Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract ARP-ST-SPE-02 T1 | 18 May 2023 PIP Tender This report takes into account the particular instructions and requirements of our client. It is not intended for and should not be relied upon by any third party and no responsibility is undertaken to any third party. Job number 283004-00 Arup Singapore Pte Ltd 182 Cecil Street #06-01 Frasers Tower Singapore 069547 www.arup.com Doc D.2/1 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Contents Page 1 General 1.1 1.1.1 1.1.2 1.1.3 1.2 1 Project Particulars Site Description Project Team Superintending Officer (SO) and Project Manager (PM) General Description of the Works 1 1 1 2 2 2 As-built Drawings 5 3 BCA Buildability and Built Environment Transformation (BET) Scheme 5 4 Base Specifications 6 5 Project Specific Data (PSD) 8 Appendices Appendix A G01-010-01 PSD for Buildable Design Appendix B C03-010-01 PSD for Green Concrete Appendix C C03-010-02 PSD for High Strength Concrete Appendix D C00-010 Design and Construct Performance Criteria Appendix E Base Specifications ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/2 Singapore Land Group Ltd. 1 Clifford Centre Redevelopment PSD Specification for Main Contract General This section sets out the general requirements, including scope of works, for carrying out any works for the project and shall be read in conjunction with all relevant work sections and other contract documents. 1.1 Project Particulars 1.1.1 Site Description The proposed development is located at 24 Raffles Place adjacent to Collyer Quay, bounded by Raffles Place MRT Station and high-rise buildings. Refer to Figure 1 for the site location. The site was occupied by a 29-storey commercial office building consisting of 7 storey high retail/carpark podium and 1 storey basement which was constructed in year 1970s. The existing foundation was a caisson type foundation. Geylang River Project Site Figure 1 Site Location Plan 1.1.2 Project Team The project team comprises the following: Organisation Project Manager/ Developer Singapore Land Architectural Design Consultant PLP Architecture Page 1 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/3 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Architect / QP A61 Architects Pte. Ltd. C&S Engineer Arup Singapore Pte. Ltd. M&E Engineer Squire Mech Pte. Ltd. Quantity Surveyor AECOM Cost Consulting and Projet Management (Singapore) Pte Ltd. Landscape Consultant Ortus Design Pte. Ltd. Green Mark & ESD Consultant GreenA Consultants Pte. Ltd Façade & Lighting Consultant Arup Singapore Pte. Ltd. Acoustic Consultant Arup Singapore Pte. Ltd. Fire Safety Consultant Ignesis Consultants Pte Ltd Design for Safety Consultant Arup Singapore Pte. Ltd. Traffic Consultant Ramboll Lighting Consultant Light Collab LLP 1.1.3 Superintending Officer (SO) and Project Manager (PM) For this contract, Superintending Officer (SO) shall mean the Architect in their capacity as contract administrator. 1.2 General Description of the Works The proposed works shall include the following: a. Construct bored piles and other foundation systems specified for the project including withdrawing/demolishing any existing foundations or any other inground obstructions obstructing the proposed new piles. b. Construction of a 4 Level basement structure including excavation, temporary support ground water and movement control, instrumentation and monitoring, removal of all encumbrances, and other temporary works. c. Construction of a 6 Level podium and 34 level tower super structure in accordance with the drawings. d. Construction of underground pedestrian link to the Raffles Place MRT station including the required temporary support works in accordance with the drawings. e. Construction of all external works and drains in accordance with the drawings and authority requirements. f. Construction of new and modified roads and traffic junctions. g. Construct new minor sewer pipes and minor sewer diversion, if required for the completion of the Works. Page 2 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/4 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract h. Obtain all necessary approvals from the relevant authorities/agencies prior to commencement of any works on sites, including and not limited to: • • • POWS submissions and any other required submissions to PUB due to proximity of the works to public sewer, water mains and drainage systems. CCTV surveys shall be carried out pre and post construction works in accordance with PUB requirement. Contractor shall take due care and precautionary measure to ensure that no damage or settlement occurs to any existing sewer, water mains and drainage systems in the course of the works. The contractor shall carry out impact assessment to establish the influence zone of the proposed works which affected the existing sewer, water mains and drainage systems. The impact assessment shall be endorsed by a Professional Engineer and submitted to PUB. LTA MSRA & permit submissions for all works within Railway Protection/Safety Zone. CAAS submissions for Obstruction Control activities such as erection of cranes or any other tall construction machineries. i. Obtain all the cable, pipelines and any other inground services drawing from relevant authorities/agencies/service providers to verify presence of any inground services and utility lines within and around the development. Carry out detection of existing underground cables and services by a Licensed Cable Detection Worker (LCDW) and inform the relevant authorities/agencies/service providers prior to commencement of any works. j. Conduct condition surveys (pre and post) of buildings, services, infrastructures, and other structures within the area of influence of the Works. k. Engage Registered Surveyor and specialist geophysical surveyor to accurately locate and to provide prominent physical marking on the locations of • • • • railway protection/safety zones, sewer and water main pipes, setbacks and corridors, drainage reserves, inground services. The Registered Surveyor shall carry out topographical surveys of the development and surrounding affected areas including level survey of all existing surrounding drains and drainage facilities as required by PUB. Topographical surveys shall be carried out prior to commencement of the works and upon completion of the works. l. The I&M contractor has been appointed by the Employer and will be novated to the Main Contractor. The Main Contractor shall be responsible for coordination and sequencing installation of instruments. Instruments shown in I&M drawings are the minimum requirement. Contractor shall review and allow provision of additional instruments as required by Contractor's QP or Authorities. Additional I&M will be under the Contractor's own cost and time. m. The Main Contractor shall provide steel casing for the installation of inclinometer in wall and coordinate with I&M Contractor to install the casing and inclinometer during secant piling works. Page 3 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/5 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract n. Design and construct ERSS system for any excavation works required for the project. Engage Singapore Registered Professional Engineer to carry out full design, authority submission and supervision of ERSS system and excavation works. Provide instrumentation and monitoring works required for the excavation works. Engage qualified site supervisors (RE/RTO) to assist the Professional Engineer in supervising the installation of ERSS system and excavation works. o. Provide Professional Engineer’s Assignee(s) if required by LTA, PUB, and any other authorities, to provide standing supervision of any critical construction works within railway protection zones and/or sewer and drainage corridors. p. Coordinate and construct substructure and below ground structure such as pile caps, underground tanks and chambers (incoming services, detention tank, fuel tank, ICs, etc.). q. Coordinate and construct structures of the proposed Clifford Centre Redevelopment in accordance with the drawings. r. The Contractor shall undertake detailed construction stage analysis to simulate the crucial stages of the structure under construction and demonstrate structural stability and safety. The analysis shall include for sensitivity of key input parameters. The Contractor shall also use construction stage analysis to simulate and demonstrate what structural compensation is required for the superstructure to be constructed within the necessary short- and long-term verticality tolerances. The Contractor shall develop a field monitoring plan for checking of actual movement of the building versus predictions. The plan shall include strain measurement of column/transfer deformation using vibrating wire-gauge, and optical survey for lateral and vertical movement. Measurement shall be monitored and checked throughout construction. The plan shall also include control strategies for monitoring and checking the performance during construction stage. s. Construct miscellaneous structures in accordance with the drawings. t. Engage competent and experienced waterproofing specialist to coordinate, design and install waterproofing system to all structures in contact with ground. u. Construct all external works and drains in accordance with PUB, LTA and NParks standards and codes, including road modification/enhancement works specified in the drawings. v. Design and provide all temporary works necessary for completing the Works. Engage Singapore Registered Professional Engineer to carry out full design and supervision of all temporary works. w. The Contractor shall engage a Singapore Registered PE for the full design of the amenity boxes located at Levels: 7th - 7th(Mid) and 18th - 19th. The design submissions and proposals shall be endorsed by a Singapore Registered PE and submitted for SO’s acceptance and onward submission to BCA. Authority submissions and supervision shall be undertaken by Project QP. x. Design and construct: Page 4 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/6 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract o All railings/barriers, catwalks, services supports, DFMA frames/supports, façade supports, canopies, purlins, BMU support, trellises, lift separator beams, bollards, glass support, hanging double slabs, and any other secondary steelworks that are not shown in the structural drawings. o All steel connections and beam penetrations. o The building crown including the crown signage support. o Cable net wall supporting frames at Collyer Quay and Raffles place. o All temporary structure including strengthening resulting from construction sequence. o All temporary ERSS works. o Contractor shall check construction sequence and temporary supports that affect load path through the transfer trusses. The Contractor shall engage Singapore Registered Professional Engineer to carry out full design, authority submission and supervision of these Works. y. Liaise and coordinate with other contractor(s) appointed separately by Client. z. Obtain authorities’ clearances for the completed works. aa. All related works required for the completion of the above. 2 As-built Drawings Contractor shall obtain authority approved plans in CAD from the SO. These plans must be updated to capture all deviations or amendments, including those captures in SO’s Instructions (SOI), Project Manager’s Instruction (PMI), Architect’s Instructions (AI), Engineer’s Instructions (EI), Request for Information (RFI), construction sketches, etc. Contractor is to submit such revised plans as as-built drawings to SO for record and authority record plan submission. The as-built plans shall be submitted progressively floor by floor not later than two weeks from casting date. Also, the Contractor is to reflect all structural deviations in the Final As-built models. 3 BCA Buildability and Built Environment Transformation (BET) Scheme The project has adopted the BCA BET scheme. The BET scheme has several mandatory requirements that relate to the construction industry transformation outcome requirements. The mandatory structural requirements adopted for this project are summarized below. Refer to the Architectural specification for full summary of the mandatory requirements applied to this project and the associated obligations of the Contractor. The following Structural BET requirements shall be noted and complied with: Page 5 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/7 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract • Structural Steel floor framing shall be adopted for a minimum of 80% of the total office area. • Composite columns shall be adopted for all office floors. • 70% system formwork shall be used. 4 Base Specifications The following sections of base specification are included in Appendix E. This base specification shall be read in conjunction with Project Specific Data (PSD) Specification included in Section 0 of this report. Table 1 List of Sections of Base Specification (Appendix E) Section Number Section Titles G01-010 General Requirements Parts C01-010 Demolition and Site Clearance C01-020 Condition Survey C02-010 Site Investigation C02-020 General Earthworks (Excavation and Filling) C02-030-01 Diaphragm Wall C02-030-02 Sheet Pilling C02-030-03 Contiguous Bored Pile Walls and Secant Pile Walls C02-040-01 Jet Grouting Method C02-050 Instrumentation and Monitoring C03-010 Concrete Construction Generally C03-020 Reinforcement C03-030 Formwork and Falsework C03-040 Designed Joints C03-050 Water-resistance to Concrete Structures C03-060 Precast Concrete Works C03-070 Prestressed Concrete Works C03-080 Concrete Repairs C03-090-01 Ferrocement C03-100 Sprayed Concrete C03-110 Fibre Reinforce Concrete C04-010 Bored Pilling C04-020 Displacement Pilling C04-030 Pile Testing C05-010 Structural Steelworks C05-020 Protective Works for Structural Steelwork Page 6 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/8 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract C06-010 Sewers Construction C06-020 Drains Construction C07-010 Construction of Roads and Footpaths C07-020 Pavement for Roads and Footpaths C07-030 Road Ancillaries C08-010 Structural Timberwork C08-020 Mass Engineered Timber Page 7 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/9 Singapore Land Group Ltd. 5 Clifford Centre Redevelopment PSD Specification for Main Contract Project Specific Data (PSD) This section specifies Project Specific Data (PSD) to be read in conjunction with Base Specifications in Error! Reference source not found.. All modifications and additions noted in this PSD take precedence over clauses noted in the base specifications. Table 2 List of PSD Specifications Section Number Section Titles Remarks G01-010-01 PSD for Buildable Design Appendix A C03-010-01 PSD for Green Concrete Appendix B C03-010-02 PSD for High Strength Concrete Appendix C PSD for General Requirements Parts Table 3 PSD for Demolition and Site Clearance No item PSD for Condition Survey Table 4 C02-010 PSD for Site Investigation No item C02-020 PSD for General Earthworks (Excavation and Filling) No item C02-030-01 PSD for Diaphragm Wall Not applicable PSD for Sheet Pilling Table 5 C02-030-03 PSD for Contiguous Bored Pile Walls and Secant Pile Walls Table 6 C02-040-01 PSD for Jet Grouting Method Not applicable C02-050 PSD for Instrumentation and Monitoring Table 7 PSD for Concrete Construction Generally Table 8 PSD for Reinforcement Table 9 PSD for Formwork and Falsework No item PSD for Designed Joints Table 10 PSD for Water-resistance to Concrete Structures Table 11 PSD for Precast Concrete Works Table 12 PSD for Prestressed Concrete Works Table 13 G01-010 C01-010 C01-020 C02-030-02 C03-010 C03-020 C03-030 C03-040 C03-050 C03-060 C03-070 C03-080 PSD for Concrete Repairs Page 8 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/10 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Table 14 C03-090-01 PSD for Ferrocement No item C03-100 PSD for Sprayed Concrete No item C03-110 PSD for Fibre Reinforce Concrete No item PSD for Bored Pilling Table 15 PSD for Displacement Pilling Not applicable PSD for Pile Testing Table 16 PSD for Structural Steelworks Table 17 PSD for Protective Works for Structural Steelwork Table 18 C06-010 PSD for Sewers Construction No item C06-020 PSD for Drains Construction No item C07-010 PSD for Construction of Roads and Footpaths No item C07-020 PSD for Pavement for Roads and Footpaths No item PSD for Road Ancillaries Table 19 C08-010 Structural Timberwork No item C08-020 Mass Engineered Timber Table 20 C04-010 C04-020 C04-030 C05-010 C05-020 C07-030 Table 3 G01-010 PSD for General Requirement Parts Clause Description General Read this section in conjunction with Project Form of Contract provision and if there are discrepancies, the Project form of Contract takes precedence over the requirement of this PSD section. 1.1.1 The Site Refer to Section 1.1 of this report 1.1.2 Project Team Refer to Section 1.1 of this report 1.2 General Description of the Works Refer to Section 1.1.3 of this report 1.3.1 Standards and Codes In case of conflicting requirements between the codes, refer to the Qualified Person (QP) for resolution. Priority of precedence of different standards and codes shall be in descending order as follows: 1. Singapore Standards SS and SS CP 2. SS ISO or ISO 3. BS or BS EN Page 9 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/11 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract 4. Other standards such as ASTM (US), AS (Australia) and DIN (German), as agreed with the QP. 1.4.9 Approved Subcontractors All sub-contractors for the works are subject to the SO’s acceptance. At the time of tender, submit the list of sub-contractors intended to be engaged for the works. Submit with the list, details such as the relevant track records of the firms, the qualification of the personnel and details of equipment to be engaged for the works. 1.4.10 Site Supervision Provide personnel with adequate and relevant experience to SO’s acceptance, to supervise the Work. Submit the CV of the supervisor(s) to SO where directed. 1.4.11 Coordination of Works Ensure that all units, components or assemblies whether from one or different sources, are available in time for incorporation into the Works. 1.5.2 Environment Contractors shall submit to relevant authorities appropriate Earth Control Measures (ECM) designed and endorsed by Qualified Erosion Control Professionals before the start of any construction work. 1.5.4 Buildability Refer to G01-010-01 PSD for Buildable Design. 1.6.6 Approved Suppliers All suppliers are subject to the SO and QP’s acceptance. 1.45 Engagement of Bizsafe Level Certified Subcontractors Refer to SO/PM/Architect/QS requirement. 1.52 Provision of Envelopes for Keys During Handover Refer to SO/PM/Architect/QS requirement. Page 10 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/12 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Table 4 C01-020 PSD for Condition Survey Clause Description 1.1.1 Prescribed Scope of Survey Carry out the condition survey and monitoring for all the immediate neighbouring properties and the following specific buildings/properties which are within the influence zone of the Works: • Arcade Building • Raffles Place MRT • OUE Link Bridge • Income @ Raffles • CIMB Plaza • Surrounding roads, drains and other infrastructure such as bus stops and pedestrian overhead bridge • CCTV survey of existing sewer networks within the vicinity of the Works. 1.4.5 Notice of Survey Provide at least 14 days’ notice of the intended date and scope of precondition and post-condition surveys to the affected parties. 4.4 Crack Survey The survey shall include at least the cracks previously identified as described below: CRACK SCHEDULE Crack No. & Location Width Comments N.A, to be determined after pre con survey 5.2 Survey Records Submit survey records as listed below within 14 days after completion of the survey: Item Description Reference Clause(s) Applicable 1. Photographic Records 4.2 Yes 2. Crack Survey Records 4.4 Yes 3. Level Survey Records 4.5 Yes 4. Records of Defects 4.8 Yes 5. Plumb Survey Records 4.7 Yes 6. Others (Insert where applicable) 5.3.3 Factual Reporting Unless specified otherwise, submit reports of monitoring results at weekly interval. 5.3.4.1 Frequency Based on the factual information received, submit interpretative reports of monitoring results at intervals of 14 days. Page 11 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/13 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Table 5 C02-030-02 PSD for Sheet Piling / Soldier Pile Wall Clause Description 2.5 Permissible Damage Criteria for Existing Critical Structures or Services Carry out Building Damage Assessment on the effects of ground movement to the neighbouring properties due to the works, for the purpose of establishing suitable values for ‘Alert’ and “Work Suspension’ levels for monitoring. Submit to SO with endorsement from a PE. Table 6 C02-030-03 PSD for Contiguous Bored Pile Walls and Secant Bored Pile Walls Clause Description 1.4.1 Development of Design Requirement The design of the SBP wall works is indicated in the drawings, together with the schematic lateral supports, i.e. reinforce concrete slabs and temporary strutting system, indicated in terms of the installation levels, the required stiffness and preloading where necessary. Based on the information, engage a Professional Engineer (Civil) with relevant experience to: • Carry out design verification checks based on actual ground conditions to confirm the required penetration length and size of all temporary or permanent strutting elements and wailings for the SBP walls and ensure that the required control on wall deflection can be achieved. • Prepare a response plan in the event that the temporary or permanent strutting elements do not perform as expected in the design in controlling the wall deflection. Ensure the response plan is feasible in considering the construction sequence and site restraints. • Prepare and submit all design and construction sequence, including drawings endorsed by the PE to the SO for review and the authorities where applicable. • Propose as a response plan in the event that measures taken to control ground movement and vibration do not perform satisfactorily. Take into account of the design requirements as set out in Clause 2.1 below. Submit the CV of the PE to the SO for acceptance. 1.4.4 Upholding of Adjoining Properties Adequately maintain roads and footpaths within and adjacent to the site and keep clear of mud and debris in compliance to relevant authorities’ requirements. 4.3.2.1 Deviation of Centre Line Maximum permitted deviation of pile centre at cut-off from specified position shall be ±50mm in any direction. Allow an additional 5mm for every additional metre of the cut-off level below the top of the guide wall for hard/soft secant piles. 4.3.2.2 Verticality For hard/soft secant piles, 1:200 for the exposed face of the pile unless otherwise agreed. 4.3.2.3 Allowance for Overbreak An additional 50mm is allowed for concrete protrusions resulting from overbreak in the ground unless otherwise agreed. Where very soft layers or obstructions are anticipated, notify the SO to agree on an additional tolerable allowance for the overbreak. 5.4.4 Testing of Self-Hardening Mixes Check for compliance with the mix proportions. Make cube samples at a rate of six per 50m3 of self-hardening slurry or part in each day’s work, three for testing at 7 days and three for testing at 28 days after casting. Page 12 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/14 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Table 7 C02-050 PSD for Instrumentation and Monitoring Clause Description 3.1 Schedule of Instrumentation Engage a qualified, competent, and suitably experienced PE to design instrumentation and monitoring works related to his/her design of ERSS system for excavation works. The proposed instrumentation and monitoring works shall be submitted to the relevant authorities for approval. 4.2.2 Ground Movements and Vibrations Determine permissible limit of ground movements and vibrations from impact assessment carried out by PE. The permissible limit shall comply to regulatory requirement and shall not exceed the following: Building & Road Limits on ground movement (mm) Horizontal Alert All areas Worksuspension Vertical (Settlement) Alert Worksuspension To comply with LTA DBC and BCA’s design requirement and impact assessment acceptance criteria. Limits on level of vibration (mm/s) Alert 10 Worksuspension 15 at 4 Hz increase to 20 at 15 Hz and above Page 13 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/15 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Table 8 C03-010 PSD for Concrete Construction Generally Clause Description 2.5 Execution Class The works are to be built in accordance with Execution Class 2, other than for post-tensioned construction where Class 3 is to be used. 3.6.1 Designated Concrete When designing the concrete mix, comply with the limiting mix parameters and constituent materials as set out below to satisfy the strength, durability and other requirements. The parts below shall be supplied as prescribed mixes in accordance with SS 5441 and SS EN 206-1 Requirements Project Project 1 Concrete designation RC32/40 RC32/40 (ref SS544-2 Table 5) (Piling) 2 Maximum aggregate size (mm) 20 20 Enter 10, 14, 20 or 40 3 Consistence class S4 S3 S1, S2, S3, S4 4 Special restrictions on cement types (enter None None reference if required) 5 Special requirements for aggregates (enter Comply Comply reference if required) with SS EN with SS EN 12620 12620 6 Use of RCA permitted? No Yes Maximum mass fraction of total coarse aggregate enter a higher mass fraction of total coarse aggregate where permitted (Ref SS 5441 cl 4.2.3c) 7 Requirements for accelerated or retarded set None None 8 Special colour requirements None None None or see 4.11.4 9 Type and dosage of fibres Refer to C3- Refer to C3Refer to C3-20 PSD 20 20 10 Chloride class Cl1.0 for GEN series, Cl0.20 for Cl 0.40 Cl 0.40 SRPC, Cl 0.40 for all other concretes or enter special requirements 11 Minimum air content None None 12 Method of placing content Tremie Normal 13 Requirement for finishing concrete None None 14 Identity testing for consistence or other Yes Yes properties required in accordance with SS EN 206-1 Annex B and SS544-1 Annex B. (If yes then details to be added into section 6 Notes 1. All sections of the specification must be completed before it is passed to the producer. The person sending the final specification to the producer must send copies of the document to all other parties (PM, Engineer, Employer as appropriate) who have contributed to the specification. 2. Where ‘None’ is entered in the table this is a default value to ensure that the specification is complete. All those involved in completing the specification need to check if ‘None’ is applicable 3. Guidance on specification of designed concrete can be found in SS544-1, section 4.2. Page 14 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/16 Singapore Land Group Ltd. 3.6.2 Designed Concrete Clifford Centre Redevelopment PSD Specification for Main Contract When designing the concrete mix, comply with the limiting mix parameters and constituent materials as set out below to satisfy the strength, durability and other requirements. The mixes below shall be supplied as designed mixes in accordance with SS544-2 and SS EN 206-1 Requirements Project Project 1 Concrete reference C50/60 C60/75 (similar for C70/85) 2 Strength class C50/60 C60/75 3 Maximum water-cement ratio where appropriate 4 Minimum cement content kg/m³ As per SS EN 206-1 As per SS EN 206-1 5 DC class where appropriate 6 Permitted cement types see SS 544-1 Cl 4.3.2, Note 3 As per SS5441 Cl4.3.2 note 3 As per SS5441 Cl4.3.2 note 3 7 Maximum aggregate size (mm) – Enter 10, 14, 20, 40 20 20 8 Chloride class (a value must be entered unless Cl 0.40 is acceptable) 9 Target density/density class (for lightweight and heavyweight concrete) 10 Consistence class S1, S2, S3, S4 S3 S3 11 Method of placing concrete Normal Normal 12 Requirement for finishing concrete None None 13 Type and dosage of fibres Refer to C3-20 0.15% (by volume) polypropylene fibrer. Refer C03-110 14 Use of RA conforming to SS 544-2 Clause 4.3, permitted? If YES: enter requirements for the following in section 3.5 Not allowed Not allowed Maximum acid-soluble sulfate, method for determination of the chloride content classification with respect to ASR, method for determination of alkali content, any limitation on use in concrete, e.g. exposure classes, maximum mass fractions, etc. (Enter details is section 3.5) None None 15 Special requirements for aggregates None None 16 Minimum air content, or other requirements to resist freeze-thaw attack 17 Special requirements for temperature of fresh concrete None None Page 15 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/17 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract 18 Special requirements for strength developments None None 19 Special requirements for heat development during hydration. See SS EN 197-1 Cl 7.2.3 for definition of low heat. Low heat for large pour Low heat for large pour 20 Special requirements for retarded stiffening None None 21 Special requirements for resistance to water penetration None None 22 Special requirements for resistance to abrasion None None 23 Requirements for tensile splitting strength None None 24 Additional technical requirements See SS544-1 Clause 4.3.3 sections n & m None None 25 Identity additional Strength testing required (If yes then details to be added into section 6 of the PSD) None None 26 Identity additional Consistence testing required (If yes then details to be added into section 6 of the PSD) None None 27 Other properties identity testing required (If yes then details to be added into section 6 of the PSD) None None Notes 1. All sections of the specification must be completed before it is passed to the producer. The person sending the final specification to the producer must send copies of the document to all other parties (SO, Engineer, Employer as appropriate) who have contributed to the specification. 2. Where ‘None’ is entered in the table this is a default value to ensure that the specification is complete. All those involved in completing the specification need to check if ‘None’ is applicable 3. Guidance on specification of designed concrete can be found in SS544-1, section 4.3. 3.6.3 Prescribed Concrete No prescribed concrete shall be used. 4.8.1 Concrete Temperature Control for Thick Section The temperature of the mixed concrete for the structures shall not exceed the specified temperatures of 30°C at the point and time of placing. The Contractor is deemed to have allowed for the cost of installing and monitoring the temperature monitoring devise together with all necessary methods of controlling the temperature in his tender. The following methods of controlling the temperature of the concrete sections thicker than 1000mm are suggested: 1. Night concreting or restricting the mixing and placing to those periods when the ambient temperature is below 30°C on a rising thermometer or below 33°C on a falling thermometer. 2. Use of white or reflective paint on mixer drums, water storage tanks, cement silos and/or storage sheds or permanent screening and shading of the concrete mixing area. Page 16 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/18 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract 3. Shading and/or mist spraying of aggregate with water complying with Clause 3.4 provided adjustments is made to the quantity of water added to the mix. 4. Cooling formwork and reinforcement with water complying with C3-10 Clause 3.6 provided no pools of water remain in the forms when the concrete is placed. 5. Using cements with a temperature of less than 60ºC at the time of adding to the mixer. 6. Reducing the temperature of the mix water by chilling or the addition of sliced, flaked or crushed ice provided that all the ice is melted before the water is added to the mix. Any formwork made of metal, concrete or other material of high thermal capacity shall be cooled with water before the concrete is placed against it. Concrete used for the casting of concrete sections thicker than 1000mm is to be cooled prior to being placed. This is to be achieved by cooling the water using finely chopped ice, shading aggregate stockpiles and cooling the aggregates. In addition, cement with low heat development during concrete curing shall be used (Refer to SS EN 197-1 Cl 7.2.3 for definition of low heat cement). This shall be Portland blast furnace cement (CEM III) to SS EN 197-1 unless otherwise directed by the Engineer. 4.8.2 Requirement s for Curing Concrete Sections Thicker than 1000mm In addition to Clause 4.12, concrete in concrete sections thicker than 1000mm shall be cured by the application of an approved pigmented liquid membrane. Starter bars and construction joints shall be masked and protected from exposure to the curing membrane. After the application of the curing membrane, the concrete is to be properly covered with an approved Polythene sheeting around the concrete members with the Polythene sheeting in close contact with the concrete surfaces. The Polythene sheeting should be adequately secured to the concrete members and fastened at the edges to prevent draughts. On completion of the above-mentioned curing treatment to the concrete, a layer of sand and/or polystyrene panels shall be applied onto the exposed surfaces of the thick concrete sections as a thermal insulation. The minimum curing period shall be at least fourteen days. Forms and exposed concrete shall be kept continuously wet for at least the first ten days after placing. Contractor is to propose concrete mock-ups of the thick sections in order to ensure that the temperature requirements are met. 4.11.1.1 Formed Finishes An Ordinary finish is to be provided in accordance with BS EN 13670 unless otherwise specified in the following table. 4.11.1.5 Special Finish Location Type of Finish Refer to Architectural Specification and Drawings. As nominated by Architect. Special finishes (other than formed or unformed, basic and ordinary finishes) are required as follows: Refer to the Architectural Specification and Drawings for location and type of finish. Contractor shall propose a concrete mix design that is suitable for achieving the minimum requirement. Page 17 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/19 Singapore Land Group Ltd. 4.11.2.1 Unformed Finishes Clifford Centre Redevelopment PSD Specification for Main Contract A Basic finish is to be provided unless specified otherwise in the following table. Location Type of Finish No item 4.12.1 Curing For cements with ground granulated blast furnace slag, minimum curing time is to be 4 days. 4.13 Accuracy of Construction Construct to tighter accuracy to items as noted below: Clause No. Description Permitted Deviation (mm) Elevator shaft requirement The contractor shall ensure the elevator shaft (individual hoist way and pit) is built square, plumb and flush to within ±25mm tolerance over the full height of the elevator shaft, from a single reference point as per SS550:2009 requirement. Any protrusion (nails, etc.) shall be removed from the elevator shaft and any holes not required for lift installation shall be covered. Any areas where tighter accuracy is required for installation of building services, building envelop, architectural finishes/fixtures, and the like The contractor shall coordinate with other trade contractors or subcontractors to establish areas/elements of structures where tighter accuracy is required for installation of façade, services, finishes/fixtures, and the like. The contractor shall ensure the structures are built in compliance with such tighter accuracy requirement. Structural elements in close proximity to development boundary lines, green buffers, drainage reserves, or other statutory demarcation and reserve lines or setbacks Encroachment to statutory demarcation and reserve lines and setbacks are not permitted. 5.1 Compliance Testing Testing type and quantity shall not be less than the testing requirement in the latest edition of BCA/IES/ACES Guide Book for Site Supervision Plan. 5.4.1 Temperature Testing of Fresh Concrete All tests are to be carried out at the point of discharge into the concrete sections thicker than 1000mm. Tests are to be carried out on samples of concrete not less than 0.25 cubic metres that are representative of the concrete batches from which they come. The temperature is to be measured in the centre of the sample, or in three evenly spaced points in the sample. The temperature shall be taken to be the single measured temperature or the average of the three measured temperatures, whichever is the higher. Samples are to be tested at a frequency of not less than one sample for every 12 cubic metres of concrete placed and as directed by the Architect. Page 18 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/20 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract The results of these tests are to be immediately available to the Architect at any time during concreting, and shall be submitted to the Architect within 3 days of completion of any concreting. Concrete temperature shall comply with the requirements of Clause 4.8.1 to within an accuracy of 1ºC. 5.5 Assessment of In0situ Compressive Strength Carry out assessment of in-situ compressive strength as scheduled below: 5.6 NonDestructive Testing Carry out non-destructive testing to the concrete structure as scheduled below: Element Location Number of tests Refer to testing requirement specified in drawings. Type of test Location Number of tests Refer to testing requirement specified in drawings. Table 9 C03-020 PSD for Reinforcement Clause Description 5.3 Material testing Carry out material testing in accordance with Table 1 and latest edition of BCA/IES/ACES Guide Book for Site Supervision Plan, whichever more stringent. Table 10 C03-040 PSD for Designed Joints Clause Description 1.4.2 Provision of Spare Material Provide no additional material Page 19 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/21 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Table 11 C03-050 PSD for Water-resistance to Concrete Structure Clause Description 2.1.1 Durability The waterproofing system is required to achieve a minimum design life of 30 years against leakage and any failure of waterproofing, water-tightness or any defects. 2.1.2 Basement Grade The basement grade designation for various areas of the project is as follows: Basement Location Usage Grade Below ground tanks, pits, ICs, etc. Lift pits Grade 2 Fuel tanks, detention tanks, ICs/sumps Grade 2 Carpark Grade 2 Plantrooms against retaining wall at B2 Grade 3 Plantroom Grade 2 UPL Grade 3 Basement Refer to Architect’s drawings and specifications for waterproofing details for other areas (toilets, roofs, etc). Adopt the following protection system: Location Protection System Lift pits/Sumps/IC etc. • External bonded waterproofing membrane on concrete base slabs and walls; and • waterproofing admixtures on concrete base slabs and walls. Interface between basement wall and slab • Water stop and re-injectable grout tubes at slab and wall interface • Waterproofing admixture for slab at interface Lowest basement slab • Waterproofing admixture in concrete base slab with drainage cavity. Basement wall • Skin wall with water stop and re-injectable grout tubes at slab and wall interface • Water stop at skin wall construction joint • Waterproofing admixture for skin wall • Drainage cavity • External bonded waterproofing membrane on concrete base slabs and walls • Water stops and re-injectable grout tubes at slab/wall interfaces and construction joints. • Waterproofing admixture in concrete base slab with drainage cavity UPL wall and slab 3.4 Waterproofing Admixtures The waterproofing admixture shall be hydrophilic crystalline admixtures. The waterproofing admixtures shall not affect the strength, workability, retardation, setting time and other properties of the concrete. The trial mix concrete shall have a corrected 30 minute water absorption of not greater than 1.0% (one percent) as measured by BS 1881:Part 122:1983 (or except Page 20 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/22 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract that the age at test shall be 7 days. The trial mix concrete shall have an average water permeability coefficient when tested at 28 days of an average water penetration depth not greater than 10mm as measured by DIN 1048: Part 5:1991. The admixture used must be shown by an independent authority to have had no reduction in performance after field exposure for a minimum of 15 years. The contractor shall carry out absorption and permeability testing by accredited laboratory. The SO reserves the right to take cores from the structure to confirm compliance. Waterproofing admixtures concrete shall be adopted/applied to the following areas and as shown in the drawings:a. Entire concrete section of concrete elements in contact with soil/ground water such as raft, ground slabs/beams, below ground tanks, lift pits, etc. b. Concrete waterproofing admixture shall extend to the sidewalls of sumps and similar depressions of the base slab so as to form a continuous watertight surface. The surfaces of such concrete shall be power floated whilst the concrete is still green in accordance with the manufacturer’s recommendations, and areas such as kickers shall be subject to additional vibration and compaction. c. For roof slab system Table 12 C03-060 PSD for Precast Concrete Works Clause Description 1.4.1.1 Develop the Design of Precast Concrete Elements Cover the following items when developing the design: 1.4.1.3 Temporary Supports Item Description 1. Structural design of the elements in the permanent building structure. 2. Design for prestress covering both temporary and permanent states. 3. Design for demoulding stresses. Yes 4. Design for Lifting, handling, transporting and storage. Yes 5. Design for all connections and joints. Yes 6. Design for waterproofing of the permanent structure and joints. Yes Applicable All temporary works including protection to precast units, temporary supports and restraints, storage, lifting hooks/ frames etc. are to be designed, supplied and installed by the Contractor. The Contractor is required to submit his proposals including method statements and supporting calculations for the approval by SO. Lifting positions, holes and points of attachment of lifting slings to precast units to be submitted for Engineer’s approval. Lifting sequence shall be coordinated with the Contractor and the Construction Manager. This should follow the construction sequence of the superstructure as specified by the Construction Manager. All additional reinforcements required for temporary lifting and propping shall be designed, supplied and installed by the Contractor. No time and Page 21 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/23 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract cost will be entertained due to lifting, bracing and propping at temporary stage. 1.4.3 Maintenance/ Replacement Manual Prepare and submit a maintenance/replacement manual for components and connections as listed below: Item Description Applicable 1. Joint Sealant system Yes 2. Structural steel connection and fasteners Yes 3. Sliding joint membrane / pad Yes Table 13 C03-070 PSD for Prestressed Concrete Works Clause Description 2.1 Contractor’s Submission and Proposals The design shown in the drawings are based on a notional prestressing system. The contractor is to engage his own PE to verify and design the final prestressing system in conjunction with the prestressing specialist and submit to Engineer for approval. 2.1.1 Design Intent No items. 2.1.2 Verification on Serviceability In developing the design for the prestressing works, take into consideration of serviceability requirements in the relevant codes and standards. 4.8.4.3 Bleeding Test Inclined tube test is required additionally. 4.8.5 Grouting Trials Grouting trials is required. 5.3 Tests Testing type and quantity shall not be less than the testing requirement in the latest edition of BCA/IES/ACES Guide Book for Site Supervision Plan. 5.3.5.1 Sampling Duct friction test is required for the project. Table 14 C03-080 PSD for Concrete Repairs Clause Description 1.4.4 Warranty Warrant the Works for a minimum period of 5 years against all defects from the date of completion. 2.1 Contractor Proposal (b) Minimum characteristic strength of the repair material shall be at least the same as the characteristic strength of the element being repaired, but not less than 45 MPa. Page 22 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/24 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Table 15 C04-010 PSD for Bored Piling γs,t Less than 25mm 2.00 1.00 2.00 Less than 15mm 2.00 1.00 2.00 1.00 γt 1.70 1.00 2.00 1.00 γb 1.40 1.00 1.60 1.00 γs R4 R1 R4 1.55 1.55 1.00 R1/R4 Partial Resistance Factor R1 Tension Resistance Compression resistance 1.35 1.55 Refer to drawing (Pile Schedule) Refer to drawing Model Factor Permitted Settlement at 2 x SWL (mm) Any of the piles, when under static or dynamic load test, is to satisfy the performance criteria as set out below: Permitted Settlement at 1.5 x SWL (mm) 2.2 Performance Criteria for Serviceability Limit State Specified Working Load (SWL) (kN) Description Pile Reference Clause Design Assumptions: • The design life of all permanent foundations is 100 years. • Preliminary test pile shall be carried out to verify the design parameters prior to working piles installation. • All piles to be base grouted. 3.2 Drilling Fluid The use of support fluid is required for all piles to ensure stability of the bore and cleanliness of the base of the pile. 3.2.1 General Requirement The drilling fluid shall be tested as per the specification at regular intervals and in particular the following key construction stages: a. When fluid is first introduced into the bore b. Immediately upon base cleaning c. Immediately before concreting Page 23 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/25 Singapore Land Group Ltd. 4.5 Cleanliness of Pile Bases 4.9 Grouting of Piles Clifford Centre Redevelopment PSD Specification for Main Contract The assessment of the base hardness is made using a tape measure with a weighted end. This weight needs to be sufficiently heavy to allow a base assessment to be made when the bore is filled with bentonite but not so heavy that it cannot be easily moved up and down during the checking procedure. A standard weight has been developed to meet these needs and weighs approximately 1kg. It is made up of a short section of T25 reinforcement welded to a square section of 10mm steel plate approximately 100mm×100mm of 20mm steel plate to form a flat base and weighing approximately 1kg. It is recommended that the pile be dipped in five locations; four around the perimeter of the pile (North, South, East and West) and one in the centre. It is important that the pile base is re-checked at the same locations to make a reasonable assessment of any rises in the base or variations in the hardness. The base quality is graded on a scale of 1 to 5 as described in the table below depending on the contact made when striking the base. Grades 4 and 5 are unacceptable and the contractor is required re-clean the pile base to remove any sludge or loose soil. Pile base hardness grading system Grade Base Quality Observation by Arup engineer with weighted measuring tape 1 Hard Sharp impact 2 Firm Sudden impact felt but some damping of impact vibrations 3 OK Distinct base detected with slight embedding of weight into soil 4 Soft Significant embedding of weight detected making definitive base difficult to detect 5 Very Soft Weight sinks slowly into soil making definitive base very difficult to detect Base grouting is required for the preliminary test pile, working load test pile, and all building piles (except for Secant bored pile walls). Contractor is to propose the base grouting methodology for the engineer’s approval. The base of grout tube/s shall be positioned 50mm above from the base of the cage with a tolerance of +25/-0m. Grouting shall commence a minimum of 2 days and a maximum of 8 weeks after casting of the pile. In addition, the minimum time between cracking the last grout tube and grouting of the first grout tube of a particular pile is 3 hours. Cracking of the grout tube/s in preparation for the subsequent base grouting operations shall occur between 2 days and 2 weeks after completion of pile construction (as defined by the end of concreting). The grouting system (pump, hoses, couplings, and grout tubes etc) shall be capable of supplying 70 bars of pressure and both the volume and pressure shall be read and recorded electronically in real time throughout the grouting process. Prior to commencing the base grouting operation, the contractor shall demonstrate the grouting system’s compliance. The contractor shall calibrate the delivery system by measuring the stiffness of the hoses, couplings, and grout tubes etc. This shall be taken into account when assessing the volume of grout injected. Page 24 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/26 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract The pile head and pile base uplift shall be measured during base grouting. The uplift of the pile shall be measured by two independent methods during base grouting. These shall be an LVDT (including data logging/recording) and a dial gauge. Details of the measurement system shall be submitted with the tender and shall be subject to the acceptance of the engineer. The pile uplift shall also be measured at an elevation 0.5m above the pile base using 2 retrievable extensometers installed within tubes cast into each pile. The proposed extensometer system shall be submitted for approval by the engineer. Fibreglass extensometers cast into the pile shall not be accepted. The level of the reference beam shall be checked by precise level, both before and after the base grouting operation. The supports of the reference beam shall be at least 3 pile diameters apart. The following base grouting criteria shall be satisfied: 1. At completion of base grouting, the pile head uplift shall be not less than 0.2mm and the pile base uplift not less than 0.3mm. The uplift at the pile head or base shall not exceed 2.0mm. 2. A minimum pressure of 30 bars on each grouting tube. The residual grout pressure of 15 bars to be held at least 2 minutes on each grout tube. 3. A minimum grout volume of 25 litres per grout tube Pressure measurements for criteria (2) will only be accepted if a minimum volume of 5 litres of grout (after allowing for the compliance of the delivery system) has been injected. If any of these criteria is not met during the first grouting phase then the pile shall be re-grouted, up to a limit of three grouting operations including the initial operation. A minimum of 3 hours must be allowed between each round of grouting. If criteria (2) and (3) are met as a result of any secondary or tertiary grouting and minimum uplift measurements of not less than 0.1mm at the pile head and 0.15mm at the pile base are achieved the base grouting will be deemed acceptable. The grout mix shall be submitted to the engineer 14 days prior to the start of grouting for approval, satisfying a minimum cube strength class of 25 N/mm2. Details of quality control on the grout shall include viscosity measurement (March Cone), density measurement and cubes for strength testing. The quality control testing requirements for the grout are given in the table below. Parameter 1. Test Criteria Cement Gout – Base Grouting UCS Three 100mm cubes per pile, for testing, 1 at 7 days and 2 at 28 days Nominal 25N/mm2 at 28 days Bleed One sample per pile 5% (max) Specific Gravity One sample per pile Target (1.84) + 5% March Cone One sample per pile Target (45 sec.) + 5% Coring of the pile/grout interface shall be performed in all preliminary and working load test piles. Coring is to extend a minimum of 1.5m below the Page 25 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/27 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract toe of the pile. Unconfined compressive strength tests to be performed on grout samples retrieved. Grout to have a UCS >1.2MPa. 5.0 Verification and Submission In addition to the items listed in the NPQS, the Piling Contractor shall submit the following with their Method Statement for completion of the works: a. ‘Emergency recovery plan’ (detailing proposed actions in the event of problems/ delays to pile construction, for example: i. Obstructions are not able to be penetrated by the piling rig ii. Breakdown of pile during pile construction iii. Concrete supply not available after completion of the bore or if supply is interrupted during pour iv. Other scenarios the contractor may reasonably anticipate b. Details of the action that would be taken to stabilise an excavation if for any reason the completion to the excavation or the concreting is delayed or prevented. c. Pro-forma pile record sheet. d. Details of installation of monitoring equipment such as inclinometer tubes for example CV for key staff including project manager and site engineers. e. CV for key staff including Project manager and Site Engineers. During the works the Contractor in addition to items detailed in the iNPQS, shall keep records of the following: a. Measured pile verticality of each pile b. Site concrete testing: slump/ flow tests and cube tests: establish a range of target values to be agreed by the engineer before the commencement of contract piling. Piling records shall be submitted to the SO within 24 hours of the completion of concreting of each pile. Table 16 C04-030 PSD for Pile Testing Clause Description 1.2 Related Section In addition to those sections listed in the Specifications document, read this work section in conjunction with the relevant requirements of other work sections as follows: • C1-20 Site Investigation • C4-10 Bored Piling Works C4-10 PSD Bored Piling Works 3.3.1 Equipment for Applying Load Contractor shall provide reaction loads sufficient to complete the specified load schedule, i.e. 1.2 times the maximum test load. 4.2.5 Instrumentation for Preliminary Piles Piles shall be instrumented as per Test Pile Details drawing All instrumentation shall be appropriate for the normal range of movement/strain/vibration reasonably associated with the scheduled test loads. Measurements shall be taken electronically at the following times: 1. During fixing operation whilst the reinforcement cage is up in the air 2. After lowering the reinforcement cage prior to concreting 3. After concreting 4. Prior to application of the test load Page 26 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/28 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract 5. 4.1.1 Location of Test Piles During the load test Preliminary Test Piles • Compression test piles shall be located within the footprint of the building and no less than 3.5 times diameter (centre to centre spacing) from the proposed permanent piles. • Each preliminary test pile shall be positioned close by to one of the Site Investigation boreholes (within 3m). • Test Pile Layout Drawing indicates suggested locations for the test. Working Load Test Piles • Working Load Test piles to be proposed by the contractor and agreed with the SO. 4.2.6 Cut Off Level Cut Off Level shall be as per Pile Schedule Drawings. Extend the pile shaft above ground level such that gauges and other apparatus to be used in testing will not be damaged by water or falling debris. Where the pile shaft is extended above the Cut Off level of a working pile in soil which would influence the load bearing capacity of the pile install de-bonding. 5.1 General Submission In addition to the items in C4-30, the contractor shall provide the following: • At least 2 weeks prior to the preliminary test pile construction, the contractor shall provide their method statement for installation of the test pile and testing procedure to the SO for their review and comment. • The Contractor shall maintain detailed soil logs (recorded by an appropriately experienced geologist with a minimum of 5 years relevant experience) throughout the excavation of the test piles. These shall be submitted as per the C4-30 Section 5.2.1. Results shall also be submitted in Excel spreadsheet format. • The following information shall also be presented: • Total load settlement plot at pile head; • Total load vs time plot at pile head; • Load vs settlement and time plot at each strain gauge level. As reference the total load on the pile shall be recorded on the plot; • Difference in total and shaft load plotted against deflection. Table 17 C05-010 PSD for Structural Steelworks Clause Description 1.1 Scope Specific Requirement on Bolted Steel-Plate or Glass-Reinforced Plastic (GRP) or Fiber-Reinforced Plastic (FRP) Tanks. All large (2m high or more) bolted steel-plate or GRP or FRP water storage tanks and their base structures shall be the subject of an independent firstprinciples design review from a qualified and competent Professional Engineer (Civil). Tanks fabrication and installation inspection and test plans shall be checked by a qualified and competent Professional Engineer (Civil). Materials must be verified as conforming prior to commencement of construction. Construction inspections (including hold point inspections) Page 27 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/29 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract must be undertaken by a qualified and competent Professional Engineer (Civil). Stee material used shall comply to specification C05-010. The record set must be reviewed by a qualified and competent Professional Engineer (Civil) prior to filling tank with water. 1.3.1 Standards and Codes Alternative steel material subject to Engineer’s Approval. 1.4.1.1 Connection Design In the event the Steelwork Contractor submits an alternative design, the Steelwork Contractor shall engage a PE(Civil) to develop the alternative design based on structural design drawings, subject to SO’s and Engineer’s acceptance. 1.4.3.1 Steel Fabricators Engage steel fabricators who possess suitable accreditation category as shown in table below for the fabrication and erection works. The minimum required grade of steel fabricator is Category S4. Accreditation category Criteria of structural steel works Category S1 1. Building, industrial plant or portal structures of over 30m in height, or 2. Large span portal, bridges or truss work of over 30m Category S2 1. Building, industrial plant or portal structures of up to 30m in height, or 2. Medium span portal, bridges or truss work of up to 30m Category S3 1. Building, industrial plant or portal structures of up to 20m in height, or 2. Short span portal, bridges or truss work of up to 20m Category S4 Structural steel structures of up to 10m in height or span Page 28 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/30 Singapore Land Group Ltd. 1.4.6 Independent Inspection and Testing Agency Clifford Centre Redevelopment PSD Specification for Main Contract Appointment of an Independent Inspection and Testing Agency is required to carry out the following scope of service: S/N Description Tick where applicable 1. Review the quality manuals, inspection & test plans Yes 2. Review fabrication and erection procedures Yes 3. Review of welding procedure specification, procedure qualification records, welder and welding operator qualification records. Yes 4. Pre-inspection meeting and audit of fabricator facilities/plants Yes 5. Review of material test certificates/records, verify or inspect materials and witness pre-treatment processes, if any Yes 6. Witness cutting/edge joint preparations, verify joint geometry and inspect fit-up condition Yes 7. Verify that welding processes are carried out in accordance with the approved welding procedures, codes/standards and relevant documents Yes 8. Perform visual inspection and verify dimensional records Yes 9. Select weld joints for testing & witness nondestructive testing and assess all results Yes 10. Witness blasting & galvanising processes Yes 11. Inspect painting and galvanising works Yes 12. Identify & verify completed structural members and witness the handling of these members onto lorry/truck for delivery to site Yes 13. Inspect delivered structural members for damage due to handling and transportation Yes 14. Inspect the assembly of structural members at erection site prior to welding Yes 15. Verify all welding procedure and welder qualification records at site Yes 16. Witness procedure trial of stud welding process Yes 17. Inspect all welds & bolt tightening Yes 18. Select weld for testing and witness site NDT Yes 19 Inspect all remaining site painting and witness repairing of all protective treatment works Yes 20. Witness fireproofing mock-up test as well as laboratory tests No 21. Witness and inspect the application of fireproofing works Yes 22. Final inspection of all structural members Yes Page 29 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/31 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract 23. 2.3 Execution Class Review all documents and records including but not limited to the following: - Dimensional - Procedures - Testing The structure shall be constructed in accordance with execution class 3. The following parts of the structure are to be constructed in accordance with execution Class 4: • Transfer trusses at Level 6 • King posts 4.1.2 Marking Hard stamping shall be used in all areas. 4.3.1 Cutting Thermal cutting is not permitted at the following areas: • 4.3.2 Holing N.A Thermal holing or full size hole punching are not permitted at the following areas: • 5.4 Tests for Structural Steel Members and Bolts Yes N.A Testing type and quantity shall not be less than the testing requirement in the latest edition of BCA/IES/ACES Guide Book for Site Supervision Plan. Page 30 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/32 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Table 18 C05-020 PSD for Protective Works for Structural Steelwork Clause Description 1.4.4 Independent Inspection and Testing Agency Appointment of an Independent Inspection and Testing Agency is required to carry out the following scope of service: S/N Description Indicate where applicable 1. Review proposal for the protective system Yes 2. Review quality control plans Yes 3. Inspect the application of: Yes 4. • Corrosion protection • Fire protection Conduct non-destructive testing Yes 1.4.7 Warranty Warrant the Works (Structural Steel Framing and Protection Works for Steel – including primary, secondary and tertiary steelwork connections, joints and stiffeners) in accordance with contract conditions for a minimum period of 10 years against all defects from the date of completion. 2.1.1 Durability Account for the required durability range of High (more than 15 years) in accordance with BS EN ISO 12944 for the protective system. 2.1.2.1 Environmental Exposure Class Account for the environmental exposure class for the project as follows: Location Member Environmental Exposure Class Remarks All internal steel elements All C3 Not exposed to weather, not near swimming pool/water feature All steel elements exposed to weather All C4 Note: Environmental exposure classification is categorised to six atmospheric environmental categories and three categories for water and soil in accordance with BS EN ISO 12944-2 Clause 5. 2.1.3.1 Period of Fire Resistance 2.1.5 Architectural Finishes Account for the level of fire protection required for the various members as follows: Location Member Fire Rating (Hour) All Structural steel As per Architect’s specifications Remarks Account for the required architectural finish effects at the various locations: Location Type of finish All architecturally exposed steel To Architects specifications Particular requirements (thickness etc.) Proprietary product specified (if any) Page 31 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/33 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract 3.2.2 Prefabrication Coating Provision of prefabrication coating is required. 3.4 Sealants Contractor to propose for SO’s acceptance. 3.5 Fireproofing Materials All fireproofing materials for steel members at various locations to be compliant with Architect’s specifications. 3.5.1 Intumescent Paints Contractor to propose for SO’s acceptance. 3.5.2.3 Proprietary Products Contractor to propose for SO’s acceptance. 3.5.3 Dry Lining Contractor to propose for SO’s acceptance. 5.2.1 Reference Areas for Paint Protection Coating The required number of reference areas is: 10 Note: Numbers in relation to the size of structure (painted area) are given in BS EN ISO 12944-7. 5.3.1 Schedule of Tests Carry out the following tests: Item Description Reference Clause(s) Applicable 1. Test for Dry Film Thickness 5.3.2.2 Yes 2. Test for Adhesion 5.3.2.3 Yes 3. Test for Porosity/Pinholes 5.3.2.4 Yes 4. Test for Dry Density and Thickness 5.3.4.1 No 5. Test for Air Erosion 5.3.4.2 No 6. Test for Deflection 5.3.4.3 No 7 Test for Compressive Strength 5.3.4.4 No 8 Test for Bond Impact 5.3.4.5 No 9 Test for Cohesion/Adhesion 5.3.4.6 No 10 Test for Contribution to Corrosion 5.3.4.7 No 11 Salt Spray Testing 5.3.4.8 No Table 19 C07-030 PSD for Road Ancillaries Clause Description 1.4.3 Provide Spare Material Supply the following spare materials and store in an area agreed with the SO: Item Quantity Road Marking Paint 5% Vehicle Guard Rails 5% Retro-reflective sign sheeting 5% Page 32 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/34 Singapore Land Group Ltd. 1.4.7.2 Other Road Ancillary Items Clifford Centre Redevelopment PSD Specification for Main Contract Warrant the road marking paint and vehicle guard rails for a minimum period as specified in LTA’s Materials and Workmanship Specification, against all defects from the date of completion. Table 20 C08-020 Mass Engineered Timber Clause Description 1.1 Scope Further requirements for MET components in Amenity Boxes to be read as per attachment “Amenity Boxes Performance Criteria”. 1.4.1 Contractor’s Submissions and Proposals Contractor’s submissions and proposals shall be endorsed by Singapore Registered PE and submitted for SO’s acceptance and onward submission to BCA. Some indicative details on the connection intention are shared as below. All connections / fixings shall align with the required architectural intention, e.g. concealed fixings, etc. i) Amenity Boxes Diagonal Truss Details ii) Amenity Boxes Roof Connection Details Page 33 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/35 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract iii) Amenity Boxes Roof (Plan View) Connection Details iv) Amenity Boxes Roof to Corewall Connection Details Page 34 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/36 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract v) Amenity Boxes Diagrid Connection Details Reference picture: Page 35 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/37 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Appendix A G01-010-01 PSD for Buildable Design ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/38 Singapore Land Group Ltd. A1 Clifford Centre Redevelopment PSD Specification for Main Contract General Read with the General Requirement section, and all other contract documents. A1.1 Scope This section covers requirements for the contractor’s design, materials and construction methods adopted in construction works to achieve the required Buildability Design Scores. A1.2 Standards and References A1.2.1 Standards Unless otherwise agreed by the QP, ensure all of the Works comply with the relevant requirements of the Standards and Codes listed below or referenced in the body of the Specification. All Standards and Codes quoted are the current version unless specific year references are noted. Singapore Standards Code of Practice on Buildability, 2019 Edition A2 Buildable Design Requirement Minimum Buildable Design Score is as follow: • Superstructure 90 points • Basement 70 points A3 Buildable Features A3.1 Mandatory Requirements Materials/construction methods listed in the tables below have to be used/adopted in construction in order to achieve the Minimum Buildable Design Scores. Page A1 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/39 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Mandatory Requirements Basement Superstructure Floor mesh - in areas 80% 80% Beam cage / Continuous stirrup - in nos. (only accept cages from factory) NA NA Column cage / Continuous stirrup - in nos. 80% 80% Wall mesh - in nos. NA NA High strength concrete (>= Grade 70, at least 5%) At least 5% NA Self-compacting concrete (>= 30%) At least 30% NA Diaphragm wall (>= 65% length of basement permanent retaining wall) NA NA Standard precast staircase of riser height of 150mm or 175mm & tread width of 275mm or 300mm for typical storeys - in nos. (or alternative system recognised and approved by BCA) 90% 90% The contractor shall be responsible to ensure that any value engineering or alternative design proposals comply with the Buildability Score requirements. Page A2 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/40 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Appendix B C03-010-01 PSD for Green Concrete ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/41 Singapore Land Group Ltd. B1 Clifford Centre Redevelopment PSD Specification for Main Contract General Read with the General Requirements section, contract preliminaries and all other contract conditions. B1.1 Scope This document specifies specific requirements for green concrete which are to be read in conjunction with C03-010 “Concrete Construction Generally”. All modification and additions noted in this document take precedence over clauses noted in C03-010. Clause references in this document tie with those in C03-010 with the same clause title. B1.2 Related Sections Read this work section in conjunction with C03-010 “Concrete Construction Generally”. The more stringent requirement shall govern. Refer to general notes drawing for the green cement and recycle aggregates requirements. B1.3 Standard and Technical Reference B1.3.1 Standard Unless otherwise approved by the QP, ensure all of the Works comply with the relevant requirements of the Standards and Codes listed below or referenced in the body of the Specification. Alternative Standards and Codes may be proposed for approval by the QP, provided it can be demonstrated that the alternative Standards and Codes comply with the requirements of the standards specified. All Standards and Codes quoted are the current version, unless specific year references are noted. The following standards apply in addition to Section 1.3.1 of C03-010 “Concrete Construction Generally”. Other Standards SS EN 12620 Specification for aggregates for concrete PD 6682-1 Aggregates. Aggregates for concrete. Guidance on the use of BS EN 12620 BS EN 450-1 + A1 Fly ash for concrete. Definition, specifications and conformity criteria SS EN 15167 Ground granulated blast furnace slag for use in concrete, mortar and grout Part 1 Definitions, specifications and conformity criteria Part 2 Conformity evaluation In the event that the standards or codes are revised or superseded, refer to the latest edition or the appropriate substitution for the relevant subjects. In case of conflicting requirements between the codes, refer to the QP for resolution, the QP’s decision shall be final. Page B1 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/42 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract B1.3.2 Technical Reference Refer to the following technical for guidance where appropriate when carrying out the works: a. Sustainable Construction: A Guide on the Use of Recycled Materials (Building & Construction Authority Singapore, 2008) B1.4 Trade Preliminaries Submit a list of project references in relation to experience in supply of green concrete. Page B2 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/43 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract B2 Materials B2.1 Cement All combined cement is to meet the requirements set out in SS 544 Part 2 Annex A. B2.1.1 Portland Cement Portland Cement shall comply to Class 42.5 as specified in SS EN 197-1. Any proposal by the Contractor to partially substitute any cementitious materials, such as fly ash, ground granulated blast furnace slag or silica fume, for Portland cement shall be submitted for SO’s approval. The Contractor shall not change the cement brand or source of any approved cementitious material until he has obtained approval in writing from the SO prior to the change. B2.1.2 Pulverized Fuel Ash (PFA) PFA shall conform to SS EN 197-1, Clause 5.2.4 (Fly ashes). PFA shall only be used with ordinary Portland cement to SS EN 197-1. Mixtures of PFA with any blended cement will not be permitted. All PFA shall come from the same single, proprietary source. B2.1.3 Ground Granulated Blast Furnace Slag (GGBS) Comply with the requirements of SS EN 197-1, Clause 5.2.2 (Granulated blast furnace slag). GGBS shall only be used with ordinary Portland cement to SS EN 197-1. Mixtures of GGBS with any blended cement will not be permitted. All GGBS shall come from the same single, proprietary source. B2.2 Aggregates B2.2.1 Fine Aggregates Comply with SS EN 12620 and not to be alkali reactive. Marine aggregates shall not be used. Washed copper slag (WCS) (Mohs hardness >6) shall be used to partially replace sand as fine aggregates in concrete with the following quality control acceptance criteria: • No visible foreign material like glass, metal wires, barnacles / shells etc. This can be achieved by dry sieving through large sieve shaker to remove the larger articles. Sieve aperture size should not be greater than 2.0 mm. • Water soluble chlorides shall not exceed 0.01% m/m in accordance with SS 73-17, tested weekly by third party accredited laboratories. • Water soluble sulphates shall not exceed 0.03% m/m in accordance with SS 73-18, tested monthly by third party accredited laboratories. • Recycled aggregate suppliers are accredited by BCA. Page B3 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/44 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract • Proof that copper slag recycling companies has submitted regular Toxicity Characteristic Leaching Procedure (TCLP) to National Environment Agency (NEA) to proof that copper slag has been processed properly. The TCLP limits are in compliance to international recognised standard for leachate test. • The supplier of concrete has informed BCA on the location of batching plant and provide records of building projects supplied with concrete using copper slag. • Consent letter from SO on supplying concrete with copper slag. B2.2.2 Coarse Aggregates Coarse aggregate shall comply with SS EN 12620 and SS 544. Aggregates shall not be alkali reactive. Marine aggregates shall not be used. B2.2.3 Sampling & Testing Sampling and testing of all aggregates shall be carried out in accordance with the following requirements: • Max masonry/ lightweight material/ asphalt/ foreign material content complying to SS 544 Part 2 Cl 4.3 Table 2. • Max fines content complying to BS 812-103.1. • Max acid-soluble sulphate (SO3) content complying to SS 73-18. • Max chloride content complying to SS 73-17. • Alkali Silica Reaction (ASR) complying to ASTM C295 and C1260. B2.2.4 Grading Grading tests shall be carried out in accordance with SS EN 12620 before the start of any production and at weekly intervals when concrete is being produced. The SP reserves the right to draw samples of aggregates from any stockpile at any time for testing and the Contractor shall deliver the samples at his cost to any approved accredited laboratory. Aggregates, whose grading, are found to fall outside the approved zone shall be rejected. B2.3 Water Water shall be clean and free from harmful matter. If taken from a source other than the Public Utilities Board, water shall be tested in accordance with BS EN 1008 and shall be subject to the SO’s approval. B2.4 Admixture To comply with the requirements of SS EN 206-1 and SS EN 934-2. Acceptance of admixtures will only be made upon provision of satisfactory information relating to name, type, dosage and justification for use. Page B4 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/45 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract B3 Design Mix B3.1 General Refer to C3-10 for required strength, durability and additional requirements. The Contractor shall submit the appropriate information as described in SS EN 206-1 and SS 544 for the SO's approval before any concrete is supplied. B3.2 Concrete Constituents For structural concrete, PFA content shall be not more than 55% by mass of the specified minimum cementitious content, and GGBS content shall content shall be not more than 85% by mass of the specified minimum cementitious content. For structural concrete, WCS can replace up to 10% by mass of sand. For nonstructural concrete, which includes slabs on grade (non-suspended slabs), pavements, ancillary works etc, WCS can replace up to 100% by mass of sand. WCS for use in concrete shall be obtained from BCA approved source. WCS for use in concrete is to be obtained from BCA approved source, which are precleared by NEA Eco-concrete containing washed copper slag should comply with the requirement of SS EN 206-1 and SS544, for non-structural elements in buildings or other building elements not subject to approval of plans by BCA. B3.3 Testing Requirement Trial mixes of three separate batches of concrete shall be made using approved materials and produced under full-scale production conditions. Sampling and testing shall be in accordance with BS EN 12350 and BS EN 12390. The workability of one trial batch shall be determined and six cubes made from the trial. Three each shall be tested at an age of 7 and 28 days respectively. The average cylinder strength of the cubes tested at 28 days shall exceed the specified characteristic strength by at least 6N/mm2. During production, the SO may require additional trial mixes to be made before a substantial change is made in the materials or in the proportions of the materials to be used. They need not be carried out when adjustments are made to the mix proportions in accordance with SS EN 206-1 and SS 544. Page B5 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/46 Singapore Land Group Ltd. B4 Clifford Centre Redevelopment PSD Specification for Main Contract Requirement for Fresh Concrete The workability of the fresh concrete shall be such that the concrete is suitable for the conditions of handling, placing and compaction. B5 Requirement for Hardened Concrete The grade of concrete to be used in the Works shall be as defined by the characteristic cylinder strength in N/mm2 at 28 days as determined from test cubes. The total chloride content of the concrete mix arising from the aggregate together with that from any admixtures and any other source shall not in any circumstances exceed the limits as specified in C3-10. When required by SO, the Contractor shall carry out tests to demonstrate that these limits are not exceeded. When directed by the SO, tests in accordance with BS 1881: Part 124 shall be made on hardened concrete to determine the total sulphate content as SO3 of any mix. The concrete shall be rejected if the sulphate content exceeds 4% by weight of cement in the mix. Page B6 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/47 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract B6 Production of Concrete B6.1 General Separate storage facilities with adequate provision for drainage shall be provided for each different size of aggregates used. Aggregates shall be handled and stored so as to minimise segregation and contamination. All aggregate deliveries shall be inspected and the grading and silt content of each size of aggregate from each pit, quarry or other source of supply shall be determined at least once weekly. The quantity of cement, the quantity of fine aggregate and the quantities of the various sizes of coarse aggregate shall be measured by weight. A separate weighing device shall be provided for weighing the cement. The amount of water shall be measured, by volume or by weight. Any solid admixtures to be added shall be measured by weight but liquid or paste admixtures may be measured by volume or weight. The batch weights of aggregate shall be adjusted to allow for a moisture content typical of the aggregates being used. The accuracy of the measuring equipment shall be within ± 3% of the quantity of cement, water or total aggregates being measured and within ±5% of the quantity of any admixture being used. All measuring equipment shall be maintained in a clean, serviceable condition. The mixing time shall be not less than that used by the manufacturer in assessing the mixer performance. Any adjustments of mix proportions made in order to minimise the variability of strength and to approach more closely the target mean strength shall be subjected to the approval of SO. Such adjustments are regarded as part of the proper control of production but the specified limits of minimum cement content and maximum water/cement ratio shall be maintained. Such adjustments to mix proportions shall not be taken to imply any reduction in the target mean strength. B6.2 Ready Mixed Concrete Ready mixed concrete shall be carried in purpose made agitators, operating continuously, or truck mixers. All concrete delivered to site shall be accompanied by a delivery docket, which can be traced to the relevant individual batching records, clearly stating the time batched, grade of concrete, specified slump, cement content and special features such as additives used. When truck mixed concrete is used, under no circumstances shall water be added in transit. Page B7 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/48 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract B7 Verification and Submissions B7.1 General All sampling and testing of fresh and of hardened concrete shall be carried out in accordance with the relevant parts of SS78, BS EN 12350 and BS EN 12390. The characteristic strength of concrete is the 28 days cylinder strength below which not more than 5% of the test results may be expected to fall. Compliance with the specified characteristic cylinder strength shall be judged by tests made on cubes at an age of 28 days unless there is evidence, approved by SO, that a particular testing regime is capable of predicting the strength at 28 days of concrete tested at an earlier age. In cases where Portland blast furnace cement or ground granulated blast furnace slag is used as a cement substitute, compliance with the specified characteristic strength may be judged by tests made on cubes at a later age than 28 days, where there are suitable evidence approved by SO. B7.2 Project Reference Concrete suppliers shall furnish a list of project reference where concrete with copper slag was supplied to. These suppliers must be listed in BCA’s list of Eco Concrete Ready Mix Concrete Suppliers. B7.3 Compliance Testing Trial mixes of three separate batches of concrete shall be made using approved materials and produced under full-scale production conditions. Sampling and testing shall be in accordance with BS EN 12350 and BS EN 12390 or/and as per requirement by BCA. The workability of one trial batch shall be determined and six cubes made from the trial. Three each shall be tested at an age of 7 and 28 days respectively. The average cylinder strength of the cubes tested at 28 days shall exceed the specified characteristic strength by at least 6N/mm2. During production, the SO may require additional trial mixes to be made before a substantial change is made in the materials or in the proportions of the materials to be used. They need not be carried out when adjustments are made to the mix proportions in accordance with SS EN 206-1 and SS 544. Supply three copies of all test results to the SO as soon as they are available. Page B8 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/49 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Appendix C C03-010-02 PSD for High Strength Concrete ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/50 Singapore Land Group Ltd. C1 Clifford Centre Redevelopment PSD Specification for Main Contract General Read with the General Requirements section, contract preliminaries and all other contract conditions. C1.1 Scope This document specifies specific requirements for high strength concrete, namely concrete with compressive strength greater than C50/60 MPa, which are to be read in conjunction with C03-010 “Concrete Construction Generally”, as well as “Section 3 Guide to Ensure Product Conformity and Quality for High Strength Concrete” and “Section 4 Guideline on the Submission to BCA for the Use of High Strength Concrete” of “BC 2 Design Guide of High Strength Concrete to Singapore Standard CP 65”. In case of conflicting requirements, the more onerous requirements shall take precedence. Clause references in this document tie with those in Section 4a with the same clause title. C1.2 Related Sections Read this work section in conjunction with C03-010 “Concrete Construction Generally”. C1.3 Standard and Technical Reference C1.3.1 Standard Unless otherwise approved by the QP, ensure all of the Works comply with the relevant requirements of the Standards and Codes listed below or referenced in the body of the Specification. Alternative Standards and Codes may be proposed for approval by the QP, provided it can be demonstrated that the alternative Standards and Codes comply with the requirements of the standards specified. All Standards and Codes quoted are the current version, unless specific year references are noted. The following standards apply in addition to Section 1.3.1 of C3-10 “Concrete Construction Generally”. Other Standards BC 2 Design Guide of High Strength Concrete to Singapore Standard CP 65 In the event that the standards or codes are revised or superseded, refer to the latest edition or the appropriate substitution for the relevant subjects. In case of conflicting requirements between the codes, refer to the QP for resolution, the QP’s decision shall be final. Page C1 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/51 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract C1.4 Trade Preliminaries C1.4.1 Mix Design Engage qualified and experienced personnel to prepare and submit concrete mix design for approval by the SO. C1.4.2 Quality Management System Work to a Quality Management System consistent with SS ISO 9001. Provide details to the SO prior to commencement of work on site. C1.4.3 Construction Joints Engage qualified and experienced personnel to prepare and submit suitable construction joints and details for approval by the SO, including joints where different grades of concrete meet. C1.4.4 Project Reference Submit a list of project references in relation to experience in supply of high strength concrete, including historical data if available. Page C2 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/52 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract C2 Performance Requirements C2.1 Concrete Mix and Concreting Process Ensure the concrete mix delivered and the concreting process will achieve the specified concrete quality uniformly and consistently for all the concrete members, taking into consideration of site conditions and reinforcement details. Page C3 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/53 Singapore Land Group Ltd. C3 Clifford Centre Redevelopment PSD Specification for Main Contract Materials All Clauses shall make reference to C03-010 “Concrete Construction Generally”. C3.1 Concrete Concrete shall conform to SS 544-2 and SS EN 206-1. C3.2 Cement High early strength cement should be avoided. C3.3 Fine Aggregates Comply with SS EN 12620 and not to be alkali reactive. C3.4 Coarse Aggregates Comply with SS EN 12620. C3.4.1 Size Not to exceed 20mm. Not too angular and elongated. C3.5 Recycled Aggregate and Recycled Concrete Aggregate Refer to C03-010. C3.6 Water Refer to C03-010. C3.7 Admixtures To comply with the requirements of SS EN 206-1 and SS EN 934-2. Acceptance of admixtures will only be made upon provision of satisfactory information relating to name, type, dosage and justification for use. Superplasticisers should be used to achieve maximum water reduction. Considerations should be made to retain reasonable workability during transportation and placing. Page C4 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/54 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract C3.8 Concrete Mix Constituents C3.8.1 Concrete Mixes C3.8.1.1 Design Mixes Cement content would usually be optimum at 450-550 kg/m³. Target water/cement ratio can be in the range of 0.30-0.35, or even lower. The mix should be cohesive with minimum voids. This can be done by theoretical calculations or subjective laboratory trials. Higher workability should be specified to avoid honeycombing. The design mix can achieve a higher ultimate strength with a low initial strength gain and cementitious additions and micro-cracking associated with high thermal gradient can be avoided. Strength compliance shall be measured at 56 days instead of 28 days. Maximum temperatures and thermal gradients and their effect on constructability and long term design properties, should be determined during preconstruction trial, including effect of curing on strength development. Page C5 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/55 Singapore Land Group Ltd. C4 Clifford Centre Redevelopment PSD Specification for Main Contract Workmanship All Clauses shall make reference to C03-010 “Concrete Construction Generally”. C4.1 Construction Joints Propose method of pouring HSC at joints where different grades of concrete meet. C4.2 Formed Finishes All formed finishes for columns to be of the standard mentioned below unless otherwise specified. Use high quality concrete and formwork. Thoroughly compact the concrete. All surfaces to be true, with clean arises. Only very minor surface blemishes may occur, with no staining or discolouration from the release agent. Prepare a sample of the specified formed finishes at the start of the Contract to the approval of the SO, to be kept and used as a reference throughout the duration of the Contract. C4.3 Accuracy of Construction Construct all work with high strength concrete within half the permissible deviations given in C03-010 “Concrete Construction Generally”. Note that the tolerances given here are not cumulative. Carry out regular checks on the accuracy of the structure and if a part of the structure is found to be out of tolerance propose any remedial work required. Page C6 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/56 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract C5 Verifications and Submissions C5.1 Compliance Testing All Clauses shall make reference to C03-010 “Concrete Construction Generally”. C5.1.1 Testing of Concrete Cubes Two additional set of samples shall be retained for cube test at 56 and 90 days, respectively, on top of the numbers specified in SS EN 206-1 and SS 544. C5.1.2 Non-Destructive Testing Carry out non-destructive testing in accordance with the relevant parts of SS78 on all actual structural elements made up with high strength concrete (hammer tests or ultrasonic pulse velocity measurements) for comparison with compliance cube test results. This is to establish that no significant difference exists between the two sets of results. Minimum 5 sets to be conducted on each element subject to correlation requirement. C5.2 Submission C5.2.1 Mix Proportion To submit materials and proportions that are evaluated in the laboratory to determine the appropriate material proportions and their relative characteristics up to full strength being achieved. To include production sized trials which will establish optimum batching and mixing sequence. For truck mixing, maximum load that can be mixed adequately should be determined. C5.2.2 Concrete Properties Fresh concrete shall be tested for (but not limited to): a) Slump b) Air content c) Temperature d) Slump loss Hardened concrete shall be tested for (but not limited to): a) Compressive strength b) Modulus of elasticity c) Modulus of rupture d) Shrinkage Page C7 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/57 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract e) Creep Tests for hardened concrete shall be based on standard cured specimens and on cores drilled from monolith mock-up of adequate size and the results to be correlated based on adequate sampling. C5.2.3 Non-compliance To submit procedures to deal with non-compliance of design strength of HSC. C5.2.4 Concrete Suppliers To submit details of qualified concrete supplier including: a) Successful production-sized trials b) Successful full scale trial casting of typical structural sub-assemblage c) Plans to measure development of strength and temperature d) Project references e) Historical data on production of similar concrete strength. f) Quality Management System, including Quality Assurance and Quality Control plans. g) Capabilities and qualifications of experienced personnel h) Testing and batching facilities i) Accreditation of test laboratory C5.2.5 Method Statement To submit the following for SO’s approval: a) Batching of concrete in plant b) Delivery of concrete up to before placement c) Placement of concrete, including during wet and hot climate d) Curing of concrete e) Test programmes f) Solutions to non-compliance test results C5.2.6 Authority Submission To assist SO by providing relevant documentation for submission and obtaining approval from authority on the use of high strength concrete. This includes: 1. to provide a Quality Control and Assurance Manual: a) Concrete mix design Page C8 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/58 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract b) The concrete supplier should carried out laboratory trial mixes on the proposed concrete mixed design to show that they are achieved the required target mean concrete strength and standard deviation with local available materials, subjected to QP’s acceptance. c) The supplier should carry out plant trial for different batches of concrete and subject the concrete for tests for the required concrete properties at different ages and provide the statistical analysis of test results. d) Quality Control Procedures at the plant 2. to provide a concrete specialist to review the Quality Control and Assurance Manual above and report on its suitability. 3. to propose a full-scale mock up and the required concrete strength and properties and quality control procedures at site such as measuring of temperature, slump tests, etc. 4. to consolidate all information into High Strength Concrete Report to BCA BC2 requirement. Page C9 ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/59 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Appendix D C00-010 Design and Construct Performance Criteria ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/60 Singapore Land Group Ltd. D1 Clifford Centre Redevelopment PSD Specification for Main Contract General Read with the General Requirements section, contract preliminaries and all other contract conditions. The Contractor shall be fully responsible for the complete design of all works identified as Design and Build. The Contractor shall develop the civil and structural design in accordance with the Employee’s requirements as stated in the contract document. It is the duty of Contractor to ensure that the proposed design is in alignment with the design intent of the architect. The Contractor shall be responsible to carry out verification on the accuracy, adequacy and correctness of the design and build information provided in the contract document. It is to be at the risk of the Contractor to rely on that information and there shall be no additional time and cost implication to the contract due to the information provided. The Contractor shall be informed and deemed to have accepted that the design and information for design and build scope shown in the contract document is the minimum requirements (but not exhaustive) and shall be subjected to any further requirements imposed by the relevant authorities. The Contractor shall adopt and accept all the design for the design and build scope shown in the contract document as if it is their own design. The Contractor shall be deemed to undertake full design responsibility and liability of the works. The Contractor shall be responsible for any deficiencies or discrepancies of the design. In the case of difference between the minimum requirements and further requirements by the relevant authorities, the more stringent requirement shall govern. The design and build scope shown on structural layouts illustrates indicative member sizes and structural systems and are generally for the Contractor’s information only. D1.1 Design Responsibility Contractor shall engage and appoint a Qualified Person who is a Singapore registered Professional Engineer to carry out full detailed design and documentation including statutory submissions to obtain all necessary clearances/approvals from all relevant authorities. Contractor’s appointed Qualified Person/Professional Engineer shall engage and appoint the required qualified site supervision team to supervise the construction works in accordance with building control acts and regulations. The Contractor shall be responsible for ensuring full compliance with the latest edition of the relevant building regulations, standards and codes of practices, and by-laws of Republic of Singapore. D1.2 Alternative Structural System Proposals The Contractor is allowed to propose any alternative structural systems with the following requirement taken into account:• To conform with the Employer’s requirements and the contract documents. • To conform with the appropriate standards, codes of practices, statutory requirements and particular requirements as specified in the contract document. ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/61 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract • To be coordinated with the requirements of architectural, mechanical, electrical and other related disciplines/specialist. • To achieve maximum operational, functional and maintenance efficiency. • To achieve maximum buildability, sustainability, standardization and optimization of construction speed. D1.3 Reference Documents The following reference document are provided as part of tender/contract document: • • • • Soil Investigation reports Wind Tunnel Test Report Architectural Drawings Structural Specification These reference documents are provided for information. The contractor and its designer shall review and carry out the necessary verifications and/or additional tests/surveys/analysis/assessments, which are deemed to be part of the Works, to satisfy himself and the approving authorities on the accuracy and completeness of information provided. D2 Scope of Works The scope of works shall include all scope necessary for the completion of design, statutory approval, and construction of the following elements: • All railings/barriers, catwalks, services supports, DFMA frames/supports, façade supports, canopies, purlins, BMU support, trellises, lift separator beams, bollards, glass support, hanging double slabs, and any other secondary steelworks that are not shown in the structural drawings. • All structural steel connections and beam penetrations. • The building crown including the crown signage support. ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/62 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Figure 2 - Crown D&B Scope Definition Figure 3 - Crown Signage Indicative Size and Location ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/63 Singapore Land Group Ltd. • Clifford Centre Redevelopment PSD Specification for Main Contract Cable net wall supporting frames at Collyer Quay and Raffles place. Figure 4 - Cable Net Notional Structural Scheme to Illustrate Scope of Work, similar at Collyer Quay • All temporary structure including strengthening resulting from construction sequence. • All temporary ERSS works. • Contractor shall check construction sequence and temporary supports that affect load path through the transfer trusses. The scope of works shall include all scope necessary for the completion of design, and construction of the following elements: • D3 The amenity boxes located at Levels: 7th - 7th (Mid) and 18th - 19th. (Note - BCA submission and construction supervision to be undertaken by project QP) General Design Requirements The following sections present the requirements for the design of all structures. ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/64 Singapore Land Group Ltd. D3.1 Clifford Centre Redevelopment PSD Specification for Main Contract Design Guidelines The system and components shall be designed in accordance with the following standards and guidelines. In case of discrepancies between the standards the SO shall be contacted for further clarification. • SS EN 1990 + NA Eurocode 0: Basis of Structural Design • SS EN 1991 + NA Eurocode 1: Actions on Structures • SS EN 1992 + NA Eurocode 2: Design of Concrete Structures • SS EN 1993 + NA Eurocode 3: Design of Steel Structures • SS EN 1994 + NA Eurocode 4: Design of Composite Steel and Concrete Structures • SS EN 1995 + NA Eurocode 5: Design of Timber Structures • Eurocode 7: Geotechnical Design SS EN 1997 + NA • SS EN 1998 + NA Eurocode 8: Design of Structures for Earthquake Resistance • BCA BC1:2012 Design Guide on Use of Alternative Structural Steel to BS 5950 and Eurocode 3 • BCA BC3:2013 Guidebook for Design of Buildings in Singapore to Requirements in SS EN 1998-1 • Building and Construction Authority Approved Document Acceptable Solutions • Land Transport Authority Code of Practice for Railway Protection • Land Transport Authority Civil Design Criteria for Road and Rail Transit Systems • Public Utility Board Code of Practice on Surface Water Drainage • Public Utility Board Code of Practice on Sewerage and Sanitary Works • Fire Code 2013 Any other relevant current Singapore Standards and codes of practice and/or guidelines issued by relevant authorities. This document shall be read in conjunction with the relevant requirements of the following specification sections: • C03 Concrete Construction Work • C05 Structural Steel Work • C08-010 Structural Timber Works • C08-20 Mass Engineered Timber D3.2 Design Life In accordance with Table NA.2.1 in the Singapore National Annex to SS EN 1990: Basis of Structural Design, the proposed structures are classified as working life category 4 and therefore be designed to achieve a durability and service life, with appropriate maintenance of 50 years. ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/65 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Table: Design Working Life Table NA2.1 from SS NA EN 1990. D3.3 Durability & Fire General requirements for durability are as set out in SS EN 1990. D3.3.1 Concrete Exposure Classification The exposure classes are as defined in Table 4.1 of SS EN 1992-1-1 and Table A.1 of SS 544-1:2019. The values of minimum concrete cover to reinforcement are in accordance with Table A.4 of SS 544-1:2019. (SS 544-1:2019 is Singapore’s adoption of BS 8500-1: 2006.). D3.3.2 Structural Steel Corrosion Protection Corrosion protection of structural steel shall comply with EN ISO 12944. Cross reference shall be made to the requirements of C05-020 and the corresponding PSD. D3.3.3 Fire Rating Structural members shall be designed to comply to fire rating requirements specified in Code of Practice for Fire Precautions in Building: 2013 by Singapore Civil Defence Force and SS EN 1992-1-2. Fire resistance periods as follows, unless noted otherwise on fire plan by architect: • Substructure – 4 Hours • Superstructure – 2 Hours Structural steel elements shall be fire protected using applied fire protection coatings. Connections of steel elements shall also be fire rated to the most onerous rating of the two connecting elements. The fireproofing system shall be approved by the Architect. Contractor shall engage a fire engineer / specialists to ensure the structural members can perform under fire load as per code and authority requirements. Fire resistance for reinforced concrete elements shall be achieved by adequate cover to the reinforcement based on the requirements of the design standard. ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/66 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract D3.4 Materials D3.4.1 Concrete Concrete shall be specified and produced in accordance with SS EN 206-1. The concrete mix designs shall achieve the durability requirements for the required exposure classes in Table A.4 of SS 544-1:2019 and DC-class based on ACEC-class determined in accordance with Table A.10 and A.12 of SS 544-1:2019. D3.4.2 Steel Reinforcement The properties of steel reinforcement to be used in the design shall comply with BS 4449 (steel for the reinforcement of concrete) and BS4483 (steel fabric for the reinforcement of concrete). This British Standard compliments SS EN 1992-1-1, Annex C. All reinforcing shall be Class B. D3.4.3 Prestressing Strand Prestressing strands shall be manufactured in compliance with BS 5896 Specification for High Tensile Steel Wire and Strand for the Prestressing of Concrete. D3.4.4 Structural Timber All timber members shall be specified and produced in accordance with SS EN 1995. The Contractor is responsible for the design of member sizes and connection details of those elements shown on the drawings, the same elements shall be regarded as indicative only and the Contractor shall be responsible for ensuring that the comply to SS EN 1995. Contractor shall if necessary, engage a fire engineer / specialists to ensure that the structural members can perform under fire load as per code and authority requirements. D3.4.5 Structural Steelwork All structural steelworks shall be designed as Class 1 to BC1 manufactured and tested in accordance with the following standards: • BS EN 10025 Hot rolled products of structural steel • BS EN 10210 Hot finished structural hollow sections of non-alloy and fine grain steels • BS EN 10219 Cold formed welded structural hollow sections of non-alloy and fine grain steels D4 Loading and Stability Reference shall be made to the loading plans, codes of practice and reference documents. In case of discrepancies between the reference documents the SO shall be contacted for further clarification. D4.1 Load Combinations Load combinations shall be considered as per Section D3.1. ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/67 Singapore Land Group Ltd. D4.2 Clifford Centre Redevelopment PSD Specification for Main Contract Dead Load Dead and superimposed dead loads shall be considered as per Section D3.1. Reference shall also be made to the loading plans. The more stringent requirement shall govern. Density of construction material shall be in accordance with Annex A of SS EN 1991-1-1. Concrete (reinforced, normal weight) 25.0 kN/m3 including normal percentage of reinforcing and prestressing steel Concrete (plain, normal weight) 24.0 kN/m3 Structural steel 78.5 kN/m3 Water 10.0 kN/m3 Planter soil 20.0 kN/m3 Glass 25.0 kN/m3 Brick/concrete block 22.0 kN/m3 D4.3 Live Load Live and stability loads shall be considered as per Section D3.1. Reference shall also be made to the loading plans. The more stringent requirement shall govern. D4.4 Wind The wind load shall be determined based on the code of practice and findings of the Wind Tunnel Test Report. The more stringent requirement shall govern. Wind actions shall be determined in accordance with SS EN 1991-4:2010 and Singapore national annex SS EN 1991-1-4 using a basic wind velocity (Vb,0) of 20m/s as recommended in the Singapore NA. D4.5 Thermal Loading In accordance with NA to SS EN 1991-1-5 the 50-year return period maximum and minimum shade temperatures are 35.7ºC and 19.5ºC respectively. A thermal range of +/-10ºC shall be used in the design. D4.6 Lateral Deflection Criteria The total lateral deflection at the top of the building under the characteristic serviceability loading combinations shall be limited to H/500, where H is the total height of the building. The relative lateral deflection over any one storey under the characteristic serviceability combinations shall be limited to h/500, where h is the height of the storey. Lateral deflection of earth retaining wall shall be limited to 0.5% of the excavation depth in accordance with BCA Advisory Note 1/09. Wall deflection and ground movements shall be ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/68 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract checked with consideration of adjacent buildings and foundations in accordance with BCA circular on impact assessment to adjacent structures from ERSS works. D4.7 Vertical Deflection Criteria The following vertical deflection criteria for slab and beams shall be adopted in the design: Construction dead loads Span/200 (max 25mm) Service Imposed Loads Cantilevers Length/180 Floor Beams Span/360 Beams carrying brittle finishes. Span/500 Span/200 (max 30mm) Total Loads Where deflections exceed 30mm pre-cambering shall be implemented to offset the deflection. D4.8 Vibration Analysis of vibration response shall follow an established and reputable method. Analysis modelling for the purpose of prediction of vibration performance shall be undertaken using a 3D model in a reputable software platform. The following limits shall be applied: • Amenity boxes shall be designed to response factor limit of 4. • All members shall achieve a minimum frequency of 4 Hz ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/69 Singapore Land Group Ltd. Clifford Centre Redevelopment PSD Specification for Main Contract Appendix E Base Specifications ARP-ST-SPE-02 | T1 | 18 May 2023 20230515_CLIFFORD CENTRE REDEVELOPMENT PSD_V1.0 Doc D.2/70 (1) G01-010 GENERAL REQUIREMENTS PARTS (2) C01-010 Demolition and Site Clearance (3) C01-020 Condition Survey (4) C02-010 Site Investigation (5) C02-020 General Earthworks (Excavation and Filling) (6) C02-030-01 Diaphragm Wall (7) C02-030-02 Sheet Pilling (8) C02-030-03 Contiguous Bored Pile Walls and Secant Pile Walls (9) C02-040-01 Jet Grouting Method (10)C02-050 Instrumentation and Monitoring (11)C03-010 Concrete Construction Generally (12)C03-020 Reinforcement (13)C03-030 Formwork and Falsework (14)C03-040 Designed Joints (15)C03-050 Water-resistance to Concrete Structures (16)C03-060 Precast Concrete Works (17)C03-070 Prestressed Concrete Works (18)C03-080 Concrete Repairs (19)C03-090-01 Ferrocement (20)C03-100 Sprayed Concrete (21)C03-110 Fibre Reinforce Concrete (22)C04-010 Bored Pilling (23)C04-020 Displacement Pilling (24)C04-030 Pile Testing (25)C05-010 Structural Steelworks (26)C05-020 Protective Works for Structural Steelwork (27)C06-010 Sewers Construction (28)C06-020 Drains Construction (29)C07-010 Construction of Roads and Footpaths (30)C07-020 Pavement for Roads and Footpaths (31)C07-030 Road Ancillaries (32)C08-010 Structural Timberwork (33)C08-020 Mass Engineered Timber 3 108 134 143 187 238 265 283 297 316 361 397 414 428 442 458 500 536 559 576 601 615 654 687 750 791 815 842 863 885 912 930 955 979 TS 1/1065 978 Doc D.2/71 This Page Has Been Intentionally Left Blank TS 2/1065 978 Doc D.2/72 (1) G01-010 GENERAL REQUIREMENTS PARTS TS 3/1065 978 Doc D.2/73 1 GENERAL This Section sets out the general requirements for carrying out any works for the Project and shall be read in conjunction with all relevant work Sections and other contract documents. In addition, under the same clause heading of each Section, any modifications and additions as listed in the Project Specific Data (PSD) shall take precedence over the original specification appended under same clause. 1.1 Project Particulars 1.1.1 The Site The Site is located at [to be specified by user]. 1.1.2 Project Team The following words shall have the meaning assigned to them: 1.1.3 . Organisation Address Represented by Architect [to be specified by user] [to be specified by user] [to be specified by user] C&S Engineer [to be specified by user] [to be specified by user] [to be specified by user] M&E Engineer [to be specified by user] [to be specified by user] [to be specified by user] Quantity Surveyor [to be specified by user] [to be specified by user] [to be specified by user] Definitions, Abbreviations and Interpretations TS 4/1065 978 Doc D.2/74 1.1.3.1 Definitions In the Specification, the following words and expressions shall have the meanings hereby assigned to them except where the context otherwise requires: "Employer" shall mean the party as set out in the Conditions of Contract. "Consultants" shall mean the Employers Appointed Architectural Consultant, Civil and Structural Engineering Consultant, Mechanical and Electrical Engineering Consultant, Quantity Surveying Consultant, Project Management Consultant and other appointed Consultants. "SO" shall mean the Superintending Officer who is the Architect, the Engineer or their representative on site, or as designated by the Employer. "Architect" shall mean the Employers Appointed Architectural Consultants who is registered with the Board of Architects in Singapore. "QP" shall mean Qualified Person who is a registered architect or a professional engineer with valid practical certificate registered in Singapore. "PE" shall mean Professional Engineer who is registered under the Professional Engineers Board, Singapore "AE" shall mean Authorised Examiner who is approved by the Commissioner for Workplace Safety and Health of the Ministry of Manpower by a Certificate in writing for the purpose of carrying out examinations and tests on lifting equipment in accordance with the Workplace Safety & Health (General Provisions) Regulations. "Contractor" shall mean the party as set out in the Conditions of Contract. "Registered Surveyor" shall mean Surveyor who is registered under the Land Surveyor Board, Singapore "as approved" shall mean as approved by the Superintending Officer in written format. "as agreed" shall mean as agreed with the Superintending Officer. "as directed" shall mean as directed by the Superintending Officer. "or other" shall mean as approved by the Superintending Officer "as required" or "as shown" or "as indicated" or "as specified" shall mean as required or as shown or as indicated or as specified in the Drawings and/or Specification. "acceptance" and "approval" are used within the following limitations: 1.1.3.2 (a) No approval or acceptance by the SO shall relieve the Contractor of any responsibility to achieve the specified quality and performance of the work under the Contract. (b) Any approval given in respect to samples of materials, workmanship or methods of construction submitted in accordance with the requirements of the Specification, are not to be interpreted as denoting any degree of satisfaction with the materials used in the Works or in the execution of the Works. Abbreviations The following abbreviations are used in the Specification: ABGSM = Association of British Generating Set Manufacturers TS 5/1065 978 Doc D.2/75 AC or ac = alternating current ACMV = Air-Conditioning and Mechanical Ventilation AISI = American Iron and Steel Institute AMCA = Air Movement and Control Association ANSI = American National Standard Institute AS = Australian Standard ASTM = American Society for Testing and Material AVA = Agri-Food and Veterinary Authority of Singapore BCA = Building and Construction Authority BMT = Building Maintenance Team BS = British Standard CAAS = Civil Aviation Authority of Singapore CCTV = Closed-circuit Television CPF = Central Provident Fund Board CP = Code of Practice DC or dc = direct current DIN = Deutsches Industrie Normen DSTA = Defence Science and Technology Agency (DSTA) ECM = Earth Control Measures ECO = Environmental Control Officer EIA = Electronic Industry Association ELCB = Earth Leakage Circuit Breaker EMA = Energy Market Authority EN = European Standards EPR = Ethylene Propylene Rubber FTRR & I = for their respective rights and interests FSSD = Fire Safety and Shelter Department GS or gs = Galvanised Steel GST = Goods and Services Tax HRC = High Rupturing Capacity IDA = Info-Communications Development Authority of Singapore IEC = International Electrotechnical Commission IECEE = IEC System for Conformity Testing and Certification of Electrical Equipment TS 6/1065 978 Doc D.2/76 IP = Index of Protection ISO = International Organization for Standardization ITE = Institute of Technical Education JIS = Japanese Industrial Standard LEW = Licensed Electrical Worker MCB = Miniature Circuit Breaker MCCB = Moulded Case Circuit Breaker MEWR = Ministry of the Environment and Water Resources MSSL = Market Support Services Licensee Max or max = maximum Min or min = minimum MOM = Ministry of Manpower MRT = Mass Rapid Transit MS or ms = mild steel NEA = National Environment Agency No. or no. = number ONORM = Osterreichisches Normungsinstitut (Austrian Standard) PBTS = Public Basic Telecommunications Service Operators PLS = Product Listing Scheme PowerGrid or Grid = PowerGrid Ltd PPE = Personal Protection Equipment PSB = TUV SUD PSB Pte Ltd PSD = Project Specific Data PTL = Public Telecommunication Licensees PUB = Public Utilities Board PVC or pvc = Polyvinylchloride RC or rc = Reinforced Concrete RCCB = Residual Current Circuit Breaker rms = root mean square SAC = Singapore Accreditation Council SCV = StarHub Cable Vision Pte Ltd SINGLAS = Singapore Laboratory Accreditation Scheme SLA = Singapore Land Authority TS 7/1065 978 Doc D.2/77 SMRT = Singapore MRT Ltd SOA = Socket-outlet assembly SPPG = SP Power Grid SPSL = SP Services Ltd SS = Singapore Standard SWA = Steel wire armoured SWG = Standard Wire Gauge (British) SingTel = Singapore Telecommunications Ltd TIA = Telecommunications Industry Association UHF = Ultra High Frequency UL = Underwriters Laboratories Inc uPVC or UPVC = Unplasticised Polyvinylchloride VHF = Very High Frequency v/v = measured by volume w/w = measured by weight WSH = Workplace Safety and Health WSHO = Workplace Safety and Health Officer XLPE = Cross linked polyethylene % = percent ± = plus or minus = or < = less than or equal to = or > = greater than or equal to < = is less than > = is greater than 1.1.3.3 Interpretations (a) Words importing the singular shall also include the plural and vice versa where the context requires. (b) The clause or subclause headings in the Specification shall not be deemed to be part thereof or be taken into consideration in the interpretation or construction thereof or of the Contract. TS 8/1065 978 Doc D.2/78 1.1.4 (c) All clauses, including all subclauses under them in the Specification shall be deemed to be directed at the Contractor unless expressly specified otherwise to the contrary, and the Contractor shall perform and/or comply with such instructions, directions, requirements and obligations specified in the Specification and required under the Contract. (d) All Acts of Parliament, statutes, regulations, bylaws, orders, local and foreign standards and codes of practice specified shall be deemed to refer to the latest and shall be deemed to include any amendments, and/or modifications and/or additions and/or re- enactments thereto. BCA Green Mark The Project shall attain the respective Green Mark Score (as per BCAs requirements) to achieve the stipulated Green Mark rating. Allow for all cost and manpower in relation to application, submission and assessment in order to receive the Green Mark rating. 1.2 General Description of the Works The Works for the project is generally described below: [to be specified by user] [to be specified by user] Refer to the PSD for the specific description of work requirements for the project. 1.3 Standards, Codes, Regulations and Technical References 1.3.1 Standards and Codes Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant requirements of the Standards and Codes referenced in the body of the Specification. Alternative Standards and Codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative Standards and Codes comply with the requirements of the standards specified. All Standards and Codes quoted are the current version unless specific year references are noted. In the event that the Standards or Codes are partially superseded or become obsolete, refer to the latest edition or the approved substitution for the relevant clauses. In case of conflicting requirements between the Codes, refer to the SO for resolution. 1.3.2 Regulations The whole of the Works and materials are to be in accordance with the Building Control Regulations, other regulations as set out by the Authorities having jurisdiction over the Works, and the relevant bylaws unless otherwise stated. Ensure that the Specification referred to are strictly adhered to when carrying out the Works, unless otherwise directed. TS 9/1065 978 Doc D.2/79 1.3.3 Technical References Ensure that the Works comply with the relevant authority regulations and directions. Where specified, be guided by the principles and methods as set out in the technical references when carrying out the Works. Alternative methods and principles may be proposed in lieu of the referenced document, subject to SOs acceptance, if it can be demonstrated that the specified quality or performance of the Works can be achieved. 1.4 Trade Preamble 1.4.1 Ambiguity Before commencing any works, obtain clarification or instructions in relation to any discrepancy or ambiguity, which is discovered within and between the Specification work sections, and/or other contract documents issued by the various parties. 1.4.2 Licences, Permits and Liaison with the Authorities Be responsible to initiate the application for all necessary licences, permits, and to carry out all necessary liaison with the Authorities, whenever necessary, for the satisfactory completion of the Works. Be responsible for ensuring that these licences and permits are obtained in good time. 1.4.3 Safety Regulations and Design for Safety Strictly observe all necessary safety requirements to comply with the Workplace Safety and Health Act and any other requirements from the Authorities having jurisdiction over the Works. Comply to the Workplace Safety and Health (Design for Safety) Regulations, and to participate in any Design for Safety (DfS) initiatives if so required for the project. Responsible to execute the Works in a safe manner and ensure that the subcontractor and Designers engaged are competent and provide them all relevant information needed for them to perform their duties under the Workplace Safety and Health (Design for Safety) Regulations. These Designers are as defined under the Workplace Safety and Health (Design for Safety) Regulations. Together with the relevant designers and subcontractors, attend the DfS review meeting held by the DfS Professional, to address to hazards or risks identified and ensure that they are properly managed through the execution GUIDE-3 of the Design Review Process. Take over the DfS Register from the Consultants and continue from Guide 2 onwards. Refer to Clause 5 "Site Safety" of this Section for further detail requirements. TS 10/1065 978 Doc D.2/80 1.4.4 Safeguarding Properties Adjacent to Site Propose and adopt site procedures and methods of working such as to limit to a minimum any disturbance and vibration to the buildings around the Site. Identify and implement protective measures necessary to safeguard the adjacent properties prior to carrying out the Works. Indemnify the Employer in accordance with contract conditions against all claims for loss and/or damage to the adjoining properties by reason of the carrying out of the Works or by reason of insufficiency of precautionary measures. Refer to Section G01-010:Clause:1.7.7 for further detail requirements. 1.4.5 Maintenance Manual Develop and submit, for the SOs acceptance, a strategy in the form of a maintenance manual and logbook, to ensure that elements that are likely to deteriorate significantly can be replaced or rectified. The maintenance manual and logbook are to describe the procedures for the satisfactory long- term care and regular maintenance of the materials and components identified in the work sections, which shall be carried out by the building owners. Include the following information, where appropriate: (a) An outline description of the installation and detailed description of specific items with product names, types, serial numbers, etc. (b) The name, address and telephone number of each supplier, fabricator, finisher, installer, etc., involved in the Works. (c) Recommendation on maintenance periods and planned preventive maintenance procedures. (d) Copies of manufacturers warranties or guarantees, service manuals, brochures, recommendations, etc. (e) Copies of test and approval certificates. (f) One original copy of documents showing "As Built" information and the like, relevant to the installation. Submit the "As-Built" information in soft copies where directed by the SO. The Contractor shall compile one single set of the information from various subcontractors for submission. (g) Compilation of a list of parts to be replaced periodically and the names and contacts of the suppliers. (h) Realignment and adjustment instructions where relevant. (i) Procedures for dismantling and reassembling. (j) Details of finishes, including colour and required maintenance. TS 11/1065 978 Doc D.2/81 Logbook pages set up for recording the times of performance of the above procedures, sufficient in number to receive the entries for a minimum of 10 years or otherwise directed. Show examples of typical entries by recording any maintenance procedures (such as cleaning) performed during the Contract Period and/or maintenance/defects liability period. The forms of the maintenance manual and logbook are to be in A4 size, printed or typed on durable printing paper, each page consecutively numbered, neatly bound in durable vinyl or similar hard cover, and permanently labelled with the project name and date of issue. The Contractor shall compile one single set of the information from various subcontractors for submission. 1.4.6 Testing Authority When tests and checks are called for in the Specification, engage a suitably equipped organisation or laboratory accredited under the Singapore Laboratory Accreditation Scheme (SINGLAS) and to SOs acceptance, to carry out the tests and checks required. 1.4.7 Quality Control Plan Prepare and submit a quality control plan for SOs acceptance. Include a set of procedures/actions to: 1.4.8 (a) Ensure the understanding of the project brief. (b) Ensure a number of checks and verification are put in place in the work process to enable the delivery of the brief. (c) Ensure the right person is employed to carry out the Works. (d) Ensure the Works are carried out based on proper operating instructions. (e) Ensure feedback and poor/defective works is picked up and attended to, and corrective/preventive action is in place. (f) Ensure prior approvals are obtained from SO for any deviations from the Specification before Works commence. (g) Ensure documents of all tests and quality checks as specified are properly done and kept as records. Building Information Modelling (BIM) Allow for the BIM requirements stipulated for the project, including all cost for necessary but not limited to manpower, license, software and hardware. Such adoption shall be in line with latest Particular Conditions for Building Information Modelling and Singapore BIM Guide published by Building and Construction Authority. 