DEP SPECIFICATION DESIGN OF MULTIPLE-PIPE SLUG CATCHERS DEP 31.40.10.12-Gen. February 2011 DESIGN AND ENGINEERING PRACTICE DEM1 © 2011 Shell Group of companies All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, published or transmitted, in any form or by any means, without the prior written permission of the copyright owner or Shell Global Solutions International BV. DEP 31.40.10.12-Gen. February 2011 Page 2 PREFACE DEP (Design and Engineering Practice) publications reflect the views, at the time of publication, of Shell Global Solutions International B.V. (Shell GSI) and, in some cases, of other Shell Companies. These views are based on the experience acquired during involvement with the design, construction, operation and maintenance of processing units and facilities. Where deemed appropriate DEPs are based on, or reference international, regional, national and industry standards. The objective is to set the recommended standard for good design and engineering practice to be applied by Shell companies in oil and gas production, oil refining, gas handling, gasification, chemical processing, or any other such facility, and thereby to help achieve maximum technical and economic benefit from standardization. The information set forth in these publications is provided to Shell companies for their consideration and decision to implement. This is of particular importance where DEPs may not cover every requirement or diversity of condition at each locality. The system of DEPs is expected to be sufficiently flexible to allow individual Operating Units to adapt the information set forth in DEPs to their own environment and requirements. When Contractors or Manufacturers/Suppliers use DEPs, they shall be solely responsible for such use, including the quality of their work and the attainment of the required design and engineering standards. In particular, for those requirements not specifically covered, the Principal will typically expect them to follow those design and engineering practices that will achieve at least the same level of integrity as reflected in the DEPs. If in doubt, the Contractor or Manufacturer/Supplier shall, without detracting from his own responsibility, consult the Principal. The right to obtain and to use DEPs is restricted, and is typically granted by Shell GSI (and in some cases by other Shell Companies) under a Service Agreement or a License Agreement. This right is granted primarily to Shell companies and other companies receiving technical advice and services from Shell GSI or another Shell Company. Consequently, three categories of users of DEPs can be distinguished: 1) Operating Units having a Service Agreement with Shell GSI or another Shell Company. The use of DEPs by these Operating Units is subject in all respects to the terms and conditions of the relevant Service Agreement. 2) Other parties who are authorised to use DEPs subject to appropriate contractual arrangements (whether as part of a Service Agreement or otherwise). 3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) or 2) which requires that tenders for projects, materials supplied or - generally - work performed on behalf of the said users comply with the relevant standards. Subject to any particular terms and conditions as may be set forth in specific agreements with users, Shell GSI disclaims any liability of whatsoever nature for any damage (including injury or death) suffered by any company or person whomsoever as a result of or in connection with the use, application or implementation of any DEP, combination of DEPs or any part thereof, even if it is wholly or partly caused by negligence on the part of Shell GSI or other Shell Company. The benefit of this disclaimer shall inure in all respects to Shell GSI and/or any Shell Company, or companies affiliated to these companies, that may issue DEPs or advise or require the use of DEPs. Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, DEPs shall not, without the prior written consent of Shell GSI, be disclosed by users to any company or person whomsoever and the DEPs shall be used exclusively for the purpose for which they have been provided to the user. They shall be returned after use, including any copies which shall only be made by users with the express prior written consent of Shell GSI. The copyright of DEPs vests in Shell Group of companies. Users shall arrange for DEPs to be held in safe custody and Shell GSI may at any time require information satisfactory to them in order to ascertain how users implement this requirement. All administrative queries should be directed to the DEP Administrator in Shell GSI. DEP 31.40.10.12-Gen. February 2011 Page 3 TABLE OF CONTENTS 1. 1.1 1.2 1.3 1.4 1.5 1.6 1.7 INTRODUCTION ........................................................................................................4 SCOPE........................................................................................................................4 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS .........4 DEFINITIONS .............................................................................................................4 SYMBOLS AND ABBREVIATIONS............................................................................5 CROSS-REFERENCES .............................................................................................7 SUMMARY OF MAIN CHANGES...............................................................................7 COMMENTS ON THIS DEP .......................................................................................7 2. GENERAL DESIGN ASPECTS..................................................................................8 3. 