University of Engineering and Technology Peshawar
ASHRAE Level II Energy Audit Report
Unsere Kinder School
(12-B University Rd, University Town, Peshawar, Khyber Pakhtunkhwa 25000)
Auditing Team:
Talha Khan: 21pwcee0015@uetpeshawar.edu.pk
Ubaidullah Khan: 21pwcee0024@uetpeshawar.edu.pk
Hammad Akhtar: 21pwcee0017@uetpeshawar.edu.pk
Supervised by:
Engr. Muhammad Saad Rehan
USPCAS-E UET Peshawar
( Plot D, Sector B/3, near Peshawar Institute of Cardiology, Phase 5 Hayatabad, Peshawar,)
CONTENTS OUTLINE:
1. Executive Summary:
1.1. Building Description
1.2. Energy Consumption Baseline
1.3. Recommendation
2. Energy Audits
2.1. Meteorological Data
2.1.1. Temperature
2.2. Energy Consumption:
2.2.1. Baseline Energy Consumption
2.2.2. Key Systems and Equipment
2.3.Building Structural system and operational plans
2.3.1. Building Envelop (floor plans)
2.3.2. Observable deficiencies
2.3.3. Building occupancy and operation
2.4. HVAC System and Equipment
2.5. Electrical Systems and Equipment
2.5.1. Pumps and Fans
2.5.2. Lighting
2.5.3. Plug load and other equipment
3.
4.
5.
6.
Energy Management systems and no/low-cost opportunities
Building management system and metering system
Energy Efficiency Measures
Standards for indoor comfort and building operation (NEECA)
1. Executive Summary:
This energy audit is done by the students of USPCAS-E UET Peshawar at Unsere Kinder
School. Unsere Kinder School is the realization of the GIS System in the full sense. It
combines the values of premium education with the latest innovation in technology to
deliver the best-of-the-breed curriculums to Children from Age 2 onwards.
Energy Consumption is primarily a major concern all over the globe, and saving energy
and finding opportunities for energy conservation is better than generating energy.
The operations of buildings account for 30% of global final energy consumption and 26%
of global energy-related emissions (8% being direct emissions in buildings and 18%
indirect emissions from the production of electricity and heat used in buildings).
Considering such threats, the world is shifting towards Green Buildings and Net-Zero
Energy Buildings. In this regard our main focus is to target educational buildings, to
make them energy efficient and environmentally friendly buildings by the process of
energy auditing (energy performance assessment) that includes Energy Consumption
analysis, calculating energy consumption by different kinds of loads (Lights, Fans,
Motors, HVAC), Identifying potential areas for improvements and recommending
Energy Efficiency Measures (EEMs) along with techno-economic analysis. This project
aims to cover three main SDGs that includes Quality Education (SDG 4), Affordable and
Clean Energy (SDG 7), and Sustainable cities and Communities (SDG 11).
This energy audit report:
• Evaluate overall energy consumption
• illustrates current energy use
• identifies and outlines potential areas of energy and cost savings.
1.1.
Building Description:
Ref
Category
Description
1
Name of building
Unsere Kinder School
2
Construction Area
60 Marla (16335 m2)
3
Enclosed Area
4
Building Type
Residential
5
Purpose of use
Educational institute
6
Total occupancy
7
Address
12-B University Rd, University
Town, Peshawar, Khyber
Pakhtunkhwa
8
Energy Manager
Izzat Khan
Table 1: Building Description
1.2.
Baseline Energy consumption:
2500
1910
2000
1327
kWh
1500
825
1000
582
407
500
494
582
532
366
676
367
364
0
October
Energy Baseline
September
August
July
Months
June
May
April
March
Feburary
Januaury
December
November
Energy Consumption (kWh)
Electricity Consumption
Year
KWH per Year
Cost per Year
Cost per KWH
2023
7,733
417,438 PKR
53.9
2024
8,432
464,865
55.13
Table 2: Electricity Consumption
1.3.
Recommendations:
Solar System Upsizing for integration of Green meter (or net metering system)
Installing motion sensors inside rooms for efficient use of lighting
Insulation of containers for reducing heating and cooling load (Styrofoam panels, Batt
insulation, Spray foam insulation, Mineral wool)
Natural Ventilation for reducing the heating load of the HVAC system
Recommendations Effects
Cost
Payback Period
Solar System
Upsizing
Motion sensors
Insulating
containers
Table 3: Recommendations
2. Energy Audits:
The process of energy auditing includes
locating the building
defining the scope of the audit
collecting the data such as energy consumption, its sources, system, and equipment
installed
Identifying the opportunities for energy conservation and their socio-economic analysis
And then recommending appropriate energy efficiency measures
2.1. Meteorological Data:
2.1.1. Temperature:
Outside Temperature
Inside Temperature
Ambient Temperature
18.6 ℃
16 ℃
21 ℃
Table 4: Temperature Data
Heating and Cooling degree days:
This data is calculated based on the average temperature in Peshawar. HDD and CDD
provide estimated energy demand for the heating and cooling of buildings.
City
12℃
14℃
16℃
18℃
20℃
Peshawar
227
359
533
751
1015
Table 5: Heating Degree Days for Peshawar
City
18℃
120℃
22℃
24℃
26℃
Peshawar
2409
1944
1522
1151
829
Table 6: Heating Degree Days for Peshawar
2.2.
Energy Consumption:
The major part of the energy is covered by electricity consumption in unsere kinder schools.
