Contents List of figures ........................................................................................................................................... 1 List of tables ............................................................................................................................................ 1 List of symbols......................................................................................................................................... 2 1. Executive summary ......................................................................................................................... 4 2. Background of the report................................................................................................................ 5 3. Introduction .................................................................................................................................... 9 4. Overall Mass balance .................................................................................................................... 12 4.1 Component balance on the overall system ................................................................................ 14 4.1.1 Total suspended solids mass balance .................................................................................. 15 4.1.2 Chemical Oxygen Demand mass balance ............................................................................ 17 4.1.3 5. Ammonia mass balance ................................................................................................ 18 Energy balance on a centrifugal pump ......................................................................................... 20 5.1 Flow diagram............................................................................................................................... 20 5.2 Piping system characteristics ...................................................................................................... 21 5.2.1 Valves and fittings ................................................................................................................ 21 4.2.2Pipe specification .................................................................................................................. 23 5.3 Pumping energy requirements to overcome loses. .................................................................... 24 5.3.1 Materials of construction ..................................................................................................... 26 5.3.2 Head loss due to friction and and pipe fittings .................................................................... 27 5.3.3 Power requirements ............................................................................................................ 28 6. Heat transfer operation ................................................................................................................ 30 a. Introduction .............................................................................................................................. 30 b. Design procedure ...................................................................................................................... 31 c. Design calculation ..................................................................................................................... 31 7. Evaluation of mass transfer operation.......................................................................................... 34 a. Background ............................................................................................................................... 34 Derivation of formula........................................................................................................................ 37 b. Sample calculation .................................................................................................................... 37 8. Conclusion ..................................................................................................................................... 40 9. References .................................................................................................................................... 41 List of Figures Figure 1: Map of Macassar...................................................................................................................... 5 Figure 2: Satellite Photographic Map ..................................................................................................... 6 Figure 3: Fine screen at inlet works ........................................................................................................ 7 Figure 4: Bio-Reactor .............................................................................................................................. 8 Figure 5: Process Flow Diagram ............................................................................................................ 10 Figure 6: Process and Instrumentation Diagram .................................................................................. 11 Figure 7: Pump Station Flow Diagram .................................................................................................. 20 Figure 8: Long Radius Elbow ................................................................................................................. 21 Figure 9: Short Radius Elbow ................................................................................................................ 