3.1 3.2 3.3 HYDRAULIC DESIGN ................................................................................................9 GENERAL ...................................................................................................................9 SLUG CATCHER SIZE...............................................................................................9 SLUG CATCHER GEOMETRY AND COMPONENTS ..............................................9 4. 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 4.10 4.11 MECHANICAL DESIGN ...........................................................................................10 GENERAL .................................................................................................................10 MAXIMUM ALLOWABLE OPERATING PRESSURE ..............................................10 DESIGN FACTOR FOR HOOP STRESS.................................................................10 OTHER STRESS ......................................................................................................10 SUPPORTS AND ANCHORS...................................................................................11 MATERIAL SELECTION...........................................................................................11 INTERNAL/EXTERNAL CORROSION PROTECTION ............................................11 OVERPRESSURE PROTECTION ...........................................................................11 MAINTENANCE........................................................................................................12 EMERGENCY DEPRESSURISATION.....................................................................12 MISCELLANEOUS ...................................................................................................13 5. 5.1 5.2 5.3 HAZARD AND RISK MANAGEMENT .....................................................................14 GENERAL .................................................................................................................14 APPLICATION OF FORMAL HEMP BASED STUDIES...........................................14 DESIGN CONSIDERATIONS...................................................................................15 6. REFERENCES .........................................................................................................18 APPENDICES APPENDIX A Figures .............................................................................................................19 DEP 31.40.10.12-Gen. February 2011 Page 4 1. INTRODUCTION 1.1 SCOPE This DEP specifies requirements and gives recommendations for design of multiple pipe slug catchers to be installed on land. This DEP contains mandatory requirements to mitigate process safety risks in accordance with Design Engineering Manual DEM 1 – Application of Technical Standards. This is a revision of the DEP of the same number dated January 2010; see (1.5) regarding the changes. 1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS Unless otherwise authorised by Shell GSI, the distribution of this DEP is confined to Shell companies and, where necessary, to Contractors and Manufacturers/Suppliers nominated by them. Any authorised access to DEPs does not for that reason constitute an authorization to any documents, data or information to which the DEPs may refer. This DEP is intended for use in facilities related to oil and gas production and gas handling. This DEP may also be applied in other similar facilities. When DEPs are applied, a Management of Change (MOC) process should be implemented; this is of particular importance when existing facilities are to be modified. If national and/or local regulations exist in which some of the requirements could be more stringent than in this DEP, the Contractor shall determine by careful scrutiny which of the requirements are the more stringent and which combination of requirements will be acceptable with regards to the safety, environmental, economic and legal aspects. In all cases the Contractor shall inform the Principal of any deviation from the requirements of this DEP which is considered to be necessary in order to comply with national and/or local regulations. The Principal may then negotiate with the Authorities concerned, the objective being to obtain agreement to follow this DEP as closely as possible. 1.3 DEFINITIONS 1.3.1 General definitions The Contractor is the party that carries out all or part of the design, engineering, procurement, construction, commissioning or management of a project or operation of a facility. The Principal may undertake all or part of the duties of the Contractor. The Manufacturer/Supplier is the party that manufactures or supplies equipment and services to perform the duties specified by the Contractor. The Principal is the party that initiates the project and ultimately pays for it. The Principal may also include an agent or consultant authorised to act for, and on behalf of, the Principal. The word shall indicates a requirement. The capitalised term SHALL [PS] indicates a process safety requirement. The word should indicates a recommendation. 