𝑔𝑔𝑔 (t), and it can support the whole load change. When the second load is added to the system, the grid—forming unit initially responds by increasing 𝑃𝑃𝑔𝑔𝑔𝑔 (t) until |𝑃𝑃𝑔𝑔𝑔𝑔 (t)|= 𝑃𝑃𝑔𝑔𝑔𝑔,𝑚𝑚𝑚𝑚𝑚𝑚 . Thus, the angle droop controller of the grid supporting units responds to load increase by increasing the Pgs,1(t) and Pgs,2(t), and they reach their new ∗ power set point approximately within 1.5 s. In this case, ∆𝑃𝑃𝑔𝑔𝑔𝑔,1 = 23 MW and ∗ ∗ ∗ ∆𝑃𝑃𝑔𝑔𝑔𝑔,3 =13MW (∆𝑃𝑃𝑔𝑔𝑔𝑔,1 /∆𝑃𝑃𝑔𝑔𝑔𝑔,3 = 2.09). and this ratio is close to D1/D2 = 2 (4.54% error), which confirms the performance of the real power controllers. In this case, when the loads are added to the system, the SG increases its reactive power to try to remedy the initial drop in the terminal voltage. Because the excitation of the 3-16 0 SG has a high gain, and other generation units contribute to power sharing, the SG’s terminal voltage returns to the nominal value. In addition, when the loads increase, the system frequency deviates from 60 Hz. Thus, the angle droop activates, the real power of the generation units changes, and the frequency returns to 60 Hz. Note that, as shown in Figure 3-18. the phase angle of the grid-forming unit (and hence, its frequency) does not change unless the power delivered by this unit is about to exceed it maximum permissible power. This, however, does not imply that Pgf does not change because this power depends on the angle differences in the system and the angles (and frequencies) of the grid supporting units do change. Figure 3-18 Performance of the controllers when the load at bus 6 increases by 20 MW at t=2 s and the load at bus 5 increases by 70 MW at t=4 s. 3-17 0 Fault This case study evaluates the performance of the proposed controllers when a fault occurs in the system. Initially the system operates at nominal conditions. Two parallel lines with similar parameters are assumed as the transmission line between buses 8 and 9. A three-phase bolted fault at t=1 s occurs at the middle of one of them, and this fault is cleared after 100 ms by opening the circuit breakers. Figure 3-19 shows the response of the controllers. During the fault, there are some oscillations in the system, but when the fault is cleared, the system returns to its nominal condition. Figure 3-19 Performance of the controllers when a three-phase bolted fault occurs at t=1 s at the middle of the transmission line between bus 8 and bus 9. Power Dispatch This case study evaluates the performance of the studied controller to track a change in P*gs,i. In this case, initially the system operates at nominal conditions. ∗ ∗ changes from 71.6 MW to 96.6 MW and 𝑃𝑃𝑔𝑔𝑔𝑔,3 changes from 85 At t=2 s, 𝑃𝑃𝑔𝑔𝑔𝑔,1 MW to 120 MW. Figure 3-20 shows that the real power controller of grid∗ supporting units track their reference value 𝑃𝑃𝑔𝑔𝑔𝑔,𝑖𝑖 which is proportional to their droop gains, and 𝑃𝑃𝑔𝑔𝑔𝑔 (t) reduces from 142 MW to 82 MW, which confirms the performance of the real power controllers. Since the system has a constant frequency at 60 Hz, the SG does not contribute to power sharing. 3-18 0 Figure 3-20 Performance of the controllers in a case of changing P*gs,1 and P*gs,3 Effect of Controller Gains on the Oscillation Frequency of the SG This section studies the effect of the gains of the inverter controllers on the oscillation frequency of the SG in an inverter-dominated power system. The rotor of the SG is a complex mechanical system. The rotor contains shaft sections with different sizes and couplings. This rotor system has a large number of torsional vibration frequencies both above and below the rated frequency. Figure 3-21 shows the structure of a shaft system model. The five torsional masses include the rotors of the generator, two low-pressure (LP) turbine sections, an intermediate-pressure (IP) turbine section, and a high-pressure (HP) turbine section. 3-19 0 Figure 3-21 Structure of a typical lumped –mass system model [3-1] The shaft system dynamic characteristics are defined by three sets of parameters: inertia constant H of the individual masses, torsional stiffness K of shaft sections connecting adjacent masses, and damping coefficient D associated with each mass [3-1]. The linearized equations of the complete rotor system by ignoring damping factor can be summarized as SG: 𝑑𝑑�∆ωsg � 𝐾𝐾4𝑆𝑆𝑆𝑆 𝑑𝑑𝑑𝑑 = 𝑑𝑑(∆ω1 ) 𝐾𝐾21 = 𝑑𝑑𝑑𝑑 𝑑𝑑(∆ω2 ) = 𝑑𝑑𝑑𝑑 2HSG 2H2 𝐾𝐾4𝑆𝑆𝑆𝑆 +𝐾𝐾𝑠𝑠 2HSG �∆𝜔𝜔sg �𝜔𝜔0 Turbine 1: 2H1 𝐾𝐾21 (Δσ4) - (Δσ2) - (Δσ1 ) + 𝐾𝐾21 2H1 (Δσ1) 𝑑𝑑(∆𝜎𝜎1 ) Turbine 2: 𝐾𝐾23 2H2 (Δσsg) 𝑑𝑑𝑑𝑑 𝑑𝑑𝑑𝑑 𝐾𝐾 +𝐾𝐾21 2H2 (Δσ2) 𝑑𝑑(∆𝜎𝜎2 ) = (Δσ3) 𝑑𝑑(∆𝜎𝜎3 ) = 𝑑𝑑𝑑𝑑 Turbine 3: 𝑑𝑑(∆ω3 ) = 𝑑𝑑𝑑𝑑 𝐾𝐾32 2H3 (Δσ2) + 𝐾𝐾34 2H3 𝐾𝐾 +𝐾𝐾34 (Δσ4) - 32 (∆𝜔𝜔3 )𝜔𝜔0 2H3 𝑑𝑑𝑡𝑡 Turbine 4: 𝒅𝒅(𝚫𝚫𝛚𝛚𝟒𝟒 ) 𝒅𝒅𝒅𝒅 = 𝑲𝑲𝟒𝟒𝟒𝟒𝟒𝟒 𝟐𝟐𝐇𝐇𝟒𝟒 (Δσsg) + 𝑲𝑲𝟒𝟒𝟒𝟒 𝟐𝟐𝐇𝐇𝟒𝟒 (Δσ3) - 𝑲𝑲𝟒𝟒𝟒𝟒𝟒𝟒 +𝑲𝑲𝟒𝟒𝟒𝟒 (∆𝝎𝝎𝟒𝟒 )𝝎𝝎𝟎𝟎 𝟐𝟐𝐇𝐇𝟒𝟒 = = (∆𝜔𝜔1 )𝜔𝜔0 (Δσ3) - 23 (∆𝜔𝜔2 )𝜔𝜔0 𝑑𝑑(∆𝜎𝜎sg ) (Δσ4) 𝒅𝒅(𝚫𝚫𝝈𝝈𝟒𝟒 ) 𝒅𝒅𝒅𝒅 = Natural Frequencies of the Shaft System The natural frequencies of the shaft system of the SG can be calculated by writing the rotor system equations in the state-space form 𝑥𝑥̇ = 𝐴𝐴𝐴𝐴. The state variables are thus the speed deviations ∆𝜔𝜔i and the rotor angle Δσi with i = 1 to 5 (four turbines and one SG). The elements of the state matrix A of the rotor system depend on the torsional stiffness coefficients, the inertia constants of the individual masses, and the generator synchronizing torque coefficient Ks. The parameters of an example complete rotor system are shown in Table 3-2. 3-20 0 Table 3-2 Inertia constants and torsional stiffness coefficients of rotor system H (s) H1= 0.124 H2= 0.232 H3= 1.155 H4= 1.192 HSG=0.855 K (pu) K12= 21.8 K23=48.4 K34=75.6 K4SG= 62.3 Ks=1.98 The eigenvalues of matrix A give the natural frequencies of the shaft system. Considering the parameters given in Table 3-2, matrix A is A=[ 0 0 0 0 0 -87.9032 87.9032 0 0 0 0 0 0 0 0 46.9828 -151.2931 104.3103 0 0 0 0 0 0 0 0 20.9524 -53.6797 32.7273 0 0 0 0 0 0 0 31.7114 -57.8440 26.1326 0 0 0 0 0 0 0 0 36.4327 -37.590 376.9910 0 0 0 0 0 0 0 0 0 0 376.9910 0 0 0 0 0 0 0 0 0 0 376.9910 0 0 0 0 0 0 0 0 0 0 376.9910 0 0 0 0 0 0 0 0 0 0 376.9910 0 0 0 0 0] 3-21 0 0 Since we are considering a rotor with five masses, there are five oscillation modes. The natural frequencies, as given by the imaginary components of the eigenvalues of the matrix A, are 1.611 Hz, 16. 376 Hz, 24.123 Hz, 30.326 Hz, and 43.996 Hz. Changing Control Gains and Their Impacts on the Oscillation Frequency of the System This subsection studies the impact of controller gains on the oscillation frequencies of the system. The oscillation frequencies of different parameters are measured by changing the gains of real power controllers. The oscillation frequency is measured for different parameters as shown in Table 3-3. 𝑇𝑇𝑚𝑚𝑆𝑆𝑆𝑆 , 𝑓𝑓𝑆𝑆𝑆𝑆 , and 𝜔𝜔𝑆𝑆𝑆𝑆 are the mechanical torque, the frequency, and the speed of the SG, respectively. In addition, 𝑓𝑓𝑖𝑖𝑖𝑖𝑖𝑖 , 𝑃𝑃𝑖𝑖𝑖𝑖𝑖𝑖,𝑔𝑔𝑔𝑔 , and 𝑃𝑃𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖𝑖 are the frequency and real power of the grid-supporting units and the real power of grid-forming unit, respectively. This value of inverter frequency is however calculated at the terminal of the inverter, outside the control architecture. The parameters shown in Table 3-3 are defined in Figure 3-3 and Figure 3-8. Table 3-3 Oscillation frequencies of an inverter-dominated power system Oscillation frequency of different variables by changing C1and C2 (Hz) Gridsupporting unit gains 𝐺𝐺1 =10 C1=1 𝐺𝐺1 =10 C1=5 𝐺𝐺1 =10 C1=10 Quantity C2=1.25 C2=5 C2=10 𝑇𝑇𝑚𝑚𝑆𝑆𝑆𝑆 1.11 1.1 1.1 1.1 1.1 1.1 1.1 1.1 1.1 𝑓𝑓𝑖𝑖𝑖𝑖𝑖𝑖 1.1, 30.59 1.05, 31.5 1.1, 31.8 30.44 30.7 30.7 𝑃𝑃𝑖𝑖𝑖𝑖𝑖𝑖 𝑔𝑔𝑔𝑔 1.11, 30.1 1.1, 30.9 1.1, 31.9 𝑇𝑇𝑚𝑚𝑆𝑆𝑆𝑆 1.1 1.1 1.1 𝑓𝑓𝑆𝑆𝑆𝑆 1.1 1.1 1.1 1.1 1.1 1.1 𝑓𝑓𝑖𝑖𝑖𝑖𝑖𝑖 1.1, 32.79 1.1, 31.2 1.1, 31.8 30.55 31.7 31.9 𝑃𝑃𝑖𝑖𝑖𝑖𝑖𝑖 𝑔𝑔𝑔𝑔 1.1, 32.56 1.1, 31.7 1.1, 31.8 𝑇𝑇𝑚𝑚𝑆𝑆𝑆𝑆 1.1 1.1 1.1 𝑓𝑓𝑆𝑆𝑆𝑆 1.1 1.1 1.1 1.1 1.1 1.1 𝑓𝑓𝑖𝑖𝑖𝑖𝑖𝑖 1.1, 31.44 1.1, 31.63 1.1, 31.4 31.5 31.54 31.5 𝑃𝑃𝑖𝑖𝑖𝑖𝑖𝑖 𝑔𝑔𝑔𝑔 1.1, 31.5 1.1, 31.56 1.1, 31.5 𝑓𝑓𝑆𝑆𝑆𝑆 𝜔𝜔𝑆𝑆𝑆𝑆 𝑃𝑃𝑖𝑖𝑖𝑖𝑖𝑖 𝑔𝑔𝑔𝑔 𝜔𝜔𝑆𝑆𝑆𝑆 𝑃𝑃𝑖𝑖𝑖𝑖𝑖𝑖 𝑔𝑔𝑔𝑔 𝜔𝜔𝑆𝑆𝑆𝑆 𝑃𝑃𝑖𝑖𝑖𝑖𝑖𝑖 𝑔𝑔𝑔𝑔 3-22 0 The steady-state simulation results for different values of controller gains show that when the real power controller gains change between their original design value (C1=1 and C2=1.25) and 10, the oscillation frequency of the SG’s real power is 1.1 Hz, which is close to the oscillation frequency of the SG calculated from rotor equations (1.611 Hz). In addition, the oscillation frequencies of real powers of the inverters are approximately 1.1 Hz and 31 Hz, which are also close to the oscillation frequencies of the SG calculated from rotor equations (1.611 Hz and 30.326 Hz). In addition, Figure 3-22 shows the real power of the all generation units when the controller gain C1 has a value greater than 10 (e.g., C1=15) and C2=20. As it shown in this figure, there is an oscillation frequency in the real power of inverters and the SG. All the generation units have the oscillation frequency close to 30 Hz, which is close to the oscillation frequency of the SG calculated from the shaft system (30.326 Hz). In addition, the real powers of the GF unit and the SG have the oscillation frequency of 1.1 Hz (1.611 Hz), which is close to the calculated oscillation frequency of the shaft system. The frequencies of the gridsupporting units also oscillate at 1.1 Hz. While our results in these particular case studies do not show resonance or instability due to the proposed power sharing strategy, some high frequency oscillations, such as those shown in Figure 3-22(a), have a large magnitude (50 MW peak to peak at 30 Hz) which is likely to be prone to exciting rotor modes. More studies are needed to achieve conclusive evidence about such stability concerns. 3-23 0 Figure 3-22 Real power of the system components and zoom-ins. (a) the real power of three inverters and the SG (b) the oscillation frequency of the real power of GS unit (c) the oscillation frequency of the real power of the GF unit (d) the oscillation frequency of the real power SG. 3-24 0 Performance Comparison Between Three-Phase and PositiveSequence Inverter Models In this subsection the performance of the EMT-type inverter models is compared with the positive-sequence models described in chapter 2. Figure 3-23 shows the results of both models. In this study, the disturbance applied is a load change. The ratios for the droop gains in the positive sequence model are the same as the ratios in the EMT models. In steady state after the load change, both methods effectively perform power sharing. In positive sequence the frequency recovers to 60 Hz and power sharing is performed in only 0.2 s after the load change, while for the EMT model it takes 1.2 s. This is because the control in the EMT model relies on small variations of the angles. A 0.05 rad change in angle, which occurs very quickly, completely changes the power sharing (at the same time it can quickly make the system unstable). 