Uploaded by Leandro Gonzaga

Public Building Design Guidelines & Standards

advertisement
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 5-1
General Lighting Load Density ....................................................................................................................................5-5
Table 5-3
Maximum Values for Lighting Power for Roads and Ground Load Density ............................................5-6
Table 5-2
Table 5-4
Table 5-5
Table 5-6
Table 5-7
Table 5-8
Table 5-9
Table 5-10
Table 6-1
Table 6-2
Table 6-3
Table 6-4
Table 6-5
Table 6-6
Table 6-7
Table 6-8
Table 6-9
Table 8-1
Table 8-2
Table 8-3
Table 8-4
Table 8-5
Table 8-6
Maximum Values for Lighting Power for Building Exterior Load Density ..............................................5-5
Recommended Design Illuminance Levels ............................................................................................................5-6
Illuminance Levels (Average) ......................................................................................................................................5-7
Efficacy Ranges of Various Lamps .......................................................................................................................... 5-10
Recommended Room Surface Reflectance .......................................................................................................... 5-10
Control Types and Equivalent Number of Control Points ............................................................................ 5-11
Minimum Connected Receptacle Load .................................................................................................................. 5-13
Receptacle Rating for Various Size Circuits ........................................................................................................ 5-14
Overall Heat Coefficient ..................................................................................................................................................6-4
Typical Change Values ....................................................................................................................................................6-6
Sprinkler installation guidelines ................................................................................................................................6-7
Hazen Williams C values ................................................................................................................................................6-8
Equivalent Pipe Length Chart ......................................................................................................................................6-8
Recommended Basic Water Requirements for Human Needs. a ............................................................... 6-10
Flow through Schedule 40 B.I. Pipes in Liters per Minute ........................................................................... 6-10
Determination of Number of Cars ........................................................................................................................... 6-12
Average Operation Interval of Cars ........................................................................................................................ 6-12
Waste water contribution per capita / day ...........................................................................................................8-5
Minimum Requirements for Various Occupancies .............................................................................................8-6
Drainage Fixture Unit Values (DFU) ...................................................................................................................... 8-11
Discharge Capacity in Liters per Second for Intermittent Flow Only ..................................................... 8-12
Maximum Unit Loading and Maximum Length of Drainage and Vent Piping ..................................... 8-14
Cleanouts........................................................................................................................................................................... 8-18
Table 8-7
Minimum Horizontal Distance Required From Building Sewer ................................................................ 8-26
Table 8-9
Pipe Connections in Blow-off Condensers and Sumps .................................................................................. 8-31
Table 8-8
Table 8-10
Table 8-11
Table 8-12
Table 8-13
Table 8-14
Table 8-15
Maximum / Minimum Fixture Unit Loading On Building Sewer Piping ................................................ 8-27
Minimum Size Condensate Drain Pipes ................................................................................................................ 8-33
Horizontal Distance of Trap Arms .......................................................................................................................... 8-35
Grease Traps ..................................................................................................................................................................... 8-39
Caulking Ferrules ........................................................................................................................................................... 8-63
Soldering Bushings ........................................................................................................................................................ 8-63
Hanger Rod Sizes ........................................................................................................................................................... 8-64
Table 8-16
Hangers and Support .................................................................................................................................................... 8-65
Table 8-18
Capacities, Airspace and Fittings for Testing ..................................................................................................... 8-75
Table 8-17
Table 8-19
Table 8-20
Table 8-21
Disposal Fields ................................................................................................................................................................. 8-72
Location of Sewage Disposal System ..................................................................................................................... 8-77
*Capacity of Septic Tanks............................................................................................................................................ 8-78
Estimated Waste / Sewage Flow Rates ............................................................................................................... 8-79
ix
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 8-22 Design Criteria of Five Typical Soils ............................................................................................................................... 8-80
Table 8-23 Septic Tank Capacity Limits ............................................................................................................................................... 8-80
Table 8-24 Sizing Roof Drains, Leaders, and Vertical Rainwater Piping (METRIC) ......................................................... 8-86
Table 8-25 Sizing of Horizontal Rainwater Piping .......................................................................................................................... 8-86
Table 8-26
Sizing of Horizontal Rainwater Piping ......................................................................................................................... 8-87
Table 8-27 Sizing Of Horizontal Rainwater Piping .......................................................................................................................... 8-87
Table 8-28 Size of Gutters ............................................................................................................................................................................ 8-88
Table 8-29 Controlled Flow Maximum Roof Water Depth ........................................................................................................... 8-90
Table 8-30 Distance of Scupper Bottoms above Roof .................................................................................................................... 8-90
Table 8-31 Minimum Length of Color Field and Size of Letters ................................................................................................ 8-93
Table 8-32 Minimum Airgaps for Water Distribution 4 ................................................................................................................. 8-96
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Abbreviations
Acronym
Definition
°C
Degrees Centigrade
A
Ampere
AC
Alternating Current
AFSU
Amenities, Facilities, Services and Utilities
AHJ
Authority Having Jurisdiction
ALBO
Acting Local Building Official
AMBF
Allowable Maximum Building Footprint
AMBV
Allowable Maximum Volume of Building
ANSI
American National Standards Institute
Backflow Prevention Devices, Assemblies and Methods ..................................................................................... 8-97
ATM
Asynchronous Transfer Mode
ATS
Automatic Transfer Switches
Table 8-35 Fixture Unit Table for Determining Water Pipe and Meter Sizes ................................................................... 8-114
B.P.
Batas Pambansa (national law)
BAS
Building Automation System
BHL
Building Height Limit
BoC
Board of Consultants
BoD
Bureau of Design
CAAP
Civil Aviation Authority of the Philippines
CDP
Comprehensive Development Plan
Table 8-41 Maximum Allowable Noise Level in General Areas .............................................................................................. 8-119
CFL
Compact Fluorescent Lighting
CHED
Commission on Higher Education
CLUP
Comprehensive Land Use Plan
Figure 3-1
CLWAUP
Comprehensive Land, Water & Air Use Plan
CLWUP
Comprehensive Land and Water Use Plan
CT
Current Transformer
DC
Development Control
DepEd
Department of Education
DG
Design Guidelines
DoH
Department of Health
DoTC
Department of Transportation and Communications
DPWH
Department of Public Works and Highways
DR
Derivative Regulation
DTI
Department of Trade and Industry
EIA
Electronic Industries Alliance
ELCB
Earth Leakage Circuit Breaker
EMI
Electromagnetic Interference
EMT
Electrical Metallic Tubing
EO
Equipment Outlet
ESE
Early Streamer Emission
EVAC
Emergency Voice Alarm Communications
FACP
Fire Alarm and Control Panel
FAR
Floor Area Ratio (same as FLAR)
Table 8-33
Table 8-34 Water Supply Fixture Units (WSFU) and Minimum Fixture Branch Pipe Sizes 3 ..................................... 8-112
Table 8-36 Minimum Required Air Chamber Dimensions ........................................................................................................ 8-115
Table 8-37 Flushometer Fixture Units for Wayer Sizing Using .............................................................................................. 8-116
Table 8-38 Equivalent Length of Pipe for Various Fittings1 ..................................................................................................... 8-116
Table 8-39 Allowance in Equivalent Length of Pipe for Friction Loss in Valves and Thread Fittings ................... 8-117
Table 8-40 Minimum Standards for Illumination ......................................................................................................................... 8-118
Figure 1-1
Overview of Parts of Volume 6 ......................................................................................................................................1-1
Figure 3-2
Philippine Solar and Wind Information for About 7 Months of a Year..................................................... 3-25
Figure 3-3
Figure 3-4
Figure 3-5
Figure 4-1
Figure 4-2
Figure 4-3
Figure 4-4
Figure 4-5
Figure 4-6
Figure 4-7
Figure 4-8
Figure 4-9
Figure 5-1
Figure 6-1
x
Ideal and Optimum Building Orientations in the Philippines ....................................................................... 3-25
Observations on the behavior of wind inside buildings (DPWH, c:2009, unpublished) .................. 3-27
Stack Effect (DPWH, C:2009, unpublished) ............................................................................................................. 3-28
Venturi Effect (DPWH, c:2009, unpublished)......................................................................................................... 3-29
Diagrams of Lateral Earth Pressures on Retaining Wall ................................................................................. 4-32
Flowchart for Foundation Selection ......................................................................................................................... 4-40
Concentrically Loaded Footing ................................................................................................................................... 4-49
Eccentrically Loaded Footing (e ≤ L/6) .................................................................................................................. 4-50
Eccentrically Loaded Footing e > L/ 6 ..................................................................................................................... 4-51
Design Flow ......................................................................................................................................................................... 4-98
Analysis and Design Process for Beams (when analysis and design software is not available) ... 4-99
Design of Compression Member Structural Members Subjected to Compression........................... 4-100
Design of Tension Members Structure Members Subjected to Tension ............................................... 4-101
Typical Power Distribution Scheme ......................................................................................................................... 5-16
Sample Work Sheet for Mechanical Engineer ...................................................................................................... 6-14
xi
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Acronym
Definition
FCC
Federal Communications Commission
NEC
National Electrical Code®
FDDI
Fiber Distributed Data Interface
NFPA
National Fire Protection Association
FLAR
Floor to Lot Area Ratio
NHA
National Housing Authority
G.I.
Galvanized Iron
NMB
Non-mobile Billboard
GFA
Gross Floor Area
OBO
Office of the Building Official
GFCI
Ground-Fault Circuit Interrupter
OFB
Outermost Face of Building
GPRA
Government Procurement Reform Act
OLBP
Outermost Limit of Building Projection
HC
Horizontal Cross-Connect
P.D.
Presidential Decree
HID
High Intensity Discharge
PBH
Provisional Building Height
HLURB
Housing and Land Use Regulatory Board
PEZA
Philippine Economic Zone Authority
HPS
High-Pressure Sodium
PRI
Primary Rate Interface
HUDCC
Housing and Urban Development Coordinating Council
PSC
Philippine Sports Commission
HZ
Hertz
PT
Potential Transformer
IC
Intermediate Cross-Connect
PVC
Polyvinyl Chloride Conduit
ICAO
International Civil Aviation Organization
PWD
Person with Disability
IEC
International Electro-Technical Commission
R.A.
Republic Act
IED
Intelligent Electronic Device
RC
Referral Code
IEEE
The Institute Of Electrical And Electronics Engineers
RF
Radio Frequency
IMC
Intermediate Metallic Conduit
RLA
Registered and Licensed Architect
IRR
Implementing rules and regulations
RLP
Registered and Licensed Professional
ISDN
Integrated Services Digital Network
ROW
Right-of-Way
kV
KiloVolts
RROW
Road Right-of-Way
LAN
Local Area Network
RSC
Rigid Steel Conduit
LBO
Local Building Official
SARP
Standard and Recommended Practices
LED
Light Emitting Diode
ScTP
Screened Twisted-Pair
LEED
Leadership in Energy and Environmental Design
SDP
Site Development Plan
LGU
Local Government Unit
SF6
Sulfur Hexafluoride
Lm
Linear Meter
SLD
Single Line Diagram
LRFD
Load and Resistance Factor Design
TGB
Telecommunications Grounding Busbar
M
Meter
TGFA
Total Gross Floor Area
m2
Meter square (Area)
THHN
Thermoplastic High Heat-resistant Nylon
MC
Main Cross-Connect
TIA
Telecommunications Industry Association
MCB
Miniature Circuit Breaker
TIEZA
Tourism Infrastructure and Enterprise Zone Authority
MCC
Motor Control Center
TLA
Total Lot Area
MCCB
Molded Case Circuit Breaker
TMGB
Telecommunications Main Grounding Busbar
MH
Metal Halide
TSB
Telecommunications System Bulletin
MLE
Mandated Legal Easement
UNE
Unión Nacional Española
Mm
Millimeter
UPS
Uninterruptible Power System
MoS
Manual of Standards
UTP
Unshielded Twisted-Pair
MTS
Manual Transfer Switch
V
Volts
NBCP
National Building Code of the Philippines
VA
Volt Ampere
NBO
National Building Official
W
Watt
NBZ
No-build Zone
W/Lm
Watts per Lumens
NCCA
National Commission on Culture and the Arts
W/M2
Watts per Meter square
xii
Acronym
Definition
xiii
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Acronym
Definition
XLPE
Cross Linked Polyethelene
ZO
zoning ordinance
xiv
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Glossary
Acronym
Definition
Addressable Device
A fire alarm system component can be individually identified of its status or used to individually control
other functions.
Addressable System
A fire alarm system consisting of an addressable fire alarm control panel and addressable devices that
primarily gives the exact location of a fire.
Alarm Indicator
A device which by visual means indicates the zone which an alarm has originated.
Alarm Zone
A part or subdivision of a protected building or premises.
Allowable Maximum
Building Footprint
The resultant area established at grade level upon which the proposed building/structure may be
erected.
Annunciator
A fire alarm system component containing one or more indicator lamps or alphanumeric displays in
which each indication provides status information.
Architectonics
The science part of architecture, unifying the architectural, structural and utility plans/designs of a
building/structure.
Architectural Design
A development or redevelopment concept that focuses on the components or elements of a building,
structure or system and unifies them into a coherent and functional whole, utilizing the principles of
strength, harmony and aesthetics in arriving at a solution to a spatial problem through the deft
application of the arts and sciences, according to a particular approach, to achieve the
development/redevelopment objective/s under the given constraints/limitations.
As-Built Plan
A scaled drawing that shows a project and infrastructure components after completion of construction
Attention Signal (alias
Preliminary Noise or
Instruction Signal)
Tone or ringing-style short signal before an announcement.
Bore Hole
A hole drilled in the ground to obtain samples for subsoil investigation.
Building
A roofed and walled structure built for permanent use.
Closed Circuit
Television(CCTV)
A video system in which signals are not publicly distributed and monitored for surveillance, security and
monitoring purposes.
Compression
When a body is subjected to a force or forces acting towards it causing it to squeeze, shorten or crush.
Concrete
A mixture of cement, fine aggregate, coarse aggregate and water.
Cross Section
(alias Cross Section Plan)
View generated by slicing an object at an angle perpendicular to its longer axis.
Dead Load
An inert, inactive load such as the weight of the members, the supported structure and permanent
attachment or accessories in bridges.
Design Life
Period assumed in the design for which the infrastructure is required to perform its function without
replacement or major structural repair.
Differential Settlement
The vertical displacement due to settlement of one point in a foundation with respect to another point of
the foundation.
Dispersal Area (Safe)
An area which will accommodate a number of persons equal to the total capacity of the stand and
building/structure it serves, in such a manner that no person within the area need be closer than fifteen
meters (15.0 m) from the stand or building/structure. Dispersal areas shall be based upon the area of
not less than 0.28 m2 per person.
Domestic sewage
Comprise of Industrial wastewater, Recycled water, Reclaimed water and Reuse water.
Ductility
Ability of a component or solid material to deform under tensile stress.
Factor of Safety
The ratio of a limiting value of a quantity or quality to the design value of that quantity or quality.
Acoustic Feedback
Feedback of the output signal of an amplifying system on the input of the system depending on the
difference in the intensity and phasing between the input and output signal.
Flange Angles
Angles used in riveted plate girders to carry tensile or compressive forces induced by bending.
Flexure
A deformation or behavior of an elastic structural element subjected to an external load perpendicular
to the axis of the element.
Footprint
The surface area of a building where it meets the natural ground or the finished grade i.e. the outer
perimeter of a building.
xv
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Force
A push or a pull in a given direction on a body that changes or tends to change its state or rest. (or its
state of motion).
Foundation
A component of an engineered structure that transmits the structure's forces into the soil or rock that
supports it
Friction Pile
A pile which derives its supports principally from the surrounding soil through which it is placed by the
development of shearing resistance between the soil and the pile.
Geomembrane
Very low permeability synthetic membrane liner of barrier used with any geotechnical engineering related
material so as to control fluid (or gas) migration in a human-made project, structure, or system.
Green Architecture
Architecture in which the plan/design is focused on making a building energy-efficient, so as to reduce its
energy consumption, water consumption, operating costs and environmental impact
Green Roof (alias Eco
Roof, Living Roof,
Vegetated Roof)
A roof that is either partially or completely covered in vegetation and built on top of a man-made roof,
deck roof, deck or other support structure
Green Wall (alias
Biowalls, Ecowalls,
Vertical Gardens)
A wall or similar vertical support/element that may be either free-standing or attached to an existing wall,
and that may be partially, substantially or fully covered with vegetative cover.
Isolated Footing
A footing designed to support a structural load from a single column. Usually a shallow foundation, and
square or circular in shape
Land-use Map
Maps that reflect the land resources and types of land use in the national economy.
Longitudinal Section
View generated by slicing an object at an angle parallel to its longer axis
Physical Planning
The activities pertaining to the preparation of a physical layout of land or property on which vertical
structures such as buildings and/or structures and horizontal developments are proposed.
Pile
A slender member that is driven (hammered), drilled or jetted into the ground. Piles are usually
constructed of timber, steel or pre-stressed reinforced concrete.
Point Bearing Piles
(alias End Bearing Piles)
A pile placed or driven on or into a material which is capable of developing the pile load by directly
resting on a bearing stratum with a reasonable factor of safety.
Post Tensioning
The system of prestressing whereby tendons are stressed after the concrete has attained the required
strength and the prestressing forces are transmitted to the concrete generally by anchoring the stressed
tendons to the members.
Precast Concrete
A structural member specially of concrete that has been cast into form either in a permanent plant or
somewhere near the site of construction before being transported to the site of installation and finally
erected at its final location.
Prestressed Concrete
Concrete reinforced with strands, pretensioned or post tensioned, wherein the effective internal stresses
are induced deliberately by forces caused by tensioned steel or other means to give an active resistance
to loads.
Pretensioning
The system of prestressing concrete members whereby wires or strands called tendons are stressed to
a predetermined amount by stretching them between anchorages prior to pouring of concrete.
Reinforced Concrete
A composite material which utilizes the concrete in resisting compression forces and some other
materials, usually steel bars or wires, to resist the tension forces.
Retaining Wall
A structure usually made of stone masonry, concrete or reinforced concrete that provides lateral support
for a mass of soil.
Seismic Retrofitting
Modification of existing structures to make them more resistant to seismic activity, ground motion or soil
failures due to earthquake.
Settlement
The downward movement of soil, or the downward movement of a foundation.
Shear Connector
A welded stud, spiral bar short length steel element that resists shear between components of a
composite beam.
Sheet Piles
A long vertical earth retention and excavation support, steel, vinyl or reinforced concrete, driven into the
ground with interlocking edges to form a continuous wall to resist water or earth pressure.
Spread Footings
Also, isolated footing. A footing designed to support a structural load from a single column. Usually a
shallow foundation, and square or circular in shape.
Stirrups
(alias Ties)
Lateral reinforcement formed of individual units, open or closed or continuously wound reinforcement.
Structural Foundation
Foundation of a structure which generally serves to transfer the loads from the structure to underlying
materials (such as soil or rock) which are known as the foundation material.
xvi
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Sustainable Design
The philosophy of designing physical objects, the built environment and services to substantially
comply with the principles of economic, social and ecological sustainability, without compromising
natural and other resources that must be bequeathed to future generations
Sway Bracing
Secondary structural members spanning between the trusses at interior panel points and provide lateral
stability and shear transfer between trusses.
Topographic Survey
(alias Ground Survey)
Collection of data to represent horizontal and vertical positions of an area, including features such as
roads, bridges and bodies of water with contours, elevations and coordinates.
xvii
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
For clarity, GFAs or TGFAs generated below grade (or sidewalk surface) level i.e.
basement or lower ground levels, are not to be counted as part of either the GFA or
TGFA, which are essentially floor areas generated above grade (or sidewalk
surface) level.


Apply prescribed setbacks and yards/court to determine AMBF.
TGFA/AMBF = provisional building height or PBH (for direct comparison with
the applicable BHL); whichever shall result in the lower number of
floors/levels applies i.e. the most stringent rule always applies.
For clarity, building height classification in relation to the BHL for buildings shall
be as follows:
Table 3-2
Conversion Table of Gross Floor Area (GFA) to Total Gross Floor Area
(TGFA), 2004 Revised IRR of P.D. No. 1096
Excluded Floor Areas
(non-GFA) as a
Percentage (%) of the
TGFA
Multiplier to
Convert the GFA to
TGFA
Residential 1
33%
1.50
Residential 2 (Basic), Residential 3 (Basic) and
Residential 4
20%
1.25
Residential 2 (Maximum), Residential 3
(Maximum) and Residential 5
16%
1.20
Commercial 1
20%
1.25
Commercial 2
25%
1.33
Commercial 3
33%
1.50
Industrial 1
25%
1.33
Industrial 2 and 3
33%
1.50
Transportation, Utility and Service Areas
33%
1.50
Agricultural and Agro-Industrial
2%-5%
1.03-1.06
Type of Building/Structure based on
Use/Occupancy
A low-rise building/structure shall be from one (1) to five (5) storeys i.e. from 3.0
m (m) to 12.0 m plus 1.0m for a parapet wall (if provided with deck roof),
collectively reckoned from grade (or sidewalk surface) level, including mezzanine
level, in the case of non-residential buildings/structures; and from one (1) to five
(5) storeys i.e. from 3.0 m (m) to 15.0 m plus 1.0m for a parapet wall (if provided
with deck roof), collectively reckoned from grade (or sidewalk surface) level,
including mezzanine level, in the case of residential buildings/structures; low-rise
buildings may or may not be provided with an elevator but must satisfy the basic
accessibility requirements;
A medium-rise building/structure shall be from six (6) to fifteen (15) storeys i.e.
from 15.0 m (m) to 45.0m plus 1.0m for a parapet wall (if provided with deck
roof), collectively reckoned from grade (or sidewalk surface) level, including
mezzanine level, in the case of non-residential buildings/structures; and from six
(6) to fifteen (15) storeys i.e. from 18.0 m (m) to 45.0 m plus 1.0 m for a parapet
wall (if provided with deck roof), collectively reckoned from grade (or sidewalk
surface) level, including mezzanine level, in the case of residential
buildings/structures; medium-rise buildings must be provided with an elevator
and must satisfy the basic accessibility requirements; and
3-5
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures

Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Is there an alternate disaster plan for the disposal of sewerage?

Communication





Are equipment securely anchored and protected?

Are there alternate means of communication when systems fail?

Are computers latched onto uninterruptible power supply (UPS)?
Is there a facility for obtaining a mobile emergency generator?


Furniture, Fixtures and Equipment Anchorage (especially crucial for hospital designs)


Are the following equipment securely braced?

- Storage equipment: filing cabinets, shelving, etc.
- Table- and floor-mounted equipment






3.5.2






3.5.3
Are there surgical fixtures?
Are there imaging equipment?
Is there a gas system?
What are the other essential equipment?
Are there fire alarm and fire-fighting equipment?
Compliance with R.A. No. 9514, the 2008 Fire Code of the Philippines (FCP) and
its 2009 or latest IRR
Area of Rescue Assistance (ARA): an area, which has direct access to an exit,
where people who are unable to use the stairs or elevators may remain
temporarily in safety, to await further instructions or assistance
Materials Selections: fire-related materials must be given priority; flamespread must be checked at various critical points
Firefighting facilities/preparedness: planning and deducing must consciously
consider the installation of fire-fighting equipment as an integral factor
Provision for gas masks, fire-resistant jackets, boots, helmets, etc.

3.5.4
Emergency water supply
Wind direction and other topographical factors like loose soil, loose rock
anchorage that may be exacerbated by heavy rainfall shall be dealt with
dispatch
Secure installations of electrical and emergency electrical power system
Design and layout of windows, doors and other openings
Location of garage and emergency equipment must allow for quick access and
use
Community facilities must be securely braced and protected
Emergency water supply (for 2-3 days)
Life-saving equipment securely located and anchored
Bracing and trimming of big trees (especially those with shallow root systems
like acacia, mango, etc.) and structures that pose danger to life
Non-mobile billboards shall follow standards set under the 2008 DPWH
Additional Rules and Regulations (ARR) supplementing Rule XX of the NBCP.
LGUs can enact ordinances that are more stringent than the ARR and Rule XX
of the NBCP but cannot relax the same.
LGU shall provide the appropriate equipment like chainsaws and other
earthmoving and transport equipment.
Floods Mitigation Checklist





Availability of recent secondary hydrologic information to ascertain flood
levels for physical planning at a community level
Site analysis and site development must seriously consider the site’s history
and experience with floods
Provisions for emergency evacuation
All of the Typhoon Mitigation Checklist
Prepare map for flood-prone areas. (DPWH, c.2009, unpublished); refer also to
DG Volume 3
Floor levels for buildings should be located above the flood level along with a
suitable freeboard, as determined based on Volume 3. The appropriate design
flood to be adopted for different types of buildings is provided in Table 3-3. The
following should also apply:

Provision of life safety harness system
Typhoon Mitigation Checklist

3-8
Are there storage tanks (for liquid oxygen and hot water)?
Fire Mitigation Checklist


- Ceiling-mounted equipment: ceiling fans, lighting fixtures, etc.
Choice of materials like glass and other non-masonry/non-metal exterior
finishing that can withstand high wind pressure must be specified


If basement parking is to be adopted, then all entries and openings to the
basement should be above the design flood level noted in Table 3-3. A
secondary evacuation route, such as a stairwell, should be provided that
provides access to a level above the design flood level.
All electrical and related services should be above the design flood level, or
flood proofed above the flood level.
Where inundation is expected to occur for more than a few hours, then
provisions should be provided for appropriate evacuation.
3-9
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
The hawker’s plaza and ‘bagsakan’ (wholesale) area are places near the semi-wet
and dry sections for the convenience of both vendors and delivery vans, most of
which supply dry goods such as groceries and sari-sari items (different/wide
variety of goods). It is recommended that the hawker’s plaza should not exceed
60% of the size of the market core, except for those markets which may have only
one or two market days per week. The ‘bagsakan’ (wholesale) area is computed at
around 10–13% of the total built-up area.
Market Stalls and Aisles
A public market basically consists of stalls and aisles. A stall is the most important
element of the market. In detailed design, great care must be exercised in
analyzing the needs of vendors, particularly in the case of the wet stalls.
The required stall area for a market must be about 60% of the total floor area. The
circulation area, which is the aisle, is 35% and the offices, toilets and utility room
at 5% of the total floor area.
The stalls are designed with high flexibility to make them functional even if the
original intention is changed. For planning purposes, the average sizes of the
different market stalls may be assumed at 2–4 m2 per stall for vegetable, fruits,
meat and dried fish, 5–9 m2 per stall for shops and sari-sari (general) store and
15–18 m2 for carinderia (eatery) and cereals.
For purposes of preliminary programming, the following illustrate the above
applications:
Wet Market Stalls


1.7 m x 2.25 m or 3.8 m2 – for meat/fish and vegetables
1.7 m x 2.25 m or 3.8 m2 – for fruits and vegetables
Dry Market Stalls



3.4 m x 4.5 m or 15.30 m2 –for cereals and carinderia(eatery)
2.25 m x 3.41 m or 7.67 m2 –for shops and sari-sari (General Store)
2.27 m x 4.49 m or 10.19 m2 – garments
Recommended stall sizes should be matched with existing stall sizes and should be
related to the market vendor analysis. Any deviations from the recommended stall
sizes should be done in increments/multiples of 1.44m2 (1.2 m x 1.2 m) or even
fractions (1/2”, 1/4”, 1/8”, 1/16”).
For two storey market buildings, the dry markets stalls shall be situated at the
upper level.
The counter aisle should be at 1.5 – 2.0 m wide while the primary and secondary
entry aisles may be assumed at 2.0 – 3.5 m wide.
The proposed dry section market stalls shall have a secure ceiling e.g. wire mesh,
cyclone wire or similar material, to be installed directly above or below the ceiling
material
3-18
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
3.8.3
3.8.4
3.8.5
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
School Building Design
Particulars
Refer to pertinent DepEd standards/ guidelines or to applicable DPWH standards
(duly approved by the DepEd) and to Annex C.
Maximum Space Requirements
(m2)
Assistant Secretary
56.00
Staff
4.00 – 6.00/pax2
Conference Room
30.00
Such as small airport/port passenger terminal buildings. Refer to pertinent
DoTC standards/guidelines (if available) and to Annex C.
Reception Room
20.00
Toilet/Bathroom
6.00
Pantry
10.00
Storage Area
10.00
Table 3-6 provides the recommended standards for use as a reference in the space
planning of typical high density non-residential buildings such as offices.
Office of the Director
Design of Other Key Structures
Design of Government Offices
Table 3-6
Space Allocation Standards for Typical Office Spaces (GFA)
Particulars
Maximum Space Requirements
(m2)
Main Lobby
0.25/pax; minimum for lobby as waiting/standing
room is 0.28
Conference Room
1.20/pax including aisles and demonstration
space
Training Room
2.40/pax including aisles and services such as
storage, production room and toilet for the staff
Director IV
36.00
Staff
4.00 – 6.00/pax2
Conference Room
25.00
Reception Room
10.00
Toilet/Bathroom
4.00
Pantry
5.00
Storage Area
6.00
Office of the Assistant Director
Director III
24.00
Staff
4.00 – 6.00/pax2
1.50 per one water closet (WC) enclosure
Toilet/Bathroom
4.00
For Agencies providing frontline services
(for Public use)
1 WC/1 – 100 for female
1 WC/1 – 200 for male
1 urinal/1 – 100 for male
1 lavatory/2 WC
1
For Agencies with no clientele
(for Employee use)
1 WC/1 – 15 for male and female
2 WC/16 – 35 for male and female
3 WC/36 – 55 for male and female
1 lavatory/40 for male and female; or
1 lavatory/2 WC
Toilet Facilities
1
Based on the Revised National Plumbing Code of the Philippines (R.A. 1378)
Includes circulatory area
2
Division-Level Unit
Division Chief
12.00
Staff
4.00 – 6.00/pax2
Includes circulation area
2
Space Requirement/s of Key Officials
Office of the Secretary
Secretary
72.00
Staff
4.00 – 6.00/pax2
Conference Room
60.00
Reception Room
30.00
Toilet/Bathroom
6.00
Pantry
10.00
Storage Area
10.00
Office of the Undersecretary
The equivalent space allocations for officers at national government
agencies/GOCCs, such as Secretary, Undersecretary and Assistant Secretary shall
apply for all affected public buildings (refer Table 3-6).
Other applicable space planning standards for other Philippine buildings i.e.
standards that are not found in the NBCP, are as follows:

Undersecretary
63.00
Staff
4.00 – 6.00/pax2
Conference Room
40.00

Reception Room
20.00

Toilet/Bathroom
6.00
Pantry
10.00
Storage Area
10.00
Office of the Assistant Secretary
3-20
The same reference standards places open plan areas at offices at 80%, with
enclosed office areas at 20%.




Hospitals and health care facilities c/o the DoH
Primary and secondary school buildings c/o the DepEd
Tertiary school buildings c/o the CHED
Markets c/o the DTI and/or the HLURB and HUDCC
Industrial buildings c/o the PEZA
Tourism facilities c/o the TIEZA
Recreational facilities c/o the HLURB and HUDCC
3-21
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
3.11.3
3.11.4
pipes/tubings/drains connected to NON-CAPITAL EQUIPMENT and
plumbing/electrical/electronic/ mechanical fixtures and the like; and other
decorative accessories such as curtains, drapes, blinds, shades and carpets/carpet
tiles, paintings, wall hangings, sculpture (large/medium/small), and
decorative/accent lighting devices, with complete fittings and accessories, and the
like.
Fixtures
These are pieces of equipment or furniture that is fixed in position in a building or
vehicle; articles attached to a building or land and considered legally part of it so
that such items normally remain in place even when the building owner moves out;
something securely fixed in place or attached as a permanent appendage,
apparatus, or appliance e.g. plumbing fixtures; the possible examples of fixtures in
a typical Philippine building/grounds include the following: visible, remoteoperated and/or tangible/operational devices or provisions that are fixed in
position in (such as permanently attached to) a building and which partake of
finishing items, such as plumbing fixtures (water closets, urinals, lavatories, water
fountains, etc.), electrical fixtures (general and task lighting, area lighting for
grounds, exterior building lighting including up-lighting or down-lighting, indoor
and outdoor switches/manual controls and convenience outlets, etc.), electronic
fixtures (indoor and outdoor/rooftop cameras, speakers, sensors, monitors, cardaccess or biometric access terminals for secure areas, automated main gates and
doors, etc.), mechanical and related auxiliary fixtures (sprinkler heads, indoor
climate management or control terminals/stations/switches, etc.), and the like; and
architectural fixtures such as large fixed/sectional mirrors, finish hardware items,
wall (or floor) safes and the like.
Equipment
These are the necessary items for a particular purpose or activity; equipment
(solid state), apparatus, gear, material (i.e. the aggregate of
portable/transportable/self-propelled equipment and/or supplies used by a
specific organization, such as the military or para-military or the government),
outfit, paraphernalia and the like; materials needed for a purpose such as
laboratory apparatus; all the fixed assets other than land and buildings of a
business enterprise; tangible property (other than land or buildings) that is used
in the operation of a business; examples of equipment include devices, machines,
tools, and vehicles; the possible examples of equipment in a typical Philippine
building are: visible and tangible/operable apparatus, gear, materiel
(transportable equipment), outfit, paraphernalia, tools relating to architectural,
structural,
electrical,
electronic
and
auxiliary
(telecommunications/audio/video/building
management
system/BMS),
mechanical, sanitary, plumbing, fire-fighting functions/operations of the building
e.g. integrated computer systems including peripherals, ticketing system including
cash registers and official receipt or trip ticket printers, point of sale (POS)
reporting system (as applicable, possibly for both ticketing/parking and
commercial leased spaces), public information/notification/address systems
3-33
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
3.12.1
Sites/Grounds





3.12.2
Land and site sustainability considerations during construction activities such
as plans and documentation needed for site excavation, sedimentation and
erosion control, air pollution control, etc.
Use of organic soil treatment products.
Minimization of over-paving through the requisite compliances with valid and
subsisting laws, rules, regulations, guidelines, standards and procedural
manuals pertaining to physical planning e.g. NBCP, Water Code, Sanitation
Code, etc. (refer also to pertinent portions of Annex E).
Management of shadows cast by the proposed buildings on adjacent lots and
buildings/structures.
Miscellaneous considerations i.e. rainfall information and hydrologic (and
flooding) characteristics of the site including flood risk assessment mitigation
studies (if available); public passage-ways such as secure pathwalks and
bicycle lanes and bicycle parking plan (if provided); community connectivity
(amenities, facilities, services and utilities/AFSU); waiting sheds and other key
street furniture; vehicle use, maneuver and parking plans (open, semi-covered
and covered); landscaping plans (hard and soft scapes); green roofs and heat
insulated areas.
Buildings/Structures




Energy conservation and management i.e. compliances with the latest
Department of Energy (DoE) guidelines on energy conservation and
management i.e. lighting and power design, etc.; use of light-emitting diodes
(LEDs), compact fluorescent lamps (CFLs) and similar energy-saving
illumination devices (provided the proper disposal methods are also in place),
etc.; extensive use of natural lighting and ventilation matched with the use of
sun-shading devices; use of renewable (non-fossil) energy sources where
applicable i.e. sun, wind, wave, current, hydro, dendro (forest products), hot
springs, animal, biogas/compost, solid waste, etc.
Water conservation and management i.e. reduction or optimization of
domestic water consumption such as use of low-flow plumbing/sanitary
fixtures and equipment, etc., domestic wastewater reuse or recycling; storm
water management and rainwater harvesting such as collection, storage,
treatment, use, reuse, recycling, disposal, etc., wastewater treatment such as
use of compact/ compartmentalized sewage treatment devices or sewage
treatment plants (STPs), etc.
Solid waste management i.e. waste management plan; material recovery/
segregation facility (MRF/MSF); use of ‘non-burn’ waste to energy (WTE) or
waste to worth (WTW) technologies that utilize local and foreign advanced
technologies compliant with the PH Clean Air Act of 1999.
Indoor environment quality considerations e.g. non-smoking areas;
minimization of emitted volatile organic compounds (VOCs) by materials
specified for the building/structure/project; air-conditioning refrigerant
3-35
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
3.13.1
Sites/Grounds


3.13.2
Less paving around the building to help retard surface water flow i.e. through
percolation into the ground, inasmuch as the collected surface water contribute
to flash flooding at lower elevations within a community.
Proper setbacks and compliance with mandated legal easements (MLEs) along
waterways to maintain floodwater at a low level such as narrower waterways
translate into higher flood levels.
Buildings/Structures









Use of concrete deck roofs instead of sloped metal roofs.
If the use of metal roofs cannot be avoided, provide much steeper roof slopes
(because flatter slopes are easily penetrated by strong winds such as wind
drag).
Use of roof that is sloped at all four (4) sides (since typhoon winds come from
all directions).
Use of green roofs (only when technically and financially feasible).
Use of very short eaves i.e. the roof extension outside the exterior wall of the
building or residence, usually provided for shade and aesthetics (inasmuch as
long eaves cause uplift which open up the roof cavity to more/extensive wind
damage); the short eaves could be paired with media agua (shed roofs) over
windows and doors; short eaves are those that are 610 mm or shorter as
measured from the finished building wall while the long eaves are those that
extend as much as 2.44 m or longer from the finished building wall (and which
may already require additional structural support); the minimum eaves shall
be at 300 mm while the maximum eaves can be as much as 3.66 m (with or
without additional structural supports), provided that the appropriate climate
change adaptive and disaster reduction considerations are all factored into the
design.
Use of gutterless roofs in sites where trees shed a large volume of leaves i.e. dry
and decomposed leaves and debris clog up the drains, downspouts and catch
basins and the accumulated water cause the un-drained roof to collapse; a
gutterless roof has to be partnered with a trench drain, sand pit or a sand and
gravel bed at the ground below to absorb the falling water.
Controlled roof cavity and/or ceiling cavity openings to relieve or equalize
pressure inside and outside the building during strong winds i.e. a certain
amount of wind has to be let in the building/structure to relieve and/or
equalize air pressures.
For flood-prone or flood-risk areas, the use of the lower level as a multi-use,
flexible use space (that can be flooded), and which can be connected to the
upper level/s of the building through stairs or ramps (for use by PWDs or large
domesticated/farm animals).
Use of stilted or floating building technologies, if technically and financially
feasible, if safe and if locally available.
3-37
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures














Tall buildings shall be provided with safe refuge zones or floors for evacuating
building occupants; these areas shall have stronger structural reinforcement
and fire protection features if compared with regular floors.
All emergency, exit and public doors servicing rooms or areas with users
numbering twelve or more occupants must all swing outward and use nondetachable pins for added safety; if 2 exits are located in an enclosed space,
these must be located far apart and at opposite sides of such space.
All fire lanes and emergency/fire exits, passageway and stairs shall be
maintained free of all forms of obstructions and fitted with emergency lighting
devices all the way to the refuge floors and/or the street below.
Location of emergency exits shall be far apart and/or opposite of each other
and in full accordance with prescriptions of the NBCP and the Fire Code.
Avoidance of use of non-fire rated substances and materials for buildings,
particularly those that produce toxic or harmful fumes during fire e.g.
polyvinyl chloride (PVC) doors and jambs, etc.
Use of medium-weight movable materials as furniture pieces i.e. those that can
readily serve as sturdy flotation devices.
Elevated floor finish line (FFL) at say 0.60 m minimum above sidewalk level
for carports and for main entrances for low-rise structures e.g. .residences in
known flood risk areas. Refer to Section 3.5.4 for flood levels for buildings.
Positioning of convenience outlets above table surface height i.e. say about
850 mm above the finished floor line (FFL)
Possible positioning of the main power panel at a reachable height just below
the finished ceiling line (FCL) i.e. at a maximum height of 300 mm below the
finished ceiling line (FCL) and at a minimum eye level (or pix) height of 1400
mm above the finished floor line (FFL).
Use of jalousie windows, which are designed for use in the tropics, and which
could serve as a fast means of escape (but requires security provisions such
grillwork or similar devices).
A fast emergency escape system using maintenance gondolas or possibly even
zip lines mounted on roofs of tall buildings directed at refuge floors/levels of
adjoining tall buildings or open refuge areas may need to be devised.
Design of low-rise buildings for survivability i.e. controlled detachment of a
designated survival room/pod from the main building/structure for purposes
of flotation or similar survival action/procedures.
Use of low-cost to optimum-cost devices or technologies than can readily
convert seawater, brackish water, inland waterway water, wastewater, etc.
into domestic water fit for cooking and drinking (potable water) i.e. solely
with the use of renewable energy i.e. sun or wind to power the conversion
process.
Use of stilted or floating building technologies, if technically and financially
feasible, if safe and if locally available.
3-39
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
valid and subsisting law that is implemented and enforced by DPWH and its
agents. The NBCP has apparently been breached and violated at will over the last
36 years of its existence, resulting in the present pitiful state of the built
environment.
An architectural permit application must be accompanied by the pertinent
architectural documents, together with computations that must be signed and
sealed only by registered and licensed Architects (RLAs), in full compliance with
law (Section 20.5 of RA No. 9266, The Architecture Act of 2004). Such
architectural computations must contain basic spatial and volumetric information
about
the
proposed
new
building/fit-out
or
repair/renovation/rehabilitation/expansion/retrofit project such as those
mandated under Rules VII and VIII (as well as Rule XII) of the 2004 Revised IRR of
the NBCP, to wit:



















3-42
Zoning classification with statements of principal, accessory and conditional
uses
Allowed building occupancy and building type
Lot type, configuration and access systems
RROW width (stating arcade width if applicable) and TLA
On-site and off-site analyses, with particular attention to topography, slopes,
hazards, etc.
Building and site/grounds orientations with respect to sun, wind, rain/storm,
noise, pollution sources, odors, view corridors (and privacy satisfaction)
Treatment of the mandated legal easements (MLE)
FLAR (FAR), GFA &TGFA
Applicable setbacks (including incremental setbacks)
Firewall compliances (as needed)
Basement level compliances (as applicable)
Open and covered parking compliances (including public transportation
connectivity)
PSO and AMBF including clear indications of the total open space within lot
(TOSL) and the unpaved surface area (USA) that shall assist in surface water
flow retardation and percolation into the aquifer
Applicable BHL (including CAAP restrictions or other agency restrictions as
applicable)
AMVB
OFB, OLBP and the angle of angular plane with respect to the RROW
The architectural and space programs
Wall/window orientations and wall to window ratio (WWR)
Site development (including urban design) features
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures





Use of natural light and ventilation, particularly of day-lighting and passive
cooling
Elevator traffic calculations and zoning (as applicable)
Building and site/grounds colors and textures, particularly those that are
absorptive and reflective of light and heat (that should illustrate the RLA’s
appreciation of tropical design as the same applies to Philippine buildings)
Graphics, signage and way-finding provisions
Design sensitivities i.e. gender and development (GAD), children and the
elderly, persons with disabilities (PWDs, physical, mental, emotional, etc.),
ethnicity and indigenous peoples, people with differing lifestyles/preferences,
religion, etc.
The foregoing are only basic architectural plan and design features of the building.
Should the DPWH IRR on sustainable building design be promulgated, the RLA
shall also be responsible for a number of sustainable building features, as well as
features that address issues and concerns pertaining to climate change adaptation
and disaster resilience. The RLA's description of the proposed building’s
sustainable design features must necessarily include descriptions of the embodied
energy levels of construction and finishing materials proposed for use in the
building, carbon footprint calculation for the building and its users over a certain
period of time, energy and water conservation features (to include rainwater
harvesting if possible), solid waste management provisions (collection, storage,
recycling, reuse, disposal), etc.
The architectural permit application must clearly show that the building fully
satisfies all the spatial requirements and all the applicable development controls
(DCs). To be sure that only RLAs shall be responsible for architectural permits and
their support documents, the author (signatory) of the architectural permit
application support documents or his/her duly designated representative should
be present (or available through electronic means) to defend the contents of the
documents when the same are reviewed by RLAs who should also be the ones in
charge of the architectural divisions of LGU OBOs i.e. full compliance with Section
35 of R.A. No. 9266 (The Architecture Act of 2004).
The architectural permit application must also show the calculations for
architectural life safety code compliances, particularly those mandated under R.A.
No. 9514 (The 2008 Fire Code of the Philippines/FCP and its 2009 IRR). Also for
inclusion is the satisfaction of the mandated compliances with B.P. Blg. 344
(Accessibility Law of 1983) particularly with respect to parking slots, ramps,
elevators and toilets for persons with disabilities (PWDs). Additionally, the
pertinent information on architectural design features that address specific user
needs and sensitivities must be included e.g. gender, age, ethnicity, religion, etc. as
well as urban design features e.g. including lists of street furniture, way-finding
provisions and directional signages as well as statements of the proposed
treatments of transitional spaces between the public domain (e.g. RROW) and the
building grounds and enclosed building spaces.
3-43
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
4.2.3
Gravity Loads
This section shall apply to designing the gravity loads as specified in NSCP Section
204 – Section 205.
4.2.4
4.2.5
Gravity loads are the weights of structural, non-structural elements, and expected
weight of occupants that is applied to structures as downward forces.
Dead Load
Dead loads consist of the permanent weights and include the weight of columns,
beams and girders, floor slab, roofing, walls, windows, plumbing, electrical
fixtures, finishes and fixed equipment. The minimum densities for design loads
from materials are shown in Table 4-1. The minimum values for dead loads in lowrise buildings are shown in Table 4-2.
Live Load
Live load is determined by the function and occupancy of the building. Loads
include the weights of temporarily placed items on the structure such as
furnishings, human occupants and construction and maintenance activities. The
standards in designing the live load of a building are provided in NSCP Section
205.
All loads shall be the maximum loads expected by the intended use or occupancy
and not be less than the loads required by this section. Live loads are provided in
Tables 4-3, 4-4 and 4-5.
4-3
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 4-3
Minimum Uniform and Concentrated Live Loads
Use or Occupancy
Use or Occupancy
Uniform Load
1
Concentrated
Load
Category
Category
Description
kPa
kN
1. Access floor systems
Office use
2.4
9.0
20. Sidewalks and driveways
Computer use
4.8
9.02
21. Storage
--
7.2
0
Fixed seats
2.9
0
Movable seats
4.8
0
Lobbies and platforms
4.8
0
23. Pedestrian bridges and walkways
Source: NSCP, 2010.
2. Armories
3. Theaters, assembly areas3 and
auditoriums
2
22. Stores
Stages areas
7.2
0
4. Bowling alleys, poolrooms and
similar recreational areas
--
3.6
0
5. Catwalk for maintenance access
--
1.9
1.3
6. Cornices and marquees
--
4
3.6
0
7. Dining rooms and restaurants
--
4.8
0
5
8. Exit facilities5
--
4.8
06
6
General storage and/or repair
4.8
--
Private or pleasure-type motor
vehicle storage
1.9
--7
Wards and rooms
1.9
4.52
Laboratories & operating
rooms
2.9
4.5
Corridors above ground floor
3.8
4.5
Reading rooms
2.9
4.52
Stack rooms
7.2
4.52
Corridors above ground floor
3.8
4.5
Light
6.0
9.02
Heavy
12.0
13.42
Call Centers & BPO
2.9
9.0
Lobbies & ground floor
corridors
4.8
9.0
Offices
2.4
9.02
Building corridors above
ground floor
3.8
9.0
Press rooms
7.2
11.02
Composing and linotype rooms
4.8
9.02
Basic floor area
1.9
06
Exterior balconies
2.94
0
Decks
1.9
0
9. Garages
10. Hospitals
11. Libraries
12. Manufacturing
13. Office
14. Printing plants
15. Residential8
4
1
3
7
7
2
Storage
1.9
0
--
--
--
17. Reviewing stands, grandstands,
Bleachers, and folding and
telescoping seating
--
4.8
0
Same as area served or
Occupancy
--
--
Classrooms
1.9
4.52
Corridors above ground floor
3.8
4.5
19. Schools
2
4
16. Restrooms9
18. Roof decks
4-6
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
8
9
Uniform Load1
Concentrated
Load
Description
kPa
kN
Ground floor corridors
4.8
4.5
Public access
12.0
--7
Light
6.0
--
Heavy
12.0
--
Retail
4.8
4.52
Wholesale
6.0
13.42
--
4.8
--
Notes for Table 4-3
See NSCP Section 205.5 for live load reductions
See NSCP Section 205.3.3, first paragraph, for area of load application.
Assembly areas include such occupancies as dance halls, drill rooms, gymnasiums, playgrounds,
plazas, terraces and similar occupancies that are generally accessible to the public.
For special-purpose roofs, see NSCP Section 205.4.4.
Exit facilities shall include such uses as corridors serving an occupant load of 10 or more persons,
exterior exit balconies, stairways, fire escapes
Individual stair treads shall be designed to support a 1.3 kN concentrated load placed in a position
that would cause maximum stress. Stair stringers may be designed for the uniform load set forth in
the table
See NSCP Section 205.3.3, second paragraph, for concentrated loads. See Table 4-4 for vehicle
barriers
Residential occupancies include private dwellings, apartments and hotel guest rooms.
Restroom loads shall not be less than the load for the occupancy with which they are associated,
but need not exceed 2.4 kPa.
4-7
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 4-4
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Vertical members of storage racks shall be protected from impact forces of operating equipment, or
racks shall be designed so that failure of one vertical member will not cause collapse of more than
the bay or bays supported by that member.
12
The 1.1 kN load is to be applied to any single fire sprinkler support point but not simultaneously to
all support joints.
Special Loads1
Use or Occupancy
Category
Vertical Load
Lateral Load
kPa
kPa
1. Construction, public access at site
(live load)
Walkway
7.2
-
Canopy
7.2
-
2. Grandstands, reviewing, stands
bleachers, and folding and
telescoping seating (live load)
Seats and footboards
1.75
See Note 3
3. Stage accessories (live load)
4. Ceiling framing (live load)
5. Partitions and interior walls
Description
11
Table 4-5
METHOD 2
METHOD 1
Tributary Area (m )
2
Catwalks
1.9
-
Follow spot, projection and
control rooms
2.4
-
Over stages
1.0
-
All uses except over
stages
0.54
-
-
6. Elevators and dumbwaiters (dead
and live loads)
ROOF SLOPE
0 to 20
20 to 60
Over 60
Uniform
Load2
(kPa)
Rate of
reduction,
r
Maximum
Reduction R
(percentage)
Uniform Load (kPa)
1. Flat or rise less than 4 units
vertical in 12 units horizontal
(33.3% slope). Arch and dome
with rise less than one-eighth of
span
1.00
0.75
0.60
1.00
0.08
40
2. Rise 4 units vertical to less than
12 units vertical in 12 units
horizontal (33.3% to less than
100% slope). Arch and dome
with rise one-eighths of span
0.75
0.70
0.60
0.75
0.06
25
No reduction permitted
3
-
0.25
2× total loads
-
7. Cranes (dead and live loads)
Total load including impact
increase
1.25 x total load5
0.10× total load6
8. Balcony railings and guardrails
Exit facilities serving an
occupant load greater than
50
-
0.75 kN/m7
3. Rise 12 units vertical in 12 units
horizontal (100% slope) and
greater. Arch or dome with rise
three-eighth of span or greater
0.60
0.60
0.60
0.60
Other than exit facilities
-
0.30 kN/m7
4. Awnings except cloth covered.4
0.25
0.25
0.25
0.25
Components
-
1.2
0.50
0.50
0.50
0.50
-
-
27 kN
5. Greenhouses, lath houses and
agricultural buildings.5
See Note 10
See Note 10
Total loads11
See NSCP Table
208-12
1.1 kN plus weight of
water-filled pipe12
See NSCP Table
208-12
9. Vehicle barriers
10. Handrails
11. Storage racks
Over 2.4 m high
12. Fire sprinkler structural support
-
8
9
Source: NSCP, 2010
Notes for Table 4-5
1
For special-purpose roofs, see NSCP Sections 205.4.4.
2
See NSCP Sections 205.5 and 205.6 for live-load reductions. The rate of reduction r in NSCP
Equation 205-1 shall be as indicated in the table. The maximum reduction, R, shall not exceed
the value indicated in the table.
3
A flat roof is any roof with a slope less than 1/4 unit vertical in 12 units horizontal (2% slope). The
live load for flat roofs is in addition to the ponding load required by NSCP Section 206.7.
4
See definition in NSCP Section 202.
5
See NSCP Section 205.4.4 for concentrated load requirements for greenhouse roof members.
Source: NSCP, 2010
Notes for Table 4-4:
The tabulated loads are minimum loads. Where other vertical by this code or required by the design
would cause greater stresses, they shall be used. Loads are in kPa unless otherwise indicated in
the table.
2
Unit is kN/m.
3
Lateral sway bracing loads of 350 N/m parallel and 145 N/m perpendiculars to seat and footboards.
4
Does not apply to ceilings that have sufficient total access from below, such that access is not
required within the space above the ceiling. Does not apply to ceilings if the attic areas above the
ceiling are not provided with access. This live load need not be considered as acting simultaneously
with other live loads imposed upon the ceiling framing or its supporting structure.
5
The impact factors included are for cranes with steel wheels riding on steel rails. They may be
modified if substantiating technical data acceptable to the building official is submitted. Live loads on
crane support girders and their connections shall be taken as the maximum crane wheel loads. For
pendant-operated traveling crane support girders and their connections, the impact factors shall be
1.10.
6
This applies in the direction parallel to the runway rails (longitudinal). The factor for forces
perpendicular to the rail is 0.20 x the transverse traveling loads (trolley, cab, hooks and lifted loads).
Forces shall be applied at top of rail and may be disturbed among rails of multiple rail cranes and
shall be distributed with due regard for lateral stiffness of the structures supporting these rails.
7
A load per lineal meter (kN/m) to be applied horizontally at right angles to the top rail.
8
Intermediate rails, panel fillers and their connections shall be capable of withstanding a load of 1.2
kPa applied horizontally at right angles over the entire tributary area including openings and spaces
between rails. Reactions due to this loading need not be combined with those of Footnote 7.
9
A horizontal load in kN applied at right angles to the vehicle barrier at a height of 450 mm above the
parking surface. The force may be distributed over a 300-mm-square area.
10
The mounting of handrails shall be such that the completed handrail and supporting structure are
capable of withstanding a load of at least 890 N applied in any direction at any point on the rail.
These loads shall not be assumed to act cumulatively with Item 9.
1
4-8
Minimum Roof Live Loads 1
4.2.6
Other Minimum Loads
Other minimum loads to be considered are:




4.2.7
Impact loads (NSCP Section 206.3). This is the dynamic effect on a body as
induced by the contact of moving load or operating equipment. Impact is
expressed as a percentage increase in the load when at rest.
Crane Loads (NSCP Section 206.9).
Heliport and Helistop Landing Areas (NSCP Section 206.10).
Soil load.
Wind Load
The most significant consideration in the computation of wind load is the location
of the structure. Areas facing the Pacific Ocean are analyzed against a maximum
wind design velocity of 250 kph and are designated as Zone 1, consistent with the
strong tropical storms that originate from this area. The wind from Zone 1 wind
weakens to 200 kph in the area designated as Zone 2. This wind exits at the
4-9
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Philippine Sea with a velocity of 150 kph in the area designated as Zone 3. Table 47 identifies specific provinces under each zone and a quick reference map is
available on NSCP Figure 207-24.
NSCP also requires the use of the occupancy importance factor, a magnifier that
increases (or reduces) the wind load. A magnifies of 15% is used for many
structures most needed during emergencies, structures that can have many
occupants in one area and facilities that house dangerous materials that may
cause additional harm to the populace if toxins are released due to structural
failure. A low of -15% is used for facilities that are not usually used as human
shelter. Table 4-6 describes occupancy/function of structure, while Table 4-9
factor the numerical value for occupancy importance factor.
Analysis of structures should include a separate consideration for the Main Wind
Force Resisting System (MWFRS) which is the assembly of structural members
that provide the overall reliability against wind forces, and the components and
cladding elements which are individual parts of the structure that cover and
complete the skeletal MWFRS.
The design wind load for buildings, including MWFRS and component and
cladding elements, shall be determined using the following methods.
Method 1: Simplified Procedure
The steps in accordance with are:
1. The basic wind Speed, V, in accordance with NSCP Section 207.5.4 shall be
determined assuming the wind can come from any horizontal direction.
2. Determine the importance factor, Iw, in accordance with NSCP Section 207.5.5.
3. Determine the exposure category in accordance with NSCP Section 207.5.6.
4. Determine the height and exposure adjustment coefficient, λ, shall be
determined from NSCP Figures 207-2 and 207-3.
5. For the Main Wind-Force Resisting System: Determine Ps for the horizontal
pressures which is the combination of the windward and leeward net
pressures and shall be determined by the following equation:
ps = λK zt Iw ps9
The net design wind pressures, pnet, for the components and cladding of buildings
shall be determined by the following equation:
where:
Kzt
=
Iw
=
ps9
4-10
Pnet = λK zt Iw pnet9
=
topographic factor as defined in NSCP Section 207.5.7
simplified design wind pressure for Exposure B at h=9 m
1.0 from NSCP Figure 207-3, kPa
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Pnet9
=
Iw
=
net design wind pressure for Exposure B at h=9 m
1.0 from NSCP Figure 207-3, kPa
Method 2: Analytical Procedure
Analytical procedure shall be used for buildings or structures that do not satisfy
the conditions for using the simplified procedure provided that the building or
structure is regular-shaped as defined in NSCP Section 207.5 and does not have
response wind loading, vortex, shedding, instability due to galloping or flutter, or
does not have a site location for which channeling effect or buffering in the wake
of upwind obstructions warrant special consideration as stated in NSCP Section
207.5.1.
The steps of analytical procedure in accordance with NSCP Section 207.5.3 are:
1. Determine the basic wind speed V and wind directionality factor K d in
accordance with NSCP Section 207.5.4 and NSCP Table 207-2 respectively.
2. Determine the importance factor, Iw, in accordance with NSCP Section 207.5.5.
3. Determine the exposure category or exposure coefficient Kz or Kh, as
applicable for each wind direction in accordance with NSCP Section 207.5.6.
4. Determine the topographic factor Kzt in accordance with NSCP Section 207.5.7.
5. Determine the gust effect Factor G or Gf, as applicable in accordance with NSCP
Section 207.5.8.
6. Determine the enclosure classification in accordance with NSCP Section
207.5.9.
7. Determine the Internal Pressure coefficients, GCpi in accordance with NSCP
Section 207.5.11.1.
8. Determine the External Pressure coefficient Cp or GCpf or force coefficients Cf,
as applicable in accordance with NSCP Section 207.5.11.2 or NSCP Section
207.5.11.3, respectively.
9. Determine the velocity pressure qz or qh, as applicable, in accordance with
NSCP Section 207.5.10. The velocity pressure, qz evaluated at height z shall be
calculated by the following equation:
where:
Kd
Kz
Kzt
qz = 47.3 x 10−6 K z K zt K d V 2 Iw
=
wind directionality factor in NSCP Table 207-2
=
topographic factor as defined in NSCP Section 207.5.7
=
velocity pressure exposure coefficient evaluated at height z
10. Determine the wind load p or F in accordance with NSCP Sections 207.5.12,
207.5.13, 207.5.14, and 207.5.15 as applicable. The design wind pressure is
given by the following equations:
For rigid buildings of all heights:
4-11
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
For flexible buildings:
q
where:
q
=
=
qi
=
qi
=
G
=
Cp
(GCpi)
=
=
p = qGCp − qi (GCpi )
qz for windward walls evaluated at height z above the ground
4-12
Occupancy Category
I Essential Facilities
qh for windward walls, leeward walls, and roofs of enclosed
buildings and fpr negative internal pressure evaluation in
partially enclosed buildings
qz for positive internal pressure evaluation in partially enclosed
buildings where height is defined as the level at the highest
opening in the building that could affect the positive internal
pressure
gust effect factor from NSCP Section 207.5.8 (See discussion in
NSCP Section 207.5.12.2)
external pressure coefficient from NSCP Figure 207-6 or 207-8
II Hazardous Facilities
III Special Occupancy Structures
internal pressure coefficient from NSCP Figure 207-5; q and qi
shall be evaluated using exposure defined in NSCP Section
207.5.6.3. Pressure shall be applied simultaneously on windward
and leeward walls and on roof surface as defined in NSCP Figures
207-6 and 207-8.
p = qh[(GCpf) – (GCpi)]
=
(GCpi )
= internal pressure coefficient from NSCP Figure 207-5
=
Occupancy Category
qh for leeward walls, side walls and roofs evaluated at height h
qh
(GCpf )
Table 4-6
p = qGf Cp − qi (GCpi )
Alternatively, design wind pressures for the MWFRS of low-rise buildings shall be
determined by the following equation:
where:
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Occupancy or Function of Structure
Occupancy having surgery and emergency treatment
areas
Fire and police stations
Garage and shelters for emergency vehicles and
emergency aircraft
Structures and shelters in emergency preparedness
centers
Aviation control towers
Structures and equipment in communication centers and
other facilities required for emergency response
Facilities for standby power-generating equipment for
Category I structures
Tanks or other structures containing housing or supporting
water or other fire-suppression material or equipment
required for the protection of Category I, II or III structures
Public school buildings
Hospitals
Designated evacuation centers
Occupancies and structures housing or supporting toxic or
explosive chemicals or substances
Non-building structures storing, supporting or containing
quantities of toxic or explosive substances
Single-story school buildings
Buildings with an assembly room with an occupant
capacity of 1,000 or more
Educational buildings such as museums libraries,
auditorium with a capacity of 300 or more students
Buildings used for college or adult education with a
capacity of 500 or more students
Institutional buildings with 50 or more incapacitated
patients, but not included in Category I
Mental hospitals, sanitariums, jails, prison and other
buildings where personal liberties of inmates are similarly
restrained
All structures with an occupancy of 5,000 or more persons
Structures and equipment in power-generating stations,
and other public utility facilities not included in Category I
or Category II, and required for continued operation
IV Standard Occupancy Structures
All structures housing occupancies or having functions not
listed in Category I, II or III and Category V
V Miscellaneous Structures
Private garages, carports, sheds and fences over 1.5 m
high
velocity pressure evaluated at mean roof height h using
exposure defined in NSCP Section 207.5.6.3
external pressure coefficient from NSCP Figure 207-10
4-13
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 4-7
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Wind Zone for the Different Provinces of the Philippines
Zone Classification (Basic
Wind Speed)
Table 4-10
Provinces
Height above Ground
Level, z (m)
Zone 1 (V=250kph)
Albay, Aurora, Batanes, Cagayan, Camarines Norte, Camarines
Sur, Catanduanes, Eastern Samar, Isabela, Northern Samar,
Quezon, Quirino, Samar, Sorsogon
Zone 2 (V=200 kph)
Abra, Agusan del Norte, Agusan del Sur, Aklan, Antique, Apayao,
Bataan, Batangas, Benguet, Biliran, Bohol, Camiguin, Capiz,
Cavite, Cebu, Compostela Valley, Davao Oriental, Guimaras,
Ifugao, Ilocos Norte, Ilocos Sur, Iloilo, Kalinga, La Union, Laguna,
Leyte, Marinduque, Masbate, Misamis Oriental, Mountain
Province, National Capital Region, Negros Occidental, Negros
Oriental, Nueva Ecija, Nueva Vizcaya, Occidental Mindoro,
Oriental Mindoro, Pampanga, Pangasinan, Rizal, Romblon,
Siquijor, Southern Leyte, Surigao del Norte, Surigao del Sur,
Tarlac, Zambales
Zone 3 (V=150 kph)
Table 4-8
Basilan, Bukidnon, Davao del Norte, Davao del Sur, Lanao del
Norte, Lanao del Sur, Maguindanao, Misamis Occidental, North
Cotabato, Palawan, Sarangani, South Cotabato, Sultan Kudarat,
Sulu, Tawi-tawi, Zamboanga del Norte, Zamboanga del Sur,
Zamboanga Sibugay
Wind Directionality Factor, K d
Structural Type
Directionality Factor Kd*
Buildings
Main Wind Force Resisting System
Components and Cladding
0.85
0.85
Arched Roofs
0.85
Chimneys, Tanks, and Similar Structures
Square
Hexagonal
Round
0.90
0.95
0.95
Solid Signs
0.85
Open Signs and Lattice Framework
0.85
Trussed Towers
Triangular, square, rectangular
All other costs sections
1
0.85
0.95
1.
B
D
Case 2
Cases 1 & 2
Cases 1 & 2
0-4.5
0.70
0.57
0.85
1.03
6
0.70
0.62
0.90
1.08
7.5
0.70
0.66
0.94
1.12
9
0.70
0.70
0.98
1.16
12
0.76
0.76
1.04
1.22
15
0.81
0.81
1.09
1.27
18
0.85
0.85
1.13
1.31
21
0.89
0.89
1.17
1.34
24
0.93
0.93
1.21
1.38
27
0.96
0.96
1.24
1.40
30
0.99
0.99
1.26
1.43
36
1.04
1.04
1.31
1.48
42
1.09
1.09
1.36
1.52
48
1.13
1.13
1.39
1.55
54
1.17
1.17
1.43
1.58
60
1.20
1.20
1.46
1.61
75
1.28
1.28
1.53
1.68
90
1.35
1.35
1.59
1.73
105
1.41
1.41
1.64
1.78
120
1.47
1.47
1.69
1.82
135
1.52
1.52
1.73
1.86
150
1.56
1.56
1.77
1.89
Case 1: a. All components and cladding.
Case 2: a: All main wind force resisting systems in buildings except those in low-rise buildings
designed using NSCP Figure 207-10.
Occupancy Category
Description
IW
I
Essential
1.15
II
Hazardous
1.15
III
Special Occupancy
1.15
IV
Standard Occupancy
1.00
V
Miscellaneous
0.87
b. All main wind force resisting systems in other structures.
2.
The velocity pressure exposure coefficient Kz may be determined from the following formula:
For 𝓏𝓏 < 4.5 m
For 4.5 m ≤ 𝓏𝓏 ≤ 𝓏𝓏g
3.
4.
5.
4-14
C
Case 1
b. Main wind force resisting system in low-rise buildings designed using NSCP Figure
207-10.
Importance Factor, Iw (Wind Loads)
refer Table 4-6 for types of occupancy under each category.
Exposure (Note 1)
Notes for Table 4-10:
* Directionality Factor Kd has been calibrated with combinations of loads specified in NSCP Section
203. This factor shall only be applied when used in conjunction with load combinations specified
in NSCP Section 203.3 and 203.4.
Table 4-9
Velocity Pressure Exposure Coefficients1 , Kh and Kz
2/a
4.5
K 𝒵𝒵 = 2.01 ( )
𝓏𝓏g
𝓏𝓏
2/a
K 𝓏𝓏 = 2.01 ( )
𝓏𝓏g
Note: 𝓏𝓏 shall not be taken less than 9.0 m for Case 1 in exposure B.
α and 𝓏𝓏g are tabulated in NSCP Table 207-5.
Linear interpolation for intermediate values of height 𝓏𝓏 is acceptable.
Exposure categories are defined in Section 207.5.6.
4-15
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 4-11
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Simplified Design Base Shear
Terrain Exposure Constants
Exposure
B
C
D
a
7.0
9.5
11.5
Zg (m)
365
275
215
𝑎𝑎̂
1/7
1/9.5
1/11.5
𝑏𝑏̂
0.84
1.00
1.07
𝑎𝑎̅
1/4
1/6.5
1/9
𝑏𝑏̅
0.45
0.65
0.80
C
0.30
0.20
0.15
D0
0.010
0.005
0.003
ℓ(m)
100
150
200
1/3
1/5
1/8
*zmin (m)
9
4.5
2.10
ℰ̅
* zmin = minimum height used to ensure that the equivalent height 𝓏𝓏̅ is or 2/3 h for trussed towers,
the height of the transmission cable above ground, or 0.6h for buildings and other structure.
For ≤ zmin 𝓏𝓏̅ shall be taken as zmin.
Method 3 – Wind Tunnel Procedure
4.2.8
NSCP Section 207.5.2 of NSCP explains that this method is used when structures
do not meet the provisions of NSCP Section 207.5.1 or have unusual shapes or
response characteristics.
Seismic Load
Other than Mainland Palawan, the Sulu, Tawi-Tawi group of Islands, the
Philippines is situated in a highly seismic zone categorized as Zone 4 similar to
those of California, Japan, China, Mexico etc. Structures and portions thereof shall
be designed and constructed to resist the effects of seismic ground motions as
provided in NSCP Section 208. Two methods of analysis are available, namely:
Static Analysis and Dynamic Analysis. The latter method may be used for any
structure but is a must for structures described in Tables 4-23 and 4-24 and NSCP
Section 208.4.8.3.
Minimum Design Lateral Forces (NSCP Section 208.5)
The section discusses computation of lateral loads and in particular explains the
static lateral load, load distribution as well as the calculation for drift.
NSCP Section 208.5.2.3.1 describes the Minimum Design Lateral Forces and its
Related Effects.
This approach is applicable to single family dwellings not more than three floors
excluding the basement and also other structures not more than two stories
excluding basement. The approach falls under seismic occupancy importance
factor =1 under standard and miscellaneous occupancies (Refer Table 4-12).
where:
V
=
I
=
seismic occupancy importance factor in Table 4-12
R
=
Ca, Cv
=
numerical equivalent to account for the inherent
overstrength of the adopted structural system. (Refer Table
4-19 to 4-22)
seismic coefficients (Refer Tables 4-15 and 4-16
respectively)
T
=
fundamental period of vibration (Method A)
W
=
Na, Nv
𝐶𝐶𝑡𝑡
=
=
=
=
Table 4-12
𝐶𝐶 𝐼𝐼
𝑉𝑉 = 𝑣𝑣 𝑊𝑊
𝑅𝑅𝑅𝑅
≤
2.5𝐶𝐶𝑎𝑎 I
𝑉𝑉 =
R
≥
0.8Z𝑁𝑁𝑣𝑣 I
𝑉𝑉 =
R
≥
3𝐶𝐶𝑎𝑎
W
R
base shear
NSCP Section 208.5.2 provides us with the static force procedure.
NSCP Section 208.5.2.1 provides calculation of the design base shear by:
W
𝑉𝑉 = 0.11𝐶𝐶𝑎𝑎 𝐼𝐼 𝑊𝑊
W (for zone 4)
1
4-16
V=
total dead load including permanent equipment loads and a
portion of the live load if the Structural Engineer finds it
necessary. A minimum of 25% of the floor live load shall also
apply for storage facilities
near source Factors (Refer Tables 4-17 and 4-18
respectively)
𝑇𝑇 = 𝐶𝐶𝑡𝑡 (ℎ𝑛𝑛 )3/4
0.0853 for steel moment-resisting frame
0.0731 for reinforced concrete moment resisting frames and
eccentrically braced frames.
0.0488 for all other buildings
Seismic Importance Factor
Occupancy Category1
Seismic Importance Factor,
I
Seismic Importance2
Factor, Ip
I.
Essential Facilities3
1.50
1.50
II.
Hazardous Facilities
1.25
1.50
III.
Special Occupancy
Structures4
1.00
1.00
IV.
Standard Occupancy
Structure4
1.00
1.00
V.
Miscellaneous Structures
1.00
1.00
See Table 4-6 for occupancy listing.
4-17
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
2
3
4
The limitation of Ip for panel connections in NSCP Section 208.8.2.3 shall be 1.0 for the entire
connector
Structural observation requirements are given in NSCP Section 107.9.
For anchorage of machinery and equipment required for life-safety systems, the value of Ip shall
be taken as 1.5.
Table 4-13
Soil Profile
Name/ Generic
Description
0.32Nv
SB
0.20
0.40Nv
Average Soil Properties for Top 30 m of Soil Profile
SC
0.32
0.56Nv
Shear Wave
Velocity, Vs
(m/s)
SD
0.40
0.64Nv
SE
0.64
0.96Nv
SPT, N
(blows/ 300 mm)
Undrained
Shear
Strength SU
(kPa)
SF
1
Rock
760 to 1500
SC
Very Dense Soil
and Soft Rock
360 to 760
> 50
> 100
SD
Stiff Soil Profile
180 to 360
15 to 50
50 to 100
SE1
Soft Soil Profile
<180
< 15
< 50
> 1500
Table 4-17
Near-Source Factor Na1
Seismic Source Type
Soil Profile Type SE also includes any soil profile with more than 3.0 m of soft clay defined as a
soil with plasticity index, PI> 20, wmc ≥ 40 percent and su< 24 kPa. The Plasticity Index, PI, and
the moisture content, wmc, shall be determined in accordance with approved national standards.
Seismic Source Type1
See Footnote 1
Site-specific geotechnical investigation and dynamic site response analysis shall be performed to
determine seismic coefficient
Soil Requiring Site-specific Evaluation. See NSCP Section 208.4.3.1
Seismic Source Description
A
Faults that are capable of producing large
magnitude events and that have a high
rate of seismic activity.
B
All faults other than Types A and C.
≥ 10 km
A
1.2
1.0
B
1.0
1.0
C
1.0
1.0
C
Faults that are not capable of producing
large magnitude earthquakes and that
have a relatively low rate of seismic
activity
Near-Source Factor, Nv1
Seismic Source
Definition
Seismic Source Type
Maximum Moment
Magnitude, M
M ≥ 7.0
6.5 ≤ M < 7.0
M < 6.5
Subduction sources shall be evaluated on a site-specific basis.
Closest Distance to Known Seismic Source2
≤ 5 km
Table 4-18
Seismic Source
Type
Closest Distance to Known Seismic Source2
≤ 5 km
10 km
≥15 km
A
1.6
1.2
1.0
B
1.2
1.0
1.0
C
1.0
1.0
1.0
Notes for Tables 4-17 and 4-18
1
The Near-Source Factor may be based on the linear interpolation of values for distances other
than those shown in the table.
2
The closest distance to seismic source shall be taken as the minimum distance between the site
and the area described by the vertical projection of the source on the surface (i.e. surface
projection of fault plane). The source projection need not include portions of the source at deptsh
of 10 km or greater. The largest value of the Near-source Factor considering all sources shall be
used for design.
Seismic Coefficient, Ca
Soil Profile Type
Seismic Zone Z
Z = 0.2
Z=0.4
SA
0.16
0.32Na
SB
0.20
0.40Na
SC
0.24
0.40Na
SD
0.28
0.44Na
SE
0.34
0.44Na
SF
4-18
Z=0.4
0.16
SB
Table 4-15
Seismic Zone Z
Soil Profile Type
Z=0.2
Hard Rock
Table 4-14
Seismic Coefficient, Cv
SA
SA
SF
1
Table 4-16
Soil Profile Type
Soil Profile
Type
1
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
See Footnote 1 of Table 4-16
4-19
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 4-19
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Earthquake – Force Resisting Structural Systems of Concrete
Basic Seismic-Force Resisting System
R
Ω0
Table 4-21
System Limitation and
Building Height Limitation
by Seismic Zone, m
Zone 2
5.5
 Heavy timber braced frames where
bracing carries gravity load
2.8
2.2
 Light-framed walls with wood shear
panels walls for structures three
stories or less
NA
NA
 All other light framed walls
NA
NA
 Heavy timber-braced frames where
bracing carries gravity load
2.8
2.2
NL
20
2.8
NL
 Light-framed walls with shear panels:
wood structural panel walls for
structures three stories or less
6.5
2.8
NL
20
 Ordinary heavy timber-braced frames
5.6
NL
20
20
2.2
NL
20
Earthquake-Force-Resisting Structural Systems of Masonry
R
Ω0
System Limitation and
Building Height
Limitation by Seismic
Zone, m
Zone 2
Zone 4
A. Bearing Wall Systems
4.5
2.8
NL
50
5.5
2.8
NL
50
B. Building Frame Systems
 Masonry shearwalls
C. Moment-Resisting Frame
Systems
 Masonry moment-resisting wall
frames (MMRWF)
6.5
2.8
NL
50
D. Dual Systems
4-20
Ω0
Zone 2
Zone 4
 Light steel-framed bearing walls with tension-only bracing
2.8
2.2
NL
20
 Braced frames where bracing carries gravity load
4.4
2.2
NL
50
 Light framed walls sheathed with wood structural panels
rated for shear resistance or steel sheets
4.5
2.8
NL
20
 Light-framed walls with shear panels of all other light
materials
4.5
2.8
NL
20
 Light-framed wall systems using flat strap bracing
2.8
2.2
NL
NP
 Steel eccentrically braced frames (EBF), moment-resisting
connections at columns away from links
8.5
2.8
NL
30
 Steel eccentrically braced frames (EBF), non momentresisting connections at columns away from links
6.0
2.2
NL
30
 Special concentrically braced frames (SCBF)
6.0
2.2
NL
30
 Ordinary concentrically braced frames (OCBF)
3.2
2.2
NL
NP
 Light-framed walls sheathed with wood structural panels/
sheet steel panels
6.5
2.8
NL
20
 Light frame walls with shear panels of all other materials
2.5
2.8
NL
NP
 Buckling-restrained braced frames (BRBF), non
moment-resisting beam-column connection
7
2.8
NL
30
 Buckling-restrained braced frames, moment-resisting
beam-column connections
8
2.8
NL
30
 Special steel plate shear walls (SPSW)
7
2.8
NL
30
 Special moment-resisting frame (SMRF)
8.0
3
NL
NL
 Intermediate steel moment frames (IMF)
4.5
3
NL
NP
 Ordinary moment frames (OMF)
3.5
3
NL
NP
 Special truss moment frames (STMF)
6.5
3
NL
NP
 Special composite steel and concrete moment frames
8
3
NL
NL
 Intermediate composite moment frames
5
3
NL
NP
 Composite partially restrained moment frames
6
3
48
NP
 Ordinary composite moment frames
3
3
NP
NP
 Steel eccentrically braced frames
8
2.8
NL
NL
 Special steel concentrically braced frames
7
2.8
NL
NL
 Composite steel and concrete eccentrically braced frame
8
2.8
NL
NL
 Composite steel and concrete concentrically braced frame
6
2.8
NL
NL
 Composite steel plate shear walls
7.5
2.8
NL
NL
 Buckling-restrained braced frame
8
2.8
NL
NL
 Special steel plate shear walls
8
2.8
NL
NL
 Masonry shear wall steel OMRF
4.2
2.8
NL
50
 Steel EBF with steel SMRF
8.5
2.8
NL
NL
B. Building Frame Systems
B. Building Frame Systems
 Masonry shear walls
R
System Limitation and
Building Height Limitation
by Seismic Zone, m
A. Bearing Wall Systems
 Light-framed walls with shear panels:
wood structural panel walls for
structures three stories or less
Basic Seismic-Force Resisting
System
Basic Seismic-Force Resisting System
Zone 4
A. Bearing Wall Systems
Table 4-20
Earthquake-Force-Resisting Structural Systems of Steel
 Masonry shear walls with SMRF
5.5
2.8
NL
50
 Masonry shear walls with steel
OMRF
4.2
2.8
NL
50
 Masonry shear walls with
concrete IMRF
4.2
2.8
NL
NP
 Masonry shear walls with
masonry MMRWF
6.0
2.8
NL
50
C. Moment-Resisting Frame Systems
D. Dual Systems
4-21
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Basic Seismic-Force Resisting System
R
Ω0
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
System Limitation and
Building Height Limitation
by Seismic Zone, m
Zone 2
Zone 4
 Steel EBF with steel OMRF
4.2
2.8
NL
50
 Special concentrically braced frames with steel SMRF
7.5
2.8
NL
NL
 Special concentrically braced frames with steel OMRF
4.2
2.8
NL
50
 Special steel concentrically braced frame
6
2.8
NL
NP
 Composite steel and concrete concentrically braced frame
5.5
2.8
NL
NP
 Ordinary composite braced frame
3.5
2.8
NL
NP
 Ordinary composite reinforced concrete shear walls with
steel elements
5
2.8
NL
NP
 Special steel moment frames
2.2
2.0
10
10
 Intermediate steel moment frames
1.2
2.0
10
NP
 Ordinary steel moment frames
1.0
2.0
10
NP
 Cantilevered column elements
2.2
2.0
NL
10
3
3
NL
NP
E. Dual System with Intermediate Moment Frames
F. Cantilevered Column Building Systems
G. Steel Systems not Specifically Detailed for Seismic
Resistance, Excluding Cantilever Systems
Table 4-22
Earthquake-Force-Resisting Structural Systems of Wood
Basic Seismic-Force Resisting System
A.
R
Ω0
System Limitation and
Building Height
Limitation by Seismic
Zone, m
Zone 2
Zone 4
Bearing Wall Systems
 Light-framed walls with shear panels: wood structural
panel walls for structures three stories or less
5.5
2.8
NL
20
 Heavy timber braced frames where bracing carries gravity
load
2.8
2.2
NL
20
 Light-framed walls with wood shear panels walls for
structures three stories or less
NA
NA
 All other light framed walls
NA
NA
 Heavy timber-braced frames where bracing carries gravity
load
2.8
2.2
NL
20
 Light-framed walls with shear panels: wood structural
panel walls for structures three stories or less
6.5
2.8
NL
20
 Ordinary heavy timber-braced frames
5.6
2.2
NL
20
B. Building Frame Systems
Vertical Distribution of Force (NSCP Section 208.5.5)
The Base Shear (V) shall be distributed over the structure height using the formula:
n
V = 𝐹𝐹𝑡𝑡 + ∑ 𝐹𝐹𝑡𝑡
i=1
Where 𝐹𝐹𝑡𝑡 is the whip effect applied at level n in addition to Fn
𝐹𝐹𝑡𝑡 = 0.07TV
𝐹𝐹𝑡𝑡 need not exceed 0.25V and is considered nil when the fundamental period T is
0.7 second or less.
The remaining force "V-𝐹𝐹𝑡𝑡 " shall be distributed over the entire height of the
structure using the formula
where:
Fx,wx,hx
Fi,wi,hi
=
=
(𝑉𝑉 − 𝐹𝐹𝑡𝑡 )𝑤𝑤𝑥𝑥 ℎ𝑥𝑥
∑𝑛𝑛𝑖𝑖=1 𝑤𝑤𝑖𝑖 ℎ𝑖𝑖
level 'x' lateral force F, floor weight 'w' and height 'h' from the
base(ground).
force weight and height of level 'i'
Horizontal Distribution of Shear (NSCP Section 208.5.6)
Forces 𝐹𝐹𝑡𝑡 , 𝐹𝐹𝑥𝑥 shall be distributed to the lateral force resisting elements in
proportion to their relative rigidities.
For rigid diaphragms, mass eccentricity is assumed to be 5% of the building
dimension perpendicular to the direction of the force.
Dynamic Analysis Procedure (NSCP Section 208.6)
Pertinent parameters are enumerated as a guidelines in three dimensional
modelling of structures with irregular plan configuration (such as those in Table
4-24).
Lateral Forces on Components of Structure, Non-Structural Components and Equipment
Supported by Structures (NSCP Section 208.7)
The section discusses the structural analysis of structure components such as non
structural walls, parapets etc.
Seismic shall be determined considering the following (NSCP Section 208.4.1):


4-22
𝐹𝐹𝐹𝐹 =
Seismic Zone (NSCP Figure 208-4, Section 208.4.4.1) either zone 4 or zone 2.
Regions are categorized as having the highest seismicity (zone 4) to an area of
least or lowest recorded seismic activity (zone 1). Except for Palawan and
some island provinces of Mindanao (zone 2). The Philippines is under zone 4.
Site Characteristics (NSCP Section 208.4.3 – Section 208.4.4). This includes,
soil type, proximity to earthquake generators and seismic source type which
essentially predicts the magnitude that the fault can generate.
4-23
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures



Occupancy (NSCP Section 208.4.2 together with NSCP Table 4-6). The code
also requires the use of occupancy importance factor, a magnifier that
increases (or reduces) the seismic load to a maximum of 50% for structures
most needed during emergencies and those that would have a many occupants
in one area as well as facilities that house dangerous materials that may cause
additional harm to the populace in case toxins are released due to structural
failure.
Building Configuration (NSCP Section 208.4.5) describes regular and
irregular structures which will become part of the basis for the method of
design.
The type of Structural System as discussed in NSCP Section 208.4.6 as well as
the Building Heights (NSCP Section 208.4.7) shall be used in the computation
of the design seismic force.
Table 4-23
4-24
Vertical Structural Irregularities
Irregularity Type and Definition
Reference NSCP Section
1. Stiffness Irregularity – Soft Story
A soft story is one in which the lateral stiffness is less than
70 percent of that in the story above or less than 80 percent
of the average stiffness of the three stories above.
208.4.8.3
Item 2
2. Weight (Mass) Irregularity
Mass irregularity shall be considered to exist where the
effective mass of any story is more than 150 percent of the
effective mass of an adjacent story. A roof that is lighter
than the floor below need not be considered.
208.4.8.3
Item 2
3. Vertical Geometric Irregularity
Vertical geometric irregularity shall be considered to exist
where the horizontal dimension of the lateral-force-resisting
system in any story is more than 130 percent of that in an
adjacent story. One-story penthouses need not be
considered.
208.4.8.3
Item 2
4. In-Plane Discontinuity In Vertical Lateral-ForceResisting Element Irregularity
An in-plane offset of the lateral-load-resisting elements
greater than the length of those elements.
208.5.8.1
5. Discontinuity In Capacity – Weak Story Irregularity
A weak story is one in which the story strength is less than
80 percent of that in the story above. The story strength is
the total strength of all seismic-resisting elements sharing
the story for the direction under consideration.
208.4.9.1
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
4.3.2
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Site Investigations
These hazards may be identified through historical records and reports from local
units and previous site investigations. Interviews from the inhabitants of the area
may also be done to cross-reference gathered historical data.
All projects require site investigations to be conducted by the duly authorized
party. Site investigations must provide sufficient information for apt planning of
the sub-surface investigation as determined by the engineer.
Recognition of the site hazards will prompt the engineers of the additional
considerations critical to the investigation, design and analysis of the site.
NSCP Section 303.1 recommends:



A geotechnical study be conducted for foundation design for structures two
stories or higher.
Anthropogenic Features
Man-made structures and other appurtenances for water supply, power
generation, agriculture, aquaculture, pumping wells, flood control, coastal
improvement, land reclamations, sanitary landfills, slope stabilization, mining and
quarrying, telecommunications, transportation, infrastructure and other edifices
near the site constitute additional considerations.
A total of 2 boreholes for structures less than 300 m2 in area and at least 3
boreholes for larger building area.
A maximum of 1 borehole for every 200 m2 of a structure.
Topography and Geologic Features
General features that must be noted are:
Terrain analysis of the project site can be carried out using remotely-sensed
imagery or topographical maps and then confirmed by conducting site
reconnaissance surveys. The project site is located on the map and the general
surface environment and terrain can be interpreted. By identifying the terrain,
specific issues can be taken into account such as sloping ground, soil and rock
(geologic) formation, hydrologic formations, fault systems.