1.3.2 Specific definitions Term Definition Bottle, primary Pipe-type part of a multiple-pipe slug catcher for separation of the fluid and storage of the liquids, sloping down under small angle(s) from the lower end of the downcomer to the liquid outlet header (see Figure 2). Bottle, secondary Pipe-type part of a multiple-pipe slug catcher for storage of the liquids only, sloping up from the liquid outlet header, and ending at the gas risers (see Figure 2b). DEP 31.40.10.12-Gen. February 2011 Page 5 Term Definition Downcomer Vertical or steeply sloping pipes of a multiple-pipe slug catcher between the inlet header and the primary bottles (see Figure 2). Entrance length The section of a primary bottle from the inlet to the gas risers. Gas outlet header Part of a multiple-pipe slug catcher on top of and connecting all risers for collection of the out going gas streams (see Figure 2). Inlet header Part of a multiple-pipe slug catcher in which the fluid is evenly distributed before entering the downcomers and in which fluid flow conditions are further improved for separation (see Figure 2). Also called distribution header. Liquid outlet header The lowest part of the multiple-pipe slug catcher, in which the liquid is collected for export. Also called liquid header. Gas riser Vertical pipe on top of a bottle, through which gas exits (see Figure 2). Separator Equipment for separating gas and liquids or various liquids of a mixed fluid. Slug catcher Part of a multi-phase pipeline system for separation of the gas and liquid phases and for temporary storage of the liquids. Slug catcher, multiple-pipe type Slug catcher, made of several parallel pipe bottles. Slug catcher, parking-loop type Slug catcher, where the separator is located apart from the storage part. The separator can be a vessel type and the storage part is made of pipeline material, which can be located away from the separator. Slug catcher, vessel type Slug catcher of limited dimensions and capacity, where separator and storage parts are combined within one or a combination of vessels. Splitter Inlet of a multiple-pipe slug catcher in which the fluid stream is split up for even distribution over the inlet header (see Figure 2). 1.4 SYMBOLS AND ABBREVIATIONS 1.4.1 Symbols A Cross-sectional area Cw Drag coefficient d Diameter of droplet (m) D Diameter (m) H Hold-up fraction g Gravity constant (m/s2) L Length (m) m Number of risers per bottle n Number of bottles V Velocity (m/s) Vol Volume (m3) Q Gas flow rate (m3/s) DEP 31.40.10.12-Gen. February 2011 Page 6 Re Reynolds number Greek symbols 1.4.2 1.4.3 η Dynamic viscosity (N.s/m2) λ Load factor (m/s) or Volumetric fraction of liquid in two-phase flow θ Angle between bottle and horizontal plane ρ Density (kg/m3) Subscripts b Bottle buffer Buffer C Constrictor G Gas IH Inlet header int Intercept L Liquid goh Gas outlet header loh Liquid outlet header outlet Outlet pb Primary bottle pipeline Pipeline R1 First riser on a bottle (from inlet) R2 Second riser on a bottle (from inlet) riser Riser s Settle sb Secondary bottle SC Slug catcher SG Superficial gas SL Superficial liquid Abbreviations BLEVE Boiling Liquid Expanding Vapour Explosion CFD Computational Fluid Dynamics DEP Design and engineering practice Dbottle Internal diameter of the multiple-pipe slug catcher bottles Ddowncorner Internal diameter of the downcomer Dgoh Internal diameter of the gas outlet header Doutlet Internal diameter of the gas outlet Driser Internal diameter of the gas risers dP Differential pressure DEP 31.40.10.12-Gen. February 2011 Page 7 1.5 GtL Gas to Liquids HEMP Hazards Effect Management Process KHI Kinetic Hydrate Inhibitor LNG Liquefied Natural Gas MAOP Maximum Allowable Operating Pressure MEG Mono Ethylene Glycol PSV Pressure Safety Valve SMYS Specified Minimum Yield Strength SGV Sphere-generated Volume CROSS-REFERENCES Where cross-references to other parts of this DEP are made, the referenced section number is shown in brackets. Other documents referenced by this DEP are listed in (6). 1.6 SUMMARY OF MAIN CHANGES This DEP is a revision of the DEP of the same number dated January 2010. The only main change made is that the previous DEP has been split into this Specification and an adjoining Informative DEP 1.7 COMMENTS ON THIS DEP Comments on this DEP may be sent to the Administrator at standards@shell.com, using the DEP Feedback Form. The DEP Feedback Form can be found on the main page of “DEPs on the Web”, available through the Global Technical Standards web portal http://sww.shell.com/standards and on the main page of the DEPs DVD-ROM. DEP 31.40.10.12-Gen. February 2011 Page 8 2. GENERAL DESIGN ASPECTS A multi-phase flow pipeline is intended for transporting the gas and liquid phases simultaneously. The slug catcher situated at the end of the pipeline is intended to separate the phases and to provide temporary storage for the liquid received. DEP 31.40.10.12-Gen. February 2011 Page 9 3. HYDRAULIC DESIGN 3.1 GENERAL The hydraulic design of slug catchers is based on theoretical and experimental work and field experience with existing slug catchers, and shall be performed by competent specialists and approved by Principal. 