SOLVED PROBLEMS IN FACILITY PLANNING & DESIGN September 2012 Solved Problems in Facility Planning & Design 2012 FORMULAS IN FACILITY PLANNING & DESIGN Facility Planning: determines how an activity’s tangible fixed assets best support achieving the activity’s objectives. Facility Location: is the placement of a facility with respect to customers, suppliers, and other facilities with which it interfaces. Structural Design: consists of the building and services (e.g., gas, water, power, heat, light, air, sewage). Layout Design: consists of all equipment, machinery, and furnishings within the structure. Handling System Design: consists of the mechanism by which all interactions required by the layout are satisfied (e.g., materials, personnel, information, and equipment handling systems). Scrap Estimate Ok = Ik - PkIk Ok = Ik (1 - Pk) Ik = Ok/ (1- Pk) I1 = On/ (1- P1) (1- P2)… (1- Pn) Where: Ok = desired output of non-defective product from operation k Ik = production input to operation k Pk = % of scrap produced in operation k 2|P a g e Solved Problems in Facility Planning & Design 2012 FORMULAS IN FACILITY PLANNING & DESIGN Equipment Fraction F= _____Total Time Required to Perform the Operation_______ Net Available Time to Complete the Operation per Machine F= SQ/ EHR Where: F= number of machines required per period S= standard time per unit produced Q= number of units to be produced period E= efficiency or actual performance expressed as percentage of standard time R= reliability of the machine expressed as percentage of ―up time‖ Factor Analysis Technique WS = WxS Where: WS = weighted score for each factor for each facility plan or location W= appropriate weight to each factor (typically between 0 to 1) based on the relative importance of each. S= assigned score to each facility plan or location (typically between 0 to 100) with respect to each factor identified. Compute the sum of the weighted scores for each facility plan or location and choose a facility plan or location with the highest score. 3|P a g e Solved Problems in Facility Planning & Design 2012 FORMULAS IN FACILITY PLANNING & DESIGN Center-Of-Gravity Technique n X= Xi W i i=1 _________________ n Wi i=1 n Y= Yi W i i=1 _________________ n Wi i=1 Where: X, Y = coordinates of the new facility at the center of gravity. Xi, Yi = coordinates of the existing facility i. Wi = annual weight shipped from facility i. Load-Distance Technique n LD = lidi i=1 Where: LD = the load distance value li = the load expressed as a weight, number of trips, or units being shipped from the proposed site to location i. di = the distance between the proposed site and location i. 4|P a g e Solved Problems in Facility Planning & Design FORMULAS IN FACILITY PLANNING & DESIGN di = (xi – x)2 + (yi – y)2 Where: (x, y) = coordinates of the proposed site (xi,yi) = coordinates of the existing facility Product Layout – Line Balancing D = OT / CT CT = OT / D Where: D= desired output rate OT = operating time per period CT = cycle time N= __(D)( t)___ OT Where: N= minimum number of work stations t= sum of task times D= desired output rate OT = operating time per period E= __ t___ N x CT Where: E= t= efficiency of the assembly line sum of task times N= minimum number of work stations CT = cycle time 5|P a g e 2012 Solved Problems in Facility Planning & Design 2012 FORMULAS IN FACILITY PLANNING & DESIGN Line Balancing Based on Incremental Utilization Method Add tasks to a workstation in order of task precedence one at a time until utilization is 100% or is observed to fall Then the above procedure is repeated at the next workstation for the remaining tasks Pro – Appropriate when one or more task times is equal to or greater than the cycle time Con – Might create the need for extra equipment Line Balancing Based on the Largest Number of Following Tasks Assign tasks to station 1, then 2, etc. in sequence. Keep assigning to a workstation ensuring that precedence is maintained and total work is less than or equal to the cycle time. Use the following rules to select tasks for assignment. Primary: Assign tasks in order of the largest number of following tasks Secondary (tie-breaking): Assign tasks in order of the longest operating time Line Balancing Based on the Longest Task Time Adds tasks to a workstation one at a time in the order of task precedence. If two or more tasks tie for order of precedence, the one with the longest task time is added Conditions for its use: ◦ No task time can be greater than the cycle time ◦ There can be no duplicate workstations Process Layout – Block Diagramming Develop the load summary chart Rank the composite movements from highest to lowest Prepare the initial layout on the grid by placing one-by-one the two-way movements based on its rank. Compute the initial total number of non-adjacent loads Develop alternative layouts eliminating or minimizing the number of non-adjacent loads 6|P a g e Solved Problems in Facility Planning & Design 2012 FORMULAS IN FACILITY PLANNING & DESIGN Process Layout – Systematic Layout Planning Determine the total flow Rank the flows Combine flow and non-flow relationships Rank the combined points Develop the combined relationship chart Develop the relationship diagram Measure the effectiveness of the relationship diagram Develop the space relationship diagram Develop the layout Measuring Effectiveness of the Relationship Diagram Min Z = Lij x Dij i j Where: Z= the least value of the product between Lij and Dij Lij = Load between departments i & j, often measured by the value of the vowel letter. A = 4, E = 3, I = 2, O = 1, U = 0, X = -1 X = -2 Dij = Distance between departments i & j Adjacent (Straight) – 1, Partial Adjacent (Diagonal) – 2, Non-Adjacent – 3 Process Layout - Manual CORELAP Algorithm Computerized Relationship Layout Planning (CORELAP) is a construction algorithm to create an activity relationship (REL) diagram or block layout from a REL chart. Each department (activity) is represented by a unit square. Numerical values are assigned to Corelap Values (CV’s): V(A) = 10,000, V(O) = 10, V(E) = 1,000, V(U) = 1, V(I) = 100, V(X) = -10,000. For each department, the Total Closeness Rating (TCR) is the sum of the absolute values of the relationships with other departments. 7|P a g e Solved Problems in Facility Planning & Design 2012 FORMULAS IN FACILITY PLANNING & DESIGN Procedure to Select Departments The first department placed in the layout is the one with the greatest TCR value. If a tie exists, choose the one with more A’s. If a department has an X relationship with the first one, it is placed last in the layout. If a tie exists, choose the one with the smallest TCR value. The second department is the one with an A relationship with the first one. If a tie exists, choose the one with the greatest TCR value. If a department has an X relationship with the second one, it is placed next-to-the-last or last in the layout. If a tie exists, choose the one with the smallest TCR value. The third department is the one with an A relationship with one of the placed departments. If a tie exists, choose the one with the greatest TCR value. The procedure continues until all departments have been placed. Procedure to Place Departments Consider the figure below. Assume that a department is placed in the middle (position 0). Then, if another department is placed in position 1, 3, 5 or 7, it is ―fully adjacent‖ with the first one. If it is placed in position 2, 4, 6 or 8, it is ―partially adjacent‖. For each position, Weighted Placement (WP) is the sum of the numerical values for all pairs of adjacent departments. The placement of departments is based on the following steps: 8|P a g e o The first department selected is placed in the middle. o The placement of a department is determined by evaluating all possible locations around the current layout in counterclockwise order beginning at the ―western edge‖. o The new department is located based on the greatest WP value. Solved Problems in Facility Planning & Design 2012 FORMULAS IN FACILITY PLANNING & DESIGN Cellular Layout – Direct Clustering Algorithm Form the Parts-Machines Matrix. Order the rows and columns. Sum the Xs in each column (machine) and in each row (part) of the machine-part matrix. Order the rows (top to bottom) in descending order of the number of Xs in the rows and order the columns (left to right) in ascending order of the number of Xs in each. Where ties exist, break the ties in descending numerical sequence. Sort the columns. Beginning with the first row of the matrix, shift to the left of the matrix all columns having an X in the first row. Continue the process row-by-row until no further opportunity exists for shifting columns. Sort the rows. Column-by-column, beginning with the leftmost column, shift rows upward when opportunities exist to form blocks of Xs Form cells. Look for opportunities to form cells such that all processing for each part occurs in a single cell. Facility Planning & Design Acronyms: ALDEP - Automated Layout Design Program PLANET - Plant Layout Analysis and Evaluation Technique CORELAP - Computerized Relationship Layout Planning CRAFT - Computerized Relative Allocation of Facilities Technique DCA – Direct Clustering Algorithm 9|P a g e Solved Problems in Facility Planning & Design 2012 ANSWER SHEET 1 PROBLEMS IN FACILITY PLANNING & DESIGN - QUALITATIVE NAME: _____________________________________ DATE: ____________________ 1. _______ 21. _________ 41. _________ 61. _________ 81. _________ 2. _______ 22. _________ 42. _________ 62. _________ 82. _________ 3. _______ 23. _________ 43. _________ 63. _________ 83. _________ 4. _______ 24. _________ 44. _________ 64. _ ________ 84. _________ 5. _______ 25. _________ 45. _________ 65. _________ 85. _________ 6. _______ 26. _________ 46. _________ 66. _________ 86. _________ 7. _______ 27. _________ 47. _________ 67. _________ 87. _________ 8. _______ 28. _________ 48. _________ 68. _________ 88. _________ 9. _______ 29. _________ 49. _________ 69. _________ 89. _________ 10. _______ 30. _________ 50. _________ 70. _________ 90. _________ 11. _______ 31. _________ 51. _________ 71. _________ 91. _________ 12. _______ 32. _________ 52. _________ 72. _________ 92. _________ 13. _______ 33. _________ 53. _________ 73. _________ 93. _________ 14. _______ 34. _________ 54. _________ 74. _________ 94. _________ 15. _______ 35. _________ 55. _________ 75. _________ 95. _________ 16. _______ 36. _________ 56. _________ 76. _________ 96. _________ 17. _______ 37. _________ 57. _________ 77. _________ 97. _________ 18. _______ 38. _________ 58. _________ 78. _________ 98. _________ 19. _______ 39. _________ 59. _________ 79. _________ 99. _________ 20. _______ 40. _________ 60. _________ 80. _________ 100. _________ SCORE: __________ PASSING RATE: 75% 10 | P a g e /100 X 100 = __________% Solved Problems in Facility Planning & Design 2012 PROBLEMS IN FACILITY PLANNING & DESIGN - QUALITATIVE 1. Using this space determination method, the present space requirements are converted to those required for the proposed layout. a. Roughed-Out Layout Method c. Space-Standards Method b. Production-Center Method d. Converting Method 2. It is the most complex Flexible Manufacturing System (FMS) layout which allows material to move among the machine centers in any order and typically includes several support stations such as tool interchange stations, pallet or fixture build stations, inspection stations, and chip/ coolant collection systems. a. Progressive Layout c. Closed-Loop Layout b. Open-Field Layout d. Ladder Layout 3. Which of the following is a walking industrial vehicle? a. Tractor Trailer c. Pallet Truck b. Straddle Carrier d. Hand Truck 4. How many lavatories do you need if a business organization has 41 to 60 employees? a. 2 c. 4 b. 3 d. 5 5. Drawing on the use of adjacency in the graph-based procedure, the _________________ is determined by summing the numerical values for all pairs of adjacent departments. a. Total Closeness Rating c. Total Adjacent Loads b. Weighted Placement Value d. Total Flow 6. What is the objective of designing the product, process, and schedule in relation to facilities planning? a. An effective production facility c. An efficient production system b. An efficient operations management d. An effective operations management 7. A principle of material handling which a material handling facility should be the result of a cohesive and structured unit of specific courses of action to determine what material needs to be moved, when, and where it will be moved, and how it will be moved. a. Planning Principle c. Standardization Principle 11 | P a g e b. System Principle d. Work Principle Solved Problems in Facility Planning & Design 2012 8. Cellular layout is a type of layout which – a. Groups machines into department according to their function. b. Groups machines into small assembly lines that produce families of parts. c. Allows production of larger lots by reducing set-up time. d. Encourages the use of larger and efficient machinery. 9. What is the preferred area requirement of the President’s Office? a. 80 – 110 sq. ft. c. 150 – 250 sq. ft. b. 100 – 150 sq. ft. d. 250 – 400 sq. ft. 10. The arrangement of all equipment, machinery, and furnishings within the structure. a. Facility Planning c. Layout Design b. Facility Location d. Handling System Design 11. Which of the following is not a characteristic of product layouts? a. Standardized product c. High material handling costs b. Sequential arrangements of machines d. Continuous production system 12. A graph is ___________ if it can be drawn so that its vertices are points in the plane and each edge can be drawn so that it intersects no other edges and passes through no other vertices. a. Open c. Planar b. Close d. Non-Planar 13. How many urinals do you need if a church has 401 to 700 members? a. 2 c. 4 b. 3 d. 5 14. This program is used to generate and evaluate plant layout which does not restrict the final layout to uniform shape, nor does it allow fixing departments to certain locations, resulting in unrealistic layouts. a. PLANET c. ALDEP b. CORELAP d. BLOCPLAN 15. A __________ is the quantity in which material is normally moved. a. Distance c. Block 12 | P a g e b. Unit Load d. Grid Solved Problems in Facility Planning & Design 2012 16. It is an analog model of the operations and inspections required in assembling a product. a. Operation Process Chart c. Assembly Chart b. Precedence Diagram d. Route Sheet 17. Which is not an automatic identification and recognition equipment? a. Bar Coding c. Magnetic Stripe b. Radio Frequency Tag d. Voice Headset 18. Which of the following assumptions is not associated with planar location models? a. A plane is an adequate approximation of a sphere. b. Any point in the plane is a valid location to consider. c. Fixed costs can be ignored. d. Travel costs are indirectly proportional to the planar distance used. 19. The algorithm in Relationship Diagramming for determining the placement of the new activity begins at the ____________ of the partial layout and evaluates all possible locations in counterclockwise order. a. Northeastern Edge c. Eastern Edge b. Northwestern Edge d. Western Edge 20. A product layout is characterized by – a. Narrow aisle ways c. Uses of general purpose equipment b. Organized by function d. Produces goods to customer order 21. An approach to scoring models in computerized layout evaluation which attempts to approximate the ―cost‖ of flow between activities. a. Adjacency-Based Scoring c. Sequence-Based Scoring b. Distance-Weighted Adjacency-Based Scoring d. Distance-Based Scoring 22. Which is not a characteristic of a process layout? a. Varied skills c. Low in-process b. General purpose d. Machine location 23. In a __________________ layout, work stations are arranged according to the general function they perform without regard to any particular product. a. Product c. Fixed Position 13 | P a g e b. Process d. Group Technology Solved Problems in Facility Planning & Design 2012 24. A layout procedure which is based on the space relationship diagram, modifying considerations, and practical limitations, a number of alternative layouts are designed and evaluated. a. Immer’s Basic Steps c. Reed’s Plant Layout Procedure b. Apple’s Plant Layout Procedure d. Muther’s Systematic Layout Planning 25. It is a form of flow pattern that is applicable when it is desired to terminate the flow very near the point where the flow originated. a. Straight Line Flow c. U-Shaped Flow b. L-Shaped Flow d. Circular Flow 26. It determines how an activity’s tangible fixed assets best support achieving the activity’s objectives. a. Facility Planning c. Layout Design b. Facility Location d. Handling System Design 27. Which of the following is not a type of crane? a. Jib c. Hoist b. Gantry d. Stacker 28. A type of layout used when the product is too large or cumbersome to move through the various processing steps. Consequently, rather than take the product to the processes, the processes are brought to the product. a. Fixed Position Layout c. Group Layout b. Product Layout d. Process Layout 29. It allows the storage location for a particular product to change or ―float‖ over time. a. Shared Storage c. Dedicated Storage b. Randomized Storage d. Class-Based Dedicated Storage 30. It is the design verification phase of product development and is used to demonstrate or prove aspects of a design. a. Prototyping c. Component part drawings b. Bill of Materials d. Assembly drawing 31. Typically, layout design problems do not have well-defined, unique, and optimum solutions. We are interested in obtaining a/ an ___________________. a. Absolute solution c. Best possible solution 14 | P a g e b. Most favorable solution d. Satisfactory solution Solved Problems in Facility Planning & Design 2012 32. How many lavatories do you need if a school has 101 to 200 students? a. 2 c. 4 b. 3 d. 5 33. This method evaluates different locations based on the load being transported and the distance. A single set of location coordinates is not identified. Instead, various locations are evaluated using a value that is measure of weight and distance. a. Factor Analysis Technique c. Load-Distance Technique b. Center of Gravity Technique d. Relationship Diagram Technique 34. A programmable equipment connected by an automated material handling system and controlled by a central computer. a. Flexible Manufacturing System c. Mixed Model Assembly Lines b. Group Technology d. Computer Method for Sequencing Operations 35. A layout construction program that uses the total closeness rating, which is the sum of all numerical values, assigned to the closeness relationships in a relationship chart between a department and all other departments. a. PLANET c. ALDEP b. CORELAP d. BLOCPLAN 36. It is the sum of the weighted ratings between the new activity to be placed in the layout and its neighbors in the layout. a. Boundary Length c. Corner Count b. Shape Ratio d. Placing Rating 37. It is the maximum work station time on the line. a. Desired Cycle Time c. Actual Cycle Time b. Lead Time d. Balanced Time 38. Regions defined by a graph are referred to as ____________. a. Faces c. Adjacents b. Edges d. Duals 39. A scale plan or model on which a thread is used to trace and measure the path of workers, materials or equipment during a specified sequence of events. a. String Diagram c. Relationship Chart 15 | P a g e b. Plant Layout d. Block Diagram Solved Problems in Facility Planning & Design 2012 40. What is the recommended range of stall width for standard car use? a. 8.5 to 9 ft. c. 