SAPRJV Contract 3303 – Third Runway and Associated Works Report Revision Record Revision A Description of Amendment Initial version Issued on 23 Jan 2021 SAPRJV Contract 3303 – Third Runway and Associated Works Content 1. Scope of Works 2. Purpose of this Method Statement 3. Responsibility 4. Resource for Assembly 5. Assembly Plan for Crawler Crane 6. Assembly Sequence 7. Proof Load Test 8. Safety 8.1 Safety System of Work 8.2 Training 8.3 Lifting Operation 8.4 General Control Measures Appendices Appendix A – Risk Assessment Appendix B – Nomination Letter of Competent Person for Assembly of Crawler Crane Appendix C – Catalogue of Sumitomo SCX2800-2 Appendix D –Erection, Dismantling and Transportation in Code of Practice for Safe Mobile Crane Appendix E – Crawler Crane Erection Training Appendix F – Permit to Erection / Dismantling / Alternation of Crawler Crane Appendix G – Layout of Zone and Lifting Plan Appendix H – Check List for Assembly Operation Appendix I – Plant Information of Lorry Crane for Serving Assembly Appendix J – Joint Inspection Check List for Crane SAPRJV Contract 3303 – Third Runway and Associated Works 1. Scope of Works This method statement states the method for assembling service crane (Model No. Sumitomo SCX2800-2) in order to facilitate the Marine bored pile work at North Boat Point. The general layout is attached in figure below. Figure 1 – Location of Working Area This document describes the assembly procedure for the service crane on site, and to assess the risk associated with the works to ensure the safety of the assemble works. 2. Purpose of this Method Statement This Method Statement is to describe the Safe Working Procedure and its Safety System of work for installation (I/D) of Crawler Crane. To ensure effective implementation of this Method Statement by all concerned parties including Subcontractors, the procedure will be discussed during the Task Launching Meeting with the respective Subcontractors. SAPRJV Contract 3303 – Third Runway and Associated Works 3. Organization and Personnel Involved The operation is organized by SAPR-JV, the main contractor for AA Contract No.3303. The key persons responsible for the works are as follows: Name Position Company Contact no. Fergus Kwong Deputy Project Manager SAPRJV 6888 6178 Jordan Chan Safety Manager SAPRJV 9868 2180 CY Yeung Safety Advisor SAPRJV 9492 8243 Jacky Poon Safety Supervisor SAPRJV 6304 8999 Abbe Lau Engineer SAPRJV 9061 4029 Denis Leung Assistant Engineer SAPR-JV 5177 6729 Felix Tsang Assistant Engineer SAPR-JV 6675 9557 Chau Hiu Fai Foreman SAPR-JV 9091 0837 For SAPRJV 3.1 SAPRJV’s Responsibility and Supervision SAPR-JV is responsible for overall site monitoring and supervision throughout the whole construction process. The responsibilities and duties of persons mentioned in Section 4 are as follows:Deputy Project Manager (a) Overall site management, programming and coordination of the works, especially on the management of the specialist sub-contractor and as necessary to liaise with relevant interested parties; opening and closing of NCR, implement the action plan of risk assessment stated. Engineer (a) Discuss the prepared method statements with relevant personnel and the concerned subcontractors (b) Participate in carrying out risk assessments on the constraint of the work area and monitor recommendation on safety measures; (d) Ensure the implementation of proper control measures as documented in the method SAPRJV Contract 3303 – Third Runway and Associated Works statements and risk assessments. (e) Assist QA manager to implement QA / QC measures based on Inspection Test Plan to ensure the works will be carried out in accordance with GMWS / ASD Specification (for Government Building) / Code of Practices / Technical Circulars. (f) Resolve site issues and design issues with AA’s PMR (g) Monitor work progress with reallocation of resources if necessary Foreman (a) Carry out day-to-day safety supervision to ensure the employed workers full compliance with in-house safety rules and regulations; (b) Control and supervise construction works carried out in a safe manner and comply with the approved method statements and statutory requirements; (c) Prepares Form 3A and discusses with the safety officer; (d) Check and inspect the construction plants used on the site are in good working order; (e) Follow up the comments made in the safety inspection reports to ensure the identified irregularities been rectified; (f) Attend weekly join site safety inspections and weekly site health and safety committee meeting; (g) Stop the unsafe behavior; (h) Ensure worker using proper PPE; (i) (j) (k) (l) Ensure safe tools and equipment to workers for carrying construction works; Ensure checked lifting gear and lifting appliance use on site; Report the inspection findings to Safety Officer. Supervise subcontractors for work progress 3.2 LT SAMBO’s Responsibility and Supervision Project Manager (a) Executes the installation of monitoring equipment in compliance with the Method Statement and up-to-date working drawing under the supervision of SAPR JV’s site representative. (b) Program and monitor works progress in compliance with the corresponding quality, safety and environmental requirements. (c) Ensure works comply with statutory regulations and coordinate with relevant authorities. SAPRJV Contract 3303 – Third Runway and Associated Works Site Engineer (a) Executes the installation of monitoring equipment in compliance with the Method Statement and up-to-date working drawings under the supervision of SAPR JV’s site representative. (b) Progressively checks performed works. (c) Ensure the works are carried out in accordance with the approved safety standards. Safety Supervisor (a) Oversee the safety performance of construction activities. (b) Advise safety rules/ behavior to all personnel on site. (c) Enforce safety rules on site. Lifting Supervisor (a) Before the commencement of lifting activities, fence off the danger zone with barriers to prevent unauthorized entry. (b) Supervise all lifting operations onsite in accordance with regulatory requirements / JV in-house rules / AA’s guidelines (c) Conduct task launching and prework risk assessment. Banksman (a) Supervising all crane / excavator operations 4. Resource for Assembly A. Plant & Equipment • Helping Crane (110 Ton Crane Lorry; Model: COMPA 1600.9) Will assist in assembling the crawler crane, and the helping crane operator and slinger /signaler agree all communications before assembling of the crawler crane B. • • • • • • Labour Competent Person (Mechanic) Superintendant Foreman Lifting supervisor Rigger Banksman Note: refer to Appendix C for details of labou SAPRJV Contract 3303 – Third Runway and Associated Works 5. Assembly Plan for Crawler Crane Model Serial No. Manufacture year Length of boom SCX2800-2 SC280-7164 2010.05 39.65m Remark 6. Assembly Sequence 6.0 Preparation Site is responsible for making sure that both working area needed and the area around the crawler crane is fenced off by water barriers / plastic barriers at all time. Any work within the fenced off area will not be permitted unless authorized by CP. And banksman shall be present in the whole assembly process to ensure any entry into working area should be authorized. Safe access, working platform and safety harness shall be necessary and use throughout the assembly works. And, the basis assembly sequence are:i) Unloading base machine from trailer ii) Installation of Lower Weight iii) Installation of Crawlers iv) Installation of Counterweight and Base Boom Section v) Installation of Extension Boom vi) Installation of Hook and Wire Rope vii) Wiring viii) Machine Specification Setting ix) Boom Erection 6.1 Unloading Base Machine from Trailer 6.1.1 Park the trailer on solid, level ground SAPRJV Contract 3303 – Third Runway and Associated Works 6.1.2 Unfasten the wire ropes and chains from the machine Note: Drag the jack-up unit (1) and connect it to the link (2) with the pin (3) 6.1.3 Store the pin (4) on the jack up unit (1) Note: Be sure to use floats (5) supplied in the attached accessory parts. Level the ground surface under the float bottom comes in contact with the ground horizontally. Accurately align the centers of jack cylinder (6) and float (5) 6.1.4 Place floats (5) just under all jack cylinders (6) Note: Float weight: 33kg 6.1.5 Connect the remote control box Note: the remote control box hose connector are located at two locations (front and rear) on the slewing lock lug of the lower frame. Depending on the job site circumstances, select either one which is in the easiest-to-see position to connect the hose safely SAPRJV Contract 3303 – Third Runway and Associated Works Note 2: Check that the panel of the remote control box is in “Jack/crawler connecting operation” as shown below. If the operation side is in “Counterweight installing/removal operation”, remove the magnet sheet on the panel or tilt to “Jack/crawler connecting operation” with turning it over Note 3: Check that the power switch on the remote control box is OFF. In case the power switch is in the ON position, tilt the knob to the OFF position 6.1.6 Move lock lever (1) to the LOCK position Note: If lock lever (1) is in the UNLOCK position, the jack cylinders and the retraction cylinders cannot be operated SAPRJV Contract 3303 – Third Runway and Associated Works 6.1.7 Start the engine Note: Increase the engine speed to approx. 1000rpm and operate the remote control box in a safe and easy-to-see place” 6.1.8 Turn the power switch on the remote control box ON. Extend the jack cylinder (2) onto float (3) by operating the jack switch Note: Do not raise the base machine higher than necessary SAPRJV Contract 3303 – Third Runway and Associated Works 6.1.9 Operate the jack switch to raise the base machine until the base machine is slight separated from the trailer deck Note: To prevent the base machine from being inclined more than 1 degree, operate the switch slightly raise the rear side of the slewing upper structure first. Then, raise the front side of the slewing structure so that I becomes level. Repeat this procedure in sequence. Check the ground strength under the float under this circumstance 6.1.10 Operate the jack switch so that the clearance between the undersurface of the lower frame and the trailer deck is approximately 50mm Note: Hold the travel device hydraulic hoses on the lower frames to prevent the hoses from being damaged Note 2: Carefully move the trailer so that the trailer deck does not come in contact with the jack cylinders or the lower frames SAPRJV Contract 3303 – Third Runway and Associated Works 6.1.11 Move the trailer forward Note: when leaving the base machine supported with the jack cylinders for a long time, retract all the jack cylinders to the minimum 6.1.12 To lower the base machine, operate the jack switch on the remote control box to retract the jacks so that the base machine is kept level Note: Retract all the jack cylinder until the clearance between the undersurface of the lower frame and the ground is approximately 700mm SAPRJV Contract 3303 – Third Runway and Associated Works Note 2: to prevent the base machine from being inclined more than 1 degree, operate the switch slightly raise the rear side of the slewing upper structure first. Then, raise the front side of the slewing upper structure so that it becomes level. Repeat this procedure in sequence 6.1.13 Turn the power switch on the remote control box OFF 6.1.14 Remove the pin (1) and remove the link (3) from the lug (2) Note: remove the lock pin (4) 6.1.15 Rotate the cabin from the transportation position to the working position 6.1.16 Install the link (3) to the lug (5) with the pin (1) SAPRJV Contract 3303 – Third Runway and Associated Works Note: lock with lock pin (4) Note 2: adjust the link (3) length so that the cabin does not play 6.1.17 Move the lock lever (1) to the UNLOCK position 6.1.18 Raise the live mast (9) until the flip cylinder reaches the stroke end with operating boom derricking drum lowering simultaneously when moving the love mast flip switch (7) to the UP side Note: When live mast (9) angle is from 90 degree to 80 degree. The flip cylinder (8) automatically extends even if releasing the finger from the live mast flip switch (7) SAPRJV Contract 3303 – Third Runway and Associated Works Note 2: When the live mast angle extends to the stroke end is approx. 79 degree, it is supported by the boom derricking drum wire rope (10) Note 3: Let out the wire rope with operating boom derricking drum lowering according to the movement of the live mast (9) with the flip cylinder (8) Note 4: when the live mast (9) angle is from 90 degree to 80 degree, the boom derricking drum hoisting stops automatically Note 5: Unwind the boom derricking drum wire rope at the super slow speed with taking care about the irregular winding 6.1.19 Lower the live mast (9) to the working position around 70 degree 6.2 Installation of Lower Weight 6.2.1 Slew the slewing upper structure after disengaging the slew lock and releasing the slew brake. Engage the slew lock and apply the skew brake after positioning the lower frame forward or rearward Note: Wipe off dust or foreign matter from the quick couplers before connecting Note 2: Be careful not to let the quick couplers come in contact with other objects Note 3: Securely connect hydraulic hoses 6.2.2 Connect two hydraulic hoses (1) for the quick raw cylinder to the couplers on the SAPRJV Contract 3303 – Third Runway and Associated Works bracket of the cabin slewing mechanism 6.2.3 Lift the lower weight with help of the assistance crane 6.2.4 Fix the lower weight (3) with reinstalling the pin (9) and remove the sling ropes 6.2.5 After disengaging the slew lock and releasing the slew brake, slew the base machine 180 degree. Engage slew lock and apply the slew brake after positioning the slewing upper structure in the opposite direction 6.2.6 Install another lower weight (3) on the other jack up unit (7) with the same method as SAPRJV Contract 3303 – Third Runway and Associated Works described above 6.2.7 Install step (10) on the lower weight (3) (4 places) 6.3 Installation of Crawlers Important: Install the lower weight before installing the crawlers. If installing the crawler without lower weight installed, the machine will tip over Important 2: Never allow the workers enter between the base machine and the crawler or enter under the crawler Important 3: Never enter under the base machine while operating jacks Important 4: Operate the jack cylinders so that the base machine is not inclined more than 1 degree. Failure to do so may result in tipping over of the machine Important 5: While connecting or disconnecting the hydraulic hoses for travel mechanism, never slew the slewing upper structure. A serious accident due to pinch may result 6.3.1 After disengaging the slew lock and releasing the slew brake, slew the slewing upper structure 90 degree. Engage the slew lock and apply the slew brake after directing the slewing upper structure at the right and left of the lower frame Note: Decide which crawler of right and left to be installed first. 