1.4.8.1 BIM Particular Conditions The Particular Conditions for Building Information Modelling shall refer to the BIM Particular Conditions, published by the Building and Construction Authority. TS 12/1065 978 Doc D.2/82 1.4.8.2 Singapore BIM Guide The Singapore BIM Guide, published by the Building and Construction Authority, will be used for references for the project. 1.4.8.3 BIM Execution Plan Together with the Consultants and BIM Professional, develop a BIM Execution Plan at the start of the project. The goals and the implementation details will be outlined in the BIM execution Plan. 1.4.9 As-built Drawings Contractor to obtain authority approved plans in CAD from SO. These plans must be updated to capture all deviations or amendments, including those captured in SO’s Instructions (SOI), Project Manager’s Instructions (PMI), Architect’s Instructions (AI), Engineer’s Instructions (EI), Request for Information (RFI), Construction sketches, etc. Contractor is to submit such revised plans as as-built drawings to SO for record and authority record plan submission. The as-built plans shall be submitted progressively floor by floor not later than two weeks from casting date. Also, the Contractor is to reflect all structural deviations in the Final As built Models. 1.5 Performance Criteria 1.5.1 General Requirement Engage methods and resources that will ensure the Works achieve the specified quality within the agreed programme and cost. 1.5.2 Environment Ensure the carrying out of the Works will not cause unacceptable pollution, noise, erosion and vibrations to the environment as stipulated by the NEA and other relevant Authorities. 1.5.3 Code on Accessibility Comply to the Code on Accessibility in the Built Environment and its latest updates. 1.5.4 Buildability (Buildable Design and Constructability) Comply to the latest amendments on Building Control Act and Regulations on Buildability and Productivity. The Contractor is responsible to achieve the Constructability Score required for the project and declare the Constructability Score achieved and on the Certificate of Compliance of Constructability Score. 1.5.5 Good Industry Practices Adopt the details of good pratices as appended in BCA publications and advisories on the Good Industry Practices Guide Book. 1.6 Materials TS 13/1065 978 Doc D.2/83 1.6.1 Materials Generally Products shall be new unless otherwise specified. All materials shall be supplied clean, undamaged and in good condition ready to be used for the Works. For products with a limited shelf life, ensure no parts or whole are expired. Where a choice of manufacturer or source is allowed for any particular product, supply the whole quantity required as the same type and from the same manufacture and/or source unless otherwise approved. Produce written evidence of sources of supply when requested. Ensure that the whole quantity of each product supplied is of consistent kind, size, quality and overall appearance. Ancillary products and accessories shall be of a type recommended by the main product manufacturer, unless otherwise specified. 1.6.2 Ordering of Materials Unless otherwise directed, do not place orders for materials before the sources and samples of the materials have been approved and the results of any preliminary tests required by the Specification have been accepted by the SO. 1.6.3 Certificates for Materials All materials and products shall be manufactured and tested in accordance with the specified or appropriate Standard. All materials and products delivered to the Site shall bear the manufacturer's name, brand name or any other data required to verify compliance with the specified requirements. Where appropriate, provide certificates from the supplier or test agencies verifying such compliance. Include, whenever applicable, the location in the Works or the delivery or batch which the certificate represents. Where certificates of manufacture or tests are not available for materials proposed for use in the Works, carry out independent testing to determine compliance with the specified requirements where directed by the SO. 1.6.4 Storage of Materials Store all materials in a manner, which is not detrimental to their use in the Works and in accordance with any specified requirements. Ensure that the storage facilities and the loadings resulting from the storage will not adversely affect the construction, the building and other buildings/amenities nearby. Engage specialist advice if appropriate. Do not permit the storage of materials, components or equipment on new or partially completed work without prior approval. 1.6.5 Rejected Materials Immediately remove from the site, all materials which are unidentified or do not comply with the Specification. TS 14/1065 978 Doc D.2/84 1.7 Workmanship 1.7.1 Workmanship Generally Ensure that all works are carried out: 1.7.2 (a) In accordance with the specified methods and procedures where applicable. (b) In accordance with good building practice. (c) In accordance with the manufacturers instructions where applicable. (d) By suitably qualified and experienced personnel. (e) With required site supervision by qualified personnel. Co-Ordination of Drawings Check all drawings and schedules to ensure that there is sufficient information to carry out the Works and that all the instructions, drawings and schedules provide compatible information on the Works to be carried out. In the event of any discrepancy being found between the contract drawings and/or schedules, and other contract documents, notify the SO immediately for resolution the SOs decision shall be final. 1.7.3 Setting Out and Levels 1.7.3.1 Accuracy Arrange the setting out, erection, juxtaposition of components and application of finishes in such manner as to ensure: 1.7.3.2 (a) Compliance with specified tolerances. (b) Satisfactory fit at junctions. (c) No visually unacceptable changes in plane, line or level. (d) True, regular finished appearance. Levels Site levels, either spot or contour, and all other levels shown in the drawings are established with respect to the datum of 100.00 m at mean sea level. Check and verify all existing and proposed levels as indicated in the drawings. Highlight and resolve any discrepancy prior to the commencement of the Works. TS 15/1065 978 Doc D.2/85 1.7.4 Delivery, Storage and Handling Deliver materials and products to the Site with labels showing brand name, product name and manufacturer's batch number. Store materials in accordance with manufacturer's recommendations. Use in order of delivery and before expiration of the shelf life date. 1.7.5 Protection of Products and Components Take measures to prevent overstressing, distortion and other damage to the products. Keep products and components clean and free from contamination. Prevent staining, chipping, scratching or other disfigurement, particularly of products exposed to view in the finished work. Keep dry to prevent premature setting, moisture movement and similar defects. Where appropriate store off the ground and allow free air movement between stored products. Prevent excessively high or low temperatures and rapid temperature changes in the products. Protect adequately from rain, damp, sun and other elements as appropriate. Ensure that products are of a suitable temperature and moisture content at time of use. Ensure that sheds and covers are of ample size, in good weatherproof condition and well secured. Keep different types and grades of products separately and adequately identified. Keep products in their original wrappings, packings or containers until immediately before use. Wherever possible, retain protective wrappings after fixing until shortly before handing over to the Employer. Ensure that protective measures are fully compatible with and not prejudicial to the products and materials. 1.7.6 Suitability of Conditions at the Start of Works Provide all trades with necessary details of related types of work. Before starting each type of work, ensure that: 1.7.7 (a) Previous work is appropriately complete, in accordance with the project documents, to a suitable standard and in a suitable condition to receive the new work. (b) All necessary preparatory work has been carried out, including provision for services, openings, supports, fixings, damp-proofing, priming and sealing. (c) The environmental conditions are suitable. Execution of Works TS 16/1065 978 Doc D.2/86 1.7.7.1 Methods Carry out the Works in accordance with accepted methods and equipment. 1.7.7.2 Allowance for Movements Ensure that the performance, appearance and proper functioning of the Works are not affected by any movement, settlement, deflection, expansion or contraction that can be reasonably expected to occur in the building or the Works. Where applicable, form joints between the Works and adjacent works to accommodate possible movements, settlement, deflection, expansion or contraction between the works. 1.7.7.3 Monitoring of Adjacent Structures Provide proposals for surveys and monitoring of movement and vibration in adjacent structures and services before work commences and during the course of the Works. Submit the assessment of the effect of wall deflection and ground settlement to adjacent properties and the proposed control limits. 1.7.7.4 Instrumentation and Monitoring Provide instrumentation to monitor the ground movement, vibration and condition of adjacent properties. Refer to the drawings for the schedule of instrumentation required. If necessary or as required by the Authorities, propose and provide additional instrumentation and monitoring for records. Take cognisance of and co-ordinate with other contractors on site who the persons may be carrying out instrumentation and monitoring works to avoid duplication of installation and readings. Refer to Section C02-050 "Instrumentation and Monitoring" for further details. 1.7.7.5 Application/Installation of Products and Components Use or fix each product and component in accordance with manufacturer's recommendations. Inform the SO if recommendations conflict with any other specified requirement. Provide suitable packings at screwed and bolted fixings to take up tolerances and prevent distortion. Adjust the location and fixing of components and products so that joints which are opened to view are even and regular. Ensure that all moving parts operate properly and freely. Do not cut, grind or plane pre-finished components and products to remedy binding or poor fit without approval. TS 17/1065 978 Doc D.2/87 1.7.8 Holes, Chases, Inserts and Fittings Obtain approval for the size and position of any hole, chase, insert or fixing required before the related work begins. Unless otherwise agreed, form all holes and chases and build in any inserts or fixings at the time of construction. Do not cut or drill any part of the Works without approval. Do not cast any conduits, recesses, pipes, etc. inside structural columns, walls, beams or slabs unless otherwise agreed. 1.7.9 Protection of Works Take all necessary precautions to prevent damage to the Works from rain and other hazards, and due to the other works in progress, until hand over. 1.7.10 Defective Work Where, in the opinion of the SO, any of the finished work or materials or workmanship in any part of the Works fail to comply with the Specification, that part of the Works will not be accepted and may be classified as defective. All work classified as defective shall be cut out and removed from the Works and replaced or otherwise dealt with in accordance with the Conditions of Contract. Propose and carry out suitable remedial measures to the SOs satisfaction. The extent and nature of any measures required as a result of defective work shall be determined by the SO. 1.7.11 Cleaning Up Where, in the opinion of the SO, any of the finished work or materials or workmanship in any part of the Works fail to comply with the Specification, that part of the Works will not be accepted and may be classified as defective. All work classified as defective shall be cut out and removed from the Works and replaced or otherwise dealt with in accordance with the Conditions of Contract. Propose and carry out suitable remedial measures to the SOs satisfaction. The extent and nature of any measures required as a result of defective work shall be determined by the SO. 1.8 Verification and Submission TS 18/1065 978 Doc D.2/88 1.8.1 Records and Certificates Unless otherwise directed, maintain 3 copies of records of all inspections and tests performed to substantiate conformity with the Contract Specification, including those carried out by subcontractors and/or third party testing agencies and manufacturers' or suppliers' certificates of test. Retain one copy of these records on site and make available for inspection at any time. Submit the other 2 copies to the SO and the Employer respectively and progressively. On completion of the Works, hand over all records to the SO, unless otherwise agreed. Submit to the SO, without delay, any records which indicate work or materials not complying with the Specification, in order that proposals for any rectification may be assessed and carried out in good time. 1.8.2 Tests to Establish Acceptability of Works In the event of failure to comply with the requirements of the Specification, propose suitable tests to establish the acceptability of the Works and be responsible for any consequential costs and delays. 1.9 Stamp Duties All documents required by or arising out of or in connection with this Contract shall be properly stamped to comply with the Stamp Duties Act. The cost and expense arising out of this obligation, including all stamp duties required, shall be borne by the Contractor and shall be deemed to have been allowed for in the Contract Sum. 1.10 TOL Fee for Land Outside Contract Boundary Where the Contractor requires land outside the contract boundary for the setting up of construction equipment and other temporary facilities for the Works, the Contractor shall check on the availability of such land and apply to the relevant Authority for the use of such land. In the event the relevant Authority allows the Contractor the use of such land, the Contractor shall at its own cost and expense comply with all the terms and conditions, pay any TOL (Temporary Occupation Licence) fees, bear all costs and expenses for the use and maintenance of and access to the said land imposed by the relevant Authority. Any materials or goods stored at such land shall be considered unused materials or goods not delivered to Site. 1.11 Provisional Sum Items Where Provisional Sum Items are included in the Contract, the Provisional Sum Items shall include all costs necessary in carrying out or supplying the Work, materials or goods. These Provisional Sum Items shall include the Contractor's profit and overheads but shall be nett of trade and cash discounts. TS 19/1065 978 Doc D.2/89 1.12 Prime Cost Sums Where Prime Cost Sums (referred to as PC Sum for the purposes of this subclause) are provided for any work, materials or goods, these sums shall be inclusive of carriage but exclusive of Contractor's profit and attendance. These PC Sums shall also be net of trade and cash discounts. Allow and separately price for profit and attendance in respect of such PC Sum in the Form of Tender. Deduct PC Sum from the Contract Sum and in lieu thereof add the sums due to the Contractor for the said work, materials, or goods. The sum allowed by the Contractor in the Contract for attendance in respect of any PC Sum shall be fixed regardless of whether the actual sum expended is greater or lesser than the PC Sum. In respect of profit, the amount to be paid shall be the percentage quoted by the Contractor against the actual sum expended in relation to the PC Sum. Should the work, materials or goods for which a PC Sum is provided in the Contract be not required, or if the Employer chooses to carry out or supply the aforesaid work, materials or goods by its own workmen or by other contractors, which the Employer is contractually entitled so to choose, then such PC Sum together with the profit and attendance allowed by the Contractor in the Contract shall be deducted in full from the Contract Sum. Should the Contractor be engaged or instructed to carry out or supply any work, materials or goods under a PC Sum, the profit and attendance allowed by the Contractor in the Contract in respect of the PC Sum shall be deducted in full from the Contract Sum. In such event, the amount to be paid to the Contractor for the work, materials or goods shall be inclusive of the Contractor's overheads and profit for the work, materials and goods. 1.13 Overclaim Leading to Overpayment If at any time during the Contract Period (including any extension thereof), the Contractor is found to have over-claimed and was paid for more than the value of the Permanent Works carried out and/or approved unfixed materials at the Site, the SO shall be empowered to deduct from the Contractor's subsequent payments the sum overpaid together with the Employer's charge, and interest calculated at the prevailing rate. 1.14 Existing Ground / Road Levels The existing ground / road levels / drain invert levels as shown in the drawings are approximate. Note that existing ground /road levels and drain invert levels may not necessarily be the same as shown in the drawings. Ascertain this and visit the Site prior to the tender and is include whatever extra cost of cut and fill in the Contract Sum. In the event of the Contractor failing to visit the Site, the tender shall be deemed to have been submitted with its satisfaction of the actual levels on Site and other related ground conditions. The Contractor is deemed to have made necessary provision in the Contract Sum to cater for additional earthwork arising from the difference in levels found on site and that shown in the drawings, and no claims or compensation shall be entertained. TS 20/1065 978 Doc D.2/90 1.15 Raising or Lowering of Existing Sewer Manholes and Other Services Manholes Include in the Contract Sum the cost of raising or lowering of existing sewer manholes and other services manholes/chambers, and their related works within the contract boundary to suit and match the proposed driveways and platform levels. 1.16 Work Method and Trade Demonstration Submit to the SO for approval the work methods of various trades as required by the SO to ensure good in-process quality control and reasonably acceptable final workmanship. A marking system, where applicable, showing, inter alia, the control, grid and level reference lines shall be included in the work methods. Ensure that subcontractors engaged for each trade shall also comply with the work methods approved by the SO. As instructed by the SO, conduct trade demonstrations for all critical work methods as approved prior to full scale production in the Contract. Should it appear to the SO at any time that the work methods proposed by the Contractor will not ensure good workmanship in the Works, the SO may require the Contractor to make at his own cost and expense such modifications to the original work methods as the SO may consider necessary or appropriate. Employ only skilled workers who are capable of executing the Works in accordance with the work methods approved by the SO. When there is a change in subcontractors, the SO may instruct the Contractor to re-conduct the relevant trade demonstration if deem necessary. Approval by the SO of the Contractors work methods, revised work methods or any details and information provided under this subclause shall not in any way relieve the Contractors liabilities or obligations under the Contract. 1.17 Site Layout Plan After the Contract is awarded, submit a site layout plan to the SO indicating proposed locations of all temporary structures (for example site offices, workers' quarters, stores, hoistways, construction equipment and labour lines) for approval before their erection. Notwithstanding such approval, any such structures shall be relocated at the Contractors own cost and expenses when required to do so by the SO. All such materials and structures shall be kept away from proposed roads, driveways, car parks and services lines. Should any hoistway or structure be erected without the approval of the SO, pull down and re- erect the hoistway or structure in an approved position within 7 days from the date of instruction by the SO. Provide for the maintenance of all such structures in a clean, hygienic and safe condition for the duration of the Works. All such structures and hoistways shall be removed on completion of the Works. 1.18 Site Offices Within an agreed period of time from the date of taking possession of the Site, erect site offices complying with the requirements of the MEWR and remove them on completion of the Works or at a time approved by the SO. Submit proposals for the design (inclusive of PE calculations), TS 21/1065 978 Doc D.2/91 configuration and layout for the approval of the SO taking full consideration the site constraints and conditions. The following rooms shall have at least the minimum stipulated areas and complete with basic facilities, fittings and furniture,which can be made available at all times for use by the SO and the Employer: . S/N Facilities, Furniture and Fittings No. of Items . . . SO Room Resident Site Staff/ Consultant Room Meeting Room Sample Room . 1. Room (Minimum size andable to accommodate all facilities specified) [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . 2. Tables and Chairs . . . . . [to be (a) 1.5m x 0.8m office table complete [to be with at least 3 drawers specified by specified by user] user] [to be specified by user] [to be specified by user] . . (b) 1.5m x 0.8m working table complete with storage space for drawings [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . . (c) 0.8m wide side tables for computer and peripherals [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . . (d) 1.2m x 0.8m table [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . . (e) Chairs with hand rests [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . . (f) Chairs without hand rests [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . . (g) High Chairs without handrests (for working table) [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . 3 Steel Cabinet complete with Shelves and Double-Leaf Doors with lock [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . 4 Soft Board complete with Accessories [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . 5 White Board complete with Accessories [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . 6 Key cabinet [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . 7 Air-Conditioner of Minimum 10,000 BTU Output [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . 8 Telephone Installation . . . . . (a) Separate telephone line [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . . TS 22/1065 978 Doc D.2/92 . . (b) Telephone set [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . 9 Drawing Rack complete with Drawing Holders [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . 10 Electrical Installation, Connections and Accessories . . . . . (a) Lighting lux level [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . . (b) 13 Ampere socket outlet [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . . (c) 15 Ampere socket outlet [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . . (d) Data point [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . . (e) Emergency light [to be [to be specified by specified by user] user] [to be specified by user] [to be specified by user] . The doors leading to the SOs room, the Resident Technical Officers room and the meeting room shall be provided with locksets and all the keys to the locksets shall be given to the SO. Allow for the maintenance of the site offices, rest areas and all the facilities, furniture and fittings therein in a clean, habitable and good working condition to the satisfaction of the SO. The Contractor shall pay all charges for the provision and use of the telephone and electricity at the site offices. Should the Contractor fail to provide any of the aforementioned facilities, furniture and fittings after the commencement date of the Contract Period, the SO shall forthwith purchase and provide the same on the Contractor's behalf and all costs and expenses for such purchase and provision plus charges shall be recovered by the Employer from any monies due or becoming due to the Contractor or be recovered as a debt due by the Contractor to the Employer. 1.19 Provision of Equipment, Apparatus, Devices, etc. 1.19.1 Facsimile Machine Provide 1 plain paper (A4 size) facsimile machine at the site office. Facsimile machine of the thermal paper type is not acceptable. Keep such machine in the Resident Site Staff room throughout the Contract Period (including any extension thereof). The facsimile machine shall be for the exclusive use by the SO and/or Employer's officers only. Another facsimile machine should be provided for the Contractors own use. Pay all charges, costs and expenses and be responsible for the continuous proper, good and efficient working conditions and maintenance of such facsimile machine. Produce the maintenance agreement with the vendor to the SO for checking when requested. The maintenance agreement shall cover the whole duration of the Contract Period (including any extension thereof). TS 23/1065 978 Doc D.2/93 1.19.2 Digital Camera on Site Provide a digital still camera on the Site throughout the Contract Period (including any extension thereof), for the purpose of photographing site occurrences (within the Site) by the SO. The digital still camera shall have zooming functions and be capable of taking pictures at a digitised resolution of at least 10 million pixels. The digital still camera shall have an expandable and removable memory storage media with a minimum capacity of 128 GB, and be provided with all the necessary software and accessories for editing and transferred digital images from the camera to the computer hardware. The Contractor shall bear all the costs and expenses incurred arising from usage of the digital camera and shall be responsible for its continuous and proper functioning. 1.19.3 Torch Lights Provide sufficient torch lights on the Site at all times for use by the SO, Resident Site Staff and/or representatives from other Authorities. These torch lights shall be in good working condition and sufficiently bright enough for use. 1.19.4 Metal Detector Provide a battery-operated portable metal detector for the purpose of detecting metal reinforcement embedded in cement mortar joints of brickwalls. The detector must have either a light or buzzer indicator to indicate the presence of metal. 1.19.5 Moisture Meter Provide a portable, battery operated, digital LCD display moisture meter with integral electrode pins for measuring moisture content of timber doors and frames delivered to the Site. The moisture meter shall be capable of measuring actual moisture content of wood in the range from 8% to 44% (minimum) with a 1% indicating tolerance at 0°C to 40°C ambient temperature. The meter shall also possess a built-in device for performing simple calibration checks. 1.19.6 Personal Protection Equipment (PPE) Provide sufficient Personal Protection Equipment (PPE) such as safety helmets, safety boots, goggles and ear plugs for use by the Employer's officers and visitors visiting the Site throughout the Contract Period (including any extension thereof). The ownership of the safety helmets and safety boots shall be reverted back to the Contractor upon the satisfactory completion of the Works. Immediately replace those PPE which the SO considers to be not in good working condition. 1.19.7 Stationery for Resident Site Staff / Consultants Provide stationery and other devices for site use by the Employer's officers upon commencement of the Works. TS 24/1065 978 Doc D.2/94 1.19.8 Photo Copying Machine Provide one plain paper photocopying machine at the site office with the following Specification: (a) minimum [to be specified by user] ppm in black and white (b) Support paper up to 160gsm and A3+ (c) Auto paper selection (d) Auto response sensor The photocopying machine shall be kept in the Resident Site Staff room throughout the Contract Period (including any extension thereof). The photocopying machine shall be for the exclusive use by the SO and/or Employers officers only. Another photo copying machine should be provided for the Contractors own use. Pay all charges, bear all costs and expenses and be responsible for the maintenance of such photocopying machine. Produce the maintenance agreement with the vendor to the SO for checking when requested. The maintenance agreement shall cover the whole duration of the Contract Period (including any extension thereof). 1.20 Provision of Temporary Site Facilities/Utilities 1.20.1 Access Roads and Protective Crossings Repair and maintain all access roads serving the Site and provide temporary protective crossings over existing drains, channels, footways, etc. throughout the Contract Period (including any extension thereof). The Contractor shall be responsible for making good all damage and/or clearing away on Completion to the requirements of the relevant Authorities and to the satisfaction of the SO. 1.20.2 Temporary Electricity Supply and Installation Engage a LEW of appropriate grade to design and in charge of all temporary electrical installations necessary for building operations and works of engineering construction in accordance to SS 650-1; for site offices, meeting rooms, dormitories and etc. located within construction site in accordance to SS 638, at the date of closing of the Tender. Throughout the Contract Period and any time period when liquidated damages are imposed under the Contract, the Contractors LEW shall ensure good safety standards and practices and including the following: (a) For redevelopment sites, the Contractor is strongly encouraged to use M/s PowerGrid Ltds power supply to provide temporary electricity supply during the construction stage. All electrical generator sets shall be licensed with valid EMA licence. However, when the generator is used for the passenger cum material hoist and other general purposes, the minimum capacity of the generator for each block shall be upgraded to 100 kVA. TS 25/1065 978 Doc D.2/95 1.20.3 (b) The electrical switch board which holds the ELCB shall be housed in a switch box located at least 1.5 m from the floor level. (c) Socket-outlet assembly complete with miniature circuit breakers (MCBs) and residual current operated circuit breakers (RCCBs) shall be provided at each storey of the building block. The installation shall last the entire Contract Period unless authorised to be removed earlier by the SO or when permanent electricity supply is secured (whichever is earlier). The temporary incoming supply cable located within the precast refuse chute shall be supported with insulated lock bands. Upon termination of the temporary electricity supply, all cables and lock bands installed in the precast refuse chute shall be removed and the surface of the precast refuse chute shall be made good to a smooth finish. (d) All sheaths of cables, sockets outlets and plugs are in good working condition. (e) All cables are properly bound and do not cause obstruction to passageways, walkways and stairs. (f) All cables are properly supported with L-shaped galvanised steel brackets or insulated lock bands and placed at a suitable height, away from any source which cause mechanical damage. (g) All plugs, socket-outlets, socket-outlet assembly (SOA), cable couplers and plug adaptors are to be of the standard industrial type and of minimum classification of latest edition SS 638 and SS 650-1. (h) The supply to provide artificial lighting shall be taken from the socket-outlet assembly located at each storey. Fluorescent lighting of 1 200 mm enclosed in suitable mechanical enclosure to a minimum classification of IP 44 shall be used to provide lighting or to achieve a minimum lighting level of 400 lux. (i) Provide sufficient temporary lighting, according to the instruction of the SO, for workers/subcontractors to carry out in-process construction works such as internal plastering/skimming, wall and floor tiling, application of water-proofing membrane etc. within the units or common areas of the building under construction. Temporary Use of Lift For each building block in the Works designed with lift facilities, when needed during the progress of works, seek the SOs approval for the temporary usage of one lift upon completion of lift testing and commissioning by the lift subcontractor. All costs and expenses incurred in complying with the provisions of this clause shall be deemed to be included in the Contract Sum. The temporary use of the lift shall be subjected to the terms and conditions stipulated hereunder. Such terms and conditions shall be incorporated into the agreement to be executed between the Contractor and the lift subcontractor. The terms and conditions shall be as follows: (a) The Contractor shall seek the approval of the SO for the use of the lifts. (b) The Contractor shall arrange for a designated person to certify that the lifts are for temporary use and seek approval from MOM before it can be used. TS 26/1065 978 Doc D.2/96 1.21 (c) The Contractor shall provide proper protection such as plywood, adhesive tapes, etc. to the lift cages, floors, car doors, architraves, transoms and landing doors, etc. The Contractor shall ensure that the protection for the lifts is always in a proper condition. Any physical damage to the lifts shall be the responsibility of the Contractor. (d) The Contractor shall engage a full-time lift attendant to operate each lift. Under no circumstance shall a lift be left unattended when it is in operation. (e) The Contractor shall ensure that the lifts are not over-loaded. (f) The Contractor shall take up additional insurance for the use of the lifts as temporary use lifts and Public Liability coverage, naming the Employer and the lift subcontractor as the co-insured, for the period of usage. Copies of the insurance policies shall be given to both the SO and the lift subcontractor before the lifts are allowed to be used. Alternately, the Contractor may pay the lift subcontractor for taking up the insurance and public liability coverage on its behalf. (g) The Contractor shall be responsible for the daily maintenance of the lifts, such as cleaning up the cages and sills in order to prevent unnecessary breakdown and damage to the lifts. (h) The lift subcontractor shall service the lifts once a month during normal working hours. (i) Smoking is strictly prohibited in the lifts. (j) At least 3 days prior to handing over each building block to the Employer, a joint inspection shall be conducted between the Contractor and the lift subcontractor for the purpose of handing the lift back to the lift subcontractor. Any damage that occurs during or as a result of or arising from the temporary usage of the lift which affect the handing over of the lift to the Employer shall be the responsibility of the Contractor. All costs and expense for rectification and repair shall be borne by the Contractor, subject to verification by the SO. Protective Roof for Temporary Site Structures Provide appropriate protective materials for the roof of these temporary structures. The protective material shall be made of 18 mm thick timber ply. For site office and workers' quarters, the timber ply shall be laid in dual double layers; with one double layer laid just beneath the metal roofing sheet and another double layer at the bottom of the steel truss system supporting the metal roofing sheet. For all other temporary structures, such as toilets, carpenter yards, etc. the protective timber roof shall be laid in single double layer beneath the roofing sheet. However, at the sole discretion of the SO, such protective materials may not be necessary if the temporary structures are deemed far beyond the nearest building block under construction. Under such cases, there shall be no adjustment to the Contract Sum. The Contractor's PE shall consult the SO on these protective roofs before proceeding with the design of the temporary structures. TS 27/1065 978 Doc D.2/97 1.22 Construction Site Hoarding Submit a complete set of the hoarding workshop drawings to be endorsed by the Contractors PE for SOs approval. The proposed layout of the images and designs used on the hoarding shall be indicated on the plans and elevation of the workshop drawings submitted. All sites will use flat panel hoardings on all sides of the contract boundary lasting throughout the Contract Period including any period when liquidated damages are imposed under the Contract. The hoarding panels shall be white or off-white zincalume steel or galvanised steel flat panel. Maintain and upkeep the hoarding panels in good condition. As and when instructed by the SO, replace the hoarding panels to the satisfaction of the SO, at the cost and expense of the Contractor. As and when instructed by the SO, remove or relocate all or part of the hoarding panels with the signage and reinstate the affected grounds to the satisfaction of the SO at the cost and expense of the Contractor. On satisfactory completion of the Works, the hoarding panels with the signage shall be cleared away upon the approval of the SO. 1.22.1 Signage on Hoarding Provide images for the "Construction in Progress" and way-finding signage to inform the public that the project is under construction and for guiding the public on the correct way to take around a construction site. The "Construction in Progress" and way-finding signage shall be mounted conspicuously on the white or off-white zincalume steel or galvanised steel flat panel hoarding throughout the external perimeter of the contract boundary. (a) Ensure that the signage is printed on adhesive laminate film that is waterproof, fade- proof and durable against the weather. The colour setting on the printer shall be Adobe RBG. The signage shall be stuck onto the flat panel hoarding. (b) The signage shall be mounted at areas of high pedestrian traffic and/or high visibility and shall last throughout the Contract Period including any period when liquidated damages are imposed under the Contract. (c) The size of the "Construction in Progress" signage shall be 4.0 m in height and 2.7 m in length on a 6.00 m high flat panel hoarding. It should be scaled proportionately for hoarding of other heights. The signage shall be mounted at a comfortable viewing angle and level for the public. Seek the SOs approval for the appropriate size for the way- finding signage. (d) The signage shall not block or obstruct the hoarding design with images depicting the overall perspectives of the project, community images and project information and construction progress at all times. Seek the SOs approval of the appropriate placement of the signage. The SO shall instruct the Contractor to remove the signage should it be placed at an inappropriate location, at the cost and expense of the Contractor. (e) Conduct regular inspection of the condition of the signage to ensure the signage are in good condition. Should any signage be found to have faded or damaged, the SO shall instruct the Contractor to replace the defective signage, at the cost and expense of the Contractor and to the satisfaction of the SO. TS 28/1065 978 Doc D.2/98 1.23 Site Management Within 14 days from the date of the Letter of Acceptance, submit to the SO for his approval the following details on site planning: (a) Site organisational structure (b) Names, roles and responsibilities of Contractor's site management, technical and supervisory staff (c) Manpower schedule for each trade (d) Schedule of heavy equipment and machinery (e) Measurement Plan and Survey method (f) Safety Management System Within 30 days from the date of the Letter of Acceptance, submit to the SO for his approval the overall construction programme for each building block and/or phases of Works of the entire project. Furnish the SO with such further details and information as the SO may require in regard to the above items. Should it appear to the SO at any time that the site planning proposed by the Contractor is not able to ensure smooth progress and good workmanship in the Works, the SO is empowered to require the Contractor to make, at the Contractors own cost and expense, all necessary modifications to the plans. Approval by the SO of the Contractor's site planning details, revised site planning details and further information provided under this subclause shall not in any way affect, vary or relieve the Contractor's liabilities or obligations under the Contract. At least 14 days before the commencement of the Works by the subcontractors or the supply of the materials by the manufacturers / suppliers, submit the names of its subcontractors for the Works and the manufacturers / suppliers of the materials to the SO. Where there are changes made by the Contractor to its subcontractors / suppliers, such information shall be submitted to the SO 14 days prior to the commencement of the Works or supply of materials. TS 29/1065 978 Doc D.2/99 1.24 Employment of Contractors Site Personnel Employ the site personnel as specified in the table below and station them full-time on site upon the approval from the SO. The Project Manager, Workplace Safety and Health Officer, Environmental Control Officer, Security Guard and at least 50% of the total number of the stipulated Site Supervisors (Architecture, Structural, or Mechanical and Electrical Engineering) shall be employed and be full time on site from the commencement date of the Contract. The Contractor is given up to one month from the commencement date to deploy the Workplace Safety and Health Co- ordinator, Site Clerk and the rest of the Site Supervisors. Upon their employment, the site personnel shall be full time on site throughout the construction period including any period when liquidated damages are imposed under the Contract, unless otherwise approved by the SO. 1.24.1 S/N Type of Personnel Number of Each Type of Personnel to be Employed Fully Agreed andAccepted Rate by the Contractor andthe Employer For the Cost and Expense Deemed to be Allowed by the Contractor for the Employment of Each Personnel 1 Project Manager [to be specified by user] $ [to be specified by user]permonth 2 Workplace Safety & Health Officer (WSHO) [to be specified by user] $ [to be specified by user]permonth 3 Workplace Safety & Health Co-ordinator [to be specified by user] $ [to be specified by user]permonth 4a Site Supervisor Architectural Structural Works for [to be specified & by user] $ [to be specified by user]permonth 4b Site Supervisor for [to be specified Mechanical & Electrical by user] Works $ [to be specified by user]permonth 5 Environmental Control Officer (ECO) [to be specified by user] $ [to be specified by user]permonth 6 Security Guard [to be specified by user] $ [to be specified by user]permonth 7 Site Administrator [to be specified by user] $ [to be specified by user]permonth 8 Customer Relations [to be specified Officer (CRO) for by user] Building Maintenance Team $ [to be specified by user]permonth Qualifications/Experience/Responsibilities of Site Personnel TS 30/1065 978 Doc D.2/100 1.24.1.1 Project Manager The Contractor's Project Manager shall be qualified, competent and possess the skill, knowledge and ability to manage and co-ordinate the project effectively. The Project Manager shall be the Contractor's Representative as required under the Contract. The Project Manager shall possess the following minimum academic qualifications and experience: (a) 1.24.1.2 For Contract Sum less than $50 million, the candidate shall have: (i) A degree in Architecture, Civil/Structural/Electrical/Mechanical Engineering, Construction Management, Building Science or Quantity Surveying with 3 years of relevant post-graduate working experience in the building construction industry. The degree shall be recognized by the respective Professional Bodies professional institutions or Building and Construction Authority; or (ii) A diploma in Architecture, Civil/Structural/Mechanical/Electrical Engineering, Building Science, Building Management, Construction Management, Building Services Engineering and at least 8 years of relevant working experience in the building construction industry. The working experience should preferably be working on past projects and shall be recognised by SO as relevant working experience. (b) For Contract Sums of $50 million and above, the candidate shall have a Degree in Architecture, Civil/Structural/Electrical/Mechanical Engineering, Construction Management, Building Science or Quantity Surveying with 5 years of relevant post- graduate working experience in the building construction industry. The degree shall be recognized either by the respective Professional Bodies, professional institutions or Building and Construction Authority. (c) Regardless of the Contract Sum, the Project Manager shall possess a Certificate in Construction Productivity Management recognised either by the respective Professional Bodies, professional institutions or Building and Construction Authority. The Project Manager who is without "Certificate in Construction Productivity Management" shall attend the course conducted by BCA Academy and obtain it within 12 months upon his employment at the site. Where there is a need to attend the course conducted by BCA Academy, the fee will not be reimbursed. Workplace Safety and Health Co-ordinator / Workplace Safety and Health Officer (WSHO) The Contractor's Workplace Safety and Health Co-ordinator shall possess recognised and approved certification in construction safety to take charge of all matters related to safety. The said Workplace Safety and Health Co-ordinator shall spend their time fully performing the following: (a) To supervise safety and promote safety conduct (b) To inspect and rectify any unsafe place of work (c) To correct any unsafe practice TS 31/1065 978 Doc D.2/101 (d) To ensure that the provisions of the Workplace Safety and Health Act and its Subsidiary Legislation made thereunder are complied with Employ a full-time Workplace Safety and Health Officer to comply with the requirements under the Workplace Safety and Health Act, Workplace Safety and Health (Workplace Safety and Health Officers) Regulations. The Workplace Safety and Health Officer shall implement appropriate safety measures and ensure a safe work environment and safe work procedures in accordance with the Workplace Safety and Health Act and Subsidiary Legislation including the provisions of the Workplace Safety and Health (Construction) Regulations 2007 and the requirements specified under the Contract. 1.24.1.3 Site Supervisors The Contractor's Site Supervisors shall be qualified and competent, and possess the relevant skills, knowledge and the ability to supervise and co-ordinate the Works; and with any one of the following requirements: (a) Possess a National Certificate in Construction Supervision (NCCS) and at least 5 years of similar capacity relevant working experience in the building construction industry (b) Possess a recognised Diploma in Architecture / Civil / Structural / Mechanical / Electrical Engineering, Building Science, Building Management, Building Services Engineering, Construction Management and at least 3 years of relevant working experience in the building construction industry (c) Possess a Degree (foreign university) in Architecture / Civil / Structural/ Mechanical / Electrical Engineering, Building Services, Construction Management and at least 2 years of relevant working experience in the local building construction industry (d) Relevant working experience of minimum 15 years working in past projects. Notwithstanding the requirements as specified in (a) to (d) (inclusive) above, where the Contractor is required to employ the Site Supervisor for mechanical/electrical Works, the Site Supervisor must be suitably qualified under the mechanical/electrical engineering academic qualifications and with the relevant work experience and also received adequate safety and health training to ensure that the work which he oversees or supervises can be carried out safely. 1.24.1.4 Environmental Control Officer (ECO) Employ an Environmental Control Officer (hereinafter referred to as "ECO" for the purposes of this subclause) to comply with the Environmental Public Health Act Environmental Public Health (Employment of Environmental Control Officers) Order 1999. The ECO shall be employed on a fulltime basis where the Contract Sum is above $50 million or on a part-time basis where the Contract Sum is between $10 million and $50 million. The ECO shall be responsible for monitoring and advising the Contractor on the following main areas: (a) Control of disease-bearing vectors and rodents. (b) Proper management and disposal of solid waste. TS 32/1065 978 Doc D.2/102 (c) Control of noise and dust pollution. (d) Drainage and silt control. (e) Air and water pollution control. (f) General housekeeping management of the project/Site. The ECO shall conduct regular site checks and take prompt corrective actions to ensure that the workers' quarters, toilets, site offices and other facilities and general surroundings of the Site are kept clean, tidy and hygienic at all times. In addition, the ECO shall also ensure that the Site is kept mosquito-free at all times. The ECO shall possess a "Certificate of Competency (CoC) in Earth Control Measures (ECM) for Construction Site Personnel". The ECO who is without "Certificate of Competency (CoC) in Earth Control Measures (ECM) for Construction Site Personnel" shall attend the course conducted jointly by PUB and IES (Institute of Engineers Singapore) and obtain it within 6 months upon his employment at the site. The ECO shall compile and submit environmental related data to the SO upon request. This data can include: (i) Water, electricity and diesel consumption on site. (ii) Concrete wastage on site. (iii) Amount of construction debris generated on site. The ECO shall also compile a record of any checks by the Authorities (e.g. NEA for noise and vectors, PUB for ECM) and the result of such checks. This record shall also be submitted to SO upon request. If the Works have been certified more than 95% completed, the Contractor may write to NEAs Regional Office to seek approval to allow the ECO to perform on a part-time basis and copied to SO. There shall be no cost recovery from the Contractor if NEA is agreeable to allow the ECO to perform on a part-time basis. 1.24.1.5 Security Guards (a) Employ Security Guards from a Security Agency licensed by the Singapore Police Force with a minimum Grade of "C". Inform the SO in writing on the security agency which supplied the Security Guards, within 2 weeks from the commencement date of the Contract Period. (b) All Security Guards shall at all times be in proper uniform of their security agency with their names and identification tags on. Essential security enforcement equipment such as whistle, torchlight, walkie-talkie, shall be provided to them. They shall respond within 5 to 10 minutes whenever they are called either through telephone or walkie-talkie. They shall also have the necessary access to the telephone at the Contractor's site office during and after normal working hours for emergency reporting purpose. The Security Guards must not be armed with weapons that are disallowed by the Singapore Police Force. TS 33/1065 978 Doc D.2/103 1.24.1.6 (c) A proper guard post with adequate security lighting and communication facilities shall be erected at every major entrance to the Site. All temporary gates/openings along the fencing/hoarding shall be guarded by a Security Guard during normal working hours and locked up after normal working hours. (d) The Security Guards shall be responsible for the general security of the Site and shall ensure that unauthorised personnel and vehicles do not enter the Site. They shall also be responsible for the security of the Contractor and site offices during and after normal working hours. (e) The Security Guards shall be employed to perform site security duties on a 24-hour basis. A minimum of one Security Guard shall be on duty at any one shift including Sundays and public holidays throughout the Contract Period (including any extension thereof). No Security Guard shall leave the Site until he is properly relieved by a replacement, even if his shift has ended. (f) A proper record of the Security Guards' attendance must be kept and made available to the SO upon request. Site Administrator Employ [to be specified by user] full-time Site Administrator(s) at the site office to answer all in- coming calls during office hours and to attend to the clerical works as and when directed by the SO. The Site Administrator shall be proficient in basic software and equipped with good public relations skills and able to handle phone enquiries competently. 1.24.1.7 Customer Relations Officer (CRO) Deploy [to be specified by user] full-time Customer Relations Officer(s) (CRO) to manage the Building Maintenance Team (BMT). Notwithstanding other provisions in this clause, if the Contractor incurs additional costs and expenses over and above the agreed rates specified herein complying with the requirements stipulated in this clause, the Contractor alone shall bear such additional costs and expenses in full. TS 34/1065 978 Doc D.2/104 1.24.2 Certified CONQUAS Personnel Ensure that site personnel employed are recognised by Building and Construction Authority (BCA) under the Certified CONQUAS Manager and Certified CONQUAS Supervisor Schemes. To fulfil this requirement, the Contractor is allowed to have their existing site personnel recognised as Certified CONQUAS Manager and Certified CONQUAS Supervisors in addition to their existing role. S/N Type of Personnel Number of Each Type of Personnel to be Employed Based on Contract Sum Value Not Exceeding $50 Million Exceeding $50 Million Fully Agreed and Accepted Rate by the Contractor andthe Employer For Cost andExpense Deemed to be Allowed by the Contractor for the Employment of Each Personnel 1 Certified CONQUAS Manager 1 1 $ [to be specified by user]per Certified CONQUAS Manager per month 2 Certified CONQUAS Supervisor 1 2 $[to be specified by user]per Certified CONQUAS Supervisor per month The number of Certified CONQUAS Personnel are specified in the table above. The Contractor is given up to 12 months from the commencement date to deploy such personnel upon approval from the SO. In the event that the site personnel employed do not have the required certification, the Contractor shall employ personnel to fulfil the requirement, at its own cost and expenses. Upon their employment, the Certified CONQUAS Personnel shall be full time on site throughout the construction period including any period when liquidated damages are imposed under the Contract, unless otherwise approved by the SO. 1.24.3 Replacement of Site Personnel The SO shall be empowered to instruct the Contractor to replace at the Contractor's own cost and expense, any site personnel not carrying out their duties to the satisfaction of the SO. 1.24.4 Compliance with Requirements and Submission of Information of Site Personnel The employment of the site personnel shall be subject to the approval of the SO. Submit to the SO within one month from the commencement of works, the name, identity card numbers and documentary evidence of the educational qualifications and experience of all the site personnel employed by the Contractor. In addition, comply with the requirements and keep records and submit information to the SO or Employer upon request to show compliance with the requirements. (a) Keep records indicating the number of days the site personnel are employed for each month. (b) Except for the security guards and safety supervisors, all the site personnel employed shall be on the Contractor's monthly payroll. Keep records of monthly CPF or levy contributions as proof of employment. TS 35/1065 978 Doc D.2/105 1.24.5 Inclusion of Cost and Failure To Employ The Site Personnel The Contractor shall be deemed to have included in the Contract Sum for all costs and expenses it incurs in complying with the requirements stipulated in this clause. In the event of the Contractor not employing the number of site personnel, required by the Contract or not employing such site personnel for the period or periods required by the Contract, without prejudice to the Employer's rights under the Contract, the Contractor shall be indebted to the Employer at the rate or rates as specified for each of the respective site personnel per month and such indebtedness shall be deducted by the Employer from any monies due or becoming due to the Contractor or be recovered by the Employer as a debt due from the Contractor. These rate or rates shall be deemed to have been fully agreed and accepted by the Contractor and the Employer as the costs and expenses allowed by the Contractor for the employment of each of the respective site personnel for each month. For the purpose of this clause, each of the site personnel shall be employed by the Contractor for at least 20 days within a calendar month before he can be considered as being employed for that particular month under the Contract, except where expressly specified otherwise. In the event that the first and/or the last calendar month of the Contract Period or any period when liquidated damages are imposed under the Contract, have less than 20 days, each of the site personnel shall be employed for the full number of days in the said first and last calendar month of the Contract Period or any period when liquidated damages are imposed under the Contract. In the event that the deployment of the site personnel fails to comply with the requirements, the cost recovery for the period of non-deployment shall be based on the stipulated monthly rates on pro-rated basis. Notwithstanding other provisions in this clause, if the Contractor incurs additional costs and expenses over and above the agreed rates specified herein in complying with the requirements stipulated in this clause, the Contractor alone shall bear such additional costs and expenses in full. 1.24.6 Application for Release of Site Personnel The SO may consider a request by the Contractor in writing to release any of its site personnel from the obligations of this clause if the Works has been certified more than 95% complete. It shall be up to the absolute discretion of the SO to decide whether the Contractor's site personnel can be released and the number of site personnel to be released as provided for under this clause. A written approval from the SO shall be obtained in this respect. 1.24.7 Superintending Officer's Decision All differences and/or disputes arising under this clause including all subclauses under it (including questions relating to interpretation) shall be determined by the SO whose decision shall be final and binding. TS 36/1065 978 Doc D.2/106 1.25 Service Roads, Driveways and Drains For completed service roads, driveways and drains within the Site contract boundary, the Contractor is obliged to maintain washing and cleaning; and making good any damage arising from their own actions to the satisfaction of the SO all at the Contractor's cost and expense. If the Contractor fails to carry out his obligations as aforesaid, the SO may engage other parties to execute the outstanding works and all costs and expenses incurred shall be borne by the Contractor. 1.26 Existing Services and Cables/Services Detection Visit and examine the Site carefully and ascertain its nature and make provision in the Contract Sum or prices for the type of ground conditions, constraints and underground services. Take due care to safeguard all existing services that will be affected by the Works. Where existing services are required to be terminated or diverted for the execution of the Works, give the necessary notices to the Authority and the Employer. Co-ordinate site survey to identify the existing services and arrange for the Works to be carried out. Where in the case the SO is of the opinion that it becomes essential to divert permanently any sewer, drain, pipe, cable, or other services, the cost for the diversion shall be borne by the Employer. Provided always that such diversion does not form part of the Works. 1.26.1 Statutory Requirements Comply with all the requirements of the various Authorities in respect of the existing services at and around the vicinity of the Site, whether underground, on or above ground, or at the site peripherals. Terminate or divert all relevant existing services as required by the Authorities before work begins. 1.26.2 Information on Services Obtain information in relation to existing services from the relevant Service Providers. Verify actual sizes and locations of all services with the Public and Statutory Authorities and make enquiries as to the presence and location of any privately-owned land drains and services. Locate, identify and mark on site before commencing work. Arrange with and offer the Authorities all necessary assistance in ensuring timely diversion, disconnection, termination, or capping off of the services. (a) Detection of services located on site. (b) Locate and mark the positions of services affected by the Works. (c) Conduct detection of suspected underground services. Propose suitable method for acceptance by the SO. (d) Mark underground services with signboards giving type and depth and inform the Authorities concerned of any such services encountered on site. TS 37/1065 978 Doc D.2/107 1.26.3 Drains in Use Protect drains, manholes, gullies, vent pipes and fittings still in use and ensure that they are kept free of debris at all times. Make good any damage arising from the Works and leave clean and in working order at completion. 1.26.4 Bypass Connections Provide as necessary to maintain continuity of services to occupied areas of the Site and adjoining properties. Give sufficient notice to occupiers if shutdown is necessary during changeover. 1.26.5 Services to Remain Notify the SO and the Authorities or Employer of any damage. Make all arrangements for repair to the satisfaction of the SO, the Authorities or Employer. 1.26.6 Cable/Services Detection Provide cables/services detecting devices to locate all existing cables/services prior to the commencement of excavation or any other work such as driving of piles, piling of earth electrode and lightning conductors or poles and columns which are liable to damage existing buried services. Engage EMA licensed cables/services detection workers to carry out all cables/services detection work. The proposed line of excavation or area of other work shall be checked for existing services in a systematic manner by making sufficient passes in a grid formation to cover the entire area of work. The extent of checking carried out shall be properly documented and countersigned by the SO. The Contractor shall be liable for all costs and charges incurred if he damages any services. Seek assistance from the relevant Authorities if it has any query on the location of existing cables/services belonging to the Government Department or Statutory Board. In the case of PowerGrid or SPSL cables/services, the Contractor may seek assistance from the Cable Damage Prevention Unit, PowerGrid or SPSL. Engage the services of EMA Registered Excavator Operator only for all excavation Works. In the event the Contractor fails to employ EMA Registered Excavator Operator, no excavation works shall be allowed. 1.27 Damage to Public/Private Property In the event damage is caused to public/private services or property such as cables, pipes, fittings and fixtures, etc. by the Contractor whether by accident or otherwise leading to black- outs or other nuisance or inconvenience to the public or is likely to bring the Employer into disrepute, all costs and expenses incurred for necessary reinstatement or repairs including charges shall be recoverable by the Employer from the Contractor by deduction from monies due or becoming due to the Contractor, or as a debt due by the Contractor to the Employer. 1.28 General Housekeeping TS 38/1065 978 Doc D.2/108 (a) Periodic Cleaning Up All rubbish and debris shall be cleared from the Site and buildings under construction at least weekly or from time to time as they accumulate or when so directed by the SO. Particular attention shall be directed to those areas where other tradesmen or contractors will be working. Housekeeping shall be carried out in such manner and at such times so as not to cause any inconvenience to either the adjoining owners, occupiers and the public. Debris shall be wet to minimise the risk of dust pollution (b) Provision of Bins for Waste and Debris During the course of construction, provide proper bulk bins of adequate size and appropriate locations for the proper storage of construction waste, chemical waste and debris in compliance with the relevant legislative requirements or regulations imposed by MEWR. (c) Dumping of Debris And Rubbish Dispose of all unwanted debris, rubble or excess earth at MEWR approved dumping grounds/sites. All charges levied for the use of the dumping grounds/sites shall be borne by the Contractor. If the Contractor indiscriminately dumps construction debris, rubble or excess earth on land owned by the Employer or the Government without written permission, it shall remove all such debris, rubble, or excess earth from such land at its own cost and expense. 1.29 Time Required for Contractor to Prepare for Project Handover Inspection Complete the Works or any phase or sub-phase thereof as set out in the Letter of Acceptance in accordance to the Contract Period or any subsequent extensions of time approved by the SO. All completed Works or any phase or sub-phase thereof shall be handed over to the Employer within or by the Contract Period or any subsequent extensions of time approved by the SO, prior to the issue of any Completion Certificate. Note that the Contract Period has been computed to include the time allowed for preparation of handing over inspections. Therefore, the duration required for the preparation of and the handing over inspections shall be incorporated into the Programme for the Works or revised Programme, if any, to be submitted to the SO for approval, as required under the Contract. 1.30 Restriction on Use of Project Information for Publicity The Contractor and its subcontractors/suppliers shall not quote or make reference to the project design, products, technologies or methods of construction used in the Works for trade promotion, advertisement, publicity, etc. or for any other purposes without the written approval of the SO. This requirement shall not be applicable to proprietary products, technologies or methods of construction introduced by the Contractor or its subcontractors/suppliers. TS 39/1065 978 Doc D.2/109 1.31 Provision of Respiratory Masks Building contractors are required to provide suitable respirators for their outdoor workers, as well as the supervising consultants' site staff at the sites, when the haze level at the Site reaches a very unhealthy level with a 24-hour Pollutant Standards Index (PSI) value measured by NEA exceeding 200 or upon appropriate public advisories by NEA. The air-purifying respirators must have an efficiency to filter 95% of 0.3 micron diameter fine particle size, commonly referred to as N95. Start to purchase and stock up the N95 respiratory masks when the haze condition is approaching the unhealthy range with the PSI Index value exceeding 100. 1.32 Publicity Provide and render all necessary assistance to the SO or other authorised persons procuring publicity materials on any aspects of the construction works in progress. When directed by the SO, provide all brochures, quotations, subcontract agreements, invoices, etc., from its subcontractors, suppliers and specialists for goods and services provided for the Works, all at the Contractor's cost and expense. 1.33 Handover Inspection (a) (b) Notify the SO in advance to request for a handing over inspection and the following functional tests, where relevant. The extent of testing shall be agreed on with the SO. S/N Type of Test 1 Chokage Test for Main and Secondary Stack Pipe 2 Chokage Test for Rainwater Down Pipes and Down Pipes 3 Chokage Test for Branch Pipes Serving Units on Lowest Floor 4 Chokage Test for Branch Pipes Serving Units on Typical Floor 5 Leakage Test for Refuse Chute Flushing System 6 Water Pipe Pressure for Concealed Pipes 7 Gradient Test for House Drains 8 Gradient Test for House Sewer Lines 9 Gradient Test for Main Roof, Pump Room Roof, Staircase Roof, Lift Machine Room Roof 10 Gradient Test for Scupper Drains and Wash Area 11 Water Test for Toilet, Kitchen, Service Yard and Private Balcony 12 Water tightness Test for Window/Wall Joints 13 Water tightness Test for Precast Wall Joints Upon receipt of the Contractors request, the SO shall arrange a joint inspection date with the Employer. The Employer shall be present to witness the functional tests. In the event the tests fail to meet the requirements of the Contract, proceed to rectify the defect with due diligence and expedition and without delay, and arrange for re-tests in accordance with the requirements under the Contract. TS 40/1065 978 Doc D.2/110 (c) If the Works are considered to have met the requirements of the Contract, including the approved workmanship standards, and there is no major defect detected during the handover inspection, the Works shall then be taken over by the Employer. Otherwise, the SO shall give the Contractor a list of outstanding defects for rectification. The Contractor shall proceed to rectify the defects with due diligence and expedition and without delay. The Contractors liability to rectify the defects under this Subclause shall not be limited to the list of defects given by the SO, but shall include all other defects surfaced in between the handing over inspections. Upon completion of the defect rectification, the Contractor shall notify the SO in writing that all outstanding defects found in the inspection, as well as all apparent defects identified between the handover inspections have been rectified and shall request another handing over inspection. The provision of the preceding Subclause (b) above shall apply, mutatis mutandis. (d) If the Contractor is unable to hand over the Works to the Employer after 2 handing-over inspections, the SO shall invoke the provisions of the Clause 6 on "Nuisance and Irregularities". (e) The Contractor shall clean all parts of the project thoroughly. If the cleanliness of an area is not satisfactory before handing over to the Employer, the Contractor shall do repeat cleaning of the area at the Contractors own cost and expense. (f) The Contractor shall, before Completion of the Works, remove all rubbish, construction equipment and surplus materials, wash and scrub clean all floors, staircases, pavings, drains and all parts of the buildings and leave the Works in a clean and hygienic condition fit for habitation. The Site and periphery shall be cleared of all rubbish left from the Contractor's work. 1.34 Defects Management 1.34.1 Employment and Deployment of Site Supervisor Employ and deploy [to be specified by user] Site Supervisors full- time on the Site for every day where defect rectification works are carried out during the Maintenance/Defects Liability Period. For defects reported, deploy a full-time Site Supervisor to manage and complete the rectification works within 14 calendar days. In the event that Contractor is unable to meet the service standards of 14 calendar days, the Contractor is required to increase the number of Site Supervisors to eliminate the delay. All cost and expense arising from the additional manpower/resources deployed is deemed to have been included in the Contract. In addition, the Employer may exercise the provisions of Clause 6 "Nuisance and Irregularities" to address the unsatisfactory works. The Contractor's Site Supervisor shall be qualified and competent, and possess the relevant skills, knowledge and the ability to co-ordinate and supervise the defect investigation and rectification works. The Site Supervisor deployed to handle defects reported to Building Maintenance Team must be able to communicate with neighbours effectively. The Site Supervisor shall attend inspections together with the neighbours to better understand their requests and/or feedback, monitor the defect rectification to ensure timely completion of the rectification works, and attend the handover inspection together with the neighbours. The Site Supervisor is also required to conduct surveillance checks on the lift operation, illegal dumping and any other duties related to the project as instructed by SO. The Site Supervisor shall possess one of the following academic qualifications and experience: TS 41/1065 978 Doc D.2/111 (a) National Certificate in Construction Supervision (NCCS) and at least 5 years of similar capacity relevant working experience in the building construction industry. (b) Recognised Diploma in Civil/Structural/Mechanical/Electrical Engineering, Building Science, Building Management, Building Services Engineering and at least 3 years of relevant working experience in the building construction industry. The SO shall be empowered to instruct the Contractor to replace, at the Contractor's own cost and expense, any Site Supervisors not carrying out their duties to the satisfaction of the SO. In the event of the Contractor not employing the number of Site Supervisors required by the Contract or not employing such Site Supervisors for the period or periods required by the Contract, without prejudice to the Employer's rights under the Contract, the Contractor shall be indebted to the Employer at the rate of $ [to be specified by user] per month per Site Supervisor not deployed and such indebtedness shall be deducted by the Employer from any monies due or becoming due to the Contractor or be recovered by the Employer as a debt from the Contractor. This rate shall be deemed to have been fully agreed and accepted by the Contractor and the Employer as the cost and expense allowed by the Contractor for the deployment of a Site Supervisor. For the purpose of this clause, a Site Supervisor shall be deployed by the Contractor for at least 20 days within a calendar month before the supervisor can be considered as being employed for that particular month under the Contract, except where expressly specified otherwise. In the event that the first and/or the last calendar month of the BMT operating period or any period when liquidated damages are imposed under the Contract, have less than 20 days, each of the Site Supervisors shall be deployed for the full number of days in the said first and last calendar month of the BMT operating period or any period when liquidated damages are imposed under the Contract. Notwithstanding other provisions in this subclause, if the Contractor incurs additional cost and expense over and above the agreed rate specified herein in complying with the requirements stipulated in this subclause, the Contractor alone shall bear such additional cost and expense in full. On expiry of the Defects Liability Period, the Contractor may submit a written request to the SO for the release of the Site Supervisor. A written approval from the SO shall be obtained with this request. 1.34.2 Timeframe for Defects Management Ensure that an operationally ready Building Management Team (BMT) is set up in a timely manner. The defects and feedback reported can be through: (a) Physical BMT on site which is 12 months subjected to extension by the Employer. (b) Virtual BMT, which is an online version of BMT. (c) Any emails/instructions from Employer and SO. TS 42/1065 978 Doc D.2/112 Unless otherwise instructed by the SO, the BMT operating hours during the physical BMT stage shall be: Mondays to Saturdays: 8.30am to 5.30pm (except Sundays and Public Holidays). Whichever channel that is provided for feedback, attend to them for a period of [to be specified by user] months from the Completion Certificate. The personnel employed by the Contractor to manage the virtual BMT subsequently after the physical BMT has ceased must also possess the skill, knowledge and ability as specified in the "Employment of Customer Relations Officer". The service level during the virtual and physical BMT shall remain the same. At the Contractors own cost and expense, provide uniforms for all site personnel, including subcontractors and suppliers, etc deployed to carry out defects rectification works reported to BMT. The design of the uniform shall be submitted to the SO for approval at least 4 weeks before the BMT commences operation. 1.34.3 Provision of BMT Office Liaise with the SO for a suitable location within the Site to host the BMT for at least 2 months before the estimated completion date. The minimum size of BMTs Office is [to be specified by user] m2 and shall comfortably accommodate a waiting area for visitors, working space for Contractors Staff, Registered Technical Officer and Employers Representatives, office furniture/equipment and materials sample display area. Use materials that are non-combustible and water-resistant properties to enclose the BMTs Office. Provision of metal gate in front of the aluminium framed glass door is required. The plan layout of the items such as furniture, equipment within the BMTs Office shall be submitted to Employer for comments before setting up. The BMTs Office shall be equipped with: - an air-conditioning system: To provide thermal comfort for the occupants - a personal computer: Based on current Specification for "Computer Hardware And Software" for the visitors to make e-appointment - Two (minimum) office desks: including lockable drawers - steel cabinet of size: 1.7 m x 0.8 m x 0.4 m, including shelves and double-leave doors - a printer (capable to print up to A3 size) - a colour scanner - a photo stating machine - a fax machine, telephone - an auto-message and voice recording machine with 120-hour recording time - adequate fluorescent lighting - a digital camera - torch lights - chairs - aluminium suggestion box of size: 0.3 m x 0.3 m - soft board and white board of size: Size 2.4m x 1.2m, including accessories Doc D.2/113 TS 43/1065 978 - hot and cold drinking water dispenser - drawing rack: complete with drawing holders and office stationary - sofa at waiting area - vinyl flooring - area to display material samples (e.g., tiles, parquet flooring, water closet, wash basin, shower mixer and shower assembly, basin mixer, bib tap, electrical sockets and switches). Provide and install a signboard of minimum size: 1.4 m x 1.0 m, before starting the operation of the BMT. The design of the signboard shall be submitted to the SO for approval. Provide and install 2 notice boards at the BMTs Office. Each notice board shall be of size: 1.8 m x 1.2 m with aluminium casing and aluminium frame door in-filled with 5mm thick clear polycarbonate sheet. 1.34.4 Information on Key Personnel Within 14 days from the Date of Completion of the first building block and/or first phase of Works, submit the following to the SO for approval: (a) Name and contact numbers of the Contractor's key management staff and the appointed Site Supervisors for defect investigation and rectification works within the Defects Liability Period (b) Name and contact numbers of the relevant manufacturers, suppliers and specialist contractors etc. (c) Name and contact numbers of the stand-by plumber and stand-by electrician TS 44/1065 978 Doc D.2/114 1.34.5 Defects Investigation and Rectification During Building Maintenance Team Operation Within `14 calendar days from the date the access to the area is granted by Employer and/or upon SOs instruction and/or written notification by the SO, at the Contractor's own cost and expense, investigate, repair, rectify and make good to the satisfaction of the SO all defects, imperfections, shrinkages and other faults arising from or out of the use of materials or workmanship not in accordance with the Contract or from neglect or failure (of the Contractor) to comply with any obligation on its part under the Contract which may become manifest. Propose and implement a Quality Management System for defects rectification to ensure that the reported defects are rectified within 14 calendar days. The Quality Management System shall be submitted to the SO for approval. Prior to the commencement of any defect rectification works, submit a schedule of repair and method statement for the approval of the SO. Mobilise only skilled and certified workers who are capable of executing the works in accordance with the method statement as approved by the SO. All works must be attended to and supervised in person by the appointed Site Supervisor. Dust and noise must be minimised, whenever possible and cleaning up must be carried out daily if the unit is occupied and/or after the repairs. Inconvenience caused to others should be minimised by completing the defect rectification works in the shortest possible time. If there is failure by the Contractor to carry out its obligations as aforesaid, the SO may invoke the relevant provisions of Clause 6 "Nuisance and Irregularities". Without prejudice to the foregoing provisions, the SO shall have the right to engage other persons or contractors to repair, rectify and make good all such defect, imperfections, shrinkages and other faults if the same are not repaired, rectified and made good within 14 calendar days from the date the access to the unit is granted by resident and/or upon the SOs instruction and/or written notification by the SO, and the cost and expense incurred shall be recovered from the Contractor. In addition, the SO may invoke the relevant provisions of Clause 6 "Nuisance and Irregularities". 1.34.6 Rectification of Defects Prior to Issuance of Final Completion Certificate For the purpose of certifying completion of defect rectification prior to the issuance of the Final Completion Certificate, one month before the expiry date of the Defects Liability Period, arrange with SO for a final joint inspection. All defects listed after this joint inspection shall be rectified by the end of the succeeding one month commencing from the expiry date of the Defects Liability Period. A second final joint inspection shall be arranged to verify the completion of defects rectification. If the Contractor fails to rectify and make good the defects on the second final joint inspection, the SO may invoke the relevant provisions of the clause on "Nuisance and Irregularities". Notwithstanding the above, the SO shall in addition have the right to engage workmen or other contractors to rectify and make good all defects and the cost of rectification and charges imposed shall be recovered from the Contractor. TS 45/1065 978 Doc D.2/115 1.34.7 Standby Plumber and Electrician for Restoring Essential Services Provide a stand-by plumber and a stand-by electrician for 24-hour stand-by duties every day, including Sundays and Public Holidays, throughout the Defects Liability Period. The plumber and electrician need not be stationed on the Site but would be called upon to rectify defects causing disruption to essential supply such as water and electricity. The Contractor or its representatives shall be contactable 24 hours a day, for every day, including Sundays and Public Holidays throughout the Defects Liability Period by means of telephone, mobile phone, radio pager, facsimile or any other suitable modes of communication. The stand-by plumber and/or stand-by electrician shall attend to such defects within an agreed time with the SO for their services is made. They shall carry out the rectification expeditiously and in a workmanlike manner to restore the essential services quickly to minimise any inconveniences to the residents. In the event that the stand-by plumber and/or stand-by electrician fails to attend or fails to attend within the time frame stipulated, the SO may exercise the relevant provisions of the clause on "Nuisance and Irregularities". 1.34.8 Protection to Lift Interior During Defect Liability Period Provide protection to all interior finishes of lift car using an approved material, to protect the lift car walls, top of the lift car and the lift car base. Handrail protection shall be made of cloth tape or other durable protection cover approved by the SO. Check and maintain the condition of the protection to the interior of the lift car regularly. In the event that the protection is found to be not in good condition, replace and make good such protection at its own cost and expense. Seek the SO approval before the removal of lift car protection. If the Contractor fails to rectify and make good any defects, the Employer reserves the right to exercise its rights under Clause 6 on "Nuisance and Irregularities". 1.35 Precautionary Measures to Be Taken during a Disease Pandemic Implement necessary precautionary measures as advised by Ministry of Health or other relevant Authorities during a disease pandemic. Based on the recommendations from government's advisory, provide full cooperation and follow up expeditiously to plan for such a contingency and stock up necessary supplies or equipment (e.g., thermometers) so as to be able to implement the required measures at short notice. TS 46/1065 978 Doc D.2/116 1.36 Works Within Railway Protection Zone And Railway Safety Zone Comply with the Land Transport Authority (LTA) Code of Practice for Railway Protection and the Mass Rapid Transit (Rail Protection, Restricted Activities) Regulations for construction of the Works and other activities within the railway protection zone and railway safety zone. Submit proposals to the SO for approval on the effective measures for the protection of MRT above ground structures together with details of activities of mobile cranes, tower cranes and other mechanical equipment adjacent to the MRT line structures. Such submissions shall be made at least one month prior to the use of such construction equipment. No jib or lifting appliance or any other moving or stationary part of the mechanical construction equipment shall encroach within 6.0 m on plan from the edge of the nearest MRT above-ground or at-grade structure unless the construction equipment is restricted to work beneath the structure. The foundation of the mechanical construction equipment shall be certified structurally sound and adequate by the Contractor's PE prior to its installation. Install an auto cut-off system on tower cranes to prevent the top of the boom from swinging closer than 6.0 m from edge of the viaduct structure. The jibs of the cranes must always be pointed away from the MRT line structure. Any temporary access shall be sufficiently stable and level for construction equipment travel. Carry out regular checks to ensure that all mechanised construction equipment is in good working condition at all times. Employ only experienced, trained and competent operators for the operation of mobile cranes, tower cranes and other mechanical equipment. Install temporary height restriction gantries with signboard 6.0 m away from the edge of both sides of the viaduct structure for any access passing underneath the MRT line structures. 1.37 Recovery of Legal Costs for Court Proceedings All legal costs, charges and expenses (including but not limited to solicitors' fees as between solicitor and client) incurred by the Employer for the purpose of, or incidental to, the enforcement by the Employer of any rights and remedies under the Contract, or any other contracts between the Employer and the Contractor or in respect of any garnishee proceedings which may be brought or commenced against the Employer by the Contractor's creditors, may be deducted by the Employer from monies due or becoming due to the Contractor including any retention monies, financial bonds, or security deposits, or other bonds. 1.38 Completion of Site Works Take note that site works refers to all site structures/facilities, such as, but not limited to, driveway, car park, guard house, childrens playground/hard courts/footpaths and landscaping works, such as earth mound formation, turfing, trees and shrubs planting where included in the Works. Plan the stages of site works to be completed and submit to the SO for approval. TS 47/1065 978 Doc D.2/117 1.39 Erection of Temporary Buildings In addition to the submission of the site layout plan, further submit detailed structural plans and design calculations, certified by the Contractors PE, for temporary buildings of 2 storeys or higher, to the SO not later than 3 months from the commencement date of the Contract Period or 2 weeks before the actual commencement of the Works for such proposals, whichever is earlier. Bear all consequences for late submission. Erect all such temporary buildings in strict compliance with its PEs plans and calculations. The works shall be supervised by the Contractor's PE. Not later than 2 weeks after the completion of the Works, the Contractor's PE shall submit a Certificate of Supervision, stating that it has carried out such supervision work and is fully satisfied that the works have been constructed in accordance with its structural plans and design calculations as approved by the SO. 1.40 Goods and Services Tax Do not include in the rates and prices quoted in the Contract Sum, the GST chargeable for the supply of goods, services or Works required in the Contract. All rates and prices quoted shall be exclusive of the GST. The Employer shall reimburse the Contractor any GST charged on the goods, services or Works supplied. The Contractor shall declare its GST status in its Tender. The Contractor shall clearly indicate whether it is, or whether it will be, a taxable person under the GST Act. The Contractor shall, if available, furnish the GST registration number to the Employer. The Contractor will be deemed to be a taxable person if no declaration to the contrary is made in the Form of Tender. A Contractor that declares itself to be a non-taxable person under the GST Act but that becomes a taxable person after it has been awarded the contract shall forthwith inform the Employer of its change in GST status. The Contractor shall be entitled to reimbursement by the Employer of any GST charged on the goods, services or Works it supplies after its change in GST status. TS 48/1065 978 Doc D.2/118 1.41 Works and Materials Warranty In every case where the Specification require the Contractor's Specialist to co-warrant the Works and/or materials to be executed or supplied under the Contract, such Specialist, subject to such other requirements as may be prescribed in the Specification, may only be employed by the Contractor with the Employer's prior written approval. The Employer will approve such employment if the Specialist gives his written undertaking to execute the Deed of Warranty prescribed in the Specification. If such written undertaking is not given, then appoint an alternative Specialist willing to give the written undertaking. The employment of any Specialist who refuses to give its written undertaking is not recognised by the Employer, and no Specialist may commence any work or supply any materials before its written undertaking is given. The Employer's prior written approval of such Specialist's employment shall not in any way affect or diminish the Contractor's contractual obligations to the Employer in respect of any Works or materials executed or supplied by such Specialist on behalf of the Contractor, and the provisions of this subclause shall not in any way affect or diminish the Employer's entitlement to withhold the payment of any sums due to the Contractor by reason of the Contractor's and/or Specialist's failure to execute and submit the Deed of Warranty within the time specified. 1.42 Cost of Water and Electricity Provide suitable and adequate supply of water and electricity for the Site including for the purposes of conducting tests on the Works. Where directed by the SO, provide and allow other contractors on the Site employed by the Employer, free and unrestricted use of the water and electricity for carrying out testing and commissioning of such other contractors' works. Bear all costs and expenses for the water and electricity consumed at the Site, including the cost of water and electricity consumed for carrying out testing and commissioning by such other contractors employed by the Employer on the Site. Where applicable, the SO may at his/her sole discretion, direct the Contractor to transfer the account for the water and electricity supply to the Employer or such Management Corporation or such other party. The Contractor shall be deemed to have included in the Contract Sum for all costs and expenses incurred in complying with the requirements stipulated in this Subclause. 1.43 Site Control and Security 1.43.1 Identification Pass Provide a serially-numbered security identification pass to each of its workers and subcontractors' workers. The identification pass shall consist of the worker's photograph, name, identification card number or passport number and name of the Contractor. Issue temporary entry passes, on a day to day basis, to workers from other contractors employed by the Employer or other Government/Statutory Board Authorities or other companies carrying out works on the Site. Be responsible for controlling and issuing these security identification passes and temporary entry passes. Maintain an updated list of the passes issued for accountability and to facilitate enforcement checks. Ensure that all workers on the Site wear and display their passes prominently and securely at all times while working on site. TS 49/1065 978 Doc D.2/119 1.43.2 Erection and Removal of Temporary Metal Hoarding Unless otherwise specified, provide, erect and maintain a continuous metal hoarding around the entire contract boundary before the commencement of Works. The hoardings shall be erected at not less than 300 mm away from any permanent structure such as footway, drain, pipeline, etc. Refer to the drawings for the location and type of hoardings to be used. Should there be failure to comply with this requirement, the SO reserves the right to impose any action deemed necessary and any cost and expense incurred thereof, including charges that shall be recoverable from the Contractor. As and when instructed by the SO, remove, relocate, reconstruct all or part of the hoardings and reinstate all the affected grounds to the satisfaction of the SO, all at the cost and expense of the Contractor. Submit a complete set of workshop drawings to be endorsed by its PE and approved by the SO. Provide metal gates/doors for the main and side entrances. Location of these entrances shall be approved by the SO. There shall be a maximum of 2 entry points for the entire Site, unless otherwise approved by the SO. Close the metal gate at the main entrance (for vehicular traffic) and lock up after working hours when construction activities have stopped. Provide a side entrance beside the main gate for passage of workers and visitors that can be monitored by the Security Officers. These entrances/gates and the perimeter shall be well-lit during the hours of darkness (7.00 pm to 7.00 am). (a) (b) Comply with the following minimum requirements for the flat panel hoardings: (i) Use a minimum of 0.60 mm thick steel with zinc/aluminium alloy coating for the metal hoardings. All exposed metal sheet surfaces of the metal hoardings shall be finished with paint coating. (ii) The full height of the hoardings shall be 6 m, the hoardings comprising an overhang roofing that has a vertical height of 1 m. There shall be no use of netting. (iii) Use corrugated panel for the overhang roofing. (iv) There shall be no struts at the exterior of the hoardings where it is visible to the public. (v) The colour for the flat/corrugated panel hoardings and the overhang roofing shall either be white or off-white. Comply with the following minimum requirements for the corrugated panel hoardings: (i) Use a minimum of 0.42 mm thick steel with zinc/aluminium alloy coating for the metal hoarding. All exposed metal sheet surfaces of the metal hoardings shall be finished with paint coating. (ii) The full height of the hoardings shall be 4 m with no overhang roofing and no netting (as shown in the drawings). TS 50/1065 978 Doc D.2/120 (iii) The colour for the flat/corrugated panel hoardings and the overhang roofing shall either be white or off-white. Use timber posts and horizontal bracings of common grade timber under strength group A of SS CP 7 and/or steel members of grade S275. Use a minimum of grade 30 concrete foundations. "DANGER - KEEP OUT", "NO TRESPASSING" and "WORK IN PROGRESS" signs in 4 official languages shall be displayed on the exterior side of the hoardings. Print these signs using the template provided. Mount the signs only on the corrugated hoardings where required and not on the flat panel hoardings. The size of these signboards is specified in the drawings. The position of the lightings is critical in achieving a professional look and feel for the entire project. Do not install the lightings (LED light fixtures) on the design panel this prevents covering the messages or community photos on the hoardings design panels. Locate the lightings above the design panel instead. Ensure that the hoardings erected are illuminated adequately to achieve a maintained illuminance of average 10 lux, or as otherwise instructed by SO. Maintain the hoardings and gates at all times to ensure no deterioration of the structures and fading of the paint works throughout the Contract Period (including any extension thereof). On satisfactory Completion of the Works, clear the hoardings away upon the approval of the SO. 1.44 Registered Trade Subcontractors At the time of tender, submit the list of subcontractors intended to be engaged for the Works. Submit with the list, with details such as the relevant track records of the firms, the qualification of personnel and details of equipment to be engaged for the Works. All subcontractors for the Works are subject to the SOs acceptance. Ensure that the Contractors appointed first-level subcontractors have valid Building and Construction Authority (BCA) or Ministry of Finance (MOF) registration at the time of appointment. If the appointed first-level subcontractor is registered with BCA, ensure that the appointed first-level subcontractor is registered under the appropriate BCA workhead. At least 14 days before commencement of the Works by the subcontractors for the respective trades, confirm the name of its subcontractors for the Works to the SO. In the event that there are changes to any of the Contractors subcontractors, submit such information to the SO. The Contractor shall be responsible for any eventual delay in the progress of the Works owing to its failure to ensure the required on-time registration of its subcontractors and no extension to the Contract Period shall be granted on account of such delays. TS 51/1065 978 Doc D.2/121 1.45 Engagement of Bizsafe Level Certified Subcontractors All subcontractors engaged by the Contractor shall possess a valid bizSAFE Level [to be specified by user] Certificate awarded by the Workplace Safety and Health Council. Ensure that all subcontractors possess a valid certification throughout the entire period which they are engaged to carry out works on site. At the point of engagement, if any of the subcontractors have not attained the aforesaid certification, seek written approval from the SO for their engagement, provided that the Contractor gives a written undertaking to the SO that the subcontractor shall attain the aforesaid certification within 6 months or before work commencement on site, whichever is earlier. The SO may invoke the provisions of Clause 6 "Nuisance and Irregularities" if they fail to meet the above requirement. 1.46 Insurance Policies The Contractor shall warrant that the insurance policies issued in accordance with the Conditions of Contract include the following requirements: (a) (b) Insurance for Work Injury Compensation (i) The Policy shall be issued in a prescribed form as agreed with the Employer. (ii) The Insured shall be "(Name of Contractor to insert) as Contractor and all its subcontractors, and the Employer as Principal FTRR & I". (iii) The period of insurance shall commence from the date the Site is handed over to the Contractor and shall end upon expiry of the Defects Liability Period under the Contract. The Policy shall firstly cover the whole of the original Contract Period plus 6 months and plus a further 12 months for Defects Liability Period. Insurance for Personal Injury and Property Damage (i) The Policy shall be issued in the joint names of the Employer, the Contractor and all its subcontractors. (ii) The limits of liability shall be read as follows: (iii) (a) In respect of any one accident: $ [to be specified by user] (b) Unlimited for the period of insurance The period of insurance shall commence from the date the Site is handed over to the Contractor and shall end upon expiry of the Defects Liability Period under the Contract. The Policy shall firstly cover the whole of the original Contract Period plus 6 months and plus a further 12 months for Defects Liability Period. TS 52/1065 978 Doc D.2/122 (iv) The period of notice for cancellation of the Policy, if such a period is stipulated, shall read 30 days. (v) The Policy shall expressly include coverage of the following risks: (vi) (a) Death, bodily injury or damage to property caused or occasioned by the Insured's subcontractors or by such subcontractors' employees. (b) Death, bodily injury or damage to property caused or occasioned by or connected with or arising from the ownership, possession or use by or on behalf of the Insured of any equipment or machinery not expressly specified in the Schedule of such equipment or machinery. (c) Liability assumed by the Insured by agreement, unless such liability would have attached to the Insured notwithstanding such agreement. (d) Liability in respect of loss or damage to property belonging to or in the charge or control of the Insured or of any servant or agent of the Insured. (e) Liability in respect of injury to or illness of any person or loss or damage to any property or land or building caused by vibration or removal or weakening of support (f) Liability in respect of injury, illness, loss or damage caused by or connected with or arising from any commodity, article or thing supplied, repaired, altered or treated by or to the order of the Insured, happening at any of the Insured's premises. The Policy shall expressly contain the following endorsements: (a) "This Policy shall cover all the Contractor's insurance obligations with regard to personal injuries or death and injury or damage to property real or personal (including property of the Employer but not the Works themselves) arising out of or in the course of or by reasons of the carrying out of the Works stated in the Contract between the Employer and the Contractor (name of Contractor to insert)." (b) "Each of the parties comprising the Insured shall for the purpose of this Policy be considered as a separate and distinct unit and the words "the Insured" shall be considered as applying to such party in the same manner as if a separate policy had been issued to each of the parties and the insurers hereby agree to waive all rights of subrogation action which they may have or acquire against any of the aforesaid parties arising out of any accident in respect of which any claim is made hereunder provided nevertheless that nothing in this clause shall be deemed to increase the limitation on extent of Insurer's liability in respect of any one accident or series of accidents as stated in the Schedule." TS 53/1065 978 Doc D.2/123 (c) 1.47 (c) "This Policy is extended to cover the employees and/or representatives of the Employer, consultants, other professional parties and Resident Site Staff whilst on the contract site as third parties." (d) "Notwithstanding anything stated in the Policy to the contrary, cover under the Policy shall not be suspended in the event of stoppage of work by the Contractor on the contract site from any cause for a period not exceeding 90 days. In the event of partial or total cessation of work, the Insured shall use diligence and do all things reasonably practicable to protect the insured property. Subject otherwise to the Terms Exceptions and Conditions of this Policy." (e) "All deductibles shall be borne by the Contractor." Insurance for Works (i) The Policy shall be issued in the joint names of the Employer and the Contractor. (ii) The Works insured shall read the project title given in the Employer's Letter of Acceptance. (iii) The sum insured shall be the same as the Contract Sum. (iv) The period of insurance shall commence from the date the Site is handed over to the Contractor and shall end upon expiry of the Defects Liability Period under the Contract. The Policy shall firstly cover the whole of the original Contract Period plus 6 months and plus a further 12 months for Defects Liability Period. (v) The period of notice for cancellation of the Policy, if such period is stipulated, shall read 30 days. (vi) The policy shall expressly contain the following endorsements: (a) "This Policy shall cover all the Contractor's Works insurance obligations stated in the Contract between the Employer and the Contractor (name of Contractor to insert)". (b) "Notwithstanding anything stated in the Policy to the contrary, cover under the Policy shall not be suspended in the event of stoppage of work by the Contractor on the contract site from any cause for a period not exceeding 90 days. In the event of partial or total cessation of work, the Insured shall use diligence and do all things reasonably practicable to protect the insured property. Subject otherwise to the Terms Exceptions and Conditions of this Policy". (c) "All deductibles shall be borne by the Contractor". Contract Documents and Reference Material on Site Keep at the Site the following: TS 54/1065 978 Doc D.2/124 1.48 (a) A complete set of the signed contract documents described in the Agreement. (b) A complete set of the further or revised Drawings and instructions referred to in the Conditions. (c) The relevant Codes of Practice or Standards referred to in the Specification. (d) These documents shall be made available for inspection and use by the SO, and any other person authorised by the SO in writing. Prohibition of Dogs in Construction Sites Do not rear or keep dogs at the Site for any purposes or under any circumstances, regardless of whether or not the dogs are licensed with Agri-Food and Veterinary Authority of Singapore (AVA). The feeding of stray dogs beyond the contract boundary by any site personnel is also prohibited. The Contractor shall be responsible for complying with this requirement and shall take the necessary measures which include but are not limited to the following: (a) Providing designated waste bins with covers for food waste disposal at workers quarters, workers rest and recreation areas, and other areas where workers are likely take their meals. The waste bins should remain closed at all times to prevent dogs from foraging for the disposed food. (b) Ensuring that the waste collector removes the food waste from the Site on a daily basis. (c) Putting up notices at prominent areas within the Site as well as on the external face of the hoarding to remind workers and members of the public not to feed stray dogs. (d) Having a system of regular site checks which should also cover the secluded spots within the Site where stray dogs could hide, such as under storage containers. The Contractor shall keep a record of such checks indicating the days, time and names of site personnel conducting the checks. The records shall be made accessible to SO upon request. (e) Having a system of regular reminders to all site personnel (security guards and customer relations officers inclusive) on this requirement. (f) Informing AVA immediately for assistance if the presence of stray dogs is found within or at the vicinity of the Site. If the Contractor is found to have breached the above requirement, the SO may invoke the provisions of Clause 6 "Nuisance and Irregularities". TS 55/1065 978 Doc D.2/125 1.49 Lightning Protection to Temporary Structures and Metal Structures Ensure that all temporary buildings such as site office, site electrical substation, workers quarters, carpenter and bar bending sheds and temporary structures with continuous metal such as steel framework, scaffolding, tower cranes, batching plants and mobile machinery such as crawler cranes and concrete pumps are adequately and effectively protected from lightning strike at all times. The lightning protection system shall be in accordance with and complying with the latest edition of SS 555. Submit detailed risk assessment and management, drawings showing the design of the lightning protection system, consisting of the air-termination system, down conductor system and earthtermination system, duly signed by the Contractors PE (Electrical) stating that the design complies with the latest SS 555. For temporary structures without Lightning Protection System (LPS), a PE certification with reasons shall be provided. The Contractors PE (Electrical) shall provide a Certification of Supervision on the lightning protection system together with the earthing reports not later than 3 weeks after the erection of the temporary structure and before usage. The Contractors PE (Electrical) shall also conduct routine inspections including submitting earthing reports once every 6 months to ensure that the Contractor has provided adequate and effective lightning protection system for the Site. The inspection and earthing reports are to be submitted to the SO and a copy shall be kept in the site office and made available for inspection at all times. 1.50 Computer Hardware and Software 1.50.1 Computerised Project Management Software Within one month from the commencement date of the Contract Period, provide and implement a Computerised Project Management Software (CPMS) during the Contract Period (including any extension thereof). The SO and the Employer's officers shall be allowed to have full and free access and usage of the CPMS at all times. Use the CPMS which shall be installed on the Site to prepare the programme for the Works based on the Critical Path Method. The programme for the Works shall include the duration, early start/finish dates, late start/finish dates and floats for all activities involved in the Works. It shall also include constraints and parameters such as fixed start/finish and target start/finish dates for the activities and milestones for the different phases or stages of the Works. The programme for the Works shall comprise summary and detailed reports in textual and graphical forms. It shall be updated monthly or as and when required by the SO to indicate, inter alia, the critical path, actual start and finish dates of completed activities, actual start dates and percentage completion of the activities in progress, and target start and finish dates of the delayed activities, their slippages and floats. Submit to the SO the actual programme for the Works within 3 weeks after the Date of Completion. 1.50.2 Computer Hardware Within one month from the commencement date of the Contract Period, provide the computer hardware during the Contract Period (including any extension thereof) and till closing of BMT. TS 56/1065 978 Doc D.2/126 1.50.2.1 Personal Computer Provide [to be specified by user] Personal Computers (PC) for the exclusive use of the SO and unless specified otherwise, 3 units of PC for BMT operation. The PC shall comply with the following minimum requirements: (a) An Intel Core i5-4670 Processor of 3.4GHz equivalent or faster processor. (b) 4 GB DDR3 1600MHz Memory equivalent or better. (c) 500 GB or more SATA 3.0Gb/s Hard Drive equivalent or better [The hard disk must have 2 partitions e.g. C and D drive]. (d) An Intel® HD Graphics 4600 equivalent or better. (e) One 24" LCD monitor equivalent or better. (f) System BIOS updateable via software should be licensed flash BIOS of the latest version. (g) One keyboard. (h) One optical USB mouse or compatible. (i) One DVD writer. (j) Wireless enabled. (k) Casing shall be secure and come with one good quality chassis lock of unique combination. AIl keys to the lock shall be given to the SO. (l) Include all the necessary features and accessories required to support the type of broadband connection services specified in this Clause and all subclauses under it. (m) Loaded with the software as specified in this clause including all subclauses under it. The PC shall be Microsoft certified. 1.50.2.2 Internet Connection The Contractor shall at its own cost and expense provide and maintain Broadband Connection Services and WiFi via a major Broadband Service Provider, e.g. Starhub, M1, SingNet or equivalent to be approved by the SO) for the PC during the Contract Period (including any extension thereof) and till closing of BMT operation. The minimum connection speed to be provided is as follows: (a) 50 Mbps for cable broadband, or (b) 100 Mbps for fibre TS 57/1065 978 Doc D.2/127 The broadband connection shall be catered solely for the PC. Access to the broadband connection must be adequately secured with password protection to prevent unauthorised usage or network eavesdropping. 1.50.2.3 Laser Printer Provide [quantity to be inserted] laser printer equivalent or better, complying with the following minimum Specification: 1.50.2.4 (a) At least 16 MB of RAM and upgradeable to at least 160 MB. (b) Able to print at least 20 pages of A4 per minute and 11 pages of A3 per minute. (c) Automatic Duplex Printing Unit. (d) Print at 600 x 600 dpi resolution or more. (e) Support high speed bidirectional IEEE 1284-compliant parallel port (C-type connector). (f) Support PCL 5e, PCL 6 and Postscript Level 3 emulation. (g) Must be able to support printing in the software specified in this Clause, including all subclauses under it. (h) Bundled with drivers for the software specified in this Clause, including all subclauses under it. Uninterruptible Power Supply (UPS) Provide [quantity to be inserted] Uninterruptible Power Supply (UPS) equivalent or better, complying with the following minimum Specification: (a) Conform to the following industry standards: IEEE 446, NEMA PE1, ANSI C62.41, IEEE587B, IEC 801146; (b) Conform to the following safety standards: UL 1778, CSA C22.2 and VDE (c) 10 minutes or more runtime at full load (d) Provide alert on AC power failure, power restore and diagnostic tests through management software (e) Provide at least 3 output ports (f) Include all connecting cables joining the UPS output ports and equipment. TS 58/1065 978 Doc D.2/128 1.50.2.5 Colour Scanner Provide [quantity to be inserted] colour scanner equivalent or better complying with the following minimum Specification: (a) Flatbed, one-pass colour and monochrome (b) At least 600dpi x 600dpi resolution (c) Able to scan A4 size documents (d) Support Universal Serial Bus(USB) port (e) Include(s) scanning software that can display the image file size to users at the preview screen (f) Able to support all image formats including but not limited to: - TIFF - BMP - JPEG - FPX - GIF - WMF - PDF (g) 1.50.3 Bundled with drivers for the software specified in this clause including all subclauses under it. Computer Software Within one month from the commencement date of the Contract Period, provide the computer software during the Contract Period (including any extension thereof). Provide the latest version of the following licensed software packages (full packs with original licences, documentation and media provided) for each PC and/or tablets provided under this Clause, including all subclauses under it: (a) Windows operating system (b) Microsoft Project (c) Microsoft Office (d) Firewall and anti-virus package (e) Internet Explorer TS 59/1065 978 Doc D.2/129 (f) BIM Revit software (g) NavisWorks (for site staff to view BIM model) Adopt the software listed above so as to ensure compatibility with Consultants IT environment and applications. Alternative software may be proposed, subject to the SOs approval and provided the software does not pose any compatibility issues. Purchase maintenance license for the Virus Scan software to cover the Contract Period (including any extension thereof). The PC must be set to automatically scan for virus at least once a day when the PC is switched on. 1.50.4 Computer Software Licensing All the computer software as specified in this Clause, including all subclauses under it shall be licensed copies obtained from Authorised distributors or dealers. The Contractor shall at its own cost and expense provide any software upgrade, to the latest version or release upon request by SO, during the Contract Period (including any extension thereof). Ensure that only authorised software are used with the hardware and obtain written approval from the SO before installing any software other than the ones specified in this Clause including all subclauses under it, into the computer hardware system. 1.50.5 Approval and Testing of Computer Hardware and Software Submit Specification and details of the computer hardware and software as specified in this Clause including all subclauses under it to the SO for approval BEFORE the purchase of the hardware and software. The Contractor shall at its own cost and expense make such necessary arrangement for the hardware and software to be tested at the relevant Consultant's office and the subsequent delivery to the work site upon request by the SO. 1.50.6 Computer Furniture and Accessories Provide the necessary furniture and accessories at the site office to accommodate and facilitate the usage of the computer hardware and software. The PC designated for the exclusive use of the SO shall be located in a fully enclosed room within the site office. The room shall be of minimum size 8 m² as specified. The room shall be provided with a lock and be partitioned in half-height glass panels. 1.50.7 Computer System Maintenance Ensure that the computer hardware and software are in good working condition and pay for all maintenance, licence fees, subscription fees, etc. for the hardware and software during the Contract Period (including any extension thereof). If the Contractor fails to make available the hardware and software within one calendar month from the commencement date of the Contract Period or fails to rectify any hardware or software faults, within one day, the SO will make the necessary arrangement to acquire or to rectify the faults and all costs and expenses thus incurred shall be deducted from payments due to or becoming due to the Contractor or recovered as a debt due from the Contractor. TS 60/1065 978 Doc D.2/130 1.50.8 Security Make all necessary arrangements and provisions to prevent theft/burglary of the computer hardware and software. Replace any stolen or missing hardware and software within 3 days of such occurrence, failing which the SO will make the necessary arrangement to acquire the systems and all costs and expenses thus incurred shall be deducted from payment due to or becoming due to the Contractor or recovered as a debt due from the Contractor. 1.50.9 Unauthorised Usage Ensure that the hardware and software are not used for any other purpose except for those approved by the SO. 1.50.10 Email Account Apply for and maintain an email account to facilitate transmission of information and correspondence. Provide the email address to the SO within 1 month from the date of the Letter of Acceptance. 1.51 Assignment of Copyright of Photographs, etc Assign the copyright of the photographs (including the prints/slides/transparencies/negative) taken and all documents prepared under this Contract to the Employer. The Employer shall have unfettered rights to use or reproduce all the photographs (including the prints/slides/transparencies/negatives) taken and all documents prepared by the Contractor under this Contract for any purpose other than for the purpose for into which the Contract was entered. In the event that third parties are engaged (by the Contractor) to take the photographs (including the prints/slides/transparencies/negatives) or prepare the documents, procure the assignment of the copyright from such third parties to itself and thereafter, assign the copyright to the Employer. The Contractor and/or any third parties are strictly prohibited from using or reproducing any of the photographs (including the prints/slides/transparencies/negatives) taken and all documents prepared under this Contract in any other publication or for any other purpose whatsoever. 1.52 Provision of Envelopes for Keys During Handover Upon successful handover of the Works to the Employer after inspection by the SO and the Employer, provide the necessary number of envelopes to contain the household keys of each area or room in the Contract. Each envelope provided shall fulfil the following requirements: (a) C6 size (114 mm by 162 mm) (b) Key envelope with string and white eyelet (c) 120 gsm paper (d) Colour white TS 61/1065 978 Doc D.2/131 Propose the type of envelope to the SO for approval. The 2 external sides of the envelope may either be printed or stamped with the following information: (e) On the Front of the envelope Print/Stamp in Arial Black Font Type of Font Size 18, the following statement: KEY TO PREMISES NO. [to be specified by user] (f) On the Back of the envelope: To print/stamp in Arial Black font type of font size 12, the following statements: S/N Location No. of keys 1 [to be specified by user] 2 [to be specified by user] 3 [to be specified by user] 4 [to be specified by user] Total 1.53 [to be specified by user] Schedule of PEs Submission Provide the required PEs submissions as specified for the Works and/or as agreed with the SO. These submissions shall include but not be to limited the following: (a) Site offices (b) Temporary buildings (c) Passenger cum material hoist foundation, masts and tie-back (d) Metal Access scaffold and working platforms. (e) Alternative system to safety net system (f) Working platforms for lift shafts and voids wall (g) Protective Shelter as Overhead Shelter (h) Tower cranes and other tall construction equipment foundation and tie-back (i) Mobile crane and piling machine access (j) Temporary staircases (k) Planking and strutting (l) Rectification of defective work (m) Design of formwork TS 62/1065 978 Doc D.2/132 1.54 (n) Formwork system for reinforced concrete water tank (o) Metal roof structural plans and fastening details Earth Control Measures The Contractor shall be responsible for the implementation of effective Earth Control Measures (ECM) during construction stage at all time. The ECM shall be implemented according to the Code of Practice on Surface Water Drainage and meet the requirement under the latest Sewerage and Drainage Act Cap 294. Note that ECM are meant for the containment and treatment of silty rainwater runoff only, and not meant for the treatment of process water from construction activities such as slurry from tunnelling, pipejacking and bore-piling works. Such process water shall be handed and treated to comply with the requirements under Environmental Protection and Management Act (Chapter 94A). Provide schematic diagrams outlining the ECM for the whole duration of the construction activities, taking into account the various ECM requirements under different phases of construction activities. The ECM plan shall be designed and endorsed by a Qualified Erosion Control Professional (QECP) and form the basis for the Contractor to price for ECM. The Contractor shall be deemed to have included all the costs and expenses for complying with all ECM requirements in the Contract Sum. Engage a QECP to design ECM. Implement ECM accordingly to the QECP's ECM plan before earth works starts. During the course of construction works, engage a QECP to review the effectiveness of the ECM regularly, in tandem with the various phases of construction works. Revise the ECM as and when advised by its QECP. Keep good records of the ECM operation and maintenance. The records shall be made readily available to the SO. Do not remove the ECM until all Works are completed and upon the advice of the Contractors QECP. Submit the ECM plan duly endorsed by its QECP to Director, Catchment and Waterways (PUB) to obtain the necessary clearance before the earth works start, in the format as prescribed by PUB. The ECM plan shall include the following content: (a) Project Brief, which shall include the following: (i) Project description (ii) Name and address of site occupier (iii) Site area and Contract Period (iv) Location map and site plan (v) Construction phases and schedules (b) ECM Design Calculations (c) Erosion Control Plan TS 63/1065 978 Doc D.2/133 1.54.1 (d) Sediment Control Plan (e) Site ECM Management System Erosion Control Plan The plan shall include minimising of bare earth areas/slopes/stockpiles via sequencing and phasing the earth works, paving up / covering bare earth surfaces with lean concrete, milled waste, erosion control blankets, close turfing, canvas, etc. 1.54.2 Sediment Control Plan The plan shall include the following: 1.54.3 (a) Concrete-lined cut-off drains (minimum C7 precast channel) along the perimeter of the construction sites. (b) Sealing of site hoarding. (c) Ramp/curb at site entrance/exit. (d) Separate drainage for bare earth surfaces and non-bare earth surfaces. (e) Silt fence properly installed and embedded onto the ground along the internal and perimeter cut-off drains. (f) Silt traps. (g) Holding sumps/ponds for silty water. (h) Adequate silty water treatment systems to treat silty water before the discharge points into public drain. (i) Turbidity curtains for works in or adjacent to water bodies, such as canals, rivers, sea or in a reclamation work. ECM Management System The Management System shall include: (a) Daily ECM inspection and report by an ECM trained site staff. (b) Regular ECM review and report by QECP. (c) Monitoring and alerts of the treated runoff quality, and if required by PUB, CCTV with Silt Imagery Detection System to monitor the discharge at the public drain. TS 64/1065 978 Doc D.2/134 Deploy an ECM trained site staff to supervise the operation and maintenance of the ECM implemented on site as well as conduct daily checks. The site staff shall be the project manager, a qualified ECO, RTO or Safety Officer, who has attained, or will attain within 3 months from commencement of contract, a valid certificate from attending and passing an IES- endorsed ECM course for site staff, such as "Certificate of Competency in ECM for Construction Site Personnel Course." 1.55 Environmental Public Health Measures at Construction Sites 1.55.1 General Requirements Comply with the Environmental Public Health Act (hereafter referred to as "the Act" for the purposes of this subclause) and its Subsidiary Legislations including the Environmental Public Health (Employment of Environmental Control Officers) Order 1999, (hereafter referred to as "the Order" for the purposes of this subclause) and any amendment or re-enactment thereto throughout the Contract Period (including any extension thereof). Upon completion of the Works, engage a NEA registered Acoustic professional to measure the boundary noise for Building Permit application, from sound generating equipment, e.g. cooling towers, generators, AC condensing units, exhaust fan outlets, refuse compactor; and recommend mitigation measures when noise levels measured are excessive. 