300 300 200 100 100 0 0 2 4 6 8 Voltages (pu) 1.04 1.02 10 Time (s) 12 7 6.5 6 5.5 5 14 16 18 20 1.02 1 0.98 0.98 60.2 4.95 0 2 4 6 8 5 10 Time (s) 5.05 12 5.1 14 5.15 16 18 20 60.2 60 59.9 59.8 59.8 0 2 4 6 8 5 200 100 0 0 2 4 6 8 5.5 10 Time (s) 12 6 6.5 14 (a) 7 16 1.02 18 20 5 10 Time (s) 5.5 6 12 14 6.5 7 16 18 20 18 20 18 20 1.04 1.02 1 1 0.98 60.2 5 4.95 0.98 60.1 60 300 100 1.04 1.04 1 200 0 Voltages (pu) 0 Frequency (Hz) Real Power (MW) 200 Frequency (Hz) Real Power (MW) 300 0 2 4 6 8 10 Time (s) 5.15 5.1 5.05 12 14 16 60.1 60.2 60 60 59.9 59.8 59.8 0 2 4 6 8 5 5.5 10 Time (s) 12 6 6.5 14 7 16 (b) Figure 3-23 From top to bottom: Real powers of generation units, bus voltages of generation units, and system frequency measured at the buses of generation units in (a) PSPS method and (b) the proposed method. 3-25 0 0 Section 4: Balancing and Market Operations of an All Inverter System The previous chapters focused on the dynamics and stability performance of an all IBR system. This chapter focuses on steady state operations and market operations. The feasibility of a 100% renewable power system has been discussed for many regions. For example, the recent bill SB100 in California committed to 100 percent clean energy for the state by 2045 [4-5] (note clean energy includes non-inverter based resources, but it is expected that variable energy resources (VER) such as wind and solar power will make up a large portion of the requirement). The Hawaii Public Utilities Commission mandated the state to achieve 100 percent renewables (again, this could include non-inverter based resources) by 2040 [4-6]. However, there still is a long way to go for the current utilities to be converted to 100% VER power systems, where wind and solar may make up large portions of the annual demand. If these systems were to be operated at a very high renewable energy penetration level, it is very likely that they reach 100% VER in some hours of the year 1. This chapter investigates two subjects. First, we investigate how the system would operate with periods of very high VER penetrations, such that penetration levels, or at least available energy from wind and solar, may reach 100% during some periods of the year. In this first section, we use a production cost simulation tool to demonstrate how current unit commitment and economic dispatch models might behave at such a high renewable penetration level, and study the associated issues related to scheduling, renewable curtailment, reserve requirements, and pricing. Second, we describe how the existing power system operation paradigms might change if the system had 100% renewables all the time, with wind and solar providing much or all of the demand (with some potential ability to store energy or shift demand required). This section is focused on a conceptual discussion rather than any new modeling, but should provide numerous ideas for future research. 1 Note that the work in this chapter focuses more on the variability and uncertainty related issues, and not the fact that these resources are inverter based, and so the focus here is on variable energy resources (VER) rather than inverter based resources (IBR). While these may be the same type of resource (e.g. wind and solar PV) as the IBR investigated in the remainder of the report, the more important aspect is their variability. 4-1 0 Note both of these subjects focus only on short term operations (days and minutes) and steady-state balancing and dispatch, and does not examine issues such as resource adequacy, network capacity requirements, revenue sufficiency for generation, system protection or system stability, the last of which is investigated in other parts of this report. These issues also need to be studied, and will be described in future work. The purpose here is less to focus on specific results from the analysis, but rather the methodology and types of results that are being examined, to determine how such a system may operate and the important factors that will need to be considered. System Operation with 100% VER During Some Periods of a Week In this section, the utilization of state-of-the-art production cost simulation tools for a system that reaches 100% generation from VER for some periods during a day, is investigated. Results from production cost modeling/operational simulation are investigated, where there is sufficient energy available from VERs to meet 100% of demand in some hours, and typical unit commitment and economic dispatch procedures as used today are carried out. Here, that includes an hourly day ahead security-constrained unit commitment (SCUC) using forecasted information representative of current forecasting performance, and then a five-minute real time security-constrained economic dispatch (SCED) with realized values. This mimics a simplified version of how U.S. independent system operators and regional transmission organizations operate today and allows us to explore challenges with both variability (system conditions are changing through time) and uncertainty (system conditions are different from what was expected in advance). The aim is to understand system operations if the current status quo procedure were continued to be used to operate such a system. Test System and Data Used Four test cases have been developed for analysis, with the average renewable energy generation for the week ranging from 13.3% to 53.5% of total demand. Details on the test cases can be found in Appendix A – they are based on the IEEE RTS-96 system [4-7], with modifications provided by NREL [4-8]. The installed capacity is provided in Table 4-1. In case 2, the renewable energy penetration is high, but the nuclear units are set to must-run in the simulation, resulting in likely curtailment. In case 3, the nuclear units are allowed to be cycled on and off with associated commitment constraints (long start-up times, minimum run times, and minimum down times) so that they can be utilized only when their energy is needed. In case 4, the nuclear resources are removed completely. The hydro energy in case1, case2 and case3 was modeled as timeseries input. 4-2 0 Table 4-1 Generation Capacity (MW) in Each Case (Peak load: 8192 MW) Cap. (MW) CC CT STEAM Hydro Nuclear VER Case 1 3550 1545 1362 1000 400 2133 Case 2&3 3550 1645 830 1000 400 11948 Case 4 3550 1645 0 0 0 11948 4-3 0 For each case, a day ahead (DA) SCUC run was made using a DA forecast of wind, solar and load, to determine unit commitment of all resource requiring more than an hour of start-up notification. Then, real time (RT) SCED was ran based on the 5-minute realized wind, solar and load to determine the actual dispatch of the resources. A comparison of available VER, based on the day ahead (DA) forecast, assumed to be made at noon on the previous day, and system demand for case 1 and case 2 is shown in Figure 4-1 (note that cases 3 and 4 have identical VER inputs as case 2 and demand is the same for all). Similarly, Figure 4-2 shows the RT available resources at a 5-minute resolution for VG and system demand. Compared with the DA forecast, there are more intervals in RT on Day 1, Day 6 and Day 7 in which the VER is greater than the system demand; this is due to a forecast error underestimating RT; in other periods, this error may overestimate VER in DA so this would also need to be considered but is not shown in the data used here. The mean absolute error (MAE) for DA VER forecast is 212 MW (approximately 10%) and 662 (approximately 5%) MW in case 1 and case 2, respectively; the lower error in the second case is due to the diversity in the renewables reducing the relative error as errors at individual plants are not perfectly correlated. Note that in this first set of runs, no reserves are carried to manage contingencies or to manage forecast error from DA to RT; this is examined later. These results will provide simple insights on commitment and dispatch of such large amounts of VER and the potential implications, which we will later build on to show how the imbalances and economic challenges (including curtailment) can be mitigated through additional procedures, like additional reserve. Figure 4-1 Comparison of VG and load in case 1 and case 2 as the input data in DA 4-4 0 Figure 4-2 Comparison of VG and load in case 1 and case 2 as the input data in RT Results for Case with No Reserves Some of the more interesting results to examine for this type of study relate to how different resources would operate, whether there are violations of supplydemand balance, and how different assumptions about resource flexibility impact results. Figure 4-3 and Figure 4-4 show the real-time penetration levels in the four cases for VER and thermal units respectively; this is the outcome of the model and includes any curtailment or load shortfalls required to balance supply and demand while respecting generation constraints such as minimum up and down time, startup time and minimum stable output level. The transmission network is also included, using a DC power flow. The tool used here is the Power Systems Optimizer tool by Polaris. 2 In case 1, the renewable energy penetration level is low, and the percentage of thermal generation is relatively less variable throughout the week. In case 2, there is significant curtailment when VER levels are high, due to the must-run nature of nuclear and the commitment constraints of the fossil resources. By allowing nuclear to be dispatchable in case 3, the system has higher renewable energy generation during afternoon hours where solar generation is high; however, the fact that fossil and nuclear units cannot be turned off due to long start up times and a need to be kept online for later needs leads to VER levels that cannot reach 100%. In addition, thermal generators were committed in DA, and the commitment decision was fixed in RT. As a result, thermal generation was still online when the VER is greater than demand during some hours of the day; this forecast error caused a reduction in VER output. If the system operators could manually decommit the thermal units in real-time in those hours, the percentage 2 Details for this tool can be found at http://psopt.com/pso/. 