Employer Doc. No. NSRP Complex Project Nghi S Son,, Vietnam Nghi Son Refinery and Petrochemical Limited Liability Company Contractor Doc. No. S-000-139 390-0002V Rev. 0 Employer Contract No.: XXXXX, Contractor JOB Code: 0 0-6495--20 Page 1 of 50 Date: 24/DEC/13 2 Specification for Cold Service Insulation Unit No.: Not Applicable Unit Abbreviation.: Nott Applicable Document Class: Z Issue Purpose Rev Date Page 0 A 24/DEC/13 /DEC/13 28/AUG/13 /13 5, 10, 20, 20 21, 22 All Description For Construction First issue Operation Centre JOB Code: Responsible Company JVD A R D 013 2 C IN E 25-D For Construction Prep'd Chk'd App'd A.A. A.A. Y.I. Y.I. M.S. M.S. Operation Centre Doc. No.: Prepared by A. Alvero Checked by Y. Ishiwata Approved by M. Sakai Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation S S-000-1390-000 0002V Rev. 0 Page 2 of 50 CONTENTS 1 SCOPE ................................................................ ................................................................................................ ................................ ................................................................ ..................................................4 .................................................. 2 REFERENCES ................................................................ ................................................................................................ ................................................................................................ ...................................................................... ......4 3 DESIGN ................................................................ ................................................................................................ ................................................................................................ .................................................6 ................................................. 3.1 General ................................................................ ................................................................................................ ................................................................................................ .................................................6 ................................................. 3.2 Piping Insulation ................................ ................................................................ ................................................................ ................................................................ ................................................................ ..................................7 3.3 Equi Equipment pment Insulation ................................ ................................................................ ................................ ................................................................ .......................................................... ..........................7 4 MATERIALS................................................................ ................................................................................................ ................................................................................................ .......................................................................... ..........8 4.1 General ................................................................ ................................................................................................ ................................................................................................ .................................................8 ................................................. 4.2 Thermal Insulation ................................ ................................................................ ................................................................ ............................................................... ...............................................................9 4.3 Weatherproof Jacket ................................ ................................................................ ................................ ................................................................ ......................................................... .........................11 4.4 Vapour Barrier Mastic, Sealants and Adhesive ................................ ................................................................ ..............................................12 .............................................. 4.5 Ancillaries ................................................................ ................................................................................................ ................................................................................................ ...........................................14 ........................................... 5 APPLICATION ................................................................ ................................................................................................ ................................................................................................ .................................................................... ....14 5.1 General ................................................................ ................................................................................................ ................................................................................................ ...............................................14 ............................................... 5.2 Piping and Cylindrical Equipment 900mm Diameter or Less ....................................................... .......................................................16 5.3 Vertical Vessels and Pipe Greater than 900mm Diameter ............................................................. .............................................................17 5.4 Horizontal Vessels and Pipe Greater than 900mm Diameter ........................................................ ........................................................18 5.5 Acoustic Insulation................................ ................................................................ ................................................................ ............................................................ ............................................................19 5.6 Fire Hazard Protection Insulation ................................................................ ................................................................................................ .................................................................... ....20 5.7 Contraction Joints ................................ ................................................................ ................................................................ ............................................................. .............................................................20 6 TABLES ................................................................ ................................................................................................ ................................................................................................ ..............................................21 .............................................. 6.1 Table 1: Insulation, Classification and General Conditions of Use.............................................. ..............................................21 6.2 Table 2: Insulation Form and Method of Securing ................................ ................................................................ .........................................23 ......................................... 6.3 Table 3: Vapour Barrier, Metal Cover and Method of Securing .................................................... ....................................................25 6.4 Table 4: Insulation Thickness for Prevention of Heat Gain (PU / PIR) ......................................... .........................................27 6.5 Table 5: Insulation Thickness for Prevention of Heat Gain (Cellular Glass) ...............................29 6.6 Table 6: Thickness of Acoustic Insulation ................................ ................................................................ ...................................................... ......................31 7 DOCUMENTATION................................ ................................................................ ................................................................ ............................................................. .............................................................31 8 FIGURES ................................................................ ................................................................................................ ................................................................................................ .............................................33 ............................................. 8.1 Figure 1 : Piping................................ ................................................................ ................................................................ ................................................................ ................................................................ .................................33 8.2 Figure 2 : Removable Covers for Flanged Valves ................................ ................................................................ ..........................................38 .......................................... A R D 013 2 C IN E 25-D NSRP Complex Project Title: Specification for Cold Service Insulation Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 3 of 50 8.3 Figure 3: Details of Insulation Vapour Barrier and Metal Jacket on Vertical Vessels ................42 8.4 Figure 4 : D Details etails of Insulation , Vapour Barrier and Metal Jacket on Horizontal Vessels ........45 8.5 Figure 5: Acoustic Insulation End Cap Fabrication Details .......................................................... ..........................................................48 8.6 Figure 6 : Acoustic Insulation Support , Classes B &C................................................................ ................................................................ .................................49 8.7 Figure 7 : Personnel Protection ................................................................ ................................................................................................ ....................................................................... .......50 A R D 013 2 C IN E 25-D Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation 1 S S-000-1390-000 0002V Rev. 0 Page 4 of 50 SCOPE (1) This specification pecification covers the use of thermal insulation for above ground, external insulation of piping and equipment in cold service between minus 100ºC and plus 31ºC for the purpose of reducing heat gain, process stabilisation and the prevention of condensate accumulation. accumulation (2) The insulation requirements of this specification pecification are suitable for use in both indoor and outdoor service with normal process plant atmospheres. Alternative designs and materials shall be considered if necessary for highly corrosive atmospheres or potential potential leaks and spills of chemicals. (3) This specification does not cover hot service insulation. For hot service insulation requirements refer to Specification for Hot Service and Acoustic Insulation (S-000 000-1390-000 01V). (4) This specification does not cover Vendor designed insulation for Refrigeration packages including cryogenic pumps, compressors and tanks. This specification is intended to cover Purchaser supplied insulation for selected parts of such packages. (5) This specification does not cover Process or Large Product Storage Tanks and Spheres, nor insulated underground piping and equipment. equipment (6) Piping and equipment quipment requiring insulation shall be specified on the following project documents: 1) Engineering Flow Diagrams and Line Lists 2) Piping General Arrangements and Isometrics Iso 3) Instrument Piping Details and Schedules 4) Project specific Vessel and Exchanger Drawings and Insulation Schedules 5) Equipment Suppliers General Arrangement Drawings for equipment items and Purchaser insulated package equipment equipment. 2 REFERENCES (1) Engineering Standards A R D 013 2 C IN E 25-D 1) S S-000-13A0-0 0001V Specification for Painting 2) S S-000-1390-0001V 0001V Specification for Hot Service and Acoustic Insulation 3) S S-000-1244-0002V 0002V Specification for or Equipment Noise Control 4) D D-000-1351-0001V 0001V Standard Drawings for Pressure Vessels Employer Doc. No. NSRP Complex Project Title: Specification for Cold Service Insulation Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 5 of 50 (2) International Standards ASTM A167 ASTM C177 Specification for Stainless and Heat Heat-Resisting Resisting Chromium Chromium-Nickel Nickel Steel Plate, Sheet and Strip. Test Method for Steady-State Steady State Heat Flux Measurements and Thermal Transmission Properties by means of the Guarded Hot--Plate Plate Apparatus ASTM C552 Standard Specification for Cellular Glass Thermal Insulation ASTM C795 Specification for Thermal Insulation for Use in Contact with Austenitic Stainless Steel. ASTM D696 Test Method for Coefficient of Linear Thermal Expansion of Plastics Between –30ºC 30ºC and 30ºC ASTM D1621 Test Method for Compressive Properties of Rigid Cellular Cellular Plastics ASTM D1622 ASTM D1623 Test Method for Apparent Density of Rigid Cellular Plastics Test Method for Tensile and Tensile Adhesion Properties of Rigid Cellular Plastics ASTM D2856 Test Method for Open-Cell Open Cell Contents of Rigid Cellular Plastics by the Air Pycnometer ASTM E84 Test Method for Surface Burning Characteristics of Building Materials ASTM E96 ASTM SC 177 ISO 15665 Test Methods for Water Vapour Transmission of Materials Test Method for Steady-State Steady State Heat Flux Measurements. Acoustic Insulation for Pipes, Valves and Flanges BS 476 Parts 23 23-31 Fire Tests on Building Materials and Structures BS 476 Part 7 Fire Tests on Building Materials and Structures – Method of Test to Determine the Classification of the Surface Spread of Flame of Products. A R D 013 2 C IN E 25-D Employer Doc. No. NSRP Complex Project Title: Specification for Cold Service Insulation BS 1449 Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 6 of 50 Steel plate, sheet and strip. Carbon and carbon carbon-manganese manganese plate, sheet and strip. General specificat specification. BS EN 10025 Hot Rolled Products of NonNon-Alloys Alloys Structural Steels: Technical Delivery Conditions 3 DESIGN 3.1 General (1) In this specification, specification, insulation for reducing heat gain is designed to provide thicknesses that limit the heat gain to 25W/m2 and that result in hot face surface temperatures that minimise the formation of condensation in ambient air temperature of 31ºC.. (2) Personnel protection shall be installed for unlined equipment quipment and piping with exposed surface temperatures of minus 10ºC and below. (3) Items requiring low level vapour relief load and systems required to operate during a fire, shall be subject to fire protection insulation. (4) Equip Equipment,, vessels and piping shall be insulated with the thickness of insulation appropriate to the insulation classification and operating temperature. (5) The insulation classification shall be identified by a type code in accordance with Table 1. (6) The design of the insulation system, including the selection of adhesives, weather coatings, vapour seals and joint sealers shall take into account that piping and equipment quipment may be subject to elevated temperatures during purging, cleaning and flushing operations. (7) Instal Installation lation of approved materials will proceed according to the manufacturers indicated requirements and recommendations. Proposed techniques which do not meet the manufacturers’ requirements will require ‘Prior Approval’. (8) Each line shall be insulated as a sing single le unit. A minimum clearance of 50mm shall be maintained between the outer surface of insulation and any obstruction such as structural steel, electrical conduit, piping or other insulated lines. (9) Instruments and associated piping subject to operating flow and/or temperature conditions approximating those in the piping or equipment quipment to which they are connected, shall be insulated to the same requirements as that piping or equipment in accordance with Table 1. (10) Insulation contraction joints shall be provided for fo all equipment and piping where differential thermal movements exceed 15mm, and shall be positioned under insulation layer support rings, clips and lugs when they are used. Contraction joints shall be constructed as stated in Section 5.7. (11) Insulation for vvessels essels and similar equipment shall be adequately supported by clips and supports lugs, welded around the equipment item and positioned in accordance with Standard Drawings for Pressure Vessels (D-000-1351 (D 1351-0001V). (12) On vertical pipe lines or lines inclined more than 45° 45 from horizontal and where straight runs are in excess of 3m length, a bolted insulation support shall be installed at the bottom and every 3m thereafter. A R D 013 2 C IN E 25-D NSRP Complex Project Title: Specification for Cold Service Insulation Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 7 of 50 (13) The width of support rings shall be such that the inner layer(s) and one half of the outer outer layer of the insulation shall be supported. (14) Pipe supports and hangers shall be either pre-insulated, pre insulated, clamp on type supports or wrapper plate type supports, providing the insulation has sufficient compressive strength to withstand the loading. 