Owner: Owner’s Engineer EPC Designer PROJECT: Red Sea Utility Assets and Infrastructure Project Package: Red Sea Project-PRIMARY POWER NETWORK FOR APPROVAL 00 REV Title: Issue for Ren approval Cheng DESCRI PREPA PTION RED Li Shihai Jia Qi Yang Bo Pan Kaitian CHECKED CHECKED CHECKED CHECKED Zhang 2021-0 Pengyin 5-17 APPROVED DATE METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION DOCUMENT No.:R13-013B01-TJS-MTS-EL-0013 Rev 00 This document is property of EPC Company. Its total or partial reproduction is strictly forbidden by any means, as well as its distribution to third parties without the express written consent. Any copy of this document in digital or paper support will be considered a not control copy. The only valid copy is the last one approved located in the document manager system PROJECT: Red Sea Utility Assets and Infrastructure Project Owner: EPC Contractor Document number: R13-013B01-TJS-MTS-EL-0013 Document Title: METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION Rev: 00 Page 2 / 26 Revision Record Version Date Section Page Description of Modification and basis 00 2021-05-17 All All First submission PROJECT: Owner: Red Sea Utility Assets and Infrastructure Project EPC Contractor Document number: R13-013B01-TJS-MTS-EL-0013 Document Title: METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION Rev: 00 Page 3 / 26 Table of content 1. INTRODUCTION...................................................................................................... 4 2. SCOPE........................................................................................................................ 6 3. DOCUMENT CONTROL.......................................................................................... 6 4. RESPONSIBILITIES................................................................................................. 6 5. OPERATION CONDITION.......................................................................................7 6. REFERENCE..............................................................................................................8 7. WORK PROCEDURE................................................................................................9 8. QUALITY CONTROL.............................................................................................13 9. HSE........................................................................................................................... 16 10. ATTACHMENT..................................................................................................... 17 PROJECT: Red Sea Utility Assets and Infrastructure Project Owner: EPC Contractor Document number: R13-013B01-TJS-MTS-EL-0013 Document Title: METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION Rev: 00 Page 4 / 26 1. INTRODUCTION In order to standardize the construction safety risk assessment and process control, this work instruction is specially prepared to ensure the safety and quality of the whole construction process and serve as the basis for the continuous improvement of the quality, environmental and occupational safety and health management system. The aim of this document is to list the construction phases of 110kV Transformer installation. In order to make the construction process clear and to ensure that the work is performed in line with the project specifications and design drawings. 2. SCOPE The scope of this procedure is applicable to all operations of 110kV Transformer installation for the Red Sea Utility Assets and Infrastructure Project. Specification types and quantities of regional transformers for 110kV substations are as follows: SS-SF1:110(+8×1.25%,-8×1.25%)/33kV, 80/100MVA, ONAF, 3phase, 60Hz, YN,d11, OLTC, Ud=16% (2SET) SS-SF2:110(+8×1.25%,-8×1.25%)/33kV, 128/160MVA, ONAF, 3phase, 60Hz, YN,d11, OLTC, Ud=16% (2SET) SS-1:110(+8×1.25%,-8×1.25%)/33kV, 80/100MVA, ONAF, 3phase, 60Hz, YN,d11, OLTC, Ud=16% (2SET) SS-A:110(+8×1.25%,-8×1.25%)/33kV, 16/20MVA, ONAF, 3phase, 60Hz, YN,d11, OLTC, Ud=16% (2SET) SS-7-10:110(+8×1.25%,-8×1.25%)/33kV, 64/80MVA, ONAF, 3phase, 60Hz, YN,d11, OLTC, Ud=16% (2SET) PROJECT: Red Sea Utility Assets and Infrastructure Project Owner: EPC Contractor Document number: R13-013B01-TJS-MTS-EL-0013 Document Title: METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION Rev: 00 Page 5 / 26 3. DOCUMENT CONTROL This method statement is a controlled document as required by the system procedure Quality Management System Manual and issued in accordance with the procedure Control of Documents and Data. Revisions of this document will be issued when the main text changes or when an appendix is added. All the necessary measures and precautions will be taken so that the above operations comply with the site regulations and procedures as described in the Project Health, Safety and Environmental Manual. The following HSE practices and procedures from the above document will be applicable for this Method Statement. Revised appendices for substitution will be issued separately and where appropriate will include a separate schedule of contents. 