Geologic information can also be gathered from geologic assessments by licensed
and recognized geologists, boring information or geotechnical reports from
previous projects in close proximity to the project site, and data from local
government units and pertinent government offices. The geologic information
must provide insight to the regional geology of the site particularly soil and rock
formation, groundwater table elevation, and other geotechnical characteristics.








4-26
Seismicity/earthquake risks
Flooding
Tidal waves
Landslides
Problematic soils (such as liquefiable soils, expansive soils and collapsible
soils)
Sinkholes
Accessibility (for construction purposes)
Waste disposal facilities
Cuts and fills
Drainage
Land use
Underground conduits that convey water, sewage, electricity, and
telecommunication lines may exist within the project site and must be preserved
from damage during sub-surface exploration and construction.
Similarly, structures adjacent to project site must not experience disturbance,
usually due to excessive vibrations and improperly designed excavations that may
induce instability or aesthetic detriment (such as misalignment of plumbing and
door settling) as determined by the Engineer.
Hazards

Adjacent structures
The aforementioned factors can affect and be affected by any soil investigation or
construction that it is essential to determine the existence and location of such.
An overview of the rainfall patterns and climatic conditions is also ideal for
holistic analysis as this provides an insight on the possible environmental
conditions to be encountered in the construction and engineering process.
Drainage and surface water conditions may also provide useful information.
Exposure to natural hazards must be comprehensively identified for sub-surface
investigation and design references. Hazards cover natural and environmental
factors that highly influence the stability and safety conditions of the project
during and after construction. Common risk factors include, but are not limited to,
the following:
Underground utility lines and other conduits
4.3.3
Accessibility of the site for mobilization and demobilization of equipment to be
used during sub-surface exploration and construction must be outlined so as to
recommend applicable methods to carry out such works.
Sub-surface Investigations
Sub-surface exploration shall observe the implementing rules and guidelines of
governing agencies of national and local government, adapted international
standards without compromising engineering principles and with high priority for
safety the of stakeholders involved.
Existing guidelines observed by local practice pertinent to this section:
4-27
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures



DPWH Standard Specifications for Highways, 2012 Edition: Highways, Bridges
and Airports (Volume II)
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
4.3.4
Soil laboratory tests must follow applicable governing standards from references
stated above. Geotechnical laboratories that will conduct tests must be ISOcertified and duly recognized to operate for local business.
Association of Structural Engineers of the Philippines National Structural Code
of the Philippines 2010, Sixth Edition: Buildings, Towers, and Other Vertical
Structures (Volume I)
Some of the geotechnical laboratory tests and corresponding standards are
provided in Table 4-25. The laboratory tests will be conducted to determine the
soil properties according to the rock sample recovered and the discretion of the
geotechnical engineer on the soil parameters required for engineering design.
Relevant DPWH Orders, Memoranda, etc.
In addition to the referenced guidelines, the DGCS shall also adopt additional
guidelines from international standards, professional industry handbooks and
globally used academic literature applicable for the implementation. The
references include:



Table 4-25
International Code Council International Building Code 2009
Geotechnical Engineering Investigation Handbook, Second Edition by Hunt,
R.E.
In this section, detailed discussion and instruction is provided on the (1) purpose
and importance of sub-surface investigations; (2) proper execution of standard
techniques and methodologies of soil explorations; and (3) output data analysis of
field investigations for geotechnical reports.
Execution of soil exploration methods shall integrate internationally-adopted
standards and DPWH-observed guidelines. Various soil exploration methodologies
will be discussed focusing on proper procedures, applicability to different soil and
rock formations, and field considerations.
Analysis of information from field explorations shall include good practices in
preparing boring logs and borehole logs to facilitate efficient geotechnical
analysis.
Parameter Observed
ASTM D2216-05
Moisture content
Specific Gravity
ASTM D854-05
Specific gravity
Grain-size Analysis (Mechanical
Sieve Analysis and Hydrometer
Analysis)
ASTM D422-63
Soil gradation
Atterberg Limits
ASTM D4318-05
Liquid limit
Plastic limit
Classification
ASTM D2487-00
Classification of soil type
Unconfined Compression Test
(for Soils)
ASTM D2166-00
Strength parameters
Unconfined Compression Test
(for Intact Rock)
ASTM D2938-95
Strength parameters
Tri-axial Test
(Unconsolidated-Undrained)
ASTM D2850-03a
Strength parameters
Tri-axial Test
(Consolidated-Undrained)
ASTM D4767-04
Strength parameters
Oedometer Test
(1-D Consolidation)
ASTM D2435-04
Consolidation parameters
Direct Shear Test
ASTM D3080-04
Strength parameters
Soil Sulfate Test
Hach Method 8051
Sulfate content
Constant-Head Test
Falling-Head Test
ASTM D2434
Hydraulic conductivity
Source: NSCP 2010
Groundwater table must be determined after drilling and rechecked 24 hours
after drilling. The Engineer must make sure that the measured groundwater table
is not due to the drilling fluid used during boring.
4-28
Test Standard
Designation
Moisture Content
Unified
Soil
System (USCS)
Significance and importance of adequate soil sub-surface investigations shall be
explained in relation with structure stability, effects on structural design, effects
on project cost, etc.
Provisions for unprecedented irregularities during soil sub-surface explorations
will be tackled in brevity.
Geotechnical Laboratory Tests and Corresponding Standards
Laboratory Test
American Standard for Testing and Materials International Geotechnical
Engineering Standards
Sub-surface investigation must extend reasonably beyond the basement
requirements of the project, if any. When hard strata is encountered (SPT Nvalue>50), coring is executed 3–5m into the hard stratum to analyze its quality
and verify it is really hard strata (or merely an intercepted boulder or such).
Laboratory Tests
Additional tests may be specified by the engineer as needed by the nature of the
project.
4.3.5
Selection of the laboratory test must reflect the actual site conditions and
consistent with the assumed failure mode of the soil material under
consideration.
Allowable Soil Bearing Capacity
To determine the allowable soil bearing capacity, the Geotechnical Engineer
should use any widely accepted method in the industry to calculate for the
ultimate soil bearing capacity. The safe soil bearing capacity shall be determined by
dividing the ultimate bearing capacity (qult) by a safety factor,𝑆𝑆𝑆𝑆, between 2.0 and
3.0. The allowable soil bearing capacity (qallow) shall be a safe bearing capacity that
4-29
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
exhibits settlement within the tolerable limits for the project. Tolerable settlement
varies upon the nature of the project.
𝑞𝑞𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎 =
𝑞𝑞𝑢𝑢𝑢𝑢𝑢𝑢
(𝑢𝑢𝑢𝑢𝑑𝑑𝑑𝑑𝑑𝑑 𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡 𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠)
𝑆𝑆𝑆𝑆
In estimating the soil bearing capacity, adjacent soil strata with relatively same
properties may be assumed homogenous under the discretion of the assigned
engineer. Any anomalies in the stratification (such as sand lenses and intercepted
boulders) must be noted and properly considered in the calculations and must be
reflected in the report.
Groundwater table effects on the soil bearing capacity must be considered. The
season when the field investigation was carried out must also be a factor; boring
during dry season may decrease the groundwater table significantly while the wet
season may increase it considerably as well. The engineer must calculate the
allowable soil bearing capacity conservatively when insufficient and/or unreliable
or questionable data is derived from the soil investigation program.
The general soil bearing capacity equation for shallow strip footings is:
where:
𝑞𝑞𝑢𝑢𝑢𝑢𝑢𝑢 = 𝑐𝑐𝑁𝑁𝑐𝑐 + 𝑞𝑞𝑁𝑁𝑞𝑞 + 0.5𝛾𝛾𝛾𝛾𝑁𝑁𝛾𝛾
𝑞𝑞𝑢𝑢𝑢𝑢𝑢𝑢
=
ultimate bearing capacity
𝑞𝑞
=
overburden pressure at footing base
𝑐𝑐
𝛾𝛾
𝐵𝐵
=
=
=
𝑁𝑁𝑐𝑐 , 𝑁𝑁𝑞𝑞 , 𝑁𝑁𝛾𝛾 =
cohesion of soil
soil unit weight beneath footing
footing width
bearing capacity factors; function of soil angle of internal friction, 𝜙𝜙
This equation is modified by different factors provided by various geotechnical
researchers depending on the considerations of the shallow foundation such as:





Footing shape
Depth of embedment
Load inclination
Ground (slope)
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 4-26
Comparison of Soil Bearing Capacity Theories
Author
Terzaghi
Hansen
Comments
Used for estimating 𝑞𝑞𝑢𝑢𝑢𝑢𝑢𝑢 for very cohesive soils and footings with
axial loads only
Used for any particular case with applicable correction factors
Meyerhof
Used for any particular case with applicable correction factors
Vesic
Used for any particular case with applicable correction factors
specially footings on slopes
The correction factors given by each author must not be compounded with other
correction factors given by another author or researcher, unless otherwise
specified.
The method selected for the analysis must be compatible with the site soil type. As
recommended, the use of more than one method is advisable to determine a safe
range of the allowable bearing capacity. From the results, a range of the allowable
soil bearing capacity is provided for the structural engineer to adopt in the design
calculations.
Soil shear strength parameters (cohesion and angle of internal friction) must be
determined in either drained or undrained conditions through laboratory testing
or correlations. Deformation properties of the soil (such as compression index,
recompression index, coefficient of consolidation, elastic modulus) must also be
determined for settlement analysis.
Lateral Earth Pressure
Lateral earth pressures are computed whenever the soil exerts horizontal
pressures on structures particularly retaining walls, sheet piles, and excavation
bracing. Refer Figure 4-1.
In computing for lateral earth pressures, widely-accepted theories and models
may be used so as the applicability of the model is justifiable.
Lateral earth pressures may be active or passive by character. When the
horizontal pressure is less than the vertical pressure, the soil is under active case;
otherwise, it is under passive case. A structure may be subjected to both pressures
at the same time depending on the geometry and other site conditions during
different phases of construction.
Eccentric loading
Some of the authors of widely-used modified bearing capacity equations and
comments regarding the use of their correction factors are provided in Table 4-26.
Further information on soil bearing capacity is provided in DGCS Volume 2C
Geotechnical and Geological Investigation.
4-30
4-31
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Any correlation from these methods to determine soil properties must be applied
with prudence. Deviations from the established procedures must all be noted
during the procedure.
To monitor consolidation settlement, piezometers may be installed to observe
changes in pore water pressure. Inclinometers and other soil movement gauges
may as well be utilized by experienced users of such technology.
GeoHazards
DGCS Volume 2A GeoHazard Assessment describes the nature of geohazards in
the Philippines, the information required to assess their likelihood at a site, and a
procedure for preparing a preliminary.
As determined by the Engineer, special soil investigation must be carried out to
determine the presence of problematic soil (such as expansive soils, liquefiable
soils, fractures and discontinuities in rock material). Any uncommon condition in
the subsurface material that will influence the project must be noted and properly
investigated.
Various signs of GeoHazards and anomalous behavior in the soil include:






Sudden soil collapse or heaving
Steep slopes
Landslide deposits
Sand lenses
Penetration resistance inconsistencies
Abrupt changes in subsurface stratification
Special caution is practiced in investigating such hazards so as not to induce any
unanticipated danger.
Once the hazard is characterized by a Geotechnical Engineer, mitigating or
remediating procedures may be applied. Any widely-accepted soil or rock
improvement method may be conducted as long as it is identified by the Engineer
as appropriate to the site condition.
Ground remediation techniques include:





Grouting
Vertical and/or horizontal drains
Surcharge preloading
Lime/cement stabilization
Geosynthetic reinforcement
The option of removing the soil can be adopted if it is viable and economical.
4-33
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
4.3.7
Shallow Foundations (Footing Design)
Shallow foundations can be used if the soil support mechanism relies on the
bearing capacity of the soil within a foundation’s zone of influence and discounts
the effect of skin friction. Shallow foundations are designed accordingly to exert
pressures less than the allowable soil bearing capacity.
In the design of shallow foundations, project requirements for basement levels are
major factors. The basement level will determine the depth of the foundation and
may prompt the engineer to decide between using shallow or deep foundation.
The footing design will observe the provisions of NSCP for structural concrete.
4.3.8
Eccentric loadings must be emphasized in the design of the footing. Effects may be
dealt with using any modification in the footing design that is permissible given
the particular restraints of the project.
Deep Foundations (Pile Design)
Deep foundation is used when the soil support mechanism relies on the skin
friction and end bearing of the foundation against the soil. Deep foundations are
used when soil bearing capacity is not enough to support the weight of the
structure, if the upper soil strata are weak, and if the project is off-shore or
subjected to high groundwater table. Accessibility and adjacent structures are
some other considerations for the use of deep foundations.
Two general schemes of pile installation may be chosen by the engineer: driven
piles and bored piles.
a. Driven piles requires installation of precast piles on-site using a pneumatic or
drop hammer heavy equipment. The installation procedure causes significant
noise and vibration to induce public disturbance and structural damage to
adjacent structures. This method, however, effectively mobilizes the skin
friction resistance of the soil. Driven piles also facilitate construction.
b. Bored piles require on-site assembly of reinforcing bars and preparation of
drilled hole. The rebar skeleton is lowered into the hole and filled with
concrete mix delivered on site. Before the concrete is poured onto the hole,
debris and other dirt must be removed from the bottom of the hole to ensure
the load transfer mechanism of the pile. Significant noise or public disturbance
and structural damage must not be caused within proximal area of the project.
This method effectively mobilizes the end-bearing more than the skin friction
resistance of the soil. Bored piles relatively take a little more time than driven
piles to install.
Any widely-accepted method can be used to estimate pile capacity. Pile capacity
mainly relies on two components which are point- or end-bearing resistance and
skin friction. End-bearing capacity depends on the stratum on which the pile end
rests. Skin friction is the frictional force exerted by the soil surrounding the pile
through its embedment length.
4-34
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
End-bearing capacity of piles is estimated by employing principles of soil bearing
as shown below.
𝑄𝑄𝑝𝑝 = 𝐴𝐴𝑝𝑝 ∗ 𝑞𝑞𝑝𝑝
𝑞𝑞𝑝𝑝 = 𝑐𝑐′𝑁𝑁𝑐𝑐 ∗ + 𝑞𝑞′𝑁𝑁𝑞𝑞 ∗
where:
𝑄𝑄𝑝𝑝
=
pile end-bearing capacity
𝑞𝑞𝑝𝑝
=
pile end-bearing pressure
=
effective overburden pressure
=
𝐴𝐴𝑝𝑝
𝑐𝑐′
=
𝑁𝑁𝑐𝑐 ∗ , 𝑁𝑁𝑞𝑞 ∗
=
𝑞𝑞′
area of pile tip
effective cohesion
pile end-bearing capacity factors
Skin friction resistance of piles is estimated by employing the principles below.
𝑄𝑄𝑠𝑠 = ∑ 𝑓𝑓𝐴𝐴𝑙𝑙 = ∑ 𝑓𝑓𝑓𝑓Δ𝐿𝐿
where:
𝑄𝑄𝑠𝑠
𝑓𝑓 = 𝐾𝐾𝜎𝜎0 ′ 𝑡𝑡𝑡𝑡𝑡𝑡𝑡𝑡′
=
skin friction capacity
𝑝𝑝
=
perimeter of pile section
𝐾𝐾
=
effective earth pressure coefficient
𝑓𝑓
Δ𝐿𝐿
𝜎𝜎0 ′
𝛿𝛿′
=
=
=
=
unit friction resistance
incremental pile length over which the frictional resistance is
evaluated
effective vertical stress at incremental depth considered
soil-pile friction angle
When piles are grouped and act as a unit, the pile group capacity must likewise be
determined. Grouped piles must be placed as near each other as required by space
allotment but more importantly, as far from each other for skin friction to develop
and mobilize. The limiting distance between piles must be specified by the
attending engineer.
Micropiles
Micropiles are bored mini piles with diameter not exceeding 300 mm. Because of
the small size of mini piles, only small dimension equipment is needed for
construction and can be used to drill through any type of soils, boulders and hard
materials. They are constructed using high strength small diameter casing or
thread bar. Typically the casing is advanced to the design depth using a drilling
technique. Reinforcing steel in the form of an all-thread bar is typically inserted
4-35
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
into the micropile casing. High strength cement grout is then pumped into the
casing. The casing may extend to the full depth above the bond zone with the
reinforcing bars extending to the full depth. The finished micropile resists
compression, uplift or tension loads and lateral loads.
The design of micropiles for buildings and bridges involves the same approach.
The structural design of micropiles, cased or uncased length, provided below is
based on the Micropile Design and Construction Reference Manual, US
Department of Transportation, Federal Highway Administration, Publication No.
FHWA NHI-05-039, December 2005.
The allowable compression load for the cased length of a micropile is:
where:
Pc−allowable = [0.4f ′ c−grout x Agrout + 0.47Fy−steel (Abar + Acasing )]
Pc-allowable
=
allowable compression load
f’c
=
unconfined compressive strength of grout
(typically a 28-day strength)
Fy-steel
=
yield stress of steel
Agrout
Abar
Acasing
=
=
=
area of grout in micropile cross section (inside
casing only, discount grout outside the casing)
cross sectional area of steel reinforcing bar (if
used)
cross sectional area of steel casing.
Strain compatibility under compression load is considered for the steel
components and grout by limiting allowable stresses to the minimum allowable
for any individual component (i.e., steel casing, steel reinforcement, or grout).
Therefore, the maximum yield stress of steel to be used in the above equation is
the minimum of yield stress of casing, yield stress of steel reinforcing rod and
maximum stress based on grout failure.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
For soil which has a high corrosion potential, it may be assumed that the steel
casing is not effective in carrying tensile loads, Acasing = 0. The reinforcing bar
should be designed to carry the entire tension design load.
Since a micropile can be subjected to lateral loads or overturning moments, they
are subject to bending stresses also, thus requiring combined stress evaluation.
The design check for combined stresses (appropriate for micropile) is:
fb
fa
+
≤ 1.0
Fa (1 − fa ) F
F′e
where:
axial stress = Pc ⁄Acasing
fa
=
Fa
=
fb
Fb
Fe′
b
=
bending stress = Mmax ⁄S ; S is the elastic section
modulus of the steel casing
=
0.47 Fy−casing
=
0.55 Fy−casing
=
=
allowable axial stress that would be permitted if axial
force alone existed
allowable bending stress that would be permitted if
bending moment alone existed
Euler buckling stress
The contribution of a central reinforcing bar to bending strength is small
compared to that of the casing, hence its effects on bending strength are ignored in
the above combined axial and bending equation. In this equation, it is
conservatively assumed that the maximum axial compression load, Pc , is carried
by the steel casing only and the yield stress of the steel casing is used.
The outside diameter of the steel casing is reduced to account for losses due to
corrosion in the computation of the allowable compression capacity of a cased
length. Also, if the micropile is used in very weak ground, the allowable
compression load may be reduced to consider the effect of buckling over the
length of the micropile. Further discussion of losses due to corrosion and buckling
are discussed in the Micropile Design and Construction Reference Manual of the
US Federal Highway Administration.
In cases where the micropiles will be subject to tensile loads, the allowable
tension load 𝑃𝑃t−allowable for the cased length of a micropile can be calculated as:
where:
Fy−steel =
4-36
Pt−allowable = 0.55 Fy−steel × (Abar + Acasing )
minimum yield stress of the bar and casing
4-37
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Section properties required for the analysis are calculated as:
Acasing =
is provided demonstrating that the confined grout can sustain higher strain levels
without crushing.
π
(OD2 − ID2 )
4
The allowable tension load for the uncased length of a micropile is given as:
Icasing
S=
(OD⁄2)
Icasing =
π
(OD4 − ID4 )
64
4.3.9
For excavation works, all applicable provisions indicated in DPWH Standard
Specifications 2012 Volume II must be observed.
The Euler buckling stress is calculated as:
Fe′ =
E
where:
=
FS
=
L
=
K
r
=
=
π2 E
FS(Kl⁄r)2
Excavations for any project must be properly designed and monitored on-site.
Depths of unsupported or unbraced excavation must not exceed 3 m unless the
conditions are deemed stable and safe by the Geotechnical Engineer.
elastic modulus of the steel casing (typically assumed to
be 200,000 MPa (29,000ksi)
factor of safety equal to 2.12
effective length factor (assumed equal to 1.0)
unsupported length of micropile
1⁄2
radius of gyration of the steel casing = (Icasing⁄Acasing )
The assumption that the entire axial load is carried by the steel casing is
conservative. A combined stress check that can account for the contribution of the
grout inside the casing to compression capacity, assuming that buckling potential
is negligible, is:
where:
Pc
Pc−allowable
+
Mmax
Mallowable
≤ 1.0
P𝑐𝑐
=
maximum axial compression load;
Mmax
=
maximum bending moment in the micropile; and
Pc−allowable =
𝑀𝑀𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎
=
Excavations and Fills
Pt−allowable = 0.55Fy−bar × Abar
determined from the above equation for
compression
Various techniques in supporting excavations may be used depending on the
nature of the project. The Geotechnical Engineer must account for several factors
like in-situ soil parameters, access, groundwater table and overall intent in
excavating.
If the groundwater is relatively shallow, dewatering may be employed, however,
caution is advised so as not to cause structural damage or significant settlement to
adjacent structures. Observation wells may also be installed near the excavation
sites to monitor dewatering progress and effects.
To design the support system for excavations, rain conditions must be considered
in the design observing the principles on lateral earth pressure in Section 4.3.5.
Methods such as shotcrete application, soil nailing and other soil reinforcement
methods for excavations can be used as long as it is supervised by experienced
engineers in using the technology.
For engineered fills, compaction degree will be specified to 95% of maximum dry
density, or better. The optimum moisture content will be determined in the
laboratory using applicable standard methods. Every layer in the compacted fill in
the field shall be tested according to the specifications.
In the selection of the fill material, special consideration must be given to the use
of the fill material particularly with the hydraulic properties of the structure.
Fb (= 0.55Fy−casing ) × S
The allowable compression load for the uncased length of a micropile is given as:
Pc−allowable = (0.4fc′ × Agrout + 0.47Fy−bar × Abar )
For the uncased portion of the pile, the reinforcing bar yield stress used in the
calculations in compression is assumed to not exceed 600 MPa (87 ksi). The limit
of 600 MPa is to prevent grout crushing at an assumed strain of 0.003 unless data
4-38
4-39
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures


Intermediate Grade ASTM A615 Grade 40 Fy =276 Mpa
High Grade ASTM A615 Grade 60 Fy =414 Mpa
Welded plain wire fabric for concrete reinforcement shall conform to
"Specifications for Steel Welded Wire, Fabric, Plain for Concrete Reinforcement"
(ASTM A 185M).
4.4.2
Grade 60 steel is generally used for high-rise buildings.
Structural Detailing (NSCP Section 407)
In general, this section shall be used as reference in detailing requirements for
constructability and ensure that placement of reinforcement is consistent with
the design intent.
NSCP Section 407.7 – "Spacing Limits for Reinforcement" shall be used in
determining effective depth used in the generated couple that resist stress as in
Bending. This will also define the number of bars that can be accommodated per
layer of bar in flexural members which in turn shall be used in the computation of
effective depth. The center to center spacing and other details of tendons are also
included in this Section of NSCP.
NSCP Section 407.8 – "Concrete Protection for Reinforcement" completes the
information needed as described in the previous paragraph. It specifies the
minimum concrete cover for cast-in-place concrete and precast concrete both for
non prestressed and prestressed members.
NSCP Section 407.13 -"Shrinkage and Temperature Reinforcement"- defines code
requirements for reinforcement that are required other than those that design
computations yield. These are usually provided in structural slabs where the
flexural reinforcement extend in one direction only.
4.4.3
Further details on structural detailing are provided in ACI Detailing Manual 2004.
Analysis and Design (NSCP Section 408)
NSCP Section 408.2 requires structural concrete members to be proportioned for
adequate strength design using load factors and strength reduction may be used
as specified in NSCP Section 409. Alternative procedure for strength design may
be used as provided in NSCP Section 426.
NSCP Section 424 permits the use of "working stress design (WSD)". This is
applicable for non-prestressed reinforced concrete members which are allowed to
be designed using service loads (without load factors) and permissible load
stresses.
Load Combinations and Load Factors (NSCP Section 409.3)
NSCP Section 409.3.1 provides the recommended load factors and combinations of
loads to be investigated.
4-42
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Strength (NSCP Section 409.4 and 409.5)
NSCP Section 409.4 provides the recommended strength reduction factor while
NSCP Section 409.5 Design Strength for Reinforcement, states that yield
strength used in calculation shall not exceed 550 MPa, except in prestressing
tendons and for transverse reinforcement in NSCP Sections 410.10.3 and
421.3.5.4.
Deflection Control (NSCP Section 409.6)
NSCP Table 409-1 provides the Minimum Thickness of Non-prestressed Beams or
One-way Slab.
NSCP Section 409.6.2.5 recommends the need to modify immediate deflection to
account for longtime deflection, creep and shrinkage by a factor stated therein
when no comprehensive analysis is prepared.
NSCP Section 409.6.3 governs the minimum thickness of nonprestressed two way
slab. NSCP Section 409.6.3.3 provides computations for thickness.
NSCP Section 409.6.3.2 contain provisions for flat slabs. NSCP Table 409-3
provides minimum thickness of flat slabs
NSCP Table 409-2 shows the Maximum Permissible Computed Deflection.
Flexure and Axial Load (NSCP Section 410)
Flexure and axially loaded members shall be analyzed using accepted classical
methods with due consideration for all possible loads and load combinations.
This section of the code provides basic assumptions and minimum requirements
that needs to be satisfied.
Shear and Torsion (NSCP Section 411)
Simultaneous to other stresses, members subjected to shear and torsion shall
proportioned and reinforced using this section of the code which provides basic
assumptions and minimum requirements.
Development Length and Splice Lengths of Reinforcement (NSCP Section 412)
Consistent with the requirements for reinforced concrete in reinforcement
placement, detailing, and arrangement, equally important are splicing and
development length. Splicing requires the tensile or compressive stress generated
by loads on the reinforcement to prevent slippage of the rebar from its position
which may cause failure when it is not being able to generate the internal stress
resistance between the concrete and rebar.
Two Way Slab (NSCP Section 413)
Basic design procedure for conventional and flat slab system.
4-43
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Axial Load Strength
where:
Ø
ØPn = 0.85Ø[.85f'c(Ag-Ast) + Astfy]
=
0.65
Spiral Column
steel ratio ρ= As/Ag
where:
As
=
area of non prestressed longitudinal tension reinforcement
ρmin
=
0.01 ρmax=0.06
Ag
=
gross area of section
Minimum spiral diameter is Ø10 mm bars and a max of Ø16 mm.
Volumetric spiral reinforcement ratio ρs, shall not be less than the value given
by:
Ag
where:
=
ρs = 0.45(Ag/Ach – 1)f'c/fyt
gross area of section
Ach
=
area of section measured from the outer edge of the spiral
reinforcement
fyt shall not exceed 700 Mpa
Design Axial Strength
ØPn
where:
Ø
=
0.80Ø[.85f'c(Ag-Ast) + Astfy]
=
0.75
Slenderness effect (NSCP 410.11)
1. For members unbraced against sidesway
klu/r ≤22
2. Members braced against sidesway
where:
klu/r ≤ 34 – 12(M1/M2) ≤ 40
k
=
the effective length factor
M1
=
the smaller absolute value of the two end moments acting on
the column
lu
=
clear height of the column
4-47
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
4.5.2
4.5.3
General Design Approach
The structural engineer must be able to check the compliance of structural design
drawings and specifications in the code of standard practice.
Material
This section shall apply to material test reports conforming to testing standards
set by the American Standard for Testing and Materials (ASTM).
Such standards are specified in the following local and international codes:



National Structural Code of the Philippines (NSCP) 2010 Sixth Edition:
Buildings, Towers, and Other Vertical Structures (Volume I); Chapter 5, Part 1
– Specifications for Steel Members.
International Conference of Building Officials Uniform Building Code 1997
(Volume 2).
American Institute of Steel Construction 2010: Ninth Edition for Allowable
Strength Design (ASD) and Thirteenth Edition for Load Resistance and Factor
Design (LRFD).
Materials included are hot-rolled structural shapes, structural tubing, pipe, plates,
bars, and sheets. Also covered are unidentified steel, rolled heavy shapes, steel
castings and forgings, bolts, washers and nuts, anchor rods and threaded rods,
welding, and headed stud anchors.



4.5.4
Structural Steel Design Requirements, NSCP Chapter 5
NSCP Section 501 General provisions
NSCP Section 502 Design Requirements for ASD and LRFD
Design for Tension Members (NSCP Section 504)
This section shall apply to designing tension members as specified in NSCP 2010,
Referral Code of the NBCP. The DGCS shall also adopt additional design guidelines
from international standards.
This covers the following topics: Slenderness Limitation (NSCP Section 504.1),
Tensile Strength (NSCP Section 504.2), Effective Net Area (NSCP Section 504.3),
Built-up Members (NSCP Section 504.4), Pin-connected Members (NSCP Section
504.5), and Eyebars (NSCP Section 504.6).
Slenderness Ratio (NSCP Section 504.1)
As specified in the governing code, the slenderness ratio, L/r, preferably should
not exceed 300, but is not applicable to rods or hangers in tension. The
specification shall aid in the design of bracing members, tension chords and
internal ties in trusses and lattice girders.
Tensile Strength (NSCP Section 504.2)
The structural engineer shall consider two limit states for tension member design,
tensile yield strength and tensile rupture strength.
4-52
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Members fail either by excessive deformation or by fracture. A member fails by
excessive deformation if the stress on the gross section is greater than the yield
stress, Fy. And if the stress on the net section is greater than the tensile strength,
Fu, a member fails by fracture. The design strength and the allowable tensile
strength shall be the lower value determined based on the limit states mentioned
above.
Effective Net Area (Ae) (NSCP Section 504.3)
The effective net area of tension members, as specified in the governing code, is
given by:
where:
Ae
U
Ae = AnU
=
=
effective net area of tension members, mm2
shear lag factor
An
=
effective net area and is the difference between the gross area (Ag)
and the area of bolt holes, mm2
The structural engineer shall take into consideration that different U values apply
for tension members provided in NSCP Table 504.3.1. Shear lag factors for
connections to tension members of different cases are:
1. Tension members where tension load is transmitted directly to each of crosssectional elements by fasteners or welds.
2. Tension members, except plates and HSS, where tension load is transmitted to
some but not all of the cross-sectional elements by fasteners or longitudinal
welds.
3. Tension members where tension load is transmitted by transverse welds to
some but not all of the cross-sectional elements.
4. Plates where the tension load is transmitted by longitudinal welds only.
5. Round HSS with a single concentric gusset plate.
6. Rectangular HSS.
7. W, M, S or HP shapes.
8. Single angles.
Pin-Connected Members (NSCP Section 504.5)
Pin – connected members in tension are subjected to several types of failure. The
design strength and allowable tensile strength shall be designed based on the
lower value obtain from the limit states of tensile rupture, shear rupture, bearing
and yielding.
4-53
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
As specified in NSCP 504.5, the following shall apply:
1. Tension acting on the net effective area
Pn = 2tbeffFu
(NSCP 504.5-1)
Pn = 0.6FuAsf
(NSCP 504.5-2)
2. Shear acting on the effective area
Sf = 0.75 (LRFD)
Ωsf = 2.0 (ASD)
3. Tension acting on the gross section
Pn = FyAg
t = 0.90 (LRFD)
4. Bearing
Pn = 1.8FyApb
 = 0.75 (LRFD)
Ωt = 1.67 (ASD)
Ω = 2.0 (ASD)
(NSCP 504.2-1)
(NSCP 510.7-1)
An example is provided for pin-connected tension members.
where:
Pn
=
force on area
Fy
=
specified minimum yield stress of steel used MPa
Rn
=
nominal bearing strength
Apb
=
projected bearing area
Ag
=
gross area of member, mm2
Fu
=
Asf
=
A
specified aluminum tensile stress of steel used
2t(a+d/2), mm2
beff
=
=
shortest distance from edge of the pin hole to the edge of the
member measured parallel to the applied force
d
=
pin diameter, mm
t
=
2t + 16, mm but not more than the actual distance from the
pinhole to the edge of the member measured perpendicular to the
force.
thickness of plate, mm
Eyebars (NSCP Section 504.6)
An example is provided for an eyebar connection.
Example: W, Single-angle, WT, Rectangular HSS, Round HSS, Double Angle Tension Members
Designing a member with given loads in tension and member length.
4-54
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Example: Eyebar Tension Members
Ω = 2.00
Verifying member strength with given loads in tension, pin diameter and eyebar
dimensions.
Pn/Ω > Pa
5. Calculate the available shear rupture strength.
1. Determine material properties for ASTM Designation, Fy and Fu (AISC Table 24); and geometric properties of the member.
Pn = 0.6FuAsf
Asf = 2t(a+d/2)
2. Check dimensional requirements such as t, w, d. dh, R (NSCP Section 504.6.2)
Using LRFD
3. Calculate the required tensile strength, Pu (LRFD) or Pa (ASD). Note that Pu is a
factored load.
Φ = 0.75
4. Calculate the available tensile yielding strength at the eyebar body (at w)
ΦPn > Pu
Determine An and Pn.
Using ASD
Ω = 2.00
5.
Pn/Ω > Pa
6. Calculate the available bearing strength.
Determine the tensile yield strength.
Using LRFD
Φ = 0.90
Pn = 1.8FyApb
ΦPn > Pu
Using LRFD
Using ASD
Φ = 0.75
Ω = 1.67
ΦPn > Pu
Pn/Ω > Pa
Using ASD
The structural engineer shall take note that the pin should also be checked for
shear yielding and bearing.
Ω = 2.00
Pn/Ω > Pa
Example: Find Ae of a Plate with Staggered Bolts
7. Calculate the available tensile yielding strength.
1. Calculate the net hole diameter, dnet.
Pn = FyAg
Using LRFD
2.
Φ = 0.90
ΦPn > Pu
dnet = dh + 1/16 in.
Compute the net width for all possible paths across the plate, w.
w = 14 – Ʃdnet + Ʃs2/4g
Calculate for An. Note that the nearest path (smallest value) shall govern in the
design.
Using ASD
Ω = 1.67
3.
Pn/Ω > Pa
8. Determine the governing strength from the lowest calculated values.
Pn = FyAg
4.
4.5.5
Determine U.
Determine Ae.
Ae = AnU
Design for Compression (NSCP Section 505)
This section shall apply to designing compression members as specified in NSCP
2010, Referral Code of the NBCP. The DGCS shall also adopt additional design
guidelines from international standards.
4-56
4-57
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
This section covers the following topics: general provisions (NSCP Section 505.1),
effective length and slenderness (NSCP Section 505.2), compressive strength for
flexural buckling of members without slender elements (NSCP Section 505.3),
compression and bending (NSCP Section 508.1-508.3), composite compression
members (NSCP Section 509.2), and compressive strength of connecting elements
(NSCP Section 510.4.4).
Effective Length
As specified in the governing code, the slenderness ratio, KL/r, preferably should
not exceed 200.
Flexural Buckling of Members without Slender Elements
As mentioned in the governing standards, this section shall apply to compression
members with non-slender (compact and non-compact sections), for uniformly
compressed elements. This includes non-slender built-up I-shaped columns and
non-slender HSS columns.
The nominal compressive strength, Pn, shall be based on the limit state of flexural
buckling. Flexural buckling is a deflection caused by bending about the axis
corresponding to the largest slenderness ratio.
The equation for determining nominal compressive strength is given by:
Pn = FcrAg
Torsional and Flexural-Torsional Buckling of Members without Slender Elements
This section is most commonly applicable to double angles and Tee sections which
are singly symmetrical shapes subject to torsional buckling and flexural –
torsional buckling.
As specified in the governing code, the nominal compressive strength, Pn, shall be
determined based on the two limit states mentioned above, torsional and flexural
– torsional buckling. Available strength of the members is available in AISC
Manual Part 4.
Single Angle Compression Members
This section as stated in the governing code shall apply to single angle
compression members wherein the nominal compressive strength, Pn, shall be
determined for axially loaded members, as well as those subject to the
slenderness modification, provided the members meet the criteria. Available
strength of the members is available in AISC Manual Part 4.
Built-Up Members
The analysis for built – up compression member is the same for any other
compression member if the cross-sectional properties are known. However, the
parts of the cross section must be properly connected.
4-58
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Requirements for members composed of two or more rolled shapes and for
members composed of plates or combination of plates and shapes with related
connections are specified in the governing code.
Member with Slender Elements
This section shall apply to members with slender sections for compressed
members. The design is similar to members without slender elements except that
a reduction factor is introduced to modify the formulas. Appropriate reduction
factors in available strength are incorporated in AISC Manual Part 4.
The nominal compressive strength, Pn, shall be based on the limit states of
torsional, flexural and flexural – torsional buckling.
Example: W-Shape Column Design Pinned Ends
Design a W-shape column to carry specific loads in axial compression, given
column length and shape.
1. Calculate the required strength, Pu (LRFD) or Pa (ASD). Note that Pu is a
factored load.
2. Select a section using AISC Manual Table 4-1.
3. Find K. For a pinned-pinned connection, K=1.0.
Y-Y axis will govern for unbraced lengths same in both x-x and y-y
directions.
And for all W-shapes, rx exceeds ry.
4. Enter the table with an effective length, KL and proceed until reaching the
least weight shape with an available strength that equals or exceeds the
required strength.
5. Select column section (for adjustments).
6. Determine available strength in compression, y-y axis effective length using
AISC Manual Table 4-1.
Using LRFD
ΦPn > Pu
Using ASD
Pn/Ω > Pa
Example: W-Shape Column Design with Intermediate Bracing
Redesigning Example C1a assuming the column is laterally braced about the y-y
axis and torsionally braced at the midpoint.
1. Calculate the required strength, Pu (LRFD) or Pa (ASD). Note that Pu is a
factored load.
2. Select a column using AISC Manual Table 4-1.
4-59
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
ΦPn > Pu
Using ASD
Pn/Ω > Pa
7. Repeat procedures (2) to (6) for all members.
Example: Double Angle Compression Member without Slender Elements
Verifying member strength with given loads in axial compression, column
dimensions and column length which are pinned at both ends.
1. Determine material properties for ASTM Designation, Fy and Fu (AISC Table 23); and geometric properties of member (AISC Table 1-15 for Double angles
and AISC Table 1-17 for MC shapes).
2. Calculate the required strength, Pu (LRFD) or Pa (ASD). Note that Pu is a
factored load.
3. Select column (AISC Table 4-9)
4. Find K and compute for KL value for both x and y-axis.
5. Determine the available strength in axial compression for both axes.
(AISC Table 4-9)
Using LRFD
ΦPn > Pu
Using ASD
Pn/Ω > Pa
6. Determine the available strength from the lowest value of the two axes
computed.
Example: Design of Rectangular HSS Compression Member with Slender Elements
Selecting a rectangular HSS member with given loads in axial compression,
column dimensions and column length. The base is fixed while the top is pinned.
1. Determine material properties for ASTM Designation, Fy and Fu (AISC Table 23).
2. Calculate the required strength, Pu (LRFD) or Pa (ASD). Note that Pu is a
factored load.
3. Find K. Solve for KLx and KLy.
4. Enter AISC Table 4-3 and proceed across the page until the lightest section is
found with an available strength that is equal to or greater than the required
strength.
5. Determine the available strength in axial compression.
Using LRFD
Using ASD
4.5.6
Pn/Ω > Pa
Flexural Members
This section shall apply to designing flexural members as specified in NSCP 2010,
Referral Code of the NBCP. The DGCS shall also adopt additional design guidelines
from international standards. The section contains provisions for determining
flexural strength of members subject to simple bending about a principal axis.
Provisions for I shaped members, channels, HSS, tees, double angles, single angles,
rectangular bars, rounds and unsymmetrical shapes.
The selection and evaluation of all members to be used is based on the deflection
requirements and strength. The design strength shall be determined based on
flexural strength, ϕMn or the allowable flexural strength, Mn/Ω.
Doubly Symmetric Compact I-Shaped Members and Channels Bent about their Major Axis
This shall apply to members with compact I – shaped beam and channel cross
sections subject to bending about their major axis as specified in the governing
code. The only limit state to consider is lateral – torsional buckling. Almost all
rolled wide – flange shapes listed identified by the governing code are qualified to
be designed by the provisions of this section.
Doubly Symmetric I-Shaped Members with Compact Webs and Non compact or Slender Flanges
Bent about their Major Axis
The strength of shapes designed according to this section is limited by local
buckling of the compression flange. Few rolled wide – flange shapes are subject to
this criterion, i.e. having noncompact flanges.
Other I-Shaped Members with Compact or Non compact Webs Bent About Their Major Axis
As specified in the governing code, this section shall apply to doubly symmetric I –
shaped members bent with noncompact webs and singly symmetric I – shaped
members (having different flanges) with compact or noncompact webs.
Doubly Symmetric and Singly Symmetric I-Shaped Members with Slender Webs Bent About
Their Major Axis
As specified in the governing code, this section shall apply to doubly symmetric
I – shaped members with slender webs, also known as “plate girders”.
I-Shaped Members and Channels Bent About Their Minor Axis
As specified in the governing code, this section shall apply to I – shaped members
and channels bent about their minor axis. The majority of W-, M-, C-, and MCshapes have compact flanges which can develop the full plastic Mp about the minor
axis.
ΦPn > Pu
4-62
4-63
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Square and Rectangular HSS and Box-Shaped Members
As specified in the governing code, this section shall apply to square and
rectangular HSS, and doubly symmetric box – shaped members bent about either
axis, having compact and noncompact webs and compact and noncompact slender
flanges.
Round HSS and Pipes
This section shall apply to both tubes and pipes. As specified in the governing
code, this section shall apply to round HSS having D/t ratios of less than 0.45E/Fy.
Tees and Double Angles Loaded in the Plane of Symmetry
As specified in the governing code, this section shall apply to tees and double
angles loaded in the plane of symmetry. The specification provides a check for
flange local buckling which applies only when the flange is in compression due to
flexure.
Single Angles
As specified in the governing code, this section shall apply to single angles with
and without lateral restraint along their length. The structural engineer shall
consider the geometric axis of bending. Also, when designing single angles without
continuous bracing using the geometric axis design provisions, My should be
multiplied by 0.80.
Rectangular Bars and Rounds
As specified in the governing code, this section shall apply to rectangular bars bent
about either geometric axis and rounds.
The structural engineer shall consider solid square, rectangular and round bars,
with the exception of rectangular bars bent about the strong axis, are not subject
to lateral-torsional buckling; rectangular bar bent about the strong axis are
subject to lateral torsional buckling; and local buckling does not apply to any bars.
Unsymmetrical Shapes
As specified in the governing code, this section shall apply to all unsymmetrical
shapes, except single angles. However, the structural engineer is advised to have
an appropriate investigation and good engineering judgment for this section to be
applied.
Proportions for Beams and Girders
According to the governing code, this section states the requirements of members
proportioned on the basis of flexural strength of the section. Specific provisions
apply for particular members such as beams and girders with hole reductions, for
I – shaped members, members using cover plates and built – up beams.
4-64
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Example: I-Shaped Flexural Member in Minor-Axis Bending
Selecting a member with given uniform loads, and limit to live load deflection
L/240. The beam is simply supported and is braced at ends only.
1. Determine material properties such as ASTM Designation, Fy and Fu (AISC Table
2-3).
2. Calculate the required flexural strength, Mu (LRFD) or Ma (ASD). Note that Mu is
a factored load.
3. Determine the minimum required moment of inertia.
Solve for Δmax and Ireq.
4. Choose the lightest section from AISC Manual Table 3-3.
The structural engineer should consider deflection governing the design for
light sections.
5. Select a trial section and take note of material’s geometric properties, i.e. Sy, Zy, Iy.
6. Check flange slenderness, i.e. if compact or noncompact.
7. Calculate the nominal flexural strength, Mn.
8. Determine the available flexural strength.
Using LRFD
Φ = 0.90
ΦMn > Mu
Using ASD
Ω = 1.67
Mn/Ω > Ma
Example: HSS-Flexural Member with Noncompact Flanges
Selecting a member with given uniform loads, and limit to live load deflection
L/240. The beam is simply supported and is braced at ends only. Selection of
member using AISC Manual.
1. Determine material properties such as ASTM Designation, Fy and Fu (AISC
Table 2-3).
2. Determine the required strength, Mu (LRFD) or Ma (ASD). Note that Mu is a
factored load.
3. Compute for the minimum moment of inertia, Imin.
Solve for Δmax
4. Select HSS member with a minimum Ix from (3) using ASIC Table 1-11; and
having adequate available flexural strength using ASIC Table 3-12.
5. Determine required strength using ASIC Table 3-12.
6. Check available flexural strength.
4-69
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
ΦMn > Mu
Using ASD
Ω = 1.67
Mn/Ω > Ma
The structural engineer shall take note that for a combination of non-compact
flange and compact web, the specification provides different equation in solving
for the nominal flexural strength.
Example: HSS Flexural Member with Slender Flanges
Verifying a member strength with given nominal uniform loads (dead load and
live load) and limit to live load deflection L/240.
1. Determine material properties such as ASTM Designation, Fy and Fu (AISC
Table 2-3).
2. Compute for the required flexural strength, Mu (LRFD) or Ma (ASD). Note that
Mu is a factored load.
3. Obtain member flexural strength using AISC Manual Table 3-13.
Using LRFD
ΦMn > Mu
Using ASD
Mn/Ω > Ma
4. Check for member deflection. The deflection should be less than the given
limit to live load deflection of L/240.
Example D9. Pipe Flexural Member
Selecting a member with given uniform loads assuming the beam has no limit to
deflection. The beam is simply supported and is braced at ends only.
1. Determine material properties such as ASTM Designation, Fy and Fu (AISC
Table 2-3).
2. Compute for the required flexural strength, Mu (LRFD) or Ma (ASD). Note that
Mu is a factored load.
3. Select a member from AISC Manual Table 3-15 with the required flexural
strength.
4. The available flexural strength of the member shall then be greater than the
required flexural strength.
Using LRFD
ΦMn > Mu
Using ASD
Mn/Ω > Ma
4-71
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
4.5.10
4.5.11
Plate Girders
This topic is included in Section 4.5.11.
Connections
This section shall apply to design of connections subjected and/or not subjected to
cyclic loading as specified in NSCP 2010, Referral Code of the NBCP. The DGCS
shall also adopt additional design guidelines from international standards.
Bolts and Threaded Parts
The provisions set forth by the governing code shall apply to the use of high –
strength bolts. As mentioned, all joint surfaces shall be free of scale, except tight
mill scale. Installation shall be assured by the any of these methods: turn – of – nut
method, direct tension indicator, calibrated wrench or alternative design bolt.
The structural engineer shall refer to the governing code for the size and use of
holes and the minimum and maximum dimensions for both spacing and edge
distance. Design strengths shall be determined based on the following limit states:
tensile rupture, shear rupture, combined tensile and shear rupture, slip and
tension and shear in slip – critical connections.
Welds
The provisions shall apply to groove welds, fillet welds, plug and slot welds and
combination of welds. The governing code specifies the effective area and the
limitations for each kind in terms of the minimum requirements for application.
Affected Elements of Members and Connecting Elements
According to the governing code, this section shall apply to elements of members
at connections and connecting elements such as plates, gussets, angles and
brackets. The design strengths and allowable strengths shall be determined based
on the following limit states: for elements in tension – tensile yielding and tensile
rupture; shear – shear yielding and shear rupture; block shear – block shear
rupture; and in compression – yielding and buckling.
Fillers
In choosing electrode for use in completing joint – penetration grove welds
subject to tension normal to the effective area, the electrode shall comply with the
requirements for matching filler metals provided by the governing code.
Splices
When tensile forces due to applied tension or flexure are to be transmitted
through splices in heavy sections, by complete penetration groove welds, material
notch – toughness requirements, weld access hole details and thermal cut surface
preparation and inspection requirements shall apply. This provision, however, is
not applicable to built – up members welded prior to shape assembly. This section
is as stated in the governing code.
4-77
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Bearing Strength
The provisions for bearing strength specified in the code shall apply to the bearing
strength at bolt holes to be determined based on the limit state of bearing. As
mentioned in the governing code, the sum of the bearing resistances of the
individual bolts shall apply to connections.
The structural engineer is advised to check the bearing strength for bearing type
and slip – critical conditions.
Column Bases and Bearing on Concrete
According to governing code the provisions are made for transferring column
loads and moments to the footings and foundations.
The design strength and allowable bearing strength shall be determined based on
the limit state of concrete crushing.
Anchor Rods and Embedments
The anchor rods, as specified in the code, shall be designed to provide the
required resistance to loads on the structure at the base of columns. The design
shall be in accordance with requirements for threaded parts. The designer shall
take into consideration the base plate hole size, anchor rod setting tolerance, and
the horizontal movement of the column when designing anchor rods resisting
horizontal forces on the base plate.
Flanges and Webs with Concentrated Forces
As specified in the governing code, this section shall apply to single – and double –
concentrated force applied normal to the flange(s) of wide flange sections and
similar built – up shapes.
The structural engineer shall take note that provision for the use of stiffeners shall
apply to members with required strength exceeding the available strength. Such
provisions are available in the governing code.
Example: All-Bolted Double Angle Connection
Selecting an all bolted double-angle connection between a given and column
flange supporting a given beam end reactions, dead and live loads. Also given are
bold diameter and hole dimension.
1. Determine material properties such as ASTM Designation, Fy and Fu (AISC
Table 2-3) and geometric properties (AISC Table 1-1).
2. Determine required bolt strength, Ru (LRFD) or Ra (ASD). Note that Ru is
factored. Check governing specifications for limiting states in bearing, shear
yielding, shear rupture, and block shear rupture on the angles, and shear on
the bolts.
Using LRFD
ΦRn > Ru
4-78
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Using ASD
Rn/Ω > Ra
3. For uncoped beams, beam web shall be checked for bolt bearing.
Using LRFD
ΦRn > Ru
Using ASD
Rn/Ω > Ra
4. Supporting member flange shall be checked for bolt bearing.
Using LRFD
ΦRn > Ru
Using ASD
Rn/Ω > Ra
Example: Bolted/Welded Double Angle Connection
Substituting welds for bolts in the support legs of a double angle connection using
a given weld electrode.
1. Determine material properties such as ASTM Designation, Fy and Fu (AISC
Table 2-3) and geometric properties (AISC Table 1-1).
2. Determine required weld strength, Ru (LRFD) or Ra (ASD). Note that Ru is
factored. Select weld size and length which shall have a tfmin lesser than bolt tf.
Using LRFD
ΦRn > Ru
Using ASD
Rn/Ω > Ra
3. Determine minimum angle thickness, tmin. Check if tmin < weld size.
4. Checks shall be done on the following limit states: bolt shear and the angles for
bolt bearing, shear yielding, shear rupture, and block shear rupture.
Using LRFD
ΦRn > Ru
Using ASD
Rn/Ω > Ra
5. Beam web shall be checked for bolt bearing.
Using LRFD
ΦRn > Ru
Using ASD
4-79
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Rn/Ω > Ra
6. Supporting member flange shall be checked for bolt bearing.
Using LRFD
ΦRn > Ru
Using ASD
Rn/Ω > Ra
4.5.14
Factored load ≤ Factored Strength
Example: All Welded Double Angle Connection
As mentioned in NSCP 2010, the design shall be in accordance with the following
equation:
Designing an all welded double angle connection between a given beam and
column flange through the aid of AISC Table 10-3. Also given is the weld electrode.
1. Determine material properties such as ASTM Designation, Fy and Fu (AISC
Table 2-3) and geometric properties (AISC Table 1-1).
where:
2. Determine required weld strength, Ru (LRFD) or Ra (ASD). Note that Ru is
factored.
Using ASD
Rn/Ω > Ra
3. Determine minimum angle thickness, tfmin. Check if tmin < tf.
4.5.12
4.5.13
4. Minimum angle thickness shall be checked, tmin.
Column Base Plate and Beam Bearing Plates
This topic is included in Section 4.5.11.
Cold-Formed Steel Structures
This section shall apply to cold-formed steel structural members design as
specified in NSCP 2010, Referral Code of the NBCP. The DGCS shall also adopt
additional design guidelines from international standards. Such standards are as
mentioned in “Material” and other reference codes:


4-80
American Iron and Steel Institute 1969: Specification for the Design of ColdFormed Steel Structural Members
4.5.15
4.5.16
Ru = φRn
Ru
=
required strength
Φ
=
resistance factor
Rn
Design the weld between the angle leg and the beam to weld such that
twmin is lesser than tw.
ΦRn > Ru
Load and Resistance Factor Design
To satisfy the requirements of the governing code, the design strength of each
structural component shall be equal or shall exceed the required strength
determined on the basis of LRFD load combinations. This can be written as:
Note: The example shown above shall be applicable when the coped section does
not control the design. If the relative size of the cope to the overall size of the
beam cannot be determined, use AISC Manual Part 9.
Using LRFD
This section pertains to the design of structural members cold-formed to shape
from carbon or low-alloy steel sheet, strip, plate, or bar not more than 25 mm in
thickness and used for load-carrying purposes specified in in the governing code.
The structural engineer shall apply specifications such as the use of design
strength method, second-order analysis and additional provisions which he/she
may deem adequate for the purpose.
φRn
=
=
nominal strength
design strength
Cold-Rolled Steel and Built-Up Members
This section shall be in conjunction with “6.11. Cold-Formed Steel Structures” as
presented in NSCP 2010, Referral Code of the NBCP.
Plastic Design
The purpose of this Specification is to provide criteria using plastic design as
presented in various sections in NSCP 2010, Referral Code of the NBCP. The DGCS
shall also adopt additional design guidelines from international standards.
Members designed by plastic design would reach the point of failure under the
factored loads but are safe under actual service or working loads.
Design Consideration
Although plastic design is specified in design codes, local and international, the
governing design standard for structural members is the Load and Resistance
Factor Design.
American Iron and Steel Institute 2001: Specification for the Design of ColdFormed Steel Structural Members
4-81
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design procedure:
1. After determining the design stresses from structural analysis (e.g. shear and
moment diagram). Maximum moments and shears are determined.
2. Use these maximum moment and shear in determining the section required to
satisfy the following:



Allowable stresses based on wood specie to be used and stress grade
of the material
Factoring in the different capacity reduction factors
Case to case detailing issues that may affect design (e.g. notches)
3. Detail as necessary
Flexure
According to NSCP Section 616.2.1, a beam of circular section may be assumed to
have the same strength in flexure as a square beam having the same crosssectional area. If a circular beam is tapered, it shall be considered a beam of
variable cross section. In NSCP Section 616.2.2, it is stated that if possible,
notching of beams should be avoided. Notches in sawn lumber bending members
shall not exceed one-sixth the depth of the member and shall not be located in the
middle third of the span.
As in all flexural members, the standard formula for flexure is:
𝑓𝑓𝑏𝑏 =
𝑀𝑀𝑀𝑀
𝐼𝐼
but since we deal mostly with rectangular sections:
Horizontal Shear
𝑓𝑓𝑏𝑏 =
6𝑀𝑀
𝑏𝑏𝑑𝑑 2
The maximum horizontal shear stress in a solid-sawn wood shall not exceed that
calculated by means of:
𝑓𝑓𝑣𝑣 =
3𝑉𝑉
2𝑏𝑏𝑏𝑏
The actual shear fv shall not exceed the allowable for the species and the grade as
given in NSCP Table 6.1 adjusted for duration of loading, as provided in NSCP
Section 615.3.4.
Horizontal Shear in Notched Beams
When rectangular-shaped girder, beams or joists are notched at points of support
on the tension side, they shall meet the design requirements of that section in
bending and in shear. Provisions and equations to be used regarding horizontal
shear in notched beams are stated in NSCP Section 616.4.
4-83
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design of Joints in Shear
Eccentric connector and bolted joints and beams support by connectors or bolt
shall be designed so that fv does not exceed the allowable unit stresses in
horizontal shear:
where:
𝑓𝑓𝑣𝑣 =
𝑑𝑑𝑒𝑒 (with connectors)
=
𝑑𝑑𝑒𝑒 (with bolts or lag screws) =
3𝑉𝑉
2𝑏𝑏𝑑𝑑𝑒𝑒
depth of the member less the distance from the
unloaded edge of the member to the nearest edge
of the nearest connector.
depth of the member less the distance from the
unloaded edge of the member to the center of the
nearest bolt or lag screw.
Allowable unit stresses in shear for joint involving bot or connectors loaded
perpendicular to grain may be 50% greater than the horizontal shear values as set
forth in NSCP Table 6.1 and, provided that the joint occurs at least five times the
depth of the member from its end. When the joint is less than five times the depth
of the member from its end, the included shear stress is calculated by:
𝑓𝑓𝑣𝑣 =
3𝑉𝑉 𝑑𝑑
( )
2𝑏𝑏𝑑𝑑𝑒𝑒 𝑑𝑑𝑒𝑒
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
For bearing of less than 150 mm in length and not nearer than 75 mm to the end
of a member, the maximum allowable load per square mm may be obtained by
multiplying the allowable unit stresses in compression perpendicular to grain by
the factor indicated by:
𝐶𝐶𝑏𝑏 =
𝑙𝑙𝑏𝑏 + 0.375
𝑙𝑙𝑏𝑏
In which 𝑙𝑙𝑏𝑏 is the length of bearing in mm measured along the grain of the wood.
The multiplying factors for indicated length of bearing on such small areas as
plates and washers is provided in Table 4-29.
Table 4-29
Multiplying Factors for Length of Bearing on Small Areas
Length of Bearing (mm)
13
25
38
50
75
100
150 or more
Multiplying Factor
1.75
1.38
1.25
1.19
1.13
1.10
1.00
In using the preceding equation and table for round washers or bearing areas,
use a length equal to the diameter.
In joists supported on a ribbon or ledger board and spiked to the studding, the
allowable stress in compression perpendicular to grain may be increased 50%.
And the 50% increase in design values for shear in joints does not apply.
Compression Perpendicular to Grain
In application where deformation is critical, the following equation shall be used
to calculate the compression-perpendicular-to-grain design values.
where:
𝐹𝐹𝐶𝐶⊥ =
′
=
𝐹𝐹𝐶𝐶⊥
𝐹𝐹𝑐𝑐⊥ ′ = 0.73𝐹𝐹𝑐𝑐⊥
compression-perpendicular-to-grain values from NSCP Table 6.1
critical compression-perpendicular-to-grain value
The duration of load modification factors given in NSCP Section 615.3.4 shall not
apply to compression-perpendicular-to-grain values for sawn lumber.
The allowable unit stresses for compression perpendicular to grain in NSCP Table
6.1 and 6.17 apply to bearings of any length at the ends of the beam and to all
bearing 150 mm or more in length at any other location.
4-84
4-85
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
4.6.4
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Column Design
Flexure and Axial Compression
According to NSCP Section 617, a simple column consists of a single piece or of
pieces properly glued together to form a single members. Spaced columns are
formed of two or more individual members with their longitudinal axes parallel,
separated at the ends and middle points of their length by blocking and joined at
the ends by timber connectors capable of developing the required shear
resistance. Built-up columns, other than connector-joined spaced columns and
glued-laminated columns, shall not be designed as solid columns.
Members subjected to both flexure and axial compression shall be proportioned
that:
𝑓𝑓𝑏𝑏𝑏𝑏
𝑓𝑓𝐶𝐶
≤1
𝐹𝐹𝑐𝑐 ′ 𝐹𝐹′𝑏𝑏𝑏𝑏 − 𝐽𝐽𝑓𝑓𝑐𝑐
The value of J shall be derived as:
For simple solid columns, l/d shall not exceed 50.
4.6.5
The effective column length, le, shall be used in design given in NSCP Section
617.3. Actual column length, l, may be multiplied by the factors given the table in
NSCP Section 617.3.
Except that J shall not be less than zero nor greater than one (0 ≤ J ≤ 1).
F’c and K shall be determined in accordance with the provision in NSCP Section
617.3, except (1) when checking the design in the plane of bending the
slenderness ratio, 𝑙𝑙𝑒𝑒 /d, in the plane of bending shall be used to calculate F’c and J
and (2) when checking the design perpendicular to the plane of bending the
slenderness ratio, 𝑙𝑙𝑒𝑒 /d in the plane of bending shall be used to calculate F’c and J
shall be set equal to zero.
Flexure And Axial Tension
Members subjected to both flexure and axial tension shall be so proportioned
that:
𝑓𝑓𝑏𝑏
𝑓𝑓𝑡𝑡
+
≤1
𝐹𝐹𝑡𝑡 𝐹𝐹𝑏𝑏 ∗
where:
𝐹𝐹𝑏𝑏 ∗
𝐹𝐹𝑏𝑏 ∗∗
𝐹𝐹𝑇𝑇 ′
𝑓𝑓𝑡𝑡
𝑓𝑓𝑏𝑏
𝑓𝑓𝑏𝑏 − 𝑓𝑓𝑡𝑡
≤1
𝐹𝐹𝑏𝑏 ∗∗
where:
𝐹𝐹𝑏𝑏 (𝐶𝐶𝐷𝐷 )(𝐶𝐶𝑀𝑀 )(𝐶𝐶𝑡𝑡 )(𝐶𝐶𝑣𝑣 ) for glulam
=
𝐹𝐹𝑏𝑏 (𝐶𝐶𝐷𝐷 )(𝐶𝐶𝑀𝑀 )(𝐶𝐶𝑡𝑡 )(𝐶𝐶𝐿𝐿 )(𝐶𝐶𝐹𝐹 )(𝐶𝐶𝑟𝑟 )(𝐶𝐶𝑖𝑖 ) for sawn lumber
=
=
=
Truss Compression Chords
tabulated bending design value multiplied by all applicable
adjustment factors except volume factor,𝐶𝐶𝑣𝑣
=
=
4.6.6
In the case of spaced columns, this combined stress formula maybe applied only if
the bending is in a direction parallel to the greater d of the individual member.
𝐹𝐹𝑏𝑏 (𝐶𝐶𝐷𝐷 )(𝐶𝐶𝑀𝑀 )(𝐶𝐶𝑡𝑡 )(𝐶𝐶𝐹𝐹 )(𝐶𝐶𝑟𝑟 )(𝐶𝐶𝑖𝑖 ) for sawn lumber
tabulated bending design value multiplied by all applicable
adjustment factors except beam stability factor,𝐶𝐶𝐿𝐿
=
Spaced Columns
Effect of buckling of a 50 mm by 200 mm or smaller truss compression chord
having effective buckling lengths of 2.40 m or less with 9 mm or thicker plywood
sheathing nailed to the narrow face of the chord in accordance with appreciate
standards shall be determined from the equation:
=
=
𝑘𝑘 − 11
𝐸𝐸
𝐾𝐾 = 0.671 √
𝐹𝐹𝑐𝑐
Combined Load Design
and
𝐽𝐽 =
𝑙𝑙𝑒𝑒
− 11
𝑑𝑑
𝐹𝐹𝑏𝑏 (𝐶𝐶𝐷𝐷 )(𝐶𝐶𝑀𝑀 )(𝐶𝐶𝑡𝑡 )(𝐶𝐶𝐿𝐿 ) for glulam
allowable tension design value parallel to grain
actual unit stress in tension parallel to grain
actual unit stress for extreme fiber in bending
𝐶𝐶𝑇𝑇 =
1 + 0.62 𝑙𝑙𝑒𝑒
𝐸𝐸0.05
𝐶𝐶𝑇𝑇
=
buckling of the stiffness factor
𝑙𝑙𝑒𝑒
=
effective buckling length used in design of chord for
compression loading
=
Modulus of Elasticity from tables of allowable unit stress,
N/mm2
𝐸𝐸0.05
E
=
=
0.819E for machine-stress-rated lumber
0.589E for visually graded lumber
The value of 𝐶𝐶𝑇𝑇 determined from this equation are for wood seasoned to a
moisture content of 19% or less at the time the plywood is nailed to the chord. For
4-86
4-87
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Bolts
wood that is unseasoned at the time of plywood attachment, 𝐶𝐶𝑇𝑇 shall be
determined from
𝐶𝐶𝑇𝑇 =
NSCP Table 6.17 provides the safe loads in KN for bolts in shear in seasoned
lumber.
1 + 0.331 𝑙𝑙𝑒𝑒
𝐸𝐸0.05
When wood is connected to concrete or masonry, the allowable shear value is
permitted to be “one half the tabulated double shear values for a wood member
twice the thickness of the member attached to the concrete or masonry".
For chords with an effective buckling length greater than 2.40 m, 𝐶𝐶𝑇𝑇 shall be taken
as the value for a chord having an effective length of 2.40 m.
The buckling stiffness factor does not apply to short columns or trusses used
under wet conditions. The allowable unit compressive stress shall be modified by
the buckling stiffness factor when a truss chord is subjected to combined flexure
and compression and the bending moment in the direction that induces
compression stresses in the chord face to which the plywood is attached.
Nails and Spikes
Safe Lateral Strength: When used to fasten wood members together. The
maximum load causing shear and bending that a common wire nail driven
perpendicular to grain of the wood shall not exceed the safe lateral strength of the
wire nail or spike in NSCP Table 6.21.
The buckling stiffness factor 𝐶𝐶𝑇𝑇 shall apply as follows:
𝑙𝑙
𝑑𝑑
Short column ( 𝑒𝑒 𝑜𝑜𝑜𝑜 11 𝑜𝑜𝑜𝑜 𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙)
Use only 2/3 of the capacity of nail driven perpendicular to the grain when wire
nail is driven parallel to the grain of the wood.
Toenails shall be designed using only 5/6 of the lateral load allowed for nails
driven perpendicular to the grain.
𝐹𝐹′𝑐𝑐 = 𝐹𝐹𝑐𝑐
𝑙𝑙
𝑑𝑑
Intermediate columns ( 𝑒𝑒 𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔 𝑡𝑡ℎ𝑎𝑎𝑎𝑎 11 𝑏𝑏𝑏𝑏𝑏𝑏 𝑙𝑙𝑙𝑙𝑙𝑙𝑙𝑙 𝑡𝑡ℎ𝑎𝑎𝑎𝑎 𝐾𝐾):
K = 0.671√𝐶𝐶𝑇𝑇 E/𝐹𝐹𝐶𝐶
𝑙𝑙
𝑑𝑑
1 𝑙𝑙𝑒𝑒 /𝑑𝑑 4
[
) ]
𝐹𝐹′𝑐𝑐 = 𝐹𝐹𝐶𝐶 1 − (
3 𝐾𝐾
Long column ( 𝑒𝑒 𝑜𝑜𝑜𝑜 𝐾𝐾 𝑜𝑜𝑜𝑜 𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔)
4.6.7
𝐹𝐹′𝑐𝑐 =
Compression at Angle to Grain
0.30 𝐸𝐸𝐶𝐶𝑇𝑇
(𝑙𝑙𝑒𝑒 /d)2
4.6.9
Safe Resistance to Withdrawal: NSCP Table 6.21 provides the safe resistance of
nails wire driven perpendicular to grain of wood against withdrawal from
anchorage.
Working Stresses for Timber
The working stress for visually stress-graded unseasoned structural timber is
provided in Table 4-30. The relative densities for species to determine allowable
loads is provided in Table 4-31.
The allowable unit stress in compression at an angle of load to grain between 0𝑜𝑜
and 90𝑜𝑜 shall be computed from the Hankinson Equation as follows:
𝐹𝐹𝑛𝑛 =
4.6.8
𝐹𝐹𝐶𝐶 𝐹𝐹𝐶𝐶⊥
2
𝐹𝐹𝐶𝐶 𝑠𝑠𝑠𝑠𝑠𝑠 𝜃𝜃 + 𝐹𝐹𝐶𝐶⊥ 𝑐𝑐𝑐𝑐𝑐𝑐 2 𝜃𝜃
Allowable values 𝐹𝐹𝐶𝐶 shall be adjusted for duration of load before use in
Hankinson’s Equatioon. Values of 𝐹𝐹𝑛𝑛 and 𝐹𝐹𝐶𝐶⊥ are not subjected to duration of load
modifications.
Timber Connectors and Fasteners
Mechanical wood connectors and fasteners are used to transfer member forces to
other structural elements. NSCP Section 619 provides us the allowable loads and
installation of timber connectors and fasteners. NSCP Tables 6.2, 6.17, 6.19 and
6.20 are the pertinent references for the allowable loads and installation for
timber connectors.
4-88
4-89
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 4-30
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Working Stresses for Visually Stress-Graded Unseasoned Structural
Timber of Philippine Woodsa
80% Stress Grade
80% Stress Grade
Species
(Common and Botanical Names)
Bending
and Tension
Parallel to
Grain
Modulus of
Elasticity
in Bending
Compression
Parallel to
Grain
Compression
P’pendicular
to Grain
Shear
Parallel
to Grain
(1)
(2)
(3)
×103
MPa
(4)
(5)
(6)
MPa
MPa
MPa
MPa
I.
II.
III.
4-90
High Strength Group
Species
(Common and Botanical Names)
Bending
and Tension
Parallel to
Grain
Modulus of
Elasticity
in Bending
Compression
Parallel to
Grain
Compression
P’pendicular
to Grain
Shear
Parallel
to Grain
(1)
(2)
(4)
(5)
(6)
MPa
(3)
×103
MPa
MPa
MPa
MPa
Lanutan-bagyo [Gonystylus macrophyllum
(miq.) Airy Shaw]
15.0
6.06
8.96
2.02
1.84
Lauan (Shorea spp.)
13.9
5.83
8.18
1.72
1.48
Agoho (Casuarina equisetifolia Forst)
26.3
8.22
14.5
5.91
2.95
Malaanonang (Shorea spp.)
13.8
5.41
8.54
1.96
1.59
Liusin [Parinari corymbosa (Blume) Miq.]
25.0
9.36
15.6
4.31
2.64
Malasaging (Aglaia spp.)
16.8
5.94
9.51
2.92
1.85
Malabayabas (Tristania spp.)
28.7
8.30
15.8
8.70
3.02
Malugai (Pometia spp.)
15.4
6.30
9.33
3.07
2.07
Manggachapui (Hopea spp.)
25.8
9.63
16.0
6.03
2.78
Miau (Dysoxylum spp.)
15.7
6.50
8.83
2.78
2.06
Molave (Vitex parviflora Juss.)
24.0
6.54
15.4
6.34
2.88
Nato (Palaquium spp.)
16.2
5.56
9.17
2.33
1.98
Narig (Vatica spp.)
21.8
8.33
13.7
4.97
2.61
Palosapis (Anisoptera spp.)
13.8
5.98
8.38
2.73
1.68
Sasalit [Teijmanniodendron ahernianum
(Merr) Bkh.]
31.3
9.72
21.60
10.2
3.38
Pine (Pinus spp.)
14.7
6.66
8.29
1.88
1.56
Yakal (Shorea spp.)
24.5
9.78
15.8
6.27
2.49
Salakin (Aphanamixis spp.)
15.7
5.67
8.83
2.94
1.88
Vidal lanutan [Hibiscus campylosiphon
Turcz. Var. glabrecens (Har. Ex. Perk.)]
19.5
5.83
8.54
2.65
2.39
Antipolo (Arthocarpus spp.)
18.6
5.35
10.8
3.90
2.06
Binggas (Terminalia spp.)
18.9
6.57
11.4
3.27
2.24
Almaciga [Agathis dammara (Lamb.) Rilh.]
11.8
5.47
6.27
1.44
1.47
Bokbok (Xanthophyllum excelsum (Blume)
Miq.]
18.1
6.36
11.3
3.41
2.18
Bayok (Pterospermum spp.)
12.6
4.75
7.33
1.30
1.20
Dao (Dracontomelon spp.)
16.2
5.43
9.44
2.27
1.92
Lingo-lingo (Vitex turczaninowii Merr.)
13.2
4.13
6.85
2.00
1.66
Gatasan [Garcinia venulosa (Blanco)
Choisy]
20.8
6.84
13.5
3.52
2.36
Mangasinoro (Shorea spp.)
12.8
5.36
7.46
1.97
1.44
Raintree [Samanea saman (Jacq.) Merr.]
11.9
2.75
7.23
3.32
2.07
Guijo (Shorea spp.)
21.8
8.47
13.2
4.26
2.40
Yemane (Gmelina arborea R. Br.)
12.6
4.09
7.87
3.40
1.96
Kamagong (Diospyros spp.)
20.9
7.20
11.7
4.39
2.47
Kamatog [Erythrophloeum densiflorum
(Elm) Merr.]
19.0
7.56
11.2
3.95
2.35
Katmon (Dillenia spp)
18.4
6.82
11.9
4.84
2.29
Kato (Amoora spp.)
18.4
8.04
10.6
3.46
1.96
Lomarau (Swintonia foxworthyi Elm.)
19.8
7.92
11.8
2.98
2.18
Mahogany, Big-leafed (Swietenia
macrophylla King)
16.5
4.66
10.5
3.83
2.71
Makaasim (Sysygium nitidum Benth)
20.5
6.72
11.4
3.70
2.40
Malakauayan [Decusocarpus
philippinensis (Fxw.) de Laub.]
18.9
6.66
11.12
2.32
2.14
Narra (Pterocarpus indicus Willd)
18.0
5.94
11.4
3.07
1.91
Pahutan (Mangifera spp.)
16.6
6.53
10.0
2.50
2.05
Moderately High Strength Group
IV.
63% Stress Grade
I.
Medium Strength Group
Apitong (Dipterocarpus spp.)
16.5
7.31
9.56
2.20
1.73
Bagtikan [Parashorea malaanonan
(Blanco) Merr.]
16.6
6.48
9.89
2.33
1.82
Dangkalan (Calophyllum spp.)
16.3
6.38
9.20
2.48
1.98
Gisau (Canarium spp.)
14.3
5.33
8.16
1.99
1.90
Moderately Low Strength Group
II.
Species
(Common and Botanical Names)
Bending and
Tension
Parallel to
Grain
Modulus of
Elasticity in
Bending
Compression
Parallel to
Grain
Compression
P’pendicular
to Grain
Shear
Parallel
to Grain
(1)
(7)
(9)
(10)
(10)
MPa
(8)
×103
MPa
MPa
MPa
MPa
Agoho (Casuarina equisetifolia Forst)
20.7
6.47
11.4
4.65
2.32
Liusin [Parinari corymbosa (Blume) Miq.]
19.7
7.37
12.3
3.39
2.08
Malabayabas (Tristania spp.)
22.6
6.53
12.5
6.85
2.38
Manggachapui (Hopea spp.)
20.3
7.58
12.6
4.75
2.19
Molave (Vitex parviflora Juss.)
18.9
5.15
12.1
5.00
2.27
Narig (Vatica spp.)
17.2
6.56
10.8
3.92
2.06
Sasalit [Teijmanniodendron ahernianum
(Merr) Bkh.]
24.7
7.65
17.0
8.07
2.67
Yakal (Shorea spp.)
19.3
7.70
12.0
4.94
1.96
High Strength Group
Moderately High Strength Group
4-91
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
63% Stress Grade
III.
4-92
63% Stress Grade
Species
(Common and Botanical Names)
Bending and
Tension
Parallel to
Grain
Modulus of
Elasticity in
Bending
Compression
Parallel to
Grain
Compression
P’pendicular
to Grain
Shear
Parallel
to Grain
Species
(Common and Botanical Names)
Bending and
Tension
Parallel to
Grain
Modulus of
Elasticity in
Bending
Compression
Parallel to
Grain
Compression
P’pendicular
to Grain
Shear
Parallel
to Grain
(1)
(7)
(9)
(10)
(10)
(1)
(7)
(10)
(10)
MPa
MPa
MPa
MPa
(8)
×103
MPa
(9)
MPa
(8)
×103
MPa
MPa
MPa
MPa
Antipolo (Arthocarpus spp.)
14.7
4.21
8.53
3.07
1.62
Binggas (Terminalia spp.)
14.9
5.17
8.98
2.57
1.77
Almaciga [Agathis dammara (Lamb.) Rilh.]
9.26
4.30
4.94
1.13
1.16
Bokbok (Xanthophyllum excelsum (Blume)
Miq.]
14.3
5.01
8.90
2.68
1.72
Bayok (Pterospermum spp.)
9.94
3.74
5.78
1.03
0.95
Dao (Dracontomelon spp.)
12.8
4.28
7.43
1.79
1.51
Lingo-lingo (Vitex turczaninowii Merr.)
10.4
3.25
5.39
1.58
1.31
Gatasan [Garcinia venulosa (Blanco)
Choisy]
16.4
5.39
10.6
2.77
1.86
Mangasinoro (Shorea spp.)
10.0
4.22
5.87
1.55
1.14
Raintree [Samanea saman (Jacq.) Merr.]
9.37
2.16
5.70
2.61
1.63
Guijo (Shorea spp.)
17.1
6.67
10.4
3.35
1.89
Yemane (Gmelina arborea R. Br.)
9.90
3.22
6.20
2.68
1.55
Kamagong (Diospyros spp.)
16.6
5.67
9.21
3.46
1.95
Kamatog [Erythrophloeum densiflorum
(Elm) Merr.]
15.0
5.95
8.79
3.11
1.85
Katmon (Dillenia spp)
14.8
5.37
9.38
3.81
1.80
Kato (Amoora spp.)
14.5
6.33
8.34
2.73
1.54
Lomarau (Swintonia foxworthyi Elm.)
15.6
6.24
9.30
2.34
1.71
Mahogany, Big-leafed (Swietenia
macrophylla King)
13.0
3.67
8.24
3.01
2.13
Makaasim (Sysygium nitidum Benth)
16.1
5.29
8.95
2.92
1.89
Malakauayan [Decusocarpus
philippinensis (Fxw.) de Laub.]
14.9
5.24
8.79
1.83
1.69
Narra (Pterocarpus indicus Willd)
14.2
4.68
8.97
2.42
1.51
Pahutan (Mangifera spp.)
13.1
5.15
7.88
1.97
1.61
IV.
Moderately Low Strength Group
50% Stress Grade
I.
Medium Strength Group
Species
(Common and Botanical Names)
Bending
and Tension
Parallel to
Grain
Modulus of
Elasticity
in Bending
Compression
Parallel to
Grain
Compression
P’pendicular
to Grain
Shear
Parallel
to Grain
(1)
(12)
(14)
(15)
(16)
MPa
(13)
×103
MPa
MPa
MPa
MPa
Agoho (Casuarina equisetifolia Forst)
16.4
5.14
9.06
3.69
1.84
Liusin [Parinari corymbosa (Blume) Miq.]
15.6
5.85
9376
2.69
1.65
Malabayabas (Tristania spp.)
17.9
5.19
9390
5.44
1.89
Manggachapui (Hopea spp.)
16.1
6.02
10.0
3.77
1.74
Molave (Vitex parviflora Juss.)
15.0
4.09
9.60
3.96
1.80
Narig (Vatica spp.)
13.6
5.20
8.59
3.11
1.63
Sasalit [Teijmanniodendron ahernianum
(Merr) Bkh.]
19.6
6.08
13.5
6.40
2.12
Yakal (Shorea spp.)
15.3
3.11
9.55
3.92
1.55
Antipolo (Arthocarpus spp.)
11.6
3.34
6.77
2.44
1.29
High Strength Group
Apitong (Dipterocarpus spp.)
13.1
5.76
7.53
1.73
1.36
Bagtikan [Parashorea malaanonan
(Blanco) Merr.]
13.1
5.10
7.79
1.84
1.43
Dangkalan (Calophyllum spp.)
12.8
5.03
7.24
1.96
1.56
Gisau (Canarium spp.)
11.2
4.20
6.43
1.56
1.49
Lanutan-bagyo [Gonystylus macrophyllum
(miq.) Airy Shaw]
11.8
4.77
7.06
1.59
1.45
Lauan (Shorea spp.)
10.9
4.59
6.44
1.35
1.17
Binggas (Terminalia spp.)
11.8
4.11
7.13
2.04
1.40
Malaanonang (Shorea spp.)
10.9
4.26
6.72
1.54
1.25
11.3
3.97
7.06
2.13
1.36
Malasaging (Aglaia spp.)
13.3
4.68
7.49
2.30
1.46
Bokbok (Xanthophyllum excelsum (Blume)
Miq.]
Malugai (Pometia spp.)
12.1
4.96
7.35
2.42
1.63
Dao (Dracontomelon spp.)
10.1
3.39
5.90
1.42
1.20
Miau (Dysoxylum spp.)
12.3
5.12
6.96
2.19
1.62
Gatasan [Garcinia venulosa (Blanco)
Choisy]
13.0
4.27
8.42
2.20
1.47
Nato (Palaquium spp.)
12.7
4.38
7.22
1.84
1.56
Guijo (Shorea spp.)
13.6
5.30
8.22
2.66
1.50
Palosapis (Anisoptera spp.)
10.9
4.71
6.60
2.15
1.33
Kamagong (Diospyros spp.)
13.1
4.50
7.31
2.74
1.54
Kamatog [Erythrophloeum densiflorum
(Elm) Merr.]
11.9
4.72
6.98
2.47
1.47
Katmon (Dillenia spp)
11.7
4.26
7.44
3.03
1.43
Kato (Amoora spp.)
11.5
5.02
6.62
2.17
1.23
Lomarau (Swintonia foxworthyi Elm.)
12.4
4.95
7.38
2.86
1.36
Pine (Pinus spp.)
11.6
5.24
6.53
1.48
1.23
Salakin (Aphanamixis spp.)
12.4
4.47
6.96
2.32
1.48
Vidal lanutan [Hibiscus campylosiphon
Turcz. Var. glabrecens (Har. Ex. Perk.)]
15.4
4.59
6.73
2.09
1.88
II.
Moderately High Strength Group
4-93
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
50% Stress Grade
III.
IV.
4-94
Species
(Common and Botanical Names)
Bending
and Tension
Parallel to
Grain
Modulus of
Elasticity
in Bending
Compression
Parallel to
Grain
Compression
P’pendicular
to Grain
Shear
Parallel
to Grain
(1)
(12)
(14)
(15)
(16)
MPa
(13)
×103
MPa
MPa
MPa
MPa
Mahogany, Big-leafed (Swietenia
macrophylla King)
10.3
2.91
6.54
2.39
1.69
Makaasim (Sysygium nitidum Benth)
12.8
4.20
7.10
2.31
1.50
Malakauayan [Decusocarpus
philippinensis (Fxw.) de Laub.]
11.8
4.16
6.98
1.45
1.34
Narra (Pterocarpus indicus Willd)
11.2
3.71
7.12
1.92
1.20
Pahutan (Mangifera spp.)
10.4
4.08
6.25
1.56
1.28
Apitong (Dipterocarpus spp.)
10.3
4.57
5.97
1.37
1.08
Bagtikan [Parashorea malaanonan
(Blanco) Merr.]
10.4
4.05
6.18
1.46
1.14
Dangkalan (Calophyllum spp.)
10.2
3.99
5.75
1.55
1.24
Gisau (Canarium spp.)
8.93
3.33
5.10
1.24
1.18
Lanutan-bagyo [Gonystylus macrophyllum
(miq.) Airy Shaw]
9.39
3.79
5.60
1.26
1.15
Lauan (Shorea spp.)
8.68
3.64
5.11
1.07
0.93
Malaanonang (Shorea spp.)
8.63
3.38
5.34
1.23
0.99
Malasaging (Aglaia spp.)
10.5
3.71
5.95
1.83
1.16
Malugai (Pometia spp.)
9.62
3.94
5.83
1.92
1.30
Miau (Dysoxylum spp.)
9.80
4.06
5.52
1.74
1.29
Nato (Palaquium spp.)
10.1
3.48
5.73
1.46
1.24
Palosapis (Anisoptera spp.)
8.65
3.73
5.24
1.70
1.05
Pine (Pinus spp.)
9.19
4.16
5.18
1.18
0.98
Salakin (Aphanamixis spp.)
9.83
3.54
5.52
1.84
1.18
Vidal lanutan [Hibiscus campylosiphon
Turcz. Var. glabrecens (Har. Ex. Perk.)]
12.2
3.64
5.34
1.66
1.50
Almaciga [Agathis dammara (Lamb.) Rilh.]
7.35
3.42
3.92
0.90
0.92
Bayok (Pterospermum spp.)
7.89
2.97
4.58
0.81
0.75
Lingo-lingo (Vitex turczaninowii Merr.)
8.27
2.58
4.28
1.25
1.04
Mangasinoro (Shorea spp.)
7.98
3.35
4.66
1.23
0.90
Raintree [Samanea saman (Jacq.) Merr.]
7.43
1.72
4.52
2.07
1.30
Yemane (Gmelina arborea R. Br.)
7.86
2.55
4.92
2.13
1.23
Medium Strength Group
Moderately Low Strength Group
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Test procedures should be able to recreate the material design stresses. In the
absence of a reliable as-built plan, a comprehensive investigation should be
conducted which includes, but not limited to, the use of the following:






Rebound hammer test and concrete coring for compression tests
The PUNDIT (Portable Ultrasonic Nondestructive Digital Indicating Tester)
test for evaluating the uniformity of concrete, locating internal concrete voids
and cracks, and estimating severity of concrete deterioration.
Rebar locator for concrete structures
Corrosion and carbonation tests for concrete
Direct measurement of structural members including plumbness detection
Load testing
Structural analysis based on the test results will then be made to complete the
study.
Analysis may be code based or performance based.
Retrofitting work will follow the results of the structural analysis and review. The
retrofitting shall be dependent of the established criteria (code based or
performance based) and shall be considered on case by case basis depending on
the discovered inadequacies of the structure being investigated.
Code based: the intention of this type of analysis is essentially to bring the
existing structure into a design level consistent with the NSCP.
Performance based: Uses as an objective the "degree of acceptable risk" which
should be agreed upon by stakeholders. The structural engineer may consider, the
acceptable damage to the structure without loss of life. To the owner, the higher
construction cost in case the owner decides on a higher design criteria.
Expected performance level can be one of the four damage states after an
earthquake:




Fully operational – use of structure is the same as before the earthquake
Operational – building suffers some damage but remains functional and will
not collapse.
Life safety – foremost in the consideration is the safety of the occupant and not
the prevention of structural and non structural member failure.
Collapse prevention. – allows minimum design criteria and would require
extensive repair (or demolition) after an earthquake event.
References are:


Earthquake Engineering: From Engineering Seismology to PerformanceBased Engineering by Yousef Bozorgnia, Vitelmo V. Bertero 2004
Fundamentals of Earthquake Engineering, Amr S. Elnashai, Luigi Di Sarno
2008, ISBN 978-0-470-02483-6 (Hbk)
4-97
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures




Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Locations and details, expansion joint detail

Slab opening, corner reinforcements, depression details

Rebar splice, development length, hook schedule

Pipe sleeve on beam, change in elevation of beams

Framing Plans

Stair details
Shearwall and shearwall footing details, ramp details
Elevated water tank detail including concrete saddles
Cistern, septic tank details
Bay sections
Foundation Plan




Foundation plan should contain property line, footing and column
designations
Location of walls with wall footings, slab on fill thickness and rebar size and
spacing
Scale should be consistent with the floor plan scale
Excavation plan
Floor Framing Plans (including deck)



Beam and slab designations, scaled location of beams and columns, floor
openings
Columns terminated at a particular floor should be hatched
Scale should be consistent with the floor plan scale.
Roof Framing Plan





Roof beams, truss, rafters, bracings designations. Scaled location of beams,
truss
Rafters, bracings
Purlin size and spacing call out
Columns terminated at a particular floor should be hatched
Scale should be consistent with the floor plan scale
Schedule and Typical Details





4-102
Slabs, beams, footings showing all necessary dimensions and rebar size and
number
Detailed column section and typical column elevation showing rebars and
splice
Restrictions
Truss and rafter schematic diagrams with sizes and connection/anchoring
detail
Purlin, sagrod, bracing connection details
4-103
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
5.2.2
Availability of Power Source
Availability of power should be known beforehand. The type and characteristics
such as the number of phases, voltage rating and the frequency in Hertz should be
known and available. Samples of electric power source are as follow:
Primary Voltage:








34.5 kV, three-phase, four wire, 60 Hz or
34.5 kV, single-phase, two wire, 60 Hz or
20 kV, single-phase, three-wire, 60Hz or
13.8 kV, three-phase, four wire, 60 Hz or
13.8 kV, single-phase, two wire, 60 Hz or
13.2 kV, three-phase, four wire, 60 Hz or
13.2 kV, single-phase, two wire, 60 Hz or
7.62 kV, single –phase, three-wire, 60 Hz
Secondary Voltage:





5.2.3
460/265 volts, three-phase, four wire, 60 Hz AC or
400/230 volts, three-phase, five wire, 60 Hz AC or
230 volts, three-phase, four wire, 60 Hz AC or
230 volts, single-phase, three wire, 60 Hz AC
230 volts, single phase, 60 Hz AC Multi-ground
Local Power Utility Company Requirements
Follow the rules and regulations of the local electric company, where applicable as
follows:



5-3
For projects requiring new electrical service, the electrical designer shall
coordinate requirements with the local utility service company. For
renovations of and/or additions to existing buildings, the electrical designer
shall investigate the existing electrical service/distribution system and
determine whether sufficient capacity is available to accommodate the new
loads. If applicable, the electrical designer shall inform the electric utility
company of the new service requirements and additional loads.
Major site distribution components, such as medium voltage and low voltage
power feeders, duct banks, and manholes, shall be shown on the civil utility
plans for coordination purposes. The routing of site utilities and location of
manholes should be determined early in the design process.
The service entrance location shall be determined concurrently with the
development of conceptual design. Space planning documents and standards
for equipment furnished by utility companies should be incorporated into the
concept design. Locations for transformers, unit substation, vaults, meters and
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 5-1
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
General Lighting Load Density
Type of Occupancy

Load Density (VA per
m²)
Office Buildings
39
Schools
33
Hospitals
22
Warehouse storages
3
Court Rooms
22
Auditoriums
11
Corridors
6
Clubs
22
Dwelling Units
33
Parking Area
3
Reception & Waiting Area/Lobby
6
Toilet & Washroom
6



The total lighting density for the exterior spaces of buildings shall not exceed the
maximum values for building areas as indicated in Table 5-2.
Maximum Values for Lighting Power for Building Exterior Load Density
Lighting Power
Exit (with or without canopy)
60 W/L.m. of door opening
Entrance (without canopy)
90 W/L.m. of door opening
High Traffic (such as retail, airport)
100 W/m² of area with canopy
Light Traffic (such as office, school)
10 W/m² of area with canopy
Loading Area
3 W/m²
Loading Door
50 W/L.m. of door opening
Total power allowance for the exterior (exclusive
of above allowances) of building perimeter for
buildings of up to 5 storey (above ground) plus
6W/L.m. of building perimeter for each additional
storey
100 W/L.m.
Source: Guidelines on Energy Conserving Design of Buildings (2007 Ed.)