6.3.2 Attach sling ropes on the lifting lug (2 places) and the lifting link (1) (I place) of the crawlers (2) Crawler (2) weight : 19T Note: Remove the pin (5) of the crawler lifting link (4) and fix the lifting link (4) after drawing it SAPRJV Contract 3303 – Third Runway and Associated Works 6.3.3 Lift the crawler with the help of assistant crane and slowly lower the crawler after hanging the crawler (2) on the lower frame pin (8) Note: When the lower frame comes in contact with the crawler adjusting bolt (9), the pin (10) of the crawler connecting cylinders aligns with the lower frame hole 6.3.4 Connect the hydraulic hoses (11) (2 hoses) for the crawler connecting cylinder. 6.3.5 Tilt the lock lever (12) to the Lock Side Note: The jack cylinders and the crawler connecting cylinders could not be operated SAPRJV Contract 3303 – Third Runway and Associated Works when the lock lever (12) is in UNLOCK position 6.3.6 Turn the power switch on the remote control box ON. Extend the crawler connecting cylinder with operating crawler connecting switch and fix the crawler (2) Note: Attach the pin (13) on the pin (10) of the crawler connecting cylinder and lock with the lock pin (14) SAPRJV Contract 3303 – Third Runway and Associated Works 6.3.7 Tilt the lock lever (12) to the UNLOCK side 6.3.8 Remove the sling ropes from the crawler 6.3.9 Store the lifting link (4) of the crawler (2) Note: Remove pin (5) of the lifting link (4) and fix with the pin (5) after storing the lifting link (4) 6.3.10 After disengaging the slew lock and releasing the slew brake, slew the upper slewing structure 180 degree. Engage the slew lock and apply the slew brake after directing the slewing upper structure in the opposite direction 6.3.11 Repeat procedure 2 to 9 and install the other crawler (2) 6.3.12 Tilt the lock lever to the LOCK site 6.3.13 Operate the jack switch on the remote control box and lower the base machine on the ground with retracting jack cylinder (15) as keeping base machine level usually Note: Simultaneously retract the jack cylinders (front: 2 cylinders, Rear: 2 cylinders) alternately with operating the jack cylinders so that the base machine is not inclined SAPRJV Contract 3303 – Third Runway and Associated Works more than 1 degree 6.3.14 Retract the jack cylinder (15) completely 6.3.15 Store the float (16) on the lower weight (17) Float weight :33kg 6.3.16 Grease through the grease fittings located at the connecting undersurface of the crawler (2) and the lower frame SAPRJV Contract 3303 – Third Runway and Associated Works 6.3.17 Turn the power switch on the remote control box OFF 6.3.18 Shutdown the engine 6.3.19 Disconnect the remote control box from the connector lower frame Note: attach the cap on the connector SAPRJV Contract 3303 – Third Runway and Associated Works 6.3.20 Connect the hydraulic hoses (18) (4 places on the one side) to the travel motor section Note: Remove the cap and the plug from each connecting portion Note2: Disconnect/connect the quick-couplers only after shutting down the engine. Failure to do so may make the connection of the coupler difficult, or damage to the O-ring may result due to remained pressure in the hydraulic circuit 6.3.21 Connect the hydraulic hose to the take-up tumbler section 6.3.22 Install step (20) on the crawler (Right and left: each 6 places) SAPRJV Contract 3303 – Third Runway and Associated Works 6.3.23 Pull in the latch-form shaft (8) 6.3.24 While lifting the outside of side walkway (1) rotate the side walkway outward from the cab side 6.4 Assembling Counterweight and Base Boom Section SAPRJV Contract 3303 – Third Runway and Associated Works 6.4.1 Increase the engine speed to approx. 1000 rpm 6.4.2 An assistant crane approaches to the rear side of the crawler crane 6.4.3 Attach the sling rope on the base counterweight assy (3) at flat lorry. Base counterweight assy: 17.8T 6.4.4 Place the base counterweight assy (3) with the help of the assistant crane to the ground which located 30cm clearance from the crawler rear end. 6.4.5 Attach sling rope to Left side counterweight and install it on the base counterweight Assy (3) Left side counterweight: 5.8T Note: Align the concave with convex 6.4.6 Detach the sling rope and attach the sling rope to Right side counterweight and install it on the base counterweight assy (3) Right side counterweight: 5.5T Note: Align the concave with convex 6.4.7 Detach the sling rope 6.4.8 Repeat procedure 5 and 6 to install all the Left and right side counterweight, there are total 6 pieces of counterweight for both left and right side SAPRJV Contract 3303 – Third Runway and Associated Works 6.4.9 Install the link (8) (4 pieces) and (9) (20 pieces) at the front and rear of the counterweight and connect each counterweight together Note: Lock with ring pin (10) Note 2: Install link (8) at the portion that is connected to the base counterweight assy (3 6.4.10 Confirm the rear end position of the backstop Note: when the rear end position does not accord, remove the pins (1), (2) and extend the rear end of the backstop. Then changing the position so that it accords to the specification, fix it with the pin and lock the pin (2) with pin (1) SAPRJV Contract 3303 – Third Runway and Associated Works 6.4.11 Attach the sling rope on the outer member of the right side backstop and lifted up by the assistant crane 6.4.12 Remove the pin (5) from the stay guide (4) Note: Remove pin (6) 6.4.13 Raise the outer member (3) with the help of the assistance crane until the hole of the stay guide (4) align with the hole of the stay (7) 6.4.14 Inset the pin (5) into the stay guide (4) Note: Lock the pin with the ring pin (6) 6.4.15 Remove the sling rope 6.4.16 Set the left side backstop with the same procedures in the right side SAPRJV Contract 3303 – Third Runway and Associated Works 6.4.17 Make sure that the boom foot pin (1) of the slewing upper structure is stored on the cylinder (2) side 6.4.18 Clean the boom foot pin (1) holes of the base section (3) and coat grease 6.4.19 Clean the holes of the boom foot pin (1) of the slewing upper structure and coat grease 6.4.20 Arrange the base machine so that the distance between the base section (3) rear end and the lower weight (16) front end is 10cm Note: Connect two slings (11) with the length of 2.6m Note2: Fold one between the two slings (17) with the length 1.0m and connect 6.4.21 Retract the quick draw cylinder (10) and lift the base section (3) to the height (the base section angle is approx. minus two degree to the horizontal) that the boom foot side SAPRJV Contract 3303 – Third Runway and Associated Works avoids lower weight Note: Extend and retract the quick draw cylinder (10) with the right side control lever after changing the winch select switch to the “Quick Draw” side. The cylinder is extended when placing the lever forward (hook lowering) and the cylinder is retracted when placing rearward (hook hoisting) 6.4.22 After raising the live mast (9). Align the pin holes of the base section (3) with the slewing upper structure boom foot pin (1) holes 6.4.23 Remove the lock bar (5) from the inside hole of the bracket (4) Note: Remove ring pin (6) SAPRJV Contract 3303 – Third Runway and Associated Works 6.4.24 Tilt switch (7) of the boom foot pin R (right) in the cabin to “IN” side and insert the boom foot pin (1) Note: Make sure the boom foot pin is completely inserted 6.4.25 Title switch (8) of the boom foot pin L (left) in the cabin to “IN” side and inset boom foot pin (1) 6.4.26 Insert the lock bar (5) into the outside hole of the bracket (4) Note: lock with lock ring (6) SAPRJV Contract 3303 – Third Runway and Associated Works 6.4.27 After removing the lock pin (12) and the pin (13) release the drum mirror (14) storing position of the base section (3) Note: Return the lock pin (12) and pin (13) to the original position of the bracket (15) 6.4.28 Connect the remote control box Note: The connecting place of the remote control box is located at the rear under surface of the right side bed Note2: Make sure that the control panel of the remote control box is in COUNTERWEIGHT REMOVAL/INSTALLATION OPERATION as shown below. SAPRJV Contract 3303 – Third Runway and Associated Works When the panel is in JACK/CRAWLER OPERATION, change to COUNTERWEIGHT REMOVAL/INSTALLATION OPERATION with turning the magnet switch on the control panel over Note3: make sure that the power switch on the remote control box is in OFF. When the switch is ON. Tilt the switch to OFF position Note 4: Before installing the counterweight, remove the crawler inner side and lower weight steps, otherwise they may make contact with and damage the counterweight 6.4.29 With the base section supported with the quick draw. Move the base machine backward to the direction of the counterweight Note: Move the machine backward with aligning the center (A) of the removal/installation frame (11) and the piping of the rotating platform (12). Or move the machine with aligning the rotating platform (12) end surface of the hydraulic sump tank (13) with the end surface (B) of the counterweight side SAPRJV Contract 3303 – Third Runway and Associated Works 6.4.30 Stop the machine when the center of the arrow mark (20) indicated on the rotating platform (12) cannot be confirmed due to the counterweight Note: The width (106mm) of the arrow mark (20) is the range that can remove and install the counterweight 6.4.31 Move the lock lever (1) to the LOCK side Note: When the lock lever (1) is in the UNLOCK position, the counterweight cannot be installed or removed SAPRJV Contract 3303 – Third Runway and Associated Works 6.4.32 Pull out the lever (15) installed on the base counterweight assy (3) (Right and left: each 2 places) 6.4.33 Pull out the lock pin (16) of both right and left installed on the removal/installation frame (11) after removing the pin (17) 6.4.34 Connect the hydraulic hose (18) for the removal/installation cylinder to the piping (14) installed on the rotating platform (12) 6.4.35 Turn the power switch on the remote control box and extend the removal/installation cylinder (19) of both right and left with operating the removal/installation cylinder switch SAPRJV Contract 3303 – Third Runway and Associated Works Note: At this time, make sure that the hook (25) of the removal/installation frame (11) was settled down the pin (26) of the rotating platform (12) side 6.4.36 Push in the lock pin (16) of both right and left to the rotating platform (12) side and lock the lock pin (16) with installing the pin (17) Note: Operate the switch with adjusting so that the counterweight does not tilt to both right and left carefully 6.4.37 With operating the removal/installation cylinder switch, retract the removal/installation SAPRJV Contract 3303 – Third Runway and Associated Works cylinder (19) of both right and left and lift the counterweight 6.4.38 Push in the lever (15) of the base counterweight assy (3) and fix the counterweight (Right and Left: each 2 places) Note: Slightly extend the removal/installation cylinder (19) so that the load is not given to the removal/installation cylinder (19) 6.4.39 Turn the power switch on the remote control box OFF 6.4.40 Disconnect the remote control box from the connector of the right side bed Note: attach the cap on the connector 6.4.41 Lower the base section (22) peak on the ground Note: Rest it on the Stand 6.4.42 Remove the sling from the quick draw cylinder and shutdown the engine SAPRJV Contract 3303 – Third Runway and Associated Works 6.5 Installation of Extension Boom The illustration below show the type and installing direction of the connect pin that is installed at each boom tip side (concave side of connecting lug) Before installing the extension, check that the base section is lowered on a stand, and all counterweight are installed 6.5.1 Check the working area is large enough to assemble the required boom length SAPRJV Contract 3303 – Third Runway and Associated Works 6.5.2 Check the boom length to be assembled by referring to configurations of Boom/Fly jib and pendant ropes Note: connect one tip end of the top section pendant rope to the link at the tip of the top section, Secure both ends of the opposite and each extension pendant rope on the boom so that the pendant rope does not fall from the boom when lifting the boom 6.5.3 Attach sling ropes to the extension to be installed and lift it with an assistant crane Note: lift the extension so that the base section connecting side is positioned slightly lower than the level 6.5.4 Align the upper connecting lugs holes of the base section and the extension Note: Install connect pin (2) so that the lock pin (1) hole is positioned upright 6.5.5 Install the connect pin (2)(flanged pin) from the outside to the inside Note: Secure the connect pin with lock pin (1) SAPRJV Contract 3303 – Third Runway and Associated Works Note2: Do not install the lower side connect pins (3) 6.5.6 Lower the extension on the ground with the assistant crane and rest the extension on the stands 6.5.7 Remove sling ropes from the extension 6.5.8 Connect all extensions required to configure the boom in order Note: Install connect pins (2) (flanged pins) except the pins of the base section Note2: Install the upper connect pin pin (2)(flanged pin) from the outside to the inside of the boom and install the lower connect pin (2)(flanged pin) from the inside to the outside of the boom. Then secure the pins with lock pin (1) 6.5.9 Attach the sling wire ropes on the top section and lift the top section with the assistant crane Note: Lift the top section so that the rear of the top section is positioned slightly lower than the level SAPRJV Contract 3303 – Third Runway and Associated Works 6.5.10 Align the front side connecting lug holes of the extension connected already with the upper connecting lug holes Note: Install the connect pin(2) so that the lock pin(1) holes is positioned upright 6.5.11 Install connect pin (2) (flanged pin) from the outside to the inside Note: secure the pin(2) with the lock pin (1) 6.5.12 Lower the tip of the top section on the ground with the help of the assistant crane and rest it on a stand 6.5.13 Remove the sling wire ropes form the top section 6.5.14 Install connect pin (2)(Flanged pin) on the lower connecting lug from the inside to the outside Note: Secure the pin (2) with the lock pin (1) Note 2: if it is difficult to align the holes, attach the sling wire near the connecting portion of the extension. 