21 Figure 10: Globe Valve .......................................................................................................................... 22 Figure 11: Gate Valve ............................................................................................................................ 22 Figure 12: Piping System Diagram ........................................................................................................ 24 Figure 13: Friction Factor Chart ............................................................................................................ 26 Figure 14: Pump curves of different speeds ......................................................................................... 29 Figure 15: Shell and tube heat exchanger ............................................................................................ 30 Figure 16: Shell and tube heat exchanger ............................................................................................ 31 Figure 17: Correction factor chart ........................................................................................................ 33 Figure 18: Vacuum Flask ....................................................................................................................... 34 Figure 19: Moisture Analyser ................................................................................................................ 35 Figure 20: Drying Curve......................................................................................................................... 36 List of Tables Table 1: Stream composition ................................................................................................................ 14 Table 2: Miscellaneous loss calculation ................................................................................................ 23 Table 3: Variable speeds of the impeller .............................................................................................. 29 Table 4: Drying Experimental Results ................................................................................................... 36 Table 5: Suspended solids result........................................................................................................... 39 1 List of Symbols V= volume (m3) A= area (m2) L= length (m) ρ = density (kg/m ) 3 µ= viscosity (Pa.s) d= diameter (m) h= height (m) P= pressure (kPa) F= flowrate (m3/hr) Re = Reynolds number (dimension less) f= friction factor (dimension less) P= power (kW) C= concentration (kg/d) k= reaction constant G= generation term G’ = consumption term R= reaction rate (kg/d) m= mass (kg) Rf = relative rougness U = overall heat transfer co-efficient (W/m2 oC Cp = Heat capacity (kJ/kg oC) Qh = Heat load (kW) Q = flow rate (l/s) v = specific velocity (m/s) ML = Mega Litres (l) 2 List of Abbreviations ppm = parts per million BOD = Biological Oxygen demand TSS = Total Suspended Solids MLSS = Mixed liquor suspended solids RAS = Return Activated Sludge 3 1. Executive summary Waste management became essential for the sake of environmental protection and nature conservation, since water is the main substance to transport human waste to natural environmental systems such as rivers and seas, waste water treatment process is used to purify that sewage. Waste water treatment process implements science, technology and engineering to treat and improve quality of the sewage before disposal to the natural environmental systems, to meet government specifications and standards. Untreated waste water is particularly detrimental to a health of living organisms as it contains millions of potentially dangerous pathogenic micro-organisms that can lead to many diseases and unhealthy environment. Waste water treatment works is one of the most important part of any town infrastructural planning as the sewerage from the residential areas is directed by the network of pipelines to a waste water treatment works to be treated and purified. Waste water treatment plant is design such that it will improve the quality of waste water to a standard where it can be re-used in more useful utilities such as, irrigation, process line cooling or as a raw material in some processes etc. good process control and operation determines the success and failure of any waste water treatment plant, there for skills such as mass and energy balance should be put into practice to guarantee the success service of treating water to the higher value of quality. This can also ensure good operation of equipment there for the will be less maintenance and operational cost. Series of experiments needs to be done in the plants daily to enable decision making. 