Clarifications For EAp1 Review Comments The LEED Prerequisite Form )and supporting documentation have been provided stating that the project has achieved an energy cost savings of 26.18% using the ASHRAE 90.1-2007 Appendix G methodology. Energy efficiency measures include thermal envelope improvements, lighting power reductions, high-efficiency motors, and fan power reductions. However, the following)ten review comments requiring a project team response must be addressed for the final review.) Please upload a summary document that includes a narrative response to each preliminary review comment that has been addressed by the project team, and a narrative describing any additional changes made to the energy models between the preliminary and final review phase. Include revised simulation input and output documentation with the response narrative. 1) TECHNICAL ADVICE: 1. The supporting documentation indicates that a district energy source is used for the Proposed Case cooling. However, it does not appear that “Treatment of District Thermal Energy in LEED v2 and LEED 2009 – Design and Construction”, which can be found at: http://www.usgbc.org/ShowFile.aspx?DocumentID=7671, has been followed. While LEED 2009 project are not required to use this guidance, using it is highly recommended. If the project team chooses to use this guidance, please indicate whether Option 1 or Option 2 has been followed and provide supporting documentation as outlined in the guidance. However, if this guidance is NOT used, and the project is receiving district cooling, the district cooling must be modeled in accordance with ASHRAE Appendix G requirements for modeling district thermal energy. In this case, the cooling energy must be modeled using purchased energy rates in the Proposed Case and the appropriate Appendix G cooling system in the Baseline Case. Provide further information supporting the chilled water rates used in the project, or if desired, revise the model to reflect the methodologies presented in the district thermal energy documents. The submitted LEED review documentation must clearly state which method, ASHRAE 90.1 Appendix G, or District Thermal Energy guidance v. 2.0 (August 2010) was used. KLIA2_LEED Clarification for EAp1 IEN Consultants 2 Clarifications from Project Team The guidance “Treatment of District Thermal Energy in LEED v2 and LEED 2009 – Design and Construction” is used for this project. Option 2 has been followed. In this project, Option 2 (Aggregate Building/DES Scenario)is used. The effects of the DES on the cooling system (including both upstream and downstream) are incorporated. The Base Case Chiller is modeled using ASHRAE Appendix G for System 8 as in the guidance. For the proposed case, a virtual DES district cooling plant is modeled as in the guidance. The average system COP is 4.1 which includes the distribution losses from the District Cooling Plant to the building has been used as this is the system COP calculated by the DES operator. The electricity rate is assigned using the local utility rate as normally applied to building and using normal ASHRAE and LEED modeling rules. For the Baseline Building, the rates are applied to the code compliant cooling plant as per ASHRAE Appendix G. For the Proposed Building, the rates are applied to the virtual plant according to the actual energy source used in the upstream DES which is electricity in this case. The electricity tariff KLIA2_LEED Clarification for EAp1 IEN Consultants 3 2) TECHNICAL ADVICE: 2. The Baseline Case skylight U-value does not appear to have been modeled according to ASHRAE 90.1-2007, Table 5.5-1. Please update the skylight description in Table 1.4.1B to indicate whether the actual skylight design includes curbs, and whether the glazing is plastic or glass, in addition to the overall skylight-to-roof area ratio. Ensure the Baseline U value and SHGC match the values in Table 5.5-1 for the corresponding skylight type and total area ratio.) ) Clarifications from Project Team The skylight does not include curb and the glazing is glass. The baseline U Value and SHGC value re-submitted is in accordance with Table 5-5-1. Table 1.4.1B is updated with description of the skylight and the U value as mentioned in the technical advice by the review team (highlighted in red). The baseline U value is also modeled in accordance with ASHRAE 90.1 Table 55-1. Table 5-5-1 (Extract from ASHRAE 90.1-2007) Fenestration Assembly Maximum Assembly Max. SHGC Skylight without curb, all % of roof 