3.2 Piping In Insulation (1) Piping systems requiring insulation shall be fully insulated, including all piping fittings and components together with supports, piping and tubing of insulated instruments drains valves and flanged joints. Valves shall be insulated up to and including luding bonnet flanges but not yoke or the packing gland. (2) Insulation shall not be applied to piping and piping components which become cold intermittently (i.e. blow down or pump out systems, drain or filling systems etc) unless required for acoustic attenuation, attenuation, personnel protection or as otherwise specified. Note: If this piping is connected to an insulated cold source, it shall be treated as a projection and insulated in accordance with paragraph 3.2(3). 3.2 (3) All metal protrusions through the insulation shall be insulated in accordance with Table 4 or Table 5. Protruding metal parts include, but are not limited to, pipe trunnion supports, pipe support clips, pipe hangers and uninsulated piping connections such as vents, sample connections and uninsulated instru instrumentation. mentation. 3.3 Equipment Insulation (1) Equipment quipment items requiring insulation shall be fully insulated including all nozzles, manways, bolted flanges, stiffener rings, exchanger channels and bonnet flanges. (2) Insulation shall not be applied to pumps, fans, compresso compressors, rs, blowers or other rotating or reciprocating equipment unless required for acoustic attenuation, personnel protection or specific process requirements. Items shall be evaluated on an individual basis. (3) Vessels and their skirts or saddles shall be thermally thermally isolated from their holding down bolts. Fabric based phenolic laminate blocks shall be used for this purpose. (4) Where equipment is supported on metal saddles, the insulation shall be carried down the saddle to the junction of the saddle and the thermal iso isolation lation material. The vapour barrier shall continue down over the isolation material. (5) Where equipment is supported through the use of attached support lugs resting on unattached structural steel members, the insulation shall be extended not less than four times, times, the insulation thickness in each direction, measured from junction of equipment with insulated support lug. Thickness of insulation over structural steel members shall be one half that specified for body of equipment equipment.. Thickness of insulation over sup support port lugs shall be the same as the body insulation. (6) Equipment support legs shall be insulated with insulation blocks as part of equipment area. Insulation is to extend down legs a distance of four times, insulation thickness, measured from leg/ leg/equipment equipment junction. nction. Thickness shall be as specified for body of equipment. equipment. The body insulation shall be brought up to and butted firmly against the leg flange. Spaces between A R D 013 2 C IN E 25-D NSRP Complex Project Title: Specification for Cold Service Insulation Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 8 of 50 flange and webs of structural members shall be filled with block cemented in place with speci specified fied insulation adhesive. (7) Skirts supporting vertical equipment shall be insulated inside and outside. Insulation shall extend downward from junction of skirt with bottom head for a distance of not less than four times the thickness of insulation, but in no case less than 300mm. Thickness shall be specified for body of equipment equipment.. Insulation shall be secured to inside of skirt with specified insulation adhesive. Insulation inside skirt shall be supported on angle or plate support. (8) All metal such as insulation support rings or stiffeners except vacuum stiffening rings, which are an integral part of the vessel, shall be insulated with two thirds the total of multi-layer multi insulation thickness with thicknesses rounded up to the nearest 10mm. Full thickness insulati insulation on is required for single layer application. (9) For metal projections not provided with insulation for the entire length, vapour weather barrier material shall be continued along the uninsulated metal for a minimum of 150mm to ensure a tight joint. A low operating operating temperature valve bonnet extension through the insulation represents a specialised case of metal projection. A mastic seal shall be provided between the bonnet and the insulation around it, as well as providing a continuance of the vapour barrier alo along ng the metal. (10) Where necessary, the insulation shall be taken over any nameplate without a break. The position of the nameplate shall be marked on the outer covering and where warning notices occur, these shall be copied on the outside of the insulation finish. A duplicate nameplate shall be installed over the outside surface of the insulation system. The method of attachment used shall not puncture the vapour seal. Before insulation work is commenced, a certified copy or rubbing of the nameplate shall be made for retention in the equipment record. (11) The pre pre-insulation insulation of vertical vessels in the horizontal position prior to erection is not permitted. 4 MATERIALS 4.1 General (1) All materials covered by this specification shall be of high quality, good appearance, and shall not have any deleterious action on the surface to be insulated. (2) Insulation materials shall be chemically inert, non sulphurous, water repellent, rot proof, vermin proof, impervious to hot water and steam, non injurious to health and non corrosive to equipment or piping materials, (even if soaked with water at ambient temperatures for extended periods). (3) Pre-formed formed insulating materials shall be manufactured at the manufacturer’s works and transported to the application site in properly constructed pack packaging aging cartons or crates. All insulation materials shall be properly stored at the application site in suitably weatherproofed storage areas. (4) The use of insulation materials containing asbestos in any form is not permitted. (5) Insulation and jacketing material materials s backed with paper or other flammable material is not acceptable. A R D 013 2 C IN E 25-D Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation 4.2 S S-000-1390-000 0002V Rev. 0 Page 9 of 50 Thermal Insulation (1) Insulation material shall be either “Polyisocyanurate” (PIR) or “Cellular Glass” and shall conform to the following requirements: 1) The cellular glass shall be of a glass thermal insulation material composed of numerous hermetically sealed cells. The material shall be made by expanding molten glass to approximately 15 times in volume. The cellular glass shall be totally inorganic and contain no binders. 2) The insulation material material shall be supplied plain faced in manufacturer's standard sizes. Single or multi layer insulation shall be supplied as defined in Table 4 or Table 5. 3) In addition to the above, the Cellular Glass insulation shall have the following physical properties an and d shall be in accordance with ASTM C552 Density 115 kg/m³ Combustibility Non combustible Compressive strength (Avg. at break 7 kg/cm2 point) Hygrocopicity Zero Water Absorption Zero Permeability Zero Capillarity Zero Coefficient of Thermal Expansion 8.5 x 10-6/°C 10 °C Specific Heat 0.84 kJ/kg°C kJ/kg Service Temperature Limits -260 260°C to +430 +430°C Sound Transmission (Avg. at normal 28dB for a 100mm thickness frequency) Thermal Conductivity *Mean Temp ((°C) Average Maximum 'k' (W/m°C) (W/m *Mean temperature is A R D 013 2 C IN E 25-D = -10 10 0.036 0 0.039 +10 0.0378 Cold face temperature + Hot face temperature 2 NSRP Complex Project Title: Specification for Cold Service Insulation Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 10 of 50 4) The Polyisocyanurate shall be CFC CFC-free, free, self-extinguishing self extinguishing type Polyisocyanurate cut from bun stock. 5) The bun stock shall be foamed and cured at the manufacturer’s factory. Only cutting and fabrication from bun stock can be performed at site. 6) The insulation material shall be supplied in manufacturer’s standard sizes. Single or multi layer insulation shall be supplied as defined in Table 4 or Table 5. 