4 2. Background of the report This report was written during the experiential training at City of Cape Town municipality in Macassar waste water treatment works to express and illustrate the knowledge and experience obtained in waste water treatment process during training period. The orientation received at the beginning of training through various divisions of the department of water and sanitation, was to outline the significance and importance of co-operation between different divisions that monitor, supervise and control the purification of waste water that originates from residential areas and industries, throughout the Western Cape. The objective is to meet and exceed government specification and standards regarding the environmental protection towards untreated waste water, as it are detrimental to the environment. Macassar waste water treatment plant was built in 1984. It is located between Macassar and Strand, but aside from the community, it has a sea view and is very close to the Easter river in so much that its final effluent is discharged to the downstream of Easter River that goes straight to the sea. It serves both communities Macassar and Strand, by treating the sewage that originates from these communities. It is a middle size plant of capacity 35ML per day. It uses biological processes to remove biodegradable nutrients from the raw sewage with the aid of micro-organisms in the activated sludge. The plant consists of two biological reactors of volume 24500 m 3 each. Each reactor has six aerators to facilitate aerobic process. The plant has six secondary settling tanks and is design to handle the sludge from both reactors. Plant purpose is to produce final effluent that complies with government specifications and standards’ regarding the disposal of waste water to the environment, this plant achieves this objective by treating the sewage through three stages termed primary, secondary and tertiary treatment processes. Figure 1: Map of Macassar 5 Figure 2: Satellite Photographic Map Primary treatment stage is when the incoming raw sewage has to be pre-treated to remove large debris such as rags, papers, plastics and wood sticks before it enters the process stream. They cannot be degraded by the micro-organisms in the biological process, and this also serves to protect the equipment of the downstream process from being damaged. This is achieved by using fine screens that will only allow sewage to pass through and block any large materials. The screenings are removed by automated grab bar rakes which pick up the materials to a screw conveyer that transport the screening materials to skips. Fine screens are followed by a grit trap chamber that removes inorganic particles like sand and small stones to protect the downstream process equipment from being damaged. Equipment such as pumps and small pipe diameter can easily block out by settled out grit inside piping system. 6 Figure 3: Fine screen at inlet works Secondary treatment is a biological process stage that uses micro-organisms to convert finely divided and dissolved nutrients and organic matters in waste water into flocculent that can easily settle out from suspension. The main objective is to reduce the organic content and nutrients in waste water which is measured as Biological Oxygen Demand (BOD) and Chemical Oxygen Demand (COD) that determines the strength of the raw sewage. An activated sludge is used as the source of supplying active micro-organisms, mainly bacteria and protozoa that can digest nutrient and organic matter which makes up the composition of a raw sewage. Components such as proteins, carbohydrates, fats, ammonia and phosphates, that renders the sewage to be septic and dangerous for disposal to the environment. Activated sludge is the concentrate underflow of suspended solids from the secondary settling tank, which is returned to the biological reactor in order to mix with the raw sewage forming mixed liquor, which gets aerated by surface aerators for an adequate contact of raw sewage with micro-organisms in the activated sludge. Aeration process in a biological reactor simply creates large surface area of contact between mixed liquor and oxygen in the air which is needed by micro-organisms in order to be alive and be capable of decomposing nutrients and organic matter in waste water (aerobic digestion). Aerators also help to direct the flow to exit the reactor as an effluent called mixed liquor suspended solids (MLSS). 7 Anaerobic zones Aerobic zones Flow direction MLSS Aerators Mixed feed Figure 4: Bio-Reactor During protein degradation under anaerobic digestion methane (CH4), ammonia (NH3) and hydrogen sulphide gas (H2S) is produced and depending on the pH NH3 will be in equilibrium with NH4+ in waste water. At pH = 7, 95% of NH3 is found in the form NH4+ hence the effluent pH of waste water must be greater than 8 to reduce NH3 in the solution. High molecular fats and carbohydrates produce biogas anaerobically as follows. CH3COOH CH4 + CO2 ………………………………………… Equation 1 CO2 + 4H2 CH4 ………………………………………… Equation 2 + 2H2O Presence of ammonia in waste water effluent in a form of NH4+ is poisonous to aquatic species at concentrations above 0.2 ppm hence the removal of ammonia is essential in the waste water treatment process before disposal to natural environmental system, the process of nitrogen content removal in waste water is called Nitrification and De-nitrification process. Bacteria responsible for Nitrification process is Nitrosomonas in the presence of oxygen, the reaction is as follows NH4+ + 1.5O5 NO2- + H2O + H+ ……………………………… Equation 3 …………………………………… Equation 4 NO2- is oxidised by nitrobacter to NO3- as follows. NO2- + 0.5O5 NO3- Facultative anaerobic bacteria uses nitrate ( NO3- ) to respire as follows. 