6.5.15 Attach the sling rope on the base secton (3) SAPRJV Contract 3303 – Third Runway and Associated Works 6.5.16 Retract the quick draw cylinder (34) and lift the base section. Align the lower connecting lugs holes of the extension and base secton. At this time, do not the the boom peak off the ground Note: Extend and retract the quick draw cylinder (10) with the right side control lever after changing the winch select switch to the “Quick Draw” side. The cylinder is extended when placing the lever forward (hook lowering) and the cylinder is retracted when placing rearward (hook hoisting) 6.5.17 Install the connect pin (8) (both side tapered pin) from the outside to the inside Note: secure the connect pin (8) with lock pin (1) Note2: Install the connect pin (8) so that the lock pin (1) hole is positioned upright 6.5.18 Remove the sling from the assistant crane 6.5.19 With operating the boom derricking drum lowering, lower the love mast (10) to the SAPRJV Contract 3303 – Third Runway and Associated Works position that the pendant rope (9) can be connected 6.5.20 Connect the extension pendant rope (12) to the top section pendant rope (11) with the connect pin (14) in the order according to the boom configuration Note: Insert the connect pin from inside and secure it with the cotter pin (15) Note2: Open the end of the cotter pin 30 degree to 90 degree 6.5.21 Connect the 1.2m pendant rope (13) to the end of the extension pendant rope with the connect pin (14) Note: Install the connect pin (14) from the inside and secure it with the cotter pin (15) Note2: open the cotter pin (9) end from 30 degree to 90 degree 6.5.22 Install the link (25) and (26) at the front and rear of the pendant link (24) with the pin (27) Note: Install the connect pin (27) from the inside and secure it with the cotter pin (28) Note2: open the cotter pin (28) end from 30 degree to 90 degree SAPRJV Contract 3303 – Third Runway and Associated Works 6.5.23 Connect the 1.24m pendant rope (13) to the link (25) with the connect pin (14) Note: Install the connect pin (14) from the upper side and secure it with the cotter pin (15) Note2: open the cotter pin (15) end from 30 degree to 90 degree 6.5.24 Connect the pendant rope (9) of the live mast side to the link (26) with connect pin (29) Note: Install the connect pin (29) from the inside and secure it with the cotter pin (30) Note2: open the cotter pin (30) end from 30 degree to 90 degree 6.5.25 With tilting the switch (32) of the live mast flip cylinder DOWN, retract the flip cylinder (31) to the minimum 6.5.26 With operating the boom derricking drum lowering, Raise the live mast (10) and tense the pendant rope (12) 6.6 Installation of Hook and Wire Rope 6.6.1 Place the hook to be used in front of the boom SAPRJV Contract 3303 – Third Runway and Associated Works 6.6.2 Let out the front drum wire rope (1) and reeve the wire rope through the right side guide sheave(2) and the point sheave (3) on the top section Note: Let out the wire rope with the length corresponded to the number of parts of line on the hook Note2: Be careful not to allow the rope on the front drum loosen too much 6.6.3 With referring to the illustrations for the wire rope reeving, reeve the wire rope into the hook and point sheaves (3) Note: When reeving the wire rope from the underside of the point sheaves (3), install the wire rope from the outside of the rope guide (4) SAPRJV Contract 3303 – Third Runway and Associated Works 6.6.4 For installing the ball hook, place it at the front of the short jib 6.6.5 Let out the rear drum wire rope and reeve the wire rope through each point sheave via the left side guide sheave of the top section for the short jib 6.6.6 After attaching the rope socket (1) at the wire rope end, connect the rope socket (1) to the top section or the hook (2) with pin (3), castle nut (4) and cotter pin (5) Note: The correct installing method of the wire rope into the rope socket (1) is illustrated below 6.6.7 Install the hoisting limiter weight (7) on the wire rope (8) SAPRJV Contract 3303 – Third Runway and Associated Works 6.6.8 Reeve the aux drum wire rope through the weight (1) and the weight support (2) and install the rope socket (3) on the wire rope end. Securely install the jib hook(13.5T) on the rope socket (3) with the pin (4), washer (5), castle nut (6) and cotter pin (7) Note: The hoisting limiter may not function if the weight support (2) is not used Note2: Confirm the wire rope size according to the imprint indication and be sure to use the weight support (2) corresponding to the wire rope diameter Note3: open the end of the cotter pin(7) from 30 degree to 90 degree 6.7 Wiring 6.7.1 Remove lock pin (2) from cable reel (1) on the boom base section. Pull the cable out of reel (1). Connect the cable to the FRONT terminal on the boom top section terminal box (5) Note: Connect cap (3) to the plug (4) SAPRJV Contract 3303 – Third Runway and Associated Works 6.7.2 Clamp the cable between cable reel (1) and terminal box (5) to the boom with clips (6) in order from terminal box (5) Note: Reeve the cable through the clip (6) as illustrated below 6.7.3 Connect connector (7) on cable reel (1) to base machine side cable end connector (8) on the boom base section Note: Connect the removed caps each other SAPRJV Contract 3303 – Third Runway and Associated Works 6.7.4 Connect base machine side cable end connector (10) on the boom base section to base machine side terminal box (9) Note: Wire the cable with some slack around the boom foot so that the cable is not tightened when and/or after the boom is erected 6.7.5 Connect the boom angle sensor cable installed on the boom base section to base machine side terminal box (9) Note: Wire the cable with some slack around the boom foot so that the cable is not tightened when and/or after the boom is erected 6.7.6 Connect the limit switch cable for the secondary boom overhoist prevent device installed on the backstop to the connector of the base machine side terminal box (9) Note: Remove the short circuit plug from the connector of the base machine side terminal box (9) Note2: Wire the cable with some slack around the boom foot so that the cable is not tightened when and/or after the boom is erected 6.7.7 Connect the boom hook hoisting limiter cable (1) to the MAIN terminal on boom top section terminal box (2) Note: Connect the removed plug (3) to the plug (4) SAPRJV Contract 3303 – Third Runway and Associated Works 6.7.8 Connect the hoisting limiter (1) to switch cable (6) Note: Connect the removed caps each other 6.7.9 Connect the short jib hook hoisting limiter cable (7) to the AUX terminal on boom top section terminal box (2) Note: Connect the removed short circuit connector (5) to the plug (4) 6.7.10 Connect the short jib hook hoisting limiter cable (7) to switch cable (8) SAPRJV Contract 3303 – Third Runway and Associated Works Note: Connect the removed caps with each other 6.8 Machine Configuration Setup 6.8.1 After moving the blue cursor to the first item to be changed by operating the up and down keys, press the circle key. Machine specification setting screen will be displayed 6.8.2 Move the blue cursor to the item to be changed by operating left and right keys SAPRJV Contract 3303 – Third Runway and Associated Works 6.8.3 After the selection is completed, press the down key. 6.8.4 The blue cursor moves to the next item below so that new item will be consequently displayed. Move the blue cursor to the item to be changed by operating left and right keys 6.8.5 After this, repeat this operation until “complete” is displayed on the screen 6.8.6 After selecting all items , when the blue cursor reaches the “Complete” column, the circle mark and “DECIDE” are displayed in the key guidance column at the screen bottom 6.8.7 Press the circle key, the screen moves to the operational specification confirmation screen 6.8.8 When the operational specification confirmation screen is displayed, recheck the displayed specifications. Then press the cross key to display the ML screen before starting to operate the machine SAPRJV Contract 3303 – Third Runway and Associated Works 6.8.9 The screen is used during normal operation 6.8.10 When the crane attachment is installed, depending on whether short jib or fly jib is installed, a different screen is displayed 6.8.11 Turn the key switch ON. When the machine specification screen is displayed, check that the displayed specifications match the actual machine specifications. Then press the Cross key SAPRJV Contract 3303 – Third Runway and Associated Works 6.9 Erection of Boom 6.9.1 After assembling the machine, recheck that all parts are correctly installed or connected. If any fault is found, reassemble the faulty section according to the correct procedure. 6.9.2 Check that all the cotter pins for all connect pins are correctly installed a) Boom connect pin b) Fly jib connect pin (if any) c) Short jib connect pin d) Fly jib mast connect pin (if any) e) Back stop connect pin SAPRJV Contract 3303 – Third Runway and Associated Works f) Pendant rope connect pin g) Fly jib pendant rope connect pin h) Wire rope socket pin 6.9.3 Check that wire rope socket wire clips are correctly installed a) Front drum wire rope socket b) Rear drum wire rope socket c) Boom derricking drum wire rope socket d) Third drum wire rope socket (if any) 6.9.4 Check that all bolts are securely tightened a) Drum and wire rope connection b) Boom foot pin c) Guide roller mounting section d) Short jib connection e) Fly jib foot pin f) Hook hoisting limited switch and weight connection g) Sheave mounting pins 6.9.5 Check that all cable connections are correctly connected a) Hook hoisting limiter cable b) Boom angle sensor cable c) Secondary boom overhoist prevention device cable d) Other front attachment cable 6.9.6 Check that the lengths of the pendant rope is correct SAPRJV Contract 3303 – Third Runway and Associated Works 6.9.7 Check that wire ropes are correctly installed and threaded 6.9.8 Check that all the wire ropes are laying on top of the boom without being restricted 6.9.9 Check that the backstop is normally installed 6.9.10 Check that no tools left behind 6.9.11 Before raising the boom check the followings a) Recheck that all the conditions to raise the boom have been met b) The ground surface on which the machine setup is done level and solid c) No obstruction such as power lines are present in the area in which the boom is to be raised d) Check that wind will not work against boom raising direction e) Check that the boom raising pads are correctly laid f) Check operation of safety devices g) Check that the rated capacity limiter displays the transport configuration 6.9.12 Turn the accelerator grip clockwise full stroke to reduce the pump delivery flow rate to SAPRJV Contract 3303 – Third Runway and Associated Works minimum 6.9.13 Run the engine at 1000 to 1200 rpm 6.9.14 Move the boom derricking drum to hoist position 6.9.15 Slowly wind the boom derricking drum wire rope with the hook kept on the ground until boom angle enters operating range 6.9.16 Return the boom derricking drum lever to neutral 6.9.17 Hoist the hook 6.9.18 Slowly travels the machine backward 6.9.19 Remove the Pads 7. Proof Load Test 7.1 According to Hong Kong regulation Chapter 59J <<Factories and Industrial Undertakings (Lifting Appliances and Lifting Gear) Regulations>>, Regulation # 5 – Lifting appliances to be tested and examined prior to use; before any lifting job, this crawler crane has been thoroughly examined by a competent examiner (eg. Register Professional Engineer). Load test be taken with RPE. 7.1.1 A proof load which shall exceed the safe working load as follows – 7.1.1.1 If the safe working load is less than 20 tonnes, the proof load shall exceed the safe working load by at least 25 percent; 7.1.1.2 If the safe working load is 20 tones but less than 50 tonnes, the proof load shall exceed the safe working load by at least 5 tonnes; 7.1.1.3 If the safe working load is more than 50 tonnes, the proof load shall exceed the safe working load by at least 10 percent. 7.1.2 And Safety Working Load shall downgrade as follow: SAPRJV Contract 3303 – Third Runway and Associated Works 7.1.3 The proposed working load will be 50 Tonnes, so Minimum test load will be (50 x 1.1)/90%(over 10years) = 61.1 Tons. 7.1.4 After examination, a certificate in the approved by competent examiner should be issued and kept at crane cabin. 8. Safety 8.1. Safety System of Work Project Manager and the Safety staff have to ensure all the system element of below to be implemented 8.1.1. Before Operation • Task Launch Meeting should be arranged. Attendees include the Site Engineers, Superintendent/ Foreman and the working crew. This training should be conducted by a Nominated Competent Person. (Remark: The Nominated Competent Person(NCP) should be trained by LTSAMBO Plant Department or by the crane’s manufacturer. By the either of both ways he/ she need to be nominated by LTSAMBO) • Related Crawler Crane and trailer should be in proper work location. The work location should be fence off with sufficient warning signage to prevent the entry of others. • All plant, equipment and tool should be maintained in good working condition and be checked before use. 8.1.2. During Operation • CP is appointed as the in-charge of supervising the I/O operations. He must be clear leadership within the crew and have empowered to stop work if they see any unsafe act or SAPRJV Contract 3303 – Third Runway and Associated Works conditions happened • Pre-work inspection and pre-work briefing should be carried out before the works, the CP has to describe the safety procedure and hazards for to the crews during the assembling and disassembling. • Ensure good communication between each party, waikie-talkie will be provided by company and the workers involve in the operation. • Installing/ dismantling operation should be carried out comply with the Manufacture’s instruction and the methods provided by LTSAMBO plant department. • No staff will be below a dismantling / erecting section. If necessary, proper support needs to provide during dismantle / erecting work. • CP need to ensure the implementation for above. 