3.2 SLUG CATCHER SIZE The size of a slug catcher (Volsc) is directly related to the maximum liquid volume it has to hold. It SHALL [PS] be able to intercept the maximum possible slug or surge (Volint) emerging from the multi-phase pipeline at any part of its agreed operating envelope. It should also contain a buffer volume (Volbuffer) in order to guarantee liquid supply to treating facilities downstream of the slug catcher. Hence: Volsc = Volint + Volbuffer Steady state and dynamic simulation tools for multiphase flow in pipelines shall be used for this purpose. 3.3 SLUG CATCHER GEOMETRY AND COMPONENTS The inlet pipe shall also be configured to avoid flow maldistribution in the inlet header. The inlet pipe shall have a straight length of 10 pipe diameters with no bends in the horizontal plane before it connects to the inlet header. Bends in the vertical plane are acceptable as they do not induce lateral flow maldistribution. Similarly, it is not necessary for the inlet pipe to connect horizontally to the inlet header. As the number of downcomers (and hence of primary bottles) per inlet manifold increases, it becomes more difficult to evenly distribute the fluid over them. If there are more than eight downcomers, the splitter arrangement shall be confirmed with Computational Fluid Dynamics (CFD). Expert advice is needed to define the CFD scope of work and to interpret the results. CFD may also be usefully used to confirm the effect of the inlet pipe on flow distribution and also if there are less than eight bottles. The approval of the Principal shall be sought for any design which uses secondary bottles. It shall be ensured that the liquid outlet header is accessible for cleaning. The designs of slug catchers for water-wet pipeline operation are still in development and all designs shall be approved by the Principal. Since one of the main HSE risks is loss of containment, the number of flanges, fittings should be kept to a minimum and instrument bridles should not be used for slug catchers. Special fluid aspects, such as corrosiveness, toxicity and presence of solids or contaminants, shall be considered. Special risks include foaming, fouling, plugging and deposits. Pressure tappings in the liquid outlet header shall be positioned to avoid the effect of solid / sludge build up. Slug catchers are maintenance items that need on occasion be taken out of service for internal inspection, cleaning out solids, repairs etc. Even if such outages cannot readily be aligned with the outages of the downstream plant, then provision shall still be made for internal maintenance by the use of a splitable slug catcher or other equivalent means. DEP 31.40.10.12-Gen. February 2011 Page 10 4. MECHANICAL DESIGN 4.1 GENERAL Slug catchers are an integral part of a pipeline system and SHALL [PS] be designed in accordance with DEP 31.40.00.10-Gen, which is an amendment to ISO 13623. In applying DEP 31.40.00.10-Gen, the following should be taken into consideration: • Under ISO 13623, a mixture of hydrocarbon gas and hydrocarbon liquid will be fluid category E. • Depending on the applicable location class, as described in Annex B of ISO 13623, the design factor on hoop stress for category D and E fluids ranges from 0.45 to 0.67. The demarcation of the slug catcher from downstream facilities shall be indicated on the process engineering flow schemes by indicating the design code breaks. In some jurisdictions, it may be necessary to design the slug catcher to the ASME B31.8 Pipeline code, and not to the ISO 13623 code. In this case note the following: • 4.2 The ASME B31.8 code is limited to temperatures down to –29°C (–20°F). The lower design temperature resulting from depressurisation (see section 4.10) may be lower, in which case either an alternative design code should be used or the blowdown should be changed to avoid the low temperature. MAXIMUM ALLOWABLE OPERATING PRESSURE If line packing is required for the operation of the pipeline system, the MAOP of the slug catcher SHALL [PS] not be less than the MAOP of the feeding pipeline system. If line packing is not required, then maintaining the MAOP of the slug catcher at the MAOP of the feeding pipeline system is preferred as this will eliminate the requirement for separate overpressure protection. If line packing is not required the MAOP of the slug catcher may be lower than for the feeding pipeline system if a significant net lifecycle cost benefit can be demonstrated from lowering the MAOP and installing dedicated overpressure protection for the slug catcher. 4.3 DESIGN FACTOR FOR HOOP STRESS The design factor to limit the hoop stress arising from pressure containment shall be selected according to DEP 31.40.00.10-Gen. NOTE: 4.4 The design factor applies to the minimum wall thickness. OTHER STRESS All applicable loads SHALL [PS] be considered when determining combined stresses during pressure testing and operations. These loads will include: a) pressure; b) thermal expansion; c) passage of slugs or surges; d) foundation and support reaction; e) settlement; f) environmental loads. Settlement includes deformations due to the possible different settlements of the slug catcher and the connecting structures and for buried slug catchers, possible deformations predicted at the transitions between exposed and buried parts, due to different settlements of the slug catcher and the connecting structures. The equivalent stresses shall not exceed the limits specified in DEP 31.40.00.10-Gen. DEP 31.40.10.12-Gen. February 2011 Page 11 4.5 SUPPORTS AND ANCHORS The foundation of locally supported slug catchers shall be in accordance with DEP 34.19.20.31-Gen. The bottles of a buried slug catcher should be situated entirely below original ground level in areas with a natural slope similar to the downward slope necessary for the gravity fill of the bottles. On a level plot, the bottles may be buried in a stable sand mound above the original ground level, with the liquid outlet header above the original ground level, or to reduce the height of the mound, in a shallow pit.See Figure 3 for examples of burial design for slug catchers. Due consideration shall be given to the fact that inspection of a buried slug catcher is difficult. The visual impact of the slug catcher on the environment should also be considered when determining its level and requirements for burial. 