4. RESPONSIBILITIES 4.1 Site Engineer Distribute the responsibilities to construction team. With the safety engineer to make sure that works are carried out in safe environment. Monitoring the work progress according to work plan and send report to his superiors. Ensures that the safety requirements are observed by his subordinates and testing equipment and tools are in safe condition. Ensures that work proceeds in accordance with the Site Quality Management plan. According to the technical specification, design drawings and the electrical conditions, compile construction scheme in advance and organize construction; supervise and guide the whole process. 4.2 Electrical testing Engineer Ensuring all testing & commissioning activities are undertaken as per approved procedures and also ensure that all necessary resources are available to meet the schedule. Supervise and guide in the whole process; Submission and archiving files after the construction is completed. Coordination with safety engineers to ensure that all activities are carried out in a safe working atmosphere. Coordination with the QA/QC engineer to carry out related inspection. 4.3 Supervisor Tool box meetings will be given prior to commencing the work. PROJECT: Red Sea Utility Assets and Infrastructure Project Owner: EPC Contractor Document number: R13-013B01-TJS-MTS-EL-0013 Document Title: METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION Rev: 00 Page 6 / 26 Incorporate all QA/QC and safety requirements as requested by the concerned engineer. Organizing tools and equipment required at work site. Meeting with any type of unforeseen incident or requirements and reporting the same to site engineer. 4.4 QA/QC Engineer Assurance of approval method are being used and conformance of the specification. The primary focal point for all project QA/QC matters. The review of project ITP is conforming to the corporate requirements, previous audit results and the nonconformance reports. Carry out surveillance detailed on project ITPs as nominated by the project team. Site inspections and surveillance is in accordance with relevant standard and assurance of quality of work as per project specification. 4.5 HSE Engineer Ensure that work permits are obtained before starting any work. Check and confirm compliance to safety requirements, such as wearing Personal Protective Equipment (PPE). Check work area for any unsafe conditions. Liaise with the Field Supervisors ensuring that work is carried out in accordance with Project Safety Plan / Procedure. 5. OPERATION CONDITION 5.1 Construction Personnel Site Engineer Electrical testing Engineer Supervisor QA/QC Engineer HSE Engineer Crane driver Lifting Supervisor Certified and experienced Installation Supervisor from Manufacturer Authorised Specialist Electrical Technician Forman PROJECT: Red Sea Utility Assets and Infrastructure Project Owner: EPC Contractor Document number: R13-013B01-TJS-MTS-EL-0013 Document Title: METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION Rev: 00 Page 7 / 26 Labor 5.2 Machinery /Equipment and tools The following necessary construction equipment / instrument, tools shall be used to carry out the 110kV transformer installation work. Crane Trailer Oil filter machine Vacuum pump Drying machine Mobile Elevating Working Platform Sling / hoisting belts Oil tank Calibrated Torque wrench Tool box Scaffolding Safety Harness Safety tools Holding and Centering tool for horizontal bar Gasket/Flange holding clamp Centering Pins for flange Set of spanners Crimping tools, wire dressing tool Dust mask Fire extinguisher Vacuum cleaners & welding machines Special tools list recommended by manufacturer Tools for circuit breaker-Set of free wheeling ratchet with hexagon socket Tools for earthing switch-Set of hand crank with extension rod Anhydrous Ethanol Dishcloth oil pipe Fire fighting sand PROJECT: Red Sea Utility Assets and Infrastructure Project Owner: EPC Contractor Document number: R13-013B01-TJS-MTS-EL-0013 Document Title: METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION Rev: 00 Page 6. REFERENCE Issued for Design Drawings. Approved Shop Drawings. Project Quality Plan. ITPs, Inspection Requests and Checklists. Project HSE Plan. Risk Matrix Technical Specification IEC 60076: Power Transformers IEC 60137: Insulated Bushings for Alternating Voltages above 1000V IEC 60076-7: Loading Guide for Oil-Immersed Power Transformers NEMA TR-1: Transformers, Regulators and Reactors IEC 60076-18: Power Transformers Part 18: Measurement of Frequency Response SASO/SSA 422: Power Transformers 54-TMSS-01: Mineral Insulating Oil for Electrical Apparatus 50-TMSS-01: Current Transformer (CT) up to 380kV 53-TMSS-03: Online Gas Analyzer 31-TMSS-06: Terminal Blocks IEEE C57.12.00: General Requirements for Liquid-Immersed Distribution, Power and Regulating Transformers IEEE C57.12.70: Terminal Markings and Connections for Distribution and Power Transformers 8 / 26 PROJECT: Red Sea Utility Assets