0%-2% KLIA2_LEED Clarification for EAp1 U all 7.72 SHGC all 0.36 IEN Consultants 4 2.1% - 5% U all 7.72 SHGC all 0.19 3) TECHNICAL ADVICE: 3. Table 1.4.2 indicates a heating system was not modeled. While the heating demand may be negligible, ASHRAE 90.1-2007, Table G3.1 Proposed #10(c), requires spaces to be simulated as being both heated and cooled. Please revise the Baseline and Proposed Cases to include a heating system following the Appendix G protocol and update the submittal documentation accordingly. Clarifications from Project Team The revised simulation has included the heating system for both Baseline and Proposed Case. However it must be reiterated here that the heating demand is zero in Malaysia. Please refer to the weather data below for Malaysia, Kuala Lumpur. KLIA2_LEED Clarification for EAp1 IEN Consultants 5 Figure 1: Weather Conditions in Kuala Lumpur. KLIA2_LEED Clarification for EAp1 IEN Consultants 6 4) TECHNICAL ADVICE: 4. The Baseline Case fan power does not appear to be modeled in accordance with ASHRAE 90.1-2007, Section G3.1.2.9. The pressure drop adjustment reported in Table 1.4.2 appears to be taken from the actual supply static pressure in the Proposed Case rather than regulated credits listed in Table 6.5.3.1.1B. Additionally, it is unclear if a separate fan power allowance was determined for each Baseline system as required by the Appendix G modeling protocol.) Please revise the sum of the supply, return, exhaust and relief fans for each HVAC system to be equal to the power calculated in Section G3.1.2.9, where CFM refers to the Baseline Case autosized supply CFM for each HVAC system. Indicate whether any ASHRAE 90.1 Addenda have been used to calculate the fan power, and note all pressure adjustments reflected in the fan power calculations. Include a supplemental table demonstrating how the fan power allowance was calculated. Report the revised total fan power in Table 1.4.2, and update Table EAp2-4 and simulation summary reports to reflect the changes. Clarifications from Project Team The baseline fan power is calculated in accordance to ASHRAE 90.1-2007. Section G3.1.2.9. The baseline building peak fan power is calculated as follow: 1. The supply air volume for each thermal zone is determined by the simulation program using a 11⁰C temperature difference between the space temperature and supply air temperature as required by G3.1.2.8. The baseline HVAC system is System 8 hence it has to be a VAV system. 2. Option 2: Fan system Input kW is used to calculate the peak fan power which is the allowable fan system input kW. 3. The table shows the sample calculation KLIA2_LEED Clarification for EAp1 IEN Consultants 7 Table 2: Sample Fan Power Calculations Revision had been made to Table 1.4.2, which had been highlighted in red. KLIA2_LEED Clarification for EAp1 IEN Consultants 8 5) TECHNICAL ADVICE: 5. The Baseline Case supply air temperature reset parameters do not appear to have been modeled according to ASHRAE 90.1-2007, Section G3.1.3.12. Please revise the Baseline Case to include supply air temperature reset controls and update the documentation accordingly Clarifications from Project Team The supply air temperature reset has been modelled in accordance to ASHRAE 90.1-2007 Section G3.1.3.12. The supply air temperature has been reset to 2.3⁰C higher than the supply air temperature of 12⁰C at minimum cooling conditions. KLIA2_LEED Clarification for EAp1 IEN Consultants 9 6) TECHNICAL ADVICE: 6. Domestic hot water has not been modeled in the Baseline or Proposed Case; Table 1.4.5 indicates office buildings in Malaysia are not provided with hot water. ASHRAE 90.1-2007, Table G3.1#11Proposed(d), allows domestic hot water to be excluded from the models if no heating system will be installed. However, since the building includes food and beverage retail outlets, please confirm how domestic hot water is provided for dish washing or other process loads (i.e. non-lavatory use). If a domestic water heating system will be installed for specific processes, revise the Baseline and Proposed Cases to include a domestic water heating system. Verify that the Proposed Case inputs match the building design and the Baseline Case inputs conform to the minimum values required in Table 7.8 for the corresponding system type. Clarifications from Project Team There is no domestic hot water system in the building. The hot water for dish washing and other loads will be heated via electricity which is accounted for in the small power load (process