5-5
Loading Docks: Exterior door lighting shall be provided at loading docks.
Fixtures for illumination of the interior of trailers shall be provided at each
truck position.
The basic lighting density for roadway shall not exceed the maximum values
as indicated in Table 5-3.
Maximum Values for Lighting Power for Roads and Ground Load Density
Type of Occupancy
Exterior Lighting
Building Area/Space
Entrances: Lighting fixtures shall be provided at all entrances and exits of
major buildings and shall be connected to the emergency lighting circuit.
Table 5-3
Source: PEC Part 1, Table 2.20.2.3
Table 5-2
Parking lots shall be designed with pole mounted luminaires that is
environment friendly and requires less energy but efficient. Emergency power
shall not be required for parking lot lighting.
Exterior lighting is to comply with the local zoning laws of Barangay,
Municipalities and Cities. Use lighting levels appropriate for exterior areas as
indicated in the available standard references. Flood lighting shall also be
provided if necessary.
Parking and roadway lighting shall be of High Intensity Discharge (HID) lamps
or Light Emitting Diode (LED). The illumination ratios shall not exceed 10 to 1
maximum to minimum ratio and a 4 to 1 average to minimum ratio.
Load Density
(W/m²)
Work Area
2
Activity area for casual use (such as picnic, grounds, gardens, parks)
1
Private driveways/walkways
1
Public driveways/walkways
1.5
Private Parking lots
1.2
Public Parking lots
1.8
Source: Guidelines on Energy Conserving Design of Buildings (2007 Ed.)
5.3.2
Illumination Levels for Various Areas
For lighting levels for interior spaces please refer to the values indicated in Table
5-4 and 5-5. The electrical designer shall have the option to use the manual
calculation and/or the applicable lighting calculation software.
Table 5-4
Recommended Design Illuminance Levels
Task
Lighting for Infrequently Used
Lighting for Working Interiors
Localized lighting for Exacting tasks
Minimum and
Maximum
(Lux)
Application
50-150
Circulation area and Corridors
100-200
Stairs
100-200
Escalators
200-300
Infrequent reading and writing
300-750
General offices, typing and computing
300-750
Conference room
500-1000
Deep-plan general offices
500-1000
Drawing offices
500-1000
Proofreading
750-1500
Designing, architecture and machine
engineering
1000-2000
Detailed and precise work
Source: Guidelines on Energy Conserving Design of Buildings (2007 Ed.)
5-6
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 5-5
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Illuminance Levels (Average)
Area
component of illumination only and ignore the indirect component of light, which
can contribute significantly to the uniformity. However, used within its limits, a
Spacing Criterion can be valuable. To use the Spacing Criterion, multiply the net
mounting height (luminaire to work plane) by the Spacing Criterion number.
Nominal Illuminance Level in
Lumens/m² (lux)
Office Area
Normal work station area, open or closed offices
500
Automated Data Processing (ADP)
500
Conference Rooms
300
Training Rooms
500
Internal Corridors
200
Applicable Lighting Software shall be used to determine the required spacing
considering the technical characteristic of the luminaires to be used.
Public Areas
Entrance Lobbies
200
Elevator Lobbies, Public Corridors
200
Stairwells
200
5.3.4
200
Staff Locker Rooms
200
Storage Rooms, Janitors’ Closets
200
Electrical Rooms, Generator Rooms
200
Mechanical Rooms
200
Communications Rooms
200
Maintenance Shops
200
Loading Docks
200
Trash Rooms
200
Design for glare, contrast, visual comfort and color rendering and correction shall
be considered by the design engineer.
Task lighting shall be used in situations, such as areas of systems furniture, where
the general lighting level would be insufficient for the specific functions required.
Specialty Areas
Dining Areas
150-200
Kitchens
500
Outleased Area
500
Physical Fitness Area
500
Child Care Centers
500
Structured Parking, General Area
50
Structured Parking, Intersections
100
Structured Parking, Entrances
500
5.3.5
5.3.6
U.S. General Services Administration
5.3.3
Lighting Layout
Lighting shall be designed to enhance both the overall building architecture as
well as the effect of individual areas within the building with consideration on
energy efficiency.
For the required spacing with respect to mounting height between luminaires or
lighting outlets shall consider the spacing criteria recommended by the
manufacturer.
Spacing criteria provide the designer with information regarding how far apart
luminaires may be spaced while maintaining acceptable illumination uniformity
on the work plane based on the photometric data of the luminaire to be used.
Criteria for spacing are generally conservative; they take into account the direct
5-7
Office Lighting
Office lighting is generally fluorescent (tubular or CFL) and/or LED type lighting
fixtures utilizing pinlight or downlight. A lighting layout with a fairly even level of
general illumination is desirable. In open office areas with systems furniture
partitions, the coefficient of utilization shall be reduced to account for the light
obstruction and absorption of the partitions.
Support Areas
Toilets
Refer also to the recommendations of the DoE Manual of Practice on Efficient
Lighting.
5.3.7
5.3.8
If the area contains special work stations for computer graphics, dimmable CFL or
LED may be required. If a large area is segregated into areas of high and low
personnel activity, switching design should provide for separate control of lights
in high- and low-activity areas of the area.
Conference Rooms and Training Rooms
These areas shall have a combination of fluorescent (tubular or CFL) and/or
dimmable LED or halogen lighting fixture.
Lobbies, Auditorium and Public Corridors
Special lighting design concepts shall be applied in these areas. The lighting design
shall be an integral part of the architecture. Wall fixtures or combination wall and
ceiling fixtures shall be considered in corridors to help break the monotony of a
long, plain space.
Mechanical and Electrical Areas
Lighting in equipment rooms or closets shall be provided by industrial-type
fluorescent fixtures or vapor-tight fixtures. Care shall be taken to locate light
fixtures so that lighting is not obstructed by tall or suspended pieces of
equipment.
Dining Areas and Services
Ample daylight is the illumination of choice in dining areas, assisted by fluorescent
(tubular or CFL) and/or LED type fixtures. Limited CFL for accents shall be
5-8
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
5.3.9
5.3.10
5.3.11
5.3.12
5.3.13
5.3.14
5.3.15
considered if comparable architectural effect to LED or incandescent lighting can
be achieved.

Fixtures for parking areas shall be fluorescent strip fixtures with wire guards or
diffusers. Care must be taken in locating fixtures to maintain the required vehicle
clearance. Enclosed fluorescent or HID fixtures should be considered for abovegrade parking structures

Structured Parking

Task oriented lighting shall be chosen wherever applicable.
When choosing lighting fixtures, take into account the color rendition and
appearance of the area to be lighted. Refer Table 5-6.
Efficacy Ranges of Various Lamps
Lamp Type
Lighting in shop, supply, or warehouse areas with ceilings above 4900 mm shall
be color-improved HPS. In areas where color rendition is known to be of
particular importance, metal halide MH shall be used.
Rated Power Ranges
(watts)
Efficacy Ranges
(lumens/watt)
Linear/Tubular Fluorescent Lamp
Emergency Lighting
Emergency lighting shall be provided to designated areas and installed on wall
below the ceiling line.
Exit Lighting
Exit lighting shall be provided to all emergency and egress areas installed surface
mounted on the ceiling or wall mounted.
Halophosphate
10 – 40
55 – 70
Triphosphor
14 – 65
60 – 83
Compact Fluorescent Lamp (CFL)
3 – 125
41 – 65
Light Emitting Diode (LED)
3 – 100
80 – 95
Incandescent Lamp
10 – 100
10 – 25
Mercury Vapor Lamp
50 – 2000
40 – 63
Metal Halide lamp
Up to 1000
75 – 95
Low Pressure Sodium Lamp
20 – 200
100 – 180
High Pressure Sodium Lamp
50 – 250
80 – 130
Source: Guidelines on Energy Conserving Design of Buildings (2007 Ed.)
Energy Conservation
The largest factor in the energy consumption of a building is lighting. The overall
efficiency of the lighting system shall depend both on the individual components
and on the interaction of components in a system. A good controls strategy shall
be applied to eliminate lighting in unoccupied areas and reduces it where day
lighting is available that can contribute significantly to energy conservation.
Necessary applicable control methods shall be applied such as through a Building
Automation System (BAS) and other available technology to comply with the
energy conservation.

Consider the maximum practical room surface reflectance in the lighting
design. Utilize light finishes to attain the best overall efficiency of the whole
lighting system. Avoid dark surfaces because these absorb light. Table 5-7
shows the recommended room surface reflectance.
Table 5-7
Visual Impact
The location and selection of the electrical system shall have visual impact on the
interior and exterior of the building or facility that shall be closely coordinated
with the architectural design. This includes colors and finishes of lights, outlets
and switches.
Design of lighting shall use the energy efficient lighting fixtures. The lighting
system shall be selected to provide an aesthetic and adaptable environment in
accordance with the intended purpose and with the minimum likely energy
requirements.
Table 5-6
High Bay Lighting
Recommended Room Surface Reflectance
Surface
% Reflectance
Ceilings
80 – 92
Walls
40 – 60
Furniture
26 – 44
Floors dimming
21 – 39
Source: Guidelines on Energy Conserving Design of Buildings (2007 Ed.)
5.3.16
General Requirements for Lighting Design
The minimum requirements in achieving energy efficient lighting design and
installations is one purpose of this guidelines. The provisions are expressed in
terms of lighting power density, luminous efficacy and illumination level. In
choosing suitable indoor illuminance level for an area, energy efficient shall be
considered plus other lighting requirements.
5-9
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
5.3.17
Lighting Calculations
The designer has the option to use sample calculations as indicated in DoE Manual
of Practice on Efficient Lighting or from lighting software.
Lighting Controls
Manual (tumbler and dimmer switches), automatic, or programmable
microprocessor lighting controls shall be provided for all lighting, except those
required for emergency or exit lighting for security purposes. The application of
5-10
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
these controls and the controlled zones shall depend on a number of space factors:
frequency of use, available daylighting, normal and extended work hours and the
use of open or closed office plans. The factors to be considered when establishing
zones, zone controls, alternate control and appropriate lighting control are:




Every task lighting shall be provided with lighting control device.
The general lighting of any enclosed area equal to or greater than 10 m²
wherein the connected loads is greater than 10 W/m² for the entire area shall
be controlled so that the lights load may be reduced by at least one-half while
retaining a uniform level of illuminance all over the area. This process shall be
made by the use of dimmers, dual switching of alternate lighting fixture, or
switching each lighting fixture.
The quantity of control devices needed shall be at least one for every 1.5 kW of
connected lighting load. It shall also comply with the preceding item. The total
number of control points to be used is shown in Table 5-8.
Control Types and Equivalent Number of Control Points
Type of Control
Equivalent Number of
Control Points
Manually operated On-Off Switch
1
Occupancy Sensor
2
Timer – Programmable from the space being controlled
2
3 Level step-control (including off) or preset dimming
2
4 Level step-control (including off) or preset dimming
3
Continuous (Automatic) dimming
3
Source: Guidelines on Energy Conserving Design of Buildings (2007 Ed.)


Exterior lighting not intended for 24 hours continuous use or both all-night
and part-night lighting circuits shall be automatically switched on by a timer,
photocell or combination of both timer-photocell. This process shall be
provided with manual bypass switch.
Exceptions:
-
At least one lighting control device shall be provided for each space enclosed
by ceiling-height partitions. The device shall have the ability to switch on and
off all the lights within the area.
Table 5-8


location should not be considered as increasing the number of controls to
meet the requirements of Table 5-8.
-
-
5.3.18
Lighting control requirements for areas, which shall be used as a whole
shall be controlled in accordance with the work activities. Its controls
shall be centralized in remote places. These areas include public lobbies
of hospitals, office buildings, warehouses, store rooms and service
corridors under central control and monitoring system.
Automatic and non-automatic control devices may decrease the quantity
of controls required by using equivalent number of controls from Table
5-8.
Automatic Control System, Programmable Controllers
Lighting Controls requiring expert operators and lighting controls for
security and safety hazards.
Power Layout
Receptacle/Convenience Outlet Load Analysis
In establishing electrical loads for buildings or facility it is important to look its
actual requirements. Future changes have the effect of redistributing electrical
loads. The minimum connected receptacle loads indicated in Table 5-9 combined
with other building or facility loads multiplied by appropriate demand factors, and
with spare capacity added, shall be used for obtaining the overall electrical load of
the building.
Building standard receptacle shall be duplex. Single receptacle shall be used on
certain equipment to be used such as for Emergency Light, Exit Light, etc. Special
purpose receptacles shall be provided for window type Air-conditioning unit,
Electric Ranges, Heating and Refrigeration and other similar equipment. Device
plates shall be plastic, colored to match the receptacles.
Use manual or automatic controls where adequate day lighting is available.
Examples of automatic controls are photoelectric switches or automatic
dimmers. These controls shall not only be provided for day lighted spaces but
also to operate rows of lights parallel to front/exterior wall.
Continuous lighting shall be applied for security purposes,
Control Location


5-11
Lighting controls shall be readily accessible to area tenants.
Controls for task lighting areas shall be installed as part of the task lighting
system. Control switches controlling the same load from more than one
5-12
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 5-9
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Minimum Connected Receptacle Load
Type of occupied area
Table 5-10
Load per square meter (VA)
Circuit Rating (Amperes)
Receptacle Rating (Amperes)
15
Not over 15
Normal systems
Office/Workstation
14
20
15 or 20
Non-workstation areas such as public and storage
10
30
30
Public areas
5
40
40 or 50
50
50
Electronic systems
Office/Workstation
13
Computer rooms
700
Source: PEC Part 1, Table 2.10.2.3(b)(3)
U.S. General Services Administration
Design the receptacle system per the following minimum requirements. The
designer shall create a design that provides for the average load requirement and
allows for flexibility for future additions and expansion. In this case the design
generally adheres to PEC requirement for general purpose receptacles in
residential buildings to provide a sufficient quantity of receptacles and meet any
future needs:







Receptacle Rating for Various Size Circuits

5.3.19
The motor nameplate horsepower shall be multiplied by the motor nameplate
service factor shall be at least 15% greater than the driven equipment operating
range maximum brake horsepower. For motors with 1.15 service factor, the
maximum load horsepower shall not exceed the motor nameplate.
For offices, minimum of 3.7 m spacing between receptacles is required.
However, for modular or workstation offices that requires computer, a
dedicated receptacle shall be provided.
For hallway and corridors (to accommodate cleaning equipment), minimum of
6 m spacing between receptacles is required.
Ground-fault circuit interrupter (GFCI) or Earth leakage circuit breaker
(ELCB) protection shall be provided on all receptacles located within 1.8
meter of sinks, water fountains, vending machines, and any equipment holding
a pool of water and connected to building plumbing.
Weatherproof receptacle shall be used for exterior installation exposed to
weather condition.
Receptacle Ratings: Where connected to a branch circuit supplying two or
more receptacles or outlets, receptacle ratings shall conform to the values
listed in Table 5-10, or where larger than 50 amperes, the receptacle rating
shall not be less than the branch-circuit rating.
Motors
Provision of necessary power supplies for the intended operation and application
as indicated on the respective equipment schedule that requires motor loads.
Sizing of required starting equipment shall be of direct-on-line or full voltage, stardelta, auto-transformer and soft starters.
Location of receptacle outlets shall be readily accessible and the number of
outlets depends on the area requirement of the structure.
For any heating, air-conditioning, or refrigeration equipment, a dedicated
receptacle is required. Special purpose receptacle shall be used for the
applicable equipment.
Branch Circuit Requirement: The type of circuit is a general purpose branch
circuit, a circuit that serves two or more receptacles or outlets for lighting and
appliances. Each receptacle shall be valued at 180VA. In general every ten
220V receptacles requires one branch circuit at 80 percent of rated capacity.
5.3.20
Motors shall be designed in accordance with the latest applicable standards and
codes.
Branch Circuits, Feeders and Conduit/Raceways
Branch Circuits
The design for the minimum branch circuit conductor size, before the application
of any adjustment or correction factors, shall have an allowable ampacity not less
than the noncontinuous load plus 125% of the continuous load. Likewise, the
feeders shall be protected against overcurrent in accordance with the provisions
PEC. The branch circuits shall be installed on the conduit/raceways that originate
from Panelboard and supply power to one or more loads as indicated in Table 5-1,
5-2 and 5-3 with its respective Load Densities or with specific load as indicated in
PEC Article 2.20.
For specific appliance and load shall be calculated based on the ampere rating of
the appliance or load served.
Feeders
The design for the minimum feeder conductor size, before the application of any
adjustment or correction factors, shall have an allowable ampacity not less than
the noncontinuous load plus 125% of the continuous load. Likewise, the feeders
5-13
5-14
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
shall be protected against overcurrent in accordance with the provisions PEC. The
feeders shall be installed on the conduit/raceways that originate at a primary
distribution center and supply power to one or more secondary
distribution centers, branch-circuit distribution centers, or a combination of these.
Conduit/Raceways for Wires
The design for the conduit/raceway systems used in supporting and protecting
electrical cable shall be in accordance with the provisions of the PEC.








5-15
Raceway system consists of manholes, ductbanks, entrance rooms and vaults,
equipment room(s), closets, and the sleeves, ducts, conduits, raceways and
outlets that comprise the horizontal pathways, backbone pathways and
workstation outlets of the technology infrastructure.
All cable trays except electronic trays shall be of trough or ladder type
construction with a maximum rung spacing of 150 mm, nominal depths of 100
mm to 150 mm, and various widths as required. There shall be a maximum
spacing of 2.4 m between cable tray supports, except fittings (elbows, tees,
etc.) which shall be supported in accordance with standards.
Raceways or cable trays or wire ways containing electric conductors shall not
contain any pipe, tube, or equal for steam, water, air, gas, drainage, or any
service other than electrical.
Metal raceways, cable armor, and other metal enclosures for conductors shall
be metallically joined together into a continuous electric conductor and shall
be connected to all boxes, fittings, and cabinets so as to provide effective
electrical continuity. Raceways and cable assemblies shall be mechanically
secured to boxes, fittings, cabinets, and other enclosures.
Electrical conduits shall be installed in concrete slab or wall or double walls
and floors.
PVC conduits shall be used for embedded and concealed installation, EMT for
concealed installation spaces up to 32 mm maximum size and RSC or IMC
conduit for exposed to weather, and in areas susceptible to damage and for
high and low-voltage feeders inside the building. PVC or RSC/IMC conduit
shall be used on underground installation with concrete encasement or duct
banks.
Flexible Steel Conduit (Aluminum Flex Not Allowed) shall be used for short
runs from ceiling Junction-Boxes to light fixtures, final connection to motors or
other appliances and equipment or where special permission is granted for
use.
Liquid tight flexible metallic conduit shall be used for damp location and for
connections to accessory devices such as: solenoid valves, limit switches,
pressure switches, etc.; for connections to motors or other vibrating
equipment; and across areas where expansion or movement of the conduit is
required.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures





5.3.22
color coded insulation shall be applied for all the low voltage system for easy
identifying the phases, neutral and earth conductors. Wires/cables shall be of
the approved type meeting all the requirement of the PEC.
Bus Duct: Where plug-in bus duct is used, it should have an integral ground
bus, sized at 50% of the phase bus to serve as the equipment grounding
conductor.
Power Distribution Panels: Circuit breaker type panels shall be the standard
protection with respective interrupting capacity.
Lighting and receptacle panelboards shall be circuit breaker type. Shall have
minimum of 30 poles for 100 amps panelboards and minimum 42 poles for
225 amp panelboards.
Panelboard shall be located in wall at accessible area or in the Electrical Room.
All panelboards, switchboard/switchgear shall have a rating not less than the
minimum feeder capacity required for the load calculated.
Panelboard
Shall be classified for the purposes as either lighting and appliance branch circuit
panelboards or power panelboards, based on their content. A power panelboard is
one having 10 percent or fewer of its overcurrent devices protecting lighting and
appliance branch circuits. Overcurrent device to be installed shall be of miniature
circuit breaker (MCB) or molded case circuit breaker (MCCB). The enclosure shall
be either flush or surface mounted in wall and shall be located on designated area
or in the Electrical Room.
To ensure maximum flexibility for future systems changes, the following be sized
as follows:


Panelboard for branch circuits must be sized with at least 25% spare capacity
Panelboard and main switchgear for feeder shall provide at least 25% spare
ampacity
5-17


5.3.23
Insulated case and power air circuit breakers shall be electrically operated.
The enclosure shall be of free standing and shall be located in the Electrical
Room.
Required interrupting current capacity shall be provided to all the overcurrent
devices based on the short circuit calculations conducted. If applicable, the
designer shall conduct relay coordination study.
Switchboards shall be front and rear accessible. In smaller switchboards, front
access only is acceptable if space is limited.
The meter section shall contain a voltmeter, ammeter and watt-hour meter
with demand register. Meters maybe of pulse type or IED for connection to the
BAS. Providing a power monitoring and management system is an acceptable
option.
Unit Substation
The unit substation shall be installed on secured and protected conspicuous area
located indoor with necessary ventilation or cooling systems to maintain indoor
temperature as required for proper operation of the equipment.
A unit substation consists of one or more transformers mechanically and
electrically connected to and coordinated in design with one or more switchgear
or switchboard assemblies with the outgoing section shall be rated below 1000
volts.
A typical unit substation consists of three sections:



An incoming section that accepts incoming medium voltage (2400 to 34,500
volts) line. Air Interrupter Switch (fused or unfused) or Metal Clad Switchgear
(SF6 or Vacuum type circuit breaker) shall be used.
A transformer section that transforms incoming voltage down to utilization
voltage (480, 400 or 230 volts). Liquid filled or Dry Type Transformer shall be
used.
An outgoing section (power load center) that distributes power to outgoing
feeders and provides protection for these feeders for the utilization voltage.
The unit substation shall bring power as close as possible to the load center
and shall provide the following features:
-
Spare overcurrent devices shall be provided as well as bus extension for
installation of future protective devices
-
Switchboards/Switchgear shall be provided with a single main service
disconnect device. The devices shall be molded case, insulated case, power air
circuit breaker (ACB) or individually mounted, draw-out type (as applicable).
-
Switchboards/Switchgear


Overcurrent Protection. Feeders shall be protected against overcurrent by
providing overcurrent device such as the circuit breaker. Where a feeder
supplies continuous loads or any combination of continuous and
noncontinuous loads, the rating of the overcurrent device shall not be less
than the noncontinuous load plus 125% of the continuous load.
Panelboard, Switchboard/Switchgear

Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
-
Reduced power losses
Better voltage regulation
Improved service continuity
Increased functional flexibility
Lower installation cost
Efficient space utilization
Every component and assembly of the unit substations shall be designed as an
integral part of a complete system
5-18
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
5.3.24
Emergency/Standby Power Systems
Generator
Emergency power requirements for the building or facility shall be provided by a
dedicated diesel generator set to supply the essential and critical loads during the
failure of the normal supply. Manual or Automatic transfer switches (MTS/ATS)
shall be provided to transfer the power supply from emergency to normal or vice
versa. Refer Figure 5-1.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
A UPS system shall be sized with 25% spare capacity.
 Critical Technical Loads

Capacity.

Generator Location
The generator shall be installed inside the buildings or facility with the required
area for the open type generator. Adequate and permanent ventilation to the
outside air in the form of louvered vents shall be required to be provided as part
of the generator room design. The required location shall be at the ground floor of
the building where it can easily be accessed. This is to ensure ease of installation
and future replacement/retirement. The emission of exhaust shall be routed
outside the atmosphere.
Silent outdoor type generator shall also be used and installed adjacent to the
building or facility.
Auxiliary Equipment
Battery shall be provided in racks within engine-generator set skid base. Voltage
regulated battery chargers shall be provided for engine-generator sets. Chargers
shall be furnished with float, taper, and equalize charge settings.
Uninterruptible Power Systems (UPS)
In some facilities, critical loads such as the computer system, etc. shall be
designed with a back-up systems such as the UPS.
Requirements for UPS systems shall be evaluated on a case by case basis. If UPS is
required, it may or may not require generator back-up. When generator back-up is
unnecessary, sufficient battery capacity shall be provided to allow for an orderly
shut-down.
5-19
Emergency Electrical Power Source Requirements
When the UPS is running on emergency power, the current to recharge the
UPS batteries shall be limited. This limited battery charging load shall be
added when sizing the emergency generator.
Electric generating system shall meet the design requirements of NFPA 110.
The engine generator shall be sized to approximately 110% of design load. Ideally
it shall run at 50% to 80% of its rated capacity after the effect of the inrush
current declines. When sizing the generator, consider the inrush current of the
motors that are automatically started simultaneously. The initial voltage drop on
generator output due to starting currents of loads must not exceed 15%.
The UPS system shall serve critical loads only. Non-critical loads shall be
served by separate distribution systems supplied from either the normal or
emergency power system.

If the UPS system is backed up by a generator to provide for continuous
operation, then the generator shall also provide power to all necessary
auxiliary equipment, i.e., the lighting, ventilation and air conditioning
supplying the UPS and serving the critical technical area.
System Status and Control Panel
The UPS shall include all instruments and controls for proper system
operation. The system status panel shall have an appropriate audio/visual
alarm to alert operators of potential problems. It shall include the following
monitoring and alarm functions: system on, system bypassed, system fault, out
of phase utility fault and closed generator circuit breaker. It shall have an
audible alarm and alarm silencer button. Since UPS equipment rooms are
usually unattended, an additional remote system status panel shall be
provided in the space served by the UPS. The alarms should also be
transmitted to the Building Automation System (if available).
UPS and Battery Room Requirements
Provide emergency lighting in both spaces. Provide a telephone in or adjacent
to the UPS room. Battery room design shall accommodate proper ventilation,
hydrogen detection, spill containment and working clearances.
Batteries
Valve Regulated Lead Acid (VRLA) Battery shall be used for the UPS with an
immobilized electrolyte that is sealed in terms of electrolyte maintenance. The
battery contains a pressure relief valve that releases excessive internal pressure
to the atmosphere when the cell pressure exceeds a manufacturer's prescribed
level. The immobilizing electrolyte medium accommodates an oxygen
recombination cycle thus minimizing gassing and water consumption.
The battery cabinet shall be sized with adequate space between shelves to allow
maintenance and test measurement access. Increased clearance shall be required
for multiple rows of batteries behind the front row in the cabinet. Batteries on pull
out drawers are shall be provided with safety and maintenance access.
5-20
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
full-load primary current of the transformer for about 0.1 s when energized
initially.
Overcurrent protection for a transformer on the primary side is typically a fused
disconnect. In some instances where there is not a high voltage panel, there shall
be circuit breaker instead.
5.4.2
It is important to note that the overcurrent device on the primary side shall be
sized according to the transformer KVA rating and not sized based on the
secondary load to the transformer.
Transformer Vault
The transformer vault that to be installed inside the buildings or facility shall be
complied with the requirement of the PEC. The required location for the
transformer vault shall be at the ground floor of the building where it can easily be
accessed from the outside. This is to ensure ease of installation and future
replacement/retirement of the padmounted transformer.
The walls and roof shall be constructed using reinforced concrete not less than
150 mm thick. The floor shall have adequate strength for the load imposed on it
and shall be not less than 100 mm thick reinforced concrete when in direct
contact with earth or not less than 150 mm thick when located above another
storey. Floor finish shall be smooth and painted with one coat of polyurethane
sealer and two coats of epoxy dustproof coating.
There shall be a maximum of two (2) padmounted transformer units in a vault.
Generally, the minimum required dimension for the vault shall be 5 m (width) X 4
m (depth) for one (1) three-phase padmounted transformer or 8 m (width) X 4 m
(depth) for two (2) three-phase padmounted transformers units. This assumes
that a 3-m clear space in front of the equipment for switching operations can be
attained when the transformer access door is open. For 2nd floor and 1st
basement installations where this is not possible, a 6 m minimum depth for the
vault shall be required. [Exception: For 2nd floor transformer vault where a
hatchway is used, the depth required is 8 m.]
There shall be no openings, such as, doors, vents, etc., from the transformer vault
to any part of the building interior. All openings of the transformer vault shall only
lead to the outside of the building.
The concrete pad for the padmounted transformer shall be 75 mm height.
A 150 mm high door sill shall be provided by the as part of the transformer
vault liquid confinement area.
Adequate and permanent ventilation to the outside air in the form of louvered
vents shall be required to be provided as part of the transformer vault design. The
vents shall have a combined net area of opening (less the area occupied by the
louvers) of not less than 20cm² per kVA of the transformer bank capacity
installed. For adequate natural air circulation, the intake and exhaust vents shall
be located on opposite sides of the padmounted transformer with half of the total
5-22
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures



5.5.1
Major items of equipment, such as unit substations, transformer vault,
switchgear, motor control centers, relay panels, and control panels, shall have
integral ground buses which shall be connected to the ground grid.
Electronic panels and equipment, where required, shall be grounded utilizing
an insulated ground wire. Where practical, electronics ground loops shall be
avoided. Where this is not practical, isolation transformers shall be furnished.
All ground wires installed in conduit shall be insulated.
System Grounding
System grounding shall be extremely important, as it affects the susceptibility of
the system to voltage transients, determines the types of loads the system can
accommodate, and helps to determine the system protection requirements.
The system grounding arrangement shall be determined by the grounding of the
following power sources:



Utility Service: The system grounding shall be usually determined by the
secondary winding configuration of the upstream utility substation
transformer.
Generator: The system grounding shall be determined by the stator winding
configuration.
Transformer: The system grounding on the system fed by the transformer
shall be determined by the transformer secondary winding configuration.
Solidly-grounded Systems
The solidly-grounded system is the most common system arrangement, and one of
the most versatile. The most commonly-used configuration is the solidly-grounded
wye, since it will support single-phase phase-to- neutral loads.
Ungrounded Systems
This system grounding arrangement shall be at the other end of the spectrum
from solidly-grounded systems.
5.5.2
An ungrounded system is a system where there shall be no intentional
connection of the system to ground.
Equipment Grounding
Metal parts of electrical equipment shall be grounded (connected to the earth) to
reduce induced voltage on metal parts from exterior lightning so as to prevent
fires from an arc within the building/structure.
Metal parts of electrical raceways, cables, enclosures, or equipment shall be
bonded together in a manner that creates a low-impedance path for ground-fault
current to facilitate the operation of the circuit overcurrent device.
5-24
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
5.5.3
A connection that provides a path to ground a conductor within the equipment. A
ground connection to any metal part of a wiring system or equipment that does
not carry current.
Lightning Protection Systems
The lightning protection system shall be designed for Early Streamer Emission
(ESE) air terminal in accordance to the UNE 21186 and similar ESE standards one
which conveys a lightning discharge to ground without electrification of its
supporting mast or pole and nearby structures. A set of protection system shall
consist of electrode, down conductor, ground rod(s), masts, fasteners and other
miscellaneous mounting hardware.
Lightning protection system shall be provided if lightning can easily strike a
building because of:
 Its length
 Its height, or the use to which it is located, or if

It is expected that a lightning strike would have serious consequences
The lightning protection ground shall be connected to the main building or facility
ground and any nearby buried metallic items and building or facility structures.
5.5.4
Test pit shall be provided and each down conductor requires a test clamp and
dedicated earth system of 10 ohms or less. Should 10 ohms not be achievable,
additional ground rods or conductor shall be provided.
Single Line Diagram
Starting at the top of the drawing with the building transformers, the designer
shall indicated all pertinent electrical equipment down to the panelboard level.
These equipment includes switchboard/switchgear, panelboards, MCCs,
generators, transfer switches, uninterruptible power supplies, and inverter
systems. For transformers, note kVA size, primary and secondary voltages,
phasing (building service entrance only), and impedance. Show the distribution
switchboard and switchgear in "expanded" form. On the drawing detail the main
breaker, tie breaker, feeder breakers, spare breakers, CTs, PTs, and meter. Note
switchboard rated amperage, voltage, and short-circuit capability. Include frame
and trip size of all breakers in the gear. Note service entrance, feeder wire and
conduit sizes.
For larger buildings, additional SLD drawings may be required. If the building uses
MCCs, separate SLDs may be required. When MCCs are necessary, shall provide in
"expanded" form. Drawings shall be called "MCC Single Line Diagram" and be
numbered sequentially with the main SLD. Indicate starter and breaker sizes, bus
tap sizes, wire, and conduit size ending with each motor or other load. If the
building has a large standby power system, shall provide an "expanded" SLD of
this system also.
In general, use the following guidelines:
5-25
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures




5-27
Exterior Distribution System Plan
Technical Specifications
Bill of Materials
Project Estimate
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures


Heat generated by equipment and appliances
Heat gained from outside air (fresh air intake and ventilation)
After consideration of the factors, the amount of heat generated inside the room
will indicate the type of airconditioning system and its capacity requirement for
the room.
The heat loss/load equation is
Q = AU∆T
where:
6.3.4
A
=
surface area
U
=
overall heat transfer coefficient depending on the type of
construction materials
∆T
=
difference in outside and inside temperature
Overall Coefficient of Heat Transfer (U)
Using the principle of heat transfer, the overall coefficient, U, can be calculated
using the resistance method. The total resistance to heat flow through a flat
ceiling, floor or wall (or a curved surface if the curvature is small) is equal to the
sum of the resistances in series.
RT = R1 + R2 + R3….+Rn
Where R1, R2, R3…. Rn are the individual resistances of the surface components and
RT is the total resistance.
The overall heat transfer coefficient is the summation of resistance of the various
components of an assembly. The general formula is:
U=
1
1
1
+ ......
R1
R2
Rn
=∑
1
R1 ⊳Rn
For a wall of a single homogenous material of conductivity, k, and thickness, L,
with surface coefficient h1 and ho:
and
RT =
1
1
1
+ +
h1
k
ho
1
U= R
T
For a wall with air space construction, consisting of two homogenous materials of
conductivities k1 and k2 and thicknesses L1 and L2, respectively, separated by an
air space of conductance c:
RT =
1
L
1
L
1
+ k1 + + k2 +
h1
c
ho
1
2
6-3
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
and
1
U= R
T
Over-all heat transfer coefficient for usual materials of construction are provided
in Table 6-1.
Table 6-1
Overall Heat Coefficient
Uo-value
Assembly
BTU/hr-sqft F
Roof Assemblies (Heat Flow Down)
Galvanized Iron Roof with Medium Density Fiber (MDF) Cement Board
ceiling, No insulation
0.55
Galvanized Iron Roof with cement (MDF) Board, 25 mm thick fiberglass
insulation
0.18
Galvanized Iron Roof with Medium Density Fiber Cement (MDF) Board, 50
mm thick fiberglass insulation
0.10
150 mm Roof Slab without ceiling
0.61
150 mm Roof Slab , 25 mm thick fiberglass insulation no ceiling
0.19
150 mm Roof Slab , no insulation, with 200mm air space and MDF Board
0.36
150 mm Roof Slab , 25 mm thick fiberglass insulation, with 200mm air space
and MDF Board
0.15
Outdoor Wall Assemblies
100 mm Concrete Block w/ 0.5 inch Plaster, both sides
0.72
150 mm Concrete Block w/ 0.5 inch Plaster, both sides
0.63
200 mm Concrete Block w/ 0.5 inch Plaster, both sides
0.56
Floor Assembly (Heat Flow up)
150 mm thick floor slab with no ceiling below
0.58
150 mm thick floor slab with 200 mm airspace and MDF ceiling
0.38
Ceiling Assembly (Heat Flow down)
150 mm thick floor slab with no ceiling below
0.43
150 mm thick floor slab with 200 mm airspace and MDF ceiling
0.64
Wall Partitions
100 mm CHB with 12 mm plaster finish on both sides
0.55
150 mm CHB with 12 mm plaster finish on both sides
0.50
25 mm thick fiberglass insulation sandwiched between Medium Density
Fiber Cement Board
0.18
50 mm thick fiberglass insulation sandwiched between Medium Density
Fiber Cement Board
0.11
Internal Heat Gain Sources: The air conditioned room may be considered to be a
black box where all the heat going into the box has to be removed by the air
conditioning. The internal sources of heat are the people, lights, appliances and
equipment.
6-4
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures


6.5.1
6.5.2
NFPA 14: Standard for the Installation of Standpipe, Private Hydrant and Hose
Systems
NFPA 20: Standard for the installation of Stationary Pumps for Fire Protection
General Design Procedure
The project drawings are the take off point for any fire protection system that
would be designed. The use of the building will determine the type of fire
protection system to be provided or should any be installed at all. Republic Act
9514 known as the Fire Code of the Philippines of 2008 and its implementing
rules and regulation shall be consulted as minimum code requirement for the fire
protection system to be provided.
Automatic Fire Sprinkler System
General: One of the most reliable extinguishing system is the automatic sprinkler
system. The design of the automatic sprinkler system shall be based on the
provisions of NFPA 13 – Standard for the Installation Sprinkler Systems. Facilities
requiring sprinkler systems shall be determined from the requirements of the Fire
Code of the Philippines of 2008.
Classification of Occupancies: Occupancy classification is used to determine
sprinkler installation only and does not supersede the requirements of the Fire
Code. Based on the available fuel during a fire, an area may be considered to be
light hazard if the combustibility of the contents is relatively low. Examples are
offices, restaurant sitting rooms, theaters. Ordinary Hazard on the other hand
have moderate to high rates of heat release. Examples of these are garages,
restaurant service areas and factories. Extra hazard occupancies have a very high
level of combustibles present. They include aircraft hangars, painting areas,
plywood manufacturing areas. Sprinkler installation guidelines are provided in
Table 6-3.
Table 6-3
Sprinkler installation guidelines
Occupancy Classification
Maximum Sprinkler
Protection Area,
m2
Sprinkler Spacing
(max:), m2
From Walls
(max:), m2
Light Hazard
20.9
4.5
2.25
Ordinary Hazard
12.0
4.5
2.25
Extra Hazard
9.2
3.6
1.8
Hydraulic Calculations
Pipe Friction Losses are determined by the Hazen-Williams formula where
P = 4.52 Q1.85
C1.85 d4.87
Where P is the friction loss in pounds per square inch per foot length of pipe, Q is
in gallons per minute. C is the Hazen-Williams coefficient dependent on the type of
pipe.
6-7
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Pm = __4.52 Q1.85__
C1.85 dm4.87
Where Pm is in pounds per square inch per foot length of pipe, Q is flow in gallons
per minute, dm is the actual internal diameter of the pipe in inches and C is the
friction loss coefficient of the pipe
In SI units Pm = 6.05 x _4.52 Q1.85 _ x 105
C1.85 dm4.87
where:
Pm
=
bars per meter length of pipe
dm
=
the actual internal diameter of the pipe in mm
Q
=
C
flow in liters per minute
=
friction loss coefficient of the pipe
Table 6-4
Hazen Williams C values
Pipe or Tube Material
100
Black steel (Dry Pipe Systems)
100
Black steel (Dry Pipe Systems)
120
Galvanized (all)
120
Plastics (listed) –all
150
Cement Lined ductile or Cast Iron
140
Table 6-5
Fittings and Valves
6.5.3
C Value
Unlined Cast or Ductile Iron
Equivalent Pipe Length Chart
Equivalent Pipe lengths in feet
1 in
1.25 in
1.5 in
2 in
2.5 in
3 in
4 in
5in
6in
45˚ Elbow
1
1
2
2
3
3
4
5
7
90˚ Standard Elbow
2
3
4
5
6
7
10
12
14
90˚ Long Radius Elbow
2
2
2
3
4
5
6
8
9
Tee or Cros
5
6
8
10
12
15
20
25
30
Butterfly Valve
-
-
-
6
7
10
12
9
10
Gate Valve
-
-
-
1
1
1
2
2
3
Swing Check Valve
5
7
9
11
14
16
22
27
32
Wet and Dry Standpipe Systems
General: A stand pipe system is an ideal supplement to an automatic
sprinkler system. A hose stream provides a high concentrated volume of
water to a fire. There are two (2) types of systems the first is the wet
standpipe system which has water in the pipes all the time and a dry
standpipe system is filled with water prior to use.
6-8
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 6-6
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Recommended Basic Water Requirements for Human Needs. a
Purpose
Recommended Minimum
(liters/person/day)
Range (liters/ person/ day)
Drinking Water
5
2 to 5
Sanitation Services
20
0 to over 75
Bathing
15
5 to 70d
Cooking and Kitchen
10
10 to 50d
Total Recommended Basic
50
Water Requirement
Source: Gleick, Peter H. “Basic Water Requirements for Human Activities: Meeting Basic Needs” Water
International, Vol. 21, No. 2(1996). Page 88.
a.
b.
c.
d.
6.6.2
Excluding requirement to grow food.
This is a true minimum to sustain life in moderate climactic conditions and with average activity levels.
An average (not minimum) of 40 l/p/d is considered adequate for direct sanitation hookups in
industrialized countries. The upper end of the range represent extremely inefficient toilets. In water short
regions, sanitation systems that use no water are available, but rarely embraced socially.
The upper values here represent societal preferences for moderately industrialized countries. Use in
some water-rich regions may exceed these amounts. The lowest values reflect minimum uses in
developing countries.
Sizing Overhead Tanks, Transfer Pumps and Level Control
Overhead tanks supplied from cisterns shall be sized for a capacity of one day.
Float switches may be provided to activate transfer pumps.
Transfer pumps shall be provided to move water from the cistern to the overhead
tank. Water shall be transferred from the cistern to the overhead tank for a period
not exceeding two hours. Pumps operating in parallel is the preferred
configuration. Each pump shall be one-half the capacity of the maximum demand.
A third pump may be provided as a stand-by unit.
Pipes shall be sized for a velocity of 1 – 3 m/sec. The flow through black iron pipes
is indicated in Table 6-7.
Table 6-7
Flow through Schedule 40 B.I. Pipes in Liters per Minute
Velocity
NominalPipe Size (inches)
(mps)
Internal diameter (inches)
0.75
1
1.25
1.5
2
2.5
3
4
0.824
1.049
1.38
1.61
2.067
2.469
3.068
4.026
1
21
34
58
79
130
189
287
384
2
41
67
116
158
261
372
574
768
3
62
101
174
237
391
558
862
1,152
Calculating the total developed head (TDH) of the pump involves the summation
of the friction loss in feet of the pipe from the cistern to the overhead tank plus the
static head in feet between the cistern and tank.
Pump Total Develop Head = Pipe Friction Loss+ Static Head+Velocity Head.
6-10
The Hazen-Williams formula mentioned in Section 5.5.2 may be utilized to
calculate friction loss. Pump selection shall take into account the available power
supply and the technical capability of the user to operate and maintain the system.
The Pump Horsepower assist the designer in determining the horsepower of the
pump to guide him in selecting the appropriate unit. Pum motor horse power may
be determined as follows:
𝑃𝑃𝑃𝑃𝑃𝑃𝑃𝑃 𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚𝑚 ℎ𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜𝑜 =
Example:
𝐹𝐹𝑙𝑙𝑙𝑙𝑙𝑙 (
𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔𝑔
𝑚𝑚𝑚𝑚𝑚𝑚
) × 𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇𝑇 𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑𝑑 ℎ𝑒𝑒𝑒𝑒𝑒𝑒 (𝑓𝑓𝑓𝑓𝑓𝑓𝑓𝑓)
3960 × 𝑝𝑝𝑝𝑝𝑝𝑝𝑝𝑝 𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒𝑒
Assume a two (2) storey school building with a canteen catering to a total
population of 360 students, teachers and staff. It is required that am overhead
tank, cistern tank connected by a pump and piping will be required. The pipe is 15
m long, with 3 elbows, 3 gate valves, 1 check valve. Based on Table 6-6, each
person will require 35 liters per day (drinking: 5 l, sanitation 20 l, cooking and
kitchen:10 l)
The overhead tank is calculated:
Over head tank capacity = 360 persons x 35 liters/person/day Table 6.6)
= 12,600 liters (or 3,315 gallons)
The cistern tank is a minimum of 2.5 times the overhead tank. The capacity is:
Cistern tank capacity = 12, 600 liters x 2.5 = 31,500 liters
To fill the tank in an hour, the pump flow capacity must be:
Pump capacity = 12,600 liters / 60 minutes
= 210 liters/ minute (55.25 gallons/minute)
From Table 6-5, a pipe 50 mmØ will be used.
The fittings to be used are:
If the floor to floor height is 3.6 m and a sink is 1.0 m above the floor, an overhead
tank may be mounted approximately 4.5 m above the point of use. The total height
shall therefore be 9.1 m above the ground or 30 feet.
Pipe length = 15 m = 49 feet
Equivalent pipe length of fittings (Table 6.5):
Elbows: 3 x 5
Gate Valve: 3 x 1
Check valve 1 x 11
Total
= 15 feet
= 3 feet
= 11 feet
= 29 feet
Pm = __4.52 Q1.85__ = __4.52 x 55.251.85___ = 0.031 psi
C1.85 dm4.87
1201.85 x 2.0674.87
Pipe friction loss = (49 feet + 29 feet) x 0.031 psi
= 2.48 psi x 2.31 feet H2O /psi
= 5.7 feet
6-11
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure 6-1
PROJECT
ROOM NO/DES.
DATE
Design Month
Design Time
Item
Sample Work Sheet for Mechanical Engineer
July
4:00 PM
Factor
CONDITIONS
Extension
DB
Sun Gain
or Tem p
Outdoor
95
82
56
78
146
Diff.
Room
75 62.5
50
60
78
Difference
20 XXX XXX XXX
Solar Gain - Glass
N
Glass
Sq. Ft. x
33 x
0.94 =
S
Glass
Sq. Ft. x
11 x
0.94 =
E
Glass
Sq. Ft. x
11 x
0.94 =
People x
W
Glass
Sq. Ft. x
153 x
0.94 =
Sq Ft
Sq. Ft. x
112 x
0.94 =
Skylight
BYPASS FACTOR
Extension
OUTDOOR AIR
20
cfm/person =
x
cfm/sf
=
=
CFM Ventilation
Solar Gain - Walls & Roof
APPARATUS DEW POINT
N
Wall
Sq. Ft. x
13 x
0.49 =
Effective
S
Wall
Sq. Ft. x
31 x
0.49 =
Sens. Heat =
Eff. Rm Sen. Heat =
E
Wall
Sq. Ft. x
17 x
0.49 =
Factor
Eff. Rm. Total Ht.
W
Wall
Sq. Ft. x
31 x
0.49 =
Roof - Sun
Sq. Ft. x
46 x
0.49 =
Roof - Shaded
Sq. Ft. x
x
=
Tansm ission Gain - Except Walls & Roof
Indicated ADP
Selected ADP
DEHUMIDIFIED AIR QUANTITY
=
ADP Temp =
All Glass
Sq. Ft. x
x
=
-
Partition
Sq. Ft. x
x
=
-
Ceiling
Sq. Ft. x
x
=
-
Floor
Sq. Ft. x
x
=
-
ERSH
Infiltration
CFM
x
=
-
Fx
x
245 =
-
x
TRM -
TADP =
x
ADP TD=
=
cfm
Difference
DTR =(1-
BF)
1.08
Internal Heat
COIL CONDITIONS
People
Coil Entering Tem perature
Pow er
hp
x
2545 =
-
Entering Air
Lights
w atts
3.413 x
1.25 =
-
OA
cfm
FDB
-
Appl., etc.
x
=
-
RA
cfm
FDB
-
Additional Heat Gains
x
=
Total
cfm
Mixed Air
cfm
-
Sub-Total
10 %
Safety Factor
=
=
Room Sensible Heat
Flow
Temperature
-
Additional Heat Gain
Temperature
cfm
Gr/lb
-
RA
cfm
Gr/lb
-
-
Total
cfm
RA Duct Heat Gain
%
-
Mixed Air
cfm
%
cfm x
-
BF x
BF x
-
TADP + (
CFM
TADP) =
x
x
People
0.68 =
x
=
x
1050 =
Appl., etc.
x
=
Additional Heat Gains
x
=
Steam
lb/hr
Sub-Total
%
Safety Factor
Room Latent Heat
=
-
=
-
=
-
Additional Heat Gain
OA
cfm x
BF X (
BF x
BF x
-
Effective Room Latent Heat
OUTDOOR AIR HEAT
Sens
cfm x (1-
BF)x
x
1.08 =
-
Lat
cfm x (1-
BF)x
x
0.68 =
-
=
-
GRAND TOTAL HEAT
TEDB -
e
LATENT HEAT
Infiltration
Gr/lb
Coil Lvg Conditions
-
Effective Room Sensible Heat
SUM
OA
%
OA
FDB
Flow
SA Duct Heat Gain
Fan HP
SUM
Humidity
Entering Air
6-14
WB %RH DP Gr/Lb
Area or
Quantity
BTUH
FDB
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Horizontal Sub-system
Backbone Cable (Data-Fiber Optic Media)
The horizontal cabling subsystem extends from a Floor Distributor (FD) to the
telecommunications outlet connected to it. The subsystem includes:
Fiber Optic Cable: Multi-mode and single-mode optical fiber cable shall be of
tight buffered or loose tube construction suitable for indoor or outdoor
applications and PVC or LSOH outer jacket.






Horizontal cables.
Jumpers and patch cords in the floor distributor.
Mechanical termination of the horizontal cables at the telecoms outlet.





Consolidation point (optional)

Horizontal cabling shall be Category 6 , 23 AWG, 4-pair UTP cable , with a PVC
jacketing material

Telecommunications outlets.
Impedance: 100 ohms + 15%, 1 MHz to 250 MHz
Category 6 patch panels shall be 1U high and support 24 modular jack ports or
2U high and support 48 modular jack ports, and shall accept RJ-45, 8-Position
modular plugs
Patch panels shall terminate the building cabling on an IDC (Insulation
Displacement Connector) type connector or module
Category 6 UTP modular jack insulation displacement contacts shall be
capable of terminating solid conductors from Ø 0.5 mm to 0.65 mm (24 to 22
AWG)
The installed system shall comply with the Category 6 performance
characteristics as required by TIA and ISO standards.
Patch Cords: Patch cords shall be provided when patching of voice and / or data
circuits is required at the cross-connections. The patch cords supplied shall be
able to support the designed applications.
The patch cord shall include the following features:


The fiber optic cables shall meet the specifications and transmission
specification defined under TIA and ISO standards.
Fiber Connect Panel / Fiber Optic Patch Panel
Patch Panel: The patch panel shall include the following features:


Mechanical termination of the horizontal cables at the floor distributor
including the connecting hardware of the inter-connect or cross-connect.
Horizontal Cable: The horizontal cable shall meet the following characteristics:
RJ-45 Cat 6 patch cords shall be installed for equipment and patch panel
Patch cords shall be factory terminated with 4-pair UTP Cat6 stranded cable
Backbone Sub-system
The cable route within a building, connecting telecommunications rooms to the
equipment room is called the backbone cabling. The building backbone cabling
subsystem extends from Building Distributor (BD) or Main Distribution Frame
(MDF) to the Floor Distributor (FD) or Intermediate Distribution Frame (IDF).
7-4
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
The patch panel shall include the following features:

Modular design with snap in SC or LC adaptors
Equipped with fixing mechanism that ensures cable retention and support of
incoming fiber optic cable
Be able to accommodate both direct termination or splicing
Fiber Optic Connector
The patch cord shall include the following features:


The fiber optic connector shall be field installable using either a two
component epoxy glue or direct termination of factory pre-polished
connectors
The fiber optic connectors shall be LC or SC type
Fiber Optic Patch Cords
The patch cord shall include the following features:


Consist of one or two single, tight buffered, multimode graded-index fiber with
a 50 micron core with125 micron cladding (multi-mode) and 9 micron core
with 125 micron cladding (single mode) to suit the installed fiber optic cable.
Factory terminated with LC or SC ceramic connectors at each end.
Backbone Cable (Data-Copper Media)
UTP (4-pair) Category 6 cable: The backbone cable shall be UTP Category 6
compliant and shall meet the following specifications:


Backbone cabling shall be 23 AWG, 4-pair UTP, with a PVC jacketing material.
Impedance: 100 ohms + 15%, 1 MHz to 250 MHz.
Patch Panel: The patch panel shall include the following features:


Category 6 patch panels shall be 1 RU (Rack Unit) high and support 24
modular jack ports or 2U high and support 48 modular jack ports, and shall
accept RJ-45, 8-position modular plugs
The Cat 6 UTP modular jack insulation displacement contacts shall be capable
of terminating solid conductors from Ø 0.5 mm to 0.65 mm (24 to 22 AWG)
7-5
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures

Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
The installed system shall comply with the Category 6 performance
characteristics as required by TIA and ISO standards

Faceplate
Patch Cords: Patch cords shall be provided when patching data circuits is
required at the cross-connections to facilitate moves, adds and changes (MAC’s).
The patch cords supplied shall be able to support the designed applications.


The patch panel shall include the following features:



RJ-45 Cat 6 patch cords shall be installed for equipment

Patch cords shall be factory terminated with 4-pair UTP Cat6 stranded cable
 Be 0.50 mm (24AWG) solid bare copper
 The nominal diameter or maximum jacket diameter shall not exceed 13.0 mm.
 Jacketing material ,non-plenum polyvinyl chloride(PVC)
IDC Wiring Block: IDC Wring Block – All multi-pair voice backbone cable shall be
terminated on a 10-pair, 25-pair , 50-pair or 100-pair insulation displacement
connection (IDC) module or wiring block and shall:



Be made of flame-retardant thermoplastic, with the base consisting of
horizontal index strips for terminating UTP cable conductors.
Have bases available in rack or frame configurations and for rack mounting
with cable management hardware.
Shall comply with TIA (Cat 5e) or ISO 11801: (Class D).
Jumper Wire: The cross-connect or jumper cable shall be 100 ohms balanced UTP
cable in 1-pair or 2-pair configuration. It shall be Category 5e compliant and shall
meet the following specifications:


Be 0.50 mm (24AWG) solid bare copper
Shall comply with TIA (Cat 5e) or ISO 11801: (Class D)
Work-area Sub-system
The work area subsystem includes patch cords, connectors, faceplates, and
telecommunications outlet as well as the work area patch cords (equipment cord)
needed to make connections. A minimum of one work area outlet location
containing one voice and data shall be installed per work area.
The subsystem includes:
Patch Cords

7-6
RJ-45 Cat 6 patch cords shall be installed for the user work area
A choice of 1,2,3,4 outlets
A clear label for application of circuit identification
Shutter door for dust and contaminants protection
Accepts RJ45 jacks
Telecommunications Outlet
Backbone Cable (Voice-Copper Media)
UTP (25-pairs) Category 5e cable: The voice backbone cable shall be 100 ohms
balanced UTP multi-pair cable in 25-pair cable configuration. It shall be Category
5e compliant and shall meet the following specifications:
Patch cords shall be factory terminated with 4-pair UTP stranded cable


7.3.3
Modular jacks shall be un-keyed, unshielded, 4-pair, RJ-45, and shall fit in a
standard utility box or modular system furniture raceway
The insulation displacement connectors shall be capable of terminating solid
cable conductors from Ø 0.5 mm to 0.65 mm (22-24 AWG).
Telecommunication Spaces
The design considerations and standards for telecommunications spaces and
rooms are described in TIA and ISO standards. The design for the
telecommunications spaces must ensure that the operational requirements
addressed and objectives are met.
Equipment Room (ER): An Equipment Room provides a controlled environment
to house telecommunications equipment, termination hardware, splice closures,
grounding and bonding facilities and protection apparatus where applicable
Equipment Room(ER) shall be designed and provisioned according to the
requirements of the standards.
Telecommunications Room (TR): A Telecommunications Room is an enclosed
space for housing telecommunications equipment, cable terminations,
interconnect and cross-connect. Telecommunications Rooms (TRs) differ from
equipment rooms (ERs) and entrance facilities (EFs) in that they are generally
considered to be floor serving.
Entrance Facility (EF): An Entrance Facility is a room or facility that provides all
necessary mechanical and electrical services that complies with all relevant
regulations, for the entry of telecommunications cables and other utility service
provider entrance cables into the building.
Building Distributor (BD): Building Distributor is the central point in a building
from where the building backbone fans out. It can be a single wiring closet,
multiple closets, a room or it can be combined with a floor distributor.
Floor Distributor (FD): A Floor Distributor is a floor serving facility that is used
to connect the horizontal cable and other cabling sub-systems or equipment.
Design Requirements
During the design phase, there are a number of electronics and communication
infrastructure requirements that must be addressed by the electronics design
7-7
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
engineer and shall be coordinated with the A/E (Architectural / Engineering) for
space planning.
Room Location
There are a number of factors that need to be considered when placing
Telecommunications Spaces (TS) within a new building or facility. Site selection
factors for the telecommunications rooms or spaces are listed below.
Telecommunications Spaces shall be:
 Dedicated to the buildings telecommunications function and related support
facilities.
 Located adjacent to vertical backbone pathway and as close as possible to the
center of the area served and preferably in the core area so that the average
horizontal cable run is 50 m or less and no individual cable run shall exceed 90
m, minimizing the length of the backbone and horizontal distribution cables.
 Located in a clean and dry area that is not subjected to flooding.
 Accessible directly from public hallways and not through offices or other utility
spaces.
Telecommunications Spaces shall not:








7-8
Be shared with electrical equipment, building services or other equipment
other than those required in direct support of the telecoms equipment and
services.
Contain other building systems, such as fire alarm panels, access control
systems, building management systems, audio-visual (A / V) equipment, etc.
Be located near electrical power supply transformers, elevator or pump
motors, generators, x-ray equipment, radio transmitters, induction heating
devices and other potential sources of electromagnetic interference (EMI) and
radio frequency interference (RFI).
Be located near sources of mechanical vibration that could be conveyed to the
room via the building structure.
Contain equipment not related to the support of the telecommunications
function (such as sprinkler, chilled water, supply and waste piping, ductwork)
shall not be installed in, pass through, pass overhead o enter the
telecommunications space.
Be located below water level unless preventive measures against water
infiltration are employed.
Be located in any place that may be subject to water or steam infiltration,
humidity from nearby water or steam, heat and any other corrosive
atmospheric or environmental conditions.
Share space in electrical closets, washrooms, janitorial closets and storage
rooms.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Room Size
The size of the Telecommunications Spaces is dependent upon the size of the area
that the room will serve and the variety of equipment installed within the room.
The Telecommunications Spaces shall provide enough space for all planned
termination and electronic equipment and cables that will be installed to within
the telecommunications room; including any environmental control equipment,
power distribution and uninterrupted power supply or UPS system.
Doors





The door shall be a minimum of 0.9 m wide and 2.4 m high, without a doorsill.
Door shall be fire rated to match the fire rating of the wall in which it is
installed, if applicable, or as required by local code requirements.
Doors shall not contain a glass viewing window or panel for added security.
If it is anticipated that large equipment will be delivered to the
Telecommunications Spaces, a double door without a doorsill and center post
is recommended.
Doors shall open outward (code permitting).
Floors



Floors shall be sealed concrete or tile to minimize dust and static electricity,
removable computer floor or raised flooring shall be of a tile type surface or
compact pressure laminate (CPL) type.
Floor loading capacity in the rooms shall be designed for a minimum
distributed load rating of 100 lbf / ft².
If a raised floor system is used, then it is possible the space will have to comply
with the requirements of Article 645 Information Technology Equipment
section of the National Electrical Code.
Walls




Interior finishes shall be in a light color to enhance room lighting.
At least one wall shall be lined with plywood backboard and mounted
vertically starting at 6-inches above the finished floor.
All plywood shall be painted with two coats of fire retardant paint.
The plywood shall be securely fastened to the wall-framing members.
Ceilings


For EF and BD, there shall be no suspended ceilings and the walls must be
continuous from floor to underside of the floor above.
Open structure ceilings shall provide the same environmental conditions as a
closed type of ceiling structure.
7-9
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures





7.3.4
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Building Entrance Facility
Hard ceilings shall have IMC or EMT type conduit or pipe sleeves installed to
facilitate the installation and fire stopping of cables.
Building entrance facility is required whenever service provider entrance cables,
public and private network cables, cable television service providers including
Direct Antenna System (DAS) used by mobile service providers entering the
building.
Wall anchors shall be flush to the plywood surface as to not obstruct the
mounting of cabling hardware. The walls shall be capable of supporting
attached equipment.

Horizontal pathways shall terminate in the Telecommunications Spaces
located on the same floor as the area being served.
Be accessible directly from public hallways and not through offices or other
utility spaces and accessible for the delivery of large equipment to the room.

Vertically aligned or stacked within a multi-floor building; each FD is placed
above each floor and shall have easy access to distribution cable pathways.

Special Design Considerations

Electromagnetic Interference (EMI)
The Telecommunications Spaces (TS) shall not be located near electrical power
supply transformers, elevators, pump motors, generators, x-ray equipment, radio
transmitters, radar transmitters, induction heating devices or other potential
sources of electromagnetic interference (EMI).
Emergency Back-up Power
Sub-panels shall be connected to an emergency power source whenever such a
source is provided to the building.
Emergency power is especially important in telecommunications spaces and
rooms with emergency or life safety systems and critical electronics systems for
the building operations that are required to remain operational during power
outages that may extend past the systems battery backup capability.
HVAC Requirements
The special requirement for the TS such as ER and IDF rooms where telecoms
and network equipment are housed-in, the electronics design consultant must
coordinate with mechanical design consultant for the Heating, Ventilation and Air
Conditioning (HVAC) requirements.



7-10
For ER ,the air handling system and environment controls for TS’s shall be
continuous and dedicated and designed to provide positive airflow and
cooling even during times when the main building systems are shut down.
The HVAC unit shall not be powered off the same electrical panel as the
telecommunications spaces.
For specialized area such as Data Center where the room house-in sensitive
electronic components that will generate heat, it shall be provided with
proper cooling to maintain operating performance.

7.3.5
The Entrance Facility (EF) room shall be as close as practicable to the
building entrance point and shall be located in a dry area not subjected to
flooding.
The building Entrance Facility (EF) room may be located next to the electrical
service room in order to reduce the length of equipment potential bonding
conductors to the electrical grounding system.
Entrance conduit shall be schedule 40 PVC, corrosion resistant plastic with a
4-inch inside diameter for underground installations.
Entrance conduit shall be encased in concrete or cement slurry when the
minimum conduit depth cannot be attained and conduits pass under
roadways, driveways, where bend points are subject to movement.
All entrance conduit penetrations or structural changes shall be approved by
the structural engineer of the building.
Pathways (Conduit, Cable tray, Trunking, Wireway, and Raceway)
The cable must have a defined route that will protect it according to the
environment in which it exists. Generally electronics engineers are expected to
use common sense to ensure the cable is adequately protected at the same time all
installation shall be in compliance with PEC or NEC and TIA or ISO pathways
standards.
Conduit: Conduit is an enclosed tube made of metal or plastic which provides
mechanical protection to the cable.






The cable should not take up more than 50% of the available cross-sectional
area of the conduit.
Maximum pathways capacity shall not exceed a 40% fill.
Conduit fill capacity shall not exceed a 40% fill, refer to cabling manufacturer
for their cable fill chart for various size and type of conduit with reference to
the nominal diameter of their cable.
Conduit systems should be available at intervals of no greater than 12 m.
Maximum of 30 m between pull points and not more than two 90° bends.
The inside bend radius of the conduit must not be less than six times the inside
diameter of the conduit.
Tray, Trunking, Wireway and Raceway: Tray is a cable containment or pathway
type that can hold cables in place as its use implies. The term cable tray is used as
the generic term for enclosed / non-enclosed, rigid, cable support structures.

The most commonly used form and terminology are:
7-11
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Labeling: Each piece patch panel and outgoing cable from the patch panels shall
be labeled. Corresponding labeling and numbering shall also be provided on the
telecoms outlets.
- Ladder ( the construction looks like a ladder)
- Solid-bottom cable tray
- Perforated or through cable tray
7.3.6

- Wire tray (welded wire construction)

Installation Requirements

General: All installation of the Structured Cabling System or Information
Technology-Generic Cabling for Customer Premises shall comply with the
governing laws and applicable codes and standards.

The installer shall be certified and experienced in the proper installation and
testing of SCS and trained by the cabling system manufacturer.

Installation practices: Install all system components and cross-connect
hardware according to manufacturer’s specifications and instruction as well as
all applicable local codes and standards. All horizontal and backbone cables shall
be installed in the following manner:










7-12
All horizontal cables shall not exceed 90 meters from the telecommunications
outlets in the work area to the horizontal cross connect or FD.

The cable’s minimum bend radius of 4 times the cable diameter.
The maximum cable pulling tension of 25 lbs. shall not be exceeded.
The cabling system and support hardware shall be installed so that it does not
obscure any valves, fire alarm conduit, boxes, or other control devices.
Cables shall be dressed and terminated in accordance with the standards,
manufacturer’s recommendations, and best industry practices.
Cables shall be neatly bundled and dressed to their respective panels or
blocks.
Each panel or block shall be fed by an individual bundle separated and dressed
back to the point of cable entrance into the rack or frame.
Each cable shall be clearly labeled on the cable jacket behind the patch panel
at a location that can be viewed without removing the bundle support ties.
The cable jacket shall be maintained as close as possible to the termination
point.
Rack, Panels & Wiring Modules: A unique identifier shall be marked on the
connecting hardware.
Equipment racks or frames and metallic pathways shall be earthed or
connected to the Telecommunications Bonding Backbone (TBB) of the
building
The TBB backbone shall be used to ground all telecommunications cable
shields, equipment, racks, cabinets, raceways, and other associated hardware
that has the potential for acting as a current carrying conductor.
Firestopping: All firestop systems shall be installed in accordance with the
manufacturer’s recommendations and shall be completely installed and available
for inspection by the local inspection authorities prior to cabling system
acceptance.
Cables shall be installed in continuous lengths from origin to destination.
Cable shall be installed above fire-sprinkler and systems and shall not be
attached to the system or any ancillary equipment or hardware.
Faceplates: A unique identifier shall be marked on each faceplate.
Grounding and Bonding: Communications grounding and bonding shall be in
accordance with the requirements of NEC and TIA or ISO telecommunications
bonding and grounding standard and shall be observed throughout the entire
cabling system.
Personnel Qualification: The installation of SCS, including pathways and
conduit layout, wiring, cable termination and, testing shall be done by a certified
installer under the supervision of a duly registered Professional Electronics
Engineer (PECE) and / or certified designer for Structured Cabling System.

Cables: Horizontal and backbone cables shall be labeled at each end.

7.3.7
Apply fire-rated materials into penetrations in fire rated barriers such as
penetrations to floor slabs in the telecommunication riser / chase to establish
the fire-resistance rating and also to avoid fumes or gases from escaping or
penetrating thru the barrier.
All penetrations through fire-rated building structures (walls and floors) shall
be sealed with an appropriate firestop system.
Testing, Administration and Documentation
Testing: All cables and termination hardware shall be 100% tested for defects in
installation and to verify cable performance under installed conditions. All
conductors of each installed cable shall be verified useable by the contractor prior
to system acceptance.


All UTP and fiber optic cable field testing shall be performed with an approved
test device 100% of cables installed shall be tested and shall all result to PASS
remarks channel or permanent link.
All field testers shall be factory calibrated each calendar year by the field test
equipment manufacturer.
Test and Evaluation Reports: Provide test documentation after the completion
of the project. Summary test results and individual test results shall be part of the
close-out submittals and as-built plans.
7-13
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures




Detectors, initiating devices, manual call points and notification devices shall
be installed throughout the building as required by the relevant authority or
authority having jurisdiction (AHJ) or the local BFP.
All buildings, facilities, structures, and premises, except those locations where
protection is not required shall have a fire detection and alarm system that
complies with the local fire code (FCP) and applicable codes and standards.
Each room shall be separately protected.
When a room is divided into sections by walls or partitions, each section shall
be separately protected.
Areas where Detection is not Required
Detectors are not required in the following locations:






Toilet or bathroom with a floor area of less than 4 m2.
Exhaust ducts exhausting from toilets or bathroom.
Spaces under raised floor with a height of 250 mm or less.
Spaces above drop ceiling with a height of 1 m or less.
Concealed spaces under the roof with a height of 1 m or less.
Covered paths, balconies, open-sided covered walkways & staircases,
overhanging roof areas, verandas, provided they are not used for storage of
goods.
Area Limitation

A separate zone shall be provided for each 800 m2 of protected floor area.
The number of detectors required for this area shall not exceed what is
specified by the fire alarm system manufacturer.
False Alarm

The system designer shall take care that in complying with the design
requirements contained herein in this document so that in any given instance
it will not result in a system that is prone to false alarms. Any alarm at the
control panel shall be treated as a fire until it can be proven to be a false
alarm, rather than being treated as a false alarm until proven to be a fire.
7-15
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Monitor and Control of Other Equipment / Systems
The requirements for buildings or facilities with sprinkler flow switch,
supervisory switch, fire pump, jockey pump and gas suppression panel are:




Each sprinkler flow switch shall be monitored by the Fire Alarm and Control
Panel (FACP) as one distinct alarm point or zone.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures


- Each alarm zone
- Each elevator lobby
Each jockey pump shall be monitored by the FACP as one distinct alarm point
or zone.
- Each elevator machine room
- Generator set room
Each gas suppression panel or pre-action deluge panel shall be monitored by
the FACP as one distinct alarm point or zone.
- Fire pump room
- Inside the enclosed exit stairwell at each floor level
One-Way Emergency Communications System (ECS)



Pressurization Fan, Exhaust Fan, Smoke Damper, HVAC, Elevator, Security System, Smoke Control
System
The one-way emergency communications sub-system, when activated by an
initiating device going into alarm, shall automatically send out an alarm tone
and a pre-recorded warning message, alternating with each other, to serve as
the programmed zone alarm.
The requirements for buildings or facilities with pressurization fan, exhaust fan,
smoke damper, HVAC, elevator, security system, smoke control system are:
A one-way Emergency Communications System(ECS) or Emergency Voice
Alarm Communication(EVAC) shall be required for the following facilities:


The microphone shall be secured inside the locked FACP cabinet, and shall be
accessible only to responsible personnel authorized to operate it.

- airports

- transportation terminals with total floor area, including indoor loading /

- seaports
unloading and parking areas, of more than 10,000 m2.
- office buildings with total floor area of more than 20,000 m2
- buildings classified as high rise building (75 ft or 23 m. above ground level)


Two-Way Telephone Communications System
The two-way telephone communications system or fireman’s telephone shall be
part of the fire alarm system and used by the fire responders in the event of fire or
emergency:



7-16
At least one telephone jack shall be provided at the following locations:
- Each floor level
Each fire pump shall be monitored by the FACP as one distinct alarm point or
zone.
A one-way emergency communications system or emergency voice alarm
communications (EVAC) shall form part of the fire alarm system:
If telephone jacks are used instead of telephone stations, at least two portable
handsets shall be stored at the Fire Command Center or FACP for use by the
responsible authorized personnel or emergency responders
For addressable systems with more than 200 automatic detectors, a two-way
telephone communications system shall be required
The FACP shall be capable of individually selecting the phone circuits for
communication and each telephone jack shall be labeled as specified
The two-way telephone communications sub-system shall operate on a
common talk or conference call mode

Each pressurization fan shall be controlled by the FACP as one distinct output
point or zone.
Each exhaust or ventilating fan shall be controlled by the FACP as one distinct
output point or zone.
Each smoke damper shall be controlled by the FACP as one distinct output
point or zone.
Each air handling unit (AHU) shall be controlled by the FACP as one distinct
output point or zone.
Each elevator shall be controlled by the FACP as one distinct output point or
zone.
Each elevator shall be controlled by the FACP as one distinct output point or
zone.
The electrically-controlled doors of the security access control system shall be
controlled by the FACP as one output group.
Each smoke control door, wall, or partition shall be controlled by the FACP as
one distinct output point or zone.
Primary Power Supply
The primary power supply to the fire alarm control panel and the entire system
shall be from the electric utility company, normally direct or derived 220 ~ 240
VAC single phase.
7-17
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures


The primary power supply circuit shall be terminated to the integral power
supply inside the FACP cabinet and no external switch shall be installed
between the circuit breaker at the electrical distribution panel and the FACP.
The primary power supply shall come from a dedicated and exclusive branch
circuit.
Secondary Power Supply / Battery Capacity
The secondary power supply, normally use a gel cell or nickel cadmium batteries
with an automatic charger.



The secondary power supply shall have sufficient capacity to operate the
system under normal non-alarm condition for a minimum of 24 hours, and at
the end of that period, capable of operating all alarm notification appliances
and emergency communications systems for a period of 5 minutes.
The changeover from primary to secondary power supply on primary power
failure, and from secondary to primary power supply on primary power
restoration, shall be automatic.
The system operating on secondary power supply is considered a trouble
condition.
Building Management System
7.4.3
A building management system (BMS) shall not control the functions of the FDAS
but can only monitor it. It shall not be used to replace in whole or in part the FDAS.
The FDAS shall be capable of operating independently at all times.
System Components, Device and Equipment
All components shall be listed (UL) by institutions recognized by relevant
authorities and suitable to use in the locality or region.
Fire Alarm Control Panel
The FACP shall be programmable equipped with panel mounted LCD text display
which will indicate the location of the alarm and fault and resets events showing
the date and time with the zone and loop number.
Location and Environment



7-18
The FACP or network display shall be located in the fire command center of
the building or complex.
In the absence of a fire command center, it should be located ideally in a
position clearly visible from the main entrance or lobby of the building.
If the fire alarm panel is located in another location acceptable to the AHJ, an
annunciator or repeater panel that fully mimics it shall be installed in a
position clearly visible from the main entrance of the building.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Smoke Detectors
The installation of smoke detectors shall comply with the listed spacing specified
in the code (NFPA 72) as applicable and appropriate. Smoke detectors shall be
designed for detection of abnormal smoke densities by the photoelectric or
ionization principle and shall have a time delay to prevent false alarm. The
placement of smoke detectors is very important. Sleeping areas need the most
protection.
Location and Spacing of Smoke Detectors



Smoke detector shall be located on the ceiling. If installed on a sidewall, it shall
be located at a point not more than 300 mm from the ceiling to the top of the
detector.
The quantity of smoke detectors connected on a single zone of a conventional
system, or to a zone monitor module in a semi-addressable system shall not be
more than 20.
For flat ceilings with a height of not more than 4 m, the following shall be
complied with:
- Smoke detector spacing shall not be more than 9 m and all points on the
ceiling shall have a detector within a distance of 6.4 m.
- Spacing of detectors from walls or partitions shall not be less than 300 mm


and not more than 4.5 m.
Smoke detectors shall not be installed less than 500 mm from any air supply
diffuser or outlet, or any other ceiling devices or fixtures that may cause
electromagnetic induction.
For ceilings with a height of more than 6 m, spot-type smoke detectors shall
not be used, instead, beam-type smoke detectors shall be used.
Heat Detectors
Heat detectors are normally used where the speed of operation of smoke
detectors is not required or where, for environmental or other such reasons,
smoke detectors cannot be used in the system. In such circumstances, heat
detectors can provide an acceptable, though less sensitive alternative. Heat
detectors are designed to operate when the temperature rises abnormally quickly
or when a pre-selected temperature is reached.
Location and Spacing of Heat Detectors


Heat detector shall be located on the ceiling. If installed on a sidewall, it shall
be located at a point not less than 150 mm and not more than 300 mm from
the ceiling to the top of the detector.
For flat ceilings of not more than 4m, heat detector spacing shall not be more
than 7.5 m. Therefore, all points on the ceiling shall have a detector within a
distance of 5.3 m.
7-19
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures

Spacing of detectors from walls or partitions shall not be less than 150 mm
and not more than 3.75 m.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures

A heat detector shall not be installed in a location wherein the ambient
condition is such that the relative humidity is above 93%.

Beam Type Smoke Detector

This type of detector is specifically designed for interior use in large open–type
areas, such as warehouses, workshops, etc. where the installation of point–type
detectors would be difficult.For ceilings with a height of more than 6 meters,
beam-type smoke detectors shall be used in place of spot type smoke detectors:


Location of Beam Type Detectors



The beam length and width coverage shall not exceed the maximum permitted
by the manufacturer’s published specifications and instructions.
Beam-type detectors and mirrors or reflectors shall be mounted on stable
surfaces to prevent false operation or trouble occurrences due to movement.
Beam-type detectors and mirrors or reflectors shall be mounted on stable
surfaces to prevent false operation or trouble occurrences due to movement.

The duct smoke detector shall be listed for use with the air velocity present in
the duct. Further, it shall be listed for use over the complete range of
temperature and humidity expected at the detector when the AHU is
operating.
The duct smoke detector shall be installed in such a way as to obtain a
representative sample of the airstream. To achieve this, the detector shall be
installed outside the duct with rigidly mounted sampling tubes protruding
into the duct.
Manual Pull Station
Manual fire detection is achieved through the activation of fire alarm manual pull
station or call point. The basic principle of manual pull station is that no one
should be able to leave a building or a storey of a building, without passing a
manual pull station or call point. The fire code recommends that manual pull
stations should be located on escape routes or fire exits.
Location and Mounting of Manual Pull Station

7-20
Manual fire alarm stations shall be located within 1.5 m of each exit door on
each floor.
Additional manual fire alarm stations shall be so located that from any point
within the building, the travel distance to activate the alarm shall not be more
than 30 m, measured horizontally on the same floor.
Manual fire alarm boxes or pull stations shall be constructed with clearly
visible operating instructions provided on the cover and the word ‘FIRE’ shall
appear on the front of the stations.
The alarm sound from audible notification appliances shall be clearly audible
throughout the floor and / or building in which they are installed. It should be
sufficient to warn and initiate evacuation of all occupants for whom the alarm
sound is intended.


Location of Duct Type Detectors

Manual fire alarm stations shall be mounted on a background of contrasting
color, and in a well-lighted location, so that they can be easily seen.
Notification Appliances
Duct Type Smoke Detector
For centralized air-conditioning systems, the return air duct of all air handling
units (AHU) shall be equipped with a duct-mounted smoke detector.
Manual fire alarm stations shall be installed at a height of 1.4 m above the
finished floor level and shall be located at easily accessible points, free from
obstructions.