and Infrastructure Project Owner: EPC Contractor Document number: R13-013B01-TJS-MTS-EL-0013 Document Title: METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION 7. WORK PROCEDURE 7.1 Installation flowchart: Rev: 00 Page 9 / 26 PROJECT: Red Sea Utility Assets and Infrastructure Project Owner: EPC Contractor Document number: R13-013B01-TJS-MTS-EL-0013 Document Title: METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION Rev: 00 Page 10 / 26 7.2 Transformer and accessories inspecting: All the accessories and equipment arrived at the site shall be subjected to receiving inspection prior to installation. Inspect equipment for any damage that may have occurred during shipment or storage. Transformer nitrogen transport, the tank should be positive pressure, the pressure should be 0.01-0.03MPa. Verify that there is no indication of external damage, and no obvious dents or scratches in doors, radiators and fin, or termination compartments. Verify that there is no evidence of insulating liquid leakage on transformer surface, at welding seam, on high or low bushing parts, and at transformer base. Compare transformers and accessories received with the bill of materials to verify that the shipment is complete. Verify that transformers and accessories conform with manufacturer’s shop drawings. If the shipment is not complete or does not comply with project requirements, notify the manufacturer in writing immediately. Open termination compartment doors and inspect components for damage or displaced parts loose or broken connections, cracked or chipped insulators, bent mounting flanges, dirt or foreign material and water or moisture. Test reports and manuals of transformer oil are complete. 7.3 Installation of principal part: Handle transformer carefully, in accordance with manufacturer recommendations to avoid damage to the enclosure, termination compartment, base, frame, tank, and internal component. Avoid subjecting transformers to impact, jolting, jarring, rough handling, etc. Use the manufacturer recommended points for lifting, jacking, and pulling transformers. Use nylon straps of the same length to balance and distribute weight when handling transformers with a crane. Ensure that people are kept a safe distance from transformers while lifting and handling. 7.4 Nitrogen Drain The nitrogen discharge port is installed in the air flow place, and the vacuum is pumped with a vacuum pump. Open the two ventilation holes of the transformer, so that the nitrogen and air convection in the body discharge nitrogen, the body contains up to 18% oxygen can enter the body for inspection. PROJECT: Red Sea Utility Assets and Infrastructure Project Owner: EPC Contractor Document number: R13-013B01-TJS-MTS-EL-0013 Document Title: METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION Rev: 00 Page 11 / 26 The body inspection process to 0.7~3m3/min flow into the transformer into the dry air, to prevent the body damp. 7.5 Treatment of insulation oil Manufacturers of oil should be data complete and have the full analysis report, the scene only to simplify the analysis, it must be full sampling analysis. If the sample is unqualified, filter oil processing must be conducted. Using the vacuum filters oil machine to filter oil, until the sample is qualified. Open the tank of valve at the top, the oil pipeline is connected to the transformer on the bottom of the valve, open the vacuum filter oil machine, will fill the insulation oil into the tank, nitrogen will be discharged from top. Turn off the valve of the fuel tank bottom and top, remove the oil filling pipe. 7.6 Machine Inspection All bolts are tight. Core of transformer without deformation should only point grounding. Winding insulation is complete, no defects. Measure the insulation of the winding resistance. Check each part of transformer principal. Check the valves open and close should be flexible, instruction is correct. 7.7 Installation of Transformer accessories 7.7.1 Sealing Treatment Each flange surface has a steel number, installation according to the steel number. All flange joints shall be sealed with an oil-resistant sealant pad. wipe the sealant pad clean before installation, and the installation position shall be accurate. 7.7.2 Installation of elevatedseat Before installation, check that the outgoing terminal board of the CT is well insulated and conduct CT test. During installation, the nameplate of the current transformer should be positioned to the outside of the oil tank, and the vent plug should be placed at the highest point of the lifting seat. The center of the current transformer and the elevating seat are consistent. 