7) In addition to the above, the Polyisocyanurate insulation shall have the following physical properties: Density 40kg/m2 min. Closed Cell Content 90% min Water Vapour Permanence at 23°C 23°C & 0.8 g /(m².h ) 50% RH. Flame Spread Less than 25, 25, ASTM E84 Class 1 to BS476 Part 7. BS 476. Pt. 7, Class 1 Coefficient of Linear Thermal Expansion At 23ºC 70X10 70X10-6 6 m/(m.K) max At -165ºC 165ºC and Contraction 50X10-6 50X10 6 m/(m.K) max Compressive strength minimum value of 0.2MPa. min. all directions. Tensile strength minimum value of all 0.3MPa. min. directions. Leachable halide content 60 ppm max. Thermal Conductivity @ 20°C 20 mean temp: Freshly blown foam (within 3 weeks of 0.020 w/mK max. production) Aged at 21ºC for 180 days (sample cut on both sides) A R D 013 2 C IN E 25-D 0.023 w/mK max. NSRP Complex Project Title: Specification for Cold Service Insulation Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 11 of 50 8) Low density mineral fibre slabs or blanket (unfaced) for application at contraction joints, also valves and flange joints as in in-fill fill material shall have the following minimum properties: Density 32-33 32 33 kg/m3 Thermal conductivity (at 25ºC mean 0.035 W/m°C temperature) Free from any shot or course fibres 9) Semi rigid mineral fibre for acoustic attenuation requirements shall meet the following requirements: Density 80 to 100 kg/m3 Alkalinity pH 6-10 6 Combustibility Non combustible Flow resistivity of acoustic mineral fibre (porous layer) 25,000 to 75,000 Ns/m4 Chloride content 20 ppm* Sodium plus Silicate content 50 ppm* * See Fig. 1 ASTM C795 for wicking type insulation over Stainless Steel 4.3 Weatherproof Jacket (1) The selection of Aluminium material in both coil and flat sheeting form for use as the thermal insulation protective metal cover shall take precedent over other metallic coverings with the exception of fire hazard protection, whe where re aluminised steel ASTM A463 steel covering shall be used. (2) Aluminium jacketing shall be flat mill finished commercial grade of alloy ASTM which shall comply with BS 1470 or ASTM B209 under the following material designations: BS 1470 – 3103 – H6 ASTM B209 Alloy 3003 – H14 or H16 (3) The thickness of the jacketing shall be as specified in Table 3. A R D 013 2 C IN E 25-D Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation 4.4 S S-000-1390-000 0002V Rev. 0 Page 12 of 50 Vapour Barrier Mastic, Sealants and Adhesive (1) The outer layer vapour barrier used to seal all piping and equipment insulation against the ingress of moisture shall be fire resistant mastic possessing good flexibility and based on a solution of copolymer of vinyl chloride and vinyl isobutyl ether in blend with high boiling aromatic solvent and cyclohexanone; and pigmented with neutral pigments and aluminium paste. te. Vapour barrier mastic shall be applied to a total nominal dry film thickness of 3mm. (2) The vapour barrier shall have the following properties: Service temperature range -30°C to +80°C +80 Flame spread (dry state) 20 or less per ASTM E84 or BS 476, Part 7, Class 1 Water vapour permeance ASTM E 96, Method E, 0.024 perms (0.016 metric perms) at 51 mils dry (1.3mm) (g/Pa.s.m2 ) Colour Aluminium Solids content 54% by volume (trowel grades) (3) The joint sealant used to seal all insulation joints on pipe work and equipment shall be based on marine oil (blend of fish oils) pigmented with neutral fillers and aluminium paste, dissolved in a small quantity of xylol. The material shall have the follow following ing properties: Coverage 0.3m²/litre at 3.2 mm Film 0.6m²/litre at 1.6 mm Film Solid Content 98% minimum, by volume Drying Time Touch 8 hours through 7 to 14 days Water vapour transmission rate ASTM E 96, Negligible (g/Pa.s.m2 ) Service temperature limits -60°C to +150°C +150 Solvent White spirit or xylol Flammability dry low flame spread (4) The fabrication adhesive used for bonding together pieces of prefabricated cellular glass insulation for fittings, flange covers and valves, also for joint bonding at contraction joints in vertical pipe work shall be a fire resistant one pack pac grey paste of trowelling consistency A R D 013 2 C IN E 25-D Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation S S-000-1390-000 0002V Rev. 0 Page 13 of 50 composed of medium oil length alkyd resin solution in xylol, pigmented with neutral fillers, and having the following following properties: Coverage 1.9 to 2m²/litre Solids content 79% by weight Drying time Bonding 2 to 10 minutes through 24 to 36 hours Service temperature limits -45°C to 150°C 150 Solvent Xylol Flammability BS 476, Pt. 7, Class 1 (5) The metal sealant suitable for gun extrusion at all metal overlays shall be a tough, durable sealant consisting of a metallic and mineral pigment filled copolymer resin solution with the following properties: Solid content 57% by volume Coated surface temperature limits 30°C °C to +180°C Flammability BS 476, Pt. 7, Class 1 Colour Aluminium (6) The heat resistant sealant for use in flashing of protrusions shall be a grey, high solids content flexible compound, based on selected oils and of a soft paste consistency of an approved type, with the following properties: Solid Content 98% by volume Service temperature limit -60°C 60°C to +150°C Water vapour permeance ASTM F-1249, F 1249, 0.6 perm (0.04metric perm tested at 3.2mm(g/Pa.s.m2 ) (7) To reduce abrasion from vibration, expansion and contraction of vessels and piping, an anti--abrasion abrasion compound shall be applied which is non non-flammable flammable and fire resistant to the inner surfaces of cellular glass. (8) Adhesive for securing insulation to metal surfaces surfaces shall be a two part adhesive compound of polyurethane modified bitumen. A R D 013 2 C IN E 25-D NSRP Complex Project Title: Specification for Cold Service Insulation 4.5 Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 14 of 50 Ancillaries (1) Adhesive tape used to secure all inner layers of insulation where applied to pipe work and equipment in two layers, shall be a pressure sensitive glass fibre reinforced tape 19mm wide. (2) Bands and seals for securing pipe work and equipment insulation and jacketing shall be Type 304 stainless steel, soft annealed temper. Bands shall be in handable coils 0.5mm thick ready to be cut as required in width sizes as shown in Table 2 and Table 3. (3) Reinforcing membrane for embedding between coats of the vapour barrier mastic shall be open weave glass cloth No. 10 having 18 x 12 threads per 25mm and with a weave lock finish. (4) Toggle fasteners to secure removable boxes shall be of quick release, spring shackle lock type and shall be sized commensurate with the weight of the box concerned. All fasteners shall be constructed from stainless steel. (5) Rivets required for metal jacket fabrication shall be the expanding Monel 'pop' blind eye type, 9.5mm long x 5mm diameter. (6) The material requirements of normal insulation accessories shall be as follows: 1) ‘S’ and ‘J’ clips – formed from 20mm wide stainless steel banding. 2) Floating rings – shall be 10mm 10mm-dia. dia. carbon steel rod conforming to EN 10025, 235JR, or equivalent national or international specification. 5 APPLICATION 5.1 General (1) Piping and equipment shall have all welding completed and shall be hydrostatically or pneumatically tested prior to application of insulation. Surfaces to be insulated shall be free of all oil, grease, loose scale and foreign matter and shall be dry. (2) The Insulation Applicator shall not perform any welding on pipe or equipment;; he shall however be responsible to carry out checks for sufficient insulation supports. (3) All lines an and equipment scheduled for cold insulation shall be coated where required in accordance with the Specification for Painting (S-000 (S 000-13A0-0001) 0001). (4) Site touch up of the shop coating including preparation and painting at field welds shall be completed prior to commencement commencement of insulation. (5) Insulation for fittings, flanges and valves shall be the same thickness as the insulation of the pipe. (6) Stiffener rings where provided on vacuum equipment and/or piping shall be insulated with the same thickness of insulation as sp specified ecified for that piece of equipment or piping. The rings shall be fully insulated independent of the equipment or piping. Initial layers of insulation shall be applied with all joints tightly butted and staggered relative to each other. (7) Additional layers of insulation, where required, shall be applied in the same manner as the first layer with side and end joints staggered between joints of preceding layers, so that no two joints coincide. A R D 013 2 C IN E 25-D NSRP Complex Project Title: Specification for Cold Service Insulation Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 15 of 50 (8) All joints of single layer or outermost layers of multi-layer multi layer insul insulation, ation, with the exception of contraction joint locations, shall be buttered with specified joint sealer before installation. In multi multi-layer layer constructions, the first layer shall be applied without sealant. The joints shall be tightly drawn together when ins insulation is applied so that only a very thin joint seal remains. (9) Insulation shall be applied with all joints fitted to eliminate voids. Large voids shall not be filled with vapour seal coating, but eliminated by refitting or replacing insulation. (10) Each line shall be insulated as a single unit. Adjacent lines shall not be enclosedwithin a common insulating cover. (11) The face of the insulation in contact with the