8 4NO3- + 5C + 4H+ 5N2 + 5CO2 + 2H2O. ……………………….. Equation 5 Nitrogen which is the main component in the formation of ammonia will be relies in the form of a gas to the atmosphere, this will decrease the concentration of ammonia in waste water. Micro-organisms they continuously re-produce themselves in a process of braking down organic constituent in waste water, which can lead to a sludge bulking that is unacceptable. Sludge wasting is the only solution for prevention of sludge bulking where by a portion of sludge concentrate is removed from the system, de-watered and transported to landfill sites. A portion of underflow concentrate of activated sludge is completely removed from the process after de-watering it in a belt pressing machine. It is initially flocculated with the polyelectrolyte flocculent, for complete gravimetric separation between sludge and clear water, belt press filter is used to recover most of water from the flocculated sludge, dry sludge of total solid 14% is produced from the filtering belt process, all recovered water returns back to the process as a filtrate. Sludge cake from the belt press is wasted to the landfill sites. Chlorine is used as a disinfection agent of the final effluent, this is classified as a tertiary treatment process step. This is for removal of pathogens and some nutrients which were not completely removed from the preceding treatment steps. This effluent goes to four maturation ponds which are wild shallow dams of about 1 meter depth to allow sunlight penetration up to the bottom of the pond and promote aerobic conditions as the oxygen from the atmosphere will be able to dissolve as much because of large surface area of contact between water and the air. The loading on the maturation ponds is calculated on the assumption that 80% of BOD has been removed in the preceding treatment process step. Before water can be discharged from the treatment plant as a final effluent further disinfection process is implemented after maturation ponds, where by chlorine is dosed to reduce the level of bacteria in the effluent. After dosing water is passed through detention period, with reduced flow rate that allows enough time of contact between chlorine dosed and the bacteria that still exist in the water. Maximum permitted level after disinfection is 400 organisms per 100ml of water. 3. Introduction Mass balance is a good practice to be carried out. On-going mass balance in a waste water process it works for good as it is in any other chemical process. It is the basis for process modelling and optimization, as the solids and any other toxic components that entering a process plant and those who are generated in the process are handled by mass balance operation. It enables wise and efficient operation of equipment in the plant to suit operation requirements. This section of the report will cover the mass balance of total suspended solids, chemical oxygen demand, ammonia and chlorine concentration over entire process. This also serves to evaluate the operation of a process, enables decisions to be made in terms of process alterations and plant expansion projects. Determination of the amount of sludge to be wasted from the process per unit time is based on mass balance calculation, as it will track exactly how much sludge is being produced per unit time. 9 Skip bins Landfill Filtrate Screenings Grit and sand Sludge cake Grit chamber Bar screens Raw sewage De-watering Biological reactors MLSS RAS Chlorine Chlorine contact chamber Maturation ponds Clear wate r Secondary settling tanks Final effluent Figure 5: Process Flow Diagram 10 Solid waste to landfil P-4 P-64 E-13 Biological Reactor 1 P-49 Screenings P-65 P-49 P-58 P-5 P-29 Bins P-8 Chlorine Tank P-37 P-28 P-33 P-31 Final Effluent P-30 P-7 V-2 Grit P-9 P-50 P-49 P-32 E-6 E-9 P-36 P-10 P-35 P-11 P-34 P-69 P-38 P-22 E-2 Raw sewage P-48 E-11 E-10 P-51 P-56 Fine screens P-19 P-39 filtrate P-39 Chlorine contact tank P-38 V-1 P-23 P-18 P-24 P-45 P-46 E-8 E-7 P-63 P-26 Sldge cake P-38 E-12 Belt press P-42 Maturation pond 1 P-43 P-44 P-3 P-52 P-12 Maturation pond 2 P-53 Biological Reactor 2 Maturation pond 3 Sludge truck to landfil P-54 P-55 Maturation pond 4 Figure 6: Process and Instrumentation Diagram 11 According to theory the amount of water coming into the plant per unit time for purification must be equal to the amount of the effluent leaving the plant per unit time. Although in practice that is not really taking place due to some losses inside the treatment works that caused by leakages and spilling in parts of the process. Overall mass balance calculation of this report is based on the assumption that the process is at steady state, meaning that there is no accumulation of mass inside the plant. 4. Overall Mass balance F5ρ5 F 2ρ 2 Macassar WWTW F1 ρ 1 F 3ρ 3 F4ρ4 F1 = Raw inflow (m3/d) F2 = Final Effluent (m3/d) F3 = Irrigation water to Strand (m3/d) (Located at Heldarberg) F4 = Irrigation water to Macassar plant (m3/d) F5 = Water that goes with the sludge to hoppers (m3/d) Ρ1 = Raw inflow density (kg/m3) 12 P2 = Final Effluent density (kg/m3) P3 = Density of irrigation water to strand (kg/m3) P4 = Density of irrigation water to macassar (kg/m3) P5 = Density of water in the sludge (kg/m3) change _ of _ mass all _ that _ adds _ to all _ that _ removes _ from of _ the _ systerm the _ mass _ of _ the _ systerm the _ mass _ of _ the _ systerm time time time dM M in M out dt inlets outlets ............................................................... Equation 6 d v 1 F 1 2 F2 3 F3 4 F4 5 F5 dt Simplifying assumption is constant There for 1 2 3 4 5 dv ( F1 F2 F3 F 4 F5 ) dt dV F1 F2 F3 F4 F5 dt dV F1 F1 F3 F4 F5 dt Assume that the volume is constant dV 0 dt F 1 F2 F3 F4 F5 27949 kg/d = 25000 kg/d + 2109.52 kg/d + 314.93 kg/d + 60.5 kg/d 27949 kg/d = 27484.95 kg/d 13 4.1 Component balance on the overall system Component balance is basically the evaluation of raw composition and the final effluent, to actually track the process as