Electricity is consumed directly from the main grid and in addition to that PV system is installed
for onsite generation. And the connected meters are Three Phase Smart Meters. The overall
energy consumption and onsite generation by PV system are as below.
Electricity Consumption
Year
KWH per Year
Cost per Year
Cost per kWh
2023
7,733
417,438 PKR
53.9
2024
8,432
464,865
55.13
Table 7: Electricity Consumption
NMI and Electricity Meters:
Meter
Three-phase whole current
3G Smart Meter
Serial No
028573
Table 8: NMI and Electricity meters
Annual Consumption Meter
4380 watts
2.2.1. Electricity Consumption Baseline
2500
1910
2000
1327
kWh
1500
825
1000
582
407
500
494
676
582
532
366
367
364
0
Months
Graph 1: Baseline energy consumption
October
Energy Baseline
September
August
July
June
May
April
March
Feburary
Januaury
December
November
Energy Consumption (kWh)
PV System and Equipment:
The PV system installed was not generating as much electricity as required, and the amount of
electricity generated was consumed on the spot because of the absence of a storage system
(batteries).
Generation
Capacity
Storage system
Inverter
Net Metering
4 KW
---
Power Max
(suntronic)
---
Table 9: PV system
2.3.
Building Structural System and Operational Plan:
This section includes
The floor plans of the building were measured by using a Laser distance meter
and mapped on AutoCAD.
The operational schedule and occupancy of each classroom inside the building
2.3.1. Building Envelop (Floor Plans):
Ground Floor:
Figure: 01
Floor: 01
Observable Deficiencies:
Ref No
Envelop
Yes/No
1
Internal Shading
No
2
External Shading
Not appropriate
3
Solar Reflective Paints
Needs to repaint
Table 10: Observable Deficiencies:
Occupancy and Operational hours:
Ground Floor:
Rooms
Occupancy
Operational hours
Classroom: 1
20
6
Classroom: 2
20
6
Classroom: 3
80
6
Classroom: 4
15
6
Classroom: 5
20
6
Classroom: 6
20
6
Library
20
5
Office
3
6
Kitchen/ Store Room
2
2
Indoor Gym
10
5
Room
Occupancy
Operational hours
Room: 1
25
6
Room: 2
15
6
Room: 3
25
6
Room: 4
15
6
Computer Lab
15
3
First Floor:
2.4.
HVAC System and Equipment:
The HVAC system installed all over the building is a split inverter type AC system with both
heating and cooling options. The description of each system and its load for each room is
described below
Ground Floor:
Rooms
AC description
Wattage
Classroom: 1
inverter (Enviro)
2368W
Classroom: 2
inverter (Gree)
5000W
Classroom: 3
inverter (Gree)
5000W
Classroom: 4
inverter (Haier)
3000W
Classroom: 5
Inverter (Dawlance)
2050W
Classroom: 6
Inverter (Orient)
2200W
Library
--
--
Office
Inverter (LG)
3000W
Kitchen/ Store Room
---
---
Indoor Gym
Inverter (Gree)
5000W
Total: 27,618W
First Floor:
Room
AC description
Wattage
Room: 1
Inverter (Haier)
3000W
Room: 2
Inverter (Haier)
3000W
Room: 3
Inverter (Dawlance)
2050W
Room: 4
Inverter (Haier)
3000W
Computer Lab
Inverter (PEL)
1700W
Total: 12,750W
2.5.
Electrical Equipment and System:
Electrical equipment includes pumps and motors, fans, lights, etc.
2.5.1. Pumps and Fans
Pumps:
Pumps
Wattage
Power Factor
Fans:
All the fans installed in each room are of the same wattage (75), So we simply
multiply the wattage of fan with the total number of rooms to get the total
wattage.
Fan Wattage
Total Rooms
Total Wattage
15
1125 watts
75W
2.5.2. Lighting Load:
All the lights installed in the building were energy-efficient (LED). However, according to IES,
there isn’t sufficient light to perform different classroom tasks, making reading, writing, and
other tasks difficult for students.
Ground Floor:
Rooms
Wattage
Classroom: 1
1 LED× 12W= 12W
Classroom: 2
3 LED× 12W= 36W
Classroom: 3
2 LED× 12W= 24W
Classroom: 4
2 LED× 12W= 24W
Classroom: 5
3 LED× 12W= 36W
Classroom: 6
2 LED× 12W= 24W
Library
2 LED× 12W= 24W
Office
1 LED× 40W= 40W
Kitchen/ Store Room
2 LED× 40W= 40W
Indoor Gym
12 LED× 12W= 144W
Total: 404W
First Floor:
Rooms
Wattage
Room: 1
6 LED× 18W= 108W
Room: 2
6 LED× 18W= 108W
Room: 3
6 LED× 18W= 108W
Room: 4
6 LED× 18W= 108W
Computer Lab
4 LED× 18W= 72W
Total: 504W
2.5.3. Other Equipment Loads:
Equipment
Wattage
7 PC× 200W= 1400W
Computer
1200W
Microwave Oven
350W
HP Printer Scanner
250W
HP Printer
100W
Small Fridge
150W
Water Dispenser
350W
HP LaserJet
Total: 3800W
3. Standards for indoor comfort and building operation (NEECA)
4. Energy Management systems and no/low-cost opportunities
5. Building management system and metering system
6. Energy Efficiency Measures