1.55.2 Noise Nuisance Judicious management and control over the activities within the Site shall be exercised by the Contractor for the abatement of noise nuisance. In this respect, implement all necessary noise control measures at its own cost and expense, to comply with the Environmental Protection and Management Act (hereafter referred to as "the Act" for the purposes of this Subclause) and its Subsidiary Legislations including the Environmental Protection and Management (Control of Noise at Construction Sites) Regulations, (hereafter referred to as "the Regulations" for the purposes of this subclause) and any amendment or re-enactment thereto throughout the Contract Period (including any extension thereof). The Contractor shall be deemed to have inspected and examined the Site and its surroundings and to have satisfied itself as to the surrounding developments and construction activities. Prior to the commencement of Works, propose a noise management plan and execute the appropriate noise control measures at its own cost and expense. 1.55.3 Noise Control at Construction Site 1.55.3.1 Noise Management Plan Within 14 days from the date of the Letter of Acceptance, submit a noise management plan complying with SS CP 602 to the SO for approval. The noise management plan shall include, but not be limited to the following: (a) Comparison charts between baseline noise monitoring results prior to the commencement of Works and the anticipated noise emission levels during construction. TS 65/1065 978 Doc D.2/135 (b) Identification of sensitive buildings, for example hospitals, schools, institutions of higher learning, homes for the aged sick, etc., and residential buildings within 150 m from the construction site boundary. (c) Site utilisation plan, indicating the locations of site facilities and noise generating equipment including, but not limited to generators, compressors and concrete pumps. (d) Specification of the machinery, equipment and plant proposed to be utilised on site as well as their indicative noise emission levels. Construction equipment and methods of work that generates excessive noise will not be allowed to be used on Site. (e) Identification of noise generating activities and delineate the sequence of work and construction methods for such activities, as well as indicate the anticipated noise levels accompanying each type of activity. (f) Proposed noise control measures for noise generating activities along with the estimated reduced noise levels in the form of administrative and engineering controls or other measures deemed effective in noise abatement. Noise control measures shall take into consideration site planning and layout (administrative controls), adoption of engineering controls and behavioural considerations of site personnel. (g) Proposed scheduling of works with due consideration to noise generating activities. (h) Contingency noise abatement measures for unavoidable works that have to be carried out after 7pm with the approval of the SO. (i) Noise monitoring system to be implemented, which includes the details of instrumentation, locations of installation, measured values of Leq and correction factor to be applied in the presence of ambient noise. (j) Public relations strategies to foster close community relationships throughout the Contract Period (including any extension thereof), such as signboards, newsletters, circulars, complaint handling procedures and investigation, standard response time to public feedback and complaints In formulating the noise management plan, take into account the working days and hours, as well as consider the effects of construction noise on personnel working in or around the site as well as the neighbourhood within proximity of the Site. Take into account the nature of land use in the area, duration of works and the effect of lengthening works period or other nuisances that may affect the neighbourhood. 1.55.3.2 Noise Control Measures Implement all noise control measures included in the approved noise management plan, including any other noise control measures as instructed by the SO or NEA from time to time. Noise control measures shall include the following, where necessary to comply with the Regulations: (a) All machinery and plant shall be identified to be sound-reduced prior to entering the Site. TS 66/1065 978 Doc D.2/136 (b) All plant, machinery and equipment shall be pasted with a weather-proof sticker clearly indicating its noise emission level (at source) under normal operating condition. (c) All machinery in operation shall have their covers properly shut at all times. (d) Noisy plant and equipment shall be housed in acoustic sheds or enclosures. (e) Noisy activities shall be barricaded with portable noise barriers and panels. (f) Noise barriers shall be erected prior to commencement of works. Noisy construction equipment (e.g., compressors) and installation (e.g., temporary refuse chute) shall be sited away from occupied blocks. All construction equipment shall be properly insulated and maintained to minimise its operating noise level. The SO has the discretion to require the Contractor to take necessary precautions, whether specified herein or not, to maintain or to repair such construction equipment or to instruct their removal from site when it is determined that the noise level generated from the construction works fails to comply with the Regulations or Code. 1.55.3.3 Noise Monitoring System Set up the wireless, web-based real-time noise monitoring system prior to the commencement of Work on Site. The cost of setting up, operating and maintaining the noise monitoring system shall be borne by the Contractor. The system shall include an integrated solar-powered sound level meter complying with IEC 61672 (Type 1) or other comparable standards approved by the SO. In addition, the system shall provide wireless, real-time transmission of the sound level data to a secured (password- protected) website, where data is presented for Leq 5-min, Leq 1-hr and Leq 12-hr periods. The system shall enable all current and historical sound level data recorded from the Site to be retrieved from the website. The system shall also incorporate a short message service (SMS) alert system to notify the designated recipients when the construction noise levels exceed the permissible noise limits stated under the Regulations. The sound level meter must comply with the following requirements: (a) An integrating-averaging sound level meter set to frequency weighting "A". (b) Equipped with a data logger for sampling the running value of "A"-weighted sound level pressure levels with adequate memory to store 5-min equivalent continuous readings on a 24-hr basis for up to 1 month. (c) Dynamic range shall be of at least 40 dB. (d) The sound level meter shall have a laboratory calibration certificate dated not more than 3 months before the commencement date of the Contract. The integrating sound level meter shall be sent to an approved accredited laboratory for calibration at an interval of every 6 months or as and when required by the SO. TS 67/1065 978 Doc D.2/137 Install the sound level meter at a suitable location at the nearest occupied building. The location shall approved by the SO or NEA. Liaise with the relevant Authorities, for example Town Council, for permission to install the sound level meter. Where there is no suitable location outside the Site, the sound level meter may be installed within the Site, subject to the approval of the SO or NEA. The installed sound level meter can be sheltered, but the microphone of the sound level meter must face the construction site and in the line of sight of the construction activities without any physical barrier or obstruction. 1.55.3.4 Sites in Close Proximity to Sensitive Buildings For construction sites close to premises that are sensitive to noise disturbances, e.g. schools, hospitals, institutions of higher learning, homes for the aged sick, the SO reserves the right to direct the Contractor to implement any noise control measures deemed necessary to reduce the noise disturbances regardless of the noise level generated and compliance with the permissible noise levels in the Regulations. For the avoidance of doubt, the measures could include, but not be limited to erection of temporary noise barriers to shield the affected buildings from excessive noise, switching to use of quieter machinery or adoption of quieter construction methods, installation of air-conditioning systems within the noise sensitive premises, etc. The Contractor shall also be responsible for dismantling all temporary noise control measures and shall make good any affected premises when requested by the occupier of the affected buildings. The Contractor shall obtain written permission from the SO prior to the dismantling of such measures. The cost of implementation of such measures, including dismantling, shall be borne by the Contractor. 1.55.4 Landscaping Works 1.55.4.1 Preservation of Trees Where any existing tree(s) on the Site is stipulated to be preserved (hereinafter referred to as "Preserved Trees" for the purpose of this Subclause), take all necessary precautions to avoid damage or injury to such tree(s) and the roots and comply with the following requirements: (a) Treatment of Preserved Trees in Area of Fill (i) Tolerable Depth of Fill: The area around Preserved Trees shall not be filled more than 300 mm in depth. (ii) Construction of Well Around Trees: Well not exceeding 1 m in depth shall be constructed around Preserved Trees. The minimum diameter of the well shall be 6 times the diameter of Preserved Trees measured at the trunk 0.5 m above ground level. Details of the well shall be as shown in the drawings. (iii) Treatment of Preserved Trees in Area of Cut (iv) Tolerable Depth of Cut: The area around Preserved Trees shall not be cut to a depth exceeding 300 mm. TS 68/1065 978 Doc D.2/138 (v) (b) Retention of Raised Planter Around Tree: An area around Preserved Trees shall be retained as raised planter to conserve the root system. The minimum diameter of raised planter shall be 6 times the diameter of Preserved Trees measured at the trunk 0.5 m above ground level. Details of retention of raised planter are as shown in the drawings. Protection of Existing Trees from Physical Damage (i) All Preserved Trees shall be protected against damage during construction operation by suitable fencing or armouring. The protection of Preserved Trees shall be placed before commencing any excavation or grading operation/work and shall be maintained in repair for the duration of the Contract Period (including any extension thereof) unless otherwise directed. The extent of fencing shall be determined by the SO. Fencing shall be erected all round not less than 1.2 m from the trunk of Preserved Trees. (ii) Individual Preserved Trees near heavy construction traffic shall be wrapped with gunny sacks and 50 mm x 100 mm planks worn vertically as armour around the trunk and spaced at no more than 50 mm apart to a height of 1.5 m above ground. (iii) Any damage to Preserved Trees root system shall be repaired immediately by the Contractor under the supervision of a qualified horticulturist. Roots that are exposed and/or damaged during grading operations shall be cut off immediately and the inside of the exposed and/or damaged area cleaned; cut surfaces shall be treated with approved sealing compound and topsoil spread over the exposed root area. (iv) Any damage to Preserved Trees branches shall be treated in accordance with the drawings. (a) Branch trimming of damaged branches - First cutting: To be made at point A 300 mm from the main trunk of Preserved Trees; depending on the diameter of the branch being cut. Depth of cut shall not be more than ½ of the diameter of the branch. - Second cutting: To be made at point B parallel to cutting at point A. The distance between these 2 cuttings shall be 75 mm to 150 mm. - Make a shallow cut at C. - Final cut to be sharp and clear. - Apply coats of anti-fungus wound sealant on cut area. (b) Wound treatment - Clean away ragged or loose edges of bark with a sharp pruning knife. - Shape the wound into an oval, pointed at both ends - Coat the entire exposed surface with tree-wound paint. TS 69/1065 978 Doc D.2/139 (v) (c) Health and Condition of Preserved Trees (i) 1.55.4.2 If any Preserved Trees are severely damaged by any mechanical equipment, etc., make good such damages and pay for any fines imposed by the Authorities. Ensure the following: (a) Compaction of soil around Preserved Trees shall be avoided. (b) No materials shall be stored within the root system. (c) There shall be no spillage of any nature within the spread of the Preserved Trees. (d) There shall be no parking of vehicles underneath the Preserved Trees. (e) There shall be no dumping of excavated materials, concrete, equipment etc., within the spread of the Preserved Trees crown. (f) Soil around Preserved Trees is properly cultivated to ensure that adequate supply of air and water get to the roots. (g) The Site is drained in periods of heavy rainfall and irrigated during periods of drought. (ii) Carry out any other routine maintenance of the Preserved Trees, e.g. branch trimming, pesticide spraying, etc. as instructed by the SO. (iii) If the growth of the Preserved Trees is stifled, the Contractor shall inter alia bear the cost of making good and charges imposed by Authorities, in accordance with Clause 6 on "Nuisance and Irregularities". Turfing, Landscaping and Tree Planting Carry out all turfing and planting works to the satisfaction of the National Parks Board (NParks) and/or the SO. All works in connection with external landscaping shall be considered accepted, only upon the successful handover to the NParks. 1.55.4.3 Supply and Spreading Approved Soil Mix (ASM) The Soil Media / Mixture used for general landscape must comply the guidelines specified in the latest edition of "Specification for Soil Mixture for General Landscaping Use", a publication by Centre for Urban Greenery and Ecology (CUGE), National Parks Board. The component of ASM, generally to be used for landscape beds shall be in the ratio 3:2:1 of loamy soil, compost and washed sand, respectively. The proportions are by volume. The ASM shall be clear of all lumps of clay, debris, stones, rubbish, hazardous materials, and roots. TS 70/1065 978 Doc D.2/140 1.55.4.4 Maintenance of Grass Throughout the Maintenance/Defects Liability Period of the Contract, all turfing shall be watered regularly and weeded until it is accepted by the SO. All weeds shall be pulled out by the roots. Allow for such watering and tending. Any dead turves, badly growing turves or otherwise unsatisfactory turves shall be removed and replaced with approved quality turves by the Contractor at its own expense. All weeds shall be removed at least twice a month. All cut grass, cuttings together with trimmings, loose stones, rubbish, etc. shall be collected and removed from the Site and disposed of expeditiously to the ENV's approved dumping grounds. After one month until the end of the Maintenance/Defects Liability Period, the Contractor shall carry out top-dressing with top soil and rolling for any depressions or unevenness of the terrain detected on the ground. 1.55.4.5 Grass Cutting Frequency Unless otherwise specified, the frequency of grass cutting for established turf area shall be once every 2 weeks, until the end of Maintenance/Defects Liability Period. All cut grass within the road reserves shall be immediately swept and removed. 1.55.4.6 Tree and Shrub Planting Unless otherwise specified, provide the necessary specified tree saplings and shrubs, plant and maintain them till established. Replace any trees or shrubs that die or are in a poor state of growth or had failed to establish. All plants proposed and the planting plan must be approved by the SO. Any plants replaced within the last 3 months just before the end of the Maintenance/Defects Liability Period, the Contractor shall undertake to maintain the plants for a period of 3 months commencing from the date of the plants replaced. At the end of Maintenance/Defects Liability Period, the plants must be healthy, lush and undamaged. At the end of Maintenance/Defects Liability Period, rectify all defects to the satisfaction of the SO. 1.55.4.7 Watering Immediately after planting, water the trees and shrubs and continue to do so at least once a day and as and when required until the trees and shrubs are well established and need no further daily watering. The Contractor is expected to water the plant at any time during the Maintenance/Defects Liability Period whenever it is required and as directed by the SO, all at the Contractor's expense. TS 71/1065 978 Doc D.2/141 1.55.4.8 Maintenance of Trees and Shrubs Carry out all necessary maintenance of the planted trees and shrubs. Maintenance shall mean watering and replacement of trees or shrubs that failed to establish, replacement of tree guards and stakes, proper pruning and trimming, weeding and clearing of unnecessary growth such as weeds and "lallang", at least once a month or at any time as directed by the SO, liming, feeding, forking of soil around the plant base (area of planting hole or bed) spraying with approved pesticide, adding compost to the top 50 mm, etc. all at Contractor's own expenses. The period of maintenance begins as soon as a tree, shrub or sod of turves is planted up to the end of the Maintenance/Defects Liability Period . If the Contractor fails to carry out regular maintenance of the turves and trees as stipulated, the SO shall engage others to carry out the necessary maintenance work. All expenses arising therefrom shall be borne by the Contractor and shall be deducted from any monies due or to become due to the Contractor, including 20% administration charges. 1.55.4.9 Handover Turfs, trees and shrubs planted in public areas, e.g. within road reserves shall be handed over to NParks. Carry out regular weeding, cut the turf, top dressing, prune the trees and shrubs, etc., and get them ready to a standard acceptable to NParks for inspection and taking over. Attend all site inspection by NParks and comply with all requirements and comments by NParks including any re-inspections till the turves, trees and shrubs are accepted and taken over by the relevant Authorities all at the Contractors own expenses. Note that the taking over of the road is dependent on the taking over of turves, trees and shrubs within road reserve. The Contractor shall therefore have to attend expeditiously to all NParkss requirements and comments. Trees, shrubs and turves in other areas shall be to a standard acceptable to the SO for handover to relevant Authorities. Allow for the compliance of the above requirements in its Tender Price. 1.55.4.10 Turfing / Grass Cutting Within Road Reserve Commence turfing works progressively as the side tables are ready. Proper care shall be taken to ensure that the turf covers the full area in time for the inspection by NParks for taking over, otherwise the close turfing shall have to be provided, all at the Contractors own costs. Carry out grass cutting once in 2 weeks throughout the Contract Period. Continue to maintain the turf by submitting schedule of maintenance to SO till successful handover the turf to relevant Authorities or NParks. The schedule of maintenance includes monthly weeding, fortnightly grass cutting, rolling, top dressing, mulching to trees and shrubs, pest and disease control, and nutrient management regime. TS 72/1065 978 Doc D.2/142 1.55.5 Temporary Site Access Within Site Boundary Propose and construct a temporary site access within the Site boundary linking the main construction entrance/exit to all building blocks, inclusive of multi-storey carpark building. Engage a PE to design the access. The drawings and calculations endorsed by the PE shall be submitted to the SO for approval before the construction of the access. The access shall be of concrete or bituminous pavement or precast concrete plank. It shall be laid over well- compacted hardcore base or other suitable material to the Contractors PE design. The access shall be inspected by the Contractors PE and the certificate of supervision issued prior to use. The precast concrete plank shall be 175 mm thick with modular size of 1.20 m by 2.20 m. The Contractor can opt for any other size subject to the SOs approval. It shall be reinforced with welded mesh and the edges shall be protected with angle iron. It can be cast with grade 40 eco-green concrete. To ensure proper site drainage, properly-graded Type C7 composite channel cut-off drains shall be laid along the perimeter of the construction site. Similar cut-off drains shall be laid along the access and other areas where required. The drainage system shall comply with the requirements specified in Clause 1.55 on "Earth Control Measures" and subclauses under it. The area between the temporary site access and the building blocks / multi-storey car park shall be laid with well compacted subgrade with lean concrete surface. The access shall be provided immediately after the completion of the first storey. The provision of access prior to the completion of first storey shall comply with the requirements specified in Clause 5.1.14 "Access for The Use of Mobile Crane and Piling Machines Next to Built-Up Area". The access shall be maintained in good working condition and free from water stagnation at all times throughout the Contract Period (including any extension thereof), or unless otherwise approved by the SO. As part of the housekeeping effort, deploy workers to clear the mud deposits/droppings regularly and maintain the access as clean and dry as practically possible. A heavy duty vehicular washing bay shall also be provided at the main entrance/exit point abutting completed public road. All tyres of vehicles shall be thoroughly clean if necessary before leaving the Site. The area at the main construction entrance/exit shall be laid with concrete surface to improve the maintainability of the site access. Where the access had been excavated for underground services work (e.g., sewer construction, underground piping system draw pit), use steel plate to temporarily cover these excavated areas and the access shall be immediately reinstated to good working condition upon the completion of the underground services work in accordance to PE design. TS 73/1065 978 Doc D.2/143 1.55.6 Temporary Sanitary Facilities Within 21 days from the date of the Letter of Acceptance, provide temporary sanitary facilities in suitable structures with adequate lighting, on the Site. Such temporary sanitary facilities shall be subject to approval by the SO. Use the Employer's Standard Drawings as a guide in designing the temporary sanitary facilities. The temporary sanitary facilities shall comprise water closets and shower compartments in the proportion of one closet and one shower to every 25 workmen, throughout the Contract Period (including any extension thereof). In addition, provide separate sanitary facilities with water closet and shower compartment for the exclusive use of the Employer's officers. Prior written approval by the SO shall be obtained before commencing the erection of these facilities. The water closets shall be of the type, make and pattern approved by the MEWR and PUB (Water). Provide and lay glazed wall tiles or other approved material to the internal walls of the temporary sanitary facilities up to a height of 1.8 m from the floor. The doors to the cubicles of the temporary sanitary facilities shall be of approved material. All waste discharge from the water closets and all waste water from the temporary sanitary facilities and from the Site shall be discharged into a public sewer. Arrange with the MEWR to carry out connection work from the temporary sanitary facilities to the public sewer and pay all charges and maintenance in connection therewith. The Contractor shall be responsible for all damages to and shall indemnify the Employer against all liabilities in respect of such sewer connections. Where a public sewer is not available or where it is not possible to connect to a public sewer, provide and install temporary septic tanks of the type, pattern and capacity approved by the MEWR, to serve the water closets, showers and baths. Prior to commencing the installation of the temporary septic tanks on the Site, engage a Licensed Plumber who shall submit his/her proposal to the MEWR and SO for approval. The proposal shall include the manner and frequency of post installation management and maintenance of the septic tanks on the Site. The Contractor and its Licensed Plumber shall be fully responsible for any mismanagement or misuse of the temporary sanitary facilities, which may result in the pollution of the controlled water course. 1.55.7 Removal of Construction Debris from Building Blocks Before the commencement of Works on site, submit proposal for the daily removal of the construction debris from the building blocks to the SO for approval. 1.55.8 Pest Control and Surveillance Engage an approved Pest Control Operator who is registered with the following to provide comprehensive pest control and surveillance work on the Site: (a) BCA, under the Work Head for Pest Control (b) NEA, under the Control of Vector and Pesticide Act TS 74/1065 978 Doc D.2/144 In this respect, submit the name of the Pest Control Operator and proof of BCA/NEA registration to the SO for approval prior to carrying out the Works. The SO may reject the Pest Control Operator selected by the Contractor and the Contractor shall not be entitled to any claims for compensation and extension of time arising from such decisions. Pest Control measures and surveillance programmes shall fully comply with the requirements of NEA as well as the following: (a) The Contractor is required to submit a detailed pest control and surveillance programme inclusive of "Source reduction regime/strategy", "Water bearing receptacle removal team" at the Site to the respective NEAs regional office and the SO prior to commencement of the Works. The frequency of fogging shall be in accordance to NEAs requirement. Fogging shall be carried out only by licensed Pest Operator using approved chemical. (b) The Contractor shall maintain a site register containing an up-to-date record of the pest control and surveillance work that has been carried out. The site register shall be made available and ready for inspection by the SO when required. (c) The Contractor shall submit monthly summarised returns of the site records required by NEA to the respective NEAs regional office. (d) On the instruction of the SO, the Contractor shall seal up all sanitary openings in the dwelling units prior to the handover of the completed Works all at the Contractor's cost and expense. The works required under this subclause shall include all necessary measures to prevent the Site from becoming conducive to the breeding or harbouring of vectors. Carry out site checks at least once a week to detect and remove all breeding and harbouring grounds. If breeding or harbouring of vectors is found at the Site, enforcement action may be taken against the Contractor by NEA. The SO may also invoke the provisions of Clause 6 "Nuisance and Irregularities". 1.55.9 Air Pollution by Construction Equipment Take all necessary measures to abate the discharge of smoke, fumes or obnoxious gases from construction equipment and other equipment on the Site. When notified by the SO that a particular construction equipment or equipment is discharging excessive smoke, fumes or obnoxious gases, stop the use of that construction equipment or equipment, and replace the same with acceptable construction equipment or equipment. No claims from the Contractor for extension of Contract Period or costs and expenses shall be allowed. TS 75/1065 978 Doc D.2/145 1.55.10 Cleaning of Public and Private Roads and Drains Ensure that all vehicles used by the Contractor, the Contractors agents, or by the Contractors subcontractors or suppliers and their agents (hereinafter referred to as the "Contractor's Vehicles" for the purposes of this subclause) shall not dirty any public or private roads and drains. In this respect, it is the Contractor's responsibility to ensure that all such Contractor's Vehicles are properly cleaned before they move onto these roads. Check with the SO if it is in doubt of any road being a public or private road and the decision of the SO in this respect shall be final and binding and conclusive against the Contractor. In the event the Site abuts a public or private road and the Contractor's Vehicles use the road for site access, provide a washing bay to wash and clean Contractor's Vehicles before they move onto the public or private road. Should vehicles of the other contractors also use such public or private road for site access, provide, at the Contractors own cost and expense, similar washing and cleaning facilities and services for these other contractors' vehicles before they move onto the public or private road. Provide also at the Contractors own cost and expense, the same facilities and services for similar purposes in the event a road abutting the Site becomes a public or private road and is used for site access by the Contractor's Vehicles or other contractors' vehicles. 1.55.11 Restriction on The Use of Styrofoam in Construction processes The use of styrofoam in the course of formwork erection or concreting works shall be disallowed, unless specific approval has been given by SO. The Contractor shall also ensure that its subcontractors do not use styrofoam in openings and recesses. 1.56 Material Sample Display Room Within 21 days from taking possession of the Site, a Material Sample Display Room of 3 m X 5 m (i.e. 15 m2) shall be provided at the Site office and situated beside the meeting room. A new air-conditioner and adequate lighting shall be provided to the Material Samples Display Room. Appropriate and proper display racks/shelves shall be provided. The display room shall be maintained neat and tidy at all times. 1.57 Audit of M&E Systems Test the M&E systems and rectify all defects before submitting all M&E systems test reports endorsed by the professional engineers and licensed electrical worker (LEW) engaged by the Contractor. The Employer reserves the right to audit any of the M&E systems installed by the Contractor. Provide the necessary manpower, equipment and means of access for the audit by the Employer. Rectify all defects detected during the audit and report to the Consultant for verification. For buildings under construction, ensure compliance with the requirements of the FSSD (dry/wet rising mains, etc). Make the necessary arrangements to enable the officers from FSSD, SO, and/or the Employer to carry out any inspection and testing during the construction stage. TS 76/1065 978 Doc D.2/146 1.58 Environmental Management 1.58.1 Environmental Management Programme 1.58.2 (a) Implement an effective Environmental Management Programme. (b) The Programme shall include monitoring and tracking to minimise: (i) electricity consumption (ii) diesel consumption (iii) water consumption (iv) concrete wastage. (c) Submit data to the SO on a monthly basis and present it as a standing item in the monthly meeting. (d) The programme shall also include measures to be taken to raise awareness and promote environment friendly habits amongst site personnel. Environment-Friendly Practices (a) Implement a system to facilitate the use recycled water obtained through Earth Control Measure for: (i) wash bay (ii) dust control (iii) tremie piles (iv) washing of site access. (b) Segregate metal and concrete waste from general construction waste for recycling purpose. (c) Provide recycling bins near the site office to facilitate recycling. (d) Use eco-green concrete, subject to Contractors PE approval where necessary, for the base slab of: (i) site office (ii) workers quarter (iii) workers toilet TS 77/1065 978 Doc D.2/147 (iv) (e) 1.59 cube room. To reduce energy consumption for the Site Office, the contractor is encouraged to carry out the following: (i) Use aircon with green rating. (ii) Use white colour for the roof of the site office. (iii) Use the east and west end for meeting room or toilet as it has lower occupancy. (iv) Reduce the office ceiling height at about 2.4 m to reduce air conditioning and lighting energy consumption. (v) Provide ultra violet film or blinds at site office windows. (vi) Maintain office temperature at more than 24°C. (vii) Provide door closer at doors where space is air conditioned. (viii) Design the site office toilet such that they do not need mechanical ventilation. (ix) Use pedestal pan integrate with wash basin. (x) Use motion sensor for lights and ventilation fan for toilet. (xi) Orientate the site office in the northsouth facing if feasible. (f) The Contractor is encouraged to be familiar and closely follow the BCAs Green and Gracious Builders Guide (e.g. use energy efficient air conditioning system complying with Singapore Energy Labelling Scheme, use T5 lights combined with motion sensors to reduce energy consumption). (g) The Contractor is also encouraged to: (i) provide more greening on Site to lower ambient temperature during construction period (ii) eliminate environmentally unfriendly products and packaging. Protection of Personnel Data TS 78/1065 978 Doc D.2/148 1.59.1 Security Take all reasonable measures to ensure that Personal Data held in connection with this Contract is protected against loss, and against unauthorised access, use, modification, disclosure or other misuse in accordance with the procedures set out in this Clause and its subclauses, and that only authorised personnel have access to the data. Do not vary the security procedures set out in this Contract without the prior written approval of the SO. 1.59.2 Use Use any Personal Data held in connection with this Contract only for the purposes of fulfilling its obligations under this Contract. 1.59.3 Disclosure Do not disclose any Personal Data obtained in connection with this Contract without the written approval of the SO. Immediately notify the SO when it becomes aware that a disclosure of Personal Data may be required by law. 1.59.4 Transfer of Personal Data Outside Singapore Do not transfer Personal Data held in connection with this Contract outside Singapore, or allow parties outside Singapore to have access to it, without the prior written approval of the SO. 1.59.5 Data Protection Requirements and Undertakings Ensure that any employee of the Contractor or any subcontractor, requiring access to any Personal Data held in connection with this Contract gives an undertaking in writing to not access, use, disclose or retain Personal Data except in performing their duties of employment and is informed that failure to comply with this undertaking may be a criminal offence and may also lead the Contractor to take disciplinary action against the employee. In respect of any Personal Data held in connection with this Contract, immediately notify the SO where the Contractor becomes aware of any breach of the obligations contained herein by itself or any subcontractor, or by their respective employees. In respect of any Personal Data held in connection with this Contract, cooperate with any reasonable requests, directions or guidelines of the Employer, or Employers nominee/agent, arising in connection with the handling of Personal Data. All the above Clauses shall continue to have effect after the termination or expiry of the Contract. TS 79/1065 978 Doc D.2/149 1.59.6 Subcontracting Whether or not the Contract contains clauses that prevent subcontracting or assignment without the consent of the SO, the written approval of the SO must still be obtained pursuant to the clauses herein, before any Personal Data can be disclosed to any subcontractor or assignee. Ensure that all clauses relating to protection of Personal Data are included in any Contract between the Contractor and subcontractor or assignee. 2 MATERIALS 2.1 Metric Components All components for incorporation into the Works shall be in metric units. However, when metric components are not available, their equivalent in imperial units may, subject to the approval of the SO, be used and such a substitution shall not constitute a variation to the Contract. 2.2 Materials and Workmanship As directed, furnish the SO with approved documents to prove that materials are as specified. The documents shall include but not be limited to any or all of the following, such that the authenticity of the materials can be easily ascertained: (a) shipping documents (b) serial numbers (c) warranty certificates In the event that any documents submitted are not original copies, they shall be duly certified by the originating parties. No information within the documents shall be tampered with, unless it is clearly discernible that the items are not related to the materials specified in the Contract. Where specific brand and model number are specified, or where alternative brands and model numbers are offered by the Contractor and accepted by the SO, it shall be deemed that the finished products are entirely of original make by the registered manufacturer and fully supported by the manufacturer's warranty. In the event that any alteration is made to the goods by a local agent or any other intermediary, obtain the approval of the SO shall be sought and the result of the alteration shall be fully supported by the manufacturer such that the manufacturer's warranty is maintained. Samples of materials shall be submitted to the SO for approval before order is placed with the supplier. Such approval by the SO shall not relieve the Contractor of its obligations under the Contract. Ensure that the materials are free from any defects, damage or any other flaws. 2.3 Sample , Mock-up and Quality Standards TS 80/1065 978 Doc D.2/150 2.3.1 Sample, Mock-up and Quality Standard All samples shall be provided as per the requirements of each technical section of the Specification. The cost and expense for inspection, testing and approval of sample and mock-up (as instructed by the SO), shall be provided by the Contractor. These samples and/or mock-ups shall be truly representative of the actual works to be constructed in every respect, inclusive of all architectural details, architectural and structural features, finishes, services, fittings, etc. Comply with the quality standards specified under each Section for setting up of sample and/or mockup. Read the Specification, drawings or details in conjunction with the quality standards specified under each Section. In case of discrepancies between the Specification, drawings or details and the quality standards specified under each Section, obtain approval from the SO before proceeding with the Works. Use the approved sample and/or mock-up as reference for the standard and quality of workmanship and materials that are acceptable to the SO. Ensure that the completed Works (including works that are not listed in the quality standards specified under this clause) are at least of the same standard and quality as that in the samples. Maintain the sample and/or mock-up in a clean, neat and tidy condition at all times. Adequate artificial lightings shall be provided where possible and as directed by SO, all at the Contractors cost and expense. Notwithstanding the approval of the SO in respect of these sample and/or mock-up units, the Contractor shall not be released from any of the duties and obligations as required of the Contractor under the Contract. These samples shall be appropriate displayed at the designated area within the Material Sample Display Room upon approval of the said sample by the SO. The SO reserves the right to instruct the Contractor to provide and display the sample for other building materials and components, especially newly introduced items, big ticket items and special items, under the Contract where deemed necessary and fit all at the Contractor's cost and expense. The approved material samples shall be provided and displayed before construction, erection or installation. All approved materials shall be labelled with the supplier's name and materials' type/grade/model. 2.4 Storage Facility for Cement Where storage of cement is required, provide adequate storage facilities at the Site to accommodate cement up to 2 weeks' requirement for the Works. The store to accommodate the cement shall be constructed so that each consignment of cement can be separately stacked. Each consignment of cement shall also be used in the same sequence as they are delivered, that is, on a "first-in first-out" basis. Ensure that the cement stored at the Site is kept dry and properly protected against loss or damage at all times. TS 81/1065 978 Doc D.2/151 2.5 Precautions Against Materials Being Taken Out Of Site The Contractor shall be responsible for the safe custody of cement and all other materials delivered to the Site and shall therefore ensure adequate protection and prevention of such materials from being taken out of the Site. The SO will not accept any excuse for materials taken out of the Site by the Contractor, the Contractors foreman or any other individual even without the knowledge of the Contractor who is deemed to have provided for proper control against such malpractice. If it is established that cement or any other material is taken out of the construction Site without specific written approval from the SO, this shall be deemed to be an irregularity, with penalties to be imposed by the SO. 2.6 Ready-Mixed Concrete from Approved Suppliers Obtain ready-mixed concrete from any of the pre-approved suppliers and provide the names and addresses of the ready-mixed concrete suppliers to the SO. The use of ready-mixed concrete shall be subject to the terms and conditions set by the SO. All delivery orders for ready-mixed concrete delivered to the Site shall be endorsed by the Employer's Resident Site Staff and submitted to the SO. Failure to inform the SO or non-compliance with the terms and conditions set by the SO for the use of ready-mixed concrete shall, inter alia, result in the Contractor forfeiting its right under the Contract to claim compensation for price fluctuations for all materials. 2.7 Provision of Spare Materials Provide all spare materials as specified under each Section. 3 LABOUR 3.1 Labour Laws Pay workmen (Contractors workmen) promptly, and observe the workmen's working hours and holidays in accordance with current laws and regulations. Keep records and produce them for inspection by the SO. 3.2 Keeping Records of Workmen Comply with all labour laws regarding the engagement of non-citizen workmen. Obtain work permits from MOM for these workmen. The Contractor shall be held solely liable for and shall indemnify the Employer in respect of all actions against the Employer for employing foreign workmen without permits. Keep proper records of all workmen engaged on Site. These records shall include the following information: (a) Name of Workmen (and alias if any) (b) Identity Card No./Passport No. TS 82/1065 978 Doc D.2/152 (c) Address (d) Work Permit No., if any (e) Expiry date of work permit This information shall be recorded before any workman is allowed to commence duty. Appropriate action shall be taken by the SO if the Contractor fails to record any of the abovementioned information of any worker found at the Site. 3.3 Employment of Illegal Immigrants (Prohibition) For the purpose of this Subclause, an "illegal Immigrant" shall refer to any person who enters the Republic of Singapore in contravention of the provisions of the Immigration Act or any statutory modification or re-enactment thereof. The Contractor shall ascertain the legitimacy of all foreign workers employed by itself and/or any subcontractor prior to employment and throughout the Contract Period (including any extension thereof). Clarification as to the legitimacy of Foreign Workers may be made with the Immigration Authority, the Ministry of Manpower and/or the Police. The Contractor and/or its subcontractors shall not employ any illegal immigrants in the execution of the Works. The Employer shall not be responsible for any such act or acts by the Contractor and/or any of its subcontractors and the Contractor shall indemnify the Employer for all consequences arising thereof. 3.4 Biometric Time Attendance System for Manpower Data Collection Propose, supply, deliver, install and set up a biometric time attendance system, including testing and commissioning, and subsequent maintenance of a biometric time attendance system for personnel entering or leaving the worksite throughout the Contract Period. Propose the mode of authentication (fingerprint, facial recognition, etc.). The system shall be located at all worksite entrances and exits for the purpose of electronically monitoring and tracking the manpower usage throughout the Contract Period. Install a CCTV at locations with the biometric time attendance system. The system shall be installed and functional upon completion of the perimeter hoarding and site entrance. Submit a detailed proposal to the SO for approval within 14 days from the date of the Letter of Acceptance. The proposal shall include, but not be limited to, the following details: (a) Type of system to be implemented (b) Track record of proposed system in similar projects and environment in Singapore (c) Proposed location(s) of the system at Site (d) Type of access barrier (e.g. tripod turnstile, flap barrier, swing barrier etc.) (e) Installation method (f) Maintenance plan TS 83/1065 978 Doc D.2/153 The system shall be able to accurately monitor and track the manpower under their respective trade. At each controlled access location, the system shall be able to achieve a maximum clearance time of 1 minute for every 10 persons. The system shall be able to generate the manpower report according to BCAs current Electronic Productivity Submission System (ePSS) in Microsoft Excel format (Refer to https://www.bca.gov.sg/epss/ ). Refer to BCAs website for the latest requirements on manpower submission to ePSS. The system shall be able to generate raw data or output in the required format which shall include but not limited to, the following details: (a) Employee name (b) Date (c) Clock in time (d) Clock out time (e) Total number of working hours at site (f) Classification of workers (e.g. tiler, painter) (g) Personal identification number (i.e. NRIC/ FIN/ WP no.) (h) CoreTrade Registration ID The system shall be able to generate trend charts to show the total manpower used in man- days under the respective trade over time. There shall be a real time monitoring and recording device installed at each controlled access point to prevent any fraudulent attempt by the site personnel. The system shall be equipped with suitable measure(s) (e.g., backup battery supply etc.) such that the integrity of the manpower monitoring data is not affected during power outage. Ensure that the system is protected against unauthorised editing of collected manpower tracking data, virus or malicious software which may otherwise corrupt the system. In the event of system breakdown, ensure that there are alternative mean(s) to continue to monitor and track the manpower under the respective trades. The Contractor shall bear all costs and expenses in carrying out the necessary repairs and/or replacements to the equipment installed to resume system operation. Submit the manpower tracking data in the Contract to BCA through the ePSS at monthly intervals or at other frequencies as required by BCA. A copy of the submitted manpower report shall also be given to the SO. Extend usage of the system to the Employer and Consultants. The list of personnel required to use the system shall be as agreed with the SO. The system shall be able to generate raw data or output which shall include but not limited to, the following details: TS 84/1065 978 Doc D.2/154 (a) Employee Name (b) Company (c) Designation (d) Date (e) Clock-in Time (f) Clock-out Time (g) RE and RTO registration number Access rights control shall be given to the personnel as summarised in the table below: Access Rights Attendance Record Contractor Consultant Employer Employer Yes Yes Yes Consultants Yes Yes No Contractors Yes No No At the end of every month, the Consultant Project Manager shall generate the manpower data and submit to the Employer. 3.5 Allocation of Man-Year Entitlements Where materials, goods or products for the Works in the Contract are to be purchased and/or obtained by the Contractor, allocate Man-Year Entitlements to such suppliers and/or subcontractors engaged (by the Contractor) for the supply of such materials, goods or products. The Contractor shall be deemed to have included in the Contract Sum for all costs and expenses arising from having complied with the requirements stipulated in this subclause. 3.6 Employment of Skilled Workers Employ workers that are capable of producing good workmanship for all key trades as agreed with the SO. These workers shall possess Skill Evaluation Certificate from local institutions where available. Submit a list of the workers to the SO for pre-screening and approval before they are allowed to commence work. These workers are also required to wear identification pass upon approval by the SO. The pass shall be easily distinguishable from other passes used at the Site, by their colour, size or pattern. TS 85/1065 978 Doc D.2/155 4 CONSTRUCTION EQUIPMENT Provide information on the construction equipment to be deployed to the Site within 3 months from the date of the Letter of Acceptance to the SO for approval. Notwithstanding the submission for SOs approval, when deemed necessary, the SO may instruct the Contractor to deploy additional equipment to the Site. No claim by the Contractor for additional payment/s will be allowed for these additional pieces of equipment. Similarly, no claim by the Contractor for additional payment will be allowed for additional equipment brought to Site by the Contractor on its accord. All construction equipment used at the Site as specified herein shall be obtained from reliable source, subjected to the Consultants approval. Where such construction equipment is used at the Site for a duration of less than a week, the SO may at his sole discretion, waive the aforementioned requirement. Under such a case, there shall be no adjustment to the Contract Sum. 4.1 Maintenance Keep all construction equipment provided to the Site in good working order at all times and comply with all statutory regulations in relation to the construction equipment. 4.1.1 Mobile Crane Before operating a mobile crane on the Site, submit the following: (a) Record of latest overhaul servicing of the crane. The latest overhaul servicing of the crane shall be conducted within 1 year before transferring it to the Site. (b) Record of checking the connecting devices between parts/components and the condition of parts/components by an AE. Any defect found when checking shall be rectified immediately; and (c) Certificate of test/thorough visual examination of lifting equipment by the AE. Maintain the crane in good working order at all times on the Site. Document and keep all records and certificates of checking and testing in the site office for inspection by the SO upon request. Attend to the following: 4.1.2 (d) Engage a licensed crane operator to check the crane daily before operation. The licensed crane operator shall have a Certificate of Competence. (e) Engage a competent mechanic to conduct servicing of the crane once in every 3 months. (f) Engage the AE to carry out test and visual examination on the crane once in every 6 months. Tower Crane Before operating a tower crane on the Site, submit the following: TS 86/1065 978 Doc D.2/156 (a) Record of latest overhaul servicing of the crane. The latest overhaul servicing of the crane shall be conducted within 1 year before transferring it to the Site. (b) Record of checking the connecting devices between parts/components and the condition of parts/components by an AE. Any defect found in the checking shall be rectified immediately. (c) Record of checking the installation and functioning of safety devices by the AE; and (d) Certificate of test/thorough visual examination of lifting equipment by the AE. Maintain the crane in good working order at all times on the Site. Document and keep all records and certificates of checking and testing in the site office for inspection by the SO upon request. Attend to the following: (e) Engage a licensed crane operator to check the crane daily before operation. The licensed crane operator shall have a Certificate of Competence; (f) Engage a competent mechanic to conduct servicing of the crane once in every 3 months; (g) Engage the AE to check the installation and functioning of the safety devices once in every 6months; and (h) Engage the AE to carry out test and visual examination on the crane once in every 6 months. For every extension of height made on the tower mast and before operating the crane with the new height, engage the AE to conduct test and thorough visual examination on the crane. 4.1.3 Passenger Cum Material Hoist Before operating a passenger cum material hoist on the Site, submit the following: (a) Record of latest overhaul servicing of the hoist. The latest overhaul servicing of the hoist shall be conducted within 6 months before transferring it to the Site. (b) Record of checking the connecting devices between parts/components and the conditions of parts/components by an AE. Any defect found in the checking shall be rectified immediately. (c) Certificate of test/thorough visual examination of lifting equipment by the AE. Maintain the hoist in good working order at all times on the Site. Document and keep all records and certificates of checking and testing in the site office for inspection by the SO upon request. Attend to the following: (d) Require an authorised hoist operator to check and operate the hoist daily before operation. (e) Engage a competent mechanic to conduct servicing of the hoist once in every 3 months. TS 87/1065 978 Doc D.2/157 (f) Engage the AE to check the connecting devices between parts/components and condition of parts/components once in every 3 months. Any defect found in the checkings shall be rectified immediately. (g) Engage the AE to carry out test and visual examination on the hoist once in every 3 months. (h) The swing gates are to be maintained, checked and certified to be in good working condition by the AE every month. (i) Interlocking gates shall be provided at every lift landing level and they shall comply with the Workplace Safety and Health Act and its Subsidiary Legislation including any amendment or re-enactment thereto. 4.2 Provision and Deployment of Equipment to Improve Site Productivity 4.2.1 Construction Machinery and Equipment to be Deployed at the Site The Contractor shall provide and deploy suitable construction machinery and equipment to improve site productivity. The Contractor shall submit the Machinery Utilization Plan within 3 months from the date of the Letter of Acceptance to the SO for approval. The Contractor shall provide for a minimum of one number of ride-on power trowel, one boom lift, one scissors lift and one telescopic handler. Notwithstanding the foregoing requirements, the Contractor shall provide an Automatic Wheel Washer per site entrance and a Mast Work Platform per building block. 4.2.2 Technical Specification (a) Ride-on Power Trowel The power trowel shall be used for power floating of finished concrete to achieve a smooth finish in accordance to the Drawings and Specification. The requirement for provision of the power trowel may be waived at the discretion of the SO if the Contract does not require power floating of finished concrete. (b) Boom Lift and Scissors Lifts The boom lift and scissors lift shall be used for any work that is needed to be carried out at soft storey, void deck space and external façade. The boom lift and scissors lift shall also be used for rectification works from the second storey to sixth storey for the building during the handing over stage. (c) Telescopic Handler The telescopic handler shall be provided on Site not later than the completion of concreting work for the sixth storey slab of the first building block or any other time as instructed by the SO and shall not be removed without his prior approval. (d) Mast Work Platform TS 88/1065 978 Doc D.2/158 The mast work platform shall be used for any external façade works (skimming and painting) for each building block in preparation for handing over. The requirement for provision of the mast work platform may be waived at the discretion of the SO if the layout of the building block does not allow for erection of mast work platform. (e) Automatic Wheel Washer The automatic wheel washer shall be used to replace the manual manpower needed at the site entrance to wash and clean the wheels of the vehicles leaving the Site. The Wheel washer shall be provided onsite upon completion of substructure works or at any time instructed by the SO and shall not be removed without his prior approval. (f) Wireless Cleaning Machine The wireless cleaning machine is a multi-function auto scrubber which delivers effective and efficient floor cleaning performance. It is able to wash and dry hard floors in a single pass, saving labour as compared to the 2-man rotary scrubber and vacuum cleaner method. The wireless cleaning machine shall be provided on site at block handover stage or at any time instructed by the SO and shall not be removed without the SOs prior approval. (g) Electric Sanding Machine The electric sanding machine is an equipment used to smoothen the wall and ceiling surface. It shall replace the manual sanding method by using sandpaper to smoothen the wall and ceiling surface. The electric sanding machine shall be provided on Site upon completion of superstructure works or at any time instructed by the SO and shall not be removed without the SOs prior approval. 5 SITE SAFETY 5.1 Site Safety Measures 5.1.1 General Requirement The Contractor shall allow for the compliance with the Workplace Safety and Health Act and its Subsidiary Legislation including the provisions of the Workplace Safety and Health (Construction) Regulations and any amendment or re-enactment thereto. The subsidiary legislations are: (a) The Workplace Safety and Health (General Provisions) Regulations (b) The Workplace Safety and Health (Registration of Factories) Regulations (c) The Workplace Safety and Health (First-Aid) Regulations (d) The Workplace Safety and Health (Exemption) Order (e) The Workplace Safety and Health (Composition of Offences) Regulations TS 89/1065 978 Doc D.2/159 (f) The Workplace Safety and Health (Incident Reporting) Regulations (g) The Workplace Safety and Health (Risk Management) Regulations (h) The Workplace Safety and Health (Workplace Safety and Health Officers) Regulations (i) The Workplace Safety and Health (Work at Height) Regulations (j) The Workplace Safety and Health (Design for Safety) Regulations Precedent to the commencement of the Works, first obtain a Certificate of Registration, under the Act and its subsidiary legislation, The Workplace Safety And Health (Registration Of Factories) Regulations. It shall be the duty of the Contractor to comply with all such requirements of the Act and its Subsidiary Legislation, as affect the Contractor or any person or persons in its employ, and as related to any work, act or operation performed or about to be performed by the Contractor. Do not permit any person to do anything not in accordance with the generally accepted principles of safe and sound practice. Ensure a safe environment on the Site at all times. All safety provisions shall be properly maintained and shall not be removed without the written approval of the SO. Ensure that necessary and sufficient precautions are taken by the Contractors workmen when safety provisions are used. Do not allow any of the safety provisions to be used unless it has deemed the provision safe. Submit a safety management system to the SO within 14 days from the date of the Letter of Acceptance for approval prior to the commencement of the Works. The submission of the safety management system shall comply with and be kept in the site office and made available for reference at all times. Display safety posters at the site office, exit/entry points of buildings and passenger cum material hoist area. Submit drawings, detailings and calculation for all temporary structures as required, certified by its PE, for approval at least one week before the commencement of the Works unless otherwise specified. The approval of the SO shall not relieve the Contractor and its PE of the need to ensure the adequacy and sufficiency of the safety provisions. The Contractor is deemed to have allowed in the Contract Sum for all cost and expense for the safety provisions and for all additional costs that may arise from amendments to the Act and its Subsidiary Legislation or changes in the requirements of MOM. Ensure that the requirements of the Regulations and the requirements specified hereunder are strictly complied with at all times. TS 90/1065 978 Doc D.2/160 5.1.2 Metal Access Scaffold and Working Platforms Provide, erect and maintain all metal access scaffold for all buildings other than buildings of 4 storeys and above or 12 m in height and above. This requirement may be waived, subject to approval by the SO, where industrialised and semi-industrialised methods of construction together with peripheral safety nets are employed. Under such case, there shall be no adjustment to the Contract Sum. Allow free use of the scaffold by all subcontractors, specialists, artisans and other tradesmen employed by the Employer or the Contractor. The metal access scaffold shall be of the type approved by the MOM. It shall comply with CP 14 and any amendment or re-enactment thereto. The metal access scaffold shall be prezinc galvanised or other scaffold approved by the SO. The metal access scaffold shall be erected, or substantially extended to, or dismantled, by approved scaffold contractor, in accordance with the Factories (Scaffolds) Regulations. The metal access scaffold and any components therein shall be designed according to the CP14 and Workplace Safety and Health (Scaffolds) Regulations by a PE employed by the Contractor. The metal access scaffold shall be removed only with the permission of the SO. Submit the PEs drawings and calculations to the SO for approval prior to the erection and dismantling. The PE shall be satisfied that his proposal shall not duly overload the RC structure. Make the submission before the commencement of the Works. Erect the metal access scaffold, for access and finishing work ahead of the structural work. The metal access scaffiold shall be supported by cantilevered platforms erected in accordance with the drawings of the PE. The cantilevered platforms shall project about 1.1 m from the edge of the building or any other distance approved by the SO. The material used for the metal working platform shall be pre-zinc galvanised steel and in compliance with SS 280. The working platform shall be adequately secured to the metal access scaffold frame at the required levels. The connections between the metal working platform and metal access scaffold frame, and between the working platforms shall be subjected to the approval of the SO. For any portion of the working platform where the use of metal is not suitable, timber working platform may be used, subject to the approval of the SO. The working platform shall be complete with at least 90 mm high coloured toeboards and metal guardrails of at least 1.1 m above the platform. The vertical distance between any 2 adjacent guardrails shall not exceed 600 mm. Any working platform or workplace and the guardrail immediately above it shall not exceed 600 mm. The working platform shall be at least 500 mm in width and distance between the edge of the platform shall not exceed 300 mm from building edge Provide, erect and maintain an overlying screening net to cover the entire external face of the scaffold. The installation of the net shall follow the erection of the fence closely. A 90 mm high toeboard shall be provided at the base of the net. After installation, there shall be no opening between separate sets of the net and any torn net shall be replaced or repaired immediately. The net shall comply with the following requirements: (a) Maximum mesh size: 15mm square (b) Twine No.: Minimum 350D (c) Knot type: Single or English knot (d) Minimum 12 ply TS 91/1065 978 Doc D.2/161 The overlying screening net shall be installed on the entire external face of the access scaffold and its installation shall follow the erection of the metal access scaffold closely. The SO shall have the right to decide on the colour of the net all at the Contractors cost and expense. The metal access scaffold shall be effectively tied to the building structure by means of tie- backs. All tiebacks shall be painted with a bright colour for easy identification. 5.1.3 Prefabricated Mesh Barricade Provide, erect and maintain a vertical prefabricated mesh barricade (hereafter referred to as "mesh barricade" for the purpose of this Clause, including all subclauses under it) for all peripheral open sides of construction level of building (excluding multi-storey carpark/garage) where a person is liable to fall from height. Mesh barricade shall be of sound construction and produced in the factory and installed at the construction level from the inside of the building. Mesh barricade and its support shall be prezinc galvanised or other approved equivalent by the SO, easily installed and dismantled, and reusable throughout the construction (super-structure) stage. External works of the building, such as painting, touching up works, repair and redecoration, and other minor works, shall be carried out using mechanical suspended scaffold or other vertical access equipment. Where the use of mesh barricade is not feasible, as interpreted by SO, during the construction (superstructure) stage, the Contractor can counter-propose localised alternative system other than the use of metal access scaffold Mesh barricade / counter-proposals for localised alternative system, its vertical support and any components therein shall be in modular sizes and designed according to the WSH (Construction) Regulations by a PE employed by the Contractor. The PEs drawings and calculation shall then be submitted to the SO for approval within 6 weeks from the Letter of Acceptance, before installation and use. Trial setting out of the mesh barricade shall be carried out on Site 2 weeks after approval of submission. The mesh barricade shall be erected ahead of the structural work (including the construction of water tank rooms) from the second storey and held by a supporting system designed by the said PE. The height of the mesh barricade shall be at least 1.1 m above the construction level. Together with the PE, ensure that the substrate to which the mesh barricade is affixed to, can resist the designed imposed loads. The PE shall satisfy himself that his proposal shall not duly overload the RC structure. Where necessary, provide, erect and maintain an overlying screening net to cover the entire internal face of the mesh barricade. The installation of the net shall follow the erection of the fence closely. Where necessary, a 90 mm high toeboard shall be provided at the base of the net from the inside of the mesh barricade. After installation, there shall be no opening between separate sets of the net and any torn net shall be replaced or repaired immediately. The net shall comply with the following requirements: (a) Maximum mesh size (square): 15 mm square (b) Twine No.: Minimum 350D (c) Knot Type: Single or English knot (d) Minimum 12 ply TS 92/1065 978 Doc D.2/162 The vertical supports of mesh barricade shall be effectively anchored to the building structure. All vertical supports shall be painted with a bright colour for easy identification. The mesh barricade shall be erected according to a pre-determined safe work procedure established by the Contractor, or substantially dismantled, by trained erectors, under the immediate supervision of a competent supervisor. The mesh barricade and its components shall only be erected and dismantled by workers using life-line and safety belts or other equivalent, if not better, means of preventing a fall. Do not use the prefabricated mesh barricade and vertical supports for other purposes. 5.1.4 Personal Protective Equipment (PPE) Provide and maintain suitable personal protective equipment to all workmen employed at the Site. Ensure that such personal protective equipment comply with the requirements of the Regulations. Ensure that all equipment are properly used by (the Contractors) workmen during the course of their work. The Contractor shall record the issuance of all equipment to the workmen. The forms shall be kept in the site office and made available for inspection at all times. The colour code of safety helmets provided by the Contractor shall comply with the requirements of the Regulations. Three mirrors of sizes 600 mm x 1500 mm are to be installed for the workers to check their personal protective equipment during Tool Box Meetings. The locations of these mirrors shall be approved by the SO. Provide life-lines and safety harness for workers who are required to carry out work within 2 m from any open sides at or near the external of the building blocks, any floor or topmost construction level, lift shafts and void areas or any other locations as directed by the SO, all at the Contractor's cost and expense. Approved Personal Protective Equipment (PPE) station shall be set up near the site entrance where PPE is issued/stored. TS 93/1065 978 Doc D.2/163 5.1.5 Safety (Anti-Fall) Net Provide and maintain a safety net system to catch person(s) falling whilst working in any location from where he/they would be liable to fall. The safety net system shall be obtained from suppliers approved by the SO. An alternative system may be proposed to be certified by its PE, and submitted to the SO for approval. The safety net shall comply with SS 292 or other approved standards. The net shall be of sufficient size and strength to catch any person for whose protection it is to be used and the net shall be so located to cover the area of the possible fall. Conduct a sample test on the safety net system, comprising the net and its supporting structures, before it is installed. Subsequent tests shall be carried out when directed by the SO. For all building blocks of 4 storeys and above, a peripheral safety net system shall be provided. Initially the net shall be installed at the second storey. As construction progresses, reposition the net to follow the topmost working level but keep at not more than 6.0 m below it. Remove the net only with the approval of the SO. Where access scaffolding is used, or any alternative safety measure approved by the SO is used, a peripheral safety net system is not required. The colour of the safety netting shall be approved by the SO. Safety netting of orange colour shall not be used unless such colour is specifically decided by the SO, all at the Contractor's cost and expense. 5.1.6 Working Platforms for Lift Shafts, Central Refuse Chute and Voids Provide working platforms, according to the design of the Contractors PE, for the erection of lift shafts and void walls except for central refuse chute. The lift shaft and central refuse chute platforms shall effectively cover the voids at alternate storeys. The lift shaft, central refuse chute and void wall platforms shall be left in place until approval is given by the SO to remove them. TS 94/1065 978 Doc D.2/164 5.1.7 Protective Shelter as Overhead Shelter Provide, erect and maintain protective shelter as overhead shelter at every point of entry/exit to buildings of 2 more storeys height. The protective shelter shall be constructed immediately below the second storey. It shall protrude at least 3.0 m from the building edge. It shall have a clear width of at least 1.5 m and a clear height of at least 2.0 m as shown in the drawings. If the protective shelter is intended for access by forklift, it shall have a clear width of at least 2.0 m and a clear height of at least 3.0 m. Ensure that the protective shelter rest on a rigid base. The protective shelter shall be aesthetically pleasing, free of rust and does not trap water. The access to, along and egress from the entry/exit points shall be kept free from obstructions and accumulation of oil, grease, water and other substances that may cause slipping and tripping. The protective shelter shall be strong enough to support a point load of at least 75 kg. It shall be endorsed in accordance with the relevant statutory requirements by a PE. The PEs drawings, detailing and calculations shall be submitted for the approval of the SO. The protective shelter may be made of curved metal roofing with a diameter of at least 1.5m or pitched metal roofing with a slope of greater than one in 2, with timber boarding below supported by steel pipes. 5.1.8 Peripheral Overhead Shelters Provide peripheral overhead shelters for buildings of more than 15 m in height. They shall be erected in place when the construction reaches the fourth storey slab. The overhead shelter shall be at least 2 m wide and erected at a height not more than 5 m from the base of the building, and inclined so that the outer edge is at least 150 mm higher than the inner edge. The overhead shelter shall be sufficiently strong to support a weight of at least 75-kg point load. 5.1.9 Barricades to Lift Openings, Voids, The Open Sides of Buildings and Excavations Barricade all lift openings, internal voids and the open sides of buildings and excavations where a person is liable to fall. The barricade shall be at least 1.1 m high with 90 mm high toeboard and shall have sufficient strength and rigidity to withstand a lateral point load of 50 kg. All services openings shall be fully covered and secured to prevent unauthorised removal. 5.1.10 Mechanical Suspended Scaffold Mechanical suspended scaffold system shall only be used for touching up, repair and redecoration and minor work. Where mechanical suspended scaffold system is to be used, first obtain a Certificate of Registration under the Workplace Safety and Health Act from MOM and a written approval from the SO prior to its installation and usage. The mechanical suspended scaffold system shall comply with the requirements of the SS 598 and any amendment or re- enactment thereto. Where the use of access scaffolding is not stipulated, suspended scaffold may be used for finishing works. Provide lifelines for the mechanical suspended scaffold users to anchor their safety belts. TS 95/1065 978 Doc D.2/165 5.1.11 Authorised Operators for Machinery and Vehicles Employ only qualified operators for its site machinery. The operator for the machinery shall possess a Skill Evaluation Certificate (SEC) from the BCA Academy or other approved training centre. For the machinery whereby BCA Academy or other approved training centre does not conduct courses or practical tests for machinery operator, only authorise an experienced and trained operator who has at least a minimum of 2 years experience in operating the machinery. In the case of vehicles, which are operated within the Contract boundary, the authorised operator shall possess a minimum valid Class 3 driving licence from the Registrar of Vehicles (Singapore) or its equivalent. The equivalent of a minimum Class 3 driving licence shall first be verified by the respective embassy in Singapore and thereafter submitted to the SO for approval. Record the particulars of the operators for the machinery and vehicles in the prescribed form and submit to the SO for approval 1 week before the commencement of the Works. The prescribed form shall be updated and kept on the Site and made available for inspection at all times. 5.1.12 Safety Training 5.1.12.1 Safety Orientation Course Employ workmen who possess valid Safety Orientation Course Certificates. The Contractor shall be required to ensure that its workmen attend a prescribed safety refresher course at an interval of time decided by the SO. 5.1.12.1 Safety Training Course When directed by the SO, send employees/staff in the Contractors employ to MOMs accredited training providers for the appropriate safety trainings. The safety training shall be applicable to all levels of employees/staff stipulated in this subclause including top management at the site. Give particular attention to the needs of young employees/staff. Further training shall be required where: (a) Employees/staff are transferred or where employees/staff take on new responsibilities or where a change in the work activity or work environment could arise; and (b) There is a change in the work equipment or systems of work in use. Training shall be repeated periodically to ensure continued competence. TS 96/1065 978 Doc D.2/166 5.1.13 Tower Cranes and Other Tall Construction Equipment Comply with all height restrictions on the use of tower crane or other tall construction equipment, imposed by the Civil Aviation Authority of Singapore and Ministry of Defence. In addition, the height clearance of tower crane or other tall construction equipment shall be submitted to the SO for approval before they are brought to the Site. Force limiting device, speed limiters and moment limit switches shall be installed for all cranes. Submit detailed layout drawings and safety requirement of the tower cranes to MOM and the SO for approval at least one month prior to their installation. The Safety Factor for tower crane shall have a minimum of 1.3, which includes the built-in factor of safety for the tower crane. The lifting load shall include the weight of the component, the spreader beam and the lifting device. The tip-load shall have the capacity to hoist the heaviest component including the necessary lifting appliances. The slewing radii of the tower cranes shall not overlap, unless the tower cranes are equipped with an anti-collision system. It is not permitted to be hoisted over temporary building structures, outside the contract boundary and other sensitive areas. The slewing limit switch shall be activated to stop the slewing action before the jib slews into the overlap zone. The jib of a tower crane shall not be allowed to slew outside the Contract boundary lines without the written approval of the SO. The free-standing mast of the tower crane must be certified by the Contractor's PE prior to its use on the Site. Submit detailed drawings and calculations of the type of foundation support and the tie-back for the tower crane, duly endorsed by its PE, together with technical information to the SO for approval. The Contractor's PE shall certify that the free-standing height of the mast is structurally adequate and sound before the tie-back is installed. No tower crane shall be installed and supported on the constructed RC structure of a building. 5.1.14 Access for The Use of Mobile Crane and Piling Machines Next to Built-Up Area Where the Contractor uses mobile cranes and piling machines on the Site which is next to existing buildings or public roads or MRT lines, the access for the mobile cranes and piling machines shall be of steel plates or reinforced concrete or bituminous pavement as approved by the SO. All such access shall be provided over adequate compacted hardcore base. Provide full access for the movement of the cranes and piling machines and for their lifting or pile driving operations. The access shall be able to distribute the load so as not to exceed the bearing capacity of the underlying materials. Engage a PE to design the access. The drawings and calculations endorsed by the PE shall be submitted for approval by the SO before the construction of the access. The access shall be constructed according to the approved drawings and maintained in a good condition at all times throughout the Contract Period (including any extension thereof). The access shall be inspected by the Contractor's PE prior to its use. TS 97/1065 978 Doc D.2/167 5.1.15 Warning Signs and Lights Display warning signs of size 900 mm x 600 mm at strategic points around the periphery of the Site where trespassing is likely to occur. Such signs shall have the words "DANGER KEEP OUT" in the 4 official languages in red on white background with reflective material and approved by the SO. Warning lights shall be placed at similar positions at night to serve as a warning. If work is carried out near public roads, all signage shall comply with the recommendations of the Temporary Road Signage Manual issued by the LTA. 5.1.16 Mobile Crane Submit layout and details of the crane access to the SO for approval prior to the use of the crane on the access. Ensure and check that the crane access is properly constructed. Keep all records of inspections of the crane access at the Site and produce them for examination when requested by the SO. The boom of the mobile crane with hoisted load shall not be allowed to swing outside the contract boundary without the written approval of the SO. All hoisting areas must be effectively barricaded. Ensure the installation of barriers to warn the crane operator of depressions, excavated areas and other obstructions. Moment limiters shall be installed for all cranes. The safety factor for mobile crane shall have a minimum of 1.3, which includes the built-in factor of safety for the mobile crane. The lifting load shall include the weight of the component, the spreader beam and the lifting device. The tip- load shall have the capacity to hoist the heaviest component including all necessary lifting appliances. A Permit-To-Hoist must be obtained before any hoisting operation is carried out. Station a lifting supervisor on the Site to oversee and guide the crane operator during positioning, hoisting and slewing. The cranes shall be tested by an AE before its use on the Site irrespective of any valid test certificate. Ensure daily checks are carried out by the crane operator and maintenance checks conducted once every 3 months. The crane must have overhaul checks before it is used on the Site. Test certificate, overhaul certificates, maintenance certificates, inspection records by the crane operator, data on the AE and the Contractor's site engineer shall be properly documented, kept on the Site and produced for inspection by the SO. 5.1.17 Crane Operator, Lifting Supervisor, Rigger and Signalman Comply with the Workplace Safety and Health (Operation of Cranes) Regulations 2011. Appoint at least one full-time lifting supervisor to supervise all lifting operations of any crane for the Site. However, where more than one crane is used on the Site, the number of lifting supervisors employed by the Contractor shall be increased as required by the SO. No lifting activity shall be allowed without the supervision of the lifting supervisor. The lifting supervisor shall have a minimum of 3 years experience in construction work and lifting operations. He must be a site foreman or site engineer and possesses a certificate on Safety Instruction Course for Lifting Supervisor. He shall spend his time fully on all lifting activities and ensure that unsafe conditions are rectified. For lifting operations within the Site not next to existing buildings, public roads or MRT lines, the crane operators shall have a minimum of 2 years experience in the operation of cranes. The Contractor can employ crane operators with less than 2 years experience for lifting operations on site but subject to the following conditions and approval by the SO: TS 98/1065 978 Doc D.2/168 (a) The site must be situated in a non-built-up area and not next to existing buildings, public roads or MRT lines. (b) The crane operator shall be enrolled for the BCA Building Specialist Sponsorship (Crane Operations) programme at the On-the-Job Training (OJT) stage and be subject to the passing requirement of the programme. (c) Other measures as and when instructed by the SO, including the removal of such crane operator if the crane operator is found to be not operating the crane in a safe manner. Notwithstanding other provisions within this Clause, the employment of such crane operator will not subject the Contractor to cost omission. The Contractor can also employ apprentices from BCA Building Specialist Sponsorship (Crane Operations) programme for lifting operations on site but subject to the following conditions and approval by the SO: (d) The site must be situated in a non-built-up area and not next to existing buildings, public roads or MRT lines. (e) Contractor and crane supplier shall brief the Employer and Consultants on the risk assessment and control measures prior to deploying an apprentice on Site. (f) Tower crane is preferred to be sited on the inner side of building so that the building acts as a buffer. (g) Cranes collapse zone must not overlap with existing buildings or public facilities when it is free standing. (h) Apprentice shall operate the crane from the beginning of the construction. In the first few months, he will get used to the crane without involving heavy lifting of precast components. (i) Apprentice can only operate in the same crane on site till project completion and not allowed to switch crane. (j) Apprentice shall not operate in a crane serving a building under construction with storey height exceeding 25 storeys. (k) Apprentice shall pass a competency assessment under the BCA Building Specialist Sponsorship (Crane Operations) programme before being allowed to lift heavy precast components for installation. (l) A maximum of one apprentice can be employed on each site. (m) Other measures as and when instructed by the SO including the removal of the apprentice if the apprentice is found to be not operating the crane in a safe manner or/and not complying with the safety measures listed above. TS 99/1065 978 Doc D.2/169 Notwithstanding other provisions within this Clause, the employment of apprentices from the BCA Building Specialist Sponsorship (Crane Operations) programme will not subject the Contractor to cost omission. For lifting operations within a site which is next to existing buildings, public roads or MRT lines, the crane operators shall have a minimum of 5 years experience in crane operation. Nevertheless, upon the approval of the SO, the Contractor is allowed to employ crane operators with a minimum of 3 years experience in crane operation instead but shall subject to the following conditions and approval by the SO: (n) The crane operators shall pass an assessment by BCA on their competency. (o) The Contractor shall carry out risk analysis based on the positions of the cranes to decide which cranes would be suitable for deploying such crane operators. Generally, this means that such operators should operate tower cranes that are at least 50 m away from any existing buildings and facilities, and the collapse zone of the crane does not overlap with existing buildings. (p) Other measures as and when instructed by the SO. (q) Riggers and signalmen shall also be appointed for all lifting operations and they must have completed an approved training course. (r) The crane operator, lifting supervisor, rigger and signalman shall carry out their duties strictly according to the relevant regulations and other duties as the SO deems necessary from time to time. Submit a list of crane operators, lifting supervisors, riggers and signalmen with their names, identification card or passport numbers, qualifications and years of experience to the SO for approval 1 week before the use of the crane. The list shall be updated and kept on site at all times. The SO reserves the right to examine the list as and when required. 5.1.18 Temporary Staircases Provide and maintain 0.8 m minimum wide temporary metal staircases from one working floor to another. Place the staircases against the adjacent staircase walls or formwork of the staircase walls that are under construction. Provide the outer sides of the staircases with metal handrails 1.1 m above the outer staircase strings. The bottom of the staircases shall be covered fully with metal plate. Engage a PE to design the staircases. Submit the PEs drawings, details and calculations for approval by the SO before the construction of the staircases. TS 100/1065 978 Doc D.2/170 5.1.19 Gas Cylinders and Related Equipment Use gas cylinders fitted with a low pressure gauge and a high pressure gauge, a reducing valve with pressure regulator, and safety relief device. The gas cylinders shall not be kept in the same room where welding, cutting or heating is being carried out or placed within 5 metres of any source of heat. The gas cylinders must always be kept upright in a wheeled-trolley. The hose connecting a gas cylinder to an apparatus for cutting, welding, heating or other related works shall be of good construction and sound material, free from defect, properly maintained, and not entangled or kinked. A flashback arrester or any other similar device which stops flashback that is acceptable to the Commissioner for Workplace Safety and Health must be fitted at every outlet of a gas cylinder and every inlet of an apparatus. The gas cylinders and hoses shall be colour-coded to conform to SS 152: Specification for Identification of Contents of Industrial Gas Cylinders or any amendments thereof. Engage a competent person to check the safety devices referred herein once in every 6 months. The competent person is any person who is competent by education, training and experience on the safety and operational aspects of the use of gas cylinders and related equipment. 5.1.20 Socket Outlet Assembly Provide, install and maintain the socket-outlet assembly (hereinafter referred to as "SOA" for the purpose of this subclause) for all temporary electrical installations. The SOA shall be manufactured in accordance with the latest edition of SS 650-1. It shall be designed for wall mounting or fitted with castors so that it can be moved around on the Site. Every electrical equipment used shall be plugged directly into the industrial SOA. 5.1.21 Others Provide and maintain guards or fences or barriers around excavations, lift pits or other similar potential places of danger to prevent accidents. The guards, fences and barriers shall be of sound material, good construction and possess adequate strength. At the site entrance gate, provide a gantry fitted with a height control device and a siren to control the height limit of construction vehicle/machinery when the vehicle/machinery leaves the Site. This limit shall comply with the requirements of LTA. The Contractor shall provide and maintain storey number indicators of size 400 mm x 400 mm at every staircase area and 900mm x 900mm at the metal scaffold enclosing passenger cum material hoist. The indicators shall be displayed at alternate storeys starting from the second storey. TS 101/1065 978 Doc D.2/171 5.2 Safety Infringement Include in the Contract Sum for all costs and expenses for complying with the safety requirements. The SO shall conduct periodic inspections on the provision of safety measures with the Contractor's site safety supervisor or the Contractor's Representative. The Contractor shall rectify immediately any contravention of or non-compliance with the Workplace Safety and Health Act and its Subsidiary Legislation, Workplace Safety and Health (Construction) Regulations or safety measures specified. All Works or part of the Works may be stopped when the SO considers the working environment or procedure is unsafe for Works to continue. In such event, the SO may invoke the provisions of Clause 6 "Nuisance and Irregularities" and the Contractor shall not be entitled to any claims for compensation or extension of Contract Period. If the contravention is not rectified by the subsequent inspection, the SO may invoke the provisions of the clause on "Nuisance and Irregularities". Upon any accident or dangerous occurrence, occurring on site, the SO, the Employer or any Competent Authority may order a total or partial stoppage of the Works, depending on the nature and extent of the accident/dangerous occurrence, to allow for investigations and/or to carry out remedial measures. Under such cases, the Contractor shall not be entitled to any claims for compensation or extension of Contract Period. The SO may, at its absolute discretion, also invoke the provisions of Clause 6 "Nuisance and Irregularities" for the following type of incidents occurring in the course of or arising out of or in consequence of the Works: (a) Fatal accident, if the SO or Competent Authority is of the opinion that the accident is the result of the defaults, acts, omissions or negligence, in part or in whole, of the Contractor. (b) Other accident which the SO, the Employer or Competent Authority is of the opinion that the accident is the result of failure of the Contractor to provide necessary and sufficient safety measures stipulated in the Contract or the Workplace Safety and Health Act and its Subsidiary Legislation, the Workplace Safety and Health (Incident Reporting) Regulations. (c) Dangerous occurrence as classified in the Subsidiary Legislation, Workplace Safety and Health (Incident Reporting) Regulations, Part II if the SO, the Employer or the Competent Authority is of the opinion that the dangerous occurrence is the result of failure of the Contractor to provide necessary and sufficient safety measures stipulated in the Contract or the Workplace Safety and Health Act and its Subsidiary Legislation, the Workplace Safety and Health (Incident Reporting) Regulations. TS 102/1065 978 Doc D.2/172 5.3 Reporting of Accidents and Dangerous Occurrence In the case of an accident or dangerous occurrence as classified under the Workplace Safety and Health (Incident Reporting) Regulations, the Contractor shall notify the Employer and relevant Authorities within one hour of an incident. After being informed of it, the SO or the Employer may at his discretion make a preliminary investigation of the circumstances and record its findings. Notwithstanding the aforementioned requirements, make an incident investigation and prepare/submit an incident investigation report to SO and the Employer within 10 days of the incident. Upon submitting this report, arrange for the injured workman, witnesses and an interpreter, if necessary, to report to SO to furnish evidence relating to the incident. If the Contractor fails to give any required notice or fails to furnish evidence of the incident as required in this Clause, the SO may at his discretion invoke the provisions of Clause 6 "Nuisance and Irregularities". 6 NUISANCE AND IRREGULARITIES 6.1 Irregularities If the Contractor is found to have committed any of the following irregularities: (a) Omitting building materials or labour, reducing the sizes of the materials, using inferior materials; or materials constructed not according to the Specification or Drawings; (b) Creating nuisance at the Site thereby causing inconvenience to the SO or the public or committing similar acts (such as not complying with site safety requirements, etc.) which are likely to bring the Employer into disrepute; (c) Non-compliance with any part of the Specification or Drawings, or non-fulfilment of any contractual obligation. The SO or Employer is empowered to respond in one the following ways: 6.2 (i) Order any irregular work to be removed and made good to the satisfaction of the SO or Employer at the Contractor's own cost and expense. (ii) In lieu of correcting work not done in accordance with the Contract, the SO or the Employer may allow such work to remain and shall recover any cost differences between the specified requirements and the non- compliance. Nuisance For nuisance committed on the Site, take immediate action to cease the nuisance committed upon instruction given by the SO or Employer. TS 103/1065 978 Doc D.2/173 7 SPECIAL CONDITIONS ON SURVEY WORKS 7.1 General Requirements for Land Survey Services The Contractor shall engage a registered surveyor at its own cost and expense to provide Land Survey Services to facilitate construction works and to carry out surveys for record purposes or for submission to authority as and when requested by the SO during construction and post construction stage. The cost incurred shall include the purchase of information and any equipment required for the survey works. The Contractor shall be held fully responsible for the accuracy of all the survey works carried out by its Registered Surveyor and for ensuring the Works fully comply with the following: 7.1.1 (a) Technical requirements and standards in the conduct of the surveys as specified in the latest version of the land surveyors board directive on engineering and hydrographic survey practices. (b) Technical requirements and standards in the conduct of the surveys as specified in the latest Singapore Land Authority (SLA) directive on cadastral survey practices; (c) Circulars that are issued from time to time by the Chief Surveyor, Singapore, SLA. (d) A field works and office works are executed by the Registered Surveyor or qualified staff under the registered surveyor direct supervision and direction. (e) All documents and survey works pertaining to the survey are certified and dated by the registered surveyor supervising the survey. (f) Latest SLAs Standard and Specification for 3D Topographic Surveying (Mapping) in Singapore For Projects with Contract Sum of $50 Million and more For projects with contract sum of $50 million and more, the Contractors Resident Surveyor or Lead Surveyor performing land surveying works on site must be a registered Technical Member of Singapore Institute of Surveyors and Valuers (SISV) from 1 Jan 2017 onwards. 7.2 Pre-condition Survey Where applicable, prior to and upon completion of the Site Works, carry out a condition survey to adjacent buildings in accordance with the requirements of Section C01-020 "Condition Survey". Submit all records to the SO and adjacent property owners where directed. The influence zone due to the excavation works with the sheet piles as support system shall be according to BCA requirement. Keep a copy of the survey report on site ready for inspection. TS 104/1065 978 Doc D.2/174 7.3 Engineering Survey Services (Construction Stage) All forms of land survey services required for the purpose to facilitate the construction works or survey works requested by the SO in relation to the construction of the projects shall be performed by the Contractors Registered Surveyor. Such surveys shall include the following: (a) Setting out of parcel boundaries, grids, piles position, building blocks, minor sewer and service roads alignments, etc. (b) Piles eccentricity checks survey. (c) Topographical survey of surrounding services and roads. (d) As-built survey of services and preparation of setting out plans, cross-sectional and longitudinal plans and surveys to monitor ground settlement, where applicable. (e) Last inspection chamber/sewer manhole. (f) SPPG electrical substation The Registered Surveyor engaged by the Contractor to prepare the pre-computation plan shall ensure the approved pre-computation plan tallies with the Consultants drawings. The Contractor receiving the approved pre-computation plan shall also check that it tallies with the Consultants drawings. Prior to the setting out of the piles position, the Contractor shall ensure that the distance between the piles position and the parcel boundary, the distance between the piles position and the building block, and the distance between the piles position and the gridlines are according to the Consultants drawings. 7.3.1 Additional Site Investigation Carry out additional ground investigation where additional information is needed for the Works or when directed by the SO. Carry out the Works in compliance with Section C02-010 "Ground Investigation" and BCA requirement. The permeability, strength of the subsoils and the groundwater level are key design parameters to be ascertained to determine the required penetration depth of the sheet pile wall to ensure overall stability and seepage cut-off. Carry out the boreholes pregressively, prior to commencement of the Works in areas according to the Contractor/s contruction programme. On completion of drilling, backfill the boreholes with a suitable bentonite/cement mix. Submit the location and schedule for the boreholes to the SOs acceptance prior to carrying out the Works. On completion, prepare the site investigation report and submit to the SO for acceptance. The Contractor shall report immediately to the SO any circumstance which indicates that in the Contractors opinion, the ground conditions differ from those reported in or which could have been inferred from the subsurface investigation reports. TS 105/1065 978 Doc D.2/175 8 CONTRACTOR TO VISIT SITE The Contractor shall be deemed to have taken note of all conditions for the construction and completion of the Contract, in particular, the following conditions pertaining to this Contract and satisfy itself on and make provision in the Contract Sum: (a) The nature of sites and soils both above and below ground with respect to various stages of construction in particular the possible existence of boulders/granite underground and other buried materials which have to be removed from site. (b) The provision of temporary access for traffic diversion while work is in progress to ensure undisrupted movement of traffic at all times. (c) The effect of existing properties, building structures / foundations. (d) The availability, supply of and conditions affecting labour within the Contract Period. (e) The effect of other contractors or persons approved by the SO, working within the contract area. (f) The probable adverse effect of the weather on the execution of the Contract. (g) The effect of execution of works due to the presence of hard soil strata, existing services, etc. (h) The means of access to facilitate the transportation and movement of construction equipment. (i) The general ground levels, spot levels of the work site. (j) The provision of earth drains; silt traps and the requirements to deal with drain diversion. (k) All aspects of local conditions, physical or otherwise, at the site that pertains to or affects in any way the construction works required at the Site concerned. (l) The effect of encountering various existing cables, pipes, sewers, etc. which may require diversion. (m) The effect of heavy vehicular and pedestrian traffic. (n) The necessary re-instatement of all affected turfing areas and works affected by this contract. TS 106/1065 978 Doc D.2/176 The Contractor must also ascertain for itself the most convenient and expeditious method of carrying out the Works. The working conditions and the space to be made available as a work site should be inspected and no claims shall be allowed on the ground of lack of knowledge of the conditions under which the work will be executed. The Contractor shall note that all information regarding existing levels given in the drawings only serves as a guide and it shall obtain its own information whenever it is doubtful. No claim by the Contractor for additional payment will be allowed on the ground of any misunderstanding or misinterpretation in respect of any such matter nor shall the Contractor be released from any risks or obligations imposed on or undertaken by itself under the Contract on any such ground or on the ground that it did not or could not foresee any matter which might affect or have affected the execution of the Works. TS 107/1065 978 Doc D.2/177 (2) C01-010 Demolition and Site Clearance TS 108/1065 978 Doc D.2/178 1 GENERAL Read this Section with G01-010 "General Requirements" and all other contract documents. 1.1 Scope This Section covers the requirements for works involving the demolition of existing buildings and other structures and general site clearance. The scope of demolition works and particular requirements are as indicated and shown in the drawings. [Note 1: The drawings should specify and indicate particular requirements relating to and information about the existing structures, restrictions on working methods, constraints imposed by the permanent works, etc. If there are particular phasing requirements due to either structural issues or access/availability, these must be adequately described, similarly occupied premises. Requirements for partial demolition should be fully described. Identify in the drawings if the works are within the MRT Protection Zone.] 1.2 Related Sections Read this Section in conjunction with the relevant requirements of the following sections: 1.3 C01-020 Condition Survey C02-020 General Earthworks (Excavation and Filling) C02-050 Instrumentation and Monitoring Standards, Codes, Regulations and Technical References TS 109/1065 978 Doc D.2/179 1.3.1 Standards and Codes Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant requirements of the Standards and Codes listed below or referenced in the body of the Specification. Alternative Standards and Codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative Standards and Codes comply with the requirements of the standards specified. All Standards and Codes quoted are the current version, unless specific year references are noted. In the event that the Standards or Codes are partially superseded or become obsolete, refer to the latest edition or the approved substitution for the relevant clauses. Singapore Standards NA to SS EN 1991-1-4 Singapore National Annex to Eurocode 1: Actions on Structures - Part 14: General actions - Wind actions SS CP 14 Code of practice for scaffolds SS CP 20 Code of practice for suspended scaffolds SS CP 49 Code of practice for noise control on construction and demolition sites SS 280-1 Specification for metal scaffoldings - Part 1: Frame scaffoldings SS 280-2 Specification for metal scaffoldings - Part 2: Modular scaffoldings SS 557 Code of practice for demolition SS 568 Code of practice for entry into and safe working in confined spaces SS 580 Code of practice for formwork Other Standards BS EN 1808 Safety requirements on suspended access equipment - design calculations, stability criteria, construction - test BS EN 12811-1 Temporary works equipment. Scaffolds. Performance requirements and general design BS EN 12812 Falsework - Performance requirements and general design BS 5228-1 Noise and vibration control on construction and open sites - Part 1: Code of practice for basic information and procedures for noise and vibration control BS 5395-1 Stairs, ladders and walkways - Part 1: Code of practice for the design construction and maintenance of straight stairs and winders BS 5607 Code of practice for safe use of explosives in the construction industry BS 5974 Temporary installed suspended scaffolds and access equipment (partially superseded by BS EN 1808) BS 5975 Code of practice for falsework BS 6187 Code of practice for demolition for full and partial demolition [Note 1: SS 557 and BS 6187 provide detailed guidance on matters relating to demolition.] 1.3.2 Regulations Unless otherwise specified, the Works shall comply with the relevant sections of the following statutory requirements: TS 110/1065 978 Doc D.2/180 1.4 (a) Workplace Safety and Health Act (b) Workplace Safety and Health Guidelines - Management and Removal of Asbestos (c) Workplace Safety and Health (Scaffolds) Regulations (d) Asbestos Hazards in Building Work Involving Old Buildings, MOM (e) Revised Regulations to Enhance Protection of Workers from Asbestos Exposure, MOM (f) Workplace Safety and Health (Medical Examinations) Regulations 2011 (g) Requirements for medical monitoring, MOM (h) Building Control Act and Regulations (i) Environmental Protection and Management Act, NEA (j) Environmental Public Health Act, NEA (k) Environmental Pollution Control (Air Impurities) Regulations (l) Code of Practice for Railway Protection, LTA (m) Guide to Carrying Out Restricted Activities within Railway Protection and Safety Zones, LTA (n) Fire Safety Act; (o) Fire Safety (Building Fire Safety) Regulation; (p) Not In Use S(p) SCDF Code of Practice for Fire Precautions in Buildings. (q) PUB (Earth COntrol Measures) (r) Code of Practice of Sewerage and Sanitary Works Trade Preamble TS 111/1065 978 Doc D.2/181 1.4.1 Contractor’s Submissions and Proposals Propose and submit for SOs acceptance method statement that shall include sequence and method of demolition, protective measures and equipment for the demolition. Do not vary methods on site from the agreed method statement without prior approval by the SO. Notify the SO any proposed variations to the method statement within 14 days unless otherwise agreed. Propose as a response plan in the event that measures taken to control ground movement and vibration do not perform satisfactorily. 1.4.2 Engineering Design and Calculations 1.4.2.1 General Engage a suitably qualified, experienced and competent PE and other qualified and experienced personnel to prepare all drawings and calculations for the following works: 1.4.2.2 (a) Temporary support structures (b) Temporary hoarding (c) Scaffolding and staging Professional Engineer The responsibilities of the PE include the following: 1.4.2.3 (a) Planning of sequence of installation and dismantling (b) Assessment of the structural integrity of existing property and abutting property (c) Design of temporary vertical and lateral supports to prevent uncontrolled collapse (d) Design to control ground water and provision of temporary drainage (e) Assessment of construction loadings permitted on existing structure (f) Submission of all calculations to BCA for approval as required under the Building Control Act and to the other authorities for record. (g) Supervision of the demolition work in accordance with the Building Control Act and Regulations Temporary Hoarding Design the temporary hoarding to withstand all imposed loads due to wind, crowds and impact, where applicable, and to provide protection to workers and the public. TS 112/1065 978 Doc D.2/182 1.4.2.4 Scaffolding and Staging Provide PE’s endorsement when the scaffolding and staging works exceeds the following criteria: (a) The deck is more than 3 m above ground. (b) The deck carries an intensity of loading higher than 1.5 KN/m2. (c) The staging is more than 3 tiers. 1.4.3 Supervision 1.4.3.1 Demolition Engage a full-time qualified and competent supervisor with suitably experienced in demolition to supervise the work strictly in accordance with the directions of the PE engaged for the responsibilities as provided in Section C01-010: Clause:1.4.2.2. A competent supervisor shall have sufficient professional or technical training, knowledge and actual experience to enable them to: 1.4.3.2 (a) carry out their assigned duties at the level of responsibility allocated to them. (b) understand fully any potential hazards related to the work under consideration. (c) detect any technical defects or omissions in that work, recognise any implications for health and safety caused by those defects or omissions. (d) be able to specify a remedial action to mitigate those implications. Scaffolding and Staging Engage a registered scaffold erector to supervise the erection of all scaffolding and staging in compliance with Workplace Safety and Health (Scaffolds) Regulations. 1.4.4 Qualifications Provide evidence of past experience for all personnel to the SO for acceptance prior to commencement of the Works. 1.4.5 Verification of Information Obtain from the SO and verify available information relevant to the following: (a) Existing site surveys (b) Existing services TS 113/1065 978 Doc D.2/183 (c) Existing building on the Site (d) Site or ground investigation Carry out additional investigation or request from the Authorities to ensure that adequate information is available to carry out the Works. Allow for conditions peculiar to the site and all other matters affecting the proposed Work and allow as necessary for the types of materials to be excavated. 1.4.5.1 Existing Site Surveys Engage a Registered Surveyor to carry out or, if given, to verify the survey prior to commencement of the Works. 1.4.5.2 Existing Services Comply with all the statutory requirements in respect of the existing services at and around the vicinity of the Site. Terminate or divert all relevant existing services as required by the authorities prior to commencement of the Works. Obtain information on the existing services, including services to private properties. Verify actual sizes and locations of all services and mark on site prior to commencement of the Work. Conduct under ground services detection. Propose suitable method to the SO for acceptance. Mark type and depth of under ground services with signboards and overhead services with headroom markers. Inform the authorities any services encountered on site. [Note 1: Details of retained features and under or above ground live services should be provided. Include where appropriate their shut-off points. This information should be given on drawings. It is important to be clear that information from the authorities will be approximate only and will not cover property connections etc. Check the contract preliminaries and other sections for clauses that may give conflicting or duplicated information.] 1.4.6 Condition Survey Prior to and upon completion of the site works, carry out a condition survey to adjacent buildings in accordance with the requirements of Section C01-020 "Condition Survey". Submit all records to the SO and adjacent property owners where directed. Keep a copy of the survey report on site ready for inspection. TS 114/1065 978 Doc D.2/184 1.4.7 Instrumentation and Monitoring Provide instrumentation to monitor the ground movement, vibration and condition of adjacent properties. Refer to Section C02-050: Clause:3.1, and the drawings for the schedule of instrumentation required. If necessary or as required by the authorities, propose and provide additional instrumentation and monitoring for records. Take cognisance of and co-ordinate with other contractors on site who may be carrying out instrumentation and monitoring works to avoid duplication of installation and readings. For general requirements of the instrumentation and monitoring works refer to Section C02- 050 "Instrumentation and Monitoring". 1.4.8 Upholding of Adjoining Properties Accept responsibility for the upholding of the adjoining buildings and roads, footpaths etc., where applicable, together with the mains and services from the time of taking possession of the Site through the duration of the Works. Adequately maintain roads and footpaths within and adjacent to the Site and keep clear of mud and debris. 1.4.8.1 Weatherproofing of Adjoining Buildings Allow for the weatherproofing of any surfaces of the adjoining buildings that are exposed by the demolition as required. [Note 1: Where it is required, the form and life expectancy of the weatherproofing should be specified and agreed, if appropriate, with the owners of the adjacent building.] 1.4.9 Site Safety 1.4.9.1 General Do not permit any person to do anything not in accordance with the generally accepted principles of safe and sound practice. Ensure a safe environment on the Site at all times. Maintain all safety provisions properly and do not remove any specific equipment, etc., without the written acceptance of the SO. Ensure that all personnel take necessary and sufficient safety precautions. 1.4.9.2 Legislation Compliance Site safety shall comply with the WSH Act and its subsidiary legislations, including WSH Regulations and Code of Practices issued by the Workplace Safety and Health Council. Obtain a Certificate of Registration under the WSH Act, and the necessary permits and approvals under the Building Control Act and Regulations prior to the commencement of the Works. TS 115/1065 978 Doc D.2/185 1.4.9.3 Site Safety Supervisor Employ a site safety supervisor with a recogniszed and approved certification in construction safety on full-time basis throughout the duration of site works. The responsibilities of the site safety supervisor include the following: 1.4.10 (a) To supervise safety and promote safety conduct (b) To inspect and rectify any unsafe place of work (c) To correct any unsafe practice (d) To ensure compliance with the provisions of the WSH Act and its subsidiary legislations Temporary Access Roads Submit the proposed alignments and levels of temporary access roads to the SO for acceptance prior to commencement of the Works. Maintain all necessary temporary access roads with drainage ditches over their full length. Divert and reinstate the permanent drainage system. 1.4.11 Temporary Access Stairways and Walkways Provide temporary access stairways and walkways in compliance with BS 5395-1, particularly with respect to minimum headroom and clearance, both vertically and perpendicular to the plane of the stairs. 1.4.12 Temporary Works Erect all temporary structures in strict compliance with the PE's design. 1.4.13 Temporary Hoarding 1.4.13.1 General Erect protective hoarding, safety netting/catch platform or other structures to ensure public safety prior to starting demolition works. Provide, erect and maintain a continuous hoarding around the entire contract boundary prior to commencement of the Works. Erect the hoarding at not less than 300 mm away from any permanent structure such as footway, drain, pipeline, etc., unless otherwise agreed. TS 116/1065 978 Doc D.2/186 1.4.13.2 Type of Hoarding The types of hoardings to be erected depend on the building locality and the demolition zone. In general, the categories of hoarding shall be as follows: Category A: Protective hoarding for use where footway is needed. Category B: Protective hoarding for use where footway is not needed. Category C: Protective hoarding erected on carriageway. Category D: Scaffold hoarding shall be minimum 6.8 m high where the distance between the building edge and the hoarding is less than 1½ times the height of the building. Category E: Metal hoarding shall be minimum 2 m high where the distance between the building edge and the hoarding is more than 1½ times the height of the building. Provide the categorty type of hoarding as indicated and specified in the drawings or as directed by the SO. Unless agreed by the SO, the hoardings shall be in accordance with SS 557. 1.4.13.3 Access Locations Provide metal gates/doors with minimum and maximum height as indicated in the drawings for the main and side entries located at approved positions. There shall be a maximum of 2 entry points for the entire site unless otherwise agreed. 1.4.13.4 Hoarding Decoration and Signage Maintain the hoarding and gates at all times to ensure no deterioration of the structure and fading of the paint works throughout the duration of the Contract. Display "DANGER", "KEEP-OUT" and "NO TRESPASSING" signs in the 4 official languages at conspicuous locations on the exterior side of the hoarding. Paint such signs in red and white background with gloss finishing enamel paint. 1.4.13.5 Project Signboard Where required, incorporate project signboard according to architectural drawings as part of the hoarding. 1.4.14 Site Inspection Visit and inspect the Site to understand the conditions and characters of the Works and to ascertain the exact position and full extent of the Works. 1.4.15 Demolished Material Take possession of all demolished material and hand over those identified in the drawings or as directed by the SO. Dispose all debris at NEA approved tips. Take special care to prevent debris from site being carried or blown onto surrounding areas. Clean vehicle wheels before the vehicle leaves site. TS 117/1065 978 Doc D.2/187 1.4.16 Rubbish Take all reasonable steps to minimise waste production on site. Dispose rubbish and unwanted non-hazardous materials at NEA approved tips and keep the site clean and tidy. Remove all rubbish, dirt and residues from voids and cavities before filling or closing in. Sort and dispose of recyclable materials at an NEA approved Material Recycling Facility where applicable. Retain waste transfer documentation on site. 1.4.17 Burning on Site Do not permit burning of materials. 1.4.18 Reinstatement and Making Good 1.4.18.1 General Avoid damage to existing structures, pavements and properties. Reinstate and make good any damage caused by or as a result of the Works. Reinstatement and making good shall also include all affected fixtures, fittings and finishes. 1.4.18.2 Consent If it is found necessary to break up existing pavement, road, footpath, etc., for purposes as required in the Contract, notify the SO accordingly prior to commencement of Works. If work is to be carried out on public roads, obtain permission from LTA. 1.4.19 Security Adequately safeguard the site, products, materials, plants and any existing buildings affected by the Works from theft. 1.4.20 Pest Control Engage a pest control operator who is registered with the BCA under the Work Head for Pest Control to provide comprehensive pest control and surveillance work on the Site. Submit the name of the pest control operator and proof of BCA registration to the SO for acceptance prior to commencement of the Works. Pest control and surveillance programmes shall comply with the requirements of the NEA as listed below: TS 118/1065 978 Doc D.2/188 (a) Submit a detailed pest control and surveillance programme to the Environmental Health Office, NEA prior to commencement of the Work. (b) Maintain a site register containing an up-to-date record of pest control and surveillance that have been carried out. Make site register available for inspection by the SO. (c) Take all necessary measures to prevent the site (including vacant flats where relevant) from becoming conducive to the breeding or harbouring of vectors. (d) Carry out site checks at least once a week to detect and remove breeding and harbouring grounds. 1.4.21 Pollution Control 1.4.21.1 General Take all reasonable precautions to prevent pollution of the site and the general environment, including streams and waterways. If pollution occurs, inform the appropriate authorities and the SO immediately and provide them with all relevant information. 1.4.21.2 Air Pollution Control Take all necessary measures to abate the discharge of smoke, fumes or obnoxious gases from any construction equipment. Stop using construction equipment discharging excessive smoke, fumes or obnoxious gases and replace it with the accepted equipment. Comply with the relevant provisions of the Environmental Pollution Control (Air Impurities) Regulations and/or any requirement of other relevant authorities. 1.4.21.3 Dust Control Take all necessary measures to control the dust such as periodically spraying demolition works with water. For buildings exceeding 6 storeys, erect fine netting adequately supported to a minimum height of 6 m above the hoarding for further dust control. 1.4.22 Fire Prevention Take all necessary precautions to prevent personal injury, death and damage to the Works or other properties from fire. Comply with SCDF’s requirements for Fire Prevention on Construction Sites. [Note 1: Existing buildings, particularly old ones and those that are listed will generally represent an extreme risk where additional precautions are necessary.] TS 119/1065 978 Doc D.2/189 1.4.23 As-Built Site Survey Carry out a complete topographical survey of the Site upon completion of the Works indicating levels of ground and remaining structures and services, and other ground features remaining on site. 1.4.24 Quality Control Plan Submit and work to a quality control plan as agreed with the SO. Refer to the Section G01-010: Clause:1.4.7. 1.5 Definitions and Abbreviations 1.5.1 Definitions 1.5.1.1 temporary works All construction works that are not part of the permanent works but are required in order to complete the permanent works. 1.5.2 Abbreviations No item. 2 PERFORMANCE REQUIREMENTS 2.1 Contractor’s Design 2.1.1 Temporary Works Design temporary works in accordance with the relevant standards and codes, and statutory requirements. The design shall include foundations or other appropriate supports. Refer to BS EN 12811-1 that specifies performance requirements and methods of structural and general design for access and working scaffolds. 2.1.2 Hoarding Design Design hoarding in accordance with the relevant statutory requirements. Ensure that the hoarding erected is able to resist all relevant design loading. 2.2 Falsework TS 120/1065 978 Doc D.2/190 2.2.1 Foundations Foundations for falsework shall be suitable to sustain the calculated maximum loads without failure or unacceptable settlement. 2.2.2 Duration of Use Falsework shall remain in place until the elements of the permanent construction are capable of selfsupport. 2.2.3 Protection from Impact Protect falsework from accidental impact such as passing vehicles, plant and cranes. Where a residual risk of impact is identified design the system accordingly. [Note 1: Bollards and barriers, or concrete encasement may be used at low level. There may be a risk due to crane swinging, etc., which needs to be considered. A horizontal load of 25 kN is sometimes adopted for design but this needs to be assessed together with the level at which it would be applied.] 2.3 Ground Movements and Vibrations Generally comply with the requirements of BS 5228-1. The vibration generated by the works in MRT structures not to exceed a peak particle velocity of 15 mm/s. Unless otherwise directed, refer to Section C02-050: Clause:4.2.2 for general restrictions on ground movements and vibration limits for adjacent structures where relevant. 2.4 Noise Nuisance Take all necessary actions to ensure compliance with the Environment Public Health Act or the current noise control regulations imposed by the NEA and any relevant authorities. 2.5 Works within Railway Protection Zone and Railway Safety Zone Comply with all the provisions under the latest LTA Code of Practice for Railway Protection and the Guide to Carrying Out Restricted Activities within Railway Protection and Safety Zones for the Works and other activities within the railway protection zone and railway safety zone. 3 MATERIALS AND EQUIPMENT TS 121/1065 978 Doc D.2/191 3.1 Falsework Comply with the requirements of SS 580, BS EN 12812, and BS 5975 where appropriate. [Note 1: SS 580 is code of practice for formwork (formerly CP 23). Note 2: BS EN 12812 specifies performance requirements and sets out the rules that have to be taken into account on falsework structure. BS 5975 gives guidance on the procedural controls to be applied to all aspects of temporary works and includes guidance on design, specification, construction, use and dismantling of falsework.] 3.2 Backfill Material Comply with the requirements of Section C02-020: Clause:3.1, unless otherwise agreed by the SO. 3.3 Scaffolds and Access Equipment Comply with the requirements of BS EN 12811-1 and BS 5974, and WSH Act and Regulations. 