9 to 10 ft. b. 8 to 8.5 ft. d. 10 to 11 ft. 41. Which of the items below is not a container? a. Pallet c. Tote Pan b. Skid d. Stretchwrap 42. It involves the assignment of specific storage locations or storage addresses for each product stored. a. Shared Storage c. Dedicated Storage b. Randomized Storage d. Class-Based Dedicated Storage 43. The arrangement of desired machinery and equipment of a plant, established or contemplated, in the way which will permit the easiest flow of materials, at the lowest cost and with the minimum of handling, in processing the product from the receipt of raw materials to the dispatch of the finished product. a. Line Balancing c. Plant Layout b. Block Diagram d. Relationship Chart 44. A tabular record for presenting quantitative data about the movements of workers, materials or equipment between any number of places over any given period of time. a. String Diagram c. Flow Diagram b. From-To Chart d. Travel Chart 45. It tells us how much to produce and when to produce. a. Product Design c. Process Design b. Schedule Design d. Facility Design 46. A layout procedure composed of three simple steps, which can be applied to any type of layout problem. These steps are: put the problem on paper, show lines of the flow, and convert flow lines to machine lines. a. Immer’s Basic Steps c. Reed’s Plant Layout Procedure b. Apple’s Plant Layout Procedure d. Muther’s Systematic Layout Planning 47. A ____________ is interpreted to mean adjacent. a. Open c. Line 16 | P a g e b. Close d. Circle Solved Problems in Facility Planning & Design 2012 48. How many water closets do you need if a business organization has 51 to 80 employees? a. 2 c. 4 b. 3 d. 5 49. A type of layout used when all machines involved in performing a particular process are grouped together and when there exist many low-volume, dissimilar products to be produced. a. Fixed Position Layout c. Group Layout b. Product Layout d. Process Layout 50. A method of determining space requirements where each work station is a production facility having its own receiving, shipping, production, and storage space requirements. a. Space Standards Method c. Calculation Method b. Conversion Method d. Flexible Method 51. How much space area requirements do you need if you will serve meals to 200 to 400 employees? a. 500 – 1000 sq. ft. c. 1,400 – 2,800 sq. ft. b. 800 – 1600 sq. ft. d. 2,400 – 3,900 sq. ft. 52. Which of these conveyors is not a belt conveyor? a. Chute Conveyor c. Telescoping Conveyor b. Flat Conveyor d. Magnetic Conveyor 53. It summarizes whether a part will be purchased or produced, how the production of a part will be achieved, what equipment will be used, and how long it will take to perform each operation. a. Operation Process Chart c. Assembly Chart b. Precedence Diagram d. Route Sheet 54. A principle of material handling which material handling flow should be as low as possible within the requirements for effectiveness and efficiency of a material handling system. a. Planning Principle c. Standardization Principle b. System Principle d. Work Principle 55. A type of layout used when production volumes for individual products are not sufficient thereby grouping products into logical product families. a. Fixed Position Layout c. Group Layout 17 | P a g e b. Product Layout d. Process Layout Solved Problems in Facility Planning & Design 2012 56. It provides information about the component parts of the product, make or buy decisions, part number, number of parts per product, and drawing references. a. Parts List c. Assembly Chart b. Bill of Materials d. Route Sheet 57. It consists of mechanism by which all interactions required by the layout are satisfied. a. Facility Planning c. Layout Design b. Facility Location d. Handling System Design 58. This a space determination method where templates or models are placed on the layout to obtain an estimate of the general configuration and space requirements. a. Roughed-Out Layout Method c. Space-Standards Method b. Production-Center Method d. Converting Method 59. A type of layout used when processes are located according to the processing sequence for the product. Material flows directly from a workstation to the adjacent workstation. a. Fixed Position Layout c. Group Layout b. Product Layout d. Process Layout 60. This location policy is referred to as _______________ if one particular time, different products use the same storage slot, albeit only one product occupies the slot when it is occupied. a. Shared Storage c. Dedicated Storage b. Randomized Storage d. Class-Based Dedicated Storage 61. It identifies the significant material flows and their corresponding paths. a. Factory Flow Analysis c. Line Analysis b. Group Analysis d. Tooling Analysis 62. It is the simplest form of flow pattern which when employed in a plant, separate receiving and shipping crews are normally required. a. Straight Line Flow c. U-Shaped Flow b. L-Shaped Flow d. Circular Flow 63. It contains the information concerning the structure of the product. a. Parts List c. Assembly Chart 18 | P a g e b. Bill of Materials d. Engineering Drawing Solved Problems in Facility Planning & Design 2012 64. Detailed design of individual products is influenced by? a. Function c. Manufacturing b. Material d. All of these 65. It is reduced if the assembly process occurs in a single dimension. a. Product Dimension c. Cost of Assembly b. Parts Standard d. Number of Parts 66. It depicts the probable movement of materials by corresponding lines superimposed on the floor plan of the area under study. a. Flow Process Chart c. Flow Diagram b. Multiproduct Process Chart d. From-To Chart 67. They denote assembly operations or sub-assemblies. a. Lines with single link c. Circles with several links b. Lines with several links d. Circles with single link 68. It consists of the mechanism by which all interactions required by the layout are satisfied e.g. materials, personnel, information, and equipment handling systems. a. Structure Design c. Layout Design b. Handling System Design d. Facility Location 69. Which of the following tools is used primarily in determining machine location for a process layout? a. Line Balancing c. Assembly Diagram b. Block Diagram d. Flow Diagram 70. Machines within a manufacturing cell are organized by – a. CORELAP c. Direct Clustering Algorithm b. Relationship Diagramming d. Block Diagramming 71. Cycle time is not – a. Daily operating time divided by the desired production b. The maximum allowable time at each work station c. How often items roll off the assembly d. The time required to complete a product from start to finish 19 | P a g e Solved Problems in Facility Planning & Design 2012 72. A common goal in designing process layouts is – a. Minimizing the number of workers b. Minimizing the idle time c. Minimizing material handling costs d. Balancing the work at each station 73. Mixed model assembly lines --a. Are simple to balance than single model assembly lines. b. Are usually U-shaped or S-shaped layouts. c. Require a more specialized workforce. d. Are most efficient when production of one type is completely finished before another type of model is introduced. 74. This drawing provides part specifications and dimensions in sufficient detail for manufacturing. a. Perspective Drawing c. Engineering Drawing b. Exploded Drawing d. Photograph of the Product 75. It establishes the prerequisite assembly steps that must be completed before performing a given assembly step. a. Operation Process Chart c. Assembly Chart b. Precedence Diagram d. Route Sheet 76. It refers to the overall design concepts or morphologies embedded within the facilities plan a. Parametric design c. Detailed design b. Conceptual design d. Design Program 77. What is the recommended range of stall width for luxury and elderly car use? a. 8.5 to 9 ft. c. 9 to 10 ft. b. 8 to 8.5 ft. d. 10 to 11 ft. 78. A principle of material handling which you try to reduce the ratio of equipment weight to product weight and suggest not to buy equipment that is bigger than necessary. a. Capacity Principle c. Unit Load Principle b. Standardization Principle d. Dead Weight Principle 79. How much space area requirements do you need if you will serve meals to 401 to 800 employees? a. 500 – 1000 sq. ft. c. 1,400 – 2,800 sq. ft. 20 | P a g e b. 800 – 1600 sq. ft. d. 2,400 – 3,900 sq. ft. Solved Problems in Facility Planning & Design 2012 80. What is the recommended reception area that can accommodate a reception and 6 – 8 people? a. 125 – 200 sq. ft. c. 300 – 400 sq. ft. b. 200 – 300 sq. ft. d. 400 – 500 sq. ft. 81. It is obtained by dividing the usable cube by the exterior envelope of the container. a. Container Nesting Ratio c. Trailer Space Utilization b. Container Space Utilization d. Storage Space Efficiency 82. It is determined by dividing the overall container height by the nested height. a. Container Nesting Ratio c. Trailer Space Utilization b. Container Space Utilization d. Storage Space Efficiency 83. It is the ratio of usable cube divided by the storage cube. a. Container Nesting Ratio c. Trailer Space Utilization b. Container Space Utilization d. Storage Space Efficiency 84. The total number of containers along the length and width of the trailer and the container stacked vertically. a. Container Nesting Ratio c. Trailer Space Utilization b. Container Space Utilization d. Storage Space Efficiency 85. A space determination method consists of a single machine plus all the associated equipment and space required for its operation. Work space, additional maintenance space, and storage space are added to the space requirements for the machine. a. Roughed-Out Layout Method c. Space-Standards Method b. Production-Center Method d. Converting Method 86. Which of the following is not an automated industrial vehicle? a. Unit Load Carrier c. Sorting Transfer Vehicle b. Mobile Yard Crane d. Automated Electrified Vehicle 87. Which of the following is a type of an Operator-to-Stock Retrieval Equipment? a. Picking Cart c. Vertical Lift Module 21 | P a g e b. Carousels d. Automatic Dispenser Solved Problems in Facility Planning & Design 2012 88. It is a quantitative method of locating a facility at the center of the movement in a geographic area based on weight and distance. It identifies a set of coordinates designating a central location on a map relative to all other locations. a. Factor Analysis Technique c. Load-Distance Technique b. Center of Gravity Technique d. Relationship Diagram Technique 89. Are physical restrictions on the order in which operations are performed on the assembly line? a. Precedence Requirements c. Balance Delays b. Station Times d. Production Time Available 90. It is generally agreed that effective facilities planning can reduce material handling costs by --a. 5 – 10% c. 30 – 40% b. 10 – 30% d. 50 – 70% 91. The quantity of equipment required for an operation. a. Equipment Effectiveness c. Equipment Fraction b. Equipment Efficiency d. Equipment Planning 92. Which of the following is/ are way/s that we can accommodate a 20 second task in an 18 second cycle time? a. Share the task c. Use a more skilled worker b. Use parallel work stations d. All of these 93. The term _____________ is used as a measure of the number of storages and retrievals performed per time period. a. Space c. Size b. Cost d. Throughput 94. It takes a load summary chart and block diagram as input and then makes pair wise exchanges of departments until no improvements in cost or non-adjacency score can be found. a. CORELAP c. CRAFT b. DCA d. PROMODEL 95. It is an adaptation of the familiar mileage chart appearing on most road maps which normally contains numbers representing some measure of the material flow between two machines, departments, buildings, or sites. a. Flow Process Chart c. Flow Diagram 22 | P a g e b. Multiproduct Process Chart d. From-To Chart Solved Problems in Facility Planning & Design 2012 96. It is the placement of a facility with respect to customers, suppliers, and other facilities with which it interfaces. a. Facility Planning c. Layout Design b. Facility Location d. Handling System Design 97. It is the time required to complete an item. a. Desired Cycle Time c. Actual Cycle Time b. Lead Time d. Balanced Time 98. It is a mechanized device to move materials in relatively large quantities between specific locations over a fixed path. a. Conveyor c. Pallet Truck b. Unit Load Carrier d. Automated Guided Vehicle 99. It is a way to visualize the amount of movement that occurs between departments. a. Relationship Diagramming c. Line Balancing b. Block Diagramming d. Digital Clustering Algorithm 100. It covers the system’s ability to be changed to produce new product types and ability to change the order of operations executed on a part. a. Routing Flexibility c. Machine Flexibility 23 | P a g e b. Material Flexibility d. Flow Flexibility Solved Problems in Facility Planning & Design 2012 SOLVED PROBLEMS IN FACILITY PLANNING & DESIGN - QUALITATIVE 1. Using this space determination method, the present space requirements are converted to those required for the proposed layout. a. Roughed-Out Layout Method c. Space-Standards Method b. Production-Center Method d. Converting Method Answer: d. Converting Method 2. It is the most complex and flexible FMS layout which allows material to move among the machine centers in any order and typically includes several support stations such as tool interchange stations, pallet or fixture build stations, inspection stations, and chip/ coolant collection systems. a. Progressive Layout c. Closed-Loop Layout b. Open-Field Layout d. Ladder Layout Answer: b. Open-Field Layout 3. Which of the following is a walking industrial vehicle? a. Tractor Trailer c. Pallet Truck b. Straddle Carrier d. Hand Truck Answer: d. Hand Truck 4. How many lavatories do you need if a business organization has 41 to 60 employees? a. 2 c. 4 b. 3 d. 5 Answer: b. 3 5. Drawing on the use of adjacency in the graph-based procedure, the _________________ is determined by summing the numerical values for all pairs of adjacent departments. a. Total Closeness Rating c. Total Adjacent Loads b. Weighted Placement Value d. Total Flow Answer: c. Total Adjacent Loads 6. What is the objective of designing the product, process, and schedule in relation to facilities planning? a. An effective production facility c. An efficient production system Answer: c. An efficient production system 24 | P a g e b. An efficient operations management d. An effective operations management Solved Problems in Facility Planning & Design 2012 7. A principle of material handling which a material handling facility should be the result of a cohesive and structured unit of specific courses of action to determine what material needs to be moved, when, and where it will be moved, and how it will be moved. a. Planning Principle c. Standardization Principle b. System Principle d. Work Principle Answer: a. Planning Principle 8. Cellular layout is a type of layout which – a. Groups machines into department according to their function. b. Groups machines into small assembly lines that produce families of parts. c. Allows production of larger lots by reducing set-up time. d. Encourages the use of larger and efficient machinery. Answer: b. Groups machines into small assembly lines that produce families of parts. 9. What is the preferred area requirement of the President’s Office? a. 80 – 110 sq. ft. c. 150 – 250 sq. ft. b. 100 – 150 sq. ft. d. 250 – 400 sq. ft. Answer: d. 250 – 400 sq. ft. 10. The arrangement of all equipment, machinery, and furnishings within the structure. a. Facility Planning c. Layout Design b. Facility Location d. Handling System Design Answer: c. Layout Design 11. Which of the following is not a characteristic of product layouts? a. Standardized product c. High material handling costs b. Sequential arrangements of machines d. Continuous production system Answer: c. High material handling costs 12. A graph is ___________ if it can be drawn so that its vertices are points in the plane and each edge can be drawn so that it intersects no other edges and passes through no other vertices. a. Open c. Planar Answer: c. Planar 25 | P a g e b. Close d. Non-Planar Solved Problems in Facility Planning & Design 2012 13. How many urinals do you need if a church has 401 to 700 members? a. 2 c. 4 b. 3 d. 5 Answer: c. 4 14. This program is used to generate and evaluate plant layout which does not restrict the final layout to uniform shape, nor does it allow fixing departments to certain locations, resulting in unrealistic layouts. a. PLANET c. ALDEP b. CORELAP d. BLOCPLAN Answer: a. PLANET 15. A __________ is the quantity in which material is normally moved. a. Distance c. Block b. Unit Load d. Grid Answer: b. Unit Load 16. It is an analog model of the operations and inspections required in assembling a product. a. Operation Process Chart c. Assembly Chart b. Precedence Diagram d. Route Sheet Answer: c. Assembly Chart 17. Which is not an automatic identification and recognition equipment? a. Bar Coding c. Magnetic Stripe b. Radio Frequency Tag d. Voice Headset Answer: d. Voice Headset 18. Which of the following assumptions is not associated with planar location models? a. A plane is an adequate approximation of a sphere. b. Any point in the plane is a valid location to consider. c. Fixed costs can be ignored. d. Travel costs are indirectly proportional to the planar distance used. Answer: d. Travel costs are indirectly proportional to the planar distance used. 26 | P a g e Solved Problems in Facility Planning & Design 2012 19. The algorithm in Relationship Diagramming for determining the placement of the new activity begins at the ____________ of the partial layout and evaluates all possible locations in counterclockwise order. a. Northeastern Edge c. Eastern Edge b. Northwestern Edge d. Western Edge Answer: d. Western Edge 20. A product layout is characterized by – a. Narrow aisle ways c. Uses of general purpose equipment b. Organized by function d. Produces goods to customer order Answer: a. Narrow aisle ways 21. An approach to scoring models in computerized layout evaluation which attempts to approximate the ―cost‖ of flow between activities. a. Adjacency-Based Scoring c. Sequence-Based Scoring b. Distance-Weighted Adjacency-Based Scoring d. Distance-Based Scoring Answer: d. Distance-Based Scoring 22. Which is not a characteristic of a process layout? a. Varied skills c. Low in-process b. General purpose d. Machine location layout Answer: c. Low in-process 23. In a __________________ layout, work stations are arranged according to the general function they perform without regard to any particular product. a. Product c. Fixed Position b. Process d. Group Technology Answer: a. Product 24. A layout procedure which is based on the space relationship diagram, modifying considerations, and practical limitations, a number of alternative layouts are designed and evaluated. a. Immer’s Basic Steps c. Reed’s Plant Layout Procedure Answer: d. Muther’s Systematic Layout Planning 27 | P a g e b. Apple’s Plant Layout Procedure d. Muther’s Systematic Layout Planning Solved Problems in Facility Planning & Design 2012 25. It is a form of flow pattern that is applicable when it is desired to terminate the flow very near the point where the flow originated. a. Straight Line Flow c. U-Shaped Flow b. L-Shaped Flow d. Circular Flow Answer: d. Circular Flow 26. It determines how an activity’s tangible fixed assets best support achieving the activity’s objectives. a. Facility Planning c. Layout Design b. Facility Location d. Handling System