Audible and visible notification appliances that produce audible and visible
alarm signals, such as horn strobes or speaker strobes, shall be used in all
public building. Any other facility that does not use audible or visible
notification appliances shall be subject to the approval of the AHJ.
A sufficient number of audible notification appliances shall be used to produce
a minimum sound level of 65 dBA, or 10 dB above the ambient noise level and
having a duration of at least 30 seconds.
The sound level produced by audible notification appliances and the ambient
noise combined shall not exceed 115 dBA.
The horizontal spacing between notification appliances shall not be more than
30 m.
Trouble conditions in the system shall not cause the automatic activation of
any notification appliance.
For facilities that use the bell sound as part of regular operations, such as
schools, horns or sounders shall be used instead.
Annunciator Panel
For all buildings or facilities, at least one secondary display, such as a LCD display
that annunciates the exact information shown at the FACP primary display, shall
be installed in another appropriate location within the protected premises.


The zone annunciator shall be directory type or graphical type, wherein the
display or indicator lamp would represent one alarm zone.
In buildings or facilities where people sleep, such as hospitals, or the like, at
least one zone annunciator per floor level shall be installed so that occupants
get immediate information on the location of the fire detection.
7-21
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures

7.4.4
In office buildings, hospitals, or the like, wherein the automatic detectors
inside the rooms or units on the same floor are connected as a zone, an
indicator light or annunciator shall be installed outside the room and clearly
visible from the corridor to indicate the actuation of the detectors.
Installation Requirements
All installation of the fire alarm system shall comply with the applicable codes and
requirements referred herein and approved by the authority having jurisdiction
(AHJ). The installation of FDAS, including conduit layout works, wiring, equipment
mounting and installation, equipment connection and termination, programming,
testing and commissioning, shall be done by qualified personnel or by installers
under the supervision of qualified personnel.
Fire Alarm Cable: NEC Article 760 covers the installation of wiring of fire alarm
systems, including all circuits controlled and powered by the fire alarm system.
Wiring shall be in accordance with local and national codes and as recommended
by the manufacturer of the fire alarm system.


Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
shall be subject for final inspection to be conducted by in the presence of the
authorized representative and electronics engineer.
As-built Plans and Drawings: As-built plans and drawings of the complete
installation including all floor plans and a single line diagram of the system shall
be provided to the user before final inspection by the AHJ. A copy of the as-built
drawings shall be on hand at the Fire Command Centre or near the FACP at all
times.
Operation and Maintenance Manuals: Operation and maintenance manuals of
the installed equipment shall be provided to the user and shall include complete
trouble-shooting instructions and guidelines. A complete copy shall be on hand at
the Fire Command Centre or near the fire alarm control panel.
All wire and cable shall be UL listed and approved by a recognized testing
agency for use for fire alarm and protective signaling system.
Number and size of conductors shall be as recommended by the fire alarm
system manufacturer, but not less than 18 AWG (1.02 mm) for Initiating
Device Circuits, Signaling Line Circuits and Notification Appliance Circuits.
Conduits and boxes: All conduits and boxes shall be in accordance with the
Philippine Electrical Code (PEC), NEC and local code requirements. All boxes and
cabinets shall be approved particular use and purpose.



Where required, all wiring shall be installed in conduit or raceway.
Conduit fill shall not exceed 40% of interior cross sectional area where
three or more cables are contained within a single conduit.
Cable must be separated from any open conductors of power, or Class 1
circuits, and shall not be placed in any conduit, junction box or raceway
containing these conductors.
Testing Documentation and Administration
Testing: The service of a competent, factory-trained engineer or technician
authorized by the manufacturer of the fire alarm equipment shall be provided to
technically supervise and participate during all of the adjustments and tests for
the system. All installation shall tested in accordance with the requirements of
the code the tests should be conducted by in the presence of the authorized
building representative and Engineer On Record (EOR) .The test results should
be entered in the log or record.
Final Inspection: At the final inspection, a factory-trained representative of the
manufacturer of the major equipment shall certify and demonstrate that the
system functions properly in every respect. All devices and equipment tested
7-22
7-23
8-5
567.8 – 946.3
Public Institutions other than hospitals
283.9 – 473.1
Factories (Liters /person/shift. exclusive of industrial waste)
56.8 -132.5
28.4
Public parks with bathhouse, showers and flush toilets
37.8
Swimming pools and bathing places*
37.8
Laundry residences
378.5-567.8
Country Clubs per resident members*
94.6 – 189.3
Country clubs per member present*
94.6- 189.3
Source: Excerpts from Table1ofChapterXVII–IRRCodeonSanitationofthePhilippinesPD856
1 per room
each
for
each
1 per 25
Over 150, add one fixture for
each additional 50 males
1:1-100
2:101-200
3:201-400
4:401-600
Over 600, add one fixture for
each additional 300 males
for
Urinals
(Fixtures/Person)
Minimum Requirements for Various Occupancies
Public picnic parks (toilet waste only)
Hospitals
Hospitals* (Liters per bed)
Over 55, add 1 fixture for
each additional 40 persons
56.8
0:1-9
1:10-50
Add one fixture
additional 50 males
283.9 - 378.5
1: 1-15
3:16-35
4: 36-55
75.7
1: 1-15
2: 16-35
3: 36-55
Day school with cafeteria but no gym or showers (Quantity estimated from
maximum no. expected to use gyms and showers in one day)
Hospitals –for employee use
45.4
1 per room
Day school with cafeterias but not gymnasiums or showers (Quantity
estimated from no. of meals served or 80% of enrollment)
Hospital waiting rooms
30.3
1 per dwelling or apartment
unit
Day school without cafeterias, gymnasium or showers*
Dwellings
Single dwelling
Multiple dwelling or apartment houses
189.3
Over 55, add 1 fixture for
each additional 40 persons
Work and construction camps (semi-permanent)
1 per 50
Day workers at schools and offices
283.9 - 378.5
1: 1-15
3:16-35
4: 36-55
Boarding schools
189.3
1: 1-15
2: 16-35
3: 36-55
132.5 - 189.3
Dormitories for Staff use
Tourist camps or trailer parks
1 per 8
26.5 – 37.8
Add 1 fixture for each
additional 25 males (over
10) and 1 for each additional
20 females (over 8)
3.8 - 11.4
Kitchen wastes at hotels, camps, boarding houses, etc. serving 3 meals/day
1 per 10
Restaurants (kitchen waste per meal serve)
Dormitories
School
189.3
Over 400, add one fixture
for each additional 500
males and 1 for each
additional 125 females
Hotels and motels
3: 1-50
4:51-100
8:101-200
11:201-400
189.3
1: 1-100
2: 101-200
3: 201-400
Boarding houses
Assembly places, theaters, Auditoriums,
convention halls, etc. for public use
151.4
Over 55, add 1 fixture for
each additional 40 persons
Rooming houses
Male Only
189.3
0:1-9
1:10-50
Add one fixture
additional 50 males
Multiple Family use
Female
Luxury camps
283.9 – 378.5
1: 1-15
3:16-35
4: 36-55
Resort camps (night and day) with limited plumbing
189.3
Male
Large dwellings with numerous fixtures
Liters/Person
1: 1-15
2: 16-35
3: 36-55
Type of Establishment
Assembly places, theaters, Auditoriums,
convention halls, etc. for permanent
employee use
Small dwellings and cottages
Water
Closet(Fixtures/Person)
Waste water contribution per capita / day
Type of Building or Occupancy
Table 8-2
Table 8-1
Female
1: 1-200
2:201-400
3:401-750
1 per 40
1 per 12
1 per 40
1 per room
1 per 40
1 per room
1 per 40
1 per dwelling or apartment
unit
1 per 40
Over 12, add 1 fixture for
each additional 20 males and
1 for each additional 15
females
1 per 12
Over 750, add one fixture for
each additional 500 persons
1: 1-200
2: 201-400
3: 401-750
1 per 40
Male
Lavatories
(Fixtures/Person)
1 per room
1 per dwelling
apartment unit
1 per 8
or
1 per 8
For females , add 1
bathtub per 30,
Over 150, add 1
bathtub per 20
Bathtubs or Showers
(Fixtures/Person)
1 per 150
1 per 150
1 per 150
1:1-150
2:151-400
3:401-750
Over 750, add one
fixture
for
each
additional 500 persons
Drinking Fountains
(Fixtures/Person)
8-6
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
8-7
1: 1-10
2: 11-25
3: 26-50
4: 51-75
Industrial
Warehouses, workshops, foundries and
similar establishments- for employees use
1: 1-15
2: 16-35
3: 36-55
Institutional other than hospitals or penal
institutions (on each occupied floor) for
employees use
3: 1-50
4:51-100
8:101-200
11:201-400
1: 1-15
3:16-35
4: 36-55
1: 1-15
3:16-35
4: 36-55
1: 1-25
2: 26-100
4: 101-200
8: 201-400
1: 1-15
2: 16-35
3: 36-55
1: 1-20
2:21-50
1 per 40
1 per 40
1 per 150
1 per 150
Secondary
Others (colleges, universities, Adult
Centers, etc.)
Worship places educational and activities
Unit
Worship places principal assembly place
Source: Table 4-1US – Uniform Plumbing Code 2009
1 per 30
1 per 75
1 per 75
1 per 30
1 per 30
1 per 25
Over 50, add 1 fixture for
each additional 50 persons
1: 1-20
2: 21-50
Over 55, add 1 fixture for
each additional 40 persons
1: 1-15
2: 16-35
3: 36-55
Over 400, add 1 fixture for
each additional 500 males
and one for each 150
females
1: 1-100
2: 101-200
3: 201-400
6: 201-300
Over 300, add 1 fixture for
each additional 200 persons
Elementary
Schools – for student use
Nursery
Schools – for staff use
All schools
Retail or Wholesale Stores
1: 1-50
2: 51-150
3: 151-300
Restaurants, pubs, and lounges
1: 1-50
2: 51-150
4: 151-300
Same as office or Public
Building employees use
Public or professional offices
Female
1 per exercise room
Male
Water
Closet(Fixtures/Person)
1 per cell
Over 55, add 1 fixture for
each additional 40 persons
1: 1-15
2: 16-35
3: 36-55
Over 55, add 1 fixture for
each additional 40 persons
1: 1-15
2: 16-35
3: 36-55
Over 400, add one fixture
for each additional 500
males and 1 for each
additional 150 females
1: 1-100
2: 101-200
3: 201-400
Cell
Exercise room
Type of Building or Occupancy
Penal institution – for prison use
Penal institution – for employees use
Office or public buildings – for employees
use
1: 1-15
3:16-35
4: 36-55
1 per 20
Over 55, add 1 fixture for
each additional 40 persons
1 per 25
Institutional other than hospitals or penal
institutions (on each occupied floor)
Office or public buildings
1: 1-10
2:11-25
3:26-50
4:51-75
Female
Over 100, add 1 fixture for
each additional 30 persons
1 per 8 patients
Male
Water
Closet(Fixtures/Person)
Individual room
Ward Room
Type of Building or Occupancy
for
for
each
each
Public
1 per 150
1 per 150
1 per 35
1 per 35
1 per 75
1 per 50
0:0-25
1:26-100
2:101-200
3:201-400
4:401-600
Over 600, add one fixture for
each additional 300 males
0:1-150
Over 150, add one fixture for
each additional 150 males
Same as office or
Building employees use
Male Only
each
each
Female
1: 1-200
2:201-400
3:401-750
1 per cell
1 per 40
1 per 40
1 per 40
Over 750, add one fixture for
each additional 500 persons
1: 1-200
2: 201-400
3: 401-750
1 per 10
1 per 10
Up to 100, 1 per 10 persons
Over 100, 1 per 15 persons
1 per 10 patients
Male
Lavatories
(Fixtures/Person)
1 per 8
1 per 8
1 shower for each 15
persons exposed to
excessive heat or to
skin contamination with
poisonous, infectious
or irritating material
1 per 20 patients
Bathtubs or Showers
(Fixtures/Person)
1 per cell block floor
1 per 150
1 per 150
1 per 150
1 per 150
1 per 150
Drinking Fountains
(Fixtures/Person)
Female
1: 1-150
2: 151-200
3: 201-400
1: 1-25
2:26-50
1 per 40
1 per 40
1 per 35
1 per 2 water closets
1 per 2 water closets
1 per 40
1 per 40
1 per 35
Over 50, add 1 fixture for
each additional 50 persons
1: 1-25
2: 26-50
1 per 40
1 per 2 water closets
Over 400, add 1 fixture for
each additional 400 persons
1: 1-150
2: 151-200
3: 201-400
Same as office or Public
Building employees use
1 per exercise room
Male
Lavatories
(Fixtures/Person)
Bathtubs or Showers
(Fixtures/Person)
1 per 150
1 per 150
1 per 150
1 per 150
1 per 150
1 per 150
0: 1-30
1:31-150
One additional drinking
fountain for each 150
persons thereafter
Same as office or Public
Building employees use
1 per exercise room
Drinking Fountains
(Fixtures/Person)
8-8
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
for
for
Urinals
(Fixtures/Person)
1 per exercise room
0:1-9
1:10-50
Add one fixture
additional 50 males
0:1-9
1:10-50
Add one fixture
additional 50 males
1:1-100
2:101-200
3:201-400
4:401-600
Over 600, add one fixture for
each additional 300 males
0:1-9
1:10-50
Add one fixture
additional 50 males
0:1-9
1:10-50
Add one fixture
additional 50 males
Male Only
Urinals
(Fixtures/Person)
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
8-9
Drinking Fountains shall not be installed in Toilets rooms.
Laundry trays, One (1) laundry tray or one (1) automatic washer standpipe for each dwelling unit or one (1) laundry tray or one (1) automatic washer standpipe or combination thereof, for each
twelve (12) apartments. Kitchen sinks, one (1) for each dwelling or apartment unit.
Automatic washer standpipe or combination thereof, for each twelve (12) apartments. Kitchen sinks, one (1) for each dwelling or apartment unit.
For each urinal added in excess of the minimum required, one water closet shall be permitted to be deducted. The number of water closets shall not be reduced to less than two-thirds (2 / 3) of
the minimum requirement.
As required by Sanitation in Places of Employment.
Where there is exposure to skin contamination with poisonous, infectious, or irritating materials, provide one (1) lavatory for each five (5) persons.
600 mm of wash sink, 450 mm of circular basin, when provided with water outlets for such space, shall be considered equivalent to one (1) lavatory.
Laundry trays, one (1) for each fifty (50) persons, Service sinks, one (1) for each hundred (100) persons.
General. In applying this schedule of facilities, consideration shall be given to the accessibility of the fixtures. Conformity purely on a numerical basis may not result in an installation suited to
the needs of the individual establishment. For example, schools should be provided with toilet facilities on each floor having classrooms.
Surrounding materials, wall and floor space to a point 600 mm in front of urinal lip and 1,200 mm above the floor, and not less than 600 mm to each side of the urinal shall be lined with nonabsorbent materials.
Through urinals shall be prohibited.
A restaurant is defined as a business that sells food to be consumed on the premises.
The number of occupants for a drive-in restaurant shall be considered as equal to the number of parking stalls.
Hand-washing facilities shall be available in the kitchen for employees
Where foods is consumed indoors, water stations shall be permitted to be substituted for drinking fountains. Offices or Public buildings for use by more than six (60 persons shall have one (1)
drinking fountain for the first one-hundred fifty (150) persons and one (1) additional fountain for each three-hundred (300) persons thereafter.
There shall be at least one (1) drinking fountain per occupied floor in schools, theaters, auditoriums, dormitories, offices or Public buildings.
The total number of water closets for females shall be equal to the total number of water closets and urinals required for males. This requirement shall not apply to Retail or Wholesales Stores.
For smaller-type Public and Professional Offices such as banks, dental offices, law offices, real estate offices, architectural offices, engineering offices and similar uses. A Public area in these
offices shall use the requirement for the Retail or Wholesale Stores.
Recreation or community room in multiple dwellings of apartment buildings, regardless of their occupant load, shall be permitted to have separate single-accommodation facilities in commonuse areas within tracts or multi-family residential occupants where the use of these areas is limited exclusively to owners, residents and their guests. Examples are community recreation or
multi-purpose areas in apartments, condos, townhouses, or tracts.
A drinking fountain shall not be required in occupancies of 30 or less.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
Notes for Table 8-2
1.
Building categories not shown on this Table shall be considered separately by the Sanitary Engineer.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
8.3.2
Sanitary Drainage Systems
Use of formula and empirical data must be directly applicable to the behavior
of liquid waste matter or solutions in terms of velocity, roughness coefficient,
slope and pressure. Sanitary and Waste will be designed with a minimum
slope of one percent (1%), or as permitted by this DGCS Volume 6.
Sizes will be computed using the following:


Manning Equations
𝑉𝑉 =
Maximum Velocity
R
S
32 mm
40 mm
50 mm
80 mm
100 mm
1
1 2⁄
𝑅𝑅 3 𝑆𝑆 ⁄2
𝑛𝑛
Minimum Velocity
=
0.75m/sec
n
=
Coefficient of Roughness 0.011 or as specified
by pipe manufacturer
Velocity of Sewage Flow
=
=
Sewage shall be computed using Drainage Fixtures Unit values in accordance
with Section 8.3.1.
=
Exception: On self-service laundries.
-
and Q = AV
3.05m/sec
Wetted perimeter
Slope
Fixture Units Equivalents
The unit equivalent of plumbing fixtures shown in Table 8-3 shall be based on
the size of the trap required, and the unit equivalent of fixtures and devices
not shown in Table 8-3 shall be based on the rated discharge capacity in liters
per second in accordance with Table 8-4.
Maximum trap loadings for sizes up to 100 mm are as follows:
-
-
-
-
1unit
3units
4units
8units
6units
8-10
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 8-3
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Drainage Fixture Unit Values (DFU)
Plumbing Appliance, Appurtenance or
Fixture
Min Trap
Size and
Trap Arm7
Nonpublic
Co on
public
2.0
Bath tub or Combination Bath/Shower
38
2.0
Bidet
32
1.0
32
2.0
50
3.0
Bidet
ClothesWasher,domestic,standpipe
5
Assembly8
Min Trap
Size and
Trap Arm7
Nonpublic
Co on
public
Assembly8
Liters/Flush
3.0
3.0
1.0
1.0
Urinal, exposed trap
382
2.0
2.0
5.0
Water Closet, 6.1 Liters / Flush
GravityTank6
75
3.0
4.0
6.0
Water Closet, 6.1 Liters / Flush
Flushometer Tank6
75
3.0
4.0
6.0
Dental Unit, cuspidor
32
3.0
4.0
6.0
382
2.0
2.0
2.0
Water Closet, 6.1 Liters / Flush
Flushometer Valve6
75
Dishwasher ,domestic, with independent
drain
4.0
6.0
8.0
32
0.5
0.5
1.0
Water Closet, greater than 6.1 LPF
GravityTank6
75
Drinking Fountain or Water cooler (per
head)
4.0
6.0
8.0
50
3.0
3.0
Water Closet, greater than 6.1 Liters /
Flush Flushometer Valve6
75
Food-waste-grinder, commercial
Floor Drain, emergency
50
0.0
0.0
Source: Excerpts from Table 8-3 UPC 2000 Edition
Footnotes of Table 8-3:
1. Indirect waste receptors shall be sized based on the total drainage capacity of the fixtures that
drain therein to, in accordance with Table 8-4.
2. Provide a 50 mm minimum drain.
3. For refrigerators, coffee maker, water stations, and similar low demands.
4. For commercial sinks, dishwashers, and similar moderate or heavy demands.
5. Buildings having a clothes washing area with clothes washers in a battery of three (3) or more
clothes washers shall be rated at six (6) fixture units each for purposes of sizing common
horizontal and vertical drainage piping.
6. Water closets shall be computed as six (6) fixture units when determining septic tank sizes
based on.
7. Trap sizes shall not be increased to the point where the fixture discharge may be inadequate to
maintain their self-scouring properties.
8. Assembly/ Public Use (See Table 8-1)
Floor Drain(for
Section7.3.2)
additional
sizes
see
50
2.0
2.0
2.0
Shower single head trap
50
2.0
2.0
2.0
Multi-head, each additional
50
1.0
1.0
1.0
Lavatory, single
32
1.0
1.0
1.0
Lavatory in sets of two or three
38
2.0
2.0
2.0
Wash fountain
38
2.0
2.0
Wash fountain
50
3.0
3.0
Mobile Home, trap
75
Receptor,indirectwaste1,3
38
Seenote1
and 3
Seenote1 and
3
Receptor,indirectwaste1,4
50
Seenote1
and 4
Seenote1 and
4
Receptor,indirectwaste
75
Seenote1
Seenote1
1
12.0
Bar
38
1.0
Bar
382
2.0
2.0
Clinical
75
6.0
6.0
Commercial with food waste
382
3.0
3.0
Special Purpose
38
2.0
3.0
3.0
Special Purpose
50
3.0
4.0
4.0
Special Purpose
75
6.0
6.0
Kitchen, domestic
(with or without food-waste-grinder and/or
dishwasher)
382
2.0
2.0
2.0
Laundry
(with or without discharge from a clothes
washer)
38
2.0
Service or Mop Basin
50
3.0
3.0
Service or Mop Basin
75
3.0
3.0
Service, flushing rim
75
6.0
6.0
2.0
2.0
Wash, each set of faucets
Table 8-4
Discharge Capacity in Liters per Second for Intermittent Flow Only
L/sec
Sinks
8-11
Plumbing Appliance, Appurtenance or
Fixture
Urinal, integral trap 3.78 Liters/Flush 3.78
Liters/Flush 1.0GPF2
50
2.0
2.0
5.0
Urinal, integral trap greater than 3.78
50
2.0
2.0
6.0
Up to 0.47
Equals
1 Unit
0.50 to 0.95
Equals
2 Units
1.00 to 1.89
Equals
4 Units
1.95 to 3.15
Equals
6 Units
Source: Table 8-4 UPC 2000 Edition
Size of Drainage Piping
The minimum sizes of vertical and / or horizontal drainage piping shall be
determined from the total of all fixture units connected thereto, and
additionally, in the case of vertical drainage pipes, in accordance with their
length.
Table 8-5 shows the maximum number of fixture units allowed on any vertical
or horizontal drainage pipe, building drain or building sewer of a given size;
the maximum number of fixture units allowed on any branch interval of a
given size; and the maximum length (in feet and meters) of any vertical
drainage pipe of a given size.
8-12
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
For a continuous flow into a drainage system, such as from a pump, sump
ejector, air conditioning equipment, or similar device, two (2) fixture units
shall be allowed for each 0.06 L/sec. of flow.
Fixture Connections (Drainage)
Drainage piping shall be provided with approved inlet fittings for fixture
connections, correctly located according to the size and type of fixture
proposed to be connected.
Two fixtures set back-to-back, or side-by-side, within the distance allowed
between a trap and its vent, may be served by a single vertical drainage pipe
provided that each fixture wastes separately into an approved double fixture
fitting having inlet openings at the same level.
Pot sinks, scullery sinks, dish washing sinks, silverware sinks, commercial
dishwashing machines, silverware-washing machines, and other similar
fixtures shall be connected directly to the drainage system. A floor drain shall
be provided adjacent to the fixture, and the fixture shall be connected on the
sewer side of the floor drain trap, provided that no other drainage line is
connected between the floor drain waste connection and the fixture drain. The
fixture and floor drain shall be trapped and vented as required by these Design
Guidelines.
Closet Rings (Closet Flanges)
Closet rings (closet flanges) for water closets or similar fixtures shall be of
an approved type and shall be bronze, copper, hard lead, cast iron,
galvanized malleable iron, ABS, PVC, or other approved materials. Each
such closet ring (closet flange) shall be approximately 175 mm in diameter
and, when installed, shall, together with the soil pipe, present a 38 mm
wide flange or face to receive the fixture gasket or closet seal.
Caulked-on closet rings (closet flanges) shall be not less than 6 mm thick and
not less than 50 mm in overall depth.
Closet rings (closet flanges) shall be burned or soldered to lead bends or stubs,
shall be caulked to cast iron soil pipe, shall be solvent cemented to ABS and
PVC and shall be screwed or fastened in an approved manner to other
materials.
All such closet rings (closet flanges) shall be adequately designed and secured
to support fixtures connected thereto.
Closet screws, bolts, washers, and similar fasteners shall be of brass, copper,
or other listed, equally corrosion resistant materials. All such screws and
bolts shall be of adequate size and number to properly support the fixture
installed.
8-13
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
shall be so constructed as to insure a positive mechanical seal. Such backwater
valves shall remain sufficiently open during periods of low flows to avoid
screening of solids and shall not restrict capacities or cause excessive
turbulence during peak loads. Unless otherwise listed, valve access covers
shall be bolted type with gasket and each valve shall bear the manufacturer’s
name cast into body and cover.
The drainage and venting systems in connection with fixtures, sumps,
receiving tanks, and mechanical waste lifting devices, shall be installed under
the same requirements as provided for in this Guidelines for gravity systems.
Sumps and receiving tanks shall be water tight and shall be constructed of
concrete, metal, or other approved materials. If constructed of poured
concrete, the walls and bottom shall be adequately reinforced and designed to
recognized acceptable standards. Metal sumps or tanks shall be of such
thickness as to serve their intended purpose and shall be treated internally
and externally to resist corrosion.
All such sumps and receiving tanks shall be automatically discharged and,
when in any “Public use” occupancy, shall be provided with dual pumps or
ejectors arranged to function independently in case of overload or mechanical
failure. The lowest inlet shall have a minimum clearance of 50 mm from the
high water or “starting” level of the sump.
Sumps and receiving tanks shall be provided with substantial covers having a
bolt and gasket type manhole or equivalent opening to permit access for
inspection, repairs, and cleaning. The top shall be provided with a vent pipe
which shall extend separately through the roof, or when permitted, may be
combined with other vent pipes. Such vent shall be large enough to maintain
atmospheric pressure within the sump under all normal operating conditions
and, in no case, shall be less in size than that required by Table 7-5 for the
number and type of fixtures discharging into the sump, nor less than 38 mm in
diameter.
When the foregoing requirements are met and the vent, after leaving the
sump, is combined with vents from fixtures discharging into the sump, the size
of the combined vent need not exceed that required for the total number of
fixtures discharging into the sump. No vent from an air-operating sewage
ejector shall combine with other vents.
Air tanks shall be so proportioned as to be of equal cubical capacity to the
ejectors connected therewith in which there shall be maintained an air
pressure of not less than 3 kg for each meter of height the sewage is to be
raised. No water operated ejectors shall be permitted.
When subsoil drainage systems are installed, such systems shall be discharged
into an approved sump or receiving tank and shall be discharged in a manner
satisfactory to the Sanitary Engineer/ Master Plumber.
Grinder Ejector Pump: With the approval of the Sanitary Engineer/ Master
Plumber, a grinder pump may be used. A Grinder Ejector pump is used to
discharge wastewater that cannot be discharged through a gravity system and
8-20
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
no joint or pipe in the building (except the uppermost 3.048 m.) of the system
shall have been submitted to a test of less than a 3.048 m. head of water. The
water shall be kept in the system, or in the portion under test, for at least
fifteen (15) minutes before inspection starts. The system shall then be tight at
all points.
8.3.4
Air Test: The air test shall be made by attaching an air compressor testing
apparatus to any suitable opening, and, after closing all other inlets and outlets
to the system, forcing air into the system until there is a uniform gage pressure
of 34.5 kPa or sufficient to balance a column of mercury 254 mm in height. The
pressure shall be held without introduction of additional air for a period of at
least fifteen (15) minutes.
Building Sewers
Every building in which plumbing fixtures are installed and every premises
having drainage piping thereon, shall have a connection to a Public or Private
sewer, except as provided below.
When no Public sewer, intended to serve any lot or premises, is available in
any thoroughfare or right of way abutting such lot or premises, drainage
piping from any building or works shall be connected to an approved Private
sewage disposal system.
Within the limits prescribed by article immediately below hereof, the
rearrangement or subdivision into smaller parcels of a lot which abuts and is
served by a Public sewer shall not be deemed cause to permit the construction
of a Private sewage disposal system, and all plumbing or drainage systems on
any such smaller parcel or parcels shall connect to the Public sewer.
The Public sewer may be considered as not being available when such Public
sewer or any building or any exterior drainage facility connected thereto, is
located more than 60.8 meter from any proposed building or exterior drainage
facility on any lot or premises which abuts and is served by such Public sewer.
No permit shall be issued for the installation, alteration, or repair of any
Private sewage disposal system, or part thereof, on any lot for which a
connection with a Public sewer is available.
On every lot or premises hereafter connected to Public sewer, all plumbing
and drainage systems or parts thereof, on such lot or premises shall be
connected with such Public sewer.
Exception: Single family dwellings and buildings or structures accessory
thereto, existing and connected to an approved Private sewage disposal
system prior to the time of connecting the premises to Public sewer may,
when no hazard, nuisance, or insanitary condition is evidenced and written
permission has been obtained from the Sanitary Engineer, remain connected
to such properly maintained Private sewage disposal system when there is
insufficient grade or fall to permit drainage to the sewer by gravity.
8-22
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Exception:
When approved by the Sanitary Engineer and where it is impractical, due to
the depth of the street sewer or to the structural features or to the
arrangement of any building or structure, to obtain a slope of 20.9 mm/m, any
such pipe or piping 100 mm through 150 mm may have a slope of not less
than 10.5 mm/m and any such piping 200 mm and larger may have a slope of
not less than 5.3 mm/m.
Building sewer piping shall be laid on a firm bed throughout its entire length,
and any such piping laid in made or filled-in ground shall be laid on a bed of
approved materials and shall be adequately supported to the satisfaction of
the Sanitary Engineer.
8.3.5
No building sewer or other drainage piping or part thereof, which is
constructed of materials other than those approved for use under or within a
building, shall be installed under or within 600 mm of any building or
structure, or part thereof, nor less than 300 mm below the surface of the
ground. The provisions of this subsection include structures such as porches
and steps, whether covered or uncovered, breezeways, roofed porte-cocheres,
roofed patios, carports, covered walks, covered driveways, and similar
structures or appurtenances.
Cleanouts
Cleanouts shall be placed inside the building near the connection between the
building drain and the building sewer or installed outside the building at the
lower end of the building drain and extended to grade. Additional building
sewer cleanouts shall be installed at intervals not to exceed 30.48 meter in
straight runs and for each aggregate horizontal change in direction exceeding
one hundred thirty-five (135) degrees (2.36 rad).
When a building sewer or a branch thereof does not exceed 3.048 meter in
length and is a straight line projection from a building drain which is provided
with a cleanout, no cleanout will be required at its point of connection to the
building drain.
All required building sewer cleanouts shall be extended to grade and shall
comply with all appropriate sections of Cleanouts, Section 8.3.6 for sizing,
construction and materials. When building sewers are located under buildings,
the cleanout requirements of Section 8.3.6 shall apply.
Each cleanout shall be installed so that it opens to allow cleaning in the
direction of flow of the soil or waste or at right angles thereto, and except in
the case of wye branch and end-of-line cleanouts, shall be installed vertically
above the flow line of the pipe.
Cleanouts installed under concrete or asphalt paving shall be made accessible
by yard boxes, or extending flush with paving with approved materials and be
adequately protected.
8-24
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Sterile Equipment: Appliances, devices, or apparatus such as stills, sterilizers,
and similar equipment requiring water and waste and used for sterile
materials shall be drained through an air gap.
Appliances: Appliances, devices, equipment, or other apparatus not regularly
classed as plumbing fixtures which are equipped with pumps, drips, or
drainage outlets may be drained by indirect waste pipes discharging into an
approved type open receptor.
When the condensate waste from air conditioning coils discharges by direct
connection to a lavatory tailpiece or to an approved accessible inlet on a
bathtub overflow, the connection shall be located in the area controlled by the
same person controlling the air-conditioned space.
When undiluted condensate waste from a fuel burning condensing appliance
is discharged into the drainage system, the material in the drainage system
shall be cast iron, galvanized iron, plastic, or other materials approved for this
use.
Exceptions: When the above condensate is discharged to an exposed fixture
tailpiece and trap, such tailpiece and trap may be brass.
Any materials approved in Section 8.3.13 “MATERIALS FOR SANITARY
DRAINAGE” may be used when, in the opinion of the Sanitary Engineer,
condensate waste from a fuel burning condensing appliance is diluted either
before or after discharge into the drainage system.
No domestic dishwashing machine shall be directly connected to a drainage
system or food waste disposer without the use of an approved dishwasher
airgap fitting on the discharge side of the dishwashing machine. Listed airgaps
shall be installed with the flood level (FL) marking at or above the flood level
of the sink or drainboard, whichever is higher.
Cooling Water: When permitted by the Sanitary Engineer, clean running
water used exclusively as a cooling medium in an appliance, device or
apparatus, may discharge into the drainage system through the inlet side of a
fixture trap in the event that a suitable fixture is not available to receive such
discharge. Such trap connection shall be by means of a pipe connected to the
inlet side of an approved fixture trap, the upper end terminating in a funnel
shaped receptacle set adjacent, and not less than 150 mm above the overflow
rim of the fixture.
Drinking Fountains: Drinking fountains may be installed with indirect
wastes.
Steam and Hot Water Drainage Condensers and Sumps: No steam pipe
shall be directly connected to any part of a plumbing or drainage system, nor
shall any water having a temperature above 60°C be discharged under
pressure directly into any part of a drainage system. Pipes from boilers shall
discharge by means of indirect waste piping, as determined by the Sanitary
Engineer or the boiler manufacturer’s recommendations.
8-30
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Such pipes may be indirectly connected by discharging into an open or closed
condenser, or intercepting sump of approved type, that will prevent the
entrance of steam or such water under pressure into the drainage system. All
closed condensers or sumps shall be provided with a vent which shall be taken
off the top and extended separately, full size above the roof. All condensers
and sumps shall be properly trapped at the outlet with a deep seal trap
extending to within 150 mm of the bottom of the tank. The top of the deep seal
trap shall have a 20 mm opening located at the highest point of the trap to
serve as a siphon breaker.
Outlets shall be taken off from the side in such a manner as to allow a water
line to be maintained that will permanently occupy not less than 50% the
capacity of the condenser or sump. All inlets shall enter above the water line.
Wearing plates or baffles shall be installed in the tank to protect the shell. The
sizes of the blow off line inlet, the water outlets, and the vent shall be as shown
in Table 8-9. The contents of condensers receiving steam or hot water under
pressure must pass through an open sump before entering the drainage
system.
Table 8-9
Pipe Connections in Blow-off Condensers and Sumps
Boiler Blowoff
Water Outlet
Vent
20 mm*
20 mm*
50 mm
25 mm
25 mm
65 mm
32 mm
32 mm
80 mm
40 mm
40 mm
100 mm
50 mm
50 mm
125 mm
65 mm
65 mm
150 mm
Source: Table 8-1 UPC 2000 Edition
*To be used only with boilers of 9.29 sq.m of heating surface or less.
Sumps, condensers, or intercepting tanks which are constructed of concrete
shall have walls and bottom not less than 100 mm in thickness, and the inside
shall be cement plastered not less than 12 mm in thickness. Condensers
constructed of metal shall be not less than No. 12 U.S. Standard gauge 2.77 mm
and all such metal condensers shall be protected from external corrosion by
an approved bituminous coating.
Sumps and condensers shall be provided with suitable means of access for
cleaning and shall contain a volume of not less than twice the volume of water
removed from the boiler or boilers connected thereto when the normal water
level of such boiler or boilers is reduced not less than 100 mm.
Strainers: Every indirect waste interceptor receiving discharge containing
particles that would clog the receptor drain shall have a readily removable
beehive strainer.
Chemical Wastes: Chemical or industrial liquid wastes which are likely to
damage or increase maintenance costs on the sanitary sewer system,
8-31
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
mm/m or one percent slope and shall be of approved corrosion-resistant
material not smaller than the outlet size as required in either Section 310.3 or
310.4 of the UPC 2000 edition, below for air-cooling coils or condensing fuelburning appliances, respectively. Condensate or waste water shall not drain
over a Public way. Indirect Drainage shall be provided for Air-conditioning
condensate waste pipes shall be independent of any drainage and waste
system and shall not be smaller than shown in Table 8-10.
Table 8-10
Minimum Size Condensate Drain Pipes
Minimum Condensate
Pipe Diameter (mm)
Equipment Capacity in Tons of Refrigeration (Kw)
Through 3 (Through 10.56)
20 mm
Through 20 (Through 70.33)
25 mm
Through 90 (Through 316.48)
32 mm
Through 125 (Through 439.6)
40 mm
Through 250 (Through 879.2)
50 mm
Source: Table 8-2 UPC 2000 Edition
The size of condensate waste pipes may be for one unit or a combination of
units, or as recommended by the manufacturer. The capacity of waste pipes
assumes a 10.5 mm/m) or one percent slope, with the pipe running 75% full
at the following conditions:
Outside Air-20%
Room Air – 80%
DB
32°C
DB
24°C
WB
23°C
WB
17°
a) Condensate drain sizing for other slopes or other conditions shall be
approved by the Sanitary Engineer. Air conditioning waste pipes shall be
constructed of materials specified in Section 7.3.
b) Point of Discharge: Air-conditioning condensate waste pipes shall
connect indirectly to the drainage system through an airgap or airbreak to:



8.3.6
A properly trapped receptor
To a points of discharge acceptable by Sanitary Engineer, including dry
wells, leach pits, the tailpiece of plumbing fixtures, etc.
Condensate or waste water shall not drain over a Public way.
Traps and Interceptors
Each plumbing fixture, excepting those having integral traps shall be
separately trapped by an approved type water seal trap. Not more than one
(1) trap shall be permitted on a trap arm.
One (1) trap may serve a set of not more than three (3) single compartment
sinks or laundry tubs of the same depth or three (3) lavatories immediately
8-33
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 8-12
Grease Traps
Total Number of Fixtures
Connected
Required Rate of Flow per
Minute, Liters
Grease Retention Capacity,
kg
1
76
18
2
95
22
3
132
31
4
189
45
Source: Table 10-2 UPC 2000 Edition
Note:
For installations with more than four (4) fixtures, the Sanitary Engineer may permit the use of larger
grease traps designed not to exceed the parameters of Section 8.3.6.9, but not to exceed 284 liters
per minute.
Recommended Procedures for Design, Construction and Installation of Commercial Kitchen
Grease Interceptors:
General: The provisions of this recommended procedure shall apply to the
design, construction, installation, and testing of commercial kitchen grease
interceptors.
Waste Discharge Requirements: Waste discharge from fixtures and
equipment in establishments which may contain grease, including but not
limited to, scullery sinks, pot and pan sinks, dishwashing machines, soup
kettles and floor drains located in areas where grease-containing materials
may exist, may be drained into the sanitary waste through the interceptor
when approved by the Sanitary Engineer.
Toilets, urinals, and other similar fixtures shall not drain through the
interceptor.
All waste shall enter the interceptor through the inlet pipe only.
Design: Interceptors shall be constructed in accordance with the design
approved by the Sanitary Engineer and shall have a minimum of two
compartments with fittings designed for grease retention.
There shall be an adequate number of manholes to provide access for cleaning
all areas of an interceptor; a minimum of one (1) per 3.048 m of interceptor
length. Manhole covers shall be gastight in construction having a minimum
opening dimension of 508 mm.
In areas where traffic may exist the interceptor shall be designed to have
adequate reinforcement and cover.
Location: Each grease interceptor shall be so installed and connected that it
shall be at all times easily accessible for inspection, cleaning, and removal of
the intercepted grease. A grease interceptor may not be installed in any part of
a building where food is handled. Location of the grease interceptor shall meet
the approval of the Sanitary Engineer.
Interceptors shall be placed as close as practical to the fixtures it serves.
Each business establishment for which a grease interceptor is required shall
have an interceptor which shall serve only that establishment.
8-39
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
separator shall flow by gravity or shall be pumped to a higher elevation by
an automatic pump. Pumps shall be adequately sized and accessible. Waste
oil tanks shall have a 50 mm minimum pump-out connection at grade and
40 mm minimum vent to atmosphere at an approved location at least
3.048m above grade.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
approved indirect waste pipes into a floor sink or other approved type
receptor.
Size of Vents:

Design of Interceptors:



Each manufactured interceptor that is rated shall be stamped or labeled by
the manufacturer with an indication of its full discharge rate in L/s. The
full discharge rate to such an interceptor shall be determined at full flow.
Each interceptor shall be rated equal to or greater than the incoming flow
and shall be provided with an overflow line to an underground tank.
Interceptors not rated by the manufacturer shall have a depth of not less
than 600 mm below the invert of the discharge drain. The outlet opening
shall have not less than 457 mm water seal and shall have a minimum
capacity as follows: where not more than three (3) motor vehicles are
serviced and / or stored, interceptors shall have a minimum capacity of
0.2 cubic meter, and 0.03 cubic meter of capacity shall be added for each
vehicle up to ten (10) vehicles. Above ten (10) vehicles, the Sanitary
Engineer shall determine the size of the interceptor required.
Where vehicles are serviced only and not stored, interceptor capacity
shall be based on a net capacity of 0.03 cubic meter for each 9.3 sq.m of
surface to be drained into the interceptor, with a minimum of 0.2 cubic
meter.
Exception:


8.3.7
A combination oil and sand interceptor may be installed when the design
is approved in writing by the Sanitary Engineer.


Each plumbing fixture trap, except as otherwise provided in these Design
Guidelines, shall be protected against siphonage and back-pressure, and
air circulation shall be assured throughout all parts of the drainage system
by means of vent pipes installed in accordance with the requirements of
this Section and as otherwise required by these Design Guidelines.



Vents Not Required:


8-45
Where permitted by the Sanitary Engineer, vent piping may be omitted on
an interceptor when such interceptor acts as a primary settling tank and
discharges through a horizontal indirect waste pipe into a secondary
interceptor. The second interceptor shall be properly trapped and vented.
Traps serving sinks which are part of the equipment of soda fountains, and
counters, need not be vented when the location and construction of such
soda fountains, and counters is such as to make it impossible to do so.
When such conditions exist, said sinks shall discharge by means of
No more than one-third (1 / 3) of the total permitted length, per Table 8-5,
of any minimum sized vent shall be installed in a horizontal position.
When a minimum sized vent is increased one (1) pipe size for its entire
length, the maximum length limitation does not apply.
Vent Pipe Grades and Connections:
Vents
Vents Required:
When connected to a common building sewer, the drainage piping of two
(2) or more buildings located on the same lot and under one (1)
ownership may be vented by means of piping sized in accordance with
Table 8-5, provided the aggregate cross-sectional area of all vents is not
less than that of the largest required common building sewer.
Exception:
Combination Oil and Sand Interceptor:

The size of vent piping shall be determined from its length and the total
number of fixture units connected thereto, as set forth in Table 8-5. The
diameter of an individual vent shall not be less than 32 mm nor less than
fifty percent (50%) the diameter of the drain to which it is connected. In
addition, the drainage piping of each building and each connection to a
Public sewer or a Private sewage disposal system shall be vented by
means of one or more vent pipes, the aggregate cross-sectional area of
which shall not be less than that of the largest required building sewer, as
determined from Table 8–5.


All vent and branch vent pipes shall be free from drops or sags and each
such vent shall be level or shall be so graded and connected as to drip back
by gravity to the drainage pipe it serves.
Where vents connect to a horizontal drainage pipe, each vent pipe shall
have its invert taken off above the drainage center line of such pipe
downstream of the trap being served.
Unless prohibited by structural conditions, each vent shall rise vertically
to a point not less than 150 mm above the flood level rim of the fixture
served before offsetting horizontally, and whenever two or more vent
pipes converge, each such vent pipe shall rise to a point at least 150 mm
in height above the flood level rim of the plumbing fixture it serves before
being connected to any other vent. Vents less than 150 mm above the
flood level rim of the fixture shall be installed with approved drainage
fittings, material and grade to the drain.
All vent pipes shall extend undiminished in size above the roof, or shall be
reconnected with a soil or waste vent of proper size.
The vent pipe opening from a soil or waste pipe, except for water closets
and similar fixtures, shall not be below the weir of the trap.
8-46
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures

Two (2) fixtures may be served by a common vertical pipe when each such
fixture wastes separately into an approved double fitting having inlet
openings at the same level.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Frost or Snow Closure:

Vent Termination:





Each vent pipe or stack shall extend through its flashing and shall
terminate vertically not less than 150 mm above the roof nor less than 300
mm from any vertical surface.
Each vent shall terminate not less than 3.048 m from, or at least 914 mm
above any openable window, door, opening, air intake, or vent shaft, nor
less than 914 mm in every direction from any lot line; alley and street
excepted.
Vent pipes shall be extended separately or combined, of full required size,
not less than 150 mm above the roof or fire wall. Flag poling of vents shall
be prohibited except where the roof is used for purposes other than
weather protection. All vents within 3.048 m of any part of the roof that is
used for such other purposes shall extend not less than 2.134 m above such
roof and shall be securely stayed.
Vent pipes for outdoor installations shall extend at least 3.048 m above
the surrounding ground and shall be securely supported.
Joints at the roof around vent pipes shall be made water tight by the use of
approved flashings or flashing material.
Lead:

Vent Stacks and Relief Vents:



For safe pans:
Not less 19.5 kg / m2 or 1.6 mm thick.
For flashings or vent terminals:



Not less than 14.7 kg / m2 or 1.2 mm thick.
Lead bends and lead traps shall not be less than 3.2 mm wall
thickness.

8-47
Each drainage stack which extends ten (10) or more stories above the
building drain or other horizontal drain, shall be served by a parallel vent
stack which shall extend undiminished in size from its upper terminal and
connect to the drainage stack at or immediately below the lowest fixture
drain. Each such vent stack shall also be connected to the drainage stack at
each fifth floor, counting down from the uppermost fixture drain by means
of a yoke vent, the size of which shall be not less in diameter than either
the drainage or the vent stack, whichever is smaller.
The yoke vent intersection with the vent stack shall be placed not less than
1.067m above the floor level, and the yoke vent intersection with the
drainage stack shall be by means of a wye branch fitting placed below the
fixture branch serving that floor.
Vertical Wet Venting:
See Table14-1 US UPC2000 Edition. Sheet lead shall be not less than the
following:

Where frost or snow closure is likely to occur in locations having minimum
design temperature below (-17.8°C), vent terminals shall be a minimum of
50 mm in diameter but in no event smaller than the required vent pipe.
The change in diameter shall be made inside the building at least 300 mm
below the roof in an insulated space and terminate not less than 254 mm
above the roof, or as required by the Sanitary Engineer.
Wet venting is limited to vertical drainage piping receiving the discharge
from the trap arm of one (1) and two (2) fixture unit fixtures that also
serves as a vent for not to exceed four (4) fixtures. All wet vented fixtures
shall be within the same story; provided, further, that fixtures with a
continuous vent discharging into a wet vent shall be within the same story
as the wet vented fixtures. No wet vent shall exceed 1.829 m in developed
length.
The vertical piping between any two (2) consecutive inlet levels shall be
considered a wet vented section. Each wet vented section shall be a
minimum of one (1) pipe size larger than the required minimum waste
pipe size of the upper fixture or shall be one (1) pipe size larger than the
required minimum pipe size for the sum of the fixture units served by
such wet vented section, whichever is larger, but in no case less than 50
mm.
Common vent sizing shall be the sum of the fixture units served but in no
case smaller than the minimum vent pipe size required for any fixture
served, or by Section 8.3.7 “Size of Vents”.
8-48
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Special Venting for Island Fixtures:


Exception:
Traps for island sinks and similar equipment shall be roughed in above the
floor and may be vented by extending the vent as high as possible, but not
less than the drainboard height and then returning it downward and
connecting it to the horizontal sink drain immediately downstream from
the vertical fixture drain. The return vent shall be connected to the
horizontal drain through a wye-branch fitting and shall, in addition, be
provided with a foot vent taken off the vertical fixture vent by means of a
wye-branch immediately below the floor and extending to the nearest
partition and then through the roof to the open air or may be connected to
other vents at a point not less than 150 mm above the flood level rim of the
fixtures served.
Drainage fittings shall be used on all parts of the vent below the floor level
and a minimum slope of 20.9 mm/m back to the drain shall be maintained.
The return bend used under the drainboard shall be a one (1) piece fitting
or an assembly of a forty-five (45) degree (0.79 rad), a ninety (90) degree
(1.6 rad) and a forty-five (45) degree (0.79 rad) elbow in the order named.
Pipe sizing shall be as elsewhere required in these Design Guidelines. The
island sink drain, upstream of the returned vent, shall serve no other
fixtures. An accessible cleanout shall be installed in the vertical portion of
the foot vent.



8.3.8




8-49
Combination waste and vent systems shall be permitted only where
structural conditions preclude the installation of conventional systems as
otherwise prescribed by this Design Guidelines.
Plans and specifications for each combination waste and vent system shall
first be approved by the Sanitary Engineer before any portion of any such
system is installed.
Each combination waste and vent system, shall be provided with a vent or
vents adequate to assure free circulation of air. Any branch more than
4.572m) in length shall be separately vented in an approved manner. The
minimum area of any vent installed in a combination waste and vent
system shall be at least fifty percent 50% the inside cross-sectional area of
the drain pipe served. The vent connection shall be downstream of the
uppermost fixture.
Each waste pipe and each trap in any such system shall be at least two (2)
pipe sizes larger than the sizes required by Section 8.3.4 of this Design
Guidelines, and at least two (2) pipe sizes larger than any fixture tailpiece
or connection.
Unless specifically required or permitted by the Sanitary Engineer, no
vertical waste pipe shall be used in any such system, except the tailpiece or
connection between the outlet of a plumbing fixture and the trap
therefore. Such tailpieces or connections shall be as short as possible, and
in no case shall exceed 600 mm.
Cleanouts may not be required on any wet vented branch serving a single
trap when the fixture tailpiece or connection is not less than 50 mm in
diameter and provides ready access for cleaning through the trap. An
accessible cleanout shall be installed in each vent for the combination
waste and vent system.
No water closet or urinal shall be installed on any such system. Other one
(1), two (2), or three (3) unit fixtures remotely located from the sanitary
system and adjacent to a combination waste and vent system may be
connected to such system in the conventional manner by means of waste
and vent pipes of regular sizes, providing that the two (2) pipe size is
based on the total fixture unit load connected to the system.
Subsoil Drains

Combination Waste and Vent Systems:

Branch lines may have forty-five (45) degree (0.79 rad) vertical offsets



Subsoil drains shall be provided around the perimeter of buildings having
basements, cellars, or crawl spaces or floors below grade. Such subsoil
drains may be positioned inside or outside of the footing, shall be of
perforated, or open-jointed approved drain tile or pipe not less than 80
mm in diameter, and shall be laid in gravel, slag, crushed rock, approved
19.1 mm crushed recycled glass aggregate, or other approved porous
material with a minimum of 100 mm surrounding the pipe on all sides.
Filter media shall be provided for exterior subsoil piping.
Subsoil drains shall be piped to a storm drain, to an approved water course,
to the front street curb or gutter, or to an alley; or the discharge from the
subsoil drains shall be conveyed to the alley by a concrete gutter. Where a
continuously flowing spring or groundwater is encountered, subsoil drains
shall be piped to a storm drain or an approved water course.
Where it is not possible to convey the drainage by gravity, subsoil drains
shall discharge to an accessible sump provided with an approved
automatic electric pump. The sump shall be at least 375 mm in diameter,
457 mm in depth, and provided with a fitted cover. The sump pump shall
have an adequate capacity to discharge all water coming into the sump as
it accumulates to the required discharge point, and the capacity of the
pump shall not be less than 1.0 L/s. The discharge piping from the sump
pump shall be a minimum of 40 mm in diameter and have a union or other
approved quick disconnect assembly to make the pump accessible for
servicing.
For separate dwellings not serving continuously flowing springs or
groundwater, the sump discharge pipe may discharge onto a concrete
splash block with a minimum length of 600 mm. This pipe shall be within
100 mm of the splash block and positioned to direct the flow parallel to the
recessed line of the splash block.
8-50
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Urinals:
Urinals shall have an average water consumption of not more than 1.0 gallon
(3.8 liters) of water per flush.
Exception:
If approved by the Sanitary Engineer, blowout urinals may be installed for
Public use in stadiums, race courses, fairgrounds, and other structures used
for outdoor assembly and for similar uses.
Non-Metered Faucets:
Lavatory faucets shall be designed and manufactured so that they will not
exceed a water flow rate of 8.4 liters per minute.
Metered Faucets:
Self-closing or self-closing metering faucets shall be installed on lavatories
intended to serve the transient Public, such as those in, but not limited to,
service stations, train stations, airports, restaurants and convention halls.
Metered faucets shall deliver not more than 1.0 liter of water per use.
Kitchen Faucets:
Faucets for kitchen sinks shall be designed and manufactured so that they will
not exceed a water flow rate of 8.4 liters per minute.
Shower Heads:
Shower heads shall be designed and manufactured so that they will not exceed
a water supply flow rate of 9.5 liters per minute.
Exception:
Emergency safety showers.
Installation:
Water-conserving fixtures shall be installed in strict accordance with the
manufacturers’ instructions to maintain their rated performance.
Materials – Alternates:
Special use fixtures may be made of soapstone, chemical stoneware, or may be
lined with lead, copper base alloy, nickel-copper alloy, corrosion-resisting
steel, or other materials especially suited for the use for which the fixture is
intended.
Zinc Alloy Components:
Zinc alloy components shall meet the applicable nationally recognized
standards and shall be used in accordance with their listing.
Overflows:
When any fixture is provided with an overflow, the waste shall be so arranged
that the standing water in the fixture cannot rise in the overflow when the
stopper is closed or remain in the overflow when the fixture is empty. The
8-52
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
overflow pipe from a fixture shall be connected on the house or inlet side of the
fixture trap, except that overflow on flush tanks may discharge into the water
closets or urinals served by them, but it shall be unlawful to connect such
overflows with any other part of the drainage system.
Strainers and Connections:
Strainers. All plumbing fixtures, other than water closets and urinals, shall be
equipped with approved strainers having an approved waterway area.
Strainers serving shower drains shall have a waterway equivalent to the area
of the tailpiece.
Connections:
Fixtures having concealed slip joint connections shall be provided with an
access panel or utility space at least 305 mm in its least dimension and so
arranged without obstructions as to make such connections accessible for
inspection and repair.
Continuous wastes and fixture tailpieces shall be constructed from the
materials specified in Section 8.3.13 ”Materials For Drainage” for drainage
piping, provided, however, that such connections where exposed or
accessible may be of seamless drawn brass not less than No. 20 B&S Gauge
0.8 mm. Each such tailpiece, continuous waste, or waste and overflow shall
not be less than 40 mm O.D. for sinks, dishwashers, laundry tubs, bathtubs,
urinals and similar fixtures, and not less than 32 mm) for lavatories, drinking
fountains, and similar small fixtures.
Approved wye or other directional type branch fittings shall be installed in all
continuous wastes connecting or receiving the discharge from food waste
disposal units, dishwashers, clothes washers, or other force discharge fixtures
or appliances. No dishwasher drain shall be connected to a sink tailpiece,
continuous waste or trap on the discharge side of a food waste disposal unit.
Prohibited Fixtures:
Water closets having an invisible seal or an unventilated space or having walls
which are not thoroughly washed at each discharge shall be prohibited. Any
water closet which might permit siphonage of the contents of the bowl back
into the tank shall be prohibited. Drinking fountains shall not be installed in
Public toilet rooms.
Prohibited Urinals:
Floor-type and wall -hung-type trough urinals shall be prohibited. Urinals
which have an invisible seal or which have an unventilated space or wall
which is not thoroughly washed at each discharge shall be prohibited.
Fixed wooden, concrete, cement, or tile wash trays or sinks for domestic use
shall not be installed in any building designed or used for human habitation.
No sheet metal lined wooden bathtub shall be installed or reconnected. No dry
or chemical closet (toilet) shall be installed in any building used for human
habitation, unless first approved by the Sanitary Engineer.
8-53
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
corrosion-resistant screws or bolts. The closet flange shall be secured to a
firm base.
Where floor-mounted, back-outlet water closets are used, the soil pipe shall
not be less than 80 mm in diameter. Offset, eccentric, or reducing floor flanges
shall not be used.
Setting:
Fixtures shall be set level and in proper alignment with reference to adjacent
walls. No water closet or bidet shall be set closer than 381 mm from its center
to any side wall or obstruction nor closer than 762 mm center to center to any
similar fixture. The clear space in front of any water closet or bidet shall not be
less than 600 mm. No urinal shall be set closer than 305 mm from its center to
any side wall or partition nor closer than.
Installations for Persons with Disabilities (PWDs):
Where facilities for the PWDs are required in applicable building regulations,
the facilities shall be installed in accordance with those regulations.
Supply Fittings:
The supply lines or fittings for every plumbing fixture shall be so installed as
to prevent backflow as required in Section 8.3.17.
Water Closets:
Water closet bowls for Public use shall be of the elongated type. In nurseries,
schools, and other similar places where plumbing fixtures are provided for the
use of children under six (6) years of age, water closets shall be of a size and
height suitable for children’s use. All water closets shall be equipped with
seats as required below.
Water Closet Seats:




Water closet seats shall be of smooth non-absorbent material.
All water closet seats, except those within dwelling units, shall be of the
open front type.
Water closet seats shall be properly sized for the water closet bowl type.
Seats for use in Public buildings shall conform to the standard listed in
Table 14-1 of Standards for Materials, Equipment, Joints and Connections
US UPC 2000 Edition.
Urinals:
8.3.10
Every water supply to a urinal shall be protected by an approved type vacuum
breaker or other approved backflow prevention device as described in Section
8.3.17.3.
Flushing Devices for Water Closet and Urinals
Flushing Devices Required: Each water closet, urinal, clinic sink, or other
plumbing fixture which depends on trap siphonage to discharge its waste
8-55
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
contents shall be provided with a flushometer valve, flushometer tank or flush
tank designed and installed so as to supply water in sufficient quantity and
rate of flow to flush the contents of the fixture to which it is connected, to
cleanse the fixture, and to refill the fixture trap, without excessive water use.
Flushing devices shall meet anti-siphon requirements required in Section
8.3.17.
Automatic Flushing Tanks: Tanks flushing more than one (1) urinal shall be
automatic in operation and of sufficient capacity to provide the necessary
volume to flush and properly cleanse all urinals simultaneously. Automatically
controlled flushometer valves may be substituted for flush tanks.
Flushometer Valves: No manually controlled flushometer valve shall be used
to flush more than one (1) urinal and each such urinal flushometer valve shall
be an approved, self-closing type discharging a predetermined quantity of
water. Flushometers shall be installed so that they will be accessible for repair.
Flushometer valves shall not be used where the water pressure is insufficient
to properly operate them. When the valve is operated, it shall complete the
cycle of operation automatically, opening fully and closing positively under the
line water pressure. Each flushometer shall be provided with a means for
regulating the flow through it.
Water Supply for Flush Tanks: An adequate quantity of water shall be
provided to flush and clean the fixture served. The water supply for flushing
tanks and flushometer tanks equipped for manual flushing shall be controlled
by a float valve or other automatic device designed to refill the tank after each
discharge and to completely shut off the water flow to the tank when the tank
is filled to operational capacity. Provision shall be made to automatically supply
water to the fixture so as to refill the trap seal after each flushing. The water
supply to flush tanks equipped for automatic flushing shall be controlled by a
suitable timing device.
Flush Valves in Flush Tanks: Flush valve seats in tanks for flushing water
closets shall be at least 25 mm above the flood level rim of the bowl connected
thereto, except in approved water closet and flush tank combinations designed
so that when the tank is flushed and the fixture is clogged or partially clogged,
the flush valve closes tightly so that water does not spill continuously over the
rim of the bowl or backflow from the bowl to the tank.
Overflows in Flush Tanks: Flush tanks shall be provided with overflows
discharging into the water closet or urinal connected thereto and shall be of
sufficient size to prevent tank flooding at the maximum rate at which the tank
is supplied with water under normal operating conditions.
Floor Drains and Shower Stalls: Floor drains shall be considered plumbing
fixtures and each such drain shall be provided with an approved type strainer
having a waterway equivalent to the area of the tailpiece. Floor drains, floor
receptors, and shower drains shall be of an approved type, suitably flanged to
provide a water tight joint in the floor.
8-56
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Location of Floor Drains: Floor drains shall be installed in the following
areas:
8.3.11
Toilet rooms containing two (2) or more water closets or a combination of one
(1) water closet and one (1) urinal, except in a dwelling unit. The floor shall
slope toward the floor drains.
Commercial kitchens
Laundry rooms in commercial buildings and common laundry facilities in
multi-family dwelling buildings.
Food Storage Areas: If drains are provided in storerooms, walk-in freezers,
walk-in coolers, refrigerated equipment, or other locations where food is
stored, such drains shall have indirect waste piping. Separate waste pipes shall
be run from each food storage area, each with an indirect connection to the
building sanitary drainage system. Traps shall be provided if required under
Section 8.3.5.5 and shall be vented.
Indirect drains may be located in freezers or other spaces where freezing
temperatures are maintained, provided that traps, when provided, are located
where the seal will not freeze. Otherwise, the floor of the freezer shall be
sloped to a floor drain located outside of the storage compartment.
Floor Slope: Floors shall be sloped to floor drains where drainage occurs on a
regular or frequent basis, or as otherwise required by the Sanitary Engineer.
Shower receptors are plumbing fixtures and shall conform to the general
requirements therefore contained in Section 8.3.8.1. Each such shower
receptor shall be constructed of vitrified china or earthenware, ceramic tile,
porcelain enameled metal or of such other material as may be acceptable to
the Sanitary Engineer. No shower receptor shall be installed unless it
conforms to acceptable standards as referenced in Table 14-1 of US UPC 2000
Edition or until a specification or a prototype or both of such receptor has first
been submitted to and approval obtained from the Sanitary Engineer.
Each shower receptor shall be an approved type and be so constructed as to
have a finished dam, curb, or threshold which is at least 25 mm lower than the
sides and back of such receptor. In no case shall any dam or threshold be less
than 50 mm or more than 229 mm in depth when measured from the top of
the dam or threshold to the top of the drain. Each such receptor shall be
provided with an integral nailing flange to be located where the receptor
meets the vertical surface of the finished interior of the shower compartment.
The flange shall be water tight and extend vertically a minimum of 25 mm
above the top of the sides of the receptor. The finished floor of the receptor
shall slope uniformly from the sides toward the drain not less than 20.9
mm/m, nor more than 41.8 mm/m. Thresholds shall be of sufficient width to
accommodate a minimum 559 mm door. Shower doors shall open so as to
maintain a minimum 559 mm unobstructed opening for egress.
8-57
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Exception: Showers which are designed to comply with the accessibility
standards listed in Table 14-1 of Standards for Materials, Equipment, Joints
and Connections US UPC 2000 Edition.
All shower compartments, regardless of shape, shall have a minimum finished
interior of 0.66 m2 and shall also be capable of encompassing a 750 mm circle.
The minimum required area and dimensions shall be measured at a height
equal to the top of the threshold and at a point tangent to its centerline. The
minimum area and dimensions shall be maintained to a point 1.778 m above
the shower drain outlet with no protrusions other than the fixture valve or
valves, shower head, soap dishes, shelves and safety grab bars or rails. Folddown seats in accessible shower stalls shall be permitted to protrude into the
750 mm circle.
Exception: Showers which are designed to comply with the accessibility
standards listed in Table 14-1 of Standards for Materials, Equipment, Joints
and Connections US UPC 2000 Edition.
When the construction of on-site built-up shower receptors is permitted by
the Sanitary Engineer, one of the following means shall be employed:
Shower receptors built directly on the ground: Shower receptors built
directly on the ground shall be water tight and shall be constructed from
approved type dense, non-absorbent and noncorrosive materials. Each such
receptor shall be adequately reinforced, shall be provided with an approved
flanged floor drain designed to make a water tight joint in the floor, and shall
have smooth, impervious, and durable surfaces.
Shower receptors built above ground: When shower receptors are built above
ground the sub-floor and rough side of walls to a height of not less than 76 mm)
above the top of the finished dam or threshold shall be first lined with sheet
plastic*, lead* or copper* or shall be lined with other durable and water tight
materials.
All lining materials shall be pitched 20.9 mm/m to weep holes in the subdrain
of a smooth and solidly formed sub-base. All such lining materials shall extend
upward on the rough jambs of the shower opening to a point no less than 76
mm above the top of the finished dam or threshold and shall extend outward
over the top of the rough threshold and be turned over and fastened on the
outside face of both the rough threshold and the jambs.
Non-metallic shower sub-pans or linings may be built-up on the job site of not
less than three (3) layers of standard 6.8 kg asphalt impregnated roofing felt.
The bottom layer shall be fitted to the formed sub-base and each succeeding
layer thoroughly hot mopped to that below. All corners shall be carefully fitted
and shall be made strong and water tight by folding or lapping, and each corner
shall be reinforced with suitable webbing hot-mopped in place. All folds, laps,
and reinforcing webbing shall extend at least 100 mm in all directions from the
corner and all webbing shall be of approved type and mesh, producing a tensile
strength of not less than 344.5 kPa in either direction. Non-metallic shower
sub-pans or linings may also consist of multi-layers of other approved
8-58
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
equivalent materials suitably reinforced and carefully fitted in place on the job
site as elsewhere required in this section.
Linings shall be properly recessed and fastened to approved backing so as not
to occupy the space required for the wall covering and shall not be nailed or
perforated at any point which may be less than 25 mm above the finished dam
or threshold. An approved type sub-drain shall be installed with every shower
sub-pan or lining. Each such sub-drain shall be of the type that sets flush with
the sub-base and shall be equipped with a clamping ring or other device to
make a tight connection between the lining and the drain. The sub-drain shall
have weep holes into the waste line. The weep holes located in the subdrain
clamping ring shall be protected from clogging.
*Lead and copper sub-pans or linings shall be insulated from all conducting
substances other than their connecting drain by 6.8 kg asphalt felt or its
equivalent and no lead pan or liner shall be constructed of material weighing
less than 19.5 kg/m2. Copper pans or liners shall be at least No. 24 B & S Gauge
0.5 mm. Joints in lead pans or liners shall be burned. Joints in copper pans or
liners shall be soldered or brazed. Plastic pans shall not be coated with asphalt
based materials.
All shower lining materials shall conform to approved standards acceptable to
the Sanitary Engineer.
Tests for Shower Receptors: Shower receptors shall be tested for water
tightness by filling with water to the level of the rough threshold. The test plug
shall be so placed that both upper and under sides of the sub-pan shall be
subjected to the test at the point where it is clamped to the drain.
Floors of Public shower rooms shall have a non-skid surface and shall be
drained in such a manner that waste water from one bather will not pass over
areas occupied by other bathers. Gutters in Public or gang shower rooms shall
have rounded corners for easy cleaning and shall be sloped not less than 2%
toward drains. Drains in gutters shall be spaced not more than 2438 mm from
side walls nor more than 4.897 mm apart.
Location of Valves and Heads: Control valves and shower heads shall be
located on the sidewall of shower compartments or be otherwise arranged so
that the showerhead does not discharge directly at the entrance to the
compartment and the bather can adjust the valves prior to stepping into the
shower spray.
8.3.12
Water Supply Riser. Every water supply riser from the shower valve to the
shower head outlet, whether exposed or not, shall be securely attached to the
structure.
Minimum Number of Required Fixtures
Fixture Count. Plumbing fixtures shall be provided for the type of building
occupancy and in the minimum number shown in Table 8-2.
8-59
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Access to Fixtures: In multi-story buildings, accessibility to the required
fixtures shall not exceed one (1) vertical story.
Fixtures accessible only to Private offices shall not be counted to determine
compliance with this section.
Separate Facilities: Separate toilet facilities shall be provided for each sex.
Exceptions: Residential installations.
In occupancies serving ten (10) or fewer people, one (1) toilet facility,
designed for use by no more than one (1) person at a time, shall be permitted
for use by both sexes.
In business and mercantile occupancies with a total floor area of 139.5 m2 or
less, one (1) toilet facility, designed for use by no more than one (1) person at a
time, shall satisfy the requirements for serving customers and employees of
both sexes.
Fixture Requirements for Special Occupancies: Additional fixtures may be
required when unusual environmental conditions or special activities are
encountered.
In food preparation areas, fixture requirements may be dictated by health
Codes.
Types of occupancy not shown in Table 8-2 shall be considered individually by
the Sanitary Engineer
Facilities in Mercantile and Business Occupancies Serving Customers
Requirements for customers and employees shall be permitted to be met with
a single set of restrooms accessible to both groups. The required number of
fixtures shall be the greater of the required number for employees or the
required number for customers.
Fixtures for customer use shall be permitted to be met by providing a centrally
located facility accessible to several stores. The maximum distance from entry
to any store to this facility shall not exceed 152.4 m.
In stores with a floor area a 13.9 m2 or less, the requirement to provide
facilities for employees shall be permitted to be met by providing a centrally
located facility accessible to several stores. The maximum distance from entry
to any store to this facility shall not 91.4 m.
Food Service Establishments: Food service establishments with an occupant
load of one hundred (100) or more shall be provided with separate facilities
for employees and customers. Customer and employee facilities may be
combined for occupant loads less than one hundred (100).
Toilet Facilities for Workers: Suitable toilet facilities shall be provided and
maintained in a sanitary condition for the use of workers during construction.
8-60
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
8.3.13
Fixtures and Fixtures Fittings for Persons with Disabilities
Plumbing fixtures and fixture fittings for persons with disabilities shall
conform to the appropriate standards referenced in Table 14-1 of US UPC
2000 Edition.
Whirlpool Bathtubs: Unless otherwise listed, all whirlpool bathtubs shall
comply with the following requirements:
A removable panel of sufficient dimension shall be provided to access the
pump.
The circulation pump shall be located above the crown weir of the trap.
The pump and the circulation piping shall be self-draining to minimize water
retention in accordance with standards referenced in Table14-1 of US UPC
2000 Edition.
Suction fittings on whirlpool bathtubs shall comply with the listed standards.
Installation of Fixtures Fittings: Faucets and diverters shall be installed and
adjusted so that the flow of hot water from the fittings corresponds to the left
hand side of the fitting during fixture operation.
Exception: In single handle mixing valves, the flow of hot water shall
correspond to the markings on the fitting.
Bidets: Materials. Bidets shall conform to the standards listed in Table14-1 of
US UPC 2000 Edition.
Backflow Protection. The water supply to the bidet shall be protected
according to Section 8.3.17, which allows for an airgap or vacuum breaker.
Future Fixtures: When provision is made for the future installation of
fixtures, those provided for shall be considered in determining the required
sizes of drain pipes. Construction for future installations shall be terminated
with a plugged fitting or fittings. Where the plugged fitting is at the point
where the trap of a fixture may be installed, the plumbing system for such
fixture shall be complete and conform with all plumbing requirements of these
Design Guidelines.
Shower and Tub/Shower Combination Control Valves: Showers and tubshower combinations in all buildings shall be provided with individual control
valves of the pressure balance or the thermostatic mixing valve type. Gang
showers, when supplied with a single temperature controlled water supply
pipe, may be controlled by a master thermostatic mixing valve in lieu of
individually controlled pressure balance or thermostatic mixing valves.
Handle position stops shall be provided on such valves and shall be adjusted
per the manufacturer’s instructions to deliver a maximum mixed water setting
of 49°C. The water heater thermostat shall not be considered a suitable
control for meeting this provision.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Underground Main Sewer and Waste Lines, Main Sewer and Waste Lines shall be
Bell and spigot cast iron pipe (CIP) and fittings conforming to ASTM A74. Or PVC
series 1000 and fittings Or HDPE and fittings, Schedule 40 ABS DWV, Schedule
40 PVC DWV, extra strength vitrified clay pipe, or other approved materials
having a smooth and uniform bore conforming to ATSM referred to in Table 141 UPC 2000 Edition, except that:
No galvanized wrought iron or galvanized steel pipe shall be used
underground and shall be kept at least 150 mm all be installed except for
individual single family dwelling units, materials exposed within ducts or
plenums shall have a flame-spread index of not more than 25 and a smokedeveloped index of not more than 50, when tested in accordance with the Test
for Surface-Burning Characteristics of the Building Materials
No vitrified clay pipe or fittings shall be used above ground or where
pressurized by a pump or ejector. They shall be kept at least 300 mm below
ground.
Copper tube for drainage and vent piping shall have a weight of not less than
that of copper drainage tube type DWV.
Drainage fittings shall be of cast iron, malleable iron, lead, brass, copper,
ABS, PVC, vitrified clay, or other approved materials having a smooth
interior waterway of the same diameter as the piping served and all such
fittings shall be compatible with the type of pipe used. Pump Discharge Pipe
shall be black iron pipe (BIP) and fittings conforming to ASTM A53.
Fittings on screwed pipe shall be of the recessed drainage type. Burred ends
shall be reamed to the full bore of the pipe.
The threads of drainage fittings shall be tapped so as to allow 20.9 mm/m
grade.
Fittings used for drainage shall be of the drainage type, have a smooth interior
waterway, and be constructed so as to allow 20.9 mm/m per foot grade.
Lead: See Table 14-1 of US UPC 2000 Edition Sheet lead shall be not less than
the following:
For safe pans: not less than 19.5 kg / m2
For flashings or vent terminals: not less than 15 kg / m2 or 1.2 mm thick.
Lead bends and lead traps shall not be less than 3.2 mm wall thickness.
Ferrules and Bushings: Caulking ferrules shall be manufactured from
bronze or copper and shall be in accordance with Table 8-13.
Soldering bushings shall be of bronze or copper in accordance with Table 8-14.
Materials for Sanitary Drainage: Sewer lines shall be designed with a
minimum slope of one percent (1%), For high-rise buildings; Soil stack shall be
cast iron pipe (CIP) and fittings conforming to ASTM A74. Or HDPE and fittings,
8-61
8-62
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 8-16
Hangers and Support
Material
Cast
Type of Joints
Lead Oakum
Compression
Gasket
Horizontal
Vertical
(1,524 mm), (3,048
mm) where foot lengths
3,048 mm are
installed1,2,3
Every other joint, unless
over 1,219 mm, then
support each joint1,2,3
Base and each floor not
to exceed 4,572 mm
Base and each floor
maximum of 4,572 mm
Cast –Iron Hubless
Shielding
Coupling
Every other joint, unless
over 1,219 mm, then
support each joint1,2,3,4
Base and each floor
maximum of 4,572 mm
Copper Tube and Pipe
Soldered or
Brazed
40mm and smaller,
1,829 mm, 50 mm and
larger,3,048 mm
Each floor, a maximum
of 3,048 mm,5
Steel and brass Pipe
for Water or DWV
Threaded of
Welded
and smaller, (3,048
mm), 25 mm and larger,
(3,658 mm)
Every other Floor, a
maximum of 7,620 mm5
Steel, Brass and
Tinned Copper Pipe for
Gas
Threaded of
Welded
15mm (1,829 mm), 20
mm and (2 5 mm),
(2,436 mm),
(32 mm) and larger,
(3,048 mm)
(12 mm) (1,829 mm)
(20mm) and 25 mm,
2,436 mm,
(32 mm) every floor
level
Schedule 40 PVC and
ABS DWV
Solvent Cemented
All sizes, (1,219 mm).
Allow for expansion
every (9,144 mm)3,6
Base and each floor
Provide mid-story
guides. Provide for
expansion every (9,144
mm)3
CPVC
Solvent Cemented
(25 mm) and smaller,
(914 mm),(32 mm) and
larger, (1,219 mm)
Base and each floor
Provide mid-story
guides6
PEX
Metal Inserts and
Metal
Compression
(813 mm)
Base and each floor
Provide mid-story
guides
PEX-ALPEX
Metal Inserts and
Metal
Compression
(12 mm),(20 mm) and
(25 mm) all (2,489 mm)
Base and each floor
Provide mid-story
guides
PE-AL-PE
Metal Inserts and
Metal
Compression
(15 mm) (20 mm) and
(25 mm) all sizes 98
(2,489 mm)
Base and each floor
Provide mid-story
guides
Polypropylene (PP)
Fusion Weld
(socket, but,
saddle,
electrofusion),
threaded (metal
threads only), or
mechanical
(25 mm) and smaller,
813 mm), (32 mm) and
larger, 4 feet (1,219
mm)
Base and each floor
Provide mid-story
guides
Source: US-UPC 2009 (Table 3-2)
Footnotes of Table 8-16:
1. Support adjacent to joint, a maximum of eighteen 457 mm
2. Brace at a maximum of 12,192 mm intervals to prevent horizontal movement
3. Support at each horizontal branch connection
4. Hangers shall not be placed on the coupling
5. Vertical water lines shall be permitted to be supported in accordance with recognized
engineering principles with regard to expansion and contraction, approved by authority having
jurisdiction
6. See the appropriate IAPMO Installation Standard for expansion and other special requirements
8-65
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
required by this section. Drain pipe shall be placed on filter material in an
approved manner. The drain lines shall then be covered with filter material to
the minimum depth required by this section and this covered with untreated
building paper, straw, or similar porous material to prevent closure of voids
with earth backfill. No earth backfill shall be placed over the filter material
cover until after inspection and acceptance.
Exception: Listed or approved plastic leaching chambers may be used in lieu
of pipe and filter material. Chamber installations shall follow the rules for
disposal fields, where applicable, and shall conform to manufacturer’s
installation instructions.
A grade board staked in the trench to the depth of filter material shall be
utilized when distribution line is constructed with drain tile or a flexible pipe
material which will not maintain alignment without continuous support.
When seepage pits are used in combination with disposal fields, the filter
material in the trenches shall terminate at least 1.524 m from the pit
excavation and the line extending from such points to the seepage pit shall be
approved pipe with water tight joints.
Where two (2) or more drain lines are installed, an approved distribution box
of sufficient size to receive lateral lines shall be installed at the head of each
disposal field. The inverts of all outlets shall be level and the invert of the inlet
shall be at least 25.4 mm above the outlets. Distribution boxes shall be
designed to insure equal flow and shall be installed on a level concrete slab in
natural or compacted soil. Distribution boxes shall be coated on the inside
with a bituminous coating or other approved method acceptable to the
Sanitary Engineer.
All laterals from a distribution box to the disposal field shall be approved pipe
with water tight joints. Multiple disposal field laterals, wherever practicable,
shall be of uniform length.
Connections between a septic tank and a distribution box shall be laid with
approved pipe with water tight joints on natural ground or compacted fill.
When the quantity of sewage exceeds the amount that can be disposed in
152.4 m of leach line, a dosing tank shall be used. Dosing tanks shall be
equipped with an automatic siphon or pump which discharges the tank once
every three (3) or four (4) hours. The tank shall have a capacity equal to 60 to
75% of the interior capacity of the pipe to be dosed at one time. Where the
total length of pipe exceeds 304.8 m, the dosing tank shall be provided with
two (2) siphons or pumps dosing alternately and each serving one half (1/2)
of the leach field.
8-71
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 8-19
Structure
Location of Sewage Disposal System
0.610
Property line adjoining Private property
Water supply wells
Streams
Table 8-20
Minimum Horizontal Distance Clearance
Required
Building
Sewer
Buildings or structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Septic Tank
Disposal Field
Single Family
Dwellings –
Number of
Bedrooms
Seepage Pit or
Cesspool
*Capacity of Septic Tanks
Multiple Dwelling
Units or
Apartments – One
Bedroom Each
Other Uses:
Maximum Fixture
Units Served per
Table7-3
Minimum
Septic Tank
Capacity
Liters
1.524
2.438
2.438
1 or 2
15
2838
2
1.524
1.524
2.438
3
20
3785
15.24 3
15.24
30.5m
45.7
Clear
25
4542
3
33
5678
4
45
7570
5
55
8516
6
60
9463
7
70
10,409
8
80
11,355
15.24
Trees
-
3.048
Seepage pits or cesspools
-
1.524
1.524
3.658
Disposal field
-
1.524
1.219 4
1.524
On site domestic water service line
-
1.524
1.524
1.524
3.048
-
1.524
1.524
9
90
12,301
3.048
10
100
13,248
Pressure Public water main
3. 048
5
3.048
30.5
2 units
15.24
Distribution box
15.240 6
4
5 or 6
3.048
3.048
Source: Table K-1 UPC 2000 Edition
Source: Table K-2 UPC 2000 Edition
Footnotes of Table 8-19:
When disposal fields and / or seepage pits are installed in sloping ground, the minimum horizontal
distance between any part of the leaching system and ground surface shall be 4.572 m.
Footnotes of Table 8-20:
1. Extra bedroom, 568 liters each.
2.
Extra dwelling units over 10, add 946 liters each.
1. Including porches and steps, whether covered or uncovered, breezeways, roofed porte-
3.
Extra fixture units over 100, add 95 liters per fixture unit.
cocheres, roofed patios, carports, covered walks, covered driveways and similar structures or
appurtenances.
2. “No building sewer or other drainage piping or part thereof, constructed of materials other than
*Septic tank sizes in this table include sludge storage capacity and the connection of domestic food
waste disposal units without further volume increase.
those approved for use under or within a building, shall be installed under or within 0.610 m of
any building or structure, or less than 0.305 m below the surface of the ground.”
3. All drainage piping shall clear domestic water supply wells by at least 15.24 m. This distance
may be reduced to not less than 7.62 m when the drainage piping is constructed of materials
approved for use within a building.
4. Plus 0.61 m for each additional 0.305 m of depth in excess of 0.305 m below the bottom of the
drain line. (See also Section 8.3.15.7).
5. For parallel construction: For crossings, approval by the Health Department shall be required.
6. These minimum clear horizontal distances shall also apply between disposal field, seepage
pits, and the ocean mean higher high tide line.
8-77
8-78
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 8-21
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Estimated Waste / Sewage Flow Rates
Type of Occupancy
Recommended Design Criteria. Sewage disposal systems sized using the
estimated waste / sewage flow rates should be calculated as follows:
Liters Per Day
Airports
56.8 per employee

18.9 per passenger
Bowling alleys (snack bar only)

283.9 per land
Camps
Campground with central comfort station
132.5 per person
Campground with flush toilets, no showers
94.6 per person
Day camps (no meals served)
56.8 per person
Summer and seasonal
189.3 per person
Churches (Sanctuary)
18.9 per seat
with kitchen waste
26.5 per seat
Dance halls
18.9 per person

Waste/sewage flow, over 5677.5 L / day Flow x 0.75 + 1125 = septic tank
size
Secondary system shall be sized for total flow per 24 hours.
Table 8-22
Design Criteria of Five Typical Soils
Required leaching
area / L
(sq.m / L)
Maximum absorption
capacity in L / sq. m of
leaching area for
a 24 hrs period
Coarse sand or gravel
0.005
203.7
Type of Soil
Factories
Fine sand
0.006
162.9
No showers
94.6 per employee
Sandy loam or sandy clay
0.010
101.8
With showers
132.5 per employee
Clay with considerable sand or gravel
0.022
44.8
Cafeteria, add
18.9 per employee
Clay with small amount of sand or gravel
0.030
32.6
Hospitals
946.3 per bed
Kitchen waste only
94.6 per bed
Laundry waste only
151.4 per bed
Hotels (no kitchen waste)
Source: Table K-4 UPC 2000 Edition
Table 8-23
227.1 per bed (2 person)
Septic Tank Capacity Limits
Institutions (Resident)
283.9 per person
Required Square meter of
Septic Tank Capacity (m2 / L)
Nursing home
473.1 per person
0.005–0.006
28,387.5
Rest home
473.1 per person
0.010
18,925.0
Laundries, self-service ,in. 10 hrs / day
189.3 per wash cycle
0.022
13,247.5
Restaurants – cafeterias
75.7 per employee
0.030
11,355.0
Toilet
26.5 per customer
Source: Table K-5 UPC 2000 Edition
kitchen waste
3.8 per meal
add for cocktail lounge
7.6 per customer
7.6 per meal
Schools – Staff and office
75.7 per person
Elementary students
56.8 per person
Intermediate and high
75.7 per student
with gym and showers, add
18.9 per student
with cafeteria, add
11.4 per student
Boarding, total waste
378.5 per person
Service station, toilets
3785 for first bay
Stores
75.7 per employee
Public restrooms, add
1 per 4.1m2 of floor space
Swimming pools, Public
37.9 per person
Theaters, auditoriums
18.9 per seat
Drive-in
37.9 per space
Source: Table K-3 UPC 2000 Edition
Maximum Septic Tank
Size Allowable (Liters)
22.7 per meal
add for garbage disposal
kitchen waste – disposable service
8-79
Waste/sewage flow, up to 5677.5 L / day Flow x 1.5 = septic tank size
8.3.16
Storm Drainage System
Similar in physical design to Sewerage system but differs in discharge content
which is storm water, the system discharges areas but not limited to: service
areas exposed to atmosphere precipitations or other influenced areas wherein
storm water is the main matter to discharge, such All roofs, paved areas, yards,
courts, and courtyards, roof, decks, balconies, parking, site areas shall be
drained into a separate storm sewer system, or into a combined sewer system
where a separate storm sewer system is not available, or to some other place
of disposal satisfactory to the Sanitary Engineer. The system is connected by
gravity flow into the Public storm drainage, physically constrained gravity
discharges requires ejector pumps for proper discharging. In Parking areas Oil
Interceptors must be added into the system sub-collector lines at points
appropriate for maintenance. In the case of one- and two-family dwellings,
storm water may be discharged on flat areas such as streets or lawns so long
as the storm water shall flow away from the building and away from adjoining
property, and shall not create a nuisance.
8-80
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
diameter and have a union or other approved quick disconnect assembly to
make the pump accessible for servicing.
For separate dwellings not serving continuously flowing springs or
groundwater, the sump discharge pipe may discharge onto a concrete splash
block with a minimum length of 600 mm. This pipe shall be within 100 mm of
the splash block and positioned to direct the flow parallel to the recessed line
of the splash block.
Subsoil drains subject to backflow when discharging into a storm drain shall be
provided with a backwater valve in the drain line so located as to be accessible
for inspection and maintenance.
Nothing in Section 8.3.17.2 shall prevent drains that serve either subsoil
drains or areaways of a detached building from discharging to a properly
graded open area, provided that:



They do not serve continuously flowing springs or groundwater;
The point of discharge is at least 3.048 m from any property line; and
It is impracticable to discharge such drains to a storm drain, to an
approved water course, to the front street curb or gutter, or to an alley.
Drain Systems: Building Subdrains. Building subdrains located below the
Public sewer level shall discharge into a sump or receiving tank, the contents
of which shall be automatically lifted and discharged into the drainage system
as required for building sumps.
Areaway Drains: All open subsurface space adjacent to a building, serving as
an entrance to the basement or cellar of a building, shall be provided with a
drain or drains. Such areaway drains shall be 50 mm minimum diameter for
areaways not exceeding 9.3 m2 in area, and shall be discharged in the manner
provided for subsoil drains not serving continuously flowing springs or
ground water (see Section 8.3.16.1) Areaways in excess of 9.3 m2 shall not
drain into subsoil. Areaway drains for areaways exceeding 9.3 m2 shall be
sized according to Table 8-23.
Window Areaway Drains: Window areaways not exceeding 0.9 m2 in area
may discharge to the subsoil drains through a 50 mm pipe. However, window
areaways exceeding 0.9 m2 in area shall be handled in the manner provided
for entrance areaways.
Filling Stations and Motor Vehicle Washing Establishments: Public filling
stations and motor vehicle washing establishments shall have the paved area
sloped toward sumps or gratings within the property lines. Curbs not less than
152 mm high shall be placed where required to direct water to gratings or
sumps.
Paved Areas: Where the occupant creates surface water drainage, the sumps,
gratings or floor drains shall be piped to a storm drain or an approved water
course.
8-82
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Roof Drainage: Primary Roof Drainage. Roof areas of a building shall be
drained by roof drains or gutters. The location and sizing of drains and gutters
shall be coordinated with the structural design and pitch of the roof. Unless
otherwise required by the Sanitary Engineer/ Master Plumber, roof drains,
gutters, vertical conductors or leaders, and horizontal storm drains for
primary drainage shall be sized based on a storm of sixty (60) minutes
duration and 100 year return period.
Secondary Roof Drainage: Where parapet walls or other construction extend
above the roof and create areas where storm water would become trapped if
the primary roof drainage system failed to provide sufficient drainage, an
independent secondary roof drainage system consisting of scuppers,
standpipes, or roof drains shall be provided. Secondary roof drainage systems
shall be sized in accordance with Section 8.3.16.1 “Roof Drainage” of these
Design Guidelines. Overflow drains shall be the same size as the roof drains
with the inlet flow line 50 mm above the low point of the roof and shall be
installed independent from the roof drains.
Where secondary roof drainage is provided by means of roof drains or
standpipes, the secondary system shall be separate from the primary system
and shall discharge independently at grade or other approved point of
discharge.
Where secondary roof drainage is provided, the overflow level(s) into the
secondary system shall be determined by the structural design of the roof,
including roof deflection, at a level not less than 50 mm above the level of the
primary drain. An allowance shall be made to account for the required
overflow head of water above the secondary inlets. The elevation of the
secondary inlet plus the required overflow head shall not exceed the
maximum allowable water level on the roof.
Scuppers shall be sized as rectangular weirs, using hydraulic principles to
determine the required length and resulting overflow head. Secondary roof
drains and standpipes shall be sized according to Table 8-24. Where
standpipes are used, the head allowance required under Section 8.3.16.1
“Secondary Roof Drainage” shall be not less than 38 mm.
Equivalent Systems: When approved by the Sanitary Engineer, the
requirements of Section 8.3.16.1 “Roof Drainage” shall not preclude the
installation of an engineered roof drainage system that has sufficient
capacity to prevent water from ponding on the roof in excess of that
allowed in the roof structural design with a rainfall rate of at least twice
that for a 100-year, 60-minute storm and with a blockage in any single point
in the storm drainage system.
Cleanouts: For building storm drains shall comply with the requirements of
Section 8.3.3.5.
Rain leaders and conductors connected to a building storm sewer shall have a
cleanout installed at the base of the outside leader or outside conductor before
it connects to the horizontal drain.
8-83
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 8-24
Sizing Roof Drains, Leaders, and Vertical Rainwater Piping (METRIC)
Size of Drain,
Leader or
Pipe
Mm
Flow
L/s
50
Maximum Allowable Horizontal Projected Roof Areas
Square Meters at Various Rainfall Rates mm/hour
25
50
75
100
125
150
1.5
202
101
67
51
40
34
80
4.2
600
300
200
150
120
100
100
9.1
1286
643
429
321
257
214
125
16.5
2334
1117
778
583
467
389
150
26.8
3790
1895
1263
948
758
632
200
57.6
8175
4088
2725
2044
1635
1363
Source: Table 11-1 UPC 2000 Edition
Footnotes for Table 8-24:
1.
2.
3.
The sizing data for vertical conductors, leaders, and drains is based on the pipes flowing 7/24
full.
For rainfall rates other than those listed, determine the allowable roof area by dividing the area
given in the 25 mm / hour column by the desired rainfall rate.
Vertical piping may be round, square, or rectangular. Square pipe shall be sized to enclose its
equivalent round pipe. Rectangular pipe shall have at least the same cross-Sectional area as
its equivalent round pipe, except that the ratio of its side dimensions shall not exceed 3 to 1.
Table 8-25
Size of
Pipe mm
Sizing of Horizontal Rainwater Piping
Flow at 10
mm/m
Slope L/s
Maximum Allowable Horizontal Projected Roof Areas, Square
Meters at Various Rainfall Rates mm / hour
25
50
75
100
125
150
80
2.1
305
153
102
76
61
51
100
4.9
700
350
233
175
140
116
125
8.8
1241
621
414
310
248
207
150
14.0
1988
994
663
497
398
331
200
30.2
4273
2137
1424
1068
855
713
250
54.3
7692
3846
2564
1923
1540
1282
300
87.3
12,375
6187
4125
3094
2476
2062
375
156.0
22,110
11,055
7370
5528
4422
3683
8-86
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 8-26
Size of
Pipe,mm
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Sizing of Horizontal Rainwater Piping
Flow at 20
mm/m
Slope L/s
Table 8-28
Maximum Allowable Horizontal Projected Roof Areas Square
Meters at Various Rainfall Rates mm / hour
25
50
75
100
125
150
80
3.0
431
216
144
108
86
72
100
6.9
985
492
328
246
197
164
125
12.4
1754
877
585
438
351
292
150
19.8
2806
1403
935
701
561
468
200
42.7
6057
3029
2019
1514
1211
1009
250
76.6
10,851
5425
3618
2713
2169
1807
300
123.2
17,465
8733
5816
4366
3493
2912
375
220.2
31,214
15,607
10,405
6248
5202
Table 8-27
Size of
Pipe,mm
Sizing Of Horizontal Rainwater Piping
Flow at 40
mm/m
Slope,L/s
80
4.3
125
17.5
200
60.3
100
150
9.8
Maximum Allowable Horizontal Projected Roof Areas Square
Meters at Various Rainfall Rates mm / hour
Maximum Rainfall mm/hour
50:8
76:2
101:6
127:0
152:4
5:2 mm/m Slope
80
31.6
21.0
15.8
12.6
10.5
100
66.9
44.6
33.4
26.8
22.3
125
116.1
77.5
58.1
46.5
38.7
150
178.4
119.1
89.2
71.4
59.5
175
256.4
170.9
128.2
102.2
85.3
200
369.7
246.7
184.9
147.7
123.1
250
668.9
445.9
334.4
267.6
223.0
80
44.6
29.7
22.3
17.8
14.9
100
94.8
63.3
47.4
37.9
31.6
125
163.5
108.9
81.8
65.4
54.5
150
252.7
168.6
126.3
100.8
84.1
175
362.3
241.5
181.2
144.9
120.8
10:4 mm/m Slope
50
75
100
125
150
611
305
204
153
122
102
200
520.2
347.5
260.1
208.1
173.7
2482
1241
250
947.6
631.7
473.8
379
315.9
42.2
31.6
25.3
21.0
1400
3976
250
108.6
15,390
375
312.0
174.6
Diameter of Gutter mm
25
28.1
300
7804
Size of Gutters
700
465
350
1988
1325
994
827
494
413
20:9 mm/m Slope
1709
1423
80
63.2
100
133.8
89.2
66.9
53.5
44.6
4125
125
232.3
155.0
116.1
92.9
77.5
150
356.7
237.8
178.4
142.7
118.9
175
512.8
341.9
256.4
204.9
170.9
200
739.5
493.3
369.7
295.4
246.7
250
133.8
891.8
668.9
534.2
445.9
4273
2847
2137
24,749
12,374
8250
6187
44,220
Source: Table 11-2 UPC 2000 Edition
22,110
5128
14,753
232
621
8547
7695
280
797
3846
3080
11,055
8853
4942
663
2564
7367
Footnotes for Table 8-25 to 27:
The sizing data for horizontal piping is based on the pipes flowing full.
For rainfall rates other than those listed, determine the allowable roof area by dividing the area given
in the 25 mm / hour column by the desired rainfall rate.
41:7 mm/m Slope
80
89.2
59.5
44.6
35.7
29.7
100
189.5
126.3
94.8
75.8
63.2
125
328.9
219.2
164.4
131.5
109.6
150
514.7
343.3
257.3
206.2
171.9
175
724.6
483.1
362.3
289.9
241.4
200
1040.5
693.0
520.2
416.2
346.5
250
1858.0
1238.4
929.0
743.2
618.7
Source: Table 11-3 (METRIC) UPC 2000 Edition
Strainers for Flat Decks: Roof drain strainers for use on sun decks, parking
decks, and similar areas which are normally serviced and maintained may be
of the flat surface-type. Such roof drain strainers shall be level with the deck
and shall have an available inlet area of no less than two (2) times the area of
the conductor or leader to which the drain is connected.
Roof Drain Flashings: Connection between the roof and roof drains which
pass through the roof and into the interior of the building shall be made water
tight by the use of proper flashing material.
8-87
8-88
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Where lead flashing material is used, it shall be a minimum of 19.5 kg/m2.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table 8-29
Controlled Flow Maximum Roof Water Depth
Where copper flashing material is used, it shall be a minimum of 3.7 kg/m 2.
Size of Leaders, Conductors, and Storm Drains: Vertical Conductors and
Leaders. Vertical conductors and leaders shall be sized on the basis of the
maximum projected roof area and Table 8-22.
Size of Horizontal Storm Drains and Sewers: The size of building storm
drains or building storm sewers or any of their horizontal branches shall be
based upon the maximum projected roof or paved area to be handled and
Table 8-25 to Table 8-30.
Size of Roof Gutters: The size of semicircular gutters shall be based on the
maximum projected roof area and Table 8-25 to 8-26.
Side Walls Draining onto a Roof: Where vertical walls project above a roof so as
to permit storm water to drain to the roof area below the adjacent roof area may
be computed from Table 8-22.