8.2. Training. • CP should attend specific training for I/D operation of Crawler Crane • Provide too box talk about routine Safe Working Procedure to all workers • All lifting operation should be carried out by competent person(including crane operator, fitter / mechanic, ganger, rigger/ signalman, experience worker)with instruction , COP and related regulations. • Safety Procedure of NTSAMBO, method statement, risk assessment etc should be used as the training material during task launching meeting and pre-work meeting 8.3. Lifting Operation • All lifting appliance will be check by the supervisor before using. • The crane operators / lorry crane operator will only response to the signal from the in-charge • Each Crane may have to be identified, to ensure correct signaling. This can be accomplished by putting a letter or number on the boom of each respective crane. • Ensure all lifting appliance and lifting gears for use have valid certificates, and in safe working order. 8.4. General Control Measures • All work gang should be provided proper personal protective equipment(PPE e.g. safety hardness) and it should be used by the workers. SAPRJV Contract 3303 – Third Runway and Associated Works For assembly work • Install the safety devices(height limit, automatic safety load indicator, sway alarm, CCTV, side mirrors). • Arrange on overall check by the fitter/mechanic, when all in order, arrange RPE examination to issue the relevant legal certification. SAPRJV Contract 3303 – Third Runway and Associated Works Appendix A – Risk Assessment EXISTING RISK LEVEL SAFE SYSTEM OF WORK RESIDUAL RISK LEVEL HAZARD/RISK Plant or Equipment Mobilization Crane movement Lifting operation CONTROL MEASURES TRAINING REQUIRED PPE REQUIRED Reflective Vest / illuminated traffic control baton ---- S RR 1 3 3 Signalman Assembly Supervisor 1 3 3 Operator / Rigger Assembly Supervisor Pre-working briefing Pre-working briefing 1 3 3 Signalman 1 3 3 Assembly Supervisor / Crane operator Assembly Supervisor Site Engineer Pre-working briefing 1 3 3 1 3 3 Assembly Supervisor / Crane operator Assembly Supervisor / Crane operator S RR Travel Accident 2 3 6 - Banksman should be provided to the site entrance to control the traffic while material delivery to site. Pre-working briefing Material drop off the transportation vehicle during loading and unloading 3 3 9 - Pre-working briefing Collision 2 3 6 - Electrocution 3 3 9 - Overturning 2 3 6 - Overturning 2 3 6 - Vehicle operator should ensure that the material was properly located in the proper position and tied. Rigger ensure that proper rigging and lifting procedure had been made before any lifting operation. Signalman should be employed for every crane movement Assembly Supervisor / crane operator should inspect the routing to ensure that no overhead electrical cable and any electrical cable laying on the routing Site Foreman / crane operator should inspect the routing to ensure that the crane stability during movement including the ground condition. Site Foreman / crane operator should inspect the ground condition and ensure that its good for lifting operation. If necessary steel plate should be used to increase the ground stability Out rigger (lorry crane) must be fully extended and supported with base plate before lifting operation - MONITORED BY LH LH - ACTIONED BY Pre-working briefing Gloves Site Engineer Site Engineer EXISTING RISK LEVEL ACTIVITY Lifting Operation (Continuous.) SAFE SYSTEM OF WORK HAZARD/RISK Falling Objects LH S RR 2 3 6 CONTROL MEASURES - - - - Unloading base machine from trailer without crawler side frames / Base machine travel down the trailer with crawler side frames Overturn 2 3 6 - Hand injury (worker release the wire ropes and chains from the trailer and the base machine, also during the jack up unite installation) Collapse 2 3 6 - 2 3 6 - Site Foreman / rigger must ensure that the lifting load must not exceed the lifting capacity Lifting zone must be fenced off before any lifting operation, and ensure that no other worker(s) was remain or entered into the lifting zone during the lifting operation Tag line should be used to position the load being lifted All lifting appliances and gears must have valid RPE’s certificate(s) and correct colour code for lifting gears All lifting appliances and gears must be inspected and ensure that it is in good working order before use Rigger / signalman must be deployed during the lifting operation Site Engineer / crane operator ensure that the trailer was located on the solid and level ground to unload the base machine. Appointed crane assembly supervisor must be close monitor the assembly operation. All hand tools must be in good working order. Good communication between coworkers. All four jack-up cylinders must be inspected by the assembly supervisor before raising up the base machine RESIDUAL RISK LEVEL TRAINING REQUIRED Pre-working briefing PPE REQUIRED ---- Pre-working briefing Pre-working briefing Pre-working briefing Gloves ACTIONED BY MONITORED BY 3 Assembly Supervisor / Rigger Site Engineer 3 3 Site Engineer 1 3 3 Assembly Supervisor Site Engineer 1 3 3 Worker Assembly Supervisor LH S RR 1 3 1 Crawlers installation Relocate the crawlers assembly to the installation position Hand injury 2 Extend A-frame Working at Height 2 Counterweight Installation Working at Height 2 Boom Installation Lifting operation (Locate boom section to connection position) 2 Struck by falling objects 2 Working at Height 2 Electrical connection and reeving wire rope L1 L2 L3 L4 L5 LH = Likelihood Very Unlikely Unlikely Possible Likely Very Likely 3 S1 S2 S3 S4 S5 6 - Good communication must be Pre-working maintain between the crane operator briefing and the signalman. Good communication between coPre-working workers briefing All hand tools must be in good working order Appropriate gloves should be worn. 3 6 Workers working at the top of the Pre-working briefing crawler crane’s machine cabinet, safety harness must tie off on appropriate anchorage point. 3 6 Workers working at the top of the Pre-working briefing crawler crane’s machine cabinet, safety harness must tie off on appropriate anchorage point. 3 6 Fencing off the working area. Pre-working Helping crane will lift the boom briefing section to connection position. Helping crane can only release after all pins were installed. 3 6 Never work or passing by below the Pre-working boom section. briefing No one should work under any others working on top section. 3 6 Access ladder should be provided to Pre-working access the upper part of the boom. briefing Workers must wear safety harness and tie-off to the appropriate anchorage point while working on top of the boom. Never walk along on the top of the boom. S = Severity RR = Risk Rating Slightly 1 - 5 = Trivial Moderate 6/8/9 = Acceptable Serious 10/12 = Moderate Major 15/16 = Substantial Catastrophic 20/25 = Intolerable 1 3 3 Signalman / rigger Assembly Supervisor Gloves 1 3 3 Worker Assembly Supervisor Safety Harness 1 3 3 Worker Assembly Supervisor Safety Harness 1 3 3 Worker Assembly Supervisor 1 3 3 Worker Assembly Supervisor 1 3 3 Worker Assembly Supervisor 1 3 3 Worker Assembly Supervisor Safety Harness Priority Low priority item Low priority item Moderate priority item High priority item Urgent item Acceptability SAPRJV Contract 3303 – Third Runway and Associated Works Appendix B – Nomination Letter of Competent Person for Assembly of Crawler Crane SAPR JV 11/F., Paul Y. Centre, 51 Hung To Road, Kwun Tong, Kowloon, Hong Kong Date : 26 January 2021 To whom it may concern Re : Competence Person Further to your request on a Competence Person on the assembly and dismantle of our Crawler Cranes, following are his details. Competence Person In-Charge: Name : CHU, Kin Man Hong Kong ID Card No. : Y066XXX(2) Experience : 12 years We hereby authorize the following personnel: 1) Mr. Chan Nam Yu 4) Mr. TSANG Yuk Fai 7) Mr. Keung Kam Tak 2) Mr. WONG Siu Hong 5) Mr. CHAN, Yiu Chung 3) Mr. CHEUNG Kin Ming 6) Mr. WU, Wai Hong They undertake the assemble and dismantle job for below Crawler crane, Model: S/N: HSC SCX2800-2 SC280-7165 HSC SC1500-2 SC150-1080 HSC SCX2000A-2 SC20A-7039 They have well experience for the job of assemble and dismantle of crawler crane. Thank you Regards KH Chua SAPR JV 11/F., Paul Y. Centre, 51 Hung To Road, Kwun Tong, Kowloon, Hong Kong Further to your request on a Competence Person on the assembly and dismantle of our Crawler Cranes, following are his details. Competence Person In-Charge: Name: Chu Kin Man Hong Kong ID Card No. : Y066XXX(2) Experience : 12 years Year Crane Model Experiences Project 2008 & 2009 Kobelco CKE2500, K7150, K7080, - Assembly 昂船洲 8 號及 9 號碼頭大橋地盤 K7055 - Dis-assembly 2010 Kobelco CKE800, CKE900, CKE1000, - Assembly 西九工程 CKE1350, CKE1800, CKE2500 - Dis-assembly 2011 KOBELCO CKE800, CKE900, - Assembly 澳門威尼斯人 CKE1000, CKE1350, CKE1800, - Dis-assembly CKE2500, K7150, K7080, K7055 - Assembly 2012 及 2013 KOBELCO CKE800, CKE900, 西區隧道, 西環泳池, 城西碼頭, CKE1000, CKE1350, CKE1800, - Dis-assembly 域多利道, 石門及皇后大道等 CKE2500, K7150, K7080, K7055 - Assembly 2014 及 2015 KOBELCO CKE1100, CKE2500, 啟德, 葵芳, 元朗, 黃大仙, 畢架 CKS800, CKS900, K7055, K7150, - Dis-assembly 山, 柴灣, 將軍澳, 石門等多區地 K7080, K7055, BM900HD-2F 盤 2016 KOBELCO CKE1100, CKE2500, - Assembly 大磡村, 灣仔, 人工島, 香港仔, CKS800, CKS900, K7055, K7150, - Dis-assembly 馬仔坑等多區地盤 K7080, K7055, BM900HD-2F - Assembly 2017 及 2018 KOBELCO CKE1100, CKE2500, 兒童醫院, 人工島, 西九, 書局街, CKS800, CKS900, CKS1350, CKS1800, - Dis-assembly 亞公岩, 大圍寶福山, 顯徑, 灣仔, CKS2500 瓊林街等多區地盤 Hitachi Sumitomo SCX1000A-3, SCX1500A-3, SCX2800-2 2019 KOBELCO CKE1100, CKE2500, - Assembly 太子道東, 太子道西, 人工島, 通 CKS800, CKS900, CKS1350, CKS1800, - Dis-assembly 洲街,粉嶺樓, 中華電力發電廠, CKS2500 茶果嶺, 大磡村, 屯門, 天水圍等 Hitachi Sumitomo SCX1000A-3, 多區地盤 SCX1500A-3, SCX2800-2 2020 Demag CC6800, CC2800-1, - Assembly 南丫島電力發電廠,三跑地盤, HSC SCX1000A-3, SCX900-2, - Dis-assembly 啟德東地盤,塘坑 fanling SCX1500-2, SCX550, bypass 地盤,古洞地盤,將軍澳 SCX2000-2, SCX2800-2 地盤 Kobelco CKE1800-1F, CKE1350 Yours Sincerely, TAT HONG HEAVYEQUIPMENT (HONG KONG) LIMITED Regards KH Chua / General Manager SAPRJV Contract 3303 – Third Runway and Associated Works Appendix C – Catalogue of Sumitomo SCX2800-2 ASIAN ISSUE Specifications HITACHI SUMITOMO Superstructure UPPER REVOLVING FRAME: All-welded, precision machined, robust construction. A machined surface provided for mounting load hoist and boom hoist assemblies, and mounting itself on turntable bearing. And pins bail frame with a 12sheave machinery and single center sheave of a 21.0 D/d ratio for 2×12-part boom hoist reeving. ASIAN ISSUE TURNTABLE BEARING WITH INTERNAL SLEWING GEAR: Heavy duty, single shear ball type; inner race of turntable bearing with integral, internal slewing (ring) gear bolted to lower frame, and outer race of turntable bearing bolted to upper revolving frame. CONTROL SYSTEM: System contains two sets of triplicate tandem valves which direct oil to various machine function and are actuated by control levers via remote controlled hydraulic servo for all motions. Working speeds can be precisely controlled by motorcycle type throttle and pilot-operated armchair single axis control levers in cooperation with “EPC” controller that varies engine rpm and hyd. pump discharge simultaneously, or varies just hyd. pump discharge while keeping engine rpm via motorcycle type grip throttle. System also takes a specially-tailored unique hydraulic circuit to maximizes drum horsepower, and reduces horsepower loss with eliminating the possibility of engine stall. Pump control system — By “EPC” controller that provides two modes of engine-pump control. MODE I: The “EPC” Controller is normally programmed to vary the engine speed and pump discharge simultaneously. Simply twisting the grip advances the engine to maximum speed and the hydraulic pumps to maximum flow at the same time. This mode is suitable to precision crane work. MODE II: By activating a switch, it is able to vary just the pump discharge by means of the grip throttle, while keeping engine speed fixed. Mode II is convenient for operations such as lifting magnet and bucket work, where the engine is normally run at full throttle. A specially-tailored pressure compensating valve — Utilized in hydraulic circuits to realize a good minute operation of two main, boom hoist and opt. luffing jib hoist drums. HYDRAULIC SYSTEM: System provided with three variable displacement axial piston pumps and one fixed displacement duplicate tandem gear pump for both independent and combined operations of all functions. Gear pump also used for system valves and cylinder controls. 2 Main/aux. crane hoist motors — Variable displacement axial piston motor with counterbalance valve and spring-applied/ hydraulically released multiple wet-disc type automatic brake as std. Boom hoist motor — Variable displacement axial piston type with counterbalance valve and spring-applied/hydraulically released multiple wet-disc type automatic brake. Luffing jib hoist drum motor — Optional extra; axial piston type with counterbalance valve and spring-applied/hydraulically released multiple wet-disc type automatic brake; available for luffing jib hoisting/lowering. Slewing motor — Two; axial piston type with springapplied/hydraulically released multiple wetdisc type brake; electrically controlled from instrument panel of operator's cab. Travel motors — Shoe-in design; axial piston motor with brake valve and spring-applied/hydraulically released multiple wet-disc type automatic brake. Oil cooler — Aluminum-make; located at a part of superstructure as separated from engine radiator together with an independent autocooling fan for better cooling efficiency and heat balance. Hydraulic oil reservoir — 450 liters capacity. Kind of hyd. oil — Standardized with ISO VG46 having viscosity ranging from 41.4 thru 50.6mm2/sec at 40°C. LOAD HOIST ASSEMBLY: Std.; front and rear main operating drums driven by independent hydraulic motor of bidirectional, variable displacement axial piston motor through 2-stage planetary reduction gear units powering the rope drum in either direction for hoisting and lowering load. Both of drums size in same dimension. Brakes — Spring-applied, power hydraulically released multiple wet-disc type automatic brake; provided within hyd. motor. Drums — One piece, parallel grooved lagging with locking ratchet wheel cast integral; involutesplined to the reduction gear unit shaft which is mounted on anti-friction bearing. Available to wind up 51m long cable of 28mm dia. at drum 1st layer. Drum locks — Electrically controlled pawl. Drum rollers — Optional extra; available for right cable winding onto drums. Drum rotation speed controller — Max. rotation speed can be tuned according to arbitrary value that is electrically controlled by dialing, and then varies pump discharge. Available on two main operating drums independently. Motor swash plate angle setting switch — Available to set motor swash plates of front/rear drum winch motors at a certain angle for easily sychronizing front and rear drum rotation speeds. BOOM HOIST ASSEMBLY: Twin-drum design; driven by single bidirectional, axial piston hydraulic motor through a 3-stage planetary reduction gear unit powering the rope drum in either direction for hoisting and lowering boom. Brake — Spring-applied, power hydraulically released multiple wet-disc type automatic brake. Drum — One piece, twin-design, parallel grooved lagging with locking ratchet wheel cast integral; bolted to planetary reduction gear unit outer case. Drum lock — Power hydraulically operated automatic pawl. Drum rotation speed controller — Max. rotation speed can be tuned according to arbitrary value that is electrically controlled by dialing, and then varies pump discharge. LUFFING JIB HOISTING MECHANISM: Optional extra; driven by bi-directional, axial piston hydraulic motor through 2-stage planetary reduction gear unit powering the rope drum in either direction for hoisting and lowering luffing jib; required when rear drum is used for liftwork with tower head top sheave machinery. Mounted on boom bottom section. Brake — Spring-applied, power hydraulically released multiple wet-disc type automatic brake; provided within hydraulic motor. Drum — One piece, parallel grooved lagging with locking ratchet wheel cast integral; bolted to planetary reduction gear unit outer case. Drum lock — Power hydraulically operated automatic pawl. Drum rotation speed controller — Max. rotation speed can be tuned according to arbitrary value that is electrically controlled by dialing, and then varies pump discharge. SLEWING: Driven by two units of bi-directional, axial piston hydraulic motors through 2 sets of planetary reduction gear unit powering slewing pinion. Slewing pinion meshes with internal teeth of slewing (ring) gear of turntable bearing inner race. Brakes — Spring-applied, power hydraulically released multiple wet-disc type; provided on each of hydraulic motor. Slewing speed controller — Max. slewing speed can be tuned according to arbitrary value that is electrically controlled by dialing, and then varies pump discharge. Lock — Mechanically operated drop pin. Speed — 1.5min.–1 <1.5rpm> OPERATOR’S CAB: A 2.3mm thickeness steel plate construction with 940mm wide and a stamped-androunded corner designs; acoustically treated, full-vision, cushion rubber mounted, wellventilated, full compartment, roomy operator’s cab with a large straighted front window with green-tinted safety glass; provided with an arrangement of “EPC” control / slewing lever, armchair control station, sunvisor, sunshade, rear-view mirrors, dual intermittent type window shield wipers with washer on both front and roof windows, sliding windows on both sides of cab, and slewing-link type sliding door. 3 Slewing-away mechanism — Provided as std; available to set a 3-meter overall width of superstructure for a good transport. Tilting mechanism — Power hydraulically tiltable cab is standrdized for a good upward visibility. Instrument panel — Contains engine monitoring lamps, graphic display panel of Load Moment Indicator, gauges & meter, warning lamps and other necessary controllers and switches. Operator’s seat — Full adjustable reclining seat with head rest and both R/H and L/H side arm rests. Air-conditioner — Provided as std.; built-in type full air-conditioner. Electric cab fan — Optional extra; wind-direction adjustable type. Microphone & loud-speaker — Optional extra; this is for operator’s convenience for loud speaking. Engine foot throttle — Optional extra; Available for right-hand foot control, with electrical control. Electric outlet — 24V; available in cab. Operator’s cab side step — Optional extra; Available for access ease to operator’s cab. Gripping bar — Provided as std. for cab side step. AM/FM radio — Provided as std. with clock. Fire extinguisher — Optional extra; powder type with 1kg capacity. MACHINERY CAB: Equipped with hinged doors on both sides for machinery access and inspection; affixed tape-type non-skid material on the roof. POWER UNIT: Make & Model Type Mitsubishi 6M70—TL Water-cooled, 4-cycle, direct injection, turbocharged, diesel w/automatic cooling fan No. of Cylinders Bore & Stroke Displacement Six (6) 130 mm × 150 mm 12,880 cc Rated Output 272 kW/2,000 min 〈370 ps/2,000 rpm〉 Maximum Torque 1,510 NÆm/1,600 min 〈154 kgf-m/1,600 rpm〉 Fuel Tank 500 liters —1 —1 The engine meets Stage/Tier 3 of current smoke emission regulations in Europe, America and Japan. A 272kW engine horsepower shown above is defined under a current international engine horsepower indication formura which includes necessary horsepower for engine alternator drive but excludes engine fan drive. A PORTABLE ENGINE-HYDRAULIC POWER PACK: Optional extra; available to supply power hydraulic to hydraulic cylinders as used as rear post backstops. Required when luffing jib att. CATWALKS: Optional extra; hitched in place along both sides of machinery cab. MACHINERY CAB RAILING: Optional extra; COUNTERWEIGHTS: Weighs 102.8ton consisting of a 22.4ton base weight and a 12-piece cast iron block of 80.4ton in its total. Counterweight self-removal device — Provided as std.; raises and lowers a 102.8ton full counterweight by a lifting mechanism with two power hyd. cylinders attached on the base weight. ELECTRICAL SYSTEM: 24-volt negative ground system; provided with two maintenance free 12-volt batteries. LIGHTING SYSTEM: Includes following lights. • Two 70 W working lights; • One 10 W interior cab light. REAR VIEW MIRRORS: Two; each provided on front-left and -right corners of superstructure. 4 Undercarriage LOWER FRAME: All-welded, precision machined, box type construction; provided with four tip blocks w/pins and lugs to hook and then assemble crawer side frames on. To mount turntable bearing, a machined surface is provided too. Hyd. removal joint-pins — Four; available to hold in place crawler side frames on lower frame with a face-contact design to bear reaction force of crawler side frame. And, four pins are each operated by hyd. cylinder thru remote control box shown in clause of “LOWER FRAME JACK-UP DEVICE” below. LOWER FRAME JACK-UP DEVICE: Contains four hydraulic jack cylinders attached on lower frame jack cylinder beams for disassembling/assembling ease of crawler side frames. Remote control box — Provided for control of lower frame jack cylinders and hyd. removal jointpins. Pontoon — All-welded construction; four pontoons each attached on outside of lower weight. CRAWLER SIDE FRAMES: All-welded, box type construction, precision machined; each provided with two steel plate hooks for an assembling ease on lower frame. Held in place by hydraulic removal heavy duty joint-pins provided on four tip blocks of lower frame. Crawler side steps — Provided at both ends of the frames for easy access to superstructure. LOWER WEIGHT: Weighs 18ton; made of cast iron. A 9ton each mounted on lower frame jack cylinder beams provided at front and rear of the lower frame DRIVE SPROCKETS: Cast steel, heat treated; one per side frame. Track drive sprocket assembly bolt-coupled to 3-stage planetary reduction gear unit outer case as an integral part of shoe-in type traction motor. Sealed between parts of rotation and non-rotation of the motor with floating seal. IDLER WHEELS: Cast steel, heat treated; one per side frame. Mounted on two bronze bushings with floating seals for lifetime lubrication. TRACK ROLLERS: Fifteen per side frame; each heat treated cast steel with double flange design. All rollers mounted on two bronze bushings with floating seals. CARRIER ROLLERS: Three per side frame; each heat treated cast steel with double flang design. All rollers mounted on bronze bushings with floating seals. TRACKS: Heat treated, self-cleaning, multiple hinged track shoes joined by full floating pins; 58 pcs. per side frame. Shoe width — 1,120mm wide as standard. Track adjustment — Manual adjustment device with oil jack and shim plate packs is standardized. Automatic track tension adjusting device — Optional extra; available instead of std. track adjustment to always keep track tension at optimum level by means of power hyd. cylinder thru idler wheel actuated by power hydraulic supplied from superstructure. TRAVEL AND STEERING: A bi-directional, shoe-in type axial piston hydraulic motor bolt-couples drive sprocket thru 3-stage planetary reduction gear unit outer case at each crawler side frame end for travel and steer. Straight-line travel (forward or reverse), pivot or differential turns, and counter-rotation for spin turns are available. Brake — Spring-applied, hydraulically released multiple wet-disc type automatic brake; located within hydraulic motor. Brakes automatically set when travel levers are in neutral or when engine is shut down. Travel speed — 1.1/0.5km/hr. (based on flat, level and firm supporting surface, and under the conditions that no load must be applied and front-end att. must be 15.25m basic boom only). Gradeability — 30% (17°) permissible based on basic machine without front-end attachment. Safety Devices LOAD MOMENT INDICATOR: This is a fully computerized automatic overload preventing system including total safe operation control system and meets EN Standards; provided with the designs of (1) no zero-point adjustment, (2) data input according to interface counter-indication/message on display panel, and (3) a graphic display panel with setting ease of viewing angle. Construction (standard version) — Comprises (1) load detecting device with amplifier, (2) boom angle detector, (3) computerized Micro Processing Unit (M.P.U.), and (4) graphic display panel. Functions — This system functions that if the lifting load reaches 90% of the rated one specified in the crane capacity chart, an intermittent pre-warning buzzer is given; if it is 100%, a warning is given by a continuous buzzer, and all peril side motions are automatically stopped. The machine, however, can be operated in safety side motions. Display panel design — A graphic display panel is designed, and it is able to input necessary operating conditions/data according to interface counter-indication/message on the display panel, and the display panel indicates ten and some kinds of the present lifting and working conditions/data like “lifting load”, “max. allowable lifting load”, “working radius”, “max. allowable working radius”, “boom angle”, “load ratio”, “boom/jib lengths”, “engine rpm” and so on when working. In addition, the display panel is provided with three warning indicators over “engine over-heat”, “hyd. oil over-temp.” and “brake oil over-temp.”. MAIN HOOK OVER-HOISTING LIMITER: Limit switch type. Available to prevent hook over-hoisting with functions of automatic drum braking with hydraulic lock, and warnings by an alarm. BOOM OVER-HOISTING AND -LOWERING LIMITER: Available in two kinds of devices; one is limit switch located on a part of boom foot for preventing boom over-hoisting, and the other is the safety function of the LMI available to automatically prevent boom over-hoisting and -lowering with the functions of automatic drum braking with hydraulic lock, and warnings by an alarm. Further boom protection from rapid boom over-hoist by hook over-hoist motion under mal-function of main hook over-hoisting limiter is available as one of functions of the LMI. BOOM BACKSTOPS: Dual; telescopic design with spring buffers. SECONDARY BOOM OVER-HOISTING LIMITER: Additional limit switch located on boom backstops; this is as a further safety device for redundant boom protection. 5 SLEW LOCK: Mechanically operated drop pin; available to firmly lock superstructure in four positions of facing front or rear or left or right to undercarriage. pressure, radiator coolant level, oil filter clogging, air filter clogging, water temp., contorol unit and glow plug.; provided on instrument panel. DRUM LOCKS: Electrically operated pawl locks is available on front and rear main drums while power hydraulically operated pawl lock is available on boom hoist drum with an automatic locking device as std. FRONT-END ATT. ERECTION MODE: This is an internal, integral function of the LMI. In the range out of crane working area, the LMI display panel automatically indicates “Now, out of crane working range” with a rigging instruction, and it is available to lift front-end att. off ground without the influence of LMI safety functions, and, after front-end att. is lifted over the range of crane working area, LMI safety function gets back automatically for safe erection work. This function is also available for the work of vice-versa. SLEWING BRAKE SAFETY CIRCUIT: Available not to start engine whenever slewing brake is off. BOOM ANGLE INDICATOR: Pendulum type; mounted on right-hand side of bottom section of crane main boom. HOOK LATCH: Provided on every kinds of hook to prevent out of place of cable from hook. LEVEL GAUGE: Bubble type; located on operator’s cab floor and a part of undercarriage. LEVER LOCKS: Provided on all control levers (except slewing lever) to lock levers in neutral. SLEWING ALARM: This is by buzzer, and flasher lamps located on both sides of machinery cab. SPEED SLOWDOWN DEVICE: This is for speed slowdown of hoisting and lowering motions of boom (and tower jib in case of luffing tower crane att.) which are available just before automatic stopping at both upper and lower side limits of boom/tower jib angle even though control lever(s) is still at hoisting/lowering position to prevent a shock. SLEWING BRAKE LAMP: Provided on operator’s cab instrument panel; this is available to confirm whether or not slewing brake is applied. SIGNAL HORN: Available as warning just before every kinds of motions are initiated. LOCK LEVER (FOOL PROOF SHUT-OFF LEVER): Located in the cab exit; this is available to automatically deactivate and lock hydraulic system. TRAVEL ALARM: An intermittent buzzer warns when travel motion is initiated. 