Design Answer: a. Facility Planning 27. Which of the following is not a type of crane? a. Jib c. Hoist b. Gantry d. Stacker Answer: c. Hoist 28. A type of layout used when the product is too large or cumbersome to move through the various processing steps. Consequently, rather than take the product to the processes, the processes are brought to the product. a. Fixed Position Layout c. Group Layout b. Product Layout d. Process Layout Answer: a. Fixed Position Layout 29. It allows the storage location for a particular product to change or ―float‖ over time. a. Shared Storage c. Dedicated Storage b. Randomized Storage d. Class-Based Dedicated Storage Answer: b. Randomized Storage 30. It is the design verification phase of product development and is used to demonstrate or prove aspects of a design. a. Prototyping c. Component part drawings Answer: a. Prototyping 28 | P a g e b. Bill of Materials d. Assembly drawing Solved Problems in Facility Planning & Design 2012 31. Typically, layout design problems do not have well-defined, unique, and optimum solutions. We are interested in obtaining a/ an ___________________. a. Absolute solution c. Best possible solution b. Most favorable solution d. Satisfactory solution Answer: d. Satisfactory solution 32. How many lavatories do you need if a school has 101 to 200 students? a. 2 c. 4 b. 3 d. 5 Answer: a. 2 33. This method evaluates different locations based on the load being transported and the distance. A single set of location coordinates is not identified. Instead, various locations are evaluated using a value that is measure of weight and distance. a. Factor Analysis Technique c. Load-Distance Technique b. Center of Gravity Technique d. Relationship Diagram Technique Answer: c. Load-Distance Technique 34. A programmable equipment connected by an automated material handling system and controlled by a central computer. a. Flexible Manufacturing System c. Mixed Model Assembly Lines b. Group Technology d. Computer Method for Sequencing Operations Answer: a. Flexible Manufacturing System 35. A layout construction program that uses the total closeness rating, which is the sum of all numerical values, assigned to the closeness relationships in a relationship chart between a department and all other departments. a. PLANET c. ALDEP b. CORELAP d. BLOCPLAN Answer: b. CORELAP 36. It is the sum of the weighted ratings between the new activity to be placed in the layout and its neighbors in the layout. a. Boundary Length c. Corner Count Answer: d. Placing Rating 29 | P a g e b. Shape Ratio d. Placing Rating Solved Problems in Facility Planning & Design 2012 37. It is the maximum work station time on the line. a. Desired Cycle Time c. Actual Cycle Time b. Lead Time d. Balanced Time Answer: c. Actual Cycle Time 38. Regions defined by a graph are referred to as ____________. a. Faces c. Adjacents b. Edges c. Duals Answer: a. Faces 39. A scale plan or model on which a thread is used to trace and measure the path of workers, materials or equipment during a specified sequence of events. a. String Diagram c. Relationship Chart b. Plant Layout d. Block Diagram Answer: a. String Diagram 40. What is the recommended range of stall width for standard car use? a. 8.5 to 9 ft. c. 9 to 10 ft. b. 8 to 8.5 ft. d. 10 to 11 ft. Answer: a. 8.5 to 9 ft. 41. Which of the items below is not a container? a. Pallet c. Tote Pan b. Skid d. Stretchwrap Answer: d. Stretchwrap 42. It involves the assignment of specific storage locations or storage addresses for each product stored. a. Shared Storage c. Dedicated Storage b. Randomized Storage d. Class-Based Dedicated Storage Answer: c. Dedicated Storage 43. The arrangement of desired machinery of a plant, established or contemplated, in the way which will permit the easiest flow of materials, at the lowest cost and with the minimum of handling, in processing the product from the receipt of raw materials to the dispatch of the finished product. a. Line Balancing c. Plant Layout 30 | P a g e b. Block Diagram d. Relationship Chart Solved Problems in Facility Planning & Design 2012 Answer: c. Plant Layout 44. A tabular record for presenting quantitative data about the movements of workers, materials or equipment between any number of places over any given period of time. a. String Diagram c. Flow Diagram b. From-To Chart d. Travel Chart Answer: d. Travel Chart 45. It tells us how much to produce and when to produce. a. Product Design c. Process Design b. Schedule Design d. Facility Design Answer: b. Schedule Design 46. A layout procedure composed of three simple steps, which can be applied to any type of layout problem. These steps are: put the problem on paper, show lines of the flow, and convert flow lines to machine lines. a. Immer’s Basic Steps c. Reed’s Plant Layout Procedure b. Apple’s Plant Layout Procedure d. Muther’s Systematic Layout Planning Answer: a. Immer’s Basic Steps 47. A ____________ is interpreted to mean adjacent. a. Open c. Line b. Close d. Circle Answer: b. Close 48. How many water closets do you need if a business organization has 51 to 80 employees? a. 2 c. 4 b. 3 d. 5 Answer: c. 4 49. A type of layout used when all machines involved in performing a particular process are grouped together and when there exist many low-volume, dissimilar products to be produced. a. Fixed Position Layout c. Group Layout Answer: d. Process Layout 31 | P a g e b. Product Layout d. Process Layout Solved Problems in Facility Planning & Design 2012 50. A method of determining space requirements where each work station is a production facility having its own receiving, shipping, production, and storage space requirements. a. Space Standards Method c. Calculation Method b. Conversion Method d. Flexible Method Answer: c. Calculation Method 51. How much space area requirements do you need if you will serve meals to 200 to 400 employees? a. 500 – 1000 sq. ft. c. 1,400 – 2,800 sq. ft. b. 800 – 1600 sq. ft. d. 2,400 – 3,900 sq. ft. Answer: b. 800 – 1600 sq. ft. 52. Which of these conveyors is not a belt conveyor? a. Chute Conveyor c. Telescoping Conveyor b. Flat Conveyor d. Magnetic Conveyor Answer: a. Chute Conveyor 53. It summarizes whether a part will be purchased or produced, how the production of a part will be achieved, what equipment will be used, and how long it will take to perform each operation. a. Operation Process Chart c. Assembly Chart b. Precedence Diagram d. Route Sheet Answer: d. Route Sheet 54. A principle of material handling which material handling flow should be as low as possible within the requirements for effectiveness and efficiency of a material handling system. a. Planning Principle c. Standardization Principle b. System Principle d. Work Principle Answer: d. Work Principle 55. A type of layout used when production volumes for individual products are not sufficient thereby grouping products into logical product families. a. Fixed Position Layout c. Group Layout Answer: c. Group Layout 32 | P a g e b. Product Layout d. Process Layout Solved Problems in Facility Planning & Design 2012 56. It provides information about the component parts of the product, make or buy decisions, part number, number of parts per product, and drawing references. a. Parts List c. Assembly Chart b. Bill of Materials d. Route Sheet Answer: a. Parts List 57. It consists of mechanism by which all interactions required by the layout are satisfied. a. Facility Planning c. Layout Design b. Facility Location d. Handling System Design Answer: d. Handling System Design 58. This a space determination method where templates or models are placed on the layout to obtain an estimate of the general configuration and space requirements. a. Roughed-Out Layout Method c. Space-Standards Method b. Production-Center Method d. Converting Method Answer: a. Roughed-Out Layout Method 59. A type of layout used when processes are located according to the processing sequence for the product. Material flows directly from a workstation to the adjacent workstation. a. Fixed Position Layout c. Group Layout b. Product Layout d. Process Layout Answer: b. Product Layout 60. This location policy is referred to as _______________ if one particular time, different products use the same storage slot, albeit only one product occupies the slot when it is occupied. a. Shared Storage c. Dedicated Storage b. Randomized Storage d. Class-Based Dedicated Storage Answer: a. Shared Storage 61. It identifies the significant material flows and their corresponding paths. a. Factory Flow Analysis c. Line Analysis Answer: a. Factory Flow Analysis 33 | P a g e b. Group Analysis d. Tooling Analysis Solved Problems in Facility Planning & Design 2012 62. It is the simplest form of flow pattern which when employed in a plant, separate receiving and shipping crews are normally required. a. Straight Line Flow c. U-Shaped Flow b. L-Shaped Flow d. Circular Flow Answer: a. Straight Line Flow 63. It contains the information concerning the structure of the product. a. Parts List c. Assembly Chart b. Bill of Materials d. Engineering Drawing Answer: b. Bill of Materials 64. Detailed design of individual products is influenced by? a. Function c. Manufacturing b. Material d. All of these Answer: d. All of these 65. It is reduced if the assembly process occurs in a single dimension. a. Product Dimension c. Cost of Assembly b. Parts Standard d. Number of Parts Answer: c. Cost of Assembly 66. It depicts the probable movement of materials by corresponding lines superimposed on the floor plan of the area under study. a. Flow Process Chart c. Flow Diagram b. Multiproduct Process Chart d. From-To Chart Answer: c. Flow Diagram 67. They denote assembly operations or sub-assemblies. a. Lines with single link c. Circles with several links b. Lines with several links d. Circles with single link Answer: c. Circles with several links 68. It consists of the mechanism by which all interactions required by the layout are satisfied e.g. materials, personnel, information, and equipment handling systems. a. Structure Design c. Layout Design 34 | P a g e b. Handling System Design d. Facility Location Solved Problems in Facility Planning & Design 2012 Answer: b. Handling System Design 69. Which of the following tools is used primarily in determining machine location for a product layout? a. Line Balancing c. Assembly Diagram b. Block Diagram d. Flow Diagram Answer: a. Line Balancing 70. Machines within a manufacturing cell are organized by – a. CORELAP c. Direct Clustering Algorithm b. Relationship Diagramming d. Block Diagramming Answer: c. Direct Clustering Algorithm 71. Cycle time is not – a. Daily operating time divided by the desired production b. The maximum allowable time at each work station c. How often items roll off the assembly d. The time required to complete a product from start to finish Answer: d. The time required to complete a product from start to finish 72. A common goal in designing process layouts is – a. Minimizing the number of workers b. Minimizing the idle time c. Minimizing material handling costs d. Balancing the work at each station Answer: c. Minimizing material handling costs 73. Mixed model assembly lines --a. Are simple to balance than single model assembly lines. b. Are usually U-shaped or S-shaped layouts. c. Require a more specialized workforce. d. Are most efficient when production of one type is completely finished before another type of model is introduced. Answer: b. Are usually U-shaped or S-shaped layouts. 74. This drawing provides part specifications and dimensions in sufficient detail for manufacturing. a. Perspective Drawing c. Engineering Drawing 35 | P a g e b. Exploded Drawing d. Photograph of the Product Solved Problems in Facility Planning & Design 2012 Answer: c. Engineering Drawing 75. It establishes the prerequisite assembly steps that must be completed before performing a given assembly step. a. Operation Process Chart c. Assembly Chart b. Precedence Diagram d. Route Sheet Answer: b. Precedence Diagram 76. It refers to the overall design concepts or morphologies embedded within the facilities plan a. Parametric design c. Detailed design b. Conceptual design d. Design Program Answer: a. Parametric design 77. What is the recommended range of stall width for luxury and elderly car use? a. 8.5 to 9 ft. c. 9 to 10 ft. b. 8 to 8.5 ft. d. 10 to 11 ft. Answer: c. 9 to 10 ft. 78. A principle of material handling which you try to reduce the ratio of equipment weight to product weight and suggest not to buy equipment that is bigger than necessary. a. Capacity Principle c. Unit Load Principle b. Standardization Principle d. Dead Weight Principle Answer: d. Dead Weight Principle 79. How much space area requirements do you need if you will serve meals to 401 to 800 employees? a. 500 – 1000 sq. ft. c. 1,400 – 2,800 sq. ft. b. 800 – 1600 sq. ft. d. 2,400 – 3,900 sq. ft. Answer: c. 1,400 – 2,800 sq. ft. 80. What is the recommended reception area that can accommodate a reception and 6 – 8 people? a. 125 – 200 sq. ft. c. 300 – 400 sq. ft. Answer: b. 200 – 300 sq. ft. 36 | P a g e b. 200 – 300 sq. ft. d. 400 – 500 sq. ft. Solved Problems in Facility Planning & Design 2012 81. It is obtained by dividing the usable cube by the exterior envelope of the container. a. Container Nesting Ratio c. Trailer Space Utilization b. Container Space Utilization d. Storage Space Efficiency Answer: b. Container Space Utilization 82. It is determined by dividing the overall container height by the nested height. a. Container Nesting Ratio c. Trailer Space Utilization b. Container Space Utilization d. Storage Space Efficiency Answer: a. Container Nesting Ratio 83. It is the ratio of usable cube divided by the storage cube. a. Container Nesting Ratio c. Trailer Space Utilization b. Container Space Utilization d. Storage Space Efficiency Answer: d. Storage Space Efficiency 84. The total number of containers along the length and width of the trailer and the container stacked vertically. a. Container Nesting Ratio c. Trailer Space Utilization b. Container Space Utilization d. Storage Space Efficiency Answer: c. Trailer Space Utilization 85. A space determination method consists of a single machine plus all the associated equipment and space required for its operation. Work space, additional maintenance space, and storage space are added to the space requirements for the machine. a. Roughed-Out Layout Method c. Space-Standards Method b. Production-Center Method d. Converting Method Answer: b. Production-Center Method 86. Which of the following is not an automated industrial vehicle? a. Unit Load Carrier c. Sorting Transfer Vehicle b. Mobile Yard Crane d. Automated Electrified Vehicle Answer: b. Mobile Yard Crane 87. Which of the following is a type of an Operator-to-Stock Retrieval Equipment? a. Picking Cart c. Vertical Lift Module 37 | P a g e b. Carousels d. Automatic Dispenser Solved Problems in Facility Planning & Design 2012 Answer: a. Picking Cart 88. It is a quantitative method of locating a facility at the center of the movement in a geographic area based on weight and distance. It identifies a set of coordinates designating a central location on a map relative to all other locations. a. Factor Analysis Technique c. Load-Distance Technique b. Center of Gravity Technique d. Relationship Diagram Technique Answer: b. Center of Gravity Technique 89. Are physical restrictions on the order in which operations are performed on the assembly line? a. Precedence Requirements c. Balance Delays b. Station Times d. Production Time Available Answer: a. Precedence Requirements 90. It is generally agreed that effective facilities planning can reduce material handling costs by --a. 5 – 10% c. 30 – 40% b. 10 – 30% d. 50 – 70% Answer: b. 10 – 30% 91. The quantity of equipment required for an operation. a. Equipment Effectiveness c. Equipment Fraction b. Equipment Efficiency d. Equipment Planning Answer: c. Equipment Fraction 92. Which of the following is/ are way/s that we can accommodate a 20 second task in an 18 second cycle time? a. Share the task c. Use a more skilled worker b. Use parallel work stations d. All of these Answer: d. All of these 93. The term _____________ is used as a measure of the number of storages and retrievals performed per time period. a. Space c. Size Answer: d. Throughput 38 | P a g e b. Cost d. Throughput Solved Problems in Facility Planning & Design 2012 94. It takes a load summary chart and block diagram as input and then makes pair wise exchanges of departments until no improvements in cost or non-adjacency score can be found. a. CORELAP c. CRAFT b. DCA d. PROMODEL Answer: c. CRAFT 95. It is an adaptation of the familiar mileage chart appearing on most road maps which normally contains numbers representing some measure of the material flow between two machines, departments, buildings, or sites. a. Flow Process Chart c. Flow Diagram b. Multiproduct Process Chart d. From-To Chart Answer: d. From-To Chart 96. It is the placement of a facility with respect to customers, suppliers, and other facilities with which it interfaces. a. Facility Planning c. Layout Design b. Facility Location d. Handling System Design Answer: b. Facility Location 97. It is the time required to complete an item. a. Desired Cycle Time c. Actual Cycle Time b. Lead Time d. Balanced Time Answer: b. Lead Time 98. It is a mechanized device to move materials in relatively large quantities between specific locations over a fixed path. a. Conveyor c. Pallet Truck b. Unit Load Carrier d. Automated Guided Vehicle Answer: a. Conveyor 99. It is a way to visualize the amount of movement that occurs between departments. a. Relationship Diagramming c. Line Balancing Answer: b. Block Diagramming 39 | P a g e b. Block Diagramming d. Digital Clustering Algorithm Solved Problems in Facility Planning & Design 2012 100. It covers the system’s ability to be changed to produce new product types and ability to change the order of operations executed on a part. a. Routing Flexibility c. Machine Flexibility Answer: c. Machine Flexibility 40 | P a g e b. Material Flexibility d. Flow Flexibility Solved Problems in Facility Planning & Design 2012 ANSWER SHEET 2 PROBLEMS IN FACILITY PLANNING & DESIGN - QUANTITATIVE NAME: _____________________________________ DATE: ____________________ 1. _______ 21. _________ 41. _________ 61. _________ 81. _________ 2. _______ 22. _________ 42. _________ 62. _________ 82. _________ 3. _______ 23. _________ 43. _________ 63. _________ 83. _________ 4. _______ 24. _________ 44. _________ 64. _________ 84. _________ 5. _______ 25. _________ 45. _________ 65. _________ 85. _________ 6. _______ 26. _________ 46. _________ 66. _________ 86. _________ 7. _______ 27. _________ 47. _________ 67. _________ 87. _________ 8. _______ 28. _________ 48. _________ 68. _________ 88. _________ 9. _______ 29. _________ 49. _________ 69. _________ 89. _________ 10. _______ 30. _________ 50. _________ 70. _________ 90. _________ 11. _______ 31. _________ 51. _________ 71. _________ 91. _________ 12. _______ 32. _________ 52. _________ 72. _________ 92. _________ 13. _______ 33. _________ 53. _________ 73. _________ 93. _________ 14. _______ 34. _________ 54. _________ 74. _________ 94. _________ 15. _______ 35. _________ 55. _________ 75. _________ 95. _________ 16. _______ 36. _________ 56. _________ 76. _________ 96. _________ 17. _______ 37. _________ 57. _________ 77. _________ 97. _________ 18. _______ 38. _________ 58. _________ 78. _________ 98. _________ 19. _______ 39. _________ 59. _________ 79. _________ 99. _________ 20. _______ 40. _________ 60. _________ 80. _________ 100. _________ SCORE: __________ PASSING RATE: 75% 41 | P a g e /100 X 100 = __________% Solved Problems in Facility Planning & Design 2012 PROBLEMS IN FACILITY PLANNING & DESIGN - QUANTITATIVE 1. Belinda Fashion Wear is a small chain of stores specializing in fashion clothing. The company currently has five stores in Manila, Quezon City, and Caloocan, and it wants to open new store in of four new mall locations in the other nearby cities. A consulting firm has been hired to help the company decide where to locate new store. The company has indicated five factors that are important to its decision, including proximity of a college, community median income, mall vehicle traffic flow and parking, quality and number of stores in the mall, and proximity of other malls or shopping areas. The consulting firm had the company weight the importance of each factor. The consultant had visited each potential location and rated them according to each factor, as follows: Location factors College proximity Median income Vehicle traffic Mall quality and size Proximity of other shopping Weight 0.30 0.25 0.25 0.10 0.10 Mall 1 40 75 60 90 80 Mall 2 60 80 90 100 30 Mall 3 90 65 79 80 50 Mall 4 60 90 85 90 70 Given that all sites have basically the same leasing cost and labor and operating cost, what is the recommended location based on rating factors? a. Mall 1 c. Mall 3 b. Mall 2 d. Mall 4 2. Zachtech Computers manufacture computer components such as chips, circuit boards, motherboards, keyboards, and LCD panels and sells them around the world. It wants to construct a new distribution center in Asia to serve emerging Asian markets. It has identified sites in Shanghai, Hong Kong and Singapore and has rated the important location factors for each site as follows: Location Factors Political Stability Economic Growth Port Facilities Container support Land and construction cost Transportation/Distribution Duties and tariffs Trade regulations Airline Service Area roads Weight 0.25 0.18 0.15 0.10 0.08 0.08 0.07 0.05 0.02 0.02 Shanghai 50 90 60 50 90 50 70 70 60 60 Hong Kong 60 70 95 80 20 80 90 95 80 70 Singapore 90 75 90 90 30 70 90 95 70 80 Recommend a site including its total score rating based on these location factors and ratings. a. Hongkong, 72 c. Singapore, 81 42 | P a g e b. Hongkong, 82 d. Shanghai, 79 Solved Problems in Facility Planning & Design 2012 3. Cradle University is going to construct a new student center and athletic complex that will include a bookstore, post office, theaters, markets, mini-mall, meeting rooms, swimming pool, and weight and exercise rooms. The university administration has hired a site selection specialist has identified four sites on campus and has rated important location factors for each site as follows: Location Factors Proximity to housing Student traffic Parking availability Plot size, terrain Infrastructure Off-campus accessibility Proximity dining facilities Visitor traffic Landscape/aesthetics Weight 0.23 0.22 0.16 0.12 0.10 0.06 0.05 0.04 0.02 South 70 75 90 80 50 90 60 70 50 West A 90 80 60 70 60 70 80 80 40 West B 65 60 80 90 40 70 70 65 60 East 85 85 70 75 60 70 90 55 70 Recommend a best site based on these location factors and ratings. a. South c. West B b. West A d. East 4. Zhan Electronics is going to construct new P1.2 billion semi-conductor plant and has selected four Export Processing Zone Areas as potential sites. The important location factors and ratings for each town are as follows: Location Factors Work Ethics Quality of Life Labor Laws/Unionization Infrastructure Education Labor skill and Education Cost of Living Taxes Incentive Package Government Regulation Environmental Regulation Transportation Space for Expansion Urban Proximity Weight 0.18 0.16 0.12 0.10 0.08 0.07 0.06 0.05 0.05 0.03 0.03 0.03 0.02 0.02 Sta. Rosa 80 75 90 60 80 75 70 60 90 40 65 90 90 60 Lipa 90 85 90 50 90 65 80 70 95 50 60 80 95 90 Bataan 70 95 60 60 85 70 85 55 70 65 70 95 90 70 Recommend a site based on these location factors and ratings. a. Sta. Rosa c. Bataan 43 | P a g e b. Lipa c. Subic Subic 75 90 70 70 95 80 75 60 80 55 80 80 90 80 Solved Problems in Facility Planning & Design 2012 5. The Charlie Forwarding Company wants to build a new distribution center in Central Luzon. The center needs to be in the vicinity of uncongested Aurora, Bataan, and Nueva Ecija. The coordinates of this sites and the number of weekly packages that flow to each are as follows: Aurora X = 17 Y = 30 W = 17,000 Bataan X = 20 Y=8 W = 12,000 Nueva Ecija X = 30 Y = 14 W = 9,000 What are the coordinates of the center of these 3 provinces? a. (25, 22) c. (24, 17) b. (18, 22) d. (21, 19) 6. The Inah Burger restaurant chain uses a distribution center to prepare the food ingredients it provides its individual restaurants. The company is attempting to determine the location for new distribution center that will service five restaurants. The grid-map coordinates of the five restaurants and the annual numbers of 40-foot trailer trucks transported to each restaurant are as follows: Restaurants 1 2 3 4 5 X 100 210 250 300 400 Y 300 180 400 150 200 Annual Truck Shipments 30 25 15 20 18 Determine the coordinates of the location using the center-of -gravity method. a. (233, 242) c. (243, 231) b. (236, 244) c. (245, 230) 7. The Inah Burger restaurant chain in the previous problem is considering three potential sites. With the following grid-map coordinates for its new distribution center: A( 350, 300). B. (150, 250), and C (250, 300). Determine the best location using the load-distance formula. a. Site A, LD = 15,205 c. Site C, LD = 15,570 b. Site B, LD = 15,325 c. Site C, LD = 15,255 8. James Company is attempting to determine the location for a new outlet mall. The region where the outlet mall will be constructed includes four towns, which together have a sizable population base. The grid map coordinates of the four towns in Cavite and the populations of each are as follows: Town X Y Population (10,000s) Rosario 30 60 6.5 Dasmarinas 50 40 4.2 Trece Martirez 10 70 5.9 Silang 40 30 3.5 Determine best location for the outlet mall using the center-of -gravity method. a. (32, 56) c. (30, 54) 44 | P a g e b. (33, 55) d. (31, 52) Solved Problems in Facility Planning & Design 2012 9. Ray-Mart, a discount store chain, wants to build a new superstore in an area in Batangas near four small towns with population between 8,000 and 42,000. The coordinates (in miles) of these four towns and the market population in each are as follows: Bauan X = 12 Y = 20 W = 26,000 Ibaan X = 18 Y = 18 W = 14,000 Mabini X = 30 Y=7 W = 9,500 Laurel X = 32 Y = 25 W = 12,000 Determine the coordinates of the best site using the center of gravity technique. a. (24, 21) c. (23, 22) b. (21, 20) d. (20, 19) 10. Marla Homes, a home improvement/ building supply chain, is going to build a new warehouse facility to serve its stores in six Metro Manila cities- Taguig, Pasig, Mandaluyong, Makati, Pasay, and Quezon City. The coordinates of this cities ( in miles), using Manila, as the origin (0,0) of a set of coordinates, and the annual truck loads that supply each city as shown as follows. Determine the best site using the center- gravity technique. Pasig X = 15 Y = 85 W = 160 Taguig X =42 Y = 145 W = 90 Mandaluyong X = 88 Y = 145 W = 105 Makati X = 125 Y = 140 W = 35 a. (77, 104) c. (79, 106) Pasay X = 135 Y = 125 W = 60 Quezon City X = 180 Y = 18 W = 75 b. (80, 107) d. (81, 105) 11. Refer to problem no. 10, Marla Homes base has two parcel of land, Site A & B in Metro Manila. Use the load-distance technique to determine which would be the best site with its load-distance value. Given: Site A B X 88 13 Y 80 127 a. Site A with LD = 38,986 c. Site B with LD = 44,121 b. Site A with LD = 40,391 d. Site B with LD = 43,542 12. Joehanna Drug Store Chain wishes to build a new warehouse to serve the whole Quezon. At the moment, it is looking at three possible locations. The factors, weights, and ratings being considered are given below: Factor Nearness to markets Labor cost Taxes Nearness to suppliers 45 | P a g e Weights 20 5 15 10 Ratings Candelaria 4 8 8 10 Lucena 7 8 9 6 Lukban 5 4 7 10 Solved Problems in Facility Planning & Design 2012 Which city should they choose? a. Candelaria, 340 c. Lukban 325 b. Lucena, 375 d. Lukban, 385 13. Caloy Distribution Center in Quezon City is due to be replaced with a much larger, more modern facility that can handle the tremendous needs that have developed with the city’s growth. Fresh produce travels to the seven store locations several times a day making site selection critical for efficient distribution. Using the data in the following table, determine the map coordinates for the proposed new distribution center. Store Locations Timog Avenue Banawe St. West Avenue Tomas Morato St. Visayas Avenue Libis Cubao a. (8, 7) c. (7, 9) Map Coordinates (x,y) (10, 5) (3, 8) (4, 7) (15, 10) (13, 3) (1, 12) (5, 5) Truck Round Trips per Day 3 3 2 6 5 3 10 b. (9, 7) d. (7, 8) 14. The following table gives the map coordinates and the shipping loads for a set of cities that we wish to connect though a central ―hub.‖ Near what map coordinates should the hub be located? City A B C D E F G a. (7, 5) c. (4, 8) Map Coordinate (x,y) (5, 10) (6, 8) (4, 9) (9, 5) (7, 9) (3, 2) (2, 6) Shipping Load 5 10 15 5 15 10 5 b. (8, 4) d. (5, 7) 15. Roy Automobile Accessories, a manufacturer of automobile fan belts is considering three locations— Subic, Clark, and Laguna for a new plant. Cost studies indicate that fixed costs per year at the sites are P30,000.00, P60,000.00, and P110,000.00, respectively; and variable cost are P75.00 per unit, P45.00 per unit, and P25.00 per unit, respectively. The expected selling price of the fan belt produced is P120.00. The company wishes to find the most economical location for an expected volume of 2,000 units per year. a. Subic, P180,000.00 c. Clark, P150,000.00 46 | P a g e b. Subic, P140,000.00 d. Laguna, P160,000.00 Solved Problems in Facility Planning & Design 2012 16. Nestor Briefcases is an exclusive producer of handcrafted, stylish cases. Priding itself on its earlier reputation, the company assembles each case with care and attention to detail. This laborious process requires the completion of six primary work elements, which are listed here. Work Element A Tan leather B Dye leather C Shape case D Mold hinges and fixtures E Install hinges and fixtures F Assemble case Precedence A B C, D E Time (min) 30 15 10 5 10 10 If the demand is 50 cases per 40-hour week, compute the cycle time for the process. a. 30 c. 46 b. 40 d. 48 17. Refer to problem no. 16, compute the lead time required for assembling one briefcase. a. 30 c. 80 b. 48 d. 45 18. Refer to problem no. 16, calculate the theoretical minimum number of workstations. a. 3 c. 4 b. 2 d. 1 19. Refer to problem no. 16, balance the line based on the most number of followers. a. 35 45 AD BCEF 45 35 AB CDEF 30 30 A BCD b. c. 47 | P a g e 20 EF Solved Problems in Facility Planning & Design 2012 d. 30 25 25 A BC DEF 20. Refer to problem no. 16, compute the line’s efficiency. a. 89% c. 81% b. 83% d. 93% 21. Refer to problem no. 16, suppose the demand for briefcases increases to 80 cases per week. Calculate a new cycle time a. 30 c. 50 b. 35 d. 45 22. Refer to problem no. 21, balance the line based on the longest task time. a. 35 45 AD BCEF 45 35 AB CDEF 30 30 A BCD 30 25 25 A BC DEF b. c. 20 EF d. 48 | P a g e Solved Problems in Facility Planning & Design 2012 23. Refer to problem no. 21, calculate the new efficiency of the manufacturing process. a. 89% c. 81% b. 83% d. 93% 24. Refer to problem no. 21, calculate the theoretical minimum number of workstations. a. 3 c. 4 b. 2 d. 1 25. Pepper & Mys Bakeshop has set a production quota of 600 party cakes per 40-hour workweek. Use the following information to compute for the cycle time. Work Element A B C D E F Predecessor A B A, E C, D Performance Time (min) 1 2 2 4 3 4 a. 3 c. 4 b. 16 d. 13 26. Refer to problem no. 25, compute the theoretical minimum number of workstations. a. 5 c. 2 b. 3 d. 4 27. Refer to problem no. 25, balance the line using incremental utilization method. a. 3 3.25 3.25 3.25 AB CDEF CDEF CDEF 2.5 2.5 5.5 5.5 ABC DEF DEF b. ABC 49 | P a g e Solved Problems in Facility Planning & Design 2012 c. 3 3.25 3.25 3.25 AB CEDF CEDF CEDF CEDF 3.0 3.0 3.25 3.25 3.25 AB AB CEDF CEDF CEDF 3.25 d. 28. Refer to problem no. 25, calculate the efficiency of the assembly line. a. 95% c. 80% b. 90% d. 83% 29. The Hanzel Pizza is revamping its order processing and pizza-making procedures. In order to deliver fresh pizza fast, six elements must be completed. Work Element A Receive order B Shape dough C Prepare toppings D Assemble pizza E Bake pizza F Deliver pizza Precedence A A B, C D E Time (min) 2 1 2 3 3 3 If the demand is 120 pizzas per night (5:00 p.m. to 1:00 a.m.), compute the cycle time for the process. a. 4 c. 14 b. 3 d. 13 30. Refer to problem no. 29, compute the lead time for the process. a. 4 c. 14 b. 3 d. 13 31. Refer to problem no. 29, Calculate the theoretical minimum number of workstations. a. 2 c. 4 50 | P a g e b. 3 d. 5 Solved Problems in Facility Planning & Design 2012 32. Refer to problem no. 29, balance the line using the most number of followers method. a. 3 5 3 3 AB CD E F 3 2 3 3 3 AB C D E F 4 1 3 3 3 AC B D E F 4 4 3 3 AC BD E F b. c. d. 33. Refer to problem no. 29, compute the efficiency of the line. a. 88% c. 89% b. 91% d. 93% 34. Refer to problem no. 29, suppose demand increases to 160 pizzas per night. What is the new cycle time? a. 4 c. 14 b. 3 d. 13 35. Refer to problem no. 34, balance the line based on the longest task time method. a. 3 5 3 3 AB CD E F 51 | P a g e Solved Problems in Facility Planning & Design 2012 b. 3 2 3 3 3 AB C D E F 4 1 3 3 3 AC B D E F 4 4 3 3 AC BD E F c. d. 36. Refer to problem no. 34, calculate the new theoretical minimum number of workstations. a. 2 c. 4 b. 3 d. 5 37. Neren’s Eye Care, Inc., is a full-service optical supplier that sells eyeglasses, contact lenses, a protective eye apparel to opticians. Bogs’ job is to assemble custom-ordered lenses into eyeglasses for customers. Sales have been good lately, and Bogs has been assembling 100 glasses a day. The manager of Neren’s asked Bogs to write down the precedence requirements and approximate assembly times for each step in the assembly process. The data are shown here. Element Description Precedence A Inspect right and left lens for scratches and proper match Pop lens into frame Position right side piece and attach to frame Position left side piece and attach to frame Package - Time (min) 1.0 A B B C, D 1.0 0.4 0.4 2.0 B C D E Assuming an 8-hour workday, how long does it take Bogs to assemble one pair of glasses? a. 2 c. 4 52 | P a g e b. 2.4 d. 4.8 Solved Problems in Facility Planning & Design 2012 38. Refer to problem no. 37, Neren’s anticipates a surge in demand with the opening of its own retail outlets. If the assembly process is set up as an assembly line, what is the maximum number of eyeglasses that can be assembled in one day, regardless of the number of workers hired? a. 200 c. 100 b. 240 d. 480 39. Refer to problem no. 38, what is the efficiency of the line? a. 80% c. 100% b. 91% d. 95% 40. Prof. Jone has assigned 15 cases in his Seminar class to be completed in a 15 week semester. The students, of course, are moaning and groaning that the caseload cannot possibly be completed in the time allotted. Prof. Jone sympathetically suggests that the students work in groups and learn to organize their work efficiently. Knowing when a situation is hopeless, the students make a list of the tasks that have to be completed in preparing a case. These tasks are listed here, along with precedence requirements and estimated time in days. Assuming students will work 5 days a week on this assignment, how many students should be assigned to each group? Element Description Precedence Time (days) A b c d e f Read case Gather data Search literature Load in data Run computer analysis Write/type case a a b d c, e 1 4 3 1 4 4 a. 3 c. 5 b. 4 d. 5 41. The precedence diagram and task times (in minutes) for assembling Reyson’s Stamp Pad are shown here. Set up an assembly line to produce 125 stamp pads in a 40-hour week. What is the cycle time? 8 5 A B F C D E 6 10 2 a. 10 c. 61 53 | P a g e 4 J H 9 7 K G I 5 2 b. 19.2 d. 2 3 Solved Problems in Facility Planning & Design 2012 42. Refer to problem no. 41, balance the line based on the most number of followers. a. 19 19 11 12 ABC DFG EHI JK 19 19 18 5 ACB DGF EHJ IK 19 17 13 12 ABC DEG FHI JK 19 16 14 12 ACB DFE GHI JK b. c. d. 43. The work elements, precedence requirements, and time requirements to assemble a picture frame are shown here. What is the cycle time capable of producing 1,600 frames per 40-hour week? Element Description Precedence Time (min) A B C D E F G H I Attach left frame side to top of frame Attach right frame side to bottom of frame Attach left and right frame subassemblies Cut 8-inch x 10-inch glass Cut 8-inch x 10-inch cardboard Place glass into frame Place cardboard into frame Secure cardboard and glass Apply descriptive label to glass A, B C, D E, F F, G D 0.35 0.35 0.70 0.50 0.50 0.20 0.20 0.50 0.10 a. 1.5 c. 0.10 54 | P a g e b. 0.70 d. 3.4 Solved Problems in Facility Planning & Design 2012 44. Refer to problem no. 43, balance the assembly line based on the computed cycle time using incremental utilization method. a. 1.4 1.2 .80 ABC DEG FIH 1.30 1.40 DABI CEF 1.40 1.40 b. 0.70 GH c. ABC DEFG 0.60 HI d. 1.45 DEAI 1.45 BCFG 0.50 H 45. Refer to Problem No. 43, What is the maximum output per week? a. 1,600 c. 1,750 b. 1,715 d. 1,656 46. Refer to problem no. 43, balance the assembly line based on the computed cycle time using most number of followers method. a. 1.4 1.2 .80 ABC DEG FIH 55 | P a g e Solved Problems in Facility Planning & Design 2012 b. 1.30 1.40 DABI CEF 1.40 1.40 0.70 GH c. ABC DEFG 0.60 HI d. 1.45 DEAI 1.45 BCFG 0.50 H 47. Refer to Problem No. 46, what is the maximum output per week? a. 1,600 c. 1,750 b. 1,715 d. 1,656 48. Refer to problem no. 43, balance the assembly line based on the computed cycle time using longest task time method. a. 1.4 1.2 .80 ABC DEG FIH 1.30 1.40 DABI CEF 1.40 1.40 b. 0.70 GH c. ABC 56 | P a g e DEFG 0.60 HI Solved Problems in Facility Planning & Design 2012 d. 1.45 DEAI 1.45 BCFG 0.50 H 49. Refer to Problem No. 48, what is the maximum output per week? a. 1,600 c. 1,750 b. 1,715 d. 1,656 50. Refer to problem no. 43, calculate the maximum number of frames that can be assembles each week. a. 2,557 c. 3,567 b. 2,452 d. 3,429 51. Refer to problem no. 50, rebalance the line for maximum production. Assuming one worker per workstation. How many workers would be required? a. 5 c. 6 b. 4 d. 3 52. Refer to problem no. 50, assume the company can sell as many frames as can be produced. If workers are paid P60.00 an hour. What is the total cost per frame? a. 1.67 c. 6.17 b. 1.47 d. 7.14 53. The Racela Finance Corporation has set a processing quota of 80 insurance claims per 8-hour day. The claims process consists of five elements, which are detailed in the following table. Racela has decided to use an assembly line arrangement to process the forms and would like to make sure they have set up the line in the most efficient fashion. Calculate the cycle time required to meet the processing quota. Element A B C D E a. 5 c. 15 57 | P a g e Precedence A B A C, D Performance Time (min) 4 5 2 1 3 b. 6 d. 16 Solved Problems in Facility Planning & Design 2012 54. Refer to problem no. 53, determine how many claims can actually be processed on your line. a. 60/ day c. 80/ day b. 70/ day d. 90/ day 55. A firm must produce 40 units/day during an 8-hour workday. Tasks, times, and predecessor activities are given below. Task A B C D E F G H Total Time (Minutes) 2 2 8 6 3 10 4 3 38 minutes Predecessor(s) A C B D, E F G Determine the cycle time to produce the 40 units per day. a. 10 c. 12 b. 38 d. 20 56. Thomas Santos, manager of a metropolitan branch office of the state department of motor vehicles, attempted to perform an analysis of the driver’s license renewal operations. Several steps were to be performed in the process. After examining the license renewal process, he identified the steps and associated times required to perform each step as follows: Job A. Review renewal application for correctness B. Process and record payment C. Check file violations and restrictions D. Conduct eye test E. Photograph applicant F. Issue temporary license Average Time to perform (seconds) 15 30 60 40 20 30 Santos found that each step was assigned to a different person. Each application was a separate process in the sequence. Santos determined that his office should be prepared to accommodate the maximum demand of processing 120 renewal applicants per hour. He observed that the work was unevenly divided among the clerks, and that the clerk who was responsible for checking violations tended to shortcut her task to keep up with the other clerks. Long lines built up during the maximum demand periods. Santos also found that jobs A, B, C, and D were handled by general clerks who were each paid P270.00 per hour. Job E was by a photographer paid P360.00 per hour. Job F, the issuing of temporary licenses, was required by state policy to be handled by a uniformed motor vehicle officer. Officers were paid P405.00 per hour, but they could be assigned to any job except photography. 