For one (1) wall – add fifty (50%) percent of the wall area to the roof area
figures.
For two (2) adjacent walls – add thirty-five (35%) percent of the total wall
areas.
Two (2) walls opposite of same height – add no additional area.
Two (2) walls opposite of differing heights – add fifty (50%) percent of
wall area above top of lower wall.
Walls on three (3) sides – add fifty (50%) percent of area of the inner wall
below the top of the lowest wall, plus allowance for the area of wall above
top of lowest wall, per (2) and (4) above.
Walls on four (4) sides – no allowance for wall areas below top of lowest
wall – add for areas above the top of the lowest wall per (1), (2), (4) and
(5) above.
Values for Continuous Flow: Where there is a continuous or semicontinuous discharge into the building storm drain or building storm sewer, as
from a pump, ejector, air-conditioning plant, or similar device, 3.8 L / min. of
such discharge shall be computed as being equivalent to 2.2 m2 of roof area,
based upon a rate of rainfall of 100 mm per hour.
Controlled-Flow Roof Drainage: Application. In lieu of sizing the storm
drainage system in accordance with this section “Size of Leaders,
Conductors, and Storm Drains”, the roof drainage may be sized on the basis
of controlled flow and storage of the storm water on the roof, provided the
following conditions are met:
The water from a 25 year frequency storm shall not be stored on the roof for
more than twenty-four (24) hours.
During the storm, the water depth on the roof shall not exceed the depths
specified in Table 8-29.
8-89
*Roof Rise mm
Max Water Depth at Drain mm
(Flat)
75
50
100
100
125
150
150
Source: Table 11-4 UPC 2000 Edition
*Vertical measurement from the roof surface at the drain to the highest point of the
roof surface served by the drain, ignoring any local depression immediately adjacent
to the drain.
No less than two (2) drains shall be installed in roof areas of 929.0 m2 or less,
and no less than one (1) additional drain shall be installed for each 929.0 m 2 of
roof area over 929.0 m2.
Each roof drain shall have a pre-calibrated, fixed (non-adjustable), and
proportional weir (notched) in a standing water collar inside the strainer. No
mechanical devices or valves shall be allowed.
Pipe sizing shall be based on the pre-calibrated rate of flow L/s of the precalibrated weir for the maximum allowable water depth, and Table 8-22 and
Table 8-23 to 8-25. The height of stones or other granular material above the
waterproofed surface shall not be considered in water depth measurement,
and the roof surface in the vicinity of the drain shall not be recessed to create a
reservoir.
Roof design, where controlled flow roof drainage is used, shall be such that
the minimum design roof live load is 146.5 kg / m 2 to provide a safety factor
above the 73.2 kg / m 2 represented by the depth of water stored on the roof
as indicated in Table 8-28.
Scuppers shall be provided in parapet walls. The distance of scupper bottoms
above the roof level at the drains shall not exceed the maximum distances
specified in Table 8-30.
Table 8-30
Distance of Scupper Bottoms above Roof
Roof Rise mm
Maximum Distance of
Scupper Bottom
Above Roof Level at Drains mm
(Flat)
75
50
100
100
125
150
150
Source: Table 11-5 UPC 2000 Edition
Scupper openings shall be a maximum of 25.4 mm high. A sufficient number of
scuppers shall be provided so that the total scupper cross-Sectional area is at
least equal to that required for horizontal storm drains in Table 8-23 to Table
8-25 (column for 12.7 mm slope).
8-90
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
pressure of 34.5 kPa or sufficient to balance a column of mercury 254 mm
in height. This pressure shall be held without introduction of additional air
for a period of at least fifteen (15) minutes. Schedule 40 plastic DWV
systems shall not be tested by the air test method.
Exceptions: When circumstances exist that make air and water tests,
impractical, and for minor maintenance, repairs and installations, the Sanitary
Engineer may perform the inspection as considered advisable by said authority
to assure that the work has been in accordance with provisions of these Design
Guidelines.
Material Uses: Rainwater piping placed within the interior of a building or
run within a vent or shaft shall be of cast iron, galvanized steel, wrought iron,
brass, copper, lead, Schedule 40 ABS DWV, Schedule 40 PVC DWV, or other
approved materials, and changes in direction shall conform to the
requirements of Section 8.3.3.4, ABS and PVC DWV piping installations shall
be installed except for individual single family dwelling units, materials
exposed within ducts or plenums shall have a flame-spread index of not more
than 25 and a smoke-developed index of not more than 50, when tested in
accordance with the Test for Surface-Burning Characteristics of the Building
Materials.
Expansion Joints Required: Expansion joints or sleeves shall be provided
where warranted by temperature variations or physical conditions.
8.3.17
Hangers and supports: Hangers and support shall be the same as referred to in
Section 8.3.14.2.
Water Supply and Distribution System
Description: The water is supplied from a local water utility service through a
metering device and into the building and / or a storage tank. The water
distribution design is based on the architectural plan. The system may be up
feed or gravity feed depending on the approach of the engineer. Potable water
is distributed by to the fixtures depending on the system adopted by the
designer.
Running Water Required: Except where not deemed necessary for safety or
sanitation by the Sanitary Engineer, each plumbing fixture shall be provided
with an adequate supply of potable running water piped thereto in an approved
manner, so arranged as to flush and keep it in a clean and sanitary condition
without danger of backflow or cross-connection. Water closets and urinals shall
be flushed by means of an approved flush tank or flushometer valve. In
jurisdictions which adopt Reclaimed Water for non-Residential Buildings
(Appendix J of UPC 2000 Edition), water closets, urinals, and trap primers in
designated non-residential buildings may be provided with reclaimed water as
defined and regulated by same referenced appendix.
Identification of a Potable and Non–Potable Water System: In all buildings
where potable water and non-potable water systems are installed, each
system shall be clearly identified. Each system shall be color coded as follows:
8-92
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Potable Water – Green Background with White Lettering: Non-potable
Water – Yellow background with black lettering, with the words “CAUTION:
NONPOTABLEWATER, DO NOT DRINK”. Each system shall be identified with
a colored band to designate the liquid being conveyed, and the direction of
normal flow shall be clearly shown. The minimum size of the letters and
length of the color field shall conform to Table 8-31.
A colored identification band shall be indicated every 6.096m but at least once
per room, and shall be visible from the floor level. Where vacuum breakers or
backflow preventers are installed with fixtures listed in Table 14-1 of UPC 2000
Edition, identification of the discharge side may be omitted. Each outlet on the
non-potable water line which could be used for special purposes shall be posted
as follows:
“CAUTION: NONPOTABLE WATER, DO NOT DRINK”
Table 8-31
Minimum Length of Color Field and Size of Letters
Outside Diameter of Pipe or
Covering
mm
Minimum Length of Color
Field
Mm
Minimum Size of Letters
mm
15 to 32
203
12.7
40 to 50
203
19.1
65 to 150
305
32
200 to 250
619.0
64
Over 250
813.0
89
Source: Table 6-1 UPC 2000 Edition
Reclaimed Water – Purple (Pantone color #512) background and shall be
imprinted in nominal 1/2” (12.7 mm) high, black, upper case letters, with the
words “CAUTION: RECLAIMED WATER, DO NOT DRINK”.
Design Criteria
Water Distribution System
Hot and Cold Water Supply
1. Operating Pressure
Minimum
Maximum
=
=
2. Pressure Drop Due to Friction
1.7 kg/sq.cm.
4.22kg/sq.cm.
Pressure drop is determined to provide minimal effect on the delivery of
water to the fixtures. Friction effect will be lower using smoother the pipes.
for Galvanized Steel Pipe
=
120
for Copper Pipe
=
120
for Cast Iron Pipe
for polymer Pipe
3. Velocity
=
=
110
130
Optimum velocity for cold water piping
Mains (maximum)
=
1.8 m/s
Branches (maximum)
=
3.0 m/s
Risers (maximum)
Pipe Sizing
=
2.4 m/s
Shall be based on water flow requirement and as provided by National Plumbing
Code minimum requirement, refer to Section 8.3.18.7 for Pipe Sizing for Potable
Water.
Connections Prohibitions
Faucets and Diverters: Faucets and diverters shall be connected to the water
distribution system so that hot water corresponds to the left side of the
fittings.
Unlawful Connections: No installation of potable water supply piping or part
thereof shall be made in such a manner that it will be possible for used,
unclean, polluted or contaminated water, mixtures, or substances to enter any
portion of such piping from any tank, receptor, equipment, or plumbing fixture
by reason of back-siphonage, by suction or any other cause, either during
normal use and operation thereof or when any such tank, receptor,
equipment, or plumbing fixture is flooded, or subject to pressure in excess of
the operating pressure in the hot or cold water piping.
No person shall make a connection or allow one to exist between pipes or
conduits carrying domestic water supplied by any Public or Private water
service system, and any pipes, conduits, or fixtures containing or carrying
8-93
8-94
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-6
A-7
Suggested Minimum Lot Sizes, Lot Dimensions and Types for C-1 Use / Occupancy
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-7
Suggested Minimum Lot Sizes, Lot Dimensions and Types for C-2 Use / Occupancy
A-8
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-8
A-9
Suggested Minimum Lot Sizes, Lot Dimensions and Types for C-2 Use / Occupancy
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-9
Suggested Minimum Lot Sizes, Lot Dimensions and Types for C-3 Use / Occupancy
A-10
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-10
Suggested Minimum Lot Sizes, Lot Dimensions and Types for C-1 Use / Occupancy
Note: The Minimum NBCP
setbacks may have to be
relaxed as these will cause
extreme hardship and losses to
the lot owner i.e. as the resultant
to utilization is much too low.
A-11
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-11
Suggested Minimum Lot Sizes, Lot Dimensions and Types for C-2 Use / Occupancy
A-12
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-12
A-13
Suggested Minimum Lot Sizes, Lot Dimensions and Types for C-2 Use / Occupancy
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-13
Suggested Minimum Lot Sizes, Lot Dimensions and Types for C-1 Use / Occupancy
A-14
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-14
A-15
Suggested Minimum Lot Sizes, Lot Dimensions and Types for C-3 Use / Occupancy
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-15
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-1
A-16
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-16
A-17
Suggested Minimum Lot Sizes, Lot Dimensions and Types for C-3 Use / Occupancy
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-17
Suggested Minimum Lot Sizes, Lot Dimensions and Types for C-3 Use / Occupancy
A-18
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-18
A-19
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-1
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-19
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-3 Maximum
A-20
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-20
A-21
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-4 Maximum
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-21
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-5 Use / Occupancy
A-22
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-22
A-23
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-1
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-23
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-1
A-24
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-24
A-25
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-1
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-25
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-2 Basic
A-26
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-26
A-27
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-2 Basic
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-27
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-2 Basic
A-28
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-28
A-29
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-2 Basic
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-29
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-2 Maximum
A-30
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-30
A-31
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-2 Maximum
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-31
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-2 Maximum
A-32
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-32
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-2 Maximum
Note: The Minimum NBCP setbacks may have
to relaxed as these will cause extreme
hardship and losses to the lot owner i.e. as the
resultant lot utilization is much too low.
A-33
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-33
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-3 basic
A-34
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-34
A-35
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-3 Basic
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-35
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-3 Basic
A-36
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-36
C
A
A-37
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-3 Basic
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-37
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-3 Maximum
A-38
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-38
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-3 Maximum
Note: The Minimum NBCP setbacks may
have to be relaxed as these will cause
extreme hardship and losses to the lot
owner i.e. as the resultant lot utilization is
much too low.
A-39
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-39
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-3 Maximum
A-40
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-40
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-4 Maximum
Note: The Minimum NBCP setbacks may have
to be relaxed as these will cause extreme
hardship and losses to the lot owner i.e. as the
resultant lot utilization is much too low.
A-41
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-41
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-4 Maximum
A-42
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-42
A-43
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-4 Maximum
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-43
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-5 Use / Occupancy
A-44
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-44
A-45
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-5 Use / Occupancy
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure A-45
Suggested Minimum Lot Sizes, Lot Dimensions and Types for R-5 Use / Occupancy
A-46
Annex B
Outermost Faces of Buildings (OFB)
and Outermost Limits of Building
Projections (OLBP) under the 2004
Revised IRR of P.D. No. 1096 (1977
NBCP)
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Contents
B.1
INTRODUCTION ........................................................................................................................................... 1
Tables, Figures and Equations
Table B-1
List of Acronyms used for this Annex ........................................................................................................................1
Figure B-1
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 3.00
Figure B-2
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 8.00
Figure B-3
Figure B-4
Figure B-5
Figure B-6
Figure B-7
Figure B-8
Figure B-9
Figure B-10
Figure B-11
Figure B-12
Figure B-13
Figure B-14
Figure B-15
Figure B-16
B-i
m RROW ...................................................................................................................................................................................2
m RROW ...................................................................................................................................................................................3
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-17
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 20.00
Figure B-18
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 20.00
Figure B-19
Figure B-20
Figure B-21
m RROW ................................................................................................................................................................................ 18
m RROW ................................................................................................................................................................................ 19
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 26.00
m RROW ................................................................................................................................................................................ 20
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 40.00
m RROW ................................................................................................................................................................................ 21
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 50.00
m RROW ................................................................................................................................................................................ 22
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 8.00
m RR ...........................................................................................................................................................................................4
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 12.00
m RROW ...................................................................................................................................................................................5
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 16.00
m RROW ...................................................................................................................................................................................6
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 16.00
m RROW ...................................................................................................................................................................................7
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 20.00
m RROW ...................................................................................................................................................................................8
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 20.00
m RROW ...................................................................................................................................................................................9
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 24.00
m RROW ................................................................................................................................................................................ 10
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 30.00
m RROW ................................................................................................................................................................................ 11
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 40.00
m RROW ................................................................................................................................................................................ 12
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 6.00
m RROW ................................................................................................................................................................................ 13
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 6.00
m RROW ................................................................................................................................................................................ 14
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 10.00
m RROW ................................................................................................................................................................................ 15
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 12.00
m RROW ................................................................................................................................................................................ 16
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 16.00
m RROW ................................................................................................................................................................................ 17
B-ii
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
B.1
Introduction
This Annex graphically illustrates the prescribed compliances for the Outermost Face
of Buildings (OFB) and Outermost Limits of Building Projections (OLBP) based on the
derived angles from the road right-of-way (RROW) centerline as dictated by the local
government unit (LGU)-approved land use or zoning classification, RROW width,
prescribed building setbacks (including incremental setbacks), building height limit
(BHL), etc. And the resultant NO-BUILD ZONE (NBZ) under the 2004 Revised IRR of
P.D. No. 1096 (the 1977 National Building Code of the Philippines/ NBCP). The
document is intended for ready reference by physical planners, architects, designers,
and the competent reviewing authorities authorized to review/ process and approve
building plans under P.D. No. 1096.
Table B-1
Term
B-1
List of Acronyms used for this Annex
Definition
C-1
Commercial 1 (Light Commercial) classification i.e. a neighborhood or
community level of commercial use or occupancy, characterized mainly
as a low-rise building/ structure for low intensity commercial/trade, service and
business activities, e.g. one to three (1 to 3) storey shopping centers, small
offices or mixed use/ occupancy buildings and the like) under Rule VII of the
2004 IRR of P.D. No. 1096 (NBCP);
C-2
Commercial 2 (Medium Commercial) classification i.e. a municipal or city level
of commercial use or occupancy, characterized mainly as a medium-rise
building/structure for medium to high intensity commercial/ trade, service and
business activities, e.g. three to five (3 to 5) storey shopping centers, medium
to large office or mixed use/ occupancy buildings/ structures and the like) under
Rule VII of the 2004 IRR of P.D. No. 1096 (NBCP);
C-3
Commercial 3 (Metropolitan Commercial) classification i.e. a metropolitan level
of commercial use/ occupancy, characterized mainly as a medium-rise to highrise building/ structure for high to very high intensity commercial/ trade, service
and business activities, e.g. large to very large shopping malls, very large office
or mixed use/ occupancy buildings and the like) under Rule VII of the 2004 IRR
of P.D. No. 1096 (NBCP);
R-1
Residential 1 classification (low density residential zone e.g. single family,
single-detached dwellings) under Rule VII of the 2004 IRR of P.D. No. 1096
(NBCP);
R-2
Residential 2 classification (medium density residential use or occupancy e.g.
low-rise single-attached, duplex or multi-level building/ structure for exclusive
use as multi-family dwellings) under Rule VII of the 2004 IRR of P.D. No. 1096
(NBCP);
R-3
Residential 3 classification (high density residential use or occupancy e.g. lowrise or medium-rise building/ structure for exclusive use as multiple family
dwellings with mixed housing types) under Rule VII of the 2004 IRR of P.D. No.
1096 (NBCP);
R-4
Residential 4 classification (medium to high density residential use or
occupancy e.g. low-rise townhouse building/ structure for exclusive use as
multiple family dwellings) under Rule VII of the 2004 IRR of P.D. No. 1096
(NBCP); and
R-5
Residential 5 classification (very high density residential use or occupancy e.g.
medium-rise or high-rise condominium building/ structure for exclusive use as
multiple family dwelling) under Rule VII of the 2004 IRR of P.D. No. 1096
(NBCP).
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-1
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 3.00 m RROW
B-2
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-2
B-3
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 8.00 m RROW
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-3
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 8.00 m RR
B-4
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-4
B-5
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 12.00 m RROW
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-5
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 16.00 m RROW
B-6
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-6
B-7
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 16.00 m RROW
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-7
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 20.00 m RROW
B-8
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-8
B-9
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 20.00 m RROW
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-9
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 24.00 m RROW
B-10
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-10
B-11
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 30.00 m RROW
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-11
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 40.00 m RROW
B-12
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-12
B-13
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 6.00 m RROW
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-13
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 6.00 m RROW
B-14
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-14
B-15
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 10.00 m RROW
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-15
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 12.00 m RROW
B-16
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-16
B-17
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 16.00 m RROW
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-17
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 20.00 m RROW
B-18
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-18
B-19
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 20.00 m RROW
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-19
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 26.00 m RROW
B-20
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-20
B-21
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 40.00 m RROW
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure B-21
RROW Angles from Centreline that Determine the OFB of Buildings / Structures along a 50.00 m RROW
B-22
Annex C
Proposed Typical Public Buildings
(Reference Concept-Level
Architectural Plans and Designs for
Proposed Typical Buildings Intended
for Public Use)
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Contents
C.1
PROPOSED TYPICAL PUBLIC BUILDINGS (REFERENCE CONCEPT-LEVEL ARCHITECTURAL PLANS
AND DESIGNS FOR PROPOSED TYPICAL BUILDINGS INTENDED FOR PUBLIC USE) ............................. 1
C.1.1
C.1.2
C.1.3
C.1.4
C.1.5
C.1.6
C.1.7
C.1.8
C.1.9
C.1.10
C.1.11
C.1.12
C.1.13
FIVE-STOREY SECONDARY SCHOOL BUILDING ....................................................................................................... 1
FOUR- TO EIGHT-STOREY PUBLIC HOUSING BUILDING .......................................................................................... 3
CIVIC CENTRE BUILDING (OPTION 1) .................................................................................................................. 9
CIVIC CENTRE BUILDING (OPTION 2) ................................................................................................................ 13
EXPANDABLE 2-STOREY HALL OF JUSTICE BUILDING ........................................................................................... 21
2-STOREY FIRE AND POLICE STATION BUILDINGS ............................................................................................... 25
CITY BUS TERMINAL BUILDING ......................................................................................................................... 29
PUBLIC MARKET BUILDING ............................................................................................................................... 31
PUBLIC GYMNASIUM BUILDING.......................................................................................................................... 36
PUBLIC POOL AND BATH BUILDING .................................................................................................................... 37
COVERED COURT BUILDING ............................................................................................................................... 39
4-STOREY PUBLIC COVERED PARKING BUILDING ................................................................................................. 40
SMALL AIRPORT PASSENGER TERMINAL BUILDING (PTB) ................................................................................... 44
Tables, Figures and Equations
Table C-1
Spatial Programming of 5-Storey Secondary School Building .........................................................................3
Table C-3
Spatial Programming of Civic Centre Building (Option 1) ............................................................................. 11
Table C-2
Spatial Programming of 5-Unit per Floor, 4-Storey/ 8-Storey Public Housing Building .....................8
Table C-4
Spatial Programming of Civic Center Building (Option 2) .............................................................................. 16
Table C-6
Spatial Programming of 2-storey Fire Station Building ................................................................................... 27
Table C-5
Table C-7
Table C-8
Table C-9
Table C-10
Table C-11
Table C-12
Table C-13
Table C-14
Table C-15
Spatial Programming of Expandable 2-storey Hall of Justice Building ..................................................... 24
Spatial Programming of Police Substation Building .......................................................................................... 29
Spatial Programming of City Bus Terminal Building ........................................................................................ 31
Spatial Programming of Public Market Building ................................................................................................. 34
Figure C-7
Figure C-8
Figure C-9
C-i
Conceptual Architectural Plans of 2-Storey Hall of Justice Building .......................................................... 22
Figure C-13
Figure C-14
Figure C-15
Figure C-16
Figure C-17
Figure C-18
Figure C-19
Figure C-20
Figure C-21
Figure C-22
Figure C-23
Figure C-24
Figure C-25
Figure C-26
Figure C-27
Figure C-28
Figure C-29
Figure C-30
Figure C-31
Figure C-32
Perspectives of 2-storey Hall of Justice Building ................................................................................................ 21
Perspective of 2-Storey Fire Station Building ...................................................................................................... 25
Conceptual Architectural Plans of 2-Storey Fire Station Building .............................................................. 26
Perspective of Police Substation Building.............................................................................................................. 28
Conceptual Floor Plan of Police Substation Building ........................................................................................ 28
Perspectives of City Bus Terminal Building .......................................................................................................... 29
Conceptual Architectural Plans of City Bus Terminal Building .................................................................... 30
Perspectives of Public Market Building .................................................................................................................. 31
Conceptual Architectural Plans of Public Market Building ............................................................................ 32
Perspective of Public Gymnasium Building........................................................................................................... 36
Conceptual Architectural Plans of Public Gymnasium Building .................................................................. 36
Perspective of Public Pool and Bath Building ...................................................................................................... 37
Conceptual Architectural Plan of Public Pool and Bath Building ................................................................ 38
Perspective of Covered Court Building ................................................................................................................... 39
Conceptual Architectural Plan of Covered Court Structure ........................................................................... 39
Perspective of Public Covered Parking Building ................................................................................................. 40
Conceptual Architectural Plans of Public Covered Parking Building......................................................... 40
Perspectives of a Small Airport Passenger Terminal Building ..................................................................... 44
Conceptual Architectural Plan of a Small Port Passenger Terminal Building (PTB) .......................... 45
Perspectives of a Small Port Passenger Terminal Building (PTB) Option 1 ........................................... 46
Conceptual Architectural Plan of a Small Port Passenger Terminal Building (PTB) Option 2….. 47
Spatial Programming of 4-storey Public Covered Parking Building .......................................................... 42
Spatial Programming of a Small Port Passenger Terminal Building (PTB) Option 1 ......................... 45
Spatial Programming of a Small Port Passenger Terminal Building (PTB) Option 2… ..................... 47
Perspectives of 4-storey Public Housing Building ................................................................................................3
Figure C-6
Figure C-12
Figure C-11
Spatial Programming of Covered Court Structure ............................................................................................. 40
Figure C-3
Figure C-5
Conceptual Architectural Plans of Civic Center (Option 2) ............................................................................ 13
Spatial Programming of Public Pool and Bath Building................................................................................... 38
Perspective of a 5-storey Secondary School Building ..........................................................................................1
Figure C-4
Figure C-10
Spatial Programming of Public Gymnasium Building ....................................................................................... 37
Figure C-1
Figure C-2
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Conceptual Architectural Plans of 5-storey Secondary School Building .....................................................1
Conceptual Architectural Plans of 4-storey Public Housing Building ..........................................................4
Perspectives of 8-storey Public Housing Building ................................................................................................6
Perspectives of 8-storey Public Housing Building ................................................................................................6
Perspectives of Civic Center Building (Option 1) ..................................................................................................9
Conceptual Architectural Plans of Civic Center Building (Option 1) ............................................................9
Perspectives of Civic Center Building (Option 2) ............................................................................................... 13
C-ii
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
C-2
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
C-5
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table C-2
Spatial Programming of 5-Unit per Floor, 4-Storey/ 8-Storey Public
Housing Building
5-UNIT PER FLOOR, 12-STOREY
BUILDING
NAME OF SPACE
SPACE PROGRAM
DIMENSION (m)
AREA(m²)
W
D
Garden/Atrium
12.8
3.6
46.08
Stairwell
4
2.85
11.4
Elevator
2.8
2.6
7.28
E.E.
1
2.6
2.6
Open Area / Circulation
16.4
24.5
334.12
TOTAL GROUND FLOOR AREA
16.4
26
411
TYPICAL UNIT [X5]
5.5
10
275
Balcony
5.5
1.5
8.25
Bedroom
2
2.7
6
Master's Bedroom
3.5
2.7
9.45
Dining and Living
3
5.8
16.8
Toilet and Bath 01
2.4
1.8
3.96
Toilet and Bath 02
2.4
1.4
3.72
Kitchen
2.4
2.6
6.24
Stairwell
4
2.85
11.4
Elevator
2.8
2.6
7.28
E.E.
1
2.6
2.6
SUBTOTAL
(sq.m)
GROUND FLOOR
TYPICAL 2ND - 11TH FLOOR
Subtotal: Typical Unit
54.42
Circulation
TOTAL TYPICAL 2ND-11TH FLOOR
AREA
109.92
16.4
27.5
406.2
Stairwell
4
2.85
11.4
Machine Room
5.4
2.6
14.04
Open Area
16.4
27.5
380.76
TOTAL ROOF DECK FLOOR AREA
16.4
27.5
406.2
ROOF DECK
TOTAL 5-UNIT PER FLOOR, 12STOREY PUBLIC HOUSING
BUILDING FLOOR AREA
C-7
5285.4
C-8
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
C-10
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table C-3
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Spatial Programming of Civic Centre Building (Option 1)
CIVIC CENTER BUILDING [OPTION 1]
NAME OF SPACE
CIVIC CENTER BUILDING [OPTION 1]
SPACE PROGRAM
DIMENSION (m)
AREA(m²)
SUBTOTAL
(sq.m)
DIMENSION (m)
AREA(m²)
W
D
Public Service
10
20
200
W
D
Public Service
10
17
170
Lobby
50
40
1400
Treasurer
10
20
200
Male's Toilet
3.5
10
35
Storage
7
10
70
Female's Toilet
3.5
10
35
E.E.
3
10
30
Utility Storage
7
10
70
GROUND FLOOR
Subtotal: Public Space
1470
Enclosed Hallways (Left Wing)
260
Enclosed Hallways (Right Wing)
226
Subtotal: Private Circulation
Subtotal: Private Spaces
5000
SECOND FLOOR
Stairwell 1
3
6
18
Stairwell 1
3
6
18
Stairwell 2
3
6
18
Stairwell 2
3
6
18
Stairwell 3
10
10
100
Stairwell 3
10
10
100
136
Subtotal: Stairwells
136
Consultation Office
10
10
100
Lobby & Open Hallways
50
40
1520
Legal Affairs Office
10
10
100
Male's Toilet
3.5
10
35
Attorney's Office
10
10
100
Female's Toilet
3.5
10
35
Traffic Office
10
10
100
Public Library
30
37
1110
Social Welfare and Development Office
10
10
100
Subtotal: Public Spaces
Engineering Design
10
10
100
Hearing Room 1
10
10
100
Engineering Office
10
10
100
Hearing Room 2
10
10
100
Planning and Development Office
10
10
100
Hearing Room 3
10
10
100
Mayor's Office
8
10
80
Attorney's Office 1
10
10
100
Vice Mayor's Office
8
10
80
Attorney's Office 2
10
10
100
Conference Room
8
7
56
Hearing Room 4
10
10
100
Files storage
8
10
80
Hearing Room 5
10
10
100
Files storage (Clerical)
3
7
21
Hearing Room 6
10
10
100
Clerical
5
7
35
Council Chamber 01
30
17
510
Personnel Office
8
10
80
Council Chamber 02
30
20
600
Administrator Office
8
10
80
Storage
7
10
70
Plan Checking Office
5
7
35
Utility Storage
7
10
70
Files Storage (Plan Checking Office)
3
7
21
E.E.
3
10
30
Budget Office
8
10
80
Enclosed Circulation
Treasurer Office
8
10
80
Subtotal: Private Spaces
Clerical
5
7
35
TOTAL SECOND FLOOR
5000
Accounting Clerical
5
7
35
10
7
70
TOTAL CIVIC CENTER BUILDING
[OPTION 01] FLOOR AREA
10000
Conference Room
Vault
10
10
100
Chief Deputy Auditor Office
8
10
80
Accounting Office
8
10
80
Clerical
5
7
35
Clerical
5
7
35
Public Service
10
17
170
SUBTOTAL
(sq.m)
2908
TOTAL GROUND FLOOR
486
Subtotal: Stairwells
C-11
NAME OF SPACE
SPACE PROGRAM
2700
84
2164
C-12
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
C-14
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table C-4
Spatial Programming of Civic Center Building (Option 2)
CIVIC CENTER BUILDING [OPTION 2]
NAME OF SPACE
SPACE PROGRAM
DIMENSION (m)
AREA(m²)
W
D
Stairwell 1
3
6
18
Stairwell 2
3
6
18
Stairwell 3
10
10.5
105
Stairwell 4
10
10.5
105
Stairwell 5
3
6.5
19.5
Stairwell 6
3
6.5
19.5
Subtotal
(sq.m)
LOWER GROUND FLOOR
Subtotal: Stairs
285
General Storage Room 1
7
8
56
General Storage Room 2
7
8
56
Parking for dump truck 1
10
4
40
Parking for dump truck 2
10
4
40
Garbage Disposal Area 1
7
6
42
Garbage Disposal Area 2
7
6
42
Driveway
10
697
6970
Parking Space [x301]
5
2.5
3762.5
Open Area / Atrium
70.5
52
3666
Islands and Walkways
940.5
TOTAL GROUND FLOOR
15900
UPPER GROUND FLOOR
C-15
General Storage Room 1
7
8
56
Planning and Development Office
10
7.3
73
Chief Engineering Office
10
6.5
65
Photocopy Room
10
4
40
Storage Room 1
7
4.5
31.5
Maintenance office
10
6.5
65
Conference room 1
10
6
60
Vault
10
17
170
Records Storage Room
7
13.8
96.6
Conference room 2
7
8.5
59.5
Files Storage Room
7
14
98
Conference room 3
7
7.5
52.5
Files Storage Room
7
14.5
101.5
Clerical Area 1
10
13.8
138
Clerical Area 2
10
13.8
138
Clerical Area 3
10
13.2
132
Clerical Area 4
10
13.2
132
Budget Office
10
8.5
85
Treasurer's Office
10
8.5
85
Public Service 1
10
24
240
Public Service 2
10
23.5
235
C-16
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
CIVIC CENTER BUILDING [OPTION 2]
NAME OF SPACE
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
SPACE PROGRAM
DIMENSION (m)
AREA(m²)
Subtotal
(sq.m)
NAME OF SPACE
SPACE PROGRAM
DIMENSION (m)
D
Auditor's Office
10
8.3
83
Females Toilet
Chief Deputy Auditor Office
10
8.3
83
Waiting Areas & Circulation
Conference room
10
6
60
Subtotal: Public Spaces
Accounting Office
10
6
60
Stairwell 1
3
6
18
Treasurer Office
10
8.5
85
Stairwell 2
3
4.5
13.5
Personnel Office
10
8.5
85
Stairwell 3
3
6
18
Engineering Design Office
10
11.5
115
Stairwell 4
3
4.5
13.5
Plan Checking Office
10
11.5
115
Stairwell 5
10
10.5
105
Water Services Office
10
11.5
115
Stairwell 6
10
10.5
105
Public Information Office
10
11.5
115
Subtotal: stairwells
Consultation Office
10
11.5
115
UPPER GROUND FLOOR TOTAL
Legal Affairs Office
10
11.5
115
SECOND FLOOR PLAN
Traffic Office
10
11.5
115
Councillor’s Office 1
10
11.5
115
Social Welfare and Development Office
10
11.5
115
Councillor’s Office 2
10
11.5
115
Control centre
20
22.3
446
Legal Counsel Office
10
11.5
115
Information Desk and Public Service
20
23.5
470
Library
20
11.5
230
Police Assembly Room
24.5
13.8
338.1
Clustered Cell 1
10
11.5
115
Police Office
24.5
32
784
Clustered Cell 2
10
11.5
115
Police Chief Office
10
6
60
Clustered Cell 3
10
11.5
115
Police Public Safety Office 1
10
8.5
85
Clustered Cell 4
10
11.5
115
Interview Room 03
5
6
30
Clustered Cell 5
10
11.5
115
Interview Room 04
5
6
30
E.E. 2
3
6.5
19.5
Police Public Safety Office 2
10
8.5
85
Shower and Locker Area
4
8
32
File/s Storage Room
6.5
6
39
Utilities Storage
3
3
9
Conference room
6.5
8.5
55.25
Dining and Dayroom Area 1
12
17
197.4
Police Office 1
10
11.5
115
Dining and Dayroom Area 2
12
23.5
282
Police Office 2
10
11.5
115
Prison Area
58
53
2210
Police Office 3
10
11.5
115
Kit
10
4
40
Police Office 4
10
11.5
115
Storage Room
7
6
42
Police Office 5
10
11.5
115
Interrogation Room
10
5.25
52.5
Police Office 6
10
11.5
115
Visiting Room 1
10
5.25
52.5
Police Office 7
10
11.5
115
Visiting Room 2
10
6.5
65
Police Office 8
10
11.5
115
Warden's Office
10
9.3
93
General Storage Room 2
7
8
56
Police Captain's Office
10
9.3
93
Clustered Cell 1
10
7.3
73
Conference Room
8
9.3
74.4
Clustered Cell 2
10
6.5
65
Patrol Guards Office
20
23.5
470
Clustered Cell 3
10
4
40
File/s Storage Room
7
14.5
101.5
Firearms and Equipment Storage Room
10
17
170
Conference Room
10
6
60
Storage Room
7
4.5
31.5
Assistant City Management Office
10
8.5
85
Clerical
10
6
60
E.E.
3
11.5
34.5
City Management Office
10
8.5
85
Males Toilet
3.5
9.5
33.25
File/s Storage Room
7
14
98
7307.45
W
D
3.5
9.5
AREA(m²)
W
Subtotal: Private Spaces
C-17
CIVIC CENTER BUILDING [OPTION 2]
Subtotal
(sq.m)
33.25
5445.55
5546.55
273
13127
C-18
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
CIVIC CENTER BUILDING [OPTION 2]
NAME OF SPACE
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
SPACE PROGRAM
DIMENSION (m)
AREA(m²)
W
D
Conference Room
7
7.5
52.5
Council Hall 2
30
21.5
Council Hall 1
30
Councillor’s Office 3
Subtotal
(sq.m)
NAME OF SPACE
SPACE PROGRAM
DIMENSION (m)
AREA(m²)
W
D
Shower and Locker Area
4
8
32
645
Utilities Storage
3
3
9
22.3
669
General Storage Room 2
7
8
56
10
7.3
73
Attorney's Office 1
10
7.3
73
Councillor’s Office 4
10
6.5
65
Attorney's Office 2
10
6.5
65
Photocopy Room
10
4
40
Photocopy Room
10
4
40
Storage Room
7
6
42
Storage Room
7
6
42
Maintenance Office
10
6.5
65
Maintenance Office
10
6.5
65
Conference Room
10
8
80
Conference Room
10
8
80
City Administrator's Office
10
6.5
65
Judge's Office 1
10
6.5
65
Vice Mayor's Office 1
10
6.5
65
Judge's Office 2
10
6.5
65
Vice Mayor's Office 2
10
6.5
65
Judge's Office 3
10
6.5
65
Mayor's Office
10
6.5
65
Judge's Office 4
10
6.5
65
General Storage Room
7
8
56
Bailiff 1 of Courthouse 1
7
7.3
51.1
General Storage Room
7
8
56
Storage of Courthouse 1
7
6.5
45.5
E.E.
3
11.5
34.5
Bailiff 2 of Courthouse 1
7
8.5
59.5
Courthouse 1
30
22.3
669
Subtotal: Private Areas
7509.8
Males Toilet
3.5
9.5
33.25
Bailiff 1 of Courthouse 2
7
6.5
45.5
Females Toilet
3.5
9.5
33.25
Storage of Courthouse 2
7
7.8
54.6
Waiting Areas & Circulation
8038.7
Subtotal: Public Spaces
8139.7
Bailiff 2 of Courthouse 2
7
7.2
50.4
Courthouse 2
30
21.5
645
Stairwell 1
3
6
18
File/s Storage Room
7
14.5
101.5
Stairwell 2
3
6.5
19.5
Conference Room
10
6
60
Stairwell 3
3
6
18
Hearing Room 03
10
8.5
85
Stairwell 4
3
6.5
19.5
Clerical
10
6
60
Stairwell 5
10
10.5
105
Hearing Room 04
10
8.5
85
Stairwell 6
10
10.5
105
Dining and Dayroom Area 1
12
17
197.4
Dining and Dayroom Area 2
12
23.5
282
Prison Area
58
53
2210
Kit
10
4
40
Subtotal: stairwells
285
TOTAL SECOND FLOOR
15900
THIRD-FOURTH FLOOR
C-19
CIVIC CENTER BUILDING [OPTION 2]
General Storage Room 1
7
8
56
Storage Room
7
6
42
E.E.
3
11.5
34.5
Interrogation Room
10
5.25
52.5
Public Attorney's Office
10
11.5
115
Visiting Room 1
10
5.25
52.5
Hearing Room 1
10
11.5
115
Visiting Room 2
10
6.5
65
Hearing Room 2
10
11.5
115
Warden's Office
10
9.3
93
Library
20
11.5
230
Police Captain's Office
10
9.3
93
Clustered Cell 1
10
11.5
115
Conference Room
8
9.3
74.4
Clustered Cell 2
10
11.5
115
Patrol Guards Office
20
23.5
470
Clustered Cell 3
10
11.5
115
Subtotal: Private Areas
Clustered Cell 4
10
11.5
115
Males Toilet
3.5
9.5
33.25
Clustered Cell 5
10
11.5
115
Females Toilet
3.5
9.5
33.25
E.E. 2
3
6.5
19.5
Waiting Areas & Circulation
Subtotal
(sq.m)
7665.9
7882.6
C-20
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table C-5
Spatial Programming of Expandable 2-storey Hall of Justice Building
EXPANDABLE 2-STOREY
HALL OF JUSTICE BUILDING
NAME OF SPACE
SPACE PROGRAM
DIMENSION (m)
AREA(m²)
W
D
Judge's Office 01
10
6
60
Judge's Office 02
10
6
60
Entry to Cells
3.6
6
21.6
Cell 1
3.8
3
11.4
Cell 2
3.8
3
11.4
Judge's Office 03
8
7.5
60
Staff's Office 01
8
7.5
60
Attorney's Office 3
8
7.5
60
Attorney's Office 4
8
7.5
60
Attorney's Consultation
8
10
80
Judge's Office 04
8
7.5
60
Staff's Office 02
8
7.5
60
File Storage
8
5
40
Male's Toilet
8
3.25
23.1635
Female's Toilet
8
3.25
23.1635
Storage
8
3
24
General Office
8
10
80
Court room 01
8.85
8.85
78.3225
Court room 02
8.85
8.85
78.3225
Court room 03
8.85
8.85
78.3225
Court room 04
8.85
8.85
78.3225
Court Lobby
17.7
20
304
Stairs 01
3
4.25
14.625
Stairs 02
3
4.25
14.625
Stairs 03
5
5
25
Stairs 04
5
5
25
37.7
47.7
1798.29
Judge's Office 01
10
6
60
Judge's Office 02
10
6
60
File Storage
4
6
24
Entry to Cells
3.6
6
21.6
Cell 1
3.8
3
11.4
Cell 2
3.8
3
11.4
Judge's Office 03
8
7.5
60
Hearing Room 01
8
7.5
60
Attorney's Office 01
8
7.5
60
Attorney's Office 02
8
7.5
60
Attorney's Consultation
8
10
80
GROUND FLOOR
Circulation
GROUND FLOOR TOTAL
307.023
SECOND FLOOR
C-23
C-24
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure C-14
Conceptual Architectural Plans of 2-Storey Fire Station Building
C-26
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table C-6
Spatial Programming of 2-storey Fire Station Building
2-STOREY FIRE STATION BUILDING
NAME OF SPACE
SPACE PROGRAM
DIMENSION (m)
AREA(m²)
W
D
Maintenance Area
10
14
140
Fire hose Storage
4
3.5
14
Turnout Storage
4
3.5
14
Medical Supplies Storage
4
3.5
14
Stairwell
3.2
3
9.6
Clinic
4
6
24
Clinic Head's Office
4
6
24
Firefighter's Captain Office
4
6
24
Chief Firefighter's Office
4
6
24
Admins Office
4
6
24
Lobby
20
8
106
Conference Room
9
5
45
Alarm / Watch Room
3
3
9
Fire Trucks
29
14
354.4
GROUND FLOOR
TOTAL GROUND FLOOR AREA
826
SECOND FLOOR
C-27
Male Firefighter's Dressing Room
6
6
36
Utility Storage
3
3
9
Male Firefighter's Toilet and Bath
7
6
42
Female Firefighter's Toilet and Bath
7
6
42
Utility Storage
3
3
9
Female Firefighter's Dressing Room
6
6
36
Male Firefighter's Quarters
16
6
96
Female Firefighter's Quarters
16.05
6
96.3
Stairwell
3.2
3
9.6
Circulation
38.1
14
157.5
TOTAL SECOND FLOOR AREA
375.9
TOTAL FIRE STATION BUILDING
FLOOR AREA
1201.9
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table C-9
Spatial Programming of Public Market Building
PUBLIC MARKET
NAME OF SPACE
DIMENSION (m)
AREA(m²)
W
D
STALL(LEFT WING) Comfort Room
7.2
9.6
69.12
1 to 16
7.2
12
86.4
7.2
7.2
51.84
4.8
9.6
46.08
4.8
12
57.6
4.8
7.2
34.56
4.8
9.6
46.08
4.8
12
57.6
4.8
7.2
34.56
4.8
9.6
46.08
4.8
12
57.6
4.8
7.2
34.56
4.8
9.6
46.08
4.8
12
57.6
4.8
7.2
34.56
7.2
9.6
69.12
7.2
12
86.4
7.2
7.2
51.84
17 to 40
41 to 64
65 to 88
89 to 112
113 to 136
Subtotal: LEFT WING
C-33
SPACE PROGRAM
967.68
C-34
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
PUBLIC MARKET
NAME OF SPACE
SPACE PROGRAM
DIMENSION (m)
AREA(m²)
W
D
7.2
7.2
51.84
7.2
12
86.4
7.2
12
86.4
1 to 6(Left)
7.2
7.2
51.84
8 to 33(Right)
4.8
7.2
34.56
4.8
12
57.6
4.8
12
57.6
4.8
12
57.6
4.8
4.8
23.04
4.8
7.2
34.56
4.8
12
57.6
4.8
12
57.6
4.8
12
57.6
4.8
4.8
23.04
4.8
7.2
34.56
4.8
12
57.6
4.8
12
57.6
4.8
12
57.6
4.8
4.8
23.04
4.8
7.2
34.56
4.8
12
57.6
4.8
12
57.6
4.8
12
57.6
4.8
4.8
23.04
8.4
7.2
60.48
8.4
12
100.8
8.4
12
100.8
8.4
12
100.8
8.4
7.2
60.48
STALL(RIGHT WING)
1 to 7 (Right)
7 to 20(Left)
21 to 34(Left)
60 to 85(Right)
35 to 48(Left)
86 to 111(Right)
49 to 62(Left)
1 to 24
Subtotal: RIGHT WING
Hallway
C-35
1621.44
50.4
36
846.72
50.4
64.8
1644.48
Arcade
513.78
TOTAL PUBLIC MARKET BUILDING
FLOOR AREA
5594.1
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table C-13
Spatial Programming of 4-storey Public Covered Parking Building
PUBLIC COVERED PARKING BUILDING
NAME OF SPACE
SPACE PROGRAM
DIMENSION (m)
AREA(m²)
W
D
5
26.2
131
5
23.6
118
10
31.2
312
GROUND FLOOR PLAN
Parking Slot
Subtotal: Parking Slots
Stair
561
3.25
2.45
Subtotal: Stairs
Island
23.8875
1.825
2.6
Subtotal: Islands
Comfort Room
7.9625
4.745
14.235
4.85
2.45
11.8825
Subtotal: Comfort Rooms
23.765
Ramp(computed at 2nd floor)
80.25
Driveway
23.075
52.4
TOTAL GROUND FLOOR AREA
505.9925
1209.13
2ND FLOOR
Parking Slot
5
10.4
52
5
7.8
39
10
31.2
312
Subtotal: Parking Slots
Stair
403
3.25
2.45
1.825
2.6
Subtotal: Stairs
Island
C-41
7.9625
23.8875
4.745
C-42
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
PUBLIC COVERED PARKING BUILDING
NAME OF SPACE
SPACE PROGRAM
DIMENSION (m)
W
D
Subtotal: Islands
Comfort Room
AREA(m²)
14.235
4.85
2.45
11.8825
Subtotal: Comfort Rooms
23.765
Ramp
98.14
Subtotal: Ramps
196.28
Driveway
23.075
52.4
TOTAL 2ND FLOOR AREA
547.9625
1209.13
3RD FLOOR
Parking Slot
5
10.4
52
5
7.8
39
10
31.2
312
Subtotal: Parking Slots
Stair
403
3.25
2.45
Subtotal: Stairs
Island
1.825
2.6
Subtotal: Islands
Comfort Room
7.9625
23.8875
4.745
14.235
4.85
2.45
Subtotal: Comfort Rooms
11.8825
23.765
Ramp
98.14
Subtotal: Ramps
196.28
Driveway
23.075
52.4
TOTAL 3RD FLOOR AREA
547.9625
1209.13
ROOF DECK
Parking Slot
5
10.4
52
5
7.8
39
10
31.2
312
Subtotal: Parking Slots
Stair
403
3.25
2.45
Subtotal: Stairs
Island
23.8875
1.825
2.6
Subtotal: Islands
Comfort Room
4.745
14.235
4.85
2.45
11.8825
Subtotal: Comfort Rooms
23.765
Ramp
98.14
Subtotal: Ramps
196.28
Driveway
C-43
7.9625
23.075
52.4
547.9625
TOTAL ROOF DECK AREA
1209.13
TOTAL COVERED PARKING BUILDING
FLOOR AREA
4836.52
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure C-30
Conceptual Architectural Plan of a Small Port Passenger Terminal
Building (PTB)
Table C-14
Spatial Programming of a Small Port Passenger Terminal Building (PTB)
Option 1
SMALL PORT
PASSENGER TERMINAL BUILDING (PTB)
OPTION 1
NAME OF SPACE
C-45
SPACE PROGRAM
DIMENSION (m)
AREA(m²)
W
D
Departure Lounge
7
20
140
Electrical Room
1.5
4
6
Departure Lounge Toilet
1.5
4
6
Arrival Toilet
1.5
4
6
Utlity Room
1.5
4
6
Information / Check-in
3
6
18
Information / Check-in Storage
3
1.8
5.4
Pantry
3
2.2
6.6
Storage
3
2
6
Office
6
13
60
Arrival
7
20
140
TOTAL SMALL PORT PASSENGER
TERMINAL BUILDING (PTB) OPTION 1
FLOOR AREA
20
20
400
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Figure C-32
Conceptual Architectural Plan of a Small Port Passenger Terminal
Building (PTB) Option 2
Annex D
Table C-15
Spatial Programming of a Small Port Passenger Terminal Building (PTB)
Option 2
SMALL PORT PASSENGER TERMINAL
BUILDING (PTB) OPTION 2
NAME OF SPACE
C-47
SPACE PROGRAM
DIMENSION (m)
AREA(m²)
W
D
Departure Lounge
8
13.4
95.375
Ticket Queueing Area
6.8
2.7
18.36
Office and Ticketing
5.2
11
57.2
Arrival Lounge
8
16
116.175
Departure Lounge Toilet
1.5
2.2
3.3
Arrival Area Toilet
1.5
2.2
3.3
Storage 1
3
1.5
4.5
Storage 2
3
1.6
4.8
TOTAL SMALL PORT PASSENGER
TERMINAL BUILDING (PTB) OPTION 2
FLOOR AREA
19
16
304
Minimum Performance Standards and
Specifications (MPSS) for New Public
Buildings (also applicable private
buildings)
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Contents
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Acronyms and Abbreviations
Term
Definition
o
C
degree Celsius
ACI
American Concrete Institute (ACI)
ACP
Architectural Code of the Philippines, DPWH 2000
ADR
Alternative Dispute Resolution
AISC
American Institute of Steel Construction
AISI
American Iron and Steel Institute
ANSI
American National Standards Institute
ASME
American Society of Mechanical Engineers
ASTM
American Society for Testing and Materials (ASTM)
AWS
American Welding Society
B.P.
Batas Pambansa (national law)
BoQ
bill of quantities
BPS
Bureau of Product Standards
BRS
Bureau of Research and Standards
CAED
Conceptual Architectural and Engineering Design
CCD
Construction Completion Deadline
CCN
Construction Completion Notice
CED
Conceptual Engineering Design
CO
convenience outlet
CoC
Certificate of Completion
CoFA
Certificate of Final Acceptance
cu.ft.
cubic foot/ feet
cu.m.
cubic meter/s
dB (A)
decibel/s
DAC
Design Approval Committee
Tables and Figures
DAED
Detailed Architectural and Engineering Design
DBS
Design-Build Services
Table D-1
DCE
detailed cost estimate
DCP
Detailed Construction Plan
DED
Detailed Engineering Design
DIN
Deustche Industrie Norm
DLP
Defects Liability Period
DILG
Department of the Interior and Local Government
DoH
Department of Health
DoLE
Department of Labor and Employment
DoTC
Department of Transportation and Communications
DPWH
Department of Public Works and Highways
DTI
Department of Trade and Industry
E.O.
Executive Order
FCP
Fire Code of the Philippines
FCL
finished ceiling line
D.1
PURPOSE .................................................................................................................................................. 1
D.2
DESIGN ..................................................................................................................................................... 3
D.2.1
SCOPE OF DESIGN SERVICES ...................................................................................................................... 3
D.2.2
D.2.3
D.2.4
D.2.5
D.2.6
D.2.7
D.2.8
D.2.9
D.2.10
COMPONENTS AND OUTPUTS OF DETAILED ARCHITECTURE AND ENGINEERING DESIGN
(DAED) BY BUILDER .................................................................................................................................... 3
GOVERNING CODES AND SPECIFICATIONS ............................................................................................... 5
ARCHITECTURAL STANDARDS................................................................................................................... 5
STRUCTURAL STANDARDS ......................................................................................................................... 8
ELECTRICAL STANDARDS ......................................................................................................................... 10
SANITARY AND PLUMBING STANDARDS ................................................................................................ 11
TOILETS ...................................................................................................................................................... 11
MATERIALS ................................................................................................................................................ 11
OTHER STANDARDS .................................................................................................................................. 15
OTHER REQUIREMENTS ........................................................................................................................... 15
D.2.11
D.3
CONSTRUCTION .................................................................................................................................... 16
D.3.1
SCOPE OF CONSTRUCTION ....................................................................................................................... 16
D.3.3
DETAILED CONSTRUCTION PLAN ............................................................................................................ 16
D.3.2
D.3.4
D.3.5
STANDARDS AND SPECIFICATIONS FOR CONSTRUCTION .................................................................... 16
TEST REQUIREMENTS ............................................................................................................................... 17
COMPLETION OF CONSTRUCTION ........................................................................................................... 17
Live Loads ........................................................................................................................................................................................9
Figure D-1 Scope of Design..............................................................................................................................................................................3
D-i
D-ii
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Term
Definition
Term
Definition
FFL
finished floor line
RC
Referral Code/s
FGL
finished grade line
RCN
Rectification Completion Notice
FRD
Final Rectification Deadline
RH
relative humidity
FFFE
Furniture/ Furnishings, Fixtures & Equipment
RI
Rectification Inspection
IC
Independent Consultant
RLAs
registered and licensed architects
IM
Information Memorandum
SIF
seismic importance factor
IMC
intermediate metallic conduit
sqm
square meter/s
IRR
Implementing Rules and Regulations
WIF
wind importance factor
ISO
International Organization for Standardization
ITB
Instructions to Bidders
ITPB
Instructions to Prospective Bidders
kg
kilogram/s
kpa
kilopascals
kph
kilometers per hour
LD
liquidated damages
m
meter/s
m3
cubic meter/s
MDP
main distribution panel
mg
milligram/s
mm
millimeter/s
mpa
megapascal/s
mpm
meters per minute
m/s
meters per second
MPSS
Minimum Performance Standards and Specifications
MSDS
material safety data sheet
NBCP
National Building Code of the Philippines
NFPA
National Fire Protection Association
NGL
natural grade line
NSCP
National Structural Code of the Philippines
NTP
Notice to Proceed
OSHS
Occupational Safety and Health Service
P.D.
Presidential Decree
PCBs
polychlorinated biphenyls
PCM
Project or Construction Manager
PEC
Philippine Electrical Code
PMC
Philippine Mechanical Code
PNS
Philippine National Standards
PRLs
professional regulatory laws
psf
pounds per square foot
psi
pounds per square inch
PVC
polyvinyl chloride
R.A.
Republic Act (national law)
RC
reinforced concrete
D-iii
D-iv
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
D.1
Purpose
The purpose of these Minimum Performance Standards and Specifications (MPSS) is
to:


D.1.1
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Establish the minimum requirements that the Builder must conform w ith in the
design and construction of new Public Buildings to be sited at their respective
PROJECT SITES (the ‘Project’).
Create certainty for both the Procuring Agency and the Builder in the standards of
performance expected of the Builder.
The Builder is the winning Bidder i.e. Designer and/or Constructor (the ‘Builder’)
under the Agreement (the ‘Agreement’). This MPSS and its Annexes form part of the
Agreement and the Builder is required to conform with all the MPSS provisions.





Architecture and R.A. No. 10587 for Environmental Planning (the last 4 only as
applicable), etc. and their derivative regulations]
R.A. No. 4566, the 1965 Contractor’s Licensing Law, implemented by the DTI
R.A. No. 8293, The 1997 Intellectual Property Code of the Philippines,
implemented by the DTI
R.A. No. 386, the New Civil Code of the Philippines (1949), particularly the civil
liability provisions under its Art. 1723
E.O. No. 1008, the Law on Construction Arbitration, implemented by the DTI
R.A. No. 9285, The Alternative Dispute Resolution (ADR) Act of 2004, its IRR and
Special Rules of Court on ADR, promulgated by the Supreme Court (SC) and
denominated as A.M. No. 07-11-08-SC
Other Documents for use as Reference for the Procurement Effort
The other key documents that shall primarily govern the procurement effort are:


D.1.2
the MPSS
Unless otherwise specified in the ITB and these MPSS, all information contained in the
ITB, these MPSS, and the Agreement supersede any information supplied in the
Information Memorandum (IM) and previous versions of the MPSS.
Governing Laws and Regulations for the Procurement Effort






D-1
the Instructions to Bidders (ITB)
R.A. No. 9184, the Government Procurement Reform Act (GPRA) and its latest
implementing rules and regulations (IRR)
R.A. No. 6957, as amended by R.A. No. 7718, the Build-Operate-Transfer (BOT)
Law and its latest IRR
P.D. No. 1096, the 1977 National Building Code of the Philippines (NBCP), its 2004
Revised IRR, duly promulgated by the DPWH and its various Referral Codes (RCs),
mostly official executive issuances or self-regulatory documents in their latest
versions [RCs such as valid and subsisting laws e.g. the Water and Sanitation
Codes (P.D. Nos. 1067 & 856) and the 2010 (or latest) edition of the National
Structural Code of the Philippines/ NSCP], respectively, etc.
R.A. No. 9514, the 2008 Fire Code of the Philippines (FCP) and its 2009 IRR, duly
promulgated by the DILG
B.P. Blg. 344, The Law to Enhance the Mobility of Disabled Persons and its IRR/
Annex as well as the applicable provisions of R.A. No. 7277, otherwise known as
The Magna Carta for Disabled Persons
the various professional regulatory laws [PRLs, e.g. R.A. No. 9266 in the case of
State-registered and licensed architects/ RLAs, R.A. No. 544, as amended by R.A.
No. 1582 for registered and licensed civil engineers/ RLCEs, R.A. No. 1364 for
Sanitary Engineering, R.A. No. 1378 for Master Plumbing, R.A. No. 8560 for
Geodetic Engineering, R.A. No. 4209 for Geology, R.A. No. 7920 for Electrical
Engineering, R.A. No. 8495 for Mechanical Engineering, R.A. No. 9292 for
Electronics and Communications Engineering, R.A. No. 9053 for Landscape
D-2
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
D.2
Design
D.2.1
Scope of Design Services
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures

Under the Agreement, the Builder shall prepare the Detailed Architecture and
Engineering Design (DAED) during the Pre-Construction Stage of the Contract Package
and Builder shall also submit its DAED to the Independent Consultant (IC) for review
and concurrence, whereby the IC shall be procured through the Procuring Agency’s
regular procurement program under R.A. No. 9184, the Government Procurement
Reform Act (GPRA) of 2003 and its latest IRR, well before the submission of the DAED.

The Builder shall prepare the DAED (a) based on its Conceptual Architectural and
Engineering Design (CAED) submitted in the Technical Proposal which is part of its
Bid, and (b) in accordance with these MPSS, as shown in Figure D-1 hereafter.
Figure D-1
Scope of Design




D.2.2
D.2.2.1
The DAED, which the Builder shall prepare and submit to the Project and/or
Construction Manager (PCM) or Independent Consultant (IC) for review and
concurrence, shall cover the following components and outputs:
Design Deliverables
The DAED shall include the following outputs which shall all conform to the MPSS for
Design, and provide a level of detail that will enable quantities to be estimated up to
the plus/ minus five percent (+5%) of the final quantities. The outputs shall be
transmitted using international paper/ sheet/ board sizes (i.e. A4 and A3 page size or
A2, A1 and A0 sheet size).

Description of the proposed technology and materials e.g. use of pre-fabricated
components and/ or conventional built-on-site technology; use of concrete/ steel/
fiber cement/ other materials, etc. (A4 page size).
Detailed/ technical specifications of materials and workmanship. As applicable,
these shall include the certificate of accreditation from the Department of Public
Works and Highways (DPWH) Bureau of Research and Standards (BRS) on the
acceptance of new materials/ technology or of equivalencies in materials for use
in the Project. (A4 and/or A3 page size).
Proof of structural quality and integrity of a completed building, particularly for
projects which used new materials/ technologies. (A4 and/or A3 page size).
Detailed architectural and engineering design (DAED) analyses and computations.
(A4 and/or A3 page size).
Quantity and cost estimates for the buildings/ structures/ grounds i.e. BoQ and
DCE. (A4 and/or A3 page size).
Detailed Construction Management Plan (DCMP) including Construction Schedule.
(A4 or A3 page size and/or A2 sheet size).
Supporting data:
- (1) Simple longitudinal and cross sectional profiles of the ITSP site;
- Geotechnical investigation report (as applicable)/ geological information
report; and
Components and Outputs of Detailed Architecture and Engineering Design
(DAED) by Builder
The DAED shall cover the pertinent Public Buildings as defined by the Procuring
Agency.
D-3

The Builder’s CAED shall form part of the MPSS. The CAED, together with the MPSS
provisions on Construction shall govern the actual construction of the Contract
Package to be undertaken by the Builder.
DAED plans, elevations, cross-sections and interior/ exterior perspectives of the
Public Buildings/ Structures at a scale of 1:100 meters (m) or as applicable,
distinguishing between the various building components i.e. architectural,
engineering and allied works [architectural interiors (AI), interior design (as
needed), furniture design, landscape architecture, etc.] and noting the vastly
different site characteristics and existing/ potential hazards to development and
continued use/ occupancy. For the structural design, sufficiently detailed
information is required for the proposed substructure (i.e. foundation and ground
floor slab) and the superstructure. For AI, material/ sample and color boards are
required for the key public areas of the Project. (A2, A1 and/ or A0 sheet size).
D.2.2.2
- Building drainage design report. (A4 and/or A3 page size)
Property Development Component
Should a property development component be introduced as a component of the
Public Building/ Complex, the same requirements shall be required for submission, in
addition to:



A market study
Business plan. (A4 and/or A3 page size)
Furniture/ Furnishings, Fixtures & Equipment (FFFE) Component
The DAED for FFFE shall include the following outputs based on the MPSS for FFFE:


Detailed Layouts, Plans and Design of FFFE, showing their dimensions;
perspectives, plans, and elevations at a scale of 1:10 m, with details at a scale of
1:5 m; materials specifications; and other basic properties. (A4 and/or A3 page
size).
Detailed Cost Estimate (DCE). (A4 and/or A3 page size).
D-4
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
D.2.3
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Governing Codes and Specifications



The minimum height of the fixed louver or transom window above the operable
windows shall be at 300 mm i.e. measured from the glass part of the window.
The DAED for the Project shall be governed by the following Design Codes and
Specifications.
P. D. No. 1096, the 1977 National Building Code of the Philippines (NBCP), its
2004 Revised IRR and its various Referral Codes (RCs) such as R.A. No. 9514, the
2008 Fire Code of the Philippines (FCP), P.D. No. 1067, the Water Code of the
Philippines, P.D. No. 856, the Sanitation Code of the Philippines, Batas Pambansa
(B.P.) No. 344, the Law to Enhance the Mobility of Disabled Persons and its IRR/
Annexes, and by executive issuances and/or self-regulatory documents such as
the National Structural Code of the Philippines (NSCP), Volume I, 2010, Philippine
Electrical Code (PEC), 2009, Revised National Plumbing Code, the 2000
Architectural Code of the Philippines (ACP), etc..
Interior window panels (if introduced along passage-ways such as corridors), when
opened, must NOT pose an obstruction nor a physical threat along such passage-ways.
D.2.4.2
The door swing-out should be 180 degrees for rooms/ enclosed spaces with 30 or
more occupants.
US Standards:
The door leaf must be at least 900 mm in clear width and 2,100 mm in clear height.
The doors MUST withstand normal wear and tear and shall be provided with keyed
lever-type locksets.
- American Concrete Institute (ACI), as applicable
PVC doors shall NOT be used. If doors made of materials other than wood are to be
introduced by the Builder, these MUST be fire-rated and thoroughly tested for toxicity
(normal and burning conditions) and shall have the prior acceptance/ approval by the
DPWH BRS.
- American Iron and Steel Institute (AISI), as applicable
- American Welding Society (AWS), as applicable

D.2.4
D.2.4.1
- American Society for Testing and Materials (ASTM), as applicable
Philippine National Standards or PNS Appendix G of PEC1 – 2009
R.A. No. 6716 on rainwater collection system
Architectural Standards
Window sills must NOT be lower than 600 millimeters (mm) NOR higher than 900
mm from the finished floor line (FFL) i.e. measured from the glass part of the window.
Toilet doors shall be of framed plywood flush or solid door construction with jamb
material [preferably of local (non-banned) or imported hardwood] duly accepted/
approved by the DPWH BRS, and painted or stained as appropriate.
Floor
The finished floor must be of non-skid finish.
The finished floor line (FFL) at enclosed spaces should be higher than the passage-way
(common area) FFL by a maximum of 25 mm.
The first level FFL elevation of the passage-way (common area) MUST be above the
one hundred (100)-year flood level to be identified by the Builder.
Windows
The total area of window openings must be at least equal to 10.0 square meters (sqm)
of the enclosed space being served (or better) to provide for natural ventilation and
illumination. Windows MUST allow the entry of daylight even if closed. If firewalls are
introduced, there shall be NO operable/ non-operable windows on such firewalls.
However, fire-rated glass blocks or light and ventilation wells may be allowed on such
firewalls, in full accordance with the NBCP and FCP, whichever is more stringent.
D-5
D.2.4.3
The architectural quality of the Public Building/ Structure MUST be in full accordance
with law, specifically with P.D. No. 1096 (1977 NBCP) and its 2004 Revised IRR, with
the applicable portions of the 2000 ACP, and as described in the architectural sections
of the Technical Specifications.
architectural documents i.e. architectural
perspectives, plans, designs, drawings, computations and like deliverables by the
Builder MUST be in full compliance with R.A. No. 9266 (The Architecture Act of 2004)
and its 2004 IRR, as well as with the applicable sections of the Development
Guidelines and Design Guidance (DGDG) for the PROJECT.
Windows must be of the transparent or translucent types, and both operable and/or
fixed/ non-operable as applicable.
Doors
There shall be at least two (2) doors for every room/ enclosed space for thirty (30) or
more occupants.
- American Institute of Steel Construction (AISC), as applicable

The window frames MUST be sturdy enough to withstand vandalism.
D.2.4.4
A ramp MUST be provided with a maximum gradient of 1:12 in compliance with the
Accessibility Law (B.P. Blg. 344) and properly labelled with the international symbol
of access, either formed of concrete/ cement or metal.
Suspended Ceiling and Ceiling Cavity
The clear height of enclosed spaces, reckoned from FFL to finished ceiling line (FCL)
MUST be at least 2.7 m.
Maintenance access to the ceiling cavity (if provided) MUST be primarily through the
passage-way (common area).
The ceiling height of the toilets may be lower than 2.7 m, only for as long as the same
still fully satisfies the minimum requirements under P.D. No. 1096, the 1977 NBCP.
D-6
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
D.2.4.5
Roof and Roof Cavity
The Builder’s choice of roofing material MUST be adequately protected from rust/
oxidation, salt air, acid rain or other sources and forms of corrosion and leaks. If of
metal, the roofing sheets MUST be of the thickest material commercially available in
the Philippines and amply protected from the elements.
While the Procuring Agency shall undertake the requisite periodic maintenance
regimen on an annual basis, the Builder MUST warrant the performance and condition
of the entire roofing system and its adjunct drainage system and shall undertake the
requisite repair/s within the minimum Constructor’s Liability period (reckoned from
the Procuring Agency issuance of the Certificate of Completion) for any damage to the
Public Building that may arise from faulty design or construction.
D.2.4.6
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
D.2.4.9
Artificial ventilation inside each room/ enclosed space MUST be supplied in full
accordance with the NBCP and/or with the MCP, whichever is more stringent.
D.2.4.10
Partitions, if introduced, MUST be fire-rated, and must be from the top of the
structural floor to the bottom (soffit) of the upper floor suspended slab.
D.2.4.7
D.2.4.8
D-7
Information Boards
The Public Buildings MUST be provided with built-in information boards, of various
types and materials, electronic or illuminated or non-electronic/ non-illuminated, of
the appropriate widths, heights and thicknesses, with mounting heights and material
and finish specifications as per applicable international standards.
The roof cavity (if introduced) MUST be naturally ventilated and pest-proofed.
Whenever applicable, the ceiling cavity for the regular floors (only if introduced), shall
be naturally ventilated and pest-proofed.
Grounds Development and Civil Works
The land area enveloping the Public Building shall be treated as part of the Project
since the same constitutes the building grounds in which pedestrian/ PWD access
systems and the wastewater lines, roadways/ streets, drainage/ flood protection
provisions and related civil works are situated above and below the surface
respectively. These areas shall be cleared and made safe for use.
Circulation and Emergency Egress: Corridors (Single-Load), Main Staircases, Service/
Emergency Egress Staircases, Fire Exit Ladders and Railings
To fully comply with the FCP, the minimum passage-way (common area) clear width
MUST be 2.44 m for the Public Buildings. All staircases MUST have a minimum clear
flight width of 1.83 m (3.66 m total clear staircase width). The clear flight width for
the service staircase/ emergency egress/ fire exit MUST be from 1.22 m to 1.83 m
(2.44 or 3.66 m total clear staircase width). The fire exit ladders MUST have a
minimum clear width of 0.80 m. All stair treads that shall get in contact with water
MUST provide all weather traction, particularly if the treads are wet and shall have a
sloped finished for easy drainage. The stair nosings shall be of sturdy metal and
round-edged, or of better design, to prevent injury during egress occasioned by
extreme/ emergency events. The staircase, corridor and ramp railings shall be of
metal pipe construction and securely anchored to the staircase, hallway and ramp.
Ventilation
Natural ventilation shall be primarily supplied for some rooms (which are not
artificially ventilated) through operable windows. However, whenever such windows
are fully closed, the source of natural ventilation may be through fixed louvers above
or beside the operable windows.
The minimum horizontal clear length of eaves (only if introduced, including exterior
gutter width) shall be: front = 2.438 meters (m); rear = 2.438 m; and sides = 1.829 m
i.e. NO interior gutter shall be introduced in the Public Buildings. Maintenance access
to the roof cavity (only if introduced) must be through the passage-way (common
area).
Partitions
The ceiling (suspended ceiling, suspended slab soffit and stair slab soffit), if exposed
shall be flat white while the roof, if of metal construction, MUST be colored light to
maximize unwanted light and heat reflectance. The paints/ coloring materials MUST
maintain their quality based on applicable Procuring Agency and/or DPWH standards
for at least five (5) years.
D.2.5
The civil works plan and design for the Project grounds MUST fully conform to the
DPWH Standard Specifications for Public Works Structures, Volume III, 1995 (Blue
Book).
Structural Standards
The structural design MUST be in accordance with P.D. No. 1096, the 1977 NBCP and
its 2004 Revised IRR, and specifically with the latest edition of the National Structural
Code of the Philippines (NSCP), Volume 1, 2010 (or later).
Classification of Structure: In accordance with the NSCP, the Public Buildings/
Structures shall be designed for the classification, based on the nature of occupancy, of
‘Essential Facilities.’
Wind Load: The Public Buildings/ Structures, their roofing and walls shall be
designed to withstand a minimum wind speed of 250.0 kilometers per hour (kph).
Painting
A Wind Importance Factor of 1.15, based on the NSCP, shall be used as generic
reference.
Where applicable, metal, wood, and plastic components MUST be coated with enamel
paint, with color subject to Procuring Agency approval. Masonry wall components
MUST be coated with latex paint, with topcoat color subject to official Procuring
Agency approval.
Seismic Load: The Public Buildings/ Structures shall be designed to withstand
earthquakes for Seismic Zone 4 with a corresponding Seismic Zone Factor of 0.40, as
specified in the NSCP.
The structure should be fully sealed against rainwater intrusion during typhoons and
heavy rains to protect sensitive materials and equipment. All doors and windows
MUST be fully sealed against strong vertical and lateral rains.
D-8
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
A Seismic Importance Factor of 1.50 shall be used as generic reference. Builders are
advised to factor in the effect of the nearby fault lines.
Live Loads: The minimum occupancy or live loads shown in Table D-1 shall be used in
the design.
Table D-1
D.2.6
Electrical Standards
D.2.6.1
Roughing-ins

- Service entrance conduit shall be made of intermediate metallic conduit (IMC).
Underground runs shall be encased in concrete envelope or reinforced concrete
envelope when crossing a roadway. Ends of conduits shall be provided with a
sealing compound.
Live Loads
Structure Part
Live Load
General Activity Level
Car Parking Level
Shop Level
- Exposed service entrance conduits shall be painted with epoxy primer in three
(3) coats application.
1.9 kpa
Toilets
Hallways/ Stairs
4.8 kpa
Deck Roof Level
1.0 kpa
- Conduits shall be properly reamed.
Note: kpa = kilopascals

Design Life: The structure shall have a design life of at least fifty (50) years.
Branch circuit conduits, boxes, fittings and supports shall run parallel to walls,
columns and beams of the building.
- Polyvinyl Chloride (PVC) solvent shall be applied on all PVC pipe joints/
connections.
- End bells shall be used at the end of PVC pipes and locknut and bushing shall be
used for metallic conduit on all boxes and gutters termination.
Consistent with law and with industry practice, the Builder’s designers and builders
shall assume the full professional responsibility and civil liability for the foundation
and structural design, supervision and construction of the Public Buildings/
Structures. In the case of structural designers who are foreign nationals, the Philippine
civil/ structural engineer affixing his/ her signature and dry seal on the structural
plans, designs and computations (submitted for building permit application) shall
solely assume the same. As such, the Procuring Agency shall NOT accept any form of
waiver anent the attached professional responsibility or civil liability over the
foundation/ structural design of the Project.



Wall Vibration: Walls must NOT unduly vibrate due to impact caused by any part of
an adult human body and must NEITHER be dented NOR punctured by deliberate
punches or kicks by adult humans.
Rib-type or double tee suspended slab soffits are acceptable but subject to the PCM or
IC acceptance of the quality of their structural connections and finish.
- The service entrance shall be at least 1.60 m above the natural grade line.
- Metal boxes, gutters, supports and fittings shall be painted with epoxy primer
in three (3) coats prior to installation.
Building Foundation: The foundation shall be designed for an allowable soil bearing
pressure of 96 kpa (2,000 pounds per square foot or psf). Consistent with best
practices, the Builder MUST undertake the prior appropriate studies/ investigations
for use as basis/ bases for the foundation and structural design of the Public
Buildings/ Structures.
Suspended Slabs as Sub-floors: Sub-floors shall only be of suspended concrete slabs
(which are either cast-on-site/ cast in situ concrete or pre-cast concrete). Sub-floor
materials that are highly flammable, that do NOT uphold the fire integrity among the
floors, that may contain formaldehydes or other potentially harmful substances, that
conducts/ transfers radiant heat and which do NOT possess positive acoustical
properties are not considered the equivalent of a suspended concrete slab and must
NOT be used for the Public Building/ Structure.
Service Entrance

D.2.6.2
- Branch circuit conduits shall be either metallic or non-metallic as applicable.
Ceiling-mounted lighting fixtures: Flexible metallic tubing shall be used as drop
pipe from a junction box to a lighting fixture.
In-sight disconnecting means: Watertight type straight or angle connectors shall
be used from pumps, condensing units and other equipment that will be in
possible contact with water or rain.
Centralized panelling: Breaker and wire gutter shall be used for proper
arrangement of main distribution panel (MDP).
Stub-out conduits for spares: 15 mm diameter PVC or IMC pipes shall be provided
as stub-out conduits at different panel boards as per schedule of loads. Ends of
stub-out conduits shall be threaded and capped.
Wires and Wiring Devices
Wires shall be properly designed in accordance with Article 3.10 and the grounding
system shall conform to Article 2.50 of the PH Electrical Code (PEC).
D.2.6.3
Wiring devices must be of modern type and approved for both location and purpose.
Lighting and Fixtures
Each room/ enclosed space must be provided with a lighting product(s) that can
produce 400 lux or better at the tabletop/ countertop level.
Duplex convenience outlets (COs) of the grounding type must be provided for all
rooms/ enclosed spaces.
D-9
D-10
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
D.2.7
The hallways must be provided with a lighting product(s) that can produce 5,000
lumens or better.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
D.2.9.1
For structural members, minimum compressive strength of 20.7 megapascals (mpa)
(3,000 pounds per square inch or psi).
Sanitary and Plumbing Standards
For non-structural members minimum compressive strength of concrete shall be 17
mpa (2,500 psi).
Waste and vent line piping system: The drain, waste and vent line piping system
must be according to American Society for Testing and Materials (ASTM) D-2729, ISO
4435 and ISO 3633.
At the very minimum, reinforcing bars shall be ASTM A706 with a minimum yield
strength, fy, of 413 mpa for 16 mm diameter and larger, and 275 mpa (33,000 psi) for
12-mm diameter and smaller. Alternately, ASTM 615 can be used subject to the
conditions specified in the NSCP, as follows:
Waterline piping system: The system must be according to E DIN1988 for
Polypropylene Random Copolymer (PP-R) type 3 pipe and ASTM A53/ A53M. The
system must provide for a waterline service entrance.