6 ENGINE MONITORING LAMPS: Available to let operator warn engine abnormal conditions as to battery charge, lubrication oil LIFTING HEIGHT INDICATION DEVICE: Available to indicate lifting height above ground or depth below ground on display panel of the LMI. Also, hook hoisting speed slowdown function is available just before automatic stopping at a desired height under hook height setting before operation. LMI SAFETY CIRCUIT-OFF SWITCH: Available in key type for a good crane safety operation management without fail. TRAVEL DIRECTION ARROW: Attached each on crawler side frames. GAUGES & METER: Engine water temperature gauge, fuel gauge and hour-meter are provided on instrument panel. WARNING LAMPS: Available to let operator warn abnormal machine conditions as to pilot pressure and brake system of two main and opt. luffing jib hoist drums; provided on instrument panel. THREE COLOR PERCENTAGE INDICATOR: Optional extra; this is with three colors of Green, Yellow and Red. Each color indicates the load percentage to rated capacity; Green shows less than 90% as safety, Yellow shows 90 to 99% as marginal, and Red shows over 100% as over-loading. As further function, Red lamp comes on automatically when operator cuts off safety circuit of LMI absentmindedly. ANEMOMETER: Optional extra; recommended for luffing jib attachment. AUX. HOOK OVER-HOISTING LIMITER: Optional extra; this is available for auxiliary crane hoist with optional short jib and/or fly jib. Performs the same function as that of “Main hook over-hoisting limiter” mentioned before. In addition to the above, following safety devices are standard for luffing jib attachment. LUFFING JIB ANGLE DETECTOR: This is one of key safety device in a case of luffing jib attachment. LUFFING JIB LOAD DETECTOR: This is also important safety device when luffing towercrane attachment is required. LUFFING JIB OVER-HOISTING AND-LOWERING LIMITER: Performs all the same function as that of “Boom over-hoisting and - lowering limiter” stated before. LUFFING JIB BACKSTOPS: Dual; telescopic design with spring buffers. SECONDARY LUFFING JIB OVER-HOISTING LIMITER: Additional limit switch located on tower jib backstops; this is as a further safety device for redundant tower jib protection. LUFFING JIB HOIST DRUM LOCK: Provided with automatic pawl-locking device like boom hoist drum pawl-locking (if luffing jib hoist drum is optionally provided). REAR POST BACKSTOPS: Two power hydraulic cylinders are designed to easily set rear post position as necessary when assembling front post and luffing jib; power hydraulic is supplied to these cylinders by a portable engine-hydraulic power pack. LUFFING JIB HOOK OVER-HOISTING LIMITER: Performs the same function as that of “Main hook over-hoisting limiter” described before. Front-end Attachment CRANE BOOM: Lattice construction, round tubular main chords, alloy, hi-ten steel, with bracing of round steel tubing. Boom connections ........................................In-line pin connections at 2.10m deep and 2.10m wide. Basic boom ............................................. Two-piece, 15.24m basic length; 7.62m heavy-duty base and tapered top sections. Provided with boomfoot pin removal cylinders. Boom head machinery .................................Five head sheaves, and two guide sheaves mounted on anti-friction bearings of conventional non-sealed grease type. Six-hanger sheave block ............................Optional extra; pinned to boom head shaft. Sheaves each mounted on antifriction bearings of conventional non-sealed grease type. Required when lifting load exceeds 145ton, and available up to 275ton lift. ........................... Five-hanger sheave block Optional extra; pinned to boom head shaft. Sheaves each mounted on antifriction bearings of conventional non-sealed grease type. Required when lifting load exceeds 145ton, and available up to 250ton lift. Ultra heavy-duty boom extensions ..............Optional extra; available in 3.05m, 6.10m and 12.20m with pendants. Heavy-duty boom extension ........................Optional extra; available in 12.20m with pendants. Maximum boom length .................................91.45m meters. Note: All of ultra heavy- and heavy-duty boom extensions are designed with no intermediate diagonal bracing(s); the diagonal bracing is only designed at one of two picture frames. Accordingly, it is able to nest luffing jib extension into appropriate boom extension in length. FLY JIB: Optional extra; lattice construction, round tubular main chords, alloy, hi-ten steel, with bracing of round steel tubing having in-line pin connections at 1.0m deep and 1.0m wide, and jib head machinery with single sheave mounted on antifriction bearings of conventioral non-grease type. Provided with jib strut, jib backstops, and jib/boom guyline pendants. Mounted on 7.62m tapared top section, and available for light load lifting operation with less than 27ton with two-part hoist line. Single part hoist line is also available for a 13.5ton lift as max. Basic fly jib ...................................................Two-piece, 12.20m basic length; 6.10m base and top sections. Fly jib extensions .........................................Available in 6.10m length with pendants. Maximum fly jib length .................................36.55m. Boom plus fly jib length ...............................Max. 70.1m + 36.55m. SHORT JIB: Optional extra; all-welded construction having single sheave head machinery. Pinned to 7.62m tapered top section. BOOM LIVE MAST: A 7m long; all-welded, box construction. Mounted in front of upper revolving frame, and pins bridle frame with a 12-sheave machinery of a 21.0 D/d ratio for a 2x12-part boom hoist line. Raised by two power hyd. cylinders from transportation position to a certain working position as a short boom for self-assembling work as this mast is available to use for selfassembling of a whole machine without helper crane in cooperation with hydraulic counterweight self-removal device, and qucik-draw power hydraulic cylinder with hook attached onto the mast. In addition, a 2-large diameter single pendant rope of short length with plate link is pinned on top of the mast for easy connection with a 2-dual extender cables. MID-POINT SUSPENSION LINK: Optional extra; required when boom length exceeds 88.40m. 7 HOOK BLOCKS: 275/145t, five sheaves plus 5-hanger sheave block with duplex type hook ....Optional extra. 250/145t, five sheaves plus 5-hanger sheave block with duplex type hook ....Optional extra. 145t, five sheaves with duplex type hook(275t use) .........................................Optional extra. 145t, five sheaves with duplex type hook(250t use) .........................................Optional extra. 80t, three sheaves ..............................................................................................Optional extra. 35t, one sheave ..................................................................................................Optional extra. 13.5t, ball hook ...................................................................................................Optional extra. Notes: An 145t hook block is each available from 250/275t hook block by dismounting a 5-hanger sheave block. BAIL AND BRIDLE: All-welded construction; provided with larger sheaves of a 21.0 D/d ratio on both bail and bridle for 2×12-part boom hoist rope reeving. Bail pinned to upper revolving frame directly, and bridle pinned to boom live mast respectirely. And, pendant ropes bridge the gap between boom live mast and 7.62m tapered top section. DRUM DATA: (*"+, (" & ! "#$ %%& ' ( () "#$ %%& ' ( () - . $*% ( × ((* ' % & (( * (*"+, (" & %$"+, %$ # × ( // 0 . "#$ "" ' ( () (*"+, (" & Notes: 1. Line speed is based on drum first layer and rated engine rpm with no load. 2. Hoisting line speed varies under load and operating conditions. 3. Crane hoist applications of front and rear main drums shall be upon kind of front-end attachment. HOIST REEVING: CABLES: Front drum ..................................................P·S (19)+39×P·7, non-spin type, 28mm dia./450m long, breaking load 755kN (77.0t). Rear drum ...............................................Optional extra; P·S (19)+39×P·7, non-spin type, 28mm dia., breaking load 755kN (77.0t). Length depends on crane hoist applications as under: 1. Fly jib application..................................................350m. 2. Short jib application ..............................................190m. Boom hoist drum ......................................XP rope with construction of IWRC 6×P·WS (31), 22.4mm dia./320m long, breaking load 417kN (42.5t). Luffing jib hoist drum ..............................Optional extra; XP rope with construction of IWRC 6×P·WS (31), 28mm dia./210m long, breaking load 657kN (67.0t). 8 Liftcrane Capacities 275 metric tons ■WORKING MASS & GROUND CONTACT PRESSURE: Note: Working mass shown above is with 15.24m basic boom, 102.8ton counterweight, 18ton lower weight and optional 275t hook block. 9 Notes — Liftcrane capacities 1. Capacities included in these charts are the maximum allowable, and are based on machine standing level on firm supporting surface under ideal job conditions. 2. Capacities are in metric tons, and are rated in accordance with European EN13000 Standards in terms of machine stability and structural strength limitations; the figures surrounded by bold lines are based on factors other than those which would cause a tipping condition. 3.Capacities are based on freely suspended loads and make no allowance for such factors as the effect of wind, sudden stopping of loads, supporting surface conditions, and operating speeds. Operator must reduce load ratings to take such conditions into account. Deduction from rated capacities must be made for weight of hook block, weighted ball/hook, sling, spreader bar, or other suspended gear. Hook block weight is as follows: 275t ...........4.3ton 250t ..........3.7ton 145t ...........3.3ton (275t use) 145t ...........2.7ton (250t use) 80t .............1.4ton 35t ............0.9ton 13.5t ........0.62ton 4. All capacities are rated for 360° slewing. 5. Least stable rated condition is over the side. 6. An 102.8ton counterweight and 18.0ton lower weight are required for all capacities on this chart. 7. Attachment must be erected and lowered over the ends of the crawler mounting. 8. Main boom length must not exceed 91.45m. Maximum fly jib length permitted — 36.55m. Maximum boom plus fly jib combination length permitted — 70.1m+36.55m. Maximum boom length when mounting short jib is 88.40m. 9. Capacities when handling load off main boom head sheaves in case of mounting fly jib or short jib on top of boom are detailed; if required, please consult us or nearest distributor. 10. Boom combination shall be in accordance with manufacturer’s standard described here in “Boom Combination Diagram” of page 16. 10 SCX2800-2 SHORT JIB CAPACITIES: Max. 13.5ton Note: Jib capacities are almost equal to the figures made by the deduction of approx. 620kg from the liftcrane capacities for boom length up to 88.40m unless restricted by the maximum jib capacity shown above. As to the details, please consult us or nearest distributor. Short jib (Option) Fly Jib Capacities 27 metric tons 30 10 30 10 48.75 12.20 18.30 10 12.3 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 46.0 48.0 50.0 52.0 54.0 56.0 58.0 60.0 64.0 68.0 72.0 76.0 80.0 80.8 No. of part line 30 10 24.40 30 10 30.50 36.55 30 27.0/12.8 13.5/13.0 27.0 13.5 23.4/14.7 13.5/14.9 27.0 13.5 13.9/16.3 13.5/16.7 23.1 13.5 13.5/16.9 27.0 13.5 13.6 13.5 22.4 13.5 13.5 11.8/18.8 27.0 13.5 13.1 13.1 21.8 13.5 10.1/20.5 13.5 11.6 8.1/20.7 27.0 13.5 12.6 12.6 21.3 13.5 9.8 13.5 11.3 8.0 26.6 13.5 12.1 12.1 20.8 13.5 9.5 13.5 7.8/24.3 11.0 7.8 25.0 13.5 11.8 11.8 20.3 13.5 9.1 13.5 7.5 10.6 7.4 23.5 13.5 11.3 11.3 19.1 13.5 8.8 13.5 7.3 10.4 6.1/28.1 7.0 22.2 13.5 11.0 11.0 18.1 13.5 8.6 13.5 7.0 10.1 5.9 6.8 4.7/31.9 21.1 13.5 10.7 10.7 17.1 13.5 8.3 13.5 6.8 9.8 5.7 6.5 4.7 20.1 13.5 10.5 10.5 16.2 13.5 8.0 13.5 6.5 9.6 5.5 6.2 4.5 19.1 13.5 10.1 10.1 15.5 13.5 7.8 13.2 6.3 9.4 5.3 6.0 4.5 18.2 13.5 10.0 10.0 14.8 13.5 7.6 12.6 6.1 9.1 5.1 5.7 4.3 17.5 13.5 9.7 9.7 14.1 13.5 7.4 12.0 6.0 8.9 5.0 5.5 4.2 16.8 13.5 9.5 9.5 13.6 13.5 7.2 11.5 5.8 8.6 4.8 5.3 4.1 15.6 13.5 9.3 9.3 13.0 13.0 7.0 11.1 5.6 8.3 4.7 5.1 4.0 14.5 13.5 9.1 9.1 12.6 12.6 6.9 10.6 5.5 8.1 4.5 5.0 3.9 13.5 13.5 9.0 9.0 12.1 12.1 6.8 10.2 5.4 7.9 4.5 4.8 3.7 12.6 12.6 8.9 8.9 11.6 11.6 6.6 9.8 5.3 7.7 4.3 4.6 3.6 11.7 11.7 8.8 8.8 11.3 11.3 6.5 9.5 5.1 7.5 4.2 4.5 3.5 11.0 11.0 8.7 8.7 10.9 10.9 6.4 9.1 5.0 7.3 4.1 4.4 3.4 10.6/55.0 10.5/55.7 8.7/55.7 8.7 10.6 10.6 6.4 8.8 5.0 7.1 4.0 4.3 3.3 8.7/56.5 10.0 10.0 6.3 8.6 4.9 7.0 4.0 4.1 3.2 9.3 9.3 6.2 8.3 4.8 6.9 3.9 4.0 3.2 9.1/60.7 8.8/61.5 6.2/62.6 7.9 4.7 6.5 3.7 3.8 3.0 7.5/67.2 4.6 6.3 3.6 3.6 2.9 4.6/68.7 6.1 3.5 3.5 2.8 3.4 2.7 6.0/72.9 3.5/74.8 3.3/78.6 2.7 2.7 2 1 1 1 1 1 1 2 1 1 1 1 2 51.80 12.20 18.30 10 13.2 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 46.0 48.0 50.0 52.0 54.0 56.0 58.0 60.0 64.0 68.0 72.0 76.0 80.0 84.0 86.1 No.of part line 30 10 24.40 30 10 30.50 30 10 30 36.55 10 30 27.0 13.5/13.4 27.0 13.5 23.3/15.2 13.5/15.4 27.0 13.5 13.9/16.7 13.5/17.2 23.1 13.5 13.5/17.3 27.0 13.5 13.6 13.5 22.5 13.5 13.5 11.8/19.2 27.0 13.5 13.1 13.1 21.9 13.5 10.1/21.0 13.5 11.6 8.1/21.2 27.0 13.5 12.7 12.7 21.5 13.5 9.9 13.5 11.3 8.1 27.0 13.5 12.3 12.3 21.0 13.5 9.6 13.5 7.8/24.8 11.1 7.9 25.7 13.5 11.9 11.9 20.5 13.5 9.2 13.5 7.5 10.8 7.5 24.3 13.5 11.5 11.5 19.7 13.5 8.9 13.5 7.3 10.5 6.1/28.5 7.1 23.0 13.5 11.2 11.2 18.6 13.5 8.6 13.5 7.0 10.2 6.0 6.9 21.8 13.5 10.9 10.9 17.7 13.5 8.3 13.5 6.8 10.0 5.8 6.5 4.7/32.3 20.7 13.5 10.6 10.6 16.7 13.5 8.1 13.5 6.6 9.7 5.5 6.3 4.6 19.8 13.5 10.3 10.3 16.0 13.5 7.9 13.3 6.4 9.5 5.4 6.0 4.5 19.0 13.5 10.1 10.1 15.3 13.5 7.7 13.0 6.2 9.3 5.2 5.8 4.4 17.8 13.5 9.8 9.8 14.6 13.5 7.5 12.4 6.0 9.0 5.0 5.6 4.2 16.5 13.5 9.6 9.6 14.0 13.5 7.4 11.8 5.9 8.8 4.9 5.4 4.1 15.3 13.5 9.5 9.5 13.5 13.5 7.1 11.4 5.8 8.6 4.8 5.3 4.0 14.1 13.5 9.3 9.3 13.0 13.0 7.0 11.0 5.6 8.3 4.6 5.0 3.9 13.1 13.1 9.1 9.1 12.5 12.5 6.9 10.6 5.5 8.1 4.5 4.9 3.7 12.2 12.2 9.0 9.0 12.1 12.1 6.8 10.1 5.4 7.9 4.4 4.8 3.7 11.3 11.3 8.9 8.9 11.6 11.6 6.6 9.8 5.3 7.6 4.3 4.6 3.5 10.6 10.6 8.8 8.8 11.0 11.0 6.5 9.5 5.1 7.5 4.1 4.5 3.5 9.9 9.9 8.8 8.8 10.3 10.3 6.4 9.1 5.0 7.3 4.1 4.3 3.4 9.3/57.7 9.3 8.7 8.7 9.6 9.6 6.4 8.9 5.0 7.1 4.0 4.2 3.3 9.1/58.4 8.7/58.3 8.7/59.1 9.0 9.0 6.3 8.6 4.9 7.0 3.9 4.1 3.2 8.1/63.4 7.9 6.2 8.1 4.8 6.7 3.7 3.9 3.0 7.4 4.6 6.5 3.7 3.7 3.0 7.9/64.1 6.2/65.2 7.0/69.8 4.6/71.3 6.2 3.6 3.5 2.9 3.5 3.4 2.8 6.0/75.6 3.5/77.4 3.3 2.7 3.3/81.3 2.7/83.5 2 1 2 1 2 1 1 1 1 1 1 1 11 54.85 12.20 10 13.2 14.