58 | P a g e Solved Problems in Facility Planning & Design 2012 A review of the jobs indicated that job A, reviewing the application for correctness, had to be performed before any other step could be taken. Similarly, job F, issuing the temporary license, could not be performed until all the other steps were completed. The checking of file violations and restrictions could be performed while the applicant is having his eye test. The branch offices were charged P450.00 per hour for each camera to perform photography. Determine the maximum number of applications per hour that can be handled by the present configuration of the process? a. 60 c. 120 b. 90 d. 180 57. Refer to problem no. 56, how many applications can be processed per hour if a second clerk is added to check for violations? a. 60 c. 120 b. 90 d. 180 58. In addition to problem no. 57, assuming one more clerk is added to job D, what is the maximum number of applications the process can handle? a. 60 c. 120 b. 90 d. 180 59. Refer to problem no. 56, what is the required cycle time of the process to accommodate 180 applications per hour? a. 15 c. 40 b. 20 d. 60 60. Refer to problem no. 56, compute for the costs per application per hour involved in the current process. a. 30.60 c. 23.40 b. 18.90 d. 38.25 61. Refer to problem no. 58, for the costs per application per hour involved in the alternative process. a. 30.60 c. 23.62 b. 18.90 d. 38.25 62. Assume that production volume is 1,600 pieces per day, the standard time is 0.004 hour per piece, 8 working hours per day, setup time at 0.2 hr per day, and scrap rate of 0.90. Find the fractional machine number. a. 1.12 c. 0.91 59 | P a g e b. 0.85 d. 1.21 Solved Problems in Facility Planning & Design 2012 63. A product requires two sequential machine operations. The first takes 3.5 minutes and the defect percentage is 12. The second takes 6.0 minutes and the defect percentage is 7. In another similar plant belonging to the same company, past annual data on identical operations and working conditions indicate that a total of 2,198 hours due to set up of machines and 2,052 hours due to machine unavailability due to maintenance per year. Assuming 250 work days per year and a daily shift of 10 hours, it is desired to determine the minimum fractional number of machines to manufacture 50,000 units per year. a. 4 c. 6 b. 5 d. 7 64. Eric Explosives Company is considering the expansion of a solid-propellant manufacturing process by adding more 1-ton capacity curing furnaces. Each batch (1 ton) of propellant must undergo 30 minutes of furnace time, including load and unload operations. However, the furnace is used only 80 percent of the time due to power restrictions in the other parts of the system. The required output for the new layout is to be 16 tons per shift (8 hours). Plant (system) efficiency is estimated at 50 percent of system capacity. Determine the number of furnaces required. a. 3 c. 1 b. 4 d. 5 65. Refer to problem no. 64, estimate the percentage of time the furnaces will be idled. a. 20% c. 33% b. 25% d. 67% 66. Charmz Developing Agency must determine how many photo-enlarger cubicles are required to maintain an output of 200 good prints per hour. The set-up and exposure time can theoretically be done in 2 minutes per print, but operators are on the average only 90 percent efficient and, in addition, 5 percent of the prints must be scrapped and redone. Also, the cubicles can be utilized for enlarging only 70 percent of the time. What is the required process capacity in prints per hour? a. 212 c. 211 b. 250 d. 200 67. Refer to problem no. 66, what average output per hour can be expected from each cubicle, taking its use factor and efficiency into account? a. 211 c. 19 b. 30 d. 200 68. Refer to problem no. 66, how many enlarger cubicles are required? a. 14 c. 16 60 | P a g e b. 10 d. 12 Solved Problems in Facility Planning & Design 2012 69. Dason Plastics manufacturer must acquire some molding machines capable of producing 160,000 good parts per year. They will be installed in a production line that normally produces 20 percent rejects because of the tight aerospace specifications. Assume that it takes 90 seconds to mold each part and the plant operates 2,000 hours per year. If the molding machines are used only 50 percent of the time and are 90 percent efficient, what actual (usable) molding machine output per hour would be achieved? a. 40 c. 45 b. 18 d. 20 70. Refer to problem no. 69, how many molding machines would be required? a. 4 c. 6 b. 8 d. 12 71. Given: Year i. ii. iii. iv. v. Demand (units) 220,000 275,000 380,000 420,000 565,000 % Scrap: 3% Standard Time: 2 minutes per unit Target Machine Efficiency: 90% Machine Breakdown: 30 minutes per day Operation Schedule: 8am – 4pm daily schedule/ 20 working days per month How many machines you will acquire/ buy on Year 1? a. 5 c. 2 b. 7 d. 9 72. Refer to problem 71, how many machines you will acquire/ buy on Year 2? a. 5 c. 2 b. 7 d. 9 73. Refer to problem no. 71, how many machines you will acquire/ buy on Year 3? a. 5 c. 2 b. 7 d. 9 74. Refer to problem no. 71, how many machines you will acquire/ buy on Year 4? a. 1 c. 2 61 | P a g e b. 10 d. 9 Solved Problems in Facility Planning & Design 2012 75. Refer to problem no. 71, how many machines you will acquire/ buy on Year 5? a. 1 c. 3 b. 10 d. 13 76. A team of Industrial Engineers conducted a work sampling of identical machines being used for a manufacturing company and they have observed the following: % Idleness Machine 1 20% Machine 2 35% Machine 3 15% Machine 4 55% The machines are running based on the schedule of operation per shift. Shift Schedule: 6am – 2pm/ 2pm – 10pm/ 10pm – 6am Break Time: 1-hr meal break and 15 minutes coffee or short break per shift. Compute for the number of machines required in a given shift. a. 1 c. 3 b. 2 d. 4 77. Mandy Garments produces T-shirts for road races. They need to acquire some new stamping machines to produce 30,000 good T-shirts per month. Their plant operates 200 hours per month, but the new machines will be used for T-shirts only 60 percent of the time and the output usually includes 5 percent that are ―seconds‖ and unusable. The stamping operation takes 1 minute per T-shirt, and the stamping machines are expected to have 90 percent efficiency when considering adjustments, changeover of patterns, and unavoidable downtime. How many machines are required? a. 5 c. 7 b. 6 d. 8 78. During one-8-hour shift, 770 non-defective parts are desired from a fabrication operation. The standard time for the operation is 12 minutes. Because the machine operators are unskilled, the actual time it takes to perform the operation is 25 minutes and, on the average, one-sixth of the parts that begin fabrication are scrapped. Assuming that each of the machines used for this operation will not be available for 45 minutes each shift and there is a probability of 0.05 that each machine will breakdown, determine the number of machines required. a. 50 c. 54 b. 52 d. 56 79. A plastic firm has four work centers (A, B, C, and D) in series with individual capacities (units per day) and actual output as shown. A 450 62 | P a g e B 390 C 360 D 400 actual output = 306/ day Solved Problems in Facility Planning & Design 2012 What is the process capacity? a. 306 c. 450 b. 360 d. 1,600 80. Refer to Problem no. 79, what is the process efficiency? a. 19% c. 68% b. 22.5% d. 85% 81. Dennis Furniture Company manufactures four-drawer oak cabinets in six stages. In the first stage, the boards forming the walls of the cabinets are cut; in the second stage the front drawer panels are woodworked; in the third stage the boards are sanded and finished; in the fourth stage the boards are cleaned, stained, and painted with a clear finish; in the fifth stage the hardware for pulls, runners, and fittings is installed; and in the final stage the cabinets are assembled. Inspection occurs at each stage of the process, and the average percentages of good-quality units are as follows: Stage 1 2 3 4 5 6 Average Percentage Good Quality 87% 91% 94% 93% 93% 96% The cabinets are produced in weekly production runs with a product input for 300 units. Determine the weekly product yield of good-quality cabinets. a. 186 c. 312 b. 288 d. 486 82. Refer to problem no. 81, what would weekly product input have to be in order to achieve a final weekly product yield of 300 cabinets? a. 186 c. 312 b. 288 d. 486 83. The Jelo Motor Company, motors are produced in a three-stage process. Motors are inspected following each stage with percentage yields of good quality in process units as follows: Stage 1 Average Percentage Good Quality 0.96 2 0.98 3 0.95 63 | P a g e Solved Problems in Facility Planning & Design 2012 The company wants to know the daily product yield for product input of 250 units per day. a. 263 c. 223 b. 238 d. 280 84. Refer to problem no. 83, how many input units it would have to start with each day to result in a final daily yield of 250 good quality units? a. 263 c. 223 b. 238 d. 280 85. Rafael Metals Company manufactures of wood burning stove. What is the product input for 15,000 stoves if the good quality of each stove is 88%? a. 13,200 c. 125,000 b. 1,800 d. 17,045 86. Lara Company operates a small telephone order system for a catalog of its clothing products. The catalog orders are processed in four stages. Errors can be made in orders at any of these stages, and the average percentages of errors that occur at each stage are as follows. Stage 1 2 3 4 %Error 19% 16% 10% 8% If an average of 460 telephone orders is processed each day, how many errorless orders will result? a. 112 c. 244 b. 259 d. 129 87. Liam Manufacturing Company has a weekly product input of 2,800 units. The average percentage of good-quality product is 87 percent. Of the poor quality products 60 percent can be reworked and sold as good-quality products. Determine the weekly product output? a. 2,654 c. 1,462 64 | P a g e b. 5,364 d. 3,218 Solved Problems in Facility Planning & Design 2012 88. Given: From/To A B C D E F A B 15 C 50 20 50 D E 75 120 50 110 100 100 F 125 120 100 Design a layout on a 3x3 grid that will minimize nonadjacent load. What is the layout of your building? a. A B C D E F C B E F A D B A F E C D D B E C F A b. c. d. 65 | P a g e Solved Problems in Facility Planning & Design 2012 89. Given: Department 1 2 3 4 5 6 1 Number of loads per week 2 3 4 5 6 50 100 20 30 50 10 20 100 50 Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building? a. 1 2 6 4 3 5 5 2 1 4 3 6 2 6 5 3 4 1 6 3 4 1 5 2 b. c. d. 66 | P a g e Solved Problems in Facility Planning & Design 2012 90. Given: 1. 2. 3. 4. 5. 6. Department Administration Social services Institutions Accounting Education Internal audit 1 Number of loads per week 2 3 4 5 3 6 5 6 8 1 1 3 9 2 6 10 1 Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building? a. 4 1 2 6 5 3 3 6 4 2 5 1 1 5 4 3 6 2 6 3 2 5 1 4 b. c. d. 67 | P a g e Solved Problems in Facility Planning & Design 2012 91. Given: Loads/day From/To A B A 30 B C D E C 30 D 60 E 20 30 80 40 Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building? a. C A D E C B D A B D E A A E C B B b. E c. C d. D 68 | P a g e Solved Problems in Facility Planning & Design 2012 92. Matthew Design Company has been asked to design the layout for a newly constructed office building of one of its clients. The closeness matrix showing the daily trips between its six department offices is given below. Department Trips between Departments 2 3 4 5 6 25 90 165 105 125 125 25 105 1 1 2 3 4 5 6 Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building? a. 3 1 5 6 4 2 2 5 3 4 1 6 5 1 4 3 6 2 1 6 2 3 5 4 b. c. d. 69 | P a g e Solved Problems in Facility Planning & Design 2012 93. Given: Flow between Departments (Number of Moves) 7 8 1 2 3 4 5 6 20 75 175 150 80 120 90 100 125 350 25 25 180 187 374 103 7 Departments 1. Shipping and receiving 2. Plastic molding stamping 3. Metal forming 4. Sewing department 5. Small toy assembly 6. Large toy assembly 7. Painting 8. Mechanism assembly Design a layout on a 3x3 grid that will minimize nonadjacent load. What is the layout of your building? a. 5 1 2 6 4 3 7 8 1 7 5 2 6 3 8 4 b. 70 | P a g e Solved Problems in Facility Planning & Design 2012 c. 4 5 6 1 3 2 8 7 6 4 7 8 2 5 1 3 d. 94. Giv en: From/To Stores Turning Milling Press Plate Assembly Warehouse Stores Turning 6 1 Milling 12 3 Press 9 Plate 1 4 7 3 Assembly 4 3 2 1 4 1 Warehouse 1 3 7 Design a layout on a 3x3 grid that will minimize nonadjacent load. What is the layout of your building? a. 71 | P a g e Press Warehouse Warehouse Plate Milling Stores Turning Solved Problems in Facility Planning & Design b. Turning Stores Milling Press Warehouse Plate Assembly c. Assembly Warehouse Turning Plate Press Assembly Stores d. 72 | P a g e Milling Assembly Plate Warehouse Turning Stores Press 2012 Solved Problems in Facility Planning & Design 95. Based on the relationship chart below, what is it recommended layout? a. 4 6 1 5 2 3 6 4 1 5 3 2 b. c. 2 3 6 1 5 4 d. 6 3 2 5 1 4 73 | P a g e 2012 Solved Problems in Facility Planning & Design 96. Based on the relationship chart below, what is its recommended layout? a. 5 b. 5 c. 6 d. 6 74 | P a g e 3 1 2 4 6 7 1 3 4 2 6 7 3 1 2 4 7 5 1 3 2 4 5 7 2012 Solved Problems in Facility Planning & Design 97. Given: Legend: A I U CV Values 10,000 100 0 Activity Legend E O X CV Values 1,000 10 -1,000 Area (sq. m) 1. Wood cutting 1,280 2. Receiving 560 A E U I 3. Framing U 1,280 I 4. Upholstery U 1,120 E 5. Fabric storage 960 6. Fabric cutting 960 7. Sewing 640 E 800 9. Offices 800 10. General Storage 480 U U O O U E U I A A 8. Shipping I X E U U I U U U U X U U I U U U U I U U U U O E O Distance between departments: Adjacent = 1, Partial Adjacent = 0.5, Non-Adjacent = 0 Using CORELAP, what is Total Closeness Rating (TCR) Value of Department 1? a. 10,000 c. 12,000 b. 11,000 d. 14,000 98. In reference to problem no. 97, what activity is the first to be placed on the grid? a. 7 c. 5 b. 2 d. 6 99. In reference to problem no. 98, what is your final layout? a. 2 75 | P a g e 10 5 6 1 3 7 8 4 9 2012 Solved Problems in Facility Planning & Design b. 4 10 1 7 3 5 6 8 9 2 10 1 4 8 9 2 3 5 6 10 5 6 8 4 7 1 3 9 c. 7 d. 2 76 | P a g e 2012 Solved Problems in Facility Planning & Design 2012 100. Given: A B C D E F G H I J K L Machines Parts-Machines Matrix Parts 1 2 3 4 5 x x x x x x x x x x x x x x x x 6 x 7 8 x x x x x x x x x x Using Digital Clustering Algorithm (DCA), prepare the final cell formation with additional machines, if needed. a. D A H B J L G K C F I E 5 6 1 4 X X X X X X X X X X X X X X 2 8 7 X X X X X 3 X X X X X X X X b. D A H B J 5 6 1 4 X X X X X X X X X X X X X X L1 2 8 X X G K X 7 3 X X L2 X C F I E c. D A H B J C F I E L G K 77 | P a g e X X X X X X X 5 6 1 4 X X X X X X X X X X X X X X 7 3 X X X X X 2 8 X X X X X X X X X Solved Problems in Facility Planning & Design d. D A H B J C F I E1 E2 5 6 1 4 X X X X X X X X X X X X X X 7 3 X X X X X 2 8 X X L G K 78 | P a g e x x X X X X X 2012 Solved Problems in Facility Planning & Design 2012 SOLVED PROBLEMS IN FACILITY PLANNING & DESIGN - QUANTITATIVE 1. Belinda Fashion Wear is a small chain of stores specializing in fashion clothing. The company currently has five stores in Manila, Quezon City, and Caloocan, and it wants to open new store in of four new mall locations in the other nearby cities. A consulting firm has been hired to help the company decide where to locate new store. The company has indicated five factors that are important to its decision, including proximity of a college, community median income, mall vehicle traffic flow and parking, quality and number of stores in the mall, and proximity of other malls or shopping areas. The consulting firm had the company weight the importance of each factor. The consultant had visited each potential location and rated them according to each factor, as follows: Location factors College proximity Median income Vehicle traffic Mall quality and size Proximity of other shopping Weight 0.30 0.25 0.25 0.10 0.10 Mall 1 40 75 60 90 80 Mall 2 60 80 90 100 30 Mall 3 90 65 79 80 50 Mall 4 60 90 85 90 70 Given that all sites have basically the same leasing cost and labor and operating cost, what is the recommended location based on rating factors? a. Mall 1 c. Mall 3 b. Mall 2 d. Mall 4 Answer: d. Mall 4 Location factors College proximity Median income Vehicle traffic Mall quality and size Proximity of other shopping Mall 1 12.00 18.75 15.00 9.00 8.00 Mall 2 18.00 20.00 22.50 10.00 3.00 Mall 3 27.00 16.25 19.75 8.00 5.00 Mall 4 18.00 22.50 21.25 9.00 7.00 TOTAL 62.75 73.50 76.00 77.75 2. Zachtech Computers manufacture computer components such as chips, circuit boards, motherboards, keyboards, LCD panels, and the like and sells them around the world. It wants to construct a new warehouse/distribution center in Asia to serve emerging Asian markets. It has identified sites in Shanghai, Hong Kong and Singapore and has rated the important location factors for each site as follows: Location Factors Political Stability Economic Growth Port Facilities Container support Land and construction cost Transportation/Distribution Duties and tariffs Trade regulations Airline Service Area roads 79 | P a g e Weight 0.25 0.18 0.15 0.10 0.08 0.08 0.07 0.05 0.02 0.02 Shanghai 50 90 60 50 90 50 70 70 60 60 Hong Kong 60 70 95 80 20 80 90 95 80 70 Singapore 90 75 90 90 30 70 90 95 70 80 Solved Problems in Facility Planning & Design 2012 Recommend a site including its total score rating based on these location factors and ratings. a. Hongkong, 72 c. Singapore, 81 b. Hongkong, 82 d. Shanghai, 79 Answer: c. Singapore, 81 Location Factors Political Stability Economic Growth Port Facilities Container support Land and construction cost Transportation/Distribution Duties and tariffs Trade regulations Airline Service Area roads