some of the components will be consumed, some will be generated during the process, there for there will be a change of composition within the system. The composition of raw and final effluent is tabulated in the table below. Table 1: Stream composition PARAMETER UNITS RAW FLOW (Ml/d) /07/2011 /08/2011 28 30.1 Raw composition Total Suspended Solids mg/l 92 300 Volatile Suspended Solids mg/l 0 0 Settleable Solids mg/l 1 14 COD mg/l 411 617 Ammonia mg N/l 54.6 47.1 Total Phosphorus mg P/l 7.9 9.5 Ortho-Phosphate mg P/l 6.4 5.8 7.7 7.6 pH Chloride mg/l 129 134 Alkalinity mg CaCO3/l 381 403 Total Suspended Solids mg/l 5 7 Total Dissolved Solids mg/l 0 48 COD mg/l 25 22 Ammonia mg N/l 0.9 3.4 Nitrate/Nitrite mg N/l 4.5 7.6 Ortho-Phosphate mg P/l 4 2.7 8 7.8 Final Effluent pH Chloride mg/l 137 125 Alkalinity mg CaCO3/l 126 146 E.coli per 100ml 4 1 14 4.1.1 Total suspended solids mass balance The in-coming raw sewage there is organic and inorganic solid that does not dissolve in water, these solids are entrained by the flow, forming up suspension with water. These solids are termed to be suspended solids since they form part of the fluid. During processing some solids are being generated in a biological reactor, as the micro-organisms degrade the organic components that make up the sewage, they gain more energy and turn to cling together forming un-dissolving solid that adds to the total amount of suspended solids. F5CTSS F2CTSS Macassar WWTW F1 CTSS F3CTSS F4CTSS . CTSS = Concentration of Total Suspended Solids in a stream to which is located (mg/l) 15 change_ in _ TSS all _ that _ adds _ to TSS _ generated all _ that _ removes_ from TSS _ consumed within _ the _ systerm TSS _ of _ the _ systerm within _ the _ systerm the _ TSS _ of _ the _ systerm within _ the _ systerm time time time time time d (CTSSV ) CTSS F GTSS CTSS F GTSS dt inlets outlet ........................... Equation 7 dV 0 dt No total suspended solids are being consumed in the system. V dCTSS CTSS F1 GTSS CTSS F2 CTSS F3 CTSS F4 CTSS F5 dt V dCTSS CTSS F1 GTSS CTSS F2 CTSS F3 CTSS F4 CTSS F5 dt Assume that there are no solids on the final effluent and the irrigation water. V dCTSS CTSS F1 GTSS CTSS F5 dt dCTSS F G F CTSS 1 CTSS 5 TSS dt V V V 2794m 3 60.5 m 3 dCTSS d 7.26 103 kg d GTSS 7392kg 3 d d 28 103 dt V 28 103 m d 2794m 3 60.5 m 3 kC 28 103 m 3 dCTSS d d TSS d 7392kg 7.26 103 kg 3 3 3 d d 3 3 dt 28 10 m 28 10 m 28 103 m d d d dCTSS 7379kg 15.7 kg kCTSS d d dt dCTSS 7363.3 kg kCTSS d dt 16 4.1.2 Chemical Oxygen Demand mass balance 3 Bio-reactor 1 Inlet works Irrigation water pump station SST’s 4 2 5 1 2 3 4 5 = Raw inflow stream = Final Effluent stream = Stream of irrigation water to strand = Stream of irrigation water to Macassar = Sludge stream to de-watering Change_ in _ COD All _ that _ adds _ to COD _ generated All _ that _ removes COD _ removed with _ in _ the _ systerm COD _ of _ the _ systerm in _ the _ systerm COD _ in _ the _ systerm in _ the _ systerm time time time time time dCCODV CCOD Fin GCOD CCOD Fout GCOD dt inlets otlets ............................. equation 8 dCCODV ' CCOD F1 GCOD CCOD F2 CCOD F3 CCOD F4 CCOD F5 GCOD dt C dV 0 dt V dCCOD ' CCOD F1 GCOD CCOD F2 CCOD F3 CCOD F4 CCOD F5 GCOD dt V dCCOD ' CCOD F1 GCOD (CCOD F2 CCOD F3 CCOD F4 CCOD F5 ) GCOD dt No COD produced during reaction there for GCOD is eliminated. 17 V dCCOD ' CCOD F1 (CCOD F2 CCOD F3 CCOD F4 CCOD F5 ) GCOD dt Concentration of COD on stream 2,3,4,5 will be the same since all other streams 3,4,5 are extracted from final effluent stream 2 after disinfection stage. ' F F3 F4 F5 GCOD dCCOD F C COD 1 C COD 2 dt V V V F F3 F4 F5 kCCODV dCCOD F CCOD 1 CCOD 2 dt V V V F F3 F4 F5 kC dCCOD F CCOD 1 CCOD 2 COD dt V V 27949m 3 27485m 3 dCCOD kg kg d d 20104 1232 kCCOD 3 3 d d dt 28 103 m 28 103 m d d dCCOD 20067kg 1209.34 kg kCCOD d d dt dCCOD 18858kg kCCOD d dt dCCOD 18858kg 20104kg k d d dt 4.1.3 Ammonia mass balance Removal of ammonia in a waste water treatment process is of vital importance as it facilitates purification. The process of ammonia removal is termed nitrification and de-nitrification process whereby oxygen is supplied for conversion of ammonia to nitrate, undergoing a three step process. 18 F5CNH4 F2CNH4 Macassar WWTW F1 CNH4 F3CNH4 F4CNH4 CNH4 = Concentration of ammonia in a stream change _ of _ ammonia all _ that _ adds _ to All _ that _ removes_ from in _ the _ systerm ammonia ammonia _ generated ammonia _ of _ the _ systerm ammonia _ consumed time time time time tine dCNH4 V dt dCNH4 V dt C V V C NH4 Fin G NH4 C NH4 Fout G NH4 inlets otlets ............................ Equation 9 ' C NH4 F1 G NH4 C NH4 F2 C NH4 F3 C NH4 F4 C NH4 F5 G NH 4 ' C NH4 F1 G NH4 C NH4 F2 C NH4 F3 C NH4 F4 C NH4 F5 G NH 4 dV 0 dt dCNH4 dt dCNH4 dt ' C NH4 F1 G NH4 (C NH4 F2 C NH4 F3 C NH4 F4 C NH4 F5 ) G NH 4 19 F F3 F4 F5 GNH4 F GNH4 C NH4 1 C NH4 2 V V V V ' dCNH4 dt dC NH 4 2480.8 kg dt dC NH 4 2480.8 kg dt dC NH 4 dt d k C 43.9 kg d 2437.71kg 27484.95 k 'C d 28 103 k C 43.09 kg d d k 'C k C k 'C 5. Energy balance on a centrifugal pump The design of a pump cannot be isolated from the piping system since the energy requirements will be the function of static head due to elevation and pressure differences between suction and discharge, and the dynamic head due to frictional losses on valves, fittings and bends. 