7.7.3 Bushing Installation Prior to start of bushing installation, bushing shall be checked thoroughly for any damage or oil leakage. Oil leakage observed if any, shall be suitably cleaned. PROJECT: Red Sea Utility Assets and Infrastructure Project Owner: EPC Contractor Document number: R13-013B01-TJS-MTS-EL-0013 Document Title: METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION Rev: 00 Page 12 / 26 Lift the bushing to inclined position with reference to the vertical. The angle of inclination shall match the angle of position to which the bushing is to be erected. Care shall be taken to avoid dragging of bushing on the floor, while lifting from its horizontal position to vertical inclined position. After lifting to vertical position, check for the required oil level. Open the blanking plates and take out the winding leads. 7.7.4 Radiator Installation Radiator Panels and flange mating surfaces shall be inspected for shipping damage. Ensure that the valves on tank flanges are in a closed position. Remove blank shipping plates on radiator flanges and inspect for moisture or contamination inside radiator headers. If the radiators are contaminated, flushing will be necessary. Lift the radiator by means of single lifting eye at the top and install the radiators in place. After all radiators are installed, the unit should be re-evacuated and topped off to the cold oil level. The fan installation and wiring connection shall be checked and confirmed as per manufacturer drawings / design drawing. 7.8 Vacuum processing and vacuum fill in oil The vacuum should be carried out on a sunny day. During the first 1 h of the vacuum, when 0.02 Mpa is pumped into the tank, there is no abnormal condition, and the average increase of 0.0067 Mpa to 0.101 Mpa per hour is continued, and the holding time is not less than 24 h. Vacuum oil injections should be carried out on sunny days. The whole process of oil injection should be vacuumed, the oil temperature should be higher than the oil temperature. Fuel injection speed should not exceed 100 L/min. Vacuum injection time >6 h, the gap between the oil injection surface and the top of the tank shall not be less than 200 mm. 7.9 The overall sealing test and resting Transformer static time is 24 hours, no leakage detection. After static, from transformer, lift seat, cooling device, gas relay and pressure release device to discharge the residual gas, adjust the position of oil level to the corresponding ambient temperature. PROJECT: Red Sea Utility Assets and Infrastructure Project Owner: EPC Contractor Document number: R13-013B01-TJS-MTS-EL-0013 Document Title: METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION Rev: 00 Page 13 / 26 8. QUALITY CONTROL 8.1 After the arrival of the cable, carefully check the cables against the technical specification to see if they meet the design requirements. 8.2 In-depth on-site inspections, timely stop illegal operations, strengthen process control, process rectification, and reduce rework afterwards. And ensure the following process in control. 8.3 The Quality Department shall ensure that all Electrical Works are conducted in accordance with the approved Field Quality Plan, Project specifications, drawings and prevailing engineering standards implemented at site. 8.4 Upon completion of construction, electrical engineer in coordination with QC shall submit RFI to owner to perform all required inspections to assure that all requirements are met and approved. 8.5 The Electrical QC Inspector shall carry out Planned Inspections, Surveillance Inspections and release hold points by signing various Quality Records as proof of Inspection conforming to Specifications. 8.6 Any comments found during the inspection should be recorded. 9. HSE 9.1 Construction HSE Risk Control Plan Hazard and Risk assessments of this Method Statement will in the form of Risk assessment attachment. These are reviewed by the HSE department & Construction department to ensure that all hazards have been identified and adequate control measures are in place. 9.2 Personal Protective Equipment (PPE) Safety helmet Safety shoe High visibility jacket Goggles 9.3 Safety precautions Barricade the work area. All safety precautionary signboards must be visibly posted. Ensure that only authorized personnel are within the working area. PROJECT: Red Sea Utility Assets and Infrastructure Project Owner: EPC Contractor Document number: R13-013B01-TJS-MTS-EL-0013 Document Title: METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION Rev: 00 Page 14 / 26 The Supervisor shall initiate daily toolbox meeting to educate his work crew on safety hazards involved in their work and the preventive measures that shall be undertaken. All required equipment / tools shall be checked before the start of work for its suitability and integrity. All safety precautions shall be followed as per approved safety plan & procedure. Ensure all involved people are aware of the same. Safety Officer to ensure that all working flat forms shall be safe and in good condition. Tradesman shall ensure that before leaving their working places, it must be clean, tidy and free from rubbish. Required equipment tools shall be checked before the start of work for suitability and integrity. Any unsafe condition or practice at site during the execution shall be reported. Ensure that proper communication system established for the exchange of instructions and essential supervisors to be provided with the list of emergency numbers. Ensure that site permit box includes permit, risk assessment, method statement and toolbox talk. 9.4 Environmental requirements Dust suppression will be done by water tankers on access roads during movement of heavy vehicle traffic (carting by tippers). Sewage will be collected in septic tanks and disposed off in bowser tanks. Take measures to ensure that the surface of the designated area is not contaminated as a result of hydrocarbon leaks from any machinery or vehicles. 