Total Shanghai 12.50 16.20 9.00 5.00 7.20 4.00 4.90 3.50 1.20 1.20 64.70 = 65 Hong Kong 15.00 12.60 14.25 8.00 1.60 6.40 6.30 4.75 1.60 1.40 71.90 = 72 Singapore 22.50 13.50 13.50 9.00 2.40 5.60 6.30 4.75 1.40 1.60 80.55 = 81 3. Cradle University is going to construct a new student center and athletic complex that will include a bookstore, post office, theaters, markets, mini-mall, meeting rooms, swimming pool, and weight and exercise rooms. The university administration has hired a site selection specialist has identified four sites on campus and has rated important location factors for each site as follows: Location Factors Proximity to housing Student traffic Parking availability Plot size, terrain Infrastructure Off-campus accessibility Proximity dining facilities Visitor traffic Landscape/aesthetics Weight 0.23 0.22 0.16 0.12 0.10 0.06 0.05 0.04 0.02 South 70 75 90 80 50 90 60 70 50 West A 90 80 60 70 60 70 80 80 40 West B 65 60 80 90 40 70 70 65 60 Recommend a best site based on these location factors and ratings. a. South b. West A c. West B d. East Answer: d. East Location Factors Proximity to housing Student traffic Parking availability Plot size, terrain Infrastructure Off-campus accessibility Proximity dining facilities Visitor traffic Landscape/aesthetics Total 80 | P a g e South 16.10 16.50 14.40 9.60 5.00 5.40 3.00 2.80 1.00 73.80 West A 20.70 17.60 9.60 8.40 6.00 4.20 4.00 3.20 0.80 74.50 West B 14.95 13.20 12.80 10.80 4.00 4.20 3.50 2.60 1.20 67.25 East 19.55 18.70 11.20 9.00 6.00 4.20 4.50 2.20 1.40 76.75 East 85 85 70 75 60 70 90 55 70 Solved Problems in Facility Planning & Design 2012 4. Zhan Electronics is going to construct new P1.2 billion semi-conductor plant and has selected four Export Processing Zone Areas as potential sites. The important location factors and ratings for each town are as follows: Location Factors Work Ethics Quality of Life Labor Laws/Unionization Infrastructure Education Labor skill and Education Cost of Living Taxes Incentive Package Government Regulation Environmental Regulation Transportation Space for Expansion Urban Proximity Weight 0.18 0.16 0.12 0.10 0.08 0.07 0.06 0.05 0.05 0.03 0.03 0.03 0.02 0.02 Sta. Rosa 80 75 90 60 80 75 70 60 90 40 65 90 90 60 Lipa 90 85 90 50 90 65 80 70 95 50 60 80 95 90 Bataan 70 95 60 60 85 70 85 55 70 65 70 95 90 70 Subic 75 90 70 70 95 80 75 60 80 55 80 80 90 80 Recommend a site based on these location factors and ratings. a. Sta. Rosa c. Bataan b. Lipa c. Subic Answer: b. Lipa Location Factors Work Ethics Quality of Life Labor Laws/Unionization Infrastructure Education Labor skill and Education Cost of Living Taxes Incentive Package Government Regulation Environmental Regulation Transportation Space for Expansion Urban Proximity Total Sta. Rosa 14.4 12.0 10.8 6.00 6.40 5.25 4.20 3.00 4.50 1.20 1.95 2.70 1.80 1.20 75.40 Lipa 16.2 13.6 10.8 5.00 7.20 4.55 4.80 3.50 4.75 1.50 1.80 2.40 1.90 1.80 79.80 Bataan 12.6 15.2 7.20 6.00 6.80 4.90 5.10 2.75 3.50 1.95 2.10 2.85 1.80 1.40 74.15 Subic 13.5 14.4 8.40 7.00 7.60 5.60 4.50 3.00 4.00 1.65 2.40 2.40 1.80 1.60 77.85 5. The Charlie Forwarding Company wants to build a new distribution center in Central Luzon. The center needs to be in the vicinity of uncongested Aurora, Bataan, and Nueva Ecija. The coordinates of this sites and the number of weekly packages that flow to each are as follows: Aurora X = 17 Y = 30 W = 17,000 81 | P a g e Bataan X = 20 Y=8 W = 12,000 Nueva Ecija X = 30 Y = 14 W = 9,000 Solved Problems in Facility Planning & Design 2012 What are the coordinates of the center of these 3 provinces? a. (25, 22) c. (24, 17) b. (18, 22) d. (21, 19) Answer: d. (21, 19) X= X= Y= Y= (17) (17,000) + (20) (12,000) + (30) (9,000) 17,000 + 12,000 + 9,000 21.03 = 21 (30) (17,000) + (8) (12,000) + (14) (9,000) 17,000 + 12,000 + 9,000 19.26 = 19 6. The Inah Burger restaurant chain uses a distribution center to prepare the food ingredients it provides its individual restaurants. The company is attempting to determine the location for new distribution center that will service five restaurants. The grid-map coordinates of the five restaurants and the annual numbers of 40-foot trailer trucks transported to each restaurant are as follows: Restaurants 1 2 3 4 5 X 100 210 250 300 400 Y 300 180 400 150 200 Annual Truck Shipments 30 25 15 20 18 Determine the coordinates of the location using the center-of-gravity method. a. (233, 242) c. (243, 231) b. (236, 244) c. (245, 230) Answer: a. (233, 242) X = (100(30) + 210(25) + 250(15) + 300(20) + 400(18)) / (30+25+15+20+18) X = 25200/108 X = 233.33 = 233 Y = (300(30) + 180(25) + 400(15) + 150(20) + 200(18)) / (30+25+15+20+18) Y = 26100/108 Y = 241.67 = 242 7. The Inah Burger restaurant chain in the previous problem is considering three potential sites. With the following grid-map coordinates for its new distribution center: A( 350, 300). B. (150, 250), and C (250, 300). Determine the best location using the load-distance formula. a. Site A, LD = 15,205 c. Site C, LD = 15,570 82 | P a g e b. Site B, LD = 15,325 c. Site C, LD = 15,255 Solved Problems in Facility Planning & Design Answer: b. Site B, LD = 15,325 Site A: d1= (X1 – Xa)2 + (Y1 – Ya)2 = (100 – 350)2 + (300 - 300) d2 = (X2 – Xa)2 + (Y2 – Ya)2 = d3 = = d4 = (210 – 350)2 + (180 – 360)2 (250 – 350)2 + (400 – 300)2 d5 = (X5 – Xa)2 + (Y5 – Ya)2 = (400 – 350)2 + (300 – 300)2 d2 = = d3 = = d4 = (100 – 150)2 + (300 - 250)2 (210 – 150)2 + (180 – 250)2 (250 – 150)2 + (400 – 250)2 = (400 – 150)2 + (200 – 250)2 d3 = = 83 | P a g e = 158.11 = 111.8 = 70.71 = 92.20 = 180.28 = 180.28 = 254.95 = 150 = 126.49 = 100 (X4 – Xb)2 + (Y4 – Yb)2 (X5 – Xb)2 + (Y5 – Yb)2 = 141.42 (X3 – Xb)2 + (Y3 – Yb)2 d5 = d2 = = (X2 – Xb)2 + (Y2 – Yb)2 (300 – 150)2 + (150 – 250)2 = 184.39 (X1 – Xa)2 + (Y1 – Yb)2 = Site C: d1 = = (X4 – Xa)2 + (Y4 – Ya)2 (300 – 350)2 + (150 – 300)2 = 250 (X3 – Xa)2 + (Y3 – Ya)2 = Site B: d1 = = (X1 – Xc)2 + (Y1 – Yc)2 (100 – 350)2 + (300 - 300)2 (X2 – Xc)2 + (Y2 – Yc)2 (210 – 250)2 + (180 – 366)2 (X3 – Xc)2 + (Y3 – Yc)2 (250 – 250)2 + (400 – 300)2 2012 Solved Problems in Facility Planning & Design 2012 (X4 – Xc)2 + (Y4 – Yc)2 d4 = (300 – 250)2 + (150 – 300)2 = = 158.11 = 180.28 (X5 – Xc)2 + (Y5 – Yc)2 d5 = (400 – 250)2 + (200 – 300)2 = LD (Site A) = = 30(250) + 25(184.39) + 15(141.42) + 20(158.11) + 18(111.8) 19,405.65 = 19,406 LD (Site B) = = 30(70.71) + 25(92.20) + 15(180.28) + 20(180.28) + 18(254.95) 15,325.20 = 15,325 LD (Site C) = = 30(150) + 25(126.49) + 15(100) + 20(158.11) + 18(180.28) 15,569.49 = 15,570 8. James Company is attempting to determine the location for a new outlet mall. The region where the outlet mall will be constructed includes four towns, which together have a sizable population base. The grid map coordinates of the four towns in Cavite and the populations of each are as follows: Town Rosario Dasmarinas Trece Martirez Silang X 30 50 10 40 Y 60 40 70 30 Population (10,000s) 6.5 4.2 5.9 3.5 Determine best location for the outlet mall using the center-of -gravity method. a. (32, 56) c. (30, 54) b. (33, 55) d. (31, 52) Answer: c. (30, 54) X = (30(6.5) + 50(4.2) + 10(5.9) + 40(3.5)) / (6.5 + 4.2 + 5.9 + 3.5) X = 604/20.1 X = 30.05 = 30 Y = (60(6.5) + 40(4.2) + 70(5.9) + 30(3.5)) / (6.5 + 4.2 + 5.9 + 3.5) Y = 1076/20.1 Y = 53.53 = 54 9. Ray-Mart, a discount store chain, wants to build a new superstore in an area in Batangas near four small towns with population between 8,000 and 42,000. The coordinates (in miles) of these four towns and the market population in each are as follows: Bauan X = 12 Y = 20 W = 26,000 84 | P a g e Ibaan X = 18 Y = 18 W = 14,000 Mabini X = 30 Y=7 W = 9,500 Laurel X = 32 Y = 25 W = 12,000 Solved Problems in Facility Planning & Design 2012 Determine the coordinates of the best site using the center of gravity technique. a. (24, 21) b. (23, 22) b. (21, 20) d. (20, 19) Answer: d. (20, 19) X = (12(26,000) + 18(14,000) + 30(9,500) + 32(12,000)) / (26,000 + 14,000 + 9,500 + 12,000) X = 1,233,000/61,500 X = 20.05 = 20 Y = (20(26,000) + 18(14,000) + 7(9,500) + 25(12,000)) / (26,000 + 14,000 + 9,500 + 12,000) Y = 1,138,500/61,500 Y = 18.51 = 19 10. Marla Homes, a home improvement/ building supply chain, is going to build a new warehouse facility to serve its stores in six Metro Manila Cities - Taguig, Pasig, Mandaluyong, Makati, Pasay, and Quezon City. The coordinates of this cities (in miles), using Manila, as the origin (0,0) of a set of coordinates, and the annual truck loads that supply each city as shown as follows. Determine the best site using the center- gravity technique. Pasig X = 15 Y = 85 W = 160 Taguig X =42 Y = 145 W = 90 Mandaluyong X = 88 Y = 145 W = 105 a. (77, 104) c. (79, 106) Makati X = 125 Y = 140 W = 35 Pasay X = 135 Y = 125 W = 60 Quezon City X = 180 Y = 18 W = 75 b. (80, 107) d. (81, 105) Answer: c. (79, 106) X = 15(160) + 42(90) + 88(105) + 125(35) + 135(60) + 180(75) 160 + 90 + 105 + 35 + 60 + 75 = 78.85 = 79 Y = 85(160) + 145(90) + 145(105) + 140(35) + 125(60) + 18(75) 160 + 90 + 105 + 35 + 60 + 75 = 105.95 = 106 11. Refer to problem no. 10, Marla Homes base has two parcel of land, Site A & B in Metro Manila. Use the load-distance technique to determine which would be the best site with its load-distance value. Given: Site A B X 88 13 Y 80 127 a. Site A with LD = 38,986 c. Site B with LD = 44,121 Answer: b. Site A with LD = 40,391 85 | P a g e b. Site A with LD = 40,391 d. Site B with LD = 43,542 Solved Problems in Facility Planning & Design For Site A: d Pasig = (15 – 88)2 + (85 – 80)2) = 73.17 d Taguig = (42 – 88)2 + (145 – 80)2 = 79.63 d Mandaluyong = (88 – 88)2 + (145 – 80)2 = 65.00 d Makati = (125 – 88)2 + (140 – 80)2 = 70.49 d Pasay = (135 – 88)2 + (125 – 80)2 = 65.07 d Quezon City = (180 – 88)2 + (18 – 80)2 = 110.94 For Site B: d Pasig = (15 – 13)2 + (85 – 127)2 = 42.05 d Taguig = (42 – 13)2 + (145 – 127)2 = 34.13 d Mandaluyong = (88 – 13)2 + (145 – 127)2 = 77.13 d Makati = (125 – 13)2 + (140 – 127)2 = 112.75 d Pasay = (135 – 13)2 + (125 – 127)2 = 122.00 d Quezon City = (180 – 13)2 + (18 – 127)2 = 199.42 2012 Load Distance: For Site A: LD = 160(73.17) + 90(79.63) + 105(65.00) + 35(70.49) + 60(65.07) + 75(110.94) = 40,390.75 = 40,391 For Site B: LD = 160(42.05) + 90(34.13) + 105(77.13) + 35(112.75) + 60(122.00) + 75(199.42) = 44,121.10 = 44,121 12. Joehanna Drug Store Chain wishes to build a new warehouse to serve the whole Quezon. At the moment, it is looking at three possible locations. The factors, weights, and ratings being considered are given below: Factor Nearness to markets Labor cost Taxes Nearness to suppliers Weights 20 5 15 10 Ratings Candelaria 4 8 8 10 Lucena 7 8 9 6 Lukban 5 4 7 10 Which city should they choose? a. Candelaria, 340 c. Lukban 325 86 | P a g e b. Lucena, 375 d. Lukban, 385 Solved Problems in Facility Planning & Design 2012 Answer: b. Lucena, 375 Factor Nearness to markets Labor cost Taxes Nearness to suppliers Weights Ratings Candelaria Lucena Lukban Weighted Ratings Candelaria Lucena Lukban 20 4 7 5 80 140 100 5 15 8 8 8 9 4 7 40 120 40 135 20 105 10 10 6 10 100 60 100 340 375 325 Sum of Weighted ratings: 13. Caloy Distribution Center in Quezon City is due to be replaced with a much larger, more modern facility that can handle the tremendous needs that have developed with the city’s growth. Fresh produce travels to the seven store locations several times a day making site selection critical for efficient distribution. Using the data in the following table, determine the map coordinates for the proposed new distribution center. Store Locations Timog Avenue Banawe St. West Avenue Tomas Morato St. Visayas Avenue Libis Cubao Map Coordinates (x,y) (10, 5) (3, 8) (4, 7) (15, 10) (13, 3) (1, 12) (5, 5) a. (8, 7) c. (7, 9) Truck Round Trips per Day 3 3 2 6 5 3 10 b. (9, 7) d. (7, 8) Answer: a. (8, 7) New Distribution Center should be located at: Cx = (10 x 3) + (3 x 3) + (4 x 2) + (15 x 6) + (13 x 5) + (1 x 3) + (5 x 10) = 255 = 8 3 + 3 + 2 + 6 + 5 + 3 +10 32 Cy = (5 x 3) + (8 x 3) + (7 x 2) + (10 + 6) + (3 x 5) + (12 x 3) + (5 x 10) = 214 = 7 3 + 3 + 2 + 6 + 5 + 3 + 10 32 14. The following table gives the map coordinates and the shipping loads for a set of cities that we wish to connect though a central ―hub.‖ Near what map coordinates should the hub be located? City A B C D E F G 87 | P a g e Map Coordinate (x,y) (5, 10) (6, 8) (4, 9) (9, 5) (7, 9) (3, 2) (2, 6) Shipping Load 5 10 15 5 15 10 5 Solved Problems in Facility Planning & Design a. (7, 5) c. (4, 8) 2012 b. (8, 4) d. (5, 7) Answer: d. (5, 7) The new hub should be located close to: Cx= (5 x 5) + (6 x 10) + (4 x 15) + (9 x 5) + (7 x 15) + (3 x 10) + (2 x 5) = 335 = 5 5 +10 + 15 + 5 + 15 +10 + 5 65 Cy = (10 x 5) + (8 x 10) + (9 x 15) + (5 + 5) + (9 x 15) + (2 x 10) + (6 x 5) = 475 = 7 5 + 10 + 15 + 5 + 15 + 10 + 5 65 15. Roy Automobile Accessories, a manufacturer of automobile fan belts is considering three locations— Subic, Clark, and Laguna for a new plant. Cost studies indicate that fixed costs per year at the sites are P30,000.00, P60,000.00, and P110,000.00, respectively; and variable cost are P75.00 per unit, P45.00 per unit, and P25.00 per unit, respectively. The expected selling price of the fan belt produced is P120.00. The company wishes to find the most economical location for an expected volume of 2,000 units per year. a. Subic, P180,000.00 c. Clark, P150,000.00 b. Subic, P140,000.00 d. Laguna, P160,000.00 Answer: c. Clark, P150,000.00 For Subic, Total Cost = P30,000.00 + P75.00(2,000) = P180,000.00 For Clark, Total Cost = P60,000.00 + P45.00(2,000) = P150,000.00 For Laguna, Total Cost = P110,000.00 + P25.00(2000) = P160,000.00 With an expected volume of 2,000 units per year, Clark provides the lowest cost location. 16. Nestor Briefcases is an exclusive producer of handcrafted, stylish cases. Priding itself on its earlier reputation, the company assembles each case with care and attention to detail. This laborious process requires the completion of six primary work elements, which are listed here. Work Element A Tan leather B Dye leather C Shape case D Mold hinges and fixtures E Install hinges and fixtures F Assemble case Precedence A B C, D E Time (min) 30 15 10 5 10 10 If the demand is 50 cases per 40-hour week, compute the cycle time for the process. a. 30 c. 46 88 | P a g e b. 40 d. 48 Solved Problems in Facility Planning & Design Answer: d. 48 30 15 10 A B C D E F 5 10 10 Cycle time= total working hours = (40 hours x 60 minutes/hour) desired units of output = 48 minutes (50 cases) 17. Refer to problem no. 16, compute the lead time required for assembling one briefcase. a. 30 c. 80 b. 48 d. 45 Answer: c. 80 Lead time= (30 + 15 + 10 + 5 + 10 + 10) = 80 minutes 18. Refer to problem no. 16, calculate the theoretical minimum number of workstations. a. 3 c. 4 b. 2 d. 1 Answer: b. 2 N= lead time = cycle time (30 + 15 + 10 + 5 + 10 + 10) = 1.66 ≈ 2 workstations 48 19. Refer to problem no. 16, balance the line based on the most number of followers. a. 35 45 AD BCEF 89 | P a g e 2012 Solved Problems in Facility Planning & Design b. 45 35 AB CDEF 30 30 A BCD 30 25 25 A BC DEF c. 20 EF d. Answer: b Task A B C D E F 45 35 AB CDEF Time 30 15 10 5 10 10 Station 1 A (48 – 30 = 18) B (18 – 15 = 3) ST1 = 45 mins Number of Followers 4 3 2 2 1 0 Station 2 C (48 – 10 = 38) D (38 – 5 = 33) E (33 – 10 = 23) F (23 – 10 = 13) ST2 = 35 mins 20. Refer to problem no. 16, compute the line’s efficiency. a. 89% c. 81% 90 | P a g e b. 83% d. 93% 2012 Solved Problems in Facility Planning & Design 2012 Answer: b. 83% lead time Efficiency = = (30 + 15 + 10 + 5 + 10 + 10) no. of workstations x cycle time = 83.33% 2(48) 21. Refer to problem no. 16, suppose the demand for briefcases increases to 80 cases per week. Calculate a new cycle time. a. 30 c. 50 b. 35 d. 45 Answer: a. 30 Cycle time = total working hours = (5 days x 8 hours/day x 60 minutes/hour) desired units of output (80 cases) 22. Refer to problem no. 21, balance the line based on the longest task time a. 35 45 AD BCEF 45 35 AB CDEF 30 30 A BCD 30 25 25 A BC DEF b. c. 20 EF d. 91 | P a g e = 30 minutes Solved Problems in Facility Planning & Design 2012 Answer: c 30 30 A BCD Time 30 15 10 5 10 10 Rank 1 2 3 6 4 5 Task A B C D E F Station 1 A (30 – 30 = 0) 20 EF Station 2 B (30 – 15 = 15) C (15 – 10 = 5) D (5 – 5 = 0) ST2 = 30 mins ST1 = 30 mins Station 3 E (30 – 10 = 20) F (20 – 10 = 10) ST3 = 20 mins 23. Refer to problem no. 21, calculate the new efficiency of the manufacturing process. a. 89% c. 81% b. 83% d. 93% Answer: a. 89% lead time Efficiency = = (30 + 15 + 10 + 5 + 10 + 10) no. of workstations x cycle time 3(30) 24. Refer to problem no. 21, calculate the theoretical minimum number of workstations. a. 3 c. 4 b. 2 d. 1 Answer: a. 3 N= lead time cycle time 92 | P a g e = (30 + 15 + 10 + 5 + 10 + 10) 30 = 2.66 ≈ 3 workstations = 88.89% Solved Problems in Facility Planning & Design 2012 25. Pepper & Mys Bakeshop has set a production quota of 600 party cakes per 40-hour workweek. Use the following information to compute for the cycle time. Work Element A B C D E F Predecessor A B A, E C, D Performance Time (min) 1 2 2 4 3 4 a. 3 c. 4 b. 16 d. 13 Answer: c. 4 1 2 2 A B C F E D 3 4 total working hours Cycle time= = 4 (40 hours x 60 minutes/hour) desired units of output = 4 minutes (600 party cakes) 26. Refer to problem no. 25, compute the theoretical minimum number of workstations. a. 5 c. 2 b. 3 d. 4 Answer: d. 4 lead time N= = (1 + 2 + 2 + 4 + 3 + 4) cycle time = 4 workstations 4 27. Refer to problem no. 25, balance the line using incremental utilization method a. 3 3.25 3.25 3.25 AB CDEF CDEF CDEF 93 | P a g e Solved Problems in Facility Planning & Design b. 2.5 2.5 5.5 5.5 ABC ABC DEF DEF 3 3.25 3.25 3.25 AB CEDF CEDF CEDF CEDF 3.0 3.0 3.25 3.25 3.25 AB AB CEDF CEDF CEDF 3 3.25 3.25 3.25 AB CEDF CEDF CEDF c. 3.25 d. Answer: c 3.25 CEDF Based on Incremental Utilization Method (IUM) WS 1 1 1 2 2 2 2 Task A A, B A, B, C C C,E C, E, D C, E, D, F Task Time 1 1+2=3 3+2=5 2 2+ 3=5 5+ 4=9 9 + 4 = 13 Incremental Utilization 25% 75% 62.5% 50% 62.5% 75% 81% # of WS’s 1/ 4 = 0.25 = 1 3/ 4 = 0.75 = 1 5/ 4 = 1.25 = 2 2/ 4 = 0.50 = 1 5/ 4 = 1.25 = 2 9/ 4 = 2.25 = 3 13/ 4 = 3.25 = 4 28. Refer to problem no. 25, calculate the efficiency of the assembly line. a. 95% c. 80% b. 90% d. 83% Answer: c. 80% Efficiency = lead time no. of workstations x cycle time 94 | P a g e = (1 + 2 + 2 + 4 + 3 + 4) 5(4) = 80% 2012 Solved Problems in Facility Planning & Design 2012 29. The Hanzel Pizza is revamping its order processing and pizza-making procedures. In order to deliver fresh pizza fast, six elements must be completed. Work Element A Receive order B Shape dough C Prepare toppings D Assemble pizza E Bake pizza F Deliver pizza Precedence A A B, C D E Time (min) 2 1 2 3 3 3 If the demand is 120 pizzas per night (5:00 p.m. to 1:00 a.m.), compute the cycle time for the process. a. 4 c. 14 b. 3 d. 13 Answer: a. 4 2 1 3 3 3 A B D E F C 2 Cycle time = total working hours = (8 hours x 60 minutes/hour) desired units of output = 4 minutes (120 pizzas) 30. Refer to problem no. 29, compute the lead time for the process. a. 4 c. 14 b. 3 d. 13 Answer: c. 14 Lead time= (2 + 1 + 2 + 3 + 3 + 3) = 14 minutes 31. Refer to problem no. 29, Calculate the theoretical minimum number of workstations. a. 2 c. 4 b. 3 d. 5 Answer: c. 4 N= lead time cycle time 95 | P a g e = (2 + 1 + 2 + 3 + 3 + 3) 4 = 3.5 ≈ 4 workstations Solved Problems in Facility Planning & Design 32. Refer to problem no. 29, balance the line using the most number of followers method. a. 3 5 3 3 AB CD E F 3 2 3 3 3 AB C D E F 4 1 3 3 3 AC B D E F 4 4 3 3 AC BD E F 4 4 3 3 AC BD E F b. c. d. Answer: d Task A B C