3.4 Prohibited Equipment Do not use the prohibited equipment and methods as scheduled in the drawings or as directed by the SO. 4 WORKMANSHIP 4.1 Survey Prior to the commencement of the Works, verify all available information. Carry out a detailed visual survey and examination of the physical condition and structural stability of the building(s) to be demolished and other surrounding buildings. Take photographs where necessary. Carry out a further survey and examination of the structures on completion of the Works. [Note 1: This clause requires a detailed post tender survey by the Contractor, an essential activity if subsequent problems are to be controlled. Information included in the tender documents or made available for inspection should be comprehensive enough to enable the Contractor to comply with all parts of this clause. Some types of structure present special hazards for demolition work, e.g., prestressed or post- tensioned constructions. Demolition procedures described in Health and Safety Executive Guidance Notes GS29/3 should be followed.] TS 122/1065 978 Doc D.2/192 4.2 Demolition Methods Identify appropriate method for demolition by completing risk assessments for the Works. Adopt specific precautionary safety measures appropriate to the proposed method. Establish and maintain safe working spaces and exclusion zones as appropriate. Ensure all personnel are familiar with and trained in the use of the particular plant and machinery that will be used. Follow the requirements of the method statement for the Works. [Note 1 : Detailed guidance is given in BS 6187 and SS 557. ] 4.3 Precautions Against Uncontrolled Collapse Ensure that the removal of certain parts of the building or structure during demolition will not affect the structural integrity of other parts. If at any time, it appears that the other parts have become unsafe or the structural integrity of the building is compromised, propose all necessary remedial actions to provide adequate support to the building to prevent uncontrolled collapse. Pre-determine where temporary support will be needed. If the structure abuts other buildings, provide such lateral support to prevent collapse. Provide adequate shoring before the existing lateral support is disturbed. 4.4 Safety Measures 4.4.1 Sequence Demolish buildings and other structures in the reverse order to that of their construction. The order of demolition for buildings should be progressive storey-by-storey, having regard to the type of construction. 4.4.2 Debris 4.4.2.1 Restrictions on Free Falling of Debris Allow demolition debris to fall freely to the ground internally or externally only where the horizontal distance from the point of fall to a public access or adjoining property is more than 6 m or half the height from which the debris is dropped, whichever is greater. In any case, ensure the erection of protective hoarding, safety netting/catch platform or other structures to protect public safety prior to starting demolition works. In cases when demolished material is allowed to fall freely externally, provide a covered hoarding with catch fan. In other cases, use chutes or skips. Prior to demolition of walls, sections of the floors should be removed by hand demolition to facilitate the free fall of debris. TS 123/1065 978 Doc D.2/193 4.4.2.2 Debris Accumulation Do not allow debris to accumulate above an average height of 2 m from ground level. Prevent debris from overloading scaffold platforms. 4.4.2.3 Use of Look-out When material is being dropped, post a look-out man to ensure safety generally. 4.4.3 Use of Swinging Ball Method Not used. [This section is not used as the use of swinging ball method is no longer practised.] 4.4.4 Use of Explosives Use of explosives will only be permitted subject to the following: (a) Obtain permission and approval from all relevant authorities. (b) Agree locations and times of use. (c) Comply with BS 5607. (d) Ensure that explosive charges are not excessive. (e) Protect properly charged boreholes. (f) Take proper precautions for the safety of persons and properties. [Note 1: The use of explosives may not be permitted in densely populated areas. ] 4.4.5 Scaffolding Defects Correct immediately any defects found during an inspection. If this is not possible, do not use the scaffold that shall be out of use immediately by removing all persons from it and placing a barrier and warning sign at each access point. 4.5 Temporary Structures Keep all such structures away from proposed roads, driveways, car parks and services lines. Maintain all such structures in a clean, hygienic and safe condition. Remove all such structures on completion of the Works. TS 124/1065 978 Doc D.2/194 4.6 Excavation Refer to Section C02-020: Clause 4.2. 4.7 Adjoining Properties When demolishing structure(s) against adjoining property, leave adequate temporary support and protection at each stage. Maintain and alter temporary supports and protection as necessary as work progresses. Ensure the Works do no cause damage to adjoining properties and do not leave unnecessary or unstable projections. Do not disturb foundations of adjoining properties. Report to the SO any defects exposed or becoming apparent in adjoining properties. Promptly repair any damage caused to adjoining properties by the Works. Make good to ensure safety, stability, weather protection and security. 4.8 Partly Demolished Structures Cut away and strip out with care to reduce the amount of making good to a minimum. Prevent debris from overloading any part of the structures to be retained. Leave partly demolished structures in a stable condition with adequate temporary supports at each stage to prevent risk of uncontrolled collapse. Prevent access of unauthorised persons to partly demolished structure(s). 4.9 Works within Railway Protection Zone and Railway Safety Zone 4.9.1 Restrictions on Plant No jib, lifting appliance or any other moving and stationery parts of the mechanical equipment shall encroach within 6m on plan from the edge of the nearest Mass Rapid Transit above- ground structures unless the equipment is restricted to work beneath the structure. Engage a Professional Engineer to certify that the foundation of the mechanical equipment is structurally sound and adequate prior to its installation. Install an auto cut-off system for tower cranes to prevent the top of boom to swing closer than 6m from edge of viaduct structure. The jibs of the cranes shall be pointed away from Mass Rapid Transit structures. The temporary access shall be stable for machinery to move on. 4.9.2 Equipment Checks Carry out regular checks to ensure that all mechanised equipment are in good working condition at all times. TS 125/1065 978 Doc D.2/195 4.9.3 Equipment Operators Employ only experienced, trained and competent operators for mobile cranes, tower cranes and other mechanical equipment. 4.9.4 Height Restriction Install a temporary height restriction gantry with signboard 6m away from the edge of both sides of the viaduct structure for any access passing underneath the Mass Rapid Transit structures. 4.10 Removal of Asbestos Material 4.10.1 Location of Asbestos If known to exist, asbestos materials are identified at locations as shown in the drawings. [Note 1: Where asbestos is present, the information should be provided in the drawings as comprehensive as possible in terms of location, type and nature for examples tiles, insulation, etc.] Undertake an independent survey to ascertain the presence, location, extent and nature of asbestos materials in the buildings. Report immediately to the SO any suspected asbestos materials discovered during demolition. Avoid disturbing such materials. Agree with the SO on safe methods for removal. 4.10.2 Regulations Undertake all asbestos removal work in strict accordance to the "Guidelines on Handling Asbestos Materials" and "Code of Practice for Handling of Asbestos Materials" issued by WSH Act, MOM. In general, notify MOM, Chief Inspector of Factories prior to commencement of the work in accordance to the Factories Act (Asbestos) Regulations, and Factories (Asbestos) (Amendment) Regulations. Submit X-ray examination report of the workers prior to commencement of the work to the OHD, MOM. [Note 1: These guidelines spell out safe work procedures and practices that workers carrying out such removal should follow.] TS 126/1065 978 Doc D.2/196 4.10.3 Preparation of Area Prior to the physical removal of the asbestos materials, carry out preparation of the asbestos work area by removing all movable objects to prevent contamination. Cover all immovable objects with polyethylene sheeting. Demarcate the asbestos work area to prevent unauthorised access, including warning signs. Remove the asbestos materials with minimal breakage and supplement by vacuuming using High Efficiency Particulate Air (HEPA) filter and/or wet method using water spray. 4.10.4 Safety Precautions Ensure all workers to use respirators, goggles and protective clothing. Collect all debris, used respirators, goggles and protective clothing into sealed and labeled impermeable containers. Consult NEA on the disposal of asbestos materials. 4.11 Precautions against Vibrations and Concussion Take special care for demolition of tall buildings to ensure that no undue vibration or concussion is caused which could result in damage to other properties, MRT structures, pedestrian crossings, underground services or drains or other adjacent properties by flying debris. 4.12 Site Drainage Prevent ponding on site from rainwater or other causes by pumping, creation of bunds, use of temporary drainage or other means prior to backfilling/levelling. 4.13 Unknown Hazards Inform the SO of any unrecorded tanks, chemicals, etc., discovered during demolition work. Agree with the SO methods for safe removal, filling, etc. 4.14 Open Basements Leave adequate buttress walls or provide temporary support to basement retaining walls up to ground level. Make the remaining sections of any retaining and buttress walls safe and secure. Make holes in basement floors to allow water drainage or penetration (depending on water table). Provide a hole not less than 600 mm in diameter for every 10 m² or as agreed with the SO. TS 127/1065 978 Doc D.2/197 4.15 Filling of Basements Leave adequate buttress walls or provide temporary support to basement retaining walls up to ground level. Make holes in basement floors to allow water drainage or penetration (depending on water table). Provide a hole not less than 600 mm in diameter for every 10m² or as agreed with the SO. Remove all organic material and soil from basements and other voids. Fill and consolidate with material as indicated in the drawings. [Note 1: Specify any particular requirements for fill material and drainage provision. The former might be e.g., well-compacted hardcore/selected material placed in layers not exceeding 150 mm thickness or foamed concrete.] [Note 2: Use this clause when it is advantageous for filling to be carried out as a demolition item. Basement party walls should be inspected to ensure they could withstand the pressure exerted by the fill. Where basements extend beneath footpaths or roads, they should be filled to the satisfaction of Land Transport Authority.] 4.16 Reinstatement and Making Good to Disturbed Areas 4.16.1 Services Temporarily disconnect and/or divert all affected services prior to the commencement of Works and reinstate immediately upon Substantial Completion of the Works. Reinstate and make good the affected Works and services in such a manner that upon substantial completion, they shall be in as good order and condition as they were at the commencement of the Contract. 4.16.2 Backfilling / Leveling / Compaction Refer to Section C02-020: Clause:4.7. 4.17 Completion Clean all rubbish, debris and surplus materials and leave the whole site clean and tidy. Complete to the required final condition of the Site as indicated in the drawings or as directed by the SO. [Note 1: Example on requirements: - Grade the site to follow the levels of adjacent areas - Cover the site using ... mm thick consolidated layer of ashes and ... mm thick consolidated layer of crushed hard rock.] TS 128/1065 978 Doc D.2/198 4.18 Preparation for Cultivation with Turfing Clean all loose stones, gravels, tree stumps and building debris in the areas indicated for turfing on the drawings. Loosen the top 100 mm deep layer and grade to fall as indicated. For specific requirements on turfing, refer to architectural specifications. 4.19 Other Particular Requirements Comply with other project specific requirements or restrictions for the Works as indicate in the drawings or directed by the SO. [Note 1: State any particular restriction on the methods or working conditions etc. if applicable to the project. ] 5 VERIFICATION AND SUBMISSION 5.1 Work Submissions Propose for the SOs acceptance, the list and timing for required submissions for the Works as follows where applicable : 5.1.1 (a) Design Submission (b) Method Statements (c) Site Management (d) Site Layout Plan (e) Survey Report (f) Scaffolding/falsework Inspection (g) Proposals for Monitoring MRT Structures for Vibration (h) Works within Railway Protection Zone and Railway Safety Zone Design Submission Submit the design, calculation and detailed drawings of temporary works, temporary hoarding, scaffolding and staging to the SO for acceptance at least 14 days before commencement of the relevant work. [Note 1: Buildings which may be adversely affected by demolition works include those housing sensitive equipment, (e.g., laboratories, hospitals, schools, etc.) Insert details of other information reasonably required to allow development of the appropriate health and safety procedures, e.g., TS 129/1065 978 Doc D.2/199 5.1.2 (a) results of tests to determine the precise nature of hazardous materials. (b) details of services supplied by the statutory boards. (c) structural calculations in support of method statements procedures and arrangements generally applicable to the demolition.] Method Statements Submit method statements covering the following and describing how and when the following tasks are carried out within 14 days from commencement of the relevant work: (a) Sequence, method and schedule of demolition (b) Sequence, method and schedule of excavation/backfilling (c) Services detection (d) Existing site surveys (e) Temporary access roads (f) Temporary access stairways and walkways (g) Temporary works (h) Temporary supports of buildings/services to be retained (i) Temporary hoardings (j) Scaffolding and staging (k) Fans and any other temporary works required (l) Plant and equipment (m) Debris disposal (n) Rubbish disposal (o) Asbestos material removal (p) Reinstatement and making good (q) Noise nuisance control (r) Vibration control (s) Pest control TS 130/1065 978 Doc D.2/200 (t) Pollution control (u) Dust control (v) Fire prevention (w) Safety measures [Note 1: Add any other additional items in the submission here. Potential risks to health and safety arising from the nature and condition of the site/existing buildings(s) shall be identified in the Specification. To specify maximum noise levels and the hours during which work may be carried out. Vibration may also be restricted if surrounding buildings are old or of historical importance, or are particularly sensitive to vibration.] 5.1.3 Site Management Submit to the SO for acceptance the following details soon as practical from commencement of the Contract: (a) Site organisation structure (b) Names and qualifications of Contractor’s staff (c) Names and qualifications of site safety supervisors (d) Names and qualifications of pest control operators (e) Names and qualifications of scaffolding inspectors (f) Quality control plan (g) Additional requirement as noted in the PSD [Note 1: Add any other additional items in the submission here. ] 5.1.4 Site Layout Plan Submit a site layout plan to the SO indicating proposed locations of all temporary structures for acceptance before their erection. Notwithstanding such acceptance, relocate any such structures when required to do so by the SO. 5.1.5 Survey Report Submit a survey report to the SO covering at least the following information: (a) Form, condition and demolition methods of the structure(s) TS 131/1065 978 Doc D.2/201 5.1.6 (b) Form, location and removal methods of any toxic or hazardous materials (c) Type and location of adjoining properties which may be adversely affected by noise, vibration, dust or removal of structure (d) Identification and location of services above and below ground (e) Type and location of any features of historical, archaeological or geological importance (f) Any potentially dangerous site conditions (g) Any constituent materials have deteriorated in strength to an extent that could result in instability due to a particular demolition process Scaffolding/ Falsework Inspection Submit scaffolding inspection record to the SO, including date of inspection, name of inspector and any defects/modifications/rectifications carried out. 5.1.7 Proposals for Monitoring MRT Structures for Vibration Submit proposals for monitoring the MRT structures for vibrations generated by the demolition works to the LTA for approval prior to the commencement of the Works, including the following: 5.1.8 (a) Proposal for monitoring the MRT structures for vibration generated by demolition work. (a) Method statement of demolition, including sequence, equipment to be used and proposals to reduce impact from falling debris onto the ground. (b) Proposal to trap/minimise dust from being sucked into MRT vent shaft and affecting the railway operation. (c) Condition survey of the affected structure carried out by an independent qualified building surveyor. Works within Railway Protection Zone and Railway Safety Zone Submit proposals on effective measures for the protection of MRT above ground structure together with the detail of activities of mobile cranes, tower cranes and other mechanical equipment adjacent to MRT structures to the SO for acceptance at least 1 month prior to the use of such equipment. 5.1.9 Quality Control Plan Prepare and submit the quality control plan for SOs acceptance prior to starting work. TS 132/1065 978 Doc D.2/202 5.2 As-built Survey After the completion of the demolition works, engage a Registered Surveyor to carry out a site survey of the Site and immediate surround. Submit copies of the survey plan as directed by the SO showing at least the following information: (a) Level of ground and structures (b) Existing structures known, both above and below ground (c) Existing services (d) Demarcation of property boundaries (e) Reserved zones as required by the authorities (f) Street furniture, drainage systems, etc. (g) Existing trees in accordance to NPark requirements TS 133/1065 978 Doc D.2/203 (3) C01-020 Condition Survey TS 134/1065 978 Doc D.2/204 1 GENERAL Read this Section with Section G01-010 "General Requirements" and all other contract documents. 1.1 Scope This Section covers the requirements for the condition survey of buildings, services and other structures within the area of influence of other construction works. This includes condition survey that is carried out prior to and or after the execution of the construction works. This Section applies generally to buildings, services and other structures that could be affected by works such as the following: (a) Demolition (b) Piling (c) Earthworks The requirements for instrumentation for monitoring are given in Section C02-050 "Instrumentation and Monitoring". [Note 1: Use the drawings to set out the specific requirements in terms of requirements or performance for a given project. The Work covers two specific aspects: the initial survey, followed by the monitoring during the course of the Work. In some cases, a post-condition survey is required. The survey is only for the purpose described, and makes no representation concerning the underlying condition or integrity of the buildings/structures/services concerned, although the responsibility of the Contractor to avoid damage to the buildings remains as stated in the related section.] 1.1.1 Prescribed Scope of Survey Carry out the condition survey for the specific buildings as identified and shown in the drawings or as directed by the SO. [Note 1: Specifier may define specific buildings here, such as conserved buildings, essential buildings, etc.] 1.2 Related Sections Read this Section in conjunction with the relevant requirements of the following section: C02-050 TS 135/1065 978 Doc D.2/205 1.3 Standards, Codes, Regulations and Technical References Undertake the Works in compliance with all standards and regulations as required by the authorities. 1.4 Trade Preamble 1.4.1 Contractor’s Submissions and Proposals Propose suitable methods of survey and instrumentation for the purpose of monitoring, for SOs acceptance and comply with such. 1.4.2 Access to Adjacent Sites Obtain appropriate permission for access to adjacent sites prior to commencement of the Works. Provide arrangements for the access as shown in the drawings or as directed by the SO. 1.4.3 Quality Control Plan Submit and work to a quality control plan as agreed with the SO. Refer to the Section G01010:Clause:1.4.7. 1.4.4 Verification of information Obtain relevant information on existing buildings, services and other structures from the SO. Verify the information given and, if necessary, carry out additional investigation or request from the Authorities to ensure that adequate information is available to carry out the works 1.4.5 Notice of Survey Provide within time specified in the drawings, notice of the intended date and scope of condition and postcondition surveys to the affected parties. 1.4.6 Instrumentation and Monitoring Install suitable instrumentation for continuous monitoring of the conditions of the prescribed buildings in the course of other construction works. Based on the condition of the buildings surveyed, propose suitable schedule of instrumentation and frequency of readings for the SOs acceptance. Take cognisance of and co-ordinate with other contractors on site who may be carrying out instrumentation and monitoring works to avoid duplication of installation and readings. For general requirements of the instrumentation, refer to Section C02-050 "Instrumentation and Monitoring". TS 136/1065 978 Doc D.2/206 1.4.6.1 Instrumentation Engineer Engage a suitably qualified and experienced engineer for the instrumentation and monitoring work to the SOs acceptance, to install, record readings and report for all instruments and monitoring. S1.5 Definitions a. Trigger Value The value of movement or vibration detected as reaching the “Alert” or “Work Suspension” level as defined below. b. Alert Level The value of movement or vibration detected at which the frequency of readings is reviewed and the instrumentation checked. c. Work Suspension Level The value of movements or vibration detected at which the work causing the movement or vibration is halted pending further review of both the structure and the methods of working. 2 PERFORMANCE REQUIREMENTS 2.1 The Survey Provide adequate information to allow agreement as to the condition of the identified buildings, services or other structures prior to the commencement of the construction works and any change in that condition that has occurred during and upon completion of the construction works. 2.2 Instrumentation and Monitoring Provide adequate record to identify changes that have occurred and allow changes to methods of the construction works in order to avoid or minimise damage to the surveyed buildings. When planning for suitable methods and instrumentation for the survey, take account of the limits on movements and levels of vibration, Section C02-050:Clause:4.2.2, as well as in the respective work sections relevant to the other construction works. Also take account of the frequency of monitoring as indicated in the respective sections. 3 MATERIALS AND EQUIPMENT 3.1 Instrumentation For general requirements of instrumentation and monitoring works, refer to Section C02-050 "Instrumentation and Monitoring". TS 137/1065 978 Doc D.2/207 3.2 Camera Use a camera capable of producing digital records of the survey unless otherwise agreed with the SO. [Note 1: Add detailed specification on the clarity of digital images required. Refer also to Section C01020:Clause:4.2.] 4 WORKMANSHIP 4.1 Working Method Plan to carry out the Works in a manner that the Works do not cause any damage to the buildings, services or other structures. Submit a workable and reliable working method to the SO for acceptance. If damage is inevitable, provide a solution to rectify the damage to the SO for acceptance prior to commencement of any work. 4.2 Photographic Record Unless otherwise agreed by the SO, submit digital colour photographs to the SO for record. Where a digital camera is used, submit an electronic copy of the photographs in a *.jpg or *.bmp format or any other format as agreed by the SO. The photographs shall show clearly all required details and shall contain a graduated scale and colour chart for reference. These photographs shall be taken under natural light condition and the intensity of light shall be uniform to reflect the natural colour of the intended objects. Use flashlight only as agreed. Ensure that all labels and markers are clearly identified within the photograph. 4.3 Installation of Instrumentation Give at least 48 hours’ notice of the intention to install any instrument unless otherwise agreed by the SO. Install all instruments and establish initial readings prior to the construction activity or area of works to which they relate unless otherwise agreed by the SO. 4.4 Crack Survey Carry out a visual survey of all structural elements in the adjacent properties for cracks in excess of 0.1 mm. Notify the SO if there are signs of structural damages. Mark the location of cracks thus identified on plans and elevations as appropriate. The survey shall include at least the cracks previously identified in the crack schedule as shown or indicated in the drawings or as directed by the SO. [Note 1: Drawings should provide and describe as actual width/hairline/taper dims; add any comment, e.g. plaster/paint flaking around crack, crack follows mortar joint/brick fractured, horizontal displacement across crack, etc.] TS 138/1065 978 Doc D.2/208 4.5 Level Survey Establish the initial (datum) reading of each survey point and submit records to the SO. Protect the datum during monitoring period. 4.6 Reflector Targets Install prism reflector targets at the locations shown in the drawings. 4.7 Plumb Survey Carry out a plumb survey to establish the verticality of the members where necessary. 4.8 Record of Defects Record any obvious defects on plans/elevations. 4.9 Reading of Crackmeters and Tiltmeters Typical details of acceptable installations for ground and building settlement points are shown in the drawings. Submit for approval details of any alternative installations. Monitor and record the levels of ground survey and building settlement points throughout the duration of the Works to the accuracy of 0.5 mm. 4.10 Readings of Vibration Sensors Readings to be carried out by qualified personnel only. 4.11 Monitoring Records Review the monitoring records on receipt. Notify the SO immediately if the alert or work suspension levels are reached and agree on any action proposed. 4.12 Reinstatement Reinstate all affected or damaged areas to the acceptance of the SO. 5 VERIFICATION AND SUBMISSION 5.1 Submissions TS 139/1065 978 Doc D.2/209 5.1.1 Method Statement Submit to the SO for acceptance, a method statement containing the following information for the buildings, services or other structures to be surveyed and monitored: 5.1.2 (a) Nature of survey to be undertaken (b) Scheduling and timing of survey and monitoring (c) Differentiating between initial survey and subsequent monitoring (d) Effect of alert and work suspension levels on timing of subsequent monitoring (e) Personnel undertaking survey and monitoring (f) Special concern and method of survey and monitoring (g) Anticipated damage to the surveyed area and proposed method of reinstatement Proposals for Monitoring Provide proposals for monitoring in the form of a method statement to the SO prior to commencement of the Work or as soon as practicable during the survey if the results indicate the need for additional monitoring. The proposals shall include the following: 5.1.3 (a) Proposed instrumentation (b) Details and drawings of instruments (c) Manufacturer’s specifications and recommendations for installation and maintenance (d) Details of sequence of assembly and connections (e) Location of instrumentation (f) Programme of installation (g) Details of monitoring arrangements and verification procedures (h) Frequency of readings (i) Format of records Quality Control Plan Prepare and submit the quality control plan for SOs acceptance prior to starting work. Refer to Section G01-010:Clause:1.4.7. TS 140/1065 978 Doc D.2/210 5.2 Survey Records Submit survey records within the time frame as as agreed by the SO after completion of the survey. Provide each neighbouring owner a copy of relevant portion of the survey as directed by the SO. Survey records shall include: (a) Photographic Records (Section C01-020:Clause:4.2) (b) Crack Survey Records (Section C01-020:Clause:4.4) (c) Level Survey Records (Section C01-020:Clause:4.5) (d) Records of Defects (Section C01-020:Clause:4.8) (e) Plumb Survey Records (Section C01-020:Clause:4.7) 5.3 Monitoring Records 5.3.1 General Submit 2 copies of preliminary records of the installation of each instrument within 24 hrs from the time of installation of each instrument. Submit final records for each instrument incorporating any comments from the SO within 7 days of completion of installation of each instrument. 5.3.2 Record information The records shall incorporate a graphical illustration of the instrument installation and shall include the following information: (a) Instrument number and location (in eastern and northern co-ordinates and level) (b) Names of personnel responsible for installation (c) Time and date for commencement and completion of instrument (d) Plant and labour used (e) Ground conditions encountered (if applicable) (f) Details of instrument installation (grout, fixings, etc.) (g) Instrument readings during installation, calibration and immediately after installation are completed (h) Location of instrument terminals, housings and any leads or cabling TS 141/1065 978 Doc D.2/211 5.3.3 (i) Details of any splices, numbers of casings or joins (j) Details of any breakdowns or delays Factual Reporting Submit the factual reports of monitoring results at intervals as specified or indicated in the drawings or as agreed by the SO. Submit to the SO in a format acceptable to the SO, a plan showing the location of the structure and instrumented lines and comprise at least the following: (a) Plots of measured parameters vs time, depth and/or location of construction activity with reference to each instrument etc., as agreed with the SO. (b) A comparison of data with predetermined trigger values (alert or work suspension levels), e.g. settlement vs time, horizontal deflections vs time, load vs depth of excavation, settlement vs location of construction activity / depth of excavation, etc. (c) Highlight of idle or damaged instrument and provide estimated time frame for corrective measures. 5.3.4 Interpretative Reporting 5.3.4.1 Frequency Based on the factual information received, submit for the SOs acceptance interpretative reports of monitoring results at intervals as agreed by the SO. When established trends indicate potential problems then such areas of concern shall be re- appraised at intervals consistent with the data collection and reports issued accordingly as required. 5.3.4.2 Report Content Interpretative Reports shall include a summary plot of all instrumented lines or points which indicate a trend (including historical data where appropriate) that could result in a work suspension level being exceeded and any instrumented line or point in which a work suspension level has been exceeded. Submit recommendations for any protective measures or actions that are necessary. 5.4 Post-completion Survey Records Submit the post-completion survey for the SO for record. Follow the same procedures as for the precondition survey unless otherwise required by the SO. TS 142/1065 978 Doc D.2/212 (4) C02-010 Site Investigation TS 143/1065 978 Doc D.2/213 1 GENERAL Read this Section with G01-010 "General Requirements" and all other contract documents. 1.1 Scope This Section covers the requirements for ground investigation, including: (a) Boring and drilling (b) Excavation of trial pits and trenching (c) Probing (d) Sampling (e) In-situ testing and laboratory testing (f) Monitoring This Section does not cover geophysical methods of investigation 1.2 Related Sections Read this Section in conjunction with the relevant requirements of the following sections: 1.3 C02-020 General Earthworks (Excavation and Filling) C02-050 Instrumentation and Monitoring Standards, Codes, Regulations and Technical References TS 144/1065 978 Doc D.2/214 1.3.1 Standards and Codes Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant requirements of the standards and codes listed below or referenced in the body of the Specification. Alternative standards and codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative standards and codes comply with the requirements of the standards specified. All standards and codes quoted are the current version, unless specific year references are noted. In the event that the standards or codes are partially superseded or have become obsolete, refer to the current edition or the approved substitution for the relevant clauses. Singapore Standards SS EN 1997-1 Eurocode 7: Geotechnical design - Part 1: General rules SS EN 1997-2 Eurocode 7: Geotechnical design - Part 2: Ground investigation and testing SS CP 79 Safety management system for construction worksites Other Standards BS EN ISO 14688-1 Geotechnical investigation and testing - Identification and classification of soil - Part 1: Identification and description BS EN ISO 14688-2 Geotechnical investigation and testing - Identification and classification of soil - Part 2: Principles for a classification BS EN ISO 14689- 1 Geotechnical investigation and testing. Identification, description and classification of rock. Part 1: Identification and description BS EN ISO 17892 Geotechnical investigation and testing. Laboratory testing of soil BS EN ISO 22475-1 Geotechnical investigation and testing. Sampling methods and groundwater measurements. Technical principles for execution BS EN ISO 22476-1 to 15 Geotechnical investigation and testing - Field Testing - Parts 1 to 15 BS EN ISO 22282-1 to 12 Geotechnical investigation and testing - Geohydraulic testing - Parts 1 to 12 BS 5930 Code of practice for site investigations BS1377-1 to 9 Soils for Civil Engineering Purposes - Parts 1 to 9 ASTM D1785 Unplasticized PVC pipe for industrial purposes Unless Singapore Standards are not available, all Eurocodes shall mean and refer to the Singapore Standard EN and their National Annexes. 1.3.2 Technical References Refer to the following technical references for guidance in carrying out the Works: (a) International Society of Rock Mechanics (ISRM), Standardisation of laboratory and field tests. Suggested Methods for determining the uniaxial compressive strength and deformability of rock materials (b) International Society of Rock Mechanics (ISRM), Testing methods. Suggested Method for determining point load strength TS 145/1065 978 Doc D.2/215 (c) BRE Special Digest 1 Concrete in aggressive ground (d) BRE Digest 251 Assessment of damage in low rise building (e) BCA/IES/ACES, Advisory Note 1/03 on Site Investigation and Testing (f) Geological Map of Singapore (g) BCA, Guidelines for Electronic Transfer of Site Investigation Data 1.4 Trade Preamble 1.4.1 Contractor’s Submissions and Proposals Propose for the SOs acceptance Provisional Bill of Quantities as provided in Appendix 1 to Section C020-010 "Ground Investigation" on the Works to be carried out as part of the ground investigation. 1.4.2 Co-ordination with Other Works Co-ordinate with other contractors who may carry out other works at the same time at the Site. Take into account site access, space occupation, safety and safeguarding of adjoining properties and each other’s works. 1.4.3 Temporary Access Provide temporary accesses required for the execution of the Works. Provide at all times during the progress of the Works proper means of access and the necessary attendance for inspection of the Works by the Employer or the Employer’s Representative as directed. 1.4.4 Water Supply Provide water required in connection with the Works, including the supply and fixing of all fittings, maintenance of the supply, removal of all fittings and making good all disturbances after completion of the Works. 1.4.5 Electrical Power Supply Make all necessary arrangements and supply any electrical power required for the Works. 1.4.6 Storage Facilities Provide proper facilities for the storage and protection of soil, rock and water samples. These facilities shall provide protection at all times from temperatures in excess of 35°C and from wetting or drying out due to weather exposure. TS 146/1065 978 Doc D.2/216 1.4.7 Quality Control Plan Submit and work to a quality control plan as agreed with the SO. Refer to the Section G01010:Clause:1.4.7. 1.4.8 Personnel 1.4.8.1 Supervising Site Personnel Engage qualified, competent and suitably experienced site personnel with the SOs acceptance, to supervise the Works and verify the accuracy of the investigation findings. Information on items to be verified, checked or monitored during the Works shall be clearly identified and made known to the supervising personnel. 1.4.8.2 Endorsing Professional Engineer Engage a suitably qualified, experienced and competent Professional Engineer (PE) to verify the accuracy of the investigation findings, tests and results, including all field and laboratory works, and interpretative reports as appropriate, and to endorse the ground investigation report. 1.4.8.3 Registered Surveyor Employ a Registered Surveyor to survey investigation points, including borehole locations and levels, and specific investigative locations, and submit the results to the SO together with the ground investigation report. 1.4.8.4 Engineering Geologist Engage a suitably experienced, qualified and competent engineering geologist at the Site to ensure the use of proper equipment, methods and procedures, materials and quality of the Works in compliance with specifications, and to ensure correct and accurate logging, sampling and testing in accordance with specified standards and codes. 1.4.8.5 Driller Engage a competent, qualified, and experienced driller who is in charge of drilling operations and the rig to ensure the use of proper equipment, methods and procedures, and materials for boring, drilling, probing, sampling, field tests, making groundwater observations in boreholes and properly recording the information obtained in accordance with the specifications and standards. TS 147/1065 978 Doc D.2/217 1.4.9 Upholding of Adjoining Properties Accept responsibility for the upholding of the adjoining buildings and roads, footpaths etc., where applicable, together with the mains and services from the time of taking possession of the Site through the duration of the Works. Adequately maintain roads and footpaths within and adjacent to the Site and keep clear of mud and debris. 1.4.10 Removal of Personnel, Improper Plant, Equipment or Tool Remove from the Site and replace any plant, equipment or tool not conforming to the requirements of the Specification and standards. Remove from the Site any personnel or operative found incapable or unsuitable for the Works, or refusing to follow or comply with the work procedure as specified, and replace without delay such personnel as directed by the SO. 1.4.11 Existing Services Affected by the Works Ensure that existing services affected by the Works are detected, protected and/or diverted. Comply with all requirements by the Authorities. 1.4.12 Damage to Overhead and Underground Mains and Services Take due care to avoid damages to electricity mains, water mains, telephone lines, sewerage mains, gas mains and the like. Ascertain the positions of all utility mains or services in the vicinity of the exploratory hole. Inform the SO immediately and propose alternative location for the SOs acceptance if any of the location of the exploratory hole coincides with the position of the utility mains or services. [Note 1: Trenching works can potentially damage underground utilities and services.] 1.4.13 Laboratory Testing Facilities Propose for SOs acceptance to carry out the laboratory testing at accredited testing laboratory or at an independent laboratory as directed by the SO. TS 148/1065 978 Doc D.2/218 1.4.14 Photographs Supply digital colour photographic records and data taken with proper lighting of samples, rock cores, excavation face of trench, trial pits, site conditions or such portion of the Works in progress or as directed by the SO, within 7 days of the taking of the photographs. Propose to the SO for acceptance with regard to the quality and format of digital images. Photographs shall show clearly all required details and shall contain a graduated scale and colour chart in a format to be agreed by the SO. Take the photographs under natural light condition with uniform intensity of light to reflect the natural colour of the intended object, e.g. cores, trenches, etc. [Note 1: As a minimum, digital images shall be at least 12 megapixels ( MP) and the camera sensor size not less than Advanced Photo System type-C (APS-C).] 1.4.15 Instrumentation and Monitoring Provide and monitor the instruments as indicated in the drawings or provided in the bill of quantities or as directed by the SO to monitor vibrations, noise and ground movements. If necessary or as required by the Authorities, propose and provide additional instrumentation and monitoring for records. Take cognisance of and co-ordinate with other contractors on site who may be carrying out instrumentation and monitoring works to avoid duplication of installation and readings. For general requirements of the instrumentation and monitoring works, refer to Section C02- 050 "Instrumentation and Monitoring". 1.4.16 Fenced Protection Protect all equipment and working area using fencing or other methods as appropriate. 1.4.17 Noise and Disturbance Take all necessary actions to ensure compliance with the Environment Public Health Act and Regulations or the current noise control regulations imposed by the NEA or any relevant authorities. The noise level at the nearest occupied building outside the Site shall not exceed the maximum permissible noise level stated in the NEA guidelines. 1.5 Definitions and Abbreviations 1.5.1 Definitions TS 149/1065 978 Doc D.2/219 1.5.1.1 Accredited Testing Laboratory This refers to an organisation or laboratory accredited under the Singapore Laboratory Accreditation Scheme (SINGLAS), and fully equipped and accredited to carry out the relevant tests and checks required by the Specification. 1.5.2 Abbreviations No item. 2 PERFORMANCE REQUIREMENTS 2.1 General Undertake the ground investigation works such that the execution, including boring, drilling, sampling, logging, making groundwater observations, and field and laboratory testing, is carried out according to the relevant standards and codes, with adequate supervision and quality control; and data are collected, recorded and interpreted by appropriately qualified personnel. Ground investigation comprising field investigations and laboratory testing, including drilling, sampling of soils and rocks, and groundwater measurements, shall be carried out and reported in accordance with internationally recognised standards and recommendations, in particular complying to the principles and requirements of SS EN 1990 and SS EN 1997-1 and SS EN 1997-2 and the related test standards cited therein. Deviations from these standards and additional test requirements shall be subject to the SOs agreement. 2.2 Sampling of Soils and Rocks Sampling of soils and rocks by drilling and excavations, and groundwater measurements shall be conducted appropriately to provide the prescribed laboratory quality class in accordance with SS EN 1997 for testing and the basis for assessment and evaluation of geotechnical parameters under SS EN 1997 requirements. 2.3 Description of Soils and Rocks Provide and report detailed descriptions for engineering purposes of all the soil and rock samples obtained. These engineering descriptions shall be accurately incorporated in the field logs to form part of the ground investigation report. For rotary cored boreholes, cores shall be logged and described in their fresh condition as the work proceeds. Where trial pits and other exploratory excavations are required and where existing natural or manmade exposures of the ground are involved, provide and report the detailed recording of the soils and rocks, their stratification, structure and fabric. TS 150/1065 978 Doc D.2/220 2.4 Method of Advancement and Locating of Boreholes The method of advancement shall be such that the boring can be completed and logged to the specified depth, with samples obtained, in-situ testing carried out and instrumentation installed as specified. Borehole locations shall be surveyed prior to drilling commencement and the drilled position shall be expressed in Northern and Eastern co-ordinate system with reference to the Singapore National Grid. All elevations, including ground level and top of instruments shall be in the nearest 50 mm relative to the Singapore Height Datum (SHD). 2.5 Reporting Requirements Reporting shall be in accordance with SS EN 1997 and all relevant authority requirements. 2.5.1 Digital Data Digital data, including AGS format data, for the survey information, boreholes and test results is required. The specific content and format shall be in accordance with BCA publication on guidelines for electronic transfer of site investigation data, and shall be subject to the SOs approval. 3 MATERIALS AND EQUIPMENT 3.1 General The drilling and sampling equipment shall be appropriate and in accordance with the following: (a) Sampling categories and laboratory quality class as defined in SS EN 1997-2. (b) Depth to be reached. (c) Required diameter of the sample. (d) Such functions required from the drilling rig as recording of the drilling parameters, automatic or manual adjustment. 3.2 Drilling and Sampling Equipment Drilling and sampling equipment adequate to the soil sampling category prescribed in SS EN 1997-2 are required to be in accordance with EN ISO 22475-1. Samples for tests as appropriate shall be in accordance with the sampling categories and laboratory quality classes prescribed in SS EN 1997-2. TS 151/1065 978 Doc D.2/221 3.3 Drilling Fluid for Rotary Coring Use clean water, air or air mist. Drilling muds or additives may be used subject to agreement with the SO. For ground conditions with artesian pressure, propose the unit weight of drilling fluid for the SOs acceptance. 3.4 Casing and Support of Borehole Sides Casing shall be used to the full depth of the boreholes at all times unless otherwise permitted by the SO. Submit for the SOs acceptance other methods of stabilisation of the borehole. Casing shall be used when there is doubt as to the effectiveness of the method of stabilisation. Methods of stabilisation involving the use of bentonite or other drilling fluids shall not be used when permeability tests are to be carried out or piezometers are to be installed. 3.5 Cement/Bentonite Grout for Backfilling Mix equal portions by weight of ordinary Portland cement and bentonite by hand or machine to a uniform colour and consistency before placing. Moisture content shall not exceed 250%. The mix shall provide a proper seal against the borehole wall and prevent the formation of potential seepage paths for groundwater through the borehole. For backfilling boreholes where there is no groundwater, add just sufficient amount of water to produce a pumpable mix. Where there is water in the exploratory hole, add only sufficient water to form a cohesive paste. 3.6 Sample Tubes Use hydraulic piston type of sampler unless otherwise agreed by the SO. Do not use plastic lining tubes in substitution for steel or aluminium sampling tubes. Use Mazier Sampler in place of the thinwalled sampler for stiff soil with the agreement of the SO. Thin-walled sampler tubes shall be made of steel or aluminium. Open tube and piston samples shall have a minimum of 75 mm internal diameter. 3.7 Standpipes TS 152/1065 978 Doc D.2/222 3.7.1 Tube Standpipe shall consist of a minimum 25 mm internal diameter unplasticised polyvinylchoride (uPVC) tube with minimum thickness of 2 mm with an end cap and slotted or perforated over its lower end. Unless otherwise agreed by the SO, the slots or perforations shall be at least 1.5 mm wide, and evenly distributed over the slotted or perforated part of the tube to provide a minimum open area of 30% of the total circumferential surface. The slotted part of the tube shall be wrapped with filter fabric as approved by the SO. The length of the slotted portion shall be 3 m at minimum. The standpipe shall be placed in the borehole, backfilled with graded filter sand (600 to 2 000 micron) up to 1.0 m below ground level or as specified or as directed by the SO. The top 0.5 m (as a minimum) of the borehole shall be sealed with a concrete plug and subsequent 0.5 m (as a minimum) depth sealed with bentonite pellets or with an approved bentonite cement grout. The top of the standpipe shall be covered by a plastic cap or similar as approved by the SO. 3.7.2 Filter Where gravel filter is required, use pea gravel or similar material, 6 to 10 mm in diameter. Where sand filter is required, the sand filter surround to the porous element shall be clean and fall wholly between the limits of grading 1200 and 210 microns and the volume of the sand filter placed shall be recorded. Ensure that no sand adheres to the soil in the sides of the unlined borehole. Where there is water in the borehole, allow sufficient time for all the sand to settle. The final elevation of the top of this sand shall be recorded. The porous element shall be placed in the hole and the remaining sand filter shall then be added as described above. 3.7.3 Grouting A grout of cement and bentonite shall be used. If water in the exploratory hole is contaminated by grout, replace with clean water using a method or procedure to be agreed by the SO. Unless otherwise approved by the SO, the grout shall consist of 4 parts of bentonite mixed with 10 parts of water to which is then added 1 part of ordinary Portland cement. [Note 1: It is common practice to seal the filter section with 0.5 m of bentonite pellets and then grout above to protect the filter.] 3.8 Piezometers The piezometer tip shall consist of a porous ceramic element or other elements not less than 150 mm long with a diameter not less than 40 mm, and shall be protected at each end by UPVC fittings. The porous element shall be a pore diameter of the order of 60 microns and permeability of the order of 3 x 10-4m/s. The tubes shall be jointed together and to the porous element with approved couplings and glue in such a manner that the joints remain leak-proof under the anticipated head of water. Piezometers shall generally be the Casagrande type or vibrating-wire type piezometers subject to the SOs approval. Refer to Section C02-050:Clause:3.10 for general requirements. TS 153/1065 978 Doc D.2/223 3.9 Field Vane Shear Tests The maximum period between calibration and use on site shall be 4 months. Submit calibration certificates for acceptance by the SO before commencement of field test. Calibration shall be repeated after completion of the site works. Permitted tolerances on vane dimensions shall be ±0.5 mm due to either manufacture or wear. Actual vane dimensions shall be measured at the start of Works to an accuracy of ±0.1mm. The vane dimensions shall be checked at the end of the Works. Permitted tolerances on the torque head measurements shall be ±5% of the measured value. 3.10 Pressuremeter Tests The pressuremeter shall be properly and appropriately calibrated at frequent intervals, including recalibrating daily or after every 10 tests or as directed by the SO for validation checks and results obtained. 3.10.1 Volume or Radius Measurements Methods of calibrating the volume or radius measurement system are required to include inflating the pressuremeter in close fitting (10% expansion) and loose fitting (80% expansion) steel cylinders, and calibrating individual feeler arms against a suitable micrometer or calliper gauge. Repeatable results to within the required accuracy have to be obtained. 3.10.2 Pressure Measurements An independent Bourdon gauge or equivalent device is required on site to check the calibration of the pressuremeter and the inflation of the pressuremeter in air at the operating testing rate. The repeatability of these tests shall be established. 3.10.3 Equipment for Pre-forming Holes Provide the necessary equipment for pre-forming holes on site, including a range of different types of core barrels of appropriate size, hand auger equipment, sampling tubes with an internal chamfer and an external diameter slightly larger than the pressuremeter, and borehole callipers. 4 WORKMANSHIP 4.1 Sinking Boreholes 4.1.1 Method of Advancement Unless otherwise specified, the following methods may be used as appropriate: (a) Rotary coring TS 154/1065 978 Doc D.2/224 (b) Percussion boring (c) Auger boring Submit proposal of a suitable method to be used and the justification for use to the SO for approval. The minimum nominal casing diameter shall be 150 mm. At ground level before boring commences, the initial casing diameter shall be sufficiently large to ensure that the borehole can be completed to its scheduled depth. 4.1.2 Circulation of Drilling Fluid and Cutting Sedimentation Pits Locate pits for circulation of drilling fluid and cutting sedimentation away from the borehole, and connect through trenches, unless otherwise agreed with the SO for other alternative methods due to site constraint. 4.1.3 Heaving of the Bottom of the Borehole Control the level of drilling fluid in the borehole at all times to be at least equal to or higher than the elevation of the groundwater to prevent heave and disturbance of the soil at the bottom of the borehole. This condition shall be strictly observed in boring through strata comprising sand or coarse silt, or in operations involving undisturbed sampling and in-situ testing. In strata comprising soft to very soft soils or when instructed by the SO, use appropriate drilling fluid in addition to full depth casing to stabilise the borehole. Drilling fluids shall not be used when permeability tests are to be carried out or piezometers are to be installed in the borehole. 4.1.4 Addition of Water Do not use water to advance the borehole other than in dry granular soils or otherwise agreed by the SO. If water is added to assist with the Works, record the depth when water is added. Maintain a positive hydraulic head in the borehole where it advances below the water table in cases where disturbance of the soils is likely. If boring indicates artesian or sub-artesian groundwater condition in granular soils, immediately add and maintain a head of water during boring and sampling in order to counteract the disturbance caused by the removal of overburden or inflow of groundwater. 4.1.5 Obstructions Use rotary coring method or a method agreed with the SO where a hard stratum or obstruction is encountered. Do not continue for more than an hour without informing the SO and obtaining the SOs further instructions. TS 155/1065 978 Doc D.2/225 4.1.6 Coring Through Hard Stratum When hard stratum is encountered, use a core barrel with a diamond-impregnated drill bit or other methods as agreed with the SO for sampling the stratum. Take samples at the change of such hard stratum. 4.1.7 Use of Clay Cutters Clay cutters shall not be used for advancing the boring in soils where they will cause excessive disturbance in soils to be sampled. Where clay cutters are permitted, they shall be of a type pattern approved by the SO, and the combined weight of clay cutter and any sinker bar shall not exceed 150 kg. 4.1.8 Continuation of Boreholes Cover any borehole remaining open overnight. The casing shall be pulled up by about 0.3 m and left in such position overnight to prevent the entry of rainwater and surface water but allow a free passage of air into the casing. Before the first sample is taken on the following new day of operation, advance the boring for at least 0.3 m. In soft soils, a head of water shall be maintained in the casing to minimise heave of the borehole. 4.1.9 Backfilling of Boreholes Do not backfill boreholes with soil arisings, unless otherwise agreed with the SO. Backfill all boreholes with cement bentonite grout, including boreholes for standpipes and piezometers together with their response zones installed at the depths specified, or as directed by the SO. Introduce the grout using a tremie pipe which shall be kept below the surface of the grout as filling proceeds. Agree with the SO on a suitable method to be used where ground condition is such that normal grouting is impracticable. Leave the area in a clean and tidy condition. 4.2 Pits and Trenches 4.2.1 Inspection Pits for Locating Underground Services Unless otherwise directed by the SO, excavate pit not less than 1.5 m2 by hand to a depth of 1.2 m and hand auger for another 1.8 m, making a total of 3.0 m to locate underground services. Use hand-operated power tools where necessary to assist the excavation. Record the positions, depths and dimensions of all services encountered in the daily reports. Exploratory holes shall not begin until the present or otherwise of all such services has been established. TS 156/1065 978 Doc D.2/226 4.2.2 Trial Pits and Trenches Excavate pits by hand to a depth of 1.2 m unless otherwise specified, or by machine to the required depth to enable visual examination and sampling from outside the excavation. Do not allow access to excavations greater than 1.2 m, unless the pits are shored, or benched or otherwise agreed with the SO. 4.2.3 Observation Pits and Trenches Excavate by hand or machine as required. Provide adequate and stable support to enable safe access for in situ examination, sampling and testing as required. The supports shall be placed so as to minimise interference with the taking of samples or inspection of the faces. Take all necessary safety checks, including checking for noxious or toxic gases or materials, or radioactive materials. 4.2.4 Dimensions of Pits and Trenches Unless otherwise specified, 4.2.5 (a) Inspection pits as in Section C02-010:Clause:4.2.1 shall have a base area not less than 1.5 m²; (b) Trenches other than as in Section C02-010:Clause:4.2.1 shall be 1 m wide. Groundwater Keep pits and trenches free from surface water run-off. Control ground water by pumping from a sump, but take adequate safety measures to maintain the stability of the excavation. 4.2.6 Description of Pits and Trenches Provide a log with detailed description of the nature of the ground encountered within the excavation, including: (a) the nature of the strata (b) the condition of the base (c) the presence of any water (d) suspected contamination (e) any special features Photograph each face of the excavation to show the details of the ground conditions and any unusual features identified. Photographs shall be taken or accompanied with a reference information board, including a colour chart, to show the pit reference number and the orientation of the face being photographed. TS 157/1065 978 Doc D.2/227 4.2.7 Sampling from Pits and Trenches If samples are recovered from trial pits and trenches, the requirements of EN ISO 22475-1 shall be followed. For small disturbed samples, samples of not less than 1 kg shall be taken at each change in soil type, change in consistency with an agreed method or as instructed by the SO. The samples shall be placed immediately in air-tight containers. For bulk disturbed samples, representative samples representative of the zone, of not less than 30 kg shall be collected over a depth interval of 0.5 m at specified depths with an agreed method or as instructed by the SO. 4.2.8 Protection to Excavations Left Open 4.2.8.1 Protection to Personnel Provide all necessary signing and lighting, together with temporary barriers/fencing. 4.2.8.2 Protection against Inclement Weather Provide all necessary precautions to protect the excavations from the effects of inclement weather. 4.2.9 Backfilling Backfill as soon as practicable using excavated material unless otherwise agreed. Compact with excavation plant or as agreed by the SO and subsequent checks to ensure the area remains level after filling. Remove any surplus material from site. Leave the area in a clean and tidy condition. 4.3 Sampling 4.3.1 Sampling by drilling The drilling equipment for sampling shall be selected according to following: (a) Sampling categories required, as defined in SS EN 1997. (b) Depth to be reached. (c) Required diameter of the sample. (d) Functions required from the drilling rig, e.g. recording of the drilling parameters, automatic or manual adjustment. The requirements of EN ISO 22475-1 shall be followed. TS 158/1065 978 Doc D.2/228 4.3.2 Open Tube and Piston Samples Soil sampling length shall be at least 1 000 mm long to have sufficient sampling length for laboratory testing. 4.3.3 Frequency of Sampling and Testing Requirements for the frequency of sampling and testing are given in the Provisional Bill of Quantities in Section C02-010:Clause:1.4.1 or otherwise instructed by the SO. Refer to SS EN 1997-2 on the mass of soil required for test on undisturbed samples. Specific sampling and in-situ testing pattern such as values of Standard Penetration Test (SPT) following every attempt to take an open-tube or piston sample, shall be approved by the SO. [Note 1: For establishing correlation between SPT-N value and Undrained Shear Strength, in- situ vane shear tests shall be carried out in separate borehole in close proximity, at 1 m away.] 4.3.4 Identification, Handling, Transport and Storing of Samples 4.3.4.1 General Handling, transporting and storing of samples shall be carried out in accordance with EN ISO 224751. TS 159/1065 978 Doc D.2/229 4.3.4.2 Identification, Storage and Disposal of Samples Remove all samples from the site of the boreholes at the end of each day's work and protect from excessive heat by storing on or near the site under cover and secured from interference. Any temporary store areas on site shall be subject to the SOs approval. Any such store area shall ensure samples are well protected from excessive heat (>35°C), rain and other elements. Samples shall be accessible and organised to allow fast location of particular specimens. Label all samples clearly and identify clearly any material that is or is suspected to be harmful. Seal, transport and store the samples so that no change in moisture content and soil structure occurs prior to laboratory testing. Store all samples in an orderly fashion at site in protective boxes in a dry place and under cover to the requirements of Section C02-010:Clause:1.4.6 until they are despatched to the designated laboratories or as directed by the SO. Remove all samples from the site so as to reach the laboratory within the same day of being taken unless otherwise agreed. The thin-walled, stationary piston and Mazier type undisturbed samples shall be stored, protected and transported with utmost care to avoid disturbance to the samples. They shall be placed and transported in approved sample containers. The sample container shall be constructed such that the sample container is padded throughout with rubber foam and contain partitions to stop the sampler tubes from moving in any direction during transporting to the laboratory. The rubber foam lining shall have a minimum uncompressed thickness of 100 mm. The sample container shall be capable of accommodating a minimum of 3 undisturbed samples and shall be of strong construction with carrying handles. Prior to the commencement of site work, submit a sample of the shipping container for approval by the SO. During transportation, all undisturbed samples shall be protected in the same manner as during storage on site. All samples are required to be kept for a period of not less than 3 months after submission of the approved final report and shall be discarded only with approval by the SO. Give the SO at least 1 week’s notice before the disposal of samples. 4.3.5 Disturbed Samples Retain disturbed samples at all changes of strata from the cutting shoe of an open tube. Store these samples in small airtight PVC containers, correctly labelled, and deliver to the SOs office or other premises as directed by the SO, upon completion of the Work. TS 160/1065 978 Doc D.2/230 4.3.6 Undisturbed Samples Take undisturbed samples by thin walled piston or other approved sampler in cohesive materials at the change of strata and at appropriate intervals as directed by the SO within each type of soil. Unless otherwise directed by the SO, use a Mazier sampler to obtain stiffer soils where the thin walled sampler is not able to take undisturbed samples. 4.3.6.1 Recovery and Preservation of Undisturbed Samples Submit for the SOs acceptance on the recovery, sealing (including wax protection), preservation, and storage of undisturbed samples immediately following their sampling, to avoid disturbance to the samples. Carry out the following procedure: (a) After the undisturbed sampling, a rubber cap shall be placed on the lower end of the sampling tube containing the cutting edge. This is to prevent damaging the cutting edge itself. (b) From the other end of the sampling tube, about 40 mm of material shall be carefully removed. The material shall be retained in a screw top clear plastic container and sealed. (c) The inside of the tube from its open end to the surface of the undisturbed sample shall be cleared of all soil debris using special cleaning tools and lightly greased. (d) A circular piece of paper having the same diameter as the inside of the sampling tube shall be placed on top of the sample. This paper is to minimise wax impregnation. (e) The inside of the tube to be covered with wax shall be thoroughly degreased and melted non-shrinking microcrystalline wax shall be poured onto the paper disc to a thickness of about 10 mm. (f) Once the wax is nearly solid, a neoprene disc having the same diameter as the inside of the tube shall be gently pressed into the wax to ensure the wax makes a good seal with the wall of the sampler. (g) Another 10 mm thickness of wax shall be poured onto the neoprene disc, and once hardened a final 30 mm thickness of wax shall be poured onto the sample. (h) Once the wax has hardened, moist sand, saw dust or soil shall be placed on the waxed sample to fill completely the sampling tube. (i) A rubber cap shall then be placed on the end of the sample tube and its edge sealed against the outside of the sample tube with adhesive vinyl tape and wax. (j) The tube shall be inverted carefully and steps (b) to (i) repeated for the cutting shoe end of the tube. (k) The sample tube shall be labelled in accordance with Section C02-010:Clause:4.3.10. TS 161/1065 978 Doc D.2/231 (l) 4.3.6.2 Until the samples are removed from the site, they shall be placed in protective boxes in a dry place and under cover to the requirements of Section C02-010:Clause:1.4.6. Unsuccessful Sampling Where an attempt to take an undisturbed sample fails, the boring shall be cleaned out for the full depth to which the sampling tube has been driven and the recovered soil saved as a disturbed sample. A fresh attempt shall then be made from the level of the base of the failed attempt. If the second attempt is still unsuccessful, adopt alternative means of sampling as agreed with the SO. [Note 1: Consider an alternative method if the sample is less than 70% recovery.] 4.3.7 Standard Penetration Test (SPT) Samples When a standard penetration test (SPT) is carried out, retain the sample from the split barrel sampler as a small disturbed sample. Where no sample is retained, take a bulk disturbed sample or obtain a sample with a Shelby type Undisturbed (UD) sampler from the test area of similar ground conditions. 4.3.8 Groundwater Samples Where directed by the SO, take a water sample of not less than 0.25 litres from each water standpipe. Store each sample in a clean, dry container. 4.3.9 Description of Samples Examine and describe all samples in accordance with SS EN 1997-2. For weathering classifications and descriptions of soils and rocks, refer to SS EN1997-2, BS EN ISO 14688-1, BS EN ISO 14688-2 (for soils) and BS EN ISO 14689-1 (for rocks). 4.3.10 Labelling of Samples All samples, including water shall be labelled immediately after being taken from the borehole or investigation point. The label shall be clearly and indelibly marked and shall show all the necessary information about the sample, including: (a) Title and reference number (b) Date of sampling (c) Investigation pit/hole reference number (d) Sample reference number (e) Depth of sample (including top and bottom of sample) TS 162/1065 978 Doc D.2/232 The following legend shall be used for the investigation hole/pit and sample reference number: Rotary wash or percussion boring BH Auger borings HA Trial pits TP Trial trench TT Mazier core sample MZ Rotary core sample RS Stationary piston undisturbed sample UP Thin-walled tube undisturbed sample UT Open-tube undisturbed sample UD Small disturbed sample DS Bulk disturbed sample DB Ground water sample WG Surface water sample WS The label shall be securely fixed onto the outside of the sample tube, jar or bag. The outside of the sample tube, jar or bag shall also be clearly and indelibly marked with the same information as the label. 4.3.11 Recording Depths Record the depths below ground at which all samples are taken. For open tube and piston samples, record the depth to the top and bottom of the sample and the length obtained. For bulk samples, record the depth of the sample zone. 4.3.12 Rock Cores 4.3.12.1 Equipment for Core Recovery Unless otherwise specified or directed by the SO, use a triple tube coring system, effected by the use of a double tube barrel with a semi-rigid liner to be agreed by the SO. Use triple tube core barrel of NX size or larger, or as directed by the SO to obtain cores of not less than 50 mm diameter in rock. [Note 1: Although NX is accepted by ISRM, ISRM does suggest a size of at least 54 mm. For rock cores, size of at least HQ (63.5 mm) is used for purposes including better core quality and sample quality recovery, more reliable test results, and better recovered joint infilling.] TS 163/1065 978 Doc D.2/233 4.3.12.2 Recovery of Cores Produce cores not less than the specified diameter throughout the length of the core. No drilling run shall exceed 1.5 m in length. Withdraw the core barrel from the hole and remove the core as often as necessary to secure the highest possible core recovery and quality. Probe rock for a minimum depth of 5 m by rotary core drilling or continue drilling until not less than 90% total core recovery is achieved in any 1.5 m run. Core recovery of less than 90% is not acceptable. If the measured core recovery is less than 90%, the subsequent core run shall be reduced (subject to a minimum core run length of 0.5 m) and if such measures are not successful, alternative coring measures shall be proposed for approval by the SO. The Total Core Recovery (TCR), Solid Core Recovery (SCR), Rock Quality Designation (RQD) and the Fracture Index (FI) as defined in BS ENISO22475-1 and BS 5930, shall be reported for each core run.Refer to the definitions listed below: Term Definition Fracture Index (FI) The number of naturally occurring fractures per metre run of core. Solid Core The intact core having a full diameter without fractures. Solid Core Recovery (SCR) Theratio of the total length of the solid core over the drilling run. Rock Quality Designation (RQD) The percentage of the total length of solid cores each exceeding 100 mm in length over the drilling run. Any length of core containing breaks caused during drilling or handling shall be considered as solid when computing the SCR, RQD and FI. 4.3.12.3 Removal of Cores Submit for the SOs acceptance a method statement detailing how the core shall be extracted from the core barrel prior to the commencement of drilling works. Care shall be exercised to ensure that fractures caused during drilling or extraction of the core from the core barrel or liner are minimised and those which cannot be avoided are identified and not included in the assessment of SCR, RQD and Fl. Carry out all operations so as to minimise disturbance to the cores. Support the core rigidly while the liner is removed and subsequently as the core is extruded. 4.3.12.4 Marking of Cores Immediately after removal of the liner, mark both ends in indelible ink or other agreed manner. Cap and seal the liner, where cores are not to be examined on site. Where cores are taken out, they shall be indelibly marked and logged on site. TS 164/1065 978 Doc D.2/234 4.3.12.5 Inspection of Cores Boxes containing the cores shall be neatly stored at the borehole locations in such a manner that inspection of the cores can easily be made. Store the boxes under cover and protected from the weather. Transport all core boxes to avoid damage and disturbance to the contents. Unexamined core samples contained within plastic lining tubes and waxed samples retained for testing shall be stiffened with laths of wood and wrapped carefully with foam sheeting to minimise disturbance during transportation. 4.3.12.6 Storage of cores Immediately after removal from the core barrel, wrap selected lengths of core in 3 layers of linen cloth, coat each layer with wax and place the cores in core boxes in a consistent sequence. Alternative wrapping for the cores is subject to the SOs acceptance. Store the core boxes on or near the site under cover and secured from public interference. Core boxes shall be constructed of sound materials such as timber, galvanised steel or reinforced plastic with a lid having secure fastenings. Handles shall be attached to the core box for lifting. Core boxes shall not contain more than 50 kg of core. The height of the core boxes shall be compatible with the diameter of the core to be stored in them. As the core is extruded, it shall be arranged in the box in proper sequence starting with the shallowest core on the left side nearest the hinge and then working along the slat and subsequently outwards towards the clasp. Slat shall be positioned and secured such that the core is restrained from movement. Wooden partition blocks not less than 25 mm in thickness shall be placed at the beginning and end of each box and at the end of each core run. These blocks shall be marked with the depth below ground level in waterproof marking ink numbers at least 20 mm high and facing the box lid. The box label or marking shall include information on locality, borehole number, core box number, depth and date. Core losses shall be shown by wooden blocks or polystyrene of a square cross section to fill the core space and of a length equal to the core lost. Send all cores to the laboratory as soon as possible after retrieving from the ground. 4.3.12.7 Testing of cores - Unconfined Compression Strength Carry out point load test or uniaxial compression strength test on selected core samples as agreed by the SO at an accredited testing laboratory. 4.4 In-situ Testing 4.4.1 General Requirements Carry out the in-situ tests in accordance with SS EN 1997-1, SS EN 1997-2 and ISRM guidelines for tests in rocks, or as directed by the SO. For the in-situ or field tests, equipment and procedures shall correspond to the requirements in appropriate parts of EN ISO 22476 or as directed or approved by the SO. TS 165/1065 978 Doc D.2/235 4.4.2 Equipment Calibration Calibrate all equipment as required in accordance with the manufacturer’s requirements. Evidence of calibration shall be provided to the SO. Where evidence is insufficient or if there are reasons to doubt or suspect that the equipment may need to be recalibrated, carry out the recalibration of the equipment as directed by the SO. 4.4.2.1 Boreholes The in-situ tests to be undertaken within boreholes, at the intervals at which they are required (where given) are specified in Section C02-010:Clause:1.4.1 Provisional Bill of Quantities. The Contractor shall undertake these tests in accordance with the Provisional Bill of Quantities unless otherwise directed by the SO. 4.4.2.2 Observation Pits and Trenches Carry out tests at the observation pits and trenches as indicated in the drawings, and any in- situ tests such as vane shear, in-situ density, cone penetration tests, soil infiltration test, trial grouting test, mackintosh probing etc., where provided in the Provisional Bill of Quantities or otherwise required by the SO. 4.4.3 Standard Penetration Tests Standard Penetration Tests (SPT) shall be undertaken in accordance with BS EN ISO 22476-3. 4.4.4 Vane Shear Tests Carry out in-situ vane shear tests in accordance with BS EN ISO 22476-9. The vane blade size is required to be 130 mm x 65 mm or larger and advanced through cohesive soil without the assistance of boring. 4.4.5 Pressuremeter Tests Carry out in-situ pressuremeter tests of the type to be approved by the SO at specified depths or as determined by the SO. All pressuremeter tests shall be in accordance with BS EN ISO 22476-4 or other internationally accepted standards to be agreed with the SO. 4.4.6 Cone Penetration Tests Carry out in-situ Cone Penetration tests (CPT) and Cone Penetration tests with porewater pressure measurement (CPTu or piezocone), or any other type of CPTs (e.g. seismic cone or pressuremeter cone) as required by the SO, in the specified locations. CPTs (including CPTu) shall be undertaken in accordance with BS EN ISO 22476-1, unless an alternative standard is agreed with the SO. Present the following parameters together with the results: TS 166/1065 978 Doc D.2/236 (a) Net cone resistance (b) Sleeve friction (c) Pore pressure (d) Friction ratio (e) Pore pressure ratio. Carry out dissipation test in silty/clayey strata where required, at locations and depths to be decided by the SO. Penetration of the piezocone shall be stopped and excess pore water pressure shall be allowed to dissipate. During these periods, remove loading on the sounding tubes. Record dissipation of excess pore pressure on a time scale. 4.4.7 Falling/Rising Head Permeability Tests Carry out permeability tests at depths in accordance with BS EN ISO 22282-2, and as specified, or otherwise directed by the SO. Indicate clearly in the interpretation of the results whether a constant-head or variable-head method has been adopted for the test. For falling head test, the water level in the borehole shall be raised by adding water to a level agreed as in the drawings and be allowed to stand for a minimum of 30 minutes to saturate the surrounding soil prior to commencement of the test. For rising head tests, the water level in the borehole shall first be lowered by bailing to a level agreed by the SO. Measure the water level at time period of 10-second intervals or at time period intervals as agreed by the SO, to obtain a representative record of the fall or rise in the water level relative to time. The level of the natural groundwater table shall be established at the time of testing. In cases where the stratum being tested may be partially saturated, the initial part of the test may be repeated a number of times until a repeatable result is obtained. [Note 1: The 10-second interval data serves as a guideline.] 4.4.8 Packer Tests Carry out Packer or water absorption tests in rock to measure water acceptance by in-situ rock mass under a given pressure in accordance with BS EN ISO 22282-3. Express the results in terms of Lugeon units. A staged test consisting different water pressures is preferable. Clearly state in each test location whether the test has been carried out using single or double packers. 4.4.9 Plate Load Tests TS 167/1065 978 Doc D.2/237 4.4.9.1 General Carry out the test in accordance with SS EN 1997-2 and BS 1377-9 at depth below the existing ground level as specific with a minimum plate size of 300 mm in diameter as required by the SO Load the plate to cause bearing failure by a constant load. The failure load is defined as the load at which the plate continues to settle at a steady rate or the plate has at least gone through 15% of the plate width, whichever is the lesser. Prior to the carrying out of the plate load test, propose for the SOs acceptance the test range and purpose, giving details on expected or estimated bearing strength and deformation characteristics of the materials to be tested and the maximum plate load test loading. Apply the test load by means of a newly calibrated hydraulic jack using kentledge or other method as accepted by SO. Provide a certificate of calibration from an accepted testing authority before test commencement. 4.4.9.2 Test Procedure Load testing shall be of the Maintained Load Method. Loading shall be in increments of producing not more than one-fifth of the design bearing pressure or smaller steps as agreed. Unloading shall be in at least three equal steps. Each loading shall be maintained for a minimum period of 5 minutes and until settlement is stabilised. At the maximum load pressure, the load shall be maintained for a minimum of 6 hours or as agreed by the SO, and until settlement is stabilised. The settlement is deemed to stabilise if the rate does not exceed 0.1 mm per hour or in proportion for a shorter maintaining time. Throughout the test, make observations of vertical movement of the plate with 2 dial gauges graduated in 0.025 mm divisions. Place a linear metric scale graduated with the appropriate number of subdivisions vertically on either side of the plate to allow independent measurement of its vertical movement with a precise level. Refer to the dial gauge readings on stiff steel beams, the ends of which shall rest on, or are fixed to reliable supports. The beam supports shall extend not less than 1 m below ground surface and not be located closer than two metres from the centre of test plate. Check the elevation of the supports frequently with reference to a fixed benchmark. Protect the entire measuring assembly against rain, direct sunlight and other disturbance that might affect its reliability. Provide all necessary facilities to enable the supervision staff to check readings during the progress of the test. Keep the test under continuous and competent supervision. Give at least 24 hours’ notice of the commencement of each test. 4.5 Laboratory Tests Conduct laboratory tests in accordance with SS EN 1997-2, and BS 1377 where the standards are appropriate and consistent with the SS EN 1997 for soil samples and rock samples. Where SS EN 1997-2 does not cover the relevant tests, ISRM or other suitable internationally standards as specified, subject to the SOs approval, shall be used for rock testing. TS 168/1065 978 Doc D.2/238 4.5.1 Classification Tests Carry out tests for the classification of soil for the determination of basic physical properties as specified: 4.5.2 (a) Moisture content (SS EN 1997-2 and BS EN ISO 17892-1) (b) Atterberg limits, including liquid limit, plastic limit and plasticity index (SS EN 1997-2 and BS EN ISO 17892-12) (c) Bulk density and dry density (SS EN 1997-2 and BS EN ISO 17892-2) (d) Particle density or specific gravity (SS EN 1997-2 and BS EN ISO 17892-3) (e) Particle size distribution with wet sieving and hydrometer methods (SS EN 1997-2 and BS EN ISO 178924) (f) Identification and classification of soil (BS EN ISO 14688-1). Chemical Tests Carry out tests for determining the organic matter, chemical substances and corrosivity properties of soil and water samples as specified in accordance to SS EN 1997-2 and BS 13773: 4.5.3 (a) Organic matter content (SS EN 1997-2) (b) Total sulphate content of soil and sulphate content in 2:1 water-soil extract (SS EN 1997-2) (c) pH value of soil (SS EN 1997-2) (d) Sulphate content (SS EN 1997-2) and pH value of ground water (BS1377-3) (e) Chloride content of soil (SS EN 1997-2). Compressibility Tests Carry out one-dimensional consolidation and swelling tests in an oedometer for determining the consolidation and swelling characteristics of soil when subject to changes in applied vertical effective stress in accordance with SS EN 1997-2 and BS EN ISO 17892-5. The loading stages shall typically include a full unload - reload cycle and the number of stages as well as the loadings required for each stage shall be agreed on with the SO. 4.5.4 Shear Strength Tests Carry out compression tests for the determination of the shear strength parameters of soils in terms of total and effective stresses in compliance with the following as appropriate: TS 169/1065 978 Doc D.2/239 (a) Consolidated Direct shear test (SS EN 1997-2 and BS EN ISO 17892-10) (b) Unconfined compression test (SS EN 1997-2 and BS EN ISO 17892-7) (c) Unconsolidated-undrained triaxial compression test by single stage or multistage loading without measurement of pore pressure (SS EN 1997-2 and BS EN ISO 17892- 8) (d) Consolidated-undrained triaxial compression test with measurement of pore pressure (SS EN 1997-2 and BS EN ISO 17892-9) (e) Consolidated-drained triaxial compression test with measurement of pore pressure (SS EN 1997-2 and BS EN ISO 17892-9). Agree with the SO, the required cell pressures for triaxial tests and the stress levels required for the direct shear tests, prior to carrying out the tests. 4.5.5 Strength Tests on Rock Samples Carry out the following tests for the determination of the shear strength parameters of rocks in compliance with SS EN 1997-2 and ISRM suggested methods for rock testing as appropriate: (a) Uniaxial compression strength test (b) Point load test (c) Brazilian tensile strength test (d) Direct shear strength of rock (intact or along rock joint). 4.6 Instrumentation and Monitoring Requirements 4.6.1 Groundwater in Boreholes Make careful observations of groundwater conditions and levels daily during each boring operation. Record the level of the water table in each borehole twice daily: once in the morning before resumption of boring and once at the end of the day. If artesian conditions are encountered, agree with the SO on the measures to be adopted. Record the readings by an electrically operated water level indicator capable of measuring the depth to water levels of up to 30 m. 4.6.2 Standpipes and Piezometers Typical installation details for standpipes and piezometers are shown in Figures 1 and 2. Figure 1. Details of Piezometer Installation TS 170/1065 978 Doc D.2/240 Figure 2. Typical details of water standpipe installation TS 171/1065 978 Doc D.2/241 4.6.2.1 Sand filter Record the volume of the sand filter placed. The response zone formed by the sand filter shall 4.6.3 M ps-inanwdatpeierze oe l ovmeel itn Ino en pd l 5csaetico,n3s0, asec, 1 stnaitllosrttahneddprip ertshe insta ap raipteboor rpeiheozloem s eatnedr at idneteprtvhassl anodf 1o m ine ,ci2fiemdina,n4d m 30in m sp inidni,c8atm edini,n1t5hemdinra, w gsino, r1dhirre, c2tehdr,b3y hthr,e4ShOr,. 5 hr, 6 hr, 7 hr, 8 hr, 16 hr, 24 hr, or when the water level has returned to its initial steady level. Protect the tops of standpipes and piezometers by surface boxes as indicated. wda. The water standpipe or piezometer shall be in working condition throughout the monitoring A r io p ello meincitm l agoefdownaetehrosutrabnedtpwipee norpplae R i fyuamnytim daem i ciznogmoeftceer m befnotrebehnatnodninteg gorvoeurt./ bentontie pellet and filter material above to prevent probable mixing up of the intended permeable and T s aema pb le sl aoyf egr rso. u n d w a t e r of not less than one litre from the standpipes and piezometer when i mapk e r m required. Unless otherwise agreed, monitor all standpipes and piezometers daily during the fieldwork. S o rreth thecwoa lynlcaebeal w an ae bowrate ory fleovr i nfcieleldaw nosrekapledriocdo,nrte atiu nrenrst,ocsleita ero Atfte mteprlestiaom n pole f tshe edekd teolivmeer atosuthretlh eclhienmeiaccahl taensdts.every standpipe and piezometer for a period of one month unless otherwise specified or agreed with the SO. Give one day's notice to all occupiers on the site on which the The tests for sulphate content (% S03), chloride content, acidity (pH value) and degree of piezometers and standpipes are situated. salinity shall be determined from the same sample. 5 VERIFICATION AND SUBMISSION 5.1 Submissions TS 172/1065 978 Doc D.2/242 5.1.1 General Unless agreed by the SO, all investigation reports shall follow the requirements of SS EN 1997- 1 and SS EN 1997-2. Reference shall be made to SS EN 1997- 2 for information on the use of laboratory and field tests for geotechnical parameters. 5.1.2 Testing laboratory Submit the proposed testing laboratories for acceptance during tender. 5.1.3 Field Reports Submit electronically, a copy of the Daily Site Record on the following working day. For all drilling, borings, sampling and field tests, the site records, logs and test data or reports shall follow the requirements of BS EN ISO 22475 (on drilling, sampling and groundwater measurements), BS EN ISO 22476 (on field testing), and BS EN ISO 22282 (on geotechnical investigation and testing) as appropriate, to include the following: (a) Location (chainage where known) (b) Borehole number (c) Date and times of boring (d) Type of plant used (e) Diameter of boring casing and core as appropriate (f) Depth of base of each stratum from surface (g) Description of strata (h) Level of the bottom of the casing when each sample is taken or in-situ test carried out or each core run drilled (i) Depths at which all samples were taken and in-situ tests carried out (j) Detailed test records (k) Level at which water was standing at the commencement and end of each day's work (l) All water levels encountered and amount of water added (if any) when boring cohesive soils (m) Length of drill runs and the actual lengths of core recovered in each drill run (n) Percentage and colour of drilling fluid returns TS 173/1065 978 Doc D.2/243 5.1.4 (o) Rotary drilling penetration rate and variations (p) Remarks on any matters not referred to the above which may be of value in interpreting and understanding the ground conditions. Borehole Logs Submit 1 copy of the Preliminary Borehole Logs, as preliminary version of borehole logs, for the preliminary description of the soils and rocks at each borehole. Provide a further copy with complete list of samples retrieved for laboratory testing within 2 days of the completion of site work at each borehole. 5.1.5 Field test set-up and data Submit calculations and sketches of the test set up and method statement for the field tests such as plate load tests to the SO for approval before commencement of the test. Engage a suitably experienced, competent and qualified PE to review and endorse all submissions. Submit all records and plot of load versus deformation characteristics within 24 hours after completion of the test. Propose format of records and reports for the SOs acceptance. 5.1.6 Laboratory Testing Schedules Prepare a blank test schedule by considering the provisional quantities in Section C02- 010:Clause:1.4.1, including the following information: (a) Borehole number (b) Sample number (c) Sample type (d) Sample depth and on the other axis the following standard laboratory tests shall be listed: (i) Moisture content (ii) Atterberg Limits (iii) Bulk density and dry density (iv) Specific gravity of soil particles (v) Particular size distribution by Wet sieving method (vi) Particular size distribution by hydrometer method (vii) Organic matter content TS 174/1065 978 Doc D.2/244 (viii) Sulphate of soil and in sample of water-soil extract (ix) pH of soil (x) Sulphate and pH of water sample (xi) Chloride of soil (xii) Oedometer (leave space for pressure range to be specified) (xiii) Direct shear test (xiv) Unconfined compression test (xv) Quick triaxial test on 38mm diameter specimen (leave space for pressure range to be specified) (xvi) Consolidated-undrained and consolidated-drained triaxial compression tests on 38mm diameter specimen (leave space for pressure range to be specified) (xvii) Uniaxial compression strength test (xviii) Point load test (xix) Three blank columns for other tests Submit these draft schedule sheets to the SO with the preliminary logs. 5.1.7 Ground Investigation Report 5.1.7.1 General Unless agreed by the SO, Ground Investigation Report as provided in SS EN 1997 shall consist of the following: (a) A presentation of all available geotechnical information, including geological features and relevant data. (b) A geotechnical evaluation of the information, stating the assumptions made in the interpretation of the test results. The information is required to be presented as 1 report or as separate parts. Submit digitally or as directed by the SO, of the ground investigation report with verification and endorsement of accuracy and correctness of the report by an appropriately qualified PE after completion. TS 175/1065 978 Doc D.2/245 5.1.7.2 Final Report Content Submit for the SOs approval the Final Report in a format to be agreed by the SO, which shall contain the following information, where applicable: (a) Factual account and description of the Works, stating the scope and purpose of the Works, including a description of the site and its topography, site plans and detail, of the planned structure and the stage of the planning the account is referring to; the names of all parties, specialists and laboratories; dates of field and laboratory investigations and tests performed; field reconnaissance of the site and the surrounding area; geology of the site; description of site operations, weather, handling of samples; and tests, including standards used. (b) Documentation and description of the methods, procedures and results, including all relevant findings and reports of: (c) (i) desk studies (ii) field investigations, such as field logs, sampling, field tests and groundwater measurements (iii) laboratory tests and results. Documentation of the evaluation and interpretation of information, including as appropriate: (i) the tabulation and graphical presentation of the results of field investigation and laboratory testing in cross-sections of the ground showing the relevant strata and their boundaries including the groundwater table in relation to the requirements of the project (ii) the values of the geotechnical parameters for each stratum (iii) a review of the derived values of geotechnical parameters. The results of the field and laboratory investigations shall be presented and reported according to the requirements defined in the EN and/or ISO standards applied in the investigations. 5.1.7.3 Approval of Final Report Preliminary version of the Final Report shall be submitted to the SO for approval before submission of the Final Report. Allow the Final Report to be included in the Programme for the SOs approval, and for revision or amendments as required by the SO. 5.2 Equipment Calibration TS 176/1065 978 Doc D.2/246 5.2.1 Field Vane Shear Tests Provide full details of the equipment used as well as calibration record and specimen calculation sheets. Submit preliminary results for both virgin and remoulded shear strength to the SO within 24 hours after completion of the test. 5.2.2 Pressuremeter Tests Provide full details of the equipment used, its range of operation, including maximum depth below ground level and calibrations record together with specimen calculation sheets. Submit preliminary results for both initial loading and reloading cycles to the SO within 24 hours after completion of the test. 5.3 Media Labelling, Data Checking and Virus Protection 5.3.1 General Clearly label all files, media and conventions. For AGS (SG) format data, all media are required to be properly labelled and clearly marked with the following: 5.3.2 (a) Title âAGS(SG) Format Dataâ (b) Project identification (PROJ_ID) (c) Project Location (PROJ_LOC) (d) Number of boreholes / CPT tests / trial pits (e) Date of Project (PROJ_DATE) (f) Name of the Contractor or Firm (g) Name of the Client (h) Version: AGS (SG) (i) Reference number of digital storage and retrieval devices or suitable devices Data Checking Check and be responsible to provide true, correct and accurate data. Data format and integrity, data completeness and data validation checks shall be carried out on each data set issued or received prior to submission. For geo-information, validate the data. Any shortfalls shall be corrected accordingly before submission to the SO. TS 177/1065 978 Doc D.2/247 5.3.3 Virus Protection All electronic data files shall be virus-free. Precluding executable files from the data set reduces the risk of virus transfer. Scan each data set medium with virus-checking programme prior to submission to the SO. 5.3.4 Data Submission Provide and submit a soft copy of the media containing electronic data which shall be the current electronic copies of all data, preliminary or final. The electronic copies of data, being submitted in suitable digital storage and retrieval devices, shall be labelled âPRELIMINARYâ or âFINALâ as appropriate. APPENDIX 1 Provisional Bill of Quantities for Works to be carried out for ground investigation Provisional Schedule of Works Item Description Qty Unit . 1 FIELD WORK . . . 1.1 Mobilisation and Demobilisation Provide drilling rigs, all necessary equipment and crew on the Site and remove upon completion, including moving rigs and equipment between borehole position. The required number of plants/rigs shall be substantiated with the actual productivity of the plants/rigs in relation to the deadline. . Item . 1.2 Authority Approval . Obtain approval from authorities, including LTA, HDB, JTC, NParks, NEA, BCA, SLA, SCDF, etc. and all other necessary clearances. Item . 1.3 Specialist/Professional Attendance on Site Provide suitably experienced, competent and qualified specialist personnel, including engineering geologists full-time on site during site operations to ensure quality work, compliance with specification and taking site instructions, ensuring consistent and correct logging according to specified standards. . Item . 1.4 Erosion Control Measures Provide adequate erosion control and water quality throughout duration of the Investigation Works. . Item . 2 EXPLORATORY HOLES . . . 2.1 Movement on Land Move the boring plant to the designated borehole position (including site clearance, erection of temporary platform if necessary, etc.), setting out of borehole position by registered surveyors and including dismantling it after completion. . No. . TS 178/1065 978 Doc D.2/248 2.2 Movement over Water / Tidal Range / Swamp . Move the boring plant to the designated borehole position (including site clearance, erection of temporary platform if necessary, etc.), setting out of borehole position by registered surveyors and including dismantling it after completion. No. . 2.3 Boring in Soil on Land / Over Water / Tidal Range / Swamp Wash boring with casing Carry out wash boring cased at depth from existing ground level to not exceeding 20 m. . a Ditto - 20 m to 40 m . m . b Ditto - exceeding 40 m . m . 2.4 . Boring in Soil on Land / Over Water / Tidal Range / Swamp Boring with bentonite Carry out boring with bentonite as stabilising fluid cased at depth from existing ground level to not exceeding 20 m. m . a Ditto - 20 m to 40 m . m . b Ditto - 40 m to 60 m . m . c Ditto - exceeding 60 m . m . 2.5 Boring in Soil on Land / Over Water / Tidal Range / Swamp Boring with polymer Carry out boring with polymer as stabilising fluid cased at depth from existing ground level to not exceeding 20 m . m . a Ditto - 20 m to 40 m . m . b Ditto - 40 m to 60 m . m . c Ditto - exceeding 60 m . m . 2.6 Boring in Soil on Land / Over Water / Tidal Range / Swamp Boring with foam Carry out boring with foam as stabilising fluid cased at depth from existing ground level to not exceeding 20 m. . m . a Ditto - 20 m to 40 m . m . b Ditto - 40 m to 60 m . m . c Ditto - exceeding 60 m . m . 2.7 Boring on Land / Over Water / Tidal Range / Swamp Diamond Drilling Diamond drilling in NX Size or larger boreholes in solid rock and other hard materials with SPT "N"values not less than 100 blows / 300 mm using triple tube core barrel to obtain cores of not less than 50 mm diameter, storing cores in core boxes, including delivery of cores in core boxes to the SO and taking of photographs at depth from existing ground level to depth not exceeding 20 m. . m . a Ditto20 m to40 m . m . b Ditto - 40 m to 60 m . m . . m TS 179/1065 978 Doc D.2/249 c Ditto - exceeding 60 m . m . 2.8 Standard Penetration Test Carry out Standard Penetration Tests (SPT), including collection of disturbed samples at depths. . No. . 2.9 Disturbed Samples . Take disturbed samples storing in airtight polythene jars correctly labelled and delivering to the SO, from existing ground level to not exceeding 20 m. No. . a Ditto 20 m to 40 m . No. . b Ditto - 40 m to 60 m . No. . c Ditto - exceeding 60 m . No. . . Undisturbed Sampling with Piston Sampler Take samples of not less than 75 mm in diameter and 1000 mm in length, using thinwalled piston sampler completely sealed either with caps and waterproof adhesive tape or with paraffin wax for depth from existing ground level to not exceeding 20 m, and deliver to an approved laboratory for testing. No. . 2.10 a Ditto - 20 m to 40 m . No. . b Ditto - 40 m to 60 m . No. . c Ditto - exceeding 60 m . No. . 2.11 . Undisturbed Sampling with Thin Wall Tube Take samples of not less than 75 mm diameter and 1000 mm length using thinwalled open tube sampler or other sampler, approved by the SO, completely sealed either with caps and waterproof adhesive tape or paraffin wax for depth from existing ground level to not exceeding 20 m, and deliver to an approved laboratory for testing. No. . a Ditto - 20 m to 40 m . No. . b Ditto - 40 m to 60 m . No. . c Ditto - exceeding 60 m . No. . Undisturbed Sampling with Mazier Sampler Take samples of not less than 75 mm diameter and 400 mm length using triple tube core barrel with retractable shoe( Mazier sampler), completely sealed either with caps and waterproof adhesive tape or paraffin wax for depth from existing ground level to not exceeding 20 m, and deliver to an approved laboratory for testing. . No. . a Ditto - 20 m to 40 m . No. . b Ditto - 40 m to 60 m . No. . c Ditto - exceeding 60 m . No. . 2.13 Undisturbed Sample Storage Box Provide sufficient UD storage box for recovered UD samples to the specification. . No. . 2.12 TS 180/1065 978 Doc D.2/250 2.14 . Piezocone on Land Move equipment from one position to the next, setting out of position by qualified surveyors and including dismantling it after completion. No. . 2.15 Piezocone over Water / Tidal Range / Swamp . Move equipment from one piezocone position to the next, setting out of piezocone position by qualified surveyors and including dismantling it after completion. The platform must be stable and shall not sway or move under disturbance from water, test equipment and personnel working on it. The platform shall be approved by the SO. (Floating pontoon shall not be used). No. . 2.16 Deep Sounding Test Carry out deep sounding tests at depth from existing level to not exceeding 15 m . m . a Ditto 15 m to30 m . . . b Ditto 30 m to50 m . . . c Ditto exceeding 50 m . . . 2.17 Dissipation Tests Carry out Dissipation Tests . Vane Shear Test on Land Move equipment from one position to the next, setting out position by qualified surveyors and including dismantling after completion. . 2.19 Vane Shear Test over Water / Tidal Range / Swamp Move equipment from one position to the next, setting out position by qualified surveyors and including dismantling after completion. . No. . 2.20 Carry out in-situ Vane Shear Test at depth from existing ground to not exceeding 20 m. . No. . a Ditto - 20 m to 40 m . No. . b Ditto - 40 m to 60 m . No. . c Ditto - exceeding 60 m . No. . 2.21 Borehole Vane Shear Test on Land Move equipment from one position to the next, setting out position by qualified surveyors and including dismantling after completion. . No. . 2.22 Borehole Vane Shear Test over Water / Tidal Range / Swamp Move equipment from one position to the next, setting out position by qualified surveyors and including dismantling after completion. . No. . 2.23 Borehole Vane Shear Test over Water / Tidal Range / Swamp Carry out in-situ Borehole Vane Shear Test at depth from existing ground to not exceeding 20 m. . No. . a Ditto - 20 m to 40 m . No. . 2.18 . . No. TS 181/1065 978 Doc D.2/251 b Ditto - 40 m to 60 m . 2.24 Mackintosh Probe on Land a.Setting out of location by a qualified surveyor, setting up, dismantling and moving the equipment to the next location. b.Carry out Mackintosh Probes tests as per specification. . 2.25 No. . . No. Mackintosh Probe over Water / Tidal Range . / Swamp a.Setting out of location by a qualified surveyor setting up, dismantling and moving the equipment to the next location. b.Carry out Mackintosh Probes tests as per specification. . No. Hand Auger Carry out hand augers, including the provision of sealed disturbed samples. . 2.28 Trial Pits Carry out trial pits as per specification, on land, at depth not exceeding 3 m. . . . a Ditto - for depth exceeding 3 m but not exceeding 5 m. . . . 2.29 Disturbed Samples Take bulk disturbed samples of not less than 30kg, store in airtight polythene bags correctly labelled and deliver to SO's office. . No. . 2.30 Disturbed Samples for Water Content Determination Collect a set of 2 sealed samples for determination of in-situ water content at the laboratory (testing measured separately) for every sampling in bulk. . Set . 2.31 Pressuremeter Test In-situ Pressuremeter test down to the depths not exceeding 20 m. . a Ditto - 20 m to 30 m . No. . b Ditto - 30 m to 40 m . No. . c Ditto - exceeding 40 m . No. . 2.32 Ground Water Take recordings of water levels in all boreholes twice daily throughout the period of ground investigation. . Supply and install standpipe with protective surface box to a depth not exceeding 15 m in borehole, commissioning and taking readings twice daily for duration of field work and weekly for one month upon completion of field work. . Supply and install standpipe with protective surface box to a depth (15 m to 25 m) in borehole, commissioning and taking readings twice daily for duration of field work and weekly for one month upon completion of field work. . 2.27 a b . m . No. . Item . No. No. . TS 182/1065 978 Doc D.2/252 c Supply and install standpipe with protective surface box to a depth exceeding 25 m in borehole, commissioning and taking readings twice daily for duration of field work and weekly for one month upon completion of field work. . No. . d Supplying and install piezometer with protective surface box, to a depth of not exceeding 30 m in borehole, commissioning and taking readings twice daily for duration of field work and weekly for one month upon completion of field work. . No. . 2.33 Groundwater Samples from Borehole Take sample of ground water of not less than 1 litre from borehole, storing in clean sealed container and delivering to an approved laboratory for testing. . 2.34 . No. . Groundwater Samples from Standpipe/ . Piezometer Take sample of ground water of not less than 1 litre from standpipe and piezometer, storing in clean sealed container and delivering to an approved laboratory for testing. No. . Item Description Qty Unit . 3 LABORATORY TESTS . . . 3.1 Moisture content determination . Set . 3.2 Atterberg limits determination (set of one liquid limit and one plastic limit) . Set . 3.3 Bulk and dry density determination . Set . 3.4 Specific gravity determination . No. . 3.5 Particle size analysis by sieving only . No. . 3.6 Particle size analysis by sieving plus sedimentation (hydrometer) . No. . 3.7 Determination of pH, sulphate content and salinity of sea/ground water . Set . 3.8 Determination of chloride content of sea/ground water . No. . 3.9 Determination of pH of soil . No. . 3.10 Determination of organic matter content of soil . No. . 3.11 Determination of total sulphate content of soil . No. . 3.12 Determination of sulphate content of aqueous soil extract . No. . 3.13 Determination of chloride content of soil . No. . 3.14 Constant Head Triaxial Permeability Test for determination of co-efficient of permeability . No. . 3.15 Consolidation test (oedometer). . No. . 3.16 Consolidated Direct shear test on a set of 3 compacted specimens (60 mm x60 mm). . No. . TS 183/1065 978 Doc D.2/253 3.17 Consolidated Drained Direct Shear Box Test with multiple reversal and re-shearing on a set of 3 reconstituted specimens (60 mm x 60 mm) . No. . 3.18 Unconsolidated undrained triaxial compression test on one 38mm diameter x 75 mm specimen. . No. . 3.19 Unconsolidated undrained triaxial compression test on one 50 mm diameter x 75 mm specimen. . No. . 3.20 Unconsolidated undrained triaxial compression test on one 70 mm diameter x 75 mm specimen. . No. . a Single-stage test (test at one cell pressure only 0.5Ïâ or 1.0Ïâ or 2Ïâ using single (1) sample). . Set . b Three-stage tests (set of 3 tests of three cell pressure 0.5Ïâ, 1.0Ïâ, 2Ïâ using single (1) sample). . Set . c Three-stage tests (set of 3 tests of three cell pressure 0.5Ïâ, 1.0Ïâ, 2Ïâ using three (3) independent samples. . Set . 3.21 Consolidated undrained triaxial compression test . with pore water pressure measurement on one 38mm diameter x 75 mm specimen, including submission of digital photographs of the undisturbed samples before and after shearing, digital files on stress path data and other relevant tests data. No. . 3.22 Consolidated undrained triaxial compression test . with pore water pressure measurement on one 50 mm diameter x 75 mm specimen, including submission of digital photographs of the undisturbed samples before and after shearing, digital files on stress path data and other relevant tests data. No. . 3.23 Consolidated undrained triaxial compression test . with pore water pressure measurement on one 70 mm diameter x 75 mm specimen, including submission of digital photographs of the undisturbed samples before and after shearing, digital files on stress path data and other relevant tests data. No. . a Single-stage test(test at one cell pressure only 0.5Ïâ or 1.0Ïâ or 2Ïâ using single (1) sample). . Set . b Three-stage tests (set of 3 tests of three cell pressure 0.5Ïâ, 1.0Ïâ, 2Ïâ using single (1) sample). . Set . c Three-stage tests (set of 3 tests of three cell pressure 0.5Ïâ, 1.0Ïâ, 2Ïâ using three (3) independent samples. . Set . TS 184/1065 978 Doc D.2/254 3.24 Consolidated drained triaxial compression test (CID) with pore water pressure measurement on one 38mm diameter x 75 mm specimen, including submission of digital photographs of the undisturbed samples before and after shearing, digital files on stress path data and other relevant tests data. . No. . 3.25 Consolidated drained triaxial compression test (CID) with pore water pressure measurement on one 50 mm diameter x 75 mm specimen, including submission of digital photographs of the undisturbed samples before and after shearing, digital files on stress path data and other relevant tests data. . No. . 3.26 Consolidated drained triaxial compression test (CID) with pore water pressure measurement on one 70 mm diameter x 75 mm specimen, including submission of digital photographs of the undisturbed samples before and after shearing, digital files on stress path data and other relevant tests data. . No. . a Single stage test (test at one-cell pressure only 0.5Ïâ or 1.0Ïâ or 2Ïâ using single (1) sample). . Set . b Three-stage tests (set of 3 tests of three-cell pressure 0.5Ïâ, 1.0Ïâ, 2Ïâ using single (1) sample). . Set . c Three-stage tests (set of 3 tests of three-cell pressure 0.5Ïâ, 1.0Ïâ, 2Ïâ using 3 independent samples. . Set . 3.27 Unconfined compression test on soil (including preparation of specimen from sampling tube or borehole core and presentation of load/deformation plot). . No. . 3.28 Uniaxial compression strength test without measurement of Poisson Ratio and Elastic Modulus on rock (including preparation of specimen from borehole core and presentation of load/deformation plot). . No. . 3.29 Uniaxial compression strength test with measurement of Poisson Ratio and Elastic Modulus on rock (including preparation of specimen from borehole core and presentation of load/deformation plot). . No. . 3.30 Point load test on rock from borehole (rock core). . No. . 3.31 Soil Compaction Test (Proctor Test) Carry out compaction test on remoulded samples: . . . a With a 2.5 kg Hammer . Set . b With a 4.5 kg Hammer . Set . 4 REPORT . . . TS 185/1065 978 Doc D.2/255 4.1 Allow for digital photographs with resolution (1600 . x 1200) pixels per frame showing boring rigs at all borehole locations, extruded undisturbed samples and rock cores with labelling and colour reference strip, stored in suitable digital storage and retrieval devices to be agreed by the SO. Copy . 4.2 Provision of the Final Report (including asbuilt survey endorsed by licensed surveyor) and 2 sets of soft copies(in suitable digital storage and retrieval devices) containing all SI data in AGS format (in accordance to the Specification for AGS format) and soft copy of the as-built survey plan. This is inclusive of daily investigation field records, reports, findings, logs or data, etc. . Copy . [Note 1: Provide a list showing provisional quantum of works to be carried out for the ground investigation, including in-situ tests, laboratory tests, sampling of soils and rocks, water level monitoring, etc. Note 2: In addition, provide a schedule of exploratory holes that tabulates provisional quantum of exploratory holes to be carried out (including boreholes, CPTs, trial pits, etc.) and where applicable, the requirements for sampling, in-situ testing and instrumentation in each hole.] TS 186/1065 978 Doc D.2/256 (5) C02-020 General Earthworks (Excavation and Filling) TS 187/1065 978 Doc D.2/257 1 GENERAL Read this Section with G01-010 "General Requirements" and all other contract documents. 1.1 Scope This Section covers the requirements for the following general earthworks items for building works: (a) Excavation (b) Filling and Embankments (c) Site-won and imported fill materials (d) Rock-fill This Section does not cover ground improvement beneath an earth structure, dredging and land reclamation earthworks. 1.2 Related Sections Read this Section in conjunction with the relevant requirements of the following sections: 1.3 C01-020 Condition Survey C02-010 Ground Investigation C02-030-1 Diaphragm Wall C02-030-2 Sheet Piling C02-030-3 Contiguous Bored Pile Walls and Secant Pile Walls C02-050 Instrumentation and Monitoring Standards, Codes, Regulations and Technical References TS 188/1065 978 Doc D.2/258 1.3.1 Standards and Codes Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant requirements of the Standards and Codes listed below or referenced in the body of the Specification. Alternative Standards and Codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative Standards and Codes comply with the requirements of the standards specified. All Standards and Codes quoted are the current version, unless specific year references are noted. In the event that the standards or codes are partially superseded or have become obsolete, refer to the current edition or the approved substitution for the relevant clauses. Singapore Standards SS EN 1997-1 Eurocode 7: Geotechnical Design - Part 1: General Rules SS EN 1997-2 Eurocode 7: Geotechnical Design - Part 2: Ground Investigation and Testing NA to SS EN 1997-1 Singapore National Annex to Eurocode 7: Geotechnical design - Part 1: General rules NA to SS EN 1997-2 Singapore National Annex to Eurocode 7: Geotechnical design - Part 2: Ground investigation and testing SS EN 1992-1-1 Design of concrete structures, Part 1-1 General rules and rules for buildings SS EN 1993-1-1 Eurocode 3 - Design of steel structures - Part 1-1General rules and rules for buildings SS CP 4 Foundations SS CP 79 Safety management system for construction worksites SS 31 Aggregate from natural sources for concrete SS 593 Code of Practice for Pollution Control Other Standards BS EN 16907-1 Earthworks - Part 1: Principles and general rules BS EN 16907-2 Earthworks - Part 2: Classification of materials BS EN 16907-3 Earthworks - Part 3: Construction procedures BS EN 16907-4 Earthworks - Part 4: Soil treatment with lime and/or hydraulic binders BS EN 16907-5 Earthworks - Part 5: Quality control BS EN 16907-6 Earthworks - Part 6: Land reclamation earthworks using dredged hydraulic fill BS EN ISO 22476 Geotechnical investigation and testing. Field testing. BS EN ISO 22282 Geotechnical investigation and testing. Geohydraulic testing. BS 3882 Specification for topsoil BS 6031 Code of practice for earthworks BS 8002 Code of practice for earth retaining structures BS 8004 Code of practice for foundations BS 5835-1 Recommendations for testing of aggregates. Compactibility test for graded aggregates TS 189/1065 978 Doc D.2/259 1.3.2 Technical References Refer to the following technical references for guidance in carrying out the Works: (a) BRE Digest 251(1995) Assessment of damage in low rise building (b) Jurong Town Council (JTC), Guidelines on Environmental Baseline Study (EBS) (2019 Edition) (c) CIRIA C760 Guidance on embedded retaining wall design (d) Singapore, TR26 Technical Reference for Deep Excavation 1.4 Trade Preamble 1.4.1 Contractor’s Submissions and Proposals 1.4.1.1 Design for Temporary Works Engage a qualified, competent and suitably experienced PE to carry out the following: (a) Design and supervise the temporary works, if necessary, and precautionary measures, including earth retaining and stabilising structures e.g., temporary stabilising slope, retaining structures and supports for stability of the earthworks. (b) Prepare a response plan in the event that the temporary works do not perform as expected in the design. (c) Prepare and submit all designs, including drawings to the SO and the authorities for approval where applicable, before the commencement of temporary works. Submit the curriculum vitae (CV) of the PE to the SO for acceptance. [Note 1: Identify temporary works and submit the design and drawings early before the commencement of the main work.] 1.4.1.2 Impact Assessment Engage a qualified, competent and suitably experienced PE to carry out an Impact Assessment on the effects of ground movement to the neighbouring properties due to the works, for the purpose of establishing permissible limiting suitable values as appropriate, for monitoring for alerts, review and suspension of work in complying with the regulating requirements, including Building Control Act and Regulations, or as directed by the SO. Submit the report with endorsement from the PE to the SO for acceptance. Refer to the current advisory, guides and requirements issued by the Commissioner of Building Control. TS 190/1065 978 Doc D.2/260 1.4.1.3 Equipment and Methods Propose suitable equipment and methods to carry out the Works. Detailed method statements, and construction sequences, and construction schedule shall be included with the submission to the SO for acceptance. The method statements shall include full details of the methods to ensure adherence to the following: 1.4.1.4 (a) Quality control, which shall be in accordance with the quality control plan in C02- 020:Clause:1.4.14 (b) Health, safety and environmental requirements Temporary Diversion of Services Where applicable, propose schemes and details for the temporary diversion of existing above ground or underground services to facilitate the works. 1.4.2 Contractor’s Responsibility The earthworks shall be executed and undertaken strictly in accordance with the relevant local regulations and by-laws that are current at the date of the tender together with all amendments and addenda which are imposed as statutory requirements in the course of the Works. Provide for all things necessary for compliance with the requirements of this Section and to complete the Works. Provide all necessary and safe temporary works required for the purpose of and to complete the earthworks. This shall include conducting ground investigations, preparing adequate designs, making statutory submissions, constructing, testing, monitoring and subsequently removing all necessary temporary works to the satisfaction of the SO and the relevant authorities. Unless endorsed by the PE and agreed with the SO, the Works shall not deviate from the designs, method statements and construction sequences for the temporary works. Strictly adhere to the use of good workmanship, proven construction techniques and timely implementation of agreed construction method and sequence to limit ground loss and movement next to the excavation. 1.4.3 Co-ordination with Other Works Co-ordinate with other contractors who may carry out other works at, or around, the same time at the Site, as well as parties who undertake preliminary works prior to commencement of the Works and those who take ownership of the site following completion of the Works. Take into account site access, space occupation, safety and safeguarding of adjoining properties and each other’s works. TS 191/1065 978 Doc D.2/261 1.4.4 Condition Survey Where applicable, prior to and upon completion of the Site Works, carry out a condition survey to adjacent buildings in accordance with the requirements of Section C01-020. Submit all records to the SO and adjacent property owners where directed. Keep a copy of the survey report on site ready for inspection. For each adjacent building or facility, a set of photographic records together with proper documentation and a schedule listing the size of the superstructure, extent of underground structure, visible defects with measurement and any other relevant details pertaining to the general condition of that building or facility are required. In the case where blasting is used, prior to commencing blasting operations, submit a written report listing any existing defects in the structures in the zone which may be affected, supported by photographs where necessary, to the SO. 1.4.5 Instrumentation and Monitoring Provide instrumentation to monitor the ground movement, vibration and condition of adjacent properties. Refer to Section C02-050:Clause:3.1, and the drawings for the schedule of instrumentation required. If necessary or as required by the authorities, propose and provide additional instrumentation and monitoring for record. The method of construction shall comply with the more severe of either the statutory limits imposed on lateral and vertical ground movements, construction noise, vibration and air pollution levels, or such limits necessary for the adequate protection and proper functioning of neighbouring roadways, buildings and facilities as agreed with the SO. Take cognisance of and co-ordinate with other contractors on site who may be carrying out instrumentation and monitoring works to avoid duplication of installation and readings. For general requirements of the instrumentation and monitoring works refer to Section C02- 050 "Instrumentation and Monitoring". 1.4.6 Upholding of Adjoining Properties Accept responsibility for the upholding of the adjoining buildings and roads, footpaths etc., where applicable, together with the mains and services from the time of taking possession of the Site through the duration of the Works. Adequately maintain roads and footpaths within and adjacent to the site and keep clear of mud and debris. Where temporary works will cause alterations to the permanent structure, such as changes in the design loadings to accommodate construction loads, provision of temporary construction openings, incorporation of the temporary works or part thereof into the permanent structure etc., complete revised designs and details of the affected permanent work certified by the PE, shall be provided. Revised designs of the permanent structure shall comply with the requirements of these specifications and shall be in general conformance with the design concept of the permanent structure, all to the satisfaction of the SO. 1.4.7 Verification of Site Information TS 192/1065 978 Doc D.2/262 1.4.7.1 Site Surveys Verify and be satisfied that the information given in the existing site survey plans provided are accurate. If necessary, engage a Registered Surveyor to carry out additional site survey before commencing any work. 1.4.7.2 Additional Site Investigation Take all necessary steps before the commencement of earthworks to verify and supplement the ground investigation report and any other information provided at tender, to the extent that is required in the method of construction. Consider all relevant factors, including those arising from the nature of the ground (e.g., ground levels, water table level, rock formations, subsoil conditions, etc.), geology of the Site, climatic conditions, the availability or lack of access, working space, storage, accommodation, the proximity of adjoining structures and roads, the local regulations regarding the obstruction of public highways and any other limitations imposed by the Site and its surroundings, for the satisfactory completion of the earthworks. Make due allowance for the effect of these constraints on the Contractor’s construction operations to ensure on-time completion of the Works. Carry out additional ground investigation where additional information is needed for the works or when directed by the SO. Carry out the Works in compliance with Section C02-010 and EN 16907-1 to 6, which describe investigation and testing methods specific to earthworks. Carry out the exploratory holes and any testing progressively prior to commencement of the Works in areas according to the Contractor’s construction programme. On completion of drilling, backfill the boreholes with a suitable bentonite/cement mix. Backfilling of trial pits may be undertaken with the pit arisings subject to the SOs approval, on the condition that it is safe to do so, and the arisings shall be placed and compacted in layers to ensure any settlement is within acceptable levels. Should settlement of the backfilled trial pits be considered a risk, the site shall be revisited at a later date(s) as agreed with the SO to check the pit locations and, where necessary, to top up and level off the ground to the satisfaction of the SO. Submit the location and schedule for the boreholes with the SOs acceptance prior to carrying out the Works. On completion, prepare the ground investigation report and submit to the SO for acceptance. 