4-5 0 of VG can be 100%. This may show a need for future systems to potentially make decisions closer to real time as forecasts are often more accurate. Hydro was counted as VER in the results; it has fixed output profile in the data used here, such as would be the case with run-of-river hydro. Case 4 shows that allowing for the removal of the nuclear provides additional flexibility to the system and reduces the curtailment levels of wind and solar, allowing for 100% penetration (note again we have no reserve requirements in these simulations); the removal of hydro would also impact the results by changing the shape of the VER. RT VER Percentage 120 case 1 case 2 110 case 3 case 4 100 90 80 Percentage (%) 70 60 50 40 30 20 10 200 400 600 800 1000 1200 1400 1600 5min intervals in one week Figure 4-3 Real-time VER penetration percentages for different scenarios 4-6 0 1800 2000 RT Thermal Percentage 100 case 1 case 2 90 case 3 case 4 80 70 Percentage (%) 60 50 40 30 20 10 200 400 600 800 1000 1200 1400 1600 1800 2000 5min intervals in one week Figure 4-4 Real-time thermal energy percentages for different scenarios The next results examine violations in supply-demand balance. A load violation occurs when the power balance equation in the RT cannot be met. In practice, this may result in area control error (ACE), frequency error, or if large enough, involuntary load shedding. However, these imbalances would more than likely result in reserve shortage had we modeled reserve in this first set of simulations. In the high renewable energy cases, load violation occurred in the form of load shortages (insufficient capacity to meet demand). The system does not have sufficient flexibility to ramp up the existing generation fleet to meet large changes in net load. The reasons why the load violation could not be relieved by release of wind and solar curtailments were because: 1) the network constraints prohibited the transmission of curtailed energy to the destination, and 2) the DA commitment decision was passed to and fixed in RT where resources couldn’t be turned on in time to manage a forecast error. The balance violations for each case in DA and RT are shown in Table 4-2. Table 4-2 Load violation and renewable energy curtailment analysis Case 1 Case 2 Case 3 Case 4 RT Violations (GWh) 0.3 14.1 25.6 87.8 RT load shortfall (% of demand) 0.04% 2.4% 4.3% 14.7% RT Renewable Curtailment (% of available generation) 2.5% 40.0% 37.2% 26.0% 4-7 0 Balancing violations were observed for all cases in RT. The RT violations were calculated by the summation of RT violations in each 5-min interval divided by 12 (one hour has 12 five-minute intervals). The total system demand in this week was 596 GWh. The ratios of RT violation quantity to the total system demand are shown in the second row of Table 4-2. At case 4, the RT load violations can be close to 15% of the total system demand, which would be unacceptably high. It is observed in the table that the quantity of balancing violation in the real-time is higher when the renewable energy penetration is allowed to get very high in the model; this shows that one may still need generators committed in DA to manage variability and uncertainty in RT and shows the importance of properly set operating reserve requirements for VER and load forecast error. Table 4-2 also shows the percentage of RT renewable energy curtailment for each case. In the low renewable energy case (case 1), the percentage of curtailment is low. Case 2, case 3 and case 4 have the same available VER, but case 2 has more VER curtailment than case 3 because nuclear energy is must run, and case 4 has less VER curtailment than both as the nuclear and hydro were not part of the solution to cause minimum generation constraints. While the curtailment rate decreases from case 2 to case 4, the reliability in terms of load balance violations also decreases. This is due to there being less dispatchable resources available in RT to accommodate the variability and uncertainty that occurs. The results shown here may show that in future high VER systems, there is a trade-off between reliability and the ability to integrate large amounts of VER without curtailment – this will depend on the specific flexibility of the fleet, and also will require operating reserves and other factors that may be able to mitigate the reliability violations. Other mitigation factors such as utilization of energy storage, which can potentially support reliability and reduce curtailment while not necessarily adding carbon to the mix, will also impact outcomes. Finally, the results for the simulations show here are for a system with centralized DA and RT clearing mechanisms such as in North American ISO/RTO regions or in most vertically integrated utilities. In other regions, such as Europe, the decision to commit and decommit or to curtail may be taken by market participants, where they have to provide sufficient energy to balance some supply requirements they have. As such, alternative methods to commit and dispatch resources may need to be evaluated in future work. The results in these examples are highly simplified and were presented primarily to provide a high-level insight into the potential for load imbalances and curtailment potential on these very high penetration VER systems. They primarily show that mitigation strategies, many of which are already being implemented in regions across the world, are required to avoid load balance and reliability violations and VER curtailment. We next discuss some of the most beneficial mitigation strategies (many others have been presented in other EPRI research) and some unique phenomena that may occur during steady-state and market operations of these very high VER penetration systems. 4-8 0 Selection of Curtailment Resources Renewable energy resources are usually curtailed for economic reasons due to local congestion or system balancing requirements to manage the oversupply issues. During hours when the demand is low (e.g., midnight) or renewable energy output is high (e.g., summer afternoon), the output of VER is reduced far below the available energy. Curtailing renewables results in a lost opportunity for clean resources to generate carbon-free power. When more renewables are integrated into the system, oversupply may happen more frequently, and curtailment of VER may become more common practice. While VER curtailment occurs in measurable ways on existing systems, it is most often due to transmission congestion where one or a few VER resources are able to manage the congestion specifically. In the above examples, VER curtailment is occurring much more frequently due to oversupply in larger regions where multiple VER plants must be curtailed to resolve the load balance. With so many VER that can be used to resolve this imbalance, and all operating at generally the same cost ($0/MWh), how to choose which resources to curtail and when becomes an important factor that has not been considered in great detail before. During times of oversupply, the market clearing engines competitively select the highest cost power resources to be curtailed. VER often offer energy costs into the market that reflect their willingness to continue producing. These values can be low positive numbers to reflect variable O&M costs, zero, or negative to reflect production-based subsidies that the resources receive when producing. These same decisions and costs are reflected in non-market regions. When a resource submits zero or negative valued cost offers, the optimization engine will try to use the resource’s capability as much as possible. Regardless of the offer of VER or other resources, all the resources are compensated with the uniform market clearing price, which in existing markets is usually positive for most parts of the day. However, when the system has 100% renewables for large periods of time, the market clearing price could often be zero or negative. 3 When this occurs for increasing portions of the year, revenue of all resources for energy provision may be significantly decreased, and it is possible that new offering strategies by resource owners as well as new market designs and products by the ISO are employed. As VER curtailments occur more as a solution to large-region over supply balance resolution, the selection of units to be curtailed is an interesting issue to be studied. When VER curtailments occur for local congestion, it is usually obvious which VERs can be curtailed based on their contribution to the congested lines. But for oversupply, they may all be able to resolve the issue through curtailment in the same manner and for the same cost. We selected oneday data from Case 4 for demonstration. Figure 4-5 shows the load, available VER, and actual production of VER in a day. VER oversupply occurred from Note that, as tax credits and other subsidies expire, the negative pricing issue may be reduced or disappear. 3 4-9 0 8am-3pm in the day, and as a result the oversupplied VER was curtailed to meet the demand in this period. Figure 4-5 Comparing the load and VER production in real-time for one day In the above test case, we assume that all the renewable resources have zero energy cost. 4 Figure 4-6 and Figure 4-7 show the curtailment of individual wind and solar units respectively. Since all the units have the same curtailment costs, the optimization engine will not select resources based on costs. Instead, there may be multiple equivalent solutions to the problem, and the current UC/ED engine must only find one. It is necessary to find out proper rules to prioritize the VER curtailments when its penetration level is high and costs to resolve the imbalance are the same. These may need to be determined outside the market to avoid potentially unfair treatment of VER plants in the market. In reality, there are some specific rules that guide the VER curtailments. For instance, wind plants in Germany rolling off the first set of subsidy contracts are going merchant with positive marginal costs (to cover the cost of extended life warranties and servicing from OEMs). These will naturally curtail early in such an event. In addition, there are systems with curtailment rules already in place based connection offer priority schemes, e.g. non-firm or flexible connections. Other utilities may curtail in order of their interconnection date. A simple market solution would be that all VER that can be curtailed to solve the solution In ISO markets, the VERs may not all have the same offers, and the different offers being provided by different VER can determine who gets curtailed. However, as the true cost of VERs is essentially the same, and may often be the case that many VER have the same offer costs, this condition is still worth further study. 