Plumbing Fixtures: These must be according to American National Standards
Institute (ANSI)/ American Society of Mechanical Engineers (ASME), A112.19.4m,
A112.19.3, A112.19.5.
Drainage system: The storm drainage system must be sized according to the rainfall
intensities, slope, and roof areas of the building. Provision shall be made for the future
installation of rainwater collection system in compliance with R.A. No. 6716 ‘An Act
Providing for the Construction of Water Wells, Rainwater Collectors, Development of
Springs and Rehabilitation of Existing Water Wells in all Barangays in the Philippines’.
For the BUILDING Project, only provision/s for connections to future rainwater
collectors, consistent with DPWH design standards are required of the Builder. These
provisions must be reflected in all CAEDs and DAEDs of the Public Buildings.
D.2.8
Septic vault: All concrete septic tanks shall be protected from corrosion by coating
with an approved bituminous coat or by other acceptable means.
Toilets
The Toilets shall be properly ventilated and provided with running water through a
piped water supply system. The supply of running water to the toilets shall be the
responsibility of the Builder.
D.2.9
The specific types and numbers of fixtures shall depend on full Builder compliances
with the applicable provisions of the NBCP and the Sanitation Code of the PH (and its
IRR and with the pertinent issuances of the DoH), whichever is more stringent.
Additionally, considerations of gender sensitivity e.g. breastfeeding stations, diaper
changing stations, sanitary product dispensers, etc. shall be factored in.
Materials
At the very minimum, all construction materials for the Project MUST conform to the
DPWH Standard Specifications for Public Works Structures, Volume III, 1995 (Blue
Book). New materials which are NOT covered by the Blue Book, however, MUST pass
the requirements of the Product Accreditation Scheme prescribed under DPWH
Department Order No. 189, series of 2002, and be accredited by the DPWH before
these are used in the Project.
D-11
Reinforced Concrete

D.2.9.2
D.2.9.3
The actual yield strength based on mill tests does NOT exceed fy by more than 125
mpa.
The ratio of the actual tensile strength to the actual yield strength is NOT less than
1.25.
Structural Steel
This shall be ASTM A36 with a minimum yield strength, fy, 248 mpa (36,000 psi). All
structural steel works shall be painted with red oxide primer and shall be final coated
with aluminum silver paint.
Protection from Heat
Air Supply: Under applicable conditions, clean fresh air shall be supplied to enclosed
spaces at an average rate of NOT less than 20 to 40 cubic meters (700 to 1400 cu.ft.)
an hour per occupant, or at such a rate as to effect a complete change of air a number
of times per hour varying from four (4) for sedentary occupants to eight (8) for active
occupants.
Where an adequate supply of fresh air cannot be obtained by natural ventilation or
where it is difficult to get the desired amount of air at the center of the workroom
without creating uncomfortable drafts near inlets, mechanical ventilation devices that
are capable of generating fresh air (and NOT merely re-circulating air inside a room or
other confined spaces such as toilets), shall be provided.
Air Movement: The air movement in enclosed spaces shall be arranged such that the
occupants are NOT subjected to objectionable drafts. The air velocity shall NOT fall
below 15 meters per minute during the rainy season and 45 meters per minute during
the summer season.
The rooms and component materials MUST provide for a suitable inside room
temperature compliant with safety and health standards on air temperature, humidity
and air movement.
Provision shall be made to control radiant heat from roofing by installing ceilings/
ceiling cavities, which may be provided with fire retardant and thermal insulation
materials.
Insulating material and ventilation inside a room should reduce infiltration of too
much radiant and convective heat and should result in the room/ enclosed space
temperature (measured at the center of the room) being at least one degree Celsius (1
oC) lower than the outside temperature.
D-12
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
The air velocity in enclosed rooms shall be from 0.25 m/s to 0.75 m/s based on the
requirements of the Occupational Safety and Health Service/ OSHS of the Department
of Labor and Employment (DoLE).
D.2.9.4
D.2.9.5
D.2.9.6
D.2.9.7
Illumination falling at countertop height MUST NOT be less than 400 lux taken with
combined artificial and natural lighting.
Resistance to Termites
Where applicable, the Public Building/ Structure MUST be resistant to termites for at
least five (5) years.
Protection from Corrosion
Where applicable, the Public Building/ Structure MUST be protected from corrosion/
rust up to at least five (5) years.
Fire Protection
Fire protection requirements for the Public Building/ Structure shall mainly be as per
R.A. No. 9514, the 2008 Fire Code of the Philippines (FCP) and its 2009 (or later) IRR.
However, the Builder must always check which of the following is the most stringent:
1) P.D. No. 1096, the 1977 National Building Code of the Philippines (NBCP) and its
2004 Revised IRR; 2) R.A. No. 9514, the 2008 FCP and its 2009 IRR; 3) the National
Fire Protection Association (NFPA) codes, standards or related issuances; or 4) other
applicable local fire safety standards. The most stringent rule shall always be applied
for the Project.
Noise Level Limit
The sound transmission class/ noise reduction rating of the Public Building and its
component materials, including walls partition and floor slabs, MUST reduce noise
level such that it will comply with accepted standards on noise reduction.
Appropriate sound-absorbing or sound insulation material MUST be used on walls
and partitions to reduce sound transmission inside the rooms/ enclosed spaces.
Acoustic materials, finishes or treatments shall be used at interior walls, ceilings and
ceiling cavities in the event of reverberation/ echoing of sound inside lower floor
rooms/ enclosed spaces.
Pertinent occupational safety and health standards such as the permissible noise
exposure limit, threshold limit value and other applicable occupational and safety
standards MUST be complied during the construction of the Public Building.
Acoustic material or finish used should offer reduction of noise and noise level which
should NOT exceed 55 dB (A) measured in an unoccupied classroom (to include
ambient noise) and MUST comply with ASHRAE provisions on indoor air quality.
Ambient noise MUST necessarily exclude intermittent heavy noise sources such as
passing vehicles e.g. airplanes, trains, tricycles, old trucks/ buses and the like.
D-13
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
D.2.9.8
Protection from Toxicity
Enclosed spaces must be designed in such a way that their locations are far from
sources of noxious elements such as paint, varnish, toilets, chemical storage and
garbage collection/ storage/ handling points.
The building and finishing material to be used like panel/ ceiling boards, paints,
varnish, etc. must NOT contain or emit any carcinogenic or toxic substances which
may pose risk on the health of occupants (such as asbestos, polychlorinated
biphenyls/ PCB, benzene and the like). A material safety data sheet (MSDS) detailing
the composition of the construction materials used, must be presented by the Builder
for joint OSHC/ DPWH/ Procuring Agency/ PCM or IC evaluation and possible OSHS
certification (on an absolute need basis).
Newly constructed rooms should be well ventilated prior to occupancy to purge and
remove the airborne contaminants trapped and emitted inside the rooms/ enclosed
spaces during painting, sanding, varnishing, etc. Purging of airborne contaminants and
ventilation of the rooms should be for at least one week or until such time that
discernible odor is gone. There should be NO toxic airborne contaminants prior to
building occupancy.
Adequate air movement and supply of fresh air should be provided via natural or
artificial means to dilute any contaminants, which may be emitted in the course of
occupancy.
The non-skid flooring should help prevent the accumulation of dust in small cracks
and crevices.
Based on US Environment Protection Agency Air Quality Standards, the dust
concentration for total dust particulates should NOT exceed 0.26 mg/m3, and for
respirable dust should NOT exceed 0.15 mg/ m3.
Rule 1076.03 Cleanliness: Dusts, gases, vapors, or mists generated and released in
work process shall be removed at the points of origin and NOT permitted to permeate
the atmosphere of the enclosed rooms/ spaces.
Rule 1093.07 Prevention of Dust Accumulation: In rooms where materials producing
flammable dusts are processed, handled and stored;


dusts shall be removed daily from floors, equipment and other horizontal surfaces,
preferably by means of appropriate vacuum apparatus; and
all fixtures, ledges, projections, bearings, sidewalks, ceilings and other parts shall
be cleaned and freed of dusts at least once a week.
Floors: Where practicable, floors or rooms in which harmful dust is liberated shall:


be smooth, impervious and easy to clean; and
NOT be covered with loose sheets, metal or other materials under which dust can
accumulate.
Resistance to water penetration: The structure shall be free from water leaks.
Relative Humidity (RH) Range: RH range shall be at 55% plus or minus 5%.
D-14
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
D.2.10
Other Standards
The set of FFFE items MUST harmonize, in terms of functionality and design, with the
intended use of the spaces at the Public Building (including the possible Property
Development Component/s).
D.2.11
FFFE materials may be wood or non-wood, resistant to termites (if of wood) for at
least two (2) years, and protected from rust for at least for five (5) years. They should
NOT contain or emit any carcinogenic or toxic substance. New materials must first be
certified by the Bureau of Product Standards (BPS) of the Department of Trade and
Industry (DTI).
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
D.3
Construction
D.3.1
Scope of Construction
D.3.2
The Builder shall undertake the Construction Works for the Contract Package as
described in the Information Memorandum.
Standards and Specifications for Construction
The construction of the Project shall be implemented according to the DAED prepared
by the Builder, as reviewed and concurred with by the Project or Construction
Manager (PCM) or by the Independent Consultant (IC).
Other Requirements
b. The Construction of the Project shall also comply with the MPSS for Construction
herein prescribed. The MPSS for Construction includes conformance to the provisions
pertaining to building under the DPWH Blue Book, Volume III.
Since the Builder will undertake Design-Build Services, the conduct of the soil
investigations and of the requisite environmental investigations, MUST all be
undertaken by the Builder on their account.
The Blue Book prescribes, among other things, the material requirements and
construction requirements for different items of work, including the tests to be
conducted during Construction by the Builder. The Blue Book incorporates provisions
of the ASTM and ACI, among others, pertaining to construction. Attention shall be
given to the relevant items of work in the following Parts of the Blue Book:
All conceptual through detailed architectural and engineering design (CAED to DAED)
plans, designs, drawings/ details, schedules, specifications, bill of quantities (BoQ),
detailed cost estimates (DCEs) and similar regulated professional practice documents
must be signed and dry-sealed by Filipino registered and licensed professionals
(RLPs) in full accordance with law e.g. only registered and licensed architects (RLAs)
shall prepare, sign and seal the pertinent architectural documents. The ‘As-Built’ plans
are to be transmitted to the Procuring Agency by the Builder at the completion of the
construction work for the Project.



During construction, the Project site must be protected by a 3.0 m tall temporary
perimeter enclosure, where the height shall be reckoned from either the natural or
finished grade line (NGL/ FGL). Such an enclosure should be of sturdy construction
such that it does NOT constitute a danger during extreme events e.g. storms,
earthquakes, fire, widespread civil disturbances, and similar occurrences.


The Builder MUST provide a certification that the parts and spares for all components
under the Contract Package shall be available to the Procuring Agency over a period of
at least ten (10) years after the completion of the Works under the Project.
D.3.3
Part A - Earthwork
Part B – Plain and Reinforced Concrete Works
Part C – Finishing
Part D – Electrical (and Electronics)
Part E – Sanitary/ Plumbing Works
For materials and technologies NOT covered by the Blue Book, or if the Builder
intends to use any new material/ technology which is NOT accredited by the DPWH
Bureau of Research and Standards (BRS), the Builder shall submit a certification from
a recognized foreign/ international institution to the effect that the new materials/
technology meets the Minimum Performance Standards and Specifications (MPSS) for
this Project and that the new materials/ technologies have been successfully used in
existing structures with proven integrity.
Detailed Construction Plan
The Builder shall prepare a Detailed Construction Plan (DCP) as part of the DAED that
it shall submit to the PCM or IC for review and concurrence. The DCP shall be based on
the preliminary Construction Plan submitted in the Technical Proposal of the Builder’s
Bid, as updated and detailed to fit the elements of the DAED. The DCP MUST identify
the procedures, processes and management systems that the Builder will apply to
ensure the implementation of the Construction Works in accordance with the
Agreement.
As a minimum, the DCP must define the following:

D-15
Construction organization and management structures for the Contract Package,
identifying key personnel and positions, Constructors, and sub-constructors.
D-16
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures






Construction methodology and procedures, including pre-fabrication if any.
Quality control and assurance system for all Works.
Construction schedule, milestones, and S-curve covering all Contract Package
components and Project site.
Major construction equipment and materials to be used.
Health, safety, and security program in accordance with Department Order No. 13,
series of 1998, of the Department of Labor and Employment (DoLE).
Measures and procedures for:
- Control and monitoring of the construction schedule as against actual
construction works;
- Supervision and monitoring of the quality control and assurance system for the
Works, including the integrity of tests conducted;
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures



- Survey and condition monitoring;
Strategies for:
Annexes for this MPSS follow.
Very Important Notes:


- Managing risks
- Obtaining all necessary approvals and permits from national and local
government authorities
D.3.4
- Details of records management and indexing protocols that will enable
referencing of all design and construction records to the Contract Package
components, work type and location
Test Requirements
The Builder shall undertake tests during construction in accordance with the
schedule of minimum testing requirements for items of work and materials covered
by the Blue Book.
D.3.5
If any new Construction materials proposed by the Builder are NOT covered by the
Blue Book, these materials shall first pass the evaluation and accreditation system of
the DPWH BRS, certified by the PCM or IC, and approved by the Procuring Agency,
before the new materials are used in the Project.
The completed Project can be safely and reliably placed into normal use and
occupancy by the competent authorities and end-users.
The Builder MUST submit (1) the As-Built Drawings, (2) an Asset Register to include a
description of all assets constructed, and (3) the Construction Completion Report for
the Project under the Contract Package, to the Procuring Agency NOT later than two
(2) months after the issuance of the Certificate of Completion for the Project.
- Monthly updating of the Construction Plan and monthly progress reports;
- Development and approval of Construction documentation; and
All parts of the Project have been completed in accordance with the DAED, as
certified by the PCM or IC, and with the MPSS for Construction, including the
rectification of all defects.


This procurement effort involves both design preparation and construction
delivery by the Builder being sought. The Builder is expected to prepare both its
Conceptual Architectural and Engineering Design (CAED) and Detailed
Architectural and Engineering Design (DAED) for the Public Building (the
‘Project’).
In the event of a possible conflict or inconsistency between the content of these
MPSS and its future Annexes or between such future MPSS Annexes, the Builder
must bring the matter to the attention of the Procuring Agency and its Project or
Construction Manager (PCM) or Independent Consultant (IC) at the soonest time
possible.
Further, for both bid preparation and design/ construction purposes, the Builder
is instructed to always adopt the provision that shall result in the most
appropriate, the most responsive and the most complete design/ construction/
operation/ maintenance solution that shall be consistent with the best local and
international industry practices for design and construction.
On matters of compliance with these MPSS and its future Annexes, the PCM or IC
shall be the designated sole authority for design review, construction assessment
and initial alternative dispute resolution (ADR) for design and construction issues
arising from differing interpretations of the MPSS.
Completion of Construction
The IC shall be required to determine and certify that the Builder has fully complied
with the following requirements for the completion of Construction and, if so, shall
notify the Procuring Agency, which shall then issue the Certificate of Completion to
the Builder in accordance with the Agreement:

D-17
All Tests for Construction comply with the pertinent provisions of the Blue Book
and other test requirements of the MPSS for Construction.
D-18
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Contents
Annex E
Development Guidelines and Design
Guidance (DGDG) for Buildings and their
Sites / Grounds
Important Note: This brief presents the potentially optimum development guidelines
and design guidance (DGDG) allowed under existing national and local Philippine (PH)
laws for the buildings and the properties/ sites/ grounds under consideration.
Property Owners are at liberty to scale down the proposed development to the
desired/ required/ affordable limit.
This deliverable offers suggestions as to what to look for while reviewing the physical
planning, design and development of various building and sites/ grounds project
components.
E.1
INTRODUCTION..................................................................................................................................... 1
E.1.1
INTENT OF THE DEVELOPMENT GUIDELINES ................................................................................... 1
E.1.2
DEVELOPMENT AND COMMUNITY PHILOSOPHY .............................................................................. 1
E.2
DEVELOPMENT GUIDELINES FOR PROPOSED BUILDINGS ............................................................... 2
E.2.1
LAND USE STANDARDS ........................................................................................................................ 2
E.2.2
GENERAL USE AND DEVELOPMENT GUIDELINES .............................................................................. 5
E.2.3
ROAD RIGHTS-OF-WAY (RROWS)/ STREETS AND LEGAL EASEMENTS .......................................... 8
E.2.4
MISCELLANEOUS GUIDELINES ............................................................................................................12
E.2.4.1
ADMINISTRATION ...............................................................................................................................13
E.2.4.2
UPDATE AND REVISION OF THESE DGDG (ON A NEED BASIS) ........................................................14
E.3
PHYSICAL PLANNING GUIDANCE........................................................................................................15
E.3.1
SITE DEVELOPMENT GUIDANCE ........................................................................................................15
E.3.2
CIVIL WORKS GUIDANCE ....................................................................................................................18
E.3.3
URBAN DESIGN GUIDANCE .................................................................................................................21
E.4
DESIGN/ POST-DESIGN GUIDANCE ....................................................................................................24
E.4.1
DETAILED DESIGN PROCESS...............................................................................................................24
E.4.2
POST-DESIGN PROCESS .......................................................................................................................28
E.4.3
ARCHITECTURAL GUIDANCE ..............................................................................................................28
E.4.4
SUGGESTED ARCHITECTURAL DESIGN OBJECTIVES........................................................................30
E.4.5
ARCHITECTURAL DESIGN CONCEPTS ................................................................................................31
E.4.6
SUGGESTED ARCHITECTURAL PLANNING AND DESIGN CRITERIA ................................................32
E.4.7
OTHER ARCHITECTURAL CONSIDERATIONS....................................................................................34
E.4.8
LANDSCAPE ARCHITECTURE GUIDANCE ..........................................................................................36
E.5
ENVIRONMENTAL GUIDANCE .............................................................................................................40
E.6
NON-MOBILE BILLBOARDS (NMBS)/ ELECTRONIC DISPLAYS AND SIGNAGES .............................59
E.6.1
REGULATION OF NMBS/ ELECTRONIC DISPLAYS WITHIN A LGU ..................................................63
E-i
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Tables, Figures and Equations
Acronyms and Abbreviations
Table E-1
Term
Definition
AFSU
amenities/ facilities/ services/ utilities
AI
Architectural Interiors
AMBF
Allowable Maximum Building Footprint
B.P.
Batas Pambansa (State law)
BHL
Building Height Limit
BoD
Bureau of Design
BOD
Bio-Oxygen Demand
Table E-2
Table E-3
Table E-4
Table E-5
Table E-6
Table E-7
Table E-8
Figure E-1
E-ii
Setbacks for Commercial and Industrial Buildings (applicable to BUILDINGS)……..………………2
Reference Table of Maximum Allowable PSO, Maximum Allowable ISA, the MACA, the
Minimum USA and the TOSL for a PUD ...............................................................................................................3
Minimum Requirements for Air Changes ...........................................................................................................6
Range of Required Sidewalk and Planting Strip Widths (total at both sides of RROW) by
RROW Width ................................................................................................................................................................. 11
Minimum Planting Strip Widths by RROW Width ....................................................................................... 11
Example of the Application of the Basic Sustainable Development Controls under P.D. No.
BOT
Build-Operate-Transfer
1096 (NBCP) ................................................................................................................................................................. 51
CBB
Wood-Wool Cement-Bonded Board
CDMP
Comprehensive Development Master Plan
for a Typical Public Building .................................................................................................................................. 55
cum
cubic meter
DGDG
Development Guidelines and Design Guidance
DoE
Department of Energy
DoLE
Department of Labor & Employment
DPWH
Department of Public Works & Highways
EMoP
Environmental Monitoring Program
EMP
Environmental Management Plan
EMS
Environmental Management Standards
EPI
Environmental Performance Indicators
FCB
Fiber Cement Board
FCL
Finished Ceiling Line
FFL
Finished Floor Line
FGL
Finished Grade Line
FLAR
floor to lot area ratio (same as FAR/ floor area ratio)
GFA
Gross Floor Area
HLURB
Housing and Land Use Regulatory Board
IRR
Implementing Rules And Regulations
LGU
Local Government Unit
m
meter
mm
millimeter
MVB
Maximum Volume of Building
MDP
Master Development Plan
MPSS
Minimum Performance Standards And Specifications
Reviewer
DPWH BoD
NBCP
National Building Code of the Philippines
NGL
Natural Grade Line
NMB
Non-Mobile Billboard
OFB
Outermost Face of Building
OSR
Open Space Requirement
P.D.
Presidential Decree
PH
Philippine/s
Embodied Energy Levels of the Construction and Finishing Materials Specified and Used
Initially Calculated Carbon Footprint for a Typical Low-Rise Public Building ............................... 58
STANDARD FORM (Type A0, A1, A2 and A3) FOR BUILDING PLANS/ CONSTRUCTION
DRAWINGS Figure III.1.(of the 2004 Revised IRR of the 1977 NBCP) ............................................... 27
E-iii
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Glossary
Term
Definition
ppm
parts per million
PPP
Public-Private Partnership
Term
Definition
PRC
Professional Regulation Commission
GFA
PSO
percentage of site occupancy
PUD
planned unit development
The total floor space within the perimeter of the permanent external building walls (inclusive of the additional
building/ enclosed area/s); areas such as open/ semi-covered parking, walks/ covered walks, courts, pools,
ponds/ grotto, generator shed/ pump room/s and elevated platforms/ view decks do NOT form part of the
GFA.
RLA
registered and licensed Architect
impervious surface
RLLA
registered and licensed Landscape Architect
A paved surface, usually just outside the building perimeter, that prevents surface water percolation i.e. the
sinking of water into the ground or paved surfaces that do not have the capability to retard surface water flow,
thereby contributing to flashfloods;
RLECE
registered and licensed Professional Electronics Engineer
RROW
RLEnP
registered and licensed Environmental Planner
RLPEE
registered and licensed Professional Electrical Engineer
The area existing between two (2) or more defined activity spaces that afford such areas direct pedestrian and
vehicular access only; in particular, the RROW/ street shall consist of the sidewalk, the curb and gutter (where
present), the carriageway and all of the other hard-scapes (including street furniture) and soft-scapes that may
be initially introduced by the Owner on the property;
RLPME
registered and licensed Professional Mechanical Engineer
street
Same as road right-of-way (RROW); common term for RROW;
RLSnE
registered and licensed Sanitary Engineer
PUD
ROI
return-on-investment
ROW
right-of-way
SDP
site development planning
A planned unit development (PUD) refers to a land development scheme for a new project site wherein said
project site must have a Comprehensive Development Master Plan (CDMP) or its acceptable equivalent i.e. a
unitary development plan/ site plan that permits flexibility in planning/ urban design, building/ structure siting,
complementarity of building types and land uses, usable open spaces for general public use services and
business activities and the preservation of significant natural land features if feasible, whereby said CDMP
must be duly approved by the LGU concerned;
SPP
Standards of Professional Practice (for State-registered and licensed architects/ RLAs in the PH)
TGFA
STS
sewage treatment system
SWMS
solid waste management system
sqm
square meter
The total floor space within a building (inclusive of extensions/ additions to such a building/ enclosed area)
and auxiliary buildings; the TGFA consists of the GFA and all other enclosed/ partially enclosed support areas
that are built up and/ or paved (with an impervious surface) together with all other usable horizontal areas/
surfaces above and below the finished grade line (FGL) that are all physically attached to such a building;
areas such as open/ semi-covered parking, walks/ covered walks, courts, pools, ponds/ grotto, generator
shed/ pump room/s and elevated platforms/ view decks all form part of the TGFA.
sqmm
square millimeter
Urban Design
TA
transaction advisor
TGFA
total gross floor area
The 2004 IRR of Republic Act (R.A.) No. 9266 (The Architecture Act of 2004) defines urban design as the
physical and systematic design undertaken by a State-registered and licensed architect (RLA) on a
community and urban plane, more comprehensive than, and an extension of the architecture of buildings,
spaces between buildings, entourage, utilities and movement systems. Presently, this definition is the primary
legal basis for interpreting the scope of urban design in the Philippines, even as it applies to projects in rural
settings such as environmentally- sustainable developments.
TLA
total lot area
TOSL
total open space within lot
WHO
World Health Organization
E-iv
E-v
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.1
Introduction
E.2
Development Guidelines for Proposed BUILDINGS
E.1.1
Intent of the Development Guidelines
E.2.1
Land Use Standards
E.2.1.1
Development Standards
The Department of Public Works and Highways (DPWH) Design Guidelines,
Criteria and Standards (the “DGCS”) and its Volume 6 (Buildings and Related/ Other
Documents) Annex [Development Guidelines and Design Guidance (the “DGDG”)]
have been formulated for the following purposes:





E.1.2
Further promote and protect the health, safety, comfort, convenience and general
welfare of the Owners and the pre-identified users of the buildings for which the
pertinent plans, designs and documents are to be reviewed by the DPWH BoD.
Protect the character and stability of the development as a physically planned
community and to promote an orderly and beneficial process of development/
redevelopment.
Regulate the location, footprint, height, bulk, gross and total gross floor areas
(GFA/ TGFA) and open space ratios of the planned buildings/ structures in order
to diminish the potentially negative effects of these elements on overall/ general
public safety, health and welfare.
Protect and enhance the open spaces of the buildings in order to preserve the
desired character and ecology of the development and its setting.
Contribute to the process of decision-making in the implementation of the
development plan/ effort.
The DPWH BoD as Reviewer shall actively interpret and continually evolve (and
improve upon) these DGDG, duly aided by qualified technical consultants (as needed),
particularly on any question or possible uncertainty that may arise regarding these
DGDG or of any other matters of importance to the well-being of BUILDING end-users.
Development and Community Philosophy
A BUILDING Project (the “Project”) shall provide the advantages of safety, community
and a productive and uplifting environment. With integrated activity spaces as a
BUILDING’s primary focus, the designers shall situate a BUILDING’s target public
users within highly functional spaces on a setting of limited open spaces, hopefully
attaining a high degree of integration of the natural and built environments.
All activities and functions must promote the well-being of the individual end-users,
and of the community as a whole, and must not be detrimental to a BUILDING’s
intended utilitarian character. A balance between the needs and expectations of
individuals and the community as a whole must be achieved and maintained.
E-1
The applicable overall development standards must necessarily include the pertinent
issuances of the PH National Government, NOT limited to certain physical planningrelated guidelines of P.D. No. 1096, otherwise known as the 1977 National Building
Code of the Philippines (NBCP) and its 2004 Revised Implementing Rules and
Regulations (IRR, effective 01 May 2005), local development-related ordinances, or
even certain issuances of the Housing and Land Use Regulatory Board (HLURB) as
may be applicable, and the like.
E.2.1.2
Compliances with the applicable stipulations of the 1977 NBCP and its 2004 Revised
IRR effective May 2005, the Referral Codes (RCs) of the NBCP (e.g. Fire/ Structural/
Electrical/ Mechanical/ Sanitation/ Architectural/ Water/ Sanitation Codes, the
Accessibility Law, etc.), applicable ordinances of the host local government unit (LGU),
which shall be applied suppletorily, and which should not be in conflict with (and
should be more stringent than) the minimum development controls prescribed under
the NBCP and its 2004 Revised IRR and RCs) and all other applicable laws are
required for all architects, engineers, designers, developers, constructors, subconstructors, etc. who shall work on Project components on-site.
Setbacks and Foot-printing within the Defined Building Sites
Being parts of planned unit developments (PUDs), the footprints of BUILDINGS must
be set at a specific minimum distance from the edge of their respective RROWs, as
follows:
Table E-1
Setbacks for Commercial and Industrial Buildings (applicable to BUILDINGS)
Road Right-of-Way (RROW) Width
(meters)
Front
(meters)
Side
(meters)
Rear
(meters)
30.0 and above
8.0
5.0
5.0
25.0 to 29.0
6.0
3.0
3.0
20.0 to 24.0
5.0
3.0
3.0
10.0 to 19.0
5.0
2.0
2.0
Below 10.0 (if introduced)
5.0
2.0
2.0
Source: Table VIII.3 of the 2004 Revised IRR of P.D. No. 1096/ 1977 NBCP
The Open Space Requirement (OSR), otherwise referred to as the Percentage of Site
Occupancy (PSO) or Allowable Maximum Building Footprint (AMBF) for buildings
under the 2004 Revised IRR of the 1977 NBCP, that MUST be satisfied for BUILDING
properties shall be at sixty percent (60.0%) of the total lot area (TLA). The applicable
breakdown of the Total Open Space within Lot (TOSL) to be satisfied shall at
maximum development be as follows:
E-2
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table E-2
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Reference Table of Maximum Allowable PSO, Maximum Allowable ISA, the
MACA, the Minimum USA and the TOSL for a PUD
the NBCP), the maximum depth of the basement can then be made equal to onehalf (0.5) of the height of the building above grade; if the prescriptions for
natural lighting and ventilation are satisfied, the basement depth can therefore
be as much as one-third (0.33) of the combined height of the building to be
constructed above grade and below grade.
Building/
% of Total Lot Area (TLA)
Structure Use or
Occupancy
Duly-Approved Zoning
Maximum
Maximum
Minimum USA TOSL d
(or Land Use)
Allowable PSOAllowable ISAc (Unpaved Open
(ISA +
(examples only)
(Paved
Open
Spaces)
USA)
Spaces)
70
PUD at an inland area
close to an operating
airport
10
20
30
70
PUD at a reclamation
area
close to
an
operating airport
15
15
30
- The center portion of all basement levels shall be reserved for the satisfaction
of the basement level may extend by a minimum clear distance of 1.4 m from
the outermost face of the building (OFB) at grade level.
- The OFB at the second and lower basement levels shall follow the line of the
OFB at grade level.
Source: Table VIII.1 of the 2004 Revised IRR of P.D. No. 1096/ 1977 NBCP

Additionally, there are applicable Angles/ Slopes emanating from the centerlines of
the road rights-of-way (“RROWs” or “streets”) that limit architectural projections and
that must be complied with to satisfy additional natural light and ventilation
requirements along both the RROWs and the front yards of the proposed buildings at
DPWH properties (reference Figure VII.G.1/ G.2 and Table VII.G.3 of the 2004 Revised
IRR of P.D. No. 1096/ 1977 NBCP).
E.2.1.3
The stated BHL excludes basement construction where legally and technically feasible.
The NBCP does NOT prescribe a minimum number of basement structures, only that
such basements not be under the RROW i.e. excluding below-grade crossings.
Basement levels are NOT suggested for BUILDING sites on reclaimed land. In the event
however that a Proponent suggests a basement level for a reclaimed BUILDING site,
the applicable rules are as follows:

Maximum Configuration of Basement Levels: While basements may be developed
for medium to very high density mixed-use developments, BUILDING planning,
design and construction shall observe the following limitations:
- The minimum RROW width that services the lot on which the basement can be
constructed should be at least 10.0 m wide.
- For basements to be allowed, the prescribed setbacks and yards must be
satisfied for the building/ structure above grade in as much as the very same
setbacks shall apply below grade to determine the maximum depth or width of
the basement level.
- If the NBCP prescriptions for introducing natural light and ventilation into all
basement levels are first satisfied (referencing Fig. VIII.G.23. of the 2004 IRR of
E-3
Minimum Provisions for Natural Lighting and Ventilation at Basement Levels: If
basements are to be developed, the following minimum provisions for natural
light and ventilation shall be satisfied:
- A primary or main natural light and ventilation shaft (vertical) with a clear
distance of at least 3.0 m shall be located at the center of the building and shall
traverse the entire combined height of the building above and below grade;
(referencing Fig. VIII.G.23. of the 2004 IRR of the NBCP).
- Secondary or support natural light and ventilation shaft/s (angular) with a
clear distance of at least 1.2 m shall emanate from the front and rear perimeters
of the building and shall traverse the entire depth of the basement; the angular
shaft/s shall be at an angle of 60º from the horizontal, consistent with the
maximum Philippine solar angle; separate angular shafts emanating from the
side perimeters of the building are encouraged.
Building Height Limit (BHL) and Basements
As a BUILDING is usually part of a planned unit development (PUD) e.g. located at an
inland area close to an operating airport, the maximum allowable height for a building/
structure on the property shall be from 3- to 25-storeys i.e. 10.0 m to 75.0 m (with
CAAP-prescribed BHL as needed) as measured from the top/ finished surface of the
average sidewalk elevation along the RROW/ street immediately fronting the
BUILDING site, or as otherwise lawfully provided under Table VII.2 and related rules
of the 2004 Revised IRR (effective 01 May 2005) of Presidential Decree (P.D.) No.
1096, otherwise known as the 1977 National Building Code of the Philippines (NBCP).
- All drainage structures below grade shall not exceed the OFB below grade.
E.2.1.4
- Both the vertical and angular shafts shall only be used for natural air and light
intake and shall not be used for any form of exhaust or air exchange to keep the
temperature inside the shafts at a minimum.
Building Bulk
The applicable Floor to Lot Area Ratio (FLAR) i.e. same as Floor Area Ratio (FAR)
rights at maximum development (including the maximum building/ enclosed area
additions) shall be at:



2.0 to 3.0 times the total lot areas (TLAs) for a building site i.e. if the development
is classified exclusively as an institutional use.
6.0 to 18.0 times the total lot area (TLA) for the building site i.e. if the
development is classified as part of a PUD at an inland area close to an operating
airport.
6.0 times the total lot area (TLA) for the building site i.e. if the development is
classified as part of a PUD at a reclamation area close to an operating airport
(reference Table VII.G.1 of the 2004 Revised IRR of the NBCP) but these may still be
adjusted through the proper representations with either the Local Building
Official (BO) or the DPWH Secretary (in his capacity as the National Building
Official/ NBO under P.D. No. 1096 (1977 NBCP), mainly if there can be potentially
resultant hardship on the part of the Building Owner, considering the very high
value of the properties (which must both yield a decent return). The applicable
Gross Floor Area (GFA) and Total Gross Floor Area (TGFA) at maximum
E-4
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.2.2
E.2.2.1
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
development (including the maximum building/ enclosed area additions) shall
arise from the utilized FLAR rights.
be provided with a window or windows with an area not less than 1/20 of the floor
area of such rooms, provided that such opening shall not be less than 240 sqmm. Such
a window or windows shall open directly to a court, yard, public street or alley, or to
an open watercourse.
General Use and Development Guidelines
The required windows may open into a roofed porch where the porch:
Parking Provision

Under the NBCP, the required parking for a public school development shall be as
follows (for confirmation):



E.2.2.2
E.2.2.3
The maneuvering area of buses shall be outside of the RROW i.e. within the
property or lot lines only (reference Table VII.4 of the 2004 Revised IRR of the
NBCP).
There shall absolutely be no openings on/ at/ within/ through all types of abutments
(such as firewalls) erected along property lines or along the edge of RROWs, except
possibly for correctly positioned and properly/ duly-permitted vent wells. In locating
window openings it should be borne in mind that in cases of extreme emergencies,
windows must serve as emergency egress to vacate the premises or access for rescue
operations. Such windows shall meet the following requirements:
Rooms for human habitation - 6.0 sqm with a least dimension of 2.0 m;
Kitchen - 3.0 sqm with a least dimension of 1.5 m; and
Bath and toilet - 1.2 sqm with a least dimension of 900 mm.
Minimum Air Spaces
The minimum air spaces shall be provided as follows:



School rooms - 3.0 cum with 1.0 sqm of floor area per person;




E.2.2.6
These can be opened from the inside without the use of any tools;
The minimum clear opening shall have a width not less than 820 mm and a height
of 1.0 m
The bottom of the opening should not be more than 820 mm from the floor;
Where storm shutters, screens or iron grilles are used, these shall be provided
with quick opening mechanism so that they can be readily opened from the inside
for emergency egress and shall be so designed that when opened they will not
drop to the ground
All areas immediately outside a fire exit window/ grille must be free of obstacles
and must lead to a direct access down into the ground or street level.
2.2.6.
Artificial Ventilation
Rooms or spaces housing heating equipment shall be provided with artificial means of
ventilation to prevent excessive accumulation of hot and/or polluted air. Whenever
artificial ventilation is required, the equipment shall be designed to meet the following
minimum requirements in air changes as shown in Table E-3 hereafter.
Table E-3
Workshop/ laboratory and offices - 12.0 cum of air space per person; and
Habitable rooms - 14.0 cum of air space per person.
Window Openings
Rooms intended for any use, not provided with artificial ventilation system, shall be
provided with a window or windows with a total free area of openings equal to at
least 10% of the floor area of the room, provided that such opening shall be not less
than 1.0 sqm. However, toilet and bath rooms, laundry rooms and similar rooms shall
E-5

Minimum Sizes and Dimensions of Rooms

E.2.2.5
Eaves, canopies, awnings (or media agua) over required windows shall not be less
than 750 mm from the side and rear property lines.
One off-RROW (off-street) passenger loading space that can accommodate two (2)
queued jeepney/ shuttle slots; or two (2) queued bus slots whichever is applicable.
Habitable rooms provided with artificial ventilation shall have ceiling heights not less
than 2.4 m measured from the floor to the ceiling. The 2004 IRR of the NBCP further
provides that for buildings of more than one (1) storey, the minimum ceiling height of
the first storey shall be 2.7 m and that for the second storey, it shall be 2.4 m. The
succeeding stories (above the 2nd storey) shall have an unobstructed typical headroom clearance of not less than 2.1 m above the finished floor. Enclosed spaces with
natural ventilation shall have ceiling heights of not less than 2.7 m while mezzanine
levels shall have a clear ceiling height of not less than 1.8 m above and below it.

Has one of the longer sides at least 65% open and unobstructed

Minimum Ceiling Heights at Buildings

Has a ceiling height of not less than 2.7 m
One (1) car slot for every 500.0 sqm of GFA or fraction thereof.
The minimum sizes of rooms and their least horizontal dimensions shall be as follows:
E.2.2.4

Abuts a court, yard, public street or alley, or open watercourse and other public
open spaces
Minimum Requirements for Air Changes
Cubic Meter (CuM)
Per Minute
Per Person
(examples)
Air Changes Per Hour
Ceiling Height
(meters)
Min.
Max.
2.4
3.0
3.7
4.9
6.1
Cafeteria
0.43
0.57
6
4-½
3-½
2-½
1-¾
Chapel
0.14
0.22
3
2
1-½
1
¾
Shop, Retail
0.22
0.29
3
2
1-½
1
¾
Office
0.29
0.43
4
3
2-¼
1-½
1
Cafeteria Kitchen
0.34
0.43
5
3-¾
3
2
1-½
E-6
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Source: Table VIII.4 of the 2004 Revised IRR of P.D. No. 1096/ 1977 NBCP
E.2.2.7
Utility meter centers shall not be obstructed or altered and the maintenance of utility
meter centers shall be conducted by authorized personnel only.
For other rooms or spaces not specifically covered in Table E-3, the applicable
provisions of the pertinent referral code/s apply.
Building Modifications
No building/ structure shall be modified to the point where it detracts from the visual
harmony of the schooling community.
E.2.2.10
No lumber, metals or other bulk materials shall be kept, stored or allowed to
accumulate on any part of the development except during limited/ permitted periods
during construction or alteration.
Additions and alterations shall only be in the same architectural style as the original
building/ structure. Additional building materials and color, on the exterior face, shall
be similar to the existing building/ structure. Roof slope and/ or parapet construction
shall likewise match those at the pre-existing building/ structure.
No machinery or equipment shall be stored or operated upon any part of the
development unless necessary and customary for the ordinary use of the property or
for limited construction or alteration work.
All building modifications must be approved by the DPWH Administrator, including
repainting, which must still comply with the prescribed/ original color scheme/s.
Roof or gutters of building additions shall not be drained onto neighbouring parcels.
E.2.2.8
Retaining walls (if provided) shall not be altered, demolished, or changed by building
additions. Walls for building additions shall have proper structural foundation, such as
cantilever footings or grade beams, independent from that of the retaining wall.
Trash and Recycling
No person, including any of the end-users and visitors, shall dump refuse on any part
of the property, except in the designated areas for such material/ refuse.
No weeds, rubbish, debris, objects or materials of any kind shall be placed or
permitted to accumulate within the development.
Garbage and recycling materials shall be placed in covered containers only, preferably
out of public view. Waste shall be segregated by using separate trash containers for
biodegradable and non-biodegradable trash. Trash collection and handling shall be
conducted according to or higher than local standards and will be contracted by the
Building Owner.
Storage
Front and optional side yard areas visible to the public shall not be used for storage of
any form. Personal property shall be stored completely out of public view.
DPWH-permitted additions and alterations to buildings/ structures shall strictly
conform to the intent of these DGDG.
Building additions (if and only if applicable) shall preferably not be constructed at the
front yard area but shall be encouraged at the rear yards, provided no violations of the
minimum standards prescribed under the 2004 Revised IRR of the NBCP are made.
Groundwater wells shall preferably not be constructed within the development.
Rainwater collection devices shall be preferably maintained but kept completely out
of public view.
E.2.3
Generator sets shall be pre-approved by the Building Designers before any installation
commences. The appropriate pollution control or mitigation devices should be
provided i.e. noise and air pollutants, etc.
Road Rights-of-Way (RROWs)/ Streets and Legal Easements
Within the BUILDING sites, the generated RROWs shall constitute the primary free
access zone i.e. where all users (pedestrians and vehicles) may pass for ingress/
egress purposes (intra-property and extra-property movements/ circulation).
The RROW is essentially made up of three (3) parts i.e. the carriageway (or roadway)
on which vehicles pass, and which usually take up to 2/3 of the RROW width, the
sidewalk on which pedestrians pass, and which usually take up to 1/3 of the RROW
width, and the curb and gutter assembly, which acts as the transition between the
carriageway (at a lower surface elevation) and the sidewalk (at a higher surface
elevation).
The RROW/ street areas extend throughout all the three (3) identifiable physical
development levels of the RROW i.e. grade (street) level, below grade (under the
surface of the street) and above grade (above the surface of the street), more properly
defined as follows:

Composting of contained and inoffensive kitchen and yard waste is encouraged only if
space can be made available. Approved composting devices shall be maintained
completely out of public view e.g. at the well-ventilated green roof (if introduced).
E.2.2.9
The burning of trash and refuse is absolutely prohibited under law.
Utilities
To avoid interference with utility and wastewater lines and surface water drainage,
future excavations onsite shall not exceed 0.30 m in depth.
E-7

RROW ABOVE GRADE - refers to the portion of the RROW reckoned from the
finished surface of the carriageway and/or the sidewalk/ arcade all the way up to
the air; if this level of the RROW is utilized for whatever purpose, it is the air rights
that come into play; the minimum clear height for the utilization of air rights
above RROW shall be 4.27 m from the finished crown elevation of the
carriageway;
RROW AT GRADE - refers to the portion of the RROW reckoned from the natural
grade line (NGL) up to the finished surface of the carriageway and/ or the
sidewalk/ arcade; this portion of the RROW is generally utilized for the movement
of the general public (motorists and pedestrians alike); and
E-8
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures

E.2.3.1
RROW BELOW GRADE - refers to the portion of the RROW reckoned from the
finished surface of the carriageway and/or the sidewalk all the way down into the
ground.
Allowed or Encouraged Structures/ Developments Within the RROW/ Street
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures

E.2.3.3




E.2.3.2
Vehicular transportation and ambulant pedestrian-related structures and like
uses whether temporary or permanent e.g. Carriageway, sidewalk, street furniture
such as waiting sheds, traffic outposts, streetlamps/ signages and their support
structures, barriers, planterboxes and the like;
Limited commercial structures/ uses above grade (RROW air rights utilization) or
below grade, provided that these are ancillary or supplementary/ complementary
to the transportation/ pedestrian-related structures/uses allowed in the previous
paragraph, and the like;
Improvements on the RROW and on all building components/ elements found at
all building physical levels e.g. Sidewalks, carriageway, arcades and medians (only
if introduced), planting strips, street furniture, elevated or underground crossings
or access-ways, and the like; and
Utility/ service structures/uses (power, water, drainage, sewerage,
telecommunications, gas, etc.) at all physical levels of the RROW provided that
these do not restrict nor impede the movement of people and vehicles and
provided further that the rights to utilize the portions of the RROW are properly
secured and permitted by the Building Administrator.
Disallowed or Prohibited Structures/ Developments at the RROW/ Street
The RROW is part of the public domain within a building site, which should be equally
enjoyed by all end-users; as such, the RROW is not to be used for the following types of
buildings/ structures/ occupancies or others similar to them:






E-9
Any form of semi-permanent/ permanent or semi-enclosed/ enclosed commercial
structure/ use and like structures/uses not specifically permitted by the Building
Administrator.
Any form of temporary, semi-permanent/ permanent or semi-enclosed/ enclosed
residential structure/use and like structures/uses not specifically permitted by
the Building Administrator.
Long-term or overnight vehicle parking i.e. Unless duly permitted by the Building
Administrator.
As a depository of stalled or abandoned vehicles, mechanical devices and the like,
which shall be removed upon instruction by the Building Administrator.
The conduct of non-institutional activities deemed incompatible with the
character of the RROW and of the building site.
Unauthorized recreational or entertainment usage and the like which will only
benefit certain entities and which will ultimately result in inconvenience/
nuisance/ safety problems to the other end-users, nor
Preservation of View Corridors and/or Sight Lines

The RROW at all BUILDING physical levels may only be used for the following types of
structures/ uses or others similar to them, to wit:


E.2.3.4
Any other form of private use, gain, enjoyment or profit at the expense of the
motoring or walking public.
The carriageway/ roadway portion of the RROW shall be free of structures,
particularly from commercial signs that will impede the view corridor and sight
lines within the RROW.
View corridors or sight lines from buildings/ structures on a higher or lower lot
shall not be entirely blocked by the intervening buildings to allow sight lines to
exist.
In case of allowed structures within the RROW for transportation or ambulant
mobility e.g. elevated or ramped crossings/ overpass and the like, the appropriate
designs shall be adopted to maximize light, ventilation and view.
Sidewalks
Subject to existing laws and regulations, the local planning authority shall be
optionally consulted in the determination as to which RROW/ street (particularly at
the building site perimeters) shall have an open sidewalk or an arcaded (or covered)
sidewalk, or a combination of both.
The minimum width of the sidewalk for a RROW width of 9.0 m or more shall be 1.2 m
on each side of the RROW or a total of 2.4 m on both sides of the RROW. For the
minimum width of sidewalk for RROW of less than 9.0 m wide (if introduced),
reference Table VIII.G.3 of Rule VIII of the 2004 IRR of the 1977 NBCP.
Sidewalk widths shall be based on the following considerations:









Volume of pedestrians (regular/ periodic end-users, visitors and the like) who will
use the sidewalks.
Type, intensity or level of operation and size/ expanse of the allowed uses/
occupancies along the RROW.
Types and volume of street furniture e.g. street lighting and traffic signs/ signal
supports, pedestrian barriers/ aids, etc., and other urban design elements that will
be allowed as permanent fixtures within the width of the sidewalk.
Width of the planting strips (if introduced).
Spatial needs for placements of utility/ service lines underneath the sidewalk and
for utility/service poles.
Compliance with accessibility requirements as stipulated under Batas Pambansa
(B.P.) Blg. 344 (Accessibility Law).
Provisions for commuters e.g. waiting sheds, loading/ unloading areas (as
introduced) and the like.
Provisions for vehicle crossings/ driveways between the carriageway and the
front yards of buildings/ structures or provisions for loading/ unloading
platforms (if allowed/ needed).
Need for introduction of allowed uses/ elements within the sidewalk area only if
there is sufficient sidewalk width e.g. bicycle lanes, jogging lanes and the like.
E-10
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures

Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Climate, light, ventilation, safety, security and overall maintenance of the sidewalk
and all BUILDING surface areas.
a separating strip between the arcaded portion and the open portion of the sidewalk
(reference is also made to Figure VIII.G.16. of the 2004 Revised IRR of the 1977 NBCP).
Sidewalks shall be of uniform width throughout the entire length of the RROW/ street.
The sidewalk width grade and finish of the dominant use/ occupancy along the RROW
shall be generally observed.
Grade of Sidewalks

The width of the sidewalk shall be as follows:
Table E-4

Range of Required Sidewalk and Planting Strip Widths (total at both sides of
RROW) by RROW Width
Road Right-of-Way (RROW) Width

Range of Required Sidewalk Widths
(total at both sides of the RROW)
30.0 m and above
from 1/6 up to 1/4 of RROW width
25.0 - 29.0 m
from 1/6 up to 1/3 of RROW width
20.0 - 24.0 m
from 1/6 up to 1/3 of RROW width
10.0 - 19.0 m
from 1/4 up to 1/3 of RROW width
Below 10.0 m
from 1/4 up to 1/3 of RROW width


Source: Table VIII.G.4 of Rule VIII of the 2004 Revised IRR of P.D. No. 1096/ 1977 NBCP
The width of the sidewalk shall include both the paved and unpaved (and possibly
planted) portions. (Refer Table E-5).
Table E-5
Minimum Planting Strip Widths by RROW Width
Road Right-of-Way
(RROW) Width
Total Minimum Widths of Planting Strip within RROW
(width per sides of the RROW in meters)
30.0 m & above
1.2 (0.6)
25.0 - 29.0 m
0.6 (0.3)
20.0 - 24.0 m
0.6 (0.3)
10.0 - 19.0 m
0.4 (0.2)
Below 10.0 m
Optional
Source: Table VIII.G.5 of Rule VIII of the 2004 Revised IRR of P.D. No. 1096/ 1977 NBCP
For allowed, disallowed and prohibited structures/ developments within the RROW,
refer to Sections 3.1 and 3.2 of these DGDG.
The sidewalk pavement shall have a non-slip surface and shall slope down from the
building line towards the curb line at not more than 1/50 and shall level off with the
curb (reference is also made to Figure VIII.G.14. of the 2004 Revised IRR of the 1977
NBCP).
Sidewalks of 2.0 m or more in width shall include a planting strip of not less than 800
mm in width up to a maximum of 1/3 of the allowed sidewalk width, separating the
curb from the sidewalk pavement. For wider RROWs (where vehicle speeds are
faster), the planting strip must always be near the curbline to protect the ambulant
pedestrian (reference is also made to Figure VIII.G.15. of the 2004 Revised IRR of the
1977 NBCP).
Combined open and arcaded sidewalks shall be provided with a planting strip of not
less than 800 mm in width up to a maximum of 1/3 of the allowed sidewalk width, as
E-11
E.2.4
Sidewalks shall, as much as possible, be level and of uniform grade throughout the
entire length of the RROW/ street.
Whenever the slope of the street does not exceed 1/12 the sidewalk grade shall
follow the level or slope of the RROW/ street (reference is also made to Figure
VIII.G.17. of the 2004 Revised IRR of the 1977 NBCP).
Whenever the slope of the street is 1/10, the sidewalk shall be maintained level
for every 20.0 to 40.0 m of run (reference is also made to Figure VIII.G.18. of the
2004 Revised IRR of the 1977 NBCP).
Sidewalks of different levels shall be joined by means of a ramp having any
convenient slope not exceeding 1/6 (reference is also made to Figure VIII.G.18. of
the 2004 Revised IRR of the 1977 NBCP).
When the grade of two (2) connecting sidewalks are between 1/10 and 1/8, the 2
sidewalks shall be joined by means of a ramp having any convenient slope not
exceeding 1/10.
No BUILDING/ structure shall be constructed unless it adjoins or has direct access to a
public space, yard or RROW/ street on at least one (1) of BUILDING sides. All
BUILDINGS/ structures shall face a RROW/ street which has been duly approved by
the proper authorities.
Miscellaneous Guidelines
No activities in the designated front yard areas (including porches and decks if
introduced) shall compromise or detract from the decidedly institutional character of
the development. The Building Administration shall be primarily responsible for
creating a list of specifically prohibited activities.
Unless specifically permitted, restricted and monitored by the Building
Administration, no business or commercial activity shall be conducted within the
BUILDING sites, particularly if such activity will result in or involve exterior
advertising (i.e. signs, non-mobile billboards/ NMBs/ electronic displays/ mobile
billboards mounted on vehicles, etc.), increased traffic or parking, significant
deliveries and/ or shipments or external storage of commercial goods.
Dangerous, noxious, and offensive activities are absolutely prohibited within the
BUILDING sites. Activities causing unreasonable or continuing annoyance or nuisance
to the BUILDING end-users are similarly prohibited. The Building Administration shall
define these.
Unless forming part of carefully considered and proposed engineering interventions,
changes to the artificial/ future surface water drainage patterns on-site are
prohibited. Adjacent properties shall be protected from surface run-off from the
building site. Drainage of site and structure run-off shall be directed to the nearest
RROW/ street or other appropriate channeling/ discharge/ collection devices.
All grounds surrounding buildings and structures shall be maintained in such a
manner as to prevent or minimize the risk of fire and other dangers to the BUILDING
E-12
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
sites, as well as the neighboring parcels. This includes landscaping maintenance,
including tree-trimming, removal of dry or high grass and removal of dead tree limbs.
observer. The Building Administrator shall develop procedures for such required
dispute resolutions in full accordance with R.A. No. 9285 (The Alternative Dispute
Resolution Act of 2004) and its IRR. Should such a process fail, the Building
Administrator shall then officially endorse the dispute to the concerned purok/ sitio
and barangay having jurisdiction over the BUILDING sites, for additional mediation.
Respect the Rights of Others. All end-users and visitors are enjoined to fully respect
other entities’ rights to enjoy and to make full use of public amenities by using
common courtesy and good judgment at all times.
Landscaping Treatment and Maintenance. The Building Administrator shall be
responsible for the maintenance of all landscaping elements onsite, including
vegetation, paving, decorative items, fountains, etc. No person shall remove any
landscaping element nor add any element to the designated public/ common areas,
unless permitted by the Building Administrator.
Parking and Vehicles. Parking on any designated on-street parking areas is
permitted only during operating hours. Parking in landscaped or other areas not
intended for vehicle use is absolutely prohibited. Vehicles violating parking
requirements will be subject to immediate towing at the vehicle owner's expense.
Washing, maintenance, and repair of motor vehicles are prohibited onsite.
Animals and Pets. Household pets (dogs, cats, etc.) may be allowed onsite subject to
control by their owner. Owners must clean up after their pets. Pet owners shall be
liable to other end-users and visitors of the building for any harm and/ or damage to
persons or property caused by pets.
E.2.4.2
Penalties and Fine System for Violation/s of These DGDG: The Building
Administrator shall formulate a system of notifying, charging and collecting fines for
violations of these DGDG or for the assignment of penalties (including waiver of rights
to access to and/or use of facilities onsite) for continued or repeated violations of
these DGDG.
Update and Revision of These DGDG (on a Need Basis)
The Building Administrator may periodically update and revise these DGDG on an
absolute need basis. Thereafter, sufficient notices shall be furnished all parties
concerned before the updated/ revised DGDG can take effect.
Firearms and Weapons. No firearms or other weapons (including dangerous
recreational items such as real bow and arrows) shall be used or brought onsite
except by authorized law officers, which includes the BUILDING’s security services.
Utilities. The Building Owner shall be responsible for maintaining or contracting for
the maintenance of all utilities and utility structures and facilities. No public access
shall be provided or allowed to any utility structure or facility.
Access to Public Facilities. All end-users and visitors must present a valid
identification card or similar device for entry and use of designated common facilities
wherever controlled access is enforced. A limited number of guests (to be determined
by the Building Administrator or facility management) may use the common facilities
if accompanied by an authorized entity.
Hours of Operation and Use. The Building Administrator shall determine the hours
for use of the public facilities onsite. Use of these facilities during non-operating hours
is prohibited.
Facility-Specific Rules. Particular public facilities onsite e.g. chapel (if introduced),
etc. may develop rules specific to their use and operation. These rules shall be posted
in full public view and shall be considered part of the DGDG. The Building
Administrator shall approve such rules and any future amendments.
E.2.4.1
Personal Items. All end-users and visitors shall remove all personal belongings when
leaving the designated public areas onsite.
Administration
Dispute Resolution Among End-users and Visitors: The Building Administrator
shall serve as either a conciliatory or mediating body to settle onsite disputes. In a
conciliation mode, the Building Administrator shall actively participate in seeking a
resolution to the dispute. In a mediation mode, the Building Administrator shall allow
the parties to resolve the dispute and simply act as a facilitator, recorder and
E-13
E-14
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.3
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Physical Planning Guidance

These guidance for physical planners, designers, constructors and developers define
the type and intensity of land use for public school developments such as those
envisioned for the BUILDING sites. These are meant to be the minimum requirements
such that the expected standard is met. The BUILDING’s technical team will have to
define their specific goals, or development characteristics, in each particular case, in
accordance with their expectations and development strategies. However, the
resulting specifications should never go below the minimum standards under these
physical planning and design guidance.
E.3.1
E.3.1.1
Nevertheless, and in order not to restrain, or even prevent possible creative or
innovative inputs by the physical planners/ designers, the guidance is not to be taken
as rigid rules, but rather as having a considerable degree of latitude and allowing
interpretation and adjustment to specific situations and site conditions, which must all
be fully compliant with the dictates of law. It will be up to the physical planning/
design authority to ascertain the adequacy, acceptability or even quality of the
particular proposals assuming the same depart from the base criteria/ considerations.



E.3.1.3
Site Development Guidance
Site development planning (SDP) and design standards must be institutionalized, as
described in the succeeding sections. Guidance that are applicable to proposed public
school facility planning as well as to general developments and to environmentallysensitive areas help ensure a functional, safe and attractive environment for the
building and grounds’ end-users and visitors.
E.3.1.4
Site Development Standards
There are several types of specific standards that are applicable to the controlled
development of institutional facilities. These standards typically include:







E.3.1.2
Development density
Building height
Building setbacks from amenity features, rows and other buildings/ structures
Floor to lot area ratio (FLAR)
Site coverage i.e. Percentage of site occupancy (PSO) by buildings and other
structures
Parking requirements
Other requirements, such as those for landscaping and open space, public access
to amenity features, signs and utility lines.
Establishing Site Development Guidelines
The exact requirements for the site development guidelines shall vary depending on
the intended character of the public school development and on the environmental
situation, although there is a generally accepted range of requirements.
E.3.1.5
Site Coverage: the percentage of the site area that may be occupied by buildings/
structures at ground level (referred to as the PSO under the 2004 Revised IRR of
the 1977 NBCP which took effect 01 May 2005).
Building Height: measured both in numbers of storeys and height in meters (m)
and related to location, existing built environment and natural features; further
restrictions are imposed on the proportion of building volume that may reach the
maximum height expressed as a percentage of the total building floor area
(referred to as Maximum Volume of Building/ MVB and partly referred to under
Floor to Lot Area Ratio or FLAR under the 2004 Revised IRR of the 1977 NBCP);
this regulation is partly intended to promote variety in the building volumes.
Car Parking: reference the minimum parking regulations under the 2004 Revised
IRR of the 1977 NBCP for mixed-use developments or for specific building
occupancies forming such developments.
Setbacks and Easements: reference the provisions of both the 1949 (1954) New
Civil Code and the 1977 NBCP and its 2004 Revised IRR.
Density
Density refers to the number of end-users or buildings/ structures per hectare (ha.),
which determines to a great extent the overall character of the development.
Building Heights
The maximum allowable heights of buildings greatly influence the character of an
institutional development due to the visibility of taller buildings. If a very natural site
appearance is desired, the BUILDINGS could be limited to three (4) or even up to five
(5) fully functional levels, combined with larger building footprints coupled with
generous open space and landscaping. Taller buildings will create a more urban
character of development, although, if combined with ample open space and
landscaping, taller buildings can be widely acceptable in a high density institutional
environment (and possibly even on reclaimed land, if not for cost and ROI
considerations). The BUILDINGS shall require elevators to move large numbers of
passengers and heavy/ very heavy furniture and equipment, which entails additional
costs for installation and maintenance.
Building Setbacks
The setbacks or minimum distances required of main buildings from amenity features,
RROWs and other buildings, are important to maintain a sense of openness and
sufficient space for landscaping, privacy of building occupants, and in some cases for
safety and security reasons. Adequate setbacks are particularly necessary for several
reasons:


Protection of buildings and their foundations from any perceivable damage.
Allowance of adequate space from the RROW for public access and recreational
use by end-users/ visitors.
Key Planning Factors:
E-15
E-16
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.3.1.6
E.3.1.7
E.3.1.8
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Floor to Lot Area Ratio (FLAR)
Floor Area Ratio (FAR), also referred to as the Floor to Lot Area Ratio (FLAR) under
the 2004 Revised IRR of the NBCP, is a measure of the intensity of development, and
refers to the ratio between the total floor area of all storeys/ levels of all the buildings
and the total site area of the DPWH properties (or total lot area/ TLA in the case of
individual buildings). The FLAR is calculated by dividing the generated gross floor
area (GFA) by the area of the site (or of the individual lot) and is expressed as a
percentage (%).
E.3.1.10
Site Coverage
The site coverage by buildings and structures, also referred to as the PSO under the
2004 IRR of the 1977 NBCP, is likewise indicated as a percentage (%), and is an
important development control on the amount of impervious surface limit i.e. not
penetrable by surface/ rain water, landscaped areas and open space within the
development.
E.3.1.11
Provisions in full accordance with the 2004 IRR of the 1977 NBCP should be made for
sufficient off-street parking to handle all vehicles, including parking/ layover/ waiting
spaces for staff/ end-users/ visitors at the defined peak period use, so that the
RROWs/ streets shall not become congested with parked/ waiting/ queued vehicles. A
special provision for larger spaces may need to be made for the parking of special
vehicles/ conveyances. The specific requirements for off-street parking will vary
greatly, depending on the location, building type and intended occupancies/ usage of
the component developments onsite.
E.3.1.9
A green roof may be introduced atop the BUILDINGS (if provided with deck roof
levels) to replace the natural ground/ vegetation lost to building footprinting. Such a
green roof may be a combination of hardscaping i.e. walks, paths, squares, railings,
barriers, landscaping furniture, lighting, plant/ soil and water holders/ structures/
E-17
E.3.1.12
Landscaping and Green Roof
In addition to the site coverage requirement, it is common practice to also require that
a minimum amount of landscaping be developed (including any naturally-occurring
vegetation onsite, as may be applicable), and that landscaping be provided in
otherwise unattractive spaces, including large parking areas, alongside RROWs and
around utility buildings and structures, in order to screen these from view. The
minimum landscaping requirement may also be expressed as a percentage (%) of total
site area.
Public Access
Adequate public access should be provided at amenity features and public facilities. In
addition to incorporating public access in the respective master development plans
(MDPs), these can be generally required by regulation, such as the introduction of
public access points to a suitable section set apart at regular distances e.g.
approximately every one thousand meters (1,000.0 m) as a possible maximum in a
developed area.
Sign Controls
Large, unattractive, and inappropriately located signs, whether commercial or
directional, can greatly detract from the appearance/ character of the BUILDING
developments. Sign control standards should be established with respect to their type,
location, size, materials used and lighting. Often, an approach applied is not to allow
any outdoor advertising signs onsite, but only well-designed identification and
directional signs constructed of materials that are compatible with the environment
and that can be discretely lighted at night.
Off-street Parking
For some BUILDING areas, it may be difficult to precisely project parking
requirements, and in fact these requirements may change over time. In these
situations, provision can be made for possible future parking needs by allowing for
vertical parking expansion in appropriate locations, but initially landscaping these as
part of the interim/ initial open space until such time as these may actually be needed.
In this manner, an excessively large area is not reserved for parking lot development,
but sufficient parking spaces will be made available for possible future use. Parking
areas of any type should be well landscaped and must fit into the overall environment
of the intended development.
containers, and the like plus softscaping i.e. soil, water, vegetation, trees and the like. A
portion of the green roof may be assigned for composting to create fresh garden soil
or for activities such as vermiculture, hydrophonics within or near a mini-greenhouse
setting. The bulk of the created spaces at the green roof may serve a variety of social
functions and amenity-related uses.
E.3.2
In the event that the DPWH officially permits the mounting of non-mobile billboards
(NMBs)/ electronic displays on any of the sides of the BUILDING’s exterior surfaces,
these must be fully compliant with the latest valid and subsisting issuances of the
DPWH and its NBO, particularly on the sizing and mounting of such NMBs at any point
or elevation onsite as well as the satisfaction of the minimum requirements for natural
light and ventilation both inside and outside the BUILDING (refer to Section 6. of this
DGDG).
Underground Utility Lines
Overhead electric and telephone lines and their supporting poles are unattractive
elements and disturb views in any environment. Although very high voltage electric
lines are difficult to place underground (particularly at reclaimed areas that still need
to settle over time), the lower voltage distribution lines can still be located
economically underground. Placing utility lines under the natural ground line (NGL) is
initially more expensive but because of lower maintenance costs, may be no more
costly over the long term than overhead lines. In areas prone to occasional high winds
that can topple utility poles and lines (or trees over the lines), underground i.e. below
NGL lines offers additional safety and maintenance advantages.
Civil Works Guidance
As with the other plan/ design disciplines, climatic characteristics establish the basic
factors that need to be taken into account in terms of building grounds and RROW
features related to access and drainage plans/ designs for public school buildings/
grounds sited in a hot-humid tropical climate such as that found in the Philippines
E-18
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
(PH). Image should also evolve in the planning stage as a consequence of the physical
and market analyses as each site is unique and hence should be allowed to name and
evolve its own character and image.
The building grounds should be developed to enable all types of end-users to move
around freely and safely. This requires the removal or treatment of site hazards e.g.
abrupt changes in ground elevation, presence of large amounts of running or surface
water, sharp rocks or geologic formations, soft soil and the like. Natural lighting and
ventilation within the grounds and the RROWs, if present/ provided, are requirements
to be fully satisfied but it is equally important to introduce provisions that protect all
end-users from excessive sun, light and heat.
The use of the correct surface colour and texture selection for construction and
finishing materials to balance reflected light and heat is a must. The use of paving
materials that allow surface water percolation is highly encouraged e.g. porous/ welldrained asphalt mixes, smooth stones, paver blocks/ tiles on sand bedding and the
like, except in areas directly above basements.
When choosing between asphalt and concrete pavement, the light and heat absorption
or reflection properties (and ambient heat generated by the material), surface traction
and surface water percolation should become key factors for material choice. Asphalt
pavement if properly founded and well-drained can last up to three (3) decades
without need for major repair, especially for inland locations.
All developments should be sufficiently drained to prevent a host of sanitation/
health-related problems, particularly where stagnant water can be found. Only
properly sized, connected and sloped drainage and sewerage lines must be in place.
E.3.2.1
E.3.2.2
If at all possible, all developments must never interfere with the normal movement of
water/ hydraulics in and around the Project site. Intervention is however encouraged
if damage is caused to the land by excessive water movements e.g. scouring and
erosion.
E.3.2.3
E.3.2.4
E.3.2.5
E.3.2.6
General Engineering Guidelines
Engineering design standards for the Project area should be evolved and established
to ensure that at least minimum infrastructure and construction requirements are met
in designated development areas. In less-developed countries or regions where these
standards have not yet been adopted or exist but are considered unsuitable,
international standards or those of a more developed country can be adopted, adapted
(modified or customized) and/ or applied. The basic types of engineering standards
are reviewed in the following sections.
E.3.2.7
Road Rights-of-Way (RROW)
For inland sites, various categories of RROWs are established based on projected
traffic usage, as well as respective RROW widths and related drainage-ways,
walkways, and landscaping requirements determined. Cross-sections of these various
types of roadways are drawn, and construction and materials specifications are
generally written in conformity to accepted international standards.
E-19
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.3.2.8
Drainage
In addition to the drainage associated with RROWs, the specifications for other types
of drainage-ways, such as for various sizes of culverts and canals, are to be
established.
Water Supply
Water supply quality standards are evolved and established based on either local
standards, if they are acceptable, or on international standards such as those set by
the World Health Organization (WHO). The source of water supply will of course
depend on local conditions, but standards should be established for the amount of
water required for various activities within an institutional development, the quality
level of the water, water pressure to be maintained, and the specifications of the
distribution system. Water supply standards should include provisions for fire
protection and water conservation techniques.
Electric Power
The source of electric power will also vary from place to place, but standards can be
evolved and established for the amount of power to be available, based on projected
demand, reliability of supply, consistency of voltage, and the specifications for
installation of the distribution system. Any possibilities for utilizing energy
conservation techniques such as solar heating/ power generation should be applied as
much as possible.
Sewage Disposal
The type of sewage disposal system will depend on the scale of development and local
conditions, and may range from the use of septic tanks to large integrated sewage
collection and treatment systems e.g. centralized sewage treatment plan (STP),
although portable compartmentalized STP units are already available in the PH
market. Standards should be evolved and established with respect to the degree of
treatment required - primary, secondary, or tertiary - and the disposal technique of
effluent, based on preventing any pollution. Investigation should be made as to the
potential for recycling sewage effluent, especially in water-deficient areas, for use as
landscaping irrigation water or other domestic or even possible potable use.
Solid Waste Disposal
The type of solid waste disposal will also vary, depending on the local situation, but
standards should likewise be evolved and established to ensure that there is proper
disposal and that the techniques of disposal, such as landfill (if introduced), will not
generate any other pollution problems. Recycling of solid waste should be required to
the greatest extent possible.
Telecommunications
International standards exist that can be applied to the development of internet,
telephone, telegraph/ telex (where still needed/ applicable), radio-telephone,
cellular/ mobile and other means of wireless (or wired) telecommunications.
E-20
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.3.2.9
E.3.2.10
E.3.2.11
E.3.2.12
E.3.2.13
E.3.3
E-21
Building Construction Standards
Standards and specifications for the construction of public school buildings and other
structures are essential. Usually, these already exist in the area in the form of the 1977
NBCP and its2004 Revised IRR, but should be reviewed to ensure that they are
suitable, including review for public safety and fire protection. For example, sprinkler
systems may now be required for low-rise buildings under R.A. No. 9514, the 2008
Fire Code of the Philippines (FCP) and its 2009 IRR.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
buildings, spaces between buildings, entourage, utilities and movement systems.
Presently, this definition is one of the primary legal basis for interpreting the scope of
urban design in the Philippines.
Urban design quality necessitates addressing the following considerations:



Sanitation and Public Health Standards

Maintaining minimum sanitation and hygiene standards is also essential in
institutional developments, especially for restaurants, bars, and toilet/ bathing
facilities. Usually sanitation standards, in the form of a national or local public health
code (such as The PH Sanitation Code), cover institutional areas but should be
reviewed to make certain that they are adequate.

Public health standards also relate to room size, ventilation, and fenestration (door,
window or other natural light and/ or ventilation opening) requirements.
Other Types of Engineering Design Standards





permeability
legibility
quality of the public realm
ease of movement
robustness
diversity
appraisal of context
defining framework within which development will take place
- pattern, grain
- movement
- legibility, landmarks, views
- blocks and plots
Engineering-related Safety and Security Standards
- density and form
- mixing uses


- landscaping
connecting the development to movement and utilities (traffic management,
parking etc.)
designing the details that make the place a unique place
- public realm
- massing
Operations and Management Guidelines
Good planning and design of a public school development is only as good as the
operation and management of the facility. Sustainable development requires an
ongoing environmental management program (EMP) that covers environmental
awareness, good practice, staff training, visitor education and environmental
monitoring and evaluation procedures.
continuity and enclosure
The four (4) basic urban design elements are:
Other types of engineering design considerations for institutional developments
include, for example, elevator equipment, mechanized walk/ walkalator systems (if
introduced), and the like, which all require specific standards, especially as related to
operational and safety factors.
Maximum attention must be given to engineering provisions fully addressing safety
and security matters i.e. fire integrity of buildings/ structures, fire protection
provisions and response mechanism (including building floor/ level fire searches and
fire-fighting), incidents/ accidents, natural disaster (earthquake, grass fire, flashflood,
animal attack and the like), crime, medical (including first aid and CPR) and related
emergency responses, telecommunications/ linkages to the proper authorities,
evacuation and the like; monitoring and prevention management devices and
techniques should be well in place when the BUILDING operates.
character
- robustness
- building and open space details
The applicable urban design applications for institutional projects envisioned for the
DPWH properties are:


Urban Design Guidance

What is urban design? The 2004 IRR of Republic Act (R.A.) No. 9266 (The
Architecture Act of 2004) defines urban design as the physical and systematic design
undertaken by a State-registered and licensed architect (RLA) on a community and
urban plane, more comprehensive than, and an extension of the architecture of


place markers and directional signage and/or way-finding systems
RROWs including possible arcades
wide open flexible use/ assembly areas and walking spaces
street furniture in urbanized and highly built-up areas
other forms of open public spaces
E-22
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.3.3.1
E.3.3.2
Street Furniture Guidelines (where applicable)
The overall quality of any development depends upon all aspects being
sympathetically designed within an overall approach. For example, ill-considered
detail in street furniture e.g. sidewalks/ paths, curb and gutter, railings/ barriers,
benches/ rest furniture, site lighting, directional signage and related way-finding
treatments, driveways, drop-off areas, bus/ mega-taxi/ jeepney stops (outside the
property line), etc. can impact unfavorably upon the overall impression of the Project.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.4
Design/ Post-Design Guidance
E.4.1
Detailed Design Process
If applicable, all aspects of detailed plan/ design preparation for all facilities/
buildings/ structures onsite must conform to the 2004 Revised Implementing Rules
and Regulations (R-IRR, effective 01 May 2005), of Presidential Decree (P.D.) No.
1096 otherwise known as the 1977 National Building Code of the Philippines
(NBCP) and its approximately twenty (20) referral codes (“RCs”, particularly R.A. No.
9514/ 2008 Fire Code of the Philippines and B.P. Blg. 344/ the Accessibility Law),
which should be familiar to most Philippine physical planners, architects, engineers
and designers, who shall necessarily assume the attendant professional responsibility
and civil liability for the projects onsite.
Signs and Information Panels
Signage should not dominate or block views and is more effective if a simple, easy to
read design is used and the chosen materials and colors blend in with the natural
setting. Outdoor displays are a good way to introduce the end-user/ visitor to the
introduced flora in the Project area.
However, if the guidelines and standards under this document or its subsequent
iterations may in effect supplant/ complement/ supplement the absent, unexplained,
insufficient or conflicting provisions under the NBCP and its 2004 Revised IRR, insofar
as the physical planning and design of the proposed facilities/ buildings/ structures
onsite are concerned, the same shall be fully complied with, particularly if the same
are more stringent than the minimum standards prescribed by the NBCP.
Lighting should be chosen to emphasize moods, themes and create a relaxed
atmosphere e.g. the use of the night-time sky can be dramatic. However, light
intrusion and over-lighting glare can obscure what little night vision is available. Care
is therefore required to limit night lighting to the minimum necessary for safety. Light
fixtures should remain close to the ground to minimize eye level glare.
E.4.1.1
Established principles for creating sustainably-planned/ designed, green architecture
(GA)-oriented and tropical design-oriented solutions are also strongly suggested for
adoption into detailed designs for all facilities and buildings/ structures onsite.
Detailed Design Documentation
The minimum design documentation for public school projects are as shown
hereafter:
Pre-Design Documents which may include the following:



E-23
The identification or confirmation (in case a master development plan/ MDP had
already been prepared) of land (and available water) uses and access systems and
the cross-effects between these and the proposed horizontal and vertical
developments, on-site analyses on the physical characteristics and development
potentials of the Project site, the proposed environmental design elements
(including those that will define movement/ access/ privacy/ security, future
access/ expansion), compliance with existing site master planning and design
guidelines for institutional estate developments, national building laws e.g.
concerning the delineation of structure footprints and construction areas and
even local development-related ordinances.
In instances where a MDP has already been prepared, the identification or
confirmation of base data on the topography, soil condition, domestic water
sources, drainage capability, flood cycles and levels, existing land use/ activities,
existing utilities, access points and road rights-of-way (RROWs), rights-of-way
(ROWs)/ legal easements, Philippine sun-path, solar angle and prevailing wind
orientations, view orientation and sight lines, visual quality, environmental
quality, climate and possible volcanic/ seismic activity/ fault-line locations, etc.
In instances where a MDP has already been prepared, the identification or
confirmation of data needed to fully comply with institutional-related planning
and design guidelines/ laws/ ordinances to finalize siting, orientation,
E-24
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures


configuration, sizing and clustering of the proposed development components, to
specify view corridors that will maximize privacy and security within each
development, to specify the appropriate structures and materials to make the
built environment earth-friendly and end-user-friendly, to specify the types of
plants suitable to the place, to specify site civil works, etc.
Pre-Design Documents for the horizontal and vertical development components
of the Project in accordance with the stipulations of the pertinent Standards of
Professional Practice (the “SPP”, effective March 2011) documents promulgated
by the Philippine Professional Regulation Commission (PRC) as part of the
Implementing Rules and Regulations (IRR) of Republic Act (R.A.) No. 9266,
otherwise known as the Architecture Act of 2004, and covering such
professional responsibilities and deliverables as spatial and building program,
architectural program, initial project cost determination, design briefs, etc., which
altogether constitute the bases for design.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures




The necessary reportage and work phase documentation.

Conceptual plans and designs for the horizontal and vertical development
components of the Project in full accordance with the stipulations of the pertinent
SPP documents (effective March 2011 and thereafter) promulgated by the PRC as
part of the IRR of R.A. No. 9266, and covering such professional responsibilities
and deliverables as the schematic architectural/ space, supportive engineering
and allied plans/ layouts, initial plan and design analyses, budgetary cost estimate
of the Project development cost, etc.; and
- Floor Plans drawn to scale of not less than 1:100 m showing: gridlines,
complete identification of rooms or functional spaces.
- Elevations, at least four (4), same scale as floor plans showing: gridlines;
natural ground to finish grade elevations; floor to floor heights; door and
window marks, type of material and exterior finishes; adjoining existing
structure/s, if any, shown in single hatched lines.
Preliminary plans and designs for the horizontal and vertical development
components of the Project in full accordance with the stipulations of the pertinent
SPP documents (effective March 2011 and thereafter) promulgated by the PRC as
part of the IRR of R.A. No. 9266 and covering such professional responsibilities
and deliverables as the preliminary architectural/ space, supportive engineering
and allied plans/ layouts, outline specifications, revised budgetary cost estimate of
the Project development cost, etc.
Contract Documents (or their official equivalents) which may include the following:

E-25
Detailed plans and designs for the horizontal and vertical development
components of the Project in full accordance with the stipulations of the pertinent
SPP documents (effective March 2011 and thereafter) promulgated by the PRC as
part of the IRR of R.A. No. 9266, and covering such professional responsibilities
and deliverables as detailed architectural/ space, supportive engineering and
allied plans/ layouts and the attendant technical specifications (all signed and
sealed by duly-qualified and suitably-experienced registered and licensed
professionals/ RLPs registered and licensed by the PRC in compliance with the
pertinent professional regulatory laws/ PRLs), schedules of materials and
finishes, final or detailed cost estimate of the Project development cost, tender
Vicinity Map/ Location Plan within a 2.0 kilometer radius for commercial,
industrial, and institutional complex and within a half-kilometer radius for
residential buildings, at any convenient scale showing prominent landmarks or
major thoroughfares for easy reference.
- Perspective drawn at a convenient scale and taken from a vantage point (bird’s
eye view or eye level).
The necessary reportage and work phase documentation.
The necessary reportage and work phase documentation.
Architectural Plans/ Drawings
- Site Development Plan (SDP) showing technical description, boundaries,
orientation and position of proposed building/structure in relation to the lot,
existing or proposed access road and driveways and existing public utilities/
services. Existing buildings within and adjoining the lot shall be hatched and
distances between the proposed and existing buildings shall be indicated.
Design Development Documents (or their official equivalents) which may include
the following:

In the case of architectural documents as defined under PH law and international
practice i.e. architectural plans, designs, drawings, details, specifications,
schedules, reportage and contract documents, R.A. No. 9266 and its IRR specify
that only registered and licensed architects (RLAs) shall prepare, sign and seal
such architectural documents.
Sec. 302.4 of the 2004 Revised IRR of the NBCP enumerates architectural documents
as follows:
Schematic Design Documents (or their official equivalents) which may include the
following:

documents, supportive engineering analyses, bid bulletins including schedules of
material suppliers, official forms for permitting purposes, etc.
- Sections, at least two (2), showing: gridlines; natural ground and finish levels;
outline of cut and visible structural parts; doors and windows properly labeled
reflecting the direction of opening; partitions; built-in cabinets, etc.;
identification of rooms and functional spaces cut by section lines.

- Reflected ceiling plan (RCP) showing: design, location, finishes and
specifications of materials, lighting fixtures, diffusers, decorations, air
conditioning exhaust and return grills, sprinkler nozzles, if any, at scale of at
least 1:100 m.
Details, in the form of plans, elevations/sections:
- Accessible ramps
- Accessible stairs
- Accessible lifts/elevators
- Accessible entrances, corridors and walkways
- Accessible functional areas/comfort rooms
- Accessible switches, controls
- Accessible drinking fountains
E-26
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
- Accessible public telephone booths
- Detail design of major architectural interior elements.
- Accessible audio visual and automatic alarm system
- Plan and layout of interior, wall partitions,
equipment/appliances at a scale of at least 1:100 m.
- Accessible access symbols and directional signs
furnishing,
furniture,
- Typical wall/bay sections from ground to roof
- Interior wall elevations showing: finishes, switches, doors and convenience
outlets, cross window sections with interior perspective as viewed from the
main entrance at scale of at least 1:100 m.
- Fire escapes/exits
- List of materials used.
- Reserved parking for disabled persons
- Stairs, interior and exterior
- Floor/ceiling/wall patterns and finishing details.
- Built-in cabinets, counters and fixed furniture
- All types of partitions

 Schedule of Doors and Windows showing their types, designations/marks,
dimensions, materials, and number of sets.

 Schedule of Finishes, showing in graphic form: surface finishes specified for
floors, ceilings, walls and baseboard trims for all building spaces per floor level.