steel surfaces shall be given a coat of Fosters 30/16 anti anti-abrasive abrasive compound or ‘Prior Approved’ equal equal. (12) Whenever the application of mastic is referred to in this specification, specification, it shall be applied in two coats (with reinforcing fabric as specified) to obtain a total dry thickness as recommended by the manufacturer, but not less than 2.4mm. The mastic shall be applied as a continuous moisture vapour mastic covering. (13) All insulation materials listed in this specification shall be kept dry and shall be applied only to thoroughly dry frost-free frost free surfaces. (14) All insulation material applied in one day shall have at lleast east one coat of the vapour barrier applied the same day. If impractical to apply the first coat of the vapour barrier, exposed insulation shall be temporarily protected with a moisture barrier, such as an appropriate polyethylene film, and sealed to the p pipe ipe or equipment surface. All exposed ends shall be protected before work stoppage. (15) Vapour stops shall be installed at all directly attached pipe support locations and at locations requiring potential maintenance, such as valves, flanges and instrumentation instrumentation connections to piping or equipment. equipment. If specified that certain valves and flanges are required to be left uninsulated until after plant start up, temporary vapour stops shall be installed. (16) No holes, thin spots or open joints in the vapour barrier shall be allowed. The vapour barrier shall be installed in such a manner than no area of the insulation is exposed to the atmosphere. (17) Metal jacketing fabrication or installation shall not result in the mastic vapour barrier being punctured. (18) Wire shall not be used to secure the insulating system. During construction, glass fibre filament tape shall be used to secure the inner layer(s) of the insulation and stainless steel bands for the outer layer. The sheet metal jacketing shall be secured with stainless steel band bands. s. The type and method of securing insulation and jacketing is summarised in Table 2 and Table 3. (19) Insulation for vessel manways, exchanger channels and bonnet flanges shall be equal in thickness and type to that applied to the main equipment equipment.. The insulation insulation shall be applied similar to the equipment with all voids kept to a minimum and packed with glass fibre insulation where unavoidable. All joints shall be tightly fitted together and staggered where possible. (20) Cellular Glass and PIR blocks shall be applied using a bedding compound to avoid voids in the inner layer that could contract water. Such bedding compound shall be approved by Employer and meet the material manufacturers installation requirements A R D 013 2 C IN E 25-D NSRP Complex Project Title: Specification for Cold Service Insulation 5.2 Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 16 of 50 Piping and Cylindrical Equipment 900mm Diameter or Less (1) Insulation to the specified thickness shall be applied by the use of pre-formed pre formed two (2) half pipe sections wherever possible. For diameters where half sections are not available, multi segments or radiused and bevelled lags shall be used. (2) Insulation shall be applied starting with a full-length full length piece and a half-length half length piece so as to stagger the circumferential joints. When more than one layer is employed, the joints in the second layer shall not match the joints of the previous layer. (3) When applying Cellular Glass, the bore of the inner layer shall be coated with a thin application (to fill surface cells only) of anti abrasion compound and allowed to dry before application of insulation to the surface. (4) All joints of single or outermost layers of insulation, w with ith the exception of contraction joints, shall be buttered with the specified joint sealer before installation and then firmly butted together. (5) Inner insulation layers applied in two half sections, shall be secured with 19mm wide pressure sensitive filament filament tape bands spaced at 220mm maximum centres applied with a 50% overlap. Single or outer layers and where inner layers are applied in radiused and bevelled segments, securing shall be by 12mm wide x 0.5mm thick stainless steel bands at 220mm maximum centres, centres, machine tensioned and sealed. (6) Insulation on bent pipe shall be neatly cut and mitred to suit the contour of the bend. All the external surfaces of the insulation shall be rasped smooth to facilitate the vapour barrier. (7) Insulation of flanges, flanged fit fittings tings and valves shall consist of prefabricated fitting covers of the same material and thickness and applied in the same manner as specified for pipe insulation. The insulation shall stop short of studs and/or nuts to permit easy removal without damage to the insulation. Voids created by stopping short at studs and/or nuts shall be packed with glass fibre in-fill in fill material. Securing bands shall be so located that maximum strength and security is obtained. (8) The installed insulation shall be vapour sealed with a vapour barrier as follows: 1) A thin coat of mastic shall be sprayed or towelled on to a minimum thickness. 2) While the mastic is still tacky, an open weave reinforcing fabric shall be laid smoothly and thoroughly embedded in the coating. Care shall be exerc exercised ised that the weave does not rupture and, the fabric shall be overlapped a minimum of 80mm at joints to provide strength equal to that maintained elsewhere. 3) Before the first coat becomes dry to the touch a second coat of mastic shall be sprayed or towelled over the reinforcing fabric with a smooth unbroken surface and allowed to dry. 4) The total thickness of barrier material shall be 3mm (nominal). (9) Insulation on cylindrical straight sections of piping shall be covered with an additional protective sheet metal jacketing to the requirements of Table 3 rolled to conform to the pipe diameter and applied in 1.0 metre lengths. The jacketing shall be applied with minimum 50mm overlaps at both longitudinal circumferential overlaps (10) All longitudinal overlaps on horizont horizontal al pipes shall be arranged weatherside down to shed water and shall be located along the lower half at approximately 135º or 225º positions. A R D 013 2 C IN E 25-D NSRP Complex Project Title: Specification for Cold Service Insulation Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 17 of 50 Longitudinal overlaps on vertical pipes shall be arranged away from the prevailing site weather conditions. (11) The met metal al covering shall be secured tightly around the insulated pipe and held in place with stainless steel bands at a maximum of 220mm centres. One band shall be located on each circumferential lap and the distance between laps divided at equal band spacing. (12) Each ch section of metal covering on vertical piping with insulation diameters larger than 250mm shall be supported from the next lower sections with two 'S' clips fabricated from banding material. The 'S' clips shall be of sufficient length to allow the minimum minimum overlap of 50mm. (13) Insulated bends and elbows on piping 80mm (3") NPS and larger, shall be metalled with 'lobster back' segments using 10mm minimum ball swage to assist shaping. The metal segments shall be banded. (14) Insulated bends and elbows on piping smaller smaller than 80mm (3") NPS and where constricted at the throat bend, shall use fabricated 'stove pipe' elbows. (15) Butt weld, socket weld and threaded valves, where insulated, shall be clad and secured as pipe. (16) Removable covers on flange joints, flange valves etc. shall be fitted with snap fasteners for quick and easy removal. 