1.4.7.3 Groundwater Level Verify the data on groundwater level from available ground investigation reports and where possible, continue groundwater monitoring on existing installations, in addition to installing new groundwater monitoring wells and piezometers, and commencing monitoring of these installations. TS 193/1065 978 Doc D.2/263 1.4.7.4 Contamination Verify information on contamination identified or believed to be present on site. Environmental Baseline Studies (EBS) or Environmental Site Assessment (ESA) in compliance with the requirements of relevant authorities as appropriate, shall be undertaken to investigate or verify contamination of soil and groundwater. In the event that contamination is either positively identified or suspected, draw to the attention of all personnel working on site together with the need to take any precautionary measures in handling contaminated materials, groundwater and obnoxious vapours from the ground. [Note 1: Contamination of soil and groundwater shall be verified or investigated in accordance with JTC’s guidelines on EBS or ESA, and relevant requirements by authorities including SLA and NEA. Note 2: Contamination may have been previously identified or suspected from the past history of the Site. In either case, details should be given, and even where no such information is available the Contractor should notify the SO of any relevant findings and take appropriate precautions while working on the Site.] 1.4.8 Existing Services Affected by the Works Refer to G01-010 "General Requirements" for the requirements to deal with existing services affected by the Works. Conduct pre-commencement site visits where necessary to establish and verify the locations and levels of all existing underground utilities within and surrounding the Site that are affected by the earthworks, and take all necessary steps either of a temporary or a permanent nature to protect, divert or shut off the affected services to the satisfaction of the relevant authorities or service providers. Any information made available at the time of the tender is indicative and is intended only as an approximate guide for verification on site. Immediately after taking possession of the Site and before commencing work, establish test holes to confirm the locations and levels of all existing underground utilities within and surrounding the Site that are affected by excavation works. If the site verification survey of underground services is incomplete or inadequate in any way, additional confirmatory test holes shall be carried out as directed by the SO. Immediately notify the SO and the relevant authority if encountering services not known to have existed at the time of tender. 1.4.9 Site Protection Protect all equipment and working area using fencing or other methods as accepted. Upon completion of construction operations, remove all temporary works to the satisfaction of the SO and to the requirement of the relevant authority. Provide approved fill material, transport, deposit in voids between the face of the excavation and the permanent structure, and compact to the required lines, levels and grades required for the satisfactory completion of the earthworks. Propose for the SOs acceptance on the use surplus excavated materials as fill provided the material meets the requirements of these Specifications. TS 194/1065 978 Doc D.2/264 1.4.10 Temporary Access Roads Provide and maintain all necessary temporary access roads and divert and reinstate the permanent drainage system. Submit the proposed alignments and levels of temporary access roads to the SO for approval prior to their construction. Provide all temporary roads with drainage ditches over the full length of the roads. All temporary works, e.g., temporary cut, fill, retaining structures, strengthening measures, etc., that will be left behind and form part of the permanent works shall comply with the requirements, standards, specifications, safety standards and serviceability conditions as the similar types for permanent works. Obtain all necessary statutory approvals on temporary access into the Site for the tenure of the contract period and comply strictly and diligently with all conditions attached with these approvals. The access as well as the portion of public road and walkway connected with it shall be kept clean and safe at all times. Provide continuous and adequate security arrangements at access points into the Site for the full duration of the Contract. 1.4.11 Obstructions The submission of the tender shall take full account of the Site, including site visits, the nature, extent and practicality of the excavation, earthworks or associated temporary works. Prior to the submission of the tender, check and verify that the existing ground and formation levels as shown on the drawings are correct. If any obstructions such as existing fences, structures, footings, boulders, concrete blocks, pipes, drains, driveways or ramps are encountered during excavation, submit proposals for their removal for the SO's acceptance. Regardless whether or not the service to be diverted is known to exist at the time of tender, give the necessary notices to the relevant authority or service provider and arrange for the diversion work to be carried out if required or as directed by the SO and the relevant authority or service provider to temporarily or permanently divert any cable, pipe or other services. Co-ordinate all service diversion works that are carried out during the tenure of the Contract Period to ensure that such works do not adversely affect the on-time completion of the Works, and bear all consequences for any delay arising from failure to do so. 1.4.12 Supervision of the Works Engage a qualified, competent and suitably experienced site engineer to the SOs acceptance, to supervise the field works. The excavation and earthworks shall be such that the design or required lines, levels and grades meet the requirements of the Works and any surplus excavated material shall be removed off the Site or as directed by the SO. The exposed faces of the excavation and all slope shall be adequately protected with approved materials and measures in timely sequence in accordance with the agreed method of construction. TS 195/1065 978 Doc D.2/265 1.4.13 Registered Surveyor Employ a Registered Surveyor who shall be responsible for surveying the site and submit the results to the SO. 1.4.14 Quality Control Plan Submit and work to a quality control plan as agreed with the SO. Refer to G01-010: Clause:1.4.7. 1.4.15 Safety Provide safety precautions to comply with all current legislation and regulations, notably: (a) Building Control Act and Regulations (b) Code of Practice for Traffic Control at Work Zone (c) Workplace Safety and Health Act and Regulations (d) SS CP 79 Safety management system for construction worksites (e) For works within LTA Railway Protection Zone, ensure the works comply fully with Code of Practice for Railway Protection. Additionally, comply also with the following: (f) BRE Digest 251 (1995) Assessment of damage in low rise building (g) Not In Use S(g) BS 8008: Guide to safety precautions and procedures for the construction and descent of machine-bored shaft for piling and other purposes. 1.4.16 (h) Factories (Building Operations and Works of Engineering Construction) Regulations (i) Factories Act Environmental Protection Provide environmental protection measures and pollution control precautions to comply with all current legislation and regulations. 1.5 Definitions and Abbreviations 1.5.1 Definitions TS 196/1065 978 Doc D.2/266 1.5.1.1 Accredited Testing Laboratory The Testing Laboratory shall mean an organisation or laboratory accredited under the Singapore Laboratory Accreditation Scheme (SINGLAS) and fully equipped to carry out all tests and checks required by the Specification. 1.5.1.2 formation The surface of the ground after completion of any excavation or filling. 1.5.1.3 obstructions Include rock, concrete, reinforced concrete, solid brickwork, sheet piles and the like, met within the excavations, but excluding those met on the surface of the ground. 1.5.1.4 S1.5.1.4 Not In Use rock Material with a large coherent mass of such size and strength, which can be loosened or fractured only by blasting, or the employment of heavy pneumatic tools, or by chemical expansion methods. Loose boulders up to 1m³ in volume that can be removed are not classified as rock. 1.5.1.5 suitable material All that which is acceptable in accordance with the Contract for use in the works and which is capable of being compacted in the manner as specified to form a durable and stable fill, having side slopes as indicated on the drawings and meeting all other necessary performance requirements. 1.5.1.6 non-suitable material Other than suitable material, including: (a) Material from swamps, marshes or bogs (b) Peat, logs, stumps or other organic matter and perishable and toxic materials (c) Material susceptible to spontaneous combustion (d) Marine clay generally and clay of liquid limit exceeding 70 and/or plasticity index exceeding 35 TS 197/1065 978 Doc D.2/267 1.5.1.7 temporary works All construction works that are not part of the permanent works but are required for their completion. 1.5.1.8 topsoil Soil which by its nutrient content is capable of supporting the growth of vegetation. 1.5.2 Abbreviations No item. Note: Refer to EN 16907 on other definitions and abbreviations as applicable for the Works. 2 PERFORMANCE REQUIREMENTS 2.1 General Carry out the earthworks in accordance with SS EN 1997-1 and SS EN 1997-2, and EN 16907-1 to EN 16907-6. 2.2 Site Clearing The whole Site shall be cleared to the extent as shown in the relevant drawings. Include clearing, grubbing and removing all trees, shrubs, vegetation and butts; and demolishing, breaking up and removing all structures above ground level, such as buildings, walls, fences and other obstruction within the Site which have been designated to be demolished or removed. All spoil and debris shall be removed and disposed as approved or as directed by the SO. Grubbing shall consist of the removal and disposal of surface vegetation, the bases of stumps, roots, the underground parts of structures, and other obstructions to a depth of at least 0.5 m below ground level, all with the agreement of the SO. Stripping topsoil shall consist of the removal of topsoil to an average depth of at least 150 mm below ground level, and its stockpiling for use in the Works, and/or its disposal, as directed by the SO. Dump all materials resulted from site clearing to the approved dump site, unless otherwise directed by the SO. Method statement on dumping with particular emphasis on prevention of environmental pollution shall be submitted for the SOs acceptance. 2.3 Preservation of Existing Trees Take precaution to protect from damage all existing trees and shrubs which are designated to be preserved by NParks or as specified or directed by the SO. When necessary, adequate temporary fencing shall be erected for each tree or a group of trees. When required, the tree shall be protected by wrapping with suitable paling materials up to 1.5 m high. TS 198/1065 978 Doc D.2/268 2.4 Demolition of Existing Structures Any existing structures and other obstruction which are designated to be removed shall be demolished, broken up, removed and disposed as approved by the SO. All salvaged materials arising from the demolition work shall, unless otherwise specified, be removed from Site as soon as possible. Refer to the drawings or as specified or required by the SO on major structures which cannot practicably be cleared by bulldozer and/or hydraulic excavator; whose demolition requires pneumatic tools, explosives and/or other specialised equipment, and depth to which extent each of such structure shall be demolished. 2.5 Temporary Earth Retaining Supports The design for the temporary supports in C02-020:Clause:1.4.1.1 shall take into account of all loads and actions as in SS EN 1997, including those due to the hydrostatic pressure, earth pressure, surcharge loads, overburden, effects of surrounding properties and varying load conditions or unfavourable conditions due to different stages of constructions. The design of temporary earth-retaining supports and related works shall be in accordance to the requirements of the relevant authorities and SS EN 1997, including the use of appropriate factors and performance criteria in terms of performance requirements with regard to permissible earthretaining wall deflection and ground movement limits, as stipulated by taking into account the effects of the designed temporary strutting or anchoring system and installation. Verify the design based on SS EN 1997-1 and SS EN 1997-2, unless otherwise agreed by the SO. 2.5.1 Pits and Trenches Design, supply, fix and remove all planking and strutting for the excavation as required. Take all necessary measures to ensure that the sides of pits and trenches remain stable at all times against all anticipated loadings; and to ensure the safety of the workmen and prevent damage to any adjoining property. The design and execution shall comply with the requirements of SS EN 1997-1 and SS EN 1997-2. 2.6 Slope Stability Provide necessary protective measures to ensure the durability and stability of slopes for the whole duration of the slope’s design life. Check slopes from both cut and fill against slip failure in accordance with SS EN 1997-1. For slopes with intermediate berms, check the stability of both the overall slope and slopes between berms. For slopes formed in weathered or fresh rock such that joints dip into the excavation are exposed, the potential for kinematic failure, including wedge, planar and topple failure shall be assessed, and appropriate remedial measures shall be installed where necessary. TS 199/1065 978 Doc D.2/269 2.7 Filling Works for Embankment Design and execute the filling works to remain stable at all times. Embankment construction over weak ground shall be staged to allow any required consolidation of the foundation strata between stages and ensure stability of the foundation. For all such cases, before proceeding to higher fill at every stage of filling works, the relevant parameters including strength and porewater of the underlying soils shall be verified and reported to the SO for approval to proceed further. 2.8 Ground Movements and Vibrations 2.8.1 Ground Movement and Vibration Control for Existing Critical Structures or Services Unless values are already stipulated in the Contract, propose for the SOs acceptance, the permissible ground movement and vibration limits due to the works taking into account the vulnerability and sensitivity of the adjacent properties after carrying out damage impact assessment as stated in Section C02020:Clause:1.4.1.2. State the limiting values for "alert" and "work suspension" levels as appropriate in the submission proposal in accordance with the requirements of Building Control Act and Regulations. [Note 1: Refer to BCA advisory notes and guidelines on excavation and impact on neighbouring properties.] Notwithstanding the above, ensure that the values of ground movements and vibrations generated by the Works shall not exceed the following requirements: 2.8.2 (a) Generally comply with the requirements of BS 5228. (b) The vibration generated by the works in MRT structures shall not exceed a peak particle velocity of 15 mm/s. (c) Unless otherwise directed, refer to Section C02-050:Clause:4.2.2 for general restrictions on ground movements and vibration limits for adjacent structures where relevant. Consolidation Settlement Upon completion of the Works, ensure that consolidation settlement due to filling activities have achieved a degree as stipulated in the drawings or directed by the SO. Make good any settlement that occurs up to the end of the period of maintenance. Upon completion of the Works, ensure that consolidation settlement due to filling activities have achieved a degree of 95% minimum, unless otherwise directed by the SO. 3 MATERIALS TS 200/1065 978 Doc D.2/270 3.1 General All materials excavated from the Site or imported into site for use as fill shall be classified as defined below in this Section unless otherwise defined by the SO or shown in the drawings. 3.2 Unsuitable Fill Unsuitable fill shall include but not be limited to: 3.3 (a) cohesive soils having a liquid limit in excess of 80% or plasticity index in excess of 55% (b) any material containing topsoil, wood, peat or waterlogged substances (c) any material containing bio-degradable or organic material (more than 2.5%) (d) any material containing scrap metal (e) material from contaminated sites (f) material which by virtue of its particle size or shape cannot be properly and effectively compacted (e.g., some slate wastes) (g) material susceptible to significant volume change (e.g. marine mud, swelling clays and collapsible soils) Classification of Materials for Compaction For the purpose of compaction defined by Section C02-020:Clause:3.7.2, materials are grouped as follows: 3.3.1 Cohesive Soil Cohesive soil includes clays and silts with at least 15% passing the 63 m BS sieve and up to 20% of gravel. It shall have a moisture content not less than the value of the plastic limit (determined in accordance with SS EN 1997-2) minus 4. 3.3.2 Well-Graded Granular and Dry Cohesive Soils Well-graded granular and dry cohesive soils include clays and silts containing more than 20% of gravel and/or having a moisture content less than the value of the plastic limit (determined in accordance with SS EN 1997-2:2010) minus 4, and well-graded sands and gravel with a uniformity coefficient exceeding 10. TS 201/1065 978 Doc D.2/271 3.3.3 Uniformly-Graded Material Uniformly-graded material includes sand and gravel with a uniformity coefficient of 10 or less, and silts and pulverised fuel ashes. [Note 1: Any soil containing 80% or more material in the particle size range from 0.06 mm to 0.002 mm will be regarded as silt for this purpose.] 3.4 Granular Fill Materials In general, granular fill materials shall conform to the requirements of types 1 and 2 materials as delineated below: 3.4.1 Type 1 Fill materials of this category shall consist of any combination of the following: 3.4.2 (a) Crushed rock (other than argillaceous rock) (b) Crushed concrete (c) Crushed (non-expansive) slag (d) Well-burned non-plastic colliery shale (e) Natural sand Type 2 Fill materials of this category shall consist of any combination of the following: (a) Crushed rock (other than argillaceous rock) (b) Crushed concrete (c) Crushed (non-expansive) slag (d) Well-burned non-plastic colliery shale (e) Natural sand (f) Natural gravel TS 202/1065 978 Doc D.2/272 3.4.3 Gradation The particle size distribution, determined in accordance with SS EN 1997-2, EN 14688-2 and EN ISO 17892-3, shall be within the grading limits below: Table 1. Gradation of Granular Fill Materials % by mass passing BS Sieve Size 3.4.4 Type 1 Type 2 75 mm 100 100 37.5 mm 85 - 100 85 - 100 20 mm 60 - 100 60 - 100 10 mm 40 - 70 40 - 100 5 mm 25 - 45 25 - 85 600 micron 8 - 22 8 - 45 63 micron 0 - 10 0 - 10 Plasticity of Fines The material passing the 425 micron BS sieve, when tested in accordance with SS EN 1997-2, shall be non-plastic for type 1 granular material and shall have a plasticity index of less than 6% for type 2 granular material. Report for each test, the amount of material retained on the sieve. [Note 1: These requirements may be a bit restrictive for general granular fill. Typically, if less than 15% fines (<63 microns), it is then acceptable even if slightly plastic. These requirements are more onerous than that for Special Fill as described below Section C02-020:Clause:3.2.] 3.4.5 Crushing Resistance In a test to determine the crushing resistance in kN required to produce "ten percent fines value" or 10% of fines by mass of the test sample, the fill materials shall have the following minimum crushing resistance: Table 2. Fill materials and minimum crushing resistance Material Load (kN)to produce 10% fines Type 1 50 Type 2 50 TS 203/1065 978 Doc D.2/273 3.5 Special Fill Material When required in the project, special fill material may consist of suitable material of which at least 95% shall pass a 125 mm BS sieve and at least 90% shall pass the 75 mm BS sieve. Up to 5% of the material may be made up from isolated boulders of maximum dimensions not exceeding half the thickness of the layer of material being placed, provided that the fill can be compacted in the manner as specified in C02-020:Clause:4.7. The coefficient of uniformity shall be greater than 10. The fraction passing a 63 m BS sieve shall be less than 20% by weight and shall have the following characteristics: 3.6 (a) Liquid limit not exceeding 35 (b) Plasticity index not exceeding 12 Rock Material Provide clean well-graded quarry waste from sources outside the Site. The material shall be resistant to weathering. The maximum size particles in the material shall pass through a rigid 200 mm square grid and the largest dimension of any particle shall not exceed 300 mm. The material shall not have more than 10% of its particles passing a 0.63 mm BS sieve. Rock used in rock fill embankments shall, except for any specified external cover to slopes or within 500 mm of formation levels, be of such size that it can be deposited in horizontal layers each not exceeding 450 mm loose depth and extending over the full available width of the embankment. 3.7 Hardcore Hardcore shall consist of any combination of the above, together with broken brick free from plaster, dust, loam, wood, rubbish or organic materials. All pieces shall be less than 75 mm in any direction. 3.7.1 Crushing Resistance The hardcore material shall have a crushing resistance of not less than 50 kN for 10% fines value. Refer to C02-020:Clause:3.1.5. 3.8 Fill Materials from Excavated Rocks Propose for the SOs acceptance on the use of excavated rocks of satisfactory quality that shall be crushed and screened to produce aggregates required for concrete, road base, subbase, or other purposes with the prior approval of the SO. Propose for the SOs acceptance on the replacement of excavated rock needed for earthwork construction with borrowed materials of satisfactory quality from alternative locations approved by the SO. Unless otherwise agreed by the SO, excavated rock shall be used in the construction of embankment, and fill as approved or directed by the SO, to the fullest practical extent, in one of the following ways: TS 204/1065 978 Doc D.2/274 3.9 (a) Excavated rock shall be broken down to a maximum particle size of 300 mm and used as rock fill. (b) Excavated rock shall be broken down to a maximum particle size of 150 mm, blended with suitable earth fill material in a proportion not exceeding 1 rock to 1 earth, and used as common fill. Materials with Excessive Moisture Content Naturally occurring materials within the Site that are non-suitable due only to excessive moisture content may be spread and dried or may be blended with other suitable materials. The use of material treated in this way shall be subject to the acceptance of the SO. 3.10 Blinding to Fill Blinding layer to the surfaces receiving sheet overlays or concrete shall be either of the following: (a) Grade 15 concrete (b) Sufficient sand, fine gravel or other approved fine material applied to fill interstices and moistened as necessary before final rolling to provide a flat, close smooth surface Sand for blinding shall meet the requirements of SS 31, Table 6, Type C or M. TS 205/1065 978 Doc D.2/275 3.11 Geotextile Sheet Unless otherwise specified, geotextiles shall be non-woven and shall be made of polypropylene, polyethylene, polyester or a combination of the aforesaid materials. Geotextiles shall not be susceptible to bacterial and fungal attack and shall be resistant to chemical action and not affected by exposure to ultra-violet light. Use Class A geotextiles where the geotextiles serve as a separation or reinforcement function, Use Class B geotextiles where the geotextiles serve as a filtration function. The property requirements for Class A and Class B geotextiles are specified below. Submit methods of laying and jointing prior to commencement of work. Table 3. Physical properties of geotexiles Class of Geotextile Physical Property Specification Class A Class B Minimum Unit Weight, g/m2 125 50 ASTM D5261 or ISO 9864 Minimum Grab Tensile Strength, N 530 270 ASTM D4632 Minimum Elongation To Break, % 60 55 ASTM D4595 Or ISO 10319 Minimum Trapezoidal Tear Strength, N 180 80 ASTM D4533 Water Permeability,cm/sec 2.0x10 -2 2.7x10 -2 Manufacturer’s test report to be submitted 4 WORKMANSHIP 4.1 Preparatory Work 4.1.1 General Carry out at least the following in preparing the Site for excavation or fill. All materials resulting from site clearing shall be dumped at the approved Contractor’s dump site, unless otherwise directed by the SO. The method statement on dumping with particular emphasis on prevention of environmental pollution shall be submitted for the SOs agreement. Confirm the extent of work before proceeding: (a) Break out old foundations, beds, drains, etc. Seal off drain ends and remove contaminated earth. Backfill as necessary. (b) Remove existing fences, gates, walls, roads, paved areas and other site features as required. TS 206/1065 978 Doc D.2/276 (c) Remove trees, shrubs and hedges as shown on the drawings. Cut down, grub up main roots and fill voids. Dispose of all wood using methods approved by the relevant authorities. (d) Clear site of rubbish and vegetation. Grub up and dispose of large roots. (e) Remove unwanted materials from Site. [Note 1: The work involving removal or planting of trees shall be carried out in accordance with the requirements of National Parks Board, Singapore (NParks). Where there are extensive site features/trees to be removed, mark the relevant items on site. Co-ordinate this requirement with clauses of the contract preliminaries and/or other sections such as demolition sections, C01-010, covering the protection of features to be retained.] 4.1.2 Ground Movements Verify the precise topography and layout of the site, with all key features and neighbouring structures accurately surveyed, as per the requirements stated in G02-020:Clause:1.4, and establish an agreed datum to monitor ground movements at the start of the Works. 4.1.3 Demolition of Existing Structures Any existing structures and other obstructions which are designated to be removed shall be demolished, broken up, removed and disposed as approved by the SO. 4.1.4 Topsoil Remove all topsoil to full depth (including turf) from the areas of cuttings and embankments, and other areas shown on the drawings. Remove topsoil also from existing embankments required to receive additional fill and from areas of new ditches and watercourses. Stripping topsoil shall consist of the removal of topsoil to an average depth of at least 150 mm below ground level, and its stockpiling for use in the Works, and/or its disposal, as directed by the SO. Stockpile all removed top soil for reuse, where practicable. Remove the topsoil in accordance with BS 3882. 4.1.5 Areas for Stockpiling Make arrangements and provide appropriate areas for stockpiling of topsoil and/or suitable material. Topsoil to be stockpiled for the Works shall be sufficiently fertile to promote and support the growth of vegetation, and shall be taken from such areas where clearing, grubbing and stripping of topsoil is required as approved or directed by the SO. Before stockpiling, separate topsoil from objectionable materials, all to the agreement of the SO and in accordance with BS 3882. Arrange for stockpile sites either within or outside the project site as agreed by the SO. TS 207/1065 978 Doc D.2/277 4.1.6 Disposal of Material Objectionable material from clearing, grubbing and stripping topsoil (including the demolition of structures) shall be disposed of as approved or directed by the SO. Subject to the SOs agreement, pile up combustible material, including all timber (except timber to be salvaged or used), all brush, stumps, roots, vegetation and other combustible refuse within the Site as agreed or directed by the SO, and burned, where burning is allowed or as agreed or directed by the SO. All burning shall be subject to the prior approval of the relevant statutory authorities, and shall be carried out in conformance with all pertinent regulations. Burning shall also be carried out at such places and at such time and in such a manner as to prevent fire from damaging vegetation and property within the project site designated to be preserved, and from spreading to areas adjoining the project site and damaging vegetation and property therein. Where burning is not permitted at any time, or if objectionable material is not to be burnt, combustible material shall be disposed of, together with incombustible material. All necessary provisions shall be made for incombustible material, including where appropriate, the remains of burning, to be disposed of in a safe and tidy manner at solid waste dumps outside the Site, whether on public or private land, unless otherwise approved or directed by the SO. 4.1.7 Ground improvement by Jet Grouting Method Carry out ground improvement if necessary prior to commencing the earthworks. For jet grouting methods of ground improvement, refer to Section C02-040-1. 4.1.8 Verification of Ground Verify the ground conditions detailed in any available ground investigation report, and evaluate and develop a specific ground investigation report for the project in accordance with SS EN 1997-1 and SS EN 1997-2. Keep a copy of the latter ground investigation on site for verification and update of the ground conditions. Continue to add to the ground investigation report throughout the full duration of the Works, including not only preconstruction ground investigation data, but all monitoring data, and test data from both the natural ground and the fill and embankment material. [Note 1: The ground investigation report in accordance with SS EN 1997-1 and SS EN 1997-2 does not necessarily take the form of a single report, but can be a collection of reports and relevant geotechnical data.] 4.2 Excavation: General Requirements 4.2.1 Drainage of Excavations TS 208/1065 978 Doc D.2/278 4.2.1.1 General Arrange for the rapid dispersal of water shed on to the Site from any source. Where practicable, and in accordance with authority’s requirements, discharge the water into the permanent outfall for the drainage system. Provide adequate means for trapping silt on temporary systems discharging into permanent drainage systems. 4.2.1.2 S4.2.1.2 Not In Use Provision of Temporary Systems Provide where necessary temporary water courses, ditches, drains, pumping or other means of maintaining the earthworks free from water. Maintain a sufficient minimum surface crossfall at all times and, where practicable, a sufficient longitudinal gradient to enable them to shed water and prevent ponding. [Note 1: Typically, minimum surface crossfall is 4%. Note 2: It may be practically impossible to keep open excavations totally dry – the intention of this Clause is for any water which does enter to be rapidly removed. Refer to EN 16907 and BS 6031 for additional guidance. Note 3: Particular care is necessary when excavating close to water mains or on sloping ground.] 4.2.1.3 Temporary Obstruction of Free Drainage Do not rely on pumping to provide drainage where temporary earth dumping obstructs the free drainage of a cutting. Construct temporary drains to a suitable outfall or install a permanent drainage through the dumping to ensure free drainage for the whole duration of the Works. 4.2.2 Surface and Percolating Water Provide for adequate measures so that the stability of the excavation and nearby ground are not undermined by surface and percolating water through the process of ground loss, consolidation and/or increase in lateral earth loading and to maintain the stability of the excavation. These measures shall at least include the following: (a) Carrying out adequate slope protection. (b) Diverting surface and percolating water clear of all excavations by means of temporary drains and sumps, and provide a groundwater recharging system, etc., if necessary. (c) Filling up and sealing on a daily basis all movement cracks that appear on the surface of adjacent ground and continue until ground movement has ceased. TS 209/1065 978 Doc D.2/279 Any bank slips, erosion of slopes and other forms of ground loss, and any consequential damage to drains, culverts, pipes, utilities, etc. occurring in the course of excavation and during the period when the excavation stays open, shall be rectified and made good. 4.2.3 Dewatering 4.2.3.1 General Give particular attention to avoid soil consolidation and ground loss next to the excavation caused by fluctuations in the water table level. In the event that temporarily pumping water out from excavations may lower down the water tables, take due care in protecting the stability of all structures and prevent any non-allowable settlement from occurring on these structures. Groundwater control and drawdown shall comply with the requirements of SS EN 1997 and be in accordance with the methods agreed with the SO. The dewatering method chosen shall ensure the stability of the excavation and the safety of nearby structures. Assess the effects of dewatering settlement on structures, services and land in the vicinity, in accordance with SS EN 1997-1 and with the acceptance of the SO. [Note 1: Techniques such as sheet piling or the injection of cement grout or bentonite clay slurry or in combination, may be necessary in some deep excavations below the ground water table.] 4.2.3.2 Damage Due to Settlement Where settlement due to consolidation is predicted to cause unacceptable damage to structures or utilities, implement measures to prevent such damage. Provide a risk register which details appropriate mitigation measures to ensure settlement does not exceed the predicted values, but also plan for appropriate remedial measures in the event that settlement exceeds predicted values. 4.2.3.3 Drainage Control Measures For excavations carried out in permeable material below groundwater level, make provisions for adequate drainage control measures to prevent piping or a general weakening of the foundations due to the flow of water. 4.2.4 Adjacent Excavations Where excavations are to be made in close proximity to each other, agree with the SO to complete the deepest excavations first and, where required, fill. Do not place excavated material adjacent to the excavation, unless the additional surcharge from such placement has been considered in the design. [Note 1: Specific ground and site conditions need to be assessed in order to determine any particular requirements to the Works.] TS 210/1065 978 Doc D.2/280 4.2.5 Surplus Excavated Material Remove all surplus materials that are not specified to be spread and levelled on site and dispose of to a suitable location. All materials resulting from site clearing shall be dumped to the approved dump site, unless otherwise directed by the SO. Method statement on dumping with particular emphasis on prevention of environmental pollution shall be submitted for his agreement. 4.2.6 Formations (a) Remove the last 150 mm of excavations above formation level just before inspection. Trim excavations to the required profiles and levels, and remove all loose materials. (b) Keep the bottom of all excavations free from mud and water, trim clean, protect from the effects of weather and thoroughly compact and consolidate by approved means. (c) Unless otherwise specified, seal formations within 4 hours of inspection with concrete or other agreed blinding. [Note 1: Depending how long the cut surface is left exposed before exposing the top of the formation for development, a thicker protective layer of 150 mm to 300 mm may be appropriate.] 4.2.7 Surcharge Adjacent to Excavation Surcharge loads or actions due to construction or other vehicles and equipment, excavated material, or other stockpiled material shall not be placed alongside the banks of the excavation without first making adequate provisions to underpin such loads and ensuring the stability of the excavation at all times. TS 211/1065 978 Doc D.2/281 4.2.8 Protection of Slopes and Banks All exposed earth slopes shall be protected with approved temporary protection immediately without delay after they are cut or formed prior to the application of permanent protection, i.e. closed turfing or hydroseeding and before proceeding further. Temporary protection shall not be removed until proper and adequate slope drainage (berm drains, cascade drains and toe drains) and permanent protection (close turfing or hydroseeding) are constructed in accordance to the drawings or as approved by SO. As earthworks progress, slope shall be protected and maintained in a diligent and expeditious manner on completion of each stage of excavation. Any deviation from the agreed method or sequence of slope protection must be approved in advance by the SO prior to implementation. The slopes of cuttings shall be cleared of all rock fragments which move when prised with a crowbar. Where, in the slopes of cuttings, layers of rock and soft material alternate, agree with the SO on the protective measures for the slope, immediately after dressing, that can be affected by weather, and the replacement of any insecure material to an approved depth and build up the resulting spaces, including the use of grade 15P / 20 concrete, shotcrete, or masonry using rock similar to the adjoining natural rock so as to ensure a stable face. Any such protective measure, materials and method shall be subject to the agreement of the SO. 4.2.9 Dimensional Tolerances Slopes in cutting shall be trimmed mechanically to neat and even surfaces which shall have gradients not steeper than that shown on the drawings. Widths of excavations shall not exceed the dimensions shown on the drawings by more than 300 mm and shall be obstruction free to complete the Works, unless otherwise approved by the SO. 4.2.10 Trafficking in Cuttings Do not permit constructional traffic other than that required for the excavation and trimming, on the surface of the bottom of a cutting unless the cutting is in rock or as agreed or directed by the SO. Make good any damage to the sub-grade arising from such traffic on the surface with same materials or materials having the same characteristics. 4.2.11 Separation of Materials Where the excavation reveals a combination of Suitable and Not Suitable Materials, carry out the excavation in such a manner that Suitable Materials are excavated separately for use in the works without contamination by Not Suitable Materials. [Note 1: It may be feasible to treat Not Suitable Materials by either blending with Suitable Materials or by the addition of additional additives but where possible this should be undertaken only after the materials have been excavated and separated.] TS 212/1065 978 Doc D.2/282 4.2.12 Temporary supports Provide temporary supports, including temporary retaining structures, strutting and ground anchors where necessary, in accordance with SS EN 1997-1 and the accepted design proposals. Ensure that the construction sequence comply with the accepted design proposals. Obtain the approval from the SO and the PE for temporary supports for every level of support before proceeding with further excavations to the next level of support. The method of construction of temporary works shall take into account the following: (a) The geology along the length and depth of the cutting (e) The water levels, hydrogeology and strata permeability along the length and depth (f) The expected movements or settlements and the anticipated effect on neighbouring structures (g) The depth of construction required (h) Any particular difficulties that special plant might meet with respect to access, clearances and working space (i) Control of heave and instability of the base of excavation (j) The adequate support of existing utilities affected by excavation (k) The operation of heavy equipment, storage of bulk materials and any other form of surcharge next to excavation (l) Control of lateral load increase and ground loss induced by water seepage through ground surface cracks behind temporary retaining structures 4.3 Excavations: Pits and Trenches 4.3.1 General Ensure the sides of pits and trenches remain stable at all times. TS 213/1065 978 Doc D.2/283 4.3.2 Supports to Excavation Where required by the nature of the materials being excavated, provide all necessary planking, strutting, shoring, ground anchoring and any necessary staging for upholding the face of the excavation. Before removing any planking, ground anchors or struts, demonstrate that there is sufficient support to the retained ground to avoid excessive movement. For temporary ground anchors, as soon as progress of the Works permits and with the acceptance of the SO, de-stress temporary ties and remove all strands if required. Identify locations where ties are to remain and ensure these are accepted. Alternatively, subject to the prior agreement, suitably batter the face of the excavation. 4.3.3 Struts and Walings Struts and wailings shall be adequate to sustain the calculated maximum loads without failure or unacceptable deflections. When necessary, preload struts to remove any slackness of the propping system. Submit the proposed magnitude of preloading for the SOs acceptance. Ensure the gaps between the waler and the retaining wall are properly wedged or packed to SOs acceptance. Indicate all working loads of struts clearly on the relevant construction drawings. Design of struts and walings shall comply with SS EN 1997, SS EN 1992, SS EN 1993. Refer to Technical Reference TR26, BS 8002 and CIRIA C760. 4.3.4 Timbered Excavation Submit for the SOs acceptance the use of timbered members for proper support to the sides of excavation as appropriate. Propose for the SOs acceptance the use of additional suitable methods as ground water cut- off system such as jet grouted piles in adverse ground conditions, including water-bearing granular soil conditions where water leakage into the excavation will cause significant groundwater drawdown leading to ground loss and/or soil consolidation resulting in adverse impact on the surroundings., All timber elements shall be removed on completion of work, but where timber is likely to be left in place, use treated timber to prevent rotting. 4.3.5 Width and Length of Pits and Trenches Trenches and pits shall not be wider than is necessary for the efficient laying and jointing of pipes or for other works to be carried out. Do not excavate more than the agreed length of trench at any one time. TS 214/1065 978 Doc D.2/284 4.3.6 Base of Excavation Ensure the bottom of all excavations is to the correct levels as required. The base of all excavations, after being trimmed and levelled, shall be well rammed and compacted to form a solid formation to the approval or as directed by the SO. The prepared formation shall be protected and prevented against damage or adverse effects from weathering, trampling by personnel and other construction activities. Fill any over-excavation of foundation pits or trenches below the specified levels with Grade 15 concrete to the specified levels. In a situation where concrete is placed without first having prior approval of the SO or verification by testing or otherwise to SOs acceptance that the base of any excavation is at least of the required bearing capacity and/or having the minimum modulus of subgrade reaction, the concrete that has been placed shall be removed to allow excavation to continue deeper. Remove any pockets of soft material or loose rock at the bottom of pits and trenches and fill the resulting cavities and any large fissures with Grade 15 concrete, or otherwise fill with Suitable Material compacted in layers as required. Do not trim the side faces within 24 hours after placing such concrete. In situations where the excavation has gone beyond or below the designated lines or levels of competent stratum, or where the prepared formation has deteriorated and become soft or unstable or not in accordance to the Drawings or specifications, such over-excavation and softened formation shall be replaced with approved granular fill or as directed by the SO. 4.3.7 Spoil Remove all surplus spoil immediately on excavation and keep reusable material tidy at all times. 4.3.8 Handling and Disposal of Excavated Materials Provide for excavation works and disposal of excavated materials to include any additional handling, the temporary formation of spoil heaps and re-excavating from within the Site and raising to higher levels as required or directed by the SO. No excavated material shall be removed from the Site except on the direction or with the approval of the SO. Depending on the construction methods and operational activities where suitable materials are permitted to be removed from the Site, any consequent deficit of fill material arising the reexcavating from shall be made good. Unless designated dump sites have been shown in the drawings, dispose surplus suitable material at the approved dump areas outside the Site as approved by the SO and in compliance with statutory requirements such as payment of royalties, environmental protection, etc. Take all precautions and preventive measures to avoid any spillage or soiling of the public roads during the earth removal operation. A method statement on dumping with particular emphasis on prevention of environmental pollution shall be submitted to the SO for agreement prior to dumping. 4.3.9 Not In Use TS 215/1065 978 Doc D.2/285 S4.3.9 Backfilling of Pits and Trenches Use Suitable Material, deposited and compacted by approved plant in accordance with Section 02020:Clause:4.7.2 or otherwise, as agreed with the SO. Remove timber sheeting and other excavation supports carefully as the filling proceeds except where they are required to be left in the position as agreed. 4.4 Excavations: Cuttings and Slopes 4.4.1 Excavation in Rock Unless otherwise specified, excavation in rock shall extend to at least 150 mm below the specified formation level and backfilled with approved materials. 4.4.2 Undulation In all cuttings, whether in earth or rock, undulation in the general plane of the slope shall not be permitted. 4.4.3 Loose Material Remove any overhanging, loose or unstable material on slopes. 4.4.4 Drainage Ensure the working areas are adequately drained throughout the period of construction. The excavation shall at all times be kept well drained and dry by means of temporary slopes, drains, sumps, etc., and by pumping. As earthworks progresses, temporary concrete drainage channels with cascades shall be provided and maintained for the efficient drainage of the area. These drains shall be cut to a gradient not exceeding 1 in 100. Temporary drains after use shall be demolished, removed and make good as required or directed by the SO. Subject to the SOs approval, provide and install a drainage and sump system at the final excavation level, and maintain the drainage and sump system for the duration the excavation is kept open. All temporary drains shall be directed to the nearest water course or to sumps which are pumped out to the roadside drain. The roadside drain shall have an adequately large section so that no mud or water spills onto the roads or pavements. Only self-priming submersible pumps of sufficient capacity such as Flygt pumps or similar equipment shall be used. Pumps shall be of sufficient number and capacity to provide adequate pumping capability in the event of breakdown. TS 216/1065 978 Doc D.2/286 4.4.5 Benching Unless otherwise specified, when cutting through any material subject to fretting, provide a 900 mm wide horizontal bench at a height of 600 mm above the table drain. Slope the cut surface at both ends of the bench in accordance with Section C02-020:Clause:4.4.6. In cutting earth overlaying rock, which is required to be cut to a slope steeper than 1:2, provide a 900 mm wide horizontal bench at the interface and slope the rock and earth surfaces in accordance with Section C02-020:Clause:4.4.6. 4.4.6 Required Slopes Cut slopes shall satisfy the requirements for stability as provided in Section C02- 020:Clause:2.6. 4.5 Excavation: Rock Blasting 4.5.1 General In a situation where rock is encountered in the course of excavation, remove it by approved means, which may include blasting. TS 217/1065 978 Doc D.2/287 4.5.2 Rock Rock refers to those geological strata of hard materials which necessitate the use of blasting or approved pneumatic tools for their removal. Rock excavation shall be carried out by methods appropriate to Site requirements as approved by the SO. Agree with the SO on the type of equipment or machinery or process, including size of the in- situ material, for the removal of material that is classified as rock and boulder. [Note 1: For determining the volume of individual boulders, the average diameter of the boulder in 3 orthogonal directions can be taken and used to calculate the volume of the boulder. In local practice, individual masses of rock less than 0.5 m3 are usually considered as boulders that may be mechanically excavated and will not need blasting or other methods, machinery or equipment required to remove rock. Note 2: In local practice, rock does not include material which can be loosened by using a dozer mounted drawn ripper of the following description with a production rate not exceeding 50 m3/hr: Tractor Unit: Equipment with a minimum weight of 37 tons and a net horse power rating of 305 brake horse power or more. The tractor unit shall be in good condition and operated by experienced personnel skilled in the use of ripping equipment. Dozer Unit: Plant with a minimum weight of 236 kN and net horsepower rating of 300 h.p. or 225 kw. The tractor unit shall be in good condition and operated by experienced personnel skilled in the operation of ripping equipment. Ripper Unit: The ripper to be attached to the abovementioned tractor should have a minimum penetration force of 120 kN. The ripper should have a single shank in good working condition with a sharpened cutting point. Note 3: Shale and clay boulders are not considered as rock. Note 4: Rippable material is considered to comprise material that cannot be excavated using standard digging methods (backhoe or face shovel) but can be ripped using one of the following: - A bulldozer with a single shank ripper (up to and including the CAT D9 Ripper or similar) and minimum operating mass of 35 tons. - A hydraulic excavator up to and including those with a minimum net flywheel power of 200 kW (CAT 330D L or similar) and with hydraulic breaker with a minimum of 1 700 kg service weight (Atlas Copco MB1700 or similar)]. 4.5.3 Use of Explosives On each occasion that the use of explosives is proposed: (a) Obtain the written consent of the SO. (b) Obtain all necessary licences and permits from the appropriate authorities and conform to all statutory acts and regulations relating to transport, storage, handling and use of the explosives. (c) Conform to the rules and regulatory requirements of the Singapore Police Force - Arms and Explosives (A&E) Police Licensing & Regulatory Department (PLRD) TS 218/1065 978 Doc D.2/288 Check that the method of blasting is safe, and that all statutory and imposed limitations are adhered to; and comply with the conditions of issue of the permit. Obtain all necessary licences for the procurement, possession, transport, storage and handling of explosives and to ensure the validity of such licences at all times. Before starting work, submit for the SOs acceptance that all the required permits are in order and that this category of work is adequately covered in the insurance policies. 4.5.4 Storage and Handling for Explosives Provide proper buildings or magazines in suitable positions for the storage of explosives in manner and quantities to be approved; and ensure no unauthorised issue or improper use of any explosives brought on the Works. Employ suitably experienced and qualified personnel to handle explosives for the purpose of the Works. Comply with the relevant security regulations dealing with the storage, handling and transport of explosives at all times. 4.5.5 Blasting Limits The maximum permissible air overpressure must not exceed 110 dB. Blasting shall be restricted to such periods as directed by the SO and as prescribed or required by the relevant authorities. In situation where blasting is deemed to be dangerous to persons or property or to any finished work or is being carried on in a reckless manner, the rock shall be excavated by other means, including chemical or mechanical splitting, or hydraulic breaking as directed or required by the SO. The use of explosives in large blasts, as in seams, drifts, shafts, pits or large holes, is prohibited unless authorised in writing by the SO. [Note 1: Using 9 kg or more of explosive is considered as large blast.] All drilling and blasting shall be done in such manner as to bring the excavation as close as possible to the required cross-section or profile and to disturb as little as possible the material to be left in place. Make all provisions for any extra work occasioned by breakage outside the required cross-section or profile when blasting by means of drill holes, tunnels or any other similar method is carried out. 4.5.6 Safety Precautions TS 219/1065 978 Doc D.2/289 4.5.6.1 General When blasting is proposed, determine the danger zone likely to be created and ensure that no damage is caused to persons or property on or off site. Provide full details as to the steps and precautionary measures to be taken to safeguard the surrounding properties. Inform the SO of the steps taken to safeguard the surrounding property and lives and to mitigate, protect or prevent any damage or annoyance caused by reason of blasting. Explosives shall be used in the quantities and manner recommended by the manufacturers and blasting specialist. Provide all necessary steps to preserve in the soundest possible condition the materials below and beyond the lines of all excavations. Delayed blasting to reduce shock waves shall be used to avoid damage to concrete and other works already completed. As the excavation approaches its final lines, blasting with pre-splitting technique of approved drillhole spacing shall be carried out to reduce blast damage and create reasonably even finished surface by means of parallel drill holes perpendicular to the toe of the excavation and parallel to the finally required face. 4.5.6.2 Road Closures When blasting operations are being carried out, close any road affected to traffic and erect the appropriate signs in accordance with the latest "Code of Practice for Temporary Traffic Control" published by the LTA and other authority requirements. Prior to the start of blasting operations, conduct a survey of all structures and services within 120 m of the site where blasting is proposed and any other structures within an area of influence or as required or directed by the SO to establish the existing or pre-blast condition of these structures. All blasting works shall be carried out within the hours as approved by the relevant authority and by the SO. 4.5.7 Removal of Loose Material Upon completion, all rock faces shall be scaled of loose blocks. [Note 1: Rock blasting will not be required for most building work. Where this is considered, it is essential to involve those experienced in such operations and to ensure full compliance with all regulations and safety precautions.] 4.6 Filling: Generally 4.6.1 General Filling works shall include the preparation, placing and compaction of Suitable Material at specified areas. TS 220/1065 978 Doc D.2/290 4.6.2 Placing Fill The areas that are to be filled shall be free from loose soil, rubbish and standing water. Take all necessary precautions to ensure stability of adjacent structures. Ensure plants employed for transporting, laying and compacting are suited to the material. Spread and level material in layers and compact as soon as practical. Lay differing materials separately so that only one type of material occurs in each layer. [Note 1: Filling needs to be well compacted so that structures, paving, drainage, etc. are not affected by settlement. All compaction works shall comply with Section C02-020:Clause:4.7. Refer to BS 6031 and EN 16907 for guidance on placement methods for even spreading.] Where fill platform is to be constructed against existing ground with a cross-slope of steeper than 1 (vertical) to 10 (horizontal), the foundation shall be excavated in all materials (including hard rock) to form benches with horizontal and vertical faces from which construction of the fill platform shall proceed. The maximum vertical height of each bench shall not exceed 500 mm. The benches shall be contiguous beneath the full width of the fill platform, and shall be of a suitable width to accommodate construction equipment such as motor-graders, trucks, rollers, etc. Unless otherwise agreed by the SO, the horizontal and vertical faces of the benches shall be scarified, and the material excavated in forming the benches can be used as fill in the platform as approved by the SO. 4.6.3 Stability of Works Filling works shall remain stable at all times. 4.6.4 Weather Condition Stop all filling works when the weather is judged by the SO as would adversely affect the compaction of the fill. 4.6.5 End Tipping End tipping of fill is not permitted unless otherwise agreed by the SO. 4.6.6 Soft Spots Where any undue movements due to the presence of soft unstable soil under the fill occur, or unsuitable material is encountered at the bottom of the fill, it shall be excavated to such depth and over such areas as approved by the SO, and shall be removed to spoil. The resulting excavation shall be backfilled with suitable material as specified in this Section or as directed by the SO, and deposited in loose lifts not exceeding 225 mm thick and compacted as described above, or with compaction equipment suitable for working in small excavation. Provide in the execution to allow for settlement or displacement of fill over soft areas, and build up to the required finished level with necessary compaction as appropriate. TS 221/1065 978 Doc D.2/291 4.6.7 Filling Under Floors, Aprons, Beside Pilecaps and Trenches Filling shall be provided and laid under floors, aprons, etc., where required or directed by the SO. Filling shall be of suitable material as specified in this Section, deposited in loose lifts not exceeding 150 mm in loose thickness, and each loose lift shall be well watered where necessary, rammed and compacted. No clay shall be used for filling under floors and aprons unless with the approval by the SO. Propose for the SOs acceptance free draining coarse grained materials to be used for backfilling in areas where compaction is practically difficult due to space constraint. 4.7 Filling: Compaction of Fill 4.7.1 General All materials shall be compacted in layers as soon as practicable after deposition. Upon completion and before overlaying, the surface of the layer shall be free from ridges, cracks, loose material, potholes, ruts or other defects. Rectify such defects to the full thickness of the layer before overlaying. Before commencing any filling, test each class of material to be compacted by an acceptable laboratory to establish the maximum value of the dry density that can be achieved and the optimum moisture content for compaction. Test in accordance with EN 13286-2. The number of tests required for each source material shall be as indicated in the Bill of Quantities or drawings or as required by the SO. [Note 1: Generally it is advisable to conduct additional tests, including laboratory Californian Bearing Ratio (CBR), and Moisture Condition Value (MCV) tests. Refer to EN 16907-2, Table 13 for an indication on the types of tests recommended, depending on how the fill will be used. Note 2: Requirements for compaction should only be relaxed for landscaping filling which does not support any structures or paving, and for which settlement behind retaining structures will not be an issue.] 4.7.2 Compaction by mechanical plants Refer to Table 4 which gives requirements for establishing appropriate use of compaction methods and mechanical plants. The depth of each compacted layer shall not be greater than the maximum depth of the compacted layer stipulated for each type of compaction plant. Earthmoving plant shall not be accepted as compaction equipment. Alternative methods or plants may be accepted which can be demonstrated to the satisfaction of the SO at site trials that the required field density can be achieved. Table 4. Requirements for the use of compaction plants Cohesive Soil Type of Compaction Well-graded granular and dry cohesive soils Uniformly -graded materials Category TS 222/1065 978 Doc D.2/292 Plants Max depth of Compacted layer (mm) Min No. of passes Max depth of Compacted layer (mm) Min No. of passes Max depth of Compacted layer (mm) Min No. of passes Smoothwheeled roller Force per 100 mm width . . . . . . . 2.1 - 2.6 kN 2.61 - 5.2 kN 125 125 8 6 125 125 10 8 125 125 10* 8* . More than 5.2 kN 150 4 150 8 Unsuitable Grid-roller Force per 100 mm width . . . . . . . 2.6 - 5.2 kN 150 10 Unsuitable 150 10 . 5.3 - 7.8 kN More than 7.8kN 150 150 8 4 125 150 12 12 Unsuitable Unsuitable Tamping roller More than 40 kN 225 4 150 12 250 Pneumatictyred roller Wheel Load . . . . . . 1 - 1.5 tonnes 125 6 Unsuitable 150 . 1.5 - 2 tonnes 150 5 Unsuitable Unsuitable 2 - 2.5 tonnes 2.5 - 4 tonnes 4 - 6 tonnes 6 - 8 tonnes 8 - 12 tonnes More than 12 tonnes 175 225 300 350 400 6 5 4 4 4 125 125 125 150 150 12 10 10 8 8 Unsuitable Unsuitable Unsuitable Unsuitable Unsuitable 450 4 175 6 Unsuitable . . . . . 75 75 16 12 150 150 16 12 4 10* Vibratory Roller Force per 100 mm width . . 0.25 - 0.45 kN 0.46 - 0.70 kN Unsuitable Unsuitable . 0.71 - 1.25 kN 1.26 - 1.75 kN 1.76 - 2.30 kN 2.31 - 2.80 kN 2.81 - 3.50 kN 3.51 - 4.20 kN 4.21 - 4.90 kN 100 125 150 175 200 225 250 12 8 4 4 4 4 4 125 150 150 175 200 225 250 12 8 4 4 4 4 4 150 200 225 250 275 300 300 6 10* 12* 10* 8* 8* 8* Vibratingplate Compactor Static pressure under base plate . . . . . . . 8.6 - 10.3 kN/m2 Unsuitable Unsuitable 75 6 75 75 10 10 100 150 6 6 2 . 10.3 - 12.1 kN/m 12.1 - 13.8 kN/m2 Unsuitable Unsuitable . 13.8 - 17.2 kN/m2 17.2 - 20.7 kN/m2 more than 20.7 kN/m2 100 150 200 6 6 6 125 150 200 6 5 5 150 200 250 4 4 4 VibroTamper Mass kilogramme . . . . . . . 50 - 65 65 - 75 More than 75 100 125 200 3 3 3 100 125 150 3 3 3 150 200 225 3 3 3 TS 223/1065 978 Doc D.2/293 . . Power rammer Mass kilogramme . . . . . 150 275 4 8 150 275 6 12 Unsuitable Unsuitable Weight of hammer over 5 kN Drop 0 m to 0 m 600 Drop over 0 m 600 4 2 600 600 8 4 450 8 Unsuitable 100 more than 150 Dropping weight compactor (a) The depth of compacted layer is the height by which an embankment is raised by each successive compacted layer. (b) The number of passes is the number of times that each point on the surface of the layer being traversed by the compaction plant (or struck in the case of power rammers or dropping weight compactors). (c) The effective width of a pneumatic-tyred roller is the sum of the widths of the individual wheeltracks together with the sum of the spacing between the wheeltracks provided that each spacing does not exceed 230 mm. Where the spacing exceeds 230 mm, the effective width shall be taken as the sum of the widths of the individual wheeltracks only. (d) The force per 100 mm width of roll is the total weight on the roller divided by the total roll width. Where a smoothwheeled roller has more than 1 axle the machine shall be assessed on the basis of the axle giving the highest value of force per 100 mm width. (e) Wheel load is the total weight of the roller divided by the number of wheels. (f) For items marked with an asterisk (*), the rollers shall be towed by track-laying tractors. Self-propelled rollers are unsuitable. (g) Where a combination of different types of plants are used, the following additional definitions apply: (i) The depth of layer shall be that for the type of plant requiring the least depth of layer. (ii) The number of passes shall be that for the type of plant requiring the greatest number of passes. Where a lighter type of plant is used to provide some preliminary compaction only to assist the use of heavier plant, this shall be disregarded in assessing the above requirements. ] 4.7.3 Required Field Density Unless otherwise agreed with the SO, produce a compacted fill material having a field density of at least the following percentage of the maximum dry density previously established for that material: (a) 95% in the case of material within 500 mm of formation level. TS 224/1065 978 Doc D.2/294 (b) 90% in the case of material more than 500 mm below formation level. Propose for the SOs acceptance to determine field density using the nuclear density meter or the sand cone replacement method where appropriate. Notwithstanding compliance with Table 4, verify by site tests at a rate of not less than 3 tests per 300 m2, with a minimum number of 3 tests per site, unless otherwise agreed by the SO, that the required field density is being achieved and make any adjustments to the compaction methods if necessary. [Note 1: The compaction values of 90% and 95% are commonly used in many cases but if structures are to be placed on top, more stringent criteria are required with compaction values of 98% or even 100%. The selection is project specific and will be dependent on the strength and stiffness of the fill after compaction - hence the importance of doing CBR and MCV or even triaxial tests on the compacted laboratory samples as mentioned for comment in Section 02-020:Clause:4.7.1.] 4.7.4 Moisture Content Maintain the moisture content of the in-situ material during compaction as close to the optimum moisture content as possible, and within the allowable range determined by the proctor or modified proctor tests as referred to in Section 02-020:Clause:4.7.1. If necessary, adjust by wetting or drying on site to consistently maintain the required in-situ field densities. 4.7.4.1 Type 1 Fill Materials The materials of Type 1 in Section C02-020:Clause:3.1.4.1 shall be transported, laid and compacted without drying out or segregation. 4.7.4.2 Type 2 Fill Materials The materials of Type 2 in Section C02-020:Clause 3.1.4.2 shall be transported, laid and compacted at a moisture content within the range 1% above to 2% below the optimum moisture content determined in compliance with BS 5835-1 and without drying out or segregation. 4.7.5 Air-Voids To reduce the potential of collapse compression of unsaturated cohesive fill due to wetting, the moisture content range at fill placement shall be controlled to achieve a compacted fill with allowable air void content not exceeding 5%. 4.7.6 In-situ Tests Refer to SS EN 1997-2 and BS EN ISO 22476 on field testing, and BS EN ISO 22282 on geohydraulic testing, as appropriate. TS 225/1065 978 Doc D.2/295 4.7.7 Compacting Different Materials When materials of widely divergent characteristics are used in fill areas, compact in separate clearly defined areas for each type of material. If defining the areas in which each material occurs is not practical, operate the compaction plant base on the material which requires the greatest compacting effort. 4.7.8 Use of Rock Fill Assess and evaluate the rock fill on Site for for satisfactory compaction to the requirements of table in Section C02-020:Clause:4.7.2 for well graded granular soil, compact the fill according to the table. Refer to Section C02-020:Clause:4.9.3.1 on spreading and levelling for rock fill. 4.7.9 Deterioration of Material If the material deposited as fill subsequently reaches a condition such that it cannot be compacted in accordance with the specified requirements, seek agreement with the SO to carry out one of the following: (a) Make good by removing the deteriorated material and replace with Suitable Material. (b) Make good the material by mechanical or chemical means to improve its property. (c) Cease work on the material until its physical condition is again such that it can be compacted as required. 4.8 Filling: Fill Adjacent to Bridge Abutments, Culverts and Retaining Walls 4.8.1 Not In Use TS 226/1065 978 Doc D.2/296 S4.8.1 Fill Material Within the limits defined in Table 5, adjacent to all structures, Special Fill Material as defined in Section C02-020:Clause:3 shall be provided. Place fill in horizontal layers of thickness appropriate to the compacting plant used and compact with care to the density specified in Section C02-020:Clause:4.7 for fill material. Table 5. Fill Adjacent to Abutments, Culverts and Retaining Walls Structure Minimum Width of Special Fill Bridge Abutment & Wingwalls 2m Culvert wingwalls H/3 Retaining walls H/3 or full width of base, whichever is greater Barrels of box culverts H/3 Barrels of pipe culverts 600 mm all round [Note: H = height of structure] 4.8.2 Filter Drain Provide a filter drain layer when filling behind structures with weep holes. The filter drain shall consist of clean, hard and durable broken stones or hardcore conforming to the grading as set out in Table 6. Table 6. Filter Drain Material BS Sieve Size Percentage by weight passing 63 mm 100 37.0 mm 85 - 100 20 mm 0 20 10 mm 0-5 3.30 mm 0 Place the larger stones adjacent to the weep holes and the smaller particles behind and above the larger layer. Unless otherwise specified, the filter drain shall: (a) have a width of 300 mm (b) extend horizontally across the whole width of the structures (c) cover every weep hole vertically by at least 300 mm. TS 227/1065 978 Doc D.2/297 4.8.3 Placing Fill For framed structures, bring up fill at both ends of the structure simultaneously with the difference in levels of fills at both ends limited to 600 mm. Do not place fill against concrete structures within 21 days after placing concrete unless sufficient supports have been provided to the walls with the acceptance of the SO. [Note 1: The SO may require calculations to be submitted to show that no damage to the concrete structures will be caused by backfilling earlier than 21 days.] 4.8.4 Compaction Place fill in horizontal layers of thickness and compact using the appropriate plant in compliance with Section C02-020:Clause 4.7.2. The degree of compaction shall be at least 95% of the maximum dry density achievable of the material unless otherwise agreed with the SO. Do not use heavy compaction equipment close to the back of the wall. [Note 1: The effect of compaction shall be taken into account in the design, and the allowable loading due to compaction equipment shall be clearly specified. Note 2: Structural fill or special fill is often better to compact to 98% which should be achievable for the type of material used as special fill, even when using hand held compacting equipment.] 4.9 Filling: Embankments and Fill Slopes 4.9.1 Material Ensure Suitable Materials are being used for embankment fill, including materials which may be initially wetter than specified but become suitable after drying. For capping layers which comprise materials used to improve the performance of the foundation soils before laying the sub-base, and to protect the subgrade from damage by construction traffic, ensure specified materials, including topsoil are placed to a consolidated thickness below the formation level. 4.9.2 Build-up and Compaction Unless justified as impractical, build up embankments evenly over the full width and maintain a sufficient cambered surface to enable ready drainage of surface water. Compact fill material as per Section C02020:Clause 4.7. 4.9.3 Rock Fill TS 228/1065 978 Doc D.2/298 4.9.3.1 Spreading and levelling Rock used in rock fill embankments shall be of maximum particle size of 300 mm so that it can be deposited in horizontal layers, each not exceeding 500 mm in compacted depth and extending over the full width of the embankment except for any specified external cover to slopes or new formation level. The materials shall be spread and levelled by a crawler tractor weighing not less than 15 tonnes. Each layer shall consist of reasonably well-graded rock and all large voids with averaging dimension of exceeding 150 mm shall be filled with broken fragments before the next layer is placed. The top surface and side slopes of embankments so formed shall be thoroughly blinded with approved fine graded material to seal the surface. There shall be a transition layer between rock fill and earth fill or the top 300 mm below formation level of at least 300 mm compacted thickness. This shall consist of uniformly-graded crushed rock between 6 mm and 150 mm as approved by the SO. Refer to Section C02-020:Clause 4.7.8 on the assessment and evaluation of rock fill for compaction method to be approved by the SO. Unless otherwise required or directed by the SO, spread and level each layer of rock fill and systematically compact by at least 12 passes using the following methods as appropriate: (a) A towed vibratory roller with a static load per metre width of roll of at least 1 800 kg, or with a static load per 25 mm width of roll of at least 80 kg. (b) A grid roller with a load per metre width of roll of at least 8 000 kg, or with a load per 25 mm width of roll of at least 200 kg. (c) Other approved plant. [Note 1: Each horizontal layer of 500 mm is the maximum thickness. Normally compacted thickness of rockfill layers should be not be less than 1.5 x the maximum particle size.] 4.9.3.2 Finishing Fill surface voids with broken fragments before the next layer is placed. Thoroughly blind the top surface and side slopes of embankments with approved fine graded material to seal the surface. [Note 1: Depending on the rockfill and the end use of the embankment, agree with the SO on the use of geotextile layers with the blinding layer if there is a risk that the voids between the rock fill are not filled and material may migrate from the embankment body into these voids.] 4.9.3.3 Use of Isolated Boulders Isolated boulders each within the range 0.02 m3 to 0.10 m3 in size may be used provided that the specified compaction requirements are met and no stone exceeding 0.02 m3 shall be placed less than 0.5 m below the top of the embankment fill. TS 229/1065 978 Doc D.2/299 4.9.4 Embankments Bridging Culverts, Pipe Drains and Bridges In constructing embankments up to and over culverts, pipe drains and bridges, bring the embankments up equally on both sides. Filling may proceed over widths less than the full width of the embankment and in steps not exceeding the depth of one layer above the adjoining area of fill. 4.9.5 Construction Traffic During construction, control constructional traffic uniformly over the full width of the embankments. If the intention is to use the surface of embankments for constructional traffic before trimming to formation level, bring up and maintain the area to a level not less than 150 mm above formation level before allowing constructional traffic on the surface. In areas of shallow filling where the ground level is within 300 mm of formation level, bring up and maintain the surface level at least 300 mm above formation level. Make good any damage caused to the subgrade. [Note 1: Many situations require control construction traffic uniformly over the full width of the embankments. However, it depends on embankment materials and its trafficability particularly if using cohesive fill. If haul roads are required and much of construction traffic should be kept off as this is particularly critical for formation surface. Refer to the guidance in BS 6031.] 4.9.6 Formation of Slope Faces (a) Form the slope faces of embankments by overfilling, cutting back and trimming neatly to the determined profile. The formed slopes shall satisfy the requirements for as provided in Section C02-020:Clause:2.6. (b) Where an embankment is to be constructed on a hillside, or where the natural surface falls away at a slope steeper than 1 vertical to 4 horizontal, cut a horizontal bench to support the toe. The minimum width of the bench shall be one third of the vertical height of the fill (measured from the toe) but not less than 600 mm. (c) Where an embankment is to be constructed on the slopes of existing embankments exceeding one vertical to four horizontal, the existing slope shall be cut in the form of horizontal terrace over the full area to be covered by the new fill. Cut the terraces in minimum width of 600 mm and stepped progressively as the fill progresses. (d) At 1.2 m below the embankment surface, no point on the completed slope shall vary from the required face by more than150 mm measured at right angles to the slope. At greater than 1.2 m below the surface, no point on the completed slope shall vary by more than 300 mm. [Note 1: Refer to Section C02-020:Clause 4.4.4 on the requirements on drainage and also Technical publication UK TRL PPR 314 on drainage of earthworks slopes.] TS 230/1065 978 Doc D.2/300 4.10 Method of Measurement All measurement of excavation shall be based on the net dimensions between the external faces of the permanent construction. Levels shall be taken and certified before and after excavation, to calculate the volume for each method of excavation. Levels taken shall be subject to approval by the SO. Maintain all boundary markers, bench marks and other such reference points which shall be offset before commencement of the Works. All offsets shall be carried out by a qualified surveyor. Should any such markers be disturbed or destroyed, these references shall be replaced immediately and the SO informed of such replacement. 4.11 Hardcore Under Concrete Slabs Use material as stated in Section C02-020:Clause:3.4. Provide thicker layer than specified if necessary to make up levels from stripped site levels to underside of slabs. [Note 1: For many small projects, a layer of hardcore beneath a ground-bearing slab will be adequate. The intention of this clause is to simplify drawings by making it unnecessary to show the precise thickness of hardcore but only minimum thickness required.] 4.12 Use of Geotextile Sheet 4.12.1 General (a) Protect from exposure to light, except for a maximum of 5 hours during laying. Protect from all materials listed as potentially deleterious by the manufacturer. (b) Before commencing laying, remove humps and sharp projections from the ground and fill hollows. Do not stretch or bridge the geotextile over irregularities and ensure that the specified lap is maintained. (c) Take care to avoid damage to geotextile by vehicles, plant or by tipping material from excessive height. Do not allow construction traffic over geotextiles until covered by the full thickness of fill. (d) Temporarily weight edges of sheet with fill and lay a maximum of 15 m of geotextile before covering to prevent uplift. Place fill as soon as possible after laying and within a maximum of 24 hours. (e) Place geotextile patches over tears with minimum lap of 300 mm beyond extent of damage and cover immediately to retain in place. (f) Geotextiles are adversely affected by exposure to ultraviolet light. Minimum lap must be maintained unless joints are stitched or stapled, even if laying in strong winds. Both of these requirements are best achieved by not laying more geotextile than can be covered by fill in the same day. TS 231/1065 978 Doc D.2/301 4.12.2 Jointing Propose and comply with one of the following methods of jointing: (a) 300 mm overlaps: Overlaps to be 300 mm to 1 000 mm, with the wider overlap necessary on very soft subgrades to allow for movement when trafficked by vehicles. Overlaps shall be weighted down immediately with small amounts of aggregates. (b) Single-stitched prayer seam with high tenacity polyester thread: Carry out sewing with portable stitching machines using high tenacity polyester or polyester/cotton thread in a single or double stitch to form a prayer seam configuration. A single line stitch is generally adequate. (c) Single welt with two rows of staggered, corrosion resistant staples - Carry out stapling on welted seams with two rows of staggered, corrosion resistant, staples. [Note 1: Seam strengths are likely to be considerably lower than those achieved by sewing.] 4.13 Preparation for Cultivation with Spot and Close Turfing Trim and cultivate cut or filled areas that are to be turfed as soon as possible after completion of the earthworks. For turfing requirements refer to the architectural specifications or drawings and G01-010 General Requirements. 4.14 Seeding Seeding or hydroseeding shall be carried out as soon as practical on slopes and other areas as shown in the drawings and/or as directed by the SO. Submit to for the SOs approval, in advance of the proposed work, full details of the proposed method of seeding and hydroseeding. The information submitted shall include, but not necessarily be limited to, a full description of the following aspects of the Works: (a) Penetration of the areas to be seeded or hydroseeded, including if appropriate the amount of topsoil to be used and its method of application. (b) Details and results of investigations to determine which types of grass or legume are comparable with the soil in the areas to be seeded. (c) Types of grass and legume (if any) and strains of seed to be used, and the function, root and growth characteristics of each type. (d) Rates of application of the grass and legume seeds. (e) Composition of fertiliser to be used at the time of seeding and its rate of application. (f) Composition of fertiliser to be used after seeding, the times of application after seeding, and the rates of application. TS 232/1065 978 Doc D.2/302 (g) Type of mulch to be used and its method and rate of application. (h) Amount of lime or other chemicals (if any) to be applied to improve the soil before, during and/or after seeding. (i) Type and amounts of binding agents to be applied with the seeds, mulch, fertiliser, etc., as appropriate. (j) Proportions and methods of preparation of the seeding mix. (k) Equipment and method to be used in preparing and placing the seeding mix and other materials. (l) Cultivation and after-care if the seeded areas, including rates and frequencies of watering, fertilising, grass cutting and general maintenance for at least 1 year after seeding. (m) Time after seeding required for establishing permanent, dense growth of grasses, which will require minimal maintenance. (n) Guarantees of success of the seeding work. All grass shall be regularly watered until the vegetation is satisfactorily established to the satisfaction of the SO. Any dead grass shall be replaced. Hydroseeding shall be carried out after the proposed slope surface exceeds 1 000 m2 or within 2 weeks after cutting or 1 week during monsoon season, whichever is earlier on all slopes and other areas as shown in the drawings and/or directed by the SO. 4.15 Monitoring of Fill Performance Provide and arrange for the performance of the fill, once placed, to be monitored. Propose for the SOs acceptance and implementation on monitoring the performance which can consist of one or more of the following as appropriate: 4.15.1 (a) Optical levelling of surface markers (b) Standpipes or piezometers (c) Load tests (d) Other methods as required or directed by the SO. Instrumentation Arrange for the supply of the instruments as specified, or required or directed by the SO and inform the SO of the date on which the equipment installation shall commence. Provide the SO with the following details: (a) A full description of the nature and type of instrument and the purpose it fulfils. TS 233/1065 978 Doc D.2/303 (b) The number required and the location and or depth at which each instrument is to be installed. (c) The frequency, accuracy and duration for which any readings are to be taken. 4.16 Accuracy and Tolerance 4.16.1 General Comply with EN 16907 except where noted below. 4.16.2 Permitted Deviations (PD) from Formation Levels (a) Beneath mass concrete foundations: ±25 mm. (b) Beneath ground bearing slabs and reinforced concrete foundations: ±15 mm. (c) Embankments and cuttings: ±50 mm. (d) Ground abutting external walls: ±50 mm, but such as to ensure that finished level is not less than 150 mm below any damp proof course. 4.16.3 Blinding to Fill Permitted deviations on surface level: +0, -25 mm. [Note 1: The zero plus tolerance is to ensure that minimum thickness of overlying concrete slabs is maintained.] 5 VERIFICATION AND SUBMISSIONS 5.1 Submissions 5.1.1 Method Statement Before work commences, provide the SO with a method statement, including at least the following information as relevant: (a) Proposed excavation and compaction plant (b) Maximum depth of each compacted layer (c) Minimum number of passes per layer (d) Method of treating slopes (e) Protection of formation and slopes TS 234/1065 978 Doc D.2/304 5.1.2 (f) Proposed temporary works (g) Dewatering control (h) Ground anchors, etc. Programme of Works Submit to the SO prior to the start of the Work unless otherwise agreed. 5.1.3 Additional Site investigation Factual Report Extend to the SO, a copy of the factual report for additional site investigation conducted under Section C02-020:Clause 1.4.6.2. 5.1.4 Temporary Works Design 5.1.4.1 General Before commencement of Work, submit details of proposals for supporting the sides of all excavation which have slopes steeper than 1:2, or less if poor conditions exist, or exceeding 1.5 m in depth which will be formed during the course of the Works. Provide adequate information to justify the adequacy of the proposals, if so requested. [Note 1: A risk assessment is generally required based on actual ground conditions and the activity to be undertaken to determine where temporary supports to excavations are required. Though 1.5 m has been taken as the depth lesser which these are not required, this will not always be the case.] 5.1.4.2 Flow chart for ground movement monitoring Submit a flow chart clearly indicating the proposed line of actions and the persons in-charge in connection with the actions to deal with critical ground movements for the SOs acceptance. 5.1.4.3 Use of ground anchors Where there are use of ground anchors as part of the temporary works, submit to the SO a detailed specification for the anchors as part of the method statement. Provide an appraisal of the suitability of the proposed anchor installation in relation to the ground conditions, the possible effects on adjoining structures and services, and the rights of adjoining owners whose structure or land may be affected. Ensure all necessary approvals and permits have been obtained from the authorities. 5.1.5 Quality Control Plan Prepare and submit the quality control plan for SOs acceptance prior to starting work. TS 235/1065 978 Doc D.2/305 5.2 Inspection and Tests of Temporary Works Inspect the temporary works scheduled as follows: (a) Intermediate inspections if the works are in place for more than 1 week (b) If there has been a change in loading conditions, including impact (c) After any adverse weather conditions Submit a method statement for acceptance indicating the proposed frequency and details of the inspections. 5.2.1 5.3 Pull Out Tests for Ground Anchors (a) Pull-out test shall comply with SS EN 1997-1 and BS EN 1537. (b) Propose numbers of tests for acceptance in the method statement. (c) Perform preliminary pull-out tests prior to the installation of working ground anchors to verify the design capacity of ground anchors. (d) Carry out acceptance tests on the working ground anchors. Fill Material Samples At least 21 days before filling work commences, submit full details of the sources and types of the proposed filling materials together with 25 kg representative samples of each type from each source. On request from the SO, collect and dispose of these samples. At the same time, deliver to an accepted accredited laboratory, sufficient representative samples of each material for the specified tests, at a rate of one set of tests per sample. [Note 1: All materials submitted should be examined, described (and photographed), and samples retained for comparison with those supplied to the Site. Tests should be made to determine the properties (grading, plasticity, SO3 content, density, California Bearing Ratio, CBR, etc.) relevant to the Works and as described in subsequent clauses, and to provide a basis for comparison with materials supplied to site.] 5.4 Testing of Fill Materials Carry out the following tests according to SS EN 1997-1 and SS EN 1997-2 and relevant standards including BS 1377 on all proposed fill materials at the rate of one test for each representative sample: (a) Classification (b) Ground Investigation TS 236/1065 978 Doc D.2/306 (c) Determination of the particle size distribution (d) Determination of the plasticity index (of material passing the 425 micron BS sieve; % of material retained to be reported) (e) Determination of the total sulphate content (f) Determination of the ten per cent fines value Carry out the following tests (but not limited to the list below) according to SS EN 1997-2 and relevant standards as required for certain materials when specified or directed by the SO: 5.4.1 (i) Determination of the dry density/moisture content relationship of granular soil (vibrating hammer method). (ii) Determination of the California Bearing Ratio. (iii) Determination of sand-geotextile frictional behaviour by direct shear. (iv) Determination of strength of aggregates. Additional Tests When directed, test all imported fill for compliance with specified limits on contamination to ensure that material is "clean" relative to the proposed end use. Propose and submit the specific criteria, schedule and timing of tests required to SO for acceptance. TS 237/1065 978 Doc D.2/307 (6) C02-030-01 Diaphragm Wall TS 238/1065 978 Doc D.2/308 1 GENERAL Read this Section with G01-010 "General Requirements" and all other contract documents 1.1 Scope This Section covers the requirements for the construction and installation of diaphragm walls as an embedded retaining wall type. Other types of embedded retaining walls are covered in: C02-030-02 Sheet Piling C02-030-03 Contiguous Bored Pile Walls and Secant Bored Pile Walls The walls may be used solely to form embedded retaining walls resisting principally horizontal loads, or to support vertical loads. 1.2 Related Sections Read this Section in conjunction with the relevant requirements of the following sections: 1.3 C01-020 Condition Survey C02-010 Ground Investigation C02-020 General Earthworks (Excavation and Filling) C02-050 Instrumentation and Monitoring C03-010 Concrete Construction Generally (including recycled material) C03-020 Reinforcement C04-030 Pile Testing Standards, Codes, Regulations and Technical References TS 239/1065 978 Doc D.2/309 1.3.1 Standards and Codes Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant requirements of the standards and codes listed below or referenced in the body of the Specification. Alternative standards and codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative standards and codes comply with the requirements of the standards specified. All standards and codes quoted are the current version, unless specific year references are noted. In the event that the standards or codes are partially superseded or have become obsolete, refer to the current edition or the approved substitution for the relevant clauses. Singapore Standards SS EN 1992-3 Eurocode 2: Design of concrete structures - Part 3: Liquid retaining and containment structures. SS EN 206 Concrete - Specification, Performance, Production and Conformity SS CP 79 Code of practice for safety management system for construction worksites SS 544-1 Concrete - Complementary Singapore Standard to SS EN 206 Part 1: Method of specifying and guidance for the specifier SS 544-2 Concrete - Complementary Singapore Standard to SS EN 206 Part 2: Specification for constituent materials and concrete Other Standards BS EN 1538 Execution of special geotechnical work - Diaphragm Walls BS EN 1008 Mixing water for concrete, specification for sampling, testing and assessing the suitability of water BS EN ISO 17660 Welding. Welding fof reinforcing steel. Load bearing welded joints BS 5228-1 Code of practice for noise and vibration control on construction and open sites - Part 1: Code of practice for basic information and procedures for noise and vibration control BS 5228 Code of practice for noise and vibration control on construction and open sites - Part 4: Code of practice for noise and vibration control applicable to piling operation BS 8002 Code of practice for earth retaining structures ISO 10414-1 Petroleum and natural gas industries - Field testing of drilling fluids Part 1: Water based fluids ISO 13500 Petroleum and natural gas industries - Drilling fluid materials Specifications and tests DIN 4126 Stability Analysis of Diaphragm Walls TS 240/1065 978 Doc D.2/310 1.3.2 Technical References Refer to the following technical reference for guidance in carrying out the Works: CIRIA C760 Guidance on embedded retaining wall design EFFC/DFI EFFC/DFI Guide to Tremie Concrete for Deep Foundations (2nd Edition, 2018) EFFC/DFI EFFC/DFI Guide to Support Fluids for Deep Foundations (1st Edition, 2019) API RP 13B-1 API Recommended Practice for Field Testing Water-based Drilling Fluids . . 1.4 Trade Preamble 1.4.1 Development of Design Requirements The notional design of the diaphragm wall works is indicated in the drawings, together with the construction sequence, schematic strutting or ground anchor system indicated in terms of the installation levels, the required stiffness and preloading. Based on the information provided, undertake and provide for the SOs acceptance the following which shall be carried out by appropriately qualified, competent and experienced personnel and PE: (a) Construction or design verification checks based on actual ground conditions to confirm the required penetration length for toe stability, horizontal and basal stability requirements, and the structural and geotechnical capacity. Size and provide all temporary or permanent propping elements and walers, ground improvement, where necessary, for improved horizontal restraint required for the diaphragm walls, and take into all necessary considerations that the required control on wall deflection can be achieved. (b) Prepare a response plan in the event that the temporary and or permanent strutting elements do not perform as expected in the design in controlling the wall deflection, and in the event that measures taken to control ground movement and vibration do not perform satisfactorily. Establish and indicate the alert levels and work suspension levels for forces and deflection of the diaphragm wall structure in the drawings. The response plan shall be feasible for timely implementation with due consideration of the construction sequence and site constraints. (c) Prepare and submit all design and construction sequence, including drawings and reviews that shall be endorsed by appropriately qualified, competent and experienced PE to the SO for his acceptance. Take into account the design requirements as set out in C02-030-01: Clause:2.1 in this Section. Submit the CV of the personnel and specialists where applicable to the SO for acceptance. TS 241/1065 978 Doc D.2/311 1.4.2 Layout Drawings Engage qualified and experienced personnel to prepare co-ordinated layout drawings for the diaphragm wall panels. Submit the drawings to SO for acceptance prior to commencing the installation works. 1.4.3 Co-ordination with Other Works Co-ordinate with other contractors who may carry out other works at the same time at the Site. Take account of site access, space occupation, safety and safeguarding of adjoining properties and each other’s works. 1.4.4 Upholding of Adjoining Properties Accept responsibility for the upholding of the adjoining buildings and roads, footpaths, etc., where applicable, together with the mains and services from the time of taking possession of the Site through the duration of the Works. Adequately maintain roads and footpaths within and adjacent to the Site and keep clear of mud and debris. 1.4.5 Verification of Site Information 1.4.5.1 Site Surveys Verify and be satisfied that the information given in the existing site survey plans provided are accurate. If necessary, engage a Registered Surveyor to carry out additional site survey before commencing any work. TS 242/1065 978 Doc D.2/312 1.4.5.2 Additional Site and Ground Investigation Carry out additional ground investigation where additional information is needed for the Works or when directed by the SO. Carry out the Works in compliance with Section C02-010 "Ground Investigation. The permeability, strength of the subsoils and the groundwater level are key parameters to be ascertained to determine the suitability of the execution method and equipment and the required penetration depth, and to ensure overall stability and seepage cut-off. Carry out the boreholes progressively, prior to commencement of the Works in areas, according to the Contractor’s construction programme. On completion of drilling, backfill the boreholes with a suitable bentonite/cement. Where rock is encountered, carry out sufficient number of boreholes before the panel excavation to establish the quality and grade of the rock for design and execution requirements. Where cavity is suspected from existing geological or published information in the area, e.g. in limestone, carry out adequate number of boreholes for sufficient information to carry out any pre-treatment works that are necessary before diaphragm wall installation commences. Submit the location and schedule for the boreholes to the SOs acceptance, prior to carrying out the Works. On completion, prepare the Site Investigation Report and submit to the SO for acceptance. 1.4.5.3 Groundwater level Verify the data on groundwater level from available ground investigation reports. Carry out additional water standpipes and piezometers if deemed necessary or as directed by the SO. 1.4.5.4 Contamination Verify information on contamination identified or believed to be present on site. In the event that contamination is either positively identified or suspected, draw to the attention of all personnel working on site together with the need to take any precautionary measures in handling contaminated materials, groundwater and obnoxious vapour from the ground. 1.4.6 Supervision of the Works Engage a qualified, competent and suitably experienced site engineer with the SOs acceptance, to supervise the field works. Information on items to be checked or requiring monitoring during construction shall be clearly identified and made known to the supervising personnel. Site Supervision Plan (SSP) for supervision of the structural and geotechnical building works shall be prepared and submitted by qualified, competent and experienced PEs to the relevant authorities, and in accordance with the current guidelines issued under the Building Control Act and Regulations. TS 243/1065 978 Doc D.2/313 1.4.7 Quality Control Plan Submit and work to a quality control plan as agreed with the SO. Refer to G01-010: Clause 1.4.7. 1.5 Definitions and Abbreviations 1.5.1 Definitions 1.5.1.1 Accredited Testing Laboratory An organisation or laboratory accredited under the SAC-SINGLAS to carry out tests required by the Specification. 1.5.1.2 cement Include all mineral admixtures such as PFA, GGBS, silica fume, etc. that have cementitious properties as in SS EN 197-1. 1.5.1.3 obstructions Include concrete, reinforced concrete, solid brickwork, sheet piles and the like of man-made object, met during drilling, but excluding those met on the surface of the ground 1.5.2 Abbreviations No item. 2 PERFORMANCE REQUIREMENTS 2.1 Verification of Performance during Execution When carrying out the performance verification as set out in C02-030-01: Clause:1.4.1, take into account the following considerations. TS 244/1065 978 Doc D.2/314 2.1.1 Wall Movements The required size of diaphragm wall system is shown on the drawings, including the wall penetration depth and the size of all permanent supports. A schematic temporary propping system indicated in terms of the installation levels, the required stiffness and preloading are also shown in the drawings, where applicable. Based on the actual ground condition encountered, verify the wall penetration depth and the adequacy of diaphragm wall system as indicated in the drawings and in accordance with SS EN 1997. The diaphragm wall movements shall be checked and reviewed throughout the execution to ensure that the wall movements are within the allowable limits as specified or indicated in the drawings and in accordance to the requirements of the relevant authorities. The diaphragm walls shall withstand all loads on it, including those due to hydrostatic pressure, earth pressure, surcharge loads, overburden, effects of surrounding properties and varying load conditions due to different stages of construction. Check that the application of partial factors assumed in the design and control on wall movement are verified by taking into account the construction effects and field performance of the intended temporary supporting system. The verification shall be in accordance with SS EN 1997. Check that the ultimate limit states (ULS) shall not be exceeded when appropriate load combinations and partial factors are applied in accordance with SS EN 1997. In addition, control of wall deflection shall also satisfy serviceability limit states (SLS) and the requirements of Building Control Authority The verification of performance shall be in accordance with SS EN 1997 and SS EN 1992 as appropriate when the diaphragm wall is used as water retaining structure. [Note 1: Refer to CIRIA 760 on the use of appropriate factors for permanent and temporary works in selecting the diaphragm wall section.] [Note 2: Temporary and permanent works shall be treated with equal importance and shall be well coordinated without ambiguity at all stages of design and construction. When an observational approach is adopted, a highly co-ordinated site team would need to be employed, and clearlydefined protocols for decision-making and monitoring requirements would have to be in place before construction commences.] 2.1.2 Embedment for Load Bearing If the diaphragm walls are also used for vertical load bearing purposes, verify the required embedment length, taking into account the actual ground conditions and the results of load tests of preliminary elements. 2.2 Use of Support Fluid Where support fluid is used, fulfill the following requirements: (a) Provide continuous support of the excavation. (b) Do not form a thick filter cake layer prior to concreting. (c) Have the ability to keep solid particles in suspension. (d) Be capable of being easily displaced and the interface layer remains on the top of the rising concrete during concreting. TS 245/1065 978 Doc D.2/315 (e) Limit the penetration of support fluid into the surrounding soil. (f) Does not pollute the ground and groundwater at all stages. (g) Does not coat the reinforcement such as to impair the bond between the reinforcement and concrete. Bentonite, polymer or a mixture of bentonite and polymer support fluids may be considered for these requirements. Testing of support fluid shall be carried out to demonstrate compliance of limits as specified in BS EN 1536 or ICE specification for piling and embedded retaining walls if applicable, or European Federation of Foundation Contractors and Deep Foundations Institute (EFFC/DFI) Guide to Support Fluids for Deep Foundations, or the manufacturer’s instructions shall be complied with, as appropriate. 2.3 Watertightness Take all necessary measures to ensure that the walls formed are substantially watertight, that is, free from running or percolating water or seepage water. Seal all damp patches. When total damp patches exposed on the excavated face of the wall exceeds 10% of the visible area or any individual damp patch is found to be more than 4 m2, repair works shall be carried out. [Note 1: For guidance, refer to BS 8102 "Code of Practice for protection of below ground structures against water from the ground", Table 2; and B1.9 of ICE "Specification for Piling and Embedded Retaining Walls", 3rd Edition.] 3 MATERIALS 3.1 Source of Materials Do not change sources of supply until it has been demonstrated that the materials from the new source can meet all the requirements of this Specification. Remove from site any materials that fail to comply with this Specification. 3.2 Support Fluid 3.2.1 Bentonite 3.2.1.1 Source Bentonite supplied to the Site shall comply with BS EN 1538. TS 246/1065 978 Doc D.2/316 3.2.1.2 Performance of Bentonite Slurry Include proportion of bentonite in the slurry by taking into account the rheological properties of the bentonite such that the slurry is sufficient to maintain the stability of the excavation in the ground conditions encountered. The density and lowest head of slurry above ground water shall together be such as to ensure the stability of the trench excavations throughout its entire depth. 3.2.1.3 Use Use in accordance with the manufacturer’s instructions unless there is a demonstrable reason to do otherwise. 3.2.1.4 Mixing Mix bentonite powder thoroughly into the water by a suitable high shearing action mixer until all lumps have been broken up and dispersed within the mix, to make a suspension which will maintain the stability of the panel excavation for the period necessary to place concrete and complete construction. Where saline or chemically contaminated groundwater occurs, take special precautions to modify the bentonite suspension or pre-hydrate the bentonite in fresh water so as to render it suitable in all respects for the construction. 3.2.1.5 Quality Control of Bentonite If bentonite is used, in any 100 tonnes of bentonite supply, moisture content shall not deviate more than ±2%. Residue of diameter greater than 75 µm shall not exceed 4%. Bentonite slurry properties obtained at the recommended dosage by the manufacturer/ supplier shall conform to Tables 1 and 2 of BS EN 1538. 3.2.1.6 Reuse of Bentonite Upon reuse, the density, maximum sand content and pH of bentonite shall to comply with the criteria as set out in Tables 1 and 2 of BS 1538. 3.2.1.7 Storage Store solid additives in separate waterproof stores or containers which will prevent the materials from becoming contaminated. Store bentonite in dry cool conditions. Take particular care with bulk storage to prevent balling together of bentonite powder due to dampness, or deterioration of properties due to dampness and heat. TS 247/1065 978 Doc D.2/317 3.2.1.8 Testing Allow for one sample of bentonite powder per panel to be tested under the same conditions as those under which testing was carried out by the supplier or manufacturer, at the date on which work commences on the panel. [Note 1: Refer to EFFC/DFI, Guide to Support Fluids for Deep Foundations.] 3.2.2 Alternative Materials If alternative drilling fluid such as polymer is to be used in lieu of bentonite, submit proposals for the additional or alternative ingredients and admixtures to the support fluid for the SOs acceptance. These proposals should include samples and full details, including the supplier and manufacturer of such ingredients. Any such materials must not detrimentally affect the concreting, or formed concrete. Comply with ISO 13500. Polymers can be used as the main component for support fluid or as additives to bentonite to improve their rheological properties. Different type of polymer exists, ranging from natural gums, cellulose modified and synthetic high molecular weight polymers (PHPA - partially hydrolysed polyacrylamide). Use of polymer fluid should rely on the Contractor’s experience and recommendation based on past experience on similar ground conditions or by performing a trial trench test to confirm support fluid characteristics and performance suitable to the specific project and to ensure trench stability during panel excavation. Testing of polymer solution shall conform to ISO 10414-1. 3.3 Water Water shall be clean and free from harmful matter in solution or suspension. If taken from a source other than the Public Utilities Board, water shall be tested in accordance with SS EN 206. 3.3.1 Water for Mixing Bentonite Water used for dispersion of bentonite shall be as nearly neutral in pH as practicable. Saline water or water contaminated by salts shall not be used unless tests are performed to show compliance with bentonite slurry performance, as required in BS EN 1538. 3.4 Concrete General requirements of concrete and constituent materials shall refer to SS EN 206, SS 544 Part 1 and SS 544 Part 2. In particular for specific diaphragm wall concrete shall additionally refer to Annex D of SS EN 206. The concrete mix design shall satisfy the specification of concrete and shall take into account the following: (a) the need for a high resistance against segregation (b) the need for adequate plasticity and good cohesiveness TS 248/1065 978 Doc D.2/318 (c) the need to flow well (d) the need to be able to compact adequately by gravity (e) the need of sufficient workability retention for the duration of the placement procedure (f) the need of a concrete final set within 20 hours. In order to minimise segregation, aggregates should be continuously graded. The specified upper value of aggregate size, Dupper shall not exceed 32 mm and -¼ of the clear space between the longitudinal bars. 3.4.1 3.4.2 Minimum Fines and Cement Content (a) The minimum cement content for any mix shall be 325kg/m³. (b) For concrete placed by tremie tube, this value shall be 380kg/m³ for a Dmax of 20 mm. (c) Where the concrete is exposed to sea water, it shall follow the requirements of SS 544- 1 and 544-2 for resisting the specified exposure class. (d) Sand content (D ≤ 4mm) shall be greater than 40% by mass of the total aggregate. (e) Fines ((D ≤ 0.125mm) shall be between 400 kg/m3 to 550 kg/m3 in the concrete (including cement and other fine materials). Water and Cement Ratio The specified maximum water and cement ratio shall not be greater than that given in the provisions valid in the place of use for resisting the specified exposure classes, and 0.60, whichever is the lower value. [Note 1: Refer to SS EN 206, Annex D on additional requirements for concrete to be used in diaphragm walls.] 3.4.3 Fresh concrete TS 249/1065 978 Doc D.2/319 3.4.3.1 Consistency Slump or slump flow measured at the time of discharge shall be in accordance with the standards shown in Table 1, unless otherwise accepted by the SO. Do not use a concrete pump to place tremie concrete directly into the pile shaft unless approved by the SO. Table 1. Slump and slump flow at time of discharge according to Standards Class of Workability Target Slump Flow BS EN 12350-8 mm Slump BS EN 12350-2 Minimum (mm) Maximum (mm) Typical Condition of Use A Not applicable 120 180 Placed into water-free B 450±50 (*) 180 240 Where concrete is to be placed by tremie under drilling fluid or water * Unless otherwise accepted, depending on special features with the approval of the SO. 3.4.3.2 Workability Retention Retention of specified properties of fresh concrete, such as slump and slump flow, for a specified duration of time. The workability retention should be 3 hours minimum with an absolute minimum slump limit of 160 mm at 3 hours or equivalent consistency using a slump flow. 3.4.3.3 Stability The stability of concrete is defined by the resistance of a concrete to segregation, bleeding and filtration. This is quantified primarily based on bleeding and filtration tests. The stability tests in the EFFC/DFI guide are in Table 2 below: Table 2. Stability tests in EFFC/DFI guide . 3.4.3.4 Specified Range Tolerance Observation Bleeding ≤ 0.10 ml/min + 0.02 ml/min . VSI 0 - Mandatory if Slump Flow Filtration ≤ 22 ml +3 ml . Static Segregation ≤ 10% +2% . Apparent Viscosity Using the inverted test or modified cone outflow test as defined in the EFFC guide. The recommended range is 2 sec to 7 sec. TS 250/1065 978 Doc D.2/320 3.5 Additions and Admixtures Additions and admixtures when used in the concrete mix shall comply with SS EN 206. 3.6 Backfill Materials Use granular fill or lean mix concrete as backfill above any cut-off level for structural concrete and take to the ground level. Unless otherwise directed, backfill not less than 24 hours and not more 3 days after placing of concrete in the diaphragm wall panel. 3.7 Reinforcement For general requirements of reinforcement, refer to Section C03-020: Clause:3. The steel elements used in the diaphragm walls shall comply with SS EN 10080. 4 WORKMANSHIP 4.1 Continuous Construction Unless otherwise accepted by the SO, carry out the construction of panels, including corner panels to be continuous once excavation has commenced. Provide measures to prevent the formation of bentonite cake. Minimise the time panels stay open at night or during weekends. In the event of unavoidable circumstances when the panels need to stay open, get the prior approval of the SO with a method statement stating the protection measures adopted. [Note : Refer to EFFC/DFI, Guide to Support Fluids for Deep Foundations and EFFC/DFI, Guide to Tremie Concrete for Deep Foundations.] 4.2 Length of Panel Plan and submit in method statements, the length of the panels to be concreted to the acceptance of the SO. Consider shorter panel length to minimise ground movement where necessary. 4.3 Ground Movement Monitoring Carry out surveys and monitoring of movement and vibration in adjacent structures and services in the course of the Works in accordance with accepted method proposals. 4.4 Guide Walls Design and construct these elements taking into account the actual site and ground conditions and the equipment to be used on site to ensure stability. Design the guidewalls for the vertical and horizontal loads specific to the project. Construct the walls in reinforced concrete or other suitable material, to a minimum depth of 1 m. TS 251/1065 978 Doc D.2/321 4.5 Void Formers Obtain approval of the size, type and position of all void formers, inserts and connectors before work proceeds. Unless otherwise specified or approved, form all void formers and all inserts and connectors cast in at the time of concreting the panel. All void formers, inserts and connectors shall be formed to minimise obstruction to the free flow of concrete. Co-ordinate and adjust the lengths and layout of the panels so that no single void former or block-out will straddle 2 adjacent panels. 4.6 Stability of Excavation Using Support Fluid Where the use of support fluid is accepted for maintaining the stability of a trench, maintain the level of the fluid in the excavation so that the fluid pressure always exceeds the pressures exerted by the soils and external groundwater with adequate factor of safety to ensure stability of the strata near ground. Always maintain slurry level above the level assumed in the approved trench stability calculations and above the bottom of the guide wall. Maintain the fluid level at a level not less than 1.5 m above the level of the external groundwater, unless it can be demonstrated that a lower level provides adequate stability and controls ground movements to an acceptable level. Allow a freeboard of minimum 20 cm between the slurry to top of the guide wall. Maintain availability for immediate use, a sufficient quantity of slurry to allow for any sudden loss. Should the loss continue despite the addition of the slurry and the stability of the trench be placed at risk, immediately advise the SO and take such immediate remedial action (backfill with LSS or lean mix concrete) as is necessary to preserve the stability of the trench and ensure the safety of neighbouring structures and services. In the event of a rapid loss of bentonite suspension from the excavation, backfill the excavation without delay and inform the SO immediately. Obtain consent from the SO before resumption of the excavation. Remove support fluid wholly or partially and replace while maintaining the required fluid head if it does not meet all requirements prior to concreting. 4.7 Cleanliness of the Base Clean the base of the excavation of as much loose, disturbed and remoulded material to the satisfaction of the SO prior to placing steel or concrete. 4.8 Spillage and Disposal Take all reasonable steps to prevent the spillage of bentonite suspension on the site in areas outside the immediate vicinity of boring. Remove discarded or contaminated bentonite from the Site without delay. Dispose of the bentonite in compliance with the by-laws and regulations of the appropriate authority. 4.9 Reinforcement TS 252/1065 978 Doc D.2/322 4.9.1 Cages and minimum space requirements Diaphragm wall cages are lowered in the trenches supported by slurry made of bentonite and to be finally tremie concreted. Minimum clear spacing between vertical bars and horizontal bars in all directions inside the cage must be provided. This aspect must be considered during the design in order to achieve proper flow of tremie concrete and ensure no honeycomb is formed and quality of concrete is not compromised. The clear spacing requirements shall comply with BS EN 1538, Clause 7.5. 4.9.2 Fixing (a) Keep the number of joints in the longitudinal bars to a minimum. (b) Arrange the joints such that the full strength of each bar is effective. (c) The reinforcement cages shall be sufficiently rigid to enable them to be handled, lifted, placed and concreted without damage. (d) The reinforcement shall be adequately fixed to avoid damage and/or displacement during handling and lifting operations. (e) Incorporate distance spacers of an accepted type, which shall be capable of resisting deformation during cage placement within the trench and which shall not entrap slurry during concreting, in the cage construction to maintain the minimum specified cover during concreting. Ensure the location of lifting points and design of lifting lugs is acceptable to the SO. Take special care to ensure adequate lapping length is provided for all the corner panels and when there is more than 1 reinforcement cage within a single panel. 4.9.3 Welding Welding shall be in accordance with BS ISO 17660-2 and BS EN ISO 17760-1. Do not use welding of cold worked high tensile reinforcement bars as a method of splicing cages. Welding of hot rolled high tensile steel bars shall be permitted provided a method is used which shall not adversely affect the properties of the bars. 4.9.4 Marking Mark the front and rear of cages following fabrication to identify them during placement. Paint lifting points with contrasting colour from the main reinforcement for ease of identification. TS 253/1065 978 Doc D.2/323 4.9.5 Placing Lower the steel reinforcement accurately into position with sufficient spacer blocks to ensure the correct cover is maintained at all times. Check spacer blocks are of suitable durability. Allow a vertical tolerance of ±50 mm on the level of the reinforcement projecting above the cut-off level. 4.10 Concreting Refer to the Section C03-010: Clause:4 and Section C03-020: Clause:4 for general concreting requirements. 4.10.1 Placing Concrete Engage a method of placing and the workability of the concrete such that a continuous monolithic concrete panel of the full cross-section is formed. Place the concrete without such interruption as would allow the workability of the previously placed batch to have deteriorated significantly. Ensure the method of placing is accepted by the SO. If necessary, incorporate an accepted set retarding additive into the mix in order to ensure extended workability of the concrete after placement. Take all precautions in the design of the mix and placing of the concrete to avoid arching of the concrete in forming the diaphragm wall Prevent contamination of the concrete by spoil, liquid or other foreign matter. 4.10.2 Workability of Concrete Refer to Section C02-30-01: Clause:3.4 for workability of concrete. Slump measured at the time of discharge into the diaphragm wall trench or at the time of discharge into the concrete pump hopper shall be in accordance with the requirements stated in BS EN 1538, SS EN 206 and SS 544 Part 1 and SS 544 Part 2. Refer to SS EN 206, Annex D for specific diaphragm wall concrete. Also refer to Section C02-030-01: Clause:3.4.3. 4.10.3 Compaction Do not use internal vibrators to compact concrete in the wall panels as this will lead to segregation. TS 254/1065 978 Doc D.2/324 4.10.4 Placing Concrete Under Water or Under Drilling Fluid Place concrete under water or drilling fluid using a tremie concrete pipe. Do not engage alternative methods of underwater placement such as the use of a drop bottom bucket or hose from a concrete pump unless otherwise accepted. Do not discharge concrete freely into the water or drilling fluid. Before placing the concrete, propose a method that is acceptable to the SO, such that there is no accumulation of silt or other material at the base of the trench or boring, and that heavily contaminated drilling fluid suspension, which could impair the free flow of concrete from the pipe of the tremie has not accumulated at the bottom of the trench or hole. Take a sample of the drilling fluid suspension from the top and the base of the trench or boring using an accepted sampling device. If the specific gravity of the suspension exceeds 1.15 or does not comply in any respect with the stated limits for the particular material, do not proceed with the placing of concrete. In this event, modify or replace the drilling fluid as agreed to meet the Specification. 4.10.4.1 Tremie Equipment Check that the hopper and pipe of the tremie is clean and watertight throughout. Extend the pipe to the base of the trench or boring and place a sliding plug or barrier in the pipe to prevent direct contact between the first charge of concrete in the pipe of the tremie and the water or drilling fluid. If the plug or barrier is sacrificial, do not retain it in the mass of the concrete. 4.10.4.2 Tremie Procedure The tremie pipe after the initial pour shall at all times penetrate the concrete, which has previously been placed with a maximum embedment of 6 m and a minimum embedment of 3 m, and shall not be withdrawn from the concrete until completion of concreting. Develop a system of level checks for the concrete and pipe outlet to ensure that this requirement is met. At all times, maintain a sufficient quantity of concrete within the pipe to ensure that the pressure from it exceeds that from the water or drilling fluid. The internal diameter of the tremie pipe shall be of sufficient size to ensure easy flow of concrete. The number of tremie pipes per panel is to be acceptable to the SO. Where more than one tremie pipe is employed during concrete pouring to any one panel, arrange the charging of concrete in the pipes so that the difference in concrete level at each pipe position is not greater than 250 mm. Confirm this level by soundings taken during the concrete pour. 4.10.4.3 Delay in Concreting Operation Should a delay or breakdown occur during the concreting operation, which in the opinion of the SO could cause a cold joint, entrapment of laitance in the tremie concrete or otherwise lead to defective concrete, abandon the concrete placing. Ensure that an adequate supply of concrete to the tremie is available at all times so that placement is continuous. TS 255/1065 978 Doc D.2/325 4.10.5 Finished Level Cast concrete to such a level that only sound concrete remains below the cut-off levels. Cut down concrete cast above the levels shown in the Drawings to within a tolerance of +0.1 m, -0.0 m. If the cut-off level is more than 1 m below the top of the guide walls, bring the concrete to 0.5 m above the cut-off level, ±150 mm. 4.11 Stop Ends 4.11.1 General Check that stop ends, inserted before placement of concrete in the panel, are clean and have a smooth regular surface. Ensure any shutter release agent is to the acceptance of the SO. Where stop ends are inserted in sections, provide adequate joint connections to ensure verticality of the complete tube. 4.11.2 Extraction Carry out the extraction of stop ends at such a time and in such a manner as to avoid any damage to the concrete placed against them, or to the adjacent soil and structures. 4.12 Joints Where concrete is cast against previously completed wall panels, clean the previously formed concrete so that solid substances are removed before the joint is formed. When the diaphragm wall joint is exposed upon subsequent excavation, repair all joints that permit jetting, spraying or water leakage. 4.13 Exposed Panels Where diaphragm wall panels are exposed within the structure, thoroughly clean the exposed surface to remove all traces of bentonite, soil, or other contaminating material so as to expose only sound concrete material. Apply this requirement irrespective of whether or not the exposed panel is to be subsequently covered by in-situ concrete. 4.14 Tolerances 4.14.1 Setting Out Establish all lines, levels and be responsible for the correct positions of all panels. Carry out setting out from the main grid lines of the proposed structure. Immediately before installation of the diaphragm wall, mark the element positions with suitable identifiable pins or markers. TS 256/1065 978 Doc D.2/326 4.14.2 Construction Tolerances The impact of construction tolerances for rebars, couplers and inserts must be considered in the design of the diaphragm wall. 4.14.2.1 Distance Between Guide Walls Achieve the following tolerances: (a) Minimum distance: the diaphragm wall thickness plus 25 mm (b) Maximum distance: the diaphragm wall thickness plus 50 mm Prop the guide walls as necessary to maintain these tolerances during the course of construction of the Works. Check that the reference line, on the face of the guide wall towards the trench and on the side of the trench nearest to the subsequent excavation, does not vary from a straight line or specified profile by more than ±6 mm in any 5 m wall length and shall be maintained so that there is no abrupt change. 4.14.2.2 Profile of Excavated Trench Measure the profile of each excavated trench to check the trench dimensions as excavation proceeds and to ensure the verticality of the trenching equipment meet the construction tolerance on verticality. Submit records of dimensions of profile to the SO. 4.14.2.3 Exposed Wall Face Achieve the verticality of the plane of the wall face to be exposed to within a tolerance of 1 in 200. Allow a further 75 mm horizontally for local protrusions beyond the wall face, resulting from irregularities in the ground excavated. 4.14.2.4 Recesses and Inserts Position recesses and inserts formed within the wall to the following horizontal and vertical tolerances: 4.14.2.5 (a) Recesses located at a depth of up to 15 m below the top of the guide walls: ±100 mm (b) Recesses located at depths in excess of 15 m: ±150 mm Positioning Reinforcement Achieve the tolerances in positioning reinforcement as follows: (a) Longitudinal tolerance at cage head measured along trench: ±75 mm. (b) Vertical tolerance at cage head in relation to top of guide wall: ±50 mm. TS 257/1065 978 Doc D.2/327 (c) 4.14.2.6 A minimum cover to reinforcement of 75 mm shall be maintained. Block-outs Position block-outs for penetrations, recesses and inserts formed within the walls within the tolerances given in Section C02-030-01: Clause:4.14.2.4. 4.14.2.7 Remedial Measures If during the general excavation, it is detected that the above stated tolerances have been exceeded, submit proposals for remedying the defects for the acceptance of the SO. In addition, the SO may require an amended method statement to be submitted for acceptance for further construction of the diaphragm walls. 