1. In the continuous CA scenario in the protocol frequency band, what is the maximum center frequency
band interval between carrier 1 (60MHz bandwidth) and carrier 2 (100MHz bandwidth) in the n41
frequency band?
A. 89.8MHz
B. 99.8MHz
C. 69.8MHz
D. 79.8MHz
Answer: D
2. Which of the following manufacturers was the first to complete the SA functional test of the domestic
IMT-2020 5G Promotion Group?
A. Huawei
B. Ericsson
C. ZTE
D. Nokia
Answer: A
3.Which piece of information will not be referenced by the automatic deletion of neighbor relations
feature?
A. Neighborhood specifications
B. Neighborhoods that have not been used for a while
C. gNodeB Neighborhood Cell Specifications
D. X2/XN Specifications
Answer: D
4. The redirection process has lower service interruption delay than the switching process.
A. True
B. False
Answer: B
5. The scheduling priority of retransmitted data is higher than that of initially transmitted data.
A. True
B. False
Answer: A
6. Which of the following in the terminal capability report indicates that the terminal supports antennas?
A. SupportedsRs-Resourse
B. maxNumberSRS
C. SupportedSRS-AntennaSwitching
D. SupportedSRS-TxPortSwith
Answer: C
7. The terminal can send a power control command to the base station to control the transmit power of the
PDSCH.
2/6
Download the latest H35-580_V2.0-ENU exam dumps PDF for Preparation.
A. True
B. False
Answer: B
8. Imbalanced terminal receiving antennas will affect RANK performance. Generally, within what range
can the average RSRP difference of different antennas be considered balanced?
A. 6dB
B. 8dB
C. 4dB
D. 2dB
Answer: A
9. The initial TA (time advance) adjustment of the terminal is obtained through which of the following
messages?
A. SIB1
B. Random access response
C. RRC connection setup
D. RRC Reconfiguration
Answer: B
10. The distribution link of the smart grid will use both wireless and wired networks.
A. True
B. False
Answer: A
11. As long as the SSB frequency or SCS between the serving cell and the neighboring cell is different,
the terminal's measurement of the neighboring cell is an inter-frequency measurement.
A. True
B. False
Answer: A
12. For SA networking, voice solutions include VONR and CSFB
A. True
B. False
Answer: B
13. For the N78 frequency band, which of the following time slot ratios (downlink, uplink) can support the
transmission of SSB beams?
A. 4:01:00
B. 3:01:00
C. 7:03:00
D. 8:02:00
Answer: C
3/6
Download the latest H35-580_V2.0-ENU exam dumps PDF for Preparation.
14. For a 60KHZ SCS configuration, how many time slots are included in a radio frame?
A. 40
B. 80
C. 160
D. 20
Answer: A
15.For a 100MHz cell, when the downlink uses type 0 allocation, what is the minimum resource allocated
in the frequency domain?
A . 16RB
B. 4RB
C. SRB
D. 2RB
Answer: A
16.How much data does the SSB that occupies 20 RB resources carry?
A. 432 bits
B. 576 bits
C. 972 bits
D. 864 bits
Answer: D
17.Which parameter indicator will not be referenced in the SCell deactivation management of carrier
aggregation?
A. Data volume in UE downlink RLC buffer
B. Spectral efficiency corresponding to SCell CQI
C. Spectral efficiency corresponding to SCell SRS
D. UE_BSR data volume scheduled uplink
Answer: C
18. When testing the downlink peak value of an NR network, which of the following should the PDSCH
DMRS type be configured to?
A. Type3
B. Type2
C. Type1
D. Type4
Answer: B
19. If the MeasAndMobParametersMRDC of the terminal MR-DC capability contains the
independentGapConfig information element, which GAP configuration is recommended for NR
inter-frequency measurement?
A. Per gNodeB GAP
B. Per FR1GAP
C. Per eNodeB GAP
4/6
Download the latest H35-580_V2.0-ENU exam dumps PDF for Preparation.
D. Per UE GAP
Answer: D
20. In the existing network, we recommend that all cells use the configuration parameters under the peak
rate scenario to improve user experience.
A. True
B. False
Answer: B
21. During downlink data transmission, if the terminal suddenly fails to report CQI, what will happen?
A. Downlink data transmission stops
B. Dropped calls
C. Use the currently used MCS for data transmission
D. Use a fixed low-order MCS
Answer: D
22. In downlink detection, what is the PDCCH BLER synchronization threshold Qin?
A. 0.1
B. 0.02
C. 0.15
D. 0.05
Answer: A
23.Which of the following factors is not involved in calculating the number of RBs for a user in downlink
scheduling?
A. RI reporting
B. MCS
C. PMI reporting
D. Cache data volume
Answer: C
24. During downlink scheduling, which of the following services has the highest scheduling priority?
A. RRC signaling
B. SIB
C. MIB
D. VoNR service
Answer: C
25. During the downlink MCS adjustment process, the base station makes the adjustment based on which
of the following measurements?
A. PDSC H SINR
B. PDCC H SINR
C. PDSC H BLER
D. PDCCHBLER​
5/6
Download the latest H35-580_V2.0-ENU exam dumps PDF for Preparation.
Answer: C
26. During the same-frequency cell reselection process, if you want to make it easier for the terminal to
reselect from the serving cell to a specific neighboring cell, how can you modify the parameters?
A. Increase Qoffset
B. Increase Qhyst
C. Reduce Qoffset
D. Reduce Qhyst
Answer: C
27. Among the A3 event parameters for intra-frequency handover, which of the following parameters
cannot be configured individually based on QCI?
A. A3 bias
B. Neighborhood Offset (CIO)
C. A3 Amplitude Hysteresis
D. A3 time lag
Answer: B
28. When using Probe to test the NSA network, it is found that the MAC layer rate of LTE uplink is 20Mbps,
but the PDCP layer rate is 0. Which of the following understandings is correct?
A. The bit error rate is too high and the data is retransmitted.
B. LTE data converges to NR's PDCP layer
C. Tool statistics anomaly
D. PDCP layer failure
Answer: B
29. In the uplink power control process, the power control of SRS is related to the power control of which
channel?
A. PRACH
B. PUSCH
C. DMRS
D. PUCCH
Answer: B
30. During uplink scheduling, what is the fixed value of the “logical channel guaranteed rate” for each
non-GBR logical channel?
A. 16kbps
B. 32kbps
C. 8kbps
D. 4kbps
Answer: C