5.3 Vertical Vessels and Pipe Greater than 900mm Diameter (1) Insulation to the specified thickness shall be applied by the use of pre-formed pre formed radiused and bevelled lags for vessel, shells and pipes, and pre-formed formed sets for vessel heads. Insulation shall be bonded to the vessel heads using a suitable bedding compound as recommended by the insulation manufacturer (2) Insulation shall primarily be supported on rings welded to the steel surfaces. Additional support upport and application aid shall be provided by the use of adhesive. (3) Insulation shall be applied starting from the bottom with vertical joints staggered. When more than one layer is employed, the joints in the second layer shall not match the joints of the previous layer. (4) When applying Cellular Glass the base of the inner layer shall be coated with a thin application (to fill cells only) of anti abrasion compound and allowed to dry before application of insulation to the surface. (5) All joints of single or outermost outermost layers of insulation, with the exception of contraction joints, shall be buttered with the specified joint sealer before installation and then firmly butted together. (6) Insulation shall be held against the metal surface with stainless steel bands in accordance accordance with Table 2 at 300mm maximum centres. (7) Heads of vessels shall be insulated with pre-formed pre formed vessel head insulation sets. Where fabrication is necessary the material shall be cleanly cut and shaped to closely follow the contour of the head. The joints joints shall be buttered in accordance with paragraph 5.3.5. The insulation shall be secured to the heads by bands drawn radially from the tan line circumferential body bands attached at 300mm centres, to a centralised floating ring of 10mm A R D 013 2 C IN E 25-D NSRP Complex Project Title: Specification for Cold Service Insulation Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 18 of 50 diameter bar. The bands shall be tensioned in suitable sequence to ensure a positive securing of the insulation material. Adhesive shall be used for initial support on bottom heads. (8) An additional layer of insulation shall be applied over the outside layer where insulation supports upports are located. (9) The installed insulation shall be vapour sealed in accordance with paragraph 5.2.8. (10) Insulation shall be covered with an additional protective sheet metal jacketing employing flat sheeting to the requirements of Table 3. (11) The panels shal shalll be applied commencing at the bottom of the vessel. Each circumferential ring of panels shall be tensioned by means of temporary tensioning bands until the final joint is made. 'S' clips shall be used as additional sheeting supports at circumferential overlaps. overlaps. (12) The panels shall have a minimum overlap of 80mm on both horizontal and vertical edges. The overlaps shall be arranged to shed water at all times. (13) The panels shall be held tight to the vessel by means of circumferential bands and seals. The bands sha shallll be positioned on all horizontal overlaps and at 450mm max. centres. (14) Over vessel heads the metal sheet shall be fabricated in an orange peel construction with all radial seams overlapping a minimum of 25mm. Radius direction joints shall be double lap seam m joints and circumferential direction joints shall be folded seam joints to ensure the sheeting does not become loose. (15) All equipment projections shall have the jacketing sealed using metal flashing cut to fit the projections. (16) Insulation and vapour barrier on the bottom head of a vessel protected by a closed skirt shall not require weather protection. 5.4 Horizontal Vessels and Pipe Greater than 900mm Diameter (1) Insulation to the specified thickness shall be pre-formed pre formed radiused and bevelled lags for vessels shel shells ls and pipes, and pre pre-formed formed insulation sets for vessel heads. (2) Insulation shall be applied starting with full length and half half-lengths lengths lags, with all circumferential joints being staggered. When more than one layer is employed, the joints in the second laye layerr shall not match the joints in the previous layer. (3) When applying Cellular Glass, the base of the inner layer shall be coated with a thin application (to fill cells only) of anti abrasion compound and allowed to dry before application of insulation to the surface. (4) All joints of single or outermost layers of insulation, with the exception of contraction joints, shall be buttered with the specific joint sealer before installation and then firmly butted together. (5) The applied insulation shall be secured in place place with circumferential stainless steel bands in accordance with Table 2 spaced at 220mm maximum centres. (6) Heads of vessels shall be insulated with pre-formed pre formed vessel head insulation sets. Where fabrication is necessary the material shall be cleanly cut and sshaped haped to closely follow the contour of the head. The joints shall be buttered in accordance with paragraph 5.4.4. The insulation shall be secured to the heads by bands drawn radially from the tan line A R D 013 2 C IN E 25-D NSRP Complex Project Title: Specification for Cold Service Insulation Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 19 of 50 circumferential body bands to a centralised floating ring ring of 10mm diameter bar. The radial bands shall be fastened to the body bands at 300mm centres and when attached to the floating ring shall be tensioned in suitable sequence to ensure a positive securing of the insulation material. (7) The installed insulation shall be vapour sealed in accordance with specified requirements (para 6.2.8). (8) Horizontal cylindrical equipment shall be finished with flat metal jacket arranged in circumferential bands with the longer dimension edge applied around the circumference of the equipment insulation. (9) The panels shall have a minimum of 80mm overlap on both longitudinal and circumferential edges, both overlaps being finished with a 4mm minimum ball swage and rendered water tight with a 4mm bead of metal seam sealer located in the ball swage. (10) The jacketing shall be held tight to the vessel by means of circumferential bands and seals. The band sizes and spacing shall be 20mm wide x 0.5mm thick bands on all circumferential laps and at 300mm maximum centres. (11) For vessel heads the metal sheet shall be fabricated in an 'orange peel’ construction with all radial seams overlapping a minimum of 25mm. Radius direction joints shall be double lap seam joints and circumferential direction joints shall be folded seam joints to ensure the sheeting does not become loose. (12) All equipment projections shall have the jacketing sealed using metal flashing cut to fit the projections. (13) Where applicable, exchangers shall be insulated, vapour sealed and clad as horizontal vessels, with the exception that the ch channel annel cover and/or bonnet covers shall have removable cladding in accordance with paragraph 5.1.20. 5.5 Acoustic Insulation (1) Where cold insulation and acoustic insulation are required, the cold insulation system shall be applied first to the pipe and the acous acoustic tic insulation shall be applied on top. To prevent condensation at the interface between the two layers, a second vapour seal shall be applied outside the porous layer of the acoustic insulation. (2) The thickness of acoustic insulation material shall be as st stated ated in Table 6. (3) The acoustic insulation material shall be applied in single or double layers as stated in Table 6. When applied in double layer the joints in individual layers shall be staggered. Fixing shall be by 12mm wide stainless steel bands at 220mm maximum centres. The entire surface of the acoustic insulation shall be sealed with reinforced vapour barrier mastic in accordance with paragraph 5.2.8. (4) The specified metallic cover finish shall be applied over the cold insulation and vapour barrier in the e manner described in Sections 5.2, 5.3 and 5.4. (5) Care shall be taken to ensure that there is absolutely no direct contact between the piping and equipment from which the noise is emitted, and the insulation metallic finish. (6) Gaps between the outer metallic cover and protruding metal part shall be sealed with a flexible, non setting, impervious seal, of material suitable for operating temperatures. A R D 013 2 C IN E 25-D NSRP Complex Project Title: Specification for Cold Service Insulation Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 20 of 50 (7) Rigid pipe supports shall be insulated down to the concrete or steel base where acoustic insulation is required for Class B & C. (8) Additional insulation shall be installed over steel support structures where vibration isolations have been omitted. (9) Where acoustic insulation of machinery is required, it shall meet the requirements of this specification specification.. The design shall be subject to review prior to commencement of insulation. 5.6 Fire Hazard Protection Insulation (1) Where fire hazard protection insulation is required Cellular Glass shall be applied. The general insulation application procedures shall be followed as described for piping and equipment under Sections 6.2, 5.3 and 5.4 inclusive except that the insulation shall be applied in a minimum of two layers. (2) The inner layer shall be coated with adhesive and allowed to dry prior to the application of the second layer. (3) The me metallic tallic insulation finish over insulation used for fire hazard protection shall be aluminised steel A463 in accordance with Table 3. 