5 VERIFICATION AND SUBMISSIONS 5.1 Submissions 5.1.1 Method Statement Prior to commencement of the Works, submit a method statement for the proposed method of installation to achieve the required performance, including: (a) All details of proposed plant and trench excavation equipment (b) The sequence of excavation and concreting of panels (c) Dimensions and details of guide walls (d) Dimensions of walls and lengths of panels - the formation of joints between panels, method of installation of waterstop between joints, the type, source, chemical and physical properties of the waterstop blade between the joints and details of sealing joints to comply with Section C02-030-01:Clause:4.12. (e) Details and properties of support fluid - the mixing, transporting and placing equipment for the bentonite slurry (f) The cleaning and reuse of bentonite slurry (g) The type, source, chemical and physical properties of the drilling fluid to be used. (h) Calculations to show that the density of the bentonite and lowest head of slurry are sufficient to maintain the stability of the trench, in the ground conditions envisaged, to its entire length (i) The method of disposal of contaminated bentonite slurry (j) Method of handling and placing reinforcement cages TS 258/1065 978 Doc D.2/328 5.1.1.1 (k) Method of forming block-outs for penetrations, recesses, inserts, starter bars (l) Details of spacers to be used on reinforcement cage (m) Details of concrete and grout mixes and method of concreting and grouting (n) Details of specialists used for grouting (o) The method of monitoring and checking the tolerances associated with the diaphragm wall panels (p) The method used to check verticality of trench (q) The method of monitoring and checking the stability of the diaphragm wall trench (r) The method of monitoring and checking the stability of neighbouring properties, highways, services and other underground structures (s) All details of proposed monitoring equipment - the names of the specialist land surveyor and instrumentation contractors to be engaged (t) Programme for the Works, including details of the manpower and equipment to be employed (u) Staff organisation chart and curricula vitae of key personnel to be employed on the Works, indicating whether they are to be part-time or full-time Walls Designed to Support Vertical Loads For walls which have been designed to support vertical loads, provide additional information as follows: (a) The method to overcome trench excavation in bearing stratum and founding level requirements. (b) Ultimate load tests with adequate instrumentation on individual bored piles or barrette piles to be conducted to verify the foundation design parameters adopted for the diaphragm wall vertical load carrying capacity. (c) Shaft grouting if required to improve the skin friction characteristics, details such as grouting pipes, grids, grouting pressure to be submitted through a method statement to the approval of the SO. The design parameters shall be established through ultimate load tests or panels required to be socketed into rock, the method to ensure the required rock socketing length, including additional site investigation to check the rockhead quality by a minimum of 3.0 m coring below the founding level. (d) The method to clean the wall base. TS 259/1065 978 Doc D.2/329 (e) 5.1.2 Base grouting at the bottom of the trench if required shall be supported by a method statement to the approval of the SO. Parameters such as limiting grouting pressure and grouting volume shall be clearly stated in the method statement and the construction drawing. Shop Drawings Submit shop drawings of the diaphragm walls and related works for the acceptance of the SO prior to the commencement of works. The drawings shall include the following: 5.1.3 (a) Layout of diaphragm walls, and guide walls with suitable survey co-ordinates and dimensions (b) Sequence of construction of wall panels, including relevant sections (c) Details of stop ends, including details of waterproofing with water stops or other proprietary products (d) Reinforcement details of wall panels, including spacers, steel bracing, etc. (e) Sizes and locations of block-outs for penetrations, recess, inserts, starter bars, etc. Verification of Bentonite Provide a certificate from the manufacturer of the bentonite powder, showing the properties of each consignment delivered to the Site. Take samples so that at least one test is carried out for every 100 tonnes of bentonite supplied. Carry out tests to provide the following information: 5.1.4 (a) Apparent viscosity and gel strength of a suspension of bentonite in water (b) Moisture content of the bentonite powder and wet screen residue on US 200 mesh sieve (c) A statement of the conditions of test, such as water analysis, mixer type, mixer speed during testing, time of stirring and time of testing after initial addition of bentonite to the water Bentonite Mixing Equipment Submit a suitable design of hopper cone and bentonite feeding device for acceptance by the SO. 5.1.5 Quality Control Plan Prepare and submit the quality control plan for SOs acceptance prior to starting work. TS 260/1065 978 Doc D.2/330 5.2 Testing For applicable testing and frequency of tests, follow EFFC/DFI, Guide to Support Fluids for Deep Foundations, as shown below: Table 3. Applicable tests and minimum frequency for bentonite support fluids Test method Fresh fluid Excavation fluid Before concreting Frequency . daily Once per element Before pour daily Viscosity Marsh funnel M R M M Density Mud balance M R M M Sand content Sand content kit N/A R M R pH pH paper M R M R Filter loss API press filter M R M M Filter cake thickness API press filter M R M M Silt content Calculation N/A N/A O O Gel strength Fan viscometer O N/A O O Test Fluid for reuse M: Mandatory, R: Recommended, O: Optional, N/A: Not Applicable 5.2.1 Compliance Testing of Support Fluid 5.2.1.1 Frequency of Testing Propose the frequency of testing drilling fluid, and the method and procedure of sampling prior to the commencement of the Work. The frequency may subsequently be varied as required, depending on the consistency of the results obtained. Measure density, Marsh viscosity, pH, filtrate and cake of freshly mixed support fluid, daily, as a check on the quality of the suspension being formed. Calibrate the measuring device to read to with 0.01 g/ml. 5.2.1.2 Batch Testing Carry out tests to determine the density, viscosity, filtrate, cake and pH value to each batch of freshly mixed or reconditioned bentonite supplied to the Works and submit the results before the batch is used in excavations. For average soil conditions, the results shall generally comply with BS EN 1538, Tables 1 and 2. Carry out the tests until a consistent working pattern has been established, taking account of the mixing process, any blending of freshly mixed bentonite suspension and previously used bentonite suspension and any process which may be used to remove impurities from previously used bentonite suspension. Shear strength test and range values shall be specified when ground conditions are such that support fluid loss and penetration can affect trench stability. Refer to DIN 4126. TS 261/1065 978 Doc D.2/331 5.2.1.3 Alternative drilling fluid For testing drilling fluid in lieu of bentonite, test in accordance with API-RP-13B-1 unless otherwise agreed or directed by the SO. 5.2.1.4 Testing from Excavation Take at least 1 sample of fluid from the base of the excavation and 1 from the top, immediately prior to placing reinforcement and concrete. Comply with values recommended in BS EN 1538, Table 2 for bentonite. 5.2.1.5 Limits Prior to Concreting Measure the density, viscosity together with sand content and filter press determinations from a sample taken at the base of the trench immediately before concreting. Ensure conformance to BS EN 1538, Table 2. Take a full range of tests when additional wall support materials, e.g. polymer are added to the slurry. Change the slurry, as directed by the SO, if a sample obtained from near the bottom of the trench indicates possibility of undue contamination by the bentonite. 5.2.1.6 Testing Laboratory Establish a suitably equipped and maintained site laboratory for testing the support fluid. Provide skilled staff and all necessary apparatus to carry out the sampling and testing. 5.2.1.7 Equipment Ensure the test equipment employed comply with accepted standards. Additional or alternative equipment may be employed with the acceptance of the SO. 5.2.1.8 Rate of Sampling Obtain samples from the panel during excavation and allow for one sampling per 5 m depth or per each change of soil type as determined by the SO. 5.2.1.9 Monitoring pH Levels Monitor the pH values when additives are added. 5.2.1.10 Alternative Materials Test alternative materials in lieu of bentonite where appropriate, or propose alternative tests to demonstrate the required properties. Ensure that storage conditions are as recommended by the supplier of the material. TS 262/1065 978 Doc D.2/332 5.2.2 Concrete Cube Testing Refer to the Section C03-010: Clause:5.1 for concrete cube testing requirements. Take test cubes for each panel constructed. Check that cubes have the same marks as the wall panel numbers and are sub-marked within each panel set. 5.3 Verification of Load Carrying Capacity Carry out load testing to verify the structural and geotechnical load carrying capacity of diaphragm walls if the wall panels are used as piles or deep foundations. Refer to Section C04-030: Clause:4.3, for details of pile test requirements. 5.4 Records and Reports 5.4.1 Records Keep the following records for each wall panel and make such records available for inspection by the SO within 24 hours of the completion of each panel. (a) Panel Number (b) Date and time of start and of finish of panel excavation (c) Details of any obstructions encountered and the time spent in dealing with obstructions (d) A log of soil type encountered from start to finish of excavation and water levels (e) Date, place and time of slurry control tests and results recorded (f) Quantity of slurry removed from site and spoil removed from site recorded by date (g) The trench verticality and profile of panel (h) Length of panel and width and depth of panel from top of guide wall level (i) Date and time of completion of cage placement. Details of cage type for reinforcement (j) Date and time of start and of completion of panel concreting (k) A graph of theoretical and placed concrete volumes with depth (l) Volume of concrete used and time of any interruptions recorded in concrete supply where these exceed 15 minutes. Volumes of normal and lean mix concrete (m) Cut-off level of concrete below top of guide wall level TS 263/1065 978 Doc D.2/333 (n) 5.4.2 Concrete test cubes, markings, date and results obtained on testing Grouting Records Provide duplicate records within 24 hours of completion of grouting, showing the following: 5.4.3 (a) Panel identification (b) Date (c) Leakage test (d) Records of pressure and uplift (e) Total uplift (f) Grout test results As-Built Drawings Keep and submit accurate records of the actual Works constructed. For those parts of the Works which will become hidden by further progress, check and verify such records while those parts of the Works are open for inspection. All drawings submitted are to have relevant particulars at the bottom right-hand corner, including the project title, Contractor's name, title of drawing, scale, date, drawing number and notes identifying revisions made. Other details to be included in the as-built drawings are as follows: (a) Diaphragm wall layout plan showing the panel size and the actual positions and eccentricities in perpendicular directions of the diaphragm walls at ground level. (b) Elevation view of the length of panel installed from cut-off level to toe of panel associated with the soil stratum and water level encountered. Cut-off level for each panel shall be expressed as reduced levels. (c) Reinforcement details of installed panels and capping beams where relevant, and grade of concrete used. TS 264/1065 978 Doc D.2/334 (7) C02-030-02 Sheet Pilling TS 265/1065 978 Doc D.2/335 1 GENERAL Read this Section with G01-010 "General Requirements" and all other contract documents. 1.1 Scope This Section covers requirements for construction or installation of sheet piling as an embedded retaining wall type to resist principally horizontal loads, or also to support vertical loads. Other types of embedded retaining walls are covered under the following sections: C02030-01 Diaphragm Wall C02-030-03 Contiguous Bored Pile Walls and Secant Pile Walls 1.2 Related Sections Read this Section in conjunction with the relevant requirements of the following sections: 1.3 C01-020 Condition Survey C02-010 Ground Investigation C02-020 General Earthworks (Excavation and Filling) C02-050 Instrumentation and Monitoring C05-010 Structural Steelwork C05-020 Protective Works for Structural Steelwork Standards, Codes, Regulations and Technical References TS 266/1065 978 Doc D.2/336 1.3.1 Standards and Codes Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant requirements of the standards and codes listed below or referenced in the body of the Specification. Alternative standards and codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative standards and codes comply with the requirements of the standards specified. All standards and codes quoted are the current version, unless specific year references are noted. In the event that the standards or codes are partially superseded or have become obsolete, refer to the current edition or the approved substitution for the relevant clauses. Singapore Standards SS EN 1993 Eurocode 3 - Design of steel structures - Part 5:Piling NA to SS EN 1993 - 5 Singapore National Annex to Eurocode 3 - Design of steel structures Piling SS EN 1997 Eurocode 7: Geotechnical Design - Part 1: General Rules Eurocode 7: Geotechnical Design - Part 2: Ground Investigation and Testing NA to SS EN 1997 - 1 Singapore National Annex to Eurocode 7: Geotechnical design General rules NA to SS EN 1997 - 2 Singapore National Annex to Eurocode 7: Geotechnical design Ground investigation and testing . . Other Standards BS EN 12063 1.3.2 Execution of special geotechnical works. Sheet pile walls. BS EN 12699 Execution of special geotechnical works. Displacement piles. BS EN 10025 Hot rolled products of structural steels. BS EN 1011-1 Welding - Recommendations for welding of metallic materials - Part 1: General guidance for arc welding BS EN 1011-2 Welding - Recommendations for welding of metallic materials - Part 3: Arc welding of ferritic steels BS EN ISO 9606-1 Qualification testing of weldersFusion weldingPart 1:Steels BS EN ISO 2409 Paints and varnishes - Cross-cut test BS 5228 Code of practice for noise and vibration control on construction and open sites - Part 1: Noise Code of practice for noise and vibration control on construction and open sites - Part 2: Vibration BS 7079 Part A1: Surface Finish of Blast Cleaned Steel for Painting and Steel Structures Technical References Refer to the following technical reference for guidance in carrying out the Works. (a) LTA Code of practice for Railway Protection (2004) TS 267/1065 978 Doc D.2/337 (b) LTA Guide to carrying out restricted activities within Railway Protection and Safety Zones (2009) (c) LTA Guide to carrying out engineering works within road structure safety zone and engineering activity on land adjoining public streets (2011) (d) BCA BC1: 2012 Design guide on use of alternative structural steel to BS 5950 and Eurocode 3 (e) BRE Digest 251 Assessment of damage in low-rise buildings (f) CIRIA Report C580 (2003) Embedded Retaining Walls - guidance for economic design (g) CIRIA Report C760 (2017) Guidance on embedded retaining wall design 1.4 Trade Preamble Not In Use S1.4.14 Safety Provide safety precautions to comply with all current legislation and regulations, notably: Building Control Regulations Code of Practice for Traffic Control at Work Zone Factories (Building Operations and Works of Engineering Construction) Regulations Factories Act SS CP 79 Safety management system for construction worksites For works within LTA Railway Protection Zone, ensure the works comply fully with Code of Practice for Railway Protection. Additionally, comply also with the following: BRE Digest 251 (1995) Assessment of damage in low rise building BS 8008: Guide to safety precautions and procedures for the construction and descent of machine-bored shaft for piling and other purposes 1.4.1 Development of Design Requirements The notional design of the sheet pile wall works is indicated in the drawings. The lateral support of strutting or ground anchor system indicated in terms of the installation levels, the required stiffness and preloading, are provided schematically where applicable. Based on the information provided, undertake and provide for the SOs acceptance the following which shall be carried out by appropriately qualified, competent and experienced personnel and PE: (a) Design or construction verification checks based on site and actual ground conditions to confirm the required penetration length, type of sheet pile and sizes of all temporary or permanent strutting elements and wailings for the sheet pile walls. TS 268/1065 978 Doc D.2/338 (b) Prepare a response plan in the event that the temporary or permanent sheet piled wall and strutting elements do not perform as expected in the design in controlling the sheet piled wall deflection, and in the event that measures taken to control ground movement and vibration do not perform satisfactorily. Establish and indicate the alert levels and work suspension levels for forces and deflection of the sheet piled wall on the drawings. The response plan shall be feasible for timely implementation with due consideration of the construction sequence and site restraints. (c) Prepare and submit all design and construction sequence, including drawings and reviews that shall be endorsed by appropriately qualified, competent and experienced PE where applicable, to the SO for his acceptance. The same submission shall be made to relevant authorities where applicable. Submit the curriculum vitae (CV) of the personnel and specialists where applicable to the SO for acceptance. 1.4.2 Layout Drawings Engage qualified and experienced personnel to prepare co-ordinated layout drawings for the sheet pile wall panels. Submit the drawings to the SO for acceptance prior to commencing the installation works. 1.4.3 Supervision of the Works Engage a competent and suitably experienced site engineer with the SOs acceptance, to supervise the field works. The supervision requirements shall be in accordance with BCA requirement depending on the size of the project. Site Supervision Plan for supervising the structural and geotechnical building works shall be prepared and submitted by qualified, competent and experienced PEs to the relevant authorities and in accordance with the current guidelines issued under the Building Control Act and Regulations. 1.4.4 Quality Control Plan Submit and work to a quality control plan as agreed with the SO. Refer Section G01- 010:Clause:1.4.7. 1.4.5 Welders' Qualifications Engage only certified welders who are qualified in the accepted welding procedure in accordance with BS EN ISO 9606-1 and have a proven record over the previous 6 months, or who have attained an equivalent standard, on the Works. Provide certificates relating to welders' tests to the SO on request. S1.4.6 Coordination with Other Works Co-ordinate with other contractors who may carry out other works at the same time at the site. Take into account of site access, space occupation, safety and safeguarding of adjoining properties and each other’s works TS 269/1065 978 Doc D.2/339 S1.4.7 Condition Survey Where applicable, prior to and upon completion of the site works, carry out a condition survey to adjacent buildings in accordance with the requirements of section C1-20 “Condition Survey and Monitoring”. Submit all records to the SO and adjacent property owners where directed. Keep a copy of the survey report on site ready for inspection. S1.4.8 Instrumentation and Monitoring Provide instrumentation to monitor the ground movement, vibration and condition of adjacent properties. Refer to Section C2-50, Clause 3.1, and the drawings for the schedule of instrumentation required. If necessary or as required by the authorities, propose and provide additional instrumentation and monitoring for records. Take cognisance of and co-ordinate with other contractors on site who may be carrying out instrumentation and monitoring works to avoid duplication of installation and readings. For general requirements of the instrumentation and monitoring works refer to Section C2-50. S1.4.9 Upholding of Adjoining Properties Accept responsibility for the upholding of the adjoining buildings and roads, footpaths etc., where applicable, together with the mains and services from the time of taking possession of the site through the duration of the works. Adequately maintain roads and footpaths within and adjacent to the site and keep clear of mud and debris. S1.4.10 Verification of Site Information Verify and be satisfied that the information given in the existing site survey plans provided are accurate. If necessary, engage a registered Surveyor to carry out additional site survey before commencing any work. Carry out additional ground investigation where additional information is needed for the works or when directed by the SO. Carry out the works in compliance with Section C2-10 “Site investigation”. Carry out the boreholes progressively prior to commencement of the works in areas according to the contractor’s construction programme. On completion of drilling, backfill the boreholes with a suitable bentonite/cement mix. Submit the location and schedule for the boreholes to SO’s acceptance prior to carrying out the works. On completion, prepare the site investigation report and submit to the SO for acceptance. S1.4.11 Existing Services Affected by Works Refer to Preliminaries and conditions of contract for the requirements to deal with existing services affected by the works. S1.4.12 Site Protection Protect all equipment and working area using fencing or other methods as accepted. TS 270/1065 978 Doc D.2/340 S1.4.13 Obstructions If any obstructions such as existing fences, structures, footings, boulders, concrete blocks, pipes, drains, driveways or ramp are encountered during excavation, submit proposals for their removal for the SO's acceptance. 2 PERFORMANCE REQUIREMENTS 2.1 Pile Embedment for Load Bearing For sheet pile walls that are also used for vertical load bearing purposes, verify the required embedment length, taking into account the actual ground conditions and the results of load tests of preliminary elements or production piles in accordance with SS EN 1997. 2.2 Penetration Depth Drive the sheet piles to a depth as shown in the drawings or when practical refusal as follows is met if earlier: (a) Not In Use S(a) Under continuous vibrating: the rate of penetration <=100 mm/min (b) Not In Use S(b) Under driving: the sheet pile penetration <= 25 mm per 10 blows If practical refusal is met earlier than the stipulated depth, carry out review and design verification as in C02-030-02:Clause:1.4.1 and report to the SO. 2.3 Driving Assistance Any driving assistance such as pre-boring, water-jetting, crush piler or preblasting shall be planned and be approved by the SO prior to start of work, taking into consideration of the influence of driving assistance methods on the performance of the piles and safety of existing structures or potentially unstable slopes. 2.4 Water Retention Fully interlock all clutches and close all corners. Specially fabricate the corner sheet piles to prevent declutching and water leakage. Particular care should be observed when driving sheet piles through hard strata to prevent damage and de-clutching, and check that installation in the actual ground is in accordance with the design. TS 271/1065 978 Doc D.2/341 S2.5 Permissible Damage Criteria for Existing Critical Structures or Services Based on the results of the damage assessment as set out in Clause 1.4.2, propose the allowable wall deflection, ground settlement and vibration limits due to the works taking into account the vulnerability and sensitivity of the adjacent properties. State the values for alert and work suspension levels in the submission in accordance with the requirements of Building Control Act [Section 7(2)] Annex (BE/CP/5 OCT 2001). Notwithstanding the above, ensure that the ground movements and vibrations generated by the works comply with the following if more stringent: Generally comply with the requirements of BS 5228 Part 1. The vibration generated by the works in MRT structures not to exceed a peak particle velocity of 15mm/s. Unless otherwise directed, refer to Section C2-50, Clause 4.2.2 for general restrictions on ground movements and vibration limits for adjacent structures where relevant. 3 MATERIALS 3.1 Steel Grade All steel for sheet piles shall be manufactured to BS EN 10248 or BS EN 10025 and to the grade as specified or indicated in the drawings with minimum steel grade S275. [Note 1: Select S270 GP or S355 GP as appropriate.] The sources of supply of materials shall not be changed until the Contractor has demonstrated that the materials from the new source can meet all the requirements of the specifications. Materials failing to comply with specifications shall be removed promptly from the Site. 3.2 Durability and Protection 3.2.1 Sheet Pile Coating Propose and provide suitable coating protection based on soil exposure conditions. Anti-rust coatings such as bitumen/primer are flammable in liquid state. Hence, coating works shall be carried out away from ignitable sources. 3.2.2 Specialist Labour The preparation of surfaces and the application of the coats to form the coating shall be carried out by specialist labour with experience in preparation of the surface and in application of the coating specified. TS 272/1065 978 Doc D.2/342 3.2.3 Surface Preparation for Coating All surfaces to be coated shall be clean and dry, and prepared by one or both of the following methods, as specified. Carry out degreasing with detergent wash compatible with the coating, where necessary. All surfaces shall be blast cleaned to Sa 2.5 of BS 7079, Part A1. Carry out blast-cleaning after fabrication. Unless an instantaneous-recovery blasting machine is used, the cleaned steel surface shall be air-blasted with clean dry air and vacuum-cleaned or otherwise freed from abrasive residues and dust immediately after cleaning. 3.2.4 Application and Type of Primer Within 4 hours after surface preparation, before visible deterioration takes place, coat the surface with an appropriate primer or the specified coating. Do not apply coating to a metal surface which is not thoroughly dry. 3.2.5 Control of Humidity during Coating Do not apply coating when the surface metal temperature is less than 3°C above the dewpoint temperature or when humidity could have an adverse effect on the coat. When heating or ventilation is used to secure suitable conditions to allow coating to proceed, take care to ensure the heating or ventilation of a local surface does not have an adverse effect on adjacent surfaces or work already done. 3.2.6 Parts to be Welded Apply the coating within 200 mm of a weld after welding. The method of application shall comply with the manufacturer’s recommendations. 3.2.7 Thickness, Number and Colour of Coats The nominal thickness of the finished coating and if necessary, of each coat shall be as specified or shown in the drawings. The average coat or finished coating thickness shall be equal to or greater than the specified nominal thickness. In no case shall any coat or finished coating be less than 75% of the nominal thickness. Apply each coat after an interval that ensures the proper hardening or curing of the previous coat. Where more than one coat is applied to a surface, each coat shall, if possible, be of a different colour from the previous coat. The colour sequence and final coating colour shall be documented. TS 273/1065 978 Doc D.2/343 3.2.8 Inspection of Coatings The finished coating shall be generally smooth, of dense and uniform texture and free from sharp protuberances or pinholes. Excessive sags, dimpling or curtaining shall be re-treated. Any coat damaged by subsequent processes or which has deteriorated to an extent such that proper adhesion of the coating is in doubt shall be removed, and the surface shall be cleaned to the original standard and recoated to provide the specified number of coats. Check the completed coating for thickness by a magnetic thickness gauge. Areas where the thickness is less than that specified shall receive additional treatment. Check the completed coating for adhesion by means of an adhesion test to BS EN ISO 2409, carried out on 10% of the piles. The adhesion of any completed coating shall not be worse than classification 2. Do not carry out adhesion tests until 7 days after coating. On completion of testing, the test area shall be made good to the standard specified in the particular specification. Areas where the adhesion is defective shall be repaired and re-inspected. 3.3 Fabricated Sheet Piles Fabricate and supply all sheet piles to the manufacturer’s recommendations. Unless otherwise approved by the SO, all steel sheet piles shall be within the dimensional tolerances as shown in Table 1. Table 1. Dimensional tolerances for steel sheet piles Dimension to which tolerance applies 3.4 Tolerance 1. Width (a) Single piles (b)Interlocked piles 2% 3% 2. Thickness of section 5% 3. Weight 5% 4. Length 50mm 5. Squareness of cut for each section (a) parallel to line of wall (b)perpendicular to line of wall 2% 10mm 6. Straightness 0.2% of pile length 7. Depth of section 4% Clutch Sealant Unless otherwise specified in the drawings, propose suitable clutch sealant to SOs acceptance. TS 274/1065 978 Doc D.2/344 3.5 Installation Equipment Satisfy the SO regarding the suitability, efficiency and energy of the installation equipment that shall be in accordance BS EN 12063. Where a drop hammer is used, the mass of the hammer shall not be less than half that of the sheet pile self-weight. For other types of hammer the energy delivered to the sheet pile shall be at least equivalent to a drop hammer of the stated mass. 3.6 Reuse of Sheet Piles Do not reuse sheet piles installed previously unless all specified requirements are demonstrated to be met and subject to the SOs approval. The thickness of the sheet pile shall be re-measured and recorded. Assess the available ultimate bending moment and shear capacity considering corrosion effects. All reuse sheet piles, if accepted by the SO, shall comply with BC1: 2012 Design guide on use of alternative structural steel to BS 5950 and SS EN 1993. 4 WORKMANSHIP 4.1 General Ensure the equipment set up, installation procedures and execution conform with BS EN 12063 and BS EN 12699 as applicable. [Note 1: BS EN 12063 is being reviewed to cover the execution of permanent or temporary sheet pile wall, combined pile walls, high modulus walls structures and the handling of equipment and materials. It applies to steel sheet pile walls, combined walls, high modulus walls, synthetic sheet pile walls (composite), precast concrete and timber sheet pile walls.] 4.2 Marking and Storage 4.2.1 Marking Mark each sheet pile with the grade accorded. 4.2.2 Storage Store sheet piles of different grades separately. Place of storage shall be safe from theft. Refer to BS EN 12063. 4.3 Clutch Sealant Apply in accordance with the manufacturer’s recommendations and in accordance to BS EN 12063. TS 275/1065 978 Doc D.2/345 4.4 Handling and Installation 4.4.1 Handling Ensure the interlocks are clean and undistorted. Avoid any significant damage to the sheet piles and coatings during all lifting, handling and pitching operations. Refer to BS EN 12063 on handling of equipment and materials. 4.4.2 Installation The execution of the sheet pile wall shall be in accordance to BS EN 12063. 4.5 (a) Select plant to suit the ground conditions and type of sheet pile. Submit details for the SOs acceptance. (b) Provide at least 24 hours’ notice to the SO prior to the commencement of installation. (c) Guide all sheet piles and hold in position with temporary gates. Ensure all sheet piles are properly interlocked. (d) Provide adequate support and restraint to the free length of sheet pile at all stages during the installation process. (e) Install the end sheet piles in advance of the intermediate sheet piles. Avoid excessive lead of the end sheet piles ahead of the general panel level. (f) Position the sheet pile installation equipment to align with the axis of the sheet pile within the erection and installation tolerances. (g) Install sheet piles to the specified level or level of resistance. (h) When pile installation encounters difficulties or hard or unexpected ground conditions, cease installation at practical refusal or cease if the sheet pile is visibly damaged, and report to the SO. (i) Where the sheet pile has not reached the specified level, investigate, review and propose to the SO on measures and methods to meet the design requirements as appropriate. Jetting Where jetting is used to assist sheet pile installation ensure that this does not affect the following: (a) The performance of the sheet piles TS 276/1065 978 Doc D.2/346 (b) The stability of surrounding structures Refer to BS EN 12699 on needs for driving assistance. 4.6 Length of Sheet Piles Sheet piles may be supplied in more than one length with the following provisions for the joints: 4.7 (a) Locate splices away from positions of maximum stress. (b) Design spliced joints for full stresses imposed due to bending, shear and bearing. (c) Do not weld interlocks where sheet piles are spliced by butt-welding unless a sealing weld is required. Splicing of Sheet Piles Spliced joints shall be designed to cater for the combined effects of bearing, shear and bending stresses imposed upon the sheet piles. Sheet pile splicing in the form of full butt weld or steel plate with fillet weld shall have similar strength as parent sheet pile. Allow minimum cooling time of 30 minutes for welds before continuing the installation works. Weld metal shall not encroach into the interlock area so as not to affect the capacity and interlocking mechanism of the sheet piles. 4.8 Corrosion of Sheet Piles Unless otherwise agreed by the SO, provide sheet piles with a sheet pile corrosion rate of not more than 0.015 m/side/year during the service life span in harsh environment. 4.9 Forming Holes in Sheet Piles Do not burn holes without the approval of the SO. Drill holes in the sheet piles for ties and attachment of walings, etc. after installation. Drill or burnt all holes using a template, and dress flush subsequently. Check that the hole size is of sufficient clearance and include allowance for bolt/tie coatings and inclination if not horizontal. Seal all holes not required in the finished works by welding a plate of the same grade, of thickness not less than the pan thickness to the pile. The minimum plate overlap is 40 mm and the minimum continuous filet weld is 6 mm. All holes shall be within a positional tolerance of ±10 mm. TS 277/1065 978 Doc D.2/347 4.10 Cutting and Welding Do not carry out cutting or welding of sheet piles without prior approval from the SO. Carry out all such cutting by means of oxyacetylene, oxypropane or the other approved method. The remaining pile shall be of clean and even appearance with grinding tools being employed to remove splatter. Mark cut offs for clear and easy identification with the source and dispose in the pre-agreed manner. Carry out cutting in such a way as to prevent damage or distortion to adjacent piles. The finished level of the cut pile shall be within 20 mm of the theoretical level. Allow a minimum cooling time of 30 minutes for welds before continuing the installation work. Carry out welding in accordance with procedures and recommendations specified in BS EN 1011-1 and BS EN 1011-2. Cut out and replace any defective welds. For structural welds, refer also to BS EN 12699. 4.11 Walings and Tie Rods Secure wailings to each pair of pile with anchor bolts, washers and bearing plates. All splices, if welded or bolted, shall be at the fifth spacing between tie rods and splices in wailings and shall be staggered by a minimum distance of 5 m. Do not weld the tie rods or use for earthing purposes. Protect tie rods against welding splash. Assemble tie rods with necessary taper washers, washers and bearing plates in accordance with the manufacturer’s recommendations. Take precautions during installation of the tie rods to avoid the following: (a) Deflection of the tie (b) Local bending of tie rod on wailing (c) Damage to the tie or protective coating of the tie Tension the ties by means of a turnbuckle only and agree on the phasing of the tensioning with the SO in advance. Take care to avoid damage to the tie rods during subsequent operations such as backfilling. Submit procedure to accomplish this for the SOs acceptance. Where settlement is expected to occur, place the ties inside a tube such that the tube settles with the ground but the tie remains in the correct position. 4.12 Steel Sheet Piles and Installation Tolerances Base the sheet pile line on nominal sheet pile size. In addition to dimensional tolerances shown in Table 1 Section C02-030-02:Clause:3.3, install sheet pile within the following tolerances: (a) Deviation perpendicular to theoretical line, ±50 mm (b) Deviation of verticality normal to and along the line of the sheet piles, 1:75 TS 278/1065 978 Doc D.2/348 (c) Top of finished sheet pile level, ±50mm 5 VERIFICATION AND SUBMISSIONS 5.1 Submissions 5.1.1 Method Statement Prior to commencement of sheet piling works, submit the following for the SOs acceptance for the proposed method of installation to achieve the required performance: 5.1.2 (a) Method of achieving penetration to depth as specified, including methods of dealing with obstructions (b) Proposals to mitigate noise and vibration, and an assessment of vibration characteristics for with piling operations or activities (c) Details on the plant and equipment proposed for the installation of the sheet piles (d) Details of method of location and avoidance of critical services (e) Proposed methods for control of the sheet piling works, including the setting out and description of the alignment controls, including the proposed methods for controlling the verticality and the rotation about longitudinal centreline of the sheet pile (f) Method of checking the verticality and corrective actions to be taken if the deviation exceeds the maximum permitted limits (g) All details of proposed monitoring equipment (h) Details of inserts for segmental sheet pile and details of clutch sealant proposed (i) Details of a quality control for the Site Works (j) Typical sheet pile record sheets Shop Drawings Submit shop drawings of the sheet pile works for the acceptance of the SO prior to the commencement of Works, where applicable. 5.1.3 Work Programme Submit work programme indicating the anticipated time required for installation of the sheet piles in the overall work programme. TS 279/1065 978 Doc D.2/349 5.1.4 Ground Investigation Confirm that the ground investigation information provided is adequate for the sheet piling works and design verification. Raise any concerns as to adequacy to the SO. Report immediately and without delay to the SO any circumstance which indicates that in the Contractor’s opinion, the ground conditions differ from those reported in or which could have been inferred from the subsurface investigation reports. 5.1.5 Test Certificates Provide the SO with test certificates accompanied by information on material analysis and mill sheets where applicable. 5.1.6 Welding Procedures Submit for acceptance full details of the welding procedures and electrodes with drawings and schedules as may be necessary. Submit relevant documents for the qualified welders as stated in Section C02-030-02:Clause:1.4.5. Ensure that during the course of the work, displacement or damage which could impair either performance or durability does not occur to completed elements. 5.1.7 Quality Control Plan Prepare and submit the quality control plan for SOs acceptance prior to starting work. S5.1.8 Monitoring of Adjacent Structures Provide proposals for surveys and monitoring of movement and vibration in adjacent structures and services before work commences and during the course of the works. Submit the assessment of the effect of wall deflection and ground settlement to adjacent properties and the proposed control limits. 5.2 Inspection and Testing 5.2.1 Inspection Allow the SO to inspect and test at any stage of fabrication. Ensure that adequate notice is given to the SO when fabrication processes can be inspected or tests can be witnessed. 5.2.2 Weld Testing Refer to Section C05-010 "Structural Steelwork" for general requirement on welding tests. Carry out welding tests as specified or indicated in the drawings or as directed by the SO. TS 280/1065 978 Doc D.2/350 S5.2.3 Radiograph of Welds The acceptance standard for radiographs of sheet pile welds to be in accordance with BS PD 5500. 5.3 Records and Reports 5.3.1 Sheet Piling Records Provide record sheets with the following information and submit 2 copies of these records to the SO within agreed time frame after the sheet pile is installed. (a) Sheet pile reference (b) Sheet pile type and steel grade (c) Overall sheet pile length (d) Length of individual sheet pile sections (e) Details of joints (f) Type of hammer, if relevant (g) Date of installation (h) Commencing surface level and final toe level (i) Top level and bottom level of the sheet pile (j) Working level and type of construction plant (k) The number of blows to drive each 250 mm over the last 2.5 m shall be recorded, if relevant (l) All information regarding unexpected installation conditions such as in terms of increased penetration rates or installation problems with the actual site or ground conditions and other interruptions or stoppages to the sequence of work (m) Where changes in the pile length have occurred due to lengthening or cutting, all relevant information, including off-cut length or extension length and reason for such change shall be included. TS 281/1065 978 Doc D.2/351 5.3.2 As-Built Drawings Unless otherwise agreed, submit as-built drawings of the sheet piling works for records. Keep accurate records of the actual Works constructed. For those parts of the Works which will become hidden by further progress, check and verify such records by the SO while those parts of the Works are open for inspection. All drawings submitted shall have relevant particulars at the bottom right-hand corner, including the project title, Contractor's name, title of drawing, scale, date, drawing number and notes identifying revisions made. Other details to be included in the as-built drawings are as follows: 5.3.3 (a) Layout plan of the sheet piles showing the actual positions and eccentricities in perpendicular directions of the sheets at ground level. (b) Elevation view of the installed sheets from cut-off level to toe. Express cut-off level in terms of Reduced Levels. Order of Piles Ensure that the piles are available at the time for incorporation in the Works. All piles and production facilities shall be made available for inspection at any time. Only new piles shall be used for permanent works. Piles shall be carefully examined at the time of delivery and damaged piles repaired or replaced. The records of testing of the steel used in the piles shall be submitted prior to commencing the Works. TS 282/1065 978 Doc D.2/352 (8) C02-030-03 Contiguous Bored Pile Walls and Secant Pile Walls TS 283/1065 978 Doc D.2/353 1 GENERAL Read this Section with G01-010 "General Requirements" and all other contract documents. 1.1 Scope This Section covers the requirements for the construction and installation of contiguous bored pile walls and secant pile walls as an embedded retaining wall type. Other types of embedded retaining walls are covered in: C02-030-01 Diaphragm Walls C02-030-02 Sheet Piling The walls may be temporary or permanent and used solely to form embedded retaining walls resisting principally horizontal loads, or also to support vertical loads. 1.2 Related Sections Read this Section in conjunction with the relevant requirements of the following sections: C01-020 Condition Survey C02-010 Ground Investigation C02-050 Instrumentation and Monitoring C04-010 Bored Piling Works C04-030 Pile Testing C03-010 Concrete Construction Generally C03-020 Reinforcement 1.3 Standards, Codes, Regulations and Technical References 1.3.1 Standards and Codes Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant requirements of the standards and codes listed below or referenced in the body of the Specification. Alternative standards and codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative standards and codes comply with the requirements of the standards specified. All standards and codes quoted are the current version, unless specific year references are noted. In the event that the standards or codes are partially superseded or have become obsolete, refer to the current edition or the approved substitution for the relevant clauses. Singapore Standards SS EN 1990 Eurocode: Basis of structural design SS EN 1992-1-1 Eurocode 2: Design of concrete structures - Part 1-1: General rules and rules for buildings SS EN 1993-1-1 Eurocode 3: Design of steel structures - Part 1-1: General rules and rules for buildings SS EN 1997 Eurocode 7: Geotechnical Design - Part 1:General Rules TS 284/1065 978 Doc D.2/354 SS EN 1997 Eurocode 7: Geotechnical Design - Part 2: Ground Investigation and Testing NA to SS EN 1997-1 Singapore National Annex to Eurocode 7: Geotechnical design - Part 1: General rules NA to SS EN 1997-2 Singapore National Annex to Eurocode 7: Geotechnical design - Part 2: Ground investigation and testing SS EN 1998-1 Eurocode 8: Design of structures for earthquake resistance - Part 1: General rules, seismic actions and rules for buildings SS EN 206 Concrete - Specification, performance, production and conformity SS 544-1 Concrete - Complementary Singapore Standard to SS EN 206- Part 1 : Method of specifying and guidance for the specifier SS 544 -2 Concrete - Complementary Singapore Standard to SS EN 206 - Part 2 : Specification for constituent materials and concrete SS 560 Specification for steel for the reinforcement of concrete - Weldable reinforcing steel - Bar, coil and decoiled product Other Standards BS EN 1536 Execution of special geotechnical works - Bored piles BS EN 1998-5 Eurocode 8: Design of structures for earthquake resistance - Part 5: Foundations, retaining structures and geotechnical aspects BS EN 13670 Execution of concrete structures BS 5228-1 Code of practice for noise and vibration control on construction and open sites - Part 1:Noise BS 5228-2 Code of practice for noise and vibration control on construction and open sites - Part 2: Vibration BS 5930 Code of practice for ground investigations BS 8002 Code of practice for earth retaining structures BS 8004 Code of practice for foundations BS 8102 Code of practice for protection of below ground structures against water from the ground In the event that the standards or codes are revised or superseded, refer to the latest edition or the appropriate substitution for the relevant subjects. 1.3.2 Technical References Refer to the following technical reference for guidance in carrying out the works. (a) BRE Digest 251 Assessment of damage in low-rise buildings (b) BRE Special Digest 1 Concrete in aggressive ground (c) CIRIA Report 139 Water-resisting basement construction - A guide (d) CIRIA C517 Temporary propping of deep excavations - Guidance on design (e) CIRIA Report C580 (2003) Embedded Retaining Walls - Guidance for economic design. TS 285/1065 978 Doc D.2/355 (f) CIRIA C760, Guidance on embedded retaining wall design (g) EFFC/DFI, Best practice guide to tremie concrete for deep foundations (2nd Ed 2018) (h) EFFC/DFI, Guide to support fluids for deep foundations (1st Ed 2019) (i) FPS, Bentonite support fluids in civil engineering (j) ICE manual of geotechnical engineering, Volume 1: Geotechnical engineering principles, problematic soils and site investigation (k) ICE manual of geotechnical engineering, Volume 2: Geotechnical design, construction and verification (l) ICE Specification for piling and embedded retaining walls (m) LTA Code of practice for Railway Protection (2004) (n) LTA Guide to carrying out restricted activities within Railway Protection and Safety Zones (2009). (o) LTA Guide to carrying out engineering works within road structure safety zone and engineering activity on land adjoining public streets (2011) (p) PD 6687-1 Background paper to the National Annexes to BS EN 1992-1 and BS EN 1992-3 1.4 Trade Preamble 1.4.1 Development of Design Requirements The notional design of the contiguous bored pile (CBP) or secant bored pile (SBP) wall works is indicated in the drawings. The lateral support of strutting or ground anchor system indicated in terms of the installation levels, the required stiffness and preloading are provided schematically where applicable. Based on the information provided, undertake and provide for the SOs acceptance the following which shall be carried out by appropriately qualified, competent and experienced personnel and PE: (a) Design or construction verification checks based on actual ground conditions to confirm the required size and penetration length of CBP or SBP. Size and provide all temporary or permanent strutting elements and walings for the CBP or SBP walls and take into all necessary considerations that the required control on wall deflection can be achieved. (b) Prepare a response plan in the event that the temporary and or permanent CBP or SBP walls and strutting elements do not perform as expected in the design in controlling the CBP or SBP wall deflection, and in the event that measures taken to control ground movement and vibration do not perform satisfactorily. Establish and indicate the alert levels and work suspension levels for forces and deflection of the CBP or SBP on the drawings. The response plan shall be feasible for timely implementation with due consideration of the construction sequence and site constraints. TS 286/1065 978 Doc D.2/356 (c) Prepare and submit all design and construction sequence, including drawings and reviews that shall be endorsed by appropriately qualified, competent and experienced PE where applicable, to the SO for his acceptance. The same submission shall be made to relevant authorities where applicable. Submit the curriculum vitae (CV) of the personnel and specialists where applicable, to the SO for acceptance. 1.4.2 Layout Drawings Engage qualified and experienced personnel to prepare co-ordinated layout drawings indicating as a minimum, pile dimensions, minimum penetration and material requirements for the CBP or SBP walls. Submit the drawings to the SO for acceptance prior to commencing the installation works. 1.4.3 Co-ordination with Other Works Co-ordinate with other contractor’s who may carry out other works at the same time at the site. Take into account of site access, space occupation, safety and safeguarding of adjoining properties and each other’s works. 1.4.4 Upholding of Adjoining Properties Accept responsibility for the upholding of the adjoining buildings and roads, footpaths, etc., where applicable, together with the mains and services from the time of taking possession of the Site through the duration of the Works. 1.4.5 Verification of Site Information 1.4.5.1 Site Surveys Verify and be satisfied that the information given in the existing site survey plans provided are accurate. If necessary, engage a Registered Surveyor to carry out additional site survey before commencing any work. TS 287/1065 978 Doc D.2/357 1.4.5.2 Additional Site Investigation Carry out additional ground investigation where additional information is needed for the Works or when directed by the SO. Carry out the Works in compliance with Section C02-010 "Ground Investigation". The permeability, strength of the subsoils and the groundwater level are key parameters to be ascertained to determine the suitability of CBP or SBP wall and the required penetration depth of the soft and hard piles to ensure overall stability and seepage cut-off. Carry out the boreholes progressively prior to commencement of the Works in areas according to the contractor’s construction programme. On completion of drilling, backfill the boreholes with a suitable bentonite/cement mix. Where rock is encountered, carry out sufficient number of boreholes before the pile excavation to establish the quality and grade of the rock for design and execution requirements. Where cavity is suspected from existing geological or published information in the area e.g. in limestone, carry out adequate number of boreholes for sufficient information to carry out any pre-treatment works that are necessary before pile installation commences. Submit the location and schedule for the boreholes to the SOs acceptance prior to carrying out the works. On completion, prepare the site investigation report and submit to the SO for acceptance. Report immediately without delay to the SO any circumstance which indicates that in the Contractor’s opinion, the ground conditions differ from those reported in or which could have been inferred from the subsurface investigation reports. 1.4.5.3 Groundwater Level Verify the data on groundwater level from available ground investigation reports. Carry out additional water standpipes and piezometers if deemed necessary or as directed by the SO. 1.4.5.4 Contamination Verify information on contamination identified or believed to be present on site. In the event that contamination is either positively identified or suspected, draw to the attention of all personnel working on site together with the need to take any precautionary measures in handling contaminated materials, groundwater and obnoxious vapours from the ground. 1.4.6 Supervision of the Works Engage qualified, competent and suitably experienced site personnel with the SOs acceptance, to supervise the field works. Information on items to be checked or requiring monitoring during construction shall be clearly identified and made known to the supervising personnel. Site Supervision Plan for supervision the structural and geotechnical building works shall be prepared and submitted by qualified, competent and experienced PEs to the relevant authorities, and in accordance with the current guidelines issued under the Building Control Act and Regulations. TS 288/1065 978 Doc D.2/358 1.4.7 Quality Control Plan Submit and work to a quality control plan as agreed with the SO. Refer to Section G01010:Clause:1.4.7. 1.4.8 As-Built Pile Surveys Surveying of as-built pile locations and pile eccentricities shall be carried out by a Registered Surveyor, and submit the asâbuilt surveys to the SO in the format as directed, within 14 days after the piles have been trimmed to the cut-off level. S1.4.9 Building Damage Assessment Carry out a Building Damage Assessment on the effects of ground movement to the neighbouring properties due to the works, for the purpose of establishing suitable values for ‘Alert’ and “Work Suspension’ levels for monitoring. Submit to SO with endorsement from a PE. S1.4.10 Safety Provide safety precautions to comply with all current legislation and regulations, notably: a. Building Control Regulations b. Code of Practice for Traffic Control at Work Zone c. Factories (Building Operations and Works of Engineering Construction) Regulations d. Factories Act e. SS CP 79 Safety management system for construction worksites f. For works within LTA Railway Protection Zone, ensure the works comply fully with Code of Practice for Railway Protection. Additionally, comply also with the following: a. BRE Digest 251 (1995) Assessment of damage in low rise building b. BS 8008: Guide to safety precautions and procedures for the construction and descent of machine- bored shaft for piling and other purposes TS 289/1065 978 Doc D.2/359 S1.5 Definitions and Abbreviations a. Accredited The Testing Laboratory shall mean an organisation or laboratory testing accredited under the Singapore Laboratory Accreditation Scheme laboratory (SINGLAS) and fully equipped to carry out all tests and checks required by the Specification. b. Cement May also include all mineral admixtures such as pfa, ggbs, silica fume etc that have cementitious properties as used in SS EN 197-1 c. Obstructions Include rock, concrete, reinforced concrete, solid brickwork, sheet piles and the like, met within the excavations, but excluding those met on the surface of the ground. d. Rock Material with a large coherent mass of such size and strength, which can be loosened or fractured only by blasting, or the employment of heavy pneumatic tools, or by chemical expansion methods. Loose boulders up to 1m³ in volume that can be removed are not classified as rock. 2 PERFORMANCE REQUIREMENTS 2.1 Verification of Performance When carrying out the performance verification as set out in C02-030-03:Clause:1.4.1 and in accordance with SS EN 1997, take into account the following considerations: TS 290/1065 978 Doc D.2/360 2.1.1 Wall Movements The required size of CBP or SBP wall system is shown in the drawings, including the wall penetration depth and the size of all permanent supports. Schematic lateral support in the form of temporary strutting system or ground anchoring system indicated in terms of the installation levels, the required stiffness and preloading are also shown on the drawings, where applicable. Based on the actual ground condition encountered, verify the wall penetration depth and the adequacy of CBP or SBP wall system as indicated in the drawings and in accordance with SS EN 1997. The CBP or SBP wall movements shall be checked and reviewed throughout the execution to ensure that the wall movements are within the allowable limits as specified or indicated in the drawings and in accordance to the requirements of the relevant authorities. The CBP or SBP walls shall withstand all loads on it; including those due to water pressure, earth pressure, surcharge loads, overburden, effects of surrounding properties and varying load conditions due to different stages of construction. Check that the application of partial factors assumed in the design and control on wall movement are verified by taking into account the construction effects and field performance of the intended temporary supporting system. The verification shall be in accordance with SS EN 1997. Check that the ultimate limit states (ULS) shall not be exceeded when appropriate load combinations and partial factors are applied in accordance with SS EN 1997. In addition, control of wall deflection shall also satisfy serviceability limit states (SLS) and the requirements of the Building Control Authority. [Note 1: Refer also to guidance provided in CIRIA C517, C580, C760 and BS 8002.] [Note 2: Temporary and permanent works shall be treated with equal importance and shall be well coordinated without ambiguity at all stages of design and construction. When an observational approach is adopted, a highly co-ordinated site team would need to be employed, and a clearly-defined protocols for decision-making and monitoring requirements shall be in place before construction commences.] 2.2 Embedment for Load Bearing Where CBP or SBP walls are used for vertical load-bearing purposes, verify the required embedment length by taking into account the actual ground conditions and the results of load tests of preliminary elements in accordance or production piles in accordance with SS EN 1997. 2.3 Use of Support Fluid Where support fluid is used, fulfil the following requirements: (a) Provide continuous support of the excavation. (b) Do not form a thick filter cake layer prior to concreting. (c) Have the ability to keep solid particles in suspension. (d) Be capable of being easily displaced and the interface layer remains on top of the rising concrete during concreting. (e) Does not pollute the ground and groundwater at all stage. TS 291/1065 978 Doc D.2/361 (f) Does not coat the reinforcement such as to impair the bond between the reinforcement and concrete. Bentonite, polymer or a mixture of bentonite and polymer support fluids may be considered for these requirements. Testing of support fluid shall be carried out to demonstrate compliance of limits as specified in BS EN 1536 or ICE specification for piling and embedded retaining walls if applicable, or FPS Bentonite support fluids in civil engineering, or manufacturer’s instructions shall be complied with performance criteria for CBP and SBP. For CBP and SBP supporting vertical loads, refer to Section C04-010:Clause:2.2 for the requirements on the performance criteria of piles under load testing. Load testing of single bored pile in place of SBP is acceptable, provided the method of construction of both bored pile and SBP is similar. [Note 1: Refer also to EFFC/DFI Guide to Support Fluids for Deep Foundations.] 2.4 Watertightness for CBP and SBP Walls The walls formed shall be substantially watertight, that is, free from running water, percolating water or seepage water. When total damp patches exposed on the excavated face of the wall exceeds 10% of the visible area or any individual damp patch is found to be more than 4 m2, repair works shall be carried out. [Note 1: CBP is not considered to be watertight unless the gap between the piles is effectively sealed. In general, hard/soft SBP walls are only regarded as providing watertightness in the short term only. A good design practice is to provide a secondary lining system or provide a hard/ hard secant pile wall if long-term water tightness is required.] [Note 2: For guidance, refer to Table 2 of BS 8102: 2009 "Code of Practice for protection of below ground structures against water from the ground"; and B1.9 of ICE "Specification for Piling and Embedded Retaining Walls", 3rd Edition.] 2.5 Concrete The concrete mix design shall satisfy the specification of concrete and shall take into account the following: (a) the need for a high resistance against segregation (b) the need for adequate plasticity and good cohesiveness (c) the need to flow well (d) the need to be able to compact adequately by gravity (e) the need of sufficient workability retention for the duration of the placement procedure (f) the need of a concrete final set within 20 hours. [Note 1: For tremie concrete, refer also to EFFC/DFI, Guide to Tremie Concrete for Deep Foundations.] TS 292/1065 978 Doc D.2/362 3 MATERIALS 3.1 General Refer to Section C04-010:Clause:3 and BS EN 1536 for general requirements of materials for CBP and SBP walls, including concrete, reinforcement, support fluid and steel casing, etc. 3.2 Not In Use S3.2 Temporary Casing Temporary casing (not less than 6m) shall be provided during excavation of secondary piles for the construction of SBP walls. 3.3 Self-hardening Slurry Mixes for SBP Walls In the construction of SBP, self-hardening slurry mix may be used for primary piles instead of concrete. The proposed mix shall be coherent and of a workability similar to concrete to facilitate placing but shall remain sufficiently soft to facilitate cutting after the pile has been completed. The compressive strength and permeability of the self-hardening slurry mixes shall meet the minimum design requirements specified by the PE who is responsible for the design of the slurry mix. 3.4 Support Fluid 3.4.1 Bentonite Bentonite supplied to the Site shall comply with BS EN 1538. If bentonite is used, in any 100 tonnes of bentonite supply, moisture content shall not deviate more than ±2%. Maximum moisture content shall not exceed 15%. Residue of diameter greater than 75 µm shall not exceed 4%. Bentonite slurry properties obtained at the recommended dosage by the manufacturer/ supplier shall conform to Tables 1 and 2 of BS EN 1538. 3.4.2 Reuse of Bentonite Upon reuse, the density, maximum sand content, viscosity and pH of bentonite shall to comply with the criteria as set out in Tables 1 and 2 of BS EN 1538. 3.5 Concrete Concrete and constituent materials for CBP and SBP wall shall be in compliance with SS EN 206 and SS 544-1 and SS 544-2. TS 293/1065 978 Doc D.2/363 3.6 Additions and Admixtures Additions and admixtures when used in the concrete mix shall comply with SS EN 206 and SS 544. 3.7 Reinforcement For general requirements of reinforcement, refer to Section C03-020:Clause:3. The steel elements used in CBP and SBP walls shall comply with SS EN 10080. 4 WORKMANSHIP 4.1 General Refer to Section C04-010:Clause 4 and BS EN 1536 for all general requirements of execution and workmanship for CBP and SBP walls, including boring, support fluid, concreting and casing support, etc. For tremie concrete, refer to EFFC/DFI, Guide to Tremie Concrete for Deep Foundations, and for supporting fluid, refer also to EFFC/DFI Guide to Support Fluids for Deep Foundations. 4.2 Placing Self-Hardening Slurry Mixes for Soft Pile of SBP Wall Place using methods appropriate to the mix employed. Use a tremie in accordance with C04010:Clause:4.7, or proprietary methods as proposed and accepted by the SO. 4.3 Setting Out and Tolerances 4.3.1 Setting Out Establish all lines, levels and be responsible for the correct positions of all piles. Carry out setting out from the main grid lines of the proposed structure. Immediately before installation of the pile, mark the pile position with suitable identifiable pins or markers. 4.3.2 Tolerance for SBP 4.3.2.1 Deviation of Centre Line Maximum permitted deviation of pile centre at cut-off from specified position shall be 25 mm in any direction. Allow an additional tolerance of 5 mm for every additional metre of the cut-off level below the top of the guide wall for hard/hard secant piles. Allow an additional tolerance of 10 mm for every additional metre of the cut-off level below the top of the guide wall for hard/soft secant piles. TS 294/1065 978 Doc D.2/364 4.3.2.2 Verticality For hard/hard secant piles, verticality tolerance is 1:200 for the exposed face of the pile unless otherwise agreed. For hard/soft secant piles, verticality tolerance is 1:100 for the exposed face of the pile unless otherwise agreed. 4.3.2.3 Allowance for Overbreak An additional 100 mm is allowed for concrete protrusions resulting from overbreak in the ground unless otherwise agreed. Where very soft layers or removal of obstructions are anticipated, notify the SO to agree on an additional tolerable allowance for the overbreak. 4.3.2.4 Reinforcement Vertical tolerance on level of steel projecting from cut-off shall be +150 mm/-50 mm (i.e. a maximum of 150 mm higher or 50mm lower), unless otherwise agreed. 4.3.2.5 Recesses For recesses formed by box-outs within the pile shaft, vertical tolerance is as C02-030- 03:Clause:4.3.2.4 and rotational tolerance shall be 10 degrees. 4.3.3 Tolerance for CBP 4.3.3.1 Deviation of Centre Line Maximum permitted deviation of pile centre at cut-off from specified position shall be 75 mm in any direction. Allow an additional tolerance of 10 mm for every additional metre of the cut-off level below the top of the guide wall. 4.3.3.2 Verticality Verticality tolerance is 1:100 for the exposed face of the pile, unless otherwise agreed. 4.3.3.3 Allowance for Overbreak An additional 100 mm is allowed for concrete protrusions resulting from overbreak in the ground unless otherwise agreed. Where very soft layers or removal of obstructions are anticipated, notify the SO to agree on an additional tolerable allowance for overbreak. TS 295/1065 978 Doc D.2/365 4.3.3.4 Reinforcement Vertical tolerance on level of steel projecting from cut-off shall be +150 mm/-50 mm (i.e. a maximum of 150 mm higher or 50 mm lower), unless otherwise agreed. 4.3.3.5 Recesses For recesses formed by box-outs within the pile shaft, vertical tolerance is as C02-030- 03:Clause:4.3.2.4 and rotational tolerance shall be 10 degrees. 4.3.4 Design Consideration Due to Construction Tolerance CBP and SBP design and execution shall take into account the construction tolerances agreed by the SO. 4.3.5 Guide Walls Guide walls shall be used in the construction of SBP to ensure sufficient interlock. In the case of CBP, guide wall is only required if a more stringent construction tolerance has been specified. Guide walls should be constructed in reinforced concrete or other suitable materials. 5 VERIFICATION AND SUBMISSIONS 5.1 General Refer to Section C04-010:Clause:5 for all general requirements of verification and submissions for CBP and SP walls, including method statements, quality control plans, records, as-built details, compliance tests and pile tests, etc. 5.2 Soft Pile of SBP Walls 5.2.1 Trial Mixes for Self-hardening Slurry Mixes Prepare trial mixes and carry out tests for suitability, unless there is adequate existing data demonstrating the mix proportions and method of manufacture that will produce hardened material of the required strength and other properties such as permeability, shrinkage, durability and consistency for compaction. 5.2.2 Testing of Self-Hardening Mixes Check for compliance with the mix proportions. [ Note 1: The ICE specification for the construction of slurry trench cut-off walls provides guidance on the requirements of self-hardening mixes.] TS 296/1065 978 Doc D.2/366 (9) C02-040-01 Jet Grouting Method TS 297/1065 978 Doc D.2/367 1 GENERAL Read this Section with G01-010 "General Requirements" and all other contract documents. 1.1 Scope This Section covers the requirements for soil improvement works using jet grouting method. 1.2 Related Sections Read this Section in conjunction with the relevant requirements of the following sections: 1.3 C01-020 Condition Survey C02-010 Ground Investigation C02-020 General Earthworks (Excavation and Filling) C02-050 Instrumentation and Monitoring Standards, Codes, Regulations and Technical References TS 298/1065 978 Doc D.2/368 1.3.1 Standards and Codes Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant requirements of the standards and codes listed below or referenced in the body of the Specification. Alternative standards and codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative standards and codes comply with the requirements of the standards specified. All standards and codes quoted are the current version, unless specific year references are noted. In the event that the standards or codes are partially superseded or have become obsolete, refer to the current edition or the approved substitution for the relevant clauses. Singapore Standards SS EN 197-1 Cement - Composition, specification and conformity criteria for common cements SS EN 206 Concrete - Specification, performance, production and conformity SS EN 1997-1 Eurocode 7: Geotechnical design - Part 1: General rules SS EN 1997-2 Eurocode 7: Geotechnical design - Part 2: Ground investigation and testing Other Standards 1.3.2 BS EN 1008 Mixing water for concrete BS EN 12390-3 Testing hardened concrete - Part 3: Compressive strength of test specimens BS EN 12716 Execution of special geotechnical work - Jet grouting BS 1377 Methods of test for soils for civil engineering purposes BS 5228 Code of practice for noise and vibration control on construction and open sites BS 5930 Code of practice for ground investigations BS 8004 Code of practice for foundations . . Technical References Refer to the following technical references for guidance in carrying out the Works: (a) BRE Digest 251 Assessment of damage in low-rise buildings (b) CIRIA C514 Grouting for ground engineering (c) CIRIA C573 A guide to ground treatment (d) CIRIA C760 Guidance on embedded retaining wall design (e) FHWA GEC 013 (2017) Ground modification methods reference manual - Volume II (f) ICE manual of geotechnical engineering, Volume 1: Geotechnical engineering principles, problematic soils and site investigation TS 299/1065 978 Doc D.2/369 (g) ICE manual of geotechnical engineering, Volume 2: Geotechnical design, construction and verification 1.4 Trade Preamble 1.4.1 Contractor’s Submissions and Proposals Based on available information on ground conditions, existing structures and utilities, operational constraints and the required performance of the improved ground as set out in Section C02-04001:Clause:2.1, engage a qualified specialist to take full responsibility for the following: (a) Plan for the design mix, injection pressures, injection quantities and other related operational parameters before the execution. (b) Plan for the complete grouting operation, including selecting the appropriate construction methods and techniques, equipment, grout mix, parameters and method of spoil containment and disposal. (c) Provide review and adjustment during the execution when necessary. (d) Propose as a response plan in the event that measures taken to control ground movement or/ and vibration do not perform satisfactorily or exceed the specified limits Submit all proposals for the SOs acceptance before work commences. 1.4.1.1 Review of Proposals Engage a qualified and competent PE with proven experience in relevant ground treatment techniques, for the SOs acceptance, for the following: (a) Review the proposals as in Section C02-040-01:1.4.1. (b) Review the quality of the jet grouting works, suitability of the selected jet grouting techniques and operating parameters during the jet grout trial as well as the actual production works. (c) Carry out a Building Damage Assessment on the effects of ground movement to the neighbouring properties due to the Works, for the purpose of establishing suitable values for review levels for instrumentation monitoring. The PE shall endorse all required submissions, including method statement, test reports and proposals on remedial measures, etc. to the SO for acceptance. Submit the curriculum vitae (CV) of the PE to the SO for acceptance. TS 300/1065 978 Doc D.2/370 1.4.1.2 Layout Drawings for Jet Grouting Engage qualified and experienced personnel to prepare co-ordinated layout drawings for the proposed jet grout columns indicating as a minimum, proposed column diameter, spacing, top and bottom level. Submit the drawings endorsed by qualified PE to the SO for acceptance prior to commencing the installation works. 1.4.2 Co-ordination with Other Works Co-ordinate with other contractor’s who may carry out other works at the same time at the Site. Take account of site access, space occupation, safety and safeguarding of adjoining properties and each other’s works. 1.4.3 Condition Survey Where applicable, prior to and upon completion of the site works, carry out a condition survey on adjacent buildings and utilities within the zone of influence in accordance with the requirements of Section C01-020 "Ground Investigation". Submit all records to the SO and adjacent property owners where directed. 1.4.4 Instrumentation and Monitoring Provide instrumentation to monitor ground movement, vibration and condition of adjacent properties. Refer to Section C02-050:Clause:3.1, and drawings for the schedule of instrumentation required. If necessary or as required by the authorities, propose and provide additional instrumentation and monitoring for records. Take cognisance of and co-ordinate with other contractor’s on site who may be carrying out instrumentation and monitoring works to avoid duplication of installation and readings. For general requirements of instrumentation and monitoring works, refer to Section C02-050. 1.4.5 Upholding of Adjoining Properties Accept responsibility for the upholding of the adjoining buildings and roads, footpaths etc., where applicable, together with the mains and services from the time of taking possession of the site through the duration of the Works. 1.4.6 Verification of Site Information 1.4.7 Site Surveys Verify and be satisfied that the information given in the existing site survey plans provided are accurate. If necessary, engage a Registered Surveyor to carry out additional site survey before commencing any work. TS 301/1065 978 Doc D.2/371 1.4.7.1 Additional site investigation Carry out additional ground investigation where additional information is needed for the Works or when directed by the SO. Carry out the Works in compliance with Section C02-010. Carry out the boreholes progressively prior to commencement of the Works in areas according to the contractor’s construction programme. On completion of drilling, backfill the boreholes with a suitable bentonite/cement mix. Submit the location and schedule for the boreholes for the SOs acceptance prior to carrying out the Works. On completion, prepare the site investigation report and submit to the SO for acceptance. 1.4.7.2 Contamination Verify information on contamination identified or believed to be present on site. In the event that contamination is either positively identified or suspected, draw to the attention of all personnel working on site together with the need to take any precautionary measures in handling contaminated materials, groundwater and obnoxious vapours from the ground. 1.4.8 Existing Services Affected by the Works Refer to preliminaries and conditions of contract for the requirements to deal with existing services affected by the Works. 1.4.9 Site Protection Protect all equipment and working area using fencing or other methods as accepted. 1.4.10 Obstructions If any obstructions such as existing fences, structures, footings, boulders, concrete blocks, pipes, drains, driveways or ramp etc. are encountered during drilling, submit proposals for their removal or repositioning of the jet grout column to avoid the obstructions for the SOs acceptance. 1.4.11 Supervision of the Works Engage competent and suitably experienced site personnel to the SOs acceptance, to supervise the field works. Information on items to be checked or requiring monitoring during construction shall be clearly identified and made known to the supervising personnel. 1.4.12 Quality Control Plan Submit and work to a quality control plan as agreed with the SO. Refer to G01-010:Clause:1.4.7. 1.5 Definitions and Abbreviations TS 302/1065 978 Doc D.2/372 1.5.1 Definitions 1.5.1.1 Accredited Testing Laboratory A laboratory accredited under SAC-SINGLAS to carry out specific test(s)required by the Specification. 1.5.1.2 Cement Include all mineral admixtures such as pulverized fuel ash (PFA), ground granulated blast- furnace slag (GGBS), silica fume, etc. that have cementitious properties as proposed in SS EN 197-1. 1.5.1.3 Grout Pumpable material (suspension, solution, emulsion) composed of water, binder and additives, that is used as high energy fluid or for cementing and which develops strength, e.g. measured as unconfined compressive strength, over time. 1.5.1.4 Hydraulic binder Cement or similar product used in aqueous suspension to produce grout. 1.5.1.5 Jet grouted element Volume of soil or weak rock treated through a single borehole. 1.5.1.6 Jet grouting A process of hydraulic disaggregation of the soil or weak rock, which is achieved by a high- energy jet of a fluid which can be the cement agent itself, and its concurrent mixing with, and partial replacement by grout, to create a jet grouted element after hardening of the hydraulic binder. 1.5.1.7 Jet grouting parameters Parameters defined as number and diameter of nozzles, pressure of the fluid(s), flow rate of the fluid(s), pressure and flow of the air (if used), grout or fluid composition, rotation speed of the jet grouting string, and rate of withdrawal or insertion of jet grouting string. 1.5.1.8 Radius of influence Distance of hydraulic disaggregation of soil by the jet, measured from the axis of the monitor that is mounted close to the end of the jet grouting string holding the nozzle. TS 303/1065 978 Doc D.2/373 1.5.1.9 Spoil return Surplus mixture of hydraulically disaggregated soil or weak rock and introduced fluids arising from the jet grouting process, and normally flowing to the ground surface via the annulus of the jetting borehole. 1.5.2 Abbreviations 1.5.2.1 SPT Standard Penetration Test 1.5.2.2 UCS Unconfined Compressive Strength 2 PERFORMANCE REQUIREMENTS 2.1 Contractor’s Proposal 2.1.1 General The required extent of ground treatment by jet grouting method is specified or indicated in the drawings, together with an indication of the required thickness, treatment area percentage and the depth of the grout layer to be installed. Plan the operation and methods taking into account the required improved ground properties as provided in Section C02-040-01:Clause:2.1.2, based on the actual ground conditions revealed by the existing boring logs and/or the additional geotechnical investigation as well as instrumentations and tests carried out during the works. Take into consideration all artificial or natural physical obstructions, site and ground conditions. 2.1.2 Improved Ground Properties After completion of the ground improvement works, carry out coring and tests, with appropriate sample quality class, to the acceptance of the SO to verify that the full thickness of jet grouted element achieves design strength (UCS) and stiffness or deformation characteristics as specified and indicated in the drawings. The cored samples shall satisfy the following: (a) The grouted section of jet grouted element shall not be less than 85% of the total intended grout length/layer thickness specified or as required by the SO. The continuity requirement shall be determined by the ratio of core recovery length to the total core length. In this computation, core recovery length is taken as the total length of recovered core minus the sum of lengths of untreated soils that extend across the entire diameter of the core. TS 304/1065 978 Doc D.2/374 (b) The strength and stiffness shall surpass the confidence level required by the SO. (c) UCS is the design UCS at 28 days unless otherwise specified or directed by the SO. When indirect methods such as SPT, etc. are used to determine the in-situ strength and stiffness of the jet grouted element, proper site-specific correlation would need to be established and agreed with the SO. [Note 1: To specify UCS and Deformation Modulus in the drawings. Deformation modulus can be specified in terms of tangent modulus, or tangent modulus/secant modulus at 50% peak strength, etc. as appropriate. In some practice, target values for jet grouted elements in terms of UCS of 600 kPa and stiffness of 150 MPa have been used. Where applicable, maximum permeability required may also be specified. Note 2: Young’s modulus refers to the secant modulus of the stress strain curve at 50% of failure strength (UCS) as defined above or as specified by the SO. Note 3: Longer duration such as 56 days may be considered in applications where for example, ground granulated blast furnace slag (GGBS) is used in the grout mix design. Note 4: Acceptance criteria for coring stated above should be treated with caution. Good core recovery may be difficult when gravels and/or coarse material are present in the jet grouted element or when the required jet grouted element strength is lower than extremely weak rock. Note 5: Design UCS and stiffness specified should be practically reasonable and take into account the anticipated ground and groundwater conditions. Note 6: Jet grouted element formed in non-homogeneous ground condition would exhibit inherent variability of test results, this should be considered accordingly in the overall design and acceptance criteria.] Note 7: Guidance in determining characteristic strength of the jet grouted element from test results is provided in BS EN 12716.] 2.1.3 Control of Ground Movement and Vibration Take care in the design and execution of the works to control settlement, heave or horizontal movement, and vibration recorded at any monitoring point to avoid damage to buildings or utilities in the vicinity of the Works. Propose suitable ground movement control criteria for SOs acceptance, taking into account the vulnerability and sensitivity of the adjacent properties and appropriate limits that meet the statutory requirements after carrying out the damage assessment as specified in Section C02- 04001:Clause:1.4.1.1. State the values for check, alert and work suspension levels in the submission in accordance with the statutory requirements. Notwithstanding the above, ensure that ground movements and vibrations arising from the Works do not exceed the limits provided as follows: (a) Generally, comply with the requirements of BS 5228-1. (b) Unless otherwise directed by the SO, refer to Section C02-050:Clause:4.2.2 for general restrictions on ground movements and vibration limits for adjacent structures where relevant. TS 305/1065 978 Doc D.2/375 3 MATERIALS AND EQUIPMENT 3.1 General Refer to BS EN 12716 for general requirements of materials and equipment for jet grouting. 3.2 Flushing Medium Use non-toxic materials as flushing medium for drilling or as part of the grout mix subject to the acceptance of the SO. 3.3 Water Water used for grout shall be clean and contain no chemicals deleterious to the setting and strength development of the grout. Mixing water shall comply with BS EN 1008 and SS EN 206. 3.4 Other Materials Use any other materials or chemicals for the works only with the approval of the SO. Ensure that all materials are non-toxic and non-corrosive and are protected from contamination or pollution at all times. 3.5 Drilling Rig and Grouting Plant Equip the drilling rig with pressure gauges/devices, flow meters and other measuring devices, including a monitor mounted close to the end of the jet grouting string holding the nozzle to allow regular checks on critical operating parameters such as fluid pressure, grout injected rate, monitor rotation and withdrawal rate. Automated instrumentation that allows continuous recording of these data should be used for monitoring. Maintain all plant and equipment used in good operating condition at all times. 4 WORKMANSHIP 4.1 Jet Grout 4.1.1 General Refer to BS EN 12716 on the requirements of workmanship for jet grouting. 4.1.2 Storage and Handling of Grout Materials Deliver grout materials in undamaged unopened containers bearing the manufacturer’s original labels. Store and handle in accordance with the recommendations of the manufacturer. TS 306/1065 978 Doc D.2/376 4.1.3 Collection and Disposal of Effluent Collect all drilling and grouting effluent in trenches, pits or tanks and do not allow spreading over or outside the Site. Take measures to ensure all effluent is not allowed to enter the public drainage system. Remove all effluent from the Site and dispose of it in accordance with the regulations of the appropriate authority. 4.2 Control of Ground Movements 4.2.1 Construction Sequence Ensure that the jet grouting operation follows the agreed method and sequence, and to the approval of the SO. 4.2.2 Grouting in Soft Clay Jet grouting in thick soft clay deposits may lead to significant ground heave/movement. The following are possible measures to control ground movements when jet grouting in thick soft clay is carried out and may be specified according to individual project circumstances: 4.2.3 (a) Minimise the angle of inclination of the drill holes, as far as it is practical. (b) Maintain the drill hole size such that slurry/spoils outflow can be maintained. Re-drill the hole whenever necessary. Depending on observations on site, be ready to change the drill diameter whenever necessary. (c) When loose sand and other collapsible soils are present and the drill hole is to be significantly inclined, use of casings to prevent drill hole collapse is advised. (d) Ensure that an adequate size of annulus is provided for a free flow of spoil return at all times. Filling of Empty Bore Fill the empty bore above the jet grout column with grout during the extraction of grouting monitor that is mounted close to the end of the jet grouting string holding the nozzle. 4.3 Obstructions If obstructions consisting of artificial or man-made materials or structures in the ground, are encountered, review and agree with the SO, on steps to be taken to ensure that the affected ground is treated satisfactorily. 4.4 Tolerances TS 307/1065 978 Doc D.2/377 4.4.1 Setting Out Establish permanent datum level points, base lines and grid lines. Maintain these setting out guides as necessary to the satisfaction of the SO. Set out the position of each treatment point with a suitable identifiable pin or marker. Check that each treatment point has a unique reference number for record purposes. 4.4.2 Position The maximum permitted deviation of the grout-hole centre from the centre shown in the setting- out is 75 mm in any direction at commencing surface level. 4.4.3 Verticality The maximum permitted deviation of the finished grout hole from the vertical axis for vertical jet grouting at any level is 1 in 75. 4.5 Protection to Treated Areas Ensure that during the course of the Works, displacement or damage does not occur to completed areas of ground treatment which can impair their performance. Submit to the SO the planned sequence and timing for the Works, having regard to the avoidance of damage to completed areas of ground treatment. 4.6 Completion of the Works After completing the grouting procedures, remove all grouting accessories or similar elements, and backfill the drill holes in the ground with cement grout. Restore the Works to its original condition as approved by the SO. 5 VERIFICATION AND SUBMISSIONS 5.1 Submission 5.1.1 Method Statement for Jet Grouting Submit a detailed method statement to the SO for acceptance before jet grouting work commences. Include the following: (a) Proposals for a jet grouting trial, including the location and monitoring of the trial (b) Full details of proposed plant and method of drilling, including proposed flushing medium (c) Specification and details of the equipment to be used such as grout mixers, injection pumps, injection nozzles and drilling rigs and jet grout equipment arrangement TS 308/1065 978 Doc D.2/378 (d) Details of the method to monitor the location, depth and verticality of the jet grout nozzles (e) The selected operational parameters for the jet grouting, including injection pressure and rate of injection of the air, water and grout (as appropriate) withdrawal rate and rotation rate, and injection nozzle size, type and number (f) Method of measuring and controlling the operational parameters (g) Depth and thickness of jet grout layer, including a layout plan showing installation location of each jet grout column, the column size, depth, overlap and spacing (h) Proposed methods for the setting out of each grout column (i) Sequence of work for installing each grout column and the overall sequence of construction for the jet grout layer, taking into consideration of the anticipated time required for installation of the ground treatment from commencement of site works to completion (j) Plan the layout of jet grout columns to avoid possibility of shadows as a result of obstruction in the line of jetting such as in the case of irregular retaining walls, e.g. steel pipe piles and sheet piles (k) Details of method to avoid critical utilities (l) Method to complete a grout column in case grouting process is discontinued before the column is completed due to equipment breakdown or other reasons (m) The target strength and stiffness of the grout columns and the proposed grout mix (n) Methods used to monitor and control ground movement during drilling and grouting (o) The method of monitoring and checking the stability of neighbouring properties, roads, utilities and other underground structures (p) Methods of testing for the quality of the grout mix and the jet grouted elements. (q) Technical details and test reports on chemical admixtures (if any) (r) Details of storage and handling of grout materials (s) The methods used for collecting, transporting and disposal of the slurry (t) Risk identification, risk management and environmental hazards analysis (u) Samples of field data collection forms/printouts and daily field reports TS 309/1065 978 Doc D.2/379 5.1.2 Programme Submit a provisional and detailed programme for the execution of the Works prior to commencement. Provide a daily update of the intended programme of ground treatment for the following day and shall give 24 hours notice of the intention to work outside normal hours and over weekends, where this is permitted. 5.1.3 Quality Control Manual Submit a quality control manual containing a Quality Assurance / Quality Control (QA/QC) programme for the Works to the SO for acceptance within a directed time frame. The quality control manual is to include at least information on the following: 5.2 (a) Quality policy (b) Organisational charts and responsibilities (c) Internal quality control and audits (d) Facilities and equipment (e) Calibration and testing of equipment (f) Testing and inspection procedures (g) Subcontractor’s and suppliers Calibration of Equipment Calibrate all measuring devices before commencement of the Works, and submit the records of the calibration done not earlier than 6 months to the SO. 5.3 Jet Grouting Trial or Preliminary Field Tests TS 310/1065 978 Doc D.2/380 5.3.1 General Before executing the proposed main jet grouting works, carry out a jet grouting trial or preliminary field tests to demonstrate the suitability of the proposed methods. Perform the jet grouting trial in full accordance with the accepted method statement. Review the method statement after taking account of the results of the trial and re-submit a revised method statement if necessary. The revised method statement shall be subject to the SOs acceptance prior to the commencement of the main jet grouting works. Location of the trial should be such that its sub-surface conditions, inclusive of material type and depth, are representative of the conditions to be treated in the main jet grouting works. In the case that multiple layers of jet grouting are required in the main jet grouting works, conduct the trial on multiple layers. Conduct the trial using the materials and equipment to be used in the main jet grouting works. 5.3.2 Details of Trial Ensure that the trial jet grouting consists of a series of overlapping columns formed at similar depth and ground conditions as shown in the drawings. 5.3.3 Use of Trial Grout Columns Unless otherwise accepted by the SO, do not use trial jet grout columns as working jet grout columns. 5.3.4 Monitoring Monitor ground movement during jet grouting works. Specifics of the monitoring shall be submitted to and agreed with the SO. 5.3.5 Results Submit the results of the trial jet grouting to the SO, together with an interpretative report assessing the results of the trial and proposing any necessary changes to the method statement. 5.3.6 Rejection In the event that the jet grouting trial fails to satisfy the required acceptance criteria, reject the method that is used for the trial. Propose remedial measures to rectify the defects and carry out another trial for the acceptance of the SO to demonstrate the suitability of the measures TS 311/1065 978 Doc D.2/381 5.3.7 Quality Control of Jet Grout Trial Propose in details and carry out tests to the acceptance of the SO to verify that the full thickness of the trial jet grout layer achieves in-situ strength and stiffness as specified in the design or indicated in the drawings or as directed by the SO. Conduct tests for the trial jet grouting works to demonstrate the effectiveness of the trial jet grouting by obtaining cores through the full depth of the jet grouted element at boreholes as shown on the drawings. Coring should be conducted at overlapping locations to ensure the required diameter is achieved. Fully log the cores in accordance with BS 5930 and test the samples for strength and stiffness in accordance with BS EN 12390-3. Refer to BS EN 12716 on the sample quality class for tests as appropriate. When indirect test method such as SPT is used for assessing the strength and stiffness of the jet grouted element, carry out a minimum of 3 additional SPT tests at the borehole(s) located at the overlapping areas where cores are retrieved. Use the strength and stiffness test results obtained from the cores correlate with SPT N values taken at comparable depths and this correlation shall be agreed with the SO and used as the basis for indirect tests conducted for subsequent quality control. [Note 1: Use past references of comparable experience instead of a single project to determine correlation. In most instances, the data from one project is not adequate.] Where the grouted layer is to reduce permeability, perform permeability tests on core samples for the acceptance of the SO. [Note 2: There is no readily available permeability equation for testing the permeability of a finite volume material in a soil of different permeability. If general permeability equation is used, the test results should account for such application and adjustments may be required to the results.] [Note 3: Refer to BS EN 12716 on permeability tests.] Carry out the field testing and laboratory testing on or before 28 days or other duration from the formation of trial jet grouting as agreed with the SO. 5.3.8 Report Compile, evaluate and assess the results of the testing and the resulting correlations in reports which shall be endorsed by both the qualified specialist for the jet grouting works and the qualified, competent and experienced PE, and submit with recommendations for the SOs acceptance prior to commencement of the production jet grouting works. 5.4 Quality Control of Main Jet Grouting Works 5.4.1 Grout Mix Check the grout mix by measuring the specific gravity using a mud balance. Conduct at random, but not less than twice a day per rig, for every rig that is grouting that day. TS 312/1065 978 Doc D.2/382 5.4.2 Spoil return Ensure there is continuous flow of spoil return through visual observation. Check the specific gravity of the spoil return using mud balance if unexpected behaviour of the spoil return is observed. 5.4.3 Works Testing Carry out all necessary testing of the contract works to demonstrate full compliance with the specified performance requirements. Perform these tests within 28 days of jet grouting. Carry out the following tests as directed by SO. 5.4.3.1 SPT Tests SPT tests may be used as a supplementary test for direct coring test provided a site-specific correlation has been established during trial jet grouting. When SPT test is used, it should be conducted at the overlapping areas of the jet grouted element. Unless otherwise directed by the SO, each cored hole required may be replaced by 2 boreholes with SPT carried out at the top, middle and bottom level of the jet grouted element at each borehole. However, the replacement of coring with SPT shall be limited to no more than 50% of the total number of coring tests specified. 5.4.3.2 Core Samples Carry out coring tests for core samples at locations as indicated in the drawings or agreed with the SO. Unless otherwise agreed by the SO, the number of tests shall not be less than the minimum test frequency as provided in BS EN 12716. To minimise sample disturbance, triple core barrel and large diameter sampler shall be used for coring. Coring shall be carried out through the full depth of the jet grouted element at the overlapping areas. A minimum of 3 samples shall be taken from the top, middle and bottom of each cored hole for testing of strength and stiffness requirements. 5.4.3.3 Laboratory Tests Carry out the laboratory tests on the test samples taken from the cores obtained at an accredited testing laboratory. The quality requirements of the jet grouted element is considered satisfactory if the desired acceptance criteria are achieved for each set of at least 3 core samples being tested at each location. Refer to BS EN 12716 on sample quality. (a) Perform unconfined compression tests with stress-strain measurement on the core samples to evaluate the UCS and Young’s modulus or Deformation Modulus as specified. (b) Perform permeability tests on core samples to the acceptance of the SO, where the grouted layer is to reduce permeability. TS 313/1065 978 Doc D.2/383 5.4.4 Acceptance Jet grouted element will not be accepted if any zone of treated soil does not meet or satisfy the performance requirements. Where the specified jet grout performance requirements are not met, repeat and retest the grouting to the SOs satisfaction. 5.4.5 Remedial Measures In the event that the tests fail to satisfy the required jet grouted elements quality and condition on continuity, reject the portion of the works represented by the tests unless otherwise agreed. Propose remedial measures to rectify the unsatisfactory works in the affected area to the acceptance of the SO. 5.4.6 Report on Test Results Submit a full report on the test results, including assessment of the results and any proposals for remedial work to the SO. The report shall include the following information: (a) The depth of the start and finish of each core run (b) The core recovery length for each core run and percentage of total core recovery with reference to definition in Section C02-040-01:Clause: (c) The date when each section of the core was drilled (d) Photograph of the core in core box taken under natural light with standard scale and colour chart (e) Results of field and laboratory testing undertaken to ascertain the quality of the jet grouted element 5.5 Records and Reports 5.5.1 Records Keep careful records for each point of installation. Submit all grouting records to the SO. The records shall include for each jet grout column: (a) Location and reference number (b) Date and time of installation (c) Reduced levels for the ground level, the top and base of the jet grout column (d) Inclination of the jet grout column (e) Details of casing size and length if used to prevent collapse of drill hole TS 314/1065 978 Doc D.2/384 5.5.2 (f) Drilling rig identification (g) Length of drilling and type of flushing medium (h) Duration and timing of each major activity (i) All operating parameters as used for the jet grout column installation, including water pressure, air pressure, grout pressure (as appropriate) and rate of rotation and withdrawal flow rate, nozzle size, nozzle type and number of nozzles (j) Volume of grout, including grout ingredients and mix proportions used (k) Grout density (l) Observations on spoil return, breakdowns, interruptions during drilling, grouting and any other relevant events (m) Display monitoring data in an acceptable continuous graphical format that facilitates rapid visual evaluation of the results of the Work (n) Pre-cutting details, if used. Summary Report At the completion of any continuous block or section of Jet Grouting, prepare a summary report. This report shall provide: (a) As built drawings showing the layout, inclination and installed depth of each jet grout column (b) The results of all including additional geotechnical investigation carried out related to the jet grouting works (c) The location and final values of all monitoring carried out during and after the jet grouting works, with graphs showing the development trend of movement, load or pressure with time throughout the jet grouting works (d) The results of the quality control testing carried out at site and proposed remedial works, where applicable. TS 315/1065 978 Doc D.2/385 (10) C02-050 Instrumentation and Monitoring TS 316/1065 978 Doc D.2/386 1 GENERAL Read this Section with G01-010 "General Requirements" and all other contract documents. 1.1 Scope This Section covers the requirements for instrumentation using a number of different methods and monitoring of the various construction works for the following: (a) Determine ground movements as a result of construction. (b) Determine the effects of settlement on existing structures, services and utilities. (c) Provide settlement and movement data in a form that will allow direct comparison with performance criteria and design expectations. In addition, instrumentation is installed to provide construction control, design verification, safety, legal protection and ground investigation data. 1.2 Related Sections Read this Section in conjunction with the relevant requirements of the following section: C02-010 1.3 Investigation Standards, Codes, Regulations and Technical References TS 317/1065 978 Doc D.2/387 1.3.1 Standards and Codes Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant requirements of the standards and codes listed below or referenced in the body of the Specification. Alternative standards and codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative standards and codes comply with the requirements of the standards specified. All standards and codes quoted are the current version, unless specific year references are noted. In the event that the standards or codes are partially superseded or have become obsolete, refer to the current edition or the approved substitution for the relevant clauses. Singapore Standards SS EN 1997-1 Eurocode 7 - Geotechnical design - Part 1: General rules SS EN 1997-2 Eurocode 7: Geotechnical design - Part 2: Ground investigation and testing Other Standards 1.3.2 BS EN ISO 18674-1 Geotechnical investigation and testing - Geotechnical monitoring by field instrumentation - Part 1: General rules BS EN ISO 18674-2 Geotechnical investigation and testing - Geotechnical monitoring by field instrumentation - Part 2: Measurements along a line - extensometers BS EN ISO 18674-3 Geotechnical investigation and testing - Geotechnical monitoring by field instrumentation - Part 3: Measurements across a line - inclinometers BS8574 Code of practice for the management of geotechnical data for ground engineering projects Technical References Refer to the following technical references for guidance in carrying out the Works: (a) Land Surveyors Board Singapore (LSB) Directives on Engineering & Hydrographic Survey Practices, Version 4.0, 2013 1.4 Trade Preamble 1.4.1 Submissions and Proposals Based on the information issued and the instrumentation and monitoring plan or as directed by the SO, propose and submit the following to the SO for acceptance: (a) Select suitable make and model of the instrumentation for the Project. (b) Develop methods and details of the instrumentation installation and monitoring. (c) Propose suitable schedule for taking the monitoring reading and production of reporting records. TS 318/1065 978 Doc D.2/388 1.4.2 Co-ordination with Other Works Co-ordinate with other contractors who may carry out other works at the same time at the site. Consider site access, space occupation, safety and safeguarding of adjoining properties and each others works. 1.4.3 Existing Services Affected by the Works Refer to preliminaries and conditions of contract for the requirements to deal with existing services affected by the Works. 1.4.4 Protection and Maintenance of Instruments Take all necessary precautions to protect the instruments and maintain the instruments in good working order after commissioning. For all instruments which project through and above the ground, take special precautions to provide protection from vehicles and plant, including substantial and readily visible barriers at a distance of 750 mm around each instrument. Heavy compaction equipment shall not approach within 1.5 m of projecting instruments. Damaged instruments shall be replaced or repaired within 7 days unless otherwise agreed by the SO. 1.4.5 Labelling and Marking of Instruments Establish and agree with the SO on a reference system for all instruments prior to installation, for easy retrieval of data for any particular location. Label all instruments with their reference number at the location where readings or measurements are taken. The labelling shall be permanent using a method or material to be agreed on with the SO. Link with QR code to a secure central database for documentation and information on all instruments, readings and data. 1.4.6 Quality Control Plan Submit and work to a quality control plan as agreed with the SO. Refer to the G01- 010:Clause:1.4.7. 1.4.7 Specialist Personnel 1.4.7.1 Borehole Installation Engage qualified crew of not less than 2 men for the SOs acceptance for the operation of each boring or drilling rig. Engage qualified personnel for the SOs acceptance for every 2 drilling or boring rigs to supervise all drilling works and to accurately record all drilling/boring and testing. TS 319/1065 978 Doc D.2/389 1.4.7.2 Registered Land Surveyor Engage a Registered Land Surveyor for surveying of settlement of the ground surface, roads, drains, buildings, and other structures. 1.4.7.3 Instrumentation Installer Engage qualified and suitably experienced personnel with the SOs acceptance to install and record readings for all the instruments. 1.4.7.4 Instrumentation Specialist Engage at least one Instrumentation Specialist with the SOs acceptance to co-ordinate all instrumentation and monitoring works, including submission of method statements, calibration, installation, data acquisition processing and verification, and presentation and reporting of instrumentation and monitoring results. The Instrumentation Specialist shall be qualified with relevant experience in the installation and monitoring of instruments, database management and interpretation of instrumentation results for geotechnical and structural engineering purposes. Evidence of experience, including curricula vitae (CVs) and records of previous similar works undertaken shall be provided to the SO. S1.4.8 Safety Provide safety precautions to comply with all current legislation and regulations, notably: a. Building Control Regulations b. Code of Practice for Traffic Control at Work Zone c. Factories (Building Operations and Works of Engineering Construction) Regulations d. Factories Act e. SS CP 79 Safety management system for construction worksites For works within LTA Railway Protection Zone, ensure the works comply fully with Code of Practice for Railway Protection. 2 PERFORMANCE REQUIREMENTS 2.1 Quality of Instrumentation TS 320/1065 978 Doc D.2/390 2.1.1 General Provide instruments and measuring devices manufactured by companies with established standards and proven experience in the field of construction or geotechnical instrumentation. Engage materials, designs and construction of such quality to provide robust, corrosion and vibration resistant instruments. Use only reliable instruments with a satisfactory proven working life and are fully functional through the duration of the Works. The accuracy and dependability of the equipment shall not be significantly affected by changes in temperature, humidity, stray currents or contaminants that may be encountered. 2.1.2 Survey Equipment All surveying equipment used in conjunction with the monitoring of instrumentation, including measuring tapes, precise levels, theodolites, digital levels and Total Station that combines Electronic Distance Measurement Equipment with a digital theodolite and electronic data recording, shall be maintained and calibrated as required by the manufacturers. Certificates of calibration for all equipment shall be submitted and approved by the SO prior to carrying out the field work. 2.1.3 Electrical Interference Ensure that electrical instrumentation is not adversely affected by other temporary or permanent electrical services and equipment, and does not affect any other services, activities or equipment within or adjacent to the Works. Where transformers are used, they shall have safety cut-out devices to guard against overheating. 2.1.4 Stabilising Electronic Readout Devices All electronic readout devices and transducers shall be shaded from direct sunlight during use. Probes which are used inside access tubes shall be placed inside the tube and allowed to come to a stable temperature for at least 10 minutes before use. Zero or starting values shall only be taken after temperature stabilisation is complete. 2.2 Field Measurements and Monitoring Instrumentation, measurements and monitoring shall be in accordance with BS ISO 18674 for the performance monitoring of the ground, of structures interacting with the ground, of geotechnical fills, and of geotechnical works as part of the geotechnical investigation and testing according to SS EN 1997-1 and SS EN 1997-2. 3 MATERIAL/EQUIPMENT TS 321/1065 978 Doc D.2/391 3.1 Schedule of Instrumentation Provide for SOs acceptance a schedule of instrumentation for the instruments tabulated in Table 1 below - showing instrument types, quantities, locations, minimum frequency of reading and duration of reading; and detailed information in drawings or plans where practicable. Carry out instrumentation and monitoring works as per schedule and as indicated in the drawings or as directed by the SO. Table 1. Instruments for schedule of instrumentation 3.2 . Instruments (if applicable) 1. Inclinometer (manual read) 2. In-place inclinometers (remote read) 3. Magnetic extensometers 4. Rod extensometers 5. Tape extensometers 6. Deep levelling datum 7. Levels / settlement marker 8. Piezometers: Casagrande 9. Piezometers: Vibrating wire 10. Vibration monitors 11. Settlement Markers 12. Tell-tales 13. Reflector targets 14. Temperature sensors 15. Strain gauges Instrumentation and monitoring plan An instrumentation and monitoring plan endorsed by the instrumentation specialists, and qualified, competent and experienced PE, and Registered Surveyor (for drawing information containing coordinates and Reduced Levels) to be submitted and approved by the SO shall contain at least the following, where applicable: (a) Layout and location of neighbouring structures in relation to the underground building works. (b) Numbers, types, locations, details and other particulars of instruments for monitoring forces and movement of structural elements, building and ground movements, and variations in the groundwater or piezometric levels. (c) Frequency and duration of monitoring. (d) Allowable ground or building movement limits. (e) Allowable vibration limits. TS 322/1065 978 Doc D.2/392 (f) Long-term instrumentation, monitoring and maintenance requirements. 3.3 Remote Data Acquisition 3.3.1 Remote Data Acquisition System 3.3.1.1 Overall system Propose for the SOs acceptance on the provision of remote data acquisition to be undertaken for the Works, detailing the equipment types, locations, database and its acquisition, storage, maintenance and retrieval system. Show information in drawings where practical and as appropriate. Use of readout boxes for remote readout. 3.3.1.2 Remote readout facilities All electrical measuring devices shall be capable of being read remotely using portable readout units connected via readout boxes. Supply readout units together with leads for plugging into the measuring device and readout boxes. 3.3.1.3 Instrument range Readout boxes shall be capable of being placed up to 200 m from their associated instrumentation or transducers with the specified accuracy of the instrumentation maintained. 3.3.1.4 Remote readout cover boxes Readout cover boxes shall be made of robust water-resistant metal construction with lockable sealed doors. Ensure all cable entries to the cover boxes are through watertight glands. 3.3.1.5 Link to site office Include modem link and connection for direct computer link to allow reading for all remotely read instrumentation and make links to the site office(s) as directed by the SO. Use readout unit devices with facilities for recording monitoring data directly onto tape or magnetic disc for subsequent computer processing. 3.3.2 Logger Stations TS 323/1065 978 Doc D.2/393 3.3.2.1 General Use reliable and safe remote data collection systems with back-up facilities in the event of mains power failure. Prove the reliability of the logger prior installation by demonstration and records of previous works. Use a flex outlet without switches for all loggers when connected to the mains electrical supply. Do not use plug sockets. 3.3.2.2 Station Requirements Logger stations shall be as follows: 3.3.3 (a) Capable of reading all instrument types proposed for each structure. (b) Programmable to log data at any specified interval, including real-time. (c) Capable of accepting new instruments to extend or repair the proposed system. (d) Easily connected to an external computer by either a direct hard wire or modem link as agreed with the SO. (e) Unaffected by external electrical influence and shall not affect other electrical equipment. (f) Safe: in the event of overheating or short circuiting, the device shall shut down. (g) Logger stations shall collect the cabling from various remotely read instruments and from local terminal boxes, so that monitoring can be conveniently carried out from a single position close to any instrumented section. Types of Cables Use cabling and connectors that are robust, water resistant and corrosion resistant for instrumentation. Use only low smoke zero halon cabling for all cables, which is durable and suitable for the proposed locations in the Works. Use items that are extinguishable non-metallic and emit no toxic fumes in the event of fire. TS 324/1065 978 Doc D.2/394 3.4 Boreholes for Instruments Boreholes for instruments shall be drilled and formed by an approved method that provides a clean and stable hole of the required diameter to the correct depth for the installation of the instruments. Boreholes shall be cased to full depth unless strata are sufficiently competent for the boreholes to be stable under dry conditions. Clean water is required for the drilling and formation of the boreholes. Drilling mud or polymer additives shall only be used with the approval of the SO. In the case of installation of piezometers, drilling mud or polymer additives shall not be permitted. During drilling, take care to ensure that minimum material is lost from outside the casing. Do not allow surging of casing and minimise flushing of drilling water up the outside of the casing. The method of forming boreholes, including the procedure for advancing casing, shall be submitted to the SO for approval before commencement of the Works. 3.5 Grouting of Boreholes Grouting is required for part or entire depth of all boreholes formed for the purpose of installation of instruments. The grout shall be of a bentonite-cement mixture to achieve an appropriate mix for the Site. Conduct trials on different mixes of bentonite-cement to ascertain the relationship with strength. The grout mix and the grouting method shall be submitted and approved by the SO. 3.6 Probe Inclinometer (Manual Read) 3.6.1 General Inclinometers shall take the form of an access tube with 4 keyways in pairs at right angles. The orientation of the keyways shall be parallel to and perpendicular to the orientation of any tunnel, excavation, retaining walls or structures, or otherwise as accepted by the SO. [Note 1: Construction tolerance in keyways would compromise accuracy in the B-B direction readings when probe wheel is aligned in the A-A direction. If deformation in both directions of the keyways is crucial, e.g. monitoring movement of a single pile, repeat readings taking in both directions by aligning the probe wheels in each direction.] 3.6.2 Probe The probe used to take measurements shall have the following features: (a) A wheelbase of 500 mm (b) A measurement range of 30°or greater from vertical (c) A resolution of 0.02 mm or greater per 500 mm with a repeatability of 0.003 degrees TS 325/1065 978 Doc D.2/395 (d) A minimum radius curve for retrieval of 2.2 m or less (e) A working temperature range of -20°C to +50°C or greater (f) A construction (externally) of stainless steel [Note 1: The measurement shall be within the calibration range.] 3.6.3 Data Recorder The inclinometer data recorder unit shall display the readings from the inclinometer probe on an alphanumeric display. The readout unit shall be powered by a rechargeable battery with a minimum life of 16 hours of continuous use or more between charges. A backup battery shall be incorporated to keep data secure for a minimum of 72 hours on depletion of primary power source. Signal shall be emitted to confirm power failure and confirm that the battery pack is operative. A suitable automatic battery charger shall be supplied with the readout unit. Data recorder with a solid-state data storage unit shall have a minimum storage and retrieval capacity of 30,000 data points directly from the probe together with time of measurement. The readout unit shall have the following features: (a) Scanning of stored data (b) Display of errors as readings are being obtained (c) Display of mean deviation and cumulative deviation of any one set of readings (d) Graphical display of displacement profile between any 2 sets of readings (e) Backlit LCD display A calibration frame shall be supplied to enable the inclinometer calibration to be checked at vertical and 10 degrees either side of vertical. 3.6.4 System Accuracy The system accuracy of the inclinometer shall be ±6 mm per 25 m of casing or better. The inclinometer and logging system shall be capable of recording movements in both directions or biaxial type. Refer to specific standards or manufacturer’s specifications or guides, wherever possible, on tolerances, characteristics, accuracy of instrumentation and monitoring for the acceptance of SO. TS 326/1065 978 Doc D.2/396 3.6.5 Calibration Device Provide a calibration device with the instrument, which calibrates both the probe and the portable readout unit for SOs acceptance. 3.7 In-place Inclinometers (Remote Read) 3.7.1 General In-place inclinometer consists of one or more built-in for measurement of the inclination at specific locations on a measuring line without removing the instrument. 3.7.2 Sensors Resolution of each sensor shall be 0.04 mm per m or better and the measuring range to be at least ±10 degrees. The precision of the sensor shall be ±0.1 mm per m. The allowable maximum gauge length (spacing between sensors) shall be no greater than 3 m. The operating temperature range shall be from -20°C to 50°C and the compensated temperature range to be from 0°C to 45°C. 3.7.3 Electrolevel System Where specified, use an electrolevel inclinometer consisting of a waterproof sensor that is remotely monitored using a computer data logging system. Use a datalogger capable of at least 14 daysâ operation in the event of power failure. 3.7.4 System Accuracy The inclinometer and logging system shall be capable of recording movements in both directions (i.e. biaxial). The system accuracy of the inclinometer shall be ±6 mm over a depth of 25 m or better. Refer to specific standards or manufacturer’s specifications or guides, wherever possible, on tolerances, characteristics, accuracy of instrumentation and monitoring, for the acceptance of SO. 3.8 Extensometers 3.8.1 Magnetic Extensometers 3.8.1.1 General Use magnetic extensometers in the form of a series of magnetic rings ("spider magnets") fixed into a maximum 150 mm diameter borehole with plastic tubing of nominal 75 mm minimum internal diameter, allowing access to magnetic points for the measurement of settlement. TS 327/1065 978 Doc D.2/397 3.8.1.2 Description The magnetic extensometer shall consist of an access tube and a series of magnetic targets which are free to slide up and down the outside of the tube, together with a datum magnet which is fixed to the tube near its base. Reference shall be made to the top of the access tube which will need to be measured by standard levelling techniques. Unless otherwise agreed by the SO, the access tube shall be a rigid PVC tube with outside diameter of 33.5 mm and inside diameter of 24.5 mm, with threaded ends that provide both an internal and external flush coupling. A rigid PVC endcap shall be fixed to the lower end of the series of tubes. All joints shall be sealed with a suitable PVC solvent cement. Where required by the SO, compression/extension tubes shall be provided to allow axial movement of access tubes to minimise distortion due to vertical strain. The tubes shall have threaded ends to provide an internally and externally flush coupled joint. The smaller diameter end tubes are fitted with "O" rings or equivalent, and are free to slide within the larger diameter central cylinder. The minimum allowable compression and extension length shall not be smaller than 0.6 m and 1.0 m respectively. 3.8.1.3 System Precision The system precision shall be ±1.0 mm. Check that the reading system is reliable and requires minimal maintenance over the required monitoring period. Thermal or other influences shall be negligible. Refer to specific standards or manufacturer’s specifications or guides, wherever possible, on tolerances, characteristics, accuracy of instrumentation and monitoring, for SOs acceptance. 3.8.2 Rod Extensometers 3.8.2.1 General Use rod extensometers in the form of a rod anchored at the remote end of the borehole passing into a plastic tube fixed in a reference collar at the open end of the hole. 3.8.2.2 System Accuracy The measurement system shall have an overall accuracy of ±0.25 mm. Refer to specific standards or manufacturer’s specifications or guides, wherever possible, on tolerances, characteristics, accuracy of instrumentation and monitoring, for SOs acceptance. S3.8.2.3 Restrictions on Rods Install no more than six rods in a single hole with each rod of a different length so that displacements at various borehole depths may be recorded. Where more than six rods are required, prepare another borehole as close as possible to the initial hole and rods set at alternate depths in each hole. TS 328/1065 978 Doc D.2/398 S3.8.2.4 Materials Rods to be fabricated from stainless steel. The grade of steel rod shall suit the environment and duration of the project. Make provision for threading the anchor points onto the rod. S3.8.2.5 Measurement of Relative Movement Measure relative movement between the end anchor and the reference collar by an automated measurement device (an electrical transducer) registering on the free end of the rod and by manual means using a system to the acceptance of the SO. Extend the reading range beyond that of the measurement device by a range adjustment device fitted at the reference collar. S3.8.2.6 Measuring Head Measuring head to be of design to allow manual readings to be taken. Extensometers to be of design that make the measurement of both elongations and reductions in the length between anchorage point and measuring head possible. Undertake remote reading using the electrical transducers linked to a logger station, with an overall accuracy of +0.25 mm and with a measuring range of 150 mm. In the event that movements potentially exceed 150 mm, make adjustment to allow continued monitoring. Use transducers that are waterproof to 15bar. Cabling to the terminal box to be capable of accepting up to six extensometers from each hole. Provide a battery operated digital readout device capable of reading to the required overall accuracy. 3.8.3 Tape Extensometers 3.8.3.1 General Use a tape extensometer comprising a steel tape, a portable measuring instrument with metric dial calliper and a pair of anchor clips. 3.8.3.2 System Accuracy Use a tape extensometer that is capable of being read to ±0.15 mm and have a range of 20 m. Demonstrate a repeatability of reading to ±0.15 mm prior to use. Refer to specific standards or manufacturer’s specifications or guides, wherever possible, on tolerances, characteristics, accuracy of instrumentation and monitoring, to the acceptance of SO. TS 329/1065 978 Doc D.2/399 3.8.4 High Precision Optical 3D Measuring Method Propose for the SOs acceptance on the use and installation of Optical 3D displacement measuring method using purpose-built glass prism (surveying) reflectors with high precision Total Station that combines Electronic Distance Measurement with a digital theodolite and electronic data recording, to produce high accuracy three-dimensional coordinates, and compute angles and distances between the points under survey. [Note 1: By repeated measurements of the 3D measuring points, time-dependent diagrams that describe the convergence of tunnel wall deformation behaviour of measuring points with high precision shall be produced.] 3.8.4.1 Total Station Measurement Accuracy The Total Station measurement shall have the following measurement accuracy: 3.9 S3.9 (a) angular accuracy of 1.0 arc second and (b) distance measurement accuracy at ± 1 mm + 2 parts per million (ppm). Not In Use Deep Levelling Datum Deep Levelling Datum shall comprise a 25 mm galvanised steel rod cast into a 250 mm diameter grout filled steel casing positioned within a 300 mm diameter steel casing. Fill the annulus between the two casings with grease. The top of the 25 mm steel rod shall be domed and centre punched. 