4.6 MATERIAL SELECTION 4.6.1 General The materials of the slug catcher shall be selected as part of the project’s overall material selection study and in accordance with DEP 39.01.10.11-Gen. and DEP 39.01.10.12-Gen. The following should be used as guidance: 4.6.2 • Solids can build up in the bottles, so under-deposit corrosion can occur. • If the ambient temperature is colder than the fluid arrival temperature, then the gas will cool and water will condense out of it. This can especially be a problem in parts of the slug catcher where the gas is normally not flowing, such as the bottles. Then the condensing water can cause top of line corrosion. Prevention of brittle fracture The lowest temperature occurring in the slug catcher during depressurisation shall be determined in accordance with DEP 80.45.10.12-Gen, the resulting low temperature SHALL [PS] be used as the slug catcher low design temperature. For guidance on the selection of the lower design temperature for slug catcher materials, reference is made to DEP 30.10.02.31-Gen. Although this DEP specifically applies to pressure vessels and piping systems (and associated codes PD 5500, ASME VIII and ASME B31.3), its content may be useful to determine the applicable minimum design temperature in consultation with the appropriate Technical Authorities. 4.7 INTERNAL/EXTERNAL CORROSION PROTECTION The potential for internal corrosion in the slug catcher shall be evaluated to determine the need for a corrosion allowance or other measures to mitigate internal corrosion. Cathodic protection of DEP 30.10.73.31-Gen. a buried slug catcher shall be in accordance with Anti-corrosion coating of both buried and non-buried slug catchers shall be in accordance with DEP 31.40.00.10-Gen. 4.8 OVERPRESSURE PROTECTION Separate dedicated overpressure protection is not required if the MAOP of the slug catcher is not less than the MAOP of the feeding pipeline system. (NB it may still require PSVs for fire relief.) If the MAOP of the slug catcher is less than the MAOP of the feeding pipeline system then it SHALL [PS] be safeguarded against overpressure accordance with DEP 31.40.10.14-Gen. DEP 31.40.10.12-Gen. February 2011 Page 12 Note that high capacity PSVs on a pipeline are prone to chattering and that this can cause severe damage and even loss of containment. Modulating PSVs can avoid chatter. 4.9 MAINTENANCE The plant’s maintenance philosophy shall consider the need to maintain the slug catcher and its ancillary equipment (such as PSVs, blowdown valves and liquid level shut down valves). It may for instance be necessary to provide installed spare PSVs (with isolation) so that they can be maintained without taking the slug catcher out of service. The slug catcher may need to be a splitable type so that the gas plant can continue production during slug catcher maintenance. The means of maintaining a slug catcher shall be assessed and incorporated into its design. For instance: 4.10 • If certain tasks require entry into the slug catcher, then the design shall make this access feasible. If the Job Hazard Analysis concludes that this shall be done wearing breathing apparatus, then the pipe size and manhole size shall be sized accordingly. • Removal of solids from the liquid header is most conveniently done if there are end flanges on both ends of the header, however safety analyses (5.3) has the aim of reducing potential leak paths by eliminating flanges. An option assessment shall be made to determine the optimal solution based on the balance of loss of containment safety risk and maintenance safety risk. • Requirements for the condition monitoring of buried slug catchers shall be established during the design stage and be designed to minimise the requirement for future excavation. EMERGENCY DEPRESSURISATION The evaluation of the slug catcher depressurisation shall be in accordance with DEP 80.45.10.12-Gen. The following shall be considered in this evaluation: a) Due to their very large inventory, it is usually impracticable to depressure a slug catcher at the same rate as the rest of the plant. b) Lower depressurisation rates have to be justified by analysing the loss of pressure retaining ability (due to the affects of pool fires etc.) against the depressurisation profile in time. c) It may be necessary to increase the wall thickness of small diameter components to bring their period of fire resistance up the same value as the rest of the slug catcher. d) Because slug catchers are depressurised quicker than their pipelines, the slug catcher’s lower design temperature is usually lower than that of the pipeline and hence the material specification may