5.1 Flow diagram Pump station De-watering unit Pump 1 Bio-reactor Sludge cake Pump 2 Filtrate Figure 7: Pump Station Flow Diagram 20 5.2 Piping system characteristics 5.2.1 Valves and fittings Figure 8: Long Radius Elbow Figure 9: Short Radius Elbow 21 Figure 10: Globe Valve Figure 11: Gate Valve 22 4.2.2Pipe specification Pipe diameter = 200mm Pipe length = 243m Table 2: Miscellaneous loss calculation Equivalent length (m) Quantity Total length (m) long radius bends 4.6 5 23 short radius bends 6 5 30 T-pies from leg 12 3 36 T-pies into leg 18 1 18 fully opened valves 1.5 3 4.5 Half opened valve 40 1 40 sum 151.5 type 23 5.3 Pumping energy requirements to overcome loses. P2= 0 pKa P1 = 0 pKa DE-WATERING h2=5.6m PLANT BIOLOGICAL REACTOR h0=1.8 m Underground height (assumed) Ground level h1=0.3m SLUDGE PUMP STATION TYPE: Centrifugal pump Figure 12: Piping System Diagram 24 Assume fluid velocity to be 1 m/s Cross sectional area of a pipe (A) A r 2 = (3.14)(0.1)2 =0.0314 m2 Reynolds number (Re) Re ud 1000 1 0.2 0.000894 2.23 105 25 Point of intersection Figure 13: Friction Factor Chart 5.3.1 Materials of construction Type: carbon steel pipe Absolute roughness (e) is 0.06 mm (assumed average) Relative roughness is the absolute roughness divided by internal diameter of the pipe Rr = 0.06 mm/200mm = 0.0003 Frictional factor from the chart (f) = 0.004 26 5.3.2 Head loss due to friction and pipe fittings Equivalent pipe length to compensate frictional losses is approximately (151.5m) obtained from pipe diameter (m) multiply by miscellaneous losses (dimension less). The length obtained will be added to actual pipe length in order to calculate a pressure drop. Pipe length = 243 m Equivalent pipe length = 151.5 m Total length used to calculate pressure drop required in a pipe line. Total length = 243 m + 151.5 m = 394.5 m L u Pf 8 f di 2 2 ................................................................. Equation 10 394.5 1000 1 8(0.0065) 2 0.2 2 = 51285 N/m2 Conversion of pressure to heads h P g .................................................................... Equation 11 51285 1000 9.8 = 5.23 m Total head required from the pump is the sum of dynamic and static head Dynamic: (a) velocity head (b) Friction head Static: (a) pressure head (b) Head due to height Dynamic head= 5.23m Static head = 5.3m Total head = 5.3 + 5.23 = 10.53 m 27 Due to high concentration of total suspended solids 10% of the total head has to be added which is (1.05m). This is to compensate slight density and viscosity change that is caused by solids in the sludge. The density of the sludge and viscosity will increase as the concentration of solids increases. Total head after adding 10% of it = 10.53+1.05 = 11.58 m Bernoulli’s equation is used to calculate how much work is required for pumping the sludge in above mentioned piping system. Work required is the function of pressure difference (ΔP) between pump intake and the discharge, as well as pressure loss due to friction (ΔPf) caused by bends, fittings and valves. P gz Pf W 0 ...................................................... Equation 12 (9.8)(-5.3)+0-(51285)/(1000)-W=0 -51.94-51.285-W=0 W = -103.225 J/kg A negative sign implies that work is done by the system (pump). 5.3.3 Power requirements Volumetric flow rate (v) in hourly basis V = 0.0314 m2 × 1m/ s = 0.0314 m3/ s = 31.4 l/s . Mass flow rate (m) . m = 0.0314 m3/s × 1000 kg/m3 = 31.4 kg/s . W m Power ............................................................................ Equation 13 = (103.225)(31.4)/(0.73) =4.4 kW 20% of power required will be added for safety factor Total power to be supplied 5.28 kW 28 The pumps evaluated consist of variable speed drive that drives the pump impeller in different speeds. The speed at which the impeller is running has direct effect in head produced by the pump at the same flow rate, which will also affect the efficiency of the pump as well. The following table shows different speeds that possibly this pump can run on and the head produced. Table 3: Variable speeds of the impeller Q (l/s) 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 VSD 1780 30.5 28.2 26 23.7 21.5 19.5 17.5 15.5 13.3 11.2 9.2 VSD 1460 22.6 20.9 19 17.2 15.5 14 12.2 10.5 8.7 7 5.4 VSD 1180 14.6 13 11.5 10 8.5 7.1 5.8 4.2 2.8 VSD 970 NPSH 10.3 9.2 7.9 6.8 5.8 4.5 3.2 2 operating curve 5.2 5.5 5.8 6.2 6.7 7.2 8 8.8 9.7 10.8 11.8 13.2 14.6 Pump Performance Curve - Macassar pump station 35 30 VSD 1780 25 VSD 1460 20 VSD 1180 15 VSD 970 10 NPSH oparating curve 5 0 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 Figure 14: Pump curves of different speeds 29 6. Heat transfer operation In Macassar Waste Water Treatment Plant there was no units that transfers heat in order to evaluate heat transfer operation, hence I decided to theoretically design a heat exchanger for cooling of a hot fluid to an adequate temperature. a. Introduction The transfer of heat to and from process fluids is an essential part of most chemical processes. The most commonly used type of heat-transfer equipment is the shell and tube heat exchanger, as this conceptual design will be based on it. As its name implies, this type of heat exchanger consists of a shell with a bundle of tubes inside it. One fluid runs through the tubes, and another fluid flows over the tubes to transfer heat between the two fluids. The set of tubes is called a tube bundle, and may be composed by several types of tubes: plain, longitudinally finned, etc. the following diagram is a three dimensional view for illustration of tubes arrangement. Figure 15: Shell and tube heat exchanger The fluid flowing on a shell side is directed by baffles for an adequate time of cooling or warming. See the following diagram for fluid flow paten. 