3.10 Levels 3.10.1 Standard Levelling Use a basic optical level of an approved make and specification with a single measurement precision of ±1 mm with a standard measuring staff. The accuracy of results here should be within ±3 mm. Refer to specific standards or manufacturer’s specifications or guides, wherever possible, on tolerances, characteristics, accuracy of instrumentation and monitoring, to acceptance of SO. TS 330/1065 978 Doc D.2/400 3.10.2 Automatic (optical) level Use a basic automatic (optical) level that consists of a micrometer attachment with a valid calibration certificate and sectional levelling staves to conduct double-run levelling with measurement precision within ±2 mm. Final accuracy of instrumentation and monitoring subject to acceptance of SO. Refer to Land Surveyors Board (LSB) Directives on Engineering & Hydrographic Survey Practices for full details on levelling survey’s standard and accuracy order. 3.10.3 Precise Levelling Where more accurate levelling with submillimetre accuracy is required, propose for the SOs acceptance on the provision of precise-levelling instruments and methodology, including the use of robust tripods, that have the accuracy with high precision necessary for the purpose of preciselevelling measurements. Use a high precision automatic or digital level coupled with invar staves for submillimetre accuracy results. Precise levelling techniques shall be employed in the double-run survey with equidistance back and fore sight at all instruments set up. Levelling sights shall not exceed 30 m. Refer to the Refer to Land Surveyors Board (LSB) Directives on Engineering & Hydrographic Survey Practices for more details. 3.11 Piezometers 3.11.1 General Piezometers are used for measuring pore pressures in ground. They are the pressure transducers that are installed beneath the ground to measure the sub-surface piezometric level within groundwater level, soil, or rock. Type and specification of piezometer transducers shall be according to manufacturer’s recommendation and with the SOs acceptance. 3.11.2 Casagrande Piezometers 3.11.2.1 Tube The Casagrande piezometer (or open standpipe) consists of a riser pipe that shall be of unplasticised polyvinylchloride (uPVC) of nominal diameter 19 mm and supplied in lengths of 3 m. The tube shall be connected at its lower end by suitable PVC fitting to a filter tip. The tube shall be connected at its lower end by suitable PVC fitting to a piezometer tip. TS 331/1065 978 Doc D.2/401 3.11.2.2 Tip Porous ceramic element or rigid uPVC perforated pipe having an expanded polystyrene lining moulded to form an inner tube of not less than 13 mm bore retained in position by a moulded flange as approved, with minimum length of 150 mm and minimum diameter 35 mm, protected by uPVC fittings. Permeability shall be approximately 3 x 10-4 m/s. If permeability test is to be carried out in piezometer, the filter tip shall be increased to at least 900 mm in length. 3.11.2.3 Filter The tip shall be placed in a sand cell consisting of clean sand between grading limits of 600 and 1 200 microns. A bentonite seal shall be placed above the sand cell to isolate the pore water pressure at the tip. 3.11.3 Vibrating Wire Piezometers 3.11.3.1 Tip Vibrating Wire Piezometers is a pressure transducer that can be sealed in a borehole or embedded in fill. Choose the type of tip to suit the expected maximum groundwater pressure and the characteristics of the surrounding ground. Use only piezometers with high air-entry tips. 3.11.3.2 S3.11.3.2 Not In Use Push-in vibrating wire piezometers Where accepted by the SO on the use of "push-in" vibrating wire piezometers, a mandrel of not less than 0.5 m in length is required. In such cases, there will be no requirement for a sand cell. Backfill using bentonite and grout as directed. The combined accuracy of the instrument and the readout device to be within ±1.0 % of the true pressure. Use instrument capable of measuring pressures up to 15bar. 3.11.3.3 System Accuracy The combined accuracy of the instrument and the readout device to be within 1.0% of the true pressure. Use instrument capable of measuring pressures up to 15 bar. Refer to specific standards or manufacturer’s specifications or guides, wherever possible, on tolerances, characteristics, accuracy of instrumentation and monitoring, for the SOs acceptance. [Note 1: Pneumatic Piezometers are not used.] TS 332/1065 978 Doc D.2/402 3.12 Vibration Monitors 3.12.1 Description Vibration monitors shall be capable of taking and recording velocities on a continuous basis in 3 perpendicular directions. The monitors shall be capable of registering vibrations of magnitude and frequencies that reflect the normal construction activities on site. Type and specification of vibration monitors shall be according to manufacturer’s recommendation and with the SOs acceptance. 3.13 Settlement Markers 3.13.1 Description Provide settlement markers with drive-in or cast-in survey nails for SOs acceptance and at agreed locations. Unless otherwise directed by the SO, levels of the top of the rods of settlement markers shall be measured using precise levelling and the datum used shall require only one set up of the level, and levelling shall be closed back to the datum. [Note 1: Install ground settlement markers on hard ground such as concrete slab, pavement or road surface, with nails of 50 mm in length with plastic helmet. For markers in soft ground, drive in or cast a steel rod of diameter 12 mm or larger into soft ground within a pipe-sleeve, with a protective cover. Note 2: Ground settlement markers shall be measured by means of precise levelling with invar staves for the establishment of initial or base reading. For subsequent periodic settlement reading, sectional, barcoded levelling staves shall be sufficient.] 3.13.2 System Accuracy See Section C02-050:Clause:3.10. 3.14 Building Settlement Markers TS 333/1065 978 Doc D.2/403 3.14.1 Description Building settlement markers or levelling studs shall be measured by means of precise levelling. Building settlement markers shall be of stainless steel, Grade 316 S13 or equivalent. The heads of the levelling studs mounted walls are required to be easily levelled without the studs being vulnerable to damage. All surfaces of levelling studs in contact with levelling rods and staves during measurements shall be clean, and proper access shall be provided to the crown levelling studs for cleaning during the survey. Building settlement markers or levelling studs, made up of stainless-steel anchor with bolt (25 mm length) shall be used for monitoring structural elements such as wall or column, where drilling is allowed. If drilling in structural elements is not allowed, install barcoded aluminium levelling strip that allows for heat expansion and contraction, for the measuring point on the wall. Refer to Land Surveyors Board (LSB) Directives on Engineering & Hydrographic Survey Practices. [Note 1: Building settlement markers or levelling studs shall be measured by means of precise levelling for establishing the initial (base) reading. For subsequent periodic settlement reading, a normal barcoded levelling staff shall be sufficient.] 3.14.2 System Accuracy Precise levelling survey shall fall in the 1st order levelling methodology, where the levelling instrument must have at least ±0.4 mm distance accuracy at 1km double run levelling loop, to achieve at ±2 mm âK, where K is distance in kilometre. Refer to Land Surveyors Board (LSB) Directives on Engineering & Hydrographic Survey Practices. 3.15 Tiltmeters 3.15.1 Description The tiltmeter system shall include tilt plates, the portable tiltmeter and a readout unit. 3.15.2 Tilt plates Tilt plates shall be mounted on the structures, and correctly aligned to the orientation of measurement, at locations indicated in the drawings and agreed with the SO. The tilt plates shall be securely bonded using an approved rapid setting epoxy adhesive compound or screwed to the surface of the structure, and shall be dimensionally stable and weather resistant. Tiltmeter range: ±53 degrees from vertical. TS 334/1065 978 Doc D.2/404 3.15.3 Portable Tiltmeter The portable tiltmeter shall be in metric unit system and housed in a rugged frame with precise machined surfaces to facilitate accurate positioning on horizontally or vertically mounted tilt plate. 3.15.4 Readout Unit The readout unit shall be suitable for the tiltmeter and shall be of a rugged, weather-proof design with easy to read display and rechargeable battery or equivalent. A sufficient length of jumper cable shall be provided for connecting the tiltmeter to the readout unit. The tiltmeter shall conform to the following criteria: Table 2. Tiltmeter conformance criteria Metric Criteria Range 30 from vertical Resolution 8 arc seconds Temperature Coefficient (0.05% of reading + 5 arc seconds)/ C Refer to specific standards or manufacturer’s specifications or guides, wherever possible, on tolerances, characteristics, accuracy of instrumentation and monitoring, for the acceptance of SO. 3.15.5 Measurement Tilt reading shall be taken by positioning the tiltmeter on the tilt plate and connecting the tiltmeter to the readout unit. At least 2 readings shall be taken by rotating the tiltmeter at 180° for each reading. 3.16 Load Cell 3.16.1 Description Install load cells at locations indicated in the drawings and agreed with the SO. Vibrating wire load cell or any other approved type shall be water-resistant and made of corrosion-free material or made from aluminium alloy for field use. 3.16.2 Use with Ground Anchors For use with ground anchors, the load cells shall be hollow centrally with inner diameter not less than 100 mm and the load cell measurement range shall be at least 2.5 times the working load of the ground anchors. The load cell shall be installed before the prestressing and locking of ground anchor load. The load cell shall be placed centrally to reduce errors that result from load misalignment and off-centre loading. Initial cell readout must be taken immediately after the installation is complete. TS 335/1065 978 Doc D.2/405 3.16.3 System Accuracy Unless otherwise agreed by the SO, load cells are required to be able to read in the expected measurement range of load to be monitored plus 50% of the maximum load. Refer to specific standards or manufacturer’s specifications or guides, wherever possible, on tolerances, characteristics, accuracy of instrumentation and monitoring, to the acceptance of SO. 3.16.4 Measurement Load cells are required to be connected to a data logger to allow automated readings to be taken at the specified frequency as directed by the SO. Shielding of the equipment is required to avoid electronic magnetic interference distorting measurement readings. 3.17 Tell-Tales 3.17.1 Description Tell-Tales shall generally comprise 2 clear plastic overlapping plates, one marked with a millimetre scale, the other with a crosshair marking to allow reading on 2 axes. If the position of the Tell-Tale is out of general sight, it shall be readable without obstruction. 3.17.2 System Accuracy Tell-Tales shall have an accuracy of ±1 mm, with a range of ±20 mm. Refer to specific standards or manufacturer’s specifications or guides, wherever possible, on tolerances, characteristics, accuracy of instrumentation and monitoring, to the acceptance of SO. 3.17.3 Measurement Take readings in both directions of separation in a consistent manner by the same personnel. Inform SO in cases where out-of-plane movement is observed that is distorting the in-plane movements and the corrective action taken. 3.18 Reflector Targets 3.18.1 Description Install prism reflector targets at the locations shown in the drawings and of the target type as agreed by the SO. Targets shall be durable, not damaged by rain and fixed and shall not be disturbed by vibration. TS 336/1065 978 Doc D.2/406 3.18.2 System Accuracy Unless otherwise agreed by the SO, targets shall provide an overall measurement accuracy of ±1 mm with readings taken from high precision Total Station which has an angular accuracy of 1.0 arc second and distance measurement accuracy at ±1 mm + 2ppm. Refer to specific standards or manufacturer’s specifications or guides, wherever possible, on tolerances, characteristics, accuracy of instrumentation and monitoring, for the SOs acceptance. Unless otherwise agreed by the SO, targets shall provide an overall measurement accuracy of ±1 mm 3.18.3 Measurement Targets shall be measured manually or automatically at the specified frequency. The position of targets on site shall be such that line of sight is maintained at all times. 3.19 Temperature Sensors 3.19.1 Description Temperature sensors shall be of a resistance temperature detector or thermocouple type as directed by the SO. 3.19.2 S3.19.2 Not In Use System Accuracy Ensure the working range of the sensors is appropriate to the expected temperature measurement range in the field and to be at -40°C to 60°C with an accuracy of ±1 C. Refer to specific standards or manufacturer’s specifications or guides, wherever possible, on tolerances, characteristics, accuracy of instrumentation and monitoring, to SO for acceptance. 3.19.3 Measurement All sensors shall be capable of being remotely monitored and the data downloaded to a computer in a file format agreed by the SO. 3.20 Strain Gauges 3.20.1 Description Securely install strain gauges at the locations shown in the drawings and of an appropriate type to be agreed by the SO. TS 337/1065 978 Doc D.2/407 3.20.2 System Accuracy Vibrating wire strain gauges shall have the following characteristics: Table 3. Vibrating wire strain gauges characteristics Metric Characteristics Strain range 2500 x 10-6 m/m Accuracy ±3.0 x10-6 m/m Resolution 0.5 x 10-6 m/m Response time not more than 10 secs. Refer to specific standards or manufacturer’s specifications or guides, wherever possible, on tolerances, characteristics, accuracy of instrumentation and monitoring, to the acceptance of SO. 3.20.3 Signal Cable Shield signal cable with flexible polyurethane jacket. Temperature-rated minimum ranges shall be from 0°C to 80°C and to be compatible with the environment in which the gauges are installed. 3.20.4 Measurement Strain gauges are required to be connected to a data logger to allow automated readings to be taken at the specified frequency. Shielding of the equipment is required to avoid electronic magnetic interference distorting measurement readings. 4 WORKMANSHIP 4.1 General 4.1.1 Instrument Maintenance Maintain all instruments, including readout and data loggers, required for monitoring in a satisfactory working order for the duration of the monitoring programme. 4.1.2 Storage Securely store all equipment and installation accessories prior to installation where they will not suffer physical damage or damage arising from excessive moisture, extremes of temperature or any adverse conditions. TS 338/1065 978 Doc D.2/408 4.1.3 Installation and Testing Install and test all equipment, including connections and fittings in accordance with the manufacturer’s recommendations. Reconfirm the depth of installation of underground instrumentation with the SO based on the soil profile encountered in the borehole for the purpose. 4.1.4 Grouting Do not backfill boreholes with soil arisings, unless otherwise agreed with the SO. Backfill all boreholes with bentonite-cement grout, with standpipes and piezometers together with their response zones installed at the depths specified, or as directed by the SO. Introduce the grout using a tremie pipe which is kept below the surface of the grout as filling proceeds. Agree the methods to be used where ground conditions make normal grouting impracticable. Leave the area in a clean and tidy condition. Refer to Section C02-010:Clause:3.2 for requirement of bentonite-cement grout materials. 4.1.5 Testing Undertake testing as necessary to ensure satisfactory functioning of the equipment at each stage of the installation. Report any instruments found to be malfunctioning at any time to the SO within 24 hours of the fault being identified and replace at the earliest opportunity. 4.1.6 Fixing and Protection 4.1.6.1 Fixing Details Securely fix all instruments and adequately protect their terminations, including any attendant wiring and terminal panels, against mechanical damage and ingress of water and dirt. Fix the equipment such that it is capable of resisting vandalism and adverse climatic conditions at surface locations. In addition, protect all instruments by hoarding or barriers as directed. Tag all external visible protective covers to equipment using aluminium rigid nameplates of minimum size 2 500 mm2, SWG 24 or similar to the acceptance of the SO, identifying the following: (a) Project title and contract number (b) Equipment reference number (c) A contact name and contact telephone number TS 339/1065 978 Doc D.2/409 4.1.6.2 Protection Details Provide as detailed in a method statement, protection details for inclinometers, piezometers, extensometers and settlement points, with the SOs acceptance. Develop alternatives if necessary, to fit in with site constraints and further improve protection to the instruments. Protection systems for other instruments shall also be developed where necessary. These protection systems shall provide a similar or better level of protection as that provided by the systems shown in the drawings. 4.1.6.3 Prevention of Damage Take all sensible measures to prevent damage to the instruments and ancillary equipment during handling, installation and subsequent operations. Replace any instrument and/or ancillary equipment damaged during handling, installation or subsequent operation immediately. Snake or coil cabling and tubing to provide sufficient slack to accommodate potential ground movement. 4.1.7 Instrument Reference System Establish a logical reference system for all the instrumentation equipment prior to installation and to the satisfaction of the SO, so records for any particular location can easily be recovered for interpretation or review. 4.1.8 Remote Readout 4.1.8.1 Location of Readout Boxes Position readout boxes for ease of access and protect from damage during construction. Propose locations unless shown otherwise in the drawings for acceptance by the SO. 4.1.8.2 Location of Logger Stations Position logger stations for ease of access and protect from damage during construction. Propose locations unless shown otherwise in the drawings for acceptance by the SO. TS 340/1065 978 Doc D.2/410 4.1.8.3 Cable Fixing and Identification Fix cabling for instrumentation neatly and securely to appropriate cable trays which in turn shall be securely fixed to the structure. Tag all cabling with an appropriate reference, identifying the instrument to which it is attached. Protect cables in galvanised pipes from ground level to one metre below cut-off level. In addition, clearly label the cables at 0.5 m interval within the protected length. Where possible, use colour-coded cables for the purpose of identification. Use single length cable for newly installed vibrating wire piezometer. Do not allow splicing unless otherwise agreed. When splicing is allowed, ensure water tightness of the splices in the event where the cables are damaged and need to be spliced. 4.1.8.4 Identification of Cables Tag each individual cable at least at the instrument end connection and at the logger connection identifying that cable. Maintain a schedule showing all cables and their respective connections. 4.2 Instrument Reading and Records 4.2.1 Schedule of Monitoring Submit a proposed schedule of instrument monitoring readings for the acceptance of the SO. Comply with the minimum frequency and duration of readings for each instrument as provided in Section C02050:Clause:3.1. Vary the frequency depending upon the stage of the Works as provided in Section C02050:Clause:3.1 or as agreed by the SO. In some cases as directed by the SO, continuous logging is required. Increase the monitoring frequency at any stage as directed by the SO if the performance of the Works being monitored does not perform as predicted, or the Works are likely to cause adverse effects on the adjacent properties if proceeding further. TS 341/1065 978 Doc D.2/411 4.2.2 Ground Movements and Vibrations When planning for suitable methods and schedule for monitoring, take account on the limits on movements and levels of vibration for the adjacent buildings and those indicated in drawings or as directed by the SO. When planning for suitable methods and schedule for the monitoring, take account on the general restrictions on movements and levels of vibration for the adjacent buildings as set out below, unless otherwise agreed by the SO or regulated by statutory requirements or indicated in the respective sections: Table 3: Restrictions on movements and levels of vibration for adjacent buildings Building 4.2.3 Limits on ground movement (mm) Limits on level of vibration (mm/s) Horizontal Vertical (Settlement) Alert Worksuspension Alert Work- suspension Alert Work-suspension . . . . . . . . . . . . . . Methods of Taking Readings Do not use any form of instrument which uses electrical resistance methods for taking readings unless otherwise agreed. 4.2.4 Initial Readings Read all instruments as soon as possible after installation and at least once per day for a period of 2 weeks thereafter until readings have stabilised. Where instruments appear not to have stabilised, for example exhibiting a continued drift in the readings, the cause shall be identified, and the fault rectified, and a new set of readings provided. When all instruments are showing consistent results for a period of 1 week, readings shall be averaged to provide a datum or base reading. The base readings shall be established before construction work starts. 4.2.5 Site Conditions When recording instrumentation readings, record all site conditions that may affect the results, including temperature and humidity readings. (Suitable supplementary instrumentation shall be installed to provide these data.) Record also the instrument type, location reference, datum and time of reading, personnel carrying out the readings and measuring instrument or readout unit reference. Record any observations of unusual conditions that could influence the instrumentation or the structure. TS 342/1065 978 Doc D.2/412 4.2.6 Reading Records After installation, the functioning of each instrument shall be demonstrated to the SO, including the recording of measured values using the appropriate readout device. As part of the commissioning, a set of datum readings will be established in accordance with Section C02-050:Clause:4.2.4. In cases where instruments are installed during construction, establish base or datum readings as quickly as possible by taking at least 3 separate sets of measurements and compare the results. These results shall be used to provide base datum in a manner to be agreed with the SO for monitoring. Record instrument readings in accepted format for subsequent processing by computer. Make corrections for temperature difference or other factors as appropriate shall be made, but uncorrected data shall also be stored and made available on request. Produce plots of deformation, stress, raw data readings against time together with plots of temperature and humidity, or other data as directed when relevant. 4.2.7 Consistency of Instrument Use Use the same recording devices, e.g. tape extensometers, level, EDM and Theodolite, etc. at any given location throughout the monitoring programme. If this becomes impractical, take new datum readings immediately with a replacement instrument, and use the new instrument for future readings. 4.2.8 Consistency of Readings Readings shall be taken by the same personnel to maintain consistency. If personnel need to be replaced for any reason, take a series of 3 duplicate readings by both the outgoing person and the replacement. 4.2.9 Consistency of Location Should a monitoring location become unavailable, read the instrument previously read from this point from an alternative point, as soon as practicable after the location becomes unavailable. Use this for all subsequent readings. Include a reference to such changes on the summary plots. 4.3 Inclinometers (Manual Read) 4.3.1 General All inclinometer tubing and instrumentation shall be resistant to aggressive/adverse substances in the ground and shall conform to the requirements for sub-surface installations. TS 343/1065 978 Doc D.2/413 4.3.2 Tubing Provide the tubing with appropriate couplings for joining tube lengths to the required borehole length. Inclinometer tube to be slotted plastic of 75 mm internal diameter that is pre-grouted into a minimum 100 mm diameter borehole, or a steel pipe of at least 150 mm when placed in a structural element. Tubing to be of uniform section and free of twist in manufacture and shall not twist during installation. The spiral twisting of the keyways shall not exceed 0.75 degrees per metre length of the tubing. The grooves in each section of the tube shall be accurately aligned using the alignment tool supplied before fixing the joint. Adequately fix and seal the cap and coupling joints so that the tube is grout and dirt. Lower the joined and sealed tubing into the borehole and grout the annulus using a bentonitecement grout tremied to the bottom of the hole. Fix the tubing from rotation while being lowered. After assembly joints and rivets shall be sealed with mastic tape and wrapped with biaxially oriented polypropylene tape or other means approved by the SO. The bottom section of the tube shall be fitted with a protective cap riveted in a similar manner to the tube joints. 4.3.3 S4.3.3 Not In Use Installation Insert a slotted plastic inclinometer tube of minimum 60mm internal diameter into a minimum 100mm diameter borehole or a steel duct of at least 150 mm cast into any pile or wall. Withdraw any temporary casing used during boring/drilling at the time of grouting the inclinometer tubing. Embed the toe of inclinometer into hard stratum below which the ground movement is negligible. Prior to installation, propose the installation level for acceptance of the SO. 4.3.4 Probe Location Provide suitable means of measuring the position of the probe down the borehole to an accuracy of ±10 mm from a reference point at the top of the borehole. Establish the co-ordinate of the reference point prior to all readings by surveying from a suitable stable benchmark. 4.3.5 Extension of Inclinometers Where inclinometers already exist and are to be extended, the new tubing shall match the existing tubing. During earthworks operations, extend the inclinometer tubes in lengths and ahead of the fill to a manner accepted by the SO. TS 344/1065 978 Doc D.2/414 4.3.6 Stability and Gain Check Check stability and gain of the reading system at weekly intervals unless otherwise agreed, and provide results to the SO. 4.3.7 Spiral and Inclination Check Carry out spiral and inclination check prior to establishing the datum reading. 4.3.8 Inclinometer in a structural element. Where an inclinometer is placed in a structural element, a secondary or auxiliary guide pipe or casing should be installed adjacent to the main guide pipe or casing to provide redundancy particularly in situations where measurements are crucial. Where an inclinometer is placed in a structural element such as embedded retaining wall or pile, the toe of the inclinometer access tube shall be at least 1.5 m below the toe of the structural element or to a depth where the stratum of SPT N ≥100 whichever is deeper. The annulus between the inclinometer access tube and the pipe casing in the structural element shall be grouted. Unless otherwise agreed by the SO, the grout shall have a minimum compressive strength measured on 100 mm cubes of 20 N/mm2 at 3 days and 35 N/mm2 at 28 days. The initial grout shall be completed in one operation until all water and diluted grout have been expelled from the top of the borehole. [Note 1: Depending on excavation depth, toe of retaining structure needs not always be founded in/ near layer with SPT N>100. Under such ground conditions and subject to the SOs acceptance, the toe of the inclinometer access tube shall be at least 1.5 m below the toe of the structural element or to a depth of at least 1 m into a stratum of SPT N ≥ 50 whichever is deeper.] 4.3.9 Ground Level Installation At the final ground level fit the inclinometer tubing with a removable cap within a lockable vandalproof cover set in a concrete surround. Cover and surround details shall be to the acceptance of the SO. TS 345/1065 978 Doc D.2/415 4.3.10 Measurement Immediately before or after taking a series of readings, the level and position of the top of the access tube shall be measured by standard levelling techniques. Before passing the probe down the access tube, a dummy probe shall be lowered to the base of the tube and pulled up to check for obstructions or constrictions. When taking readings, insert the inclinometer probe in the tube. Lower the probe to the base where time is given to adjust to environmental conditions. The probe is then raised taking measurements every 0.5 m until reaching the top. The inclinometer shall travel along the whole length of the tube with wheels engaged in each pair of the keyways in turn to obtain deformation measurements in both directions. The measurements shall be stored in the data logger that displays the checksum following a complete set of readings to check for errors. Repeat the procedure on the opposite face, following the manufacturer's method and sign convention. 4.4 In-place Inclinometers (Remote Read) 4.4.1 General Ensure all inclinometer tubing and instrumentation shall be resistant to aggressive/adverse substances in the ground and conform to the requirements for sub-surface installations. Ensure that the in-place inclinometer is capable of providing continuous, unattended monitoring data. 4.4.2 S4.4.2 Not In Use Installation Insert a slotted plastic inclinometer tube of 75 mm internal diameter into a minimum 100mm diameter borehole or a steel duct of at least 150 mm cast into any pile or wall. Any temporary casing used during boring/drilling shall be withdrawn at the time of grouting the inclinometer tubing. Embed the toe of inclinometer into hard stratum below which the ground movement is negligible. Prior to installation, propose the installation level for the acceptance of the SO. 4.4.3 Tubing Provide the tubing with appropriate couplings for joining tube lengths to the required borehole length. Adequately fix and seal the cap and coupling joints so that the tube is grout- and dirttight. Lower the joined and sealed tubing into the borehole and grout the annulus using a bentonitecement grout tremie to the bottom of the hole. Fix the tubing from rotation while being lowered. TS 346/1065 978 Doc D.2/416 4.4.4 Not In Use S4.4.4 Sensor Install the biaxial electrolevels at spacing acceptable to the SO and connect with a rod to give a fixed gauge length. At the end of the sensor and the gauge extension, fit a spring-loaded wheel assembly. Do not use sensors mounted on sleds. Check that the spacing of sensor is no greater than 3 m. 4.4.5 Stability and Gain Check Check stability and gain of the reading system at weekly intervals by means of 3 "dummy" electrolevels using precise resistors and provide results to the SO. 4.4.6 Spiral and Inclination Check Carry out spiral and inclination check prior to establishing the datum reading. 4.4.7 Ground Level Installation At the final ground level fit the inclinometer tubing with a removable cap within a lockable vandalproof cover set in a concrete surround. Cover and surround details shall be to the acceptance of the SO. 4.5 Extensometers 4.5.1 Magnetic Inclinometer Extensometers TS 347/1065 978 Doc D.2/417 4.5.1.1 Installation Set a datum magnetic ring at approximately 2 m above the base of the inclinometer tubing and also within the instrument chamber base, located at the top of the borehole. The tubes and magnets shall be assembled prior to installation in such a way that the magnets remain in the correct position in relation to the tube. The tube shall be coated with a thick grease over its upper part where the tube passes through compressible subsoils. Then lower the tube together with all magnets and necessary accessories fixed in position into a 100 mm diameter borehole backfilled with a suitable bentonite-cement grout mix. The magnetic rings to be housed in splay PVC holders ("spider magnets") suited to the ground. Once in position the spider magnets shall be released. Where the access tube passes through upper stiff crusts or fill material, sleeve with a larger diameter tube to pass freely through these materials as settlement takes place. Where extensometer is used in earth filling situation, the access tube and outer sleeve shall be extended as filling progresses. The top of the access tube, and the larger diameter sleeve where present, shall be protected with a suitable cover with facility for locking. Unless otherwise shown in drawings, install the magnetic rings at depth with an interval not exceeding 3 m. Grout the complete downhole assembly in place ensuring that the access tube and magnets remain undisturbed during grouting operations. Seal the access tube to prevent ingress of ground water. 4.5.1.2 Measurement Immediately before or after taking a series of readings, the level of the top of the access tube shall be measured by standard levelling techniques. Measure relative movement between the magnetic ring and the reference magnetic ring (at either the top or bottom) by a reed switch attached to a stainless-steel tape. The position of each magnet shall be measured twice, once while moving upwards and once while moving downwards towards the magnet by raising and lowering the steel tape and reed switch assembly from the top of the borehole. Refer to specific standards or manufacturer’s specifications or guides, wherever possible, on tolerances, characteristics, accuracy of instrumentation and monitoring, to the acceptance of SO. 4.5.2 Rod Extensometers TS 348/1065 978 Doc D.2/418 4.5.2.1 Rods and Rod Assembly Isolate each rod individually by its own plastic sleeve and grout the complete assembly in place, fixing the anchors to the ground but allowing free movement of each rod within its sleeve. Ensure a single reference housing receives all of the rods from a drill hole and provide protection to the reference head and measurement device. Rods shall be stainless steel of a grade suitable to the site environment and duration of the measurement and monitoring. Make provision for threading the anchor points onto the rod. Install no more than 6 rods in a single hole with each rod of a different length so that displacements at various borehole depths shall be recorded. Where more than 6 rods are required, prepare another borehole as close as possible to the initial hole and rods set at alternate depths in each hole. 4.5.2.2 S4.5.2.2 Not In Use Use of Casing Use casing to stabilise holes through unstable ground. Determine the lengths of rods using the level of the ground at the hole location. For grout used for backfilling, use bentonite/cement mix with just sufficient water to allow it to be tremied to the bottom of the holes. 4.5.2.3 Measuring Head Measuring head shall allow manual readings to be taken as well as automated readings. Cabling to the terminal box shall be capable of accepting up to 6 extensometers from each hole. Provide a battery-operated digital readout device capable of reading to the required overall accuracy. Extensometers shall provide measurements of both elongations and reductions in the length between anchorage point and measuring head possible. Undertake remote reading using the electrical transducers linked to a logger station with a measuring range of 150 mm. If movements potentially exceed 150 mm, make adjustment to allow continued monitoring. Use transducers that are waterproof to 15 bar. TS 349/1065 978 Doc D.2/419 4.5.2.4 Measurement Immediately before or after taking a series of readings, the level of the top of the access tube shall be measured by standard levelling techniques. Measure relative movement between the end anchor and the reference collar by an automated measurement device (an electrical transducer) registering on the free end of the rod and by manual means using a system to the acceptance of the SO. Extend the reading range beyond that of the measurement device by a range adjustment device fitted at the reference collar. Refer to specific standards or manufacturer’s specifications or guides, wherever possible, on tolerances, characteristics, accuracy of instrumentation and monitoring, to the SO for acceptance. 4.5.3 Tape Extensometers Locate and fix anchors in a manner acceptable to the SO. Use the same extensometer for each set of readings to maintain consistency. Provide a minimum of 2 tape extensometers at the commencement of work and these are to be calibrated against each other, so that in the event of damage to one tape, accuracy is not compromised. 4.5.3.1 Measurement Take measurements by connecting the tape hook to one eyebolt and then extend the tape across to the next bolt. Adjust the tension of the tape and take the tape and calliper readings. 4.6 Deep Levelling Datum 4.6.1 Installation Install a 300 mm diameter casing not less than 4 500 mm into firm/competent ground where SPT N = 50 subject to the SOs approval. Install the 250 mm diameter casing of not less than 1 500 mm beneath the 300 mm casing and fill with water cement grout that is just pumpable. Ensure the founding depth of deep levelling datum shall be such that the founding strata is not affected or will not be influenced by the construction activities or Works. Fill the annulus between the 2 casings with grease. The top of the 25 mm steel rod shall be domed and centre punched. 4.6.2 Protection Propose for the SOs acceptance measures to protect the top of the Deep Levelling Datum by a manhole cover and by a surface protection barrier. 4.7 Piezometers TS 350/1065 978 Doc D.2/420 4.7.1 Piezometer installation Install each piezometer in a separate borehole of 100 mm nominal diameter. Carry out the complete installation as soon as practicable, and no later than 24 hours, after drilling in order to minimise the amount of deterioration or alteration of the ground at the location of the piezometer tip. Carry out drilling to the required depth without the use of air- flush in the vicinity of the tip position. 4.7.2 Use of casing Use casing to stabilise the hole through unstable ground. If casing is used to maintain the hole open, withdraw it carefully so as not to damage the instruments or cables, concurrently with the progress of the backfilling. 4.7.3 Installation of Sand Filter In placing the sand, ensure that no sand adheres to the soil in the sides of an unlined hole. Where there is water in a hole, allow sufficient time for all the sand to settle, and take measurements of the upper surface of the sand from time to time to ensure this. Record the final elevation of the top of the sand. The filter element shall have a pore diameter of the order of 60 microns. Join the tubes together and to the porous element with threaded couplings, tape and glue in such a manner that the joints remain leakproof under the anticipated head of water. Use tube of at least 12 mm internal diameter to allow air bubbles to rise freely. Make arrangements to ensure that no sand adheres to the soil on the sides of the unlined borehole. If there is water in the borehole, allow sufficient time for all sand to settle. Record the final elevation of the top of the sand level. Place the porous element in the hole and add the remaining sand filter as described above. Measure the final elevation of the top level of the sand filter by a flat-ended sounding rod. Take sufficient number of soil samples from the drill-hole to accurately determine the subsurface profile and agree with the SO on the appropriate tip levels for the piezometers. 4.7.3.1 Bentonite Seal Install seals consisting of bentonite pellets above, and if necessary, below a sand filter. The seal plug shall not be less than 1.0 m thick. Fill the remainder of the hole with a bentonite- cement grout, and the top part with concrete with caps and air vents as indicated on the drawing. Tamp the bentonite seal formed of either stiff hard rolled balls or pellets over the sand to a thickness of approximately 1.5 m. Backfill the hole with bentonite-cement grout mix to the acceptance of the SO. Terminate grout backfill at the base of the instrumentation chamber. TS 351/1065 978 Doc D.2/421 4.7.3.2 De-airing of Piezometer Tip Check that the tip of each piezometer is air free and the porous stone of the tip is fully saturated by submergence in clean de-aired water for a period of at least 24 hours prior to installation. Confirm complete de-airing of the porous stone by periodic weighing. 4.7.3.3 Testing Before Installation Test all piezometers before installation by submergence in still clean water to a series of depths appropriate to the anticipated pressure range of operation in order to verify the calibration and accuracy of the instrument. 4.7.3.4 Records Keep accurate records of the depths of the piezometers, sand surrounds and seals, and record readings at each stage of the installation. For push-in piezometers, record the increase in pore pressure as well as dissipation using a data logger. Check the maximum pressure allowable during installation to be 50% of the maximum for which the piezometer is rated. 4.7.3.5 Commissioning Test On completion of the installation, commission all standpipes and piezometers as appropriate, using a falling head test by filling the standpipe or piezometer full with water to the top of the PVC tubing. Carry out a simple falling head test and monitor the drop in water level in the piezometer at intervals of 15 secs, 30 secs, 1 min, 2 mins, 4 mins, 8 mins, 15 mins, 30 mins, 1 hr, 2 hrs, 3 hrs, 4 hrs, 5 hrs, 6 hrs, 7 hrs, 8 hrs, 16 hrs, 24 hrs, or when the water level has returned to its initial steady level. Before taking initial readings, stabilise the piezometer by alternately baling and filling at least 10 times. Measure the depth to water using an electric type dip meter. The water standpipe or piezometer shall be in working condition throughout the monitoring period. Rectify any damaged piezometer before handing over. Take samples of ground water of not less than one litre from the piezometer when required. Store the water samples in clean sealed containers, clearly label and deliver to the laboratory for chemical tests. The tests for sulphate content (% SO3), chloride content, acidity (pH value) and degree of salinity shall be determined from the same sample. 4.8 Strain Gauges Ensure strain gauges and cabling to be compatible for their intended location. Protect them against any disturbance from the site activities. 4.8.1 Not In Use TS 352/1065 978 Doc D.2/422 S4.8.1 Strain Gauges Embedded in Concrete Use the embedment variety or securely attach to mounting plates welded to bars that are then attached to the reinforcement. The method of attachment shall prevent displacement of the gauge or damage to the wires and cables during fixing of reinforcement, concreting, driving or other processes. Attach the bars at 2 locations only to limit the bending induced in the bars to less than 50µε during installation. 4.8.2 Strain Gauges for Temporary Struts Use spot weldable strain gauges to the SOs acceptance. At the beginning of strut monitoring, install strain gauges in strut together with load cells for calibration purposes. Establish a correlation between the gauges and loads measured by the load cells and submit the results for review by the SO. Gauges from the same type and source shall then be used to monitor other selected struts in place of load cells. The locations of struts required strain gauges are shown in the drawings. 4.9 Tell-Tales Fix the overlapping plates securely so that a gap of not greater than 1 mm separates them at the start of monitoring and so that the cross-hairs are zeroed. Record the location, orientation and plate separation for each Tell-tale on the reading sheets. 4.10 Markers, Crackmeters and Tiltmeters Typical details of acceptable installations for ground and building settlement points are shown in the drawings. Submit for approval details of any alternative installations proposed. 4.10.1 Accuracy of Levels Monitor and record the levels of ground survey and building settlement points throughout the duration of the Works, using a precise level and staff accurate to 0.5 mm or better. 4.11 Inspection of Adjacent Property Keep adjacent roads, neighbouring properties and structures clear of equipment and spoils and regularly inspect the surface of the ground, properties and structures. Report to the SO immediately any signs of subsidence, movement or cracks. 4.12 Completion Remove all specialist monitoring and make good all installations to the satisfaction of the SO upon completion of the monitoring, or at other such times if accepted by the SO. TS 353/1065 978 Doc D.2/423 5 VERIFICATION AND SUBMISSIONS 5.1 Submissions 5.1.1 Description of Instrumentation Provide fully detailed drawings, together with descriptions of the principal features, mode of operation, the measuring range and the degrees of accuracy of the equipment. 5.1.2 Method Statement Submit detailed method statements for the installation of all instruments for the acceptance of the SO prior to installation. 5.1.2.1 Content Method statements shall include, at least the following information: (a) Details and drawings of instruments (b) Manufacturers specifications and recommendations for installation and maintenance, etc., details of drilling equipment and drilling methods (c) Details of all materials (including samples) (d) Details of sequence of assembly and connections (e) Details of any backfill, proposed grout mixes (f) Details of monitoring arrangements and verification procedures The method statement shall also include a programme of installation related to the main construction activities to the acceptance of the SO. 5.1.3 Installation Drawings Submit detailed drawings showing the precise location and depth for instrument installation for the acceptance of the SO prior to commencement of installations. 5.1.4 Schedule of Manpower and Resources Provide a detailed schedule of manpower and equipment resources to be employed for the Works for SOs acceptance before commencement within timeframe as directed. TS 354/1065 978 Doc D.2/424 5.1.5 Data Management System Submit full details of the proposed data management system for the acceptance of the SO. These shall include proposed formats for data acquisition, checking, processing, and subsequent reporting to the SO for all instruments. 5.1.6 Anomalous Readings Whenever sets of data are measured, review the measurements with to earlier sets of data for any anomalous readings or gross errors in measurements which differ from the expected value or trend. Immediately proceed to take additional readings to verify data. If the anomalous measurement values persist, notify the SO and carry out investigation to find the reasons for the anomalous readings. 5.1.7 Calculations Provide calculations to convert raw output to processed data for all instrumentation. Provide a sample calculation with appropriate data listings to the SO, endorsed by a qualified, competent and experienced PE who is directly responsible for the instrumentation and monitoring. 5.1.8 Maintenance and Inspection Schedule Submit a maintenance and inspection schedule prior to installation or use of the instrumentation for the acceptance of the SO. 5.1.9 Quality Control Manual Submit a Quality Manual containing a Quality Assurance / Quality Control (QA/QC) programme for the Works to the SO for acceptance within directed time frame. The Quality Manual shall include at least information on the following: (a) Quality policy (b) Organisation charts and responsibilities (c) Internal quality control and audits (d) Facilities and equipment (e) Calibration and testing of equipment (f) Testing and inspection procedures (g) Sub-contractors and suppliers TS 355/1065 978 Doc D.2/425 5.2 Calibration of Instrumentation Correctly calibrate all the installed instrumentation in use. Carry out calibration and provide certificates by an accepted accredited agency. Carry out periodic checks at appropriate intervals to confirm the validity of calibration of equipment in accordance with the manufacturers instructions and make any necessary adjustments. Check instruments to have a validity of calibration at least 3 months after their last intended reading in the project. Repeat calibration if anomalous readings are recorded. Keep records of checks, errors recorded and whether any adjustment was undertaken. 5.2.1 Records of Calibration Keep records of all calibration certificates and of dispatch of equipment off site for rewhen required. Retain copies of all certification and other records on site and make available for the SOs inspection when required. After installation, the functioning of each instrument shall be demonstrated to the SO, including the recording of measured values using the appropriate readout device. As part of the commissioning, 3 sets of readings shall be taken and compared. When instruments are installed before earthwork starts, then these 3 sets of readings shall also be taken before construction starts. If there are significant differences or anomalies, then further readings shall be taken. Once 3 sets of comparable readings have been taken, these shall be averaged to form the base readings, representing conditions before construction starts. In cases where instruments are installed during construction, 3 sets of readings shall be taken in quick succession and the results compared. Use these results to provide base readings in a manner to be agreed with the SO. 5.3 Records and Reporting 5.3.1 General Submit 2 copies of preliminary records of the installation of each instrument within 24 hours from the time of installation of each instrument. Submit final records for each instrument incorporating any comments from the SO within 7 days of completion of installation of each instrument. 5.3.2 Record Information Submit installation record sheet for each instrument installed. TS 356/1065 978 Doc D.2/426 5.3.2.1 Instrumentation Installation Record Sheet The format of the instrumentation installation record sheet together with execution details shall be submitted to the SO for approval at least one week before installation commences. The record sheet shall include the following information in addition to the general information required: 5.3.2.2 (a) Existing ground level at the time of installation. (b) A log of ground conditions or geotechnical information. (c) Planned and as-installed instrument location in plan and elevation. (d) Planned and as-installed instrument orientation. (e) Type of backfill materials used, and dimensions such as length, width, diameter, depth and volumes of backfill. (f) Plant and equipment used, including diameter and depth of any drill casing used. (g) Verification measurements or readings during installation to ensure that all installation steps have been followed correctly, including acceptance tests. (h) Weather conditions. (i) Problems encountered, delays, unusual features of the installation, and any events that can influence the instrument readings or measurements. (j) A record of commissioning information, tests and readings. (k) Legend and any colour coding used. Instrumentation Installation Report Submit to the SO the specified number of copies of each installation report within one working day of completion on the installation, including taking of initial readings supplementing the planned details with the as-built details. The records shall incorporate a graphical illustration of the instrument installation and shall include the following information to supplement the installation record sheet: (a) Instrument number and location (co-ordinates in accordance with the project grid reference and level). (b) Names of personnel responsible for installation. (c) Time and date for commencement and completion of installation. (d) Details and records of boreholes. TS 357/1065 978 Doc D.2/427 5.3.3 (e) Plant and labour used. (f) Ground conditions encountered (if applicable). (g) Details of instrument installation (grout, fixings, etc). (h) Instrument readings during installation, and immediately after calibration and installation is complete. (i) Location of instrument terminals, housings and any leads or cabling. (j) Details of any splices, numbers of casings or joints. (k) Details of any breakdowns or delays. Datum Readings of Survey Points The Registered Surveyor shall establish the initial (datum) reading of each survey point and submit records with Registered Surveyors endorsement to the SO. Unless otherwise agreed, submission of the datum readings should occur prior to any excavation and construction works. 5.3.3.1 Survey Datum to be established for Monitoring Works The Registered Surveyor shall establish the horizontal and vertical survey datum from Singapore Land Authority (SLA) Integrated Survey Network (ISN) markers in SVY21 datum; and vertical datum from Vertical Control Points (VCPs). Refer to Land Surveyors Board (LSB) Directives on Engineering & Hydrographic Survey Practices. 5.3.3.2 Periodic Maintenance Survey of Monitoring survey datum The survey datum shall be surveyed at quarterly intervals as a verification of the stability of the base datum and that their accuracy is up-to-date with correct datum reference for the periodic monitoring survey works. Refer to Land Surveyors Board (LSB) Directives on Engineering & Hydrographic Survey Practices. 5.3.4 Submission of Readings Submit all instruments readings in approved tabular and graphical formats (electronic and paper based), within 24 hours of monitoring. TS 358/1065 978 Doc D.2/428 5.3.5 Presentation of Reading in Graphic Format Submit to the SO for acceptance on the graphic presentation of the measurement data. prior to the commencement of instrumentation field work. Hand plotted graphs are not acceptable. Provide the same time-axis scale for all time-plots. Submit for SOs acceptance on the format of plots involving presentation of parameters together such as fill thickness, settlement and excess water head measurements at about the same location. Submit for SOs acceptance on the presentation layout, scale and details for the instrumentation at the time of submitting the format of plots. 5.3.6 Factual Reporting Submit reports of monitoring results in a factual report at intervals as agreed by the SO, in an acceptable format, including a plan showing the location of the structure and instrumented lines and shall comprise at least the following: (a) Incorporate plots of measured parameters vs time, depth and/or location of construction activity with reference to each instrument, etc. as agreed with the SO. (b) Include a comparison of data with predetermined trigger values. (e.g. settlement vs time, horizontal deflections vs time, load vs depth of excavation, settlement vs location of construction activity / depth of excavation, etc.). (c) Highlight idle or damaged instrument and provide estimated time frame for corrective measures. Submit reports of monitoring results in a factual report at intervals to be agreed with the SO. Propose to the SO for his acceptance on the frequency of reporting as appropriate. 5.3.7 Interpretative Reporting 5.3.7.1 Frequency Where required or directed by the SO, propose for the SOs acceptance on the frequency of submitting the interpretative reports as appropriate based on the factual information received for the Works. When established trends indicate potential problems then such areas of concern shall be reappraised and monitored at revised frequency as directed by the SO. 5.3.7.2 Report Content Interpretative Reports shall include a summary plot of all instrumented lines or points which indicate a trend (including historical data where appropriate) that could result in a trigger level being exceeded and any instrumented line or point in which a trigger level has been exceeded. TS 359/1065 978 Doc D.2/429 This Page Has Been Intentionally Left Blank TS 360/1065 978 Doc D.2/430 (11) C03-010 Concrete Construction Generally TS 361/1065 978 Doc D.2/431 1 S1 Not In Use GENERAL Read this Section with G01-010 "General Requirements" and all other contract documents. Read in conjunction with BS EN 13670 Execution of Concrete Structures. 1.1 Not In Use S1.1 Scope This work section covers general requirements for the use of structural quality concrete in plain, reinforced or prestressed structures. Relevant requirements may also be adopted for non-structural concrete, for example in external works. For particular requirements of specialists works such as prestressing and pre- cast, refer to the respective sections. 1.2 Related Sections Read this Section in conjunction with the relevant requirements of the following sections: C03-020 Reinforcement C03-030 Formwork and Falsework C03-040 Designed Joints 1.3 Standards, Codes, Regulations and Technical References 1.3.1 Not In Use S1.3.1 Standards and Codes Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant requirements of the standards and codes listed below or referenced in the body of the Specification. Alternative standards and codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative standards and codes comply with the requirements of the standards specified. All standards and codes quoted are the current version, unless specific year references are noted. In the event that the standards or codes are partially superseded or have become obsolete, refer to the current edition or the approved substitution for the relevant clauses. Singapore Standards SS EN 197-1 Cement – Part 1: Composition, Specification and Conformity Criteria for Common Cements SS EN 197-2 Cement – Part 2: Conformity evaluation SS EN 197-4 Cement - Part 4: Composition, specifications and conformity criteria for low early strength blast furnace cements TS 362/1065 978 Doc D.2/432 SS EN 206 Concrete – Specification, performance, production and conformity SS EN 1990 Eurocode – Basis of structural design NA to SS EN 1990 Singapore National Annex to Eurocode – Basis of structural design SS EN 1992-1-1 Eurocode 2: Design of concrete structure – Part 1-1 General rules and rules for buildings NA to SS EN 1992-1-1 Singapore National Annex to Eurocode 2: Design of concrete structure – Part 1-1 General rules and rules for buildings SS EN 1992-1-2 Eurocode 2: Design of concrete structure – Part 1-2 General rules – Structural fire design NA to SS EN 1992-1-2 Singapore National Annex to Eurocode 2: Design of concrete structure – Part 1-2 General rules – Structural fire design SS EN 1992-2 Eurocode 2: Design of concrete structures – Part 2: Concrete bridges Design and detailing rules SS EN 1992-3 Eurocode 2: Design of concrete structures – Part 3 Liquid retaining and containment structures SS EN 12620 Specification for aggregates for concrete SS EN 13791 Assessment of in-situ compressive strength in structures and precast concrete components SS EN 15167 Ground granulated blast furnace slag for use in concrete, mortar and grout Part 1:Definitions, specifications and conformity criteria Part 2:Conformity evaluation SS EN 934-1 Admixtures for concrete, mortar and grout – Part 1: Common requirements SS EN 934-2 Admixtures for concrete, mortar and grout – Part 2: Definitions, requirements, conformity, marking and labelling SS EN 934-4 Admixtures for concrete, mortar and grout – Part 4: Admixtures for grout for prestressing tendons SS EN 934-6 Admixtures for concrete, mortar and grout – Part 6: Sampling, conformity control and evaluation of conformity SS 544-1 Concrete – Complementary Singapore Standard to SS EN 206 – Part 1: Method of specifying and guidance for the specifier SS 544-2 Concrete – Complementary Singapore Standard to SS EN 206 – Part 2: Specification for constituent materials and concrete SS 592 Assessment of in-situ compressive strength in structures and precast concrete components – Complementary guidance to that given in SS EN 13791 SS 78 Testing concrete Part B1– Guide to the use of non-destructive methods of test for hardened concrete. Part B7– Recommendations for assessment of concrete strength by the near-to-surface tests Other Standards BS EN 932 Tests for general properties of aggregates. BS EN 933-1 Tests for geometrical properties of aggregates. Determination of particle size distribution. Sieving method BS EN 1008 Mixing water for concrete, specification for sampling, testing and assessing the suitability of water, including water recovered from processes in the concrete industry, as mixing water for concrete BS EN 13670 Execution of concrete structures BS EN 12350-1 Testing fresh concrete Part 1: Sampling and common apparatus TS 363/1065 978 Doc D.2/433 1.3.2 BS EN 12350-2 Testing fresh concrete – Part 2: Slump-test BS EN 12504 Testing concrete in structures - Part 1 Cored Specimen – taking, examining and testing in compression. BS EN 12390-1 Testing hardened concrete – Part 1: Shape, dimensions and other requirements for specimen and moulds BS EN 12390-2 Testing hardened concrete – Part 2: Making and curing specimens for strength tests BS EN 12390-3 Testing hardened concrete – Part 3: Compressive strength of test specimens BS EN 12390-7 Testing hardened concrete – Part 7: Density of hardened concrete BS EN 12390-8 Testing hardened concrete – Part 8: Depth of penetration of water under pressure BS 5606 Guide to Accuracy in Building BS 8204 Part 1 Code of practice Screeds, bases and in situ floorings. Concrete bases and cementitious levelling screeds to receive floorings. PD 6682-1 Aggregates. Aggregates for concrete. Guidance on the use of BS EN 12620 Regulations (a) 1.3.3 Building Control Act and Regulations Technical References Refer to the following technical references for guidance in carrying out the Works: (b) SAC CT 05 - SAC Criteria for Certification Bodies (Ready-Mixed Concrete) (c) SAC CT 06 - SAC Criteria for Ready-Mixed Concrete Producers (d) BCA, Guidebook on Sustainable Construction : A Guide on Concrete Usage Index (e) BCA, Guidebook on Sustainable Construction : The Use of Recycled Materials (f) British Cement Association Guide. Kickerless Construction, Ref. 47.023, 1988. (g) Building Research Establishment. Concrete in aggressive ground. Special Digest 1. 3rd edition. Watford: Building Research Establishment, 2005. (h) CIRIA Report C766 Early age thermal crack control in concrete (2019) (i) PD 6682-1:2009 Aggregates. Aggregates for concrete. Guidance on the use of BS EN 12620 (j) ERMCO, The European Guidelines for self-compacting concrete - specification, production and use. Brussels, European Ready-Mixed Concrete Organisation, 2005. TS 364/1065 978 Doc D.2/434 1.4 S1.4 1.4.1 (k) Harrison, T. A. and Brooker, O. How to use BS 8500 with BS 8110. Camberley, The Concrete Centre, 2005 MONKS, W. Plain formed concrete finishes. Technical Report 52. First edition. Camberley: The Concrete Society, 1999. (l) Concrete Society Materials Group, Development in durability design and performance-based specification of concrete. CS 109. Camberley: The Concrete Society, 1996. (m) THE Concrete Society, Guidance on the use of stainless steel reinforcement. Technical Report 51. First edition. Camberley: The Concrete Society, 1998. (n) Quillin, K., Nixon, P.J., Mattiiews, J. D., and Longworth, T. I. Concretes with high ggbs contents for use in hard/firm secant piling. Information paper IP 17/05. Watford: Building Research Establishment, 2005. (o) Bamforth, P. B. Enhancing reinforced concrete durability. Technical Report 61. First edition. Camberley: The Concrete Society, 2004. (p) Concrete Society. Concrete industrial ground floors - a guide to design and construction. Technical Report 34. Third edition. Camberley: The Concrete Society, 2003. (q) Building Research Establishment. Shrinkage of natural aggregates in concrete. Digest 357. Watford: Building Research Establishment, 1991. (r) Dhir, R. K., Limbachiya, M. C. and Beggs, A. Resolving application issues with the use of recycled concrete aggregate. University of Dundee, DETR Research Contract 39/3/478 (CC 1697), March 2001. (s) Building Research Establishment. Alkali-silica reaction in concrete. BRE Digest 330 (in four parts). Watford: Building Research Establishment, 2004. (t) Quillin, K. Delayed ettringite formation - In-situ concrete . Information Paper IP11/01. Watford: Building Research Establishment, 2001. Su) CONQUAS 21 (BCA) Not In Use Trade Preambles Not In Use TS 365/1065 978 Doc D.2/435 S1.4.1 Concrete Product Concrete for building and civil engineering structures is required to be supplied by Ready- Mixed Concrete (RMC) plants which are certified under the Singapore Accreditation Council (SAC) Certification Scheme for RMC based on SS EN 206, SS 544 and SAC CT 05 and SAC CT 06. This shall include on-site batching plants as well as plants supplying concrete for structural elements. Comply with the Building Control Regulations on ready-mixed concrete and product conformity certificate. Engage qualified and experienced personnel to prepare and submit concrete mix design to SO's acceptance. 1.4.2 Product Control System The concrete producer is required to have a documented production control system stated clearly in a production control manual based on SS EN 206, SS 544 and SAC CT 05 and CT 06. Comply with the Building Control Regulations on ready-mixed concrete and product conformity certificate. 1.4.3 Construction Joints Engage qualified and experienced personnel to prepare and submit proposal on suitable construction joints and details for acceptance by the SO. S1.4.4. Noise Nuisance Take all necessary actions to ensure compliance with the Environment Public Health Act, under Section 46 or the latest noise control regulations imposed by the NEA or any relevant authorities. The noise level at the nearest occupied building outside the Site is not to exceed the following maximum permissible noise level, or shall have met the noise control guidelines introduced by NEA whichever is the more stringent: Type of occupied buildings Applicable period Maximum allowable equivalent continuous noise level measured over a period of 5 minutes in dB (a) Hospital, school, home for 7am to 7pm 75 7pm to 7am 55 7am to 7pm 90 7pm to 10pm 70 10pm to 7am 55 7am to 7pm 90 7pm to 7am 70 the aged, sick etc. (b) Residential buildings located less than 150m from the construction site (b) Buildings other than those in (a) above TS 366/1065 978 Doc D.2/436 2 PERFORMANCE REQUIREMENTS 2.1 Certified Concrete Product Ensure that concrete for building and civil engineering structures shall be obtained from RMC plants which have been certified under the SAC’s Certification Scheme for RMC as provided in SS EN 206 and in Building Control Regulations. 2.2 Control on Shrinkage and Temperature Effects Control the construction such that any crack due to shrinkage and temperature effects does not exceed 0.1 mm wide. 2.3 Control on cracks Control and minimise cracking from all causes. Unless otherwise indicated in drawings, or agreed or directed by the SO, limits on cracking shall follow the SS EN 1992. 2.4 Construction Loads Ensure during construction that the structure is not subjected to loads that will cause short- term or long-term distress to the concrete. 2.5 Execution Class The Execution Class shall be based on SS EN 1990 and as defined in BS 13670. Unless otherwise indicated in the drawings or directed by the SO, other than for construction such as high strength concrete, post-tensioned construction, bridges and critical structures etc, minimum class for general construction shall be Execution Class 2. S2.6 Modifications Obtain written agreement of the SO to any modification of this Specification before any work is started. S2.7 Acceptance Procedure The SO shall comment on all information supplied within five working days of receipt. Acceptance or agreement by the SO shall have no effect unless given in writing. 3 S3 Not In Use MATERIALS Concrete shall conform to SS 544-2 and SS EN 206-1. TS 367/1065 978 Doc D.2/437 3.1 Cement 3.1.1 Portland Cement Comply with SS EN 197. 3.1.2 Sulfate-resisting Portland Cement Comply with the requirements of SS EN 197-1, Clause 7.4.2 3.1.3 Pulverized Fly Ash (Pfa) Comply with the requirements of SS EN 197-1, Clause 5.2.4 (Fly ashes). 3.1.4 Ground Granulated Blastfurnace Slag (GGBS) Comply with the requirements of EN 197-1, Clause 5.2.2 (Granulated blastfurnace slag). 3.1.5 High Alumina Cement Do not use. 3.1.6 Silica fume Comply with the requirements of EN 197-1, Clause 5.2.7 (Silica fume). 3.2 Fine Aggregates Comply with SS EN 12620 and fine aggregates shall not be alkali reactive. 3.2.1 Not In Use S3.2.1 Testing Be in accordance with BS EN 932 Tests for general properties of aggregates, and BS EN 9331 Tests for geometrical properties of aggregates and in accordance with SS EN 12620 3.2.2 Not In Use TS 368/1065 978 Doc D.2/438 S3.2.2 Grading The grading of the fine aggregates, determined in accordance with EN 933-1, shall comply with the requirements of SS EN 12620 as appropriate to the aggregate size. Grading shall be based on sieve analysis as described in SS EN 12620 and to be within the limits of the grading zones described as per the mix requirements and in the standards subject to a tolerance of 5%. The producer shall document and, on request, declare the typical grading for each fine aggregate size produced. In addition, unless otherwise agreed by the SO, fine aggregates shall comply with the requirements specified in SS EN 12620 Table 4. 3.2.3 Alternative to sand Propose for the SOs acceptance on the use of quarry dust for substitution for sand as fine aggregates in specified applications. 3.3 Coarse Aggregates Comply with SS EN 12620. All coarse aggregates shall comply with the general grading requirements specified in SS EN 12620 Table 2, appropriate to their size designation. 3.4 Water All water used for mixing concrete, mortar and grout, for cleaning out formwork and for curing shall be clean and free from harmful matter in solution or suspension. If taken from a source other than the Public Utilities Board, test in accordance with BS EN 1008. 3.5 S3.5 Not In Use Admixtures Comply with the requirements of SS EN 934-2 and SS EN 206-1. Submit for the SO’s acceptance of admixtures with detailed information, including name, type, dosage and justification for the use. 3.5.1 Not In Use TS 369/1065 978 Doc D.2/439 S3.5.1 Air Entrainment Air entraining admixtures shall comply with SS EN 934-1 and SS EN 934-2. Where other types of admixture are to be used together with air entrainers, comply with the requirements of SS EN 206 and SS 544 that the performance is not compromised. 3.5.2 S3.5.2 Not In Use Chloride Content Calcium chloride and chloride-based admixtures shall not be used, and shall not be added to concrete containing steel reinforcement, prestressing steel reinforcement or other embedded metal. Comply with SS EN 206 on the limits of chloride content. Provide written evidence of conformance. 3.5.3 Waterproofing Admixture Refer to Section C03-050 "Water Resistance to Concrete Structures" for general requirements of waterproofing admixture. 3.6 Method of Specifying Concrete 3.6.1 Not In Use S3.6.1 Designated Concrete Submit for the SO’s acceptance designated concrete as defined in SS 544 to be produced that shall satisfy requirements for strength and durability, and for designated applications. Submit for the SO’s acceptance the product conformity certification and the third-party certification in accordance to SS EN 206 and SS 544. [Note 1: Use of designated concretes is intended to encourage standardisation.] Designated Concrete The parts below shall be supplied as prescribed mixes in accordance with SS 544-1 and SS EN 2061 1 Requirements Defaults Defaults Defaults Concrete designation RC32/40 RC35/45 RC40/50 20 20 20 (ref SS544-2 Table 5) 2 Maximum aggregate size (mm) Enter 10, 14, 20 or 40 TS 370/1065 978 Doc D.2/440 3 Consistence class S3 S3 S3 None None None Special requirements for aggregates (enter None. Comply None. Comply None. Comply reference if required) with SS EN with SS EN with SS EN 12620 12620 12620 S1, S2, S3, S4 4 Special restrictions on cement types (enter reference if required) 5 6 Use of RCA permitted? Maximum mass fraction of total coarse Yes for Yes for Yes for superstructure. superstructure. superstructure. 20% 20% 20% aggregate enter a higher mass fraction of total coarse aggregate where permitted (Ref SS 544-1 cl 4.2.3c) 7 Requirements for accelerated or retarded set None No No 8 Special colour requirements None None None None or see 4.11.4 9 10 Type and dosage of fibres Refer to C3-20 Refer to C3-20 Refer to C3-20 Chloride class Cl1.0 for GEN series, Cl0.20 for Cl 0.40 Cl 0.40 Cl 0.40 SRPC, Cl 0.40 for all other concretes or enter special requirements 11 Minimum air content None None None 12 Method of placing content Normal Normal Normal 13 Requirement for finishing concrete None None None 14 Identity testing for consistence or other No No No properties required in accordance with SS EN 206-1 Annex B and SS544-1 Annex B. (If yes then details to be added into section 6 Notes 1. All sections of the specification must be completed before it is passed to the producer. The person sending the final specification to the producer must send copies of the document to all other parties (SO, Engineer, Employer as appropriate) who have contributed to the specification. 2. Where ‘None’ is entered in the table this is a default value to ensure that the specification is complete. All those involved in completing the specification need to check if ‘None’ is applicable 3. Guidance on specification of designed concrete can be found in SS544-1, section 4.2. TS 371/1065 978 Doc D.2/441 3.6.2 Designed Concrete Submit for the SOs acceptance designed concrete as an alternative to designated concrete as defined in SS 544 to be used where the requirements are outside of those covered by designated concretes. [Note 1: The environment to which the concrete is to be exposed is identified in SS 544 Part1. Using the intended working life and the minimum cover to reinforcement, the limiting values of composition are determined for each of the identified exposure classes using the guidance in A.4 of SS 544 Part 1. The requirements for the concrete are selected from the composite of limiting values plus structural and fire considerations, and the specification requirements will follow in accordance with 4.3 of SS 544 Part 1. Note 2: Guidance on the specification of designed concrete to resist identified exposure classes is given in A.4 of SS 544 Part 1.] 3.6.3 S3.6.3 Not In Use Prescribed Concrete Submit for SO’s acceptance where prescribed concrete is to be used in accordance with SS EN 206 and SS 544, and with evidence that the initial testing to determine that the specified proportions shall achieve the intended performance in the fresh and hardened states with an adequate margin as required in SS EN 206. Where prescribed concrete is used, ensure that the specified proportions do not result in damaging alkali-silica reaction (ASR). Where required, provide concrete mixes in the PSD 3.6.4 S3.6.4 Not In Use Chloride Content Limit the chloride content of the proposed concrete, including chloride contained in the admixtures, to that specified in SS EN 206-1, Clause 5.2.8 (Chloride content), ad SS 544-2 Clause 5.3 (Chloride content). Provide written evidence of conformity. 3.6.5 Sulfate Content Limit the sulfate content in the proposed concrete in accordance with SS 544-2, Clause 4.3 (Aggregates). 3.6.6 Calcium Chloride Calcium chloride shall not be included in any concrete. TS 372/1065 978 Doc D.2/442 3.6.7 Alkali-Silica Reaction Ensure that the requirements with preventative measures in accordance with SS EN 206, Clause 5.2.3.5 (Resistance to alkali-silica reaction) and SS 544-2 Annex D (Minimizing the risk of damaging alkali-silica reaction in concrete) and SS 544-1 Clause A.8.1 (Alkali- aggregate reaction) are met to avoid any alkali-silica reaction. Test aggregates to determine any varieties of susceptible silicas and for other requirements by the authorities or by the SO. 3.6.8 Additions or Changes Do not make additions or changes to the fresh concrete after batching without the prior agreement of the SO. In the event of any addition to the fresh concrete before discharging on site, the concrete shall be deemed non-conforming until identity testing for strength shows that the concrete is acceptable unless the addition is made by the producer using a procedure agreed in advance with the SO. 3.7 Not In Use S3.7 Ready-Mix Concrete Plant S3.7.1 Third Party Accreditation All concrete shall be ready-mix concrete. Ready-mixed concrete shall be supplied by a producer from a plant holding current accredited third-party certification meeting requirements of SS EN 206-1, Annex C and SS 544. Provide the SO with confirmation of the producer’s certification in accordance with SS EN 206-1 Annex C3 and SS 544. S3.7.2 Information Required Details of a ready-mix concrete plant proposed for use shall be forwarded to the SO for acceptance. Provide contingency plans prior to commencement of work in the event of supplies being interrupted during a pour due to a plant breakdown. Where feasible, details of a suitable backup plant/supplier should be submitted to the SO for acceptance. S3.7.3 Addition of water to ready-mixed concrete Water should not be added on site but if it is added to the concrete truck mixer drum before discharge on site, the concrete shall be deemed non-conforming until identity testing for strength shows that the concrete is acceptable unless the addition is made by the producer using a procedure agreed in advance with the SO. The water added shall be recorded on the delivery ticket. Note: The addition of water on site is undesirable and should be avoided wherever possible. It is considered prudent to sample such concrete including the production and testing of concrete cubes to verify that the required concrete strength has been achieved. TS 373/1065 978 Doc D.2/443 3.8 Surface Hardener The surface hardener shall consist of aggregate particles which have a hardness of not less than 7, as measured on Moh’s hardness scale. 3.9 Sustainable Construction 3.9.1 General Refer to the guidelines in BCA Publication on Sustainable Construction on ways to use less natural aggregates which include: 3.9.2 S3.9.2 (a) Recycling, upcycling and use of recycled materials (b) Efficient use of natural materials through lower concrete usage Not In Use Alternative substitutes Submit for SO’s acceptance on the use of alternative substitutes, including recycled materials to natural aggregates in accordance to SS EN 12620 and SS 544, particularly on the requirements for both the use and testing of recycled concrete aggregates and recycled aggregates. Do not use recycled aggregate and recycled concrete aggregate without approval. If allowed, recycled aggregate and recycled concrete aggregate shall confirm to SS 544-2 Clause 4.3 (Aggregates), section 3.3 (Fine aggregates), section 3.4 (Coarse aggregate), and other relevant local standards and guidelines. Refer also to the guidelines in BCA Publication on Sustainable Construction: A Guide on the Use of Recycled Materials. [Note 1: Any recycled materials shall comply with material tests as set out in this Section. Recognised non-construction post-consumer or post-industrial by-products to be used for recycled content include: - ground granulated blast furnace slag (ggbfs) - air-cooled blast furnace slag (acbfs) - pulverised fuel ash (PFA) - furnace bottom ash (FBA) - silica fume With cement replacement, due consideration shall also be given to concrete curing time and method as appropriate.] TS 374/1065 978 Doc D.2/444 3.9.3 Recycled concrete aggregates from demolition waste Submit for SOs acceptance on the use of recycled concrete aggregates that are mainly derived from the crushed concrete from demolition waste, for non-structural works involving constructing nonload-bearing walls, small drains, kerbs, footpaths, non-suspended slabs, lean concrete, etc. and for road works as the sub-base in according to the requirements of Sections C070-010 and C07-020. 3.9.4 Concrete Usage Index For demonstrating on the optimal use of concrete, the Concrete Usage Index (CUI) which is an indicator of the amount of concrete used per unit floor area in building works as defined in the BCA Guidebook on Sustainable Construction: A Guide on Concrete Usage Index, shall be used. 3.10 S3.10 Not In Use Information on Concrete by Producer Submit to the SO for approval, details of the proposed concretes in accordance with SS EN 206-1, Clause 7.2 (Information for the producer of the concrete to the user) and SS 544-1 clause 5.2 (Information from the producer of the concrete to the specified or user), as appropriate. S3.11 Storage of Materials All materials shall be stored in an agreed manner that prevents damage or degradation and is in accordance with all manufacturers requirements 4 WORKMANSHIP 4.1 Not In Use 4.2 Not In Use S4.1 Transportation of Concrete Supply and transport all concrete to the point of discharge from the mixer/agitator in accordance with SS EN 206-1 Clause 7 (Delivery of fresh concrete) and SS 544-2 Clause 14 (Transport of concrete). 4.2.1 Not In Use TS 375/1065 978 Doc D.2/445 S4.1.1 Delivery Tickets Information shall be in accordance with SS EN 206-1, Clause 7.3 (Delivery ticket for ready- mixed concrete) and SS 544-2, Clause 11 (Delivery of fresh concrete) and shall be completed and available prior to discharge of concrete into the structure. 4.2.2 Not In Use 4.3 Not In Use S4.2 Inserts Ensure that any cast-in inserts are securely fixed prior to placing concrete. 4.4 S4.3 Not In Use Placing and Compaction Place and compact the concrete in accordance with BS EN 13670 Clause 8.4 (Placing and Compacting). Place and fully compact the concrete to avoid cold joints and honeycombing, and to minimise segregation, excessive blemishes or other defects in the hardened concrete. Compaction shall be carried out without causing damage of displacement to the formwork, reinforcement, tendons, ducts, anchorages, inserts etc. 4.5 Not In Use S4.4 Kickers Kickers shall be monolithic with the slab, of sound construction and not less than 100 mm high. Where kickerless construction is specified on the drawings provide details of the proposed method of securing and sealing the column and wall shutters at floor joints to the SO for agreement, taking guidance from the British Cement Association Guide: Kickerless Construction. Ensure robustness of the chosen method of construction and cast a sample wall and column panel for the SO’s approval. S4.5 Premature Cessation Suitable arrangements for premature cessation of a pour shall be agreed and in place before work starts. Should premature cessation of a pour arise, agree with SO the extent and timing of any necessary remedial work before resumption of placing. TS 376/1065 978 Doc D.2/446 4.6 Construction Joints 4.6.1 Not In Use TS 377/1065 978 Doc D.2/447 S4.6.1 General Engage qualified and experienced personnel to prepare and submit suitable construction joints and details for acceptance by the SO. Position and form joints such as to suit the structure and to avoid distress to the structure. Unless otherwise agreed with the SO, limit pour sizes as listed in the Table 1: Table 1. Pour sizes Construction Max. Area (m²) Max. Dimension (m) Water-resisting walls 25 5 Water-resisting slabs 100 10 Slabs with major restraint at both ends 100 13 Slabs with major restraint at one end only 250 20 Slabs with little restraint in any direction 500 30 Walls 40 10 Note: Details and locations of construction joints should be agreed well in advance of any construction. The Contractor shall position and form construction joints to suit the structure and so as to not cause any long or short term distress to the structure particularly from thermal and shrinkage effects. Pour sizes should be agreed early in the construction period between the Contractor and the SO. The Table has been included to provide a benchmark – the values given will be appropriate where the experience and the resources of the Contractor are more limited, but may be amended subject to the SO’s satisfaction with the values proposed. It should be noted that the pour size is unrelated to the number of restraints imposed upon slabs. The size and location of restraints define where special measures have to be taken regardless of pour sizes. Where the maximum size of pour permitted differs significantly from the values suggested by the Table, the actual size should be specified in the Project Specifications. The Contractor may also propose his own variation. Controlled large area pours are frequently carried out where the economic conditions are suitable and suitable construction methods are available. Ideally pours should only be restricted to the area that the contractor can place in a working day. Further guidance can be obtained by reference to Large Area Pours for Suspended Slabs Reinforcing LINKS Issue 3 by RCC 1992 and published by British Cement Association. The advice on pour sequencing, joint details etc. is different for ground supported slabs particularly industrial and warehouse slabs. Guidance for this is given in a number of documents such as Concrete Society Technical Report No 34, British Cement Association ‘Concrete ground floors: their design, construction and finish’ etc. 4.6.2 Not In Use TS 378/1065 978 Doc D.2/448 S4.6.2 Preparation of Construction Joints Carefully prepare construction joint surfaces to expose the coarse aggregate and leave a roughened surface to provide a key. Apply a layer of cement grout on the joint surface prior to pouring fresh concrete against a construction joint. [Note: This is done to ensure aggregate interlock at the joint face; the most satisfactory results are generally obtained by carrying out the preparation while the concrete is still green. Methods of removing laitance are normally either brush with water spray or pressured water jet. Timing of the operation is critical. Attempts to produce a suitable finish after the concrete has hardened will often be unsatisfactory because of inadequate exposure of the aggregate, high cost, or tendency to fracture the coarse aggregate. For vertical surfaces (e.g. stop ends) expanded metal mesh can be an alternative method of providing a roughened face, although for water-resistant concrete particular attention is required to ensure that the joint is properly formed and that the form does not itself provide an entry route for water. Details and locations of construction joints and pour sizes should be agreed well in advance of any construction. Construction joints should be positioned and formed to suit the structure. For further guidance, refer to publications by Concrete Society, British Cement Association ‘Large Area Pours for Suspended Slabs’ and Technical Report No 34 Concrete ground floors: their design, construction and finish, etc.] 4.7 S4.7 Not In Use Concreting in Hot Weather Comply with the recommendations of SS 544-1, Clause A.8.2 (Delayed ettringite formation), and Clause A.9.3 (Work in hot weather), and refer to SS EN 206, Clause 5.2.9 and SS 544-2, Clause 5.4 (Concrete temperature) where appropriate. Cool formwork made of metal, concrete or other material with water before placing concrete against it. Ensure no standing water is left in formwork. 4.8 Pours with Temperature Control In pours, when temperature control measures are necessary to achieve the performance requirement of crack control due to temperature and shrinkage, mentioned in Section C3010:Clause:2.2, or when rich mixes are to be placed at high ambient temperatures, or when directed by the SO, take actions on the following: (a) Propose suitable methods to SO for acceptance to ensure the temperature of the concrete does not exceed 70°C during hydration. TS 379/1065 978 Doc D.2/449 (b) Control the temperature gradient across the section by the provision of thermal insulation to prevent a differential greater than 20°C. (c) Monitor the temperature of the concrete through the section. (d) Continue temperature monitoring until the hottest part of the section is less than 20°C greater than the minimum daily ambient temperature. (e) Protect the concrete from abrupt changes in temperature at the end of the curing period. (f) Inspect and remove any bleeding water and weak concrete at the top surface prior to the setting of concrete. Replace surface concrete and re-compact if necessary. Propose for SOs acceptance on adjustment of the limits on temperature differential taking into consideration the assessment of information concerning the aggregate type and its effect on the thermal coefficient of expansion of the concrete. [Note 1: In some practice, a concrete temperature limit is 65ºC instead of 70ºC.] 4.9 S4.9 Not In Use Control of Early Age Thermal Cracking When concrete is to be placed in conditions or in an element where early age thermal cracking is likely, all reasonable measures shall be adopted that minimise the risk of early age thermal cracking to a level acceptable to the SO. Where a risk of thermal cracking is identified, the location of monitoring apparatus and interpretation of the values recorded shall be agreed with the S.O. prior to installation. Where cracking occurs that it is expected will result in corrosion of the reinforcement, unacceptable water leakage, impaired durability or reduced structural adequacy, it will be rectified as agreed with the SO. Unless otherwise specified in table below, isolated crack in general reinforced concrete superstructure shall be limited to 0.3 mm wide. Location Crack width Water tight structures 0.2mm Note: All parties should be aware that concrete will crack and that in most cases this is not harmful. The 0.3 mm surface crack width limit for superstructures is taken from NA to SS EN 19921-1:2004 Table NA 4. TS 380/1065 978 Doc D.2/450 4.10 Protection from Rain Protect the concrete during transportation and after placing using tarpaulins, polythene sheeting etc. If heavy rain commences during concreting or as directed by the SO, implement appropriate protection measures before continuing. 4.11 Concrete Finishes All concrete formed and unformed finishes shall be classified Basic, Ordinary, Plain and Special Concrete finishes in accordance with BS EN 13670. 4.11.1 S4.11.1.1 Not In Use Formed Finishes Unless otherwise specified in the drawings or directed by the SO, formed concrete finishes shall be Ordinary Finish in accordance with BS EN13670. Prepare a sample of the specified formed finishes at the start of the Contract for SO’s acceptance, and to be kept and used as a reference throughout the duration of the Contract. Note: It is important not to 'over-specify' the quality of finish, particularly where it is covered over by following work. All finishes assume that the concrete is fully compacted. The 'normal' finish assumed for all work is BS EN 13670 Ordinary finish for formed finish. Finishes of higher quality will usually cost more –but the costs may be offset where no applied finishes are then required. A BASIC finish is that normally applicable to such items as sides of foundations and ground beams etc. where no particular requirement is needed other than to ensure compliance with all other clauses of the specification such as concrete compaction, cover to reinforcement etc. ORDINARY finish: This is for use where visual quality is not important or it is to receive applied finishes. It is recommended that this finish is not used where surfaces are only to be painted. The use of small panel forming systems is considered suitable for producing this finish. Joints between formwork panels will show and the step may be up to 5 mm. grain marks are generally due to slight absorbance variations causing local colour variation, but the surface is generally smooth. Panels and blot holes may not be in a regular pattern. Colour of the finish will vary with the concrete delivered, the release agent used and reuse of the forming material. Project sample panels should not be specified for this finish. As the concrete finish is not important visually, making good is acceptable and so blowholes and minor surface blemishes can either be dealt with or accepted untreated by agreement between the SO and Constructor based on achieving an overall standard similar to the reference panels. If a system formwork is to be used, the finish off the formwork will generally be acceptable and the SO is expected to be aware of its quality. PLAIN finish is for use where visual quality is of some importance such as areas occasionally seen or to be directly painted. The use of sheet material to limit jointing in forming material is considered suitable for producing this finish. In any one visible elevation the sheets should be of the same type and have had the same number of previous uses. Joints between formwork panels will show and the step may be up to 3 mm. Tie-bolt holes should ideally be recessed, TS 381/1065 978 Doc D.2/451 or alternatively filled flush, although this may not be so aesthetically pleasing. Panels and bolt holes should be in a regular pattern. Colour of the finish will change with concrete delivered and reuse of the forming material. A special project panel should not be specified for this finish, but a project example should be produced as one of the first areas of concrete poured on the project and used as the benchmark for the rest of the concrete. SPECIAL finishes should be specified for in the architectural formed finishes and when a worked finish is required. Sample panels will be required using the forming system and concrete to be used on the project for producing the particular finish. The size and complexity of the sample should be agreed to test the project detail and confirm that the execution can produce the finish on a repetitive basis will be a special finish to a particular requirement. A site sample is necessary. Where this is required, there needs to be clear understanding of what is needed. Particular care is necessary in the selection of concrete and formwork materials, and in consideration of placing, compacting etc. Specification considerations for producing special finishes: a. Required surface regularity must be achievable b. Allowable colour variation of the surface based on generic colour of the concrete. c. Extent of acceptable blowholes. These depend on formwork type, concrete, release agent and compaction – some blowholes are inevitable. d. How much making good may be expected – some is inevitable e. Arris type required f. use of cover spacers g. arrangement of formwork joints and tie holes (filled but ideally recessed) h. Location of a ‘sample’ or similar finish a. special tolerances – must be achievable j. light reflectance Where finishes to precast beams and slabs are required to allow in‑situ concrete to act compositely, these areas to be clearly identified and described. Where surface finishes to concrete are required to be smooth and level to provide bearings for precast slabs or beams these areas shall also be clearly identified and described. For further information on special finishes refer to NSCS Guidance. S4.11.1.2 Basic Finish There are no requirements for finish other than to enable adequate compaction, to provide adequate cover to reinforcement and to achieve specified tolerances S4.11.1.3 Ordinary Finish There are no special formwork requirements for this finish, Concrete should be thoroughly compacted and the formed surface should be free from major inherent blemishes and honeycombing. There is no requirement for consistency of colour for the struck surface. Surface defects may be made good subject to agreeing a method with the SO. Steps at joints between forms to be a maximum of 5 mm. TS 382/1065 978 Doc D.2/452 S4.11.1.4 Plain Finish A plain concrete finish requires the careful selection of the concrete, release agent, and the use of good quality formwork. The concrete must be thoroughly compacted and all surfaces should be true with clean arrises. Only very minor inherent surface blemishes should occur, with no discolouration from the release agent or grout runs from adjacent pours. The struck surface should be of a consistent colour from the materials used. The arrangement of formwork panels and tie-bolt holes should be in a regular pattern. Steps at joints between forms to be a maximum of 3 mm. It is expected that this finish will not require making good. S4.11.1.5 Special Finish A special finish requires the careful selection of the concrete, release agent, the use of good quality formwork and through compaction. Special finishes (other than formed or unformed, basic and ordinary finishes) are required as follows: TS 383/1065 978 Doc D.2/453 S4.11.2.1 Unformed Finishes Unless otherwise specified in the drawings or directed by the SO, unformed concrete finishes shall be Basic Finish. [Note 1: Some practice uses ‘Brushed Finish’. Brush surface of concrete while still green, with a stiff broom or wire brush to produce a lightly textured surface. Bristles shall be 1.6 mm diameter unless otherwise agreed by the SO. Brush consistently and continuously across each area designated.] Note: Basic finish: This is normally applicable for areas to receive a levelling or wearing screed. A closed finish produced by levelling, and use of a skip float or similar process. Float marks and ridges will occur. No further work is required. Ordinary finish: This is for use in areas to receive flooring materials, types of false floor or other raised finish. It may not be suitable for thin vinyl flooring without grinding or an underlayment. If thin vinyl with minimum additional work is required, a Plain finish should be specified. This is a level uniform surface produced typically by hand or power floating but not by skip float or similar process. The finish is to be free from ridges but fine float marks are to be expected. This may be acceptable for the application of finishes such as tiles or carpet. Plain finish: This is for use in areas without any other finish other than paint or surface coatings, and provides a dense smooth surface typically produced by hand or power trowelling. This may be suitable for directly trafficked surfaces – see BS 8204: Screed, cases and in-situ flooring. Special finish: This is for industrial floors, areas of special trafficking or areas requiring a specific texture (e.g. tamped or brushed), and can be produced by further working other finishes. This is a finish where special requirements have to be given. Where power finishing is not practically possible or not permitted due to working time restrictions, there is a risk of reinforcement ripple occurring if using a skip float. A thin bonded smoothing compound may be necessary in the situation where a smooth wearing surface is required, or an underlayment can be used where a thin flooring material is to be laid. Where the element is to provide a smooth wearing surface or to receive directly applied flooring without the need for a levelling screed, the regularity should comply with the requirements of BS 8204-2 or Concrete Society publication TR34 Concrete Industrial ground floors – A guide to their design and construction. S4.11.2.2 Basic Finish The concrete shall be levelled by skip float, or similar process to produce a closed uniform surface. No further work shall be carried out. S4.11.2.3 Ordinary Finish The concrete shall be finished by floating or panning or a similar process, to produce a level, uniform surface. No further work shall be carried out. TS 384/1065 978 Doc D.2/454 S4.11.2.4 Plain Finish The concrete shall be finished by trowelling or a similar process, to produce a dense, smooth, level, uniform surface. No further work shall be carried out. S4.11.2.5 Special Finish To be produced by further working of a finish or other improvements as specified herewith. 4.11.2 Not In Use 4.12 Curing and Protection 4.12.1 Not In Use S4.12.1 Curing Cure the surface of the concrete to avoid premature drying-out. Methods of curing shall be in accordance with BS EN 13670, Clause 8.5 (Curing and protection) and as agreed with the SO. On completion of compaction and operations on the concrete, the surface shall be cured without delay. Commence curing immediately after compaction: protection from radiation to be in place within 30 minutes of final tamping. Curing membranes shall be compatible with any finishes to be applied subsequently. The duration of applied curing shall be a function of the development of the concrete properties in the surface zone. Unless otherwise directed by the SO or shown in the drawings, propose for the SO’s acceptance on the curing class to be used. The curing classes shall be as defined by curing period or percentage of the specified characteristic 28 days compressive strength, according to Table 4, BS EN 13670. Refer to BS EN 13670 Annex F Table F.1 for curing time. In any case, cure time shall not be less than 3 days after casting. S4.12.2 Protection Protect the structure against damage. Propose methods for the repair of any damage occurring to make good subject to the agreement of the SO. S4.12.3 Early age thermal cracking When concrete is to be placed in conditions or in an element where early age thermal cracking is likely, measures shall be adopted that minimise the risk of early age thermal cracking to a level acceptable to the SO. Ensure that the temperature of the concrete does not exceed 65°C and that the temperature differential does not exceed the appropriate values given in CIRIA report C660 (Bamforth 2007), Table 7.1. Where a risk of thermal cracking is identified, the location of monitoring apparatus and interpretation of the values recorded shall be agreed with the SO prior to installation. TS 385/1065 978 Doc D.2/455 4.12.2 Not In Use 4.11.2.1 Not In Use 4.11.2.2 Not In Use 4.13 Not In Use S4.13 Accuracy of Construction Propose and submit to the SO for acceptance on the permissible deviations for the corresponding works or structure to be undertaken, and specific items or elements or part of the structure where tighter accuracy shall be required. Carry out regular checks on the accuracy of the structure and if a part of the structure is found to be out of tolerance, propose any remedial work required. The following are the permitted tolerances for the structure as defined on the drawings. These tolerances take precedence over BS EN 13670. The tolerances for position refer to the tolerance from the reference lines and datum. Any deviation in secondary lines is included in the tolerances given. Note: It is important that ambiguity in the specification of permissible deviations is removed in order to avoid possible disagreements at a later stage. The values given below are obtained from the UK National Structural Concrete Specification for Building Construction for guidance only. The following values take precedence over those given in BS EN 13670. They are practical values which are believed to be sensibly achievable on site. There may be cases where tighter values are needed – but there will usually be a cost associated with this. Further guidance on dimensional deviations for in-situ concrete can be found in Table 1 of BS 5606:1990. 4.13.1 S4.13.1 Not In Use Hierarchy of Specified Permissible Deviations The hierarchy of tolerance adopted in this specification is such that the tolerance of each level must be contained within the tolerances level of the level above where 1 is the highest level: First – the overall tolerance of the structure Second – the positional tolerance of all parts of elements of the structure within the overall tolerance Third – the dimensional tolerance of the individual elements within their positional tolerance Fourth – the opposition tolerance of reinforcement and fixings within the individual elements dimensional tolerance clause 4.13.2 Size of Elements TS 386/1065 978 Doc D.2/456 4.13.2.1 Slab thickness Permitted deviations on slab thickness shall be as given in Table 2. Table 2. Permitted deviations on slab thickness Thickness, t (mm) 4.13.2.2 Permitted deviation, D (mm) Up to and including 150 ±6 Over 150 up to and including 600 ± 10 Over 600 up to and including 1000 ± 15 Over 1000 ± 20 Formed elements The linear dimension L of formed elements (including beams, columns, walls, openings) shall be accurate to be kept within the values given in Table 3 and as illustrated in Figure 1 where L is length, height or width of element in the direction considered. Table 3. Permitted deviations on formed elements L Permitted deviation, D (mm) Up to and including 600mm 8 Over 600mm up to and including 1.5m 10 Over 1.5m up to and including 8m 15 Over 8m up to and including 15m 20 Over 15m up to and including 30m 30 Over 30m 30 + 1mm per metre or part over 30m Figure 1 TS 387/1065 978 Doc D.2/457 4.13.3 Twist of Elements The distance from any one corner to the plane containing the other 3 corners to be accurate within the values given in the Table 4 and as illustrated in Figure 2. Figure 2 Table 4. Permitted deviation ontwist of elements L 4.13.4 Permitted deviation, D (mm) Up to and including 600mm ±6 Over 600mm up to and including 3m ± 10 Over 3m up to and including 8m ± 15 Over 8m ± 15 + 2mm per metre or part over 8m Squareness of elements Permitted deviation on squareness of elements shall be within the values given in Table 5 and as illustrated in Figure 3. Figure 3 Table 5. Permitted deviation on squareness of elements L 4.13.5 Permitted deviation, D (mm) Up to and including 600mm ±6 Over 600mm up to and including 2m ± 10 Over 2m up to and including 4m ± 15 Over 4m ± 15 + 1mm per metre or part over 4m Position on Plan TS 388/1065 978 Doc D.2/458 4.13.5.1 Foundations Permitted deviation for position on plan of any element of the foundation relative to the intended position = ± 30 mm as illustrated in Figure 4. Figure 4 4.13.5.2 Elements above foundation Permitted deviation for position on plan of any element above the foundation relative to the intended position = ± 10 mm measured at floor level as illustrated in Figure 5. Figure 5 4.13.5.3 Edge of slab Permitted deviation of position on plan of slab edges is relative to the intended position = ± 10mm measured at floor level. 4.13.6 Level of Elements The following tolerances are for surfaces that will receive further levelling finishes and are prestrike. 4.13.6.1 Intended level Permissible deviation from intended level = ± 10mm 4.13.6.2 Top of foundation Permissible deviation of the top surface of any foundation = ± 25 mm TS 389/1065 978 Doc D.2/459 4.13.6.3 Level of intersecting beams Permissible deviation of beams intended to be at the same level = + 10 mm Level between 2 points 6 m apart Permissible deviation 10 mm as illustrated in Figure 6. Figure 6 Any point under a 3 m straight edge Permissible deviation for any position on floor 6mm as illustrated in Figure 7. Figure 7 4.13.7 Cast-in Fixings Permissible deviation from intended position = 6mm as illustrated in Figure 8. Figure 8 TS 390/1065 978 Doc D.2/460 4.13.8 Verticality of Elements Plumb over a height, including beams or edges above each other shall be accurate to within the values given in Table 6 and as illustrated in Figure 9. Figure 9 Table 6. Verticality of elements Height(m) 4.13.9 (mm) Up to and including 1.5 5 Over 1.5 up to and including 2.5 10 Over 2.5 up to and including 4 15 Over 4 up to and including 8 20 Over 8 20+1mm per metre or part over 8m (to a maximum of 50mm) Bow of Elements Unspecified bow is as measured between extremities. Permissible deviation shall not exceed the values given in Table 7. Table 7. Permitted deviation for bow of elements Length (m) (mm) Up to and including 1.5 ±5 Over 1.5 up to and including 3 ±8 Over 3 up to and including 5 ±10 Over 5 up to and including 8 ±15 Over 8 ±15 +1mm per metre or part over 8m (with a maximum of 25mm) TS 391/1065 978 Doc D.2/461 4.13.10 Specified Pre-camber Permissible deviation shall not exceed the values given in Table 8 and as illustrated in Figure 10. Figure 10 Table 8. Permitteddeviation for specified pre-camber Specified camber (mm) 4.13.11 (mm) Up to and including 20 ±5 Over 20, up to and including 40 ±10 Over 40 ±15 Abrupt Changes to Continuous Surfaces where Finish is not Specified Permissible deviation shall not exceed 3 mm as illustrated in Figure 11. = Permitted up to 3 mm. TS 392/1065 978 Doc D.2/462 4.13.12 Cast-in Foundation Bolts Preset foundation bolt or bolt groups when prepared for adjustment. Permitted deviation from specified position as illustrated in Figure 12. Figure 12 Preset foundation bolt or bolt groups when not prepared for adjustment. Permitted deviation from specified position as illustrated in Figure 13. Figure 13 Preset wall bolt or bolt groups when not prepared for adjustment. Permitted deviation from specified position as illustrated in Figure 14. Figure 14 4.13.13 Openings for Services Permitted deviations for openings = +10 mm for size and ±25 mm for location. 4.14 Premature Cessation after Placing and Compaction Propose for the SOs acceptance on suitable arrangement for premature cessation of a pour shall be agreed and in place before work starts. Should premature cessation of a pour arise, agree with SO the extent and timing of any necessary remedial work before resumption of placing. 5 VERIFICATION AND SUBMISSIONS TS 393/1065 978 Doc D.2/463 5.1 Compliance Testing Carry out sampling and testing during concreting operations in accordance with SS EN 206 and SS 544-2. Agree with the SO on the electronic submission of all test results to the SO as soon as they are available. 5.1.1 S5.1.1 Not In Use Delivery Tickets for Ready Mixed Concrete Delivery ticket information shall be in accordance with SS EN 206-1 Clause 7.3 (Delivery ticket for ready mixed concrete) and SS 544-2 Clause 11 (Delivery of fresh concrete) to be completed and available prior to discharge of concrete into the structure. Where the Constructor authorises the addition of extra water this shall be recorded on the delivery ticket. All delivery tickets shall be retained by the Constructor until the structure is handed over to the Employer. Where a ticket is marked ‘nonconforming’ a copy shall be passed to both the Constructor and SO within 24 hours of placing the concrete. 5.1.2 Addition of Water No water or other materials shall be added to the ready-mix truck mixer drum before discharge, and comply with SS EN 206 Clause 7.5. In special cases, admixtures, pigments, fibres or water may be added where: (a) this is under the responsibility of the producer (b) the consistence and the limiting values conform to the specified values (c) there is a documented procedure for undertaking this process in a safe manner within the factory production control (d) if water is added, a conformity control shall be carried out on a sample of the final product. The quantity of any water, admixtures, pigments or fibres (if the content of fibres is specified), added to the truck mixer shall be recorded on the delivery ticket in all cases. And the concrete shall be remixed until the added constituent has been completely dispersed throughout the batch of load and, in the case of an admixture, has become fully effective. 5.1.3 Not In Use TS 394/1065 978 Doc D.2/464 S5.1.3 Compression Testing of Concrete Cubes Test concrete cubes in an independent accredited laboratory. Testing of fresh concrete shall be in accordance with BS EN 12350. Concrete test cubes shall be manufactured, initially cured and subsequently transported to an independent accredited SAC SINGLAS laboratory in accordance with BS EN 12390-2, for testing in accordance with BS EN 12390. 5.1.3.1 Electronic Tagging of concrete cubes Unless otherwise agreed with the SO, all concrete cubes are required to be electronically tagged to allow accurate tracing of the cube samples. Propose suitable electronic tagging system for SOs acceptance. Propose and provide an electronic recording system with the following capability: 5.2 (a) Relevant data can be authenticated at the request of the SO (b) Results can be transmitted to the SO via the internet system, within 3 hours of the test (c) Data management software is supplied and capable of providing analysis of the results, including standard deviation computations. The software shall also be capable of displaying the cube testing data and analysis graphically. (d) All data can be compiled and electronically submitted to the SO at the end of the project. Delivery Tickets for Ready Mixed Concrete Delivery ticket information shall be in accordance with SS EN 206 Clause 7.3 (Delivery ticket for ready mixed concrete) and SS 544-2 Clause 11 (Delivery of fresh concrete) to be completed and available prior to discharge of concrete into the structure. 5.3 Inspection 5.3.1 Inspection Before Concreting Inspect the formwork, spacers, fixed reinforcement and inserts before placing the concrete. Allow concrete to be placed only when the works are inspected and satisfactorily accepted by the SO. 5.3.2 Inspection After Concreting Inspect the concrete after the specified curing period. Identify any remedial work required and submit proposal of rectification for agreement by the SO. TS 395/1065 978 Doc D.2/465 5.4 Temperature Control Provide evidence that the temperature of the concrete will not exceed 70°C during hydration where large sections and/or rich mixes are being used. 5.5 Assessment of In-situ Compressive Strength Propose for the SOs acceptance an in-situ concrete testing schedule on the test types, locations, the number of tests and test standards to be carried out. Carry out assessment of in-situ compressive strength as indicated in the schedule, drawing or as directed by the SO, and carry out the assessment in accordance with SS EN 13791. Carry out assessment of characteristic in-situ compressive strength by testing of cores or indirect methods in accordance with SS EN 13791 to the concrete structure as indicated in the schedule or as directed by the SO. S5.6 Non-Destructive Testing Carry out non-destructive tests as indicated in PSD. Carry out the tests in accordance with the relevant parts of SS 78, BS EN 12350, BS EN 12390, BS EN 12504, SS EN 13791 Cl 9 and SS 592. S5.7 Action in the Event of Non-conformity Any test or inspection reports that show that any part of the structure does not meet the specified criteria shall be reported to the SO, as soon as the results are available. Provide proposals for dealing with the non-conformity to the SO within five working days of reporting the results. SS EN 13791 Cl 9 and SS 592 provide guidance on the situation. A course of action shall be agreed within a further five working days. The cost of all additional testing and remedial works shall be at the Constructor’s expense. S5.8 As-Built Drawings Obtain authority approved plan from SO; update the plan to capture all deviations or amendments, if any, including those captured in SO’s Instructions (SOIs), Project Manager’s Instructions (PMIs), Architect’s Instruction (AIs), Engineer’s Instruction (EIs), Request for Informations (RFIs), etc.; submit the plan as as-built drawings to SO for record and authority record plan submission. The as-built plan shall be submitted progressively floor by floor not later than two weeks from casting date. S6 Added clause TS 396/1065 978 Doc D.2/466 (12) C03-020 Reinforcement TS 397/1065 978 Doc D.2/467 1 GENERAL Read this Section with G01-010 "General Requirements" and all other contract documents. 1.1 Scope This Section covers general requirements for bars and welded fabric reinforcements used in reinforced concrete elements. 1.2 Related Sections Read this Section in conjunction with the relevant requirements of the following sections: C03-010 Concrete Construction Generally C03-060 Precast Concrete Works C03-070 Prestressed Concrete Works C03-080 Concrete Repair C05-010 Structural Steelwork C05-020 Protective Works for Structural Steelwork 1.3 Standards, Codes, Regulations and Technical References 1.3.1 Not In Use S1.3.1 Standards and Codes Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant requirements of the standards and codes listed below or referenced in the body of the Specification. Alternative standards and codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative standards and codes comply with the requirements of the standards specified. All standards and codes quoted are the current version, unless specific year references are noted. In the event that the standards or codes are partially superseded or have become obsolete, refer to the current edition or the approved substitution for the relevant clauses. Singapore Standards SS EN1992-11 Eurocode 2: Design of concrete structures, Part 1-1 General rules and rules for buildings SS EN1992-2 Eurocode 2: Design of concrete structures – Part 2: concrete bridges – Design and detailing rules SS EN13670 Execution of concrete structures SS ISO Steels for the reinforcement of concrete.Reinforcement couplers for mechanical splices of bars – 15835-1 Part 1: Requirements SS ISO Steels for the reinforcement of concrete. Reinforcement couplers for mechanical splices of bars – 15835-2 Part 2: Test methods TS 398/1065 978 Doc D.2/468 SS ISO Steels for the reinforcement of concrete. Reinforcement couplers for mechanical splices of bars – 15835-3 Part 3: Conformity assessment scheme SS 560 Specification for steel for the reinforcement of concrete – Weldable reinforcing steel – Bar, coil and decoiled product SS 561 Specification for steel fabric for the reinforcement of concrete SS CP83 Construction computer-aided design (CAD) SS 566 Specification for steel for the reinforcement of concrete - Plain bars Other Standards BS EN Steel for the reinforcement of concrete – Weldable reinforcing steel - General 10080 BS EN Steel for the reinforcement and prestressing of concrete. Test methods. Part 1: Reinforcing bars, ISO15630- rods and wire 1 BS EN Steel for the reinforcement and prestressing of concrete. Test methods.Part 2:Welded fabric and ISO15630- lattice girders 2 BS EN Fibres for concrete – Part 1: Steel fibres – Definitions, specifications and conformity 14889-1 BS EN Fibres for concrete – Part 2: Polymer fibres – Definitions, specifications and conformity 14889-2 BS EN Welding – Welding of reinforcing steel – Part 1: Load bearing welded joints ISO 17660-1 BS EN Welding. Welding of reinforcing steel. Non load-bearing welded joints ISO 17660-2 BS EN Specification and qualification of welding procedures for metallic materials. Welding ISO 15614 procedure test. Arc and gas welding of steels and arc welding of nickel and nickel alloys BS EN Qualification testing of welders. Fusion welding. Steels ISO 96061 BS 1011 EN Welding. Recommendation for welding of metallic materials. Part 1 General guidance for arc welding Part 3 - Arc welding of stainless steels BS 4449 Steel for the reinforcement of concrete – Weldable reinforcing steel – Bar, coil and decoiled product – Specification BS 4483 Steel fabric for the reinforcement of concrete – Specification BS 6744 Stainless steel bars – Reinforcement of concrete – Requirements and test methods BS 7973 Spacers and chairs for steel reinforcement and their specification Part 1:2001: Product performance requirements Part 2:2001 Fixing and application of spacers and chairs and tying of reinforcement BS 8666 Scheduling, dimensioning, bending and cutting of steel reinforcement for concrete – Specification BS ISO Epoxy-coated steel for the reinforcement of concrete 14654 PD 6687 Background paper to the UK National Annexes to BS EN 1992-1 ISO 1460 Metallic coatings — Hot dip galvanized coatings on ferrous materials — Gravimetric determination of the mass per unit area ISO 1461 Hot dip galvanized coatings on fabricated iron and steel articles — Specifications and test methods TS 399/1065 978 Doc D.2/469 1.3.2 1.3.3 Regulations (a) Workplace Safety and Health (Construction) Regulations 2007 (b) Approved Documents issued under the Building Control Act Technical References Refer to the following technical reference for guidance in carrying out the Works: (a) BCA/IES/ACES Guide book for Site Supervision Plan (2019) (b) MOM, Circular on Collapse of Reinforcement Cage for Thick Concrete Slab (01 September 2015) (c) CIRIA Report Number 92 Reinforcement Connector and Anchorage Methods (d) CIRIA C568 (2001) Specifying, detailing and achieving cover to reinforcement. (e) Concrete Society Technical Report No. 51 Guidance on the use of stainless steel reinforcement 1.4 Trade Preamble 1.4.1 Reinforcement Drawings Produce detailed reinforcement drawings based on reinforcement schedules shown in the drawings. Submit the detailed reinforcement drawings which shall include information on structural elements, location and references, to the SO for acceptance prior to construction. Engage qualified, competent and experienced personnel to prepare the detailed reinforcement drawings for submission to the SO for acceptance prior to construction. 1.4.2 Workshop Drawings and Bar Schedules In cases where reinforcement or bar schedules are required, engage qualified, competent and experienced personnel to prepare workshop drawings and bar schedules prior to construction. 1.5 Definitions and Abbreviations 1.5.1 Definitions TS 400/1065 978 Doc D.2/470 1.5.1.1 anchorage Length required for development of design stress in rebars, obtained by providing the required development length or hook/bends if sufficient length cannot be achieved. 1.5.1.2 bar chair Used to support and provide the cover for the top reinforcement steel, as joint linking single or multi- layer reinforced steel bars and welded fabric reinforcement, used concurrently with concrete spacers 1.5.1.3 concrete cover The least distance between the surface of embedded reinforcement and the outer surface of the concrete 1.5.1.4 coupler Coupling sleeve or threaded coupler for mechanical splicing of reinforcing bars for the purpose of providing a transfer of axial tension and/or compression from one bar to the other where: - a coupling sleeve is a device fitting over the ends of 2 reinforcing bars - a threaded coupler is a threaded device for joining reinforcing bars with matching threads. 1.5.1.5 lapping Method of creating a single structural entity from 2 rebar segments by overlapping 2 lengths of a rebar, then wiring them together to maintain the required continuity of stress in the splice zone. 1.5.1.6 mechanical splice Complete assembly of a coupler, including any additional intervening material or other components providing a splice of 2 reinforcing bars 1.5.1.7 reinforcing steel Steel product with a circular or practically circular cross-section which is suitable for the reinforcement of concrete. 1.5.1.8 starter bar Rebar cast into the concrete to give a lapped/mechanical splice connection to provide continuity of reinforcement across a cold joint or construction joint. TS 401/1065 978 Doc D.2/471 1.5.1.9 test unit For testing purposes, a batch is divided into test units with a maximum mass of 100 t. Each test unit comprises products of the same steel grade and nominal diameter from same cast. The manufacturer certifies that all products in the test unit originate from same cast. 1.5.1.10 welding Process of joining 2 pieces of metal together by heating to a suitable temperature with or without the application of pressure, and with or without the use of a filler material. 1.5.1.11 welded fabric reinforcement Arrangement of longitudinal and transverse bars, rods or wires of the same or different nominal diameter and length that are arranged substantially at right angles to each other and factory electrical resistance welded together by automatic machines at all points of intersection 1.5.2 Abbreviations No item. 2 PERFORMANCE REQUIREMENTS 2.1 Material Verification 2.1.1 Not In Use S2.1.1 Reinforcement Reinforcement shall in general comply with SS CP 83, SS 560 and SS 561. Check the following and verify that the reinforcements are in compliance with approved drawings and accordance to specified standards: 2.1.2 (a) Source of reinforcement (b) Mill certificate (c) Factory production control (FPC) certificate from an accredited certification body Couplers Performance requirements of couplers for the intended purpose shall be in compliance with CIRIA Report Number 92 on Reinforcement Connector and Anchorage Methods. In addition, materials testing shall be carried out as tabulated in C03-020:Clause:2.2. TS 402/1065 978 Doc D.2/472 2.2 Reinforcement Detailing Reinforcement shall be scheduled and detailed in accordance with SS EN 1992-1-1 and BS 8666, taking into consideration as a minimum on the following: (a) Bar bending - minimum scheduling radii and bend allowances. (b) Anchorage and lap length. All reinforcement shall be anchored so that the forces are safely and effectively transmitted to the surrounding concrete by bond without causing cracking or spalling. (c) Arrangement of laps and lapped bars. (d) Reinforcement spacing. (e) Minimum and maximum reinforcement areas. 3 MATERIALS 3.1 Reinforcing Bars Only reinforcement bars complying with SS 560 and SS EN 1992-1-1 shall be used. 3.2 Galvanised Reinforcement Comply with ISO 1461 after cutting and bending. Thickness of galvanised coating shall be in accordance with ISO 1461. [Note 1: Former practice uses SS 117 which has been withdrawn.] 3.3 Stainless Steel Bar Reinforcement Comply with BS 6744 unless otherwise specified or indicated in drawings or agreed by the SO. [Note 1: Refer to BS 6744 on the guidance on the choice of stainless steel for a given application.] 3.4 Not In Use TS 403/1065 978 Doc D.2/473 S3.4 Epoxy Coated Bar Reinforcement Comply with BS ISO 14654, bond classification type 1 or 2 as indicated in the drawings. Handle and fix to avoid damage to the coating, and avoid exposing the underlying steel. Note: Implicit in this specification is the assumption that conventional steel reinforcement will be used. In special circumstances (e.g. in particularly severe exposure conditions) the use of alternative materials might be considered and this would need to be referred to in the Project Specification. These include epoxy coated, galvanised and stainless steel reinforcement and non-ferrous reinforcement (i.e. fibre reinforced plastics). Where use of these alternative reinforcement materials is considered, specialist advice is available if required (e.g. Concrete Society Technical Report No. 51 Guidance on the use of stainless steel reinforcement). The following references may be found helpful as reference for Epoxy coated Reinforcement, Hot dip galvanising, PVC coating: a. Comite Euro-International du Beton (CEB), Coating protection for reinforcement, State of the art report 1995, Thomas Telford. b. Non-ferrous reinforcement: Interim guidance on the design of reinforced concrete structures using fibre composite reinforcement, Inst. Struct. Engineers August 1999. 3.5 Welded Fabric Reinforcement Comply with the requirements of SS EN 1992-1-1 and SS 561. 