be different. For instance, the pipeline may be specified for the minimum design ambient temperature (e.g. 0°C), but the slug catcher may be specified for the blowdown temperature (e.g. –29°C). It is thus common that materials that were specified for the pipeline cannot be used for the construction of the slug catcher. e) Care has to be taken when calculating the slug catcher minimum blowdown temperature, particularly if the slug catcher has a very large and complicated geometry as the metal wall temperature will not be uniform during the blowdown. The two parts that may be particularly subjected to low temperatures are: • The pipe wall in the vicinity of the blowdown nozzle. The heat transfer coefficient between the high velocity cold gas and the nozzle will be relatively high, bringing the metal temperature close to that of the cold gas. It is common to use an insert (e.g. of stainless steel) to shield the nozzle from the high velocity cold gas. • The slug catcher low points, particularly the bottom of the bottles and the liquid outlet header. In the early part of depressurisation, the slug catcher DEP 31.40.10.12-Gen. February 2011 Page 13 inventory may enter the retrograde region, forming light hydrocarbon condensate which will run to the bottom of the slug catcher. Later in the depressurisation, when the pressure is below the retrograde region, this liquid will boil, generating low temperatures. It is possible that most of the rest of the slug catcher walls have only dropped a few degrees below the ambient temperature. 4.11 MISCELLANEOUS The constrictor at the start of each downcomer can be achieved by an unequal tee or by a forging. There is no minimum pipe length at the constricting diameter, so the swage to the larger diameter should be welded fitting to fitting with the tee. The transition in bottle slope for dual slope slug catchers is best achieved with a bend. The bend can be several metres long to avoid difficulty in fabrication. The gas risers should be approximately vertical. It is acceptable to use a tee with a 90° branch as the resulting riser will only be approximately 1.5° from the vertical. The spacing between bottles shall be sufficient to allow construction and maintenance (e.g. painting, inspection). In the concept identification and concept selection project phases, the minimum spacing allowed is 1.5 bottle diameters. In project specification and detailed design project phases, the construction of the slug catcher will be determined and this will affect the bottle spacing. For instance, if the liquid outlet manifold is to be constructed from tees, then the closest mechanically feasible bottle spacing will be when the tees are welded fitting to fitting, without intervening spools. Consideration should be given to not constructing the manifolds from tees, but as a single item with extruded branches. This may be cheaper, require less welding on site and allow closer bottle spacing. This would also overcome an additional disadvantage of using tees they are usually internally profiled like a barrel and these form pockets that cannot drain. DEP 31.40.10.12-Gen. February 2011 Page 14 5. HAZARD AND RISK MANAGEMENT 5.1 GENERAL Loss of containment from a slug catcher presents a major potential contribution to the level of facility safety risk both for personnel within, and members of the public outside, the fence. Slug catchers typically contain a large inventory of non-stabilised flammable hydrocarbons that cannot be rapidly disposed of to flare in the event of an emergency. In addition, if the reservoir fluids are sour, the associated toxic gas risk in the event of a release can be far reaching. The application of the Hazards Effect Management Process (HEMP) is a mandatory requirement of EP 2005-0300 for any major facility component, including slug catchers. This process begins at the concept identification phase and continues through to the finalisation of detailed design. Selection of the slug catcher concept and its location effectively determine the residual HSE risk level to be managed during the commissioning and operating phases. During subsequent design work the focus is on optimising the design details that ensure constructability, technical integrity, operability and maintainability. Relevant formal HEMP based studies and ALARP demonstration requirements are summarised in (5.2), and design considerations in (5.3). 5.2 APPLICATION OF FORMAL HEMP BASED STUDIES Table 5.1 summarises the formal HEMP (EP2005-0300) based studies relevant to the achievement and demonstration of ALARP HSE risk levels. This list is derived from the Opportunity and Project Management Guide, EP 2006-5500, Chapter 4 and its companion document, GS.06.50034. Specialist HSE advice should be sought to identify the optimum type and timing of studies for inclusion in the project HSE Plan. DEP 31.40.10.12-Gen. February 2011 Page 15 Table 5.1 HSE in slug catcher design Activity Key Reference Concept Identification & Concept Selection Concept Phase HAZID: Identify major hazards and coarsely assess associated risks. HAZID, EP95-0312 Concept Layout Study: Assess slug catcher location options to optimise process, safety and operability benefits. None specific. Major Hazards Assessment: For each option being considered; carry out plausible scenario based Physical Effects Modelling, PEM, and preliminary QRA to produce fire/explosion and