5.7 Contraction Joints (1) Contraction joints shall be positioned in sufficient number and at such distance to allow the contraction raction of piping and equipment to take place without disturbance or damage occurring within the insulating system. Contraction joints shall be determined based on the expected movement. Joints on horizontal piping and equipment shall be installed at 6m max. max. centres and a minimum of one mid way between fixed points. (2) On vertical piping and equipment contraction joints shall be provided directly below insulation support rings where practical. The same method described for non vertical piping shall be employed employed,, with the added provision that the side of the contraction joint cover adhered to the outer layer of insulation shall be above the contraction joint. (3) Contraction joints on non vertical piping shall be provided using a 25mm wide break in the insulation. Co Contraction ntraction joints in multi layers of insulation shall be positioned approximately 200mm apart. A layer of insulation sealer shall be applied to the mating surfaces between layers in the area between contraction joints. All joints are to be packed with mineral mineral fibre in-fill fill material compressed to 50% of its thickness. Single or outer layer insulation contraction joints shall be covered with a 150mm by 25mm thick collar of insulation centred over the joint. One side of this cover layer of insulation shall be fixed fixed using insulation adhesive. The other side is to be liberally coated with insulation sealer on the inner surface which mates to the outer layer of insulation. A heavy fillet of insulation sealer shall be applied to the butt end of the sealed side. Bands Bands shall be used at each end of the contraction joint cover for security. The mastic vapour barrier system shall be applied over the contraction joint cover. (4) On vertical piping contraction joints shall be provided directly below insulation support rings where re practical. The same method described above for non non-vertical vertical piping shall be employed, with the added provision that the side of the contraction joint cover adhered to the outer layer of insulation shall be above the contraction joint. A R D 013 2 C IN E 25-D Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation S S-000-1390-000 0002V Rev. 0 Page 21 of 50 (5) Detailed drawings of contraction joint design shall be submitted for review, prior to execution of the work. 6 TABLES 6.1 Table 1: Insulation, Classification and General Conditions of Use Classification Insulation Insulation Insulation Thickness Thickness Symbol Table Selection Reference Service Insulation Material Notes Consideration Without Polyisocyanurate Each defined steam-out out (PIR) section of equipment operating at CC different temps. Prevention of may be insulated heat gain Normal operating (process lines) where normal operating Table 4 or Table temp of process 5 fluid and nominal pipe size temps. are to suit its individual temp. With steam steam-out Cellular Glass For shell and tube exchanger shells and below 31ºC channel use the CC1 lower of the inlet and outlet temps. Personnel protection Over piping and equipment CP provide open Personnel mesh metal protection with guards over Stood off metal - guard CPG - surfaces which would normally be left uninsulated and which may be accessible. See Note A R D 013 2 C IN E 25-D Employer Doc. No. NSRP Complex Project Title: Specification for Cold Service Insulation Classification Insulation Insulation Insulation Thickness Thickness Symbol Table Selection Reference Contractor Doc. No. S S-000-1390-000 0002V Service Rev. 0 Page 22 of 50 Insulation Material Notes Consideration Selected acoustic insulation symbol Acoustic attenuation for A noise control at B various level of C requirement Table 6 Acoustic shall be added to Category any other Attenuation insulation symbol subject to that applies. If calculated no other insertion loss insulation requirements symbols apply, acoustic symbols A, B or C shall be used alone Note 1: Symbology on P& P&IDs IDs shall indicate only the eligibility of the lines for Personnel Protection. The exact extent shall be determined locally at site based on the criteria of exposed surfaces below minus 10ºC and located within 600mm horizontally or 2100mm vertically of a n normal ormal access, walkway, or work area. For personnel protection, pipe and equipment shall be preferably protected by stood off metal guard. Only where this is not feasible, thermal insulation shall be installed. Pipe and equipment designated for personnel pr protection otection shall be fully painted in accordance with the Specification for Painting (S (S-000--13A0-0001) 0001). Basically CPG shall be applied. If CPG is not feasible CP (thermal insulation) shall be applied. A R D 013 2 C IN E 25-D Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation 6.2 Rev. 0 S S-000-1390-000 0002V Page 23 of 50 Table 2: Insulation Form and Method of Securing Item Straight Pipe Nominal Diameter (D) of Insulation Material Method of Securing Item Form Insulation Material Pre-formed Pre pipe 12mm wide stainless steel sections band 150mm ≤ D Multi-piece Multi piece pipe sections D > 150mm or radiused and bevelled lags All sizes reducers Bends and Elbows band Oversized sections and Welded valves and butt-weld weld tees and 12mm wide stainless steel lags as per "straight" pipe cut and shaped to As for "straight pipe" fit All sizes As for "straight pipe" cut As for "straight pipe" and shaped to fit Flanged Valves and All sizes Joints Oversized sections and As for "straight pipe" lags as per "straight pipe" cut and shaped to fit Equipment Heads See Note 900mm > D 900mm ≤ D 750mm ≤ D Equipment Shells 750mm < D ≤ 3600mm D > 3600mm A R D 013 2 C IN E 25-D Flat blocks shaped to fit 20mm wide stainless steel bands Radiused and bevelled 20mm wide stainless steel Head segments in sets bands As for "straight pipe" in 20mm wide stainless steel sets bands Radiused and bevelled 20mm wide stainless steel lags in sets bands Flat blocks shaped to fit 20mm wide stainless steel in sets bands Employer Doc. No. NSRP Complex Project Title: Specification for Cold Service Insulation Item Nominal Diameter (D) of Contractor Doc. No. S S-000-1390-000 0002V Insulation Material Form Item Casings of Pumps, Manholes and All sizes Material Flat blocks cut and Adhesive tape as necessary shaped to fit. to secure. Exchanger Channel and Bonnet Flanges Note 1: Bottom heads enclosed with weather protective support skirt shall not require metal cover finish. Note 2: Adhesive tape used to secure all inner layers of insulation where applied to pipe work and equipment in two layers, shall be a pressure pressure-sensitive sensitive glass fibre reinforced A R D 013 2 C IN E 25-D Page 24 of 50 Method of Securing Insulation Handholes, tape 19mm wide. Rev. 0 Employer Doc. No. NSRP Complex Project Title: Specification for Cold Service Insulation 6.3 Rev. 0 Contractor Doc. No. S S-000-1390-000 0002V Page 25 of 50 Table 3: Vapour Barrier, Metal Cover and Method of Securing Item Nominal Diameter (D) of Item 200mm ≤ D 201mm < D ≤ Straight Pipe 450mm 450mm < D Welded valves and butt-weld weld tees and All sizes reducers Bends and Elbows Flanged Valves and Joints All sizes All sizes Vapour Barrier Two coats of Metal Cover Method of Securing Thickness Cover 0.5mm continuous membrane 0.8mm steel band reinforced vapour barrier mastic As for “straight pipe” As for “straight pipe” As for “straight pipe” 12mm wide stainless 0.9mm As for “straight pipe” As for “straight pipe” As for “straight pipe” As for "straight pipe" As for "straight pipe" As for "straight pipe" Two coats of continuous Equipment Heads membrane See Note 1 0.9mm reinforced vapour 20mm wide stainless steel bands barrier mastic Two coats of continuous Equipment Shells All sizes membrane 0.9mm reinforced vapour 20mm wide stainless steel bands barrier mastic Casings of Pumps, Two coats of Manholes and continuous Handholes, All sizes membrane Exchanger Channel reinforced vapour and Bonnet Flanges barrier mastic A R D 013 2 C IN E 25-D 0.9mm 20mm wide stainless steel bands NSRP Complex Project Title: Specification for Cold Service Insulation Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 26 of 50 Note 1: Bottom heads enclosed with weather protective support skirt shall not require metal cover finish. Note 2: Adhesive tape used to secure all inner layers of insulation where applied to pipe work and equipment in two layers, shall be a pressure-sensitive pressure sensitive glass fibre reinforced tape 19mm wide. Note: 3: Al Alll cladding overlaps both longitudinal and circumferential shall be reinforced with a self adhesive, crease resistant flashing tape covered with heavy duty aluminium foil and a high grade bitumen backing. A R D 013 2 C IN E 25-D Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation 6.4 Rev. 0 Page 27 of 50 S S-000-1390-000 0002V Table 4: Insulation Thickness for Prevention of Heat Heat Gain (PU / PIR) Normal Operating Temperature (°C) and Thickness (mm) Nominal Pipe Size +31 to -10 -11 11 to -20 -21 21 to -30 -31 to -40 -41 to -50 -51 51 to -60 60 -61 61 to -70 -71 to -80 -81 to -90 -91 91 to -100 100 in mm 1 25 40 50 50 60 70 70 80 80 90 90 1½ 40 40 50 60 70 70 80 80 90 90 100 2 50 40 50 60 70 70 80 90 90 100 100 3 80 50 60 70 70 80 90 90 100 110 110 4 100 50 60 70 80 80 90 100 100 110 120 6 150 50 60 70 80 90 100 110 110 120 130 8 200 50 70 80 90 90 100 110 120 130 130 10 250 50 70 80 90 100 110 120 120 130 140 12 300 60 70 80 90 100 110 120 130 130 140 14 350 60 70 80 90 100 110 