D E F Time 2 1 2 3 3 3 Number of Followers 5 3 3 2 1 0 Station 1 A (4 – 2 = 2) C (2 – 2 = 0) ST1 = 4 mins Station 2 B (4 – 1 = 3) D (3 – 3 = 0) ST2 = 4 mins 96 | P a g e Station 3 E (4 – 3 = 1) Station 4 F (4 – 3 = 1) ST3 = 3 mins ST4 = 3 mins 2012 Solved Problems in Facility Planning & Design 2012 33. Refer to problem no. 29, compute the efficiency of the line. a. 88% c. 89% b. 91% d. 93% Answer: a. 88% lead time Efficiency = = (2 + 1 + 2 + 3 + 3 + 3) no. of workstations x cycle time = 87.5% 4(4) 34. Refer to problem no. 29, suppose demand increases to 160 pizzas per night. What is the new cycle time? a. 4 c. 14 b. 3 d. 13 Answer: b. 3 1 2 B A 3 3 3 D E F C 2 Cycle time = total working hours = (8 hours x 60 minutes/hour) desired units of output = 3 minutes (160 pizzas) 35. Refer to problem no. 34, balance the line based on the longest task time method. a. 3 5 3 3 AB CD E F 3 2 3 3 3 AB C D E F b. 97 | P a g e Solved Problems in Facility Planning & Design 2012 c. 4 1 3 3 3 AC B D E F 4 4 3 3 AC BD E F d. Answer: b Task A B C D E F 3 2 3 3 3 AB C D E F Time 2 1 2 3 3 3 Station 1 A (3 – 2 = 1) B (1 – 1 = 0) ST1 = 3 mins Rank 4 6 5 1 2 3 Station 2 C (3 – 2 = 1) Station 3 D (3 – 3 = 0) Station 4 E (3 – 3 = 0) Station 5 F (3 – 3 = 0) ST2 = 2 mins ST3 = 3 Mins ST4 = 3 mins ST5 = 3 mins 36. Refer to problem no. 34, calculate the new theoretical minimum number of workstations. a. 2 c. 4 b. 3 d. 5 Answer: d. 5 N= lead time cycle time 98 | P a g e = (2 + 1 + 2 + 3 + 3 + 3) 3 = 4.6 ≈ 5 workstations Solved Problems in Facility Planning & Design 2012 37. Neren’s Eye Care, Inc., is a full-service optical supplier that sells eyeglasses, contact lenses, protective eye apparel to opticians. Bogs’ job is to assemble custom-ordered lenses into eyeglasses for customers. Sales have been good lately, and Bogs has been assembling 100 glasses a day. The manager of Neren’s asked Bogs to write down the precedence requirements and approximate assembly times for each step in the assembly process. The data are shown here. Element Description Precedence A Inspect right and left lens for scratches and proper match Pop lens into frame Position right side piece and attach to frame Position left side piece and attach to frame Package - Time (min) 1.0 A B B C, D 1.0 0.4 0.4 2.0 B C D E Assuming an 8-hour workday, how long does it take Bogs to assemble one pair of glasses? a. 2 c. 4 b. 2.4 d. 4.8 Answer: d. 4.8 0.4 1 1 A B C E 2 D 0.4 Cycle time = total working hours desired units of output = (8 hours x 60 minutes/hour) = 4.8 minutes (100 eyeglasses) Lead time = (1 + 1 + 0.4 + 0.4 + 2) = 4.8 minutes 38. Refer to problem no. 37, Neren’s anticipates a surge in demand with the opening of its own retail outlets. If the assembly process is set up as an assembly line, what is the maximum number of eyeglasses that can be assembled in one day, regardless of the number of workers hired? a. 200 c. 100 b. 240 d. 480 Answer: b. 240 Maximum eyeglasses/day = (4.8 minutes x 100 eyeglasses) 2 minutes 99 | P a g e = 240 eyeglasses Solved Problems in Facility Planning & Design 1 1.8 2 A BCD E 2012 With maximum time in a workstation of 2 minutes it can produce 240 eyeglasses with 3 workers 39. Refer to problem no. 38, what is the efficiency of the line? a. 80% c. 100% b. 91% d. 95% Answer: a. 80% lead time Efficiency = = (1 + 1 + 0.4 + 0.4 + 2) no. of workstations x cycle time = 80% 3(2) 40. Prof. Jone has assigned 15 cases in his Seminar class to be completed in a 15 week semester. The students, of course, are moaning and groaning that the caseload cannot possibly be completed in the time allotted. Prof. Jone sympathetically suggests that the students work in groups and learn to organize their work efficiently. Knowing when a situation is hopeless, the students make a list of the tasks that have to be completed in preparing a case. These tasks are listed here, along with precedence requirements and estimated time in days. Assuming students will work 5 days a week on this assignment, how many students should be assigned to each group? Element Description Precedence Time (days) A b c d e f Read case Gather data Search literature Load in data Run computer analysis Write/type case a a b d c, e 1 4 3 1 4 4 a. 3 c. 5 b. 4 d. 6 Answer: b. 4 1 4 1 4 B D E A Cycle time = C F 3 4 total working hours desired units of output 100 | P a g e = (15 weeks x 5 days) (15 cases) = 5 days Solved Problems in Facility Planning & Design lead time N= = (1 + 4 + 3 + 1 + 4 + 4) cycle time 2012 = 3.4 ≈ 4 workstations or students 5 41. The precedence diagram and task times (in minutes) for assembling Reyson’s Stamp Pad are shown here. Set up an assembly line to produce 125 stamp pads in a 40-hour week. What is the cycle time? 8 5 A B F C D E 6 10 2 4 J H 9 7 K G I 5 2 a. 10 c. 61 3 b. 19.2 d. 2 Answer: b. 19.2 Cycle time = total working hours = (40 hours x 60 minutes/hour) desired units of output = 19.2 minutes (125 stamp pads) 42. Refer to problem no. 41, balance the line based on the most number of followers. a. 19 19 11 12 ABC DFG EHI JK 19 19 18 5 ACB DGF EHJ IK b. 101 | P a g e Solved Problems in Facility Planning & Design c. 19 17 13 12 ABC DEG FHI JK 19 16 14 12 ACB DFE GHI JK 19 19 18 5 ACB DGF EHJ IK d. Answer: b. Task Time Number of Followers Rank A B C D E F G H I J K 8 5 6 10 2 4 5 7 2 9 3 7 6 6 5 4 4 4 3 1 1 0 1 3 2 4 7 6 5 8 10 9 11 Station 1 A (19.2 – 8 = 11.2) C (11.2 – 6 = 5.2) B (5.2 – 5 = 0.2) ST1 = 19.0 102 | P a g e Station 2 D (19.2 – 10 = 9.2) G (9.2 – 5 = 4.2) F (4.2 – 4 = 0.2) ST2 = 19.0 Station 3 E (19.2 – 2 = 17.2) H (17.2 – 7 = 10.2) J (10.2 – 9 = 1.2) ST3 = 18 Station 4 I (19.2 – 2 = 17.2) K (17.2 – 3 = 14.2) ST4 = 5 2012 Solved Problems in Facility Planning & Design 2012 43. The work elements, precedence requirements, and time requirements to assemble a picture frame are shown here. What is the cycle time capable of producing 1,600 frames per 40-hour week? Element Description Precedence Time (min) A B C D E F G H I Attach left frame side to top of frame Attach right frame side to bottom of frame Attach left and right frame subassemblies Cut 8-inch x 10-inch glass Cut 8-inch x 10-inch cardboard Place glass into frame Place cardboard into frame Secure cardboard and glass Apply descriptive label to glass A, B C, D E, F F, G D 0.35 0.35 0.70 0.50 0.50 0.20 0.20 0.50 0.10 a. 1.5 c. 0.10 b. 0.70 d. 3.4 Answer: a. 1.5 .10 I .35 .50 A D .20 C F H .50 .70 B E .35 .50 G .20 Cycle time = total working hours desired units of output = (40 hours x 60 minutes/hour) = 1.5 minutes (1600 frames) 44. Refer to problem no. 43, balance the assembly line based on the computed cycle time using incremental utilization method a. 1.4 1.2 .80 ABC DEG FIH 103 | P a g e Solved Problems in Facility Planning & Design b. 1.30 1.40 DABI CEF 1.40 1.40 ABC DEFG 1.45 1.45 DEAI BCFG 0.70 GH c. 0.60 HI d. 0.50 H Answer: c 1.40 1.40 ABC DEFG 0.60 HI Based on Incremental Utilization Method (IUM) WS 1 1 1 1 2 2 2 2 2 3 3 Task A A, B A, B, C A, B, C, D D D, E D, E, F D, E, F, G D, E, F, G, H H H, I Task Time 0.35 0.35 + 0.35 = 0.70 0.70 + 0.70 = 1.40 1.40 + 0.50 = 1.90 0.50 0.50 + 0.50 = 1.00 1.00 + 0.20 = 1.20 1.20 + 0.20 = 1.40 1.40 + 0.50 = 1.90 0.50 0.50 + 0.10 = 0.60 # of WS’s 0.35/ 1.50 = 0.23 = 1 0.70/ 1.50 = 0.47 = 1 1.40/ 1.50 = 0.93 = 1 1.90/ 1.50 = 1.27 = 2 0.50/ 1.50 = 0.33 = 1 1.00/ 1.50 = 0.67 = 1 1.20/ 1.50 = 0.80 = 1 1.40/ 1.50 = 0.93 = 1 1.90/ 1.50 = 1.27 = 2 0.50/ 1.50 = 0.33 = 1 0.60/ 1.50 = 0.40 = 1 Effective CT = 1.40 45. Refer to Problem No. 44, what is the maximum output per week? a. 1,600 c. 1,750 104 | P a g e b. 1,715 d. 1,656 Incremental Util 23% 47% 93% 63% 33% 67% 80% 93% 63% 33% 40% 2012 Solved Problems in Facility Planning & Design 2012 Answer: b. 1,715 Maximum Output per Week = 2,400 mins per week = 1,715 units/ week -----------------------------1.40 46. Refer to problem no. 43, balance the assembly line based on the computed cycle time using most number of followers method. a. 1.4 1.2 .80 ABC DEG FIH 1.30 1.40 DABI CEF 1.40 1.40 ABC DEFG 1.45 1.45 DEAI BCFG b. 0.70 GH c. 0.60 HI d. 0.50 H Answer: b Based on the Most Number of Task Followers: Task A B D C E F G H I Time 0.35 0.35 0.70 0.50 0.50 0.20 0.20 0.50 0.10 105 | P a g e No. of Task Followers 4 4 4 3 2 2 1 0 0 Rank 2 3 1 4 5 6 7 8 9 Solved Problems in Facility Planning & Design Station 1 D (1.50 – 0.50 = 1.00) A (1.00 – 0.35 = 0.65) B (0.65 – 0.35 = 0.30) I (0.30 – 0.10 = 0.20) ST = 1.5 – 0.20 = 1.30 Station 2 C (1.50 – 0.70 = 0.80) E (0.80 – 0.50 = 0.30) F (0.30 – 0.20 = 0.10) 2012 Station 3 G (1.5 – 0.20 = 1.30) H (1.3 – 0.50 = 0.80) ST = 1.5 – 0.10 = 1.40 ST = 1.5 – 0.80 = 0.70 Effective CT = 1.40 1.30 1.40 DABI CEF 0.70 GH 47. Refer to Problem No. 46, what is the maximum output per week? a. 1,600 c. 1,750 b. 1,715 d. 1,656 Answer: b. 1,715 Maximum Output per Week = 2,400 mins per week = 1,715 units/ week -----------------------------1.40 48. Refer to problem no. 43, balance the assembly line based on the computed cycle time using longest task time method. a. 1.4 1.2 .80 ABC DEG FIH 1.30 1.40 DABI CEF 1.40 1.40 ABC DEFG b. 0.70 GH c. 106 | P a g e 0.60 HI Solved Problems in Facility Planning & Design d. 1.45 1.45 DEAI BCFG 0.50 H Answer: d Based on the Longest Task Time Task A B C D E F G H I Task Time (min) 0.35 0.35 0.70 0.50 0.50 0.20 0.20 0.50 0.10 Station 1 D (1.50 – 0.50 = 1.00) E (1.00 – 0.50 = 0.50) A (0.50 – 0.35 = 0.15) I (0.15 – 0.10 = 0.05) ST = 1.5 – 0.05 = 1.45 Rank 5 6 1 2 3 7 8 4 9 Station 2 Station 3 B (1.50 – 0.35 = 1.15) H (1.5 – 0.50 = 1.00) C (1.15 – 0.70 = 0.45) F (0.45 – 0.20 = 0.25) G (0.25 – 0.20 = 0.05) ST = 1.5 – 0.05 = 1.45 ST = 1.5 – 1.00 = 0.50 Effective CT = 1.45 1.45 1.45 DEAI BCFG 0.50 H 49. Refer to Problem No. 48, what is the maximum output per week? a. 1,600 c. 1,750 b. 1,715 d. 1,656 Answer: d. 1,656 Maximum Output per Week = 107 | P a g e 2,400 mins per week = 1,656 units/ week -----------------------------1.45 2012 Solved Problems in Facility Planning & Design 2012 50. Refer to problem no. 43, calculate the maximum number of frames that can be assembles each week. a. 2,557 c. 3,567 b. 2,452 d. 3,429 Answer: d. 3,429 Number of frames(in a week) = 5 days 8 hours x week x 60 minutes day x hour 1 frame = 3428.57 ≈ 3429 0.70min 51. Refer to problem no. 50, rebalance the line for maximum production. Assuming one worker per workstation. How many workers would be required? a. 5 c. 6 b. 4 d. 3 Answer: a. 5 Cycle time = total working hours = (40 hours x 60 minutes/hour) desired units of output = 0.7 minutes (3428 frames) Lead time = (0.35 + 0.35 + 0.70 + 0.50 + 0.50 + 0.20 + 0.20 + 0.50 + 0.10) = 3.4 minutes N= lead time = cycle time 3.4 = 4.86 ≈ 5 workers 0.7 52. Refer to problem no. 50, assume the company can sell as many frames as can be produced. If workers are paid P60.00 an hour. What is the total cost per frame? a. 1.67 c. 6.17 b. 1.47 d. 7.14 Answer: d. 7.14 Cost per worker = 3428 frame week x 1 week 5 day x 1 day 8 hour x 1 hour P60.00 Total cost = P1.42833 x 5 workers = P7.14 / frame 108 | P a g e = P1.42833 / worker Solved Problems in Facility Planning & Design 2012 53. The Racela Finance Corporation has set a processing quota of 80 insurance claims per 8-hour day. The claims process consists of five elements, which are detailed in the following table. Racela has decided to use an assembly line arrangement to process the forms and would like to make sure they have set up the line in the most efficient fashion. Calculate the cycle time required to meet the processing quota. Element A B C D E Precedence A B A C, D Performance Time (min) 4 5 2 1 3 a. 5 c. 15 b. 6 d. 16 Answer: b. 6 4 5 2 A B C 3 E D 1 total working hours Cycle time = = desired units of output (8 hours x 60 minutes/hour) = 6 minutes (80 insurance claims) 54. Refer to problem no. 53, determine how many claims can actually be processed on your line. a. 60/ day c. 80/ day b. 70/ day d. 90/ day Answer: c. 80/ day No. of claims = 8 hour day 109 | P a g e x 60 minutes hour x _1 claim = 80 / day 6 minute Solved Problems in Facility Planning & Design 2012 55. A firm must produce 40 units/day during an 8-hour workday. Tasks, times, and predecessor activities are given below. Task A B C D E F G H Total Time (Minutes) 2 2 8 6 3 10 4 3 38 minutes Predecessor(s) A C B D, E F G Determine the cycle time to produce the 40 units per day. a. 10 c. 12 b. 38 d. 20 Answer: c. 12 Cycle Time = 8 hrs x 60 mins/hr = 480 = 12 minutes 40 units 40 56. Thomas Santos, manager of a metropolitan branch office of the state department of motor vehicles, attempted to perform an analysis of the driver’s license renewal operations. Several steps were to be performed in the process. After examining the license renewal process, he identified the steps and associated times required to perform each step as follows: Job A. Review renewal application for correctness B. Process and record payment C. Check file violations and restrictions D. Conduct eye test E. Photograph applicant F. Issue temporary license Average Time to perform (seconds) 15 30 60 40 20 30 Santos found that each step was assigned to a different person. Each application was a separate process in the sequence. Santos determined that his office should be prepared to accommodate the maximum demand of processing 120 renewal applicants per hour. He observed that the work was unevenly divided among the clerks, and that the clerk who was responsible for checking violations tended to shortcut her task to keep up with the other clerks. Long lines built up during the maximum demand periods. Santos also found that jobs A, B, C, and D were handled by general clerks who were each paid P270.00 per hour. Job E was by a photographer paid P360.00 per hour. Job F, the issuing of temporary licenses, was required by state policy to be handled by a uniformed motor vehicle officer. Officers were paid P405.00 per hour, but they could be assigned to any job except photography. 110 | P a g e Solved Problems in Facility Planning & Design 2012 A review of the jobs indicated that job A, reviewing the application for correctness, had to be performed before any other step could be taken. Similarly, job F, issuing the temporary license, could not be performed until all the other steps were completed. The checking of file violations and restrictions could be performed while the applicant is having his eye test. The branch offices were charged P450.00 per hour for each camera to perform photography. Determine the maximum number of applications per hour that can be handled by the present configuration of the process? a. 60 c. 120 b. 90 d. 180 Answer: a. 60 Precedence Diagram 60 C 15 A 30 20 30 B E F D 40 CT = 60 seconds Max. no. of application per hour = 3,600 = 60 applications per hour 60 57. Refer to problem no. 56, how many applications can be processed per hour if a second clerk is added to check for violations? a. 60 c. 120 b. 90 d. 180 Answer: b. 90 30 15 A C 30 20 30 B E F D 40 111 | P a g e Solved Problems in Facility Planning & Design 2012 CT = 40 seconds Max. no. of applications per hour = 3,600 = 90 applications per hour 40 58. In addition to problem no. 57, assuming one more clerk is added to job D, what is the maximum number of applications the process can handle? a. 60 c. 120 b. 90 d. 180 Answer: c. 120 30 C 15 A 30 20 30 B E F D 20 CT = 30 seconds Max. no. of applications per hour = 3,600 = 120 applications per hour 30 59. Refer to problem no. 56, what is the required cycle time of the process to accommodate 180 applications per hour? a. 15 c. 40 b. 20 d. 60 Answer: b. 20 Max. no. of applications per hour = 180 application per hour CT = 3,600 = 20 seconds 180 15 A 15 C 15 20 15 B E F D 20 112 | P a g e Solved Problems in Facility Planning & Design 2012 60. Refer to problem no. 56, compute for the costs per application per hour involved in the current process. a. 30.60 c. 23.40 b. 18.90 d. 38.25 Answer: d. 38.25 Job No. of Worker & Labor Cost Current A B C D E F 1 x 270 = 270.00 1 x 270 = 270.00 1 x 270 = 270.00 1 x 270 = 270.00 1 x 360 = 360.00 1 x 405 = 405.00 ------------1845.00 camera +450.00 ------------2295/ 60 applications P38.25 per application 61. Refer to problem no. 58, for the costs per application per hour involved in the alternative process. a. 30.60 c. 23.62 b. 18.90 d. 38.25 Answer: c. 23.62 Job No. of Worker & Labor Cost Alternative A B C D E F camera 1 x 270 = 270.00 1 x 270 = 270.00 2 x 270 = 540.00 2 x 270 = 540.00 1 x 360 = 360.00 1 x 405 = 405.00 ------------2385.00 +450.00 ------------2835/ 120 applications P23.62 per application 62. Assume that production volume is 1,600 pieces per day, the standard time is 0.004 hour per piece, 8 working hours per day, setup time at 0.2 hr per day, and scrap rate of 0.10. Find the fractional machine number. a. 1.12 c. 0.91 113 | P a g e b. 0.85 d. 1.21 Solved Problems in Facility Planning & Design 2012 Answer: c. 0.91 F = 1600(0.0004)/ (8 – 0.2)(0.90) = 0.91 63. A product requires two sequential machine operations. The first takes 3.5 minutes and the defect percentage is 12. The second takes 6.0 minutes and the defect percentage is 7. In another similar plant belonging to the same company, past annual data on identical operations and working conditions indicate that a total of 2,198 hours due to set up of machines and 2,052 hours due to machine unavailability due to maintenance per year. Assuming 250 work days per year and a daily shift of 10 hours, it is desired to determine the minimum fractional number of machines to manufacture 50,000 units per year. a. 4 c. 6 b. 5 d. 7 Answer: b. 5 P2 = 50,000/0.93 = 53,763.44 P1 = 53,763.44/0.88 = 61,094.82 F = ((53,763.44)(6) + (61094.82)(3.5))/(60*250*10)(2,198/2,500)(2,052/2,500)) = 5 64. Eric Explosives Company is considering the expansion of a solid-propellant manufacturing process by adding more 1-ton capacity curing furnaces. Each batch (1 ton) of propellant must undergo 30 minutes of furnace time, including load and unload operations. However, the furnace is used only 80 percent of the time due to power restrictions in the other parts of the system. The required output for the new layout is to be 16 tons per shift (8 hours). Plant (system) efficiency is estimated at 50 percent of system capacity. Determine the number of furnaces required. a. 3 c. 1 b. 4 d. 5 Answer: a. 3 F = 30 mins per ton x 16 tons per shift/ 8 x 60 x 0.50 x 0.80 = 480/ 192 = 2.5 = 3 65. Refer to problem no. 64, estimate the percentage of time the furnaces will be idled. a. 20% c. 33% b. 25% d. 67% Answer: d. 67% Percentage of Idle Time: Total hours available per shift = 3 furnaces @ 8 hours Total hours of actual use per shift = 16 tons (0.5 hr/ ton) Idle Time Percentage of Idle Time = 16 hours idle/ 24 hours total 114 | P a g e = 24 furnace hours = 8 furnace hours = 16 hours = 67% idle time Solved Problems in Facility Planning & Design 2012 66. Charmz Developing Agency must determine how many photo-enlarger cubicles are required to maintain an output of 200 good prints per hour. The set-up and exposure time can theoretically be done in 2 minutes per print, but operators are on the average only 90 percent efficient and, in addition, 5 percent of the prints must be scrapped and redone. Also, the cubicles can be utilized for enlarging only 70 percent of the time. What is the required process capacity in prints per hour? a. 212 c. 211 b. 250 d. 200 Answer: c. 211 Required process capacity = good output/ process efficiency = 200/ 0.95 = 211 prints/ hr 67. Refer to problem no. 66, what average output per hour can be expected from each cubicle, taking its use factor and efficiency into account? a. 211 c. 19 b. 30 d. 200 Answer: c. 19 Output/ hr = (unit