toxic risk contours; also cover events that may impact the slug catcher. (Note that additional, or complementary, risk assessment may be necessary to meet regulatory requirements). Physical Effects Modelling, EP 95-0314 Quantitative Risk Assessment, EP 95-0352 Coarse HAZOP and Initial Instrumented Protective Function, IPF, and Safety Integrity Levels, SIL studies. HAZOP EP 95-0313 Classification and implementation of instrumented protective functions DEP 32.80.10.10-Gen. Include HSE assessment and ALARP justification for the slug catcher in the concept selection report. HSE Cases EP2005-0310 Front End Engineering Design, FEED Detailed Layout Study. None specific. Preliminary Bow-tie Study, identification of HSE (Safety) Critical Elements, SCEs, and Performance Criteria. Bow-Ties EP 2005-0300-SP-02 Detailed PEM and Fire and Explosion Assessment (may also involve a FIREPRAN study) leading to a Fire Safety Report. FIREPRAN EP 95-0350 DEP 80.47.10.30-Gen Assessment of Fire Safety of onshore Installations Detailed QRA. As above Main HAZOP and IPF studies. As above Human Factors Engineering, HFE, Analysis (covering maintainability and operability including Job Hazard Analyses) HFE in New Facilities Projects, Yellow Guide Preliminary Construction Health Risk Assessment, HRA HRA EP 2005-0300-PR-10 Issue End FEED Design HSE Case HSE Cases EP 2005-0310 Detailed Design Update and finalise all FEED studies Finalise Design HSE Case 5.3 HSE Cases EP 2005-0310 DESIGN CONSIDERATIONS Concept identification will consider different sizes and types of slug catcher, and possibly options that do not require a slug catcher, for example: • A single large two phase pipeline will need a larger slug catcher than two smaller pipelines. • Dehydrating the gas and condensate before they enter the two-phase pipeline, whilst adding upstream facilities, may eliminate the need for frequent corrosion inhibition and associated sphering. The slug catcher would then only need to be DEP 31.40.10.12-Gen. February 2011 Page 16 sized for the slug resulting from flowrate changes, not the sphere generated slug. Furthermore, frequent solids removal is also eliminated. These are important issues that impact ongoing operational exposure and risk, which shall be taken into account in concept selection. After concept selection has been made, scope for risk reduction is limited to refinement of the chosen design and related operation. Once the concept is selected the factors that influence safety in design are addressed, with Bow-tie Analysis also contributing to identification of risk reduction opportunities. Some key considerations that may influence loss of containment risk levels and contribute to achievement of ALARP are: a) Location of slug catcher within a facility in terms of jet fire related threats that the slug catcher may pose to the adjacent facilities and vice versa. Jet fire impingement on adjacent facilities should either not be able to occur or not occur for long enough to lead to rupture. b) Overpressure protection (including consideration of process unit interfaces and incoming pipeline packing expectations), isolation, and blowdown rate. c) Corrosion allowances, corrosion management. d) Reduction in potential leak paths (e.g. number of flanges, fittings and nozzle connections). This includes minimising the number of small bore connections, as they are more easily broken by mechanical impact, vibration etc. Reduction in potential leak paths is a very effective way of reducing risk, however note the requirement in (4.9) for maintainability. e) Reduction in opportunities for escalation due to flame impingement and radiation (e.g. orientation of flanges, routing of connecting pipework, proximity of other process units). A specific example here is the addition of solid plate decking on platforms installed to access flanged manways; this decking will deflect any potential jet fires that may otherwise impinge directly onto the slug catcher. f) Small bore connections to the slug catcher should be DN 50 (NPS 2) minimum. Temperature Indicators should be located in thermowells directly in the DN 50 connections. Pressure Indicators should be via small bore instrument tubing (< 10 mm) connected to the DN 50 connection to the slug catcher thereby limiting the release should these be damaged or fail. Note that this same approach should be adopted for adjacent facilities where there is a potential for jet fire impingement. g) Connections (of any size) to the slug catcher can be broken and as the slug catcher inventory is typically very large, it is important to provide the means of stopping the release of the inventory. Isolation valves SHALL [PS] therefore be installed directly on the slug catcher nozzles for all connecting pipework. This includes connections to appurtenances such as level bridles. As it is necessary to close these valves in an emergency, they shall be either manual (in which case they need to be accessible to be able to operate them) or automatic (in which case they need to be accessible to carry out their maintenance). h) Active and Passive fire protection: Consideration could be given to remotely operated, manually activated, water monitors. Passive fire protection could be considered, but only where jet fire impingement could credibly occur. i) Segregated catchment and fire safe drainage systems graded to prevent escaping liquids being able to form