4 4-10 0 be curtailed pro-rata. This may not always occur automatically through existing market clearing algorithms. Figure 4-6 Curtailment for wind resources in one day Figure 4-7 Curtailment for PV resources in one day Electricity Price Behavior The wholesale electricity markets operated by ISOs use locational marginal prices (LMP) to reflect the value of electric energy at different locations, accounting for the patterns of load, generation, and the transmission line constraints. Resources are paid LMP at their location multiplied by their energy output for all hours 4-11 0 that they generate. It is possible that VER are the marginal unit, and as a result set the system LMP. On systems with very high penetrations of VER, the LMP may become zero or negative for increasing portions of the year. We explore these conditions with the cases described earlier. Table 4-3 shows the hourly load, generation dispatch, LMP and total costs for case 4 in one day. The demand was 100% supplied by renewables from hour 08:00 to 13:00, and the LMPs and total costs are zero in this period. However, it was observed that at hour 14:00, the LMP is zero, but the total cost is non-zero. At this hour, the VER penetration is still high (97%), but some thermal generation units were still required. The reason is that the VER output is expected to decline after hour 14. Due to ramp up time limits of thermal units, the system cannot call up them immediately when they are needed. As a result, the SCUC will select the thermal units to pre-ramp up to meet the upcoming VER output declining. In traditional marginal cost pricing (sometimes called traditional LMP), the price is set by the incremental cost to serve the next increment of load, which in any case where there is VER curtailment, would be the VER unit. This is true even when other units are online but are at minimum generation. In hour 14, the marginal unit is still the VER unit, so the LMP is still $0/MWh. However, when units are producing energy at costs above the LMP as directed by the ISO (and not selfscheduled), they must be made whole. This results in ‘uplifts’ to the system, and “make whole payments” are enabled to compensate the monetary loss of the thermal generator that was online. 5 Many of such intervals with zero LMP and non-zero costs were observed in the simulations. These results show that overall revenues could be significantly decreased in the energy market both for VER and other resources. This may warrant new offering strategies by asset owners or new market designs by ISOs. In fact, many ISOs have recently implemented new pricing designs which may allow certain sets of resources at minimum generation to set price and for additional costs like start-up and no-load costs to be factored in to the price [4-9]. It is unclear how these designs may be impact future systems with very high VER penetrations, and whether other revenues through ancillary service markets, capacity markets, or out-of-market contracts may provide the needed revenue to remain in the market and recover fixed and variable costs. Further research into this is definitely required. 5 Note that in most cases, make whole payments are netted across a day or commitment period, so it may only receive the make whole payment if its profits were negative throughout the entire day or commitment period. 4-12 0 Table 4-3 Existence of intervals with zero system price (marginal cost) but non-zero costs Time Load (MW) Thermal Gen (MW) VER Gen (MW) LMP ($/MW) Total Cost ($) 2024.04.08 00:00 3100 2838 263 31 79069 2024.04.08 01:00 3073 2862 211 31 79861 2024.04.08 02:00 3077 2759 319 31 76580 2024.04.08 03:00 3150 2664 486 30 73700 2024.04.08 04:00 3331 2785 546 31 77414 2024.04.08 05:00 3554 2124 1430 28 59210 2024.04.08 06:00 3732 833 2899 27 25829 2024.04.08 07:00 3879 51 3827 26 1963 2024.04.08 08:00 4001 0 4001 0 0 2024.04.08 09:00 4069 0 4069 0 0 2024.04.08 10:00 4070 0 4070 0 0 2024.04.08 11:00 4043 0 4043 0 0 2024.04.08 12:00 4011 0 4011 0 0 2024.04.08 13:00 3963 0 3963 0 0 2024.04.08 14:00 3927 112 3815 0 31469 2024.04.08 15:00 3896 1008 2888 27 198166 2024.04.08 16:00 3901 2051 1850 30 55684 2024.04.08 17:00 4131 2620 1511 36 91642 2024.04.08 18:00 4417 2758 1659 107 88381 2024.04.08 19:00 4355 2532 1823 36 71710 2024.04.08 20:00 4014 2033 1981 28 55616 2024.04.08 21:00 3603 1376 2227 23 37914 2024.04.08 22:00 3293 903 2390 13 25625 2024.04.08 23:00 3159 708 2451 23 18892 Figure 4-8 compares the average DA LMP across the network for one week for case 1 (low VER) and case 4 (high VER). It is observed that even in the low VER case, the LMP could be zero, as shown in hour 84 and 85 for case 1. In these hours, there existed VER curtailment due to the commitment status of thermal units (for example, there are minimum on/off time requirements for thermal units). In the high VER case, the LMP is zero during much more hours. In addition, the LMP switches from zero to high values more frequently, because quick start units with higher marginal costs will be called on more frequently or penalty prices from infeasibilities (which will most likely be reserve shortages) that occur more often. As a result, the market may have significantly higher price volatility at higher VER penetrations. 4-13 0 DA LMP 100 DA LMP for case 1 90 DA LMP for case 4 80 70 Price ($/MWh) 60 50 40 30 20 10 0 20 40 80 60 100 120 140 160 Hour in one week Figure 4-8 DA LMP in one-week period in the system Figure 4-9 shows the real-time LMP for case 4. The RT LMP switches between zero and a very high penalty price (≥$1000/MWh 6) very frequently. Compared with the DA price, the RT LMP has more extreme values. The reason is that in real-time horizon, the system condition is more variable and has less options to correct errors than are available in the DA (i.e., most units cannot be called on or off in RT). As a result, there may exist lots of violations on these systems. These load violations would typically result in ACE, (or frequency deviations in practice), but if large enough could lead to involuntary load shedding, but most often would result in being short on reserve. Having such high prices due to these administratively set penalty prices has as much implications for revenue adequacy as do the large increase in zero or negative prices. In some cases, it may balance out the average price to similar values as to what they are in existing lower VER penetration systems. More research into appropriate values and how often these penalty conditions occur on higher VER penetration systems is required. These penalty prices are typically based on reserve shortage price values. They typically range from a few hundred dollars per MWh to as much as $2,000/MWh. 6 4-14 0 RT LMP 2500 2000 Price ($/MWh) 1500 1000 500 0 200 400 600 800 1000 1200 1400 1600 1800 2000 5min Intervals in one week (case4) Figure 4-9 RT LMP in one-week period for case 4 The revenue of the thermal units can be directly impacted by these potentially large changes in LMPs. The significant increase in zero-or negative LMPs can cause thermal units to lose money in the market because its revenue is zero but the cost might not be zero. On the contrary, when the LMP is set to a high penalty price, a thermal unit’s revenue in the market can be much higher than its operation cost. Table 4-4 shows the cost, revenue and net benefit in DA and RT for case 4 in one week. The revenue was calculated by the summation of the product of LMP and thermal unit dispatch in each interval, and was done separately for both DA and RT which is different from the two-settlement revenue used in actual ISOs. The net benefit was the difference between the revenue and the cost. In DA, the revenue was much smaller than the cost, thus the net benefit was negative. The reason for small revenues in DA was because the LMP in DA was relatively small. The revenue in RT was calculated by the two-settlement pricing mechanism, i.e. the revenue is the product of RT LMP and the quantity difference between DA and RT dispatch. When the RT (hourly integrated) dispatch is less than the DA schedule, the revenue of a generator is negative in RT. The RT revenue in Table 4-4 was a negative number whose absolute value is large. This was caused by the large LMPs with penalty values ($1000/MWh) in RT. Large make whole payments were needed to compensate the generators in this case. The assumptions of not including reserve to allow for more resources to accommodate the forecast uncertainty and the lack of virtual trading would significantly alter these results and should be looked at further. Nonetheless, compared to the current situation, RT markets may become even more volatile and an even more important source of revenue for certain technologies. Additional research on price setting, settlement rules, additional market products, and offering strategies and allowance should be conducted to ensure that resources needed for reliability are able to recover costs without 4-15 0 excessive costs incurred by consumers on these very high VER penetration systems. Further analysis on the revenues such as the impact of price caps and other factors is also warranted. Table 4-4 Cost and Revenue for case 4 (two-settlement pricing mechanism was applied while calculating the revenue) Cost ($) Revenue ($) Net benefit ($) DA 9.5M 1.6M -7.9M RT 8.6M -135M* -143.6M The absolute value of the revenue is large because the RT LMP is the penalty value (>1000/MWh) in many intervals. * Effects of Enabling Technologies Demand response and energy storage resources are playing an increasingly important role in power systems to balance the power supply and demand and create a more flexible and reliable grid. Demand response providers with the ability to aggregate