Harar project procurement process & Current Status Committed to Breakthrough! Harar project procurement process & Current Status TECHNICAL VALUATION TEAM Name 1. Obbo Anteneh Demire 2. Obbo Shiferaw kumbi 3. Obbo Derara Emana 4. Obbo Million Andarge 5. Obbo Alemisa Gebisa Position • Manager ,Construction Management[ COOP ] • Senior Civil Engineer[ COOP ] • Senior Civil Engineer[ COOP ] • Associate Civil Engineer [ COOP ] • A/Manager, Procurement Team[ COOP ] Harar project procurement process & Current Status Harar project procurement process & Current Status 1.Introduction This document seeks to describe the procurement process that has so far been completed in order to secure an international Consultant to advise the bank on the construction of its Headquarters building. As a result, procurement processes and summary of evaluation report will be presented in this power slide to demonstrate what has been done so far. 2.Pre-Bid Preparatory work The following activates were conducted prior to the bidding document being floated. Expected building size shall be B+G+M+5 The bidding document preparation for Harar project has been conducted in between January 10, 2022 and February 18, 2022. The bidding document has been presented to Procurement committee on February 25,2022 Following the presentation, the Procurement committee also recommended that the final draft to be distributed once certain critical comments on the draft bidding document has been corrected. After Procurement committee direction, the final bidding document has been duplicated in between March 22, 2022 and March 24, 2022 and made ready for distribution. Harar project procurement process & Current Status 3.Discharging Bid Document During this stage, the bidding document was provided to prospective bidders through invitation, which was advertised in a highly circulated local Reporter Newspaper and the bid floated on the air from March 25th to April 18th, 2022. 4.List of Bidder Who Collected the Bidding Document Following the official announcement from March 25th to April 5th, 2022, exactly sixteen (16) bidders, as listed below, were able to collect the bidding document from the cooperative bank of Oromia procurement office:S/No Bidders Name S/No Bidders Name 1 ASRAT KETEMA G.C 1 ANWAR EBRAHIM G.C 2 HAKICON Engineering PLC 2 MEKASH AMBAW B.C 3 TEKROM Construction PLC 3 MCG Construction PLC 4 MEDCON Engineering and Construction PLC 4 ASAMINEW TESHOME Construction PLC 5 GUTEMA FIRISA Construction PLC 5 YIRGALEM Construction PLC 6 SHANGI FURNITURE PLC 6 BLC Construction 7 DUGDA Construction PLC 7 HEBRON Construction PLC 8 SELALE Engineering PLC 8 KUSHLADDER Construction PLC Harar project procurement process & Current Status 5.Bidder response Following the release of the bidding document, bidders replied appropriately and submitted their documents until April 18th,2022. 6.Bid Opening Ceremony The bid opening ceremony was held on the 7th floor of Rang Real Estate Building at CBO's V.P. (Finance and Facility) office in the presence of procurement committee officers and staff. Both the technical and financial documents were opened at different times, one after the other. In this situation, the technical document was opened on April 19, 2022, and the financial document was opened on June 6, 2022, after the technical document evaluation and recommendation was done. On April 19,2022, during Bid opening only six (6) applicants submitted their bidding document; namely: Hakicon Engineering plc, Yirgalem Construction plc MCG Construction, Gutema Ferisa Construction Hebron Construction Anewar Ibrahim Building Contractor but rejected due to unable to include their power of attorney letter Harar project procurement process & Current Status 7.Formation of Technical evaluation Team To this end, Technical evaluation Team was formed on April 25, 2022 by the procurement committee to handle the evaluation of bidding document. Therefore by the procurement committee the following outlined staffs were assigned to evaluate the bidding document submitted by the bidders. Name 1. Obbo Anteneh Demire 2. Obbo Shiferaw kumbi 3. Obbo Derara Emana 4. Obbo Million Andarge 5. Obbo Alemisa Gebisa Position • Manager ,Construction Management[ COOP ] • Senior Civil Engineer[ COOP ] • Senior Civil Engineer[ COOP ] • Associate Civil Engineer [ COOP ] • A/Manager, Procurement Team[ COOP ] 8.Bid Evaluation Process The process for bid document evaluation started immediately after the bid officially opened and the evaluation was proceed with in House evaluation starting from April 25, 2022 and the corresponding technical evaluation was concluded by May 23,2022. Accordingly , the committee officially notified the evaluation report with technical recommendation. Harar project procurement process & Current Status 8.Feedback on the Evaluation Report Following the Evaluation report ,the Procurement committee was called for discussion on the Technical document evaluation report. In this regard ,the procurement committee was thoroughly discussed on the technical evaluation report and recommendation ,at the end ,the committee with minute number PACA/011/2022 passed decision to further more assess the outlined bidder whose technical document has minor deviation from evaluation criteria set in bidding document and at the same time clarification request were sent to bidder: Hakicon Engineering plc, Yirgalem Construction plc Gutema Ferisa Construction Hebron Construction 9.Field Assessment Between June 1 and June 8, 2022, in accordance with the procurement committee's minute direction, the technical valuation team assessed the bidder’s site and went through all of the bidders' technical experience as well as their office setup. Finally, the technical evaluation team concluded its visit by noting the following points: Harar project procurement process & Current Status All bidders are technically qualified and capable for the project. Their office setting is wellorganized, with various organizational structures. All bidders have demonstrated their ability to complete projects worth more than Birr 100 million on time and to the highest quality. It was recognized that all bidders are qualified enough to execute the project in question 10.Discharge of Final Technical Evaluation Report Following the field assessment and clarification request response ,the technical valuation team once again met and discussed on field assessment and clarification responses made by bidder. And finally on June 8,2022 ,the final Technical evaluation report was discharged with an internal memo. 11.Financial Bid Opening and Financial Evaluation Report The financial proposal opening was conducted on June 6,2022, and written request for evaluation delivered to evaluation team was on June 9, 2022 .following the official memo, the evaluation team thoroughly evaluate the bidder financial proposal and On June 13,2022 with an internal memo notify the financial evaluation findings to Director Supply chain management at the same time on the memo the director requested to notify the bidders on their offer after arithmetic checking. Harar project procurement process & Current Status 12.Claim After Arithmetic checking and Resolution Following the release of the result of arithmetic checking on the bidder financial proposal ,One of the bidder has raise its claim with formal letter on its financial proposal offer after arithmetic checking and also requested the copy of opening of financial proposal to be opened. Hence the procurement committee after thoroughly discussion has accepted the claim and decided to open the financial copy. Hence the financial copy was opened in the presence of all bidder. 13.Procurement committee final Decision Following claim, the procurement committee sat again for final resolution and finally came up with the ongoing bid process to be cancelled and the procurement process to be continued by shortlisting . 14.Current Status