WATER NETWORK MANAGEMENT SERVICE AND WORKS CONTRACT – IRISH WATER DOCUMENT NO. ISSUED SHD-WNMP-MS-0002-01 CLIENT Irish Water PROJECT TITLE Water Network Management Service and Works Contract CONTRACT NO. 16/010 SITE LOCATION WNP DOCUMENT TITLE TEMPORARY TRAFFIC MANAGEMENT INSTALLATION AND REMOVAL ISSUE CONTROL and COPYRIGHT For the purposes of this project, this document is issued on loan to the person named below (the holder) on the understanding that it will remain in the safe custody of the holder and be returned to the Project's Document Controller upon completion of the contract or the termination of the holder’s employment (as applicable). The holder will be responsible for complying with the instructions that accompany any revisions of this document. Note: Where pertinent conditions and situations dictate, this document will be supplemented by approved Project-Specific Work Instructions and Risk Assessments. Amendments will be identified by the revision number in RED at the end of the line revised, except to risk assessments where the revisions will be in BLUE highlighted print. The controlled copy number will be entered in RED ink. Deletions will be in GREY, with strikethrough. CONTROLLED COPY NO. ISSUED TO: JOB TITLE : If you have an electronic copy of this document, please consider the environment before printing and whether you need to print the entire issue (double-sided) or just an appropriate page. DELEGATE PRINT NAME POSITION MAIN AUTHOR TIM FERGUSON SITE ENGINEER REVIEWER SUMIT CHAWLA PROJECT MANAGER APPROVER SIARHEI NEMICH OPERATIONS MANAGER 01 31/01/2020 Issued for Construction 00 31/01/2020 Issued for Review REVISION DOCUMENT NO. DATE SIGNATURE STATUS DESCRIPTION SHD-WNMP-MS-0002-01 1 CONTROLLED COPY DISTRIBUTION LIST Controlled Copy No. Issued to: 01 Site File Note To verify which employees, contractors and subcontractors have received copies of this Method Statement, please refer to the Controlled Copy Number Listing held by Document Control CONTENTS 1.0 Introduction ............................................................................................................................................................. 2.0 Reference Documents ........................................................................................................................................... 3.0 Safety Documents .................................................................................................................................................. 4.0 Procedures ..................................................................................................................................................... 5.0 Personnel ..................................................................................................................................................... 6.0 PPE ..................................................................................................................................................... 7.0 Plant, Tools & Equipment 8.0 Materials ................................................................................................................................................................ 9.0 Methodology 10.0 Access and Egress ............................................................................................................................................... 11.0 Work Boundaries .................................................................................................................................................. 12.0 Emergency Procedures .......................................................................................................................................... 13.0 Manual Handling ..................................................................................................................................................... 14.0 Demarcation ........................................................................................................................................................... 15.0 Supervisory Requirements ..................................................................................................................................... 16.0 Programme ............................................................................................................................................................. 17.0 Waste Management & Housekeeping .................................................................................................................... 18.0 Environmental Issues ............................................................................................................................................. 19.0 Quality 20.0 Risk Assessment .................................................................................................................................................... 21.0 Employee Signing on Register ................................................................................................................................ ...................................................................................................................................... ...................................................................................................................................................... .................................................................................................................................................................. Appendices Appendix A Safety Risk Assessments 2 1.0 INTRODUCTION The purpose of this document is to prescribe the work methods and hazard identification associated with the Installation and removal of Temporary Traffic Management operations as part of the Water Network Management Service and Works Contract. This Method statement was prepared following the Shareridge procedure SOP 49 Method Statements and SSWP’s. The following are to be completed prior to works commencing. ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ Detailed photographic survey carried out of the areas affected by the work. Statutory Notices issued and advance warning signs erected. Traffic management drawings and particulars in place. Permits to work, as and when required. Service scan and mark up undertaken. Structural/Condition Surveys undertaken for properties in the works’ zone of influence. All relevant authorities and bodies consulted. All health and safety documentation to be briefed by the site supervisor and signed off by site operatives. Relevant customer side waivers will be received, signed, prior to works commencing on or within properties. The following are the works to be carried out. ▪ Safe Installation and removal of complete Temporary Traffic Management System including all signs, cones, barriers and the like. ShareRidge site staff will be in attendance to supervise and complete the work required. 2.0 REFERENCE DOCUMENTS Refer to Appendix A for relevant Risk Assessments. ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ 3.0 ▪ ▪ ▪ ▪ 4.0 IW Standard Detail Drawings Approved Design (Document number TBC upon design approval). Relevant Utility Drawings Traffic Management Plan Environmental Management Plan Site Waste Managment Plan Site Management Plan Chapter 8 of the Traffic Signs Manual (November 2010) Guidance for the Control and Management of Traffic at Road Works, Second Edition 2010. SAFETY DOCUMENTS Construction Phase Health and Safety Plan. Relevant Method Statements. Safe Work Plans. Site specific Temporary Traffic Management Plan PROCEDURES Below is a list of Shareridge procedures that may be referred to for TTM activities. SOP 05 Pre-Start Procedure SOP 06 Pre-Commencement of Works Procedure SOP 56 Traffic Management 3 5.0 PERSONNEL MAN POWER REQUIRED Team leader Plant operators General operatives Flagmen TTOS TRAINING Manual Handling Safe pass Site Induction CSCS SLG CSCS Health and Safety at Roadworks First Aid 6.0 REQUIRED BY All All All At least one person on site where temporary traffic management is being set up, removed or modified - TTOS At least one person on site if Traffic management is in place and SLG card holder is absent At least one person on site, usually team leader PPE ShareRidge will ensure that adequate PPE is provided, as required during the contract. Site operatives will maintain, in good condition, and request replacements where necessary. The site supervisor will take charge of issuing PPE and recording the issue of same to site operatives. All visitors to site are to ensure that they are in possession of the appropriate PPE (NO PPE = NO VISIT). Site operatives will be aware of how to use the PPE provided, correctly. HARD HAT Other PPE that may be required: 7.0 ▪ ▪ ▪ ▪ ▪ ▪ EAR PROTECTION • HIGH VISIBILITY CLOTHING RUBBER SOLED BOOTS GLOVES SAFETY GLASSES Wet Weather Gear PLANT, TOOLS & EQUIPMENT All plant operators will hold suitable training certification for the item of plant to be operated. Competency cards will be carried and available for inspection prior to works taking place and throughout the works. Records of training cards will be maintained in the site file. Plant is to be inspected prior to use by the plant operator, to ensure it is suitable and fit for purpose, in line with the manufacturer’s recommendations. Weekly inspections of plant will be recorded on form GA2 and maintained in the Site Safety File. Certification will also be provided for all plant in accordance with relevant guidelines and regulations. Warning signs will be erected at the site of works to caution plant operators regarding the presence of overhead cables, underground services and any site specific hazards. All portable electrical equipment will be 110v and is to be PAT Certified. A risk assessment on HAVS and noise will be briefed with this method statement. 4 ▪ 8.0 All lifting equipment must be suitable for purpose and is subject to a schedule of inspections and thorough examinations. Inspection labels must be clearly visible. Item Description Source Certificate Required Special Requirements Chaper 8 Signage Barriers/Fencing Vans ShareRidge ShareRidge ShareRidge No No Yes TT Lights Tested Reflective/Clean Road Legal MATERIALS The following is a list of materials which will be used for this works activity. ▪ Cones ▪ Safety Barriers ▪ Chapter 8 Signage ▪ Temporary traffic signals ▪ Stop/Go signs 9.0 METHODOLOGY The following principles will be adhered to in the development of an effective traffic management plan. ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ The work of erecting, altering and removing traffic management arrangements must be carried out and / or supervised by an individual in possession of a CSCS card for the Signing, Lighting and Guarding. Once the site has been set up it can be maintained by an individual who has completed the one-day Health and Safety at Roadworks Training. Avoidance or reduction of risk where risks cannot be eliminated. To WARN traffic of the risk sufficiently in advance of works & obstructions in the road. To INFORM traffic of the nature of the risk ahead. To DIRECT the travelling public & to aid them in their decisions while moving though the space & the requirement for safety zones adjacent to the works area. To inform the travelling public of the END of the area subjected to the traffic management plan. To provide clear, credible & appropriate signage & speed limit reductions where these are considered necessary. To minimise the potential for conflict between road users. All