customers capable of reducing their electric demand can participate in the wholesale markets and provide the flexibility to adjust their load in response to market schedules and dispatches. Energy storage resources can either provide energy (in discharging mode) or consume energy (in charging mode) to the power grids. Both resources are also typically very responsive, able to adjust power output in short periods of time (i.e., they have very high ramp rates). Thus, they have more flexibility in the electricity market and power system operation. In this section, we mainly focused on how energy storage resources can impact system balancing, the curtailment of VER and the LMP when the system has high levels of VER. To this end, we added 1883 MW (about 11% of the total generation capacity) energy storage resources with maximum energy of 18835 MWh (10 hours of energy) to case 4. A comparison of dispatch results of the system with and without energy storage resources is shown in Table 4-5. By adding 11% storage to the system, the load violation ratio reduced from 14.7% to 0.9%, and the VER curtailment quantity reduced from 120 GWh (26%) to 73 GWh (16%). The reason for the reduced curtailment is that when there is more supply than demand (which usually causes curtailments), the excess electricity generation can be used to charge storage. Figure 4-10 compares the DA and RT LMPs for case 4 with and without energy storage resources being added on it. The average DA LMP reduced from $24.2/MWh to $13.2/MWh, and the average RT LMP reduced from $2529.3/MWh to $550.8/MWh. In addition, the price spikes also have significant reductions. For instance, the RT intervals with price spikes (higher than $1000/MWh) significantly reduced from 979 to 210 5-minute intervals. The RT production costs for the system with and without energy storage resources are compared in Table 4-5. The total generation cost for the original case was $8.6M in the studied week. When adding 11% energy storage devices, 4-16 0 the weekly generation cost was reduced to $4.4M (decrease by 49%); note this included 10 hours of energy, which is a longer duration than typical storage that is currently being built; future work may look at different power versus energy ratios. A comparison of the hourly aggregated generation cost between these two cases is shown in Figure 4-12. In some hours, the cost with storage can be higher, but for most of the hours the cost is significantly reduced. This reduction in costs from a relatively small amount of ESRs is significant. It is primarily due to the large charging/discharging hours we assumed for the energy storage devices (they can charge/discharge at the maximum capacity for 10 hours), as well as the reduced VER curtailment and thermal unit de-commitments. Table 4-5 Comparison of solutions for the system with and without storage Without Storage Load violation in RT 87.8 GWh (14.7% of load) 5.1 GWh (0.9% of load) Curtailment in RT 120 GWh (26% of total available VER) 73 GWh (16% of total available VER) DA mean LMP ($/MWh) 24.2 13.2 RT mean LMP ($/MWh) 599.3 167.8 RT price spike (>$1000/MWh) intervals 348 248 RT Generation costs ($) 8.6M 4.4M 4-17 0 With Storage DA LMP 600 DA LMP without storage 500 DA LMP with storage Price ($/MWh) 400 300 200 100 0 20 40 60 80 100 120 140 160 Hour in one week RT LMP 2500 RT LMP without storage RT LMP with storage 2000 Price ($/MWh) 1500 1000 500 0 200 400 600 800 1000 1200 1400 1600 5min intervals in one week Figure 4-10 Comparing LMPs with and without energy storage resources Figure 4-11 A comparison of hourly aggregated operation costs in RT for one week 4-18 0 1800 2000 Determination and Impact of Reserve Requirements Operating reserves refer to the generating capacity available above and below that scheduled to meet demand in case the scheduled or forecasted supply or demand of power is disrupted. A shortage of deployable active power reserve may cause significant ACE, frequency deviation, reliability compliance violations, load shedding, or even blackouts. In steady-state, VERs increase the variability and uncertainty of the system and hence impact the amount of operating reserves that need to be held to maintain system reliability. It is a challenge for system operators to determine how much each reserve product needs to be increased with high VER penetration levels [4-10][4-11]. Previous results in this study, as mentioned, do not consider reserves, for a first order evaluation into economic supply-demand balancing issues. However, in order to provide more realistic results, we now also examine how reserve requirements impact and mitigate issues for system operations at very high VER penetrations. In this section, we conducted the study by adding four types of operating reserves to case 4: regulation up reserve, regulation down reserve, spinning reserve, and supplemental reserve. EPRI has developed a reserve determination tool called Dynador [4-3] to calculate the system reserve requirement based on input system demand and VER data. Similar concepts were used here to determine reserve requirements as are used in that tool, though less detailed consideration was given compared to the methods used within Dynador. Whereas Dynador forecasts the reserve requirement for the following day or hour, based on projected system conditions, here we used a relatively simple method to provide a brief examination of how reserves help mitigate the issues described in the previous sections. Dynador and similar methods have been shown to improve upon the existing methods, but that was not the focus of this study. In this study, the requirement for each type of reserve is calculated as follows: Regulation up reserve We adopted the method used in the Southwest Power Pool to calculate the regulation up reserve [4-2]. The regulation reserve is determined by four components: load magnitude, load variability, renewable energy resource magnitude and renewable energy resource magnitude. The total regulation reserve requirement is calculated by the summation of each component times a coefficient, as shown in Equation 4-1: up RegReq = a up LF (t ) + bup [ LF (t + 1) − LF (t )] + cup RF (t ) + d up [ RF (t + 1) − RF (t )] Eq. 4-1 where LF(t) is the load forecasting at time t, RF(t) is the renewable energy resource forecasting at time t, and aup, bup, cup, and dup are coefficients to determine the weight of each component. The typical values used in SPP of aup, bup, cup, and dup is 1%, 1%, 5% and 10%, respectively, as shown in [4-2]. 4-19 0 Regulation down reserve The regulation down reserve requirement can be calculated using Equation 4-2: down RegReq = a down LF (t ) − b down [ LF (t + 1) − LF (t )] + c down RF (t ) − d down [ RF (t + 1) − RF (t )] Eq. 4-2 where aup, bup, cup, and dup are coefficients to weight each component. Their values were also set to 1%, 1%, 5% and 10%, respectively, in the simulations. Spinning reserve The spinning reserve is used to manage instantaneous contingency events on the system, and typically in the US is required to respond within 10 minutes. We set the spinning reserve requirement equal to the largest single contingency (in MW) in the system, similar to many regions. Supplemental reserve Supplemental reserves must be able to become synchronized with the grid and ramp to a specified output level within 30 minutes. Its requirement can be calculated based on historical data. For example, in ERCOT it is calculated by using the 70th to 95th percentile (depending on the risk of net load ramping) of hourly net load uncertainty (load minus the estimated uncurtailed total output from Intermittent Renewable Resource) from the same month of the previous three years. In ISO New England, it is set as 50% of the second-largest system contingency. Due to data unavailability, we simply use the ISO New England method for the supplemental reserve requirement in the simulation. Using the reserve calculation methods mentioned above, we can obtain the requirement for each type of reserve in the test system. We assume here that all of the reserves are provided by thermal generators, and VER cannot provide operating reserves. By adding those reserve requirements, we rerun the production cost model for case 4. A comparison of the renewable energy percentages in real-time between the original case (i.e. case 4) and the new case with calculated reserves is shown in Figure 4-12. It is observed that the maximum renewable energy penetration is 57% in the new case, without any 100% VER generation intervals, which is less than the previous cases. This result is as expected, because thermal generators have to be committed to provide operating reserves even in the intervals where VER alone are sufficient to meet the demand. Obviously, this may show the need for more flexible thermal plants that have lower minimum generation levels, or energy storage or demand response resources that could provide such reserves, and thus allow for greater penetration of renewables. Also note that, as systems get larger, the impact of largest contingencies typically gets smaller on a percentage basis and therefore reserves may not have quite as large an impact. It may also show the benefits of having VER provide various types of operating reserve. 4-20 0 Figure 4-12 A comparison of the renewable energy percentage with and without operating reserves for case 4 A summary of the studied case with four types of reserves is shown in Table 4-6. Compared with the results in Table 4-4 (the “without storage” case), the load violations in RT were reduced significantly by carrying reserves (note there are significant reserve shortfalls instead). The average LMP in DA and RT and the RT price spikes were also reduced (albeit with additional reserve shortage prices). This indicates that the reserves in the system can help reduce price volatility and improve the generation and demand balance. However, there is a cost for doing so. The total production cost in RT increased from $8.6M to $12.6M. Additionally, the curtailment ratio of VER was increased. This was because more thermal generation (and less VER) was dispatched when reserves were considered. While the VER input did not change, the VER curtailment increased. The average RT prices and the total reserve shortage for the four types of reserves are also shown in Table 4-6. The reserve prices were relatively high; this was because of reserve shortages in many intervals where the reserve prices were the penalty price, e.g. $1000/MWh. When not counting the reserve shortage intervals, the average reserve price for regulation up, regulation down, spinning and non-spinning is $2.4/MWh, $12/MWh, $1.8/MWh and $0.2/MWh, respectively. The large amount of reserve violations and the high reserve prices indicate that the conventional reserve determining method might not be suitable in the VER case. For example, the regulation requirement formulation from (1)-(2) depends on the demand variability. However, the variability of net demand should be more significant in this case. As a result, a new reserve determination tool such as the Dynador is required for high VER cases. 