load) for the food and beverage retail outlets. The small power load used is the same for both Base Case and Proposed Case which includes the electricity to be used for heating the water. KLIA2_LEED Clarification for EAp1 IEN Consultants 10 7) TECHNICAL ADVICE: 7. In Table 1.4.5, lighting power densities have been reported for the Space-by-Space method. However, the total area for each space type has not been provided, the listed space types do not correspond to the space types reported in Table EAp2-1, and the gross lighted floor area (3,027,673 square feet) differs from the total building area reported in Section 1.1A (2,748,532 square feet). Additionally, it appears as though certain spaces in the Baseline Case have been modeled using the lighting power density for the Building Area Method, such as “Religious Building-Seating” (the “Fellowship Hall” space type in Table 9.6.1 is appropriate for this category). Please revise the Baseline Case to ensure the lighting power densities are consistent with ASHRAE 90.1-2007, Table 9.6.1. Specifically indicate in Table 1.4.5 the area per space function, ensuring consistency with the space types reported in Table EAp2-1, and report the overall weighted average lighting power density for both the Baseline and Proposed Case. Clarifications from Project Team The gross lighted area and gross floor area differs due to Level 1. The building is elevated above level 1. However, there is still lighting within the building footprint which are circulation spaces for the staff, ground service vehicles and also the baggage handling areas which have to be lighted as well. These areas are within the building footprint but these areas are not included as part of the Gross Floor Area calculations submitted by the architect originally. As such, the Gross Floor Area and Gross Lighted area differs. However, the areas have now been revised to include the areas at level 1 as well. Hence the Gross Lighted Area is now equal to the Gross Floor Area. The installed lighting power densities for the various areas have been revised accordingly using the space by space method. Please see the revision in red. For the input to the energy model, an area weighted average is used for the lighting input as there are too many rooms and types of services in the airport building. The following table shows the sample calculation of the lighting power density used in the energy model. KLIA2_LEED Clarification for EAp1 IEN Consultants 11 Sample Calculation for Sector 1_Level 1a Space Type Area (m2) ASHRAE LPD(W/m2) Electrical/Mechanical 132.2 Corridor/Transition Seating ASHRAE lighting power(W) Current Lighting (W) Small power(W) 16 2115.36 782.91 15588.9 0 5 0 0 0 5506.4 5 27531.85 33014.43 51419.4 area_Transportation Airport concourse 6350.8 6 38105.28 38105.28 59698.3 Active storage 14.3 9 129.06 71.7 71.7 Stairs 150 6 899.52 449.76 749.6 Restroom 284 10 2843.4 2538.32 1421.7 Baggage area 0 11 0 0 0 Terminal_Ticket counter 0 16 0 0 0 Retail 1099 18 19779.48 17801.5 38789.8 Dining area_Family dining 478 23 11001.13 9901.2 16884.3 Fellowship hall 102 10 1021.4 612.84 510.7 Office 244 12 2927.04 2439.2 7634.7 Lounge 46.8 13 608.92 234.2 440.3 Hotel 0 12 0 0 0 Food preparation 0 13 0 0 0 104847.08 105951.189 193209.328 TOTAL 14408.13 KLIA2_LEED Clarification for EAp1 IEN Consultants 12 Input to IES For ASHRAE Area Lighting Power Density Total Small power Tenant small power Receptacle Power Input to IES for Proposed Case Area Total Task Lighting Power Consumption(W) Total Task Fan Power Consumption (W) Lighting Power Density (W/m2) Small power (W/m2) Tenant small power (W/m2) Receptacle Power (W/m2) KLIA2_LEED Clarification for EAp1 14408.13 7.28 9.02 3.86 0.530 14408.13 132 75 7.36 9.02 3.86 0.530 IEN Consultants 13 8) TECHNICAL ADVICE: 8. It is unclear if daylight harvesting has been modeled in the Proposed Case. Table 1.4.5 indicates daylight dimming controls are not provided, but Section 4.2 of the supporting document 2011_0630_KLIA2_EA1_Optimize Energy Performance rev04.pdf describes the daylight harvesting analysis conducted for the Proposed Case. Please clarify if daylight harvesting is included in the Proposed Case. Clarifications from Project Team Day-lighting has been modelled in the Proposed Case. Daylight dimming controls are not provided but daylight sensors are provided which will switch off the perimeter lighting when there is sufficient daylight inside the building. KLIA2_LEED Clarification for EAp1 IEN Consultants 14 9) TECHNICAL ADVICE: 