works will be carried out in accordance with Traffic Management Plans and all works on live carriages will be carried out in accordance with Chapter 8 of the Traffic Signs Manual. Site specific traffic management plans will be prepared in accordance with this Method Statement. Enabling Works ▪ ▪ ▪ All battery powered devices i.e. temporary traffic signals, walkie talkies etc. to be fully charged and tested as fully operational. Check all signs are clean, unmarked and are the appropriate size for TTMP. Full Traffic Management Plan provided to Work gang as part of the Site-Specific Health and safety plan. This will include all design parameters and sign location and distances in accordance with Chapter 8 of the Traffic Signs Manual (November 2010) and Guidance for the Control and Management of Traffic at Road Works, Second Edition 2010. (Temporary Traffic Management Plan to be supplied or designed in accordance with SHARERIDGE Temporary Traffic Management Design procedures found in Traffic Management section of Construction Phase Health and Safety Plan) 5 ▪ Team leader or qualified person appointed by the supervisor,who will be adequately trained as a TTOS (Temporary Traffic Operations Supervisor) and hold a valid CSCS card for Signing, Lighting and Guarding at Roadworks, will hold a prestart meeting informing the rest of the team of the proposed method of installation. Installation ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ Team will arrive on site and park all vehicles at a safe location off the road and not obstructing any pedestrians. The traffic management team will first inspect the site to make sure work can be carried out in a safe manner. They will then proceed to the locations where the required signs are to be erected. Each works location will be independently risk assessed to determine that the proposed TTMP plan is adequate to facilitate the safe execution of the works. Any further amendments to the TTMP plan will be incorporate to reflect the site conditions. These amendments will be clearly All signs, cones, barriers etc. is off loaded and stored safely away from the road, and not obstructing any pedestrians. WK 001 Roadworks ahead signs are to be setup first at their shown locations on the TTMP both approaching and leaving the works. (Sign leaving the works to be accompanied by P 010 END supplementary plate) All other warning, informative, and direction signs are taken to their location as shown on the TTMP and left face down off the road not obstructing pedestrians. Work zone, longitudinal safety zone and taper lengths are set out on off the road, not obstructing pedestrians, using cones to mark the beginning and end of each zone. The space between is then filled with other cones at various intervals depending on design parameters. Two WK 061 flagman warning signs and a WK 095 stop here on red sign are now setup facing approaching traffic in accordance with design parameters. Flagmen located on footpath next to each stop here on red sign will each have a stop/go sign, they will communicate with each other once traffic has quietened and area will be put on all stop. All Stop will remain in place until the rest of the TTMP has been set up. Other team members will now erect signage starting from the furthest away from work zone and work their way in. Cones earlier marked out on side of road will be moved on to road and placed in there required positions marking out zones and tapers. Barriers will now be moved in to place forming a perimeter around work area. All other signs will now be erected according to TTMP. Set out crew will now communicate to the flagmen the setup is complete and the all stop can be removed. Flagman signs and stop here on red signs used for set up are removed and stored in a safe location. Removal ▪ ▪ ▪ ▪ ▪ ▪ ▪ ▪ A check of the site will take place making sure all that is left is only traffic management equipment and that the road is now safe for live traffic. Two WK 061 flagman warning signs and a WK 095 stop here on red sign are now setup facing approaching traffic in accordance with design parameters. Flagmen located on footpath next to each stop here on red sign will each have a stop/go sign, they will communicate with each other once traffic has quietened and area will be put on all stop. All Barriers, cones and signs on the road are to be removed and stored off the road safely not obstructing pedestrians. Once the road is clear, removal team will communicate this to the flagman who will cease the all stop and remove flagman and stop here on red signs and store safely off the road not obstructing pedestrians. Warning signs will now be removed from their positions starting with those closest to the work zone working out. Last signs to be removed are the Roadworks ahead signs facing approaching traffic. Reload vehicles with all equipment. 6 ▪ ▪ Final check of site. Safely leave site. 10.0 ACCESS AND EGRESS Site access and egress will be briefed by the site supervisor to all site operatives during the site induction. Any restrictions on access and egress will also be briefed to site operatives by the site supervisor. 11.0 WORK BOUNDARIES The site of works will be demarcated with rigid barriers or Heras fencing. This will be agreed with The Employer and the Local Authority prior to works commencing. 