4-21 0 Table 4-6 Summary of simulation results with four types of reserves Case 4 – no reserves Items Case 4- with reserves Load violation in RT 87.8 GWh (14.7% of load) 3GWh (0.5% of load) Curtailment in RT 120 GWh (26% of total available VER) 251 GWh (54% of total available VER) DA mean LMP ($/MWh) 24 15 RT mean LMP ($/MWh) 599 159 RT price spike (>$1000/MWh) intervals 348 199 Total RT Production costs ($) 8.6M 12.6 M RT mean regulation up reserve price ($/MWh) - 408 RT mean regulation down reserve price ($/MWh) - 322 RT mean spinning reserve price ($/MWh) - 118 RT mean supplemental reserve price ($/MWh) - 82 Total regulation up reserve shortage in RT - 2840 MWh Total regulation down reserve shortage in RT - 6120 MWh Total spinning reserve shortage in RT - 892 MWh Total supplemental reserve shortage in RT - 747 MWh In the above simulation, we assumed that VER cannot provide operating reserves. However, VER can be dispatched at any value up to the forecasted energy output. Thus, they can provide all types of operating reserves defined above as long as system operators have the confidence that they can deliver in real-time. The case was modified to allow VER to provide reserves, and the production cost simulation reran. A comparison of renewable energy percentages between the original case and the modified case is shown in Figure 4-13. The results between the two cases are very close. The system can still achieve 100% VER in many intervals when reserves requirements were enforced and VERs were allowed to provide those reserves. 4-22 0 A summary of the simulation results by allowing VER to provide reserves is shown in Table 4-7. The values in this case are close to the original case 4 results. There still exists lots of load and reserve shortage in the system, but there is no shortage on regulation down reserve. The total amount of reserves shortage is higher when allowing VER to provide reserves. The reason was because in the 100% VER intervals all the VERs have been dispatched at the maximum capability so there is no head room to ramp up. In addition, no thermal generators were dispatched at 100% VER intervals. As a result, the capacity for providing regulation up, spinning (up) and supplemental (up) reserves in the system is zero at those intervals. On the contrary, the VERs can be dispatched down, thus there exists sufficient regulation down reserve capacity. This indicates that although allowing VER to provide reserve can provide some benefits, there are consequences are well, in particular a shortfall in reliability due to the uncertainty related to wind and solar power. This also indicates that the current UC/ED model may needed to be changed to allow VERs to provide reserves properly when the system demand is 100% supplied by VERs. Further investigation is needed on how to correctly model VER providing reserves in future work, as it is not clear that the model is performing as would be expected here. Figure 4-13 Comparison of the original case with the new case that allows renewables to provide reserves 4-23 0 Table 4-7 Summary of simulation results for case 4 with and without VER providing reserves VER providing reserves Items VER does not provide reserves Load violation in RT 7.2GWh (1.2% of load) 3GWh (0.5% of load) Curtailment in RT 122 GWh (26.4% of total available VER) 251 GWh (54% of total available VER) DA mean LMP ($/MWh) 23.8 15 RT mean LMP ($/MWh) 581 159 RT price spike (>$1000/MWh) intervals 340 199 Total RT Production costs ($) $8.9M $12.6 M RT mean regulation up reserve price ($/MW) 581 408 RT mean regulation down reserve price ($/MW) 0 322 RT mean spinning reserve price ($/MW) 841 118 RT mean supplemental reserve price ($/MW) 552 82 Total regulation up reserve shortage in RT 8301 MWh 2840 MWh Total regulation down reserve shortage in RT 0 MWh 6120 MWh Total spinning reserve shortage in RT 29482 MWh 892 MWh Total supplemental reserve shortage in RT 8724 MWh 747 MWh These results thus show how different aspects of operations will need to be considered in the future. As the case with reserves is more realistic to how the system would be operated in reality, it shows that the curtailment levels are not purely a function of supply-demand balancing but will also need to consider other issues such as forecast error and within interval variability and uncertainty, as well as aspects like frequency response. In some aspects, case 2 and 3 may be already carrying headroom that will provide similar results as the case with reserves, except that when reserves are required additional headroom is often created. Allowing storage on the system, or allowing VERs to provide reserves, can help mitigate the situation, allowing for curtailment of renewables to be used to provide reserves or to be stored for future use. Overall, the amount of curtailments, steady-state reliability and violations, economics and production costs, and prices/revenues will be dependent on many different conditions, and it 4-24 0 is important to understand the details of these conditions first in order to understand the most beneficial mitigation strategies. Conceptual Discussion of Electric Power Systems with 100% VER and Without Dispatchable Thermal Resources In this section, we provide some additional insights on the types of operating paradigms and software that may be evolving along with the potential move to very high VER penetration systems. Each are discussed qualitatively in brief. We recommend further research on these sections to understand quantitatively the impacts and what, if any, solutions may be required. Change of SCUC and SCED Models SCUC and SCED are key models in today’s electricity markets to manage the resources and balance the demand. The SCUC is used in the day-ahead market to meet the forecasted demand and ancillary service requirements subject to unit and transmission constraints. The SCED is used to achieve real-time reliable grid operation at the lowest costs. With more VER being integrated into the grid, the operation paradigm is expected to experience significant changes. VERs have no startup and shut down time, minimum generation level, minimum on and off time, or start up and shut down costs. These features are significantly different from conventional thermal generators. When a system has 100% VERs for an entire horizon, the SCUC is no longer required for system operations. Even for systems with very high penetrations or those with 100% penetrations during only one or a few hours of the horizon, there may be substantial changes to SCUC. In today’s market operations, fast start units can be called up during intra-day and just tens of minutes before to meet the load imbalance caused by uncertainty. In a 100% VER system, the logic to call up quick start resources may be different and will depend on available headroom in VERs, as the release of curtailment may also act similar to fast-start resources. In general, it is likely that UC becomes less relevant, and more about ensuring that storage, demand response and curtailed VER are used in the most efficient manner to mitigate variability and uncertainty challenges. The SCED model should also have significant changes, with RT operations becoming significantly more complex. During intervals where only the zero-cost resources need to provide energy, there is no cost for SCED to minimize. The optimization engine may randomly select resources to be curtailed, or have some pre-ordained order (location may also impact due to congestion). As a result, there may be multiple solutions to the SCED model. It is important to identify new rules for determining which units are selected for curtailments. A solution might be changing the objective from minimizing the operation costs to minimizing the curtailment in the system. On a VER, DR and storage system, the optimization algorithm also becomes much different. The objective may be to reduce DR calls and store the most 4-25 0 storage throughout the horizon, rather than minimize costs. This algorithm has many implications. What should the prices be? How difficult will it be to solve? What parameters are required from the participating resources? Many more of these types of questions can come up with this and the many other types of resource mix and operational algorithms that best utilization those mixes. Further research is definitely needed to understand how these may work. Change of Reserve Determination Method In a power system where the demand is 100% supplied by VER, solar and wind resources form the baseload. In case of low wind and solar irradiation, the system must carry sufficient extra capacity to reliably operate the grid under all possible scenarios. This requires ensuring VER capacity well beyond the reserves required from thermal plants. Overbuilding capacity is an option, but for scenarios with high wind and solar irradiation, this will lead to extensive curtailments. Besides overbuilding capacity, other measures to ensure sufficient reserves in the grid is massive storage deployment, demand side resources and integration with other energy systems such as transport and heat requirements. How and who to provide the reserve needs in a grid with 100% VER is an important issue in the future power systems. Traditionally, the operating reserves have been provided by conventional generators such as thermal and hydro units, and in some cases demand response. In the 100% renewable energy systems, those reserves need to be provided by demand response, energy storage and VER themselves. One significant difference from traditional operation paradigm is that there may be no need to have various types of reserve products in the 100% VER power systems. In conventional power systems, different types of reserves need to be defined because the thermal generators have different response time. For example, those units with AGC are qualified to provide regulation reserve, because they can respond to ISO’s setpoint signal in a few seconds. Units with longer start up (or ramp up) time may be qualified to provide spinning or supplemental reserves. However, VER have different capabilities than the conventional generators when they are inverter based. They can respond to the setpoints immediately. In addition, they have negligible start up or ramp up time. Considering these features of VER, we might consider two types of operating reserves to the system: Load following reserve: It refers to the capacity available during normal conditions for assistance in active power balance to correct future anticipated imbalance in the system. Contingency reserve: It refers to the capacity available for assistance in active power balance during infrequent events that are more severe than balancing needed during normal conditions and are used to correct instantaneous imbalances. The contingency reserve can be set to the size of the largest resource in the system. 