120 130 140 140 16 400 60 70 80 90 100 110 120 130 140 150 18 450 60 70 80 90 100 110 120 130 140 150 20 500 60 70 80 100 110 120 130 130 140 150 24 600 60 70 80 100 110 120 130 140 150 150 Flat Flat 60 80 90 110 120 130 150 160 170 180 Single Layer Design Basis: Multi layers Maximum Heat gain = 25w/m2 Ambient Temp.: 23.6ºC Wind speed: 3.6 m/sec Emissivity: 0.15 Humidity: 90% Note 1: 80mm is the maximum single layer thickness above 80mm multilayer application is required Note 2: Insulation thickness may have to be rounded up depending on what thicknesses are commercially available A R D 013 2 C IN E 25-D Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation S S-000-1390-000 0002V Double and Triple Layer shall be constructed with layer thickness as follows: A R D 013 2 C IN E 25-D Thk 1st Layer 2nd Layer 3rd layer 90 50 40 100 50 50 110 50 60 120 30 40 50 130 30 50 50 140 40 50 50 150 50 50 50 160 50 60 50 170 50 60 60 180 60 60 60 Rev. 0 Page 28 of 50 Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation 6.5 Rev. 0 S S-000-1390-000 0002V Page 29 of 50 Table 5: Insulation Thickness for Prevention of Heat Gain (Cellular Glass) Normal Operating Temperature (ºC) and Thickness (mm) +31 to -11 11 to -21 21 to -31 to -41 to -51 51 to -61 61 to -71 to -81 to -91 91 to -10 -20 -30 -40 -50 --60 -70 -80 -90 -100 100 Nominal Pipe Size in mm 1 25 40 50 50 60 70 70 80 80 90 90 1½ 40 40 50 60 70 70 80 80 90 90 100 2 50 40 50 60 70 70 80 90 90 100 100 3 80 50 60 70 70 80 90 90 100 110 1 110 4 100 50 60 70 80 80 90 100 100 110 120 6 150 50 60 70 80 90 100 110 110 120 130 8 200 50 70 80 90 90 100 110 120 130 130 10 250 50 70 80 90 100 110 120 120 130 140 12 300 60 70 80 90 100 110 120 130 130 140 14 350 60 70 80 90 100 11 110 120 130 140 140 16 400 60 70 80 90 100 11 110 120 130 140 150 18 450 60 70 80 90 100 11 110 120 130 140 150 20 500 60 70 80 100 110 120 130 130 140 150 24 600 60 70 80 100 110 120 130 140 150 150 Flat Flat 60 80 90 110 120 130 150 160 170 180 Single Layer Design Basis: Multi layers Maximum Heat gain = 25w/m2 Ambient Temp.: 23.6ºC Wind speed: 3.6 m/sec Emissivity: 0.15 Humidity: 90% Note 1: 80mm is the maximum single layer thickness above 80mm multilayer application is Required A R D 013 2 C IN E 25-D Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation S S-000-1390-000 0002V Double and Triple Layer shall be constructed with layer thickness as follows: A R D 013 2 C IN E 25-D Thk 1st Layer 2nd Layer 3rd layer 90 50 40 100 50 50 110 50 60 120 30 40 50 130 30 50 50 140 40 50 50 150 50 50 50 160 50 60 50 170 50 60 60 180 60 60 60 Rev. 0 Page 30 of 50 Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation 6.6 S S-000-1390-000 0002V Rev. 0 Page 31 of 50 Table 6: Thickness of Acoustic Insulation (1) The level of acoustic attenuation is indicated by the class symbol below as required by Table 1. Where acoustic symbol A, B or C is combined with thermal insulation for prevention of heat gain the specified acoustic insulation thickness shall be applied together with the moisture vapour barrier followed by the thermal insulation, thickness and moisture vapour barrier. (2) When the following following acoustic insulation cladding thickness requirements differ from the thermal insulation protection sheeting requirements the greater of the two thicknesses shall be selected. The metal cladding shall be applied last over the composite insulating system. Minimum Thickness of Class Acoustic (Porous) Layer Insulation (mm) Acoustic Insulation Cladding Thickness Cladding Material (mm) A 50 0.70 Aluminized Steel B 100 0.70 Aluminized Steel C 100 (in two 50 mm layers) 1.4 (in two 0.7 mm layers) Aluminized Steel (3) Classes A, B and C correspond to the classification given in S-000 000-1390-0001V 0001V “Specification for Hot Service and Acoustic Insulation” Insulation”. (4) Class C attenuation may be achieved by applying two layers each of 50mm thick porous insulation and 0.70mm thick sound barrier acoustic insulation cladding sequentially. 7 DOCUMENTATION (1) The Insulation Contractor shall ensure that detailed method statements and quality plans are submitted for Purchaser review and agreement, covering all insulation activities and shall include, but not be limited to, the following: Programme of work schedules in sufficient detail to allow inspection planning Safe storage and handling of materials, safe disposal of unwanted materials. Insulation system to be used Written information identifying identifying selected materials and manufacturers. (see note 1) Copies of manufacturer’s current data sheets for all materials Material delivery dates Documented experience list using the selected insulation system and materials (see note 1) Proposed insulation, cladding and fixing expansion details A R D 013 2 C IN E 25-D NSRP Complex Project Title: Specification for Cold Service Insulation Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 32 of 50 Stood off personnel protection guard details. (see note 1) Removable flange and valve cover details for both metal box and flexible types. (see note 1) • QA/QC procedures for the work to be carried out. • Test and Inspection Inspection procedures and plans. (see note 1) • Copy of proposed Inspection/Record Sheets. • Written information regarding temporary protection arrangements in the event of: (a) Outdoor or partial outdoor application (b) Application in the presence of other trades (c) Site te storage Note 1: - This information shall also be submitted by the Insulation Contractor for Purchaser review and agreement prior to contract awardDetails of proposed Tank insulation system. A R D 013 2 C IN E 25-D NSRP Complex Project Title: Specification for Cold Service Insulation 8 FIGURES 8.1 Figure 1 : Piping A R D 013 2 C IN E 25-D Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 33 of 50 Employer Doc. No. NSRP Complex Project Title: Specification for Cold Service Insulation Figure 1 ( Cont.) A R D 013 2 C IN E 25-D Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 34 of 50 Employer Doc. No. NSRP Complex Project Title: Specification for Cold Service Insulation Figure 1 (Cont.) A R D 013 2 C IN E 25-D Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 35 of 50 Employer Doc. No. NSRP Complex Project Title: Specification for Cold Service Insulation Figure 1 ( Cont.) A R D 013 2 C IN E 25-D Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 36 of 50 Employer Doc. No. NSRP Complex Project Title: Specification for Cold Service Insulation Figure 1 ( Cont.) A R D 013 2 C IN E 25-D Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 37 of 50 NSRP Complex Project Title: Specification for Cold Service Insulation 8.2 A R D 013 2 C IN E 25-D Figure 2 : Removable Covers for Flanged Valves Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 38 of 50 Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation S S-000-1390-000 0002V Figure 2 (cont.) A R D 013 2 C IN E 25-D Rev. 0 Page 39 of 50 Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation S S-000-1390-000 0002V Figure 2 (cont.) A R D 013 2 C IN E 25-D Rev. 0 Page 40 of 50 Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation S S-000-1390-000 0002V Figure 2 (cont.) A R D 013 2 C IN E 25-D Rev. 0 Page 41 of 50 NSRP Complex Project Title: Specification for Cold Service Insulation 8.3 A R D 013 2 C IN E 25-D Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 42 of 50 Figure 3: Details of Insulation Vapour Barrier and Metal Jacket on Vertical Vessels Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation S S-000-1390-000 0002V Figure 3 (cont.) A R D 013 2 C IN E 25-D Rev. 0 Page 43 of 50 Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation S S-000-1390-000 0002V Figure 3 (cont.) A R D 013 2 C IN E 25-D Rev. 0 Page 44 of 50 NSRP Complex Project Title: Specification for Cold Service Insulation 8.4 A R D 013 2 C IN E 25-D Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 45 of 50 Figure 4 : Details of Insulation , Vapour Barrier and Metal Jacket on Horizontal Vessels Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation S S-000-1390-000 0002V Figure 4 (cont.) A R D 013 2 C IN E 25-D Rev. 0 Page 46 of 50 Employer Doc. No. NSRP Complex Project Contractor Doc. No. Title: Specification for Cold Service Insulation S S-000-1390-000 0002V Figure 4 (cont.) A R D 013 2 C IN E 25-D Rev. 0 Page 47 of 50 NSRP Complex Project Title: Specification for Cold Service Insulation 8.5 A R D 013 2 C IN E 25-D Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Figure 5: Acoustic Insulation End Cap Fabrication Details Rev. 0 Page 48 of 50 NSRP Complex Project Title: Specification for Cold Service Insulation 8.6 A R D 013 2 C IN E 25-D Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Figure 6 : Acoustic Insulation Support , Classes B &C Rev. 0 Page 49 of 50 NSRP Complex Project Title: Specification for Cold Service Insulation 8.7 A R D 013 2 C IN E 25-D Figure 7 : Personnel Protection Employer Doc. No. Contractor Doc. No. S S-000-1390-000 0002V Rev. 0 Page 50 of 50