12.0 ▪ ▪ ▪ ▪ ▪ ▪ ▪ EMERGENCY PROCEDURES Site rules will be listed and briefed in the site induction. The emergency preparedness and response plan will contain relevant emergency plans and emergency contact details. This will be maintained on site in the site folder. A qualified first aider will be available for the duration of the works. Accident and incident reporting will be as per the ShareRidge reporting procedures, with prescribed forms to be completed as required. The fire assembly point and relevant muster points will be briefed during the site induction. All incidents and accidents are to be reported in the first instance to the ShareRidge site supervisor, immediately. The nearest Hospital, with full Accident & Emergency facilities, is located at the following address. A detailed route map will be available on site and is also contained in Appendix B. Emergency Services Details Hospital: Location Emergency Department, University Hospital Limerick, St. Nessan's Road, Dooradoyle, Co Limerick V94 F858 112/999 Contact number 061 482 343. Fire: Location Limerick City Fire Station Mulgrave St Co Limerick Contact number 112/999 061 407 100 Garda: Location ESB Virgin Henry St Garda Station Henry St Limerick City Co Limerick Contact number Utility Strike Emergency Contact 1850372999 Eircom 1908 BT 112/999 061 212 400 1850245424 01 432 6555 7 GNI 13.0 ▪ ▪ ▪ 1850205050 HSA 1890 289389 MANUAL HANDLING Good practice will be used through using T.I.L.E (Task, Individual, Load and Environment). All loads will be shared between operatives and manual lifting is to be avoided where practical. All manual lifting should in the first instance be assessed if it is possible to perform the task by using hydraulic lifting aids and if so, then the lifting aid must take priority and be deployed if safe and practicable to do so. Site operatives will be in possession of a valid manual handling certificate. 14.0 DEMARCATION Pedestrian and vehicle routes will be segregated by physical barriers. These routes will be clearly demarcated using appropriate signage. All and any traffic management required for surveying and investigation works will be in accordance with the relevant traffic management plan and installed by a competent SLG trained operative, under supervision. 15.0 ▪ ▪ ▪ ▪ ▪ ▪ ▪ SUPERVISORY REQUIREMENTS Contracts Manager Operations Manager Project Manager Construction Manager Site Supervisor Site Engineer Team Leader 16.0 PROGRAMME A four week lookahead programme will be submitted to The Employer. This will outline start and finish dates for all relevant works. 17.0 WASTE MANAGEMENT AND HOUSEKEEPING All waste will be kept to a minimium, cleaned up as work procedes, promoting good housekeeping practice, keeping the site clean and tidy in accordance with the Site Waste Managment Plan SHD-WNP-WMP and SOP 25 - Waste Management Procedure. Waste will be handled in accordance with the requirements specified in the site-specific Site Waste Managment Plan SHD-WNP-WMP and SOP 25 - Waste Management Procedure. All waste disposals will be arranged via the ShareRidge site supervisor. All waste skips and drums will be kept in the established laydown area. 18.0 ENVIRONMENTAL ISSUES 8 All Environmental Incidents and Non-conformance will be dealt with and reported in accordance with the Project Environmental Plan and Shareridge Environmental procedures (see below). The contract environmental plan outlines how environmental requirements will be managed for the contract and specific controls that will be implemented on site. Drip trays and spill kits will be available on site. Any spillages will be cleaned up and reported to the site supervisor immediately. No materials will be stored within 10 meters of any watercourse when not working. No plant will be parked overnight within 10 meters of any watercourse. All drains and gullies will be protected. Material Safety Data Sheets (MSDS) will be maintained on site for all hazardous materials. Fuel will be stored on suitable drip trays when required and secured in site van when not in use. See below a list of Shareridge procedures that may be referred to for Environmental safety. SOP 25 SOP 26 SOP 27 SOP 28 SOP 29 SOP 30 SOP 25 SOP 25 19.0 Waste Management Procedure Chemical Handling and Storage Procedure Environmental Emergencies and incidents Spill Control Procedure Refuelling Procedure Provision of Management of Project Environmental Issue Project Environmental Plan Procedure Management of the Environmental Performance of Contractors QUALITY Works will be carried out in accordance with relevant approved designs and any relevant specifications. All works will comply with the ShareRidge Quality Procedures, ITP and Project Quality Plan. See below a list of Shareridge procedures that may be referred to for quality management. SOP 07 SOP 08 SOP 43 SOP 44 SOP 48 SOP 52 20.0 Material/submittal Approval Procedure Sub Contract Submittal/Approval Design Control Control of Non-Conforming Product Preparation and Updating of Project Quality Plan On Site Procedure (Construction, mains testing, swabbing and disinfection, materials testing, etc.,) RISK ASSESSMENT Please refer to attached ShareRidge Risk Assessments. 21.0 EMPLOYEE SIGNING ON REGISTER 9 I, the undersigned have been briefed and discussed fully this method statement and its associated risk assessments. I have understood the above method statement and risk assessment and will adhere to all its method of working and conditions set down. Print Name Company Signature Date SHOULD CIRCUMSTANCES ARISE THAT LEAD TO A CHANGE IN THE AGREED WORKING METHOD THEN WORK WILL CEASE UNTIL A REVISED METHOD STATEMENT/RISK ASSESSMENT IS AGREED. 10 APPENDIX A Risk Assessments The following is a list of risk assessments that relate to this method statement. Risk assessments were prepared following Shareridge procedure SOP 50 – Assessment and control of hazards and risks (risk assessments). Plant and equipment damage RA-008 RA-002 RA-012 RA-013 RA-017 RA-021 RA-022 RA-023 RA-024 RA-031 RA-033 RA-041 Use of small plant Manual handling Noise Stress Working near live traffic Traffic management Security Housekeeping Dealing with the public Pedestrians First Aid 11 11