4-26 0 The load following reserve should consider the variability and uncertainty of the load and renewable energy generations. As discussed in a previous EPRI report [4-3], there are three central needs for operating reserves: 1. Hold capacity now to meet the variability that occurs within the scheduling time interval. (Intra-interval variability need) 2. Hold capacity now to meet the variability that occurs beyond the scheduling time interval. (Inter-interval variability need) 3. Hold capacity now to meet the uncertainty that occurs within and beyond the scheduling time interval. (Uncertainty need) In a system with very high VER penetration, the net load can be negative in most hours. The forecast error may not be meaningful if the error is less than the amount that is planned to be curtailed, because all of the VER can simply avoid curtailment without impact to the system. Thus, the amount of VER curtailed must be used along with the VER forecasting data to calculate the reserve capacity need for intra-interval variability, inter-interval variability and uncertainty. The contingency reserve requirement can be defined as the capacity of the largest unit in the system. With large VER connections that can trip offline, these large “mega farms” might set the contingency reserve requirement. However, it may be likely in these cases that the VER forecast error magnitude may dominate the need for reserve compared to instantaneous loss of a unit. The requirements may need to be considered together and used as a shared product. This is similar to how there may not be much need for VER forecast error induced reserve on low VER penetration systems today. The existing fleet and residual headroom typically can take care of those impacts. Electricity Market Design Evolution The impacts of zero and negative prices and high price spikes was discussed earlier. The ways in which the market creates incentives for both short-term reliability needs and long-term resource adequacy may be a lot different on these high VER penetration systems. The existing market design which is dominated by energy market revenues, was put in place when variable costs were a large part of overall electricity costs and incentives to get fuel for less and improve heat rates were the main drive of electricity market design and deregulation. These drivers may be losing importance on a system with high VER penetrations. Instead, there may be a whole set of other incentives for these systems as shown below: Decrease capital costs including O&M costs Decrease T&D losses Decrease needs for additional infrastructure Increase capacity factor, capacity value and geographic diversity Provide as much energy as anticipated (decrease forecast error) Provide energy at not necessarily same times as others 4-27 0 Provide reliability services Provide energy during extreme conditions when needed There has been some initial discussions in industry over what market designs may work best on these very high VER penetration systems. The following are some examples of the different alternatives from a generally high-level: Use existing energy market dominated electricity markets as is. Make sure that shortage pricing reflects true value or get price responsive demand to come in and potentially set the price as often as generation. Introduce configuration-based markets – forward markets that get the right resources built in time that are configured to have the attributes that are required on this system. These may be similar to capacity markets but emphasize that capacity is not as important of an attribute. The residual energy market may still exist but is mostly for ensuring reliability and is not important in terms of investments and revenue. Reregulation occurs – some say there is less need to have competitive markets where most resources have the same costs and lower benefit to economic dispatch and marginal cost pricing. This may still allow competitive RFPs for technologies as determined by utilities and/or government organizations. There is much more research required on how these markets evolve and what might lead to the most efficient resource mix that can ensure long-term reliability and how those resources can be operated to ensure short-term reliability. It is important to start thinking about those potential designs earlier than later, as immediate changes to the market structure can create distortions and poor decisions. The technical details along with the high level structures are both important to study further with these potential evolutions. 4-28 0 Section 5: Summary and Future Work This project investigates the operation and the associated reliability implications of an all inverter-interfaced generation system given the new operational features and challenges of such a system. First, an operating paradigm of an all IBR system at constant frequency was discussed, that was conceptualized based on an attempt to fully utilize the fast control capability of inverter sources without restricting their behavior to mimic a synchronous machine response. Its viability and system reliability with respect to stability performance were evaluated based on detailed inverter models and associated inverter controls that have been developed and used in various simulation scenarios. It has been observed that such a constant frequency operational paradigm could be feasible without jeopardizing grid reliability. A phase angle based droop scheme was proposed to ensure adequate power sharing among all available resources upon a generation/load imbalance event. It was observed that the resource located electrically closer to the event would experience the larger burden, and any topology changes would change the power flows across the system, thus, practicality of such a scheme requires further investigation. Realizing that an all IBR system might be too far in the future, more realistic scenarios of inverter dominated systems with small percentages of energy provided by rotating generators were also studied. Interactions of the fast inverter controls with the slower synchronous machines controls were investigated, and preliminary results do not indicate any reliability concerns. With respect to grid forming inverters, further R&D and industry engagement and collaboration is required to define performance specifications of such inverter controls. Based on these, representative inverter models can be developed to perform planning studies on actual systems to investigate potential reliability benefits that grid forming inverters may result in, in relation to their number and locations. Also the impact of the dynamics of the inverter dc bus and the source behind it should be considered for more detailed studies. Finally, steady-state and balancing operational challenges of an all variable energy resource (VER) system were also investigated. Preliminary simulation results indicate that state-of-the-art production cost simulation tools can handle such scenarios. By simulating several cases with different VER penetration levels, it was observed that the factors affecting time intervals during a day for which 100% energy is provided by VER include the existence of must-run units, whether there are long minimum on and off time units and system reserve 5-1 0 requirements and determination methods. It was discussed that traditional unit commitment and economic dispatch models may need to be revised, since VER have zero marginal costs and very quick start up time. Unlike the synchronous generator dominated power systems, the commitment decisions become less critical. Minimizing curtailment may be a better alternative than minimizing operating cost. It was also observed that under 100% VER scenarios the system’s LMPs are more variable with frequent changes from zero to extreme penalty prices. Demand response and energy storage resources could help reduce price volatility, load violations and renewable energy curtailments. Future work under this topic may include market design and price formation evolution, further analysis of revenue implications, more detailed investigation of storage and demand response ability to support system balance, further understanding of the reliability implications and how load and reserve shortfalls manifest themselves, and handling the increased levels of uncertainty and variability with advanced models. Other related work might include resource adequacy methods for 100% or very high VER penetrations, understanding how resource planning may be impacted at such high penetrations, and methods and tools for optimizing the resource mix (including generation, transmission, distribution and demand side resources) for high renewable futures. 