30 Figure 16: Shell and tube heat exchanger b. Design procedure Let us assume that we are designing a shell and tube heat exchanger for cooling a process stream of methanol from temperature of 95 oC to 40 oC using final effluent of Macassar WWTW that is at ambient temperature. The flow rate of methanol is 100,000 kg/h. water temperature raised from 25 o C to 40 oC. Now I need to work out how much area of heat transfer is needed to accomplish the duty in terms of sizing the heat exchanger. Properties of the fluids used in a heat exchanger such as corrosiveness of fluid should be investigated and known for decisions to be made in terms of materials of construction and to decide which fluid must flow inside the tubes or outside. According to the above mentioned problem statement water is more corrosive than methanol, there for water should flow inside the tubes and methanol in a shell side outside the tubes simple because it will less costly to repair corroded tubes after long time operation of an heat exchanger than to repair corroded shell. c. Design calculation Heat capacity methanol (Cp) = 2.84 kJ/kg oC (amount of energy required to increase temperature for 1 oC) Heat load (Qh)= mCpΔT ......................................... Equation 14 100,000 2,84(95 40) 3600 =4340 kW (rate at which heat is transferred) 31 Heat capacity water = 4,2 kJ/kgoC oC (amount of energy required to increase temperature for 1 oC) Cooling water flow 4340 4,2(40 25) = 68.9 kg/s Log mean temperature difference ( ΔTlm) T1 t 2 T2 t1 T t ln 1 2 T2 t1 ΔTlm ........................................... Equation 15 95 40 40 25 95 40 ln 40 25 = 31oC Log mean temperature difference is a function of heat exchanger design, it varies with the number of tube passes and shell passes. Correction factor has to be taken in to consideration in order to obtain correct temperature difference. Correction factor is taken from a chart that resembles the specific design of a heat exchanger in terms of number of tubes that passes and a shell passes. Use one shell pass and two tubes passes R T1 T2 t 2 t1 ................................................. Equation 16 95 40 40 25 = 3,67 P t 2 t1 T1 t1 ............................................... Equation 17 40 25 95 25 = 0.21 32 Point of intersection Figure 17: Correction factor chart Correction factor (Ft) from the chart Ft = 0,85 Tm = Ft x Tlm = 0.85 x 31 = 26 oC Overall heat transfer co-efficient (U) U = 600 W/m2 oC Heat load is also expressed as Qh UATm A Q UTm 4340 103 600 26 .............................................. Equation 18 = 278 m2 33 7. Evaluation of mass transfer operation Filtration and the drying unit were chosen for the evaluation of mass transfer. This is the small scale unit used in the laboratory for sludge concentration analysis. a. Background Sludge of variable concentration which is mixed liquor suspended solids and the return activated sludge were analysed for the determination of their concentration for process optimization in a biological reactor. As the concentration of sludge in a reactor was to be maintained roughly around 3500 mg/l, due to food per micro-organism ratio and optimum performance of a reactor. A sample of sludge that was to be analysed was grabbed directly from the reactor, with muddy appearance that was caused by mass of solids that were suspended in the solution. The main objective of the experiment was to completely separate the solids from known amount of clear water. The solids has to be dried and weighed in order to determine its total mass that was in suspension per unit volume of clear water. The known volume of grabbed sample will be charged in a vacuum filtering funnel to be filtered, using a thin filter paper that allows clear water to pass through but it blocks all other solids from penetrating, this forms a layer of solids packed upon that known mass filter paper. Water will be stored in the flask receiver at the bottom of the filter as a filtrate of known volume. Figure 18: Vacuum Flask 34 Although the cake of solids that are upon a filter paper are still wet since some of the moisture is bound inside the solids structure, hence drying has to take part in order to remove all the moisture that was left inside the solids structure, in order to obtain the mass of bone dry solids. The operation is carried out such that the mass of wet sludge solids is weighed before drying takes place in a unit called moisture analyser. (Citation) has discovered from scientific research that some of the solids in the sludge are more volatile than others . Figure 19: Moisture Analyser The experiment was carried out to determine the total suspended solids both volatile and nonvolatile solids that forms the sludge. The temperature of a drying unit was maintained at 1050C in order to vaporise only water and leave out all the solids dry. Drying time was determined graphically. Since the mass of wet sample was known and the moisture analyser has built-in weighing balance for continuous mass weighing during drying process. Mass data captured during drying process at consecutive intervals when drying at constant temperature, produced a hyperbolic graph. After all the moisture has been removed the graph becomes linear. 