9. Exterior lighting has been modeled identically in the Baseline and Proposed Cases. Please verify that the Proposed Case exterior lighting reflects the actual building design, and the Baseline Case reflects the allowed lighting power from ASHRAE 90.1-2007, Section 9. Lighting associated with applications not covered in Section 9, such as tarmac or runway lighting, may be modeled identically in both cases and treated as a process load. Provide a supplemental table which demonstrates all of the modeled lighting applications along with how the Baseline and Proposed Case lighting power was calculated. Ensure that no credit is taken in the Proposed Case for lighting reductions on non-tradable surfaces. Additionally, note that additional lighting power allowance cannot be claimed in the Baseline Case for surfaces that are not provided with lighting in the actual design, and lighting fixtures cannot be double counted for different exterior surfaces. Report the tradable and non-tradable surface lighting power separately (in units of Watts or Kilowatts) for both the Baseline and Proposed Case in Table 1.4.5, and verify that these values are appropriately reflected in the model outputs and Prerequisite Form Tables EAp2-4 and EAp2-5. KLIA2_LEED Clarification for EAp1 IEN Consultants 15 Clarifications from Project Team The table below show the calculation of the lighting power for the nontradable surface which is the building façade and the tradable surface which is the building ground, namely the apron lighting. Table 1: Non Tradable Surfaces Non-Tradable Surfaces Total Façade Area(m2) Allowable Façade Lighting in ASHRAE Lighting Power (kW) ASHRAE (W/m2) Building Facade 109028 Proposed Case Lighting Lighting Power for Proposed Case (kW) (W/m2) 2.2 239.86 2.2 239.86 Table 2: Tradable Surfaces Tradable Surfaces Location Power Consumption Per Fixture (W) No. of Fixtures Total Lighting Power Consumption (kW) Building GroundWalkway 3m wide or greater Building GroundWalkway 3m wide or greater Sector 1 800 11 8.80 Sector 2 800 12 9.60 Building Ground- Sector 3 800 13 10.40 Sector 4 800 15 12.00 Walkway 3m wide or greater Building GroundWalkway 3m wide or greater TOTAL 40.80 KLIA2_LEED Clarification for EAp1 IEN Consultants 16 The exterior lighting is operating 12 hours per day throughout the entire year. The energy consumption of the exterior lighting are added into the total building energy consumption separately. Areas Total Power Consumption (kW) Operational Hours Per Year Building Façade 239.86 12 * 365 =4380 Total Energy Consumption Per Year (kWh) 1,050,594 12 * 365 =4380 178,704 Building Ground- 40.8 Walkway 3m wide or greater TOTAL KLIA2_LEED Clarification for EAp1 1,229,298 IEN Consultants 17 10) TECHNICAL ADVICE: The submittal documentation for IEQc6.2 indicates many offices and other support spaces will be equipped with task lighting and personal fans. It is unclear if these loads were incorporated into the models. Please provide a narrative describing how these measures were modeled, including any schedule assumptions and the total power associated with each measure, and report the energy consumption associated with these end-uses separately in Tables EAp2-4 and EAp2-5. Clarifications from Project Team The power consumption of the task light and task fan have been added as process load separately into the proposed case in the revised energy model. It is assumed that 80% of the task light and task fan will be switched on over the entire 24 hours operation of the airport building. The power consumption of the task light and task fan are from the manufacturer technical catalogue. The power consumption of the task light and task fan is estimated to be 2.5W each. However, as the task light and task fan are USB type that can either be plugged into computer or plugged into USB socket, another 2.5W is added to the power consumption to account for the losses due to the adaptor and the power socket. Hence 5W is used for each task light and each task fan to account for the power consumption. The energy consumption of the task light and task fans are reported separately in Table EAp2-4 and EAp2-5. KLIA2_LEED Clarification for EAp1 IEN Consultants 18 Figure 2: Schedule of Task Light and Task Fan KLIA2_LEED Clarification for EAp1 IEN Consultants 19
0
You can add this document to your study collection(s)
Sign in Available only to authorized usersYou can add this document to your saved list
Sign in Available only to authorized users(For complaints, use another form )