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 46.0 48.0 50.0 52.0 54.0 56.0 58.0 60.0 64.0 68.0 72.0 76.0 80.0 84.0 86.1 No.of part line 18.30 30 10 24.40 30 10 30 30.50 10 30 36.55 10 30 27.0/13.7 13.5/13.9 27.0 13.5 23.2/15.6 13.5/15.8 27.0 13.5 13.9/17.2 13.5/17.6 23.2 13.5 13.5/17.8 27.0 13.5 13.8 13.5 22.6 13.5 13.5 11.8/19.7 27.0 13.5 13.3 13.3 22.1 13.5 10.1/21.4 13.5 11.7 8.1/21.6 27.0 13.5 12.8 12.8 21.6 13.5 10.0 13.5 11.4 8.1 27.0 13.5 12.4 12.4 21.1 13.5 9.6 13.5 7.8/25.2 11.1 7.9 26.6 13.5 12.1 12.1 20.6 13.5 9.3 13.5 7.6 10.8 7.5 25.1 13.5 11.6 11.6 20.2 13.5 9.0 13.5 7.4 10.6 6.1/29.0 7.3 23.7 13.5 11.3 11.3 19.1 13.5 8.8 13.5 7.1 10.3 6.0 7.0 22.6 13.5 11.1 11.1 18.2 13.5 8.5 13.5 6.9 10.1 5.8 6.6 4.7/32.8 21.5 13.5 10.8 10.8 17.2 13.5 8.3 13.5 6.6 9.8 5.6 6.4 4.6 20.5 13.5 10.5 10.5 16.5 13.5 8.0 13.5 6.5 9.6 5.4 6.1 4.5 19.1 13.5 10.3 10.3 15.8 13.5 7.8 13.3 6.3 9.3 5.3 5.9 4.4 17.6 13.5 10.0 10.0 15.1 13.5 7.6 12.8 6.1 9.1 5.1 5.7 4.3 16.2 13.5 9.8 9.8 14.5 13.5 7.5 12.2 6.0 9.0 5.0 5.5 4.1 15.0 13.5 9.6 9.6 13.9 13.5 7.3 11.7 5.8 8.7 4.8 5.4 4.0 13.8 13.5 9.5 9.5 13.4 13.4 7.1 11.3 5.6 8.5 4.6 5.1 3.9 12.8 12.8 9.3 9.3 12.9 12.9 7.0 10.8 5.5 8.3 4.5 5.0 3.8 11.8 11.8 9.1 9.1 12.3 12.3 6.9 10.5 5.4 8.0 4.5 4.9 3.7 11.0 11.0 9.0 9.0 11.5 11.5 6.7 10.1 5.3 7.8 4.4 4.7 3.6 10.3 10.3 8.9 8.9 10.6 10.6 6.6 9.8 5.2 7.6 4.3 4.5 3.5 9.5 9.5 8.8 8.8 9.9 9.9 6.5 9.5 5.1 7.5 4.1 4.4 3.4 8.8 8.8 8.8 8.8 9.3 9.3 6.4 9.1 5.0 7.3 4.0 4.3 3.4 8.3 8.3 8.4 8.4 8.6 8.6 6.4 8.9 5.0 7.1 4.0 4.2 3.2 8.2/60.3 8.0/61.0 8.1/60.9 8.1/61.7 7.5 7.5 6.2 8.1 4.8 6.9 3.8 4.0 3.1 7.0 4.7 6.5 3.7 3.8 3.0 7.0/66.0 6.7/66.7 6.2/67.8 6.1 4.6 6.4 3.6 3.6 2.9 6.0/72.5 4.6/73.9 3.5 3.5 2.8 5.6 3.5 3.4 2.7 5.2/78.2 3.2/83.9 2.7 2.7 1 2 1 1 1 1 1 1 2 2 1 1 1 57.90 12.20 10 14.1 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 46.0 48.0 50.0 52.0 54.0 56.0 58.0 60.0 64.0 68.0 72.0 76.0 80.0 84.0 88.0 91.4 No.of part line 18.30 30 10 24.40 30 10 30 30.50 10 30 36.55 10 30 27.0 13.5/14.3 27.0 13.5 13.8/17.6 23.2/16.1 13.5/16.3 27.0 13.5 13.7 13.5/18.1 22.7 13.5 13.5/18.2 27.0 13.5 13.4 13.4 22.2 13.5 10.1/21.9 13.5 11.8/20.1 27.0 13.5 13.0 13.0 21.7 13.5 10.1 13.5 11.5 8.1/22.1 27.0 13.5 12.6 12.6 21.3 13.5 9.7 13.5 7.7/25.7 11.1 8.0 27.0 13.5 12.1 12.1 20.8 13.5 9.4 13.5 7.6 10.9 7.6 25.8 13.5 11.8 11.8 20.4 13.5 9.1 13.5 7.4 10.6 6.1/29.5 7.4 24.5 13.5 11.5 11.5 19.6 13.5 8.8 13.5 7.1 10.4 6.0 7.0 23.2 13.5 11.2 11.2 18.7 13.5 8.6 13.5 7.0 10.1 5.8 6.8 4.7/33.2 22.1 13.5 10.9 10.9 17.7 13.5 8.3 13.5 6.8 10.0 5.6 6.5 4.6 20.6 13.5 10.6 10.6 17.0 13.5 8.1 13.5 6.5 9.7 5.5 6.3 4.5 18.9 13.5 10.4 10.4 16.2 13.5 7.9 13.4 6.4 9.5 5.3 6.0 4.4 17.3 13.5 10.1 10.1 15.5 13.5 7.7 13.1 6.2 9.3 5.1 5.8 4.3 16.0 13.5 10.0 10.0 14.9 13.5 7.5 12.6 6.0 9.1 5.0 5.6 4.1 14.7 13.5 9.8 9.8 14.3 13.5 7.4 12.1 5.9 8.8 4.9 5.4 4.0 13.6 13.5 9.6 9.6 13.8 13.5 7.2 11.6 5.8 8.6 4.8 5.3 4.0 12.6 12.6 9.4 9.4 13.1 13.1 7.0 11.1 5.6 8.4 4.6 5.1 3.9 11.6 11.6 9.3 9.3 12.1 12.1 7.0 10.8 5.5 8.1 4.5 5.0 3.7 10.8 10.8 9.1 9.1 11.2 11.2 6.8 10.4 5.4 8.0 4.4 4.8 3.7 10.0 10.0 9.0 9.0 10.5 10.5 6.7 10.1 5.3 7.8 4.3 4.6 3.5 9.3 9.3 8.9 8.9 9.7 9.7 6.6 9.8 5.1 7.6 4.2 4.5 3.5 8.6 8.6 8.8 8.8 9.1 9.1 6.5 9.5 5.1 7.4 4.1 4.4 3.4 8.1 8.1 8.2 8.2 8.4 8.4 6.4 9.0 5.0 7.3 4.0 4.3 3.3 7.3/62.9 7.1/63.6 7.1/63.6 7.0 7.3 7.3 6.3 7.9 4.9 7.0 3.9 4.0 3.2 6.8/64.4 6.4 6.4 6.2 6.8 4.8 6.7 3.7 3.9 3.0 6.0 4.6 6.2 3.7 3.7 2.9 6.2/68.7 6.2/69.4 6.1/70.5 5.4/75.1 4.6 5.4 3.5 3.5 2.9 3.5 3.4 2.7 4.6/76.6 4.7 3.3 2.7 4.5/80.8 3.5/82.7 3.2/86.6 2.7 2.7/88.8 1 2 1 1 1 1 1 1 2 2 1 1 1 60.95 12.20 10 14.1 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 46.0 48.0 50.0 52.0 54.0 56.0 58.0 60.0 64.0 68.0 72.0 76.0 80.0 84.0 88.0 91.4 No.of part line 12 18.30 30 10 24.40 30 10 30 30.50 10 30 36.55 10 30 27.0/14.6 13.5/14.8 27.0 13.5 23.2/16.5 13.5/16.7 27.0 13.5 13.8/18.1 13.5/18.5 22.8 13.5 13.5/18.7 27.0 13.5 13.5 13.5 22.3 13.5 13.5 11.7/20.6 27.0 13.5 13.1 13.1 21.8 13.5 10.1/22.3 13.5 11.5 8.1/22.5 27.0 13.5 12.6 12.6 21.4 13.5 9.8 13.5 11.3 8.0 27.0 13.5 12.3 12.3 21.0 13.5 9.5 13.5 7.7/26.1 11.0 7.8 26.5 13.5 12.0 12.0 20.6 13.5 9.2 13.5 7.5 10.7 6.0/29.9 7.5 25.2 13.5 11.6 11.6 20.1 13.5 8.9 13.5 7.3 10.5 6.0 7.4 23.9 13.5 11.3 11.3 19.1 13.5 8.6 13.5 7.0 10.2 5.9 7.2 4.9/33.7 22.3 13.5 11.1 11.1 18.2 13.5 8.5 13.5 6.8 10.0 5.7 7.0 4.9 20.3 13.5 10.8 10.8 17.4 13.5 8.2 13.5 6.6 9.8 5.5 6.9 4.6 18.7 13.5 10.6 10.6 16.7 13.5 8.0 13.5 6.5 9.6 5.4 6.6 4.5 17.1 13.5 10.3 10.3 16.0 13.5 7.8 13.3 6.3 9.3 5.2 6.6 4.4 15.7 13.5 10.1 10.1 15.3 13.5 7.6 12.8 6.1 9.1 5.0 6.4 4.3 14.5 13.5 9.9 9.9 14.8 13.5 7.5 12.3 6.0 9.0 4.9 6.2 4.1 13.3 13.5 9.7 9.7 13.8 13.5 7.3 11.9 5.8 8.8 4.8 6.0 4.0 12.3 12.3 9.6 9.6 12.8 12.8 7.1 11.5 5.7 8.6 4.6 6.0 3.9 11.3 11.3 9.4 9.4 11.8 11.8 7.0 11.1 5.5 8.4 4.5 5.8 3.8 10.5 10.5 9.3 9.3 11.0 11.0 6.9 10.7 5.5 8.1 4.5 5.6 3.7 9.7 9.7 9.1 9.1 10.1 10.1 6.8 10.3 5.4 8.0 4.4 5.5 3.6 9.0 9.0 9.0 9.0 9.4 9.4 6.6 10.0 5.3 7.8 4.3 5.4 3.5 8.3 8.3 8.6 8.6 8.8 8.8 6.5 9.3 5.1 7.6 4.1 5.2 3.4 7.7 7.7 7.9 7.9 8.1 8.1 6.5 8.7 5.0 7.5 4.1 5.0 3.4 6.6 6.6 6.8 6.8 7.0 7.0 6.4 7.5 4.9 7.1 4.0 4.8 3.2 6.3/65.6 6.0/66.3 6.2/66.2 6.0/67.0 6.0 6.0 6.2 6.5 4.8 6.8 3.8 4.6 3.0 5.6 4.7 5.9 3.7 4.4 3.0 5.3/71.3 5.1 5.5 4.9 4.6 5.1 3.6 4.2 2.9 5.3/73.1 4.5/77.7 4.5/79.2 3.5 4.0 2.8 4.4 3.5 3.9 2.7 3.9/83.5 3.5/85.3 3.4 2.7 3.2/89.2 2.7 1 2 1 1 1 1 1 1 2 2 1 1 1 64.00 12.20 18.30 10 15.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 46.0 48.0 50.0 52.0 54.0 56.0 58.0 60.0 64.0 68.0 72.0 76.0 80.0 84.0 88.0 92.0 96.0 96.7 No.of part line 30 10 24.40 30 10 30.50 30 10 36.55 30 10 30 27.0 13.5/15.2 27.0 13.5 23.1/17.0 13.5/17.2 27.0 13.5 13.8/18.5 13.5/19.0 22.9 13.5 13.5/19.1 27.0 13.5 13.6 13.5 22.4 13.5 13.5 11.7/21.0 27.0 13.5 13.1 13.1 22.0 13.5 10.1/22.8 13.5 11.6 8.1/23.0 27.0 13.5 12.8 12.8 21.5 13.5 9.8 13.5 11.3 8.0 27.0 13.5 12.4 12.4 21.1 13.5 9.6 13.5 7.7/26.6 11.1 7.8 27.0 13.5 12.1 12.1 20.7 13.5 9.3 13.5 7.5 10.8 7.6 25.8 13.5 11.8 11.8 20.2 13.5 9.0 13.5 7.3 10.6 6.0/30.4 7.4 23.8 13.5 11.5 11.5 19.6 13.5 8.8 13.5 7.0 10.3 5.9 7.3 21.9 13.5 11.2 11.2 18.7 13.5 8.5 13.5 6.9 10.1 5.7 7.0 4.9/34.1 20.1 13.5 10.9 10.9 17.8 13.5 8.3 13.5 6.7 9.8 5.5 6.9 4.7 18.3 13.5 10.6 10.6 17.1 13.5 8.1 13.5 6.5 9.6 5.4 6.7 4.5 16.7 13.5 10.5 10.5 16.4 13.5 7.9 13.4 6.4 9.5 5.3 6.5 4.4 15.3 13.5 10.3 10.3 15.8 13.5 7.8 13.1 6.1 9.3 5.1 6.4 4.3 14.1 13.5 10.1 10.1 14.6 13.5 7.5 12.7 6.0 9.1 5.0 6.3 4.1 13.0 13.0 9.8 9.8 13.5 13.5 7.4 12.2 5.9 8.8 4.9 6.1 4.0 12.0 12.0 9.7 9.7 12.4 12.4 7.3 11.8 5.8 8.7 4.7 6.0 4.0 11.0 11.0 9.5 9.5 11.5 11.5 7.1 11.3 5.6 8.5 4.6 5.9 3.8 10.1 10.1 9.3 9.3 10.6 10.6 7.0 11.0 5.5 8.4 4.5 5.7 3.7 9.3 9.3 9.3 9.3 9.8 9.8 6.9 10.5 5.4 8.2 4.4 5.5 3.7 8.6 8.6 9.0 9.0 9.1 9.1 6.8 9.7 5.3 8.0 4.3 5.5 3.5 8.0 8.0 8.3 8.3 8.4 8.4 6.6 9.1 5.2 7.8 4.2 5.3 3.5 7.4 7.4 7.6 7.6 7.8 7.8 6.5 8.4 5.1 7.5 4.1 5.2 3.4 6.3 6.3 6.5 6.5 6.6 6.6 6.4 7.2 5.0 7.3 4.0 4.9 3.2 5.3 5.3 5.4 5.4 5.6 5.6 6.2 6.2 4.9 6.5 3.9 4.6 3.1 5.3/68.2 5.2/68.9 5.2/68.9 5.1/69.7 5.3 4.7 5.5 3.7 4.5 3.0 4.8 4.8 5.3 4.5 4.6 4.8 3.7 4.3 2.9 4.5/73.9 4.3/74.7 4.4/75.8 3.9 3.5 4.1 2.8 4.0 4.0 3.5 3.6 2.7 3.7/80.4 3.7/81.9 3.4 3.0 3.0 2.7 3.1/86.1 2.5/91.8 2.7 2.5/94.0 1 2 2 1 2 1 1 1 1 30 10 1 1 1 30 10 1 67.05 12.20 18.30 10 15.0 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 46.0 48.0 50.0 52.0 54.0 56.0 58.0 60.0 64.0 68.0 72.0 76.0 80.0 84.0 88.0 92.0 96.0 96.7 No.of part line 30 10 24.40 30 10 30.50 36.55 30 27.0/15.5 13.5/15.7 27.0 13.5 23.2/17.4 13.5/17.6 27.0 13.5 13.8/19.0 13.5/19.4 23.1 13.5 13.5/19.6 27.0 13.5 13.7 13.5 22.6 13.5 13.5 11.6/21.5 27.0 13.5 13.3 13.3 22.1 13.5 10.1/23.2 13.5 11.6 8.1/23.4 27.0 13.5 12.9 12.9 21.7 13.5 9.9 13.5 11.3 8.1 27.0 13.5 12.5 12.5 21.2 13.5 9.6 13.5 7.7/27.0 11.1 7.9 26.2 13.5 12.2 12.2 20.8 13.5 9.3 13.5 7.5 10.8 7.6 25.1 13.5 11.8 11.8 20.4 13.5 9.1 13.5 7.4 10.6 6.0/30.8 7.3 23.2 13.5 11.6 11.6 20.0 13.5 8.8 13.5 7.1 10.4 6.0 7.0 21.2 13.5 11.3 11.3 19.1 13.5 8.6 13.5 6.9 10.1 5.8 6.8 4.6/34.6 19.5 13.5 11.1 11.1 18.3 13.5 8.4 13.5 6.8 10.0 5.6 6.5 4.5 17.9 13.5 10.8 10.8 17.5 13.5 8.2 13.5 6.5 9.8 5.5 6.3 4.5 16.3 13.5 10.6 10.6 16.8 13.5 8.0 13.5 6.4 9.6 5.3 6.1 4.4 15.0 13.5 10.3 10.3 15.5 13.5 7.8 13.3 6.3 9.3 5.1 5.9 4.3 13.7 13.5 10.1 10.1 14.3 13.5 7.6 13.0 6.1 9.1 5.0 5.7 4.1 12.6 12.6 10.0 10.0 13.1 13.1 7.5 12.5 6.0 9.0 4.9 5.5 4.0 11.6 11.6 9.8 9.8 12.1 12.1 7.4 12.1 5.8 8.8 4.8 5.4 4.0 10.6 10.6 9.6 9.6 11.1 11.1 7.2 11.6 5.7 8.6 4.6 5.2 3.9 9.8 9.8 9.5 9.5 10.2 10.2 7.1 11.0 5.6 8.4 4.5 5.0 3.7 9.0 9.0 9.3 9.3 9.4 9.4 7.0 10.1 5.5 8.2 4.5 4.9 3.7 8.3 8.3 8.6 8.6 8.6 8.6 6.9 9.3 5.4 8.0 4.4 4.8 3.6 7.5 7.5 7.9 7.9 8.0 8.0 6.8 8.6 5.3 7.8 4.3 4.6 3.5 7.0 7.0 7.2 7.2 7.4 7.4 6.6 8.0 5.2 7.6 4.1 4.5 3.4 5.9 5.9 6.0 6.0 6.2 6.2 6.5 6.9 5.0 7.1 4.0 4.3 3.2 4.9 4.9 5.0 5.0 5.3 5.3 5.9 5.9 4.9 6.1 3.9 4.1 3.2 4.3/70.9 4.2/71.6 4.3/71.5 4.1 5.0 4.8 5.2 3.7 3.9 3.0 4.4 4.4 4.9 4.0/72.3 4.1 4.5 4.4 3.7 3.7 3.0 3.7 4.0 3.7 3.5 3.6 3.6 2.9 3.7 3.7 3.5/76.6 3.5/77.3 3.5/78.4 3.4 3.2 2.8 3.0/83.0 3.0 3.0 2.7 2.7 2.7 2.9/84.5 2.5 2.2 2.4/88.8 2.3/90.6 2.5 1.8/94.5 1.9 1.8 1 2 1 1 1 1 1 1 2 2 1 1 1 70.10 12.20 18.30 10 15.9 16.0 18.0 20.0 22.0 24.0 26.0 28.0 30.0 32.0 34.0 36.0 38.0 40.0 42.0 44.0 46.0 48.0 50.0 52.0 54.0 56.0 58.0 60.0 64.0 68.0 72.0 76.0 80.0 84.0 88.0 92.0 96.0 No.of part line 30 10 24.40 30 27.0 27.0 13.5/16.1 23.0/17.9 27.0 13.5 13.8/19.4 13.5/19.9 22.9 13.5/18.1 27.0 13.5 13.8 13.5 22.6 13.5 27.0 13.5 13.3 13.3 22.1 13.5 10.0/23.7 26.1 13.5 13.0 13.0 21.7 13.5 10.0 24.8 13.5 12.6 12.6 21.2 13.5 9.6 23.7 13.5 12.3 12.3 20.9 13.5 9.4 22.6 13.5 12.0 12.0 20.5 13.5 9.1 21.6 13.5 11.7 11.7 20.2 13.5 8.9 20.6 13.5 11.4 11.4 19.6 13.5 8.7 19.2 13.5 11.1 11.1 18.7 13.5 8.5 17.7 13.5 11.0 11.0 17.8 13.5 8.3 16.3 13.5 10.7 10.7 16.6 13.5 8.1 14.9 13.5 10.5 10.5 15.3 13.5 7.9 13.6 13.5 10.3 10.3 14.1 13.5 7.8 12.5 12.5 10.1 10.1 13.0 13.0 7.6 11.5 11.5 9.9 9.9 12.0 12.0 7.5 10.6 10.6 9.8 9.8 11.0 11.0 7.3 9.6 9.6 9.6 9.6 10.1 10.1 7.1 8.8 8.8 9.3 9.3 9.3 9.3 7.0 8.1 8.1 8.5 8.5 8.6 8.6 6.9 7.5 7.5 7.8 7.8 7.9 7.9 6.8 6.9 6.9 7.1 7.1 7.3 7.3 6.7 5.7 5.7 6.0 6.0 6.1 6.1 6.5 4.8 4.8 5.0 5.0 5.1 5.1 5.8 3.9 3.9 4.0 4.0 4.3 4.3 4.8 3.7/73.5 3.5/74.2 3.6/74.1 3.4/74.9 3.5 4.0 3.5 3.2 3.0/79.2 2.8/79.9 3.0/81.0 2 1 2 1 2 1 1 10 30 30.50 10 30 36.55 10 30 13.5 11.6/21.9 13.5 11.6 8.1/23.9 13.5 11.3 8.1 13.5 7.6/27.5 11.1 7.9 13.5 7.6 10.9 7.6 13.5 7.4 10.6 6.0/31.3 7.4 13.5 7.1 10.5 6.0 7.1 13.5 7.0 10.2 5.8 6.9 4.6/35.0 13.5 6.8 10.0 5.6 6.6 4.6 13.5 6.6 9.8 5.5 6.4 4.5 13.5 6.5 9.6 5.3 6.1 4.4 13.5 6.3 9.5 5.2 6.0 4.3 13.2 6.1 9.3 5.0 5.8 4.1 12.8 6.0 9.1 4.9 5.6 4.1 12.3 5.9 8.9 4.8 5.5 4.0 11.8 5.8 8.7 4.7 5.3 3.9 10.8 5.6 8.5 4.6 5.1 3.8 10.1 5.5 8.3 4.5 5.0 3.7 9.3 5.5 8.1 4.4 4.9 3.6 8.6 5.4 8.0 4.3 4.7 3.5 7.9 5.3 7.8 4.2 4.6 3.5 6.8 5.1 7.0 4.0 4.4 3.3 5.7 5.0 6.0 4.0 4.1 3.2 4.8 4.8 5.1 3.8 4.0 3.0 4.0 4.5 4.3 3.7 3.8 3.0 3.3 3.6 3.7 2.9 3.7 3.5 3.4 3.1 2.8 2.7 2.9 2.9 2.7 2.5 2.7 2.5/85.7 2.4/87.1 2.4 2.0 2.0 1.9/91.4 2.4 1.9/93.2 1.8/94.0 1.8 1 1 1 1 1 1 13 Notes — Fly jib capacities 1. Capacities included in these charts are the maximum allowable, and are based on machine standing level on firm supporting surface under ideal job conditions. 2. Capacities are in metric tons, and are rated in accordance with European EN13000 Standards in terms of machine stability and structural strength limitations; the figures surrounded by bold lines are based on factors other than those which would cause a tipping condition. 3.Capacities are based on freely suspended loads and make no allowance for such factors as the effect of wind, sudden stopping of loads, supporting surface conditions, and operating speeds. Operator must reduce load ratings to take such conditions into account. Deduction from rated capacities must be made for weight of hook block, weighted ball/hook, sling, spreader bar, or other suspended gear. Hook block weight is as follows: 35t .............0.9ton 13.5t .........0.62ton 4. All capacities are rated for 360° slewing. 5. Least stable rated condition is over the side. 6. An 102.8ton counterweight and 18.0ton lower weight are required for all capacities on these charts. 7. Attachment must be erected and lowered over the ends of the crawler mounting. 8. Maximum fly jib length permitted — 36.55m. Maximum boom plus fly jib combination length permitted — 70.1m+36.55m. 9. Capacities when handling load off main boom head sheaves in case of mounting fly jibon top of boom are detailed; if required, please consult us or nearest distributor. 14 Liftcrane Working Ranges 15 Boom Combination Diagram Boom length (m) Boom length (m) Boom combination Boom combination 7.6 15.25 18.30 6UH 7.6 12UH 7.6 3UH 6UH 24.40 7.6 3UH 7.6 12UH 7.6 12UH 12H 7.6 6UH 7.6 6UH 6UH 6UH 12UH 7.6 3UH 7.6 12UH 12UH 12UH 7.6 12UH 12H 7.6 54.85 7.6 3UH 7.6 21.35 6UH 51.80 7.6 7.6 7.6 6UH 57.90 7.6 60.95 7.6 3UH 7.6 7.6 6UH 12UH 12UH 6UH 6UH 12UH 6UH 7.6 12H 12UH 7.6 12H 12UH 12UH 12H 7.6 12UH 12H 12H 7.6 64.00 27.45 7.6 12UH 7.6 7.6 3UH 6UH 6UH 7.6 30.50 7.6 12UH 7.6 3UH 6UH 6UH 12UH 12UH 12H 7.6 12UH 12H 12H 7.6 67.05 33.50 7.6 36.55 7.6 3UH 7.6 7.6 12UH 7.6 3UH 6UH 6UH 7.6 12UH 6UH 7.6 12UH 6UH 12UH 7.6 3UH 70.10 7.6 73.15 7.6 3UH 7.6 12UH 7.6 39.60 12UH 6UH 6UH 6UH 12UH 12UH 6UH 12H 12UH 7.6 12H 12H 7.6 12H 12UH 12UH 12H 12H 7.6 12UH 12H 12H 12H 7.6 76.20 12UH 7.6 7.6 3UH 6UH 7.6 12UH 6UH 7.6 12UH 42.65 7.6 12UH 7.6 3UH 6UH 6UH 12UH 12UH 12H 12H 7.6 12UH 12H 12H 12H 7.6 79.25 7.6 3UH 45.70 7.6 48.75 7.6 3UH 12UH 6UH 6UH 12UH 12UH 12UH 12UH 7.6 3UH 7.6 12UH 7.6 12UH 7.6 82.30 7.6 85.35 7.6 3UH 88.40 7.6 91.45 7.6 3UH 6UH 12UH 6UH 6UH 12UH 6UH 6UH 12UH 6UH 12H 12UH 12UH 12UH 12H 12H 12UH 12H 12H 12UH 12H 7.6 12H 7.6 12H 12H 7.6 12H 12H 12H 7.6 Note: 1. The meanings of figures and symbols shown above are as follows: 7.6 7.6 : 7.62m HD base section : 7.62m HD tapered top section 2. A star mark ( 3UH : 3.05m Ultra HD boom extension 12UH 6UH : 6.10m Ultra HD boom extension 12H : 12.0m Ultra HD boom extension : 12.0m HD boom extension ) indicates manufacturer's recommended boom configuration in a consideration that it is able to set boom length in the pitch of 3.05 meters from its maximum length; other boom configuration with no star mark ( is not able to do such an arrangement of boom length. 16 ) General Dimensions $"% ! "# "" Note: The above general arrangement is under liftcrane application with 15.25m basic boom, and optional 275t hook block. 17 Transport Data Dimensions(mm) Mass(kg) 2 !" ) !! * + , + . / ) &' + $ ! '+ .&0 ! '+ , 1 !" /+ Q'ty Description 2 !" ) !! * + , + . / ) &' + $ ! '+ .&0 ! '+ 32 + + 18 3 !" #$ %&'( 32 Dimensions(mm) Mass(kg) Q'ty Description + ! + " + #$ %& /* ' +, , ,, * * - . ' , #$ %& ()* +# 19 Description Q'ty Dimensions(mm) Mass(kg) # $% &&' () * ! )%+! , *- # "# " ! ! ! ! 