35 Table 4: Drying Experimental Results time (s) 0 60 120 180 240 300 360 420 480 mass (g) 0.906 0.7 0.552 0.401 0.332 0.307 0.281 0.279 0.279 1 0,9 0,8 0,7 0,6 Mass (g) 0,5 No moisture present 0,4 0,3 0,2 0,1 0 0 100 200 300 400 500 600 Time (s) Figure 20: Drying Curve The total amount of suspended solids was obtained by the use of empirical formula obtained from the conversions done on the experimental findings. S .S C A 106 B C A D .................................................................... Equation 19 36 A = weight of filter paper (g) B =weight of wet sludge and filter paper (g) C = weight of dried sludge and filter paper (g) D = filtrate volume (ml) S.S = total suspended solids concentration (mg/l) Derivation of formula Since the main objective of the experiment was to determine the amount of solids per unit volume of sample, the total amount of water in the sample was worked out. Total water = (weight of wet sludge +filter paper) – (weight of dried sludge +filter paper) – (weight of filter paper) + (filtrate volume) Total water (ml) = B – C – A + D Conversion of water volume from millilitres to litres was necessary as the concentration of sludge was expressed in terms of (mg/l). Total water (l) = ml÷1000 = litres Total amount of dried sludge (g) = (weight of dried sludge + filter paper) – (weight of a filter paper) =C–A Conversion of weight of dried sludge from grams to milligrams by multiplying with 1000 Amount of dried sludge (mg) = (C-A) × 1000 S .S C A 1000 B C A D 1000 S .S C A 106 B C A D b. Sample calculation From the experiment that was carried out the following data was recorded. a. b. c. d. Filter paper was weighed in a weighing balance and the mass was = 0.211 g 20 ml was filtered in a vacuum funnel and gives a filtrate of 19 ml The amount of wet sludge in a filter paper was weighed = 0.965 g Wet sludge was dried in a moisture analyser, dried sludge mass = 0.287 g 37 Equation 19 was used to calculate the number of total suspended solids from above data. S .S 0.287 0.211 106 0.965 0.287 0.211 19 = 3904 mg/l The sample calculation shown above was for calculation of mixed liquor suspended solids concentration; the same formula can be used for calculation of return activated sludge concentration which is roughly twice as much that of mixed liquor suspended solids under good conditions of process operation. The results obtained will be used to work out the sludge age or wasting rate for a day in the plant using the following formula. 38 Table 5: Suspended solids result MIXED LIQUOR SUSPENDED SOLIDS (MLSS) Filter paper + Wet sample Total mass of dried sludge Filtrate Suspended Solids (A) g 0.212 0.211 (B) g 1.059 0.965 (C) g 0.295 0.287 (D) ml 18 19 (SS) mg/l 4474 3904 0.211 0.213 0.213 0.208 0.205 0.971 0.956 1.042 1.055 0.943 0.281 0.281 0.284 0.278 0.288 18.5 18.5 18.5 17 18 3635 3744 4045 3984 4499 0.208 0.208 0.197 0.209 0.205 1.143 1.146 1.441 0.842 0.885 0.307 0.306 0.32 0.262 0.256 18.5 18.5 18.5 18 18.7 5175 5122 6332 2884 2667 0.205 0.209 0.208 0.21 0.208 0.879 1.03 0.815 0.758 1.055 0.267 0.271 0.275 0.245 0.278 17.5 17 17 18 17 3464 3506 3704 3655 3984 0.206 0.211 0.212 0.209 0.979 0.965 0.998 1.03 0.267 0.287 0.256 0.271 18 19 18 17 3561 3904 4002 3506 Filter paper Date weight 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 39 8. Conclusion From this report I concluded that there is less accurate information and data available about physical and chemical properties of the biological process. In water purification processes for completion of material balance calculations in terms of their reaction kinetics accurate data is required. For process optimization process controllers should be receiving test data from lab technicians inside treatment plant frequently to enable decisions to be made in terms of process operation. The data will be modelled by mass balance equations and also to fore see problems that may take place, to minimize process risk that can lead to failure of the plant or equipment in the plant. The energy balance performed in a centrifugal pump of Macassar sludge pump station showed power requirement of 5.28 kW. Comparing power requirement of the centrifugal pump with the actual installed motor of 5.5 kW, I can come to conclusion that this centrifugal pump still operates under its specification. Determination of suspended solids in the sludge was of vital importance as the sludge age was worked from it. Much deviations were observed in the results because of inaccurate operation of the plant, which was caused by lack of realisation about the importance modelling material balance equations. My in-service training was a good experience to me, I learned to understand how biological process work, problem solving skills and lot more in terms of process operation. It is quite interesting to see different departments co-operate to achieve one objective, which is to improve the quality of waste water discharged to the environment. For the improvement of the quality of training, structural plan should be made such that the students can be rotated in various departments to obtain as much knowledge as they can. 40 References 1. 2. 3. 4. 5. Coulson and Richardson’s (chemical engineering design 5th edition 1963) Robert. L (chemical engineering journal of mass and heat transfer 1992) www.google.co.za/Wikipidia/heat exchanger/valves Core notes of N3 waste water treatment course T.W. Fraser Russell, Anne Skaja Robinson, Norman J. Wagner( Heat Transfer Series 1934) 41
0
You can add this document to your study collection(s)
Sign in Available only to authorized usersYou can add this document to your saved list
Sign in Available only to authorized users(For complaints, use another form )