9.5 Waste management Waste produced at site should be collected. Check should be kept so as to ensure that contaminated waste materials are safely disposed of. All wastes must be placed as per the classification and handled centrally, and the flammable waste must be recovered timely. The constructors shall adhere to civilized construction, living up to the following: the person cleans who is in charge of it, cleaning is made the moment it is completed, and the site is cleaned after the project is completed and the materials are used up. 9.6 Training & Competence PROJECT: Red Sea Utility Assets and Infrastructure Project Owner: EPC Contractor Document number: R13-013B01-TJS-MTS-EL-0013 Document Title: METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION Rev: 00 Page 15 / 26 We shall conduct Safety and environmental induction of all staff and workers highlighting the work activities and its safety measures to be followed at site. Equipment operators will have third party competency to operate the equipment. All tools and equipments shall be in safe condition and fit for it purpose. At the start of each shift, equipment shall be visually checked for mechanical and structural soundness. All equipments shall be carefully examined and all hoses and couplings checked for leaks and general conditions. 9.8 Working in the holiday or at night Work with the PTW during the holiday or at night, and incorporate requirements of “ TRS-HS-COS-0015- Extended Hours Night Work and Holiday Work Control ” . Monitor the noise level of project boundary and adjust work task to reduce disturbance on local communities on holidays and night. 9.9 Emergency procedures The on-site construction area shall be led by the safety director of HSE department, an emergency command group shall be set up, a medical duty room shall be set up in the management office area of the construction area, and an emergency concentration point of construction personnel shall be set up in the construction area. In case of the site personnel detecting an emergency situation(medical case, fire, sever weather, flooding, traffic accident, COVID-19 etc.) must inform the site safety officer and Emergency Coordinator. If necessary, Emergency Coordinator informs others to evacuate to nearest assembly point. Emergency Coordinator reports to the Emergency Committee Manager. A roll call shall be taken, and every person is accounted for, awaiting further instructions. Emergency Coordinator will assess the situation and ensure that the necessary steps and arrangements have been made. The medical staff of the infirmary should deal with or rescue the wounded according to the situation. If they need to go to the hospital for rescue, they should call the ambulance team immediately. Inspect the site of the accident and all evidence to be preserved. Full accident investigation to commence immediately after the emergency response and implement an action plan. PROJECT: Red Sea Utility Assets and Infrastructure Project Owner: EPC Contractor Document number: R13-013B01-TJS-MTS-EL-0013 Document Title: METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION 10. ATTACHMENT Appendix A: Risk Assessment Rev: 00 Page 16 / 26 RISK / IMPACT ASSESSMENT CONTROL SHEET Appendix A: Risk Assessment Contract No. Project Title RA Reference RA Date RA Revision No. Task / Activity Red Sea Utility Assets and Infrastructure Project METHOD STATEMENT FOR 110kV TRANSFORMER INSTALLATION 2021.05.17 A0 Engineering SEVERITY RATING: MATRIX Please Note If the severity rating lies between 4 to 25, then corrective actions needs to be taken by concerned persons with documentary evidence provided in conjunction with WI HSE 001B and 001C People/Equipment/Production Health Safety Loss & Environmental Impact Probability (P) Environmental Severity (S) OH&S 1-3 Acceptable Low – L Minor / <3 Days Injury Minor 4-9 Medium – M Moderate / >3 Days Injury Moderate High – H Major / Permanent Disability Injury Major 20-25 Immediate Very High - VH Catastrophic / Fatality Catastrophic Working group Designation Before task commences 10-16 Before task commences Fill in & enclosed herewith WI HSE 001B Note: *Mandatory 1 2 3 4 1 1 2 3 4 5 2 2 4 6 8 10 3 3 6 9 12 15 4 4 8 12 16 20 5 5 10 15 20 25 Unlikely May Happen Likely Very Likely Certain or Imminent and 001C Verified by: Project Manager: Signature:________________Date Approved by: Client Name:_________________Signature:_______________Date: Project Manager Consultant Approval: Signature:________________Date: Safety Officer: Signature:________________Date: Name:_________________Signature:_______________Date: - 5 DISTRIBUTION: Page 1 of 9 Original to: Site HSE File / / / / Copy to: HSE Department RISK / IMPACT ASSESSMENT CONTROL SHEET 110kV TRANSFORMER INSTALLATION Task: Risk Assessment Date Rating (see SN Activity Description Hazard /Aspect Type (R/NR) 1 Transformer Transportation R Hazard is anything with potential to cause harm or loss. Risk is the harm resulting from the hazard. Risk Value enclosed legend page for details) Risk / Impact OH&S E R=SXP OH&S SXP S P S P Existing Controls (OH&S) Existing Controls (Environmental) 2021.05.04 Rating (see enclosed legend page for details) OH&S E SXP Collision with another vehicle or existing facilities Damage structures to 4 3 3 3 12 9 1) Banks-men shall be assigned to vehicles on site 2) All drivers shall use the seatbelt while driving 3) Supervisors shall ensure that all pedestrians’ access to work site, is well controlled 4) Clear traffic signs shall be provided at the work site Collapse and falling of load or material from the truck. Traffic accidents / Personnel Injury / Propert Damage 3 2 3 3 6 9 1) Warning hazard lights and signs will be installed on any extended parts of the equipment or materials to be transported. 2) Traffic Rules and Regulations shall be strictly followed during the transportation process. 3) All Loads shall be secured properly by support ,lashing and locking system. 4) All loose accessories like tools, chains, belts and wood lumbers shall be secured during travelling. 5) While loaded trucks are on stop/standby status, rear tires shall be secured by wooden blocks. 6) All hauling personnel and truck drivers must have a proper PPE while inside the jobsite. Page 2 of 9 1)all vehicles, plant and equipment are kept in good working order and serviced regularly in line with manufacturer’s specifications. Leaking equipment must be repaired immediately or removed from the site. 2)All maintenance of equipment and vehicles shall be performed in the workshop or other suitable designated area. 3)Demarcate an area in which equipment and vehicles may be stored. The location of this area shall be approved by the Environmental Engineer. 4)And take measures to ensure that the surface of the designated area is not contaminated as a result of hydrocarbon leaks from any machinery or vehicles. 5)One -way routes to be maintained in all construction plots. E Risk Value Applicable Sign. Legal & Resp. Other Requirement Person OH&S E S X P SXP S P S P 4 1 3 1 4 3 3 1 3 1 3 3 EPC contract, HSEMP, CESMP RISK / IMPACT ASSESSMENT CONTROL SHEET 110kV TRANSFORMER INSTALLATION Task: SN Activity Description Hazard /Aspect Type (R/NR) 2 Risk Assessment Date Rating (see preparatory work R Risk Value enclosed legend page for details) Risk / Impact OH&S E R=SXP Hazard is anything with potential to cause harm or loss. Risk is the harm resulting from the hazard. S P S P Truck movement losses direction or struck on access road. Traffic accidents / Delays 3 3 1 The site did not install the security chain according to the provisions Personal injury 2 3 1 Construction personnel personal protective equipment wearing error. Personal injury 3 3 2 2 9 4 Inadequate preparation of equipment materials Construction is lagging behind 2 3 1 2 6 2 OH&S SXP E SXP 2 9 2 2 6 2 Existing Controls (OH&S) Existing Controls (Environmental) 2021.05.04 Rating (see enclosed legend page for details) OH&S 1) Traffic controllers shall control vehicle movements during operation. 2) Vehicles shall use main headlight during poor visibility. 3) Work shall be stopped during extreme poor visibility conditions 4) All vehicles shall be fitted with reverse alarms. 1) Install special person to hang plastic chain before starting work. 2) Full supervision, non-staff is prohibited. 3) Plastic chain hanging warning signs. 1) Specialized personnel will be arranged to inspect the construction entrance. 2) People who are not properly dressed are not allowed to enter. 1) Before construction, prepare the list of tools. 2) Get all your tools ready a day in advance 3) At the construction site, all the tools of the site personnel are laid out in the fixed area and the quantity is counted. 4) After completion of construction, all tools shall be taken back with the same number of tools as before construction Page 3 of 9 1) All warning chains are in the form of plastic chains. E Risk Value OH&S E S X P SXP S P S P 3 1 1 1 3 2 2 2 1 1 4 1 2 1 1 1 2 1 2 2 1 1 4 1 2) After the work is finished, special personnel will recycle. The construction site shall finish the work and make the site clear. Applicable Sign. Legal & Resp. Other Requirement Person RISK / IMPACT ASSESSMENT CONTROL SHEET 110kV TRANSFORMER INSTALLATION Task: Risk Assessment Date Rating (see SN Activity Description Hazard /Aspect Type (R/NR) 3 Installation of principal part R enclosed legend page for details) Risk / Impact Hazard is anything with potential to cause harm or loss. Risk is the harm resulting from the hazard. Lifting equipment and personnel without audit Electrically powered toolsElectricity Rotating parts Sharp edges Slip, Trip and Fall OH&S E Risk Value R=SXP OH&S SXP Existing Controls (OH&S) Existing Controls (Environmental) 2021.05.04 Rating (see enclosed legend page for details) OH&S E SXP S P S P accidents /Personnel Injury/Property Damage 4 4 3 3 16 9 1) The lifting weight shall be strictly verified before lifting. 