Construction Science Mr. M Mathenjwa Cost construction 11/03/2025 • COSTING CONSTRUCTION WORK MATERIAL & LABOUR LECTURE CONTENT •Did you know…? •Costing construction work – materials & labour: 1. Introduction 2. Foundations 3. Cavity walls 4. Flooring 5. Painting WHY IS IT IMPORTANT TO ACCURATELY COST CONSTRUCTION WORK? 1. INTRODUCTION • One of the important branches of building technology is to prepare the estimates of the cost involved in constructing a building. • The overall cost of a project determines its viability and enables the client to arrange capital for financing the construction. • The main components of the cost of constructing a building are the cost of materials, labour, plant and contractor’s profit. • This chapter gives some examples on how to prepare approximate estimates. The costs of materials and labour are never constant and they also differ from one region to another. For latest information on the cost of materials, labour and plant reference should be made to publications which update this information at regular intervals. PAINTING • Painting is necessary to give doors, windows, walls etc. a finish that enhances their appearance and provides protection from dust, dirt and other harmful substances. In this section only the external surfaces of walls are considered. Some of the main factors that affect the amount of paint required are the type of surface, the number of coats and the type of paint. EXAMPLE 4 - The front wall of a house, shown in the below figure, is finished with roughcast rendering and needs two coats of masonry paint. The spreading rate of paint is 3m² per litre. Find the cost of paint and labour if one 5 litre can of masonry paint costs £15.89, and the labour cost is £4.30 per m². 4. FLOORING • Softwood boards and chipboard sheets are used as floor covering materials in dwelling houses. The thickness of these materials depends on the spacing between the floor joists. For a spacing of 400 mm between the joists, 18 mm thick floorboards and chipboard sheets are satisfactory. The coverage provided by tongued and grooved floor boards/chipboard is slightly less than their actual surface area as the tongue of one board fits into the groove of the next one. A floorboard measuring 2400 x 121 x 18 mm provides coverage of 0.272m². • The figures on the right, shows the joists and floorboards of an upper floor. EXAMPLE 3 - Find the cost of providing and fixing: (a) softwood floorboards in a room measuring 4.5m x 3.9m (b) chipboard flooring in a room measuring 5.0m x 4.2m Floorboards measuring 3000 x 121 x 18 mm thick cost £16.99 for a pack of five. One pack covers an area of 1.71m². Cost of labour is £9.00/m². One sheet of chipboard measuring 2400 x 600 x 18 mm thick costs £5.30. One sheet covers an area of 1.44m². Labour cost is £4.50 /m². Allow wastage @ 10%. 3. CAVITY WALLS • The cavity walls in dwelling houses consist of a 102.5 mm thick outer leaf of bricks and a 100 mm thick inner leaf of lightweight concrete blocks. The space between the two leaves, called the cavity, is 50 to 75 mm wide and provided with 50 mm thick Rockwool or other insulation material suitable for the purpose. • The below figure shows a brick and a block as they are laid in the construction of walls. The dimensions shown are without the mortar joints. With 10 mm thick mortar joints their dimensions are: Bricks: 225 x 102.5 x 75mm/Concrete blocks: 450 x 100 x 225mm • The quantity of mortar required for 1m² of brickwork is 0.026m³ and for 1m² of blockwork is 0.012m³. EXAMPLE 2: Calculate the number of bricks and 100 mm thick aerated concrete blocks, and the quantities of cement and sand, to construct a 4.0m x 2.8 m high cavity wall with a 2.0m x 1.2 m high window. Allow for 5% extra bricks and blocks and 10% extra mortar. Labour rates are: £15.00/m² for brickwork and £11.50/m² for blockwork. SOLUTION: 2. FOUNDATIONS • Concrete is by far the most commonly used material in the construction of foundations of buildings. For plain concrete 1:3:6 concrete mix is usually used, but for reinforced concrete 1:2:4 or a stronger mix is used. • In this section we will consider how to work out the mass of the cement and the aggregates. This gives a better quality of concrete as we can take into account the moisture content of the aggregates if they are not dry. • Consider a 1:3:6 concrete mix. The density of concrete is approximately 2400 kg/m3 or in other words, 1m3 of concrete has a mass of 2400 kg . To prepare 1m3 of concrete the quantities of cement and the aggregates are: • The amount of water depends on where the concrete is to be used. For Strip foundations the amount of water could be about 50% of the amount Of cement, giving a water cement ratio of 0.5. • EXAMPLE 1 (NB!!!) - Calculate the cost of materials and labour required to construct the 1:3:6 concrete strip foundation shown in the figure, given that: Solution: solution Volumes, the quantities of material to prepare 1m3 of concrete are given. For preparing 3,552m³ of concrete, the quantities of materials and their costs are: EnD • Scope? • Unit converions • Indices • Basic algebra and transpositions