capacity) (utilization) (efficiency) Where unit capacity = 60 mins/ hr/ 2 mins/ print = 30 prints/ hr Output/ hr = (30 prints/ hr) (0.70) (0.90) = 18.9 prints/ hr = 19 68. Refer to problem no. 66, how many enlarger cubicles are required? a. 14 c. 16 b. 10 d. 12 Answer: d. 12 Number of cubicles = 210.5 prints/ hr required/ 18.9 prints/ hr-cubicle = 11.4 or 12 cubicles 69. Dason Plastics manufacturer must acquire some molding machines capable of producing 160,000 good parts per year. They will be installed in a production line that normally produces 20 percent rejects because of the tight aerospace specifications. Assume that it takes 90 seconds to mold each part and the plant operates 2,000 hours per year. If the molding machines are used only 50 percent of the time and are 90 percent efficient, what actual (usable) molding machine output per hour would be achieved? a. 40 c. 45 b. 18 d. 20 Answer: b. 18 Output/ hr Where, unit capacity Output/ hr 115 | P a g e = (unit capacity) (utilization) (efficiency) = 60 mins/ hr/ 1.5 mins/ part = 40 parts/ hr = (40 parts/ hr) (0.50) (0.90) = 18 parts/ hr Solved Problems in Facility Planning & Design 70. Refer to problem no. 69, how many molding machines would be required? a. 4 c. 6 b. 8 d. 12 Answer: c. 6 Number of Molding Machines = (160,000/ 0.80)(1.5)/ (2000)(60)(0.50)(0.90) = 300,000/ 54,000 = 5.56 = 6 machines 71. Given: Year vi. vii. viii. ix. x. Demand (units) 220,000 275,000 380,000 420,000 565,000 % Scrap: 3% Standard Time: 2 minutes per unit Target Machine Efficiency: 90% Machine Breakdown: 30 minutes per day Operation Schedule: 8am – 4pm daily schedule/ 20 working days per month How many machines you will acquire/ buy on Year 1? a. 5 c. 2 b. 7 d. 9 Answer: a. 5 Given: H = 480 E = 0.85 R = 480-30 = 450/480 = 0.9375 T = 2 mins per unit O1 = 220,000 per year O2 = 275,000 per year O3 = 380,000 per year O4 = 420,000 per year O5 = 565,000 per year P = 3% Solution: Q1 = 220,000/ (1 – 0.03) = /12 = /20 = 945.017 per day Q2 = 275,000/ (1 – 0.03) = /12 = /20 = 1,181.271 per day Q3 = 380,000/ (1 – 0.03) = /12 = /20 = 1,632.302 per day Q4 = 420,000/ (1 – 0.03) = /12 = /20 = 1,804.124 per day Q5 = 565,000/ (1 – 0.03) = /12 = /20 = 2,426.976 per day HER = 480 x 0.85 x 0.9375 = 382.5 F1 = 945.017 x 2 = 4.9 = 5 machines 382.5 116 | P a g e 2012 Solved Problems in Facility Planning & Design 72. Refer to problem 71, how many machines you will acquire/ buy on Year 2? a. 5 c. 2 b. 7 d. 9 Answer: c. 2 F1 = 945.017 x 2 = 4.9 = 5 machines 382.5 F2 = 1,181.271 x 2 = 6.2 = 7 machines 382.5 Therefore, buy only 2 machines (7 – 5 = 2) in year 2 73. Refer to problem no. 71, how many machines you will acquire/ buy on Year 3? a. 5 c. 2 b. 7 d. 9 Answer: c. 2 F2 = 1,181.271 x 2 = 6.2 = 7 machines 382.5 F3 = 1,632.302 x 2 = 8.5 = 9 machines 382.5 Therefore, buy only 2 machines (9 – 7 = 2) in year 3 74. Refer to problem no. 71, how many machines you will acquire/ buy on Year 4? a. 1 c. 2 b. 10 d. 9 Answer: a. 1 F3 = 1,632.302 x 2 = 8.5 = 9 machines 382.5 F4 = 1,804.124 x 2 = 9.4 = 10 machines 382.5 Therefore, buy only 1 machine (10 – 9 = 1) in year 4 75. Refer to problem no. 71, how many machines you will acquire/ buy on Year 5? a. 1 c. 3 b. 10 d. 13 Answer: c. 3 F4 = 1,804.124 x 2 = 9.4 = 10 machines 382.5 F5 = 2,426.976 x 2 = 12.7 = 13 machines 382.5 Therefore, buy only 3 machines (13 – 10 = 3) in year 5 117 | P a g e 2012 Solved Problems in Facility Planning & Design 2012 76. A team of Industrial Engineers conducted a work sampling of identical machines being used for a manufacturing company and they have observed the following: % Idleness Machine 1 20% Machine 2 35% Machine 3 15% Machine 4 55% The machines are running based on the schedule of operation per shift. Shift Schedule: 6am – 2pm/ 2pm – 10pm/ 10pm – 6am Break Time: 1-hr meal break and 15 minutes coffee or short break per shift. Compute for the number of machines required in a given shift. a. 1 c. 3 b. 2 d. 4 Answer: c. 3 SQ = 405 (0.80) + 405 (0.65) + 405(0.85) + 405(0.45) = 1113.75 minutes E = not given so considered 1 R = not given so considered 1 H = 8 x 60 = 480 – 60 –15 = 405 per shift F = 1113.75/ 405 = 2.75 = 3 machines 77. Mandy Garments produces T-shirts for road races. They need to acquire some new stamping machines to produce 30,000 good T-shirts per month. Their plant operates 200 hours per month, but the new machines will be used for T-shirts only 60 percent of the time and the output usually includes 5 percent that are ―seconds‖ and unusable. The stamping operation takes 1 minute per T-shirt, and the stamping machines are expected to have 90 percent efficiency when considering adjustments, changeover of patterns, and unavoidable downtime. How many machines are required? a. 5 c. 7 b. 6 d. 8 Answer: a. 5 Number of stamping machines = (30,000/ 0.95)(1 minute/ T-shirt)/ (200)(60)(0.60)(0.90) = 31,578.95/ 6480 = 4.9 = 5 machines 78. During one-8-hour shift, 770 non-defective parts are desired from a fabrication operation. The standard time for the operation is 12 minutes. Because the machine operators are unskilled, the actual time it takes to perform the operation is 25 minutes and, on the average, one-sixth of the parts that begin fabrication are scrapped. Assuming that each of the machines used for this operation will not be available for 45 minutes each shift and there is a probability of 0.05 that each machine will breakdown, determine the number of machines required. a. 50 c. 54 118 | P a g e b. 52 d. 56 Solved Problems in Facility Planning & Design 2012 Answer: d. 56 Given: S = 12 mins. E = 12/25 = 0.48 R = 1 – 0.05 = 0.95 H = 480 – 45 = 453 mins. P = 1/6 = 0.167 Q= 770 = 924 Parts 1 – 0.167 Solution: F = SQ = 12 x 924 HER 435 x 0.48 x 0.95 = 55.92 = 56 machines 79. A plastic firm has four work centers (A, B, C, and D) in series with individual capacities (units per day) and actual output as shown. A 450 B 390 C 360 D 400 actual output = 306/ day What is the process capacity? a. 306 c. 450 b. 360 d. 1,600 Answer: b. 360 Process Capacity = capacity of most limited component in the line = 360 units/ day 80. Refer to Problem no. 79, what is the process efficiency? a. 19% c. 68% b. 22.5% d. 85% Answer: d. 85% Process Efficiency = actual output/ process capacity = 306/ 360 = 85% 119 | P a g e Solved Problems in Facility Planning & Design 2012 81. Dennis Furniture Company manufactures four-drawer oak cabinets in six stages. In the first stage, the boards forming the walls of the cabinets are cut; in the second stage the front drawer panels are woodworked; in the third stage the boards are sanded and finished; in the fourth stage the boards are cleaned, stained, and painted with a clear finish; in the fifth stage the hardware for pulls, runners, and fittings is installed; and in the final stage the cabinets are assembled. Inspection occurs at each stage of the process, and the average percentages of good-quality units are as follows: Stage 1 2 3 4 5 6 Average Percentage Good Quality 87% 91% 94% 93% 93% 96% The cabinets are produced in weekly production runs with a product input for 300 units. Determine the weekly product yield of good-quality cabinets. a. 186 c. 312 b. 288 d. 486 Answer: a. 186 O = (300)(0.87)(0.91)(0.94)(0.93)(0.93)(0.96) = 185.3 = 186 82. Refer to problem no. 81, what would weekly product input have to be in order to achieve a final weekly product yield of 300 cabinets? a. 186 c. 312 Answer: c. 486 I = I = 300 / (0.87)(0.91)(0.94)(0.93)(0.93)(0.96) 485.5 = 486 120 | P a g e b. 288 d. 486 Solved Problems in Facility Planning & Design 2012 83. The Jelo Motor Company, motors are produced in a three-stage process. Motors are inspected following each stage with percentage yields of good quality in process units as follows: Stage 1 Average Percentage Good Quality 0.96 2 0.98 3 0.95 The company wants to know the daily product yield for product input of 250 units per day. a. 263 c. 223 b. 238 d. 280 Answer: c. 223 O = O = (250)(0.96)(0.98)(0.95) 223.44 = 224 84. Refer to problem no. 83, how many input units it would have to start with each day to result in a final daily yield of 250 good quality units? a. 263 c. 223 b. 238 d. 280 Answer: c. 223 I = I = 250 / (0.96)(0.98)(0.95) 279.72 motors = 280 85. Rafael Metals Company manufactures of wood burning stove. What is the product input for 15,000 stoves if the good quality of each stove is 88%? a. 13,200 c. 125,000 Answer: d. I = I = I = O/(1 - P) 15,000/(1 - 0.12) 17,045.45 = 17,045 121 | P a g e b. 1,800 d. 17,045 Solved Problems in Facility Planning & Design 2012 86. Lara Company operates a small telephone order system for a catalog of its clothing products. The catalog orders are processed in four stages. Errors can be made in orders at any of these stages, and the average percentages of errors that occur at each stage are as follows. Stage 1 2 3 4 %Error 19% 16% 10% 8% If an average of 460 telephone orders is processed each day, how many errorless orders will result? a. 112 c. 244 b. 259 d. 129 Answer: b. 259 O = O = O = 460 (1 - 0.19)(1 - 0.16)(1 - 0.10)(1 - 0.08) 460(0.81)(0.84)(0.90)(0.92) 259.15 = 259 87. Liam Manufacturing Company has a weekly product input of 2,800 units. The average percentage of good-quality product is 87 percent. Of the poor quality products 60 percent can be reworked and sold as good-quality products. Determine the weekly product output? a. 2,654 c. 1,462 b. 5,364 d. 3,218 Answer: 2,654 O = O = O = 2,800(0.87) + 2,800(0.13)(0.60) 2,436 + 218.4 2,654.4 = 2,654 88. Given: From/To A B C D E F 122 | P a g e A B 15 C 50 20 50 E 75 120 50 110 D 100 100 F 125 120 Solved Problems in Facility Planning & Design 2012 Design a layout on a 3x3 grid that will minimize nonadjacent load. What is the layout of your building? a. A B C D E F C B E F A D B A F E C D D B E C F A b. c. d. Answer: c. B 235 35 125 A 220 100 E C 220 Zero non-adjacent loads 123 | P a g e F D Solved Problems in Facility Planning & Design 2012 Layout: B A F E C D 89. Given: Department 1 2 3 4 5 6 1 Number of loads per week 2 3 4 5 6 50 100 20 30 50 10 20 100 50 Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building? a. 1 2 6 4 3 5 5 2 1 4 3 6 b. 124 | P a g e Solved Problems in Facility Planning & Design c. 2 6 5 3 4 1 6 3 4 1 5 2 d. Answer: b. 5 10 50 50 2 3 20 20 100 Zero non-adjacent loads Layout: 125 | P a g e 1 100 30 4 50 5 2 1 4 3 6 6 2012 Solved Problems in Facility Planning & Design 2012 90. Given: Department 1. Administration 2. Social services 3. Institutions 4. Accounting 5. Education 6. Internal audit 1 Number of loads per week 2 3 4 5 6 3 6 5 6 10 8 1 1 3 9 2 1 Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building? a. 4 1 2 6 5 3 3 6 4 2 5 1 1 5 4 3 6 2 6 3 2 5 1 4 b. c. d. 126 | P a g e Solved Problems in Facility Planning & Design 2012 Answer: d. 1 Diagram: 6 8 3 9 10 1 5 3 3 6 1 1 4 5 6 Non-adjacent loads 5-2 1 5-4 2 Total = 3 2 2 Layout: 6 3 2 5 1 4 91. Given: Loads/day From/To A B A 30 B C D E C 30 D 60 E 20 30 80 40 Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building? a. C A D E B 127 | P a g e Solved Problems in Facility Planning & Design b. C B D A B D E A A E C B E c. C d. D Answer: c. Diagram: C 30 80 B D 30 80 E 40 20 Zero non-adjacent loads 128 | P a g e 60 A 2012 Solved Problems in Facility Planning & Design 2012 Layout: B D E A C 92. Matthew Design Company has been asked to design the layout for a newly constructed office building of one of its clients. The closeness matrix showing the daily trips between its six department offices is given below. Department Trips between Departments 2 3 4 5 6 25 90 165 105 125 125 25 105 1 1 2 3 4 5 6 Design a layout on a 2x3 grid that will minimize nonadjacent load. What is the layout of your building? a. 3 1 5 6 4 2 2 5 3 4 1 6 b. 129 | P a g e Solved Problems in Facility Planning & Design c. 5 1 4 3 6 2 1 6 2 3 5 4 d. Answer: b. Diagram: 105 2 25 5 125 90 25 105 4 1 125 165 Zero non-adjacent loads Layout: 130 | P a g e 3 2 5 3 4 1 6 6 2012 Solved Problems in Facility Planning & Design 2012 93. Given: Flow between Departments (Number of Moves) 7 8 1 2 3 4 5 6 20 75 175 150 80 120 90 100 125 350 25 25 180 187 374 103 7 Departments 1. Shipping and receiving 2. Plastic molding stamping 3. Metal forming 4. Sewing department 5. Small toy assembly 6. Large toy assembly 7. Painting 8. Mechanism assembly Design a layout on a 3x3 grid that will minimize nonadjacent load. What is the layout of your building? a. 5 1 2 6 4 3 7 8 1 7 5 2 6 3 8 4 b. 131 | P a g e Solved Problems in Facility Planning & Design c. 4 5 6 1 3 2 8 7 6 4 7 8 2 5 1 3 d. Answer: d. 25 6 Diagram: 4 25 125 374 7 7 120 8 350 90 75 5 80 1 3 150 Zero non-adjacent loads 132 | P a g e 2 175 187 2 180 100 103 2012 Solved Problems in Facility Planning & Design 2012 Layout: 6 4 7 8 2 5 1 3 94. Giv en: From/To Stores Turning Milling Press Plate Assembly Warehouse Stores Turning 6 1 Milling 12 3 Press 9 Plate 1 4 7 3 Assembly 4 3 2 1 4 1 Warehouse 1 3 7 Design a layout on a 3x3 grid that will minimize nonadjacent load. What is the layout of your building? a. Press Warehouse Warehouse Plate Milling Stores Turning b. 133 | P a g e Turning Stores Milling Press Warehouse Plate Assembly Solved Problems in Facility Planning & Design 2012 c. Assembly Warehouse Turning Plate Press Assembly Stores d. Milling Assembly Plate Warehouse Turning Stores Press Answer: c. Diagram: 7 Assembly 1 2 3 Turning 134 | P a g e 3 4 8 Milling Plate Warehous 1 3 Press 5 1 1 6 Stores 9 5 Non-adjacent load Assembly-Stores 5 Total = 5 Solved Problems in Facility Planning & Design Layout: Assembly Warehouse Milling Plate Press Turning Stores 95. Based on the relationship chart below, what is it recommended layout? a. 4 6 1 5 2 3 6 4 1 5 3 2 2 3 6 1 5 b. c. 4 135 | P a g e 2012 Solved Problems in Facility Planning & Design d. 6 3 2 5 1 4 Answer: c. 2 3 6 1 5 4 2 3 6 1 5 4 96. Based on the relationship chart below, what is its recommended layout? 136 | P a g e 2012 Solved Problems in Facility Planning & Design a. 5 b. 5 3 1 2 4 6 7 1 3 4 2 6 7 3 1 2 4 7 5 1 3 2 4 5 7 c. 6 d. 6 Answer: d. 6 6 137 | P a g e 1 3 2 4 5 7 1 3 2 4 5 7 2012 Solved Problems in Facility Planning & Design 2012 97. Given: Legend: A I U CV Values 10,000 100 0 Activity Legend E O X CV Values 1,000 10 -1,000 Area (sq. m) 1. Wood cutting 1,280 2. Receiving 560 A E I 3. Framing U U 1,280 I 4. Upholstery U 1,120 E 5. Fabric storage 960 6. Fabric cutting 960 A E A 7. Sewing 8. Shipping 640 800 9. Offices 800 10. General Storage 480 I U O U O X U E E U I U U X U U I U U U U U I U U U I U U U U O E O Distance between departments: Adjacent = 1, Partial Adjacent = 0.5, Non-Adjacent = 0 Using CORELAP, what is Total Closeness Rating (TCR) Value of Department 1? a. 10,000 c. 12,000 b. 11,000 d. 14,000 Answer: c. 12,000 TCR – Department 1 = 10,000(1) + 1,000(1) + 100(0) + 10(0) + 0(6) + absolute - 1000 (1) = 12,000 98. In reference to problem no. 97, what activity is the first to be placed on the grid? a. 7 c. 5 b. 2 d. 6 Answer: d. 6 TCR – Department 6 = 10,000(2) + 1,000(1) + 100(1) + 10(0) + 0(5) + absolute - 1000 (0) = 21,100 138 | P a g e Solved Problems in Facility Planning & Design 99. In reference to problem no. 98, what is your final layout? a. 2 10 5 6 1 3 7 8 4 9 10 1 7 3 5 6 8 9 2 10 1 4 8 9 2 3 5 6 b. 4 c. 7 139 | P a g e 2012 Solved Problems in Facility Planning & Design d. 2 10 5 6 8 4 7 1 3 9 10 5 6 8 4 7 1 3 9 Answer: a. 2 DEPARTMENT 1 2 3 4 5 6 7 8 9 10 140 | P a g e 1 A E U X U U U U U 2 A I U E E X I U I 3 E I I U U U U U U 4 U U I E I I I U U 5 X E U E A E U U U 6 U E U I A A A U U U 7 U X U I E A U U O O 8 U I U I U U U O O E 9 10 U U U I U U U U U U U U O O O E O O A 1 1 0 0 1 2 1 0 0 0 E 1 2 1 1 3 1 1 1 0 1 I 0 3 2 4 0 1 1 2 0 1 O 0 0 0 0 0 0 2 1 3 2 U 6 2 6 4 4 5 3 5 6 5 X 1 1 0 0 1 0 1 0 0 0 TCR ORDER 12,000 5 13,300 3 1,200 8 1,400 6 14,000 2 21,100 1 12,120 4 1,210 7 300 10 1,120 9 2012 Solved Problems in Facility Planning & Design 5000 10000 5000 10000 5000 6 10000 10000 5000 wp5 500 6000 10500 5000 1000 5 6 500 6000 10500 10000 5000 5-6 = A = 10,000 5-5-7 = E = 1,000 6-7 = A = 10,000 500 1000 1050 550 50 0 0 0 5 150 50 500 1150 50 6 7 150 50 100 50 5 4 6 7 100 50 100 4-5 = E = 1,000 4-6 = I = 100 4-7 = I = 100 0 0 0 8 6 7 10 0 1000 505 10 5 0 0 1000 1000 500 0 8-10 = E = 1,000 5-10 = U = 0 6-10 = U = 0 4-10 =U = 0 7-10 = O = 10 0 0 0 0 0 0 0 0 10 8 5 4 6 7 0 50 100 50 0 0 3-10 = U =0 3-5 = U = 0 3-6 = U = 0 3-8 = U = 0 3-4 =I =100 3-7 = U = 0 10 5 0 0 50 500 1500 1500 500 10 8 1 5 4 3 6 7 5 150 10 5,150 6 7 9 0 0 10050 5000 5 4 3 -500 5 10 8 1 10050 5100 50 10 0 9-10 = O =10 9-5 = U = 0 9-6 = U = 0 9-8 = O = 10 9-4 = U = 0 9-7 = O = 10 9-1 = U = 0 9-3 = U = 0 2-10 = I =100 2-8 = I = 100 2-1 = A = 10,000 2-3 = I = 100 2-9 = U = 0 2-7 = X = -1000 2-6 = E = 1,000 2-5 = E = 1,000 FINAL 2 141 | P a g e 0 0 0 8-5 = U = 0 8-6 = U =0 8-4 = I = 100 8-7 = U = 0 5 4 500 0 10 8 1 5 4 3 6 7 9 500 -500 0 2012 Solved Problems in Facility Planning & Design 2012 100. Given: Parts-Machines Matrix Parts 1 2 3 4 5 x x x x x x x x x x x x x x x x A B C D E F G H I J K L Machines 6 x 7 8 x x x x x x x x x x Using Digital Clustering Algorithm (DCA), prepare the final cell formation with additional machines, if needed. a. D A H B J L G K C F I E b. D A H B J L1 G K L2 5 6 1 4 X X X X X X X X X X X X X X 2 8 7 3 X X X X X X X X X X X X X 5 6 1 4 X X X X X X X X X X X X X X 2 8 X X X 7 3 X X X C F I E 142 | P a g e X X X X X X X Solved Problems in Facility Planning & Design c. 5 6 1 4 D A H B J C F I E L G K X X X X X X X X X X X X X X 5 6 1 4 D A H B J C F I X X X X X X X X X X X X X X d. 7 3 X X X X X 2 8 X X X X X X X X X 7 3 X X X X X X E1 E2 2 8 x x X L G K X X X X X Answer: b. D A H B J L1 G K L2 5 6 1 4 X X X X X X X X X X X X X X 2 8 X X X X 7 3 X X C F I E 143 | P a g e X X X X X X X 2012 Solved Problems in Facility Planning & Design Solutions: Present machine layout and parts movement PRESENT LAYOUT PARTS MACHINES OUTPUT/ASSEMBLY A 1 B 2 C 5 3 D E 4 F 5 G 6 6 H 3 7 I 8 1 J 4 K 7 L 2 8 Sum of Xs per column and row in order 5 D A H L B C F G I J E K 144 | P a g e 2 3 X X 6 1 4 X 8 X X X X X X X X X X X X X X X X X X 7 X X X X X X 2012 Solved Problems in Facility Planning & Design Matrix with sorted columns D A H L B C F G I J E K 5 6 1 4 X X X X X X X X X X X X 2 8 7 X X X X X 3 X X X X X X X X X X Matrix with sorted rows D A H B J L G K C F I E 5 6 1 4 X X X X X X X X X X X X X X 2 8 7 X X X X X 3 X X X X X X X X Final cell formation with additional machines, if needed D A H B J L1 G K L2 6 1 4 X X X X X X X X X X X X X 2 8 X X X 7 3 X X X C F I E 145 | P a g e 5 X X X X X X X X 2012 Solved Problems in Facility Planning & Design Proposed cellular layout PROPOSED LAYOUT PARTS MACHINES OUTPUT/ASSEMBLY 5 D 5 6 A 1 H 6 B 4 J 2 1 4 L G 2 8 K 8 7 L2 3 C F 146 | P a g e I 7 E 3 2012 Solved Problems in Facility Planning & Design 2012 REFERENCES [1] Clark, J. E., ―Facility Planning, Principles, Technology, Guidelines‖. Pearson Prentice Hall, 2008 [2] Francis, R.L., McGinnis, L.F., Jr., and White, J.A. ―Facility Layout and Location – An Analytical Approach, Second Edition‖. Prentice Hall, Inc., 1992 [3] Garcia-Diaz, A., and Smith, J.M. ―Facilities Planning and Design‖. Pearson Prentice Hall, 2008 [4] James, R. W. and Alcorn, P.A. ―A Guide to Facilities Planning‖. Pearson Prentice Hall, 1991 [5] Russel, R.S. and Taylor, B.W., III ―Operations Management, Third Edition‖, Prentice Hall, Inc., 2000 [6] Schonberger, R.J., and Knod, E.M., Jr., ―Operations Management – Customer-Focused Principles, Sixth Edition‖. Times Mirror Education Group, 1997 [7] Tompkins J. A. et al., ―Facilities Planning, Latest Edition‖. J. Wiley, 2003 147 | P a g e