pool fires under the slug catcher (assuming that released fluids are capable of forming flammable pools – this should be determined as part of the hazard assessment). Considerations that influence other slug catcher related safety and health risks are: • Identification of operating, maintenance and emergency response procedures and any required implementation in the design. These barriers or controls and those responsible for making the controls work shall be included in the bowtie analysis. DEP 31.40.10.12-Gen. February 2011 Page 17 • Safe entry to the slug catcher (including when one piece of the slug catcher is in operation and the other is under maintenance) shall undergo a design phase Job Hazard Analysis as part of the design development to determine all requirements, including: o Isolation requirements (locations of blinds etc) o How to purge and ventilate o Safe removal and disposal of pyrophoric solids Other considerations are: • Loss of containment risk assessments for slug catchers and other facility components with large inventories include an assessment of the likelihood and consequences of a potential catastrophic failure. The likelihood of a well designed, operated and maintained slug catcher rupturing catastrophically is extremely low. However the use of historical data (often correlated with other data for facility components judged similar) does generate a frequency. The modelling of potential consequences (amount released, fire and explosion effects, toxic effects) as a result of such catastrophic failures often falls outside the modelling range. The tendency to use of the BLEVE (Boiling Liquid Expanding Vapour Explosion) model that assumes that the entire inventory of the vessel failing undergoes vapour expansion, something that is not credible for a multiple pipe slug catcher simply because of its size, can serve to exaggerate assessments. However unlikely, the consequences of a catastrophic failure of a slug catcher will be dramatic and an aversion to such consequences, regardless of likelihood, tends to dominate societal risk discussions with local and regulating authorities. Specialist expert advice shall be sought to support the assessment and communication of societal risk with respect to such catastrophic events. • Although burial appears an attractive way to reduce risk of leaks, fire and escalation, burial makes inspection of the slug catcher difficult and hence they shall not be buried unless approved by the Principal. NOTE: Although pipelines are buried, they are inspected by intelligent pigging, whereas it is currently not possible to inspect a slug catcher that way. DEP 31.40.10.12-Gen. February 2011 Page 18 6. REFERENCES In this DEP, reference is made to the following publications: NOTES: 1. Unless specifically designated by date, the latest edition of each publication shall be used, together with any amendments/supplements/revisions thereto. 2. The DEPs and most referenced external standards are available to Shell staff on the SWW (Shell Wide Web) at http://sww.shell.com/standards/. SHELL STANDARDS Prevention of brittle fracture in New Equipment DEP 30.10.02.31-Gen. Design of cathodic protection systems for onshore buried pipelines DEP 30.10.73.31-Gen. Pipeline engineering (amendments/supplements to ISO 13623) DEP 31.40.00.10-Gen. Pipeline overpressure protection DEP 31.40.10.14-Gen. Classification and implementation of instrumented protective functions DEP 32.80.10.10-Gen. Reinforced concrete structures DEP 34.19.20.31-Gen. Selection of materials for life cycle performance (EP) – Materials selection process DEP 39.01.10.11-Gen. Selection of materials for life cycle performance (EP) – Upstream equipment DEP 39.01.10.12-Gen. Emergency depressuring and sectionalizing DEP 80.45.10.12-Gen. Assessment of the fire safety of onshore installations DEP 80.47.10.30-Gen. AMERICAN STANDARDS Process piping ASME B31.3 Gas Transmission and Distribution Piping Systems ASME B31.8 ASME Boiler and Pressure Vessel Code – Section VIII: Rules for construction of pressure vessels ASME VIII Issued by: American Society of Mechanical Engineers ASME International Three Park Avenue, M/S 10E New York, NY 10016-5990 USA BRITISH STANDARDS Unfired fusion welded pressure vessels PD 5500 Issued by: British Standards Institution 389 Chiswick High Road London W4 4AL UK INTERNATIONAL STANDARDS Petroleum and natural gas industries - Pipeline transportation systems Issued by: ISO Central Secretariat 1, ch. de la Voie-Creuse Case postale 56 CH-1211 Genève 20 Switzerland Copies can also be obtained from national standards organizations. ISO 13623 DEP 31.40.10.12-Gen. February 2011 Page 19 APPENDIX A Figures 1 Typical multiple pipe slug catcher 2 Multiple pipe slug catcher details 3 Examples of burial design DEP 31.40.10.12-Gen. February 2011 Page 20 me t re s liquid outlet section 20 0 to 40 0 bottle section ≈2 5m e tr es gas outlet section inlet section Figure 1 Typical multiple pipe slug catcher DEP 31.40.10.12-Gen. February 2011 Page 21 inlet splitter inlet header gas outlet gas outlet header downcomer primary bottle 1st gas riser 2nd gas riser Figure 2a Multiple pipe slug catcher details primary bottle secondary bottles are not fed from the inlet manifold secondary bottle Figure 2b Multiple pipe slug catcher details - Primary and secondary bottles DEP 31.40.10.12-Gen. February 2011 Page 22 Figure 3 Examples of burial design