5-2 0 Section 6: References [1-1] G. Barbose, “U.S. Renewables Portfolio Standards - 2016 Annual Status Report,” 2016. [1-2] B. Kroposki, B. Johnson, Y. Zhang, V. Gevorgian, P. Denholm, B. M. Hodge, and B. Hannegan, “Achieving a 100% renewable grid: Operating electric power systems with extremely high levels of variable renewable energy,” IEEE Power Energy Mag., vol. 15, no. 2, pp. 61–73, Mar. 2017. [2-1] G. Denis, T. Prevost, P. Panciatici, X. Kestelyn, F. Colas and X. Guillaud, “Improving robustness against grid stiffness, with internal control of an AC voltage-controlled VSC,” in 2016 IEEE Power and Energy Society General Meeting (PESGM), 2016. [2-2] B. B. Johnson, M. Sinha, N. G. Ainsworth, F. Dörfler and S. V. Dhople, “Synthesizing Virtual Oscillators to Control Islanded Inverters,” IEEE Transactions on Power Electronics, vol. 31, pp. 6002-6015, 8 2016. [2-3] R. A. Mastromauro, “Voltage control of a grid-forming inverter for an AC microgrid: A real case study,” in 3rd Renewable Power Generation Conference (RPG 2014), 2014. [2-4] NERC Subcommittee, “Balancing and Frequency Control,” 2011. [2-5] “Real Power Balancing Control Performance,” 2012. [2-6] I. Howard F. Illian, “Frequency Control Performance Measurement and Requirements,” 2010. [2-7] D. Ramasubramanian, Z. Yu, R. Ayyanar, V. Vittal and J. Undrill, “Inverter Model for Representing Inverter Interfaced Generation in Large Scale Grid Simulations,” IEEE Transactions on Power Systems, vol. 32, pp. 765-773, 1 2017. [2-8] P. Pourbeik, J. Sanchez-Gasca, J. Senthil, J. Weber, P. Zadehkhost, Y. Kazachkov, S. Tacke, J. Wen and A. Ellis, “Generic Dynamic Models for Modeling Wind Power Plants and other Renewable Technologies in Large Scale Power System Studies,” IEEE Transactions on Energy Conversion, vol. PP, pp. 1-1, 2016. 6-1 0 [2-9] A. B. Birchfield, T. Xu, K. M. Gegner, K. S. Shetye and T. J. Overbye, “Grid Structural Characteristics as Validation Criteria for Synthetic Networks,” IEEE Transactions on Power Systems, vol. 32, pp. 32583265, 7 2017. [2-10] Texas 2000-Bus System: ACTIVSg2k. [2-11] D. Ramasubramanian, “Impact of Inverter Interfaced Generation and Load on Grid Performance,” 2017. [2-12] Guidelines for Studies on Weak Grids with Inverter Based Resources: A Path from Screening Metrics and Positive Sequence Simulations to Point on Wave Simulations. EPRI, Palo Alto, CA: 2018. 3002013639. [2-13] 2017 NERC Frequency Response Annual Analysis: https://www.nerc.com/comm/OC/BAL0031_Supporting_Documents_2 017_DL/2017_FRAA_Final_20171113.pdf [2-14] Frequency Response Primer: A Review of Frequency Response with Increased Deployment of Variable Energy Resources, EPRI, Palo Alto, CA: 2018. 3002014361. [3-1] P. Kundur, Power System Stability and Control. New York, NY: McGraw-Hill, 1994. [3-2] D. Ramasubramanian, E. Farantatos, S. Ziaeinejad, and A. MehriziSani, “Operation paradigm of an all inverter interfaced generation bulk power system,” IET Gener. Transm. Distrib., Aug. 2018, accepted for publication (GTD-2018-5179.R1). [3-3] R. R. Kolluri, I. Mareels, T. Alpcan, M. Brazil, J. de Hoog, and D. A. Thomas, “Power sharing in angle droop controlled microgrids,” IEEE Trans. Power Syst., vol. 32, no. 6, pp. 4743–4751, Nov. 2017. [3-4] H. Moussa, A. Shahin, J. P. Martin, S. Pierfederici, and N. Moubayed, “Optimal angle droop for power sharing enhancement with stability improvement in islanded microgrids,” IEEE Trans. Smart Grid, vol. 9, no. 5, pp. 5014–5026, Sep. 2018. [3-5] B. John, A. Ghosh, and F. Zare, “Load sharing in medium voltage islanded microgrids with advanced angle droop control,” IEEE Trans. Smart Grid, accepted for publication, Jun. 2017. [4-1] FERC Open Access Transmission Tariff. https://www.ferc.gov/industries/electric/indus-act/oatt-reform/order890/pro-forma-oatt-rehearing.pdf?csrt=5308760181500748066. [4-2] The Evolution of Ancillary Services to Facilitate Integration of Variable Renewable Energy Resources. EPRI, Palo Alto, CA, 3002008987, 2016. 6-2 0 [4-3] An Enhanced Dynamic Reserve Method for Balancing Areas. EPRI, Palo Alto, CA. 2017, 3002010941. [4-4] NERC. Balancing and frequency control. Princeton, NJ. January 26, 2011. [4-5] Senate Bill No. 100. https://leginfo.legislature.ca.gov/faces/billNavClient.xhtml?bill_id=2017 20180SB100. [4-6] Planning Hawaii's grid for future generations, Integrated Grid Planning Report, Mar. 1, 2018. [4-7] C. Grigg, et al., The IEEE Reliability Test System-1996. A report prepared by the Reliability Test System Task Force of the Application of Probability Methods Subcommittee. IEEE Transactions on Power Systems, vol. 14, no. 3, pp.1010-1020, Aug. 1999. [4-8] https://github.com/GridMod/RTS-GMLC. [4-9] R. Hytowitz,B. Frew, G. Stephen, E. Ela, J. Lau, N. Singhal and A. Bloom. Impacts of Price Formation Efforts Considering High Renewable Penetration Levels and System Resource Adequacy Targets. NREL Technical Report, October 2018. [4-10] EPRI Video Tutorial - Illustrating Operating Reserve Needs and Methods- Operating Reserve and Operational Support Tools to Help Meet Variability and Uncertainty, Palo Alto, CA, 2016. [4-11] E. Ela, Dynamic Operating Reserve and Advanced Scheduling Techniques to Support Variability and Uncertainty in Power Systems Case Studies on the Western Interconnection, EPRI, Palo Alto, CA, 3002008366, 2016. 6-3 0 0 Appendix A: Test Case and Scenarios for Chapter 4 Test System Description The IEEE reliability test system (RTS-96), recently augmented by NREL to include additional renewables, was used for the analysis 7. Its one-line diagram is shown in Figure A-1. It has 121 branches, 74 substations, and 278 generation injections, which consist of 72 thermal units, 1 nuclear unit, 6 wind units, 20 hydro units, 70 PV and 109 rooftop PV. Three load zones are included to mimic the grids in LA Division of Water and Power, Nevada Energy, and Arizona Public Service Company, respectively. The peak load of the system is 8192 MW. Figure A-1 NREL Reliability Test System Test Scenarios Description Based on the original data, four different cases are developed, as shown below: Case 1: Low renewable energy penetration case. Case 2: High renewable energy penetration case. Case 3: Nuclear resource set as non-Must Run in Case 2. Case 4: Nuclear and Hydro units in Case 2 removed. 7 More information and the test system details can be found at https://github.com/GridMod/RTS-GMLC. A-1 0 Case 1 is a low renewable energy penetration case, which includes lots of thermal generators. Case 2 is a high renewable energy penetration case, in which a significant amount of renewable energy resources has been added to the system. In both case 1 and case 2, there is a 400 MW nuclear power plant which is simulated as must-run unit in the study. To eliminate the impact of must-run units to the system operation, in Case 3 the nuclear resource was set as non-must run (nuclear can still be economically dispatched between the minimum and maximum capacity) based on case 2. To further remove the impacts of nuclear units and focus on non-hydro renewable energy resources, Case 4 was created by removing all the nuclear and hydro units of Case 2. The generation capacity of the various resources in each case is shown in Table A-1. A one-week production cost simulation was conducted for each case. The average percentages of generation of different resources for each case are shown in Table A-2. Table A-1 Generation Capacity (MW) in Each Case (Peak load: 8192 MW) Cap. (MW) CC CT STEAM Hydro Nuclear VER Case 1 3550 1545 1362 1000 400 2133 Case 2&3 3550 1645 830 1000 400 11948 Case 4 3550 1645 0 0 0 11948 Table A-2 Average percentages of Generation in One Week Case 1 Case 2 Case 3 Case 4 Thermal (%) 68.6 37.2 32.5 31.2 Hydro (%) 18.1 14.1 14.6 0.0 VER (%) 13.3 46.4 48.6 53.2 A-2 0 0 Export Control Restrictions The Electric Power Research Institute, Inc. (EPRI, www.epri.com) Access to and use of this EPRI product is granted with conducts research and development relating to the generation, delivery the specific understanding and requirement that respon- and use of electricity for the benefit of the public. An independent, sibility for ensuring full compliance with all applicable nonprofit organization, EPRI brings together its scientists and engineers U.S. and foreign export laws and regulations is being as well as experts from academia and industry to help address undertaken by you and your company. This includes an obligation to challenges in electricity, including reliability, efficiency, affordability, ensure that any individual receiving access hereunder who is not a U.S. health, safety and the environment. EPRI members represent 90% of the citizen or U.S. permanent resident is permitted access under applicable electric utility revenue in the United States with international participation U.S. and foreign export laws and regulations. in 35 countries. EPRI’s principal offices and laboratories are located in Palo Alto, Calif.; Charlotte, N.C.; Knoxville, Tenn.; and Lenox, Mass. In the event you are uncertain whether you or your company may lawfully obtain access to this EPRI product, you acknowledge that it is your Together...Shaping the Future of Electricity obligation to consult with your company’s legal counsel to determine whether this access is lawful. Although EPRI may make available on a case by case basis an informal assessment of the applicable U.S. export classification for specific EPRI products, you and your company acknowledge that this assessment is solely for informational purposes and not for reliance purposes. Your obligations regarding U.S. export control requirements apply during and after you and your company’s engagement with EPRI. To be clear, the obligations continue after your retirement or other departure from your company, and include any knowledge retained after gaining access to EPRI products. You and your company understand and acknowledge your obligations to make a prompt report to EPRI and the appropriate authorities regarding any access to or use of this EPRI product hereunder that may be in violation of applicable U.S. or foreign export laws or regulations. Program: Technology Innovation © 2019 Electric Power Research Institute (EPRI), Inc. All rights reserved. Electric Power Research Institute, EPRI, and TOGETHER...SHAPING THE FUTURE OF ELECTRICITY are registered service marks of the Electric Power Research Institute, Inc. 3002014775 Electric Power Research Institute 3420 Hillview Avenue, Palo Alto, California 94304-1338 • PO Box 10412, Palo Alto, California 94303-0813 USA 800.313.3774 • 650.855.2121 • askepri@epri.com • www.epri.com 0
0
You can add this document to your study collection(s)
Sign in Available only to authorized usersYou can add this document to your saved list
Sign in Available only to authorized users(For complaints, use another form )