2) All the sling and sling have passed the inspection. 3) Lifting equipment must be operated by licensed personnel. 4) In the process of hoisting, sufficient safe distance must be kept between the hoisting equipment and the electrical equipment. Personnel Injury Electrocution Burn injury 3 2 1 1 6 1 1) Ensure periodic inspection and maintenance of power tools by competent electrician.. 2) Ensure competency of person before using a power tool. 3) Ensure provision of appropriate PPEs for the task. 4) Ensure to keep other workers away to avoid accident from hand tools movement. 5) Adequate space ensured between personnel while using hand tools. Avoid using tools standing on slippery, uneven surfaces and over loose objects. Page 4 of 9 1)all vehicles, plant and equipment are kept in good working order and serviced regularly in bunded area in line with manufacturer’s specifications. Leaking equipment must be repaired immediately or removed from the site. 2)All maintenance of equipment and vehicles shall be performed in the workshop or other suitable designated area. 3)Demarcate an area in which equipment and vehicles may be stored. The location of this area shall be approved by the Environmental Engineer. 4)And take measures to ensure that the surface of the designated area is not contaminated as a result of hydrocarbon leaks from any machinery or vehicles. E Risk Value OH&S E S X P SXP S P S P 2 2 2 1 4 2 1 2 3 1 2 3 Applicable Sign. Legal & Resp. Other Requirement Person RISK / IMPACT ASSESSMENT CONTROL SHEET 110kV TRANSFORMER INSTALLATION Task: Risk Assessment Date Rating (see SN Activity Description Hazard /Aspect Type (R/NR) Hazard is anything with potential to cause harm or loss. Manual handling Risk / Impact Risk is the harm resulting from the hazard. Risk Value enclosed legend page for details) OH&S E R=SXP OH&S SXP Existing Controls (OH&S) Existing Controls (Environmental) 2021.05.04 Rating (see enclosed legend page for details) OH&S E SXP S P S P Physical harm Can occur through attempting to lift, pull or push a load outside physical capabilities. 2 2 1 2 4 2 Mechanical handling devices shall be used wherever possible, i.e. crane, rigging equipment, forklifts, pallet trucks or trolleys. sprains, Back pains, Work related upper ,limb disorders 2 2 1 2 4 2 Cuts, and Abrasions Can occur where loads are handled without wearing suitable personal protective equipment. 2 2 1 2 4 2 E Risk Value OH&S E S X P SXP S P S P 2 1 1 1 2 1 Manual handling training shall be implemented for the workforce to ensure that they are aware of the hazards present and the precautions necessary. 2 1 1 1 2 1 1) Wherever possible, load s shall be covered or packed in such a way so as not to harm the carrier. 2) Personnel shall wear suitable personal protection to reduce the possibility of harm. 3) Tow persons lifting shall be utilized whenever possible (taking into account the size and weight of the load to be moved 2 1 1 1 2 1 Page 5 of 9 Maintain daily housekeeping, recyclable/non recyclable waste stored separately. Applicable Sign. Legal & Resp. Other Requirement Person RISK / IMPACT ASSESSMENT CONTROL SHEET 110kV TRANSFORMER INSTALLATION Task: Risk Assessment Date Rating (see SN Activity Description Hazard /Aspect Type (R/NR) 4 Working at height The operation is carried out at a height above 2m (including 2m) of the fall height where it is possible to fall. R enclosed legend page for details) Risk / Impact Hazard is anything with potential to cause harm or loss. Risk is the harm resulting from the hazard. Falling of materials from height Personnel Injury Property damage OH&S E Risk Value R=SXP OH&S SXP S P S P 4 3 4 2 12 Existing Controls (OH&S) Existing Controls (Environmental) Rating (see enclosed legend page for details) OH&S E SXP 8 2021.05.04 1) Safety harness will be worn and attached to a secure anchor point when erection work is being undertaken. 2) Safe means of access onto work platform such as ladders/ scaffolding will be provided and maintained. 