3.6 Not In Use S3.6 Fibre Reinforcement Comply with BS EN 14889 and to be of type and dosage as included in C3-20-PSD. 3.7 Proprietary reinforcement systems Proprietary reinforcement systems shall comply with the requirements of SS EN 1992-1-1 and SS 560. Carry out installation in strict accordance with the manufacturer’s recommendations, subject to acceptance by the SO. 3.8 Reinforcement Cage Ensure that the fabrication and erection of reinforcement cages are in accordance with the drawings, and provide safe design and proper construction of the reinforcement cage to ensure its stability during lifting, prior to and during concreting. Temporary lifting design shall be submitted for SOs review and acceptance. TS 404/1065 978 Doc D.2/474 3.9 Reinforcement Material All materials and equipment used in reinforcement cage fabrication shall be fit for the intended purpose and meet design specifications. Materials and equipment shall be designed to conform to relevant Singapore Standards. Where any material is designed to an international or other standard, an engineer must certify that it conforms to the relevant Singapore Standard and the use of the material is subject to acceptance of the SO. Materials and equipment must also be manufactured in accordance with a quality assurance system that ensures compliance with the design specification. 3.10 Not In Use S3.10 Couplers Steel reinforcement couplers for mechanical splices of bars shall comply with requirements of SS ISO 15835-1 and SS ISO 15835-3. Only straight metric threaded and swaged couplers shall be used. Unless otherwise approved by the SO, tapered systems are not acceptable for use. The couplers shall be of a type which is simple to install and can be verified to be installed correctly by visual inspection. The manufacturer of the couplers shall be certified to ISO 9001 quality assurance, or equivalent, for the manufacture of couplers. The Supplier/ Installer shall be certified to ISO 9001 quality assurance, or equivalent, for rebar end processing and for coupler installation. Carry out installation in strict accordance with the manufacturer’s recommendation, subject to acceptance by the SO. All couplers shall be legibly and durably marked with identification of the manufacturer, nominal bar size intended for and clear stamp of the batch or heat number. The batch or heat number shall be traceable to the original cast. The relevant material mill certificates for couplers shall be submitted with each delivery. The certificates shall show the salient material properties of the couplers. Note: Prepare reinforcing bars adequately to receive couplers. Where threaded couplers are used ensure the threaded ends are not damaged and that an adequate length of bar is contained within the coupler. 3.11 Not In Use TS 405/1065 978 Doc D.2/475 S3.11 Spacers Detail, supply and fix all spacers in accordance to the requirements of BS 7973. Obtain SO’s acceptance for spacers where the concrete will be exposed subsequently. Mortar spacers shall have durability and strength characteristics not less than the surrounding concrete. Note: Steel spacers within the cover zone may cause corrosion problems subsequently. Particular care is needed for formed finishes that will be exposed in the completed structure. Refer also to CIRIA C568 Specifying, detailing and achieving cover to reinforcement, 2001. 4 WORKMANSHIP 4.1 Conditions of Rebars Rebars shall not be surrounded by concrete unless free from mud, oil, paint, retarders, loose rust, loose mills scale, grease or any other deleterious substance which can be shown to affect adversely the steel or concrete chemically or reduce the bond. Light surface rust is acceptable unless detrimental to the finished structure by causing rust staining to adjacent exposed concrete or formwork. 4.2 Storage and Handling All reinforcement shall be delivered in properly identifiable tagged bundles, mats or prefabricated assemblies. Store reinforcement clear of the ground, and protect from mud, oil and other substances that may adversely affect its use in the works. Deliver and store steel fabric horizontally. Reinforcement shall not be dropped from height, mechanically damaged or shock loaded in any way. 4.3 Not In Use TS 406/1065 978 Doc D.2/476 S4.3 Cutting, Bending and Fixing Scheduling, dimensioning, bending and cutting of steel reinforcement for concrete shall be in accordance with BS 8666 and Clause 6.3 SS EN 13670. The contractor shall allow for temporary safe supports of all reinforcement during fixing, especially for deep structural elements/sections such as the pilecaps and rafts. Calculations and details of temporary supports for the reinforcement of any deep structural elements shall be designed by a professional engineer (PE) and submitted to the SO for record. The cost for the above shall be borne by the contractor. The contractor shall prepare appropriate bending schedule for the cutting and bending of reinforcement bars in accordance with the reinforcement drawings. Reinforcement should not be bent or straightened in a manner which will damage the material. Reinforcement fixing shall not commence until satisfactory testing of representative batches has been completed. Steel reinforcement shall be clean and free from pitting, paint, oil, grease, split concrete or grout, adhering earth or loose rust, etc. at the time of fixing and concreting. All laps of fabric and all intersections of bars shall be securely connected with malleable iron wire of suitable size or by an alternative method approved by the SO. 4.4 Not In Use S4.4 Tying of Reinforcement. Unless otherwise shown in the drawings or specified or directed by the SO, tie reinforcement with black annealed mild-steel 16-gauge tying wire. Tie stainless steel reinforcement using 16 swg annealed stainless steel wire. Bend all ends away from the concrete face and remove all loose ends before placing concrete. Note: The need to bend the ends of the tying wire away from the surface and remove all loose ends before placing concrete is of great importance in avoiding subsequent problems of corrosion and spalling. 4.5 Welding of Reinforcement All work shall be carried out by properly qualified welders using approved procedures. Permitted only with the prior written approval of the SO. Where permitted, carry out in accordance with BS EN ISO 17660-1, BS EN ISO 15614 and BS EN 1011. 4.5.1 Welding Procedures All work is to be carried out by welders properly qualified to BS EN ISO 9606-1 and using approved procedures. 4.5.2 Welding of Galvanized Reinforcement Unless otherwise agreed by the SO, welding of galvanised reinforcement is not permitted. TS 407/1065 978 Doc D.2/477 4.5.3 Welded Lap Joints Welding joints in parallel bars of the principal tensile reinforcement shall be staggered. Welding shall be avoided on joints where imposed loads is predominantly cyclical; and at bends. 4.6 Not In Use S4.6 Laps and Splices No splices shall be made in the rebar except where shown on the drawings or where accepted by the SO. In such splices, the rebar shall be placed in contact and wired. Splices in adjacent bars shall be staggered. Laps shall be in accordance to SS EN 1992-1-1 Clause 8 and BS 8666 as appropriate. Lap reinforcement shall be as shown in the drawings unless otherwise agreed with the SO. 4.7 Chairs and Spacers Chairs and spacers shall be suitable for achieving the specified cover to the reinforcement. Concrete and cementitious spacers shall have at least the same strength and the same corrosion protection as the concrete in the structure. 4.8 Not In Use S4.8 Deviation in Concrete Cover and Lap lengths Rebars shall be secured against displacement outside the specified limits in accordance with SS EN 1992-11, Clause 4.4.1.3. Deviation in concrete cover and lap lengths also shall comply with the requirements specified in SS EN 13670. Before concreting, check thoroughly that the specified cover dimensions have been complied. Note: Allow for additional cover where surface treatment will reduce the as-cast value 4.9 Couplers Requirement All couplers shall be free from rust or foreign material on the inside surface. Types of couplers used shall be simple to install and the correctness of installation shall be verified by quick visual inspection and to have achieved a connection providing the required full strength of the parent bars. The required torque/swag shall be established and verified on site and submitted for approval by the SO. Couplers shall be internally greased and covered with plastic caps to a protection detail acceptable to the SO. 4.10 Not In Use TS 408/1065 978 Doc D.2/478 S4.10 Cages for Precast Units Make up cages and fix securely in accordance with the reinforcement drawings to provide adequate rigidity and to ensure that the specified cover and fit within the moulds are achieved. Reinforcement not exceeding 12 mm in diameter which projects from the face of the units may be bent to facilitate the casting or demoulding of the unit subject to approval by the SO for each case. Bending shall be in accordance with BS 8666 and Clause 6.3 BS EN 13670. 4.11 Exposed Reinforcement In the event that reinforcement is expected to be exposed for a prolonged period over 3 months or such that loose rust and scale form, apply a corrosion protection coating for the SOs acceptance. Ensure the coating is compatible with the concrete and does not reduce the bond of the reinforcement. 4.12 Anchorages Protect all steel parts from corrosion and keep all threaded parts protected until used. Keep all devices free from any coating or contamination. Anchorages, including buried dead anchorages, shall be fixed with due regard to cover requirements for corrosion resistance and fire protection. 4.13 Inspection and Supervision Proper inspection and supervision procedures for reinforcement cage fabrication shall be established and agreed upon by the SO, and complied with in all phases. A proper and timely inspection and supervision regime shall be in place to ensure that all design requirements laid down in the specifications and structural drawings are complied with in construction; and to check that the completed portions of the structure are in compliance with the Specification. Reject the use of materials that do not conform to the Specification requirements and are not in accordance with the drawings or have resulted from improper construction. Material testing, including chemical test, tensile test, shear test, bend and rebend test, shall be conducted by an accredited laboratory that has appropriate and relevant accreditation for the tests. Inspection and supervision of reinforcement works shall be extended to the selection of samples for testing, to perform intermittent or spot checks and to check test results. S4.14 Ground Bearing Slabs Where these are reinforced with a single layer of fabric in the upper part of the slab, the fabric may be placed in position on top of the first compacted layer of concrete, followed by the top layer of concrete, placed within 30 minutes of the first layer. Note: It is important to ensure that the reinforcement ends up in the intended position; the strategy suggested here, provided the top layer is placed within the specified timescale, should prevent the mesh being trodden down into the slab depth. TS 409/1065 978 Doc D.2/479 S4.15 Surface Condition At the time of placing concrete, ensure the reinforcement is clean, free of corrosive pitting, loose rust and mill scale and other substances that may adversely affect the bond with concrete. Light surface rust is acceptable unless detrimental to the finished structure by causing rust staining to adjacent exposed concrete or formwork. Note: Light surface rust is often thought of as beneficial in terms of bond, and is readily distinguishable from the loose scale and rust which reduce the performance. S4.16 Safe Access for Steel Fixing & Inspection The Contractor shall include details of his proposed access to, and working platforms at, steel fixing work faces where the height of the platform exceeds 2m above the general level. 5 VERIFICATION AND SUBMISSION 5.1 Not In Use S5.1 Information for Execution Prior to putting the reinforcement on site, provide mill certificate to confirm that each batch of steel and mesh supplied to the site complies with BS EN 10080, SS 560, SS 561 or SS 566 as appropriate. Include information such as country of origin and the name of supplier for review. Following is a summary of the information that shall be included into the execution specification and method statement to be submitted for the SO’s acceptance: (a) Types of reinforcement (b) Permitted types of anchorages or couplers (c) Cutting and bending schedules or identify that this is a task for the contractor (d) Mandrel diameter for bending bars (e) Mandrel diameter for welded reinforcement and fabric bent after welding (f) Any requirements to straighten bent bars (g) Provisions for welding of reinforcement (h) Specifying if spot-welding is not permitted (i) Position of reinforcement, including cover, the position of laps and joints (j) Special requirements, if any TS 410/1065 978 Doc D.2/480 (k) 5.2 Nominal concrete cover Method Statement Prior to procuring any material and execution of the Works, submit and seek acceptance of the SO on procedure of fabrication, means of access (at height), lifting design and temporary stability proposal, and including on method statements and proposals as follows, where applicable: 5.3 (a) Provision of scaffolding access (b) Provision of access openings for thick slab reinforcement fabrication (c) Equipment and lifting plans (d) Method of temporarily securing/ supporting of reinforcement cage (e) Training and documented instructions (f) Equipment for fabrication, lifting, and installation (g) Methodology - erection and fabrication (h) Provision for fall prevention / protection (i) Storage and maintenance of components Material Testing Unless otherwise agreed and approved by the SO, Table 1 gives the test type, method, frequency and conformity criteria for material testing: Table 1. Material testing Material Type Steel Reinforcement Type of Test Tensile No. of Samples per Test Test Method Acceptance Criteria Testing Frequency BS EN ISO 15630-1 SS 560 Under 20 mm 1 sampling set at beginning of project and at every 100t or part thereof 3 pieces per size SS 560 Clause 8.2.3.1 20 mm to 40mm 1 sampling set at beginning of project and at every 500t or part thereof 1 piece per size SS 560 Clause 8.2.3.2 Bend & Rebend Conformity Criteria Remark Mill certificate and FPC certificates for each batch to be kept at site for each Batch delivered TS 411/1065 978 Doc D.2/481 Bond Over 40mm 1 sampling set at beginning of project and at every 1000t or part thereof 1 piece per size SS 560 Clause 8.2.3.3 Chemical 1 sampling set at beginning of project and at every 3000t or part thereof 1 cast analysis for Chemical Composition Analysis SS 560 Clause 7.1 15 pieces per fabric size (1 sheet 1mx1m per fabric size) . Mill certificate and FPC certificates for each batch to be kept at site for each batch delivered Grade 500B > 540 N/mm² Coupler specification for each type/brand to be kept at site and endorsed by qualified, competent and experienced PE. Tensile test Welded Steel Fabric Reinforcement Couplers for Mechanical Static Tensile Splices of Steel Reinforcement (Category B) BS EN ISO156302 SS 561 1 test unit at beginning of project and at every 25t ISO 15835-2 SS ISO 15835-1, 2 sample 1 test per sets per sample set coupler type & size at beginning of project and at every subsequent 200 couplers SS ISO 15835-3 Permanent/ Elongation Slip Grade 600B > 648 N/mm² SS ISO 15835-1 Clause 5.4.2 . SS ISO 15835-1 Clause 5.3.3 . SS ISO 15835-1 Clause 5.5.2 . SS ISO 15835-1 Clause 5.6 . (Up to 60% Fyk) Ductility Couplers for Mechanical Splices of Steel Reinforcement(Category F) high-cycle fatigue loading test (Optional) Couplers for Mechanical Splices of Steel Reinforcement(Category S) low-cycle loading test (Optional) 1 test set per coupler type/brand & size 1 control bar per sample set TS 412/1065 978 Doc D.2/482 5.4 Safe Work Procedure A Safe Work Procedure (SWP) for the fabrication and installation of reinforcement cage shall be prepared by a suitably qualified, experienced and competent PE, and submitted to the SO for acceptance. The SWP shall include: 5.5 (a) identifying the work that is high risk construction work (b) stating hazards relating to the high-risk construction work and risks to health and safety associated with those hazards (c) describing the measures to be implemented to control the risks (d) describing how the control measures to be implemented, monitored and reviewed. Risk Management Submit to the SO, the risk management and assessment study in identifying, evaluating and controlling risks on hazards associated with work involving the fabrication, installation, and lifting of reinforcement cage. TS 413/1065 978 Doc D.2/483 (13) C03-030 Formwork and Falsework TS 414/1065 978 Doc D.2/484 1 GENERAL Read this Section with G01-010 "General Requirements" and all other contract documents. 1.1 Scope This Section covers the requirements for the design, erection, use, alteration and dismantling of the formwork and falsework structure for reinforced concrete structures. 1.2 Related Sections Read this Section in conjunction with the relevant requirements of the following section: C03-010 1.3 Standards, Codes, Regulations and Technical References 1.3.1 Not In Use S1.3.1 Standards and Codes Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant requirements of the standards and codes listed below or referenced in the body of the Specification. Alternative standards and codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative standards and codes comply with the requirements of the standards specified. All standards and codes quoted are the current version, unless specific year references are noted. In the event that the standards or codes are partially superseded or have become obsolete, refer to the current edition or the approved substitution for the relevant clauses. Singapore Standards SS 280-1 Specification for metal scaffoldings – Part 1: Frame scaffoldings SS 280-2 Specification for metal scaffoldings – Part 2: Modular scaffoldings SS580 Code of Practice of Formwork Other Standards BS EN12812 Falsework – Performance requirements and General design BS5975 Code of Practice for temporary works procedures and the permissible stress design of falsework. CIRIA Report 136 Formwork Striking Times – criteria, prediction and methods of assessment Concrete Society Technical Report 52, 1999 Plain formed concrete finishes Concrete Society Publication, 2nd Edition 1995 Formwork: a guide to good practice TS 415/1065 978 Doc D.2/485 1.3.2 Regulations (a) Workplace Safety and Health Act 2011 (WSH Act) (b) Workplace Safety and Health (Risk Management) Regulations (c) Safety Requirements for Formwork Structures, MOM (d) Workplace Safety and Health (Construction) Regulations 2007 (e) Workplace Safety and Health (Scaffolds) Regulations 1.4 Trade Preamble 1.4.1 Contractor’s Submissions and Proposals Engage qualified, competent and experienced personnel to: 1.4.2 (a) carry out design and supervision of the formworks and falsework supports in accordance with statutory requirements and all relevant regulations. (b) design shall be endorsed by a Professional Engineer and submit to MOM when required statutorily. Qualifications of Supervising Personnel A formwork and falsework supervisor shall be suitably qualified, competent and experienced with theoretical and practical knowledge of formwork and false structures and received adequate safety and health training to familiarise himself with hazards associated with formwork and falsework structures of similar nature, type, size and purposes. Provide evidence of past relevant experience for all supervising personnel to the SO for acceptance prior to commencement of the Works. 1.4.3 Quality Control Plan Submit and work to a quality control plan as agreed with the SO. Refer to Section G01:010:Clause:1.4.7 for guidance. 1.5 Definitions and Abbreviations 1.5.1 Definitions TS 416/1065 978 Doc D.2/486 1.5.1.1 base plate A metal component to transfer the load of vertical member to the base; could be adjustable with a screw jack or other device. 1.5.1.2 brace Used to provide lateral stability. 1.5.1.3 falsework A temporary support system used to support a permanent structure formwork while it is not self supporting. 1.5.1.4 fore head A U-shape housing used to support the joist or the like. 1.5.1.5 formwork Part of temporary works used to give the required shape and support in-situ concrete. 1.5.1.6 formwork structure Integrated system of formwork and falseworks. 1.5.2 Abbreviations No item. 2 PERFORMANCE REQUIREMENTS 2.1 Control Measures for Safety and Structural Integrity Allow and provide for the integration of all control measures early in the design process to eliminate or, if not reasonably practicable, minimise risks to health and safety throughout the life of the structure being designed. All necessary measures to ensure structural integrity and safety shall be factored in and taken account of, at the concept development phase of a structure when making decisions about the following: (a) Design and its intended purpose (b) Possible methods of construction, maintenance, operation, demolition or dismantling and disposal (c) Materials to be used TS 417/1065 978 Doc D.2/487 (d) Legislation, codes of practice and standards need to be considered and complied with Refer also to SS 580 and WSH (Construction) Regulations. 2.2 Cambers Provide all information on cambers to the structural elements such as beams, slabs and cantilevers indicating the locations and pre-camber in terms of mm or % span in the formwork design and drawings. Measurements of camber shall be made after initial setting of concrete and before stripping of formwork. 2.3 Loads and Actions The formwork and falsework structure and system shall be endorsed by a PE and shall allow for all loads and actions expected to be applied during construction, including loads applied by the following: (a) The formwork and falsework deck, supporting members, and formwork and falsework frames. (b) Any false decks provided. (c) Concrete pouring techniques and method. (d) The concrete pour which includes both the weight of the concrete and dynamic factors applied. The concrete pour rate and pour sequence shall be specified. (e) Workers on the formwork deck and false decks. (f) Stacked materials. (g) Crane lifted materials on both the complete and incomplete formwork or false deck. (h) All formwork structures capable of sustaining the total dead load, live load and impact load imposed on the formwork and falsework structures in compliance with WSH Act and Regulations and SS EN Eurocodes and standards on safety and application of factors as appropriate. (i) Wind actions - all structures for formwork and falsework shall consider and include: (i) wind actions or loads on the formwork and falsework structure or system in accordance with SS Eurocodes, and shall be detailed as provided in SS 580 TS 418/1065 978 Doc D.2/488 (ii) providing an allowance for wind action or loading for vertical forms. [Note 1: Refer also to Building Control Act Approved Document on the relevant standards and codes on wind action. Note 2: Refer to Code of basic data for the design of buildings. Loading. Wind loads CP 3 Chapter V Part 2, using 33 m/s as the basic wind speed (3 second gust speed) Note 3: Refer to Loading for buildings. Code of practice for wind loads - BS 6399: Part 2, using 22 m/s as the basic wind speed (hourly mean speed).] 3 MATERIAL 3.1 General Only materials that have established properties and are in compliance with relevant Standards shall be used. 3.2 Formwork and Falsework Use Provide and construct formwork and falsework in order to contain and execute the concrete works, to give the required surface finish to the concrete finishes and to provide the stable and secure support throughout the period of the intended use. For proprietary formwork and falsework uses, comply strictly to the manufacturers requirement and recommendations and submit details for SOs acceptance. 3.3 Formwork and Falsework Material All materials and equipment used in formwork and falsework construction shall be fit for the intended purpose and meet design specifications. Materials and equipment shall conform to Singapore Standards or other relevant standards, as appropriate. Materials and equipment shall be manufactured in accordance with a quality assurance system that ensures compliance with the relevant accepted standards and design specification. Submit for the SOs acceptance certification from a PE and evidence that the materials and equipment conform to the relevant Singapore Standard. Refer to SS 580 and WSH (Construction) Regulations. 3.4 Testing and Inspection Provide a suitable system acceptable to the SO to ensure that only materials and components that comply with formwork and falsework drawings, standards and specification are used at all times. Do not use materials and components that are damaged, excessively worn or not fit for the intended use or purpose. Keep records on site. Provide all necessary testing to demonstrate that the materials and equipment have had their relevant properties suitable and fit for the intended use or purposes in cases where these are unobtainable from the standards. TS 419/1065 978 Doc D.2/489 3.5 Form lining All lining agents used shall be non-staining, on-structural material to suit the method of construction and finish required. 3.6 Formwork Ties Submit proposals for the SOs acceptance on the provision of formwork ties that are rods or bars within the permanent structure to retain the form robustly against movements during execution of the works and due to concrete and concreting works. In water-resisting construction, use ties of a type that does not induce seepage and reduce the waterresistance of the structure. 4 WORKMANSHIP 4.1 Conditions of formwork Provide and check that formwork is clean and free from debris and water before commencement of concreting works. 4.2 Joints All joints shall be sealed and be sufficiently tight to avoid leakage of grout. 4.3 Tolerance The finished concrete shall be within required tolerances as specified in SS 580 Table 4. 4.4 Block Outs and Cast-in Items Clear out block-out items after concreting works. Details and setting-out levels and positioning for any insert / cast-in items shall be checked and verified as indicated in the drawings. Resolve any clashes between built-in frame, holes, cast-in items and reinforcement before any concreting works. TS 420/1065 978 Doc D.2/490 4.5 Inspection and Supervision Provide and comply with the established inspection and supervision procedures for the execution class in accordance to SS EN 1992 on workmanship and reliability for concrete works, as agreed and accepted by the SO. The procedures shall provide for proper and timely inspection regime that is applicable and appropriate to the Works as laid down in the Specifications and in the drawings or as directed by the SO. Prior to any commencement of concreting works, provide all necessary checks, including endorsement by the PE who designs the formwork and falsework structure that the structure is erected in accordance with design and drawings. Submit to the SO, a certificate of supervision of the formwork and falsework works certifying that the formwork and falsework structure has been constructed and built in accordance to the approved drawing and is safe for the intended use or purpose. Refer also to C03-030:Clause:5.5 on managing risks and hazards. 4.5.1 Formwork and Falsework Supervisor Provide a formwork and falsework supervisor to undertake the inspection and supervision work - carrying out regular and periodic checks on all phases of the work in progress, as well as on the completed or partially completed portions of the structure, to assess their compliance to the specifications and the approved drawings. The formwork and falsework supervisor or site supervisor for the execution works shall have the authority to: 4.5.2 (a) refuse the use of materials which do not conform to the specifications, standards, approved drawings or as directed by the SO, and those materials which are likely to result in improper construction; (b) stop any work in progress which is not in accordance with the approved plans and specifications for the job. The supervisor shall have the power to order for the removal or repair of faulty construction or for any construction performed without an inspection. Alignment and Tolerances of Structure and Its Components. Provide a formwork and falsework structure or system that shall provide the dimensions, shape, and size of the hardened or finished form and appearance of the concrete works as specified or indicated in the drawings. Provide and execute the formwork and falsework structure or system such that the structure is built to correct dimensions and shape as specified or indicated in the drawings. The structure or system shall have adequate rigidity to maintain its shape and dimensional integrity under different types of construction loads; and shall be stable and robust in ensuring and maintaining accurate alignment of all members in position at all times. The formwork and falsework structure or system shall have its dimensions such as width, height and length of the formwork and falsework calculated precisely and to allow for workmanship and construction, so that the dimensions of the finished or as-installed members are within the acceptable limits of tolerance as specified or indicated in the drawings for the intended purpose and use. TS 421/1065 978 Doc D.2/491 4.6 Striking/Dismantling 4.6.1 Stripping Carry out the stripping operation in an orderly, progressive manner in accordance with the approved methods with the acceptance of the SO. Refer also to C03-030:Clause:5.4. Refer to SS 580 on the minimum period before striking of the form unless otherwise specified in the drawings or directed by the SO. [Note 1: Stripping formwork can be one of the most hazardous phases of concrete construction. While falling objects are the primary hazard, there may also be fall hazards as a result of floor collapse and manual tasks hazards from a person working in awkward postures, repetitive handling of materials and equipment. Refer to Formwork Code of Practice SS 580.] [Note 2: For minimum period before striking of form, refer to SS 580:2012 Table 5 as shown below. Type of formwork Minimum period before striking Vertical formwork to columns, walls and sides of large beams 1 day Soffit of slabs and beams <500mm thick 3 days Soffit of slabs < 500mm thick 3 days Soffit of beams 3 days Soffit of slabs =500mm thick Depends on concrete materials Soffit of cantilever beams and slabs 7 days Props to slabs and beams 14 days Props to cantilever beams and slabs 21days ] TS 422/1065 978 Doc D.2/492 4.6.2 Dismantling Dismantling of a formwork structure at a work site shall not commence until the concrete is set and the necessary approval from the SO is granted. The time to remove props or supports to concrete members in flexure shall be based on the attainment of the design characteristic strength of the concrete and the approval of the SO. Subject to the approval of the SO, shuttering shall not be detached until concrete properties are such that the concrete structure can be fully self-supporting and capable of carrying imposed loads and actions as intended. For the assessment of the in-situ strength of concrete, pull-out tests shall be performed or concrete cubes shall be tested. The concrete cubes for testing shall be cured under the same conditions as the in-situ concrete, achieved by temperature-matched curing by which cube samples are immersed in water whose temperature is matched to the structure. Subject to the acceptance by the SO, proprietary quick-strip systems can be used to allow the removal of soffit shuttering without disturbing the propping. Carry out striking with care to avoid damage to arisses and projections. Immediately, put in place necessary measures to protect some of the concrete works from damage after removal of the forms. Remove the formwork slowly so as not to induce or impose a shock load on the partly hardened concrete. [Note 1: In case of slabs and beams, soffit formwork may be removed when the in-situ strength of concrete is 10 N/mm2 or 2 times the stress to which it will be subjected, whichever is the greater. Note 2: When concreting in cold weather, the formwork to beam sides, walls and columns, if struck at early stages the concrete will still be "green concrete" and can be easily damaged. Note 3: If the formwork is not required elsewhere, leave it in place until the concrete has cooled from its high early temperature.] 5 VERIFICATION AND SUBMISSIONS 5.1 Method Statement Submit and seek approval of SO on the sequence of propping/re-propping and back propping, prior to procuring any material and execution of the Works: (a) Materials for falsework and formwork (b) Target age and strength of concrete at striking (c) Method of determining strength (d) Not In Use TS 423/1065 978 Doc D.2/493 5.2 S(d) Method to ensure that slabs/beams are not struck understrength/overloaded. (e) calculation of imposed loads on lower slabs System Forms Submit proposal in full details for SOs acceptance before the system forms are used. Details shall include the following information: (a) Material properties (b) Uses (c) Training and manufacturers recommendations and instructions (d) Design specifications and requirements (e) Concrete mix (f) Placing methods (g) Methods of forming openings (h) Methodology for erection and dismantling (i) Storage and maintenance of components (j) Provision for fall prevention/protection (k) Any other specific requirements Where jumpforming or slipforming and the like are proposed, details of system forms for submission to the SO shall include at least the following: (i) Materials to be used (ii) Proposed rate of slip (iii) Concrete mix (iv) Methods of checking strength during the pour (v) Methods of forming openings (vi) Details of cast-ins (vii) Methods of fixing reinforcement TS 424/1065 978 Doc D.2/494 5.3 (viii) Placing methods (ix) Procedures for stopping the slip (x) Protection (xi) Concrete repairs Submission on Erection and Dismantling for Approval and Permit Before commencement of the Works, submit and obtain all necessary approvals and permits from relevant authorities on the erection and dismantling of formwork and falsework structure and supports. 5.4 Safe Work Procedure for the stripping/dismantling operation A safe work procedure (SWP) for the stripping operation shall be prepared and provided to those who will be involved in this high-risk activity. The SWP shall see to the following: 5.4.1 (a) Identify the work that is high risk construction work. (b) State hazards relating to the high-risk construction work and risks to health and safety associated with those hazards. (c) Ensure materials dismantled from the formwork structure are removed promptly or stock-piled in areas where persons are not required to work or pass. (d) Ensure protruding nails, wire ties and other forms of accessories not necessary to subsequent work are pulled, cut or otherwise made safe. (e) Describe measures to be implemented to control the risks. (f) Describe how control measures are to be implemented, monitored and reviewed. Submission of SWP Submit for SOs acceptance the SWP as follows: (a) Number of persons in the stripping crew. (b) The sequence of stripping activities. (c) Details on how the frames and/or other supports to be removed, including how far U- heads are to be lowered. (d) Whether the support system shall be completely removed in a zone prior to removal of the formwork deck. TS 425/1065 978 Doc D.2/495 (e) When back-propping is required or only part of the support system shall be removed, how the structural members shall remain in place and/or the type and layout of members that shall replace the formwork system. (f) Any other special requirements involved in the stripping and/or building process, including the checking of back-propping after post-tensioning, etc., if applicable. 5.5 Risk Management 5.5.1 Hazards Undertake and submit for the acceptance by the SO, the risk management and assessment of hazards associated with work involving the erection, alteration and/or dismantling of formwork that shall include the following: 5.5.2 (a) Formwork and falsework collapse before, during and after placement of concrete. (b) Falls from heights. Refer to the Code of Practice on Managing the Risk of Falls at Workplaces published by MOM. (c) Slips and trips. (d) Falling objects. (e) Storage and handling of hazardous materials. (f) Movements of heavy vehicles and heavy objects involving crane forklifts, etc. (g) Other hazards identified or directed by the SO. Safe Work Procedure for high risk construction work Prepare and submit for the acceptance of the SO, safe work procedure for high risk construction work, or as directed by the SO before the work starts. Identify and submit for the SOs acceptance, a range of activities that are defined as high risk construction work, including work: (a) involving a risk of a person falling more than 3 metres or falling into depth; (b) involving demolition of an element of a structure that is loadbearing or otherwise related to the physical integrity of the structure; (c) involving structural alterations or repairs that require temporary support to prevent collapse; (d) carried out in or near a confined space; (e) carried out in or near a shaft or trench with an excavated depth greater than 1.5 metres; TS 426/1065 978 Doc D.2/496 (f) carried out on, in or adjacent to a road, railway or other traffic corridor that is in used by traffic other than pedestrians; (g) execution in SS 580. TS 427/1065 978 Doc D.2/497 (14) C03-040 Designed Joints TS 428/1065 978 Doc D.2/498 1 GENERAL Read this Section with G01-010 "General Requirements" and all other contract documents. 1.1 Scope This Section covers general requirements for designed settlement and expansion joints, and crack induced construction joints in concrete structures as in SS EN 1992. For general requirements of normal construction joints refer to Section C03-010 "Concrete Construction Generally". 1.2 Related Sections Read this Section in conjunction with the relevant requirements of the following sections: C03-010 Concrete Construction Generally C03-050 Water-resistance to Concrete Structures 1.3 Standards, Codes, Regulations and Technical References 1.3.1 Standards and Codes Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant requirements of the standards and codes listed below or referenced in the body of the Specification. Alternative standards and codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative standards and codes comply with the requirements of the standards specified. All standards and codes quoted are the current version, unless specific year references are noted. In the event that the standards or codes are partially superseded or have become obsolete, refer to the current edition or the approved substitution for the relevant clauses. Singapore Standards SS EN 1992 Design of Concrete Structures SS560 Specification for steel for the reinforcement of concrete Weldable reinforcing steel - Bar, coil and de-coiled product Other Standards 1.3.2 BSEN13670 Execution of Concrete Structures BS ENISO17660-1 Welding of reinforcing steel (load-bearing welded joints) BS ENISO17660-2 Welding of reinforcing steel (Non load-bearing welded joints) BS6093 Code of Practice for design of joints and jointing in building construction Guide Technical References Refer to the following technical references for guidance in carrying out the Works: TS 429/1065 978 Doc D.2/499 (a) CIRIA Report 146 Design and construction of joints in concrete structures (b) Concrete Society, Technical Report TR 34 Concrete Industrial Ground Floors - A guide to design and construction, 4th Edition (c) Not In Use S(c) ACI, Standard Joints in concrete construction: ACI 224.3R-95 (d) CIRIA Design for movement in buildings (2014) 1.4 Trade Preamble 1.4.1 Contractor’s Submissions and Proposals The type of designed joints and locations are indicated in the drawings. Engage qualified and experienced personnel to propose the following for SOs acceptance: 1.4.2 (a) Suitable joint materials, including joint fillers and waterproofing element, etc. to comply with the performance requirements as set out in clause 2.1 below (b) Details and construction method to install the joint materials as proposed Provision of Spare Material Deliver to the Site in robust protective packages marked for identification, and store where directed, additional joint materials for minor replacement or repairs in the near future, as specified or directed by the SO, which shall include the following: 1.4.3 (a) Joint filler (b) Joint sealant (c) Sealant backer rod Warranty Warrant all designed joints for a minimum period of 10 years, in accordance with contract conditions against all defects from the date of completion. [Note 1: This may be defined as a life to first maintenance. Ensure that there are no overriding requirements in the Client’s form of appointment. It is essential to be clear as to what the warranty is expected to cover. This will usually be the cost of repair/replacement of defective materials or workmanship, but not any consequential costs associated with the Works.] 1.4.4 Maintenance Manual Prepare and submit a maintenance/replacement manual covering the designed joints and materials for the project. Refer to the Section G01-010:Clause:1.4.5. TS 430/1065 978 Doc D.2/500 1.4.5 Quality Control Plan Submit and work to a quality control plan as agreed with the SO. Refer to Section Section G01010:Clause:1.4.7 for details. 2 PERFORMANCE REQUIREMENTS 2.1 Contractor’s Proposal When carrying out the proposals as set out in Section C03-040:Clause:1.4.1, take account of the design intent and matters that need consideration as recommended in BS 6093 and the following requirements in this Section, and provide manufacture data to confirm suitability. 2.1.1 Characteristics of the Joints Satisfy the required characteristics of the joints as detailed on the drawings in terms of joint designation, type of joint, horizontal and vertical movement, watertightness and fire-rating. [Note 1: For each type of joint and joint type designation, the characteristic requirements of the joint are typically as follows: (a) Movement: Vertical (b) Movement: Horizontal (c) Watertightness, where applicable (d) Fire rating Note 2: Joint Type: Examples include expansion joint, settlement joint etc. Note 3: Examples of specified values of characteristics requirements are 15 mm movement, one hour fire rating, etc.] 2.1.2 Durability Warrant that the joints shall have a design life of 10 years. [Note 1: The joints may be specified with a design life shorter than that of the building. Ensure the maintenance/replacement manual specifies and provides for the replacement of the joint materials upon the expiry of the specified design life.] 2.1.3 Proprietary Products When a proprietary product is specified, verify and submit evidence for SOs acceptance that the product satisfies the performance requirements as stated in this Section. In the event that the desired performance of the selected product cannot be verified, notify the SO and propose alternative product for acceptance. TS 431/1065 978 Doc D.2/501 3 MATERIALS 3.1 Movement Joint System and Fillers Propose suitable products for the SOs acceptance, giving details on the product information, type and model, performance requirements and product manufacturer. Refer to the properties of joint fillers and movement joints in BS 6093. Provide the proprietary product or approved equivalent for the movement joint system and filler as specified, scheduled or as indicated in the drawings. 3.2 Joint Waterproofing Material Propose suitable product to SOs acceptance, giving details on the product information, type and model, performance requirements and product manufacturer. Provide the proprietary product or approved equivalent for joint waterproofing materials as specified, scheduled or as indicated in the drawings for the following: 3.2.1 (a) Waterstops (b) Sealants (c) Gaskets (d) Baffles (e) Primer (f) Preformed sealing strips Water stops Refer to Section C03-050:Clause:3.5. 3.2.2 Sealants, Gaskets and Baffles For general requirement refer to Section C03-050:Clause:3.8. Refer to BS EN ISO 11600 on a systematic performance classification scheme for sealants that are used in building and construction applications. TS 432/1065 978 Doc D.2/502 3.2.3 Primer Apply primer on concrete surfaces to facilitate the application of sealant. Primer used shall be sealant manufacturer’s recommendation and compatible with the proposed sealant. [Note 1: Adhesion of sealants can be a problem, particularly in wet or damp conditions, and therefore good preparation of joint surfaces is essential. The use of primers is recommended.] 3.2.4 Preformed Compressible Sealing Strips For general requirements, refer to Section C03-050:Clause:3.8.3. 3.3 Dowel System 3.3.1 Sliding Dowel System Propose suitable product to the SO for acceptance, giving details on the product information and model, performance requirements and product manufacturer. Provide the proprietary product or approved equivalent for the sliding dowel system as specified, scheduled or as indicated in the drawings. 3.3.2 Tie Bars Tie bars shall be grade 250, and shall be clean and free from loose mill scale, loose rust, oil and other deleterious substances. 3.3.3 Mesh Tie Strips Mesh tie strips shall comply with SS 561, and shall be clean and free from loose mill scale, loose rust, oil and other deleterious substances. 3.3.4 Dowel Bars Dowel bars shall comply with SS 560, and shall be provided in straight, sawn (not sheared) ends. 3.3.5 De-bonding Propose a proprietary de-bonding compound or plastic sleeve for SOs acceptance. Apply to half of the dowel bars. 3.3.6 Cap Propose suitable product for SOs acceptance. Fit with not less than 20 mm of compressible material to the de-bonded end of the dowel. TS 433/1065 978 Doc D.2/503 3.4 Sheet Membrane for Sliding Joints Propose a suitable product to SOs acceptance, giving details on the product information and model, performance requirements and product manufacturer. Provide the proprietary product or approved equivalent for the sheet membrane for sliding joints as specified, scheduled or as indicated in the drawings. [Note 1: The requirements for the membrane are in terms of a high resistance to lateral deformation and a low coefficient of friction. Layers of heavy grade, or other similar polythene sheets have been used for this purpose.] 3.5 Crack inducers 3.5.1 Bottom of Slab Crack Inducer Propose a suitable product to SOs acceptance, giving details on the product information and model, performance requirements and product manufacturer. Provide the proprietary product or approved equivalent for the bottom of slab crack inducer as specified, scheduled or as indicated in the drawings. [Note 1: Examples include preservative-treated softwood or plastic, triangular section with 50 mm height or proprietary type. Specify these in thick slabs to reduce the depth of the insert or surface groove. Note 2: The Concrete Society Technical Report TR 34 does not recommend the use of bottom of slab crack inducers where crack inducing surface grooves are formed by cutting. There is a risk of misplaced cracking occurring when the surface cut groove is not properly aligned with the bottom inducer or when cutting is delayed for too long. The depth of the insert should be at least one quarter of the depth of the slab. Insert proprietary type, or provide for example: 3.5.2 (a) Plastics with detachable top section, to approval; 75 mm deep. (b) Stainless steel strip, 3 mm x 50 mm deep.] Inserted Crack Inducer Propose a suitable product to SOs acceptance, giving details on the product information and model, performance requirements and product manufacturer. Provide the proprietary product or approved equivalent for inserted cracker inducer as specified, scheduled or as indicated in the drawings. TS 434/1065 978 Doc D.2/504 3.5.3 Crack Inducing Grooves Refer to the drawings for the required dimensions of the crack inducing grooves, if any. [Note 1: Except at expansion and isolation joints, the movement at joints on a floor is generally very small and the usual rules for the dimensions of sealing grooves may be relaxed. This enables thin joints to be formed by sawing, and these fine joints are more durable under the passage of wheel loads. A sawn groove will be about 6 mm wide, but wider grooves can be cut if required. The depth of the grooves should be at least one quarter of the depth of the slab. Insert required depth and width for example: (a) Depth: 50 mm. (b) Width: as narrow as possible.] 4 WORKMANSHIP 4.1 Forming Joints 4.1.1 Accuracy Position and form joints accurately, straight, well-aligned and truly vertical or horizontal or parallel with setting out lines of the building. Construct the joint within an acceptable tolerance of 2 mm unless otherwise specified. 4.1.2 Pour Sequence Plan the pour sequence in such manner as to minimise restraints. Do not use a chequered board sequence for water-resisting construction. For elements cast monolithically that include wall and floor slabs, align joints as far as practically possible, to minimise cracking. [Note 1: Special considerations apply to ground slabs such as those used in warehouse construction, e.g. refer to The Concrete Society Technical Report TR 34 and the current edition of Deacon, RC’s Concrete ground floors: their design, construction and finish. Note 2: Where the casting of members is long in length, it can be helpful to leave short gaps to be infilled subsequently; for maximum effect, they should be left open for at least 3 months, but given the possible constraints this would impose, an alternative is to give more detailed consideration to where shrinkage is likely to occur and its effect on the structure, and take into account that about half the total shrinkage will occur within about 28 days.] 4.1.3 Modifications Modifications to any joint design or location, if necessary, shall be agreed on before proceeding. TS 435/1065 978 Doc D.2/505 4.1.4 Placing Concrete Prevent concrete entering joints or penetrating compressible joint fillers resulting in making movement joints ineffective. Do not place concrete simultaneously on both sides of movement joints. 4.2 Workmanship for Construction Joints Propose suitable joint location and detail for SOs acceptance. Take note of any desired location indicated in the drawings. Construction joints shall be formed wherever there is a discontinuity in placing concrete in elements of concrete structures. A water stop, which shall be either a hydrophilic expansion strip or a water bar embedded in the structure, shall be incorporated in all construction joints in elements which form the external hull of underground structures, retaining walls and where otherwise specified in the drawings. Spacing of construction joints shall be in accordance with good concreting practice and adequate precautions shall be taken against shrinkage cracking. Concreting shall be carried out continuously. The joints shall be at right angles to the general direction of the member and shall take due account of shear and other stresses. Concrete shall not be allowed to run to a featheredge and vertical joints shall be formed against a stop board. The top surface of a layer of concrete shall be level and reasonably flat unless design considerations make this undesirable. Joint lines shall be so arranged that they coincide with features of the finished work, wherever possible. If a kicker (i.e. a starter stub) is used, it shall be at least 70 mm high and carefully constructed. Prior to re-commencement of concreting on a joint, the surface of the concrete against which new concrete will be cast shall be free from laitance and shall be roughened. Take care to ensure that the joint surface is clean and thoroughly wetted immediately before the fresh concrete is placed against it. For general requirements refer to Section C03-050:Clause:4.14. [Note 1: Although construction joint positions can often be agreed upon orally for a simple and straightforward project, it is definitely desirable, if joints are not shown in the drawings, to agree on joint positions and have them recorded in advance. A marked-up print will suffice. In slabs and beams, it is a general rule to place construction joints in areas of low vertical shear and flexural stresses although where this is impossible, the joint must be detailed to provide shear resistance, e.g. a rebate should be formed in a wall to receive a slab that spans into it. In other cases, joints can be stepped or sloped.] TS 436/1065 978 Doc D.2/506 4.3 Workmanship for Expansion, Contraction and Other Movement Joints Expansion, contraction and other movement joints shall be incorporated in the Works as shown on the drawings or as directed by the SO. Polyethylene or similar material shall be used for expansion joint fillers and not fibre boards or bitumen impregnated material. Filler material shall be stored flat on a dry surface adequately protected from rain or moisture. Filler material that has been damaged or has started to deteriorate shall not be incorporated in the Works. The joint shall be sealed by an accepted sealer applied in strict accordance with the manufacturer's instructions to the dimensions shown on the drawings. The surface of the concrete to which the sealer is to adhere shall be straight and cleaned of all filler material, dirt, oil, grease and other matter. The sealer shall be applied by methods recommended by the manufacturer so that the sealer is brought flush to the surface of structure and a smooth surface is achieved. Excess material and spillage shall be properly cleaned off and removed. Dowel bars shall be installed and cast in across the movement joint where shown in the drawings. The bars shall be straight with clean cut ends of the diameters and lengths as shown in the drawings or in the schedules. The bars shall be firmly supported in the positions shown in the drawings so that they are not displaced during the casting of the concrete in the first part of the structure. After the concrete has hardened and the formwork removed, the projecting ends shall be cleaned of all concrete spillage and painted with 2 coats of an accepted bituminous paint and caps shall be fitted to the free ends of the bars. The projecting ends of dowel bars are required to be protected from bending or other damage prior to concreting the succeeding bay. The bituminous paint shall be applied as soon as practicable, but end caps shall not be fitted until immediately prior to the succeeding concreting operations. 4.4 Workmanship for Joint Waterproofing For general requirements, refer to Section C03-050:Clause:4.14. 4.4.1 Connection with Diaphragm wall All leaks in the diaphragm walls and connections shall be sealed. At the junctions with the base slab and roof slab, horizontal continuous runs of re-injectable grout tubes within the slab sections shall be installed on properly prepared surfaces to the satisfaction of the SO. After completion of the base slab and roof slab, regardless whether there is any leak, the junction with the base slab and roof slab shall be grout injected. 4.4.2 Sealants Apply in accordance manufacturer’s recommendation or as agreed by the SO. Avoid overspill onto the adjacent concrete surface. TS 437/1065 978 Doc D.2/507 4.5 Crack-inducing Grooves Insert temporary strips into the fully compacted concrete. Compact and level the slab along the strips. Remove strips. If the type of aggregate so permits, saw grooves in the top surface of the slab sufficiently early (within 24 hours of casting slab) to prevent random cracking. [Note 1: Narrow crack inducing grooves in floor slabs may not need to be sealed, e.g. in industrial premises where conditions are dry. However, in wet conditions, and where there are hygienic or dust control requirements, sealing will be necessary. The lower part of the groove may be filled with preformed foamed plastics strip to reduce sealing costs. The use of a "gun grade" material will be found more convenient with narrow grooves, as hot-poured sealants tend to overflow and spread across the adjacent floor surface. Two-stage compressible sealing strip systems are an alternative.] [Note 2: When construction takes place under a completed roof, grooves may be cut up to 7 days after casting. When construction is in the open in hot and sunny weather, the grooves must be cut within 24 hours. This Clause is based on the view that to reduce the possibility of random cracking, the grooves are best cut within 24 hours. In any case, there is little advantage in delaying the operation. Early sawing may be precluded by concrete mixes containing the following: 4.6 (a) Very hard aggregates, e.g. quartzite or flint (b) High proportions of cement replacement materials - ground granulated blast-furnace slag (GGBS) or pulverized fuel ash (PFA)] Bottom of Slab Crack Inducers Fix bottom of slab crack inducers securely to sub-base. 4.7 Inserted Strip Crack Inducers 4.7.1 Forming groove Fully compact and level the concrete, insert steel T bar and withdraw to form void. 4.7.2 Placing strip Carefully insert strip to accurate line and level, then re-compact and re-level slab. 4.8 Control of Jointing on Site Control of jointing on site is essential and is required to take account of critical factors, particularly where specifically identified or directed by the SO, including the following: (a) Joint clearances are maintained within specified limits; (b) Continuity of seals is maintained. TS 438/1065 978 Doc D.2/508 4.9 (c) Operations which are difficult (such as forming and sealing of cloaks and cavity trays) are correctly and properly executed. (d) The correct assembly sequence is followed. (e) Work to be hidden by subsequent work is inspected before being covered; (f) Features which are difficult and costly to rectify are checked. Preparation for Jointing The component surfaces shall be properly prepared to receive jointing materials. Contaminants, including dust, loose particles, moisture, oils and greases, and corrosive materials are required to be cleaned from the joint faces before application of primers and sealants. Rough surfaces shall be ground flat before installation of gaskets. Temporary protective coating meant for the delivery of components to site shall be properly removed before the application of the sealant or gasket. 4.10 Application and insertion of jointing products Follow the manufacturer’s recommendations on the application of products. The sequence of building operations shall be such that ready access by the operator to the joints is ensured and that interaction with other trades is avoided. 4.11 Safety in application of jointing products Refer to the manufacturer’s literature and recommendations on the use of products and the precautions to be taken in dealing with hazardous materials, including sealants and primers that contain flammable solvents or toxic constituents, which may cause dermatitis and nausea in certain individuals. In particular, care is needed in the safe disposal of hazardous waste and containers in accordance with statutory requirements. Assess risks arising from hazardous substances at work and determine the measures needed to prevent or adequately control exposure to them. Propose for the SOs acceptance all necessary measures to eliminate the hazardous substance by changing the process or substituting with a safe or safer substance. Where this is not reasonably practicable, propose for SOs acceptance, control measures of the exposure, including the use of enclosure, ventilation equipment, general ventilation, safe systems of work and handling procedures. Other measures shall include personal protective equipment to control exposure. 5 VERIFICATION AND SUBMISSIONS 5.1 Submission 5.1.1 Tender Submission Submit the following information with the tender: (a) Technical details, including catalogues of the joint system TS 439/1065 978 Doc D.2/509 5.1.2 (b) Certificates to show compliance with the codes set out in the specifications (c) Sample of typical joint materials (d) Records of past projects where the proposed joint system has been successfully installed Method Statement Provide a method statement for the acceptance of the SO prior to commencement of the Works containing at least the information given below: 5.1.2.1 Materials For each material or system proposed, manufacturersâ data, test results, design life certificates, health and safety information. 5.1.2.2 Sequence Proposed sequence for each of the operations required to complete the works. 5.1.2.3 Methods All tools and equipment to be used, application methods, proposed methods for undertaking the various elements of the Works, including details of access and indicating how any restrictions on noise and nuisance shall be met. 5.1.2.4 Site Organisation and Quality Control Provide details of how the Works shall be controlled, sampling regimes, proposed testing methods and organisation. 5.1.2.5 Project Reference Contractor shall submit the project references where the materials have been used previously with satisfactory performances. 5.1.3 Product Certificates For all materials proposed, submit certificates from manufacturers showing evidence of compliance with the specified quality requirements. 5.1.4 Maintenance / Replacement Manual Cover all joint systems and materials in the maintenance manual to be submitted before handing over. Propose and submit for the SOs acceptance on the details and requirements to be in the building maintenance manuals which shall provide as appropriate: TS 440/1065 978 Doc D.2/510 (a) An inspection frequency and schedule (b) An expected replacement schedule for jointing products (c) An identification of joints where lack of maintenance would lead to significant consequential damage (d) Guidance on how to maintain joints (including any special precautions needed to avoid inappropriate repairs) (e) Means to identify products or types of jointing products used [Note 1: Generally, joints may be inspected at intervals equivalent to 1/5 of life expectation and additionally, after the first year in service, all joints subject to movement should be inspected for signs of premature failure.] 5.1.5 Warranty Submit the warranty for SOs acceptance upon completion of the works. 5.2 Samples/Mock-ups Submit samples of all joint systems and materials for SOs acceptance prior to ordering of the material. Identify and label the samples appropriately. 5.3 Tests 5.3.1 Watertightness For joints specified as watertight, test all joints after installation with a spraying hose for water tightness. If there is any leakage, dampness and presence of seepage water, propose and carry out rectification or replacement to the SOs acceptance. 5.3.2 Fire Resistance For joints specified with fire rating requirements, submit certificate or evidence demonstrating compliance with SCDF requirements. If certificate is not available, submit samples of the materials to SCDF for testing to obtain the certification. TS 441/1065 978 Doc D.2/511 (15) C03-050 Water-resistance to Concrete Structures TS 442/1065 978 Doc D.2/512 1 GENERAL Read this Section with G01-010 "General Requirements" and all other contract documents. 1.1 Scope This Section covers primarily the requirements of waterproofing for below ground in-situ concrete structures to exclude water. It may be adapted to cover the concrete element of water retaining structures, e.g. tanks and swimming pools. For waterproofing applied as surface finish to such structures, refer to Architectural specifications. 1.2 Not In Use S1.2 Related Sections Read this Section in conjunction with the relevant requirements of the following section: C03-010 Concrete Construction Generally C03-040 Designed Joints 1.3 Standards, Codes, Regulations and Technical References 1.3.1 Standards and Codes Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant requirements of the standards and codes listed below or referenced in the body of the Specification. Alternative Standards and Codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative standards and codes comply with the requirements of the standards specified. All standards and codes quoted are the current version, unless specific year references are noted. In the event that the standards or codes are revised or superseded, refer to the current edition or the appropriate substitution for the relevant subjects. Singapore Standards SS EN 1992-1-1 Design of concrete structures - Part 1-1 General rules and rules for buildings SS EN 1992-3 Design of concrete structures - Part 3: Liquid retaining and containment structures SS EN 13791 Assessment of in-situ compressive strength in structures and precast concrete components SS EN 206 Concrete- Specification performance, production and conformity SS 544-1 Concrete - Complementary Singapore Standard to SS EN 206 Part 1: Method of specifying and guidance for the specifier SS 544-2 Concrete - Complementary Singapore Standard to SS EN 206 Part 2: Specification for constituent materials and concrete SS 637 Code of practice for waterproofing of reinforced concrete buildings TS 443/1065 978 Doc D.2/513 SS 374 Preformed waterproofing membranes for concealed roof Other Standards 1.3.2 BS EN 12390-8 Testing hardened concrete - Depth of penetration of water under pressure BSEN 13670 Execution of concrete structures BS EN 14188-3 Joint fillers and sealants - Specification for preformed joint seals BS EN ISO 527-1 Plastics. Determination of tensile properties - Part 1: General principles BS EN ISO 527-2 Plastics. Determination of tensile properties - Part 2: Test conditions for moulding and extrusion plastics BS ISO 16938 Buildings and civil engineering works - Determination of the staining of porous substrates by sealants used in joints. BS 1881-122 Testing concrete - Part 122: Method for determination of water absorption BS 6093 Design of joints and jointing in building construction - Guide BS 6213 Selection of construction sealants - Guide BS 8000-16 Workmanship on construction sites - Part 16: Code of practice for sealing joints in buildings using sealants BS 8102 Code of practice for protection of structures against water from the ground DIN EN ISO 2286 Rubber- or plastics-coated fabrics - Determination of roll characteristics - Part 3: Method for determination of thickness ISO 11600 Building construction - Jointing products - Classification and requirements for sealants ASTM D638 Standard test method for tensile properties of plastics ASTM D5385 Standard test method for hydrostatic pressure resistance of waterproofing membranes ASTM E96-00e1 Standard test methods for water vapour transmission of materials ASTM E154-99 Standard test methods for water vapour retarders used in contact with earth under concrete slabs, on walls, or as ground cover Technical References Refer to the following technical references for guidance in carrying out the Works: 1.4 (a) BCA publication, Good Industry Practices - Waterproofing for Internal Wet Areas (b) BCA publication, on Good Industry Practices - Waterproofing for External Wall (c) CIRIA Report 139 Water-resisting basements (d) CIRIA 766 Control of cracking caused by restrained deformation in concrete (e) CD 358 Waterproofing and surfacing of concrete deck (Appendix B: Procedures for certification of waterproofing systems on concrete bridge decks) Trade Preamble TS 444/1065 978 Doc D.2/514 1.4.1 Contractor’s Submissions and Proposals Engage qualified and experienced personnel to develop the design and propose for the SOs acceptance a complete waterproofing system to comply with the performance and quality requirements as set out in this specification. 1.4.2 Co-ordination with Other Works Co-ordinate all relevant interfacing work packages and trades as follows: 1.4.3 (a) Structural substrate works (b) Services work crossing or penetrating the waterproofing works Warranty Provide a warranty for a period of 10 years in accordance with contract conditions for the entire waterproofing system, including all components and accessories. The waterproofing warranty shall cover the water tightness of the underground structures for the waterproofing systems and shall be given jointly and severally by the Contractor, manufacturer, supplier and applicator. [Note 1: Some practices use a warranty period of 15 years. Note 2: The warranty must be specific for the task at hand and several warranties may be required depending on the nature of the protection and system required by the project.] 1.4.4 Maintenance Manual Prepare and submit for the SOs acceptance a maintenance/replacement manual for the waterproofing system, including the joint fillers, re-injectable grout tubes and sealants, to be carried out by the building owners. Refer to Section G01-010:Clause:1.4.5 for details. 1.4.5 Quality Control Plan Submit and work to a quality control plan as agreed with the SO. Refer to the Section G01010:Clause:1.4.7. 1.4.6 Specialist Personnel Propose for the SOs acceptance competent and suitably experienced waterproofing specialist personnel, including operatives and applicators, and material suppliers to meet the specified performance requirements of all aspects of the waterproofing works. The waterproofing works shall be executed by suitably experienced operatives or applicators who have met the skills criteria using the products on other similar works and under similar conditions. [Note 1: In some cases, the Work may be carried out as part of the general substructure concrete. There may be a specialist who will be responsible for the supply of the products which may be installed by others.] TS 445/1065 978 Doc D.2/515 2 PERFORMANCE REQUIREMENTS 2.1 Design Input Requirements Account for the following design input requirements when carrying out the proposals in Section C03050:Clause:1.4.1 and refer to the BCA publication "Good Industry Practices - Waterproofing for Internal Wet Areas". 2.1.1 Durability Unless otherwise agreed by the SO, the waterproofing system is required to achieve a minimum design working life of 10 years, the assumed period for which the waterproofing system is to be used for its intended purpose with anticipated maintenance but without major repair being necessary. [ Note 1: In some projects, a minimum design working life of 15 years is used for the waterproofing system.] [Note 2: The working life under this sub clause may be different from the concrete working life.] 2.1.2 Basement Grade Unless otherwise specified in the drawings or directed by the SO, use grades of internal environment, with regard to basement usage and performance level, as defined in BS 8102, taking into consideration of the functional environmental requirements, groundwater conditions, risk assessment and options for drainage outside the structure. Propose for the SOs acceptance on the grade of performance level required for the dryness of buildings as defined in BS 8102. [ Note 1: CIRIA 139 provides guidance on levels of dryness which relate to habitable use and archive storage.] [ Note 2: The performance level for the dryness of buildings may be quantified further as appropriate, for the selection and delivery of the appropriate basement environment and that it requires consideration of anticipated ground water levels, level of ventilation provided, the sub- slab drainage and external drainage generally, and a risk analysis and assessment. Note 3: For all grades, where reliance is being placed on the concrete to provide the water resistance to the structure, there is a need to place particular emphasis on achieving the correct mix design and ensuring high standards of workmanship.] 2.1.3 Material Performance 2.1.3.1 Material Quality Ensure that all materials comply with the relevant product standards as defined in this specification. TS 446/1065 978 Doc D.2/516 2.1.3.2 Hydrostatic Head Resistance All materials used for waterproofing the structure are to be capable of resisting the hydrostatic head associated with the relevant site conditions. 3 MATERIALS 3.1 Materials Compatibility Ensure that all materials used are compatible and comply with the manufacturer’s recommendations. 3.2 Damp-proof Membranes Suitable materials for damp-proof membranes include the following: (a) Heavy-duty polyethylene sheets (b) Bituminous sheets (c) Bituminous felt Minimum thickness of the damp-proof membranes to be used for different types of ground conditions shall be in accordance with SS 637. The sheeting shall be laid and jointed in accordance with the manufacturer’s written instructions, lapped 150 mm at joints and taped with a waterproof tape, laid over lean concrete. [Note 1: This is a standard requirement for conventional ground slab construction to stop ground water or vapour rising; it will not in itself be appropriate or effective in situations where there is a very high water table and the structure is, or is likely to be, subject to water pressure or ingress.] 3.3 Tanking Membranes Use preformed membranes or liquid-applied membranes. 3.3.1 Preformed Bonded Membranes 3.3.1.1 Suitable Materials Suitable materials for bonded membranes include the following: (a) Not In Use S(a) Flexible and self-adhesive bituminous-based membrane with a minimum thickness of 1.5 mm, based on high performance 250 micron thick polymer films. TS 447/1065 978 Doc D.2/517 (b) Flexible membrane capable of forming a full bond with concrete subsequently cast, with a minimum thickness of 1.5 mm. The membrane shall form a continuous and permanent mechanical bond to poured concrete to prevent lateral water migration between the membrane and structural concrete. Do not use bentonite-based membranes. [Note 1: Do not use bentonite-based membranes unless the intent is to provide a hydrophilic solution as of a multi-tiered protection system and subject to SOs approval.] Membranes shall be robust for the intended application and purpose without tearing or separating during the placement and application process. Membranes shall be tested prior to acceptance by test methods, acceptance parameters and rectification methods agreed to by the SO. 3.3.1.2 Physical Properties Required physical properties of bonded membranes are as follows in Table 1: Table 1. Physical properties of bonded membranes Performance parameter Thickness Typical value Test method 1.5mm min. DIN EN ISO2286-3 50m to 70m ASTM D5385 DIN16726 Water vapour transmission rate 0.06g/m²/day ASTM E96 Tensile strength (carrier film) Longitudinal 48.4 N/mm² Transverse 45.4 N/mm² SS 374 Puncture resistance 280N ASTM E154 Hydrostatic head resistance 3.3.2 Liquid-Applied Membranes 3.3.2.1 Components Provide a system comprising a primer and one or more layers of a two-component liquid-applied elastomeric membrane. [Note 1: Liquid applied waterproofing systems are fully bonded to the substrate and thus should resist water tracking under them if water penetrates. Dynamic crack accommodation is normally by elastic deformation of the membrane. However, some systems, less commonly used, are reinforced with glass fabric - these accommodate dynamic cracks by a combination of local debonding and elastic deformation. Reinforced membranes typically have a higher tensile strength but are less elastic than unreinforced systems.] TS 448/1065 978 Doc D.2/518 3.3.2.2 Properties Required properties of liquid-applied membranes are as follows in Table 2: Table 2. Properties of liquid applied membranes Performance Typical value Test method Total dry film thickness Minimum 2.5 mm . Tensile strength unaged 180 days heat aged at 70°C 28 days water soaked at 23°C 500 hr UV aged 8.6 10.6 9.1 8.8 BS EN ISO 527-1 and 527-2 Elongation to failure (%) unaged 180 days heat aged at 70°C 28 days water soaked at 23°C 500 hr UV aged 117 124 122 123 BS EN ISO 527-1 and 527-2 Refer to BS EN ISO 527 for determining the tensile properties of plastics and plastic composites under defined conditions. Refer to CD 358, Appendix B which gives a series of procedures for the certification of waterproofing systems for concrete bridge decks. 3.3.3 Primer For bitumen-based membranes, use a bituminous primer in accordance with the manufacturer’s recommendations. Concrete surface shall be prepared to U3 finish, prior to the application of a bituminous primer coat. 3.4 Waterproofing Admixtures (Hydrophobic & Hydrophilic) Where the required waterproofing performance is to be achieved by the use of concrete admixture systems, provide full details of the proposed admixtures and mixes to the supplier and the final design mix to the SO for agreement and approval. The waterproofing admixtures shall make the concrete impermeable to water and hydrophobic with pore-blocking content as its primary function. Provide at least 15 years of a successful track record of the products in the same manner used for the regional demarcation of waterproofing for concrete. The required characteristics are as follows in Table 3: Table 3. Required characteristics for admixtures Performance Typical value Test method Water absorption at 7 days Not more than 1% BS 1881: Part 122 Water permeability coefficient under 5.0kg/cm2 not greater than 10-13 m/s DIN 1048 Average penetration depth Pore-blocking content determination not greater than 15 mm >0.025% (by weight) BS EN 12390-8 ASTM D5368 (Method C) choose chloroform as extracted solvent. TS 449/1065 978 Doc D.2/519 3.5 Waterstops All waterstops shall be capable of providing hydrostatic resistance appropriate to the structure and joint in which installation is provided. 3.5.1 Active Waterstops Expansive hydrophilic waterstops shall have a volumetric increase of between 200% and 300% when in contact with water. Do not use bentonite-based hydrophilic waterstops unless with approval of the SO. Hydrophilic waterstops shall be provided with a delay coating that retards the onset of expansion to prevent premature expansion prior to concrete casting. The hydrophilic waterstops shall exhibit good consistency in measured swell rate during the repetitive wetting and drying cycle. 3.5.2 Passive Waterstops Use flexible rubber or PVC for passive waterstops. 3.6 Injection System Provide a complete applicator system, including hoses, junction boxes, resin, pumps and all other components required for its installation and use as provided by the manufacturer or as directed by the SO. The injectable tube system shall be suitable for resinous or cementitious grout. 3.6.1 Resin Use flexible aqua-reactive injection resin which is chemically resistant and produces an expanded closed-cell foam on contact with water. Provide details of the proposed product to the SO for agreement prior to starting work. 3.6.2 Hoses Hoses shall be tough, re-injectable, flexible and chemically inert, and capable of not being choked by the hardened grout from previous injection cycles. 3.6.3 Junction Boxes Junction boxes shall be installed in locations which are readily accessible. 3.6.4 As-built Manual Upon completion of the Works, submit a manual containing detailed instructions for grouting and flushing, material data, as-built record drawings showing location of all tubes and their respective junction boxes, and other information relevant to future maintenance. TS 450/1065 978 Doc D.2/520 3.7 Chemical/Cement Grout or Gel Use approved chemical grout, which shall form a continuous, uniform gel. Mix proportions shall be as recommended by the manufacturer. 3.8 Materials for Joints Unless otherwise agreed by the SO, the classification and requirements for sealing joints to meet anticipated movement in service shall follow ISO 11600. 3.8.1 Waterbar systems for Joints Joints are required to have adequate width to accommodate anticipated movements and to ensure the jointing waterbar performs within its required capabilities. The gap of the joints must be sealed for watertightness. Waterbars are used in conjunction with surface sealants and hydrophilic waterstops as a multi- tier system against liquid ingress under high static or dynamic pressures. [Note 1: Refer to BS 6213 for more details.] 3.8.1.1 Waterbar system for use within a wet environment Where there is permanent contact with water, waterbars are from approved polyurethane or polysulphide compounds. 3.8.1.2 Waterbars for use under traffic loads Use high modulii dynamic systems under traffic loading conditions. [Note 1: Refer to CD 358 on Waterproofing and surfacing of concrete bridge decks which gives a series of procedures for the certification of waterproofing systems for concrete bridge decks.] 3.8.2 Gaskets Use natural rubber compounds protected by a synthetic rubber skin. If special properties, such as resistance to oils, are desired, synthetic rubber and plastics materials have to be specifically formulated for the intended use. Gaskets can be solid or hollow sections of various profiles formed from cellular or non-cellular material or combinations of these materials or sections. 3.8.3 Sealing Strips Submit for the SOs acceptance on the types of sealing strips which are mastic strips and impregnated or coated cellular strips to be used. 3.8.4 Joint fillers Use joint fillers that meet the requirements of BS EN 14188. TS 451/1065 978 Doc D.2/521 3.8.5 Baffles Comply with BS 6093. 3.9 Waterproof Renders Where required, propose for the SOs acceptance proprietary products, organic or inorganic, which modify the permeability of the concrete for waterproof renders. [Note 1: These may be used in conjunction with âwaterproof concreteâ or structurally integral protection without any admixtures to improve the vapour resistance of the structure. It is not recommended for use as a primary form of waterproofing.] 3.10 Formwork Ties Propose for the SOs acceptance, a type of formwork ties capable of maintaining the water resistance of the structure. To prevent future water migration through tie form voids for the case of using removable tie form, cast in galvanised formwork ties that shall be approved by the SO for use with the external wall. The 2 ends of a tie shall be infilled with suitable non-shrink grout mixed with hydrophobic type waterproofing additive. 4 WORKMANSHIP 4.1 Construction Loads Ensure during construction that the structure is not subjected to loads that will cause distress to the concrete and the waterproofing system. 4.2 Storage Keep all materials clean and dry, avoid damage and use strictly in accordance with the manufacturer’s recommendations. 4.3 Protection Apply protection to materials in accordance with the accepted proposals given in the method statement. 4.4 Pour Sizes Control pour sizes to optimise work practice. Refer to Section C03-010:Clause:4.5.1. [Note 1: Pour size is independent of crack width or spacing if reinforcement is continuous. Refer to SS EN 1992-3.] [Note 2: Restrictions on pour size will depend, amongst other considerations, on the demonstrated ability and track record of the contractor and on a risk assessment for the structure; the consequences of water ingress can vary for different structures and requirements.] TS 452/1065 978 Doc D.2/522 4.5 Fixing Formwork Do not use methods of fixing formwork which result in holes through the concrete section when the formwork is removed. 4.6 Pipe Penetrations Use a puddle flange or other appropriate sealing detail. Avoid post-formed openings. [Note 1: It is much harder to ensure an effective seal around a post-fixed item.] 4.7 Temporary Propping Allow adequate area around any temporary penetrations to incorporate waterstops and to ensure full compaction of concrete. Submit in advance to the SO for his acceptance the details and method statements required for construction. 4.8 Inspection Carry out inspection jointly with the SO before backfilling or covering up to identify defects which may lead to water penetration. Perform further joint inspection to identify any water penetration after backfilling and when any groundwater has returned to normal level. 4.9 Repairs Where concrete shows signs of liquid penetration, through leakage or damp patches, submit proposals for rectification, including details of proposed materials and methods of application, to the SO that comply with BS 8102, Clause 8.8 and 8.9. Ensure that all repair materials are compatible with materials used in the original construction. [Note 1: Standard methods are injection of resin material, breaking out and recasting or internal rendering. In some instances, the latter may not be acceptable. It is necessary to consider the required finish and the specified performance in evaluating proposals, including the consideration of reestablishment of ground water level resulting in a greater possibility of leaks appearing.] 4.10 Waterstops Use waterstops in all construction and movement joints in concrete specified as water resistant unless otherwise noted and agreed with the SO. Obtain the agreement of the SO for the methods to be used to maintain the waterstops in position and to avoid damage during concreting and formwork removal. [Note 1: This is a reasonable starting point for specifying. It is important to be aware, however, that waterstops can themselves provide an entry route for water if they are not correctly fixed. With good workmanship, it is still necessary in construction joints. The need for movement joints in substructures should be assessed carefully - if not needed, their omission is advantageous in removing one possible entry point for water.] TS 453/1065 978 Doc D.2/523 4.10.1 Internal Waterstops or Waterbars Submit details to the SO for acceptance of the methods to be used to ensure full compaction around the waterstop or waterbar. [Note 1: The location of a waterstop or waterbar may itself provide a passage for water if the material is incorrectly fixed and/or the concrete does not form a continuous dense surround.] 4.10.2 Hydrophilic Waterstops Locate in a smooth groove formed in the kicker or at the edge of a slab. [Note 1: Hydrophilic waterstops are generally preferred in situations where there are permanently wet conditions.] 4.11 Bonded Membrane Systems 4.11.1 Finishes The finishes shall meet the membrane manufacturer’s requirements. In general, provide the following minimum conditions: 4.11.2 (a) Prepare slabs to receive a waterproof membrane to at least a "Plain Finish" as defined in BS EN 13670. (b) For vertical surfaces provide at an "ordinary finish" as defined in BS EN 13670 and where necessary, grind to remove arrases and fill locally with mortar using a steel trowel to produce a smooth finish. Application Lay primer and membrane strictly in accordance with manufacturer’s instructions, including instructions on length and location of laps. 4.11.3 Change in Concrete Surface Lay the material across a change in the plane of the concrete surface provided it is sufficiently pliable to enable the adhesive to remain in contact with the primed concrete. Where this cannot be achieved, provide preformed angles or other fixtures as required and bond to the concrete surface. 4.11.4 Protection Provide protection as soon as possible after laying by boards or other material with the agreement of the SO, in accordance with the membrane manufacturer’s recommendations. TS 454/1065 978 Doc D.2/524 4.11.5 Continuity Ensure that there is continuity of waterproofing at all junctions within the structure and provide explicit details showing how this will be achieved. 4.12 Liquid-applied Membranes Apply to concrete which has at least gained the required 28 days strength and with a moisture content less than 5% prior to application, unless otherwise recommended by the manufacturer. [Note 1: Some systems can be applied to 7-day-old concrete. Confirm with the manufacturer if required.] 4.12.1 Temperature Generally, apply at a temperature less than 35°C unless otherwise recommended by the manufacturer. 4.13 Pressure Grouting (a) Drill grouting holes in carefully selected locations. (b) Locate drill holes away from embedded reinforcement by using a magnetic induction digital display type cover meter. If drill hits reinforcement, stop drilling immediately, relocate hole and inform the SO. (c) On completion, make good holes with 1:3 ratio of a damp cement and sharp sand mix, thoroughly rammed in and finished neat and flush. 4.14 Workmanship for Joints 4.14.1 Sealants for Joints Prepare the joints and apply the sealants, back-up materials, bond breakers and joint fillers in accordance with the requirements of BS 6093, BS 6213 and BS 8000. 4.14.2 Gaskets Apply in accordance with the requirements of BS 6093, BS 6213 and BS 8000. 4.14.3 Sealing Strips Apply in accordance with the requirements of BS 6093, BS 6213 and BS 8000 Refer to BCA publication on "Good Industry Practices - Waterproofing for External Wall". TS 455/1065 978 Doc D.2/525 5 VERIFICATION AND SUBMISSIONS 5.1 Submissions 5.1.1 Tender Submit details of the proposed waterproofing system and supporting documents such as method statement, material testing results, samples, maintenance procedure during and after the warranty period, and track record with the tender submission for the SOs review and acceptance. 5.1.2 Method Statement Submit a detailed method statement describing the waterproofing system to be used, installation details, manufacturersâ details and requirements and protective measures to be adopted at all stages of the application. 5.1.3 Suitability of System Before starting work, provide written confirmation to the SO from the Supplier of the waterproofing system that the proposed concrete mix, placing methods, release agents, curing compounds, movement joint details, surface finishes, methods of supporting reinforcement and loads will not adversely affect the performance of the system. [Note 1: It is not always easy to obtain the written confirmation described here, and there may be a number of caveats which make any such statement of less value, but this does provide an opportunity to ensure that all parties understand what is required and the expected level of performance.] 5.1.4 Shop Drawings Submit shop drawings to the SO for acceptance showing the positions of joints and details of all materials to be used. Details shall include schedules of junction pieces and isometric layouts of waterbars. 5.1.5 Details Submit co-ordinated details for the SOs acceptance, including the following: (a) Junctions between roof/base slabs and external walls (b) Pipe penetrations through external walls (c) Junctions between base slab and piles/king posts TS 456/1065 978 Doc D.2/526 5.1.6 Product Certificates For all materials proposed, submit certificate from manufacturers showing evidence of compliance with the specified quality requirements. 5.1.7 Maintenance/Replacement Manual Cover all waterproofing systems used and materials specified in the maintenance manual to be submitted before handing over. 5.1.8 Warranty Submit the warranty for the SOs acceptance upon completion of the Works. 5.1.9 Quality Control Plan Prepare and submit a quality control plan for the SOs acceptance prior to commencement. Submit all quality control records progressively during the course of construction. 5.2 Samples/Mock-ups Submit samples of the proposed system and materials for the SOs acceptance prior to ordering of materials. Identify and label all samples appropriately. 5.2.1 Mock-up Panels Prior to commencement of work, submit proposal on mock-up panels for the SOs acceptance, that shall be constructed at agreed locations as selected by the SO to test products specified in this Section and arrive at acceptable methods of installation. 5.3 Inspection and Rectification Carry out visual inspection to the completed works. If there is any leakage, dampness and presence of water seepage resulting from hydrostatic pressure or capillary action on the surfaces of the structural elements that are visible, submit proposals for rectification for the SOs acceptance and carry out the rectification works. The rectification works shall achieve the same design working life and performance as specified by the waterproofing system. TS 457/1065 978 Doc D.2/527 (16) C03-060 Precast Concrete Works TS 458/1065 978 Doc D.2/528 1 GENERAL Read this Section with G01-010 "General Requirements" and all other contract documents. 1.1 Scope This Section covers requirements for the design, fabrication, handling, storage, transportation and erection of structural precast concrete elements, including elements used in composite structures. 1.2 Related Sections Read this Section in conjunction with the relevant requirements of the following sections: C03-010 Concrete Construction Generally C03-020 Reinforcement C03-030 Formwork and Falsework C03-040 Designed Joints C03-050 Water-resistance to Concrete Structures C03-070 Prestressed Concrete Works C05-010 Structural Steelwork C05-020 Protective Works for Structural Steelwork For precast concrete used as cladding, refer also to the architectural specifications. 1.3 Standards, Codes, Regulations and Technical References TS 459/1065 978 Doc D.2/529 1.3.1 Standards and Codes Unless otherwise agreed by the SO, ensure all of the Works comply with the relevant requirements of the standards and codes listed below or referenced in the body of the Specification. Alternative standards and codes may be proposed for approval by the SO, provided it can be demonstrated that the alternative standards and codes comply with the requirements of the standards specified. All standards and codes quoted are the current version, unless specific year references are noted. In the event that the standards or codes are partially superseded or have become obsolete, refer to the current edition or the approved substitution for the relevant clauses. Singapore Standards 1.3.2 SS EN 197-1 Cement: Composition, specification and conformity criteria common cements SS EN 206 Concrete: Specification, performance, production and conformity SS EN 1992-1-1 Eurocode 2 - Part 1-1: General rules and rules for buildings SS EN 1992-3 Eurocode 2 Part 3: Liquid retaining and containing structures SS EN 12620 Specification for aggregates for concrete SS CP 81 Precast concrete slab and wall panels SS 544-1 Concrete - Complementary Singapore Standard to SS EN 206 - Part 1: Method of specifying and guidance for the specifier SS 544-2 Concrete - Complementary Singapore Standard to SS EN 206 - Part 2: Specification for constituent materials and concrete Technical References Refer to the following technical reference for guidance in carrying out the Works: (a) CONQUAS, Quality Standards for Civil and Structural Works (b) BCA Buildability Series Publications, Reference Guide on Standard Prefabricated Building Components (c) BCA Buildability Series Publications, Structural Precast Concrete Handbook (2nd Edition) 1.4 Trade Preamble 1.4.1 Contractor’s Submissions and Proposals The layout and design intent of the concrete structures are shown in the drawings. Based on the design intent, engage qualified and experienced personnel, including a PE where appropriate, to carry out the following proposals for the Works, for the SOs acceptance. Make relevant submissions to the authorities for approval as directed. All structural calculations and drawings shall be endorsed by the PE, and comply with statutory requirements for approval, where applicable. TS 460/1065 978 Doc D.2/530 1.4.1.1 S1.4.1.1 Not In Use Develop the design of precast concrete elements Develop the design to produce the necessary details for fabrication and incorporation of the precast elements to the main structure for the SO’s acceptance. Cover the items as indicated in the drawings and shall include the following items when developing the design, where applicable or directed by the SO: Note: Use this clause amended as required where the Contractor is required to do design work. The appropriate insertions will also be required in the contract documents to cover responsibilities, design warranties etc, where there are particular requirements concerning the connections ensure that the following information is provided: 1.4.1.2 (a) Structural design of the elements in the permanent building structure, including temporary stages (b) Design for prestress, covering both temporary and permanent states (c) Design for demoulding stresses (d) Design for lifting, handling, transporting and storage (e) Design for all connections and joints (f) Not In Use S(f) Design for waterproofing of the permanent structure and joints (g) Sequence of forming the joint; (h) Critical dimensions allowing for permitted deviations, e.g. minimum permissible bearing; (i) Critical details, e.g. accurate location required for a particular reinforcing bar; (j) Method of correction of possible lack of fit in the joint (k) Details of temporary propping and time when it may be removed (l) Description of general stability of the structure with details of any necessary temporary bracing; (m) Extent to which the uncompleted structure may proceed above the completed and matured section; (n) Details of any special materials (o) Fully specified weld sizes. Mould and Formwork Design all mould and formwork for the fabrication of the precast elements, including all accessories for the lifting, handling and storage of the elements. TS 461/1065 978 Doc D.2/531 1.4.1.3 Temporary Supports Provide all necessary temporary supports and ensure that the precast elements are stable after erection but before the completion of the building structure. Provide all necessary precautionary measures to ensure that any part of the concrete structures is not subjected to loads that will cause short- or long-term distress. 1.4.2 Shop Fabrication Drawings Engage qualified personnel to develop the design drawings and produce shop fabrication drawings for the fabrication of the precast elements. Submit all shop fabrication drawings for SOs acceptance prior to fabrication. 1.4.3 Maintenance/Replacement Manual Prepare and submit a maintenance/replacement manual for components and connections, including the following items, where applicable or directed by the SO : (a) Joint Sealant system (b) Structural steel connection and fasteners (c) Sliding joint membrane /pad Refer to Section G01-010:Clause:1.4.5 for details. 1.4.4 Quality Control Plan Submit and work to a quality control plan as agreed with the SO. Refer to Section G01-010:Clause:1.4.7. S1.5 Supervision of Precast Structural Elements For precast structural elements which are manufactured off-site in Singapore or overseas, the Contractor shall appoint a Qualified Person (QP) to supervise the construction of the precast structural elements. The Contractor shall apply for a separate permit to commence works to the Commissioner of Building Control. The appointed QP shall submit a certificate of supervision of the precast structural elements on a daily basis or frequency agreed with the SO. The appointed QP shall appoint, if required, accredited site supervisor(s) to assist him in the supervision of the construction of the precast structural elements. All work and appointment of personnel related to the supervision of precast structural elements shall be deemed to have been included in the Contractor’s pricing and programme. 2 PERFORMANCE REQUIREMENTS 2.1 Contractor’s Proposal Brief In carrying out the design and proposals in Section C03-060:Clause:1.4.1, account for the input requirements as set out below. TS 462/1065 978 Doc D.2/532 2.1.1 Design Code The design of precast concrete elements shall be in accordance with SS EN 1992 and SS CP 81. 2.1.2 Design Consideration The elements shall be designed and detailed for all stresses induced by the worst loads, movement, creep and shrinkage during the intended design life. The elements, inserts or fixings, and positions shall be capable of resisting all stresses induced during the processes of manufacturing, lifting/handling, demoulding, transportation, storage and erection. The lifting and erection inserts, lifting hooks and erection devices shall be in compliance with the SS Eurocodes and standards as appropriate. As a minimum, the design loads and actions shall comply with requirements in the SS Eurocodes and the Building Control Regulations. Refer to the design drawings for other information on any specific design loadings if any. Consider additional design requirements for the precast elements as shown in the drawings and shall include the following, where applicable or directed by the SO: 2.1.3 (a) Construction loads arising from adoption of construction method (b) Propped or unpropped horizontal precast structure construction during erection (c) Semi-precast individual element strengthening at erection stage, etc. Joints and Connections The joints and connections shall be designed to transmit all forces developed at the joints of structures. When proprietary mechanical connection system is proposed, for the consideration of Design for Manufacture and Assembly (DfMA), product technical specifications and verification testing etc. shall be submitted to the SO for acceptance, and development of necessary quality control procedure during implementation. Joints, connections and sealants shall be designed for protection against water, weather, corrosion and fire to provide continued watertightness and weathertightness, and structural integrity of the buildings. 2.1.4 Water Retaining Structures In the case of water retaining structures, design the elements for maximum crack width as specified in the drawings or as directed by the SO, or otherwise in accordance with SS EN 1992-3 on allowable limits, for durability and low permeability against water seepage. TS 463/1065 978 Doc D.2/533 2.2 Fabrication Ensure the precast concrete elements are fabricated in a manner that when erected and all connections are in place, the design intent of the overall structure is achieved. Incorporate the requirements of all other trades with work requiring blockouts, recesses, notches, embedded metals or any other items. Ensure that exposed final concrete surfaces or finishes of the precast concrete elements are structurally sound and of the required concrete surface finishes that are smooth, and free from honeycomb and unacceptable bubble holes. In general, ensure that workmanship requirements as set out in the CONQUAS, "Quality Standards for Precast Components" are met. Ensure that the specified architectural finishes requirements, as indicated in the design drawings or as directed by the SO, are achieved. 2.2.1 Manufacturing Requirements Appointment of precast component manufacturer/supplier shall be approved by the SO, which is subject to the manufacturer/supplier having the necessary licence granted by the BCA with accreditation of quality control system and production facilities in its factory. Prior to mass production of precast concrete components, produce at yard for the SOs approval, each type of the following precast components: one mock-up of each major type of element, such as one façade; one wall; one column; one staircase and one household shelter as agreed with SO. The SO may at his absolute discretion require more sample panels to be produced for his/her approval. Provide remedial work to precast concrete components that are not satisfactorily manufactured as directed by the SO. Replace the precast concrete components that are rejected by the SO as a result of gross variation from the specified surface finishes. Position all reinforcements in the moulds with the prescribed concrete covers as shown in the Structural Drawings. Seek approval from the SO if such work cannot be incorporated into the precast concrete components. Aluminium window frames may either be installed on site or cast-in together with the precast concrete components. In all cases, protect the aluminium window frames with suitable wrapping and temporary bracing against deformation during concreting, and after production, protect from dirt, grout and other deleterious material by additional cushion protection wrapping with self-adhesive protective tape, etc. prior to delivery. Ensure adequate lapping over the joints of 2 protective tapes. Ensure protective tapes completely adhere to the frame and provide protection. In the case of aluminium window frames being installed on site, check and ensure: (a) The safety and integrity of the aluminium window frames and that no part of the precast concrete sill is hacked; (b) The watertightness between the aluminium window frames and precast concrete components with approved grouting and sealant. TS 464/1065 978 Doc D.2/534 2.2.2 Inspection of Manufacturing Make provision for the SO to inspect the manufacturing plant and the precast concrete components at all times. Any precast concrete component on site and at the manufacturing plant that does not comply with the design requirements and/or approved quality checking procedures shall be rejected by the SO. 2.3 Erection Erect the precast concrete elements at the designated location in accordance with the design intention. Any deviation shall be within the acceptable tolerance limit as specified in Section C03-060:Clause:4.3.3. 2.4 Joints and Connections Fabricate and erect the elements in such manner that the joints are in accordance with the design and detail. Any deviation in the joint width shall be within the acceptable tolerance such that the effectiveness of the joint’s resistance against the forces shall not be affected, and the joint is protected from water, weather, corrosion and fire, where applicable. Connection details shall be compatible with the design assumptions for the precast concrete structure. Materials used for connections shall be robust and compatible with the durability requirements of the overall structure. Avoid harmful bimetallic contacts, which may result in galvanic corrosion. 3 MATERIALS 3.1 Moulds Check and ensure that all moulds, regardless of materials, conform to the shape, lines and dimensions of the precast concrete elements to be fabricated. The moulds shall be sufficiently rigid to produce the casting tolerances and finishes specified. Use rubber seal or equivalent, in all horizontal and vertical mould joints to prevent leakage of mortar or cement paste. Design the moulds to prevent damage to the concrete, at all stages, during concreting, curing and demoulding, from the following: (a) Restraint, as the concrete shrinks (b) Stripping operation, when the precast concrete elements are lifted from the mould (c) Dimensional changes due to demoulding of precast concrete elements. TS 465/1065 978 Doc D.2/535 Use rubber lining with sufficient rigidity and consistency to allow repeated use for achieving a consistent quality of patterned finish. Use high quality rubber mat with dimension stability with SOs acceptance, for carrying the tiles of precast concrete elements with tile finish. Self-vibrating table moulds or suitably incorporated form vibrators may be used, subject to satisfactory demonstration of the component quality achieved in terms of compaction and surface finish using the mix proposed for the fabrication of the elements. 3.2 Concrete Refer to Section C03-010:Clause:3 for general requirements for material of concrete. For material requirements in ferrocement products refer to Section C03-090-01 "Ferrocement". 3.3 Reinforcement Refer to Section C03-020:Clause:3, for general requirements for material of reinforcement. 3.4 Prestressing Components Refer to Section C03-070:Clause:3, for general material requirement for prestressing. 3.5 Structural Steel Components Refer to Section C05-010:Clause:3, for general material requirement for structural steel component in the precast elements, and Section C05-020:Clause:3 for the corrosion protection of such components. 3.6 S3.6 Not In Use Non-Shrink Grout Non-shrink grout for structural bedding of precast concrete elements shall be of at least the same strength as the concrete of the building structures, or higher as required in the design. The grout shall be able to minimise stress induced arising from shrinkage, which causes cracks along the interface between the grout and the precast concrete elements. Proprietary products may be used as an alternative to mortar or non-shrink grout, subject to the SO’s acceptance. Demonstrate compliance of the product with the specified requirements. Grout material to comply with SS EN 197-1 and BS EN 13139 3.7 Mortar Mortar for non-structural bedding of precast concrete elements shall be made of sand, cement and water in proportions by volume of the following: TS 466/1065 978 Doc D.2/536 (a) One part of Portland cement to SS EN 197-1 (b) Two parts of sand to SS EN 12620 Determine the quantity of water required to achieve a mix suitable for jointing details shown on the drawings. Do not add other ingredients without the SOs approval. Mortar designated as dry-pack for non-structural bedding of precast concrete elements shall be of a tacky mix consistency that can be properly compacted by external ramming prior to setting upon precast installation. 3.8 Permanent Inserts or Fixings Cast-in inserts or fixings which would be permanently exposed either externally or within the cavity of the building envelope shall be of corrosion resistant material, e.g. hot-dip galvanised, painted mild steel or stainless steel, subject to the SOs acceptance. In other situations, agree with the SO on any protective treatment required. 3.9 Waterproofing Refer to Section C03-050:Clause:3, for general requirements of material for concrete waterproofing. 3.9.1 Sealant Refer to Section C03-050:Clause:3.8.1. Use suitable backer rod at joints where sealant is required for waterproofing. 3.9.2 Waterproofing and Sealant Materials for Joints 3.9.2.1 General Requirements The SO reserves the right to reject the use of any type of sealants if their performances is deemed unsatisfactory. All sealant materials used at public accessible areas such as common corridors, stair-cases, stair- landings, etc. shall be protected with non-shrink mortar or grout where appropriate or directed by the SO. 3.9.2.2 Application of Sealant Materials Ensure that joints and joint sealants of precast concrete structures are correctly installed to provide continued watertightness and weathertightness of building with minimum maintenance. Joint surface preparation, primers, sealant compounds and backup materials shall be installed to give the highest standard of materials and workmanship which shall conform to all applicable requirements as specified in the Specifications. Whenever possible, sealants shall be applied with a power-actuated gun. The gun shall have a nozzle of proper size and provide sufficient pressure to completely fill the joints. All compound smears, primers, solvents, etc. used in caulking and sealing work, shall be immediately and entirely removed from adjacent materials as the work progresses. TS 467/1065 978 Doc D.2/537 3.9.2.3 Joint Width and Sealant Depth After Installation The joint width shall depend on the dimension of the panels and the coefficient of expansion. Unless otherwise agreed by the SO, the maximum joint widths and maximum expansions for the common sealants shall be as listed in Table 1: Table 1. Common Sealants - Maximum joint widths and expansions Type of Sealant Butyl Acrylic One Part Polyurethane Two Parts Polyurethane One Part Polysulphide Two Parts Polysulphide Maximum Joint Width (mm) Maximum Movement in Tension or Compression (%) 20 20 20 20 20 20 ± 10 ± 15 to ± 25 ± 20 ± 25 ± 25 ± 25 The normal design joint widths shall be 14 or 15, 25, as shown in the structural drawings. For joints up to 13 mm wide, the depth of the sealant shall be equal to the width. For joints over 13 mm wide, the depth shall be equal to 1/2 the width, but not less than 13 mm. Sealants installed shall not be less than 6 mm wide or 6 mm deep. 3.9.2.4 Sealant Backup Fillers Backup filler shall be used to with joints to control the depth of the sealant, to facilitate tooling of the sealant, and to serve as a bond breaker which prevents the bonding to the back of the joint. Acceptable backup materials shall be those which compress and respond to movement. These include the rod type of sponge materials such as foamed polyethylene, polystyrene, polyurethane, polyvinyl chloride or synthetic rubber. The backup materials shall also be compatible and non-staining to the selected sealants. 3.9.2.5 Joint Preparation Before sealing the joints, ensure concrete surfaces are smooth, clean and free of all mortar dust or other contaminants that may affect adhesion. Sealant and primer shall be supplied by the same manufacturer, and the primer shall be as recommended for the particular sealant used. 3.10 Jointing TS 468/1065 978 Doc D.2/538 3.10.1 General Refer to SS EN 1992. Grout, mortar-pack or concrete the load bearing joints and connections. Ensure the method of installation adopted can fully grout, mortar-pack or concrete the joints and connections. Fill non-load bearing joints between precast concrete components and adjoining structures with appropriate grout and/or mortar protected by proprietary sealants and backing rod. Apply special coatings or epoxy bonding compounds to connections and joints of precast concrete components, whether welded, bolted, dowelled, grouted, mortar-packed or concreted, as instructed or directed by the SO. 3.10.2 Sleeve for Rebar Jointing Use one of the following types of sleeve connectors subject to satisfactory tests to determine structural strength and deformation characteristics: (a) Grouted, resin-filled or swaged sleeve capable of transmitting both tensile and compressive forces according to design requirement (b) Sleeve connectors that mechanically align the square-sawn ends of 2 bars to allow the transmission of compressive forces only Submit proposals and details of sleeve connector for joints to the SO for acceptance, including information on product manufacturer and model. Provide the proprietary product or approved equivalent of sleeve connector for joints as shown in the drawings or as directed by the SO. 3.10.3 Welding Refer to Section C03-020:Clause:4.3.3 for welding of reinforcement and Section C05-010:Clause:4.5 and Section C05-010:Clause:5 for welding of structural steel components. 3.11 Precast Prestressed Concrete Plank 3.11.1 Design Criteria and Material for Precast Prestressed Concrete Plank Low slump concrete shall be used for the production of precast prestressed concrete plank. The strength of concrete at 28 days shall be of a minimum grade of C32/40 or specified design grade, and at transfer, shall not be less than 25 N/mm². The use of calcium chloride, ion or other salts is strictly prohibited. The minimum grade of concrete for the cast-in-situ structural topping shall be C32/40. Submit for the SOs approval the initial prestressing records and the allowable strands slippage for plank production. 3.12 Precast Prestressed Hollow Core Slab TS 469/1065 978 Doc D.2/539 3.12.1 Design Criteria and Material for Precast Prestressed Hollow Core Slab The requirements for precast prestressed hollow core slab shall be the same as those specified for the precast prestressed concrete plank, except that the transfer strength for concrete shall not be less than 30 N/mm². 3.13 Precast Ferrocement Sun-breakers All structural and architectural drawings on this provision shall only serve as a guide. Where required or specified in the drawings, prepare and submit workshop drawings for the SOs acceptance on all relevant details, including: (a) Details on reinforcement of sun-breaker panels in elevations and sections. (b) Fixing and connection details. (c) Necessary steel bolts, hooks or other approved materials required for handling and erection purposes. Indicate the size and location of these materials clearly in the details. [Note 1: Consider the durability aspects with the local experience of more than twenty years on the use of precast ferrocement sun-breakers. If used, consider specifying limits on the size and or weight of ferrocement panels to avoid large panels.] 3.13.1 Steel Reinforcement Steel reinforcement shall be as specified in Section C03-020, including all sub-clauses under it. In addition, all welded mesh and steel bar used shall be galvanised in accordance with BS EN ISO 1461. Wire mesh with 1.5 mm diameter at 25 mm spacing shall be galvanised with zinc coating of 325 g per m² and 250 g per m² minimum for average coating. Local coating shall have minimum proof stress of 300 N per mm². 3.13.2 Technical Specifications 3.13.2.1 Ferrocement Mix Design The ferrocement sun-breaker panels shall be cast from a mix design satisfying the following requirements: (a) Minimum cement to sand ratio by weight of 1:2 (b) Maximum water to cement ratio by weight of 0.45 (c) Air dry density of hardened concrete (including steel) not less than 2,200 kg/m² (d) 28 days-average cube strength from 3 test cubes shall be not less than 40 N per mm² TS 470/1065 978 Doc D.2/540 The amount of admixture in the mix design shall be in accordance with the manufacturer's instruction. Before commencing, the manufacture of precast ferrocement sun-breaker, submit a proposed mix design to the SO for approval. 3.13.2.2 Other Properties (a) Initial Surface Absorption Test (ISAT) shall be carried out in accordance with BS 1881. The hardened panel shall have ISAT value less than that stipulated below: Table 2. ISAT values of hardened panel Time (min) ISAT Value (m/m²/s) 3.13.2.3 10 0.100 30 0.055 60 0.035 (b) Carbonation depth of hardened panel at installation shall be less than 3 mm. (c) Cover tolerance shall be such that no more than 3 points per section shall have a cover measurement of less than 5 mm, but not less than 3 mm. Finishes The panel shall be cast on a steel base mould with the finish surface cast-face down. The finish surface is the external surface of the sun-breaker elevation where the tile and motifs are located. 3.13.2.4 Dimensional Tolerances All tolerances shall be as specified in sub-clauses in "Manufacturing Tolerances" and in "Erection Tolerance". 3.13.3 Manufacturing Process The panel shall be cast flat on a steel base mould. The mortar shall be compacted by vibrators and the top surface shall be steel trowelled smooth. All reinforcement shall be galvanised and adequately supported with approved spacers. After setting and demoulding, mark the panels and neatly store with easy access and visibility to every piece. All panels must be properly cured. Seek the approval of the SO with respect to the curing method, duration and facilitates prior to actual production. The curing method shall be equivalent to 3 days of moist curing. Prior to commencement of the production, at least one sample of the panels shall be produced, erected and installed at site for the approval of the SO. Make adjustments to the manufacturing process or equipment if so directed by the SO. Maintain a record of daily work progress on a proper drawing showing where panels of a particular date of manufacture have been installed. TS 471/1065 978 Doc D.2/541 3.13.4 Quality Assurance Works for Precast Ferrocement Sun-breakers For precast ferrocement sun-breakers, the requirements for inspection and testing, sampling rate and passing criteria shall be as submitted to the SO for acceptance and development of necessary quality control procedure, or as directed by the SO. 3.14 Precast Facades with Cast-in Window Frame 3.14.1 Protection of Cast-In Window Frames Ensure that cast-in window frames are protected from damage before delivery to precast plant. Protect cast-in window frames from dirt, grout, grease, deleterious materials and surface scratch with quality translucent self-adhesive tape of light colour for inspection of window frame quality at precast plant prior to casting, as well as for inspection at site upon the delivery of precast facades. The self- adhesive tape shall be made of durable material that can withstand the weathering. The protective tape shall not stain or stick to the aluminium surface, or leave a sticky surface upon the removal. During manufacturing of precast component, the cast-in window frame shall be properly braced and secured to position such that it will not move or deform during concreting. Ensure that the wrapping with self-adhesive tape is robust to withstand handling during casting, storage and transportation to site. The adhesive tape shall be intact with cast-in window frame along the edges with no visible gaps. The corners of cast-in window frames and intersections of window frame members shall be adequately wrapped with sufficient laps and returns to prevent ingress of concrete grout during casting. All fastening screws, joints and gaps that are in contact with the wet concrete shall be sealed adequately to prevent grout ingress during casting. Cast-in window frames with torn, loose wrappings, and frames with visible gaps at edges that will be in contact with wet concrete shall not be used for casting. Poorly protected window frames shall be made good or replaced. 3.14.2 Quality Control at Window Factory Ensure that adequate quality assurance measures are in place in the production and the assembly of cast-in window frames. Quality assurance checks on surface defects such as dents, scratches and other defects such as dimension out of the manufacturing tolerances, warpage, twisting, skewing, track misalignment, shall be conducted at the window factory before wrapping up with the protective tape. A label sticker shall be provided at one location on the internal face of cast-in window frame to indicate the product serial number, window marking (including its orientation such as top, left or right-hand side, if applicable) on each cast-in window frame. This is to facilitate down-stream traceability and inspections, and prevent mistakes in the placement of window frame in precast production. For sliding window, provide internal bracing to control the sagging of horizontal aluminium members adjacent to the window opening during handling and precast production process. The cost for measures taken to enhance the window identification, to control the alignment of aluminium members during handling and for quality assurance in precast production is deemed to have been included in the tender sum. 3.14.3 Quality Control at Precast Plant TS 472/1065 978 Doc D.2/542 3.14.3.1 Inspection Upon the Delivery of Cast-In Window Frames Ensure that cast-in window frames delivered to precast plant are of good quality at the point of receiving. The inspections at precast plant shall include, but shall not be limited to, inspections on the workmanship of protective wrapping, dimension and surface defects such as dents and scratches. 3.14.3.2 Storage of Cast-in Window Frames Store cast-in window frames at a sheltered yard to prevent deterioration of protection system due to weathering. The storage shall be demarcated, barricaded and raised to prevent soiling, contacting with deleterious materials and accidental damage. 3.14.3.3 Care and Protection During Casting and Transportation Ensure cast-in window frames are handled with care during the production process. Assign experienced personnel, including supervisors and a team of skilled workers with the SOs acceptance for the production of precast facades with cast-in window frames, repair and delivery. Any part of cast-in window frames which is in direct contact with the dummy frames, bracings and stoppers of the mould system, additional protective material shall be provided to prevent any premature damage to the cast-in window frames. Additional protection may be needed to prevent grout leakage at the comers. To avoid excessive staining due to dropping of fresh concrete, protective measures shall be taken to cover the window frames during the casting process. For the transportation from precast plant to site, provide adequate measures at the critical contact points between the precast facades and the steel frames on the trailers to prevent damage to the cast-in window frame. Before casting, exercise due diligence and care in the precast production to ensure that the orientation of cast-in window frame is checked when it is placed on the mould. Measure and check the position of the cast-in window frame against the approved precast shop drawings before casting. Upon the demoulding of precast facades, the orientation, position of cast-in window frame and the clearance between the aluminium members shall be measured to detect any possible sagging or bulging occurred during the casting. 3.14.3.4 Watertightness Test Provide the equipment, labour and material to conduct watertightness test at the precast plant to ensure there is no water seepage at the interface joint between the cast-in window frame and adjacent concrete. The watertightness test shall be carried out using a continuous jet of water sprayed on the joint/interface with a nozzle and water hose. For each window, 4 points shall be selected for testing and each point shall be sprayed for 20 min. The location of test shall be selected by the SO. The velocity of the water at each nozzle shall be 2 m per second. The capacity of the water delivered from each nozzle shall be 600 litres per hour. Hold the nozzle at a distance 1 m away from the joint/interface and pointed towards the joint/interface horizontally. Test 10% of the precast facades with cast-in window frame for the watertightness at the interface joint. Carry out the watertightness test as soon as the precast production has commenced to ascertain the initial casting workmanship, as well as the performance of the cast-in window frames. Submit for the SOs approval on the window type or window configuration and the location on window frame to be tested. The percentage of testing required with the agreement by the SO shall depend on the quality and performance cast-in window and the test results. TS 473/1065 978 Doc D.2/543 3.14.3.5 Functional Test For quality assurance, check the functionality and the performance of cast-in window frames randomly at the early stage of the project. This is to ensure that any inadequacy of the bracing system can be detected early. For sliding windows, the inner frames shall be installed for repeated sliding operations to check for smoothness, alignment and safety in operation. For casement and top-hung windows, the inner frames shall be tested by repeated opening and closing to check for smoothness, alignment and safety. 3.14.4 Inspection and Protection on Site 3.14.4.1 Inspection on Delivery of Precast Facades with Cast-In Window Frames When precast facades with cast-in window frames are delivered to site, check the condition of the cast-in window frames before installation. 3.14.4.2 Protection of Precast Facades with Cast-in Window Frames The precast components with cast-in window frames delivered to site are protected with the translucent selfadhesive tape. Provide additional protective material such as bubble wrap of minimum thickness of 5 mm or any other materials which are equivalent in performance and subject to the approval of SO to further protect the cast-in window frames from impact and abrasive forces on site. 3.14.5 Submission of Window Shop Drawings and Delivery of Cast-in Window Frames to Precast Plant Submit the window shop drawings to SO for approval within a reasonable time frame from the date of the Letter of Acceptance. The time frame for the window shop drawing submission shall be tied in with the approved master construction programme for the initial delivery schedule of precast components to prevent any delay in precast supply. Deliver mock-up cast-in window frames to the precast plant to facilitate the mould fabrication at the window opening. The time frame for the delivery of mock-up window frames shall be carefully planned to tie in with the initial delivery schedule of precast components to site and tie in with the approved master construction programme. Provide the mock-up frames, make improvements in the protective wrapping, including increasing the number of layers if required to enhance grout tightness, and on window frame construction where necessary. Ensure sufficient lead time in the deliver
0
You can add this document to your study collection(s)
Sign in Available only to authorized usersYou can add this document to your saved list
Sign in Available only to authorized users(For complaints, use another form )