 Details of other major Architectural Elements.
Figure E-1
- Cost Estimates.
Plans and specific locations of all accessibility facilities of scale of at least 1:100 m.
Detailed design of all such accessibility facilities outside and around buildings/
structures including parking areas, and their safety requirements all at scale of
1:50 m or any convenient scale.
Fire Safety Documents
- Layout plan of each floor indicating the fire evacuation route to safe dispersal
areas, standpipes with fire hose, fire extinguishers, first aid kits/cabinets, fire
alarm, fire operations room, emergency lights, signs, etc.
STANDARD FORM (Type A0, A1, A2 and A3) FOR BUILDING PLANS/
CONSTRUCTION DRAWINGS Figure III.1.(of the 2004 Revised IRR of the 1977
NBCP)
- Details of windows, fire exits with grilled windows and ladders.
- Details of fire-resistive construction of enclosures for vertical openings.
- Details of fire-resistive construction materials and interior decorative materials
with fire-resistive/ fire-retardant/ fire-spread ratings
- Other Related Documents
E.4.2
- Other related documents
Post-Design Process
The post-design process shall generally include the following sets of activities:




MODEL TITLE BLOCK for Building Plans/Construction Drawings Figure III.2. (of the 2004 Revised IRR of the
1977 NBCP)

Architectural Interiors/ Interior Design
- Space Plan/s or layout/s of architectural interior/s.
- Architectural interior perspective/s.
- Furniture/ furnishing/ equipment/process layout/s.
- Access plan/s, parking plan/s and the like.
E-27
E.4.3
Pre-construction activities which include other project management work, design
review and modification, contractor pre-qualification, bidding and award/
selection.
Construction activities which include actual construction and finishing works,
construction management.
Post-construction activities which include project documentation, commissioning
works, turnover, acceptance, occupancy.
The necessary reportage and work phase documentation.
Architectural Guidance
Climatic characteristics establish the basic factors that need to be taken into account
in terms of building features related to the architecture of low-/ medium-density
terminal buildings in a hot-humid tropical climate.
E-28
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Image: This consideration should evolve in the planning stage as a consequence of the
physical and market analysis. Each site is unique and hence should name its own
characteristic image.
or recycled wood are preferred over naturally grown/ harvested tree varieties,
particularly PH hardwoods which are scarce and some species of which are banned
for construction use. The use of alternative construction and finishing materials such
as the CBB or FCB and the like, which use both natural and artificial components, are
also encouraged to avail of their superior material qualities (as compared with some
conventional construction materials).
Building Form, Finishes and Layout: It is accepted that most rooms will be
preferably/ optionally air-conditioned (for indoor climate control) but end-users
should also be able to benefit from outdoor breezes. However, the main objectives are
to encourage breezes to pass through the non-air-conditioned communal/ common
building spaces and outdoor spaces. The orientation and construction of buildings to
exploit the maximum amount of air movement is very important.
The use of imported construction/ finishing materials is only recommended if the
comparative environmental planning/ design value of the material is high to very
high.
Interior/ Architectural Interior (AI): In any mixed-use development facility, and
especially in hot-humid tropical areas such as the PH, the interiors/ AI should be
considered carefully. Major internal spaces are the heart of any facility, being the areas
through which all people move. The treatment of such spaces should reflect a Project's
unique quality.
While natural ventilation is a must, it is equally important to complement it with
sufficient provisions that protect the end-users from excessive sun, light and heat. The
use of the correct exterior color selection to balance reflected light and heat is a must
while the selection of non-traditional building materials that have high to very high
insulating, pest-proofing, fire-resisting, water-repelling and other beneficial
properties is encouraged e.g. wood-wool cement-bonded board (CBB), fiber cement
board (FCB) and the like which come in different densities, textures and finish
preparations.
The broad factors to be observed are:







Major buildings should be designed with relatively open, elongated plan form with
rooms generally distributed in single rows to allow maximum cross ventilation
and penetration of breezes (passive cooling techniques through the floor, walls
and ceiling when and where applicable).
Suggested Architectural Design Objectives
E.4.4.1
General Design Objectives

Projecting canopies or broad overhanging eaves should provide shading to
outdoor sitting and circulation areas – shading devices provide both essential
protection and a means to define and articulate architectural characteristics.


High ceilings or use of double roof construction should be used as applicable;
enclosed ceiling cavities, if introduced must either be actively or passively cooled.

Inexpensive insulating and pest-proofing devices for all building elements should
be considered.
Window openings should ideally be considered in relation to sunlight i.e. The
integration of shading devices that minimize direct radiation, reduce sky glare,
permit adequate natural lighting and allow outward views.
Materials: These should reflect the development image, visual context, the Project
site's setting within the area and degree of harmony, or contrast, being sought. Where
possible, properly-treated/ processed local materials, preferably pest-proof and more
importantly, fire-resistant or retardant, should be extensively used.
High quality materials and furniture, roadway, footpath and hard open space surfaces,
shade structures, fencing, walls, lighting, bollards, rails and the like, can make an
immense difference to the quality of the grounds development. The materials and
architectural form can help integrate them with their environment.
General/ overall environmental sustainability is a foremost consideration in base
construction and finishing material selection. Commercially-grown hardwood/
softwood varieties, processed wood products from wood wastes/ debris/ driftwood
E-29
E.4.4
Main public facilities should be accessible from open galleries.
The use of water and water mist/ spray can also be employed to cool the building
environment and its grounds.
Sympathy and Consistency of Detail: The design should evolve from careful study of
the BUILDING Project sites and their surroundings, and once in place, the intent
should be visible and consistent, extending from broad concepts to the choice of
motifs.

E.4.4.2
Cost-effective space planning/ design/ implementation/ startup/ operation/
maintenance.
Good return-on-investment (ROI) for the building owner.
Enhancement of owner’s image through the creation of an appealing architectural
design solution.
Improvement of the quality of functions, services, circulation and security through
sensitive/ sensible/ practical design and efficient architectural and space
planning.
Enhancement of public areas such as the lobbies, lounges, waiting areas, etc. to
foster better relations with entities being served; improvement of personnel
efficiency of the public school facilities through the betterment of building usage
conditions and environment.
Specific Design Objectives





Optimization of spatial provisions for internal building/ structure circulation/
traffic.
Optimization of space provisions for basic building operational tasks.
Optimization of space provisions for amenities/ facilities/ services/ utilities (the
“AFSU”).
Balance among end-users, planned spaces and identified activities that shall take
place inside the building/ structure/ facility.
Balance between the building and the natural environment.
E-30
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures






Balance between the building’s function and form.

Balance between present and future end-user needs.

Balance between the BUILDING’s strength and economy.

Balance between the user-friendliness of the BUILDING and its grounds/
perimeter areas with overall operations/ upkeep/ maintenance considerations.
Balance between energy efficiency and a good operating environment.
Architectural Design Concepts
E.4.5.1
General Concepts


Since the Project is essentially institutional and supposed to be sited on lots with
optimal sizes and configurations, with projected numbers of future building users and
with the certain possibility of future operational expansion, it may be worth
considering to provide for maximized vertical expansion flexibility, only if
countenanced under existing development controls such as the 2004 Revised IRR of
the 1977 NBCP.


Specific Concern on What the Proposed BUILDING/ Structures Should Have
There are many specific concepts that will be generated by Project consultants for
discussion with the Building Owner, and among these are:









E-31

Balance between the BUILDING’s interior and exterior i.e. Organic design or the
interplay of interior and exterior spaces a preferred spatial and design solution.
E.4.5
E.4.5.2
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
The correct physical orientation to achieve maximum indoor climate control and
energy efficiency.
The maximization of operational efficiency indoors and outdoors through the
correct use of materials, lighting, forms, finishes and textures, etc.
Employment of passive cooling/ lighting technology as applicable for both the
buildings and their grounds.
The projected building exterior/ interior images should convey combinations of
strength, stability, efficiency, honesty, nationalism (and possibly even hints of
dedication to civic duty and public service), approachability at all times,
accessibility and possibly even a sense of appreciation for art/ history and culture.
Exterior/ interior areas must use a good mix of light colors for body, and dark
colors for accent to achieve a good measure of climate and psychological control.
If possible, forms should follow lines so that the buildings’ appearance would not
age easily in terms of aesthetic appeal.
The buildings should all be human in scale and proportion, with the direct
application and judicious mix of both asian and western space planning/
architectural design standards.
Provision of a visitor-friendly and worker-friendly environment i.e. The buildings
and their grounds should be safe and easy to use at all times for people of all ages,
physical capabilities and backgrounds.
Provision of optimum room for future operational expansion and growth.


Maximization of the use of all horizontally, generated spaces through the use of all
available vertical spaces.
Maximization of the use of all horizontally generated spaces by allowing for the
flexibility and multiplicity of space uses.
Generated space plans should reflect considerations of time and motion studies.
Generated space plans must reflect considerations for territoriality i.e. The human
bubble which can be opened or closed depending on the type of activity and the
situations called for.
Generated space plans may either show considerations for the way people tend to
behave inside enclosed/ confined spaces or measures to curb what may be
considered as unproductive/ undesirable behaviour.
Maximization of use of locally available (but of good quality) and/ or imported but
locally-sourced materials to generate cost savings, to facilitate project
implementation, and for ease of upkeep/ maintenance.
Maximization of building and equipment lifecycles through the proper selection/
mix of the necessary components.
Maximization of the use of trees, plants and other soft landscaping elements to
cleanse/ purify the atmosphere at the micro-environment level and to achieve
exterior and interior micro-climate control e.g. Near-ground ambient
temperature/ heat levels caused by heat-/ light-reflective materials.
Optimum to maximum attention given to health and sanitation matters.
Maximum attention given to safety and security matters, particularly the fire
integrity and defensibility of buildings/ structures.
E.4.6
Suggested Architectural Planning and Design Criteria
E.4.6.1
Function
This criterion has to be addressed above all others inasmuch as it pertains to how the
resulting BUILDINGS shall be utilized to realize key Building Owner goals and
objectives. Inasmuch as the Projects are mainly public service-related structures, the
key considerations are:



The types and numbers of end-users.
The types of activities that shall take place within each building by such as official
business, personal transactions, instructional, social, recreational, religious,
commercial.
The quantity/ quality of spaces to be generated, by type.
As all of the foregoing factors are closely interrelated, an exhaustive identification and
analysis of the end-users together with the hierarchy of their needs and activities, as
well as of the optimum spaces required to satisfy these end-user needs/ activities
shall be undertaken by Project consultants to establish and possibly rank or prioritize
all the necessary amenities/ facilities/ services/ utilities (AFSU).
E-32
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.4.6.2
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Form or Integration of Architectural Design Elements
BUILDINGS. The resulting structure should be safe for everyone to use i.e. including
children, the elderly and the persons with disabilities (PWDs), women, etc.
This criterion pertains to the need to relate existing site/ building conditions with the
planned physical/ social/ psychological environments as well as with the envisioned
quality of generated spaces. Various design elements have to be carefully utilized to
realize the best architectural solution and of these, form is one of the most important.
E.4.6.3
E.4.6.4
The satisfaction of the minimum physical planning and design standards by
compliance with all applicable local and international laws must be observed by all
Project consultants, particularly the State-registered and licensed environmental
planners (the “RLEnPs”) and the State-registered and licensed architects (“RLAs”)
who will be held primarily responsible and liable for their respective Project roles
under the concerned PH PRLs and the New Civil Code (1949/ 1954).
Although form is the logical consequence of having initially established the buildings’
function/s (which is/ are the primary consideration/s for any building plan/ design),
it shall be qualitatively expressed in terms of lines, scale, proportion, the use of light
and shade, textures, finishes and color. If properly integrated, all of these would
contribute in projecting a very stable and efficient image for the Owner/ Proponent,
which will ultimately redound to each end-user's pride in his/ her abode, recreational
space and/or workplace.
Before getting engaged in local mixed-use projects, foreign or expatriate physical
planning and/ or architectural consultants must secure the necessary permits from
the PRC i.e. a Special/ Temporary Permit (STP) to practice a State-regulated
profession on PH soil, the PH Department of Labor & Employment (DoLE), the Bureau
of Immigration and Deportation (BID), as well as from the PH Department of Foreign
Affairs (DFA).
Adherence to Basic Architectural Design Principles
BUILDINGS should preferably all be "self-contained systems" that shall be planned/
designed to promote health and sanitation, worker efficiency and minimal disturbance
to the natural and built environments.
A judicious mix of the basic architectural design principles of unity of design and of
the use of repetition, rhythm, balance and emphasis should be regularized in support
of the public nature of the proposed BUILDING’s and grounds.
Budget and Economy in Space Planning/ Architectural Design
The availability of funds for planning/ design/ implementation/ startup/ operation/
maintenance will influence all planning/ design options that shall be made available to
the Building Owner by the Project planning or architectural consultant.
E.4.6.5
The satisfaction of the sub-criterion of design economy starts with correct space
planning and this is the reason why this particular component of the Pre-Design
service should be carried out well. Design should only result from careful interior
space planning and site development planning but such good plans can only become
possible with the utmost cooperation of the Owner/ Proponent, the end-users, other
identifiable stakeholders and the host community in general. Therefore, interactive
discussions between the parties and the Project consultants are a must and should be
regularized.
Time Consideration
From the architectural planning/ design viewpoint, this criterion has to do mainly
with the anticipation of future BUILDING use changes, supplementary operational
requirements and expansion potentials all of which would have to be satisfied to
forestall future growth difficulties. A normal planning-design horizon is from 10 - 15
years on a Project life cycle of 25 years.
E.4.6.6
From the Project implementation standpoint, this criterion would mean
considerations such as those that will affect construction phasing and the project
timetable (from pre-construction to occupancy/ startup of the structure).
Safety, Security, Accessibility and Environmental Considerations
These architectural planning/ design criteria must reflect the Project consultant’s
major concern for the well-being of all identified end-users of the proposed
E-33
E.4.6.7
E.4.7
E.4.7.1
Maximum attention given to architectural provisions fully addressing safety and
security concerns i.e. fire integrity of buildings/ structures, fire protection provisions
and response mechanism (including fire/ floor/ level searches and fire-fighting),
incidents/ accidents (including possible yacht-related events/ occurrences at the
marina), natural disaster (earthquake, tsunami, grass fire, flashflood, animal attack
and the like), crime, medical (including first aid and CPR) and related emergency
responses, telecommunications/ linkages to the proper authorities, evacuation and
the like; monitoring and prevention management devices and techniques should be
well in place when the institutional facilities operate.
Application of Internationally-Recognized Architectural Planning and Design Standards and of
Anthropometrics
In as much as the proposed BUILDINGS shall be accorded a high profile and
international character by virtue of its function, a judicious mix of Filipino, Asian and
Western planning/ design standards shall be applied. Anthropometrics must always
play a key role in making the institutional environment easy and safe to use. The
resultant anthropometrics-based plans/ designs shall ultimately redound to the
attainment of savings and efficiency of operations.
Other Architectural Considerations
Other architectural considerations for the envisioned BUILDINGS shall be as follows:
General Architectural Design
Architectural design guidelines for public service-related facilities must be more
flexible than development standards to allow for the creativity of the Architect/
Designer. However, when a certain design character is desired in an area or
development site, basic guidelines should be established and provided to the
Architects/ Designers for their use in the space planning and design process. These
E-34
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
guidelines are also to be used by the approving authorities in their review of the
proposed facility design.
E.4.7.2
Some basic types of guideline considerations are mentioned elsewhere hereafter e.g.
standards on mixed-use facility layouts, room sizes, length of corridors, and other
standards, which are generally available in design reference books on such subjects.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.4.7.6
Local Styles and Motifs
E.4.7.4

E.4.7.7
Use of Local Building Materials
For example, metal roofs and expansive masonry walls generate very hot building
interiors in high temperature environments, leading to increased demand for airconditioning (which is contrary to energy conservation).
Environmental Relationships
Building design should relate to the natural environment. For example, in tropical and
subtropical areas, buildings should incorporate indoor-outdoor (or organic designoriented) relationships through use of open-sided lobbies, patios, and courtyard
gardens. In tropical climates, designing for natural ventilation may preclude the need
for air-conditioning during much of the year but demand for air-conditioned facilities
should never be discounted as the PH is a hot-humid tropical zones i.e. high humidity
E-35

Roof Lines
To the greatest extent possible, local building materials should be utilized, especially if
they relate to the local architectural style (primarily based on functional
considerations), as is often the case with wood or stone construction. Also, the use of
local building materials may be less expensive than imported materials and provides
employment and may provide some measure of possible income for residents of the
host area. Exceptions to this standard are where use of traditional local materials,
even though attractive and functional, may create environmental problems.
E.4.7.5

In some instances, there is a problem of completely integrating the local style due to
differences in scale and function, but usually some local motifs can still be utilized.
Local motifs, including handcrafted materials, can also be incorporated into the
interior decor of the facilities. If no local styles prevail, sometimes a neutral
international but environmentally-oriented style is appropriate, rather than wholly
importing a style from elsewhere that is not related to the area.
The design of roofs (flat, pitched, overhang, etc.) is an especially critical design
element inasmuch as rooflines are very visible for low-rise buildings, and these
greatly influence the character and appearance of the buildings/ structures to be
erected onsite. Rooflines should preferably reflect the local architectural style
(primarily based on functional considerations) and be consistent with the
characteristics of the natural environment.
Design for Persons with Disabilities (PWDs)
More emphasis is now being placed on architectural designs for the PWDs (in
compliance with both Batas Pambansa Bilang (B.P.) Blg. 344: The Accessibility Law of
1982 and its IRR and with R.A. No. 7277 (otherwise known as the Magna Carta for
Disabled Persons of 1991) and its IRR, including provisions for the physically
impaired, sensory-impaired, slower moving elderly people, and the mentally impaired.
This design approach is also being extended to end-users who are PWDs. Barrier-free
architectural design should be applied to the envisioned BUILDING and attractions,
with techniques applied such as:
If there are distinctive local, traditional, or historic architectural styles already
developed in the host area/s and environs, these should be incorporated into the
institutional facility designs to the greatest extent possible so that these facilities fit
into the local environment, reinforce the architectural character of the area, and
impart a distinct sense of place to the BUILDING development.
E.4.7.3
levels. Building design should also take advantage of any views fronting the site to
help maximize organic relationships with the host site.
E.4.8
Developing hard, relatively smooth, wide indoor paved surfaces;
Ramped access with automatic door openings or through bars at entrances to
buildings/ structures, and
Restrooms and public telephones designed for use by persons in wheelchairs.
In high ambulatory/ pedestrian traffic areas, vehicular traffic should be well separated
from pedestrian access-ways for safety reasons in general and especially for the safety
of the PWDs. At such areas, presentation techniques should include those that can be
appreciated by the sensory-impaired and mentally impaired, with special programs
organized where relevant.
Design for Gender and Age
Emphasis shall also be placed on design considerations that address various
sensitivities related to gender and age i.e. the physical needs of end-users such as
women, young adults, children, babies and the elderly, particularly as the same relates
to ambulatory activities.
Landscape Architecture Guidance
One of the strongest features for institutional developments is the quality of the
outdoor environment. Successful developments carefully blend landscaping and
architecture to achieve a consistent, unified and unique Project character.
Considerations for institutional developments in particular, include:
Thematic design should be related to the planning and architectural elements of the
facility. For example, the use of boulders (introduced onsite) and local trees can
provide both a sense of enclosure and integration with the existing landscape while
lush courtyards can help extend interior spaces outward.
Each BUILDING development requires some form of appropriate open space which
should be dedicated for the use and enjoyment of all visitors/ end-users. These should
ideally be designed around existing vegetation and landforms. Even the smallest
planting pockets, if well-designed, can offer elements of form, texture, shadows,
fragrances and color. People will enjoy external spaces for passive recreation and
socializing in a sunny/ warm but humid climate if the space is well-shaded and
correctly orientated.
E-36
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Aside from the foregoing elements, planting/ vegetation can be used for shelter/
shade and reduction of glare. The cost of running air-conditioning can be reduced by
using vegetation to shield roofs and walls from direct sunlight.
Planting can also be used to screen substations and garbage bins, as a barrier to
prevent people straying, to stop soil erosion and stabilize slopes and as a space
definer. The use of naturalized plant species can also reduce water usage.
Xeriscape landscaping is the selection and zoning of plants according to their water
requirements. This design strategy is very cost-effective, as maintenance and watering
are minimized. It is also aesthetically- and ecologically-sound in principle since plants
are selected to harmonize with their environment. Landscaping schemes should
therefore attempt to group plants according to water and maintenance requirements
The selection of material for hard landscapes depends on the purpose. The use of
materials also helps to define changes of use (vehicles/ pedestrians), level, ownership
and approaches to focal points. Attention should be given to color, pattern, noise,
sunlight, heat and maintenance. The appropriate use of water, its sight and sound, can
enrich the enjoyments of the environment and resort facility immensely and be
employed to cool the environment.
Other Landscape Architectural Considerations
Other landscape architecture considerations for the envisioned BUILDING
developments are as described in the following sections.
General Landscaping Design
Generous and suitable landscaping is an essential element in creating an attractive
and interesting public service-related environment and also serves important
functional purposes. Even in urban environments, exterior and interior landscaping
can help create a desired character of the facility. Landscape architecture is concerned
with the relationship and appearance of the total environment, with particular
reference to plants and landscaping features such as water bodies, footpaths, and
outdoor furniture and lighting. Good landscaping attempts to provide unity and
cohesion in the local environment and a sensitive balance between man-made
features and the natural elements.
More specifically, landscaping in public service-related developments involves the
effective use of plant materials and other features for such purposes, according to
certain principles as:






E-37
Creating an attractive setting conducive to relaxation and recreation (even just for
short periods).
Screening objectionable views and providing privacy.
Providing vegetative buffers to absorb unpleasant sounds, smells, and dust.
Arranging plants to provide relief from intense sun glare and rain, as well as to
reduce surface/ ambient temperatures.
Minimizing the effects of high winds, yet still allowing for the flow of gentle
breezes.
Organizing the plant material to complement a landform, to enhance a building
line or facade, to gradually unfold an attractive vista or to frame a major entrance
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures



area; in some cases, the plants themselves can be used to provide focal points and
major visual features.
Situating plants in strategic places where they can be best appreciated; many
plants are more attractive if planted in mass and seen from a distance whereas
others must be seen at close range to be fully appreciated.
Arranging and massing trees and shrubs, particularly native flowering species, to
provide dramatic color and textural variation.
Introducing visitors to new species and varieties of plants, especially from the
local area (as applicable).
Landscaping can also be used to screen and ameliorate poor building design or
inappropriate use of building materials, not an uncommon situation in public servicerelated developments.
Where available, local indigenous plant material should be utilized in landscaping
because local plants grow well in their own environment and reinforce the natural
vegetative character of the sites. However, certain imported exotic plants that do well
in the local environment may also be appropriate. Major plants and especially mature
trees endemic to the development site should be saved and incorporated into the final
landscaping plan as much as possible.
Plant material that is easy and inexpensive to maintain and conserves resources
should be used e.g. not using plant species which require large amounts of water, etc.
Water features such as ponds and small waterfalls can offer very interesting accents
and visual focal points in a landscaped area, but these should be carefully designed for
ease of maintenance and conservation of water such as re-circulating the water used
in ornamental fountains and waterfalls.
Footpaths are an important element of landscaping for institutional developments and
visitor facility sites. In addition to serving their pedestrian function, footpaths should
be attractive, safe and practical to use, as well as be designed to offer interesting
views. Outdoor furniture (benches, tables, etc), shelters, and kiosks are often
important to include when landscaping mixed-use facilities; these should be suitably
designed reflecting the building design, properly located, and well constructed.
Night lighting in landscaped areas is important for both functional reasons of safety
and security and for aesthetic appreciation of buildings and landscaping. Lighting is
used at entrances, access drives, and parking lots, along footpaths, in recreational
areas, to illuminate interesting building and landscape features, for information signs
and in service yards. Except in service and high security areas, the most suitable type
of lighting is typically indirect and not too bright e.g. use of low-shaded lights along a
footpath that light the pathway but do not shine in the walkers’ eyes.
A properly registered and licensed Landscape Architect (RLLA) must be
commissioned directly by the Building Owner/s or through/ with the separatelycommissioned registered and licensed Architect (RLA) or Environmental Planner
(RLEnP) to jointly collaborate on the landscape architectural design of the Project.
Design for Persons with Disabilities (PWDs)
More emphasis is now being placed on designing for the persons with disabilities or
PWDs (in compliance with both B.P. Blg. 344 and R.A. No. 7277), including the
physically impaired, sensory-impaired, slower-moving elderly people, and the
E-38
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
mentally impaired. Barrier-free design should be applied particularly
transportation facilities and attractions, with techniques applied such as:




Developing hard, relatively smooth, wide walkway paving surfaces.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
to
curbs with ramped cuts at intersections.
E.5
Environmental Guidance
E.5.1
Environmental Awareness
ramped access with automatic door openings or through bars at entrances to
buildings/ structures.
restrooms, drinking fountains, and public telephones designed for use by persons
in wheelchairs.
Design for Gender and Age
E.5.1.1
Emphasis shall also be placed on design considerations that address various
sensitivities related to gender and age i.e. the physical needs of end-users such as
women, young adults, children, babies and the elderly, particularly as the same relates
to ambulatory activities.
E.5.1.2
Environmental awareness is growing throughout the world As such, the promotion of
sustainable development in the Philippines can only bring positive results as it can
provide a basis for achieving sustainability in the planning and design of public
facilities, encourage responsible decisions in energy and water conservation and
waste management, and emphasize the importance of bio-diversity.
Environmental Management
A proactive approach to environmental management may include a commitment to
continuous improvement in the area of general land and facility management. Possible
co-operative working agreements between government and the community at large,
particularly in urban or rapidly urbanizing settings should be established e.g.
sponsoring environmental management and/ or conservation education activities and
monitoring sensitive ecological sites.
Staff Training
Producing an environmental management plan (EMP) is an essential factor in
developing a pro-active approach. A clear environmental policy statement or Code of
Ethics to be adopted and endorsed by the Building Administrator shall ensure
compliance to environmental management standards (EMS). This policy would
guarantee responsibilities of key Building Administration site personnel towards the
natural and built environments, alongside training and communications procedures
instituted to continually and progressively inform/ educate BUILDING end-users and
visitors about such a policy.
An environmental policy statement from the Building Administrator could include
realistic environmental management objectives and targets. Procedures and targets
may be specified for environmental issues such as environmental protection, waste
management (including reuse/ recycling), energy and water conservation, education
and research, purchasing or cleaning policies, landscaping and visitor education.
Depending on the results of ongoing coordination and research work, additional
material on the immediately foregoing environmental considerations may be
subsequently supplied.
E.5.1.3
For large-scale institutional developments, it may be necessary to employ an
environmental officer to establish environmental procedures and supervise and
monitor their practice/ implementation/ enforcement. Consequently, the impact of an
institutional development upon the surrounding environment could be monitored.
Adequate staff training will also help ensure the mixed utilization of measures to
improve environmental performance. Fostering innovation within the development
and amongst the BUILDING staff/ end-users/ visitors will encourage improvements in
environmental management and performance.
End-User/ Visitor Education
In campus developments (such as PUDs or portions thereof) that are properly
planned, the environmental work often becomes part of the marketing package, as
E-39
E-40
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.5.1.4
environmental constraints such as landscape features, water elements, available or
introduced wildlife (such as birds), etc. all become blended into the development and
gradually become part of the attraction.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.5.2.2
The sewage treatment system (STS) of an institutional development must be
adequate, especially when sited at environmentally-sensitive locations (as applicable).
Maintenance Guidelines
A realistic maintenance program is crucial in the continuing promotion and success of
the Project's image. It must be remembered that even the best-designed developments
can be seriously compromised by poor maintenance.
E.5.2.3
Recognition of the close links between the environment and long term economic
viability will promote commitment towards improved environmental management of
the development.
Effective environmental management practices may involve recycling and waste
management programs, energy and water conservation, staff training and end-user/
visitor education and involvement.
E.5.1.5
Monitoring of the construction and operation phases of the intended development can
improve the effectiveness of environmental management practices and minimize
adverse environmental or social impacts.
An environmental monitoring program (EMoP) should record regulatory
requirements and set realistic management and performance targets or standards,
such as for example, a ten percent (10%) reduction in electricity use.
E.5.2
E.5.2.1
The EMoP should also establish environmental performance indicators (EPI) that are
easy to measure and that might indicate specific problems preventing the
achievement of specific targets. Regular data collection, record keeping and reporting
procedures to examine actual performance will need to be established.
E.5.2.5
Applicable Definitions
Sewage
refuse liquids or waste matter carried off by sewer pipes/ lines.
Sewerage
the removal and disposal of sewage and surface water through sewer
pipes/ lines.
a man-built subterranean conduit to carry sewage and sometimes
surface and rain/ storm water.
Sewage from mixed use facilities must be treated in accordance with the effluent
standards of DENR Administrative Order No. 35, series of 1990 or later issuances that
are valid and subsisting.
Awareness
The applicable provisions of Rule IX (Sanitation) of the 2004 Revised IRR (effective 01
May 2005) of P.D. No. 1096, the 1977 NBCP and the pertinent NBCP referral code/s
(RCs) covering the sewerage requirements of the Project must be fully satisfied. A
properly registered and licensed Sanitary Engineer (RLSnE) must be commissioned
directly by the DPWH (and/or the BUILDING project Proponent/s) or possibly
through/with the separately-commissioned registered and licensed Architect (RLA)
or Environmental Planner (RLEnP) to jointly collaborate on the planning and design
of the sewage handling and sewerage system.
Possible Arrangements
The use of treated/ processed sewage water for toilet flushing or for watering plants
should be encouraged to help reduce the amount of sewage.
On Sewage Disposal
In the absence of a sewer system, septic tanks may in the interim fully process sewage
before direct discharge to the wastewater drainage system.
E.5.2.6
Absorption pits are economical options but may inevitably and deleteriously affect
groundwater quality.
Checklists (Dos and Donts)
Is a responsible and sufficiently experienced/ trained person going to oversee the
operation of the STS for the proposed BUILDING?
Sewerage Guidance
Sewer
E-41
E.5.2.4
Monitoring and Evaluation
Baseline environmental data should always be collected before any construction or
development work commences. An environmental audit, or an audit of some aspects
of performance (such as energy or water conservation and efficiency or waste
management practices) shall be useful in providing future baseline data and in
identifying specific areas where alternative practices can contribute towards
improved environmental performance.
General Requirements
Are the areas for sewage collection/ treatment and for sewerage conveyance secure
and amply buffered/ segregated from other activity areas?
E.5.3
Wastewater Guidance
E.5.3.1
Applicable Definitions
Drain
to draw off liquids gradually and/ or completely; a pipe or conduit
through which liquids are drained;
Wastewater
water that has been used, rejected for any other use and needing to be
disposed of or physically removed from a site; wastewater may
organic and/ or inorganic and may include natural surface run-off,
surface drainage water for paved/ artificially impervious surfaces,
Drainage
a device or system for draining liquids;
E-42
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Wastewater
Management
E.5.3.2
excess rainwater, storm water, kitchen water, bath/ shower water,
and similar types of water; the term also refers to sewage; and
a process of collecting, storage and disposal (through treatment,
recycling, creative re-use, etc.) of wastewater (including sewage) for
economic and social (including environmental) gain; management
entails planning, supervision and monitoring of wastewater resources
and facilities and the enforcement of guidelines for safe and
economical wastewater re-use or disposal.
E.5.3.5
Applicable Definitions
Water
Wastewater drainage is a mandatory requirement for all establishments.
Water Management
A sanitary inspection must be satisfied for the renewal of the annual LGU-issued
permit to operate the BUILDING.
General Requirements
Flooding by natural causes must be prevented as much as possible by the correct and
economical engineering interventions e.g. interceptor trenches, culverts, dikes,
retention or impounding structures and the like (as needed).
Awareness
the liquid that is a major constituent of most living organisms,
which descends from the clouds as rain, forms water bodies/
passages and subsequently collected naturally or artificially and
distributed for use.
a very limited and closed/ controlled commercial system
involving water generation/ collection and distribution for
domestic and other uses by consumers.
a managed system/ procedure of collecting, storage,
distribution, conservation (including limited recycling) of safe
domestic and potable water secured from commercial or other
sources; management entails planning, supervision and
monitoring of use and consumption of the resource and the
enforcement of guidelines for safe and economical water usage.
Water sources can be rainwater, freshwater, well-sourced water, other types of
harvested ground water (as applicable).
Design Considerations
Distances between source points and usage points must be minimized.
b. A three to four (3-4) day supply reserve may be ideal for most types of institutional
operations and should be considered in the designed water storage capacity.
Similarly, a RLSnE must be commissioned directly by the DPWH (and/or the
BUILDING Owner/s) or through/with the separately-commissioned RLA or RLEnP to
jointly collaborate on the planning and design of the wastewater system.
Design Considerations
Awareness
Wastewater must be processed by chemical means to limit its negative effect on living
organisms i.e. bio-oxygen demand (BOD) of 10 parts per million (ppm) or less or
better.
The Rule IX (Sanitation) of the 2004 Revised IRR (effective 01 May 2005) of P.D. No.
1096, the 1977 NBCP and the pertinent NBCP referral code/s covering the water
supply requirements of the proposed Project must be fully satisfied.
Checklists
Conservation
Shall a responsible and sufficiently experienced/ trained person be in charge of the
wastewater management program for the BUILDING?
Faucets within the BUILDING/ facilities. Together with faucets (with additional flow
controllers), there is also need to always supply a full large pail of water for use in
toilets and a drum of water on standby i.e. which double as an emergency water
supply in case of fire.
Wastewater may be mixed. However, sewage water and kitchen wastewater may be
mixed with other types of wastewater only after they have undergone the proper
treatment or processing.
Is the area for wastewater (including sewage) collection, storage, treatment, recycling,
etc. amply buffered/ segregated from other activity areas?
E-43
Water Supply Guidance
General Requirements
The applicable Rule IX (Sanitation) of the 2004 Revised IRR (effective 01 May 2005) of
P.D. No. 1096, the 1977 NBCP and the pertinent NBCP referral code/s covering the
wastewater requirements of the proposed Project must be fully satisfied.
E.5.3.4
E.5.4
Water Supply
Sanitary plans/ designs and an accomplished Sanitary Permit form, duly signed and
sealed by a RLSnE, is required before commencing any level of construction work
involving sanitary and outdoor plumbing work.
E.5.3.3
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Use low-pressure distribution systems to minimize system leakages.
Similarly, a RLSnE must be commissioned directly by the Building Owner/s or
through/ with the separately-commissioned RLA or RLEnP to jointly collaborate on
the planning and design of the water supply system.
E-44
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Checklists
Shall a responsible and sufficiently experienced/ trained person be in charge of the
water management program for the BUILDING?
Is the area for water collection, storage, etc. protected from contamination, secure and
amply buffered/ segregated from other activity areas?
E.5.5
Solid Waste Guidance
E.5.5.1
Applicable Definitions
Waste
Solid Waste
Solid Waste
Management
E.5.5.2
Segregation of organic and inorganic solid wastes must be performed immediately
after collection. Ideally, separate waste bins must be supplied at the source so that
segregation is done earlier, but this may be difficult to implement/ maintain. The
following practice of color-coding solid wastes may be followed:
Green garbage bags for biodegradable wastes e.g. materials that decompose or that
can be reduced to finer particles such as kitchen and garden wastes;
Black garbage bags for non-biodegradable wastes e.g. materials that do not
decompose such as plastics, styropor, tetra-packaging, ceramics, glass, construction
debris (concrete, metals and the like);
Yellow garbage bags for pathological/ infectious wastes e.g. used cotton/ gauze/
bandages/ strips, used sanitary napkins/ tampons/ condoms, used tissue paper/ table
napkin, hospital/ medical./ dental wastes, body or animal parts, cadavers/ carcasses,
body fluids, blood, used dental or medical implements, syringes and the like; and
organic or inorganic waste matter that is solid i.e. three (3)dimensional in form, that results from any type of human/ artificial
activity or from natural occurrences/ processes and that must be
removed from a site for a valid reason; this includes garbage,
rubbish and also excreta; and
Transparent garbage bags for types of waste to be identified by the users.
a process of collecting, storage and disposal (through removal, fill,
composting, breakdown, treatment, recycling, creative re-use, etc.)
of solid waste matter for economic and social (including
environmental) gain; management entails planning, supervision
and monitoring of solid wastes and handling facilities and the
enforcement of guidelines for their safe and economical re-use or
disposal.
Sorting and storage facilities must be well away from activity or guest areas so that
foul odors do not permeate such areas.
Do not store organic solid wastes (particularly kitchen and leftover food or food
waste) on-site as these readily decompose, attract pests and unwanted insects/
animals and emit foul odor.
Hauling or removal off-site should be done either late at night or dawn when most
end-users are away.
The use of open dumpsites is absolutely discouraged as it is a major health hazard.
General Requirements
E.5.5.5
Solid waste incineration is an unlawful practice under the Clean Air Act.
Solid Waste Prevention Strategies
Any waste management system must be integrated with that of the rest of the host
community and the LGU.
Limit the use of paper products within the BUILDING as much as possible e.g. use of
electronic files instead of hardcopies (wherever applicable).
Awareness
Actively promote waste segregation and recycling practices on-site by giving endusers/ visitors and staff incentives to do so.
Solid waste handling or disposal sites must never be allowed in identified
preservation and conservation areas, particularly within watersheds (or portions
thereof, including downstream areas).
The applicable provisions of the Solid Waste Management Act (and its IRR) and the
pertinent referral code/s covering the waste handling/ management requirements of
the proposed Project must be fully satisfied.
A RLEnP, with specific expertise/ specialization and/or experience in environment
consulting, must be commissioned directly by the Buulding Owner/s or through/ with
E-45
Collection and Handling
Solid waste collection must be performed routinely every 12 hours if possible.
a damaged, defective or superfluous organic or inorganic material,
whether liquid, solid or gas, resulting from any type of human/
artificial activity or from natural occurrences/ processes, that is
rejected for use and necessitates physical removal from a site for
health, safety, environmental, social and other valid reasons;
A solid waste management program for the Project must be well coordinated by all
stakeholders (public and private sectors) as it is not the sole responsibility of the
public sector i.e. BUILDING end-users/ visitors.
E.5.5.3
E.5.5.4
the separately-commissioned RLA, to collaborate on the planning and design for the
solid waste management system (SWMS).
If land is available, composting should be considered to realize zero organic waste.
E.5.5.6
Checklists
Shall a responsible and sufficiently experienced/ trained person be in charge of the
solid waste management program for the BUILDING?
Is the disposal area (including areas for collection, storage, fill, composting,
breakdown, treatment, recycling) provided with a separate access system?
E-46
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.5.5.7
E.5.5.8
Where is the removed/ hauled waste being deposited? It must be the solid waste
source point’s i.e. the waste generator’s business to find out exactly where the waste is
destined because it may just be deposited in a nearby area which could eventually
affect the source point’s operations/ safety.
The applicable provisions periodic issuances of the Department of Energy (DoE) shall
be used as the primary reference for energy conservation in the BUILDING and its
grounds.
Energy Management
usable sources of natural or artificially generated/ sourced
power such as heat, fuel, wind, moving water, wave/ tidal
action, geothermal, muscle, decomposition (biogas),
electricity, natural fuels (firewood), combinations thereof
and the like, that can be harnessed for use economically and
without much negative effect on the environs/ setting of the
energy source (to include considerations for human/
animal/ plant communities);
E.5.5.11
Design Considerations
The use of independently-supplied power is the most ideal source for light and
electricity i.e. generator (preferably diesel, silent-type). A backup generator should be
on board.
E.5.5.12
If a 24-hour generator is used, it may have to be installed along with a waterproduction unit that can also operate for 24 hours. Noise and fume abatement
measures must all be in place.
Conservation
To maximize cooling of structures/ buildings, the correct architectural orientation
with respect to sun and wind must be prioritized, sometimes over view orientation.
Passive cooling techniques, wide/ extended overhangs and other green architecture
(GA) solutions or tropical architecture devices should be widely employed in the
planning and design of the mixed use structures/ buildings.
a managed system/ procedure of acquiring, accessing,
storing, distributing, conserving (including possible
recycling) of safe sources of power secured from commercial
or other sources; management entails planning, supervision
and monitoring of use and consumption of the resource and
the enforcement of guidelines for safe and economical power
usage.
Positioning structures under/ behind/ beside exterior natural or artificial shading
devices should be practiced i.e. ornamental or shade trees, heat-reflecting or
absorbing (as applicable) walls or greenery, etc.
Use light exterior colors for the structures to reflect unwanted light and heat and
provide for a cooler interior.
Awareness
A properly registered and licensed Professional Electrical Engineer (RLPEE) must be
commissioned directly by the Building Owner/s or through/ with the RLA or RLEnP
to collaborate on the planning and design of the energy system (including all electrical
devices). The planning and design of systems for electronics and communications
devices are best handled by a properly registered and licensed Electronics Engineer
(RLEE) while the planning and design of the mechanical systems of the proposed
development shall be by a properly registered and licensed Professional Mechanical
Engineer (RLPME).
An electrical inspection must be satisfied for the renewal of the annual LGU-issued
permit to operate the mixed use facility.
A mix of power sources is recommended so that any system shall not be overly
dependent on one (1) power source.
a limited and closed/ controlled commercial system
involving power generation and distribution for domestic
and other uses by consumers; and
The applicable provisions of Rule XIII (Electrical and Mechanical Regulations) of the
2004 Revised IRR of the NBCP and the pertinent referral code/s covering the power/
mechanical (heating, ventilation, air-conditioning, refrigeration, etc.) requirements of
the proposed Project must be fully satisfied.
General Requirements
Electrical plans/ designs and an accomplished Electrical Permit application form, duly
signed/ sealed by a RLPEE, is required prior to commencement of the applicable level
of construction work involving electrical work.
Applicable Definitions
Energy Supply
E-47
E.5.5.10
Energy Guidance
Energy
E.5.5.9
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.5.5.13
Electric fans are preferred over air-conditioners. However, the Project must always
offer end-users the option to avail of either means of artificial ventilation.
Efficiency
Use only low consumption - high output electrical devices.
E.5.5.14
Use only rated electrical devices to be able to monitor consumption properly.
Renewable Energy Resources
If the technology becomes fully accessible at a low acquisition/ operating/
maintenance cost, the use of devices that can economically harness solar, wind, tide/
wave and geothermal power in appropriate quantities for domestic use should be
promoted.
E-48
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.5.5.15
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Checklists
The most efficient combination of luminaires, lamps and ballasts appropriate for the
lighting task and for the environment shall be selected so that lamp light output is
used effectively. The selected luminaire should meet the requirements with respect to
light distribution, uniformity and glare control. The use of highly polished or mirror
reflectors are recommended to reduce the number of lamps installed without
reducing the illumination level. Where ballasts are used, these should be of the
electronic type or low-loss type with a power factor of at least 85%.
Shall a responsible and sufficiently experienced/ trained person be in charge of the
energy management program for the BUILDING?
E.5.5.16
Is the area for energy generation, interface, storage, etc. safe, secure and amply
buffered/ segregated from other activity areas?
Energy Efficient Lighting Design
The highest practical room surface reflectance should be considered in the lighting
design. The use of light finishes will attain the best overall efficiency of the entire
lighting system. Dark surfaces should be avoided because these absorb light. (Table
3.3 of the DoE Guidelines on Energy Conserving Design of Buildings lists the
recommended room surface reflectances.)
There are multiple sustainable design provisions under the 2007 Department of
Energy (DoE) Guidelines on Energy Conserving Design of Buildings, particularly under
its Section 3.3 (General Requirements of Energy-Efficient Lighting Design). These all
form part of nationally-instituted energy efficiency guidelines that are all intended to
conserve power, a design and construction practice that has a positive effect on both
the natural and built environments.
E.5.6
Selective switching possibilities should be provided so that individual or specific
group of fixtures can be turned off when not needed and lighting levels can be adapted
to changing needs.
Hereafter is the list of key energy efficiency guidelines (particularly with reference to
the lighting of the building) to help make buildings of truly sustainable design i.e.
effectively making Green Buildings.
The lighting system shall be so designed (such) that day-lighting can be coordinated
with artificial lighting, taking into consideration the problems of glare, brightness
imbalance and heat buildup in the building interior.
General Requirements of Energy-Efficient Lighting Design
The lighting design shall utilize energy-efficient lighting equipment. The lighting
system shall be chosen (so) as to provide a flexible, effective and pleasing visual
environment in accordance with the intended use, but with the least possible energy
requirements.
The use of task-oriented lighting shall be used whenever practicable.
In the design of general lighting in buildings with centralized air-conditioning
equipment, consideration should be given to integrated lighting and air-conditioning
systems which use luminaires with heat removal capabilities.
The lighting system shall be designed for expected activity. The task shall be analyzed
in terms of difficulty, duration, criticalness and location in order to determine the
lighting needs throughout the space, always keeping in mind that higher illumination
levels than necessary are likely to waste energy while on the other hand, levels lower
than needed could impair visual effectiveness. (Table 3.1 2007 of the DoE Guidelines on
Energy Conserving Design of Buildings lists the recommended illuminance levels.)
The most efficient lamps appropriate to the type of lighting, color rendition and color
appearance shall be selected. The use of such types of lamps reduces power
requirements. (Refer to Table 3.2 of the DoE Guidelines on Energy Conserving Design of
Buildings re Efficacy Ranges and Color Rendering Indices of Various Lamps.)
In selecting lighting systems, the costs of operation and energy usage and not simply
the initial cost should be considered.”
E.5.7
Sustainable Design for Buildings
E.5.7.1
Basic Sustainable Design Compliances with P.D. No. 1096, the 1977 National Building Code of
the Philippines (1977 NBCP)
There are several basic sustainable design provisions under P.D. No. 1096 (otherwise
known as the 1977 National Building Code of the Philippines (NBCP), particularly
under its 2004 Revised Implementing Rules and Regulations (IRR), and partly under
some of its Referral Codes (RCs, covering certain building safety aspects and physical
planning/ building design sensitivities) and under some derivative regulations (RCs).
These all form part of nationally-instituted sustainable development controls that are
all intended to prevent over-building and over-paving, both nuisance practices by
some building designers and constructors that have a very negative effect on both the
natural and built environments.
Below is the matrix showing an example of the application of the basic sustainable
development controls under P.D. No. 1096 (NBCP) to help make buildings of truly
sustainable design i.e. effectively making Green Buildings.
In general, the normal artificial light source should be the fluorescent lamp. In downlight installation, high-pressure discharge lamps can be used. In large high bay areas,
high-pressure discharge lamps should be used. Where good color rendering is
required, the tubular fluorescent lamp and other high-pressure discharge lamps
except high-pressure sodium lamps should be used. However, if moderate color
rendering is of comparatively minor importance, high-pressure sodium lamps can be
used. If very good color rendering is required, the tubular fluorescent lamp should be
used.
E-49
E-50
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
which do not provide transparency to the interior. Only exterior wall surfaces are
counted in the ratio, and not roof surfaces.
Table E-6
The WWR is often a factor in the energy efficiency of a building, with a low ratio
generally indicating better efficiency as windows usually perform less well than the
rest of the exterior walls as a thermal barrier. Note however that while windows may
not be thermally ideal due to the heat that is permitted to penetrate the building
interior i.e. which has to be balanced by artificially cooling the building interior, its
energy efficiency value lies in the amount of natural light that it draws inside the
building i.e. thereby helping reduce the artificial lighting load.
Example of the Application of the Basic Sustainable Development Controls
under P.D. No. 1096 (NBCP)
Applicable Basic Sustainable Development
Compliances with Basic Sustainable Development Control/s
Control/s Under P.D. No. 1096 (the 1977 NBCP)
as applied to a Public School Building Project Development Control to
be Satisfied
Compliances by the
Remarks
on a Corner-Through Lot (or a Corner Lot
for a Public School
Building Project
Abutting 3 or More Streets)
Building Project
Allowable maximum building footprint (AMBF) or
maximum percentage of site occupancy (PSO)
AMBF or Maximum PSO Building Footprint of
Fully compliant and is
set at 60.0% of the Total 3,198.12 sqm results in a LOWER than the maximum
Lot Area (TLA) of 5,464.64PSO of only 58.52% of thePSO by 1.48% of the TLA.
sqm
TLA
Building Height Limit (BHL)
BHL at 15.0 meters (or 5 BHL at only (approx.) 13.5 Fully compliant and is
regular storeys)
meters
LOWER than the set BHL
by 1.5 meters
Floor to Lot Area Ratio (FLAR)
Maximum FLAR at 2.5
times TLA
Gross Floor Area (GFA)
Maximum GFA at 2.5 timesGenerated GFA of approx.Fully compliant and is
TLA
4,302.08 sqm is at only LOWER than the maximum
(approx.) 0.79 of the TLA GFA by 1.71 times the TLA
Total Gross Floor Area (TGFA)
Maximum TGFA at
approx.1.25 times GFA
Total Window Surface Area (TWSA) to TGFA RatioTWSA at a minimum of
10% of TGFA
Unpaved Surface Area (USA) or Unpaved Open
Spaces
The entry of controlled amounts of natural light into the building interior is an
absolute necessity in helping prevent the sick building syndrome, engendered by the
unchecked growth of harmful microorganisms e.g. spores, etc. that may thrive within
dark and damp interior building spaces.
Applied FLAR at only
Fully compliant and is
(approx.) 0.78 times TLA LOWER than the maximum
FLAR by 1.71 times the
TLA
Generated TGFA of 5,377.6
Fully compliant
sqm is at 1.25 times GFA
TWSA at approx. 10.4% ofFully compliant and
TGFA
EXCEEDS the set minimum
by 0.4% of TGFA
Minimum USA at approx. Generated USA of 1,965.05
Fully compliant and
30% of the TLA
sqm is at approx. 35.96% of
EXCEEDS the set minimum
the TLA
by 5.96% of TLA
Minimum Required Parking Slot, Parking Area and One (1) car slot for every Off-RROW (street) open Fully compliant
Loading Space Requirements
five (5) classrooms: one (1)parking provisions include:
off- road right-of-way
Eight (8) slots facing the
(RROW/ street) (or offNEC Building;
street) passenger loading One (1) off- road right-ofspace that can
way (RROW/ street) (or offaccommodate two (2)
street) passenger loading
queued jeepney/ shuttle space that can
slots; and one (1) school accommodate two (2)
queued jeepney/ shuttle
bus slot for every two
hundred (200) students slots;
one (1) school bus slot for
every two hundred (200)
students; and
two (2) parking slots for
loading/ unloading trucks
(which can accommodate 4
regular cars when not in
use).
While not explicitly provided for in the 2004 Revised IRR of the 1977 NBCP, the
window-to-wall ratio (WWR) of a building is the percentage (%) of a building's facade
taken up by windows i.e. the percentage of the exterior building walls taken up by
light-transmitting (i.e. transparent or translucent glazing) surfaces, including
windows and translucent surfaces such as glass bricks, thereby implying that natural
ventilation via operable windows is not necessarily a factor in the determination of
the WWR. The WWR does not include glass surfaces used ornamentally or as cladding,
E-51
Based on certain trends, it may be reasonable to say that for a typical building, an
optimal 30% WWR for hot-humid tropical settings (like in the Philippines) may be
enough to exploit daylight (i.e. too much daylight inside the building interior is also
not a desirable situation), since there is no significant increase in daylight availability
for larger or taller window sizes and since there is need to balance the intensity of the
building interior-penetrating daylight via opaque surfaces.
E.5.7.2
As an example, a WWR of 29.0% is well within the desired WWR range, helping make
the building truly sustainably designed i.e. effectively making it a Green Building.
Carbon Reduction (and Embodied Energy) of Construction and Finishing Materials Specified/
Used for Buildings
Carbon reduction is a complex challenge for all organizations, not least those in the
construction industry i.e. taking a comprehensive view of the construction sector
value chain means considering all aspects of the design, construction, use (and
demolition) of buildings and infrastructure, beyond simple occupancy itself. Any
energy efficiency improvements in building occupancy mean that the carbon emitted
indirectly through the supply chain could form an even larger proportion of that
building's lifetime footprint.
This indirect, embodied carbon (or spent energy) arises from the extraction of various
raw materials, the energy intensive processes associated with the manufacture,
handling/ transportation/ delivery, installation, use, maintenance, etc. of the building
materials, and the activities of a multitude of constructors i.e. embodied energy of
construction and finishing materials as discussed in the previous section.
With the processes to be monitored and managed lying beyond direct control of the
industry's main developers and prime constructors, construction organizations must
reduce carbon throughout their extended supply chains. After all, this is a growing
priority because, in addition to the environmental benefits, where there's carbon
there's cost, and where there's cost there could be savings i.e. benefits to both the
building owner and the general public.
Hereafter are some concepts that were partially or substantially incorporated in the
physical planning and design of a building project:
Review the selection of raw materials: The extraction, production and
transportation of basic construction materials are both energy- and carbon-intensive,
E-52
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
so it is critical to select suppliers of building products and materials who are actively
working to manage their own carbon impacts.
Investigate the origin of the raw materials: Natural stone, for example, produces
minimal emissions during the production process but the transportation from the
source to manufacturing site can be the largest cause of emissions, e.g. in transporting
from quarry sites. In such cases, managing the transportation process is crucial to
managing supply chain emissions. This contrasts with concrete where typically the
carbon emissions during production are much higher than those released during
transportation.
Consider construction phase emissions: Key factors contributing to construction
process emissions include the multiple, temporary sites, transportation, waste arising,
and heavy machinery which are common for large building projects.
Consider how to influence the occupancy and use of buildings and
infrastructure: These “downstream” emissions are generated in the occupancy/ use
phase but are greatly influenced by specifications from architects, choices made by
developers and building owners, and from the way the buildings are used by the
people who ultimately work and live in them. The purpose and design of a building
also contributes to its embodied carbon. The people using it, the use of lighting,
heating, ventilation and air conditioning, and the proportions and differing insulating
properties of glass, metal, concrete, masonry (plaster, brick, etc.) and wood can all
have a tangible impact on the carbon footprint.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
does the device produce more energy or save more energy than it took to make it (or
make it usable/ beneficial)?
Embodied energy is an accounting method which aims to find the sum total of the
energy necessary for an entire product life-cycle. Determining what constitutes this
life-cycle includes assessing the relevance and extent of energy into raw material
extraction (sourcing), transport (and handling), manufacture, assembly, installation,
dis-assembly, deconstruction and/or decomposition (and disposal) as well as human
and secondary resources. Different methodologies produce different understandings
of the scale and scope of application and the type of energy embodied. Source :
Wikipedia (with some additions/ edits from PTCC Project Team)
A matrix showing the embodied energy levels of the construction and finishing
materials specified and used for a typical public building is provided in Table E-7.
Most of the construction and finishing materials specified/ used for the sample public
building are locally sourced and have only low to medium qualitative embodied
energy ratings, thereby helping make the building of truly sustainable design i.e.
effectively making it a Green Building.
Being mindful of these factors, good examples of design, coupled with good occupier
habits and behaviours, can generate a lower carbon impact during end use as well as
construction e.g. buildings using locally-sourced, sustainable timber, ground-source
heat pumps using natural energy to provide heating and cooling, rainwater harvesting
and grey water recycling facilities to provide 100% of toilet water use and thereby
help to reduce overall water consumption by as much as 20%.
Key concerns for the design and construction teams were:





Manage carbon throughout the construction supply chain/s;
Measure the footprint of individual products in order to identify carbon “hot
spots” (carbon intensive areas e.g. Areas with equipment that are heavy power
users) and focus efforts on carbon reduction;
Suggest the use of suppliers that offer low carbon products and those that can
demonstrate a consideration for both the direct and indirect impacts of their
products and services;
Conceptualize a carbon strategy and implementation plan; and
Understand the likely carbon footprint generated in the occupancy/ use phase,
and encourage the building owner/ end-users to plan for sustainability
throughout the useful life of the building. Source : carbon trust : building a lower
carbon construction Industry (with paraphrasing and additions/ edits from PTCC
Project Team)
Embodied Energy is the sum of all the energy required to produce goods (materials)
or services, considered as if that energy was incorporated or “embodied” in the
product itself. The concept can be useful in determining the effectiveness of energyproducing or energy-saving devices, or the "real" replacement cost of a building, and,
because energy-inputs usually entail greenhouse gas emissions, in deciding whether a
product contributes to or mitigates global warming. One fundamental question is:
E-53
E-54
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table E-7
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Embodied Energy Levels of the Construction and Finishing Materials
Specified and Used for a Typical Public Building
Common Building Construction or Architectural Finishing
Materials for A Typical Public Building
Material Source
Qualitative
Embodied
Energy
Rating (EER) of Materials Used
Local
Negligible to Low to
High to
Very Low
Medium Very High
Foreign
Common Building Construction Materials Used
√
Premium termiticide concentrate
x
Pre-mixed concrete
x
√
Basic steel (hot-dipped galvanized)
x
√
Zinc-chromate corrosion resistant agent
x
Bituminous waterproofing paint
x
Extruded aluminum frames
x
Tanguile lumber (kiln-dried)
x
√
Medium density fiberboard (MDF)
x
√
√
√
√
Membrane waterproofing
x
√
Cementitious waterproofing, 90 mils thick
x
√
Pre-painted long span cold roll steel, coil coated (pre-painted)
aluminum zinc alloy roof panels
x
√
19 mm tempered glass sheets with film for UV protective layer
x
√
Tanguile marine plywood
x
Polyvinylchloride (PVC) conduit
x
√
Intermediate metal conduit (IMC)
x
√
Electrical metallic tubing (EMT)
x
√
Flexible steel conduit (FSC)
x
√
Thermoplastic insulated wire (TIW) and cables (TIC)
x
√
Thermoplastic cover plates for wiring devices
x
Diesel engine electric generating unit with accessories, auxiliary
equipment
√
√
√
Long fluorescent: T-8, 3000K, energy-savings type
x
√
Electronic digital ballasts (EDB)
x
√
Galvanized iron, (GI) main water lines, schedule 40
x
√
x
√
Common Architectural Finishing Materials Used
E-55
Negligible to Low to
High to
Very Low
Medium Very High
Foreign
√
x
x
√
9. Gypsum wallboard and ceiling board
x
√
10. Metal spandrel ceiling for eaves
11. Acoustical boards, fine- fissured
12. Toilet fixtures, vitreous china
13. Toilet compartments, 12 mm thick “phenolic” board with laminate
finish
√
x
x
√
√
x
x
√
1. All paints (non-toxic and contain an effective amount of fungicide x
and mildew-proofing agent to prevent the paint from showing a mold
growth or shall be inherently fungistatic by the nature of their
constituents)
√
2. Flatwall & quick dry enamel, oil-based
x
√
3. Gloss varnish, lacquer solvent
x
√
4. Exterior wall masonry liquid water repellant, water-based alkyl
silane
x
√
5. Plain cement floor
x
√
6. Ceramic tiles, heavy traffic
x
√
Initially Calculated Carbon Footprint for a Typical Low-Rise Public Building
"A measure of the total amount of carbon dioxide (CO2) and methane (CH4)
emissions of a defined population, system or activity, considering all relevant
sources, sinks and storage within the spatial and temporal boundary of the
population, system or activity of interest. Calculated as carbon dioxide
equivalent (CO2e)
using
the
relevant
100-year global
warming
potential (GWP100)."
√
x
High density polypropylene pipes to fixtures, type 3 (or high density
cross-linked polyethylene pipes), type PE-Xa with disinfectionresistant compression sleeve fittings
Local
A carbon footprint has historically been defined by Championne as "the total sets
of greenhouse gas (GHG) emissions caused by an organization, event, product or
person." However, calculating the total carbon footprint is impossible due to the large
amount of data required and the fact that carbon dioxide can be produced by natural
occurrences. It is for this reason that Wright, Kemp, and Williams, writing in the
journal Carbon Management, have suggested a more practicable definition:
√
x
x
Qualitative
Embodied
Energy
Rating (EER) of Materials Used
8. Epoxy paint
E.5.7.3
x
Receptacles, hospital grade, 220V, grounding type
7. Vinyl floor tiles
Material Source
√
High pressure laminate (HPL)
Annealed copper wire for conductors
Common Building Construction or Architectural Finishing
Materials for A Typical Public Building
Greenhouse gases can be emitted through transport, land clearance, and the
production and consumption of food, fuels, manufactured goods, materials, wood,
roads, buildings, and services. For simplicity of reporting, it is often expressed in
terms of the amount of carbon dioxide, or its equivalent of other GHGs, emitted.
Most of the carbon footprint emissions come from "indirect" sources, i.e. fuel burned
to produce goods far away from the final consumer/ end-user. These are
distinguished from emissions which come from burning fuel directly in one's car or
stove, commonly referred to as "direct" sources of the consumer's/ end-user’s carbon
footprint, where the term end-user can refer to the building constructor, owner
and/or occupants.
The concept name of the carbon footprint originates from the concept of the ecological
footprint, discussion for which was developed by Rees and Wackernagel in the 1990s,
and which estimates the number of "earths" that would theoretically be required if
everyone on the planet consumed resources at the same level as the person
calculating their ecological footprint. However, carbon footprints are much more
specific than ecological footprints since they measure direct emissions of gases that
cause climate change into the atmosphere.
Measuring Carbon Footprints
An individual's, nation's, or organization's carbon footprint can be measured by
undertaking a GHG emissions assessment or other calculative activities denoted
as carbon accounting. Once the size of a carbon footprint is known, a strategy can be
E-56
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
devised to reduce it, e.g. by technological developments, better process and product
management, changed Green Public or Private Procurement (GPP), carbon capture,
consumption strategies, and others.
Several free online carbon footprint calculators exist, where the pertinent websites
ask you to answer more or less detailed questions about transportation choices,
building size, activities, usage of electricity, heating, and heavy appliances, etc. The
website then estimates the carbon footprint based on the answers to such questions.
The mitigation of carbon footprints through the development of alternative projects,
such as solar or wind energy (done onsite or offsite) or reforestation (done offsite),
represents one way of reducing a carbon footprint and is often known as carbon
offsetting.
The main influences on carbon footprints include population, economic output, and
energy and carbon intensity of the economy. These factors are the main targets of
individuals and businesses in order to decrease carbon footprints. Scholars suggest
the most effective way to decrease a carbon footprint is to either decrease the amount
of energy needed for production (including construction) or to decrease the
dependence on carbon emitting fuels (during actual building use/ occupancy).
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Table E-8
Initially Calculated Carbon Footprint for a Typical Low-Rise Public Building
Non-Food Carbon-Consuming Components for a Typical
Low-Rise Public Building During Construction Onsite
and During Projected Use/ Occupancy of the Building
(Over a One Year Period)
B. Calculated Carbon Footprint
Quantity
Carbon Dioxide
Unit of Carbon equivalent (CO2e)
Consumption in metric tons (MT)
Initially Calculated Non-Food Carbon Consumption During Construction Onsite (Over an Aggregated One Year
Period)
Lighting and power consumption onsite
Say 36,000
KwH
20.03
LPG (cooking gas for worker meals)
Say 1,430
Liter
2.10
Three (3) service vehicles i.e. mainly cars and SUVs aged
Say 429
from six (6) to ten (10) years old
Vehicle Unit
76.44
Two (2) service vehicles i.e. mainly trucks aged from six (6)
Say 572
to ten (10) years old
Vehicle Unit
101.92
Fuel for Various Heavy Equipment onsite
Liter
4.20
Say 2,860
Subtotal for I.
204.69
Initially Calculated Non-Food Carbon Consumption During Projected Use/ Occupancy of the Building (Over the First
One Year Period)
Lighting and power consumption
Say 72,000
KwH
40.05
LPG (cooking gas for cafeteria)
Say 1,430
Liter
2.10
Other Ways to Reduce Carbon Footprint
Ten (10) service vehicles i.e. mainly cars and SUVs aged
Say 1,430
from six (6) to ten (10) years old
Vehicle Unit
254.80
The most common way to reduce the carbon footprint of humans is to Reduce, Reuse
and Recycle. The reduction of the carbon footprint is addressed in the previous
section on carbon reduction and embodied energy of construction and finishing
materials for the building. Nothing should be disposed off into the soil i.e. all the
ferrous (metal) materials which are prone to degrade or oxidize with time should be
sold as early as possible at reduced price. This can also be done by using reusable
items rather than disposable ones. If that option isn't available, it is best to properly
recycle the disposable items after use. When one recycles at least half of their waste,
they can potentially save a minimum of 1.2 tons of carbon dioxide annually.
Two (2) service vehicles i.e. mainly trucks aged from six (6)
Say 572
to ten (10) years old
Vehicle Unit
101.92
Subtotal for II.
398.87
Total for I. and II.
603.56
Yet another option for reducing the carbon footprint of humans is to use less airconditioning in the building i.e. introduce passive cooling techniques since the
Philippines is in a hot-humid tropical location. By adding insulation to the walls and
roof of a building, and installing weather-stripping around doors and windows, one
can also lower their artificial ventilation costs. Setting the thermostat just two (2)
degrees lower in summer could potentially save about 1 ton of carbon dioxide each
year (for possibly each cooling unit). Source: Wikipedia (with some additions/ edits
from PTCC Project Team)
Based on the use of the UK-based Carbon Footprint calculator (at
http://www.carbonfootprint.com/calculator.aspx), the matrix hereafter shows that
the approximated carbon footprint for a typical low-rise public building during its
construction (aggregated 1.0 year period) and initial use/ occupancy (over its first 1.0
year period), which altogether may total 603.56 metric tons (MT) in carbon dioxide
equivalent (CO2e) units, a relatively low building carbon footprint, thereby helping
make the building of sustainable design i.e. effectively making it a Green Building.
E-57
E-58
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.6
Non-Mobile Billboards (NMBs)/ Electronic Displays and
Signages
Policy: It is the declared policy of the State to ensure an improved quality of life for all
through continuing efforts to improve the natural/ built and physical/ non-physical
environments. It is also the policy of the State to preserve public spaces as public
domain and not to allow the use of such spaces for private enjoyment nor benefit.
Definition of Terms: As used in these DGDG, the following terms shall be as defined
hereafter:
“ABO” or Acting Building Official is the official designation of the DPWH for its LGU
appointees under Sec. 477 of the LGC, and who are tasked with the implementation
and enforcement of the NBCP and its derivative regulations.
“Air Right” means the right to physically develop and subsequently benefit or profit
from the continued use of the air space above the NATIONAL AND LOCAL road rightof-way (RROW) or other NATIONAL AND LOCAL rights-of-way (ROWs) or legal
easements or private/ public property outside or along such ROWs or easements
within the jurisdiction of the pertinent LGU, subject to the payment of lease to the
appropriate public party for availing of such rights. The upper limit of the air rights is
the airways navigational path such as the clearance limits of aerodrome and flight
patterns (particularly for helicopters using helipads within the LGU) and the partial
availment of such air rights shall require the official evaluation and permission of the
Civil Aviation Authority of the Philippines (CAAP).
“Alignments” are the surface areas/ spaces traversed by a NATIONAL RROW, similar
ROWs, legal easements or similar public spaces within the LGU, which form part of the
public domain and are therefore disallowed sites for non-mobile billboards.
“barangay” means the basic government unit distinct from the LGU.
“Billboard and Electronic Display” means an attention-getting device in the form of
notices/ signages/ graphics/ images visible to public view, that are designed to
promote, entice, sell, offer, for commercial purposes, a product or services, and
consisting of a support structure, a display or message area, a lighting system and
related components. The term also refers to all types of identification, description,
illustration, images, pictures, display or device which is affixed to or represented
directly or indirectly upon a portion of a building/ structure, support structure or land
and which directs attention to a product, place, activity, person, institution, business,
idea or belief. The term shall be generic and shall collectively refer to but not be
limited to multi-media or tri-vision billboards, neon, electronic displays or other
illuminated signs, painted signs and the like. The classifications of the key types of
billboards that may be erected at the defined regulated areas under these DGDG; nonmobile billboards (NMBs)/ electronic displays shall only be permitted in the zones
defined under these DGDG while the Permitted Construction shall only be within
private lots inasmuch as NMBs/ electronic displays are prohibited in all parts of and
types of ROWs i.e. streets, utilities, rivers/ water bodies, including mandated legal
easements (MLEs), unless specifically recommended under these DGDG;
“Billboard or Electronic Display Unit” or “BEDU” shall refer to one (1.0) independent
NMB or electronic display with a total display area of anywhere between seven point
five square meters (7.5 sqm) minimum to two hundred twenty five square meters
(225.0 sqm maximum, including border and trim but excluding supports) maximum
for existing/ proposed NATIONAL urban RROWs/ ROWs within the LGU. For NMBs/
E-59
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
electronic signs mounted on facades of buildings, the BEDU shall be sized in
accordance with the zoning classification and in proportion to the building height limit
(BHL), architectural projections and outermost face of buildings/ billboards (OFB),
the outermost limit of building projections (OLBP) and the permissible proportions of
openings/ fenestrations for mandated natural light and ventilation and related
provisions under the NBCP as well as the various safety provisions under the FCP,
duly determined by a RLA.
“Building Height Limit or BHL” means the maximum height to be allowed for a
building/ structure based on their proposed use/occupancy. As defined under the
NBCP, the BHL is generally measured from the established grade line to the topmost
portion of such a building/ structure, inclusive of a non-mobile billboard mounted on
top of such a building/ structure. Under this Ordinance, BHL shall also mean Billboard
Height Limit.
“Cantilevered Support Structure” means a support structure that is not directly
planted on the ground or any portion of the national RROW, similar ROWs or legal
easement within the LGU; such a structure may rest on a portion of a building or
another support structure not originally planned/ designed to support a billboard; a
cantilevered structure is necessary so that the effective width of the sidewalk or
similar components of the RROW are neither compromised nor lessened;
“Carriageway” or “Roadway” means the portion or component of a national RROW
within the LGU, on which land-based transportation conveyances such as motor
vehicles are allowed to pass or park. For national RRROWs within the LGU, the term
may be “Railway” and for national WROWs within the LGU, the applicable term may
be “Waterway” or “Vessel-way”.
“Content” means the message and image components of a billboard or electronic
display which may be advertising, commercial, directional or general public
information in intent.
“DILG” means the Department of Interior and Local Government.
“DOTC” means the Department of Transportation and Communication which
maintains exclusive control over certain types of national ROWs and RROWs. “DPWH”
means the Department of Public Works and Highways which maintains exclusive
control over national road rights-of-way (RROWs) within the LGU and which is the
primary implementing agency and enforcer of the NBCP, its 2004 or latest
implementing rules and regulations (IRR), its applicable referral codes (RCs such as
R.A. No. 9514, the 2008 FCP and its 2009 IRR, the National Structural Code of the
Philippines/ NSCP, 2010 or latest edition, the Philippine Electrical Code, latest edition,
the Electronics Code, if any in its latest edition, etc.) and its applicable derivative
regulations (DRs including National Executive Orders (EOs), National Administrative
Orders (AOs), DPWH Department Orders/ DOs, DPWH Department Administrative
Orders/ DAOs and DPWH Memoranda Circulars/ MCs).
“Display or Electronic Display” means the material or device mounted on the nonmobile billboard or electronic display support structure together with its content/
message. A display/ electronic display surface area in excess of one square meter (1.0
sqm), with a least dimension of one meter (1.0 m), shall be considered part of a NMB/
BEDU.
“FCP” means the 2008 Fire Code of the Philippines, otherwise known as R.A. No. 9514
or its future iterations, duly supported by its 2009 and/ or latest IRR and/or related
E-60
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
executive issuances by the DILG, the agency tasked with its full implementation and
enforcement.
“Firewall” means a reinforced masonry or reinforced concrete separator with the
appropriate fire-resistive rating and which shall be positioned between buildings/
structures to maintain the fire integrity of each building/ structure. Firewalls that are
erected along and/or above property lines utilize a substantial portion of the
maximum development potential of a property and shall therefore have no openings
except for the permitted vent wells specified under P.D. No. 1096, the 1977 National
Building Code of the Philippines (NBCP) and its 2004 and/ or latest Implementing
Rules and Regulations (IRR). Firewalls are not envisioned as a mounting surface for
billboards and other types of display under the NBCP and its IRR as such billboards/
displays also constitute a fire and safety hazard to an adjoining property.
“IRR” means the Implementing Rules and Regulations of this Ordinance.
“Intersections” are common surface areas or spaces shared by two (2) or more
national RROWs, similar ROWs or legal easements within the LGU, or a mix of such
public spaces, which form part of the public domain and are therefore disallowed sites
for non-mobile billboards.
“LGC” - the 1990 Local Government Code, otherwise known as R.A. No. 7160 and its
derivative regulations as implemented and enforced by the DILG.
“LGU” – The Local Government Unit of Makati City, as defined under the LGC.
“Legal Easement” means a public open space mandated under law that must be
absolutely free of all forms of physical obstructions that can negatively affect natural
light and ventilation within such a space or that can impede access to or the full
recreational use of such a space by the general public. Legal easements also refer to
the public area within the LGU that may lie between the legally usable portions of a
private/public property and natural or built bodies of water or waterways.
“Lighting System” means the luminaries/ complete lighting units, power source and
connections, controls and all support structures/ devices that ensure the continuous
illumination of a display/ electronic display.
“MMDA” means the Metropolitan Manila Development Authority.
“Minimum BEDU” shall refer to one (1.0) display with a total display area of seven
point five square meters (7.50 sqm), with a least dimension of one meter (1.0 m).
“Maximum BEDU” shall refer to one (1.0) display with a total display area of two
hundred and twenty five square meters (225.0 sqm), with a least dimension of seven
point five meters (7.5 m).
“NBCP” means the 1977 National Building Code of the Philippines, otherwise known
as Presidential Decree or P.D. No. 1096 or its future iterations, duly supported by its
2004 and/or latest IRR and/or related executive issuances by the DPWH, the agency
tasked with its full implementation and enforcement, particularly in the case of the
DPWH NBCDO Memorandum Circular No. 1, series of 2008.
“NBO” or National Building Official is the official designation of the DPWH Secretary as
per the NBCP.
“Non-Conforming Billboard/ Electronic Display Unit (BEDU)” means any non-mobile
billboard or electronic display lawfully constructed prior to the enactment of this
Ordinance, but which thereafter fails to conform to its provisions.
E-61
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
“Non-Mobile Billboard/ Electronic Display Unit (BEDU)” means a billboard/ electronic
display positioned at a fixed location, usually along a NATIONAL road right-of-way
(RROW) within the LGU, where it can be readily and continuously viewed by the
passing public.
“Official Signs” mean directional or information-conveying signs, in whatever form
allowed under the IRR of this Ordinance, that are officially issued and erected by or
through the national government or by the LGU for the purpose of public service.
“PCE” - professional communications engineer.
“PEE” - professional electrical engineer.
“Property Line” means the imaginary or defined line or a set of such interconnected
lines and denoting the limits of a property.
“RLAr” - registered and licensed architect.
“RLCE” - registered and licensed civil engineer.
“RLEnP” - registered and licensed environmental planner.
“ROW” means a national Right-of-Way, including the airspace and the leasable air
rights above such a ROW within the LGU.
“RROW” or national “Road-Right-of-Way” or “Street” means a public open space
within the LGU, for the continuous flow of pedestrian and vehicular traffic, including
the air space above such RROW, that must be free of all forms of prohibited physical
obstructions. The national RROW or street within the LGU is the surface area lying
between two (2) or more parallel properties and its width is horizontally measured
from opposite property lines.
“RRROW” means a national Railroad-Right-of-Way within the LGU, consisting of the
railway/ tramway/ tracks on which the trains actually pass, the buffer areas on either
side of the railway for operational safety and fixed facilities for passenger exchanges,
inclusive of the airspace above such a RRROW.
Regulated Area means all areas inside the boundaries of the LGU which are adjacent to
and within fifty meters (50.0 m) of the edge of the national road right-of-way (RROW)
within the LGU (applicable to NMBs only).
“Residual Areas” are spaces that may fall outside the alignments or intersections of
two (2) or more national RROWs, similar ROWs or legal easements or a mix of such
public spaces within the LGU, which still form part of the public domain and are
therefore disallowed sites for NMBs.
“Scenic Vista” shall refer to a naturally occurring or a good combination of natural and
artificial/man-made features in the viewable landscape and which offers the viewer a
refreshing visual experience or respite.
“Setback” means a one (1)-dimensional quantity denoting the level horizontal distance
measured at a ninety degree angle (90˚) from the line formed by the outermost face of
a building/ structure or billboard/ electronic display support structure to a property
line, whereby both lines run parallel to each other.
“Sidewalk” means the portion on each side of the national road right-of-way (RROW)
within the LGU, for the exclusive use of pedestrians and the disabled who are in
transit.
E-62
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
“Signages” are devices limited to identifying location/ addresses and names of
establishments, as distinguished from NMBs/ electronic displays which offer goods/
services to consumers, but like non-mobile billboards/ electronic displays, these are
exposed to public view and therefore come under “public safety, public welfare, and
public domain”, and as per local/ national enabling laws (e.g., R.A. No. 7160, the 1991
Local Government Code of the Philippines/ LGCP and its latest IRR), are therefore
subject to the permitting processes, regulations, and the imposition of taxes, fees and
charges by the LGU, as provided for in this Ordinance.
“Support Structure” means the rigid framework on which the display/ electronic
display or attention-catching device of a non-mobile billboard/ electronic display shall
be mounted. The foundation and superstructure for part of the support structure.
“Temporary Sign” means a sign made of fabric/ cloth, vinyl/ plastic or similar light
and/or combustible material, with or without frame i.e., streamers, bills, posters and
the like that are installed within or outside a ROW within the LGU, for display/public
viewing for a limited period of time, subject to the issuance of the required permit/s.
‘Urban Design” - refers to the physical and systematic design undertaken by a RLA on
a community and urban plane, more comprehensive than, and an extension of the
architecture of buildings, spaces between buildings, entourage, utilities and
movement systems, including the siting, sizing and placement of NMBs/ electronic
displays and signages.
“UROW” means the Utility Right-of-Way means the area within the LGU on which
public utility lines e.g. power, telecommunications, water supply, drainage, sewer, gas,
etc. are allowed to pass, including buffer/ safety zones, service/ maintenance areas
and the airspace above such a UROW.
“View Corridor” means the visually unobstructed width, depth and height of all
available sight lines running through and along national RROWs, legal easements and
similar ROWs, open spaces within lots including yards and courts or through and
along designated public spaces including recreational areas within the LGU. View
corridor also means specific ranges of sight lines from a building or structure to a
specific natural or man-built object and/ or development considered of beauty or
value.
“WROW” means a national Water Right-of-Way found in inland waterways such as
rivers, streams, canals and the like found within the LGU, and consisting of the
waterway/ vessel-way on which boats/ ships/ barges pass, the embankments and
portions of the shore areas used to access the waterway/ vessel-way, including the
airspace above such a WROW.
E.6.1
“Yard” means a two (2)-dimensional space consisting of the vacant land area between
the outermost portion of a NMB/ electronic display including its support structure
and the property lines.
Regulation of NMBs/ Electronic Displays within a LGU
Any NMB or electronic billboard erected, modified, retrofitted, rehabilitated or
otherwise altered and exhibited shall comply with the following requirements:
E-63
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.6.1.1
Position Within/ Along National RROWs, ROWs and Legal Easements within the LGU
No NMB/ electronic display shall be located in a position that obstructs or obscures
the view of vehicular or pedestrian traffic in such a manner as to endanger their safe
movement thereof. NMBs shall not be erected in a manner that can confuse or
obstruct the view or interpretation of any official traffic sign, signal or device.
The outermost portion or projection of a NMB/ electronic display or its support
structure or its lighting system shall be located at least five meters (5.0m) from the
outermost line of the national street or RROW, RRROW, UROW, WROW, legal
easement and the like.
Non-mobile billboards/ electronic displays shall not be erected on any structure or
portion thereof found within the national RROW, RRROW, UROW, WROW, legal
easement and the like. The air rights over such ROWs and legal easements shall not be
availed of for the purpose of erecting NMBs. As such, no part of a NMB shall extend
over any part of the RROW at grade or above grade.
Temporary signs, regardless of material, intended use and size, including electionrelated signs or signs showing the names and/or likeness of elective/ appointed
officials, shall not be strung or installed over or across a national RROW, RRROW,
UROW, WROW, legal easement and the like, unless otherwise permitted by the
barangay concerned or by the LGU but in no case shall the period of display exceed
seven (7) calendar days. The barangay or LGU must thereafter remove said temporary
sign/s.
Reckoned from the edge of the national RROW within the LGU, all large NMB/
electronic billboard displays i.e. in excess of thirty square meters (30.0 sqm) in display
area shall have a minimum clear/ unobstructed viewing distance of twenty five
meters (25.0 m).
No NMB/ electronic display shall be located within more than two hundred meters
(200.0m) of the outermost portion of all interchanges or of the outermost portion of
the national right-of-way (ROW) of all underpasses, overpasses, bridges, tunnels,
station/ terminal/ inter-modal/ multi-modal structures and the like or from the
center of an intersection. For existing/ proposed national RROW widths of forty
meters (40.0m) wide or wider, a distance of from fifty to one hundred and fifty meters
(50.0m to 150.0m) shall apply.
No part of a NMB/ electronic display including its support structure shall be placed on,
in or over any public property/ domain, including national public/
transportation/utility ROWs or utility/drainage easements or upon telephone/utility
poles or upon natural features such as trees, rocks and the like. In particular, nonmobile billboards/ electronic displays shall not be erected or maintained or violate
the air rights above a carriageway/ roadway, railway or waterway/ vessel-way.
NMBs/ electronic displays shall not be erected at residual areas at or along
intersections of national RROWs, RRROWs, ROWs and legal easements or at or along
intersections of such public spaces.
NMBs/ electronic displays that may obscure or obstruct the view of vehicular or
pedestrian traffic or that may interfere, imitate, resemble or be confused with official
traffic signs, signals or devices shall not be permitted. No NMB/ electronic display that
prevents a clear and unobstructed view of official traffic signs in approaching or
merging traffic shall be permitted.
E-64
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
No NMB/ electronic display that may impair any scenic vista or view corridor from the
national RROW/ legal easement or from a building/ structure along such RROW/ legal
easement shall be permitted.
properties, unless a current and valid lease agreement for the use of such air rights
exists.
A NMB/ electronic display mounted on a fire-walled property shall not utilize the air
rights of a private/ public property adjoining such a fire-walled property without the
written consent of the property owner or lawful possessor of the affected property
and without the permit of the barangay concerned or the LGU. In case of the presence
of official consent by the affected property’s owner or lawful possessor for a firewallmounted NMB/ electronic display, the same may opt to share in the income that may
be derived from the NMB/ electronic display in exchange for the use of the air rights.
In case of the lack of consent or refusal by the affected property’s owner or lawful
possessor for a firewall-mounted NMB/ electronic display, only a painted display may
be placed on the firewall, still subject to the prior consent of the affected property’s
property owner or lawful possessor and to the prior permission of the barangay
concerned or the LGU. Neither a NMB/ electronic display mounted on the firewall nor
a display painted on the firewall shall be allowed if there is lack of consent or official
refusal/ objection by the affected property’s owner or lawful possessor.
NMBs/ electronic displays may only be single-faced or double-faced. In the case of
a double-faced NMBs/ electronic displays, the allowed display surface area/ BEDU on
each face shall not exceed one hundred twenty five square meters (125.0 sqm) per
BEDU/ display/ face, a maximum size that must be proportional to the RROW width
e.g. for RROWs that are 40.0 m or wider, provided that applicable setback, yard and
building height limit (BHL) requirements of the NBCP and its IRR are satisfied.
Triple, quadruple or higher multi-faced non-mobile billboards/ electronic displays
shall not be allowed as these are already configured as buildings or solid structures
that unnecessarily block natural light and ventilation and pose public safety problems.
E.6.1.2
NMBs/ electronic displays shall not be placed within or above any portion of a RROW
or ROW, particularly at the sides, below or on top of the exterior of public structures
such as elevated expressways and transit alignments/ stations/ terminals and the like
which occupy the RROW, including the airspace/ air rights above such RROWs/
ROWs, but may be allowed at the enclosed sides of loading platforms and pedestrian
access-ways at such public structures.
Position within Private Property or Public Property Outside RROWs/ ROWs/ Legal Easements
within the LGU (including those mounted on building facades and firewalls)
All NMBs/ electronic displays shall be erected in conformity with the front, side
and rear setback and yard requirements prescribed in the latest pertinent executive
issuance pertaining to and/or the latest IRR of the National Building Code of the
Philippines (NBCP), with the DPWH NBCDO Memorandum Circular No. 1, series of
2008 and in the applicable LGU zoning regulations. In case of conflict between such
laws/ regulations, the provisions of the NBCP shall generally prevail. However, if the
provisions under the pertinent LGU ordinance are more stringent than the NBCP, then
such LGU ordinance shall prevail.
NMBs/ electronic signs mounted on facades of buildings along a national RROW/
street shall be sized in accordance with the zoning classification and in proportion to
the applicable setbacks, building height limit (BHL), the permissible proportions of
openings/ fenestrations for mandated natural light and ventilation, outermost face of
buildings/ billboards (OFBs) and outermost limits of building projections (OLBP) and
related provisions under the NBCP as well as the various safety provisions under the
FCP, duly determined by a registered and licensed architect (RLA). NMBs/ electronic
signs mounted on facades of buildings and in between independent structures for
NMBs along a national RROW/ street/ other ROW shall be similarly restricted as
NMBs on independent structures, based on applicable development controls found in
the NBCP and/or specific executive issuances of the DPWH Secretary, such as but not
limited to NBCDO Memorandum Circular No. 1, Series of 2008, in his capacity as the
National Building Official (NBO).
No part of a NMB/ electronic display shall be placed on, in or over any private/ public
property without the written consent of the property owner or lawful possessor and
without the permit of the barangay concerned or the LGU. This particularly applies to
NMBs/ electronic displays and their outdoor lighting provisions, as applicable,
mounted on firewalls and deliberately intruding into the air rights of adjoining
E-65
No NMB/ electronic display shall be erected or maintained upon or above the roof of
any building/ structure if the same is in violation of the NBCP and its IRR, applicable
executive issuances or more stringent laws.
E.6.1.3
No NMB/ electronic display shall be constructed on a property where the same can
obscure or shade the prescribed openings, windows or doors of adjacent buildings/
structures. NMBs/ electronic display shall not be made of reflective material that can
redirect unwanted light towards adjacent buildings/ structures, particularly at
residential structures at night time.
NMB/ Electronic Display Spacing and Density
Independent structures for NMBs/ electronic displays located upon or oriented
towards traffic traveling upon the same side of a national RROW/ street at all its
development levels at grade and above grade, with maximum permitted BEDU shall be
spaced no less than five hundred meters (500.0 m) apart in the case of building
exterior wall-mounted BEDU and no less than two hundred and fifty meters (250.0 m)
apart in the case of freestanding or self-mounted BEDU. For narrower national
RROWs, the spacing may be between a minimum of two hundred and fifty meters to a
maximum of five hundred meters (min. 250.0 m – max. 500.0 m) depending on the
allowed vehicle speeds on the RROW as determined by the DPWH. These foregoing
distances shall be measured along a straight line between the two (2.0) nearest points
of the NMBs/ electronic displays. The minimum spacing required shall not apply to
two (2.0) displays viewed from different directions but which share a common
support structure.
Regardless of national RROW/ other ROW widths, NMBs/ electronic displays shall not
be located within a one hundred meter (100.0 m) radius (radial distance) of another
NMB/ electronic display even if the two (2.0) NMB s/ electronic displays are on
different RROWs/ streets/ other ROWs.
Building-mounted NMBs/ electronic displays located upon or oriented towards
traffic traveling upon the same side of a national or LGU RROW/ street, with maximum
permitted BEDU shall be spaced on a case-to-case basis as determined through the
proper application of development controls mandated under the NBCP (minimum
E-66
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.6.1.4
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
standards) and/or under the pertinent LGU ordinance (with standards more stringent
than that of the NBCP), duly prepared by a registered and licensed architect (RLA).
satisfaction of the applicable setback, yard and building height limit (BHL), maximum
architectural projection/ OLBP and/or outermost face of building/ billboard (OFB)
requirements of the NBCP and its 2004 and/or latest IRR and the pertinent LGU
Zoning Ordinance (ZO).
Display Content and Lighting for NMBs/ Electronic Displays
For Zone 2 (Along Secondary RROWs/ ROWs)
All display content for NMBs/ electronic displays and temporary signs must conform
to the standards set by the Advertising Board of the Philippines (a self-regulatory
agency) and/or the government agency tasked or to be tasked with reviewing and
approving the display.
A NMB/ BEDU shall have a surface or display area of between seven point five (7.5)
sqm minimum and thirty (30.0) sqm maximum for existing/ proposed national urban
RROWs/ ROWs.
The maximum dimension of any one (1.0) side of a maximum BEDU shall be one point
five meters (1.5 m), subject to compliance with the applicable NMB height limitation
under these DGDG.
All display content exhibited in a foreign language shall similarly exhibit the
corresponding translation in either English or the local dialect/s.
No NMB/ electronic display with any commercial content shall be permitted within all
properties zoned as residential nor within residential subdivisions. In the case of a
new residential subdivision, only commercial NMBs/ electronic displays containing
information on the residential subdivision shall be allowed.
No NMB/ electronic display with any commercial content shall be erected within a
two hundred meter (200.0 m) distance of the nearest property line of declared
historic or cultural sites or of institutional sites such as schools, churches, hospitals,
government buildings, public parks/ playgrounds/ recreation areas, convention
centers, cemeteries or any other area which must be free of NMBs/ electronic displays
with commercial content.
E.6.1.5
E.6.1.6
Lighting: NMBs shall be illuminated only by luminaries exuding a fixed/ nonoscillating/ non-fluctuating amount of light that shall not produce glare or unwanted
reflectance when directed at a display.
All NMBs/ electronic displays shall be erected in conformity with the building
height limits (BHL, also applicable as Billboard Height Limits), the outermost limits on
building projections (OLBP) and the outermost face of buildings (OFB, also applicable
as outermost face of billboards), duly prescribed in the 2004 and/or latest IRR of the
NBCP and in the applicable LGU Zoning Ordinance (ZO) and related developmentoriented national and local laws and regulations.
Allowable variations from the standard measurements per Zone shall generally
conform with the following:
A NMB/ BEDU shall have a surface or display area of between thirty (30.0) sqm
minimum and two hundred twenty five (225.0) sqm maximum for existing/ proposed
national urban RROWs/ ROWs.
The maximum dimension of any one (1.0) side of a maximum BEDU shall be seven
point five meters (7.5 m), subject to compliance with the applicable NMB height
limitation under these DGDG.
No freestanding NMB/ electronic display shall exceed twenty five meters (25.0 m) in
height, measured from the average elevation of the surface of the natural ground or
existing sidewalk or carriageway level (whichever is higher) up to the highest point of
the NMB or any of its components. This maximum height is contingent on the prior
E-67
Placement of Billboards/ Electronic Displays with respect to Emergency Exits, Doors and
Windows.
No NMB/ electronic display shall be erected in such a manner that any portion of its
display or supports will interfere in any way with the free use or operation of any fire
escape, emergency exit, door, window, standpipe and the like. A NMB/ electronic
display shall not be erected, constructed and maintained so as to obstruct any
emergency exit or other openings or to prevent free passage from one part of a roof to
any part thereof. A NMB/ electronic display in any form or shape shall not in any
manner be attached to a fire escape or be so placed as to interfere with an opening
required for introducing natural light and ventilation into a building/ structure. This
provision shall particularly apply to all tall buildings.
Allowable Dimensions for Non-Mobile Billboard Displays/ Electronic Displays
For Zone 1 [Along Major RROWs/ ROWs, at Planned Units Developments (PUDs) and
at Special Development Zones/ SDZs]
No freestanding NMB/ electronic display shall exceed twenty five (25.0 m) in height,
measured from the average elevation of the surface of the natural ground or existing
sidewalk or carriageway level (whichever is higher) up to the highest point of the
NMB or any of its components. This maximum height is contingent on the prior
satisfaction of the applicable setback, yard and BHL, maximum architectural
projection/ OLBP and/or OFB requirements of the NBCP and its 2004 and/or latest
IRR and the LGU ZO.
E.6.1.7
NMBs/ electronic displays shall also not be used to wrap buildings to deprive
occupants natural light, ventilation and view. This particularly applies to all types of
residential and office buildings as well as above-grade parking buildings, where
exhaust venting shall be severely compromised by such non-mobile billboards/
electronic displays, even if perforations are introduced.
Responsible State-regulated Professionals for NMBs/ Electronic Displays
As of the effective date of this Ordinance, the permit documents for the erection and
maintenance of all NMBs/ Electronic Displays under these DGDG shall be as follows:



Registered and licensed Architect (RLAr) for the Architectural and Urban Design
Analyses;
Registered and licensed Environmental Planner (RLEnP) for the Environmental
Analyses;
Registered and licensed Civil Engineer (RLCE) with specialization in structural
design for the Structural Design and Analyses;
E-68
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures


E.6.1.8
Registered and licensed Professional Electrical Engineer (PEE) for the Electrical
Design and Analyses for Non-Mobile Billboards; and
Registered and licensed Professional Communications Engineer (PCE) for the
Electronic Design and Analyses for Electronic Displays.
General Regulations for Signages
Temporary Signs: Temporary signs shall be limited to hangings such as buntings,
banners and posters mounted on existing posts, fences or buildings – except in any
part of the RROWs, shall have a life of thirty (30) calendar days, renewable, with the
date of expiry printed on the sign, which shall be removed at owner’s expense or if
removed by the LGU, removal costs shall be charged accordingly to the signage owner;
signs on construction fences shall be allowed only for the duration of the construction
work, and should be maintained at original quality at all times; events signs are
considered temporary signs.
Dimensions of signage and illumination: Signage dimensions shall range from a
minimum of 0.045 sqm for address and occupant signs to a maximum of 6.0 sqm for
event signs as well as building directory signs. The most common sign, the wall sign,
shall range from 1.0 sqm to 3.0 sqm.
Other building signs: Certain uses shall be allowed special signs. Places that serve as
congregation areas for large crowds (e.g. places of worship; sports stadiums,
racetracks, etc.) shall be allowed event signs to announce details of the occasion.
Structures that have multiple tenants shall be allowed a building directory sign.
Projecting signs shall be allowed for fire/ security stations and general/ specialized
hospitals, medical centers. Petrol identification signs (pole signs) shall be specific to
petrol filling kiosks/ service stations.
For certain types of uses, signage regulations shall be consistent no matter the zone
these are located in. These allowed uses include fire/ security stations; general/
specialized hospitals, medical centers; hotels; multi-family dwellings; parking
structures; parks/ playgrounds/ gardens; petrol filling kiosks/ service centers;
residential inns, condominiums/ condotels/ apartments; single-detached dwellings;
supermarkets/ food stores; transit stations/ terminal; wet/ dry markets; and zoos,
other nature centers.
Detailed Signage Regulations
Address & occupant signs: for buildings or structures shall be allowed a maximum
area of 0.045 sqm (0.15 m x 0.3 m) and a height of between 1.2 - 1.6 m from sidewalk
level, except for fire stations. For fire/ security stations, there shall be no limit to the
dimensions for the maximum area. For signage locations and illumination, the allowed
use and/or specific regulations shall be as discussed hereafter.
Building identification signs and/or logo signs: Building identification sign and/or
logo sign (halo-lighted, internally lighted or externally lighted) and building
identification sign and/or logo sign (at top of building) shall be allowed a maximum
area of 3.0 sqm, a height of not more than 4.0 m or not more than 4% of building
height, whichever is smaller, and be located near the top of building.
Building identification sign and/or logo sign, address sign (illuminated) shall be
allowed a maximum area of 3.0 sqm, a minimum height of 2.2 m and a maximum
height of 4.0 m, and shall be located at the ground floor of building façade near the
E-69
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
wall entrance or at perimeter wall, gate or fence. The allowed maximum height of each
letter is 1.0 m.
Building identification sign and/or logo sign (canopy sign) shall be allowed at
entrance canopy. The allowed maximum height of each letter is 0.6 m.
Canopy signs: shall be allowed a minimum height from bottom of the sign to the
finished surface of the sidewalk at 2.2 m and a maximum height from top of wall sign
to sidewalk surface level of 4.0 m. For signage illumination, maximum areas, and
locations, refer to the allowed use and/or specific regulations by zone hereafter.
Events signs: shall be allowed a minimum height from the bottom of sign to sidewalk
level of 2.2 mts. and maximum height from top of sign to finished surface of the
sidewalk at 4.0 m, where the sign shall be located at the building façade near the
entrance. For signage illumination and maximum areas, refer to the allowed use
and/or specific regulations.
Free-standing ground signs (e.g. building directory): shall not be higher than 1.8
m, shall have a minimum letter height of 0.2 m, and shall be located within the
property line. If the 2nd floor finished floor line (FFLL) is less than 6.0 m from the
finished sidewalk level, the minimum height shall be set at 3.0 m from finished
sidewalk level to the bottom of sign while the maximum height shall be 6.0 m from
finished sidewalk level to the top of sign. If 2nd floor FFL is more than 6.0 m from
finished sidewalk level, the top of sign should not extend beyond 2 nd floor level. Signs
are allowed up to 75% of width of frontage of rented space but shall not exceed 1.0 m
high or 6.0 m wide, and the maximum projection allowed shall only be at 0.2 m from
property line.
Monument signs: shall be allowed a maximum area of 3.0 sqm including the base
material which is attached to the ground and shall be located at the entrance area,
except for petrol filling kiosks/ service stations. For monument signs located at petrol
filling kiosks/ service stations, the signs shall be allowed a maximum area of 2.0 sqm
and shall be mounted on the ground.
Petrol identification signs (pole signs): shall be illuminated, shall have a maximum
area of 2.0 sqm and shall have a minimum height of 3.0 m up to a maximum of 5.0 m
from the finished sidewalk level.
Projecting signs: shall be illuminated, shall have a maximum area of 1.0 sqm with a
minimum height from bottom of sign to finished sidewalk level of 2.2 m and a
maximum height from top of wall sign to finished sidewalk level of 4.0 m, and be
attached perpendicular to the building façade near the entrance. The projecting sign
shall not obstruct the sidewalk.
Wall signs: shall be allowed a minimum height from bottom of the sign to finished
sidewalk level of 2.2 m and a maximum height from top of wall sign to finished
sidewalk level of 4.0 m with the exception of parking structures, transit stations/
terminals and petrol filling kiosks/ service stations. For parking structures and transit
stations/ terminals, wall signs shall be allowed a minimum height of 2.4 m measured
from the bottom of sign to crown of RROW carriageway. For petrol filling kiosks/
service stations, the wall sign shall be at the edge of the roof/ parapet. For signage
illumination, maximum areas and similar locations, refer to the allowed use and/or
specific regulations by zone as shown hereafter.
E-70
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.6.1.9
Official Signs Exempted
The following official signs are exempt from the restrictions of this Ordinance that
may also apply to signs:




E.6.1.10
Official highway route number signs, street name signs, directional, or other
official government signs;
Directional, information or public service signs, such as those advertising
availability of restrooms, telephone or similar public conveniences;
Official traffic signs, signals, devices and the like; and
Official signs for memorial or historical places.
Possible Exemption for Non-Mobile Billboards/ Electronic Displays Only Above the Sidewalk
Portion of the RROW
Satisfaction of the following conditions, whereby the permitted non-mobile billboard/
electronic display is made to effectively contribute to positive urban design/
redevelopment, may allow the placement or erection of non-mobile billboards/
electronic displays but only above the sidewalk portion of the RROW:




E.6.1.11
If the NMB/ electronic display and its cantilevered support structure is used to
effectively hold in place and disguise/ conceal overhead electrical, telephone,
cable TV and similar utility lines that hover above the sidewalk and that may pose
possible danger to pedestrians; provided that such utility lines are also effectively
concealed from the view of persons within a property/ building or structure
without unduly compromising considerations of natural light and ventilation.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E.6.1.12
Sustainability of NMBs/ Electronic Displays
All of the construction and finishing materials, related to the erection, operation and
maintenance of NMBs/ BEDUs, particularly including the mode of disposal, reuse,
recycling, etc. of such materials such as used paints, stickers, tarpaulin, plastics,
metals, glass, expended luminaires, and the like, shall conform with the pertinent
environmental laws and regulations, including those related to professional practices
in the fields of environmental planning, environmental investigation and
environmental design (in which architecture and urban design are included), as well
as accepted and/or prescribed international sustainability practices such as
international agreements and protocols in which the Republic of the Philippines is a
signatory.
Of particular importance are the determination of embodied energy levels in such
materials, which is part of the carbon (footprint) reduction effort worldwide. The
embodied energy used in the sourcing, manufacture, transportation/ handling/
delivery, installation, use and operation/ maintenance of such materials must require
the least consumption and production of carbon and must thereby promote health and
general wellbeing (including nuisance avoidance) of all affected by the introduction of
the pertinent non-mobile billboard/ BEDU.
If the NMB/ electronic display and its cantilevered support structure is also used
to effectively provide a shelter from the elements for the pedestrians passing
underneath; as such, the non-mobile billboard serves as a component of a virtual
covered sidewalk system.
If the NMB/ electronic display to cover the utility lines is officially permitted by
the DPWH with the MMDA and/or the DILG.
If the allowed NMB/ electronic display does not exceed 1.2 meters in height and
provides a clear vertical distance of at least 4.0 meters for pedestrians passing
underneath.
State Regulation of NMB/ Electronic Display Content
Since the content of NMBs/ electronic displays have an undeniable effect on its
viewers, particularly the young, the State must perforce regulate such NMB/
electronic billboard content such that public morals are preserved in general and such
that undue attacks on beliefs, customs and traditions, lawful practices and on the
exploited and/or marginalized sectors of society are likewise prevented, with the
proper presentation of the content and of the display’s context without directly
venturing into censorship.
Only limited self-regulation among industry players may be allowed, such that the
LGU shall continue to exercise overall supervision on all matters pertaining to
regulation of NMBs/ electronic displays within its jurisdiction. In such a manner,
liabilities and violations can be clearly established by the LGU and subsequently
addressed by the proper authorities.
E-71
E-72
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Current Interpretations of Rule XII of P.D. No. 1096 (1977 NBCP)
This Annex graphically illustrates interpretations of the prescribed compliances for buildings under
Rule XII of the 2004 Revised IRR of P.D. No. 1096 (the 1977 National Building Code of the
Philippines/ NBCP) and is intended for ready reference by physical planners, architects, designers,
and the competent reviewing authorities authorized to review/ process and approve building plans
under P.D. No. 1096.
Annex F
Current Interpretations of Rule XII of
P.D. No. 1096 (1977 NBCP)
F-1
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-2
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-3
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-4
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-5
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-6
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-7
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-8
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-9
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-10
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-11
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-12
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-13
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-14
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-15
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-16
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-17
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-18
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-19
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-20
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
F-21
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Annex G
F-22
Generic Documents Guide for a Large
National Government Office Building
Project
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Generic DOCUMENTS GUIDE for a
A-16
(Approx. 1.7 hectares Total Lot Area/ TLA, approx. 60,000 sqm Total Gross Floor Area/ TGFA,
Large Footprint, Medium-rise with Deck Roof Level and No Basement Level)
A-18
LARGE NATIONAL GOVERNMENT OFFICE Building Project
Generic Plan and Design Drawing Schedule
at Approximately 275 A0 (i.e. about 30” x 40”) Size Sheets
Very Important Note: In the case of repair, renovation, rehabilitation, retrofit,
expansion, heritage conservation, fit-out, and similar works/ projects for buildings/
structures, the AS-BUILT PLANS AND DESIGNS of such buildings/ structures,
together with the respective SCOPE OF WORKS BRIEF i.e. an image map
showing the plans, sections, elevations, etc. with call-outs of the intended
construction works, MUST be provided by the Designer and/or Project Proponent
before the rest of the Plans/ Designs/ Documents listed hereafter.
A. Design
Discipline
1. ARCHITECTURAL (A)
Sheets
Note: By law (R.A. No.
9266), only registered and
licensed architects/ RLAs
shall prepare, sign and seal
all professional outputs for
buildings i.e. those that are
classified as Architectural
Documents
B. Sheet Code
(and Number)
1. Primary
Drawing/s
A-1
PERSPECTIVES
A-2
SITE DEVELOPMENT
PLAN
A-19
A-20
A-21
A-22
A0 Sheet Content
2. Secondary
Drawing/s and/or
Primary
Information
VICINITY MAP;
LOCATION PLAN
3. Secondary/
Other
Information
TABLE OF
CONTENTS
A-23
A-24
A-25
A-26
A-27
A-28
A-29
A-3
A-4
A-5
A-6
A-7
A-8
A-9
A-10
A-11
A-12
A-13
A-14
A-15
G-1
C.
A-17
LOWER GROUND
FLOOR PLAN
UPPER GROUND
FLOOR PLAN
SECOND FLOOR PLAN
THIRD FLOOR PLAN
FOURTH FLOOR PLAN
FIFTH FLOOR PLAN
SIXTH FLOOR PLAN
SEVENTH FLOOR
PLAN
ROOF DECK PLAN
FRONT ELEVATION
LEFT-SIDE ELEVATION
REAR ELEVATION
RIGHT-SIDE
A-30
A-31
A-32
A-33
A-34
A-35
A-36
A-37
ELEVATION
LONGITUDINAL
SECTION
CROSS SECTION
BETWEEN GRIDS 2&3
CROSS SECTION
BETWEEN GRIDS 6&7
CROSS SECTION
BETWEEN GRIDS 8&9
PARTIAL SECTION
BETWEEN GRIDS 2&3
CURTAIN WALL
(FRONT)
PARTIAL SECTION
BETWEEN GRIDS 3&4
REAR WALL
PARTIAL SECTION
BETWEEN GRIDS 6&7
CURTAIN WALL
(FRONT)
PARTIAL SECTION
BETWEEN GRIDS 8&9
(FRONT)
PARTIAL PLAN:
SHOWING CONC.
LEDGES
PARTIAL PLAN:
CANOPY @7TH FLOOR
LEVEL
PARTIAL PLAN:
CONCRETE CANOPY
@7TH FLOOR LEVEL
CANOPY @ SEVENTH
FLOOR DETAILED
SECTION
CROWN & PORTHOLE
DETAILS
TOWER DETAILS
REFLECTED CEILING
PLAN LOWER GROUND
REFLECTED CEILING
PLAN UPPER GROUND
REFLECTED CEILING
PLAN SECOND FLOOR
REFLECTED CEILING
PLAN THIRD FLOOR
REFLECTED CEILING
PLAN FOURTH FLOOR
REFLECTED CEILING
PLAN FIFTH FLOOR
REFLECTED CEILING
PLAN SIXTH FLOOR
REFLECTED CEILING
PLAN SEVENTH
FLOOR
LIGHTING PLAN-DECK
AND MACH. ROOM
SCHEDULE OF DOORS
DETAIL SECTION
CONCRETE LEDGE
(REAR)
DETAIL SECTION:
CONCRETE LEDGE
(LEFT & RIGHT SIDE)
SPOT DETAIL
PARAPET DETAILS
ISOMETRIC DRAWING
LEGEND
LIGHTING FIXTURE
LEGEND
LIGHTING FIXTURE
LEGEND
LIGHTING FIXTURE
LEGEND
LIGHTING FIXTURE
LEGEND
LIGHTING FIXTURE
LEGEND
LIGHTING FIXTURE
LEGEND
LIGHTING FIXTURE
LEGEND
LIGHTING FIXTURE
LEGEND
LIGHTING FIXTURE
DOOR FIN. &
ACCESSORIES
CALLOUTS
CEILING FIN.
CALLOUTS
CEILING FIN.
CALLOUTS
CEILING FIN.
CALLOUTS
CEILING FIN.
CALLOUTS
CEILING FIN.
CALLOUTS
CEILING FIN.
CALLOUTS
CEILING FIN.
CALLOUTS
CEILING FIN.
CALLOUTS
CEILING FIN.
G-2
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
A-38
A-39
A-40
A-41
A-42
A-43
A-44
A-45
A-46
A-47
A-48
A-48
AI-49
AI-50
AI-51
AI-52
AI-53
2. ARCHITECTURAL
G-3
AI-1
SCHEDULE OF
WINDOWS, TAGS AND
COUNT
FIXED/SLIDING
WINDOW DETAIL
FIXED/SLIDING
WINDOW DETAILS
CURTAIN WALL
DETAILS
DOOR TAGS AND
COUNT
FLOOR PATTERNROOF DECK
PLAN MAINSTAIRS: LGUG
PLAN MAINSTAIRS:
UG-7TH FLOOR
PLAN MAINSTAIRS: 7TH
FLOOR-DECK LEVEL
MAIN STAIRS SECTION
PARTIAL SECTION: 5THROOD DECK LEVEL
PARTIAL SECTION:
TYP. FLOORS
FIRE EXIT DETAILS
ENTRANCE STAIR
DETAIL
DISABLED RAMP
DETAILS
CANOPY DETAILS
ENTRANCE STAIR
DETAILS
KITCHEN EQUIPMENT
DETAILS
SCHEDULE OF
EXTERIOR PAINTING
WORKS
SCHEDULE OF
EXTERIOR
ARCHITECTURAL
METALWORK
SCHEDULE OF
MURALS AND PUBLIC
ART/ EXTERIOR
SCULPTURE
SCHEDULE OF
OUTDOOR TILEWORK,
TAGS AND COUNT
PLANS, DRAWINGS,
DETAILS AND
SCHEDULE OF
ARCHITECTURAL
COMPLIANCES WITH
THE ACCESSIBILITY
LAW
WINDOW FIN. &
ACCESSORIES
PARTITION PLAN-
LEGEND
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
INTERIORS (AI)*
Sheets
Note: By law (R.A. No.
9266), only registered and
licensed architects/ RLAs
shall prepare, sign and seal
all professional outputs for
buildings i.e. those that are
classified as Architectural
Interior (AI) Documents
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
DOOR FIN. &
ACCESSORIES
LEGEND
FLOOR FIN.
ISOMETRIC VIEW
LOWER GROUND
WALL FIN.
AI-2
PARTITION PLANUPPER GROUND
LEGEND
WALL FIN.
AI-3
PARTITION PLANSECOND FLOOR
PARTITION PLAN
THIRD FLOOR
PARTITION PLAN
FOURTH FLOOR
PARTITION PLAN
FIFTH FLOOR
PARTITION PLAN
SIXTH FLOOR
PARTITION PLAN
SEVENTH FLOOR
FLOOR PATTERNLOWER GROUND
FLOOR PATTERNUPPER GROUND
FLOOR PATTERNSECOND FLOOR
FLOOR PATTERNTHIRD FLOOR
FLOOR PATTERNFOURTH FLOOR
FLOOR PATTERNFIFTH FLOOR
FLOOR PATTERNSIXTH FLOOR
FLOOR PATTERNSEVENTH FLOOR
SCHEDULE OF
FINISHES FOR
ARCHITECTURAL
INTERIOR WORKS
SCHEDULE OF
FINISHES FOR
ARCHITECTURAL
INTERIOR WORKS
SCHEDULE OF
FINISHES FOR
ARCHITECTURAL
INTERIOR WORKS
SCHEDULE OF FINISH
FOR ARCHITECTURAL
INTERIOR WORKS
TYPICAL HALLWAY
DETAILS
SIXTH FLOOR
HALLWAY DETAIL
PARTIAL PLAN: MAIN
LEGEND
WALL FIN.
LEGEND
WALL FIN.
LEGEND
WALL FIN.
LEGEND
WALL FIN.
LEGEND
WALL FIN.
LEGEND
WALL FIN.
LEGEND
FLOOR FIN.
LEGEND
FLOOR FIN.
LEGEND
FLOOR FIN.
LEGEND
FLOOR FIN.
LEGEND
FLOOR FIN.
LEGEND
FLOOR FIN.
LEGEND
FLOOR FIN.
LEGEND
FLOOR FIN.
OUTLINE
SPECIFICATIONS
AI-4
AI-5
AI-6
AI-7
DETAIL SECTION
SPOT DETAIL
NOSING DETAIL
AI-8
AI-9
SPOT DETAILS
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
OUTLINE
SPECIFICATIONS
OUTLINE
SPECIFICATIONS
AI-10
AI-11
AI-12
NOTES
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
AI-13
AI-14
AI-15
AI-16
AI-17
AI-18
AI-19
AI-20
AI-21
AI-22
CALLOUTS
OTHER FIN.
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
CALLOUTS
SPECIFICATIONS
CALLOUTS
G-4
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
AI-23
AI-24
AI-25
AI-26
AI-27
A-28
AI-29
AI-30
AI-31
A1-32
AI-33
G-5
LOBBY DETAILED
ELEVATION
DETAILED ELEVATION:
MAIN LOBBY
PLAN: COLUMN
CLADDING
SECTION: COLUMN
CLADDING
SECTION: ACCENT
WALL
DETAIL SECTION:
RAILING
DETAIL ELEVATION:
RAILING
PARTIAL ELEVATION:
RAILING @ MAIN
LOBBY
WALL DETAIL
SECTIONS
CEILING DETAILS
TOILET DETAILS
-LOWER GROUND
FLOOR
-UPPER GROUND
FLOOR
-SECOND FLOOR
TOILET DETAILS
-THIRD FLOOR
-FOURTH FLOOR
TOILET DETAILS
-FIFTH FLOOR
-SIXTH FLOOR
PANTRY DETAILS
-UPPER GROUND
FLOOR
PANTRY DETAILS
-SECOND FLOOR
PANTRY DETAILS
-THIRD FLOOR &
FOURTH FLOOR
PANTRY DETAILS
-FIFTH FLOOR
AI-34
PANTRY DETAILS
-SIXTH FLOOR
AI-35
PANTRY DETAILS
-SEVENTH FLOOR
AI-36
PLAN: GM BACKWALL
& BACK CABINET
ELEVATIONS,
SECTIONS & DETAILS
PARTIAL PLAN:
GM/CONF. RM,
DIVIDER CAB.
ELEVATION, SECTIONS
FINISHES &
SPECIFICATIONS
SPOT DETAIL: COLUMN
CLADDING
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
SPOT DETAIL:
HANDRAIL
SECTION: ALUMINUM
SHEET
MOULDING DETAILS
SPOT DETAILS
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
AI-37
AI-38
AI-39
AI-40
AI-41
AI-42
AI-43
AI-44
AI-45
AI-46
AI-47
AI-48
AI-49
AI-50
AI-51
AI-52
AI-53
AI-54
& DETAILS
KITCHEN EQUIPMENT
LAYOUT
LOWER GROUND
FURNITURE LAYOUT,
TAGS & COUNT
UPPER GROUND
FLOOR FURNITURE
LAYOUT, TAGS &
COUNT
SECOND FLOOR
FURNITURE LAYOUT,
TAGS & COUNT
THIRD FLOOR
FURNITURE LAYOUT,
TAGS & COUNT
FOURTH FLOOR
FURNITURE LAYOUT,
TAGS & COUNT
FIFTH FLOOR
FURNITURE LAYOUT,
TAGS & COUNT
SIXTH FLOOR
FURNITURE LAYOUT,
TAGS & COUNT
SEVENTH FLOOR
FURNITURE LAYOUT,
TAGS & COUNT
-SIGNAGE AND
GRAPHICS DESIGN
DETAIL
-SIGNAGE AND
GRAPHICS DESIGN
PLANS, TAG AND
COUNT
SCHEDULE OF
HARDWARE AND
COUNT
SCHEDULE OF
FIXTURES, TAG AND
COUNT
SCHEDULE OF
FURNISHINGS, TAG
AND COUNT
SCHEDULE OF STAIRS,
ESCALATORS AND
ELEVATORS
SCHEDULE OF SMALL
OFFICE EQUIPMENT,
TAG AND COUNT
SCHEDULE OF
GRAPHICS, SIGNAGES
AND WAYFINDING
DEVICES
SCHEDULE OF
FURNITURE AND
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS,
KITCHEN EQUIPMENT
LIST
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
G-6
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
AI-55
AI-56
AI-57
AI-58
AI-59
AI-60
AI-61
AI-62
AI-63
AI-64
AI-65
AI-66
3. INTERIOR DESIGN
(ID)** Sheets
Note: By law (R.A. No.
8534), only registered and
licensed
interior
designers/ RLIDs shall
prepare, sign and seal all
professional outputs for
buildings i.e. those that are
classified as Interior
Design (ID) Documents
G-7
ID - 1
ID - 2
ID - 3
MOVABLE ITEMS
SCHEDULE OF
FURNITURE AND
MOVABLE ITEMS
SCHEDULE OF
FURNITURE AND
MOVABLE ITEMS
SCHEDULE OF
FURNITURE AND
MOVABLE ITEMS
SCHEDULE OF
MILLWORK ITEMS
SCHEDULE OF
INTERIOR PAINTING
WORKS
SCHEDULE OF
INTERIOR
ARCHITECTURAL
METALWORK
SCHEDULE OF
INDOOR TILEWORK,
TAGS AND COUNT
SCHEDULE OF TOILET
FIXTURES AND
ACCESSORIES
SCHEDULE OF
ARCHITECTURAL
LIGHTING FIXTURES
(INCLUDING
MONUMENTAL
LIGHTING) AND
ACCESSOTIES
SCHEDULE OF
INDOOR PLANTS AND
HOLDERS
PARKING AND
TRAFFIC PLAN
PLANS, DRAWINGS,
DETAILS AND
SCHEDULE OF
ARCHITECTURAL
INTERIOR
COMPLIANCES WITH
THE ACCESSIBILITY
LAW
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
DESIGN & DETAILS
- CUSTOM FURNITURE
DESIGN & DETAILS
- CUSTOM FURNITURE
DESIGN & DETAILS
- CUSTOM FURNITURE
DESIGN & DETAILS
SCHEDULE OF
FURNITURE AND
MOVABLE ITEMS
SCHEDULE OF
DRAPES, CURTAINS,
CUSHIONS, WINDOW
ACCESSORIES, ETC.
AND ATTENDANT
HARDWARE ITEMS
SCHEDULE OF DÉCOR
ITEMS, PAINTINGS
AND INTERIOR
SCULPTURE
SPECIFICATIONS
OUTLINE
SPECIFICATIONS
OUTLINE
SPECIFICATIONS
OUTLINE
SPECIFICATIONS
OUTLINE
SPECIFICATIONS
LA - 1
ID - 4
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
ID - 7
OUTLINE
SPECIFICATIONS
OUTLINE
SPECIFICATIONS
NOTES
ID - 8
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
NOTES
OUTLINE
SPECIFICATIONS
ID - 5
ID - 6
-SYSTEMS FURNITURE
DESIGN & DETAILS
-SYSTEMS FURNITURE
DESIGN & DETAILS
OUTLINE
SPECIFICATIONS
OUTLINE
SPECIFICATIONS
NOTES
-SYSTEMS FURNITURE
OUTLINE
NOTES
NOTES
NOTES
OUTLINE
SPECIFICATIONS
NOTES
-PLANTING PLAN &
GENERAL NOTES
CALLOUTS, OUTLINE
SPECIFICATIONS
GENERAL NOTES
LA - 2
-PLANT LIST &
DETAILS
OUTLINE
SPECIFICATIONS AND
CALLOUTS
CONSOLIDATED
PLANT LIST
LA - 3
SOFTSCAPING PLAN,
DESIGN AND DETAILS
HARDSCAPING PLAN,
DESIGN AND DETAILS
CALLOUTS, OUTLINE
SPECIFICATIONS
OUTLINE
SPECIFICATIONS AND
CALLOUTS
OUTLINE
SPECIFICATIONS AND
CALLOUTS
LA - 4
5. SITE DEVELOPMENT
PLAN (SDP) Sheets
Note: By law (R.A. No.
9266), only registered and
licensed architects/ RLAs
shall prepare, sign and seal
all professional outputs for
buildings and their grounds
i.e. those that are classified
as Site Development Plan
(SDP) Documents
NOTES
NOTES
ID - 9
NOTES
NOTES
OUTLINE
SPECIFICATIONS
NOTES
4. LANDSCAPE***
ARCHITECTURAL (LA)
Sheets
Note: By law (R.A. No.
9053), only registered and
licensed
landscape
architects/ RLLAs shall
prepare, sign and seal all
professional outputs for
buildings i.e. those that are
classified as Landscape
Architectural
(LA)
Documents
NOTES
LA - 5
LANDSCAPING
LIGHTING AND
SIGNAGE PLAN,
DESIGN AND DETAILS
SDP-1
SITE DEVELOMENT
PLAN
MAIN FENCE DETAILS
ISOMETRIC DETAILS
PLAN: GUARD’S
OUTPOST
GUARD’S OUTPOST
-WINDOW SCHEDULE
SDP-2
SDP-3
G-8
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
SDP-4
6. CIVIL WORKS (CW)
Sheets
Note: By law (R.A. No.
544, as amended by R.A.
No. 1582), only registered
and
licensed
civil
engineers/ RLCEs shall
prepare, sign and seal all
professional outputs for
buildings i.e. those that are
classified as Civil Works
(CW) Documents
SDP-5
GATE PLAN AND
DETAILS
SDP-6
PEDESTRIAN GATE
PLAN AND DETAILS
CW – 1
GRADING PLAN AND
DETAILS
SITE DRAINAGE PLAN,
DESIGN AND DETAILS
CW – 2
G-9
-PARAPET DETAIL
SECTION
SECURITY BOOTH
-WINDOW SCHEDULE
-PARAPET DETAIL
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
CALLOUTS
FINISHES & OUTLINE
SPECIFICATIONS
ISOMETRIC DETAILS
Note: By law (R.A. No.
544, as amended by R.A.
No. 1582), only registered
and
licensed
civil
engineers/ RLCEs shall
prepare, sign and seal all
professional outputs for
buildings i.e. those that are
classified as Structural (S)
Engineering
Design
Documents
S-2
FOUNDATION/
COLUMN KEY PLAN
S-3
FOUNDATION DETAILS
S-4
S-5
COLUMN SCHEDULE
COLUMN SCHEDULE
S-6
SHEAR WALL
SCHEDULE
SHEAR WALL
SCHEDULE
LOWER GROUND
FLOOR FRAMING PLAN
UPPER GROUND
FLOOR FRAMING PLAN
SECOND FLOOR
FRAMING PLAN
THIRD FLOOR
FRAMING PLAN
FOURTH-SIXTH FLOOR
FRAMING PLAN
SEVENTH FLOOR
FRAMING PLAN
LOWER ROOF DECK
FRAMING PLAN
UPPER ROOF
FRAMING PLAN AND
DETAILS
S-7
S-8
S-9
S-10
S-11
S-12
S-13
CW – 3
CW – 4
7. STRUCTURAL (S)
Engineering Design
Sheets
-ROOF DECK PLAN
-FRONT ELEVATION
-LEFT ELEVATION
-REAR ELEVATION
-RIGHT ELEVATION
-CROSS SECTION
-LONGITUDINAL
SECTION
PLAN: SECURITY
BOOTH
-FRONT ELEVATION
-LEFT ELEVATION
-REAR ELEVATION
-RIGHT ELEVATION
-CROSS SECTION
-LONGITUDINAL
SECTION
FLAGPOLE PALN AND
DETAILS
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
S-1
S-14
PERIMETER WALL AND
FENCE DESIGN AND
DETAILS
DRIVEWAY, ROAD AND
SIDEWALK PLAN,
DESIGN AND
DDETAILS
CONSTRUCTION
NOTES
S-15
S-16
GENERAL NOTES,
NOTES ON CONCRETE
MIXES AND PLACING,
NOTES ON
REINFORCING STEEL
BARS, NOTES ON
FOUNDATION, NOTES
ON CONCRETE WALLS,
NOTES ON MASONRY
WALLS, NOTES ON
BEAMS AND GIRDERS,
NOTES ON CONCRETE
S-19
SCHEDULE OF
MOMENT RESISTING
GIRDERS
SCHEDULE OF
GIRDERS
SCHEDULE OF
GIRDERS
SCHEDULE OF BEAMS
S-20
S-21
SCHEDULE OF BEAMS
SCEDULES OF SLABS
S-17
S-18
SLABS, NOTES ON
STRUCTURAL STEEL,
NOTES ON COLUMNS &
DESIGN CRITERIA
CALLOUTS & OUTLINE
SPECIFICATIONS
PILE CAP SCHEDULE
CALLOUTS & OUTLINE
SPECIFICATIONS
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
NOTES
NOTES
CALLOUTS & OUTLINE
SPECIFICATIONS,
TYPICAL CORBEL
DETAIL
TYPICAL BAR DETAILS
FOR BEAMS
TYPICAL SLAB
DETAILS, DROP SLAB,
CORNER SLAB &
TYPICAL DETAIL OF
SLAB OPENINGS
G-10
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
S-22
TRUSS DETAILS
S-23
MAIN STAIR DETAILS
S-24
LEFT / RIGHT WING
FIRE EXIT DETAILS
S-25
S-26
S-27
S-28
S-29
8. ELECTRICAL (E)
Engineering Design
Sheets
Note: By law (R.A. No.
7920), only registered and
licensed
professional
electrical
engineers/
PEEs shall prepare, sign
and seal all professional
outputs for buildings i.e.
those that are classified as
Electrical (E) Engineering
Design Documents
E-1
E-2
E-3
E-4
E-5
E-6
E-7
E-8
E-9
E-10
E-11
G-11
MACH. RM DETAILS /
BEAM SCHEDULE OF
MACHINE ROOM
TOWER / MAST
DETAILS
PARAPET WALL
SUPPORT AND WALL
DETAILS
OVERHEAD / GROUND
WATER TANK DETAILS
UPPER ROOF
FRAMING PLAN AND
DETAILS
LOAD SCHEDULE
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
E-12
E-26
FIFTH FLOOR
LIGHTING LAYOUT
SIXTH FLOOR
LIGHTING LAYOUT
SEVENTH FLOOR
LIGHTING LAYOUT
ROOF DECK LIGHTING
LAYOUT
GROUNDS POWER
LAYOUT
LOWER POWER
LIGHTING LAYOUT
UPPER POWER
LIGHTING LAYOUT
SECOND POWER
LIGHTING LAYOUT
THIRD POWER
LIGHTING LAYOUT
FOURTH POWER
LIGHTING LAYOUT
FIFTH POWER
LIGHTING LAYOUT
SIXTH POWER
LIGHTING LAYOUT
SEVENTH POWER
LIGHTING LAYOUT
ROOF DECK POWER
LAYOUT
ROOF DECK POWER
LAYOUT
DETAILS
E-27
DETAILS
E-28
DETAILS
9. MECHANICAL (M)
Engineering Design
Sheets
M-1
Note: By law (R.A. No.
8495), only registered and
licensed
professional
mechanical engineers/
PMEs shall prepare, sign
and seal all professional
outputs for buildings i.e.
those that are classified as
Mechanical
(M)
Engineering
Design
Documents
M-2
-DRAWING INDEX,
LEGENDS AND
ABBREVIATIONS &
GENERAL NOTES
-SCHEDULE OF
EQUIPMENT
HVAC PIPE SYMBOLS,
HVAC DUCT
SYMBOLS& SITE
DEVELOPMENT PLAN
-LOWER GROUND A/C
AND VENTILATION
LAYOUT
-UPPER GROUND
FLOOR A/C AND
VENTILATION LAYOUT
CALLOUTS & OUTLINE
SPECIFATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
CONNECTION DETAILS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS,
BEAM DETAILS &
SPOT DETAILS
SCHEDULE OF BEAMS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
E-13
E-14
E-15
E-16
E-17
E-18
E-19
E-20
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
E-21
GENERAL NOTES
E-24
E-22
E-23
E-25
LOAD SCHEDULE
LOAD SCHEDULE AND
EMERGENCY LOAD
SCHEDULE
EMERGENCY LOAD
SCHEDULE
LIGHTING FIXTURE
SCHEDULE
PANELBOARD
SCHEDULE
GROUNDS LIGHTING
LAYOUT
LOWER GROUND
LIGHTING LAYOUT
UPPER GROUND
LIGHTING LAYOUT
SECOND FLOOR
LIGHTING LAYOUT
THIRD FLOOR
LIGHTING LAYOUT
FOURTH FLOOR
LIGHTING LAYOUT
E-25
M-3
M-4
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
LEGEND,
CALLOUTS & OUTLINE
SPECIFICATIONS,
NOTES
NOTES
NOTES
NOTES
G-12
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
M-5
-SECOND FLOOR A/C
AND VENTILATION
LAYOUT
M-6
-THIRD FLOOR A/C
AND VENTILATION
LAYOUT
M-7
-FOURTH FLOOR A/C
AND VENTILATION
LAYOUT
M-8
-FIFTH FLOOR A/C AND
VENTILATION LAYOUT
M-9
-SIXTH FLOOR A/C
AND VENTILATION
LAYOUT
M - 10
-SEVENTH FLOOR A/C
AND VENTILATION
LAYOUT
M - 11
M - 12
M - 13
G-13
-ROOFDECK A/C AND
VENTILATION LAYOUT
-GENSET DETAILED
PLAN & SECTION,
ACCU BALCONY
DETAILED PLAN AND
SECTION *
MISCELLANEOUS
DETAILS
-SCHEMATIC DIAGRAM
M - 14
-MISCELLANEOUS
DETAILS 1
M - 15
-MISCELLANEOUS
DETAILS 2
UNIT DESIGNATION
AND QUANTITY
LEGEND,
CALLOUTS & OUTLINE
SPECIFICATIONS,
UNIT DESIGNATION
AND QUANTITY
LEGEND,
CALLOUTS & OUTLINE
SPECIFICATIONS,
UNIT DESIGNATION
AND QUANTITY
LEGEND,
CALLOUTS & OUTLINE
SPECIFICATIONS,
UNIT DESIGNATION
AND QUANTITY
LEGEND,
CALLOUTS & OUTLINE
SPECIFICATIONS,
UNIT DESIGNATION
AND QUANTITY
LEGEND,
CALLOUTS & OUTLINE
SPECIFICATIONS,
UNIT DESIGNATION
AND QUANTITY
LEGEND,
CALLOUTS & OUTLINE
SPECIFICATIONS,
UNIT DESIGNATION
AND QUANTITY
LEGEND,
CALLOUTS & OUTLINE
SPECIFICATIONS,
UNIT DESIGNATION
AND QUANTITY
CALLOUTS & OUTLINE
SPECIFICATIONS
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
NOTES
10. FIRE PROTECTION
(FP)**** Design
Sheets
FP - 1
Note: By law (R.A. No.
8495), only registered and
licensed
professional
mechanical engineers/
PMEs shall prepare, sign
and seal all professional
outputs for buildings i.e.
those that are classified as
Mechanical
(M)
Engineering
Design
Documents
FP - 2
NOTES
NOTES
NOTES
NOTES
FP - 3
FP - 4
FP - 5
FP - 6
NOTES
FP - 7
FP - 8
FP - 9
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
DETAILS
CALLOUTS & OUTLINE
SPECIFICATIONS,
ELEVATIONS &
DETAILS
NOTES
STAIRWELL
PRESSURIZATION
FAN SEQUENCE
OF OPERATION
SMOKE
EVACUATION FAN
SEQUENCE OF
OPERATION
NOTES
DUCT SCHEDULE
NOTES,
DIMENSIONS &
PIPE SIZE
FP - 10
FP - 11
FP - 12
FP - 13
-FIRE PROTECTION
DRAWING INDEX, FIRE
PROTECTION
LEGENDS,
ABBREVIATIONS &
SYMBOLS, FIRE
PROTECTION
GENERAL NOTES, SITE
DEV’T PLAN,
SCHEDULE OF
PUMPS,SCHEDULE OF
CONTROLLERS,
SCHEDULE OF PIPE
SLEEVES & PIPE SIZE
CONVERSION TABLE
-LOWER GROUND
FLOOR FIRE
PROTECTION LAYOUT
-UPPER GROUND
FLOOR FIRE
PROTECTION LAYOUT
-SECOND FLOOR FIRE
PROTECTION LAYOUT
-THIRD FLOOR FIRE
PROTECTION LAYOUT
-FOURTH FIRE
PROTECTION LAYOUT
-FIFTH FIRE
PROTECTION LAYOUT
-SIXTH FIRE
PROTECTION LAYOUT
-SEVENTH FIRE
PROTECTION LAYOUT
-ROOF DECK FIRE
PROTECTION LAYOUT
-FIRE PUMP ROOM
AND EQUIPMENT
LAYOUT
--DETAILED SECTION
DETAIL OF AIR VENT
-SCHEMATIC FLOW
DIAGRAM OF
STANDPIPE SYSTEM
-MISCELLANEOUS
DETAILS 1
CALL OUTS & OUTLINE
SPECIFICATIONS
CALL OUTS & OUTLINE
SPECIFICATIONS
CALL OUTS & OUTLINE
SPECIFICATIONS
CALL OUTS & OUTLINE
SPECIFICATIONS
CALL OUTS & OUTLINE
SPECIFICATIONS
CALL OUTS & OUTLINE
SPECIFICATIONS
CALL OUTS & OUTLINE
SPECIFICATIONS
CALL OUTS & OUTLINE
SPECIFICATIONS
CALL OUTS & OUTLINE
SPECIFICATIONS
BLOW UP DETAIL
DETAIL OF LADDER
RUNGS
DETAILED SECTION
DETAIL OF AIR VENT
LEGENDS AND
SYMBOLS
ISOMETRY
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
LEGEND
NOTES
NOTES
NOTES
MATERIAL:
Carbon Steel
BOLT DIAMETER
G-14
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
FP - 14
-MISCELLANEOUS
DETAILS 2
FP - 15
-MISCELLANEOUS
DETAILS 3
11. ELECTRONIC (EC)*****
Engineering Design
Sheets
EC – 1
Note: By law (R.A. No.
9292), only registered and
licensed
professional
electronic
engineers/
PECEs shall prepare, sign
and seal all professional
outputs for buildings i.e.
those that are classified as
Electronic
(EC)
Engineering
Design
Documents
EC – 2
-DRAWING INDEX,
LEGENDS AND
ABBREVIATIONS,
GENERAL NOTES,
PIPE SYSMBOLS, SITE
DEVELOPMENT PLAN
- GROUNDS AUXILIARY
SYSTEM LAYOUT
EC – 3
EC – 4
EC – 5
EC – 6
EC – 7
EC – 8
EC – 9
EC – 10
-SCHEMATIC DIAGRAM
EC – 11
-LOWER AND UPPER
GROUND FLOOR BMS
-SECOND AND THIRD
FLOOR BMS
-FOURTH AND FIFTH
FLOOR BMS
-SIXTH AND SEVENTH
FLOOR BMS
-ROOF DECK BMS
DETAILS
EC – 12
EC – 13
EC – 14
EC – 15
EC – 16
G-15
-LOWER AND UPPER
GROUND FLOOR
AUXILIARY SYSTEM
LAYOUT
-SECOND AND THIRD
FLOOR AUXILIARY
SYSTEM LAYOUT
-FOURTH AND FIFTH
FLOOR AUXILIARY
SYSTEM LAYOUT
-SIXTH AND SEVENTH
FLOOR AUXILIARY
SYSTEM LAYOUT
-ROOF DECK
AUXILIARY SYSTEM
LAYOUT
-BMS POINTS LIST
-SCHEMATIC DIAGRAM
MATERIAL: Carbon Steel
CALLOUTS & OUTLINE
SPECIFICATIONS,
ISOMETRIC VIEW
CALLOUTS & OUTLINE
SPECIFICATIONS
PLANS
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
NOTES
NOTES
TABLES
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
12. PLUMBING (P)
Design Sheets
Note: By law (R.A. No.
1378), only registered and
licensed
master
plumbers/ MPs shall
prepare, sign and seal all
professional outputs for
buildings i.e. those that are
classified as Plumbing (P)
Design Documents
Note: Depending on the
Lower
Court’s
interpretation (for final
adjudication
by
the
Supreme Court), registered
and licensed sanitary
engineers/ SEs may
apparently prepare, sign
and seal all professional
outputs for buildings i.e.
those that are classified as
Plumbing (P) Design
Documents.
The
concerned entities must
make
the
necessary
representations with the
Client.
EC – 17
DETAILS
EC – 18
DETAILS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
P-2
UPPER GROUND
FLOOR PLUMBING
LAYOUT
CALLOUTS & OUTLINE
SPECIFICATIONS
NOTES
P-3
- SECOND FLOOR
PLUMBING LAYOUT
THIRD FLOOR
PLUMBING LAYOUT
FOURTH FLOOR
PLUMBING LAYOUT
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS,
TYPICAL CONNECTION
OF WS TO DS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
NOTES
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
NOTES
P-6
P-7
P-8
P-9
P-10
P-11
CALLOUTS & OUTLINE
NOTES
NOTES
LOWER GROUND
PLUMBING LAYOUT
P-5
NOTES
STAIRWELL
PRESSURIZATION
FAN SEQUENCE
OF OPERATION
NOTES
P-1
P-4
LEGEND
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
P-12
FIFTH FLOOR
PLUMBING LAYOUT
SIXTH FLOOR
PLUMBING LAYOUT
SEVENTH FLOOR
PLUMBING LAYOUT
ROOF DECK
PLUMBING LAYOUT
RISER DIAGRAM OF
COLD WATER
RISER DIAGRAM OF
DOWNSPOUT ALONG
GRID LINE-B
RISER DIAGRAM OF
SANITARY DRAINAGE
NOTES
NOTES
NOTES
NOTES
CALLOUTS & OUTLINE
SPECIFICATIONS
G-16
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
P-13
P-14
P-15
DETAIL OF GROUND
WATER TANK
DETAIL OF ELEVATED
WATER TANK
-ROUGHING-IN OF
TOILETS
P-16
-ROUGHING-IN OF
TOILETS
P-17
-ROUGHING-IN OF
TOILETS
P-18
-ROUGHING-IN OF
TOILETS
P-19
-DETAIL OF PUMP
INSTALLATION, PUMP
DISCHARGE RISER
PIPING DETAIL,
SCHEDULE OF
EQUIPMENT
-MISCELLANEOUS
DETAILS
P-20
DETAIL OF
WATERTIGHT
MANHOLE, DETAIL OF
AIR VENT, DETAIL OF
LADDER RUNGS,
DETAIL OF PIPE
SLEEVE, DETAIL OF
OVERFLOW
PIPE/DRAIN BOX
CALLOUTS & OUTLINE
SPECIFICATIONS
ISOMETRIC
CALLOUTS, OUTLINE
SPECIFICATIONS
ISOMETRIC
CALLOUTS, OUTLINE
SPECIFICATIONS
ISOMETRIC
CALLOUTS, OUTLINE
SPECIFICATIONS
ISOMETRIC
CALLOUTS, OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECIFICATIONS
CALLOUTS & OUTLINE
SPECICATIONS,
DETAIL OF LADDER
RUNG
P-21
-MISCELLANEOUS
DETAILS
CALLOUTS, OUTLINE
SPECIFICATIONS
13. SANITARY (SE)
Engineering Design
Sheets
SE - 1
CALLOUTS
Note: By law (R.A. No.
1364), only registered and
licensed
sanitary
engineers/ SEs shall
prepare, sign and seal all
professional outputs for
buildings i.e. those that are
SE-2
SITE PLAN SHOWING
OUTSIDE SANITARY
UTILITIES, TABLE OF
CONTENTS AND
LEGEND/ SYMBOLS
SEWAGE TREATMENT
PLANT (STP)
G-17
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
classified as Sanitary (S)
Engineering
Design
Documents
NOTES
SE-3
SE-4
STP DETAILS
MISCELLANEOUS
DETAILS
CALLOUTS, OUTLINE
SPECIFICATIONS
TABLE OF
DIMENSIONS,
NOTES
Notes:
*includes Fixtures, Furnishings and Equipment (Non-capital) i.e. FFE and Graphic Design, including all forms of
Way-finding Systems (such as those for office and parking spaces);
**includes Furniture and Movables Design (FMD) and Décor Items; and
***includes all hard and soft landscaping components.
****oftentimes included as part of the Mechanical (M) Design sheets; and
*****includes Building Management System (BMS) and other automation features.
TABLE OF RISER
CLAMPS, TABLE
OF CLEVIS
HANGERS, TABLE
OF TRAPEZE
HANGERS, TABLE
OF BRACKET
DIMESIONS
TABLE OF
DIMENSIONS,
NOTES, TABLE
OF MINIMUM
THRUST BLOCK
BEARING AREAS
IN SQUARES
METRES FOR
PIPE SIZES 75mm
- to 600mm∅
G-18
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
SECTION 03410 – PRECAST CONCRETE WALLS ............................................................................................................. 92
Generic Table of Contents for the Technical Specifications for a
DIVISION 04 - MASONRY ........................................................................................................................................... 96
(Approx. 1.7 hectares Total Lot Area/ TLA, approx. 60,000 sqm Total Gross Floor Area/ TGFA,
Large Footprint, Medium-rise with Deck Roof Level and No Basement Level)
SECTION 04220 – CONCRETE MASONRY UNIT WORK ................................................................................................ 101
LARGE NATIONAL GOVERNMENT OFFICE Building Project
at Approximately 480 A4 Size Pages
Very Important Note: In the case of repair, renovation, rehabilitation, retrofit,
expansion, heritage conservation, fit-out, and similar works/ projects for buildings/
structures, the SCOPE OF WORKS BRIEF for such buildings/ structures i.e. a
general description of the intended construction works, MUST be provided by the
Designer and/or Project Proponent before the rest of the Plans/ Designs/
Documents listed hereafter. The provisions that DO NOT apply to the types of
work listed above shall be deleted on an need/ applicability basis.
INTRODUCTION........................................................................................................................................................... 1
DIVISION 01 - GENERAL REQUIREMENTS .................................................................................................................... 6
SECTION 01010 – SUMMARY OF WORKS ....................................................................................................................... 6
SECTION 01011 - CONTRACT DOCUMENTS .................................................................................................................... 6
SECTION 01040 - COORDINATION.................................................................................................................................. 7
SECTION 01060 - REGULATORY AND OTHER REQUIREMENTS ....................................................................................... 7
SECTION 01090 - REFERENCE STANDARDS .................................................................................................................... 8
SECTION 01300 - SUBMITTALS ..................................................................................................................................... 10
SECTION 04810 – UNIT MASONRY ASSEMBLES .......................................................................................................... 103
DIVISION 05 - METAL .............................................................................................................................................. 113
SECTION 05120 – STRUCTURAL STEEL........................................................................................................................ 113
SECTION 05500 – METAL FABRICATIONS ................................................................................................................... 119
SECTION 05510 – MISCELLANEOUS METALS .............................................................................................................. 126
SECTION 05520 – HANDRAILS AND RAILINGS (STAINLESS STEEL) .............................................................................. 127
SECTION 05540 – LIGHT STEEL FRAMING SYSTEM ..................................................................................................... 134
DIVISION 06 – WOOD AND PLASTICS ...................................................................................................................... 135
SECTION 06200 – CARPENTRY AND JOINERY ............................................................................................................. 135
DIVISION 07- THERMAL AND MOISTURE PROTECTION ............................................................................................ 138
SECTION 07100 – WATERPROOFING.......................................................................................................................... 138
SECTION 07145 – MEMBRANE-TYPE ELASTOMERIC WATERPROOFING .................................................................... 142
SECTION 07260 – BATT INSULATION .......................................................................................................................... 145
SECTION 07431 – INSULATED METAL ROOF PANELS .................................................................................................. 146
SECTION 07610 – SHEET METAL ROOFING AND CLADDING ....................................................................................... 150
SECTION 07800 – ROOF ACCESSORIES ....................................................................................................................... 160
SECTION 07920 – CAULKING AND SEALING ............................................................................................................... 161
SECTION 01312 - PROJECT MEETINGS .......................................................................................................................... 14
DIVISION 08 - DOORS AND WINDOWS .................................................................................................................... 162
SECTION 01352 - PROJECT HEALTH AND SAFETY ......................................................................................................... 17
SECTION 08110 – STEEL DOORS AND FRAMES ........................................................................................................... 162
SECTION 01400 - QUALITY CONTROL ........................................................................................................................... 20
SECTION 08120 – ALUMINUM DOORS ....................................................................................................................... 166
SECTION 01500 - TEMPORARY FACILITIES (TEMFACIL) ................................................................................................ 22
SECTION 08130 – AUTOMATIC ENTRANCE SYSTEM ................................................................................................... 168
SECTION 01600 - MATERIAL AND EQUIPMENT ............................................................................................................ 24
SECTION 08210 – WOOD PANEL AND FLUSH DOORS ................................................................................................. 172
SECTION 01700 - CONTRACT CLOSEOUT ...................................................................................................................... 26
SECTION 08331 – OVERHEAD COILING DOORS .......................................................................................................... 176
SECTION 01710 - CLEANING ......................................................................................................................................... 28
SECTION 08520 – ALUMINUM WINDOWS ................................................................................................................. 180
DIVISION 02 - SITE CONSTRUCTION ........................................................................................................................... 29
SECTION 02250 – SOIL TREATMENT FOR SUBTERRANEAN TERMITE CONTROL ......................................................... 29
SECTION 08700 – HARDWARE ................................................................................................................................... 184
SECTION 08800 – GLASS AND GLAZING...................................................................................................................... 189
SECTION 02300 - EARTHWORK .................................................................................................................................... 31
DIVISION 09 – FINISHES........................................................................................................................................... 192
SECTION 02444 - PERIMETER FENCES AND GATES ....................................................................................................... 38
SECTION 09220 – PORTLAND CEMENT PLASTER ........................................................................................................ 192
DIVISION 03 - CONCRETE........................................................................................................................................... 41
SECTION 03100 - PORTLAND CEMENT CONCRETE PAVEMENT .................................................................................... 41
SECTION 03210 – REINFORCED CONCRETE .................................................................................................................. 63
SECTION 03300 – CAST-IN-PLACE CONCRETE .............................................................................................................. 74
G-19
SECTION 04050 – BASIC MASONRY MATERIALS ........................................................................................................... 96
SECTION 09290 – GYPSUM CEILING BOARDS ............................................................................................................. 195
SECTION 09295 – GYPSUM WALLBOARD (DRY WALL) ............................................................................................... 198
SECTION 09310 – CERAMIC TILE WORK ..................................................................................................................... 201
SECTION 09510 – ACOUSTICAL CEILING SYSTEM ....................................................................................................... 204
G-20
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
SECTION 09575 – SPANDREL CEILING ........................................................................................................................ 205
SECTION 16425 – LOW VOLTAGE SWITCHBOARD ...................................................................................................... 404
SECTION 09650 – HOMOGENOUS TILES..................................................................................................................... 206
SECTION 16460 – AUTOMATIC TRANSFER SWITCH .................................................................................................... 413
SECTION 09660 – PLAIN CEMENT FLOOR FINISH........................................................................................................ 209
SECTION 16470 – PANELBOARDS ............................................................................................................................... 420
SECTION 09666 – VINYL FLOOR TILES ......................................................................................................................... 211
SECTION 16500 – LUMINARIES AND ACCESSORIES .................................................................................................... 425
SECTION 09678 – CONCRETE FLOOR ADDITIVES/ SEALER .......................................................................................... 212
SECTION 16510 – RROW LIGHTING ............................................................................................................................ 431
SECTION 09750 – NATURAL STONE ............................................................................................................................ 213
SECTION 16550 – LIGHTNING PROTECTION SYSTEMS................................................................................................ 438
SECTION 09910 – PAINTING ....................................................................................................................................... 214
SECTION 16680 – GROUNDING SYSTEM .................................................................................................................... 441
SECTION 09965 – EPOXY PAINT.................................................................................................................................. 217
SECTION 16720 – FIRE DETECTION AND ALARM SYSTEM........................................................................................... 445
DIVISION 10 – SPECIALTIES ..................................................................................................................................... 218
SECTION 10280 – TOILET PARTITION SYSTEM ............................................................................................................ 218
SECTION 10800 – TOILET AND BATH ACCESSORIES .................................................................................................... 224
SECTION 10810 – PANTRY ACCESSORIES ................................................................................................................... 226
SECTION 10890 – WALK-THROUGH METAL DETECTOR.............................................................................................. 227
DIVISION 11 – EQUIPMENT ..................................................................................................................................... 235
SECTION 16740 – STRUCTURAL CABLING SYSTEM ..................................................................................................... 451
SECTION 16755 – PABX SYSTEM SPECIFICATION ........................................................................................................ 452
SECTION 16770 – BACKGROUND MUSIC AND PAGING SYSTEM (BGM/PA) ............................................................... 460
SECTION 16780 – CLOSED CIRCUIT TELEVISION SYSTEM (CCTV) ................................................................................ 464
SECTION 16900 – INSTRUMENTATION, ATC & BMS SYSTEM ..................................................................................... 467
SECTION 16950 – TESTING AND COMMISSIONING OF ELECTRICAL SERVICES ........................................................... 477
SECTION 11130 – LOADING DOCK EQUIPMENT ......................................................................................................... 235
SECTION 11260 – KITCHEN EQUIPMENT .................................................................................................................... 245
DIVISION 12 - FURNISHINGS.................................................................................................................................... 259
SECTION 12210 – BLINDS ........................................................................................................................................... 259
SECTION 12482 – ENTRANCE FLOOR MATS AND FRAMES ......................................................................................... 261
DIVISION 14 – CONVEYING SYSTEM ........................................................................................................................ 265
SECTION 14210 – ELEVATORS .................................................................................................................................... 265
DIVISION 15 - MECHANICAL .................................................................................................................................... 270
SECTION 15300 – FIRE PROTECTION WORKS ............................................................................................................. 270
SECTION 15320 – FIRE PUMPS ................................................................................................................................... 287
SECTION 15400 – PLUMBING ..................................................................................................................................... 292
SECTION 15780 – MECHANICAL (HVAC) ..................................................................................................................... 309
SECTION 15910 – DUCTWORK ACCESSORIES ............................................................................................................. 354
DIVISION 16 - ELECTRICAL ....................................................................................................................................... 357
SECTION 16000 – ELECTRICAL GENERAL PROVISIONS................................................................................................ 357
SECTION 16010 – ELECTRONICS & COMMUNICATION GENERAL PROVISIONS .......................................................... 372
SECTION 16110 – RACEWAYS AND BOXES ................................................................................................................. 375
SECTION 16122 – HIGH-VOLTAGE CABLE AND ACCESSORIES ..................................................................................... 382
SECTION 16200 – ENGINE GENERATOR SETS ............................................................................................................. 385
SECTION 16266 – PARALLELING SWITCHGEAR .......................................................................................................... 396
SECTION 16271 – POWER TRANSFORMER ................................................................................................................. 400
SECTION 16272 – DRY TYPE TRANSFORMER .............................................................................................................. 402
G-21
G-22
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
CHECKLIST FOR USE BY THE DPWH FOR ASSESSING DOCUMENTS SUBMITTED
FOR DESIGN REVIEW
(based on Sec. 302 of the 2004 Revised Implementing Rules and Regulations/ IRR of P.D. No. 1096, the
1977 National Building Code of the Philippines/ NBCP)
1. Duly accomplished prescribed request form/s for design review, with the following support documents:
a. In case the design review applicant is the registered owner of the lot:
i.
Certified true copy of OCT/ TCT, on file with the Registry of Deeds,
ii.
Tax Declaration, and
iii. Current Real Property Tax Receipt.
b. In case the design review applicant is not the registered owner of the lot, in addition to the above;
duly notarized copy of the Contract of Lease, or the Deed of Absolute Sale.
Annex H
2.
Five (5) sets of survey plans, design plans, specifications and other documents duly prepared, signed
and sealed over the printed names of the duly registered and licensed professionals (RLPs), as
follows:
a. Geodetic Engineer (GE), in case of lot survey plans e.g. relocation, topographic, etc.;
b. Architect (Ar), in case of architectural documents, including architectural interior (AI) documents
and related physical planning documents for a Project site of less than five hectares (-5.0 has.) in
total land area/ TLA (reference Sec. 20.5 of R.A. No. 9266, the Architecture Act of 2004); in case
of interior design (ID) documents, including furniture design, an interior designer (IDr) must sign
and seal;
c. Civil Engineer (CE), in case of civil/ structural documents;
d. Professional Electrical Engineer (PECE), in case of electrical documents;
e. Professional Mechanical Engineer (PME), in case of mechanical documents;
f. Sanitary Engineer (SnE), in case of sanitary documents;
g. Master Plumber (MP), in case of plumbing documents;
h. Professional Electronics Engineer (PEE), in case of electronics documents;
i. Landscape Architect (LAr), in case of landscape architectural documents for building grounds
(hard scape and soft scape); and
j. Environmental Planner (EnP), in case of master development plans (MDPs) and related physical
planning documents for a Project site of more than five hectares (5.0 has.) in total land area
(TLA).
3.
Five (5) sets of special studies duly prepared, signed and sealed over the printed names of the duly
accredited professionals, as follows:
a. Civil Engineer (CE), Environmental Planner (EnP) or Architect (Ar), with duly-qualified
specialization in transportation planning, in case of the traffic impact analysis (TIA); and
b. Civil Engineer (CE), Environmental Planner (EnP) or Architect (Ar), or an Environment Specialist,
with duly-qualified specialization in environmental investigation, in case of the environmental
impact analysis (EIA), required to secure the Environmental Compliance Certificate (ECC).
4.
Architectural Documents
a. Architectural Plans/ Drawings
i.
Vicinity Map/ Location Plan within a two kilometer (2.0 km) radius for commercial,
industrial, and institutional complex and within a 0.5 km radius for residential buildings, at
any convenient scale showing prominent landmarks or major thoroughfares for easy
reference.
ii.
Site Development Plan (SDP) showing technical description, boundaries, orientation and
position of proposed building/structure in relation to the lot, existing or proposed access road
and driveways and existing public utilities/ services. Existing buildings within and adjoining
Check List for Use by the DPWH for
Assessing Documents Submitted for
Design Review
H-1
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
the lot shall be hatched and distances between the proposed and existing buildings shall be
indicated.
iii. Perspective drawn at a convenient scale and taken from a vantage point (bird’s eye view or
eye level).
iv. Architectural Program (including Space Program), with Space Plans cum Stacking Diagrams
(only for multi-storey buildings) drawn to scale of not less than 1:100 meters (m).
v.
Floor Plans drawn to scale of not less than 1:100 meters (m) showing: gridlines, complete
identification of rooms or functional spaces.
vi. Elevations, at least four (4), same scale as floor plans showing: gridlines; natural ground to
finish grade elevations; floor to floor heights; door and window marks, type of material and
exterior finishes; adjoining existing structure/s, if any, shown in single hatched lines.
vii. Sections, at least two (2), showing: gridlines; natural ground and finish levels; outline of cut
and visible structural parts; doors and windows properly labeled reflecting the direction of
opening; partitions; built-in cabinets, etc.; identification of rooms and functional spaces cut by
section lines.
viii. Reflected ceiling plan (RCP) showing: design, location, finishes and specifications of
materials, lighting fixtures, diffusers, decorations, air conditioning exhaust and return grills,
sprinkler nozzles, if any, at scale of at least 1:100 m.
ix. Details, in the form of plans, elevations/sections:
(a) Accessible ramps
(b) Accessible stairs
(c) Accessible lifts/ elevators
(d) Accessible entrances, corridors and walkways
(e) Accessible functional areas/ comfort rooms
(f) Accessible switches, controls
(g) Accessible drinking fountains
(h) Accessible public telephone booths
(i)
Accessible audio visual and automatic alarm system
(j)
Accessible access symbols and directional signs
(k) Reserved parking for persons with disabilities (PWDs)
(l)
Typical wall/ bay sections from ground to roof
(m) Stairs, interior and exterior
(n) Fire escapes/ exits
(o) Built-in cabinets, counters and fixed furniture
(p) All types of partitions
(q) Provisions for PWDs, the elderly, gender and development (GAD), and the like;
(r) Provisions to address concerns of climate change adaptation (CCA) and disaster risk
reduction (DRR)
x.
Schedule of Doors and Windows showing their types, designations/ marks, dimensions,
materials, hardware provisions, and number of sets.
xi. Schedules of Finishes, showing in graphic form: surface finishes specified for floors, ceilings,
walls and baseboard trims for all building spaces per floor level.
xii. Details of other major Architectural Elements; and
xiii. Technical Specifications (including operation/ use and maintenance) for all architectural
works.
b. Architectural Interiors (AI)
i.
General Space Plan/s or general layout/s of architectural interiors.
ii.
Architectural interior perspective/s.
iii.
Furniture/ furnishing/ equipment (FFE) layouts and process layout/s.
iv.
Access plan/s, parking plan/s and the like.
H-2
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
v.
Detailed design of major architectural interior elements i.e. floors, walls, ceiling, doors and
related fenestrations, fixed counters and cabinetry, hardware, etc.
vi.
General plan, layout and design of the architectural interiors, including walls/ partitions,
furnishing/ furniture/ equipment (FFE)/ appliances at a scale of at least 1:100 m, including
ceiling cavity and roof cavity plans, as needed.
vii.
Interior wall elevations showing: finishes, switches, doors and convenience outlets, cross
window sections with architectural interior perspective as viewed from the main entrance at
scale of at least 1:100 m.
viii.
General floor/ ceiling/ wall patterns and general finishing details.
ix.
Technical Specifications (including operation/ use and maintenance), Schedules and related
list/s of materials to be used for architectural interior finishing works.
x.
Cost Estimates.
c. Plans and specific locations of all accessibility facilities of scale of at least 1:100 m., including the
detailed design of all such accessibility facilities outside and around buildings/structures including
parking areas, and their safety requirements all at scale of 1:50 m or any convenient scale.
d. Fire Safety Documents
i.
Layout plan of each floor indicating the fire evacuation route to safe dispersal areas,
standpipes with fire hose, fire extinguishers, first aid kits/ cabinets, fire alarm, fire operations
room, emergency lights, signs, etc.s
ii.
Details of windows, fire exits with grilled windows and ladders.
iii.
Details of fire-resistive construction of enclosures for vertical openings.
iv.
Details of fire-resistive construction materials and interior decorative materials with fireresistive/ fire-retardant/ fire-spread ratings
v.
Other Related Documents
f. Physical Planning documents (for Project Sites at less than 5.0 hectares in Total Land Area/ TLA)
i.
Vicinity Map/ Location Plan at a scale of at least 1:10,000 m.
ii.
Framework Plan at a scale of at least 1:2,500 m showing existing and proposed access
systems, connectivities, identified hazards, orientations (wind, sun, odor, noise, etc.), view
corridors, and like information.
iii.
Master Development Plan (MDP) at a scale of at least 1:1,250 m showing all setbacks and
mandated legal easements (as applicable), proposed road rights-of-way (RROW, clearly
delineating the carriageway and sidewalks), proposed building footprints at grade level,
proposed outermost faces of buildings (OFB) at the second levels/ floors, floor to lot area
(FLAR) used, gross floor area (GFA) to be generated, total GFA (TGFA) to be generated,
building heights, and like information, to fully comply with Rules VII and VIII of the 2004
Revised IRR of P.D. No. 1096, the 1977 NBCP.
iv.
Proposed Land Use Distribution (breakdown).
g. Other related documents
5.
Interior Design
i.
Detailed space plan/ layout and design of all interior design elements, including furniture and
furnishings at all fully enclosed areas/ spaces, at a scale of at least 1:50 m.
ii.
Interior design perspective/s showing details of special finishing and furnishing items.
iii.
Special floor/ ceiling/ wall patterns and finishing details.
iv.
Technical Specifications (including operation/ use and maintenance), Schedules and related
list/s of materials to be used for interior design finishing works.
v.
Cost Estimates.
6. Civil/ Structural Documents
a. Site Development Plan (SDP)
H-3
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
Site Development Plan showing technical description, boundaries, orientation and position of
proposed non-architectural horizontal structure such as: sewerage treatment plan (STP), silos,
elevated tanks, towers, fences, etc. building/ structure in relation to the lot, existing or proposed
access road and driveways and existing public utilities/ services. Existing buildings within and
adjoining the lot shall be hatched and distances between the proposed and existing buildings shall
be indicated.
b. Structural Plans
i.
Foundation Plans and Details at scale of not less than 1:100 m.
ii.
Floor/ Roof Framing Plans and Details at scale of not less than 1:100 m.
iii.
Details and Schedules of structural and civil works elements including those for deep wells,
water reservoir, pipe lines and sewer system.
c. Structural Analysis and Design for all buildings/structures except for one storey and single
detached building/structure with a total floor area of 20.0 square meters (sqm) or less.
d. Boring and Load Tests
Buildings or structures of three (3) storeys and higher, boring tests and, if necessary, load tests
shall be required in accordance with the applicable latest approved provisions of the National
Structural Code of the Philippines (NSCP). However, adequate soil exploration (including boring
and load tests) shall also be required for lower buildings/ structures at areas with potential
geological/geotechnical hazards. The written report of the civil/ geo-technical engineer including
but not limited to the design bearing capacity as well as the result of tests shall be submitted
together with the other requirements in the application for a building permit. Boring test or load test
shall also be done according to the applicable provisions of the NSCP which set forth requirements
governing excavation, grading and earthwork construction, including fills and embankments for any
building/structure and for foundation and retaining structures.
e. Seismic and Wind Load Analyses
a. Other related documents
7. Electrical Documents
Electrical plans and technical specifications containing the following:
a. Location and Site Plans
b. Legend or Symbols
c. General Notes and/or Specifications
d. Electrical Layout
e. Schedule of Loads, Transformers, Generating/ UPS Units (Total kVA for each of the preceding
items shall be indicated in the schedule)
f. Design Analysis
g. One Line Diagram
8.
H-4
Mechanical Documents
a. Location Plan and Key Plan
b. General Layout Plan for each floor, drawn to a scale of not less than 1:100 m, indicating the
equipment in heavier lines than the building outline with names of machinery and corresponding
brake horsepower shall be indicated.
c. Longitudinal and Transverse Sections of building and equipment base on the section lines drawn to
scale of at least 1:100 m showing inter-floor relations and defining the manner of support of
machines/equipment. Sections shall run longitudinally and transversely through the building length
or width other than particularly detailed section for each machinery/equipment (fired and unfired
pressure vessel, elevator, escalator, dumbwaiter, etc.).
d. Isometric drawing of gas, fuel, oil system showing: Assembly of pipes on racks and supports,
Legend and General Notes, capacity per outlet and complete individual piping system.
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
e. Plans drawn to scale of 1:100 m indicating location of store rooms, fuel tanks, fire extinguishing
systems, fire doors, fire escape ladders and other protective facilities.
f. Detailed drawings of all duct work installations, indicating dampers, controls, filters, fireproofing,
acoustical and thermal insulation.
g. Detailed Plans of machinery foundations and supports drawn to scale of at least 1:50 m.
h. Detailed Plans of boilers and pressure vessels with a working pressure of above 70 kPa regardless
of kilowatt rating.
i. Design Computations and Detailed Plans of elevators, escalators, and the like drawn to scale of
1:50 m.
j. For all installations, additions or alterations involving machinery of at most 14.9 kW, the signature
of a duly licensed Mechanical Engineer shall be sufficient except fired and unfired pressure
vessels, elevators, escalators, dumbwaiters, central/split/packaged type air conditioners and piping
systems of steam, gas or fuels.
k. Detailed plans of fire suppression systems, location of automatic and smoke detectors and alarm
and initiating devices use to monitor the conditions that are essential for the proper operation
including switches for the position of gate valves as well as alert and evacuation signals; the
detailed layout of the entire safe area to be protected and the heat/smoke ventilation system.
9. Sanitary Documents
a. For deep well, water purification plants, water collection and distribution systems, reservoirs,
drainage and sewer systems, sewage treatment plants, malaria control structures, and sewage
disposal systems:
i.
Location Plan and Site Plan
ii.
Detailed Plan and layout drawings of minimum scale 1:100 m.
iii.
Design Analysis and Technical Specifications
iv.
Cost Estimates
b. For pest and vermin control, sanitation and pollution control facilities:
i.
Detailed plan, layout & drawing of abatement and control device of minimum scale 1:100 m.
ii.
Design analysis and technical specification
iii.
Cost Estimates
10. Plumbing Documents
For all plumbing installations, additions and/or alterations involving hot and cold water supply, fixtures,
sewage drainage and vent system, storm drainage and sewerage system within or adjacent to the
building:
a. Location Plan and Site Plan of minimum scale 1: 2000 m
b. Plumbing Plans, Layouts and Details, of minimum scale 1: 50 m
c. Legend and General Notes
d. Isometric drawings of the systems
e. Design analysis and technical specifications
f. Cost Estimates
11.
Electronics Documents
Electronic plans and technical specifications for wired or wireless telecommunications systems,
broadcasting systems, including radio and TV broadcast equipment for commercial and training
purposes, cable or wireless television systems, information technology (IT) systems, security and alarm
systems, electronic fire alarm systems, sound-reinforcement systems, navigational aids and controls,
indoor and outdoor signages, electronically-controlled conveyance systems, electronic/computerized
process controls and automation systems, building automation, management and control systems,
including, but not limited to the following:
a. General layout plans with legends
H-5
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
b.
c.
d.
e.
f.
g.
Single line diagram
Riser diagram
Isometry of the system
Equipment specifications
Design analysis, as applicable
Cost estimates
b. Geodetic Documents
Lot Survey Plans, including but not limited to:
a. Vicinity Map/ Location Plan
b. Lot Plan
c. Relocation Survey Plan and Report
d. Line and Grade
e. Detailed Topographic Plan of the site and immediate vicinity
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
xvi.
xvii.
xviii.
xix.
xx.
xxi.
xxii.
xxiii.
Department of Agrarian Reform (DAR)
Department of Agriculture (DA)
Department of Labor and Employment (DOLE)
National Housing Authority (NHA)
National Council for the Welfare of Disabled Persons (NCWDP)
Philippine Reclamation Authority (PRA)
Metropolitan Manila Development Authority (MMDA)
National Commission on Culture and the Arts (NCCA)
c. Environmental Planning documents (for Project Sites at 5.0 hectares or larger in Total Land Area/ TLA)
a. Vicinity Map/ Location Plan at a scale of at least 1:10,000 m.
b. Framework Plan at a scale of at least 1:2,500 m showing existing and proposed access systems,
connectivities, identified hazards, orientations (wind, sun, odor, noise, etc.), view corridors, and like
information.
c. Master Development Plan (MDP) at a scale of at least 1:1,250 m showing all setbacks and
mandated legal easements (as applicable), proposed road rights-of-way (RROW, clearly
delineating the carriageway and sidewalks), proposed building footprints at grade level, proposed
outermost faces of buildings (OFB) at the second levels/ floors, floor to lot area (FLAR) used, gross
floor area (GFA) to be generated, total GFA (TGFA) to be generated, building heights, and like
information, to fully comply with Rules VII and VIII of the 2004 Revised IRR of P.D. No. 1096, the
1977 NBCP.
d. Land Use Distribution (breakdown).
12. Clearances from Other Agencies
a. A locational clearance shall be obtained by the design review applicant from the Office of the City/
Municipal Zoning Administrator.
b. Whenever necessary, written clearances shall be obtained from the various authorities exercising
and enforcing regulatory functions affecting buildings/ structures by the design review applicant.
Application for said clearances shall be requested by the design review applicant. Such authorities
which are expected to enforce their own regulations are:
i. Department of Public Works and Highways (DPWH)
ii. Air Transportation Office (ATO, now the Civil Aviation Authority of the Philippines or CAAP)
iii. Housing and Land Use Regulatory Board (HLURB)
iv. Local Government Unit (LGU)
v. Department of Tourism (DOT)
vi. Department of Environment and Natural Resources (DENR)
vii. Department of Transportation and Communication (DOTC)
viii. Department of Interior and Local Government (DILG)
ix. Philippine Ports Authority (PPA)
x. Department of Education (DepEd)
xi. Department of Health (DOH)
xii. Philippine Institute of Volcanology and Seismology (PHIVOLCS)
xiii. Laguna Lake Development Authority (LLDA)
xiv. Manila Waterworks and Sewerage System (MWSS)
xv. National Water Resources Board (NWRB)
H-6
H-7
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
2014 DPWH-BoD SPACE ALLOCATION STANDARDS BY OFFICE TYPE (Gross Floor Area/ GFA)*
*The GFA excludes the main common areas such as common areas e.g. lobbies, building cores, stairs and fire exits, service or
utility balconies and decks, parking spaces and access-ways (within the building footprint) and similar spaces.
PARTICULARS
MAXIMUM SPACE REQUIREMENTS (in Sq.M.)
SPACE REQUIREMENT/S OF KEY OFFICIALS
A. OFFICE OF THE SECRETARY OR ITS EQUIVALENT SG-31 POSITION
1. Secretary
72.00
2. Staff
4.00 - 6.00/ pax¹
3. Conference Room
60.00
4. Reception Room
30.00
5. Toilet/ Bathroom
6.00
6. Pantry
10.00
7. Storage Area²
10.00
B. OFFICE OF THE UNDERSECRETARY OR ITS EQUIVALENT SG-30 POSITION
1. Undersecretary
63.00
2. Staff
4.00 - 6.00/ pax¹
3. Conference Room
40.00
4. Reception Room
20.00
5. Toilet/ Bathroom
6.00
6. Pantry
10.00
7. Storage Area²
10.00
C. OFFICE OF THE ASSISTANT SECRETARY OR ITS EQUIVALENT SG-29 POSITION
1. Assistant Secretary
56.00
2. Staff
4.00 - 6.00/ pax¹
3. Conference Room
30.00
4. Reception Room
20.00
5. Toilet/ Bathroom
6.00
6. Pantry
10.00
7. Storage Area²
10.00
D. OFFICE OF THE DIRECTOR IV OR ITS EQUIVALENT SG-28 POSITION
1. Director IV
36.00
2. Staff
4.00 - 6.00/ pax¹
3. Reception Room
10.00
4. Toilet/ Bathroom
4.00
5. Pantry
5.00
6. Storage Area²
6.00
E. OFFICE OF THE DIRECTOR III OR ITS EQUIVALENT SG-27 POSITION
1. Director III
24.00
2. Staff
4.00 - 6.00/ pax¹
3. Toilet/ Bathroom
4.00
F. DIVISION-LEVEL UNIT
1. Division Chief
12.00
2. Staff
4.00 - 6.00/ pax¹
3. Lobby/ Lounge
0.25/ pax
¹includes circulation area
²for storage of supplies, equipment, records/ files and other materials
H-8
Design Guidelines, Criteria and Standards: Volume 6 – Public Buildings and Other Related Structures
2014 DPWH-BoD SPACE ALLOCATION STANDARDS BY TYPE OF USAGE (Gross Floor Area/ GFA)*
*The GFA excludes the main common areas such as common areas e.g. lobbies, building cores, stairs and fire exits, service or
utility balconies and decks, parking spaces and access-ways (within the building footprint) and similar spaces.
PARTICULARS
A. MAIN LOBBY
B. BUREAU-LEVEL FACILITIES
1. Conference Room
2. Pantry
3. Storage Area¹
C. TRAINING ROOM
MAXIMUM SPACE REQUIREMENTS (in Sq.M.)
SPACE REQUIREMENT/S
0.25/ pax; minimum for lobby as waiting/
standing room is 0.28/ pax
D. QUARTERS
1. Single Bedroom
2. Twin-Sharing Bedroom
3. Toilet/ Bathroom
4. Pantry
E. TOILET FACILITIES²
1. For Agencies providing frontline services (for
Public use)
30.00
10.00
15.00
2.40/ pax including aisles and services such as
storage, production room and toilet for the staff
4.00
8.00
4.00
10.00
1.50 per one water closet (WC) enclosure
 1 WC/ 1-100 for female
 1 WC/ 1-200 for male
 1 urinal/ 1-100 for male
 1 lavatory/ 2 WC
2. For Agencies with no clientele (for Employee
 1 WC/ 1-15, 2WC/ 16-35, 3WC/ 36-55 for
use)
male and female
 1 lavatory/ 40 for male and female; or 1
lavatory/ 2 WC
¹for storage of supplies, equipment, records/ files and other materials
²based on the Revised National Plumbing Code of the Philippines (R.A. No. 1378)
H-9
Download
Study collections