20 Q'ty $% & ' ( ! " # Dimensions(mm) $% & ( Mass(kg) Description ) $% & + , ! " # , ! " # , -" ." ( ' / * ) ( " & * * * 0 1 21 Description Q'ty Dimensions(mm) " " " + , $ Mass(kg) % & ! " " " # $ ' ' " # $ ( ) " ' "*" 22 " " % & Description Q'ty Dimensions(mm) - % $ -% %( ) * Mass(kg) & %- #( #( ) * +! , ' . / % ' & -% '' %' % % ( &# - ) * 0/ %' % # &# ' ) * 0/ '# %' * ) * % ' %(& $ . / ! !! " " 23 Standard and Optional Equipment Standard equipment Superstructure 24 ¡Mitsubishi 6M70-TL diesel engine with a 272kW <370ps> rated output; ¡Hydraulic system with three variable displacement axial piston pumps and one fixed displacement duplicate tandem gear pump; provided with an aluminum-make independent oil cooler; ¡Control system with one each of quadruplicate and triplicate tandem valves and pilot-operated armchair single axis control levers; provided with motorcycle type “EPC” controller (easyprecise-minute engine rpm and hyd. pump oil flow control device), and specially-tailored pressure compensating valves. In addition, drum rotation speed control is desighed on; ¡Front and rear main operating drum winches of 245kN<25t> line pull with 596mm dia. drum lagging driven by independent variable hyd. motor; each provided with multiple wet-disc type automatic brake with no free-fall function; ¡Boom hoist mechanism with a twin-drum design driven by a hyd. motor with automatic brakes; provided with drum rotation speed control design; ¡Slewing mechanism with heavy-duty turntable bearing; driven by two hyd. motors w/springapplied, power hydraulically released multiple wet-disc brakes; provided with speed control design; ¡Bail frame with a 10-sheave machinery and single center sheave; pinned to a rear part of upper revolving frame; ¡940mm wide, full-vision operator’s cab with a stamped-and-rounded corner design and large front window; provided with an arrangement of armchair operator control station and instrument panel. Slewing-away and tilting mechanisms, and air-conditioner are provided too; ¡102.8ton counterweight; provided with a selfremoval device for full weight; ¡Machinery cab with hinged doors; ¡24-volt electrical system with two 12-volt batteries; ¡Lighting system: • Two working lights; • One interior cab light; ¡Rear view mirrors: ¡Accessories; • AM/FM radio w/clock; • Engine hourmeter; • Engine tachometer;indicated on display panel of LMI; • Fuel gauge; • Eng. water temp. gauge; • Engine over-heat indicator; available on display panel of LMI; • Hyd. oil over-temp. indicator; available on display panel of LMI; • 24V electric outlet; • Dual, intermittent window shield wipers with washers; available on both front and roof windows; • Cigar lighter; • Ashtray; • Book holder; • Sunvisor; • Sunshade; • Cup holder; • Non-skid surfaces; • Cab floor mat; ¡Cab front step; ¡Cab side step; ¡Gripping bar (for cab side step); ¡Under-cover (under engine bed); ¡Centralized lubrication system (for live mast and slewing circle). Optional equipment ¡Tower head section sheave machinery; ¡Luffing jib hoisting mechamism; ¡Drum rollers; available on front/rear main drums; ¡Catwalks, along both sides of machinery cab; ¡Machinery cab railing; ¡Working light; ¡Re-fuel pump; ¡Engine foot throttle; ¡Microphone & loud speaker; ¡Fire extinguisher; ¡Electric cab fan; ¡Add. air cleaner element; ¡Reeving winch; ¡Portable engine-hydraulic power pack; required when luffing jib att. Standard equipment Optional equipment Undercarriage ¡7,520mm width by 9,045mm long crawler lower with removable crawler side frames; provided with four of tip blocks with pins, lugs and hyd. joint-pin removal cylinders; ¡Crawler drive units with shoe-in type traction motor with wet-disc type automatic brakes; ¡Lower frame jack-up device w/4-vertical hyd. jack-up cylinder and remote control unit; ¡1,120mm wide track shoes; ¡Manual track tension adjusting devices; ¡18ton lower weight; ¡Lifetime lubricated track lower; ¡Crawler side steps. ¡Automatic track tension adjusting device, i/o manual one as std. Liftcrane Att. ¡15.25m basic crane boom; 7.62m base section, and 7.62m tapered top section w/five head sheaves, and two guide sheaves; provided with boom foot pin removal cylinders; ¡Boom live mast and bridle frame with a 12sheave machinery; provided with “quick draw” power hyd. cylinder; ¡Main crane hoist cable; 28mm dia./450m long; ¡Boom hoist cable; 22.4mm dia./320m long. ¡3.05m ultra heavy-duty boom extension; ¡6.10m ultra heavy-duty boom extension; ¡12.20m ultra heavy-duty boom extension; ¡12.20m heavy-duty boom extension; ¡12.20m basic fly jib; 6.10m base and top sections with jib strut and boom / jib quyline pendants; ¡6.10m fly jib extension; ¡Short jib; ¡275/145t duplex type hook (145t hook with 5 sheaves hanger block); ¡250/145t duplex type hook (145t hook with 5 sheaves hanger block); ¡80t hook block; ¡35t hook block; ¡13.5t ball hook; ¡Six-hanger sheave block (pinned to boom head shaft); required together with 275t hook block when lifting load exceeds 145ton, and available up to 275ton lift; ¡ Five-hanger sheave block (pinned to boom head shaft); required together with 250t hook block when lifting load exceeds 145ton, and available up to 250ton lift. ¡Aux. crane hoist cable, 28mm dia./350m long; available for fly jib application; ¡Aux. crane hoist cable, 28mm/190m long available for aux. short jib application; ¡Mid-point link; required when boom length exceeds 88.40m; ¡Boom skywalk; available for all sections of lificrane main boom; ¡Boom hooking bracket. Liffting jib Att. See Specifications catalogue of Luffing Jib Att. 25 Standard equipment Safety Devices 26 ¡Load Moment Indicator; this is a computerized automatic over-load preventing system incl. total safe operation control system; provided with a graphic display panel indicating ten and some kinds of present lifting conditions; ¡Lock lever (Fool proof shut-off lever); ¡Emergency engine stop switch; ¡Speed slowdown device; ¡Before-work check monitor; ¡LMI safety circuit-off switch; ¡Main hook over-hoisting limiter; ¡Boom over-hoisting and -lowering limiter; ¡Secondary boom over hoisting limiter; ¡Slewing alarm; ¡Travel alarm; ¡Slew lock; ¡Independent lever lock; ¡Main and aux. drum pawl locks; ¡Boom hoist drum pawl lock (w/automatic locking device); ¡Lifting height indication device; ¡Boom angle indicator; ¡Level gauge; fitted on floor of operator’s cab and a part of undercarriage; ¡Slewing brake lamp; ¡Warning lamps; available for pilot line; ¡Slewing brake safety circuit; ¡Signal horn; ¡Hook latch; ¡Engine monitoring lamps; ¡Travel direction arrow; ¡Front-end att. erection mode. Optional equipment ¡Three color percentage indicator; ¡Anemometer (recommended for luffing jib attachment); ¡Cabin roof window guard; ¡Aux. hook over-hoisting limiter; Followings are standard in case of luffing jib attachment: ¡Luffing jib angle detector; ¡Luffing jib load detector; ¡Luffing jib hook over-hoisting limiter; ¡Luffing jib over-hoisting and -lowering limiter; ¡Luffing jib hoist drum pawl lock (if luffing jib hoist drum is optionally provided); ¡Luffing jib backstops; ¡Secondary luffing jib over-hoisting limiter; ¡Rear post backstops (hyd. cylinder type). MEMO 27 SCX2800-2 • We are constantly improving our products and therefore reserve the right to change designs and specifications without notice. • Units in this specification are shown under International System of Units; the figures in parenthesis are under Gravitational System of Units as old one. Address Inquires to: Printed in Japan 1109(A)01T.EA187-1c (Superedes 1106(A)05H.EA187) SAPRJV Contract 3303 – Third Runway and Associated Works Appendix D – Erection, Dismantling and Transportation in Code of Practice for Safe Mobile Crane Code of Practice for Safe Use of Mobile Cranes 10. Erection, Dismantling and Transportation 10. Erection, Dismantling and Transportation 30 10. Erection, Dismantling and Transportation Code of Practice for Safe Use of Mobile Cranes 31 Code of Practice for Safe Use of Mobile Cranes 10. Erection, Dismantling and Transportation 32 10. Erection, Dismantling and Transportation Code of Practice for Safe Use of Mobile Cranes 33 Code of Practice for Safe Use of Mobile Cranes 10. Erection, Dismantling and Transportation 34 SAPRJV Contract 3303 – Third Runway and Associated Works Appendix E – Crawler Crane Erection Training SAPRJV Contract 3303 – Third Runway and Associated Works Appendix F – Permit to Erection / Dismantling / Alteration of Crawler Crane Permit to * Erection/Dismantling/Alteration of Crawler Crane / Telescopic mobile crane 履帶式/ 油壓式起重機 *架設/拆卸/更改許可證 # Permit No. 許可證編號 : 安全部填寫 #Fill by General Information 基本資料 Commencement Date: 工作日期: Supplier of Crane: 起重機供應商: Manufacturer and Model: 生產商及型號: (Please tick) Work type: (請填上 X號)工作類別: Work location: 工作地點: Owner of Crane: 起重機擁有人: Serial Number: 機身編號: Dismantling 拆卸 Erect 架設 Issue of Permit 發出許可証 Alteration 更改 Permit Issuer 許可證發出者 Name 姓名: Signature 簽署: Company 公司: Date & Time 日期及時間: Crawler Crane Erection/Dismantling/Alteration Competent Person 起重機架設 / 拆卸 / 更改合資格人士 Receipt of Permit 接收許可證 I declare that work to be undertaken by myself, or any person under my control, regarding the aforesaid crane erection, dismantling or alternation shall be carried out in accordance with the safety laid down on the this permit. 本人茲聲明由本人管轄的人員及本人在進行架設/拆卸/更改上述的起重機的工作時,一 律遵照此許可證背面列明的所 有安全要求。 Name 姓名: Signature 簽署: Company 公司: Date & Time 日期及時間: Competent Person MUST strictly follow and monitor the Safety Requirements listed on this permit. 起重機架設/架設/拆卸/更改合資格人士需嚴格執行及監察背頁安全要求一覽表所列出的所有安全要求。 Crawler Crane Erection/Dismantling/Alteration Competent Person 起重機架設 / 拆卸 / 更改合資格人士 Completion of Works 完成工作 I declared that work in the above has been completed or stopped and the men in my charge withdrawn. 本人聲明上述工作經已完成或停工,及本人管轄的人士,已經安全離開。 Name 姓名: Signature 簽署: Company 公司: Date & Time 日期及時間: Cancellation of Permit 註消許可證 Permit Issuer 許可證發出者 I acknowledge this Permit hs been cancelled. 本人現註消此工作許可證。 Name Company 姓名: 公司: Signature 簽署: Date & Time 日期及時間: * 請刪除不適用部分 Please cross out the inapporpriate part 安全要求一覽表 Safety Requirement List [] Completed / Checked 已完成已檢查 [X] Incomplete / Not Checked 未完成未檢查 Competent Person MUST strictly follow and supervise the safety requirements as below: 負責人士需嚴格執行下列的安全要求 1. Provision of the method statement and risk assessment for the crane subject to *dismantle / erect / alteration before start of work. 在開始工作前已提供有關起重機的*架設/拆卸/更改的施工方案及風險評估。 2. Provision of appointment letter of competent person by crane supplier or owner 已提供由起重機供應商或擁有人發出的起重機架設/拆卸更改合資格人士授權信。 3. Provision of evidence of related experience and valid training certificate possess by competent person 已提供起重機架設拆卸更改合資格人士的訓練及經驗證明。 4. Provision of appointment letter of working crew by crane supplier or owner 已提供由起重機供應商或擁有人發出的工作隊伍授權信。 5. Provision of evidence of related experience and valid training certificate possess by working team 已提供工作隊伍的訓練及經驗證明。 6. Detail explanation of method statement, risk assessment and procedures of the crane subject to *dismantle / erect / alteration was conducted by Task Launching Meeting and/or Pre-Work Risk Assessment before start of work. 在開始進行中架設/拆卸/更改的工作前,已進行安全施工開展會及/或開工前風險評估 評估並清楚 地解釋施工方案、風險評估及工作步驟。 7. All relevant documents, licenses and certificates were verified by competent person before start of work. 在開始進行工作前,起重機架設拆卸更改合資格人士已經確保所有有關文件, 證件及證書 有效。 8. Physical inspection check was conducted to all equipment and machinery before start of work, and ensures all the equipment and machinery used is in good condition. 在開始進行工作前,已檢查所有工具及機器的狀態並確保一切狀態正常。 9. Ensure the load test has been taken according to COP's requirement before issuing certificate 確保頒發證書之前已根據COP的要求進行了負載測試 10. Provide full supervision by competent person during the entire process of work. 架設拆卸更改起重機的整個程序及期間的所有時間應由合資格人士監督。 Name 姓名 : Signature 簽署 : Company 公司 : Date & Time 日期及時間 : END OF PERMIT 工作證完結 *請刪除不適用部分 Please cross out the inappropriate pat SAPRJV Contract 3303 – Third Runway and Associated Works Appendix G – Layout of Zone and Lifting Plan Appendix H - Layout of Zone and Lifting Plan Lifting Plan Position A: For Tracks Dismantle 110T Lorry crane, SWL 23.9 ton@ 4.65m Heaviest component at 4.65 m Crawler Track wt. 18.7 ton 110T Lorry crane SWL 23.9ton@4.65m Heaviest component at 4.65 m Counter weight wt. 17.8 ton Position B: For Counterweight Dismantle 110T lorry crane SWL 5.27 ton@17.00m Heaviest component at 17m Boom Base wt. 3.6 ton Position C: For Main Boom Dismantle SAPRJV Contract 3303 – Third Runway and Associated Works Appendix H – Check List for Assembly Operation Contract no.: Project Name: Project Name: C 3303 Third Runway and Associated Works LTSAMBO Checklist for assembly operation Item Description 1 Fenced off area for assembly and operation. 2 Working condition, eg. Weather, has been assessed and it is acceptable to start working. 3 Workers PPE. 4 Helping cranes with validated certificate. 5 Visual check the condition of helping crane. 6 Lifting gears with validated certificates. 7 Safety briefing with all workers. 8 Review this method statement. 9 Correct sequence of assembly operation. Yes / No Checked by 10 11 12 * Point 10 – 12: Special items, if any, for supervisor filling in the blank at that specific working site. Checked by: _____________________ __________________________ Certified by: _____________________ __________________________ SAPRJV Contract 3303 – Third Runway and Associated Works Appendix I – Plant Information of Lorry Crane for Serving Assembly SAPRJV Contract 3303 – Third Runway and Associated Works Appendix J – Joint Inspection Check List for Crane Crane Model : Serila No : Date : / / 2020 Site : Working Hour of Crane : Joint Inspection Check list for Crane Result V=In Safe working Order N= To be repaired Item Result Component Check Item Result Component Check Item Result Component Check 1 Engine 13 Body and Frame 24 Greasing 2 Brake and Steering System 14 Dilver's Room 25 Oil and Coolant 3 Hydraulic System 15 Slewing Gear 26 Service Record 4 Electrical System 16 Safety Device 27 Wire Lubrication 5 Card System Panel 17 Auto Control 28 Noise Absorbing Hood 6 Winch I 18 Crawler frame 29 Jib Head 7 Winch II 19 Tracker Rollers 30 Cat walk 8 A-frame 20 Driver and idler wheel 9 Boom(bottom) 21 Sliding shoe & Chain guide 10 Pulleys(bottom) 22 Chain and pad Shoes Single Hook 11 Boom Holsl Wire 23 Tensioning Device Pulley Block 12 Counter Weight 24 Shifting Device Hook Filling 1 2 3 4 5 6 Driver Room's Lighting Cabin's Lighting Top Lighting(L/R) Winch Lighting Swing Lighting(L/R) Weight of Limit Switch Joint Inspection Checklist for Crane Recommendation by RPE : Item 7 8 9 10 11 12 Jib Upper Limit Cut Switch Bypass of Limit Switch Raido & Its Speaker Voice Enlarge & Its Speaker Hand Free Mic Top Wiper Hook Equipments 13 14 15 16 17 18 19 Front Wiper Battery and Electrolyte +/- Pole of Battery 4 Fans bove E.Card Box Engine Starter Dynamo Electric Output LML System Descroption / Comment 1 2 3 4 5 6 Inspection by Endorsed by Site Filter/ Inspection Registered Professional Engineer
0
You can add this document to your study collection(s)
Sign in Available only to authorized usersYou can add this document to your saved list
Sign in Available only to authorized users(For complaints, use another form )