3) All materials, tools and equipment shall be kept in safe places at all times while working at heights. All materials and tools to be harnessed during working at height, exclusion zone to be established under and around working area. 4) Authorized personnel shall erect below and around the working area suitable barriers in order to areas. Appropriate warring signs shall be posted and personnel controlled by close supervision. Page 6 of 9 Maintain daily housekeeping, general waste/hazardous waste stored separately. E Risk Value OH&S E S X P SXP S P S P 2 2 2 1 4 2 Applicable Sign. Legal & Resp. Other Requirement Person RISK / IMPACT ASSESSMENT CONTROL SHEET 110kV TRANSFORMER INSTALLATION Task: Risk Assessment Date Rating (see SN Activity Description Hazard /Aspect Type (R/NR) 5 Installation of accessories R Hazard is anything with potential to cause harm or loss. Risk / Impact Risk is the harm resulting from the hazard. Risk Value enclosed legend page for details) OH&S E R=SXP OH&S SXP S P S P Existing Controls (OH&S) Existing Controls (Environmental) 2021.05.04 Rating (see enclosed legend page for details) OH&S E SXP E Risk Value OH&S E S X P SXP S P S P The transformer lead wire bolt is loose. Property Damage 4 3 4 2 12 8 Arrange personnel to check each screw carefully. Maintain daily housekeeping, general waste/hazardous waste stored separately. 2 2 2 1 4 2 Tools were left in the low voltage lead casing. Property Damage 4 4 2 2 16 4 1) Get all your tools ready a day in advance 2) At the construction site, all the tools of the site personnel are laid out in the fixed area and the quantity is counted. 3) After completion of construction, all tools shall be taken back with the same number of tools as before construction Maintain daily housekeeping, general waste/hazardous waste stored separately. 3 2 2 1 6 2 insulated sleeve damage Property Damage 3 3 1 2 9 2 1) Careful work, avoid damage, do not place casing on the ground 2) When hoisting, someone must help to avoid excessive casing swing. Maintain daily housekeeping, general waste/hazardous waste stored separately. 2 2 1 1 4 1 Incorrect installation of gas relay Property Damage 4 3 2 2 12 4 1) The installation must be carried out in the direction of the manufacturer's logo without any wrong installation, and the final inspection should be re-checked Maintain daily housekeeping, general waste/hazardous waste stored separately. 3 2 2 1 6 2 Page 7 of 9 Applicable Sign. Legal & Resp. Other Requirement Person RISK / IMPACT ASSESSMENT CONTROL SHEET 110kV TRANSFORMER INSTALLATION Task: Risk Assessment Date Rating (see SN Activity Description Hazard /Aspect Type (R/NR) 6 Vacuum processing and vacuum fill in oil R Hazard is anything with potential to cause harm or loss. enclosed legend page for details) Risk / Impact Risk is the harm resulting from the hazard. OH&S E Risk Value R=SXP OH&S SXP S P S P Existing Controls (OH&S) Existing Controls (Environmental) 2021.05.04 Rating (see enclosed legend page for details) OH&S E SXP OH&S E S X P SXP S P S P 3 2 2 1 6 2 Impurity wire into the transformer interior Impurity metal mesh wire into the transformer internal pollution winding, cause short circuit, causing equipment damage 5 3 3 2 15 6 Strictly clean the surface of the accessories with anhydrous ethanol, scrub clean, and rinse the components in direct contact with the transformer with qualified oil. Too high or too low vacuum. equipment damage 5 3 3 2 15 6 Vacuum degree is strictly in accordance with the specifications and requirements of manufacturers. 3 2 2 1 6 2 The filling oil level is wrong equipment damage 5 3 3 2 15 6 Oil must be added from the bottom of the transformer 3 2 2 1 6 2 Page 8 of 9 1)Rinsing with plastic bucket at the bottom of the residue, so as not to insulate oil flow to the ground, causing pollution E Risk Value Applicable Sign. Legal & Resp. Other Requirement Person RISK / IMPACT ASSESSMENT CONTROL SHEET 110kV TRANSFORMER INSTALLATION Task: Risk Assessment Date Rating (see SN Activity Description Hazard /Aspect Type (R/NR) 7 Working in Extreme Weather Condition R Hazard is anything with potential to cause harm or loss. Risk / Impact Risk is the harm resulting from the hazard. Risk Value enclosed legend page for details) OH&S E R=SXP OH&S SXP E SXP Existing Controls (OH&S) Rating (see enclosed legend page for details) OH&S S P S P Hot weather Heat Stress 3 3 1 2 9 2 1) Implement the hot weather procedure. 2) Stop all work when temperature levels reach 50 ºC. 3) Provide shelter where workers can find shade and protection form the direst sunrays. 4) Provide periodic water breaks where workers can drink before, during and after work. 5) Establish a work regimen where workers can be rotated, allowing short rest periods to prevent harmful effects due to hear. 6) Supervisors shall monitor their work force by looking for signs of dehydrating, especially in older persons or workers that have health problems. 7) Ensure that each team includes a first aid provider. 8) An ambulance shall be made available at all time. Wind (Dust) Irritation to eyes and lungs 3 3 3 3 9 9 1) All works shall use eye protection. 2) Provide dust masks during windy/ dusty condition. weather Existing Controls (Environmental) 2021.05.04 Mandatory R – routine / NR – non routine Page 9 of 9 1)Dust suppression control measures shall be carried out at regular intervals. 2)Excavation work and backfill work shall be stopped during wind weather. 3)Establish a heat stress point at site with a flagging system E Risk Value OH&S E S X P SXP S P S P 3 1 1 1 3 2 3 1 3 1 3 3 Applicable Sign. Legal & Resp. Other Requirement Person 10